2017 Annual NTPEP Meeting
Seaport Hotel & World Trade Center
Boston, Massachusetts
Thermoplastic Pipe (TPP)
Technical Committee Meeting Minutes
Working Session #7
Tuesday, March 14, 2017 1:00 PM – 3:05 PM
1) 1:00 PM-1:15 PM: Call to Order and Introductions
2) 1:15 PM-1:25 PM: Review of Current Technical Committee Members
a) See attachment – Any new Members will be added
3) 1:25 PM-1:40 PM: Summary of the technical committee (for those states who do
not participate in quarterly calls or who are new to NTPEP) – Information in the
“footer” was discussed (regarding NTPEP purpose). (LA) – How are DOTs
handling a “Compliant” Mfg. found to be “Non-Compliant”– Matt discussed how
ILDOT handled this in the past. Their acceptance was based upon the material
received in the field. Audits are based on the “process” not the material.
Corrective Actions are issued when non-compliances are found. Found two
instances of “Non-Compliant” Mfgs. last year. Notification was sent and both were
given a follow-up audit. • Poly Update – Changes to Work Plan and better process for making plaques by the NTPEP
Designated Lab.
• SRPE Update – Have a balloted Work Plan and will be working on Audit Worksheets
4) 1:40 PM-1:50 PM: Review of Outstanding Action Items Presentation of updates to the Work Plans, Audit Reports and Comparison Sample Reports –
• Will be updating all necessary documents.
Presentation on combining all plastic pipe Work Plans into a single Thermoplastic Pipe Work Plan –
• Will combine current work plans (HDPE, PVC, and POLY) into one. SP01 was updated to
help this effort. Why do this? – to have a better way to address changes and similar
information. Reinforcing steel has done this successfully. Structure of Committee “top”
will change if needed.
• John Schuler presentation – referenced the “comparison samples” (formerly called “Split”)
and how they could be used. Using Excel spreadsheets to analyze data in the future.
• Issues found during an audit that do not completely follow the standards. Currently being
noted as an “Observation”. Propose this type of issue is addressed in the Mfg’s QSM. WI
had issues with allowing this proposal and cautioned how it will be used. Clarification was
2017 Annual NTPEP Meeting
Seaport Hotel & World Trade Center
Boston, Massachusetts
made that this would be for items that are “above” the minimum specification
requirements.
5) 1:50 PM-2:10 PM: Update-Research/Specifications: Mike Pluimer- Presentation on the use of recycle in pipe with the following comments:
• Did the Service Life Model take into account Ph ? No, it has no real affect
• Cell class is enough to insure quality. Next, need to determine the minimum frequency for
testing
• What about M252? Information could be used
6) 2:10 PM-2:20 PM: Industry Concerns
a) Panametric checks for wall thickness – calibration frequency? Would we
consider a Task Group for looking into SP01 and Work Plan? Yes b) AASHTO Specs. referencing NTPEP? – Will investigate
c) NYDOT – Consider bringing ASTM F894 & F714 pipe into NTPEP? Need to
investigate first and then develop a Task Force.
7) 2:20 PM-2:45 PM: Open Discussion
a) English Units vs. Metric – Metric is referenced by the spec. and Comparison
Reports show English Units. b) How are DOTs using the data from the audit? Various ways
8) 2:45 PM-3:05 PM: Review of Action Items for 2017 - Done
9) 3:05 PM Adjourn
NTPEP’s Role: The National Transportation Product Evaluation Program (NTPEP) does not approve products. The audit programs evaluate a Manufacturer’s quality system manual and ensure that it is being followed during day-to-day production. Additionally, random samples of the materials listed in the Project Work Plan are selected for testing with the results uploaded into DataMine for the State DOT’s and the audited Manufacturer to use however they see fit. Once the audit and testing is complete, the Manufacturer is listed as “Compliant” on DataMine which the States may use to assist with populating a qualified product/producer list (QPL). Keep in mind that States may have additional requirements in order to be added to their QPL.
2017 Annual NTPEP Meeting
Seaport Hotel & World Trade Center
Boston, Massachusetts
Committee Name: NTPEP-Technical Committee on Thermoplastic Pipe (HDPE, PPP, PVC):
Name Email Address Agency Name Designation
Member Type
Meggers, Dave [email protected] Kansas Department of
Transportation
Chair Voting
Ashurst Jr., Kean Hart [email protected] Kentucky Transportation Center Chair Voting
Short, Temple [email protected] South Carolina Department of
Transportation
Chair Voting
Mueller, Matt. [email protected] American Association of State
Highway and Transportation
Officials
Liaison None
Eames, Alexandra Louise [email protected] American Association of State
Highway and Transportation
Officials
AASHTO Staff None
Ingram, Steven [email protected] Alabama Department of
Transportation
Member Voting
Jenkins, Andre Lemar [email protected] Alabama Department of
Transportation
Member Non-Voting
Sullivan, Paul E. [email protected] Arizona Department of
Transportation
Member Voting
Mroczkowski, Andrew [email protected] Connecticut Department of
Transportation
Member Voting
Knight, Chase [email protected] Florida Department of
Transportation
Member Voting
Douds, Richard [email protected] Georgia Department of
Transportation
Member Voting
Rotherham, Brad [email protected] Illinois Department of
Transportation
Member Voting
Anderson, Kenny [email protected] Indiana Department of
Transportation
Member Voting
Jones, Kevin [email protected] Iowa Department of Transportation Member Voting
Abernathy, Bruce Lee [email protected] Maryland Department of
Transportation
Member Voting
Therese R. Kline [email protected] Michigan Department of
Transportation
Member Voting
Meyerhoff, Mike [email protected]
.gov
Missouri Department of
Transportation
Member Voting
Seward, Kenny R. [email protected] Oklahoma Department of
Transportation
Member Voting
Zwanka, Merrrill E [email protected] South Carolina Department of
Transportation
Member Non-Voting
2017 Annual NTPEP Meeting
Seaport Hotel & World Trade Center
Boston, Massachusetts
Shi, Bin [email protected] Utah Department of Transportation Member Voting
Schuler, John [email protected]
v
Virginia Department of
Transportation
Member Voting
Lilla, Edward [email protected] Wisconsin Department of
Transportation
Member Voting
Paredes, Mario [email protected] TRI (NTPEP Designated
Laboratory
Other Non-Voting
Villarreal, Daniel [email protected]
m
Microbac (NTPEP Designated
Laboratory
Other Non-Voting
McElfresh, Terry Terry.McElfresh@ads-
pipe.com
ADS, Inc. Other Non-Voting
Baryluk, Greg R [email protected] ADS, Inc. Other Non-Voting
Chestnut, Brian W bchestnut@lane-
enterprises.com
Lane Enterprises, Inc. Other Non-Voting
Baker, Dan [email protected] Springfield Plastics Other Non-Voting
Keller, Jason [email protected] Contech Engineered Solutions Other Non-Voting
Currence, Dan [email protected] PPI Other Non-Voting