Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Research ArticleThe Principle-Agent Conflict Problem in a Continuous-TimeDelegated Asset Management Model
Yanan Li and Chuanzheng Li
School of Finance Capital University of Economics and Business Beijing 100070 China
Correspondence should be addressed to Yanan Li 415758824qqcom
Received 9 July 2021 Revised 6 August 2021 Accepted 17 August 2021 Published 26 August 2021
Academic Editor Xiaofeng Zong
Copyright copy 2021 Yanan Li and Chuanzheng Li is is an open access article distributed under the Creative CommonsAttribution License which permits unrestricted use distribution and reproduction in anymedium provided the original work isproperly cited
is paper considers the principle-agent conflict problem in a continuous-time delegated asset management model when theinvestor and the fundmanager are all risk-averse with risk sensitivity coefficients cf and cm respectively Suppose that the investorentrusts his money to the fund manager e return of the investment is determined by the managerrsquos effort level and incentivestrategy but the benefit belongs to the investor In order to encourage the manager to work hard the investor will determine themanagerrsquos salary according to the terminal income is is a stochastic differential game problem and the distribution of incomebetween the manager and the investor is a key point to be solved in the custodymodele uncertain form of the incentive strategyimplies that the problem is different from the classical stochastic optimal control problem In this paper we first express theinvestorrsquos incentive strategy in term of two auxiliary processes and turn this problem into a classical one en we employ thedynamic programming principle to solve the problem
1 Introduction
Since professional asset management institutions can makeefficient investment decisions save investorsrsquo time and effortand simplify the investment process more andmore investorsnow entrust their money to fund managers securities firmsand other asset management organizations Nowadaysscholars pay more and more attention to asset managementproblems We can refer to [1ndash5] to name just a few
e whole asset management process involves twoparties the investor and the manager e return of theinvestment is closely related to the managerrsquos effort level andinvestment strategy but the interests belong to the investorSo the investor and managerrsquos relation poses a principal-agent conflict An important part of discussing the assetmanagement problem is finding the investorrsquos optimal in-centive mode under the principle agent conflict
ere are many papers committed to solving principal-agent conflict problems Most of the early literature studiesinvestigate the discrete-time case (we can refer to [6ndash8] or asummary book [9]) e problem in continuous-time
models is discussed for the first time in [10] It points outthat the investorrsquos optimal incentive mode is linear Seereferences [11ndash14] for further work In recent years themaximum principle or the martingale representation the-orem is often used to solve this problem in continuous-timemodels For the literature using the maximum principle wecan refer to [15 16] and for the literature of using themartingale representation theorem we can refer to [17 18]However since this problem often needs to solve a backwardstochastic differential equation (BSDE) that rarely has ex-plicit solutions there are few articles which give analyticalsolutions to this problem In order to get explicit solutions ofprincipal-agent conflict problems the authors of [19] ex-press the investorrsquos incentive strategy in terms of twoauxiliary processes and turn the principle agent probleminto a classical stochastic differential game problem
Although there are many papers committed to solvingprincipal-agent conflict problems in continuous-timemodels the delegated asset management problems areusually investigated in discrete-time models for the sake ofsimplicity us there are some contributions in this paper
HindawiMathematical Problems in EngineeringVolume 2021 Article ID 3770868 10 pageshttpsdoiorg10115520213770868
(i) is paper considers the delegated asset manage-ment problem in a continuous-time model
(ii) Learning from [19] this paper gives explicit valuefunctions and the optimal strategies of both sides byexpressing the investorrsquos incentive strategy in termsof two auxiliary processes and turning the probleminto a classical stochastic differential game problem
(iii) In order to make the model more realistic thispaper brings in risk sensitivity coefficients to rep-resent the subjectsrsquo risk aversion attitudes
is paper is organized as follows In Section 2 weestablish a continuous-time model of the fund managementproblem In Section 3 we discuss the managerrsquos optimiza-tion problem under fixed investorrsquos incentive strategy Bysubstituting the managerrsquos optimal strategy into the inves-torrsquos optimal problem both the investor and the managerrsquosoptimal strategies are obtained in Section 4
2 The Principal-Agent Conflict Model
Similar to the model in [20] let us assume that the investoremploys a professional fund controller (manager) to investand the investor will get a profit and pay the manager at theterminal moment T Since the managerrsquos effort level cannotbe observed the investor will determine the managerrsquos salaryaccording to the terminal profit of the investment einvestorrsquos return is determined by the terminal investmentprofit and the managerrsquos salary e terminal investmentprofit is related to the managerrsquos investment strategy andeffort level and the incentive mechanism largely determinesthe managerrsquos strategy erefore the investor needs to findthe optimal incentive mechanism (the managerrsquos salary) tomaximize his terminal net income Meanwhile according tothe investorrsquos incentive mechanism the manager shall de-cide his investment strategy and the best effort level tomaximize his net salary (terminal salary minus effort cost)is is a non-cooperative game problem Next let us build amathematical model of this problem in probability space(ΩF P)
Similar to the model in [18] we suppose that themanagerrsquos effort will affect the fund income Rn
t whichsatisfies
dRnt R
nt r + μ + nt( 1113857dt + σdW(t)1113858 1113859 (1)
where μge 0 σ ge 0 and rgt 0 is the risk-free interest rateW(t) is a Brownian motion on (ΩF P) and nt1113864 1113865tge0 is themanagerrsquos effort level Here for the convenience of cal-culation we assume that the drift coefficient of Rn
t is a linearfunction of the managerrsquos effort level In fact as long as thedrift coefficient of Rn
t has the form of Rnt (r + f(nt)) for
some function f(n) the same method in this paper can beused after replacing n with f(n) For more general forms ofthe drift coefficient of Rn
t the existence of the time valuemakes it hard to obtain explicit solutions
Considering the managerrsquos strategy π (bπt nπt ) where
bπt represents the wealth that the manager decides to operateat moment t(e manager may not want to operate all the
wealth since the cost of the effort will increase with thewealth operated increases e money left will get a risk-freereturn) and nπ
t represents the managerrsquos effort level at t Bysome simple calculations we can get that the investmentincome under this strategy satisfies
dXπt rX
πt + b
πt μ + n
πt( 1113857( 1113857dt + b
πt σdW(t) (2)
Define the natural filtration produced by W(t) asFW
t1113864 1113865tge0 Now let us give the definition of both the managerand the investorrsquos admissible strategies Considering themanagerrsquos strategy π (bπt nπ
t ) If bπt and nπt are bounded
positive predictable stochastic processes under the strategyπ (2) has a unique solution
We call that strategy π (bπt nπt ) is admissible Denote
the set of all the managerrsquos admissible strategies by Π
Remark 1 Here we do not consider the case when b 0 orn 0 since in that case the model is meaningless
Suppose that the investorrsquos incentive strategy is afunction of the investment income at T and denote it byw(middot) If supπisinΠE[w(Xπ
T)]ltinfin the managerrsquos value functionunder w(middot) is a decreasing convex function with respect tothe initial wealth we say thatw(middot) is the investorrsquos admissiblestrategy Denote the set of all the investorrsquos admissiblestrategies by 1113954Π
Now let us analyze the whole game process Referring to[15] we know that investors play a leading role in the gameManagers need to decide their effort level and investmentstrategy according to the investorsrsquo incentive strategyerefore first we need to fix w(middot) and investigate themanagerrsquos optimal problem We can get the managerrsquosoptimal effort and investment strategy in terms of w(middot) as abyproduct en by substituting the managerrsquos optimalstrategy into the wealth process we can solve the investorrsquosoptimal problem by using the dynamic programmingprinciple
erefore firstly we fix the investorrsquos incentivestrategy w(middot) and consider the managerrsquos optimal problemSuppose that the manager is risk-averse and denote hisrisk sensitivity coefficient by cm lt 0 Referring to [18] wesuppose that the manager needs to pay (θn2b2) to manageb units of capital in unit time under the effort level n Hereθgt 0 is a constant which represents the effort cost pa-rameter e objective of the manager is to find the op-timal effort level and investment strategy to maximize hisnet income (salary minus effort cost) which is equivalentto minimize
Jπm(t x w) E e
cm w XπT( )minus 1113946
T
te
r(Tminus t) θ nπt( 1113857
221113872 1113873bπt dt1113888 1113889
|Xπt x
⎡⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎣
⎤⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎦
(3)Denote the managerrsquos optimal strategy by πw then the
value function is
Vm(t x w) infπisinΠ
Jπm(t x w) J
πw
m (t x w) (4)
2 Mathematical Problems in Engineering
Suppose that the investor is risk-averse too his risk-sensitive coefficient is cf lt 0 Next we consider the inves-torrsquos optimal problem
If the managerrsquos salary is too high the investorrsquos incomewill be reduced If the managerrsquos salary is too low themanagerrsquos enthusiasm wanes which also deduces the in-vestorrsquos terminal income erefore the investor needs tofind a reasonable incentive strategy to maximize his netincome that is minimize
Jwf(t x) E e
cf XwT
minus w XwT( )( )|X
wt x1113876 1113877 (5)
where Xwt is the investment income process under strategy
πw us the investorrsquos value function is
Vf(t x) infwisin1113954Π
Jwf(t x) (6)
Remark 2 e problem discussed above is not a standardstochastic optimal control problem since the form of w(middot) isuncertain and we cannot solve it directly by using standardstochastic optimal methods In Section 3 we give anotherform of the incentive strategy and transform the gameproblem into a classical one en we can use the dynamicprogramming principle to solve the problem
3 The Managerrsquos Optimization Problem
Define Dt er(Tminus t) β(t π) cmDt(θnπ2t 2)bπt and
Γ(t T π) eminus 1113938
T
tβ(uπ)du en Jπm(t x w) can be denoted
by
Jπm(t x w) E Γ(t T π)e
cmw XπT( )|X
πt x1113876 1113877 (7)
Using the results of Section 34 in [21] we know thatunder the incentive strategy w(middot) the managerrsquos valuefunction Vm(t x w) satisfies the HJB equation
minus Vmt(t x w) infπisinΠ
minus β(t π)Vm(t x w) + rx + bπt μ + n
πt( 11138571113858 11138591113864
Vmx(t x w) +bπ2t σ2
2Vmxx(t x w)1113897
(8)
and the boundary condition
Vm(T x w) ecmw(x)
(9)
Since Vm(t x w) is a decreasing convex function of xfor forall(t x y z c) isin [0 T) times R times [0infin) times (minus infin 0) times (0infin)we can define the Hamiltonian function
H(t x y z c) infngt0bgt0
h(t x y z c n b) (10)
where
h(t x y z c n b) minus Dt
cmθn2b
2y +(rx + b(μ + n))z +
b2σ2
2c
(11)
Theorem 1
nlowastyzct
z
θcmyDt
(12)
blowastyzct
minus μ + nlowastyzct 2( 1113857( 1113857
σ2z
c (13)
is the minimum point of h in (10)
Proof According to the definition we know that h is aconvex function of (n b) So the minimum point of h in (10)is the stable point under constraint conditions ngt 0 bgt 0 Bysome simple calculations we have
hn(n b t x y z c) minus θDtbncmy + bz
hb(n b t x y z c) σ2cb +(μ + n)z minusDtθncmy
2
(14)
Combining the above two equations we can obtain thestable point of h
nlowastyzct
z
θcmyDt
gt 0
blowastyzct
minus μ + nlowastyzct 2( 1113857( 1113857
σ2z
cgt 0
(15)
e proof is done
Remark 3 In this case the optimal investment strategy issimilar to that without principal-agent relationships eonly difference is that the numerator of the optimal in-vestment strategy is changed from (μ + n
lowastyzct ) into
(μ + (nlowastyzct 2)) Clearly this is due to the existence of the
agency relationship
Apparently the investorrsquos incentive strategy and themanagerrsquos value function are one-to-one In the followingwe will use auxiliary stochastic processes (Zt Γt) to deter-mine the managerrsquos value function and transform the in-vestorrsquos incentive strategy into (Zt Γt) en the problem inSection 2 can be translated into a classical stochastic optimalcontrol problem
First let us give the space of auxiliary stochastic pro-cesses (Z Γ) Fix t isin [0 T) let Z [t T] timesΩ⟶(minus infin 0) Γ [t T] timesΩ⟶ (0infin) be FW-predicable pro-cesses which satisfy
E 1113946T
tZ2sσ
2s + Γsσ
2s1113872 1113873ds1113890 1113891lt +infin (16)
Mathematical Problems in Engineering 3
Denote the set of all the processes satisfying the aboveconditions by V(t)
For some (Z Γ) isinV(t) and Yt ge 0 define theFW-progressively measurable process YZΓ on the filtrationspace (ΩF P FW
t1113864 1113865tge0) by
YZΓs Yt minus 1113946
s
tH r Xr Y
ZΓr Zr Γr1113872 1113873dr
+ 1113946s
tZrdXr +
12
1113946s
tΓrdlangXrangr s isin [t T]
(17)
where Xr is the investment income process Clearly forfixed Yt Z Γ YZΓ
T is only related to the investment incomeprocess and is FT measurable suppose that it is an in-centive strategy (we prove it in Corollary 1) In the fol-lowing we give the relationship between YZΓ
s and themanagerrsquos value function First we give the followinglemma
Lemma 1 Define
πlowastZΓ blowastZΓ
nlowastZΓ
1113872 1113873
blowastYZΓ
t ZtΓtt1113882 1113883
tge0 nlowastYZΓ
t ZtΓtt1113882 1113883
tge01113874 1113875
(18)
and then we have πlowastZΓ isin Π
Proof On the one hand since Z Γ YZΓ are all predictablestochastic processes referring to (12) and (13) we can getthat blowastZΓ and nlowastZΓ are bounded positive predictable sto-chastic processes On the other hand b
lowastyzct and n
lowastyzct are
independent of x Taking blowastZΓ and nlowastZΓ into (2) we can getthe Lipschitz continuity and linear growth of the coefficientsin (2) with respect to Xt then (2) has a unique solution eproof is done
Denote the investment income process under πlowastZΓ byXlowastZΓ We also have the following theorem
Theorem 2 Denote the managerrsquos value function with aterminal return (lnYZΓ
T cm) by Vm(t x YZΓT ) We can ob-
tain that
Yt Vm t x YZΓT1113872 1113873 (19)
Furthermore the managerrsquos optimal strategy is πlowastZΓ
Proof forallπ isin Π s isin [t T] we have
YZΓs Yt minus 1113946
s
tH r X
πr Y
ZΓr Zr Γr1113872 1113873dr
+ 1113946s
tZrdX
πr +
12
1113946s
tΓrdlangX
πrangr
(20)
Using Itorsquos formula we have
deminus 1113946
r
tβ(u π)du
YZΓr e
minus 1113946r
tβ(u π)du
minus H r Xπr Y
ZΓr Zr Γr1113872 11138731113960
+ rXπr + b
πr μ + n
πr( 1113857( 1113857Zr
+bπ2r σ2
2Γr minus β(r π)1113891dr
+ eminus 1113946
r
tβ(u π)du
σZrdW(r)
(21)
It follows from (16) that eminus 1113938
r
tβ(uπ)duσZrdW(r) is a
martingale Integrating and taking expectations on bothsides of (21) we can get
Yt geE eminus 1113946
T
tβ(u π)du
YZΓT |X
πt x
⎡⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎣⎤⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎦ J
πm t x Y
ZΓT1113872 1113873
(22)
Furthermore by simple calculations under πlowastZΓ isin Πwe have
dYZΓt β t πlowastZΓ
1113872 1113873YZΓt dt + b
lowastYZΓt ZtΓt
t ZtσdWt (23)
Using (23) and Itorsquos formula we can obtain
deminus 1113946
r
tβ u πlowastZΓ
1113872 1113873duY
ZΓr e
minus 1113946r
tβ u πlowastZΓ
1113872 1113873dublowastYZΓ
t ZtΓtt ZtσdWt
(24)
With similar methods integrating and taking expecta-tions on both sides of (24) we have
Yt E eminus 1113946
T
tβ u πlowastZΓ
1113872 1113873duY
ZΓT |XlowastZΓt x
⎡⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎣⎤⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎦
JπlowastZΓ
m t x YZΓT1113872 1113873ge J
πm t x Y
ZΓT1113872 1113873
(25)
is implies that πlowastZΓ is the managerrsquos optimal strategyand
Yt Vm t x YZΓT1113872 1113873 (26)
Up till now fixing (Z Γ) isin V(t) we can get themanagerrsquos optimal strategy and represent the managerrsquosvalue function In Section 4 we begin to consider the in-vestorrsquos optimization problem at is finding the optimal(Z Γ) isin V(t) to maximize the investorrsquos net profit
4 The Investorrsquos Optimization Problem
Suppose that the investorrsquos wealth is x at t Apparently theinvestorrsquos value function is uniquely determined by thewealth process and the managerrsquos value function So the
4 Mathematical Problems in Engineering
objective of the investor is to find the optimal (Z Γ) isinV(t)
to minimize his value function Define
v(t x y) inf(ZΓ)isinV(t)
E ecf XlowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
πt x Y
ZΓt y1113876 1113877
(27)
Referring to eorem 41 in [19] we know that if As-sumption 32 Assumption 43 and Assumption 44 in [19]hold the investorrsquos value function satisfies
Vf(t x) infyisin 0ecmR[ ]
v(t x y) (28)
Here R is the minimum pay in order to make sure thatthe manager takes the job
Section 41 gives the verification of the threeassumptions
41 7e Verification of Assumptions
Assumption 1 (Assumption 32 in [19]) H has at least oneextreme point (b
lowastyzct n
lowastyzct ) For any t isin [0 T]
(Z Γ) isin V(t) we have πlowastZΓ isin Π
Proof is is the result of eorem 1 and Lemma 1e Hamiltonian function can be expressed as
H(t x y z c) infbgt0
F(t x y z b) +b2σ2
2c1113896 1113897 (29)
Here
F(t x y z b) infngt0
minus Dt
cmθn2b
2y +(rx + b(μ + n))z1113896 1113897
(30)
Define
YZs Yt minus 1113946
s
tF r Xr Y
Zr Zr1113872 1113873dr + 1113946
s
tZrdXr s isin [t T]
(31)
and we have the following assumption
Assumption 2 (Assumption 43 in [19]) F has at least oneextreme point n
lowastyzbt furthermore (b nlowastY
ZZb) isin Π
Proof On the one hand the right hand of F is a parabolawith an opening up with respect to n so the minimum pointis attained at the axis of the parabola (zDtcmθy) that isnlowastyzbt (zDtcmθy) On the other hand since Zlt 0 is
predictable we can get that nlowastYZ
t Ztbt (bZtDtcmθbYZ
t ) is apositive predictable process Furthermore b and n
lowastyzbt are
independent of x is implies the Lipschitz continuity andlinear growth of the coefficients in (2) with respect to theinvestment income process then (2) has a uniquesolution
Assumption 3 (Assumption 44 in [19]) forallbgt 0 (1b2σ2) isbounded
Proof We can get the result directly from σ gt 0 bgt 0
427e Investorrsquos Value Function Clearly as soon as we getv(t x y) we can obtain Vf(t x) e following theoremgives the partial differential equation satisfied by v(t x y)
Theorem 3 v(t x y) is the viscosity solution of
minus vt(t x y) inf(ZΓ)isinV(t)
G(t x y Z Γ) (32)
v(T x y) ecfx
yminus cfcm( 1113857
(33)
where
G(t x y Z Γ) rx + blowastZΓt μ + n
lowastZΓt1113872 11138731113960 1113961vx
+σ2 blowastZΓt1113872 1113873
2
2vxx +
Dtcmθ nlowastZΓt1113872 1113873
2
2blowastZΓt yvy
+σ2 blowastZΓt1113872 1113873
2
2Z2vyy + σ2 b
lowastZΓt1113872 1113873
2Zvxy
(34)
Proof By the definition of v(t x y) we can obtain that itsatisfies (33) Furthermore according to the dynamic pro-gramming principle we have
v(t x y) inf(ZΓ)isinV(t)
v t + h XlowastZΓt+h Y
ZΓt+h1113872 1113873 (35)
By using Itorsquos formula with respect to v(s XlowastZΓs YZΓ
s )
from t to t + h we have
v t + h XlowastZΓt+h Y
ZΓt+h1113872 1113873 v(t x y) + 1113946
t+h
tvt s X
lowastZΓs Y
ZΓs1113872 1113873
+ G s XlowastZΓs Y
ZΓs Zs Γs1113872 1113873ds
(36)
Combining with the above two equations we can get
vt(t x y) + inf(ZΓ)isinV(t)
G(t x y Z Γ) 0 (37)
at is v(t x y) satisfies (32) e proof is doneNext we are going to solve (32) and (33) Considering
the boundary condition we guess
v(t x y) ecfDtxy
minus cfcm( 1113857E(t) (38)
where E(t) is a function of t which satisfies E(T) 1If the variables in the solution can be separated from
each other (32) can be easily solved However (32) containsecfDtx which is a cross term of t and x To cancel the crossterm we introduce zt DtX
lowastZΓt Using Itorsquos formula we
can get
dzt minus rDtXlowastZΓt dt + DtdX
lowastZΓt
DtblowastZΓt μ + n
lowastZΓt1113872 1113873dt + σdW(t)1113960 1113961
(39)
Mathematical Problems in Engineering 5
We can also obtain zT XlowastZΓT Define
V(t z y) inf(ZΓ)isinV(t)
E ecf zTminus lnYZΓ
Tcm( )( )|zt z1113876 1113877
inf(ZΓ)isinV(t)
E ecf X lowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
lowastZΓt
z
Dt
1113890 1113891
v tz
Dt
y1113888 1113889
(40)
Obviously solving v(t x y) is equivalent to solvingV(t z y) Using a similar method as the one in eorem 3we can get that
minus Vt inf(ZΓ)isinV(t)
minusμ + n
lowastZΓt 21113872 11138731113872 1113873 μ + n
lowastZΓt1113872 1113873
σ2Dt
Z
ΓVz
⎧⎨
⎩
minuscmθ n
lowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2σ2yDt
Z
ΓVy
+μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2D
2t
Z2
Γ2Vzz
+nlowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2cmθyDt( 1113857
2Z2
Γ2Vyy
+nlowastZΓt μ + n
lowastZΓt 21113872 11138731113872 1113873
2
σ2cmθyD
2t
Z2
Γ2Vzy
⎫⎪⎬
⎪⎭
(41)
V(T z y) ecfz
yminus cfcm( 1113857
(42)
e first step in solving (41) is to find its minimum pointDefine MZΓ (ZΓ) it is shown in Section 3 that (Z Γ) and(MZΓ nlowastZΓ) are one-to-one en (41) is transformed into
minus Vt inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMVz1113896
+(μ +(n2))
2
2σ2D
2t M
2Vzz minus
cmθn2(μ +(n2))
2σ2yDtMVy
+n2(μ +(n2))
2
2σ2cmθyDt( 1113857
2M
2Vyy
+n(μ +(n2))
2
σ2cmθyD
2t M
2Vzy1113897
(43)
Now the problem of finding the minimum point in (41) ischanged into a problem of finding theminimumpoint in (43)
According to (38) we suppose thatV(t z y) E(t)ecfzyminus (cfcm) By some simple calculationswe can get that
Vz(t z y) cfV(t z y)
Vzz(t z y) c2fV(t z y)
yVy(t z y) minuscf
cm
V(t z y)
y2Vyy(t z y)
cf cf + cm1113872 1113873
c2m
V(t z y)
yVzy(t z y) minusc2f
cm
V(t z y)
(44)
Taking them into (43) we have
minus Eprime(t)V(t z y) inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMcf1113896
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
21113897E(t)V(t z y)
(45)
Since the right hand of (45) is continuous the minimumpoint can only be attained at the stable points or theboundary points which depends on the parameter valuesDenote the minimum point of (45) by (nlowastt Mlowastt ) and denotethe corresponding minimum point of (41) by (Zlowastt Γlowastt ) It isshown from the Appendix that nlowastt and DtM
lowastt are constants
concerning μ θ cf and cm Let nlowastt nlowast
Remark 4 On the one hand the exponential form of theobjective function implies that blowastt is independent of Xlowastt Onthe other hand the benefit and the cost brought by themanagerrsquos effort are only related to blowastt so nlowastt is independentof Xlowastt Furthermore in this paper we consider the dis-counted benefit and cost brought by the managerrsquos effort sonlowastt is independent of t
Remark 5 It is shown from figures in the Appendix that nlowast
decreases with an increase in μ(the drift coefficient of thefund wealth process) θ(the effort cost coefficient) and|cm|(the managerrsquos risk aversion level) It increases with anincrease in |cf|(the investorrsquos risk aversion level)
6 Mathematical Problems in Engineering
Remark 6 Define Ylowastt Vm(t x YZlowastΓlowastT ) considering (12)
and (13) we can get that (Zlowastt Ylowastt ) θcmDtnlowast and Dtb
lowastt
(minus (μ + (nlowast2))σ2)DtMlowastt are constants
Taking the minimum point into (45) and solving it wecan get
V(t z y) eB(Tminus t)
ecfz
yminus cfcm( 1113857
(46)
Here
B minusμ + n
lowast2( 1113857( 1113857 μ + nlowast
( 1113857
σ2DtMlowastt cf
+μ + n
lowast2( 1113857( 11138572
2σ2D
2t Mlowast 2t c
2f +
cfθnlowast2 μ + n
lowast2( 1113857( 1113857
2σ2DtMlowastt
+nlowast2 μ + n
lowast2( 1113857( 11138572
2σ2θ2D2
t Mlowast 2t cf cf + cm1113872 1113873
minusnlowast μ + n
lowast2( 1113857( 11138572
σ2c2fθD
2t Mlowast 2t
(47)
0 000
002
004
006
008
010
n
035 040 045030the drift coefficient of the fund
0ndash
000
002
004
006
008
010
n
20 25 3010 15The effort cost coefficient
0
000
002
004
006
008
010
n
020 025 030015The managerrsquos risk aversion level
0
011 012 013 014 015010The investorrsquos risk aversion level
000
002
004
006
008
010
n
Figure 1 e effects of parameters on the optimal effort level
Mathematical Problems in Engineering 7
is a constant As a consequence we can also get the followingresults
v(t x y) eB(Tminus t)
ecfDtxy
minus cfcm( 1113857
Vf(t x) v t x ecmR
1113872 1113873 eB(Tminus t)
ecf Dtxminus R( )
(48)
43 7e Investorrsquos Excitation Mechanism In this section letus analyze the investorrsquos excitation mechanism DenoteYlowastt YZlowastΓlowast
t From the above analysis we know that
dYlowastt
Dtcmθnlowast2
blowastt Ylowastt
2dt + b
lowastt Zlowastt σdWt
Ylowastt e
cmR
(49)
Using Itorsquos formula we have
d lnYlowastt
Dtcmθnlowast2
blowastt
2dt + b
lowastt
Zlowastt
Ylowastt
σdWt minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
dt
(50)
Furthermore we can get that the investment incomeunder nlowast and blowastt satisfies
dXlowastt rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt + blowastt σdWt (51)
which implies
d lnYlowastt
Dtcmθnlowast2
blowastt
2minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
1113888 1113889dt +Zlowastt
Ylowastt
dXlowastt minus rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt( 1113857
cm
Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 11138571113888 1113889dt
+ cmθnlowastDt dX
lowastt minus rX
lowastt dt( 1113857
(52)
Define constant
A Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 1113857gt 0
(53)
and then we can obtaind lnY
lowastt cmAdt + cmθn
lowastDt dX
lowastt minus rX
lowastt dt( 1113857 cm Adt + θn
lowastdDtXlowastt( 1113857
(54)
So
lnYlowastT minus cmR cm A(T minus t) + n
lowastθ XlowastT minus Dtx( 11138571113858 1113859 (55)
can be deduced immediately Since lnYT cmw(XT) wecan get the strategy
w XT( 1113857 A(T minus t) + nlowastθ XlowastT minus Dtx( 1113857 + R (56)
It is a linear function of XlowastT minus Dtx which is the dis-counted profit of the investment
Remark 7 It follows from the above results that the man-agerrsquos wages increase with the increase of the cost coefficientthe effort level and the discounted profit of the investmentFurthermore the longer the work the higher the salary It isconsistent with reality
We can also get the following corollary
Corollary 1
Ylowasts Vm s X
lowasts YlowastT( 1113857 e
cm R+A(Tminus t)+nlowastθ Xlowasts minus Dtx( )[ ] (57)
is implies that Vm(s Xlowasts YlowastT) is a decreasing convexfunction of Xlowasts us the assumption in Section 2 that YlowastT isan incentive strategy is proved
Appendix
Define
I(n M t) minus(μ +(n2))(μ + n)
σ2DtMcf
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
2
(A1)
We know that there are three kinds of points which maybe the minimum point of (45)
8 Mathematical Problems in Engineering
(i) e points which satisfy In(n M t) 0 IM
(n M t) 0(ii) e points which satisfy n 0 IM(0 M t) 0(iii) e points which satisfy M 0 In(n 0 t) 0
With parameters fixed we can easily decide which is theminimum point of (45) In the following we will investigatethe form of those points
e first kind of points (n1t M1t) is the solution of thefollowing equations
In(n M t) minusDtcf
σ232μ + n1113874 1113875M
+Dtcfθ
2σ232n2
+ 2μn1113874 1113875M +D
2t c
2f
2σ2μ +
n
21113874 1113875M
2
+θ2D2
t cf cf + cm1113872 1113873
2σ2n3
+ 3μn2
+ 2μ2n1113872 1113873M2
minusc2fθD
2t
σ23n
2
4+ 2μn + μ21113888 1113889M
2 0
(A2)
IM(n M t) minusDtcf
σ2(μ + n) μ +
n
21113874 1113875
+Dtcfθ
2σ2n2 μ +
n
21113874 1113875 +
D2t c
2f
σ2μ +
n
21113874 1113875
2M
+θ2D2
t cf cf + cm1113872 1113873
σ2n2 μ +
n
21113874 1113875
2M
minus2c
2fθD
2t
σ2n μ +
n
21113874 1113875
2M 0
(A3)
We can deduce from (A2) that
DtM1t n1t + μ minus n
21tθ21113872 1113873 +(μ2) minus θn
21t41113872 1113873 minus θμn1t
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf minus cf21113872 1113873 + cfθμ minus cfθn1t21113872 1113873 + θ2μ cf + cm1113872 1113873n1t1113960 1113961
(A4)
It also follows from (A3) that
DtM1t n1t + μ minus n1t( 1113857
2θ21113872 1113873
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t1113872 1113873
2θ2 cm + cf1113872 1113873 + cf1113876 1113877
(A5)
Combining the above two equations we can get that
n1t + μ minusn1t( 1113857
2θ2
1113888 1113889 minuscf
2+ cfθμ minus
cfθn1t
2+ θ2μ cf + cm1113872 1113873n1t1113890 1113891
+θn
21t
4+ θμn1t minus
μ2
1113888 1113889 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf1113960 1113961 0
(A6)
Clearly by solving (A5) and (A6) we can get that n1 andDtM1t are constants
Denote the second kind of point by (0 M2t) us M2t
satisfies (A5) with n replaced with 0 and we can get thatDtM2t is a constant
Denote the third kind of points by (n3t 0) ey satisfy(A4) By solving it we can get that n3t is a constant
Denote the minimum point of (45) by (nlowastt Mlowastt ) Itfollows from the above analysis that nlowastt and DtM
lowastt are all
constants For different μ θ cf and cm by calculating (A6)(A2) or (A3) we can get different nlowast
By using R we plot the following figures which indicatethe effect of μ θ cf and cm on nlowast (Figure 1)
Data Availability
No data were used to support this study
Conflicts of Interest
e authors declare that they have no conflicts of interest
Acknowledgments
is work was supported by the National Natural ScienceFoundation of China (11901404)
References
[1] A Almazan K C Brown M Carlson and D A ChapmanldquoWhy constrain your mutual fund managerrdquo Journal of Fi-nancial Economics vol 73 no 2 pp 289ndash321 2004
[2] M K Brunnermeier and L H Pedersen ldquoMarket liquidityand funding liquidityrdquo Review of Financial Studies vol 22no 6 pp 2201ndash2238 2009
[3] P H Dybvig H K Farnsworth and J N CarpenterldquoPortfolio performance and agencyrdquo Review of FinancialStudies vol 23 no 1 pp 1ndash23 2010
Mathematical Problems in Engineering 9
[4] S Gervais A W Lynch and D K Musto ldquoFund families asdelegated monitors of money managersrdquo Review of FinancialStudies vol 18 no 4 pp 1139ndash1169 2005
[5] V Guerrieri and P Kondor ldquoFund managers career con-cerns and asset price volatilityrdquo 7e American EconomicReview vol 102 no 5 pp 1986ndash2017 2012
[6] S Ross ldquoe economic theory of agency the principalrsquosproblemrdquo 7e American Economic Review vol 63 pp 134ndash139 1973
[7] J A Mirrlees ldquoe optimal structure of incentives and au-thority within an organizationrdquo7eBell Journal of Economicsvol 7 no 1 pp 105ndash131 1976
[8] B Holmstrom ldquoMoral hazard and observabilityrdquo 7e BellJournal of Economics vol 10 no 1 pp 74ndash91 1979
[9] P Bolton and M Dewatripont Contract 7eory MIT PressCambridge UK 2005
[10] B Holmstrom and P Milgrom ldquoAggregation and linearity inthe provision of intertemporal incentivesrdquo Econometricavol 55 no 2 pp 303ndash328 1987
[11] H Schattler and J Sung ldquoe first-order approach to thecontinuous-time principal-agent problem with exponentialutilityrdquo Journal of Economic7eory vol 61 no 2 pp 331ndash3711993
[12] H Schattler and J Sung ldquoOn optimal sharing rules in dis-crete-and continuous-time principal-agent problems withexponential utilityrdquo Journal of Economic Dynamics andControl vol 21 no 2-3 pp 551ndash574 1997
[13] H M Muller ldquoe first-best sharing rule in the continuous-time principal-agent problem with exponential utilityrdquoJournal of Economic 7eory vol 79 no 2 pp 276ndash280 1998
[14] H M Muller ldquoAsymptotic efficiency in dynamic principal-agent problemsrdquo Journal of Economic 7eory vol 91 no 2pp 292ndash301 2000
[15] J Cvitanic X Wan and J Zhang ldquoOptimal compensationwith hidden action and lump-sum payment in a continuous-time modelrdquo Applied Mathematics and Optimization vol 59pp 99ndash146 2009
[16] J Cvitanic and J Zhang Contract 7eory in Continuous TimeModels Springer-Verlag Berlin Germany 2013
[17] Y Sannikov ldquoA continuous-time version of the principal-agent problemrdquo7eReview of Economic Studies vol 75 no 3pp 957ndash984 2008
[18] Z He ldquoA Model of dynamic compensation and capitalstructurerdquo Journal of Financial Economics vol 100 no 2pp 351ndash366 2011
[19] J Cvitanic D Possamai and N Touzi ldquoDynamic pro-gramming approach to principal-agent problemsrdquo Financeand Stochastics vol 22 pp 1ndash37 2018
[20] Z He and W Xiong ldquoDelegated asset management invest-ment mandates and capital immobilityrdquo Journal of FinancialEconomics vol 107 no 2 pp 239ndash258 2013
[21] H Pham Continuous-time Stochastic Control and Optimi-zation with Financial Applications Springer-Verlag NewYork NY USA 2009
10 Mathematical Problems in Engineering
(i) is paper considers the delegated asset manage-ment problem in a continuous-time model
(ii) Learning from [19] this paper gives explicit valuefunctions and the optimal strategies of both sides byexpressing the investorrsquos incentive strategy in termsof two auxiliary processes and turning the probleminto a classical stochastic differential game problem
(iii) In order to make the model more realistic thispaper brings in risk sensitivity coefficients to rep-resent the subjectsrsquo risk aversion attitudes
is paper is organized as follows In Section 2 weestablish a continuous-time model of the fund managementproblem In Section 3 we discuss the managerrsquos optimiza-tion problem under fixed investorrsquos incentive strategy Bysubstituting the managerrsquos optimal strategy into the inves-torrsquos optimal problem both the investor and the managerrsquosoptimal strategies are obtained in Section 4
2 The Principal-Agent Conflict Model
Similar to the model in [20] let us assume that the investoremploys a professional fund controller (manager) to investand the investor will get a profit and pay the manager at theterminal moment T Since the managerrsquos effort level cannotbe observed the investor will determine the managerrsquos salaryaccording to the terminal profit of the investment einvestorrsquos return is determined by the terminal investmentprofit and the managerrsquos salary e terminal investmentprofit is related to the managerrsquos investment strategy andeffort level and the incentive mechanism largely determinesthe managerrsquos strategy erefore the investor needs to findthe optimal incentive mechanism (the managerrsquos salary) tomaximize his terminal net income Meanwhile according tothe investorrsquos incentive mechanism the manager shall de-cide his investment strategy and the best effort level tomaximize his net salary (terminal salary minus effort cost)is is a non-cooperative game problem Next let us build amathematical model of this problem in probability space(ΩF P)
Similar to the model in [18] we suppose that themanagerrsquos effort will affect the fund income Rn
t whichsatisfies
dRnt R
nt r + μ + nt( 1113857dt + σdW(t)1113858 1113859 (1)
where μge 0 σ ge 0 and rgt 0 is the risk-free interest rateW(t) is a Brownian motion on (ΩF P) and nt1113864 1113865tge0 is themanagerrsquos effort level Here for the convenience of cal-culation we assume that the drift coefficient of Rn
t is a linearfunction of the managerrsquos effort level In fact as long as thedrift coefficient of Rn
t has the form of Rnt (r + f(nt)) for
some function f(n) the same method in this paper can beused after replacing n with f(n) For more general forms ofthe drift coefficient of Rn
t the existence of the time valuemakes it hard to obtain explicit solutions
Considering the managerrsquos strategy π (bπt nπt ) where
bπt represents the wealth that the manager decides to operateat moment t(e manager may not want to operate all the
wealth since the cost of the effort will increase with thewealth operated increases e money left will get a risk-freereturn) and nπ
t represents the managerrsquos effort level at t Bysome simple calculations we can get that the investmentincome under this strategy satisfies
dXπt rX
πt + b
πt μ + n
πt( 1113857( 1113857dt + b
πt σdW(t) (2)
Define the natural filtration produced by W(t) asFW
t1113864 1113865tge0 Now let us give the definition of both the managerand the investorrsquos admissible strategies Considering themanagerrsquos strategy π (bπt nπ
t ) If bπt and nπt are bounded
positive predictable stochastic processes under the strategyπ (2) has a unique solution
We call that strategy π (bπt nπt ) is admissible Denote
the set of all the managerrsquos admissible strategies by Π
Remark 1 Here we do not consider the case when b 0 orn 0 since in that case the model is meaningless
Suppose that the investorrsquos incentive strategy is afunction of the investment income at T and denote it byw(middot) If supπisinΠE[w(Xπ
T)]ltinfin the managerrsquos value functionunder w(middot) is a decreasing convex function with respect tothe initial wealth we say thatw(middot) is the investorrsquos admissiblestrategy Denote the set of all the investorrsquos admissiblestrategies by 1113954Π
Now let us analyze the whole game process Referring to[15] we know that investors play a leading role in the gameManagers need to decide their effort level and investmentstrategy according to the investorsrsquo incentive strategyerefore first we need to fix w(middot) and investigate themanagerrsquos optimal problem We can get the managerrsquosoptimal effort and investment strategy in terms of w(middot) as abyproduct en by substituting the managerrsquos optimalstrategy into the wealth process we can solve the investorrsquosoptimal problem by using the dynamic programmingprinciple
erefore firstly we fix the investorrsquos incentivestrategy w(middot) and consider the managerrsquos optimal problemSuppose that the manager is risk-averse and denote hisrisk sensitivity coefficient by cm lt 0 Referring to [18] wesuppose that the manager needs to pay (θn2b2) to manageb units of capital in unit time under the effort level n Hereθgt 0 is a constant which represents the effort cost pa-rameter e objective of the manager is to find the op-timal effort level and investment strategy to maximize hisnet income (salary minus effort cost) which is equivalentto minimize
Jπm(t x w) E e
cm w XπT( )minus 1113946
T
te
r(Tminus t) θ nπt( 1113857
221113872 1113873bπt dt1113888 1113889
|Xπt x
⎡⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎣
⎤⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎦
(3)Denote the managerrsquos optimal strategy by πw then the
value function is
Vm(t x w) infπisinΠ
Jπm(t x w) J
πw
m (t x w) (4)
2 Mathematical Problems in Engineering
Suppose that the investor is risk-averse too his risk-sensitive coefficient is cf lt 0 Next we consider the inves-torrsquos optimal problem
If the managerrsquos salary is too high the investorrsquos incomewill be reduced If the managerrsquos salary is too low themanagerrsquos enthusiasm wanes which also deduces the in-vestorrsquos terminal income erefore the investor needs tofind a reasonable incentive strategy to maximize his netincome that is minimize
Jwf(t x) E e
cf XwT
minus w XwT( )( )|X
wt x1113876 1113877 (5)
where Xwt is the investment income process under strategy
πw us the investorrsquos value function is
Vf(t x) infwisin1113954Π
Jwf(t x) (6)
Remark 2 e problem discussed above is not a standardstochastic optimal control problem since the form of w(middot) isuncertain and we cannot solve it directly by using standardstochastic optimal methods In Section 3 we give anotherform of the incentive strategy and transform the gameproblem into a classical one en we can use the dynamicprogramming principle to solve the problem
3 The Managerrsquos Optimization Problem
Define Dt er(Tminus t) β(t π) cmDt(θnπ2t 2)bπt and
Γ(t T π) eminus 1113938
T
tβ(uπ)du en Jπm(t x w) can be denoted
by
Jπm(t x w) E Γ(t T π)e
cmw XπT( )|X
πt x1113876 1113877 (7)
Using the results of Section 34 in [21] we know thatunder the incentive strategy w(middot) the managerrsquos valuefunction Vm(t x w) satisfies the HJB equation
minus Vmt(t x w) infπisinΠ
minus β(t π)Vm(t x w) + rx + bπt μ + n
πt( 11138571113858 11138591113864
Vmx(t x w) +bπ2t σ2
2Vmxx(t x w)1113897
(8)
and the boundary condition
Vm(T x w) ecmw(x)
(9)
Since Vm(t x w) is a decreasing convex function of xfor forall(t x y z c) isin [0 T) times R times [0infin) times (minus infin 0) times (0infin)we can define the Hamiltonian function
H(t x y z c) infngt0bgt0
h(t x y z c n b) (10)
where
h(t x y z c n b) minus Dt
cmθn2b
2y +(rx + b(μ + n))z +
b2σ2
2c
(11)
Theorem 1
nlowastyzct
z
θcmyDt
(12)
blowastyzct
minus μ + nlowastyzct 2( 1113857( 1113857
σ2z
c (13)
is the minimum point of h in (10)
Proof According to the definition we know that h is aconvex function of (n b) So the minimum point of h in (10)is the stable point under constraint conditions ngt 0 bgt 0 Bysome simple calculations we have
hn(n b t x y z c) minus θDtbncmy + bz
hb(n b t x y z c) σ2cb +(μ + n)z minusDtθncmy
2
(14)
Combining the above two equations we can obtain thestable point of h
nlowastyzct
z
θcmyDt
gt 0
blowastyzct
minus μ + nlowastyzct 2( 1113857( 1113857
σ2z
cgt 0
(15)
e proof is done
Remark 3 In this case the optimal investment strategy issimilar to that without principal-agent relationships eonly difference is that the numerator of the optimal in-vestment strategy is changed from (μ + n
lowastyzct ) into
(μ + (nlowastyzct 2)) Clearly this is due to the existence of the
agency relationship
Apparently the investorrsquos incentive strategy and themanagerrsquos value function are one-to-one In the followingwe will use auxiliary stochastic processes (Zt Γt) to deter-mine the managerrsquos value function and transform the in-vestorrsquos incentive strategy into (Zt Γt) en the problem inSection 2 can be translated into a classical stochastic optimalcontrol problem
First let us give the space of auxiliary stochastic pro-cesses (Z Γ) Fix t isin [0 T) let Z [t T] timesΩ⟶(minus infin 0) Γ [t T] timesΩ⟶ (0infin) be FW-predicable pro-cesses which satisfy
E 1113946T
tZ2sσ
2s + Γsσ
2s1113872 1113873ds1113890 1113891lt +infin (16)
Mathematical Problems in Engineering 3
Denote the set of all the processes satisfying the aboveconditions by V(t)
For some (Z Γ) isinV(t) and Yt ge 0 define theFW-progressively measurable process YZΓ on the filtrationspace (ΩF P FW
t1113864 1113865tge0) by
YZΓs Yt minus 1113946
s
tH r Xr Y
ZΓr Zr Γr1113872 1113873dr
+ 1113946s
tZrdXr +
12
1113946s
tΓrdlangXrangr s isin [t T]
(17)
where Xr is the investment income process Clearly forfixed Yt Z Γ YZΓ
T is only related to the investment incomeprocess and is FT measurable suppose that it is an in-centive strategy (we prove it in Corollary 1) In the fol-lowing we give the relationship between YZΓ
s and themanagerrsquos value function First we give the followinglemma
Lemma 1 Define
πlowastZΓ blowastZΓ
nlowastZΓ
1113872 1113873
blowastYZΓ
t ZtΓtt1113882 1113883
tge0 nlowastYZΓ
t ZtΓtt1113882 1113883
tge01113874 1113875
(18)
and then we have πlowastZΓ isin Π
Proof On the one hand since Z Γ YZΓ are all predictablestochastic processes referring to (12) and (13) we can getthat blowastZΓ and nlowastZΓ are bounded positive predictable sto-chastic processes On the other hand b
lowastyzct and n
lowastyzct are
independent of x Taking blowastZΓ and nlowastZΓ into (2) we can getthe Lipschitz continuity and linear growth of the coefficientsin (2) with respect to Xt then (2) has a unique solution eproof is done
Denote the investment income process under πlowastZΓ byXlowastZΓ We also have the following theorem
Theorem 2 Denote the managerrsquos value function with aterminal return (lnYZΓ
T cm) by Vm(t x YZΓT ) We can ob-
tain that
Yt Vm t x YZΓT1113872 1113873 (19)
Furthermore the managerrsquos optimal strategy is πlowastZΓ
Proof forallπ isin Π s isin [t T] we have
YZΓs Yt minus 1113946
s
tH r X
πr Y
ZΓr Zr Γr1113872 1113873dr
+ 1113946s
tZrdX
πr +
12
1113946s
tΓrdlangX
πrangr
(20)
Using Itorsquos formula we have
deminus 1113946
r
tβ(u π)du
YZΓr e
minus 1113946r
tβ(u π)du
minus H r Xπr Y
ZΓr Zr Γr1113872 11138731113960
+ rXπr + b
πr μ + n
πr( 1113857( 1113857Zr
+bπ2r σ2
2Γr minus β(r π)1113891dr
+ eminus 1113946
r
tβ(u π)du
σZrdW(r)
(21)
It follows from (16) that eminus 1113938
r
tβ(uπ)duσZrdW(r) is a
martingale Integrating and taking expectations on bothsides of (21) we can get
Yt geE eminus 1113946
T
tβ(u π)du
YZΓT |X
πt x
⎡⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎣⎤⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎦ J
πm t x Y
ZΓT1113872 1113873
(22)
Furthermore by simple calculations under πlowastZΓ isin Πwe have
dYZΓt β t πlowastZΓ
1113872 1113873YZΓt dt + b
lowastYZΓt ZtΓt
t ZtσdWt (23)
Using (23) and Itorsquos formula we can obtain
deminus 1113946
r
tβ u πlowastZΓ
1113872 1113873duY
ZΓr e
minus 1113946r
tβ u πlowastZΓ
1113872 1113873dublowastYZΓ
t ZtΓtt ZtσdWt
(24)
With similar methods integrating and taking expecta-tions on both sides of (24) we have
Yt E eminus 1113946
T
tβ u πlowastZΓ
1113872 1113873duY
ZΓT |XlowastZΓt x
⎡⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎣⎤⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎦
JπlowastZΓ
m t x YZΓT1113872 1113873ge J
πm t x Y
ZΓT1113872 1113873
(25)
is implies that πlowastZΓ is the managerrsquos optimal strategyand
Yt Vm t x YZΓT1113872 1113873 (26)
Up till now fixing (Z Γ) isin V(t) we can get themanagerrsquos optimal strategy and represent the managerrsquosvalue function In Section 4 we begin to consider the in-vestorrsquos optimization problem at is finding the optimal(Z Γ) isin V(t) to maximize the investorrsquos net profit
4 The Investorrsquos Optimization Problem
Suppose that the investorrsquos wealth is x at t Apparently theinvestorrsquos value function is uniquely determined by thewealth process and the managerrsquos value function So the
4 Mathematical Problems in Engineering
objective of the investor is to find the optimal (Z Γ) isinV(t)
to minimize his value function Define
v(t x y) inf(ZΓ)isinV(t)
E ecf XlowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
πt x Y
ZΓt y1113876 1113877
(27)
Referring to eorem 41 in [19] we know that if As-sumption 32 Assumption 43 and Assumption 44 in [19]hold the investorrsquos value function satisfies
Vf(t x) infyisin 0ecmR[ ]
v(t x y) (28)
Here R is the minimum pay in order to make sure thatthe manager takes the job
Section 41 gives the verification of the threeassumptions
41 7e Verification of Assumptions
Assumption 1 (Assumption 32 in [19]) H has at least oneextreme point (b
lowastyzct n
lowastyzct ) For any t isin [0 T]
(Z Γ) isin V(t) we have πlowastZΓ isin Π
Proof is is the result of eorem 1 and Lemma 1e Hamiltonian function can be expressed as
H(t x y z c) infbgt0
F(t x y z b) +b2σ2
2c1113896 1113897 (29)
Here
F(t x y z b) infngt0
minus Dt
cmθn2b
2y +(rx + b(μ + n))z1113896 1113897
(30)
Define
YZs Yt minus 1113946
s
tF r Xr Y
Zr Zr1113872 1113873dr + 1113946
s
tZrdXr s isin [t T]
(31)
and we have the following assumption
Assumption 2 (Assumption 43 in [19]) F has at least oneextreme point n
lowastyzbt furthermore (b nlowastY
ZZb) isin Π
Proof On the one hand the right hand of F is a parabolawith an opening up with respect to n so the minimum pointis attained at the axis of the parabola (zDtcmθy) that isnlowastyzbt (zDtcmθy) On the other hand since Zlt 0 is
predictable we can get that nlowastYZ
t Ztbt (bZtDtcmθbYZ
t ) is apositive predictable process Furthermore b and n
lowastyzbt are
independent of x is implies the Lipschitz continuity andlinear growth of the coefficients in (2) with respect to theinvestment income process then (2) has a uniquesolution
Assumption 3 (Assumption 44 in [19]) forallbgt 0 (1b2σ2) isbounded
Proof We can get the result directly from σ gt 0 bgt 0
427e Investorrsquos Value Function Clearly as soon as we getv(t x y) we can obtain Vf(t x) e following theoremgives the partial differential equation satisfied by v(t x y)
Theorem 3 v(t x y) is the viscosity solution of
minus vt(t x y) inf(ZΓ)isinV(t)
G(t x y Z Γ) (32)
v(T x y) ecfx
yminus cfcm( 1113857
(33)
where
G(t x y Z Γ) rx + blowastZΓt μ + n
lowastZΓt1113872 11138731113960 1113961vx
+σ2 blowastZΓt1113872 1113873
2
2vxx +
Dtcmθ nlowastZΓt1113872 1113873
2
2blowastZΓt yvy
+σ2 blowastZΓt1113872 1113873
2
2Z2vyy + σ2 b
lowastZΓt1113872 1113873
2Zvxy
(34)
Proof By the definition of v(t x y) we can obtain that itsatisfies (33) Furthermore according to the dynamic pro-gramming principle we have
v(t x y) inf(ZΓ)isinV(t)
v t + h XlowastZΓt+h Y
ZΓt+h1113872 1113873 (35)
By using Itorsquos formula with respect to v(s XlowastZΓs YZΓ
s )
from t to t + h we have
v t + h XlowastZΓt+h Y
ZΓt+h1113872 1113873 v(t x y) + 1113946
t+h
tvt s X
lowastZΓs Y
ZΓs1113872 1113873
+ G s XlowastZΓs Y
ZΓs Zs Γs1113872 1113873ds
(36)
Combining with the above two equations we can get
vt(t x y) + inf(ZΓ)isinV(t)
G(t x y Z Γ) 0 (37)
at is v(t x y) satisfies (32) e proof is doneNext we are going to solve (32) and (33) Considering
the boundary condition we guess
v(t x y) ecfDtxy
minus cfcm( 1113857E(t) (38)
where E(t) is a function of t which satisfies E(T) 1If the variables in the solution can be separated from
each other (32) can be easily solved However (32) containsecfDtx which is a cross term of t and x To cancel the crossterm we introduce zt DtX
lowastZΓt Using Itorsquos formula we
can get
dzt minus rDtXlowastZΓt dt + DtdX
lowastZΓt
DtblowastZΓt μ + n
lowastZΓt1113872 1113873dt + σdW(t)1113960 1113961
(39)
Mathematical Problems in Engineering 5
We can also obtain zT XlowastZΓT Define
V(t z y) inf(ZΓ)isinV(t)
E ecf zTminus lnYZΓ
Tcm( )( )|zt z1113876 1113877
inf(ZΓ)isinV(t)
E ecf X lowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
lowastZΓt
z
Dt
1113890 1113891
v tz
Dt
y1113888 1113889
(40)
Obviously solving v(t x y) is equivalent to solvingV(t z y) Using a similar method as the one in eorem 3we can get that
minus Vt inf(ZΓ)isinV(t)
minusμ + n
lowastZΓt 21113872 11138731113872 1113873 μ + n
lowastZΓt1113872 1113873
σ2Dt
Z
ΓVz
⎧⎨
⎩
minuscmθ n
lowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2σ2yDt
Z
ΓVy
+μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2D
2t
Z2
Γ2Vzz
+nlowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2cmθyDt( 1113857
2Z2
Γ2Vyy
+nlowastZΓt μ + n
lowastZΓt 21113872 11138731113872 1113873
2
σ2cmθyD
2t
Z2
Γ2Vzy
⎫⎪⎬
⎪⎭
(41)
V(T z y) ecfz
yminus cfcm( 1113857
(42)
e first step in solving (41) is to find its minimum pointDefine MZΓ (ZΓ) it is shown in Section 3 that (Z Γ) and(MZΓ nlowastZΓ) are one-to-one en (41) is transformed into
minus Vt inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMVz1113896
+(μ +(n2))
2
2σ2D
2t M
2Vzz minus
cmθn2(μ +(n2))
2σ2yDtMVy
+n2(μ +(n2))
2
2σ2cmθyDt( 1113857
2M
2Vyy
+n(μ +(n2))
2
σ2cmθyD
2t M
2Vzy1113897
(43)
Now the problem of finding the minimum point in (41) ischanged into a problem of finding theminimumpoint in (43)
According to (38) we suppose thatV(t z y) E(t)ecfzyminus (cfcm) By some simple calculationswe can get that
Vz(t z y) cfV(t z y)
Vzz(t z y) c2fV(t z y)
yVy(t z y) minuscf
cm
V(t z y)
y2Vyy(t z y)
cf cf + cm1113872 1113873
c2m
V(t z y)
yVzy(t z y) minusc2f
cm
V(t z y)
(44)
Taking them into (43) we have
minus Eprime(t)V(t z y) inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMcf1113896
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
21113897E(t)V(t z y)
(45)
Since the right hand of (45) is continuous the minimumpoint can only be attained at the stable points or theboundary points which depends on the parameter valuesDenote the minimum point of (45) by (nlowastt Mlowastt ) and denotethe corresponding minimum point of (41) by (Zlowastt Γlowastt ) It isshown from the Appendix that nlowastt and DtM
lowastt are constants
concerning μ θ cf and cm Let nlowastt nlowast
Remark 4 On the one hand the exponential form of theobjective function implies that blowastt is independent of Xlowastt Onthe other hand the benefit and the cost brought by themanagerrsquos effort are only related to blowastt so nlowastt is independentof Xlowastt Furthermore in this paper we consider the dis-counted benefit and cost brought by the managerrsquos effort sonlowastt is independent of t
Remark 5 It is shown from figures in the Appendix that nlowast
decreases with an increase in μ(the drift coefficient of thefund wealth process) θ(the effort cost coefficient) and|cm|(the managerrsquos risk aversion level) It increases with anincrease in |cf|(the investorrsquos risk aversion level)
6 Mathematical Problems in Engineering
Remark 6 Define Ylowastt Vm(t x YZlowastΓlowastT ) considering (12)
and (13) we can get that (Zlowastt Ylowastt ) θcmDtnlowast and Dtb
lowastt
(minus (μ + (nlowast2))σ2)DtMlowastt are constants
Taking the minimum point into (45) and solving it wecan get
V(t z y) eB(Tminus t)
ecfz
yminus cfcm( 1113857
(46)
Here
B minusμ + n
lowast2( 1113857( 1113857 μ + nlowast
( 1113857
σ2DtMlowastt cf
+μ + n
lowast2( 1113857( 11138572
2σ2D
2t Mlowast 2t c
2f +
cfθnlowast2 μ + n
lowast2( 1113857( 1113857
2σ2DtMlowastt
+nlowast2 μ + n
lowast2( 1113857( 11138572
2σ2θ2D2
t Mlowast 2t cf cf + cm1113872 1113873
minusnlowast μ + n
lowast2( 1113857( 11138572
σ2c2fθD
2t Mlowast 2t
(47)
0 000
002
004
006
008
010
n
035 040 045030the drift coefficient of the fund
0ndash
000
002
004
006
008
010
n
20 25 3010 15The effort cost coefficient
0
000
002
004
006
008
010
n
020 025 030015The managerrsquos risk aversion level
0
011 012 013 014 015010The investorrsquos risk aversion level
000
002
004
006
008
010
n
Figure 1 e effects of parameters on the optimal effort level
Mathematical Problems in Engineering 7
is a constant As a consequence we can also get the followingresults
v(t x y) eB(Tminus t)
ecfDtxy
minus cfcm( 1113857
Vf(t x) v t x ecmR
1113872 1113873 eB(Tminus t)
ecf Dtxminus R( )
(48)
43 7e Investorrsquos Excitation Mechanism In this section letus analyze the investorrsquos excitation mechanism DenoteYlowastt YZlowastΓlowast
t From the above analysis we know that
dYlowastt
Dtcmθnlowast2
blowastt Ylowastt
2dt + b
lowastt Zlowastt σdWt
Ylowastt e
cmR
(49)
Using Itorsquos formula we have
d lnYlowastt
Dtcmθnlowast2
blowastt
2dt + b
lowastt
Zlowastt
Ylowastt
σdWt minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
dt
(50)
Furthermore we can get that the investment incomeunder nlowast and blowastt satisfies
dXlowastt rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt + blowastt σdWt (51)
which implies
d lnYlowastt
Dtcmθnlowast2
blowastt
2minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
1113888 1113889dt +Zlowastt
Ylowastt
dXlowastt minus rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt( 1113857
cm
Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 11138571113888 1113889dt
+ cmθnlowastDt dX
lowastt minus rX
lowastt dt( 1113857
(52)
Define constant
A Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 1113857gt 0
(53)
and then we can obtaind lnY
lowastt cmAdt + cmθn
lowastDt dX
lowastt minus rX
lowastt dt( 1113857 cm Adt + θn
lowastdDtXlowastt( 1113857
(54)
So
lnYlowastT minus cmR cm A(T minus t) + n
lowastθ XlowastT minus Dtx( 11138571113858 1113859 (55)
can be deduced immediately Since lnYT cmw(XT) wecan get the strategy
w XT( 1113857 A(T minus t) + nlowastθ XlowastT minus Dtx( 1113857 + R (56)
It is a linear function of XlowastT minus Dtx which is the dis-counted profit of the investment
Remark 7 It follows from the above results that the man-agerrsquos wages increase with the increase of the cost coefficientthe effort level and the discounted profit of the investmentFurthermore the longer the work the higher the salary It isconsistent with reality
We can also get the following corollary
Corollary 1
Ylowasts Vm s X
lowasts YlowastT( 1113857 e
cm R+A(Tminus t)+nlowastθ Xlowasts minus Dtx( )[ ] (57)
is implies that Vm(s Xlowasts YlowastT) is a decreasing convexfunction of Xlowasts us the assumption in Section 2 that YlowastT isan incentive strategy is proved
Appendix
Define
I(n M t) minus(μ +(n2))(μ + n)
σ2DtMcf
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
2
(A1)
We know that there are three kinds of points which maybe the minimum point of (45)
8 Mathematical Problems in Engineering
(i) e points which satisfy In(n M t) 0 IM
(n M t) 0(ii) e points which satisfy n 0 IM(0 M t) 0(iii) e points which satisfy M 0 In(n 0 t) 0
With parameters fixed we can easily decide which is theminimum point of (45) In the following we will investigatethe form of those points
e first kind of points (n1t M1t) is the solution of thefollowing equations
In(n M t) minusDtcf
σ232μ + n1113874 1113875M
+Dtcfθ
2σ232n2
+ 2μn1113874 1113875M +D
2t c
2f
2σ2μ +
n
21113874 1113875M
2
+θ2D2
t cf cf + cm1113872 1113873
2σ2n3
+ 3μn2
+ 2μ2n1113872 1113873M2
minusc2fθD
2t
σ23n
2
4+ 2μn + μ21113888 1113889M
2 0
(A2)
IM(n M t) minusDtcf
σ2(μ + n) μ +
n
21113874 1113875
+Dtcfθ
2σ2n2 μ +
n
21113874 1113875 +
D2t c
2f
σ2μ +
n
21113874 1113875
2M
+θ2D2
t cf cf + cm1113872 1113873
σ2n2 μ +
n
21113874 1113875
2M
minus2c
2fθD
2t
σ2n μ +
n
21113874 1113875
2M 0
(A3)
We can deduce from (A2) that
DtM1t n1t + μ minus n
21tθ21113872 1113873 +(μ2) minus θn
21t41113872 1113873 minus θμn1t
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf minus cf21113872 1113873 + cfθμ minus cfθn1t21113872 1113873 + θ2μ cf + cm1113872 1113873n1t1113960 1113961
(A4)
It also follows from (A3) that
DtM1t n1t + μ minus n1t( 1113857
2θ21113872 1113873
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t1113872 1113873
2θ2 cm + cf1113872 1113873 + cf1113876 1113877
(A5)
Combining the above two equations we can get that
n1t + μ minusn1t( 1113857
2θ2
1113888 1113889 minuscf
2+ cfθμ minus
cfθn1t
2+ θ2μ cf + cm1113872 1113873n1t1113890 1113891
+θn
21t
4+ θμn1t minus
μ2
1113888 1113889 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf1113960 1113961 0
(A6)
Clearly by solving (A5) and (A6) we can get that n1 andDtM1t are constants
Denote the second kind of point by (0 M2t) us M2t
satisfies (A5) with n replaced with 0 and we can get thatDtM2t is a constant
Denote the third kind of points by (n3t 0) ey satisfy(A4) By solving it we can get that n3t is a constant
Denote the minimum point of (45) by (nlowastt Mlowastt ) Itfollows from the above analysis that nlowastt and DtM
lowastt are all
constants For different μ θ cf and cm by calculating (A6)(A2) or (A3) we can get different nlowast
By using R we plot the following figures which indicatethe effect of μ θ cf and cm on nlowast (Figure 1)
Data Availability
No data were used to support this study
Conflicts of Interest
e authors declare that they have no conflicts of interest
Acknowledgments
is work was supported by the National Natural ScienceFoundation of China (11901404)
References
[1] A Almazan K C Brown M Carlson and D A ChapmanldquoWhy constrain your mutual fund managerrdquo Journal of Fi-nancial Economics vol 73 no 2 pp 289ndash321 2004
[2] M K Brunnermeier and L H Pedersen ldquoMarket liquidityand funding liquidityrdquo Review of Financial Studies vol 22no 6 pp 2201ndash2238 2009
[3] P H Dybvig H K Farnsworth and J N CarpenterldquoPortfolio performance and agencyrdquo Review of FinancialStudies vol 23 no 1 pp 1ndash23 2010
Mathematical Problems in Engineering 9
[4] S Gervais A W Lynch and D K Musto ldquoFund families asdelegated monitors of money managersrdquo Review of FinancialStudies vol 18 no 4 pp 1139ndash1169 2005
[5] V Guerrieri and P Kondor ldquoFund managers career con-cerns and asset price volatilityrdquo 7e American EconomicReview vol 102 no 5 pp 1986ndash2017 2012
[6] S Ross ldquoe economic theory of agency the principalrsquosproblemrdquo 7e American Economic Review vol 63 pp 134ndash139 1973
[7] J A Mirrlees ldquoe optimal structure of incentives and au-thority within an organizationrdquo7eBell Journal of Economicsvol 7 no 1 pp 105ndash131 1976
[8] B Holmstrom ldquoMoral hazard and observabilityrdquo 7e BellJournal of Economics vol 10 no 1 pp 74ndash91 1979
[9] P Bolton and M Dewatripont Contract 7eory MIT PressCambridge UK 2005
[10] B Holmstrom and P Milgrom ldquoAggregation and linearity inthe provision of intertemporal incentivesrdquo Econometricavol 55 no 2 pp 303ndash328 1987
[11] H Schattler and J Sung ldquoe first-order approach to thecontinuous-time principal-agent problem with exponentialutilityrdquo Journal of Economic7eory vol 61 no 2 pp 331ndash3711993
[12] H Schattler and J Sung ldquoOn optimal sharing rules in dis-crete-and continuous-time principal-agent problems withexponential utilityrdquo Journal of Economic Dynamics andControl vol 21 no 2-3 pp 551ndash574 1997
[13] H M Muller ldquoe first-best sharing rule in the continuous-time principal-agent problem with exponential utilityrdquoJournal of Economic 7eory vol 79 no 2 pp 276ndash280 1998
[14] H M Muller ldquoAsymptotic efficiency in dynamic principal-agent problemsrdquo Journal of Economic 7eory vol 91 no 2pp 292ndash301 2000
[15] J Cvitanic X Wan and J Zhang ldquoOptimal compensationwith hidden action and lump-sum payment in a continuous-time modelrdquo Applied Mathematics and Optimization vol 59pp 99ndash146 2009
[16] J Cvitanic and J Zhang Contract 7eory in Continuous TimeModels Springer-Verlag Berlin Germany 2013
[17] Y Sannikov ldquoA continuous-time version of the principal-agent problemrdquo7eReview of Economic Studies vol 75 no 3pp 957ndash984 2008
[18] Z He ldquoA Model of dynamic compensation and capitalstructurerdquo Journal of Financial Economics vol 100 no 2pp 351ndash366 2011
[19] J Cvitanic D Possamai and N Touzi ldquoDynamic pro-gramming approach to principal-agent problemsrdquo Financeand Stochastics vol 22 pp 1ndash37 2018
[20] Z He and W Xiong ldquoDelegated asset management invest-ment mandates and capital immobilityrdquo Journal of FinancialEconomics vol 107 no 2 pp 239ndash258 2013
[21] H Pham Continuous-time Stochastic Control and Optimi-zation with Financial Applications Springer-Verlag NewYork NY USA 2009
10 Mathematical Problems in Engineering
Suppose that the investor is risk-averse too his risk-sensitive coefficient is cf lt 0 Next we consider the inves-torrsquos optimal problem
If the managerrsquos salary is too high the investorrsquos incomewill be reduced If the managerrsquos salary is too low themanagerrsquos enthusiasm wanes which also deduces the in-vestorrsquos terminal income erefore the investor needs tofind a reasonable incentive strategy to maximize his netincome that is minimize
Jwf(t x) E e
cf XwT
minus w XwT( )( )|X
wt x1113876 1113877 (5)
where Xwt is the investment income process under strategy
πw us the investorrsquos value function is
Vf(t x) infwisin1113954Π
Jwf(t x) (6)
Remark 2 e problem discussed above is not a standardstochastic optimal control problem since the form of w(middot) isuncertain and we cannot solve it directly by using standardstochastic optimal methods In Section 3 we give anotherform of the incentive strategy and transform the gameproblem into a classical one en we can use the dynamicprogramming principle to solve the problem
3 The Managerrsquos Optimization Problem
Define Dt er(Tminus t) β(t π) cmDt(θnπ2t 2)bπt and
Γ(t T π) eminus 1113938
T
tβ(uπ)du en Jπm(t x w) can be denoted
by
Jπm(t x w) E Γ(t T π)e
cmw XπT( )|X
πt x1113876 1113877 (7)
Using the results of Section 34 in [21] we know thatunder the incentive strategy w(middot) the managerrsquos valuefunction Vm(t x w) satisfies the HJB equation
minus Vmt(t x w) infπisinΠ
minus β(t π)Vm(t x w) + rx + bπt μ + n
πt( 11138571113858 11138591113864
Vmx(t x w) +bπ2t σ2
2Vmxx(t x w)1113897
(8)
and the boundary condition
Vm(T x w) ecmw(x)
(9)
Since Vm(t x w) is a decreasing convex function of xfor forall(t x y z c) isin [0 T) times R times [0infin) times (minus infin 0) times (0infin)we can define the Hamiltonian function
H(t x y z c) infngt0bgt0
h(t x y z c n b) (10)
where
h(t x y z c n b) minus Dt
cmθn2b
2y +(rx + b(μ + n))z +
b2σ2
2c
(11)
Theorem 1
nlowastyzct
z
θcmyDt
(12)
blowastyzct
minus μ + nlowastyzct 2( 1113857( 1113857
σ2z
c (13)
is the minimum point of h in (10)
Proof According to the definition we know that h is aconvex function of (n b) So the minimum point of h in (10)is the stable point under constraint conditions ngt 0 bgt 0 Bysome simple calculations we have
hn(n b t x y z c) minus θDtbncmy + bz
hb(n b t x y z c) σ2cb +(μ + n)z minusDtθncmy
2
(14)
Combining the above two equations we can obtain thestable point of h
nlowastyzct
z
θcmyDt
gt 0
blowastyzct
minus μ + nlowastyzct 2( 1113857( 1113857
σ2z
cgt 0
(15)
e proof is done
Remark 3 In this case the optimal investment strategy issimilar to that without principal-agent relationships eonly difference is that the numerator of the optimal in-vestment strategy is changed from (μ + n
lowastyzct ) into
(μ + (nlowastyzct 2)) Clearly this is due to the existence of the
agency relationship
Apparently the investorrsquos incentive strategy and themanagerrsquos value function are one-to-one In the followingwe will use auxiliary stochastic processes (Zt Γt) to deter-mine the managerrsquos value function and transform the in-vestorrsquos incentive strategy into (Zt Γt) en the problem inSection 2 can be translated into a classical stochastic optimalcontrol problem
First let us give the space of auxiliary stochastic pro-cesses (Z Γ) Fix t isin [0 T) let Z [t T] timesΩ⟶(minus infin 0) Γ [t T] timesΩ⟶ (0infin) be FW-predicable pro-cesses which satisfy
E 1113946T
tZ2sσ
2s + Γsσ
2s1113872 1113873ds1113890 1113891lt +infin (16)
Mathematical Problems in Engineering 3
Denote the set of all the processes satisfying the aboveconditions by V(t)
For some (Z Γ) isinV(t) and Yt ge 0 define theFW-progressively measurable process YZΓ on the filtrationspace (ΩF P FW
t1113864 1113865tge0) by
YZΓs Yt minus 1113946
s
tH r Xr Y
ZΓr Zr Γr1113872 1113873dr
+ 1113946s
tZrdXr +
12
1113946s
tΓrdlangXrangr s isin [t T]
(17)
where Xr is the investment income process Clearly forfixed Yt Z Γ YZΓ
T is only related to the investment incomeprocess and is FT measurable suppose that it is an in-centive strategy (we prove it in Corollary 1) In the fol-lowing we give the relationship between YZΓ
s and themanagerrsquos value function First we give the followinglemma
Lemma 1 Define
πlowastZΓ blowastZΓ
nlowastZΓ
1113872 1113873
blowastYZΓ
t ZtΓtt1113882 1113883
tge0 nlowastYZΓ
t ZtΓtt1113882 1113883
tge01113874 1113875
(18)
and then we have πlowastZΓ isin Π
Proof On the one hand since Z Γ YZΓ are all predictablestochastic processes referring to (12) and (13) we can getthat blowastZΓ and nlowastZΓ are bounded positive predictable sto-chastic processes On the other hand b
lowastyzct and n
lowastyzct are
independent of x Taking blowastZΓ and nlowastZΓ into (2) we can getthe Lipschitz continuity and linear growth of the coefficientsin (2) with respect to Xt then (2) has a unique solution eproof is done
Denote the investment income process under πlowastZΓ byXlowastZΓ We also have the following theorem
Theorem 2 Denote the managerrsquos value function with aterminal return (lnYZΓ
T cm) by Vm(t x YZΓT ) We can ob-
tain that
Yt Vm t x YZΓT1113872 1113873 (19)
Furthermore the managerrsquos optimal strategy is πlowastZΓ
Proof forallπ isin Π s isin [t T] we have
YZΓs Yt minus 1113946
s
tH r X
πr Y
ZΓr Zr Γr1113872 1113873dr
+ 1113946s
tZrdX
πr +
12
1113946s
tΓrdlangX
πrangr
(20)
Using Itorsquos formula we have
deminus 1113946
r
tβ(u π)du
YZΓr e
minus 1113946r
tβ(u π)du
minus H r Xπr Y
ZΓr Zr Γr1113872 11138731113960
+ rXπr + b
πr μ + n
πr( 1113857( 1113857Zr
+bπ2r σ2
2Γr minus β(r π)1113891dr
+ eminus 1113946
r
tβ(u π)du
σZrdW(r)
(21)
It follows from (16) that eminus 1113938
r
tβ(uπ)duσZrdW(r) is a
martingale Integrating and taking expectations on bothsides of (21) we can get
Yt geE eminus 1113946
T
tβ(u π)du
YZΓT |X
πt x
⎡⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎣⎤⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎦ J
πm t x Y
ZΓT1113872 1113873
(22)
Furthermore by simple calculations under πlowastZΓ isin Πwe have
dYZΓt β t πlowastZΓ
1113872 1113873YZΓt dt + b
lowastYZΓt ZtΓt
t ZtσdWt (23)
Using (23) and Itorsquos formula we can obtain
deminus 1113946
r
tβ u πlowastZΓ
1113872 1113873duY
ZΓr e
minus 1113946r
tβ u πlowastZΓ
1113872 1113873dublowastYZΓ
t ZtΓtt ZtσdWt
(24)
With similar methods integrating and taking expecta-tions on both sides of (24) we have
Yt E eminus 1113946
T
tβ u πlowastZΓ
1113872 1113873duY
ZΓT |XlowastZΓt x
⎡⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎣⎤⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎦
JπlowastZΓ
m t x YZΓT1113872 1113873ge J
πm t x Y
ZΓT1113872 1113873
(25)
is implies that πlowastZΓ is the managerrsquos optimal strategyand
Yt Vm t x YZΓT1113872 1113873 (26)
Up till now fixing (Z Γ) isin V(t) we can get themanagerrsquos optimal strategy and represent the managerrsquosvalue function In Section 4 we begin to consider the in-vestorrsquos optimization problem at is finding the optimal(Z Γ) isin V(t) to maximize the investorrsquos net profit
4 The Investorrsquos Optimization Problem
Suppose that the investorrsquos wealth is x at t Apparently theinvestorrsquos value function is uniquely determined by thewealth process and the managerrsquos value function So the
4 Mathematical Problems in Engineering
objective of the investor is to find the optimal (Z Γ) isinV(t)
to minimize his value function Define
v(t x y) inf(ZΓ)isinV(t)
E ecf XlowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
πt x Y
ZΓt y1113876 1113877
(27)
Referring to eorem 41 in [19] we know that if As-sumption 32 Assumption 43 and Assumption 44 in [19]hold the investorrsquos value function satisfies
Vf(t x) infyisin 0ecmR[ ]
v(t x y) (28)
Here R is the minimum pay in order to make sure thatthe manager takes the job
Section 41 gives the verification of the threeassumptions
41 7e Verification of Assumptions
Assumption 1 (Assumption 32 in [19]) H has at least oneextreme point (b
lowastyzct n
lowastyzct ) For any t isin [0 T]
(Z Γ) isin V(t) we have πlowastZΓ isin Π
Proof is is the result of eorem 1 and Lemma 1e Hamiltonian function can be expressed as
H(t x y z c) infbgt0
F(t x y z b) +b2σ2
2c1113896 1113897 (29)
Here
F(t x y z b) infngt0
minus Dt
cmθn2b
2y +(rx + b(μ + n))z1113896 1113897
(30)
Define
YZs Yt minus 1113946
s
tF r Xr Y
Zr Zr1113872 1113873dr + 1113946
s
tZrdXr s isin [t T]
(31)
and we have the following assumption
Assumption 2 (Assumption 43 in [19]) F has at least oneextreme point n
lowastyzbt furthermore (b nlowastY
ZZb) isin Π
Proof On the one hand the right hand of F is a parabolawith an opening up with respect to n so the minimum pointis attained at the axis of the parabola (zDtcmθy) that isnlowastyzbt (zDtcmθy) On the other hand since Zlt 0 is
predictable we can get that nlowastYZ
t Ztbt (bZtDtcmθbYZ
t ) is apositive predictable process Furthermore b and n
lowastyzbt are
independent of x is implies the Lipschitz continuity andlinear growth of the coefficients in (2) with respect to theinvestment income process then (2) has a uniquesolution
Assumption 3 (Assumption 44 in [19]) forallbgt 0 (1b2σ2) isbounded
Proof We can get the result directly from σ gt 0 bgt 0
427e Investorrsquos Value Function Clearly as soon as we getv(t x y) we can obtain Vf(t x) e following theoremgives the partial differential equation satisfied by v(t x y)
Theorem 3 v(t x y) is the viscosity solution of
minus vt(t x y) inf(ZΓ)isinV(t)
G(t x y Z Γ) (32)
v(T x y) ecfx
yminus cfcm( 1113857
(33)
where
G(t x y Z Γ) rx + blowastZΓt μ + n
lowastZΓt1113872 11138731113960 1113961vx
+σ2 blowastZΓt1113872 1113873
2
2vxx +
Dtcmθ nlowastZΓt1113872 1113873
2
2blowastZΓt yvy
+σ2 blowastZΓt1113872 1113873
2
2Z2vyy + σ2 b
lowastZΓt1113872 1113873
2Zvxy
(34)
Proof By the definition of v(t x y) we can obtain that itsatisfies (33) Furthermore according to the dynamic pro-gramming principle we have
v(t x y) inf(ZΓ)isinV(t)
v t + h XlowastZΓt+h Y
ZΓt+h1113872 1113873 (35)
By using Itorsquos formula with respect to v(s XlowastZΓs YZΓ
s )
from t to t + h we have
v t + h XlowastZΓt+h Y
ZΓt+h1113872 1113873 v(t x y) + 1113946
t+h
tvt s X
lowastZΓs Y
ZΓs1113872 1113873
+ G s XlowastZΓs Y
ZΓs Zs Γs1113872 1113873ds
(36)
Combining with the above two equations we can get
vt(t x y) + inf(ZΓ)isinV(t)
G(t x y Z Γ) 0 (37)
at is v(t x y) satisfies (32) e proof is doneNext we are going to solve (32) and (33) Considering
the boundary condition we guess
v(t x y) ecfDtxy
minus cfcm( 1113857E(t) (38)
where E(t) is a function of t which satisfies E(T) 1If the variables in the solution can be separated from
each other (32) can be easily solved However (32) containsecfDtx which is a cross term of t and x To cancel the crossterm we introduce zt DtX
lowastZΓt Using Itorsquos formula we
can get
dzt minus rDtXlowastZΓt dt + DtdX
lowastZΓt
DtblowastZΓt μ + n
lowastZΓt1113872 1113873dt + σdW(t)1113960 1113961
(39)
Mathematical Problems in Engineering 5
We can also obtain zT XlowastZΓT Define
V(t z y) inf(ZΓ)isinV(t)
E ecf zTminus lnYZΓ
Tcm( )( )|zt z1113876 1113877
inf(ZΓ)isinV(t)
E ecf X lowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
lowastZΓt
z
Dt
1113890 1113891
v tz
Dt
y1113888 1113889
(40)
Obviously solving v(t x y) is equivalent to solvingV(t z y) Using a similar method as the one in eorem 3we can get that
minus Vt inf(ZΓ)isinV(t)
minusμ + n
lowastZΓt 21113872 11138731113872 1113873 μ + n
lowastZΓt1113872 1113873
σ2Dt
Z
ΓVz
⎧⎨
⎩
minuscmθ n
lowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2σ2yDt
Z
ΓVy
+μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2D
2t
Z2
Γ2Vzz
+nlowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2cmθyDt( 1113857
2Z2
Γ2Vyy
+nlowastZΓt μ + n
lowastZΓt 21113872 11138731113872 1113873
2
σ2cmθyD
2t
Z2
Γ2Vzy
⎫⎪⎬
⎪⎭
(41)
V(T z y) ecfz
yminus cfcm( 1113857
(42)
e first step in solving (41) is to find its minimum pointDefine MZΓ (ZΓ) it is shown in Section 3 that (Z Γ) and(MZΓ nlowastZΓ) are one-to-one en (41) is transformed into
minus Vt inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMVz1113896
+(μ +(n2))
2
2σ2D
2t M
2Vzz minus
cmθn2(μ +(n2))
2σ2yDtMVy
+n2(μ +(n2))
2
2σ2cmθyDt( 1113857
2M
2Vyy
+n(μ +(n2))
2
σ2cmθyD
2t M
2Vzy1113897
(43)
Now the problem of finding the minimum point in (41) ischanged into a problem of finding theminimumpoint in (43)
According to (38) we suppose thatV(t z y) E(t)ecfzyminus (cfcm) By some simple calculationswe can get that
Vz(t z y) cfV(t z y)
Vzz(t z y) c2fV(t z y)
yVy(t z y) minuscf
cm
V(t z y)
y2Vyy(t z y)
cf cf + cm1113872 1113873
c2m
V(t z y)
yVzy(t z y) minusc2f
cm
V(t z y)
(44)
Taking them into (43) we have
minus Eprime(t)V(t z y) inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMcf1113896
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
21113897E(t)V(t z y)
(45)
Since the right hand of (45) is continuous the minimumpoint can only be attained at the stable points or theboundary points which depends on the parameter valuesDenote the minimum point of (45) by (nlowastt Mlowastt ) and denotethe corresponding minimum point of (41) by (Zlowastt Γlowastt ) It isshown from the Appendix that nlowastt and DtM
lowastt are constants
concerning μ θ cf and cm Let nlowastt nlowast
Remark 4 On the one hand the exponential form of theobjective function implies that blowastt is independent of Xlowastt Onthe other hand the benefit and the cost brought by themanagerrsquos effort are only related to blowastt so nlowastt is independentof Xlowastt Furthermore in this paper we consider the dis-counted benefit and cost brought by the managerrsquos effort sonlowastt is independent of t
Remark 5 It is shown from figures in the Appendix that nlowast
decreases with an increase in μ(the drift coefficient of thefund wealth process) θ(the effort cost coefficient) and|cm|(the managerrsquos risk aversion level) It increases with anincrease in |cf|(the investorrsquos risk aversion level)
6 Mathematical Problems in Engineering
Remark 6 Define Ylowastt Vm(t x YZlowastΓlowastT ) considering (12)
and (13) we can get that (Zlowastt Ylowastt ) θcmDtnlowast and Dtb
lowastt
(minus (μ + (nlowast2))σ2)DtMlowastt are constants
Taking the minimum point into (45) and solving it wecan get
V(t z y) eB(Tminus t)
ecfz
yminus cfcm( 1113857
(46)
Here
B minusμ + n
lowast2( 1113857( 1113857 μ + nlowast
( 1113857
σ2DtMlowastt cf
+μ + n
lowast2( 1113857( 11138572
2σ2D
2t Mlowast 2t c
2f +
cfθnlowast2 μ + n
lowast2( 1113857( 1113857
2σ2DtMlowastt
+nlowast2 μ + n
lowast2( 1113857( 11138572
2σ2θ2D2
t Mlowast 2t cf cf + cm1113872 1113873
minusnlowast μ + n
lowast2( 1113857( 11138572
σ2c2fθD
2t Mlowast 2t
(47)
0 000
002
004
006
008
010
n
035 040 045030the drift coefficient of the fund
0ndash
000
002
004
006
008
010
n
20 25 3010 15The effort cost coefficient
0
000
002
004
006
008
010
n
020 025 030015The managerrsquos risk aversion level
0
011 012 013 014 015010The investorrsquos risk aversion level
000
002
004
006
008
010
n
Figure 1 e effects of parameters on the optimal effort level
Mathematical Problems in Engineering 7
is a constant As a consequence we can also get the followingresults
v(t x y) eB(Tminus t)
ecfDtxy
minus cfcm( 1113857
Vf(t x) v t x ecmR
1113872 1113873 eB(Tminus t)
ecf Dtxminus R( )
(48)
43 7e Investorrsquos Excitation Mechanism In this section letus analyze the investorrsquos excitation mechanism DenoteYlowastt YZlowastΓlowast
t From the above analysis we know that
dYlowastt
Dtcmθnlowast2
blowastt Ylowastt
2dt + b
lowastt Zlowastt σdWt
Ylowastt e
cmR
(49)
Using Itorsquos formula we have
d lnYlowastt
Dtcmθnlowast2
blowastt
2dt + b
lowastt
Zlowastt
Ylowastt
σdWt minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
dt
(50)
Furthermore we can get that the investment incomeunder nlowast and blowastt satisfies
dXlowastt rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt + blowastt σdWt (51)
which implies
d lnYlowastt
Dtcmθnlowast2
blowastt
2minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
1113888 1113889dt +Zlowastt
Ylowastt
dXlowastt minus rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt( 1113857
cm
Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 11138571113888 1113889dt
+ cmθnlowastDt dX
lowastt minus rX
lowastt dt( 1113857
(52)
Define constant
A Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 1113857gt 0
(53)
and then we can obtaind lnY
lowastt cmAdt + cmθn
lowastDt dX
lowastt minus rX
lowastt dt( 1113857 cm Adt + θn
lowastdDtXlowastt( 1113857
(54)
So
lnYlowastT minus cmR cm A(T minus t) + n
lowastθ XlowastT minus Dtx( 11138571113858 1113859 (55)
can be deduced immediately Since lnYT cmw(XT) wecan get the strategy
w XT( 1113857 A(T minus t) + nlowastθ XlowastT minus Dtx( 1113857 + R (56)
It is a linear function of XlowastT minus Dtx which is the dis-counted profit of the investment
Remark 7 It follows from the above results that the man-agerrsquos wages increase with the increase of the cost coefficientthe effort level and the discounted profit of the investmentFurthermore the longer the work the higher the salary It isconsistent with reality
We can also get the following corollary
Corollary 1
Ylowasts Vm s X
lowasts YlowastT( 1113857 e
cm R+A(Tminus t)+nlowastθ Xlowasts minus Dtx( )[ ] (57)
is implies that Vm(s Xlowasts YlowastT) is a decreasing convexfunction of Xlowasts us the assumption in Section 2 that YlowastT isan incentive strategy is proved
Appendix
Define
I(n M t) minus(μ +(n2))(μ + n)
σ2DtMcf
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
2
(A1)
We know that there are three kinds of points which maybe the minimum point of (45)
8 Mathematical Problems in Engineering
(i) e points which satisfy In(n M t) 0 IM
(n M t) 0(ii) e points which satisfy n 0 IM(0 M t) 0(iii) e points which satisfy M 0 In(n 0 t) 0
With parameters fixed we can easily decide which is theminimum point of (45) In the following we will investigatethe form of those points
e first kind of points (n1t M1t) is the solution of thefollowing equations
In(n M t) minusDtcf
σ232μ + n1113874 1113875M
+Dtcfθ
2σ232n2
+ 2μn1113874 1113875M +D
2t c
2f
2σ2μ +
n
21113874 1113875M
2
+θ2D2
t cf cf + cm1113872 1113873
2σ2n3
+ 3μn2
+ 2μ2n1113872 1113873M2
minusc2fθD
2t
σ23n
2
4+ 2μn + μ21113888 1113889M
2 0
(A2)
IM(n M t) minusDtcf
σ2(μ + n) μ +
n
21113874 1113875
+Dtcfθ
2σ2n2 μ +
n
21113874 1113875 +
D2t c
2f
σ2μ +
n
21113874 1113875
2M
+θ2D2
t cf cf + cm1113872 1113873
σ2n2 μ +
n
21113874 1113875
2M
minus2c
2fθD
2t
σ2n μ +
n
21113874 1113875
2M 0
(A3)
We can deduce from (A2) that
DtM1t n1t + μ minus n
21tθ21113872 1113873 +(μ2) minus θn
21t41113872 1113873 minus θμn1t
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf minus cf21113872 1113873 + cfθμ minus cfθn1t21113872 1113873 + θ2μ cf + cm1113872 1113873n1t1113960 1113961
(A4)
It also follows from (A3) that
DtM1t n1t + μ minus n1t( 1113857
2θ21113872 1113873
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t1113872 1113873
2θ2 cm + cf1113872 1113873 + cf1113876 1113877
(A5)
Combining the above two equations we can get that
n1t + μ minusn1t( 1113857
2θ2
1113888 1113889 minuscf
2+ cfθμ minus
cfθn1t
2+ θ2μ cf + cm1113872 1113873n1t1113890 1113891
+θn
21t
4+ θμn1t minus
μ2
1113888 1113889 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf1113960 1113961 0
(A6)
Clearly by solving (A5) and (A6) we can get that n1 andDtM1t are constants
Denote the second kind of point by (0 M2t) us M2t
satisfies (A5) with n replaced with 0 and we can get thatDtM2t is a constant
Denote the third kind of points by (n3t 0) ey satisfy(A4) By solving it we can get that n3t is a constant
Denote the minimum point of (45) by (nlowastt Mlowastt ) Itfollows from the above analysis that nlowastt and DtM
lowastt are all
constants For different μ θ cf and cm by calculating (A6)(A2) or (A3) we can get different nlowast
By using R we plot the following figures which indicatethe effect of μ θ cf and cm on nlowast (Figure 1)
Data Availability
No data were used to support this study
Conflicts of Interest
e authors declare that they have no conflicts of interest
Acknowledgments
is work was supported by the National Natural ScienceFoundation of China (11901404)
References
[1] A Almazan K C Brown M Carlson and D A ChapmanldquoWhy constrain your mutual fund managerrdquo Journal of Fi-nancial Economics vol 73 no 2 pp 289ndash321 2004
[2] M K Brunnermeier and L H Pedersen ldquoMarket liquidityand funding liquidityrdquo Review of Financial Studies vol 22no 6 pp 2201ndash2238 2009
[3] P H Dybvig H K Farnsworth and J N CarpenterldquoPortfolio performance and agencyrdquo Review of FinancialStudies vol 23 no 1 pp 1ndash23 2010
Mathematical Problems in Engineering 9
[4] S Gervais A W Lynch and D K Musto ldquoFund families asdelegated monitors of money managersrdquo Review of FinancialStudies vol 18 no 4 pp 1139ndash1169 2005
[5] V Guerrieri and P Kondor ldquoFund managers career con-cerns and asset price volatilityrdquo 7e American EconomicReview vol 102 no 5 pp 1986ndash2017 2012
[6] S Ross ldquoe economic theory of agency the principalrsquosproblemrdquo 7e American Economic Review vol 63 pp 134ndash139 1973
[7] J A Mirrlees ldquoe optimal structure of incentives and au-thority within an organizationrdquo7eBell Journal of Economicsvol 7 no 1 pp 105ndash131 1976
[8] B Holmstrom ldquoMoral hazard and observabilityrdquo 7e BellJournal of Economics vol 10 no 1 pp 74ndash91 1979
[9] P Bolton and M Dewatripont Contract 7eory MIT PressCambridge UK 2005
[10] B Holmstrom and P Milgrom ldquoAggregation and linearity inthe provision of intertemporal incentivesrdquo Econometricavol 55 no 2 pp 303ndash328 1987
[11] H Schattler and J Sung ldquoe first-order approach to thecontinuous-time principal-agent problem with exponentialutilityrdquo Journal of Economic7eory vol 61 no 2 pp 331ndash3711993
[12] H Schattler and J Sung ldquoOn optimal sharing rules in dis-crete-and continuous-time principal-agent problems withexponential utilityrdquo Journal of Economic Dynamics andControl vol 21 no 2-3 pp 551ndash574 1997
[13] H M Muller ldquoe first-best sharing rule in the continuous-time principal-agent problem with exponential utilityrdquoJournal of Economic 7eory vol 79 no 2 pp 276ndash280 1998
[14] H M Muller ldquoAsymptotic efficiency in dynamic principal-agent problemsrdquo Journal of Economic 7eory vol 91 no 2pp 292ndash301 2000
[15] J Cvitanic X Wan and J Zhang ldquoOptimal compensationwith hidden action and lump-sum payment in a continuous-time modelrdquo Applied Mathematics and Optimization vol 59pp 99ndash146 2009
[16] J Cvitanic and J Zhang Contract 7eory in Continuous TimeModels Springer-Verlag Berlin Germany 2013
[17] Y Sannikov ldquoA continuous-time version of the principal-agent problemrdquo7eReview of Economic Studies vol 75 no 3pp 957ndash984 2008
[18] Z He ldquoA Model of dynamic compensation and capitalstructurerdquo Journal of Financial Economics vol 100 no 2pp 351ndash366 2011
[19] J Cvitanic D Possamai and N Touzi ldquoDynamic pro-gramming approach to principal-agent problemsrdquo Financeand Stochastics vol 22 pp 1ndash37 2018
[20] Z He and W Xiong ldquoDelegated asset management invest-ment mandates and capital immobilityrdquo Journal of FinancialEconomics vol 107 no 2 pp 239ndash258 2013
[21] H Pham Continuous-time Stochastic Control and Optimi-zation with Financial Applications Springer-Verlag NewYork NY USA 2009
10 Mathematical Problems in Engineering
Denote the set of all the processes satisfying the aboveconditions by V(t)
For some (Z Γ) isinV(t) and Yt ge 0 define theFW-progressively measurable process YZΓ on the filtrationspace (ΩF P FW
t1113864 1113865tge0) by
YZΓs Yt minus 1113946
s
tH r Xr Y
ZΓr Zr Γr1113872 1113873dr
+ 1113946s
tZrdXr +
12
1113946s
tΓrdlangXrangr s isin [t T]
(17)
where Xr is the investment income process Clearly forfixed Yt Z Γ YZΓ
T is only related to the investment incomeprocess and is FT measurable suppose that it is an in-centive strategy (we prove it in Corollary 1) In the fol-lowing we give the relationship between YZΓ
s and themanagerrsquos value function First we give the followinglemma
Lemma 1 Define
πlowastZΓ blowastZΓ
nlowastZΓ
1113872 1113873
blowastYZΓ
t ZtΓtt1113882 1113883
tge0 nlowastYZΓ
t ZtΓtt1113882 1113883
tge01113874 1113875
(18)
and then we have πlowastZΓ isin Π
Proof On the one hand since Z Γ YZΓ are all predictablestochastic processes referring to (12) and (13) we can getthat blowastZΓ and nlowastZΓ are bounded positive predictable sto-chastic processes On the other hand b
lowastyzct and n
lowastyzct are
independent of x Taking blowastZΓ and nlowastZΓ into (2) we can getthe Lipschitz continuity and linear growth of the coefficientsin (2) with respect to Xt then (2) has a unique solution eproof is done
Denote the investment income process under πlowastZΓ byXlowastZΓ We also have the following theorem
Theorem 2 Denote the managerrsquos value function with aterminal return (lnYZΓ
T cm) by Vm(t x YZΓT ) We can ob-
tain that
Yt Vm t x YZΓT1113872 1113873 (19)
Furthermore the managerrsquos optimal strategy is πlowastZΓ
Proof forallπ isin Π s isin [t T] we have
YZΓs Yt minus 1113946
s
tH r X
πr Y
ZΓr Zr Γr1113872 1113873dr
+ 1113946s
tZrdX
πr +
12
1113946s
tΓrdlangX
πrangr
(20)
Using Itorsquos formula we have
deminus 1113946
r
tβ(u π)du
YZΓr e
minus 1113946r
tβ(u π)du
minus H r Xπr Y
ZΓr Zr Γr1113872 11138731113960
+ rXπr + b
πr μ + n
πr( 1113857( 1113857Zr
+bπ2r σ2
2Γr minus β(r π)1113891dr
+ eminus 1113946
r
tβ(u π)du
σZrdW(r)
(21)
It follows from (16) that eminus 1113938
r
tβ(uπ)duσZrdW(r) is a
martingale Integrating and taking expectations on bothsides of (21) we can get
Yt geE eminus 1113946
T
tβ(u π)du
YZΓT |X
πt x
⎡⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎣⎤⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎦ J
πm t x Y
ZΓT1113872 1113873
(22)
Furthermore by simple calculations under πlowastZΓ isin Πwe have
dYZΓt β t πlowastZΓ
1113872 1113873YZΓt dt + b
lowastYZΓt ZtΓt
t ZtσdWt (23)
Using (23) and Itorsquos formula we can obtain
deminus 1113946
r
tβ u πlowastZΓ
1113872 1113873duY
ZΓr e
minus 1113946r
tβ u πlowastZΓ
1113872 1113873dublowastYZΓ
t ZtΓtt ZtσdWt
(24)
With similar methods integrating and taking expecta-tions on both sides of (24) we have
Yt E eminus 1113946
T
tβ u πlowastZΓ
1113872 1113873duY
ZΓT |XlowastZΓt x
⎡⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎢⎣⎤⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎥⎦
JπlowastZΓ
m t x YZΓT1113872 1113873ge J
πm t x Y
ZΓT1113872 1113873
(25)
is implies that πlowastZΓ is the managerrsquos optimal strategyand
Yt Vm t x YZΓT1113872 1113873 (26)
Up till now fixing (Z Γ) isin V(t) we can get themanagerrsquos optimal strategy and represent the managerrsquosvalue function In Section 4 we begin to consider the in-vestorrsquos optimization problem at is finding the optimal(Z Γ) isin V(t) to maximize the investorrsquos net profit
4 The Investorrsquos Optimization Problem
Suppose that the investorrsquos wealth is x at t Apparently theinvestorrsquos value function is uniquely determined by thewealth process and the managerrsquos value function So the
4 Mathematical Problems in Engineering
objective of the investor is to find the optimal (Z Γ) isinV(t)
to minimize his value function Define
v(t x y) inf(ZΓ)isinV(t)
E ecf XlowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
πt x Y
ZΓt y1113876 1113877
(27)
Referring to eorem 41 in [19] we know that if As-sumption 32 Assumption 43 and Assumption 44 in [19]hold the investorrsquos value function satisfies
Vf(t x) infyisin 0ecmR[ ]
v(t x y) (28)
Here R is the minimum pay in order to make sure thatthe manager takes the job
Section 41 gives the verification of the threeassumptions
41 7e Verification of Assumptions
Assumption 1 (Assumption 32 in [19]) H has at least oneextreme point (b
lowastyzct n
lowastyzct ) For any t isin [0 T]
(Z Γ) isin V(t) we have πlowastZΓ isin Π
Proof is is the result of eorem 1 and Lemma 1e Hamiltonian function can be expressed as
H(t x y z c) infbgt0
F(t x y z b) +b2σ2
2c1113896 1113897 (29)
Here
F(t x y z b) infngt0
minus Dt
cmθn2b
2y +(rx + b(μ + n))z1113896 1113897
(30)
Define
YZs Yt minus 1113946
s
tF r Xr Y
Zr Zr1113872 1113873dr + 1113946
s
tZrdXr s isin [t T]
(31)
and we have the following assumption
Assumption 2 (Assumption 43 in [19]) F has at least oneextreme point n
lowastyzbt furthermore (b nlowastY
ZZb) isin Π
Proof On the one hand the right hand of F is a parabolawith an opening up with respect to n so the minimum pointis attained at the axis of the parabola (zDtcmθy) that isnlowastyzbt (zDtcmθy) On the other hand since Zlt 0 is
predictable we can get that nlowastYZ
t Ztbt (bZtDtcmθbYZ
t ) is apositive predictable process Furthermore b and n
lowastyzbt are
independent of x is implies the Lipschitz continuity andlinear growth of the coefficients in (2) with respect to theinvestment income process then (2) has a uniquesolution
Assumption 3 (Assumption 44 in [19]) forallbgt 0 (1b2σ2) isbounded
Proof We can get the result directly from σ gt 0 bgt 0
427e Investorrsquos Value Function Clearly as soon as we getv(t x y) we can obtain Vf(t x) e following theoremgives the partial differential equation satisfied by v(t x y)
Theorem 3 v(t x y) is the viscosity solution of
minus vt(t x y) inf(ZΓ)isinV(t)
G(t x y Z Γ) (32)
v(T x y) ecfx
yminus cfcm( 1113857
(33)
where
G(t x y Z Γ) rx + blowastZΓt μ + n
lowastZΓt1113872 11138731113960 1113961vx
+σ2 blowastZΓt1113872 1113873
2
2vxx +
Dtcmθ nlowastZΓt1113872 1113873
2
2blowastZΓt yvy
+σ2 blowastZΓt1113872 1113873
2
2Z2vyy + σ2 b
lowastZΓt1113872 1113873
2Zvxy
(34)
Proof By the definition of v(t x y) we can obtain that itsatisfies (33) Furthermore according to the dynamic pro-gramming principle we have
v(t x y) inf(ZΓ)isinV(t)
v t + h XlowastZΓt+h Y
ZΓt+h1113872 1113873 (35)
By using Itorsquos formula with respect to v(s XlowastZΓs YZΓ
s )
from t to t + h we have
v t + h XlowastZΓt+h Y
ZΓt+h1113872 1113873 v(t x y) + 1113946
t+h
tvt s X
lowastZΓs Y
ZΓs1113872 1113873
+ G s XlowastZΓs Y
ZΓs Zs Γs1113872 1113873ds
(36)
Combining with the above two equations we can get
vt(t x y) + inf(ZΓ)isinV(t)
G(t x y Z Γ) 0 (37)
at is v(t x y) satisfies (32) e proof is doneNext we are going to solve (32) and (33) Considering
the boundary condition we guess
v(t x y) ecfDtxy
minus cfcm( 1113857E(t) (38)
where E(t) is a function of t which satisfies E(T) 1If the variables in the solution can be separated from
each other (32) can be easily solved However (32) containsecfDtx which is a cross term of t and x To cancel the crossterm we introduce zt DtX
lowastZΓt Using Itorsquos formula we
can get
dzt minus rDtXlowastZΓt dt + DtdX
lowastZΓt
DtblowastZΓt μ + n
lowastZΓt1113872 1113873dt + σdW(t)1113960 1113961
(39)
Mathematical Problems in Engineering 5
We can also obtain zT XlowastZΓT Define
V(t z y) inf(ZΓ)isinV(t)
E ecf zTminus lnYZΓ
Tcm( )( )|zt z1113876 1113877
inf(ZΓ)isinV(t)
E ecf X lowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
lowastZΓt
z
Dt
1113890 1113891
v tz
Dt
y1113888 1113889
(40)
Obviously solving v(t x y) is equivalent to solvingV(t z y) Using a similar method as the one in eorem 3we can get that
minus Vt inf(ZΓ)isinV(t)
minusμ + n
lowastZΓt 21113872 11138731113872 1113873 μ + n
lowastZΓt1113872 1113873
σ2Dt
Z
ΓVz
⎧⎨
⎩
minuscmθ n
lowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2σ2yDt
Z
ΓVy
+μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2D
2t
Z2
Γ2Vzz
+nlowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2cmθyDt( 1113857
2Z2
Γ2Vyy
+nlowastZΓt μ + n
lowastZΓt 21113872 11138731113872 1113873
2
σ2cmθyD
2t
Z2
Γ2Vzy
⎫⎪⎬
⎪⎭
(41)
V(T z y) ecfz
yminus cfcm( 1113857
(42)
e first step in solving (41) is to find its minimum pointDefine MZΓ (ZΓ) it is shown in Section 3 that (Z Γ) and(MZΓ nlowastZΓ) are one-to-one en (41) is transformed into
minus Vt inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMVz1113896
+(μ +(n2))
2
2σ2D
2t M
2Vzz minus
cmθn2(μ +(n2))
2σ2yDtMVy
+n2(μ +(n2))
2
2σ2cmθyDt( 1113857
2M
2Vyy
+n(μ +(n2))
2
σ2cmθyD
2t M
2Vzy1113897
(43)
Now the problem of finding the minimum point in (41) ischanged into a problem of finding theminimumpoint in (43)
According to (38) we suppose thatV(t z y) E(t)ecfzyminus (cfcm) By some simple calculationswe can get that
Vz(t z y) cfV(t z y)
Vzz(t z y) c2fV(t z y)
yVy(t z y) minuscf
cm
V(t z y)
y2Vyy(t z y)
cf cf + cm1113872 1113873
c2m
V(t z y)
yVzy(t z y) minusc2f
cm
V(t z y)
(44)
Taking them into (43) we have
minus Eprime(t)V(t z y) inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMcf1113896
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
21113897E(t)V(t z y)
(45)
Since the right hand of (45) is continuous the minimumpoint can only be attained at the stable points or theboundary points which depends on the parameter valuesDenote the minimum point of (45) by (nlowastt Mlowastt ) and denotethe corresponding minimum point of (41) by (Zlowastt Γlowastt ) It isshown from the Appendix that nlowastt and DtM
lowastt are constants
concerning μ θ cf and cm Let nlowastt nlowast
Remark 4 On the one hand the exponential form of theobjective function implies that blowastt is independent of Xlowastt Onthe other hand the benefit and the cost brought by themanagerrsquos effort are only related to blowastt so nlowastt is independentof Xlowastt Furthermore in this paper we consider the dis-counted benefit and cost brought by the managerrsquos effort sonlowastt is independent of t
Remark 5 It is shown from figures in the Appendix that nlowast
decreases with an increase in μ(the drift coefficient of thefund wealth process) θ(the effort cost coefficient) and|cm|(the managerrsquos risk aversion level) It increases with anincrease in |cf|(the investorrsquos risk aversion level)
6 Mathematical Problems in Engineering
Remark 6 Define Ylowastt Vm(t x YZlowastΓlowastT ) considering (12)
and (13) we can get that (Zlowastt Ylowastt ) θcmDtnlowast and Dtb
lowastt
(minus (μ + (nlowast2))σ2)DtMlowastt are constants
Taking the minimum point into (45) and solving it wecan get
V(t z y) eB(Tminus t)
ecfz
yminus cfcm( 1113857
(46)
Here
B minusμ + n
lowast2( 1113857( 1113857 μ + nlowast
( 1113857
σ2DtMlowastt cf
+μ + n
lowast2( 1113857( 11138572
2σ2D
2t Mlowast 2t c
2f +
cfθnlowast2 μ + n
lowast2( 1113857( 1113857
2σ2DtMlowastt
+nlowast2 μ + n
lowast2( 1113857( 11138572
2σ2θ2D2
t Mlowast 2t cf cf + cm1113872 1113873
minusnlowast μ + n
lowast2( 1113857( 11138572
σ2c2fθD
2t Mlowast 2t
(47)
0 000
002
004
006
008
010
n
035 040 045030the drift coefficient of the fund
0ndash
000
002
004
006
008
010
n
20 25 3010 15The effort cost coefficient
0
000
002
004
006
008
010
n
020 025 030015The managerrsquos risk aversion level
0
011 012 013 014 015010The investorrsquos risk aversion level
000
002
004
006
008
010
n
Figure 1 e effects of parameters on the optimal effort level
Mathematical Problems in Engineering 7
is a constant As a consequence we can also get the followingresults
v(t x y) eB(Tminus t)
ecfDtxy
minus cfcm( 1113857
Vf(t x) v t x ecmR
1113872 1113873 eB(Tminus t)
ecf Dtxminus R( )
(48)
43 7e Investorrsquos Excitation Mechanism In this section letus analyze the investorrsquos excitation mechanism DenoteYlowastt YZlowastΓlowast
t From the above analysis we know that
dYlowastt
Dtcmθnlowast2
blowastt Ylowastt
2dt + b
lowastt Zlowastt σdWt
Ylowastt e
cmR
(49)
Using Itorsquos formula we have
d lnYlowastt
Dtcmθnlowast2
blowastt
2dt + b
lowastt
Zlowastt
Ylowastt
σdWt minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
dt
(50)
Furthermore we can get that the investment incomeunder nlowast and blowastt satisfies
dXlowastt rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt + blowastt σdWt (51)
which implies
d lnYlowastt
Dtcmθnlowast2
blowastt
2minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
1113888 1113889dt +Zlowastt
Ylowastt
dXlowastt minus rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt( 1113857
cm
Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 11138571113888 1113889dt
+ cmθnlowastDt dX
lowastt minus rX
lowastt dt( 1113857
(52)
Define constant
A Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 1113857gt 0
(53)
and then we can obtaind lnY
lowastt cmAdt + cmθn
lowastDt dX
lowastt minus rX
lowastt dt( 1113857 cm Adt + θn
lowastdDtXlowastt( 1113857
(54)
So
lnYlowastT minus cmR cm A(T minus t) + n
lowastθ XlowastT minus Dtx( 11138571113858 1113859 (55)
can be deduced immediately Since lnYT cmw(XT) wecan get the strategy
w XT( 1113857 A(T minus t) + nlowastθ XlowastT minus Dtx( 1113857 + R (56)
It is a linear function of XlowastT minus Dtx which is the dis-counted profit of the investment
Remark 7 It follows from the above results that the man-agerrsquos wages increase with the increase of the cost coefficientthe effort level and the discounted profit of the investmentFurthermore the longer the work the higher the salary It isconsistent with reality
We can also get the following corollary
Corollary 1
Ylowasts Vm s X
lowasts YlowastT( 1113857 e
cm R+A(Tminus t)+nlowastθ Xlowasts minus Dtx( )[ ] (57)
is implies that Vm(s Xlowasts YlowastT) is a decreasing convexfunction of Xlowasts us the assumption in Section 2 that YlowastT isan incentive strategy is proved
Appendix
Define
I(n M t) minus(μ +(n2))(μ + n)
σ2DtMcf
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
2
(A1)
We know that there are three kinds of points which maybe the minimum point of (45)
8 Mathematical Problems in Engineering
(i) e points which satisfy In(n M t) 0 IM
(n M t) 0(ii) e points which satisfy n 0 IM(0 M t) 0(iii) e points which satisfy M 0 In(n 0 t) 0
With parameters fixed we can easily decide which is theminimum point of (45) In the following we will investigatethe form of those points
e first kind of points (n1t M1t) is the solution of thefollowing equations
In(n M t) minusDtcf
σ232μ + n1113874 1113875M
+Dtcfθ
2σ232n2
+ 2μn1113874 1113875M +D
2t c
2f
2σ2μ +
n
21113874 1113875M
2
+θ2D2
t cf cf + cm1113872 1113873
2σ2n3
+ 3μn2
+ 2μ2n1113872 1113873M2
minusc2fθD
2t
σ23n
2
4+ 2μn + μ21113888 1113889M
2 0
(A2)
IM(n M t) minusDtcf
σ2(μ + n) μ +
n
21113874 1113875
+Dtcfθ
2σ2n2 μ +
n
21113874 1113875 +
D2t c
2f
σ2μ +
n
21113874 1113875
2M
+θ2D2
t cf cf + cm1113872 1113873
σ2n2 μ +
n
21113874 1113875
2M
minus2c
2fθD
2t
σ2n μ +
n
21113874 1113875
2M 0
(A3)
We can deduce from (A2) that
DtM1t n1t + μ minus n
21tθ21113872 1113873 +(μ2) minus θn
21t41113872 1113873 minus θμn1t
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf minus cf21113872 1113873 + cfθμ minus cfθn1t21113872 1113873 + θ2μ cf + cm1113872 1113873n1t1113960 1113961
(A4)
It also follows from (A3) that
DtM1t n1t + μ minus n1t( 1113857
2θ21113872 1113873
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t1113872 1113873
2θ2 cm + cf1113872 1113873 + cf1113876 1113877
(A5)
Combining the above two equations we can get that
n1t + μ minusn1t( 1113857
2θ2
1113888 1113889 minuscf
2+ cfθμ minus
cfθn1t
2+ θ2μ cf + cm1113872 1113873n1t1113890 1113891
+θn
21t
4+ θμn1t minus
μ2
1113888 1113889 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf1113960 1113961 0
(A6)
Clearly by solving (A5) and (A6) we can get that n1 andDtM1t are constants
Denote the second kind of point by (0 M2t) us M2t
satisfies (A5) with n replaced with 0 and we can get thatDtM2t is a constant
Denote the third kind of points by (n3t 0) ey satisfy(A4) By solving it we can get that n3t is a constant
Denote the minimum point of (45) by (nlowastt Mlowastt ) Itfollows from the above analysis that nlowastt and DtM
lowastt are all
constants For different μ θ cf and cm by calculating (A6)(A2) or (A3) we can get different nlowast
By using R we plot the following figures which indicatethe effect of μ θ cf and cm on nlowast (Figure 1)
Data Availability
No data were used to support this study
Conflicts of Interest
e authors declare that they have no conflicts of interest
Acknowledgments
is work was supported by the National Natural ScienceFoundation of China (11901404)
References
[1] A Almazan K C Brown M Carlson and D A ChapmanldquoWhy constrain your mutual fund managerrdquo Journal of Fi-nancial Economics vol 73 no 2 pp 289ndash321 2004
[2] M K Brunnermeier and L H Pedersen ldquoMarket liquidityand funding liquidityrdquo Review of Financial Studies vol 22no 6 pp 2201ndash2238 2009
[3] P H Dybvig H K Farnsworth and J N CarpenterldquoPortfolio performance and agencyrdquo Review of FinancialStudies vol 23 no 1 pp 1ndash23 2010
Mathematical Problems in Engineering 9
[4] S Gervais A W Lynch and D K Musto ldquoFund families asdelegated monitors of money managersrdquo Review of FinancialStudies vol 18 no 4 pp 1139ndash1169 2005
[5] V Guerrieri and P Kondor ldquoFund managers career con-cerns and asset price volatilityrdquo 7e American EconomicReview vol 102 no 5 pp 1986ndash2017 2012
[6] S Ross ldquoe economic theory of agency the principalrsquosproblemrdquo 7e American Economic Review vol 63 pp 134ndash139 1973
[7] J A Mirrlees ldquoe optimal structure of incentives and au-thority within an organizationrdquo7eBell Journal of Economicsvol 7 no 1 pp 105ndash131 1976
[8] B Holmstrom ldquoMoral hazard and observabilityrdquo 7e BellJournal of Economics vol 10 no 1 pp 74ndash91 1979
[9] P Bolton and M Dewatripont Contract 7eory MIT PressCambridge UK 2005
[10] B Holmstrom and P Milgrom ldquoAggregation and linearity inthe provision of intertemporal incentivesrdquo Econometricavol 55 no 2 pp 303ndash328 1987
[11] H Schattler and J Sung ldquoe first-order approach to thecontinuous-time principal-agent problem with exponentialutilityrdquo Journal of Economic7eory vol 61 no 2 pp 331ndash3711993
[12] H Schattler and J Sung ldquoOn optimal sharing rules in dis-crete-and continuous-time principal-agent problems withexponential utilityrdquo Journal of Economic Dynamics andControl vol 21 no 2-3 pp 551ndash574 1997
[13] H M Muller ldquoe first-best sharing rule in the continuous-time principal-agent problem with exponential utilityrdquoJournal of Economic 7eory vol 79 no 2 pp 276ndash280 1998
[14] H M Muller ldquoAsymptotic efficiency in dynamic principal-agent problemsrdquo Journal of Economic 7eory vol 91 no 2pp 292ndash301 2000
[15] J Cvitanic X Wan and J Zhang ldquoOptimal compensationwith hidden action and lump-sum payment in a continuous-time modelrdquo Applied Mathematics and Optimization vol 59pp 99ndash146 2009
[16] J Cvitanic and J Zhang Contract 7eory in Continuous TimeModels Springer-Verlag Berlin Germany 2013
[17] Y Sannikov ldquoA continuous-time version of the principal-agent problemrdquo7eReview of Economic Studies vol 75 no 3pp 957ndash984 2008
[18] Z He ldquoA Model of dynamic compensation and capitalstructurerdquo Journal of Financial Economics vol 100 no 2pp 351ndash366 2011
[19] J Cvitanic D Possamai and N Touzi ldquoDynamic pro-gramming approach to principal-agent problemsrdquo Financeand Stochastics vol 22 pp 1ndash37 2018
[20] Z He and W Xiong ldquoDelegated asset management invest-ment mandates and capital immobilityrdquo Journal of FinancialEconomics vol 107 no 2 pp 239ndash258 2013
[21] H Pham Continuous-time Stochastic Control and Optimi-zation with Financial Applications Springer-Verlag NewYork NY USA 2009
10 Mathematical Problems in Engineering
objective of the investor is to find the optimal (Z Γ) isinV(t)
to minimize his value function Define
v(t x y) inf(ZΓ)isinV(t)
E ecf XlowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
πt x Y
ZΓt y1113876 1113877
(27)
Referring to eorem 41 in [19] we know that if As-sumption 32 Assumption 43 and Assumption 44 in [19]hold the investorrsquos value function satisfies
Vf(t x) infyisin 0ecmR[ ]
v(t x y) (28)
Here R is the minimum pay in order to make sure thatthe manager takes the job
Section 41 gives the verification of the threeassumptions
41 7e Verification of Assumptions
Assumption 1 (Assumption 32 in [19]) H has at least oneextreme point (b
lowastyzct n
lowastyzct ) For any t isin [0 T]
(Z Γ) isin V(t) we have πlowastZΓ isin Π
Proof is is the result of eorem 1 and Lemma 1e Hamiltonian function can be expressed as
H(t x y z c) infbgt0
F(t x y z b) +b2σ2
2c1113896 1113897 (29)
Here
F(t x y z b) infngt0
minus Dt
cmθn2b
2y +(rx + b(μ + n))z1113896 1113897
(30)
Define
YZs Yt minus 1113946
s
tF r Xr Y
Zr Zr1113872 1113873dr + 1113946
s
tZrdXr s isin [t T]
(31)
and we have the following assumption
Assumption 2 (Assumption 43 in [19]) F has at least oneextreme point n
lowastyzbt furthermore (b nlowastY
ZZb) isin Π
Proof On the one hand the right hand of F is a parabolawith an opening up with respect to n so the minimum pointis attained at the axis of the parabola (zDtcmθy) that isnlowastyzbt (zDtcmθy) On the other hand since Zlt 0 is
predictable we can get that nlowastYZ
t Ztbt (bZtDtcmθbYZ
t ) is apositive predictable process Furthermore b and n
lowastyzbt are
independent of x is implies the Lipschitz continuity andlinear growth of the coefficients in (2) with respect to theinvestment income process then (2) has a uniquesolution
Assumption 3 (Assumption 44 in [19]) forallbgt 0 (1b2σ2) isbounded
Proof We can get the result directly from σ gt 0 bgt 0
427e Investorrsquos Value Function Clearly as soon as we getv(t x y) we can obtain Vf(t x) e following theoremgives the partial differential equation satisfied by v(t x y)
Theorem 3 v(t x y) is the viscosity solution of
minus vt(t x y) inf(ZΓ)isinV(t)
G(t x y Z Γ) (32)
v(T x y) ecfx
yminus cfcm( 1113857
(33)
where
G(t x y Z Γ) rx + blowastZΓt μ + n
lowastZΓt1113872 11138731113960 1113961vx
+σ2 blowastZΓt1113872 1113873
2
2vxx +
Dtcmθ nlowastZΓt1113872 1113873
2
2blowastZΓt yvy
+σ2 blowastZΓt1113872 1113873
2
2Z2vyy + σ2 b
lowastZΓt1113872 1113873
2Zvxy
(34)
Proof By the definition of v(t x y) we can obtain that itsatisfies (33) Furthermore according to the dynamic pro-gramming principle we have
v(t x y) inf(ZΓ)isinV(t)
v t + h XlowastZΓt+h Y
ZΓt+h1113872 1113873 (35)
By using Itorsquos formula with respect to v(s XlowastZΓs YZΓ
s )
from t to t + h we have
v t + h XlowastZΓt+h Y
ZΓt+h1113872 1113873 v(t x y) + 1113946
t+h
tvt s X
lowastZΓs Y
ZΓs1113872 1113873
+ G s XlowastZΓs Y
ZΓs Zs Γs1113872 1113873ds
(36)
Combining with the above two equations we can get
vt(t x y) + inf(ZΓ)isinV(t)
G(t x y Z Γ) 0 (37)
at is v(t x y) satisfies (32) e proof is doneNext we are going to solve (32) and (33) Considering
the boundary condition we guess
v(t x y) ecfDtxy
minus cfcm( 1113857E(t) (38)
where E(t) is a function of t which satisfies E(T) 1If the variables in the solution can be separated from
each other (32) can be easily solved However (32) containsecfDtx which is a cross term of t and x To cancel the crossterm we introduce zt DtX
lowastZΓt Using Itorsquos formula we
can get
dzt minus rDtXlowastZΓt dt + DtdX
lowastZΓt
DtblowastZΓt μ + n
lowastZΓt1113872 1113873dt + σdW(t)1113960 1113961
(39)
Mathematical Problems in Engineering 5
We can also obtain zT XlowastZΓT Define
V(t z y) inf(ZΓ)isinV(t)
E ecf zTminus lnYZΓ
Tcm( )( )|zt z1113876 1113877
inf(ZΓ)isinV(t)
E ecf X lowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
lowastZΓt
z
Dt
1113890 1113891
v tz
Dt
y1113888 1113889
(40)
Obviously solving v(t x y) is equivalent to solvingV(t z y) Using a similar method as the one in eorem 3we can get that
minus Vt inf(ZΓ)isinV(t)
minusμ + n
lowastZΓt 21113872 11138731113872 1113873 μ + n
lowastZΓt1113872 1113873
σ2Dt
Z
ΓVz
⎧⎨
⎩
minuscmθ n
lowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2σ2yDt
Z
ΓVy
+μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2D
2t
Z2
Γ2Vzz
+nlowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2cmθyDt( 1113857
2Z2
Γ2Vyy
+nlowastZΓt μ + n
lowastZΓt 21113872 11138731113872 1113873
2
σ2cmθyD
2t
Z2
Γ2Vzy
⎫⎪⎬
⎪⎭
(41)
V(T z y) ecfz
yminus cfcm( 1113857
(42)
e first step in solving (41) is to find its minimum pointDefine MZΓ (ZΓ) it is shown in Section 3 that (Z Γ) and(MZΓ nlowastZΓ) are one-to-one en (41) is transformed into
minus Vt inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMVz1113896
+(μ +(n2))
2
2σ2D
2t M
2Vzz minus
cmθn2(μ +(n2))
2σ2yDtMVy
+n2(μ +(n2))
2
2σ2cmθyDt( 1113857
2M
2Vyy
+n(μ +(n2))
2
σ2cmθyD
2t M
2Vzy1113897
(43)
Now the problem of finding the minimum point in (41) ischanged into a problem of finding theminimumpoint in (43)
According to (38) we suppose thatV(t z y) E(t)ecfzyminus (cfcm) By some simple calculationswe can get that
Vz(t z y) cfV(t z y)
Vzz(t z y) c2fV(t z y)
yVy(t z y) minuscf
cm
V(t z y)
y2Vyy(t z y)
cf cf + cm1113872 1113873
c2m
V(t z y)
yVzy(t z y) minusc2f
cm
V(t z y)
(44)
Taking them into (43) we have
minus Eprime(t)V(t z y) inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMcf1113896
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
21113897E(t)V(t z y)
(45)
Since the right hand of (45) is continuous the minimumpoint can only be attained at the stable points or theboundary points which depends on the parameter valuesDenote the minimum point of (45) by (nlowastt Mlowastt ) and denotethe corresponding minimum point of (41) by (Zlowastt Γlowastt ) It isshown from the Appendix that nlowastt and DtM
lowastt are constants
concerning μ θ cf and cm Let nlowastt nlowast
Remark 4 On the one hand the exponential form of theobjective function implies that blowastt is independent of Xlowastt Onthe other hand the benefit and the cost brought by themanagerrsquos effort are only related to blowastt so nlowastt is independentof Xlowastt Furthermore in this paper we consider the dis-counted benefit and cost brought by the managerrsquos effort sonlowastt is independent of t
Remark 5 It is shown from figures in the Appendix that nlowast
decreases with an increase in μ(the drift coefficient of thefund wealth process) θ(the effort cost coefficient) and|cm|(the managerrsquos risk aversion level) It increases with anincrease in |cf|(the investorrsquos risk aversion level)
6 Mathematical Problems in Engineering
Remark 6 Define Ylowastt Vm(t x YZlowastΓlowastT ) considering (12)
and (13) we can get that (Zlowastt Ylowastt ) θcmDtnlowast and Dtb
lowastt
(minus (μ + (nlowast2))σ2)DtMlowastt are constants
Taking the minimum point into (45) and solving it wecan get
V(t z y) eB(Tminus t)
ecfz
yminus cfcm( 1113857
(46)
Here
B minusμ + n
lowast2( 1113857( 1113857 μ + nlowast
( 1113857
σ2DtMlowastt cf
+μ + n
lowast2( 1113857( 11138572
2σ2D
2t Mlowast 2t c
2f +
cfθnlowast2 μ + n
lowast2( 1113857( 1113857
2σ2DtMlowastt
+nlowast2 μ + n
lowast2( 1113857( 11138572
2σ2θ2D2
t Mlowast 2t cf cf + cm1113872 1113873
minusnlowast μ + n
lowast2( 1113857( 11138572
σ2c2fθD
2t Mlowast 2t
(47)
0 000
002
004
006
008
010
n
035 040 045030the drift coefficient of the fund
0ndash
000
002
004
006
008
010
n
20 25 3010 15The effort cost coefficient
0
000
002
004
006
008
010
n
020 025 030015The managerrsquos risk aversion level
0
011 012 013 014 015010The investorrsquos risk aversion level
000
002
004
006
008
010
n
Figure 1 e effects of parameters on the optimal effort level
Mathematical Problems in Engineering 7
is a constant As a consequence we can also get the followingresults
v(t x y) eB(Tminus t)
ecfDtxy
minus cfcm( 1113857
Vf(t x) v t x ecmR
1113872 1113873 eB(Tminus t)
ecf Dtxminus R( )
(48)
43 7e Investorrsquos Excitation Mechanism In this section letus analyze the investorrsquos excitation mechanism DenoteYlowastt YZlowastΓlowast
t From the above analysis we know that
dYlowastt
Dtcmθnlowast2
blowastt Ylowastt
2dt + b
lowastt Zlowastt σdWt
Ylowastt e
cmR
(49)
Using Itorsquos formula we have
d lnYlowastt
Dtcmθnlowast2
blowastt
2dt + b
lowastt
Zlowastt
Ylowastt
σdWt minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
dt
(50)
Furthermore we can get that the investment incomeunder nlowast and blowastt satisfies
dXlowastt rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt + blowastt σdWt (51)
which implies
d lnYlowastt
Dtcmθnlowast2
blowastt
2minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
1113888 1113889dt +Zlowastt
Ylowastt
dXlowastt minus rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt( 1113857
cm
Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 11138571113888 1113889dt
+ cmθnlowastDt dX
lowastt minus rX
lowastt dt( 1113857
(52)
Define constant
A Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 1113857gt 0
(53)
and then we can obtaind lnY
lowastt cmAdt + cmθn
lowastDt dX
lowastt minus rX
lowastt dt( 1113857 cm Adt + θn
lowastdDtXlowastt( 1113857
(54)
So
lnYlowastT minus cmR cm A(T minus t) + n
lowastθ XlowastT minus Dtx( 11138571113858 1113859 (55)
can be deduced immediately Since lnYT cmw(XT) wecan get the strategy
w XT( 1113857 A(T minus t) + nlowastθ XlowastT minus Dtx( 1113857 + R (56)
It is a linear function of XlowastT minus Dtx which is the dis-counted profit of the investment
Remark 7 It follows from the above results that the man-agerrsquos wages increase with the increase of the cost coefficientthe effort level and the discounted profit of the investmentFurthermore the longer the work the higher the salary It isconsistent with reality
We can also get the following corollary
Corollary 1
Ylowasts Vm s X
lowasts YlowastT( 1113857 e
cm R+A(Tminus t)+nlowastθ Xlowasts minus Dtx( )[ ] (57)
is implies that Vm(s Xlowasts YlowastT) is a decreasing convexfunction of Xlowasts us the assumption in Section 2 that YlowastT isan incentive strategy is proved
Appendix
Define
I(n M t) minus(μ +(n2))(μ + n)
σ2DtMcf
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
2
(A1)
We know that there are three kinds of points which maybe the minimum point of (45)
8 Mathematical Problems in Engineering
(i) e points which satisfy In(n M t) 0 IM
(n M t) 0(ii) e points which satisfy n 0 IM(0 M t) 0(iii) e points which satisfy M 0 In(n 0 t) 0
With parameters fixed we can easily decide which is theminimum point of (45) In the following we will investigatethe form of those points
e first kind of points (n1t M1t) is the solution of thefollowing equations
In(n M t) minusDtcf
σ232μ + n1113874 1113875M
+Dtcfθ
2σ232n2
+ 2μn1113874 1113875M +D
2t c
2f
2σ2μ +
n
21113874 1113875M
2
+θ2D2
t cf cf + cm1113872 1113873
2σ2n3
+ 3μn2
+ 2μ2n1113872 1113873M2
minusc2fθD
2t
σ23n
2
4+ 2μn + μ21113888 1113889M
2 0
(A2)
IM(n M t) minusDtcf
σ2(μ + n) μ +
n
21113874 1113875
+Dtcfθ
2σ2n2 μ +
n
21113874 1113875 +
D2t c
2f
σ2μ +
n
21113874 1113875
2M
+θ2D2
t cf cf + cm1113872 1113873
σ2n2 μ +
n
21113874 1113875
2M
minus2c
2fθD
2t
σ2n μ +
n
21113874 1113875
2M 0
(A3)
We can deduce from (A2) that
DtM1t n1t + μ minus n
21tθ21113872 1113873 +(μ2) minus θn
21t41113872 1113873 minus θμn1t
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf minus cf21113872 1113873 + cfθμ minus cfθn1t21113872 1113873 + θ2μ cf + cm1113872 1113873n1t1113960 1113961
(A4)
It also follows from (A3) that
DtM1t n1t + μ minus n1t( 1113857
2θ21113872 1113873
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t1113872 1113873
2θ2 cm + cf1113872 1113873 + cf1113876 1113877
(A5)
Combining the above two equations we can get that
n1t + μ minusn1t( 1113857
2θ2
1113888 1113889 minuscf
2+ cfθμ minus
cfθn1t
2+ θ2μ cf + cm1113872 1113873n1t1113890 1113891
+θn
21t
4+ θμn1t minus
μ2
1113888 1113889 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf1113960 1113961 0
(A6)
Clearly by solving (A5) and (A6) we can get that n1 andDtM1t are constants
Denote the second kind of point by (0 M2t) us M2t
satisfies (A5) with n replaced with 0 and we can get thatDtM2t is a constant
Denote the third kind of points by (n3t 0) ey satisfy(A4) By solving it we can get that n3t is a constant
Denote the minimum point of (45) by (nlowastt Mlowastt ) Itfollows from the above analysis that nlowastt and DtM
lowastt are all
constants For different μ θ cf and cm by calculating (A6)(A2) or (A3) we can get different nlowast
By using R we plot the following figures which indicatethe effect of μ θ cf and cm on nlowast (Figure 1)
Data Availability
No data were used to support this study
Conflicts of Interest
e authors declare that they have no conflicts of interest
Acknowledgments
is work was supported by the National Natural ScienceFoundation of China (11901404)
References
[1] A Almazan K C Brown M Carlson and D A ChapmanldquoWhy constrain your mutual fund managerrdquo Journal of Fi-nancial Economics vol 73 no 2 pp 289ndash321 2004
[2] M K Brunnermeier and L H Pedersen ldquoMarket liquidityand funding liquidityrdquo Review of Financial Studies vol 22no 6 pp 2201ndash2238 2009
[3] P H Dybvig H K Farnsworth and J N CarpenterldquoPortfolio performance and agencyrdquo Review of FinancialStudies vol 23 no 1 pp 1ndash23 2010
Mathematical Problems in Engineering 9
[4] S Gervais A W Lynch and D K Musto ldquoFund families asdelegated monitors of money managersrdquo Review of FinancialStudies vol 18 no 4 pp 1139ndash1169 2005
[5] V Guerrieri and P Kondor ldquoFund managers career con-cerns and asset price volatilityrdquo 7e American EconomicReview vol 102 no 5 pp 1986ndash2017 2012
[6] S Ross ldquoe economic theory of agency the principalrsquosproblemrdquo 7e American Economic Review vol 63 pp 134ndash139 1973
[7] J A Mirrlees ldquoe optimal structure of incentives and au-thority within an organizationrdquo7eBell Journal of Economicsvol 7 no 1 pp 105ndash131 1976
[8] B Holmstrom ldquoMoral hazard and observabilityrdquo 7e BellJournal of Economics vol 10 no 1 pp 74ndash91 1979
[9] P Bolton and M Dewatripont Contract 7eory MIT PressCambridge UK 2005
[10] B Holmstrom and P Milgrom ldquoAggregation and linearity inthe provision of intertemporal incentivesrdquo Econometricavol 55 no 2 pp 303ndash328 1987
[11] H Schattler and J Sung ldquoe first-order approach to thecontinuous-time principal-agent problem with exponentialutilityrdquo Journal of Economic7eory vol 61 no 2 pp 331ndash3711993
[12] H Schattler and J Sung ldquoOn optimal sharing rules in dis-crete-and continuous-time principal-agent problems withexponential utilityrdquo Journal of Economic Dynamics andControl vol 21 no 2-3 pp 551ndash574 1997
[13] H M Muller ldquoe first-best sharing rule in the continuous-time principal-agent problem with exponential utilityrdquoJournal of Economic 7eory vol 79 no 2 pp 276ndash280 1998
[14] H M Muller ldquoAsymptotic efficiency in dynamic principal-agent problemsrdquo Journal of Economic 7eory vol 91 no 2pp 292ndash301 2000
[15] J Cvitanic X Wan and J Zhang ldquoOptimal compensationwith hidden action and lump-sum payment in a continuous-time modelrdquo Applied Mathematics and Optimization vol 59pp 99ndash146 2009
[16] J Cvitanic and J Zhang Contract 7eory in Continuous TimeModels Springer-Verlag Berlin Germany 2013
[17] Y Sannikov ldquoA continuous-time version of the principal-agent problemrdquo7eReview of Economic Studies vol 75 no 3pp 957ndash984 2008
[18] Z He ldquoA Model of dynamic compensation and capitalstructurerdquo Journal of Financial Economics vol 100 no 2pp 351ndash366 2011
[19] J Cvitanic D Possamai and N Touzi ldquoDynamic pro-gramming approach to principal-agent problemsrdquo Financeand Stochastics vol 22 pp 1ndash37 2018
[20] Z He and W Xiong ldquoDelegated asset management invest-ment mandates and capital immobilityrdquo Journal of FinancialEconomics vol 107 no 2 pp 239ndash258 2013
[21] H Pham Continuous-time Stochastic Control and Optimi-zation with Financial Applications Springer-Verlag NewYork NY USA 2009
10 Mathematical Problems in Engineering
We can also obtain zT XlowastZΓT Define
V(t z y) inf(ZΓ)isinV(t)
E ecf zTminus lnYZΓ
Tcm( )( )|zt z1113876 1113877
inf(ZΓ)isinV(t)
E ecf X lowastZΓ
Tminus lnYZΓ
Tcm( )( )|X
lowastZΓt
z
Dt
1113890 1113891
v tz
Dt
y1113888 1113889
(40)
Obviously solving v(t x y) is equivalent to solvingV(t z y) Using a similar method as the one in eorem 3we can get that
minus Vt inf(ZΓ)isinV(t)
minusμ + n
lowastZΓt 21113872 11138731113872 1113873 μ + n
lowastZΓt1113872 1113873
σ2Dt
Z
ΓVz
⎧⎨
⎩
minuscmθ n
lowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2σ2yDt
Z
ΓVy
+μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2D
2t
Z2
Γ2Vzz
+nlowastZΓt1113872 1113873
2μ + n
lowastZΓt 21113872 11138731113872 1113873
2
2σ2cmθyDt( 1113857
2Z2
Γ2Vyy
+nlowastZΓt μ + n
lowastZΓt 21113872 11138731113872 1113873
2
σ2cmθyD
2t
Z2
Γ2Vzy
⎫⎪⎬
⎪⎭
(41)
V(T z y) ecfz
yminus cfcm( 1113857
(42)
e first step in solving (41) is to find its minimum pointDefine MZΓ (ZΓ) it is shown in Section 3 that (Z Γ) and(MZΓ nlowastZΓ) are one-to-one en (41) is transformed into
minus Vt inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMVz1113896
+(μ +(n2))
2
2σ2D
2t M
2Vzz minus
cmθn2(μ +(n2))
2σ2yDtMVy
+n2(μ +(n2))
2
2σ2cmθyDt( 1113857
2M
2Vyy
+n(μ +(n2))
2
σ2cmθyD
2t M
2Vzy1113897
(43)
Now the problem of finding the minimum point in (41) ischanged into a problem of finding theminimumpoint in (43)
According to (38) we suppose thatV(t z y) E(t)ecfzyminus (cfcm) By some simple calculationswe can get that
Vz(t z y) cfV(t z y)
Vzz(t z y) c2fV(t z y)
yVy(t z y) minuscf
cm
V(t z y)
y2Vyy(t z y)
cf cf + cm1113872 1113873
c2m
V(t z y)
yVzy(t z y) minusc2f
cm
V(t z y)
(44)
Taking them into (43) we have
minus Eprime(t)V(t z y) inf(nM)isinR+timesRminus
minus(μ +(n2))(μ + n)
σ2DtMcf1113896
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
21113897E(t)V(t z y)
(45)
Since the right hand of (45) is continuous the minimumpoint can only be attained at the stable points or theboundary points which depends on the parameter valuesDenote the minimum point of (45) by (nlowastt Mlowastt ) and denotethe corresponding minimum point of (41) by (Zlowastt Γlowastt ) It isshown from the Appendix that nlowastt and DtM
lowastt are constants
concerning μ θ cf and cm Let nlowastt nlowast
Remark 4 On the one hand the exponential form of theobjective function implies that blowastt is independent of Xlowastt Onthe other hand the benefit and the cost brought by themanagerrsquos effort are only related to blowastt so nlowastt is independentof Xlowastt Furthermore in this paper we consider the dis-counted benefit and cost brought by the managerrsquos effort sonlowastt is independent of t
Remark 5 It is shown from figures in the Appendix that nlowast
decreases with an increase in μ(the drift coefficient of thefund wealth process) θ(the effort cost coefficient) and|cm|(the managerrsquos risk aversion level) It increases with anincrease in |cf|(the investorrsquos risk aversion level)
6 Mathematical Problems in Engineering
Remark 6 Define Ylowastt Vm(t x YZlowastΓlowastT ) considering (12)
and (13) we can get that (Zlowastt Ylowastt ) θcmDtnlowast and Dtb
lowastt
(minus (μ + (nlowast2))σ2)DtMlowastt are constants
Taking the minimum point into (45) and solving it wecan get
V(t z y) eB(Tminus t)
ecfz
yminus cfcm( 1113857
(46)
Here
B minusμ + n
lowast2( 1113857( 1113857 μ + nlowast
( 1113857
σ2DtMlowastt cf
+μ + n
lowast2( 1113857( 11138572
2σ2D
2t Mlowast 2t c
2f +
cfθnlowast2 μ + n
lowast2( 1113857( 1113857
2σ2DtMlowastt
+nlowast2 μ + n
lowast2( 1113857( 11138572
2σ2θ2D2
t Mlowast 2t cf cf + cm1113872 1113873
minusnlowast μ + n
lowast2( 1113857( 11138572
σ2c2fθD
2t Mlowast 2t
(47)
0 000
002
004
006
008
010
n
035 040 045030the drift coefficient of the fund
0ndash
000
002
004
006
008
010
n
20 25 3010 15The effort cost coefficient
0
000
002
004
006
008
010
n
020 025 030015The managerrsquos risk aversion level
0
011 012 013 014 015010The investorrsquos risk aversion level
000
002
004
006
008
010
n
Figure 1 e effects of parameters on the optimal effort level
Mathematical Problems in Engineering 7
is a constant As a consequence we can also get the followingresults
v(t x y) eB(Tminus t)
ecfDtxy
minus cfcm( 1113857
Vf(t x) v t x ecmR
1113872 1113873 eB(Tminus t)
ecf Dtxminus R( )
(48)
43 7e Investorrsquos Excitation Mechanism In this section letus analyze the investorrsquos excitation mechanism DenoteYlowastt YZlowastΓlowast
t From the above analysis we know that
dYlowastt
Dtcmθnlowast2
blowastt Ylowastt
2dt + b
lowastt Zlowastt σdWt
Ylowastt e
cmR
(49)
Using Itorsquos formula we have
d lnYlowastt
Dtcmθnlowast2
blowastt
2dt + b
lowastt
Zlowastt
Ylowastt
σdWt minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
dt
(50)
Furthermore we can get that the investment incomeunder nlowast and blowastt satisfies
dXlowastt rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt + blowastt σdWt (51)
which implies
d lnYlowastt
Dtcmθnlowast2
blowastt
2minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
1113888 1113889dt +Zlowastt
Ylowastt
dXlowastt minus rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt( 1113857
cm
Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 11138571113888 1113889dt
+ cmθnlowastDt dX
lowastt minus rX
lowastt dt( 1113857
(52)
Define constant
A Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 1113857gt 0
(53)
and then we can obtaind lnY
lowastt cmAdt + cmθn
lowastDt dX
lowastt minus rX
lowastt dt( 1113857 cm Adt + θn
lowastdDtXlowastt( 1113857
(54)
So
lnYlowastT minus cmR cm A(T minus t) + n
lowastθ XlowastT minus Dtx( 11138571113858 1113859 (55)
can be deduced immediately Since lnYT cmw(XT) wecan get the strategy
w XT( 1113857 A(T minus t) + nlowastθ XlowastT minus Dtx( 1113857 + R (56)
It is a linear function of XlowastT minus Dtx which is the dis-counted profit of the investment
Remark 7 It follows from the above results that the man-agerrsquos wages increase with the increase of the cost coefficientthe effort level and the discounted profit of the investmentFurthermore the longer the work the higher the salary It isconsistent with reality
We can also get the following corollary
Corollary 1
Ylowasts Vm s X
lowasts YlowastT( 1113857 e
cm R+A(Tminus t)+nlowastθ Xlowasts minus Dtx( )[ ] (57)
is implies that Vm(s Xlowasts YlowastT) is a decreasing convexfunction of Xlowasts us the assumption in Section 2 that YlowastT isan incentive strategy is proved
Appendix
Define
I(n M t) minus(μ +(n2))(μ + n)
σ2DtMcf
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
2
(A1)
We know that there are three kinds of points which maybe the minimum point of (45)
8 Mathematical Problems in Engineering
(i) e points which satisfy In(n M t) 0 IM
(n M t) 0(ii) e points which satisfy n 0 IM(0 M t) 0(iii) e points which satisfy M 0 In(n 0 t) 0
With parameters fixed we can easily decide which is theminimum point of (45) In the following we will investigatethe form of those points
e first kind of points (n1t M1t) is the solution of thefollowing equations
In(n M t) minusDtcf
σ232μ + n1113874 1113875M
+Dtcfθ
2σ232n2
+ 2μn1113874 1113875M +D
2t c
2f
2σ2μ +
n
21113874 1113875M
2
+θ2D2
t cf cf + cm1113872 1113873
2σ2n3
+ 3μn2
+ 2μ2n1113872 1113873M2
minusc2fθD
2t
σ23n
2
4+ 2μn + μ21113888 1113889M
2 0
(A2)
IM(n M t) minusDtcf
σ2(μ + n) μ +
n
21113874 1113875
+Dtcfθ
2σ2n2 μ +
n
21113874 1113875 +
D2t c
2f
σ2μ +
n
21113874 1113875
2M
+θ2D2
t cf cf + cm1113872 1113873
σ2n2 μ +
n
21113874 1113875
2M
minus2c
2fθD
2t
σ2n μ +
n
21113874 1113875
2M 0
(A3)
We can deduce from (A2) that
DtM1t n1t + μ minus n
21tθ21113872 1113873 +(μ2) minus θn
21t41113872 1113873 minus θμn1t
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf minus cf21113872 1113873 + cfθμ minus cfθn1t21113872 1113873 + θ2μ cf + cm1113872 1113873n1t1113960 1113961
(A4)
It also follows from (A3) that
DtM1t n1t + μ minus n1t( 1113857
2θ21113872 1113873
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t1113872 1113873
2θ2 cm + cf1113872 1113873 + cf1113876 1113877
(A5)
Combining the above two equations we can get that
n1t + μ minusn1t( 1113857
2θ2
1113888 1113889 minuscf
2+ cfθμ minus
cfθn1t
2+ θ2μ cf + cm1113872 1113873n1t1113890 1113891
+θn
21t
4+ θμn1t minus
μ2
1113888 1113889 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf1113960 1113961 0
(A6)
Clearly by solving (A5) and (A6) we can get that n1 andDtM1t are constants
Denote the second kind of point by (0 M2t) us M2t
satisfies (A5) with n replaced with 0 and we can get thatDtM2t is a constant
Denote the third kind of points by (n3t 0) ey satisfy(A4) By solving it we can get that n3t is a constant
Denote the minimum point of (45) by (nlowastt Mlowastt ) Itfollows from the above analysis that nlowastt and DtM
lowastt are all
constants For different μ θ cf and cm by calculating (A6)(A2) or (A3) we can get different nlowast
By using R we plot the following figures which indicatethe effect of μ θ cf and cm on nlowast (Figure 1)
Data Availability
No data were used to support this study
Conflicts of Interest
e authors declare that they have no conflicts of interest
Acknowledgments
is work was supported by the National Natural ScienceFoundation of China (11901404)
References
[1] A Almazan K C Brown M Carlson and D A ChapmanldquoWhy constrain your mutual fund managerrdquo Journal of Fi-nancial Economics vol 73 no 2 pp 289ndash321 2004
[2] M K Brunnermeier and L H Pedersen ldquoMarket liquidityand funding liquidityrdquo Review of Financial Studies vol 22no 6 pp 2201ndash2238 2009
[3] P H Dybvig H K Farnsworth and J N CarpenterldquoPortfolio performance and agencyrdquo Review of FinancialStudies vol 23 no 1 pp 1ndash23 2010
Mathematical Problems in Engineering 9
[4] S Gervais A W Lynch and D K Musto ldquoFund families asdelegated monitors of money managersrdquo Review of FinancialStudies vol 18 no 4 pp 1139ndash1169 2005
[5] V Guerrieri and P Kondor ldquoFund managers career con-cerns and asset price volatilityrdquo 7e American EconomicReview vol 102 no 5 pp 1986ndash2017 2012
[6] S Ross ldquoe economic theory of agency the principalrsquosproblemrdquo 7e American Economic Review vol 63 pp 134ndash139 1973
[7] J A Mirrlees ldquoe optimal structure of incentives and au-thority within an organizationrdquo7eBell Journal of Economicsvol 7 no 1 pp 105ndash131 1976
[8] B Holmstrom ldquoMoral hazard and observabilityrdquo 7e BellJournal of Economics vol 10 no 1 pp 74ndash91 1979
[9] P Bolton and M Dewatripont Contract 7eory MIT PressCambridge UK 2005
[10] B Holmstrom and P Milgrom ldquoAggregation and linearity inthe provision of intertemporal incentivesrdquo Econometricavol 55 no 2 pp 303ndash328 1987
[11] H Schattler and J Sung ldquoe first-order approach to thecontinuous-time principal-agent problem with exponentialutilityrdquo Journal of Economic7eory vol 61 no 2 pp 331ndash3711993
[12] H Schattler and J Sung ldquoOn optimal sharing rules in dis-crete-and continuous-time principal-agent problems withexponential utilityrdquo Journal of Economic Dynamics andControl vol 21 no 2-3 pp 551ndash574 1997
[13] H M Muller ldquoe first-best sharing rule in the continuous-time principal-agent problem with exponential utilityrdquoJournal of Economic 7eory vol 79 no 2 pp 276ndash280 1998
[14] H M Muller ldquoAsymptotic efficiency in dynamic principal-agent problemsrdquo Journal of Economic 7eory vol 91 no 2pp 292ndash301 2000
[15] J Cvitanic X Wan and J Zhang ldquoOptimal compensationwith hidden action and lump-sum payment in a continuous-time modelrdquo Applied Mathematics and Optimization vol 59pp 99ndash146 2009
[16] J Cvitanic and J Zhang Contract 7eory in Continuous TimeModels Springer-Verlag Berlin Germany 2013
[17] Y Sannikov ldquoA continuous-time version of the principal-agent problemrdquo7eReview of Economic Studies vol 75 no 3pp 957ndash984 2008
[18] Z He ldquoA Model of dynamic compensation and capitalstructurerdquo Journal of Financial Economics vol 100 no 2pp 351ndash366 2011
[19] J Cvitanic D Possamai and N Touzi ldquoDynamic pro-gramming approach to principal-agent problemsrdquo Financeand Stochastics vol 22 pp 1ndash37 2018
[20] Z He and W Xiong ldquoDelegated asset management invest-ment mandates and capital immobilityrdquo Journal of FinancialEconomics vol 107 no 2 pp 239ndash258 2013
[21] H Pham Continuous-time Stochastic Control and Optimi-zation with Financial Applications Springer-Verlag NewYork NY USA 2009
10 Mathematical Problems in Engineering
Remark 6 Define Ylowastt Vm(t x YZlowastΓlowastT ) considering (12)
and (13) we can get that (Zlowastt Ylowastt ) θcmDtnlowast and Dtb
lowastt
(minus (μ + (nlowast2))σ2)DtMlowastt are constants
Taking the minimum point into (45) and solving it wecan get
V(t z y) eB(Tminus t)
ecfz
yminus cfcm( 1113857
(46)
Here
B minusμ + n
lowast2( 1113857( 1113857 μ + nlowast
( 1113857
σ2DtMlowastt cf
+μ + n
lowast2( 1113857( 11138572
2σ2D
2t Mlowast 2t c
2f +
cfθnlowast2 μ + n
lowast2( 1113857( 1113857
2σ2DtMlowastt
+nlowast2 μ + n
lowast2( 1113857( 11138572
2σ2θ2D2
t Mlowast 2t cf cf + cm1113872 1113873
minusnlowast μ + n
lowast2( 1113857( 11138572
σ2c2fθD
2t Mlowast 2t
(47)
0 000
002
004
006
008
010
n
035 040 045030the drift coefficient of the fund
0ndash
000
002
004
006
008
010
n
20 25 3010 15The effort cost coefficient
0
000
002
004
006
008
010
n
020 025 030015The managerrsquos risk aversion level
0
011 012 013 014 015010The investorrsquos risk aversion level
000
002
004
006
008
010
n
Figure 1 e effects of parameters on the optimal effort level
Mathematical Problems in Engineering 7
is a constant As a consequence we can also get the followingresults
v(t x y) eB(Tminus t)
ecfDtxy
minus cfcm( 1113857
Vf(t x) v t x ecmR
1113872 1113873 eB(Tminus t)
ecf Dtxminus R( )
(48)
43 7e Investorrsquos Excitation Mechanism In this section letus analyze the investorrsquos excitation mechanism DenoteYlowastt YZlowastΓlowast
t From the above analysis we know that
dYlowastt
Dtcmθnlowast2
blowastt Ylowastt
2dt + b
lowastt Zlowastt σdWt
Ylowastt e
cmR
(49)
Using Itorsquos formula we have
d lnYlowastt
Dtcmθnlowast2
blowastt
2dt + b
lowastt
Zlowastt
Ylowastt
σdWt minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
dt
(50)
Furthermore we can get that the investment incomeunder nlowast and blowastt satisfies
dXlowastt rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt + blowastt σdWt (51)
which implies
d lnYlowastt
Dtcmθnlowast2
blowastt
2minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
1113888 1113889dt +Zlowastt
Ylowastt
dXlowastt minus rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt( 1113857
cm
Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 11138571113888 1113889dt
+ cmθnlowastDt dX
lowastt minus rX
lowastt dt( 1113857
(52)
Define constant
A Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 1113857gt 0
(53)
and then we can obtaind lnY
lowastt cmAdt + cmθn
lowastDt dX
lowastt minus rX
lowastt dt( 1113857 cm Adt + θn
lowastdDtXlowastt( 1113857
(54)
So
lnYlowastT minus cmR cm A(T minus t) + n
lowastθ XlowastT minus Dtx( 11138571113858 1113859 (55)
can be deduced immediately Since lnYT cmw(XT) wecan get the strategy
w XT( 1113857 A(T minus t) + nlowastθ XlowastT minus Dtx( 1113857 + R (56)
It is a linear function of XlowastT minus Dtx which is the dis-counted profit of the investment
Remark 7 It follows from the above results that the man-agerrsquos wages increase with the increase of the cost coefficientthe effort level and the discounted profit of the investmentFurthermore the longer the work the higher the salary It isconsistent with reality
We can also get the following corollary
Corollary 1
Ylowasts Vm s X
lowasts YlowastT( 1113857 e
cm R+A(Tminus t)+nlowastθ Xlowasts minus Dtx( )[ ] (57)
is implies that Vm(s Xlowasts YlowastT) is a decreasing convexfunction of Xlowasts us the assumption in Section 2 that YlowastT isan incentive strategy is proved
Appendix
Define
I(n M t) minus(μ +(n2))(μ + n)
σ2DtMcf
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
2
(A1)
We know that there are three kinds of points which maybe the minimum point of (45)
8 Mathematical Problems in Engineering
(i) e points which satisfy In(n M t) 0 IM
(n M t) 0(ii) e points which satisfy n 0 IM(0 M t) 0(iii) e points which satisfy M 0 In(n 0 t) 0
With parameters fixed we can easily decide which is theminimum point of (45) In the following we will investigatethe form of those points
e first kind of points (n1t M1t) is the solution of thefollowing equations
In(n M t) minusDtcf
σ232μ + n1113874 1113875M
+Dtcfθ
2σ232n2
+ 2μn1113874 1113875M +D
2t c
2f
2σ2μ +
n
21113874 1113875M
2
+θ2D2
t cf cf + cm1113872 1113873
2σ2n3
+ 3μn2
+ 2μ2n1113872 1113873M2
minusc2fθD
2t
σ23n
2
4+ 2μn + μ21113888 1113889M
2 0
(A2)
IM(n M t) minusDtcf
σ2(μ + n) μ +
n
21113874 1113875
+Dtcfθ
2σ2n2 μ +
n
21113874 1113875 +
D2t c
2f
σ2μ +
n
21113874 1113875
2M
+θ2D2
t cf cf + cm1113872 1113873
σ2n2 μ +
n
21113874 1113875
2M
minus2c
2fθD
2t
σ2n μ +
n
21113874 1113875
2M 0
(A3)
We can deduce from (A2) that
DtM1t n1t + μ minus n
21tθ21113872 1113873 +(μ2) minus θn
21t41113872 1113873 minus θμn1t
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf minus cf21113872 1113873 + cfθμ minus cfθn1t21113872 1113873 + θ2μ cf + cm1113872 1113873n1t1113960 1113961
(A4)
It also follows from (A3) that
DtM1t n1t + μ minus n1t( 1113857
2θ21113872 1113873
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t1113872 1113873
2θ2 cm + cf1113872 1113873 + cf1113876 1113877
(A5)
Combining the above two equations we can get that
n1t + μ minusn1t( 1113857
2θ2
1113888 1113889 minuscf
2+ cfθμ minus
cfθn1t
2+ θ2μ cf + cm1113872 1113873n1t1113890 1113891
+θn
21t
4+ θμn1t minus
μ2
1113888 1113889 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf1113960 1113961 0
(A6)
Clearly by solving (A5) and (A6) we can get that n1 andDtM1t are constants
Denote the second kind of point by (0 M2t) us M2t
satisfies (A5) with n replaced with 0 and we can get thatDtM2t is a constant
Denote the third kind of points by (n3t 0) ey satisfy(A4) By solving it we can get that n3t is a constant
Denote the minimum point of (45) by (nlowastt Mlowastt ) Itfollows from the above analysis that nlowastt and DtM
lowastt are all
constants For different μ θ cf and cm by calculating (A6)(A2) or (A3) we can get different nlowast
By using R we plot the following figures which indicatethe effect of μ θ cf and cm on nlowast (Figure 1)
Data Availability
No data were used to support this study
Conflicts of Interest
e authors declare that they have no conflicts of interest
Acknowledgments
is work was supported by the National Natural ScienceFoundation of China (11901404)
References
[1] A Almazan K C Brown M Carlson and D A ChapmanldquoWhy constrain your mutual fund managerrdquo Journal of Fi-nancial Economics vol 73 no 2 pp 289ndash321 2004
[2] M K Brunnermeier and L H Pedersen ldquoMarket liquidityand funding liquidityrdquo Review of Financial Studies vol 22no 6 pp 2201ndash2238 2009
[3] P H Dybvig H K Farnsworth and J N CarpenterldquoPortfolio performance and agencyrdquo Review of FinancialStudies vol 23 no 1 pp 1ndash23 2010
Mathematical Problems in Engineering 9
[4] S Gervais A W Lynch and D K Musto ldquoFund families asdelegated monitors of money managersrdquo Review of FinancialStudies vol 18 no 4 pp 1139ndash1169 2005
[5] V Guerrieri and P Kondor ldquoFund managers career con-cerns and asset price volatilityrdquo 7e American EconomicReview vol 102 no 5 pp 1986ndash2017 2012
[6] S Ross ldquoe economic theory of agency the principalrsquosproblemrdquo 7e American Economic Review vol 63 pp 134ndash139 1973
[7] J A Mirrlees ldquoe optimal structure of incentives and au-thority within an organizationrdquo7eBell Journal of Economicsvol 7 no 1 pp 105ndash131 1976
[8] B Holmstrom ldquoMoral hazard and observabilityrdquo 7e BellJournal of Economics vol 10 no 1 pp 74ndash91 1979
[9] P Bolton and M Dewatripont Contract 7eory MIT PressCambridge UK 2005
[10] B Holmstrom and P Milgrom ldquoAggregation and linearity inthe provision of intertemporal incentivesrdquo Econometricavol 55 no 2 pp 303ndash328 1987
[11] H Schattler and J Sung ldquoe first-order approach to thecontinuous-time principal-agent problem with exponentialutilityrdquo Journal of Economic7eory vol 61 no 2 pp 331ndash3711993
[12] H Schattler and J Sung ldquoOn optimal sharing rules in dis-crete-and continuous-time principal-agent problems withexponential utilityrdquo Journal of Economic Dynamics andControl vol 21 no 2-3 pp 551ndash574 1997
[13] H M Muller ldquoe first-best sharing rule in the continuous-time principal-agent problem with exponential utilityrdquoJournal of Economic 7eory vol 79 no 2 pp 276ndash280 1998
[14] H M Muller ldquoAsymptotic efficiency in dynamic principal-agent problemsrdquo Journal of Economic 7eory vol 91 no 2pp 292ndash301 2000
[15] J Cvitanic X Wan and J Zhang ldquoOptimal compensationwith hidden action and lump-sum payment in a continuous-time modelrdquo Applied Mathematics and Optimization vol 59pp 99ndash146 2009
[16] J Cvitanic and J Zhang Contract 7eory in Continuous TimeModels Springer-Verlag Berlin Germany 2013
[17] Y Sannikov ldquoA continuous-time version of the principal-agent problemrdquo7eReview of Economic Studies vol 75 no 3pp 957ndash984 2008
[18] Z He ldquoA Model of dynamic compensation and capitalstructurerdquo Journal of Financial Economics vol 100 no 2pp 351ndash366 2011
[19] J Cvitanic D Possamai and N Touzi ldquoDynamic pro-gramming approach to principal-agent problemsrdquo Financeand Stochastics vol 22 pp 1ndash37 2018
[20] Z He and W Xiong ldquoDelegated asset management invest-ment mandates and capital immobilityrdquo Journal of FinancialEconomics vol 107 no 2 pp 239ndash258 2013
[21] H Pham Continuous-time Stochastic Control and Optimi-zation with Financial Applications Springer-Verlag NewYork NY USA 2009
10 Mathematical Problems in Engineering
is a constant As a consequence we can also get the followingresults
v(t x y) eB(Tminus t)
ecfDtxy
minus cfcm( 1113857
Vf(t x) v t x ecmR
1113872 1113873 eB(Tminus t)
ecf Dtxminus R( )
(48)
43 7e Investorrsquos Excitation Mechanism In this section letus analyze the investorrsquos excitation mechanism DenoteYlowastt YZlowastΓlowast
t From the above analysis we know that
dYlowastt
Dtcmθnlowast2
blowastt Ylowastt
2dt + b
lowastt Zlowastt σdWt
Ylowastt e
cmR
(49)
Using Itorsquos formula we have
d lnYlowastt
Dtcmθnlowast2
blowastt
2dt + b
lowastt
Zlowastt
Ylowastt
σdWt minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
dt
(50)
Furthermore we can get that the investment incomeunder nlowast and blowastt satisfies
dXlowastt rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt + blowastt σdWt (51)
which implies
d lnYlowastt
Dtcmθnlowast2
blowastt
2minus blowast 2t σ2
Zlowast 2t
2Ylowast 2t
1113888 1113889dt +Zlowastt
Ylowastt
dXlowastt minus rX
lowastt + blowastt nlowast
+ μ( 1113857( 1113857dt( 1113857
cm
Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 11138571113888 1113889dt
+ cmθnlowastDt dX
lowastt minus rX
lowastt dt( 1113857
(52)
Define constant
A Dtblowastt θnlowast2
2minus12D
2t blowast 2t θ2cmn
lowast2σ2 + Dtblowastt θnlowast
nlowast
+ μ( 1113857gt 0
(53)
and then we can obtaind lnY
lowastt cmAdt + cmθn
lowastDt dX
lowastt minus rX
lowastt dt( 1113857 cm Adt + θn
lowastdDtXlowastt( 1113857
(54)
So
lnYlowastT minus cmR cm A(T minus t) + n
lowastθ XlowastT minus Dtx( 11138571113858 1113859 (55)
can be deduced immediately Since lnYT cmw(XT) wecan get the strategy
w XT( 1113857 A(T minus t) + nlowastθ XlowastT minus Dtx( 1113857 + R (56)
It is a linear function of XlowastT minus Dtx which is the dis-counted profit of the investment
Remark 7 It follows from the above results that the man-agerrsquos wages increase with the increase of the cost coefficientthe effort level and the discounted profit of the investmentFurthermore the longer the work the higher the salary It isconsistent with reality
We can also get the following corollary
Corollary 1
Ylowasts Vm s X
lowasts YlowastT( 1113857 e
cm R+A(Tminus t)+nlowastθ Xlowasts minus Dtx( )[ ] (57)
is implies that Vm(s Xlowasts YlowastT) is a decreasing convexfunction of Xlowasts us the assumption in Section 2 that YlowastT isan incentive strategy is proved
Appendix
Define
I(n M t) minus(μ +(n2))(μ + n)
σ2DtMcf
+(μ +(n2))
2
2σ2D
2t M
2c2f +
cfθn2(μ +(n2))
2σ2DtM
+n2(μ +(n2))
2
2σ2θ2D2
t M2cf cf + cm1113872 1113873
minusn(μ +(n2))
2
σ2c2fθD
2t M
2
(A1)
We know that there are three kinds of points which maybe the minimum point of (45)
8 Mathematical Problems in Engineering
(i) e points which satisfy In(n M t) 0 IM
(n M t) 0(ii) e points which satisfy n 0 IM(0 M t) 0(iii) e points which satisfy M 0 In(n 0 t) 0
With parameters fixed we can easily decide which is theminimum point of (45) In the following we will investigatethe form of those points
e first kind of points (n1t M1t) is the solution of thefollowing equations
In(n M t) minusDtcf
σ232μ + n1113874 1113875M
+Dtcfθ
2σ232n2
+ 2μn1113874 1113875M +D
2t c
2f
2σ2μ +
n
21113874 1113875M
2
+θ2D2
t cf cf + cm1113872 1113873
2σ2n3
+ 3μn2
+ 2μ2n1113872 1113873M2
minusc2fθD
2t
σ23n
2
4+ 2μn + μ21113888 1113889M
2 0
(A2)
IM(n M t) minusDtcf
σ2(μ + n) μ +
n
21113874 1113875
+Dtcfθ
2σ2n2 μ +
n
21113874 1113875 +
D2t c
2f
σ2μ +
n
21113874 1113875
2M
+θ2D2
t cf cf + cm1113872 1113873
σ2n2 μ +
n
21113874 1113875
2M
minus2c
2fθD
2t
σ2n μ +
n
21113874 1113875
2M 0
(A3)
We can deduce from (A2) that
DtM1t n1t + μ minus n
21tθ21113872 1113873 +(μ2) minus θn
21t41113872 1113873 minus θμn1t
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf minus cf21113872 1113873 + cfθμ minus cfθn1t21113872 1113873 + θ2μ cf + cm1113872 1113873n1t1113960 1113961
(A4)
It also follows from (A3) that
DtM1t n1t + μ minus n1t( 1113857
2θ21113872 1113873
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t1113872 1113873
2θ2 cm + cf1113872 1113873 + cf1113876 1113877
(A5)
Combining the above two equations we can get that
n1t + μ minusn1t( 1113857
2θ2
1113888 1113889 minuscf
2+ cfθμ minus
cfθn1t
2+ θ2μ cf + cm1113872 1113873n1t1113890 1113891
+θn
21t
4+ θμn1t minus
μ2
1113888 1113889 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf1113960 1113961 0
(A6)
Clearly by solving (A5) and (A6) we can get that n1 andDtM1t are constants
Denote the second kind of point by (0 M2t) us M2t
satisfies (A5) with n replaced with 0 and we can get thatDtM2t is a constant
Denote the third kind of points by (n3t 0) ey satisfy(A4) By solving it we can get that n3t is a constant
Denote the minimum point of (45) by (nlowastt Mlowastt ) Itfollows from the above analysis that nlowastt and DtM
lowastt are all
constants For different μ θ cf and cm by calculating (A6)(A2) or (A3) we can get different nlowast
By using R we plot the following figures which indicatethe effect of μ θ cf and cm on nlowast (Figure 1)
Data Availability
No data were used to support this study
Conflicts of Interest
e authors declare that they have no conflicts of interest
Acknowledgments
is work was supported by the National Natural ScienceFoundation of China (11901404)
References
[1] A Almazan K C Brown M Carlson and D A ChapmanldquoWhy constrain your mutual fund managerrdquo Journal of Fi-nancial Economics vol 73 no 2 pp 289ndash321 2004
[2] M K Brunnermeier and L H Pedersen ldquoMarket liquidityand funding liquidityrdquo Review of Financial Studies vol 22no 6 pp 2201ndash2238 2009
[3] P H Dybvig H K Farnsworth and J N CarpenterldquoPortfolio performance and agencyrdquo Review of FinancialStudies vol 23 no 1 pp 1ndash23 2010
Mathematical Problems in Engineering 9
[4] S Gervais A W Lynch and D K Musto ldquoFund families asdelegated monitors of money managersrdquo Review of FinancialStudies vol 18 no 4 pp 1139ndash1169 2005
[5] V Guerrieri and P Kondor ldquoFund managers career con-cerns and asset price volatilityrdquo 7e American EconomicReview vol 102 no 5 pp 1986ndash2017 2012
[6] S Ross ldquoe economic theory of agency the principalrsquosproblemrdquo 7e American Economic Review vol 63 pp 134ndash139 1973
[7] J A Mirrlees ldquoe optimal structure of incentives and au-thority within an organizationrdquo7eBell Journal of Economicsvol 7 no 1 pp 105ndash131 1976
[8] B Holmstrom ldquoMoral hazard and observabilityrdquo 7e BellJournal of Economics vol 10 no 1 pp 74ndash91 1979
[9] P Bolton and M Dewatripont Contract 7eory MIT PressCambridge UK 2005
[10] B Holmstrom and P Milgrom ldquoAggregation and linearity inthe provision of intertemporal incentivesrdquo Econometricavol 55 no 2 pp 303ndash328 1987
[11] H Schattler and J Sung ldquoe first-order approach to thecontinuous-time principal-agent problem with exponentialutilityrdquo Journal of Economic7eory vol 61 no 2 pp 331ndash3711993
[12] H Schattler and J Sung ldquoOn optimal sharing rules in dis-crete-and continuous-time principal-agent problems withexponential utilityrdquo Journal of Economic Dynamics andControl vol 21 no 2-3 pp 551ndash574 1997
[13] H M Muller ldquoe first-best sharing rule in the continuous-time principal-agent problem with exponential utilityrdquoJournal of Economic 7eory vol 79 no 2 pp 276ndash280 1998
[14] H M Muller ldquoAsymptotic efficiency in dynamic principal-agent problemsrdquo Journal of Economic 7eory vol 91 no 2pp 292ndash301 2000
[15] J Cvitanic X Wan and J Zhang ldquoOptimal compensationwith hidden action and lump-sum payment in a continuous-time modelrdquo Applied Mathematics and Optimization vol 59pp 99ndash146 2009
[16] J Cvitanic and J Zhang Contract 7eory in Continuous TimeModels Springer-Verlag Berlin Germany 2013
[17] Y Sannikov ldquoA continuous-time version of the principal-agent problemrdquo7eReview of Economic Studies vol 75 no 3pp 957ndash984 2008
[18] Z He ldquoA Model of dynamic compensation and capitalstructurerdquo Journal of Financial Economics vol 100 no 2pp 351ndash366 2011
[19] J Cvitanic D Possamai and N Touzi ldquoDynamic pro-gramming approach to principal-agent problemsrdquo Financeand Stochastics vol 22 pp 1ndash37 2018
[20] Z He and W Xiong ldquoDelegated asset management invest-ment mandates and capital immobilityrdquo Journal of FinancialEconomics vol 107 no 2 pp 239ndash258 2013
[21] H Pham Continuous-time Stochastic Control and Optimi-zation with Financial Applications Springer-Verlag NewYork NY USA 2009
10 Mathematical Problems in Engineering
(i) e points which satisfy In(n M t) 0 IM
(n M t) 0(ii) e points which satisfy n 0 IM(0 M t) 0(iii) e points which satisfy M 0 In(n 0 t) 0
With parameters fixed we can easily decide which is theminimum point of (45) In the following we will investigatethe form of those points
e first kind of points (n1t M1t) is the solution of thefollowing equations
In(n M t) minusDtcf
σ232μ + n1113874 1113875M
+Dtcfθ
2σ232n2
+ 2μn1113874 1113875M +D
2t c
2f
2σ2μ +
n
21113874 1113875M
2
+θ2D2
t cf cf + cm1113872 1113873
2σ2n3
+ 3μn2
+ 2μ2n1113872 1113873M2
minusc2fθD
2t
σ23n
2
4+ 2μn + μ21113888 1113889M
2 0
(A2)
IM(n M t) minusDtcf
σ2(μ + n) μ +
n
21113874 1113875
+Dtcfθ
2σ2n2 μ +
n
21113874 1113875 +
D2t c
2f
σ2μ +
n
21113874 1113875
2M
+θ2D2
t cf cf + cm1113872 1113873
σ2n2 μ +
n
21113874 1113875
2M
minus2c
2fθD
2t
σ2n μ +
n
21113874 1113875
2M 0
(A3)
We can deduce from (A2) that
DtM1t n1t + μ minus n
21tθ21113872 1113873 +(μ2) minus θn
21t41113872 1113873 minus θμn1t
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf minus cf21113872 1113873 + cfθμ minus cfθn1t21113872 1113873 + θ2μ cf + cm1113872 1113873n1t1113960 1113961
(A4)
It also follows from (A3) that
DtM1t n1t + μ minus n1t( 1113857
2θ21113872 1113873
n1t2( 1113857 + μ( 1113857 2n1tθcf + n1t1113872 1113873
2θ2 cm + cf1113872 1113873 + cf1113876 1113877
(A5)
Combining the above two equations we can get that
n1t + μ minusn1t( 1113857
2θ2
1113888 1113889 minuscf
2+ cfθμ minus
cfθn1t
2+ θ2μ cf + cm1113872 1113873n1t1113890 1113891
+θn
21t
4+ θμn1t minus
μ2
1113888 1113889 2n1tθcf + n1t( 11138572θ2 cm + cf1113872 1113873 + cf1113960 1113961 0
(A6)
Clearly by solving (A5) and (A6) we can get that n1 andDtM1t are constants
Denote the second kind of point by (0 M2t) us M2t
satisfies (A5) with n replaced with 0 and we can get thatDtM2t is a constant
Denote the third kind of points by (n3t 0) ey satisfy(A4) By solving it we can get that n3t is a constant
Denote the minimum point of (45) by (nlowastt Mlowastt ) Itfollows from the above analysis that nlowastt and DtM
lowastt are all
constants For different μ θ cf and cm by calculating (A6)(A2) or (A3) we can get different nlowast
By using R we plot the following figures which indicatethe effect of μ θ cf and cm on nlowast (Figure 1)
Data Availability
No data were used to support this study
Conflicts of Interest
e authors declare that they have no conflicts of interest
Acknowledgments
is work was supported by the National Natural ScienceFoundation of China (11901404)
References
[1] A Almazan K C Brown M Carlson and D A ChapmanldquoWhy constrain your mutual fund managerrdquo Journal of Fi-nancial Economics vol 73 no 2 pp 289ndash321 2004
[2] M K Brunnermeier and L H Pedersen ldquoMarket liquidityand funding liquidityrdquo Review of Financial Studies vol 22no 6 pp 2201ndash2238 2009
[3] P H Dybvig H K Farnsworth and J N CarpenterldquoPortfolio performance and agencyrdquo Review of FinancialStudies vol 23 no 1 pp 1ndash23 2010
Mathematical Problems in Engineering 9
[4] S Gervais A W Lynch and D K Musto ldquoFund families asdelegated monitors of money managersrdquo Review of FinancialStudies vol 18 no 4 pp 1139ndash1169 2005
[5] V Guerrieri and P Kondor ldquoFund managers career con-cerns and asset price volatilityrdquo 7e American EconomicReview vol 102 no 5 pp 1986ndash2017 2012
[6] S Ross ldquoe economic theory of agency the principalrsquosproblemrdquo 7e American Economic Review vol 63 pp 134ndash139 1973
[7] J A Mirrlees ldquoe optimal structure of incentives and au-thority within an organizationrdquo7eBell Journal of Economicsvol 7 no 1 pp 105ndash131 1976
[8] B Holmstrom ldquoMoral hazard and observabilityrdquo 7e BellJournal of Economics vol 10 no 1 pp 74ndash91 1979
[9] P Bolton and M Dewatripont Contract 7eory MIT PressCambridge UK 2005
[10] B Holmstrom and P Milgrom ldquoAggregation and linearity inthe provision of intertemporal incentivesrdquo Econometricavol 55 no 2 pp 303ndash328 1987
[11] H Schattler and J Sung ldquoe first-order approach to thecontinuous-time principal-agent problem with exponentialutilityrdquo Journal of Economic7eory vol 61 no 2 pp 331ndash3711993
[12] H Schattler and J Sung ldquoOn optimal sharing rules in dis-crete-and continuous-time principal-agent problems withexponential utilityrdquo Journal of Economic Dynamics andControl vol 21 no 2-3 pp 551ndash574 1997
[13] H M Muller ldquoe first-best sharing rule in the continuous-time principal-agent problem with exponential utilityrdquoJournal of Economic 7eory vol 79 no 2 pp 276ndash280 1998
[14] H M Muller ldquoAsymptotic efficiency in dynamic principal-agent problemsrdquo Journal of Economic 7eory vol 91 no 2pp 292ndash301 2000
[15] J Cvitanic X Wan and J Zhang ldquoOptimal compensationwith hidden action and lump-sum payment in a continuous-time modelrdquo Applied Mathematics and Optimization vol 59pp 99ndash146 2009
[16] J Cvitanic and J Zhang Contract 7eory in Continuous TimeModels Springer-Verlag Berlin Germany 2013
[17] Y Sannikov ldquoA continuous-time version of the principal-agent problemrdquo7eReview of Economic Studies vol 75 no 3pp 957ndash984 2008
[18] Z He ldquoA Model of dynamic compensation and capitalstructurerdquo Journal of Financial Economics vol 100 no 2pp 351ndash366 2011
[19] J Cvitanic D Possamai and N Touzi ldquoDynamic pro-gramming approach to principal-agent problemsrdquo Financeand Stochastics vol 22 pp 1ndash37 2018
[20] Z He and W Xiong ldquoDelegated asset management invest-ment mandates and capital immobilityrdquo Journal of FinancialEconomics vol 107 no 2 pp 239ndash258 2013
[21] H Pham Continuous-time Stochastic Control and Optimi-zation with Financial Applications Springer-Verlag NewYork NY USA 2009
10 Mathematical Problems in Engineering
[4] S Gervais A W Lynch and D K Musto ldquoFund families asdelegated monitors of money managersrdquo Review of FinancialStudies vol 18 no 4 pp 1139ndash1169 2005
[5] V Guerrieri and P Kondor ldquoFund managers career con-cerns and asset price volatilityrdquo 7e American EconomicReview vol 102 no 5 pp 1986ndash2017 2012
[6] S Ross ldquoe economic theory of agency the principalrsquosproblemrdquo 7e American Economic Review vol 63 pp 134ndash139 1973
[7] J A Mirrlees ldquoe optimal structure of incentives and au-thority within an organizationrdquo7eBell Journal of Economicsvol 7 no 1 pp 105ndash131 1976
[8] B Holmstrom ldquoMoral hazard and observabilityrdquo 7e BellJournal of Economics vol 10 no 1 pp 74ndash91 1979
[9] P Bolton and M Dewatripont Contract 7eory MIT PressCambridge UK 2005
[10] B Holmstrom and P Milgrom ldquoAggregation and linearity inthe provision of intertemporal incentivesrdquo Econometricavol 55 no 2 pp 303ndash328 1987
[11] H Schattler and J Sung ldquoe first-order approach to thecontinuous-time principal-agent problem with exponentialutilityrdquo Journal of Economic7eory vol 61 no 2 pp 331ndash3711993
[12] H Schattler and J Sung ldquoOn optimal sharing rules in dis-crete-and continuous-time principal-agent problems withexponential utilityrdquo Journal of Economic Dynamics andControl vol 21 no 2-3 pp 551ndash574 1997
[13] H M Muller ldquoe first-best sharing rule in the continuous-time principal-agent problem with exponential utilityrdquoJournal of Economic 7eory vol 79 no 2 pp 276ndash280 1998
[14] H M Muller ldquoAsymptotic efficiency in dynamic principal-agent problemsrdquo Journal of Economic 7eory vol 91 no 2pp 292ndash301 2000
[15] J Cvitanic X Wan and J Zhang ldquoOptimal compensationwith hidden action and lump-sum payment in a continuous-time modelrdquo Applied Mathematics and Optimization vol 59pp 99ndash146 2009
[16] J Cvitanic and J Zhang Contract 7eory in Continuous TimeModels Springer-Verlag Berlin Germany 2013
[17] Y Sannikov ldquoA continuous-time version of the principal-agent problemrdquo7eReview of Economic Studies vol 75 no 3pp 957ndash984 2008
[18] Z He ldquoA Model of dynamic compensation and capitalstructurerdquo Journal of Financial Economics vol 100 no 2pp 351ndash366 2011
[19] J Cvitanic D Possamai and N Touzi ldquoDynamic pro-gramming approach to principal-agent problemsrdquo Financeand Stochastics vol 22 pp 1ndash37 2018
[20] Z He and W Xiong ldquoDelegated asset management invest-ment mandates and capital immobilityrdquo Journal of FinancialEconomics vol 107 no 2 pp 239ndash258 2013
[21] H Pham Continuous-time Stochastic Control and Optimi-zation with Financial Applications Springer-Verlag NewYork NY USA 2009
10 Mathematical Problems in Engineering