Synchronized manufacturing refers to the entire production system working together in harmony to achieve the goals of the firm

Citation preview

Page 1: Theory of Constraints with respect o Synchronous Manufacturing

Theory of Constraints

Synchronous Manufacturing

Page 2: Theory of Constraints with respect o Synchronous Manufacturing

2

Introduction

• Synchronized manufacturing (SM) is any systematic way that attempts to move material quickly and smoothly through the various resources of the plant in concert with market demand

• Synchronized manufacturing refers to the entire production system working together in harmony to achieve the goals of the firm

Page 3: Theory of Constraints with respect o Synchronous Manufacturing

3

Hockey-Stick Phenomenon

• In most organizations there is a rush to meet quotas at the end of each month (or other time period)

• This rush results in the expediting of parts through the system

• Expediting of parts results in confusion, delays, extra setups, and usually overtime expenses

Page 4: Theory of Constraints with respect o Synchronous Manufacturing

4

Hockey-Stick Phenomenon

• The end-of-period rush!

Period1 2 3 4

Output($)

Page 5: Theory of Constraints with respect o Synchronous Manufacturing

5

Hockey-Stick Phenomenon • Problem arises because two sets of

measurements are being used– At beginning of month, cost accounting

efficiency measures are used• High efficiencies, minimal setups, etc.

– At the end of the month, financial performance measures are used

• Net profit, return on investment (ROI) and cash flow

• To achieve these two types of measurement, high levels of inventory are needed which augments the problem even further

Page 6: Theory of Constraints with respect o Synchronous Manufacturing

6

The Goal

• The goal of the firm is to make money both now and in the future– What about the following:

• Providing jobs

• Consuming raw materials

• Increasing sales

• Increasing market share

• Developing technology

• Producing high quality products

Page 7: Theory of Constraints with respect o Synchronous Manufacturing

7

Measuring the Goal

• Two sets of performance measures are used to determine how well the company is meeting its goal (making money):– Financial

• Higher level measures

– Operational• Shop floor measures

Page 8: Theory of Constraints with respect o Synchronous Manufacturing

8

Financial Measures

• 1. Net Profits– An absolute measurement of making money– Net profit has no meaning until we know how

much investment it took to generate it, thus, we need to index it as a return on investment

• 2. Return on Investment– A relative measurement

Page 9: Theory of Constraints with respect o Synchronous Manufacturing

9

Financial Measures

• 3. Cash Flow– A survival measurement– Cash flow is important since cash is necessary

to pay bills for day-to-day operations; without cash, the firm will go bankrupt even though it is very sound in normal accounting terms

• We need all three of these measurement used together

Page 10: Theory of Constraints with respect o Synchronous Manufacturing

10

Financial Measures

• The financial measurements are good for telling us when we are making money, but they are inadequate in judging the impact of specific actions on the goal

• Need to bridge the gap between specific operational decisions we must make and the bottom line measurements of the entire firm

Page 11: Theory of Constraints with respect o Synchronous Manufacturing

11

Operational Measures

• Throughput– The rate at which the system generates money

through sales

• Inventory– All the money the system invests in purchasing

things the system intends to sell

• Operating Expense– All the money the system spends in turning

inventory into throughput

Page 12: Theory of Constraints with respect o Synchronous Manufacturing

12

Operational Measures

NET PROFIT RETURN ON INVESTMENT

CASH FLOW

THROUGHPUT INVENTORY OPERATINGEXPENSE

Page 13: Theory of Constraints with respect o Synchronous Manufacturing

13

Operational Measures

NET PROFIT RETURN ON INVESTMENT

CASH FLOW

THROUGHPUT INVENTORY OPERATINGEXPENSE

The Indirect Impact of Inventory and Carrying Charges

CARRYINGCHARGES

Page 14: Theory of Constraints with respect o Synchronous Manufacturing

14

Operational Measures• The indirect impact of inventory on the three

bottom line measurements is typically estimated through the use of carrying charges

• Lowering inventory reduces a number of operating expenses, such as:– interest charges– storage space– scrap– obsolescence– material handling– rework

Page 15: Theory of Constraints with respect o Synchronous Manufacturing

15

The Goal Revisited

• If we examine the operational measures, we can restate the goal in their terms:

The Goal of a firm is to increase throughput while simultaneously reducing inventory and reducing operating expense

Page 16: Theory of Constraints with respect o Synchronous Manufacturing

16

Productivity

• Productivity– All the actions that bring a company closer to

its goals

• Does not guarantee profitability– Has throughput increased?– Has inventory decreased?– Have operational expenses decreased?

Page 17: Theory of Constraints with respect o Synchronous Manufacturing

17

Balanced vs. Unbalanced Capacity• Historically, manufacturers have tried to

balance the capacity of each resource across a sequence of processes in an attempt to match capacity with market demand– The goal was constant cycle time across all

stations

• However, synchronous manufacturing views constant workstation capacity as a bad decision– Why is this the case?

• Let’s consider the balanced capacity situation

Page 18: Theory of Constraints with respect o Synchronous Manufacturing

18

A C D25

B E F50 30 30 3015

• Consider a Balanced Capacity:– A simple process line with several stations

– The output rate for the line has been established• Production people try to make the capacities of all

stations the same by adjusting machines or equipment used, workloads, skills, and type of labor assigned, tools used, overtime, etc...

Balanced vs. Unbalanced Capacity

Page 19: Theory of Constraints with respect o Synchronous Manufacturing

19

• Balanced Capacity (continued)– This would be possible only if the output times

of all stations were constant or had a very narrow distribution

– A normal variation in output times causes downstream stations to have idle time when the upstream stations take longer to process materials than was originally planned

Balanced vs. Unbalanced Capacity

Page 20: Theory of Constraints with respect o Synchronous Manufacturing

20

F

A

A

A

B

B

B

B

B

B

C

C

C

C

C

C

D

D

D

D

D

D

D

D

D

D

E

E

E

E

E

F

F

F

F

• Balanced Capacity (continued)

Balanced vs. Unbalanced Capacity

Page 21: Theory of Constraints with respect o Synchronous Manufacturing

21

Balanced vs. Unbalanced Capacity

• Balanced Capacity (continued)– Conversely, when the upstream stations process

the materials in a shorter time, inventory builds up between stations

– This effect is called statistical variation, and it is cumulative

– The only way that this variation can be smoothed out is by increasing work in process to absorb the variation, or increase the capacities of each resource downstream

Page 22: Theory of Constraints with respect o Synchronous Manufacturing

22

Balanced vs. Unbalanced Capacity

• Unbalanced Capacity– Rather than balancing capacities, the flow of

product through the system should be balanced– The rule with capacities is that capacities within

the process sequence should not be balanced to the same level

– Rather, attempts should be made to balance the flow of product through the system

Page 23: Theory of Constraints with respect o Synchronous Manufacturing

23

Process Time (B)Process Time (A)

Dependent Events and Statistical Fluctuations

• Dependent Events– In a process sequence, the ability to do the next

process is dependent on the previous one

Page 24: Theory of Constraints with respect o Synchronous Manufacturing

24

Dependent Events and Statistical Fluctuations

• Statistical Fluctuations– Normal variation about a mean– When these occur in a dependent sequence

without any inventory between workstations, there is no opportunity to achieve the average output

• When one process takes longer than average, the next process cannot make up the time

Page 25: Theory of Constraints with respect o Synchronous Manufacturing

25

Capacity Related Terminology• Capacity

– Available time for production

• Bottleneck– Capacity is less than demand placed on resource

• A bottleneck limits the throughput.

• Non-bottleneck– Capacity is greater than demand placed on resource

• Avoid changing a non-bottleneck into a bottleneck

• Capacity-constrained resource (CCR)– Capacity is close to demand placed on resource

Page 26: Theory of Constraints with respect o Synchronous Manufacturing

26

X Y Market

Case A

X YBottleneck Nonbottleneck

Demand/month 200 units 200 unitsProcess time/unit 1 hour 45 minsAvail. time/month 200 hours 200 hours

What’s Going to Happen?

• Bottleneck feeding a non-bottleneck

Page 27: Theory of Constraints with respect o Synchronous Manufacturing

27

What’s Going to Happen?

Y X Market

Case B

X YBottleneck Nonbottleneck

Demand/month 200 units 200 unitsProcess time/unit 1 hour 45 minsAvail. time/month 200 hours 200 hours

• Non-bottleneck feeding a bottleneck

Page 28: Theory of Constraints with respect o Synchronous Manufacturing

28

X Y

Assembly

MarketCase C

X YBottleneck Nonbottleneck

Demand/month 200 units 200 unitsProcess time/unit 1 hour 45 minsAvail. time/month 200 hours 200 hours

What’s Going to Happen?• Output of bottleneck and non-bottleneck

assembled into a product

Page 29: Theory of Constraints with respect o Synchronous Manufacturing

29

X Y

Market Market

Case D

X YBottleneck Nonbottleneck

Demand/month 200 units 200 unitsProcess time/unit 1 hour 45 minsAvail. time/month 200 hours 200 hours

What’s Going to Happen?• Bottleneck and non-bottleneck have

independent markets for their output

Page 30: Theory of Constraints with respect o Synchronous Manufacturing

30

Basic Manufacturing Building Blocks

• The previous four cases can be thought of as the basic building blocks for manufacturing

• A production process can be simplified into one of these four building blocks to simplify analysis and control– Group all non-bottleneck resources together and

display them as a single non-bottleneck resource

Page 31: Theory of Constraints with respect o Synchronous Manufacturing

31

Components of Production Cycle Time

• Setup time– the time that a part spends waiting for a

resource to be set up to work on this same part

• Process time– the time that the part is being processed

• Queue time– the time that a part waits for a resource while

the resource is busy with something else

Page 32: Theory of Constraints with respect o Synchronous Manufacturing

32

Components of Production Cycle Time

• Wait time– the time that a part waits not for a resource but

for another part so that they can be assembled together

• Idle time– the unused time

• the cycle time less the sum of the setup time, processing time, queue time, and wait time

Page 33: Theory of Constraints with respect o Synchronous Manufacturing

33

Finding the Bottleneck

• Two ways to find a bottleneck– 1. Capacity resource profile

• As examined in the simulation

– 2. Use knowledge of plant, look at the system in operation, and talk to supervisors and employees

• As seen in THE GOAL

Page 34: Theory of Constraints with respect o Synchronous Manufacturing

34

Bottleneck Non-bottleneck

Saving Time

A MirageAn Hour Saved For Entire Plant

Page 35: Theory of Constraints with respect o Synchronous Manufacturing

35

Drum-Buffer-Rope

• Drum– Control point to control flow of product

through the system– Located at the bottleneck or the CCR

• Buffer– Inventory in front of a bottleneck (time buffer)

• Rope– Communication to entry point of material to be

processed

Page 36: Theory of Constraints with respect o Synchronous Manufacturing

36

Drum-Buffer-Rope

CBA50 30 25

Time Buffer

F30

E30

D15 Finished

Goods

Drum

Major Capacity Constraint

RawMaterials

A Rope tying the gating operation to the buffer

Market Demand

A Rope tying Market Demand to the CCR schedule

Page 37: Theory of Constraints with respect o Synchronous Manufacturing

37

Drum-Buffer-Rope

• Two major constraints on a firm– The market demand for its products– The capacity of the CCR

• Thus, we need to base the schedule on the CCR by taking into account only its limited capability and the market demands that it is trying to satisfy

Page 38: Theory of Constraints with respect o Synchronous Manufacturing

38

Drum-Buffer-Rope

• Once the CCR’s schedule is established,– we need to determine how to schedule all the

non-constraining resources– Schedule for succeeding operations can be

derived easily• After a part has been processed at the CCR it is

scheduled to start at the next operation

Page 39: Theory of Constraints with respect o Synchronous Manufacturing

39

Drum-Buffer-Rope• The challenge is to schedule the preceding

operations and to protect the CCR from disturbances that might occur at the preceding resources– If disturbances at preceding operations can be

overcome in two days, then set the time buffer at three days

– Schedule the operation immediately preceding the CCR to complete the needed parts three days before they are scheduled to run at the CCR

– Then back schedule the remaining operations

Page 40: Theory of Constraints with respect o Synchronous Manufacturing

40

Drum-Buffer-Rope

• The procedure laid down so far will protect the throughput of the plant

• BUT, meeting customer due dates is also important and needs to be protected– Need to create a buffer of parts at final

assembly for items that do not go through the CCR to protect against disturbances in procurement and manufacturing

Page 41: Theory of Constraints with respect o Synchronous Manufacturing

41

Drum-Buffer-Rope

Final Assembly

Subassembly

Subassembly

CCR

Page 42: Theory of Constraints with respect o Synchronous Manufacturing

42

How to Beat the Drum

• A CCR limits the throughput of the plant and controls due-date performance

• Must ensure that the CCR is not scheduled to produce more than its capacity and not to waste any of its capacity by allowing any slack in its schedule

Page 43: Theory of Constraints with respect o Synchronous Manufacturing

43

How to Beat the Drum

• First:– Schedule forward in time form the present

• Decide what product to schedule first, second, etc...

• When the available capacity of the CCR for the first day is used up, begin scheduling the second day, etc...

• The only remaining problem is how to choose the sequence in which the various products are to be done by the CCR

Page 44: Theory of Constraints with respect o Synchronous Manufacturing

44

How to Beat the Drum• Customers due dates for the various

products will provide the first cut schedule

• There are four case where we may need to modify the customer due-date schedule for sequencing products through the CCR– Completion times for the various products are

greatly different– One CCR feed another CCR– Setups on the CCR– A CCR produces more than one part for the

same product

Page 45: Theory of Constraints with respect o Synchronous Manufacturing

45

Locating the Time Buffers

• Concentrate protection not at the origin of disturbance, but before critical operations

• Inventory of the right parts in the right quantities at the right times in front of the right operations gives high protection

• Inventory anywhere else is destructive

Page 46: Theory of Constraints with respect o Synchronous Manufacturing

46

Ropes

• Release and process materials according to the schedule determined by the plants constraints

• Do not release materials in order to supply work to workers, or for any other reason

Page 47: Theory of Constraints with respect o Synchronous Manufacturing

47

Example• The following diagram contains the product structure, routing,

and processing time information for product A. The process flows from the bottom of the diagram upward. Assume one unit of items B, C, and D are needed to make each A. The manufacturing of each item requires three operations at machine centers 1, 2, and 3. Each machine center contains only one machine. a machine setup time of 60 minutes occurs when ever a machine is switched from one operation to another (within the same item or between items)

• Design a schedule of production for each machine center that will produce 100 A’s as quickly as possible

Page 48: Theory of Constraints with respect o Synchronous Manufacturing

48

Example

A

B C D1 1 1

1

2

31

1 2

2 3

3

B3

B2

B1

C3

C2

C1

D3

D2

D1

7

3

5

15

10

2

5

8

10

Page 49: Theory of Constraints with respect o Synchronous Manufacturing

49

Example• Solution:

– Identify the bottleneck machine– To keep the bottleneck busy, schedule the item

first whose lead time to the bottleneck is less than or equal to the bottleneck processing time

– Forward schedule the bottleneck– Backward schedule the other machines to

sustain the bottleneck schedule– Remember that the transfer batch size does not

have to match the process batch size

Page 50: Theory of Constraints with respect o Synchronous Manufacturing

50

Example• The bottleneck machine is calculated by

summing the processing times of all operations to be performed at a machine

Machine 1 Machine 2 Machine3B1 5 B2 3 C1 2B3 7 C3 15 D3 5C2 10 D2 8 D1 10

22 26* 17

Page 51: Theory of Constraints with respect o Synchronous Manufacturing

51

Example• Machine 2 is identified as the bottleneck, so we

schedule machine 2 first. From the product structure diagram, we see three operations that are performed at machine 2 - B2, C3, and D2. If we schedule item B first, a B will reach machine 2 every 5 minutes (since B has to be processed through machine 1 first), but B takes only 3 minutes to process at machine 2, so the bottleneck will be idle for 2 minutes of every 5 minutes. A similar result occurs if we schedule item D first on machine 2. The best alternative is to schedule item C first

Page 52: Theory of Constraints with respect o Synchronous Manufacturing

52

BottleneckSequence

Completion Timefor 100 A’s (mins)

Total IdleTime (min)

TotalProcessingTime (min)

C3, B2, D2 2,737 994 3,731

C3, D2, B2 3,135 1,447 4,582

Example• We will process the items in batches of 100

to match our demand requirements

– The bottleneck sequence is C3, B2, D2– Machine center 1 sequence is C2, B1, B3– Machine center 3 sequence is C1, D1, D3

Page 53: Theory of Constraints with respect o Synchronous Manufacturing

53

Quality Implications

• More tolerant than JIT systems– Excess capacity throughout system, except at

the bottleneck• Quality control needed before bottleneck

• Want quality assurance at each process downstream from the bottleneck to ensure passing product is not scrapped

Page 54: Theory of Constraints with respect o Synchronous Manufacturing

54

Batch Sizes

• What is the batch size?– One?

• Transfer batch

– Infinity?• Process batch

– Using transfer batches that are smaller than the process batch quantity causes shorter production times and less WIP inventory

Page 55: Theory of Constraints with respect o Synchronous Manufacturing

55

How to Treat Inventory

• The negative impact of inventory is not only in its additional carrying costs, but in– longer lead times– creating problems with engineering changes

• Dollar Days– A measurement of the value of inventory and the

time it stays within an area

(value of inventory)(number of days within a department)

Page 56: Theory of Constraints with respect o Synchronous Manufacturing

56

How to Treat Inventory

• Benefits from Dollar Day Measurement– Marketing

• discourages holding large amounts of finished goods inventory

– Purchasing• discourages placing large purchase orders that on

the surface appear to take advantage of quantity discounts

– Manufacturing• discourage large work in process and producing

earlier than needed

Page 57: Theory of Constraints with respect o Synchronous Manufacturing

57

Comparing SM to MRP

• MRP uses backward scheduling– Works backward in time from the desired

completion date (BOM explosion)

• Synchronous manufacturing uses forward scheduling– Focuses on the critical resources which are

scheduled forward in time, ensuring the loads placed on them are within capacity

– The non-bottleneck resources are then scheduled to support the resource

Page 58: Theory of Constraints with respect o Synchronous Manufacturing

58

Comparing SM to JIT

• JIT:– is limited to repetitive manufacturing– requires a stable production level– does not allow very much flexibility in the

products produced – still requires work in process when used with

kanban so that there is "something to pull"

• Vendors need to be located nearby because the system depends on smaller, more frequent deliveries

Page 59: Theory of Constraints with respect o Synchronous Manufacturing

59

Conclusion

• Five steps in the Theory of Constraints– 1. Identify the system constraints– 2. Exploit the system constraints– 3. Subordinate everything to that decision– 4. Elevate the system constraints– 5. If the constraints have been broken, go back

to step 1. Do not let INERTIA take over