82
The Zambian Case Study Progress and Status of Integrating Accountability and Evidence-based Policymaking Approaches in National Development Planning Processes Requesting Division: Capacity Development Division (CDD) Development Planning and Statistics Cluster, UNECA Submitted By: Dr. Stephen Gumboh, DA National Consultant- Planning ZAMBIA SEPTEMBER 2018

The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

The Zambian Case Study

Progress and Status of Integrating Accountability and

Evidence-based Policymaking Approaches in National

Development Planning Processes

Requesting Division: Capacity Development Division (CDD)

Development Planning and Statistics Cluster, UNECA

Submitted By:

Dr. Stephen Gumboh,

DA National Consultant- Planning

ZAMBIA

SEPTEMBER 2018

Page 2: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page ii

Acronyms ........................................................................................................................ iv

Geopolitical Map of Zambia ............................................................................................ vi

Executive Summary ........................................................................................................ vii

1.0 Introduction ........................................................................................................... 1

1.1 Background ................................................................................................................. 1

1.2 Rationale ..................................................................................................................... 2

1.3 Objective and Scope ..................................................................................................... 3

1.4 Methodology ................................................................................................................ 3

1.5 Organization ................................................................................................................ 5

2.0 Analysis of Models and Processes of National Development Plans .......................... 7

2.1 Participatory Development Approach .......................................................................... 7

2.2 Sectoral Development Planning Approach ................................................................... 7

2.3 Integrated Multi-sectoral Development Approach ....................................................... 8

2.4 Strategic Planning Model ............................................................................................. 9

2.5 Theory of Change Model ............................................................................................ 10

1.0 The National Development Planning in Zambia ................................................... 17

3.1 Zambia Social and Economic Context ........................................................................ 18

3.2 Pre-2005 Developing Planning in Zambia .................................................................. 19

3.3 Post – 2005 Development Planning Frameworks ........................................................ 23

4.0 Status and Progress in the National Development Planning Process in Zambia .... 25

4.1 Post - 2005 National Development Plan Frameworks ................................................. 26

4.1.1 Vision 2030 .................................................................................................................................... 26

4.1.2 Fifth National Development Plan ................................................................................................ 26

4.1.3 Sixth National Development Plan ................................................................................................ 27

4.1.4 Revised Sixth National Development Plan .................................................................................. 27

4.1.5 Public Investment Planning, Appraisal and Management Framework ................................... 28

4.1.6 National Planning and Budgeting Policy .................................................................................... 28

4.1.7 Monitoring and Evaluation Frameworks ................................................................................... 29

4.2 Implementation Challenges of the Previous NDPs...................................................... 29

4.4 Lessons Learnt from Implementing Prior NDPs ........................................................ 31

4.3 Assessment of the Status and Progress of NDP Process in Zambia ............................. 36

4.3.1 Assessment of Status on NPBP Objectives ................................................................................. 36

4.3.2 Assessment of Progress on NPBP Objectives ............................................................................. 37

Objective One: Integrate National Planning and Annual Budgeting Processes ................................... 37

Objective Two: Strengthen Synergies in the Various Planning Processes ............................................ 39

Page 3: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page iii

Objective Three: Facilitate Participatory/ Decentralized Development Planning and Budgeting

Processes ..................................................................................................................................................... 41

Objective Five: Facilitate Greater Evidence - Based Decision Making in Development Planning and

Budgeting .................................................................................................................................................... 44

5.0 Seventh National Development Plan (2017-2021): Formulation Processes and

Implementation Frameworks .......................................................................................... 45

5.1 Conceptual Framework of the 7th NDP ..................................................................... 47

5.2 Formulation Process of the 7th NDP .......................................................................... 48

Stage One – Issuance of National Policy Statement ................................................................................ 48

Stage Two – Review of National Development Policies .......................................................................... 48

Stage Three – Public Consultations .......................................................................................................... 49

Stage Four – Developing the Plan Zero Draft ......................................................................................... 50

Stage Five – Programme and Project Appraisal ..................................................................................... 52

Stage Six – Alignment of District / Provincial Indicators to NDP Indicators ....................................... 52

Stage Seven – Draft Plan (With various Options) ................................................................................... 52

Stage Eight – Draft NDP/Green Paper..................................................................................................... 53

Stage Nine – NDP Launch ......................................................................................................................... 53

5.3 Implementation Framework of the 7th NDP ................................................................ 53

5.4 Opportunities and Challenges .................................................................................... 54

6.0 Conclusions and Recommendations ..................................................................... 58

6.1 Key Issues .................................................................................................................. 58

6.2 Lessons Learnt ........................................................................................................... 59

6.3 Follow-up Actions and Recommendations .................................................................. 60

References ..................................................................................................................... 63

Annex 1: Types of Plans, Timelines and Purpose ........................................................... 66

Annex 2: Institutional and Consultative Framework for Development Planning ............. 67

Annex 3: National Performance Framework .................................................................. 68

Annex 4: National Development Planning /Formulation Process .................................... 69

Annex 5: The Five Steps in Evidence-Based Policymaking ............................................. 70

Page 4: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page iv

Acronyms

ABB Activity Based Budgeting

CAGs Cluster Advisory Groups

CDC Commonwealth Development Cooperation

CSO Central Statistics Office

DDCC District Development Coordination Committee

DPD Development Planning Department

FNDP Fifth National Development Plan

GW-M&E Government Wide – Monitoring and Evaluation

HIPC Highly Indebted Poor Countries

ICT Information Communication Technology

IFMIS Integrated Financial Management Information System

IMF International Monetary Fund

INDP Interim National Development Plan

IRDPs Integrated Rural Development Programmes

MDGs Millennium Development Goals

M&E Monitoring and Evaluation

MIS Management Information System

MMD Movement for Multi-party Democracy

MoF Ministry of Finance

MoNDP Ministry of National Development Planning

MPSAs Ministries, Provinces and other Spending Agencies

MTEF Medium-Term Expenditure Framework

NDCC National Development Coordination Committee

NDP National Development Plan

NERP New Economic Recovery Programme

NIMIS National Integrated Management Information System

NPBP National Planning and Budgeting Policy

NPF National Performance Framework

NSDS National Strategy for the Development of Statistics

OBB Output Based Budgeting

PEM Public Expenditure Management

PEMFA Public Expenditure Management and Financial Accountability Reforms

PDCC Provincial Development Coordination Committee

PFM Public Financial Management

PFMRS Public Financial Management Reform Strategy

Page 5: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page v

PIM Public Investment Management

PIP Public Investment Plan

PIPA Programme Implementation and Project Appraisal

PIPAM Public Investment Planning, Appraisal and Management

PIPD Public Investment Planning Department

PRSP Poverty Reduction Strategy Paper

R-SNDP Revised Sixth National Development Plan

RISDP Regional Indicative Strategic Development Plan

SAGs Sector Advisory Groups

SDGs Sustainable Development Goals

SPF Sector Performance Framework

SNDP Sixth National Development Plan

TNDP Transitional National Development Plan

UNIP United National Independence Party

7thNDP Seventh National Development Plan

WDCs Ward Development Committees

Page 6: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page vi

Geopolitical Map of Zambia

Page 7: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page vii

Executive Summary

Over many decades past, many African governments have put much emphasize on

developing planning as a conduit of economic emancipation. The strategic priority in

development planning had been to ensure that the country’s development is enhanced to

achieve high levels of economic growth and significant reduction in the levels of poverty.

However, in many instances, earnest attempts by most governments to link development

programmes to national priorities have been largely impaired by lack of adherence to

development policy direction, more often leading to development choices of programmes that

did not meet the criteria for budget consideration. The major challenge in this quest for

economic emancipation has been lack of adequate capacity of African national planning

institutions in their planning processes.

The United Nations Economic Commission for Africa (UNECA) initiated the process

to build the much-needed capacity in some of the national planning institutions in Africa with

the aim of embedding the idea of integrating accountability frameworks and evidence-based

policies in development planning processes in form of National Strategies. The initiative to

enhance capacity in the development of National strategies was first targeted at five countries

in Africa namely Benin, Cameroon, Egypt, Kenya and Zambia. The bedrock of National

strategies was an evidence-based and data-driven policy-making approach that relies on

building credible accountability frameworks into the planning process with specific, verifiable,

measurable and monitorable milestones and targets.

Against the background, the UNECA engaged the relevant institutions in the targeted

countries to assist in the implementation of specific activities as related to national development

planning in their respective countries. Among the many activities was the development of a

case study of the development processes for each of the respective countries.

Page 8: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page viii

The case study provided a platform to assess the status and progress of specific national

planning institutions; including opportunities for gender mainstreaming and also to examine

the countries’ existing evaluation and monitoring frameworks. This was meant to gauge entry

points for integrating accountability and evidence-based policymaking approaches in

development planning processes. The entry points were to assist in the development of specific

National Strategies for strengthening accountability and evidence-based policymaking in the

national planning processes.

The case study therefore sought to establish as to whether development policy reforms

undertaken by Government over the years have had any bearing on the effectiveness of the

development planning processes in the country and as to whether possibilities existed to

establish accountability and evidence-based policy making mechanisms in the Country’s

development planning processes.

In the study, a number of key areas of development planning in Zambia were analyzed.

The study presented a chronological order of the status and progress made in enhancing

development planning processes with the view of providing opportunities for integrating

accountability and evidence-based policy making approaches in development planning

processes.

Among the many issues identified in the report were those that bordered on strategic

formulation of macro-economic and fiscal frameworks and stakeholder consultations based on

communication strategies designed for the purpose. Also, there was the issue of the need for a

development plan with a clear focus/ strategy to conform with the shift from sectoral approach

to Integrated or Multi-sectoral approach meant to enhance the promotion of local participation

in development planning process. Other issues identified as key aspects in the development

processes were those linked to development cooperation and public investment planning,

appraisal and management.

Page 9: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page ix

In terms of implementation strategy, the development of an integrated implementation

plan was one key issue identified. This pertained to the elaboration of inter- and intra-sectoral

synergies to complement efforts towards the implementation of various strategies under

development outcomes. The formulation of a change management strategy was another key

issue in the development processes. Change management strategy was to include change

management programmes that would bring about mind-set change among all stakeholders,

including the general public.

The guidance provided in the planning and budgeting policy makes it a key aspect to

the achievement of the Vision 2030. This is because the policy specifically defines national

measurement framework to track implementation progress of the Vision 2030 for each sector

by considering the key result areas, key performance indicators and baseline and target values.

The anticipation is that with its enactment into the National Planning and Budgeting legislation,

decision making and efficiency in the development planning process would be greatly

enhanced.

The study provided lessons to a number of areas of concern. These bordered mainly on

the challenges and problems detrimental to Public Finance Management (PFM) efforts, budget

credibility and development results. In the Zambian case, it was clear that the challenges

identified attributed to weak links between policy cycle and financial cycle. This was due to

failure to align the budget planning, programming and expenditure to national Development

Plan (NDP) and the Vision 2030. This was compounded further by the non-linkage of the of

budget planning to the National Performance Framework (NPF). The absence of the NPF

presented a difficult to quantifying and linking outcomes and impact to Vision 2030.

The development of the NPF was key as it was an appropriate tool to operationalize the

national long-term vision. This would be done by re-packaging long term strategic objectives

into the medium term by logically identifying and interpreting the strategic objectives

Page 10: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page x

contained in the national long-term vision. In terms of tracking implementation progress

towards realizing objectives in the Vision 2030, the NPF would enhance policy cycle and

strategic vision through the establishment of a strong linkage between defined national

outcomes and key performance indicators in the NPF with NDP and the Vision 2030.

With regard to budget credibility, the key lesson was that with the development of

sector specific performance frameworks (SPF), this would further enhance and improve the

alignment of the NPF with the MTEF, NDP and Vision 2030. Key to this was the establishment

of Sector Annual M&E plans based on SPF. In this way, systematic M&E of each sector

strategic goals, objectives, programmes and projects would be enhanced.

The re-engineering of the legacy systems into Results Based Budgeting was another

key lesson as this was meant to create linkages between the policy and financial cycle as well

as planning and implementation of the NDP and Vision 2030. It is envisaged that the

introduction of evidence-based policy making approach in the national development planning

process would further enhance the identification of gaps where evidence of programme

effectiveness is lacking. With this strategy, policymakers would be enabled to use evidence in

making development and budget decisions.

With the understanding that evidence-driven policy making relies much on systems to

monitor implementation and measure key outcomes, this therefore warrants the development

of a National M&E policy framework that would spell out the M&E best practices, principles,

processes, standards and procedures. The underpinning factor would be the development of an

Implementation Plan, M&E guidelines, manuals and tools for use or adaption across

government.

In order to enhance accountability and evidence- based policy making in development

planning processes, the study provided some recommendations vital for the successful

Page 11: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page xi

development of the National Strategy for Strengthening Accountability and Evidence Based

Policy Making Mechanisms in Development Planning Processes in Zambia.

The recommendations mainly focused on the need for Government to heightened the

development of the NPF to enhance policy cycle and strategic vision through establishment of

strong linkage between defined National Outcomes and Key Performance Indicators in the NPF

with those in NDP and the Vision 2030; the development of Sector Performance Frameworks

(SPF) to improve the alignment of the MTEF with the NDP and the Vision 2030; the

development of the National M&E Policy Framework and Master Plan to guide

implementation across Government levels, agencies and sectors; development of a strategy to

strengthen enhancement of capacity (both human and institutional) across Government levels,

agencies and sectors; and also the development of a comprehensive Change Management Plan

to address issues of communication and objectivity in the development planning processes.

With the adoption of evidence-based policy making approach in the development

planning processes, the belief is that the Government would be able to reduce wasteful

spending by identifying and eliminating ineffective programmes in the planning processes. By

implication, this would enable freeing up of budgets for the expansion of innovative

programmes as well as strengthening accountability in the collection and reporting data on

programme operations and outcomes.

Page 12: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 1

1.0 Introduction

1.1 Background

Over many decades past, many African governments have put much emphasize on

developing planning as a conduit of economic emancipation. The strategic priority in

development planning had been to ensure that the country’s development is enhanced to

achieve high levels of economic growth and significant reduction in the levels of poverty.

However, in many instances, earnest attempts by most governments to link development

programmes to national priorities have been largely impaired by lack of adherence to

development policy direction, more often leading to development choices of programmes that

did not meet the criteria for budget consideration. The major challenge in this quest for

economic emancipation has been lack of adequate capacity of African national planning

institutions in their planning processes.

United Nations Economic Commission for Africa (UNECA), under its Capacity

Development Division took up the challenge to build capacity in five African countries namely

Benin, Cameroon, Egypt, Kenya and Zambia. UNECA’s objective was to assist the targeted

countries with strategies to integrate accountability frameworks and evidence-based policies in

their development planning processes and strengthen capacity to collect, compile and produce

the data necessary to inform and support development planning. The bedrock of this process

was an evidence-based and data-driven policy-making approach, which relies on building

credible accountability frameworks into the planning process with specific milestones and

targets that can be verified, measured, and monitored. Against this background, the UNECA’s

engaged the relevant institutions to assist it in the implementation of specific activities as

related to national development planning in the targeted countries. Among the many activities

was the development of case studies of the countries development processes. The purpose of

the case studies was to provide a platform to assess the status and progress of specific national

Page 13: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 2

planning institutions; including opportunities for gender mainstreaming and also to examine

the countries’ existing evaluation and monitoring frameworks. This was meant to gauge entry

points for integrating accountability and evidence-based policymaking approaches and by

using the case studies as entry points, to assist in the development of specific national strategies

for strengthening accountability and evidence-based policymaking in the countries’ national

planning processes.

1.2 Rationale

Zambia is one country that has coped with socio-economic factors that have influenced

its policy decisions on development for over five decades. These development policy decisions

have had a great influence in many areas of governance which in most cases were contradictory

to long-term development needs of the country. The impacts of such decisions were enormous

in situations where there were no effective planning processes for national development. With

the understanding that the fundamental objective of the planning process in any country is to

support its achievement of the social and economic development objectives, the absence of

effective planning processes meant that the country’s development was not supported

appropriately (Mulungushi, 2007).

With the notion that for the country like Zambia to foster its accelerated and sustainable

growth and to implement strategies for development as a means of meeting its development

aspirations, this case study seeks to establish as to whether development policy reforms

undertaken by Government over the years have had bearing on the effectiveness of the

development planning processes in the country or there are greater opportunities to establish

accountability and evidence based policy making mechanisms in its development planning

processes.

Page 14: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 3

1.3 Objective and Scope

The objective of the case study for Zambia is meant to assess the status and progress

of national planning processes in the five decades of its existence and to further examine its

existing evaluation and monitoring frameworks with the purpose of gauging the entry points

for strengthening accountability and evidence-based policymaking mechanisms in the

country’s development planning processes.

The case study though setting the stage for the development of the national strategy for

development planning processes, is to be used correspondingly as an avenue for capacity

building of development planning institutions. The study is to advocate for a robust institutional

and procedural approach to development planning by placing strong emphasis on creating

opportunities for capacity building within key development planning institutions. Ultimately,

the aim of the case study is to build internal skills and understanding of development planning

processes and procedures in the implementation of development programmes.

1.4 Methodology

Initial understanding of case studies globally was that it was aimed at analyzing specific

issues within the boundaries of a specific environment, situation or organization. According to

its design, case study methodologies could be divided into three categories: explanatory,

descriptive and exploratory. Explanatory case studies are those that aim at answering the ‘how’

or ’why’ questions over occurrence of events. This type of case studies focus on phenomena

within the contexts of real-life situations. On the other hand, descriptive case studies aim to

analyze the sequence of interpersonal events after a certain amount of time has passed. Case

studies belonging to this category usually describe culture or sub-culture, and they attempt to

discover the key phenomena. As for Exploratory case studies, these aim to find answers to the

questions of ‘what’ or ‘who’.

Page 15: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 4

To meet the objectives of this specific case study, structured methodology and approach

was followed. The structured methodology and approach for the case study considered the

exploratory and descriptive categories. These were found ideal to guarantee adequate coverage

of all aspects of the case study objectives.

The case study methodology was mainly qualitative in the sense that it mainly bordered

on the reviews of documents relevant to the task. Case studies are well suited for the purpose

in that with the phenomenon to be studied, it was easy to intensively investigate the

characteristics of development planning processes globally and assess these characteristics

pertaining to Zambia. By closely examining these characteristics and comparing and

contrasting them, it was study to explore the significant features of the global phenomenon and

how it varies with the Zambian circumstances. The review therefore was significant for the

purpose of appraising the contents and the current progress and status of development planning

approaches globally, continental, regional and national levels as captured in various document

and reports and then try to re-align to the key objectives of the case study, subsequently

narrowed to the existing policies and procedures for development planning processes in

Zambia.

The review was mainly to act as a base on what would constitute the most appropriate

mechanisms to strengthen accountability and evidence based policymaking strategies in the

development planning processes of Zambia. Some of the documents reviewed included:

National Budgeting and Planning Policy and Draft Bill, 2016; Public Finance Act; National

Development Plans (Fifth/ Sixth and Revised Sixth NDPs); Transitional National Development

Plan; Poverty Reduction Strategy Paper and other relevant reports and articles on the

development planning processes.

After the documentation reviews, the desktop analysis of the data was conducted. This

was mainly for the purpose of identifying the gaps that needed consideration in the

Page 16: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 5

development of a national strategy for strengthening accountability and evidence-based

policymaking in Zambia’s national planning processes. The analysis was based on both policy

and processes as reviewed in the relevant documents referred to above. The analysis assisted

greatly in identifying the most important facts surrounding the case study and the key issue or

issues. This also allowed for specification of alternative courses of action and evaluation of

each course of action. Finally, the study was able to provide some recommendation on the best

course of action for the development of the National Strategy for strengthening Accountability

and Evidence Based Policy Making Mechanisms in the Developing Planning Processes in

Zambia.

1.5 Organization

The study is organized in six (6) chapters. Chapter one is the introduction which covers the

rationale of the study, its objective and scope, the methodology and its organization. Chapter two

presents an analysis of the models and processes of National Development Plans. These include

participatory development approaches, sectoral development planning approaches, integrated multi-

sectoral development approaches, strategic planning model and theory of change model. The chapter

also provides the national, sectoral, regional, continental and global perspective of development

planning with emphasis on some international best practice. Chapter three brings in the aspect of

national development planning in Zambia by presenting the socio-economic context of the country. It

further considers the pre-2005 development planning phenomenon in Zambia and the post-2005

development planning frameworks. Chapter four provides an analysis of the status and progress in the

national development planning process in Zambia post- 2005. This covers Vision 2030 , the Fifth,

Sixth and the Revised Sixth National Development Plans, the Public Investment Planning, Appraisal

and Management Framework, National Planning and Budgeting Policy, Monitoring and Evaluation

Frameworks. Implementation Challenges of the Previous NDPs and lessons learnt from Implementing

Prior NDPs are then presented. Thereafter an assessment of the status and progress of NDP Process in

Zambia is further present with emphasis of the status and progress on NPBP Objectives. Chapter five

discusses the Seventh National Development Plan (2017-2021) formulation processes in line with its

Page 17: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 6

conceptual and implementation frameworks. The chapter further brings out the opportunities and

challenges of the processes. Chapter six presents the conclusions by highlighting key issues and lessons

learnt in the study. Finally, follow-up actions and recommendations are provided.

Page 18: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 7

2.0 Analysis of Models and Processes of National Development

Plans In development, there are various models and approaches that are used for development

planning processes. Some of these models and approaches include participatory development,

sectoral and multi-sectoral development, strategic planning and theory of change.

2.1 Participatory Development Approach

This is an approach that is local-community-led. It introduces a bottom-up style of

development in order to remedy the government-led approach's shortcomings. The approach

specifically focuses on qualitative improvements in local society's participation in the

development planning processes. Participatory development planning emphasizes the

involvement of the entire community in the strategic and management processes of planning;

or, community-level planning processes, urban or rural. With this approach, views among all

of its participants harmonized and this helps to prevent conflict of views between opposing

parties. It is one approach where marginalized groups have an opportunity to participate in the

planning process (Chapagain, 2012)

2.2 Sectoral Development Planning Approach

Under the sectoral development planning, there are a number of approaches that can be

used in development planning. The Spatial Development Perspective is one of the approaches

of developments planning. The approach provides a multidimensional analysis of the national

space and indicates areas of potential to be developed over a period of 20 to 30 years. As for

the ‘Spatial Development Plans’, the approach differs from the aforementioned approaches in

that it is more of a comprehensive nature, addressing development over various sectors. These

plans are more specific in proposing what type of development should happen at which locality

and time. There is also the ‘Spatial Frameworks and Spatial Strategies’ approach which mainly

applies to provincial and district levels. These frameworks provide general guidelines to which

Page 19: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 8

public and private sectors must adhere. In the modern era, there is also the ‘National Planning

Approach’ that is free market-oriented whereby private sector investment and development is

attracted through public sector investment (Wikipedia, 2017).

In terms of sector development plan, these entail detailed statement of performance,

issues and opportunities, development objectives, policies and strategies that support the

developments in a specific sector e.g. Education, Agriculture, Water and Sanitation etc. It

provides a framework for the identification of public policy initiatives and projects in the

segment, including the role of the government agencies and the private sector in the

development of the specified sector.

2.3 Integrated Multi-Sectoral Development Approach

The integrated development approach emphasis on the need of coordinating different

perception of development under a single management system of essential components

required to get development moving. It is designed to provide an important role for

stakeholders in planning, decision making and implementation of the programmes. The main

emphasis is on rational development and coordination of all principal factors required for cross-

sectoral development (Chapagain, 2012)

Multi-sectoral approach emphasizes much on regional comparative advantage and

linkages. The approach enables resources to be focused on priority sectors unlike the case for

sectoral where resources are spread thinly across sectors with minimal impact. Further multi-

sectoral approach enables the triggering of mutually supporting activities in multiple sectors.

With the view that multi-sectoral approach has limited number of priorities to focus on; this

has greatest impact or higher rate of return on sector prioritized. This is contrasted with the

sectoral approach where there is no emphasis on unique priority areas and as a result the

approach does not have greatest impact due to single sector focus.

Page 20: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 9

2.4 Strategic Planning Model

Strategic planning is one such model is utilized in development planning processes.

The model encompasses the setting of goals, determination of actions to achieve the goals, and

mobilization of resources to execute the actions. It is more aligned to describing how the ends

(goals) will be achieved by the means (resources) (Montather, 2015). The model is more of an

organization's process of defining its strategy, or direction, and making decisions on allocating

its resources to pursue this strategy. It may also extend to control mechanisms for guiding the

implementation of the strategy.

The aim is at identification, prioritization and validation of policies, it further defines

objectives, strategies and associated costs. This process includes all aspects of the economy

such as political realities, and economic, social, technological, legislative and environmental

issues, particularly when dealing with the situational analysis of an organization.

The ultimate aim of strategic planning model is to identify, prioritize and validate

policies, programmes and projects at the sub-district, district, provincial and national levels.

This is done in a systematic manner and with agreed instruments as well as the participation of

all stakeholders. This is to ensure that all considerations are made for all aspects that can go

wrong or right during implementation of programmes (Wikipedia, 2017).

The justifications for model approach are many depending on level at which it is to be

considered and effectively implemented. In other thought, the model is able to define the vision

and mission in which fundamental long-term aims are articulated. It does, more importantly,

provide further the definition of mechanisms and institutional and organizational frameworks

for implementation, monitoring and evaluation of development strategies that are made. This

is in recognition that the planning processes and the associated institutional structures are

important to deal with the environmental factors, systematizing planning and economic

Page 21: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 10

management. The model further introduces logic to decision-making of the organization

through political and technical interactions.

2.5 Theory of Change Model

A Theory of Change (ToC) model is appropriate to development planning. It is a model

that articulates, in a systematic way, how strategies, activities or programmes contribute to a

set of specific outcomes through a series of intermediate results. It describes the pathway

through which change is to come about (i.e. what is needed for goals to be achieved) in the

context of how the economy is going to diversify; what results will be needed to attain

diversification; and what interventions are to bring about these results. It also describes the

underlying assumptions and conditions necessary to bring about this change. It further defines

the pieces and steps necessary to bring about a given long-term goal (http://theoryofchange.org,

2017)

In terms of process, the Theory of Change model uses a specific type of methodology

for planning, participation, and evaluation in government sectors to promote social change. The

model defines long-term goals and then maps backward to identify necessary preconditions. It

further explains the process of change by outlining causal linkages in an initiative, i.e., its

shorter-term, intermediate, and longer-term outcomes. The identified changes are mapped –as

the “outcomes pathway” – showing each outcome in logical relationship to all the others, as

well as chronological flow. The links between outcomes are explained by “rationales” or

statements of why one outcome is thought to be a prerequisite for another. The innovation of

model thus lies in making the distinction between desired and actual outcomes, and in requiring

stakeholders to model their desired outcomes before they decide on forms of intervention to

achieve those outcomes (Wikipedia, 2017)

Page 22: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 11

2.6 National, Sectoral, Regional, Continental and Global Perspective

Globally, development planning is a multifaceted and cross-cutting undertaking that

plays an important role in shaping and accelerating the achievement of a country’s development

goals and priorities. By design, development planning is a long-term programme that is meant

to effect some permanent structural changes in an economy. In terms of process, it is

government that sets out objectives about the way it wants the economy to develop in the future

and then intervenes to try to achieve those objectives. The process entails a country coming up

with strategies that are carefully mapped out with a strategic focus to bring about the desired

national development aspirations. This requires high – level planning1 approach that entails

countries coming up with well-researched and well-reasoned development plans that prioritize

and synchronize activities so as to rationalize the scarce resources meant for development with

the aim of ensuring that national development plans utilize the available resources more

effectively to achieve well-defined objectives.

In the analysis of literature, development planning is generally understood as concept

that is anchored on effective and inclusive participation in planning processes; evidence-based

plans which are standardized and aligned to the National Development Plans (NDPs) and the

National Vision; integration of cross-cutting issues and policies; fulfillment of mandates of

development institutions according to their technical capacities; transparency and value for

money in service delivery as well as integration of development policies, legislation, plans and

programmes. Thus, perceptions of development planning may be at variant depending on

policy direction and strategic focus.

1 Hansen, Higgins & Savoie (1990) defined high level planning as “policy that reflects both what is happening

within national society and national economy at any particular time and the prevailing economic and social

philosophy at that time; and these interact with one another”.

Page 23: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 12

Development planning especially in developing countries had its initial focus on social

development and an overriding emphasis on the reduction of extreme poverty. This was in

pursuit of macroeconomic stability, growth and poverty reduction and structural transformation

in their development agenda. This global perception of development planning has since

evolved from a narrow focus on poverty reduction in developing countries to a much broader

objective of inclusive growth underpinned by structural economic transformation2. From the

foregoing, it can be understood that development planning is an important process for

economic development. This is more reason why countries have engaged and will continue to

adopt planning instruments in their development pursuits.

The understanding is that development planning provides a systematic approach to

identifying, articulating, prioritizing and satisfying the economic and social needs and

aspirations of a country within a given or limited resource envelope (UNECA, 2016). This

could be attested by the number of local and global initiatives that are targeted at development

goals. In developing countries for instance, most of the strategic projections of development

objectives for their development plans emanate from global, continental, national, regional and

sectoral institutions while others are formulated in multilateral and international frameworks.

The broader development plans often take into consideration various global and

continental development goals and frameworks. Global development agendas such as the

Millennium Development Goals (MDGs)3, Sustainable Development Goals (SDGs)4 and

2 In terms of structural economic transformation, this requires a more inclusive approach to planning; more

effective mechanisms of implementation and robust monitoring and evaluation systems that track progress and

corrective measures to improve plan implementation.

3 The Millennium Development Goals (MDGs are a set of 8 "Global Goals" adopted by the United Nations for

global development.

4 The Sustainable Development Goals (SDGs), officially known as “Transforming our world: the 2030 Agenda

for Sustainable Development are a set of 17 "Global Goals" with 169 targets between them and are spearheaded

by the United Nations.

Page 24: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 13

Poverty Reduction Strategies have shaped the development priorities of most of the developing

countries in their quest for social development and the eradication of extreme poverty.

At continental level, various approaches to development planning have influenced the

development path in most of the developing countries. In Africa for instance, the first phase of

development planning in the 1960s was characterized by centralized planning with three to

five-year planning phases. These plans promoted state-engineered economies with resources

allocated by governments. This also culminated in most of the state-owned enterprises

operating in most of the productive sectors of the economies.

The second phase in the evolution of planning in Africa was marked by a wholesale

abandonment of planning under neoliberal Structural Adjustment Programmes (SAPs), which

emerged in the 1980s-1990s with the support of the IMF and the World Bank. SAPs aimed to

reduce the role of the State in production and service delivery and placed emphasis on

macroeconomic stability, downsizing of public sector institutions, privatization and reducing

government spending and budget deficits.

Poverty Reduction Strategies (PRSPs) were introduced in the early 2000 with the aim

of reversing the negative effects of a decade of SAPs. PRSPs placed strong emphasis on

poverty reduction but as a condition for debt relief. This made most of the countries to embark

on at least two generations of PRSPs as eligibility criteria for debt relief (UNECA, 2016).

In the recent past, continental bodies have put in place or designed framework for their

own development. One such framework is the ‘Africa 2063 development Agenda’5 developed

by the Africa for Africa’s development. Agenda 2063 is an ambitious, Pan-African people-

centered vision and action plan that aims to position Africa for growth over the next 50 years,

5 It is a strategic framework for the socio-economic transformation of the continent over the next 50 years. It

builds on, and seeks to accelerate the implementation of past and existing continental initiatives for growth and

sustainable development.

Page 25: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 14

incorporating lessons and experiences from the past. It is a global strategic rolling plan with

short- (10 years), medium- (10–25 years), and long-term (25–50 years) perspectives. Critical

success factors for Agenda 2063 include the participation of multiple stakeholder groups at all

stages, a results-based approach with measurable objectives, and inculcating the right set of

African values in line with the African Renaissance which suggests the transformation of

attitudes, values, and mindsets. As both a vision and an action plan, Agenda 2063 boldly calls

for Africa's “positive socio-economic transformation”. It goes beyond drivers for economic

growth or development, and calls for transformational change, open governance, and shared

prosperity (African Union Commission, 2015).

In terms of regional perceptive6, development planning takes multi-jurisdictional

approach in addressing development. This is with regard to socio-economic issues in terms of

physical boundaries and also the extent of the development being perceived. Economic

regionalism for instance focuses on coordinated development activities tied to a comprehensive

economic development strategy for a geographically connected region. Economic regionalism

therefore entails the existence of linkages and collaborations among stakeholders within an

economic region of geographical proximity. Regionalism as a concept in planning may be

considered as a framework for addressing socio-economic and environmental challenges of

multiple jurisdictions anchored on capable institutional frameworks (Wikipedia, 2017).

For regionalism to be seen as progressive, many regional organizations have designed

institutional frameworks that supports participation and representation to produce effective

economic growth strategies while promoting equity.

A key example of regional development framework is the Regional Indicative Strategic

Development Plan (RISDP). RISDP is a comprehensive development and implementation

6 A region is defined spatially in relations to the definite physical boundaries of an area or based upon the nature

of the particular focus of attention.

Page 26: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 15

framework which guides the regional integration agenda of the Southern African Development

Community (SADC) over a period of fifteen years (2005-2020). It is designed to provide clear

strategic direction with respect to SADC programmes, projects and activities in line with the

SADC Common Agenda and strategic priorities, as enshrined in the SADC Treaty of 1992.

The ultimate objective of the plan is to deepen integration in the region with a view to

accelerating poverty eradication and the attainment of other economic and non-economic

development goals (SADC, 2012).

At national level, many developing countries have continued to engage in development

dynamics which are designed to create conditions for sustainable growth with option for a long-

term vision of development. These engagements have been undertaken using a number of

approaches as stated earlier.

2.7 International Best Practice

The experiences of developing countries mostly in Africa and Asia provide lessons in

development planning approaches, especially in the context of the post-20157 development

agenda and Sustainable Development Goals (SDGs) and most especially on the design,

implementation and monitoring of development plans (UNECA, 2015)

In Asia, the transition to sustained growth has consistently been associated with policies

aimed at macroeconomic stabilization; improving life in the rural sector, increasing agricultural

productivity, and ensuring an ample supply of food; liberalizing the economy and creating

conditions of economic freedom. There are other factors such as industrialization on the basis

of foreign direct investment (FDI); systems of politics and governance; and cultural patterns

that manifest in policy choices. In Africa, initiatives in these directions have in some instances

7 The Post-2015 Development Agenda refers to a process led by the United Nations that aims to help define the

future global development framework that succeeded the Millennium Development Goals.

Page 27: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 16

been present, but the simultaneous pursuit of all policy objectives has proven otherwise

(Donge, Henley and Lewis, 2015).

In terms of practice, the Africa- Asia experiences provide some relevant primary

lessons for Zambia’s development planning process. One of the lessons includes the notion that

development planning is crucially imperative for Zambia as it strives to achieve socio-

economic gains for prosperity (UNECA, 2015). Equally, the need for committed leadership to

guide the development planning is one key lesson. Effective leadership is another vital aspect

in development planning in that it is required to drive the planning process towards the

achievements of the intended objectives within the available means. Thus, national ownership

of development planning processes and effective leadership by the government as well as

alignment with national development plans and strategies is one of the essential lessons from

the Asia experience.

Further, another critically paramount lesson to advancing development planning agenda

is the understanding that there is “no one size fits all approach” to development planning. In

other words, approaches that work for one country may not necessarily work for another.

Furthermore, approaches that work at one point in time for any given country may not be

appropriate at another point in time. Additionally, stability is a critical lesson in the

development planning process in the sense that discontinuities including those caused by

constitutional and unconstitutional regime changes may contribute to implementation failures

in the process. Evidence-based development planning must therefore be nationally-driven and

not to follow approaches that can not apply to a country’s demographic and socio-economic

potential to eradicate poverty and foster economic growth in Africa (UN News Centre, 2010)

As for political commitment, this is one aspect that is vital for nurturing a strong

development planning institutional structures. This is to avoid situations where development

planning structures are subjected to the whim of the political dispensation. This arise from the

Page 28: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 17

notion that in the early stages of the planning process in most developing countries, the

effectiveness of development planning institutional structures depended on the political

commitment to nurture and sustain them.

In terms of aid, one of the pivotal lessons for Zambia is reliance on aid while owning

and leading its development process by designing a robust development plan with a clear set

of priorities and assigning donors to specific sectors of development and this can only be

achieved when there is strong commitment toward the development goals defined.

Arising from the lessons learnt from Asia, there is now a promising revival of

development planning in most of the African countries as well as a growing role for the state

in the economy. Many African countries are now developing plans and national development

strategies, with targets for growth, jobs, and structural transformation and with a mix of the

state and market, public and private sectors and long-term vision of ownership by Africans

(Khor, 2013).

3.0 The National Development Planning in Zambia

Zambia is one of the African countries that lie geographically between thirty degrees

east and fifteen degrees south of the equator. It has a total land area of 752,614 square

kilometers and is neighboured by eight countries namely Angola and Namibia to the west and

Page 29: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 18

southwest, Botswana and Zimbabwe to the south, Democratic Republic of Congo to the north

and northeast and to the east Tanzania, Malawi and Mozambique. It became a sovereign state

on 24th October 1964. Its population is estimated at 15.9 million (Central Statistical Office,

Zambia, Census, 2016).

Administratively, the country is divided into 10 regional areas (provinces) with Lusaka

as its capital city. Other major cities are Livingstone, Ndola, Kitwe and Chipata. Zambia’s ten

provinces and 108 districts have very different conditions and potentials, which are critical to

deal with social and economic sectors in terms of development.

3.1 Zambia Social and Economic Context

The Zambian economy is a duality in terms of its structure. On one hand there is a

modern industrial sector dominated by the copper industry and a small manufacturing sector

and on the other, there is the agricultural sector dominated by a large number of peasant

farmers.

Over the five decades of its post-independence existence, the government has made

efforts to correct the imbalance through support to the agricultural sector as part of the

structural economic transformation agenda. However, the achievements have been falling short

of the intended goals. The agricultural sector has over the years not made significant

contributions towards raising the incomes of the majority of the poor people in the poverty

stricken rural areas of the country (Gumboh, 2012, MoNDP, 2016, BoZ, 2016).

With regards to development, the country has over years equally coped with socio-

economic factors that have influenced its policy decisions on development. These policy

developments have had a great influence in many areas of governance which in most cases

were contradictory to long-term development needs of the country. The impacts of such

decisions were enormous in situations where there were no effective planning processes for

national development (Mulungushi, 2007).

Page 30: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 19

With the logic that the fundamental objective of the planning process in any country is

to support its achievement of the social and economic development objectives, it therefore

follows that the country, as one of the developing economies, has had to undertake many radical

reforms in its quest to improve development planning for economic efficiency.

The Government of Zambia (GRZ), like many other governments of developing countries, has

faced a number of challenges in implementing its development agenda, specifically when development

entails the transformation of Zambia’s landscape in terms of physical infrastructure (transportation,

energy, water supply, sanitation) and social infrastructure (quality healthcare, education and public

administration). This transformative developmental agenda was in turn expected to create the

productive capacity for national growth and prosperity.

In addition to the institutional challenge of inadequate capacity to explore accountability

frameworks and evidence-based policy tools in the process of development planning, lack of a clear

and central mechanism to guide the translation of development plans into strategic and prioritized

programmes led to public funds being allocated inefficiently. The success and realization of

development programmes therefore called for adherence to sound preparation and well-managed,

transparent planning processes throughout the programme life cycle, combined with a timely matching

of programme preparation and procedures. This not only ensures well defined programmes but also

ease of implementation and monitoring, which are vital for the delivery of any development programme.

Such an approach will also ensure that development is effectively planned and scarce resources are

optimally allocated, which will ultimately enhance the credibility of the National Budgeting system.

3.2 Pre-2005 Developing Planning in Zambia

From the time of its sovereignty, Zambia, through various governments, has developed

a number of development plans in the quest to transform its economy. Some of the notable

developmental efforts of various governments in Zambia over the five decades of its existence

as a sovereign state are: Emergency Development Plan (1964-1965), Transitional National

Page 31: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 20

Development Plan (1965-1966). First National Development Plan (1966-1970); Second

National Development Plan (1972-1976); Third National Development Plan (1979-1983);

Interim National Development Plan 1987-1988; Fourth National Development Plan (1989-

1993); The Poverty Reduction Plan (1999-2004); Poverty Reduction Strategy Paper (2002–

2004); Public Investment Programme (2002-2004); Transitional National Development Plan

(2002-2005);

In the analysis of the development plan strategies, it was clear that the initial plans focus

was at reserving the imbalances in terms of equitable development throughout Zambia

(Mulungushi, 2007). The plans were all aimed at counteracting the adverse effects of pre-

independence era which created structural imbalances and lopsided development. This was the

more reason why the government had initiated the process of economic and social

infrastructure development and diversification of the agricultural and industrial base. The First

National Development Plan (1966-1970), for instance was aimed at improving social and

economic infrastructure starting with the key sectors such as the transport and communication,

health, and education. This was done with the aim of enhancing human capital development

most especially for the purpose of maximizing Zambianisation of jobs (First National

Development Plan, 1965).

The Second National Development Plan (1972-1976), on the other hand, was designed

to carry further the process of economic and social growth by placing major emphasis on rural

development (through Rural Reconstruction Programmes and later Integrated Rural

Development Programmes) equally aimed at reducing income disparities and regional

imbalances in the economy. Having built basic economic and social infrastructure in the

previous plans, Government embarked on the process of industrialization. This was done by

putting up industries in rural areas depending on the local resource endowments as a strategy

to local industrialization (Second National Development Plan 1971).

Page 32: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 21

Under the umbrella of the Third National Development Plan (1979-1983), the

government continued with its rural development and diversification programmes particularly

through the Integrated Rural Development Programmes (IRDPs). The Interim National

Development Plan (INDP) (1987-1988) was prepared as a stop-gap measure and as a bridging

gap between the International Monetary Fund (IMF) and World Bank programme and the

Fourth National Development Plan based on the New Economic Recovery Programme

(NERP). After the INDP, the government went back to develop the Fourth National

Development Plan (1989-1993), whose objectives were of the long and short-terms. The Fourth

NDP objectives mainly aimed at integrating women in the development process as a strategy

of engendering development; identification and promotion of productive informal sector

activities, which had potential for growth and employment generation; reduction in the existing

socio-economic and regional disparities and improvement in the living standards in rural areas;

according high priority to the development of agriculture; promotion of regional development

on the basis of the characteristics and development potential of each region among others

(Fourth National Development Plan 1988).

At the inception of the liberalization of the economy in 1994, after the change of

political power from United Nations Independence Party (UNIP) government to the Movement

for multi-party Democracy (MMD) government, this era saw the abolition of central planning.

In principle, it was the era that brought to an end - the preparation of the five-year plans. With

the economy liberalized, the government initiated the idea of preparing Policy Framework

Papers, Poverty Reduction Plan, Public Investment Programme and Poverty Reduction

Strategy Paper as planning documents.

The Poverty Reduction Plan (PRP) (1999-2004), for instance, stipulated development

priority areas that included achieving broad based economic growth through agriculture and

rural development; provision of public physical infrastructure; increasing productivity of urban

Page 33: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 22

micro - enterprises and the informal sector; developing human resources; and coordinating

monitoring and evaluation of poverty reduction programmes and activities (National Poverty

Reduction Plan, 2000).

As for Public Investment Programmes (PIPs), these covered capital programmes

designed by Ministries, Provinces and Other Spending Agencies (MPSAs). In the absence of

five-year development plans, the PIP provided the framework for capital programmes to be

implemented in three subsequent years. The idea of the PIP was to prioritize programmes in

the public sectors earmarked for implementation in accordance with the available resources.

For this reason, the PIP showed the resource gaps and formed a basis for resource mobilization

internally and from donors (Public Investment Programme, 2002).

The development of the Poverty Reduction Strategy Paper (PRSP) for Zambia was

initiated in 2000 and its implementation ran up to 2004. The PRSP was part of Highly Indebted

Poor Countries (HIPC)8 initiative aimed at reducing indebtedness of the poorest countries by

cancelling debts and using the savings to finance targeted poverty reduction programmes. The

PRSP document was thus a prerequisite for accessing HIPC funds for Poverty Reduction.

The Transitional National Development Plan (TNDP) (2002-2005) was the off-short plan

meant to fill the gap before the Fifth National Development Plan (2006-2010). TNDP was a

continuation of PRSP in that it included all sectors of the economy. This was aimed at further

projecting economic planning from a national outlook. Whereas PRSP only dealt with a few

sectors such as Economic, Social, Population and Good Governance, the TNDP included

sectors omitted such as Defense and Security, Central Policy and Administration. The belief

was that the economy was an integrated entity and should therefore ensure that all sectors

moved in tandem (TNDP 2002).

8 HIPC was designed by the World Bank and International Monetary Fund (IMF) as part of their

structural adjustment programmes.

Page 34: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 23

3.3 Post – 2005 Development Planning Frameworks

In the review of the Public Expenditure Management (PEM), it was clearly established

that the Government of Zambia had in the past ten years, undertaken a number of reforms to

enhance public expenditure management. Notable among the reforms was the Public

Expenditure Management and Financial Accountability (PEMFA) Reforms (2003- 2007),

whose key components included the development of the Medium-Term Expenditure

Framework (MTEF), and the Integrated Financial Management and Information system

(IFMIS).

By developing and implementing the MTEF, Government aimed to achieve objectives

anchoring on reforming the framework governing public expenditure management in order to

make it more results-oriented and geared to achieving development outcomes; improving the

efficiency, effectiveness and accountability of government institutions when developing and

implementing their programmes and activities; provision of more concrete information to

Cabinet on the performance of the budget for decision- making purposes and for setting future

targets and priorities; provision of information to help reallocate resources between institutions

and programmes; reduction in expenditure when necessary; and institutionalization of

accountability throughout the process by aligning budgets to policy priorities and targeted

outputs/outcomes and increased transparency of the budgeting process (MTEF document,

2005)

The IFMIS whose development was initiated in 2005, on the other hand, was aimed at

assisting the Government to strategically manage public financial resources through an

automated and integrated information system. In its design, the IFMIS was meant to enhance

accountability, transparency and cost effective public service delivery. It was envisaged to

improve service delivery in public sector, by enhancing the production of timely and reliable

financial statements, strengthening financial controls to ensure better availability of the

Page 35: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 24

financial data and enhanced transparency and accountability of the executive to the public

(IFMIS Report, 2010).

Public Financial Management Reform Programme (PFMRP) (2013-2015) that

succeeded the PEMFA, focused on the legal and institutional framework for supervising all

phases of the budget cycle, including formulation and preparation of the budget, budget

execution and expenditure management. The broad objectives of the PFM were to achieve

overall fiscal discipline, allocation of resources to priority needs and efficient and effective

delivery of public services (PFMRP, 2013)

The PFM reform strategy applied an all-inclusive, systematic view of the PFM system

which is aimed at consolidating macroeconomic stability as one of the key objectives of

National Development Planning. The PFM reform strategy is mainly focused on the need to

further improve Government’s capacity to utilize public funds towards meeting the growth and

employment targets for the medium term and ultimately those of the vision 2030. The PFM

reform strategy included key components of the PFM system as well as cross-cutting issues

related to capacity building, public procurement and internal controls and audits among others.

The PFM reforms encompassed ten components among which were the Integrated Planning

and Budgeting and the Monitoring and Evaluation (M&E) components, key to the development

planning efficiency in Zambia.

In the PFM context, the Integrated Planning and Budgeting component was aimed at

improving the development planning and budgeting processes to enhance the development and

service delivery impact of the public service. Core programmes of the component included the

development of the planning and budgeting legislation; development of manuals for planning,

budgeting and M&E; capacity building on all administrative levels to ensure compliance to

planning and budgeting Act; designing of the change process; sensitization on Planning and

Budget Act and its impact on processes (PFMRP, 2013).

Page 36: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 25

The M&E Component, on the other hand, focused on strengthening monitoring and

evaluation systems with the aim of providing evidence-based development planning, budgeting

and programme implementation. Among the key programmes in the M&E component was the

establishment of M&E functions in all MPSAs; development of the MIS and budget execution

monitoring (NPBP,2014).

4.0 Status and Progress in the National Development Planning

Process in Zambia

In the post - 2005, national development plans become the cornerstone of the

development planning processes in Zambia. These plans have been undertaken through long

term, medium term and annual plans in the form of twenty-five - year National Long-Term

Vision and five-year National Development Plans (NDPs). All the types of development plans

with timelines and purpose are as presented in Annex 1.

Page 37: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 26

4.1 Post - 2005 National Development Plan Frameworks

4.1.1 Vision 2030

The Vision 2030 is the national long-term development framework for Zambia. The

Vision 2030 expresses the aspirations of the Zambian people to be accomplished by the year

2030. It articulates the appropriate national and sector goals to meet the people’s aspirations.

It is based on policy-oriented research on key national strategic issues and on a process of

discussion and dialogue with the private sector, civil society and the general citizenry on the

long-term goals and future of Zambia (Vision, 2030).

In the Vision, the desirable long-term paths of the socio-economic indicators to satisfy

the people’s aspirations are outlined. These socio-economic indicators articulate possible long-

term alternative development policy scenarios at different points through to the target year. The

vision is the basis for interface by all sectors and provides directions for short and medium-

term plans. Its realization is dependent on the actions and measures to be undertaken by

Government, private sector cooperating partners, civil society and as individuals in the

development and eventual implementation of the short and medium-term national development

plans. The development plans are perceived to create necessary conditions upon which long

term objectives and targets are to be achieved.

The Vision is anchored on seven key basic principles and these include sustainable

development; upholding democratic principles; respect for human rights; fostering family

values; positive attitude to work; peaceful coexistence; and upholding good traditional value

(Vision 2030).

4.1.2 Fifth National Development Plan

In terms of development planning, the Fifth National Development Plan (FNDP), 2006

– 2010 was the first important step towards the realization of the Vision 2030. It was anchored

on the vision’s strategic focus of “Economic infrastructure and human resources development”

Page 38: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 27

with its emphasis on financial and budgetary accountability, entailing the ability to account for

the allocation, use and control of public funds, public assets and properties (FNDP, 2006).

4.1.3 Sixth National Development Plan

The Sixth National Development Plan (SNDP), (2011-2015), the successor to the

FNDP, on the other hand, had its focus on the challenges that were faced in the implementation

of the FNDP, vis-a-vis the binding constraints to pro-poor growth and to enhance the

achievements made therein. The focus was more on macroeconomic objectives with emphasis

on the enhancement of macroeconomic stability; improvements in public expenditure

management; expansion in domestic revenue base; promotion of rural development;

acceleration of economic diversification and productive employment; and enhancement of the

quality of human development.

In light of the above objectives, the SNDP concentrated mostly at policies, strategies,

and programmes that were to contribute significantly to addressing the challenges of realizing

broad based pro-poor growth, employment creation and human development (SNDP, 2011).

4.1.4 Revised Sixth National Development Plan

The re-engineering of the SNDP to take on board the Patriotic Front’s Government

priorities to advance its development agenda culminated into the Revised Sixth National

Development Plan (R-SNDP), (2013-2016). Like other previous plans, the R-SNDP was

correspondingly aimed at achieving the objectives set out in the Vision 2030. It was primarily

a Public Investment Plan (PIP) which contained quantifiable programmes to inform sector

planning and budgeting processes. The plan with its strategic focus on “People Centered

Economic Growth and Development” provided a framework for accelerating socio-economic

development in the medium term. It had a comprehensive medium-term strategy for an all-

inclusive and sustainable development agenda (R-SNDP, 2013)

Page 39: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 28

4.1.5 Public Investment Planning, Appraisal and Management Framework

The development of Programme Implementation and Project Appraisal (PIPA) Manual

was one key achievement in the enhancement of the development planning processes. The

PIPA was developed in 2015 but was eventually reviewed in 2016 into Public Investment

Planning, Appraisal and Management (PIPAM) Framework to incorporate guidelines and

procedures.

The rationale for developing the PIPAM Framework was based on the notion that

investment was a key development planning aspect because of its greater impact on the

effective management of public investments mostly undertaken by implementing MPSAs in

Zambia. The scenario was that with the lack of a clear and central mechanism to guide the

translation of policy into strategic and prioritized public investments, the implication was that

public funds to development were inefficiently allocated (PIM Concept Note, 2015).

The introduction of the principle of project planning and appraisal for all public

investments however emphasized on sound preparation and well-managed, transparent

processes throughout the project life cycle, combined with timely matching of project

preparation and project financing. The sound preparation of public investment projects not only

ensures well defined projects but also ease of implementation and monitoring (PIPA, 2015).

4.1.6 National Planning and Budgeting Policy

The major achievement in the development planning processes was anchored on the

development of the planning and budgeting framework as part of the integrated planning and

budgeting reforms. The Government took major steps towards obligation by putting in place

the National Planning and Budgeting Policy, drafting of National Planning and budgeting Bill

and re-aligning of the key development planning institutions. All these were regarded as

prerequisites to improving development planning efficiency in Zambia.

Page 40: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 29

4.1.7 Monitoring and Evaluation Frameworks

Progressively, under the M&E component, major strides were registered in a number

of areas. Significant progress had been made in the development of a comprehensive

framework to monitor National Development Plans. Harmonized tools, templates and

performance indicators for reporting of progress had equally been developed. Equally of

significance was the aspect of having M&E functions institutionalized in all MPSAs. In

addition, the issue of capacity building for M&E practitioners was noted to have been

progressively pursued with the establishment of an automated reporting system having reached

an advanced stage.

4.2 Implementation Challenges of the Previous NDPs

Zambia like any other developing country has had many different planning tools

developed and applied in its development quest. Despite all the developed tools being in place,

the national development planning processes have always been associated with various

challenges. These challenges mainly were on weak linkages between the national development

plans, budgets and programme implementation and lack of synergies in the various planning

processes.

Weak linkages between national development plans and national budgets are mainly

attributed to the failure of the latter to be informed by the former in the formulation and

implementation processes. The weak linkages had to do with the absence of a clear planning

system for identification, selection and appraisal of programmes before inclusion into the

NDPs. The lack of a clear planning system for effective alignment of the national budgets to

the NDPs was a great factor to the failure to appropriate financing of the programmes

articulated in the NDPs.

On the other hand, the lack of synergies in the various planning processes is an attribute

of the absence of the robust planning system to synchronize and link the national budgets to

Page 41: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 30

National Development Plans. The difficulty to create synergies among the different tiers of

Government, that is, national, sector, provincial and district levels gave rise to fragmentation

in planning processes. For instance, priority sectoral plans for agriculture, education and roads

which were prepared by MPSAs were observed to have been done with no proper links to the

NDPs (Mulungushi, 2007).

Furthermore, inadequacy provision of guidance on development planning also led to a

gap between national development planning and the processes at the lower levels of

government. In addition, the consultative process and structure at the national, provincial and

district level, though supported by policy guidelines did not even have legal backing in the

sense that no legislation was passed for such arrangement, thus hampering the effective

implementation, monitoring and evaluation of the NDPs. This consequently compromised the

impact of these plans on economic growth, employment creation and poverty reduction.

Specifically, the FNDP, SNDP and R-SNDP which were structured as both policy and

investment plans had their own challenges. Specify challenge bordered on the plans having too

many designated priority sectors which resulted in resources being thinly spread with minimal

impact. This was further compounded by weak inter-sectoral coordination and programme

linkages leading to poor implementation sequencing and, ultimately wastes of resources (7th

NDP Concept note, 2016)

Further the support of FNDP and SNDP/R-SNDP through the annual budgets and

medium-term expenditure framework was identified as a major implementation challenge

because the amounts of funding and unpredictability of budgetary releases negatively affected

programme implementation and achievement of desired outputs and outcomes. Detailed

analysis of expenditures revealed that despite the NDPs having increased allocations to sectors

targeting key sector development programmes, the allocations in the budgets were not

Page 42: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 31

sufficient to implement most of the programmes. Equally, delays to avail funds on time to

MPSAs presented a further challenge in programme implementation. In addition, there was

noticeable mismatch between the programmes contained in the annual budgets and NDPs and

this was evidently clear to an extent that even when resources were released for programmes,

there were variations that led to resources being expended on non-core activities of the NDPs.

Poor uptake of results was another challenge in the NDP implementation as this led to

implementing agencies not having timely policy guidance with regard to the implementation

of the NDPs. The major attribute to this challenge bordered on poor appreciation of monitoring

and evaluation in MPSAs for internal use, coupled with fragmented systems within and

between MPSAs. With this challenge, data was untimely produced or simply not adequately

aligned to the information gaps of the users.

The lack of a national programme/project appraisal system was another challenge in

the NDP implementation. This was extremely significant in the effective implementation of

the previous NDPs. The absence of the system resulted in weak prioritization of

programmes/projects and this negatively impacted on programme implementation. The

delayed implementation of projects resulted in escalation of costs, as most projects overran

their completion dates, thereby putting pressure on the budget.

Although the NDPs provided for M&E frameworks and systems to support decision-

making processes, the frameworks and systems presented a challenge in that these were not

able to provide data as expected as most sectors lacked or had limited and weak Management

Information Systems (MISs) that made it difficult for information to be available on timely

basis.

4.4 Lessons Learnt from Implementing Prior NDPs

Lessons learnt from implementing prior NDPs greatly enlightened the need for effective

links between policy cycle and financial cycle. Consequently, this institutional weakness

Page 43: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 32

reveals the challenge of non-alignment of the budget planning, programming and expenditure

with NDPs and the Vision 2030, thus posing an adverse effect on PFM efforts, budget

credibility and development results.

The failure to link budget planning to National Performance Framework (NPF)9

presented some difficulties to quantify and link outcomes and impact to Vision 2030 as

intended. This was more pronounced in the efforts to track implementation progress towards

realizing the Vision 2030 objectives. With the development of NPF, it is expected that policy

cycle and strategic vision is going to be enhanced through the establishment of strong linkage

between defined National Outcomes and Key Performance indicators in the NPF with NDP

and the Vision 2030 (Mwenda, 2016). In Annex 3, the main components of the NPF are

graphically depicted.

As for budget expenditure, it was learnt that expenditure being linked to activity and

less on observed outcomes and impacts of previously implemented programmes/projects

provided a difficulty when comparing expenditure against achievements i.e. outcomes and

impact on the NDP and the Vision 2030. This scenario made it difficult to ascertain from the

budget programmes and activities if MPSAs were fully implementing the outcomes outlined

in the NDP.

The under - utilization of evidence-based policy making in the entire process reveals

the outright lack of documented analytical status of implemented programmes and projects, as

well as the poor utilization of recommendations from programme review process. This mainly

emanated from ineffective M&E data collection and dissemination as this had a greatest impact

on M&E processes in situations where data collection is manually generated and fragmented.

9 National Performance Frameworks describe what the Government wants to achieve over a period of time, by

articulating more fully the Government purpose, strategic objectives and expected outcomes. They help to sharpen

the focus of Government and enable the priorities to be clearly understood and provide a clear structure for

delivery.

Page 44: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 33

This situation makes the flow of data and information from sectors to be infrequent, largely

incomplete and sometimes inaccurate due to lack of documented process and guidelines.

Equally the lack of multi-year evaluation plans and evaluation policies is one lesson as

an attribute to the uneven and irregularities in M&E across government. With this scenario,

some sectors were well advanced in monitoring and had well developed indicators emphasizing

more on monitoring with very limited evaluations carried out. This was more attributed to

weakness in M&E capacity (in terms of numbers and skills) across sectors.

In the analysis of soft factors10, monitoring and evaluation tools are crucial for effective

functioning and implementation of M&E-MIS. This called for identification, appointment and

relevant capacity development of M&E-MIS champions in every sector by instituting change

process and promotion of the paradigm shift from viewing M&E functions as an additional

workload to being an important management tool geared towards promoting change and

realizing institutional and national goals and objectives.

In the absence or weak programme implementation, it was difficult to note tangible

outcomes in the programme implementation process. In some circles, poor implementation and

accountability systems at various levels were singled out as major factors to discrepancies in

outcomes.

In spite of most of the MPSAs having institutionalized M&E functions in their

structures, it was learnt that the issue of capacity (both human and institutional) in the M&E

and MISs in most MPSAs is critical in the development planning process. With regard to

institutional lapse in terms of monitoring and evaluation aspects, it was learnt that this was a

key issue in almost all M&E institutionalized MPSAs and this was attributed to institutions

10 Soft factors of Monitoring and Evaluation refer to psychological and latent elements (such as staff morale,

skills development and career progressions, motivation, commitment, respect for M&E leadership etc.)

Page 45: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 34

being more preoccupied to a greatest extent on collecting data and tracking and reporting on

inputs, activities and outputs, and to a lesser extent, on undertaking results analysis.

Evidently, it was clearly informed that MISs were key tools to the provision of basic

information to enable decision makers at every stage of the programme implementation process

to make evidence-based decisions on policy and programming choices and budget

requirements.

It was further learnt that the alignment of sector plans and programmes with the

National Development Plan tended to be difficult in view of budget allocation being activity

based. This compounded the problem of variations in programmes contained in the NDP and

those in the Budget, thus providing a difficulty to ascertaining as to whether budget

programmes and activities were fully being implemented towards the achievement of outcomes

as outlined in the NDP.

The weak challenge function during the programming phase of the budget was learnt

to have a lot of implication in the development planning process. This was attributed to most

of the MPSA activities or programmes being pushed through into the budget without first being

screened to ascertain whether these activities or programmes were in line with the development

aspirations of the nation as articulated in the NDP.

On the unified methodology, cross-sectoral processes, it was learnt that the

development of Government-Wide MISs was key in the development planning processes as

they provide support to ensuring comprehensive capture of data from disbursements-

expenditure outputs and results. The development of the Government-Wide M&E system is a

key mechanism by which the Government policies and programmes can be monitored and

evaluated at various levels in an inter-linked, standardized and time specific manner.

Additionally, reliable data for use in planning was learnt to be cardinal if validity and

relevance of information used is ensured in the development planning process of the NDPs.

Page 46: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 35

The examination of the M&E system showed that there was very little or no prioritization of

statistical data in informing decision making and plans in the development planning process of

the NDPs. In this respect, it was of paramount importance to prioritize the need for reliable

data that measure the variables that feed into the plan so that planning is not only scientific but

authentic. It was important therefore to make sure that the country has reliable data collected

and analyzed so as to effectively inform the development planning process of the NDPs.

Despite the recognition that statistics were vital in any development process for

planning, programme implementation, and monitoring and evaluation of progress, it was learnt

that this was not the case in Zambia. This is due to the fact that the Central Statistics Office

(CSO)11 was found not equal to its task as various Government ministries, departments, and

agencies were equally producing and disseminating sectoral data.

More critically, the production of statistics for outcome and impact indicators through

Censuses and Surveys by CSO and the production of mostly unstructured data by MPSAs from

their routine work with little involvement of CSO often lead to erroneous, inconsistent input

and output indicators. This results in the non-availability of timely and quality statistics to serve

as evidence for policy formulation, planning, and decision making in national development.

With these lessons above, it can be evidently stressed that evidence-based development

planning requires taking a holistic approach that is collective in nature if it is to bring about the

overall development objectives of the country. This approach requires an institutional design

of an evolving network that is flexible, open and capable of restructuring itself over time.

11 CSO is the focal government agency responsible for the development and management of official statistics

and making the data accessible to government organs, business community and public at large.

Page 47: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 36

4.3 Assessment of the Status and Progress of NDP Process in Zambia

In pursuant to the constitutional requirement under Article 118 (as amended by Act no.

20 of 2009) of the Constitution of Zambia12, the Government undertook some radical steps

towards meeting some of the essential features of an accountable and robust development

planning system. The National Planning and Budgeting Policy (NPBP) was the first ever policy

developed and aimed at strengthening the coordinated approach in undertaking national

development planning and budgeting processes in Zambia. The policy was anchored on the

vision of “a coordinated and integrated development planning and budgeting system that is

responsive, transparent, and accountable and results oriented” (NPBP, 2014).

4.3.1 Assessment of Status on NPBP Objectives

The NPBP objectives emphasized much on the integration of the national planning and

annual budgeting processes with greater results-orientation and strengthening of synergies in

the various planning processes. The other objectives centered on facilitation of more

participatory/ decentralized development planning and budgeting processes and the

enhancement of budget credibility. Key to the study is the objective to do with the facilitation

of greater evidence- based decision making in development planning and budgeting (NPBP,

2014).

In the policy, there is a provision for the development of an institutional framework to

provide for the formulation, approval, implementation, monitoring and evaluation of long term

and medium term NDPs. This is more to do with institutional linkages that are significant to

the national development planning efficiency. The integration of NDPs with Government’s

MTEF and annual budget formulation and execution processes is another key aspect in policy.

12 Article 118 required the enactment of the budgeting and planning legislation to provide for matters that relate

to the medium term and long-term development plan and annual budget as an enhancement strategy to

development planning in Zambia.

Page 48: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 37

It additionally consists of a provision for the division of responsibilities and powers in the

planning and budgeting processes between the various arms of the executive, the legislature,

local authorities and non-state actors13 (NPBP, 2014).

With the anticipated enactment of the National Planning and Budgeting legislation, the

legal basis for aligning and integrating planning and budgeting processes would be much

possible. Once the legislation is in place, this will further enhance the strategic and priority

development setting and transparency, accountability and good governance in appraisal,

selection and implementation of development programmes.

4.3.2 Assessment of Progress on NPBP Objectives

As part of the assessment strategy, comprehensive analysis of the development

planning objectives, strategies and implementation in terms of status is provided therein. The

analysis brings out salient features of each objective in terms of the progress made towards its

achievement.

Objective One: Integrate National Planning and Annual Budgeting Processes

The objective focused on the integration process of key frameworks in planning and

budgeting. The most identifiable among the frameworks are Activity Based Budgeting and the

Medium-Term Expenditure Framework. The objective is consequently premised on three

strategies and these include harmonization of the programme classification used in

development planning with that used in the annual budgeting process, strengthening inter and

intra institutional arrangements for linking planning and budgeting at all levels and expansion

of the scope of Activity Based Budgeting (ABB) to Output Based Budgeting (OBB).

13 An individual or entity that is not part of the public sector

Page 49: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 38

The Government initiated the ABB as a budgeting system in 2003. The ABB was the

“first generation” of budget reforms undertaken when formulating the 2004 Budget. This

entailed moving from incremental “line item budgeting”- where the focus was on the inputs to

be bought by MPSAs to ABB, where the focus shifted to programmes and activities, supported

by the spending plans of MPSAs. With the ABB process, the annual budget formulation

process began to be undertaken in a more strategic, medium-term context by producing a

“Green Paper” 14containing a rolling three-year MTEF.

The Introduction of MTEF in 2004 as the basis for budgeting in Zambia re-emphasized

the direction for improving public expenditure through better prioritization of programmes and

achieving better value for money spent. The major thrust for MTEF was on its emphasis for

planning of development to target diversification through increased public investment in

economic and social infrastructures and an improved legal framework for Public Financial

Management (PFM).

The initiation of the ABB and MTEF were observed to have laid the groundwork for

linking planning and budgeting processes by utilizing the planning and budgeting module

embedded in the IFMIS. The assessment found that the system had only been fully

implemented in 38 sites out of the 48 originally planned (IFMIS Report, 2010). As a result, its

effectiveness proved difficult to determine as the realized plans being actualized in the

implemented sites could not be assessed at the stage. The delay to effect the integration of the

planning and budgeting processes in the IFMIS were anchored on issues with regard to the

chart of accounts embedded in IFMIS that needed to be re-defined first so as to be in line with

that for development planning.

14 A consultative document through which the public are requested to submit comments and submissions for

incorporation into the budget for the subsequent years

Page 50: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 39

Another Government attempt to integrate the budget with national development

planning process was in the shift from ABB to OBB in 2015. This shift was aimed at enhancing

the budget’s role as a vehicle to spearhead development and deliver public services. It was

mainly initiated for the purpose of enhancing the implementation of various developmental

projects and service delivery across the country. The current ABB system, which Government

had been implementing since 2004, had posed challenges especially with regard to the

management, analysis, reporting and performance of the budget. The shift to OBB from ABB

was to enhance the process through which Government agencies were to be funded on basis of

delivery of planned and actual outputs and outcomes (MoF, Budget Call Circular, 2015).

The practicality of the shift from the ABB to OBB was first piloted in the Ministry of

Education in the 2016/17 budgeting process. This was with the possibility of rolling it out to

other MPSAs in the subsequent budgets and this was much dependent on the outcome of its

implementation in the pilot institution.

Objective Two: Strengthen Synergies in the Various Planning Processes

In realizing the synergies in various planning processes, the objective therefore takes

this into consideration and anchors its achievement on three strategies that include the

integration of planning and budget coordinating structures at district, provincial and national

levels; legal establishment of planning and budget coordinating structures at district, provincial

and national levels; and provision of clarity and periodic specification of the functions of each

of the functions required to planned and budgeted for.

Progressively, the Government heeded to the need to re-align institutions to promote

synergies in the planning, implementation, monitoring, evaluation and coordination of national

development programmes and projects. To this effect, the Ministry of National Development

Planning (MoNDP) was created and separated from the Ministry of Finance setup and given

the mandate coordinate among others; the setting up of the national vision, goals and

Page 51: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 40

development priorities, stimulation of consensus among various stakeholders, formulation of

medium term development plans to promote integrated development at national, sectoral and

regional levels and the identification, design and appraisal of public investments to facilitate

attainment of the country’s development aspirations (MoNDP, Re - Organization Report,

2016).

To execute the above mandates, the Ministry’s institutional framework was also

provided. Among the key departments in the planning processes that were set up were the

Development Planning Department (DPD) and Public Investment Planning Department

(PIPD).

The DPD was designated the central role for managing and coordinating the

formulation and implementation of national development policies, strategies and programmes

so as to guide the country’s socio-economic development process while the PIPD was

mandated with the responsibility of providing oversight in the planning, designing and

appraisal of national public investment programmes so as to facilitate development and

effective implementation of programmes and projects.

To enhance synergies at district, provincial and national levels, planning and budget

coordinating structures were equally integrated. At the time of the assessment, this strategy was

well advanced in that all provinces had functional Planning Units in place as part of the

objective. The pivotal role of the Planning Units was to enhance the planning, monitoring and

coordination of all development programmes at provincial and district levels. This was more

on the strategy to localize planning in sectors and provinces so as to enhance the ‘bottom-up’

approach and participatory planning in the development planning processes in Zambia

(Development Planning Report, 2015).

The strategy to legally establish planning and budget coordinating structures at district,

provincial and national levels was assessed to be well advanced and very much embedded in

Page 52: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 41

the draft National Planning and budgeting legislation. These structures pertained to the already

existing structures in the form of National Development Coordinating Committee (NDCC),

Provincial Development Coordinating Committee (PDCC) and District Development

Coordinating Committee (DDCC) structures.

The NDCC is designed as the national forum for coordinating the planning,

implementation and monitoring of development programmes and projects with the mandate to

oversee the operation of the National Development Planning framework as envisaged in the

National Planning and Budgeting legislation. In the development planning processes, the

NDCC has the mandate to perform the function of approving and issuing guidelines and

subsequent revisions thereof, for the formulation of long and medium term national

development plans, and the medium term and annual budgets.

As for the PDCC, its mandate is to coordinate and monitor the formulation,

implementation, monitoring and evaluation of Provincial Development Plans (PDP), and the

medium term and annual budgets and also to harmonize the long and medium-term

development plans and medium term and annual budgets inclusive of the Provincial Public

Investment Plans (PPIPs). This would similarly apply to the DDCC though very much

functional at the district level.

To provide operational legality, respective roles and responsibilities of key stakeholder

institutions are clearly outlined in the draft legislation. Annex 2 presents an illustration of the

institutional and consultative framework for development planning.

Objective Three: Facilitate Participatory/ Decentralized Development Planning

and Budgeting Processes

This objective has its strategies linked to those envisaged in the Decentralization policy

initiated by Government in 2002. These strategies are anchored on the objective in the

decentralization policy that is strategically focused on the empowerment of the local

communities through devolution of functions from the centralized structure to that of

Page 53: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 42

decentralized levels and matched with resources to enable efficiency and effective delivery of

services (National Decentralization Policy, 2007). To fulfill the objective, issues of

accountability and transparency in the management and utilization of resources at district levels

are found to be of utmost importance.

The capacity development strategy at the local councils and communities’ levels will

focus on enhancing development planning, financing, coordination and the management of

service delivery. The aim is to enable councils to effectively carry out the development function

at the local level. The introduction of an integrated budgeting system specifically for district

development and financial management is one key strategy of the objective (Decentralization

Implementation Plan, 2009)

On the strategy to facilitate participatory/ decentralized development planning and

budgeting processes, this lays on strengthening the existing structures for state and non-state

actor participation in planning and budgeting processes. Within the precepts of the NPBP,

respective roles and responsibilities of other key stakeholders such Cabinet, Parliament,

Cabinet Office, Ministry of Finance, Ministries, Provinces and Other Spending Agencies and

Non-State Actors are clearly distinguished.

Cabinet, for instance, is mandated with the responsibility to provide policy direction

and approval of Policies, Plans and Budgets. As for Parliament, the main responsibility is to

provide the oversight functions to the policy implementation process. On the other hand,

Cabinet Office is tasked with the responsibility of providing overall policy guidance and

monitoring implementation of the policy.

Prior to the formation of the Ministry of National Development Planning (MoNDP),

Ministry of Finance (MoF) initially was tasked with the responsibility to facilitate and manage

the NPBP. In addition, MoF was tasked to provide policy direction to MPSAs on the

implementation of the policy as well as its implementation. It also had the mandate to

Page 54: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 43

coordinate the national vision, goals and development priorities and stimulate consensus

among various stakeholders. In the new dispensation with the creation of the separate Ministry

responsible for national development planning, the MoF mandate is more on the financing

development programmes as provided in the development plans as those functions of

development planning are more embedded in the mandates of the MoNDP.

On the other hand, Sector MPSAs are tasked with the mandate to prepare and

implement sector specific plans and budgets in line with the policy. The role of Non- state

actors is defined as that of providing complementarities to the implementation, monitoring and

evaluation of the NDP programmes (NPBP, 2013).

Objective Four: Enhance Budget Credibility

This objective is as embedded in the Constitution of Zambia under article 118 earlier

cited. The strategy lays on ensuring that national development plans inform the budgeting

process. This strategy is anchored on the MTEF whose green paper provides an overall medium

macro/fiscal resource framework and expenditure policies. This is one of the positive

developments in the process.

With regard to strengthening capacity to undertake ex-ante appraisal of capital projects

before being included in the plans and being allocated resources in the annual budget, this

strategy is encompassed in the PIPAM Framework. The framework is clear on the appropriate

linking of the process of appraising and selecting projects to the budget cycle regardless as to

whether the project evaluation cycle run on a different timetable (PIPAM, 2016)

The strategy to strengthen inter and intra institutional arrangements for linking planning

and budgeting at all levels is reinforced by the creation the Ministry of National Development

Planning to coordinate the national vision, goals and development priorities and stimulate

Page 55: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 44

consensus among various stakeholders and in liaison with the Ministry of Finance on the

budgeting matters at all levels.

With the strategy to build capacity (both human and institutional) in various

development institutions, this is being pursued vigorously and on-going. So far about 30 key

staff in various MPSAs had been trained in project planning and appraisal techniques and these

were to act as trainers of trainees as part of the internal capacity building strategy.

Objective Five: Facilitate Greater Evidence - Based Decision Making in

Development Planning and Budgeting

This objective is anchored on the enhancement of the effective use of

information/statistics in the planning and budgeting decision-making strategies. Further, this

includes the integration of results from planning and budget reviews and evaluation processes

into the preparation of MTEF and annual budget and subsequent development plans at all levels

of Government (NPBP, 2014)

The strategy to enhance the effective use of information/statistics in planning and

budgeting decision making is underpinned in the PFMRS and the Concept Paper on the

National Integrated Management Information System (NIMIS Project) 2013 – 2018. In the

PEMRS, it is informed that an appropriate M&E system would enable evidence-based planning

and decision-making in the use of public finances. The Concept Paper on the other hand,

underscores the need for a coordinated outcome and results-based approach to development

(Concept Paper, 2013).

The development of the National Strategy for the Development of Statistics (NSDS) is

another tangible progress in the development planning process. The NSDS, which is a five-

year plan (2014-2018), seeks to remedy the foregoing by coordinating and harmonizing the

production and dissemination of official statistics in the country. It provides for, inter alia, the

framework for partnership amongst producers, users’ and suppliers of statistics; and it

Page 56: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 45

envisions where producers and users of statistics should be in five years’ time by clearly

spelling out the Roadmap and Milestones (NSDS, 2014)

Regarding the strategy to integrate results from planning and budget reviews and

evaluation processes into the preparation of MTEF and annual budget and subsequent

development plans at all levels of Government, this is premised on the development of the

Government Wide - M&E – MIS. The pursuit for a Government Wide - M&E - MIS is a

response to Government’s need to track implementation progress towards realizing the

objectives of Vision 2030 and subsequent NDPs.

5.0 Seventh National Development Plan (2017-2021):

Formulation Processes and Implementation Frameworks

In the process, many developing countries globally have since developed or are

developing long term visions to guide their steps towards these development objectives. These

long-term visions are characterized by stronger ownership and a more consultative and

participatory process involving a broad spectrum of stakeholders, including civil society, the

private sector, and development partners (UNECA, 2016).

The first test of the NPBP with regard to development planning in Zambia was in the

preparation of the Seventh National Development Plan (7th NDP), 2017 -2021. Formulation of

the 7th NDP followed the key stages of development planning as outlined in the NPBP. The

formulation processes for the 7th NDP followed an appropriate mix of top-down and bottom-

up approaches. The process was anchored on the principles of participatory, credibility,

sustainability and responsiveness to development issues affecting the nation (7th NDP Concept

Note. 2016).

Page 57: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 46

The 7th NPD development planning process departed from the sectoral-based planning

to an integrated (multi-sectoral) approach. It was anchored on the theme “Accelerating

development efforts towards Vision 2030 without leaving anyone behind”. The goal of the 7th

NDP in line with the theme emphasize on the creation of a diversified and resilient economy

for sustained growth and socio-economic transformation driven, among others, by agriculture.

The formulation process of the 7th NDP was guided by the National Planning and

Budgeting Policy of 2014, while the Decentralization Policy of 2014 provided the principles

of implementation” (7th NDP, 2017). The formulation process was further informed by the need

to harness the demographic dividend15 in view of Zambia’s youthful population (7th NDP,

2017).

The realization of the 7th NDP goal is premised on a number of developmental

outcomes. The key outcomes include economic diversification and job creation; reduction of

poverty and vulnerability; reduced developmental inequalities; enhanced human development;

and the creation of enabling environment for a diversified and inclusive economy (7th NDP,

2017).

The perception is that the 7th NDP will bring about “inclusive development without

leaving anyone behind”16 and achieving more with fewer resources, through integration and

coordination of developmental efforts. These are to be achieved by taking into account regional

and global development agendas, such as the Regional Indicative Strategic Development Plan

15 The demographic dividend refers to the economic benefit a society enjoys when fertility and mortality decline

rapidly and the ratio of working-age adults significantly increases relative to young dependents.

16 This was one of goals of the UN post-2015 development agenda meant to drive transformation shifts to move

from reducing to ending extreme poverty, in all its forms globally by ensuring that no person – regardless of

ethnicity, gender, geography, disability, race or other status – is denied basic economic opportunities and human

rights.

Page 58: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 47

(RISDP),17 African Union Agenda 2063, Sustainable Development Goals (SDGs) and the

Common Market for Eastern and Southern Africa (COMESA) protocols.

5.1 Conceptual Framework of the 7th NDP

The 7th NDP is premised on the Theory of Change which is a model that articulates, in

a systematic way, how strategies, activities or programmes contribute to a set of specific

outcomes through a series of intermediate results. It describes the pathway through which

change will come about. In the context of the 7th NDP, this shows how the economy is going

to be diversified; what results will be needed to attain diversification; and what interventions

will bring about these results. It also describes the underlying assumptions and conditions

necessary to bring about this change (7th NDP, 2017)

Within the scope of the 7th NDP, the ToC model has been elaborated in greater detail

in the NPF with a view to translate the Vision 2030 into strategic objectives and long-term

outcomes through various pathways. The 7th NDP thus draws from the long-term outcomes

outlined in the NPF which form the basis on which medium-term outcomes of the Plan are

anchored. The ToC also provides a clear framework for stakeholder consultation.

Building on the ToC and recognizing the multi-faceted and interlinked nature of

sustainable development, the interventions in the 7th NDP are to be tackled simultaneously

through an integrated multi-sectoral development approach to planning. The approach takes

recognition of the fact that the world is a complex system; it is linked through trading,

investment and transport and communications systems to events in other parts of the world.

This approach is supported by the recommendations of the 2015 Study on “Harnessing

Demographic Dividend: The future we want for Zambia”. In this view, the approach, therefore,

requires timely, strategic, targeted and simultaneous investments in various sectors of the

17 The RISDP is a comprehensive development and implementation framework guiding the regional integration

agenda of the Southern African Development Community (SADC) over a period of fifteen years (2015-2020)

Page 59: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 48

economy through integrated efforts that will translate policies into equitable, cost-effective

interventions that leave no one behind (7th NDP).

Using an integrated approach, the 7th NDP is expected to create an environment for the

domestication of Sustainable Development Goals, AU Agenda 2063, RISDP and other

international, regional, multilateral and bilateral development strategies. It is further

anticipated that by taking this approach for 7th NDP, this will be a springboard to the promotion

of partnerships in a transformative way (7th NDP).

5.2 Formulation Process of the 7th NDP

The formulation process started in 2015 - two years prior to the end of the preceding

NDP. This was in line with the formulation process that stipulated the timeline in which the

process was to commence, that is, two years prior to the expiry of the existing plan. All the

stages/ processes undertaken in the formulation process of the 7th NDP graphically depicted in

Annex 4.

Stage One – Issuance of National Policy Statement

The first action in the formulation process was the issuance of national policy statement

on development by Cabinet. The policy statement provided policy direction and strategic focus

on the development of the 7th NDP. As a matter of procedure, the Concept Note, Roadmap and

Organizational Framework had to be prepared and subsequently approved by Cabinet before

full commencement of the process.

Stage Two – Review of National Development Policies

In the second stage, reviews of national development policies and programme

(including situation analysis and recommendations from M&E processes) were conducted. The

reviews considered the NDP progress reports, Evaluation reports, Demographic Dividend

Report among others and the outcome culminated into the Issues paper.

Page 60: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 49

Stage Three – Public Consultations

Following the approval of the issues paper, concept note, roadmap and organization

framework by Cabinet, the 7th NDP formulation process was officially flagged off by the Vice

President. The immediate activities after the flagging off were public consultations which were

undertaken concurrently with the formulation of macro-economic and fiscal frameworks. The

key stakeholders consulted included economic and social sectors, provinces, districts, private

sector, interest groups, civil society and political parties.

Consultations were supposed to have been based on communication strategies designed

for the purpose. However, this was not the case because consultations were observed to have

been done in an Ad Hoc manner with the concept note being used as the consultation document.

There were also key challenges in the consultation process that mainly bordered on

meeting the technical capabilities of the teams and inadequate resources to undertake

consultations as planned. As for resources, it is contended that “where there are inadequate

resources in the implementation process, there is prone to be implementation problems”

(Makinde, 2005). In this view, resources may include both human and material. These may

pertain to the adequacy and skillfulness of personnel mandated with the execution of the

activities and the relevance and adequacy of information in the implementation process. This

was mostly noticeable in the formulation process of the 7th NDP. This situation greatly affected

the process and thus created an ‘Implementation Gap’18 in the process. With regard to the 7th

NDP, the gap, in some instances, resulted into activities been undertaken way beyond the

timelines.

18 The implementation gap arises when there is a sizeable gap between a policy decision and its implementation.

It is this gap that most often results in the policy implementation being delayed or to its eventual failure.

Page 61: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 50

Stage Four – Developing the Plan Zero Draft

Notwithstanding the challenges above, the drafting of the plan eventually commenced

in 2016 and this ultimately led to the production of a zero draft for the plan with

focus/strategies, priority programmes defined. The plan zero draft took into account issues

from the consultative process. Programme briefs and costing were also developed, while

Districts and Provinces also articulated their contextualized plans. Regarding the preparation

of the development plan focus/ strategy, a shift from sectoral approach to Integrated or multi-

sectoral with a regional perspective was advocated.

The multi-sectoral approach was advocated for the 7th NDP. This was under the

perception that sectoral approach had failed to promote horizontal and vertical integration in

formulation and management of NDPs. The perception was that sectoral approach resulted in

wastage of resources by thinly spreading them across sectors. There were also the issues of

limited or no linkages between sectors to support common objective. This promoted policy

inconsistencies as various policies were viewed from sector standpoint rather than holistically.

This made planning difficult as sector programmes/projects were not coordinated but was

presented only in a form of a “shopping list” (Gumboh, 2016)

The multi-sectoral approach, on the other hand, was provided the opportunity to

enhance the promotion of local participation in development planning process. This however

provided for paradigm shift in development management through structural changes in design,

targeting, and implementation of programmes and reduction in the mismatch between

economic growth numbers and poverty levels (7th NDP Concept note, 2016). The approach

required priority areas of focus to be based on regional comparative advantages so as to

promote economic diversification and reduce regional development imbalances.

In the multi-sectoral approach process, certain pre-conditions had to be met to fulfill

the objective. These bordered on the accelerated implementation of key reforms on land,

Page 62: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 51

financial management, institutional reforms, e-Government, planning and budgeting, private

sector development, National Statistics Development Strategy, re-organization of consultative

bodies, full decentralization (fiscal and devolution), stronger political support and

communication strategy, and incorporation of the Sustainable Development Goals (SDGs) into

the 7th NDP. These were perceived as key elements for successful implementation of the 7th

NDP under the integrated approach. At the time of the assessment, most of these reforms were

work in progress with significant strides made on most of the pre-conditions.

Another key component identified in the development planning processes was that of

Development Cooperation. This implied the engagement of Cooperating Partners in the process

by taking into consideration their contribution to development programmes of the country

through financing and technical assistance in the form of loans and grants (Lupunga &

Kayekesi, 2015).

The rationale for development cooperation was anchored within the context of Vision

2030 which articulates the nation’s long-term development path and objectives. In the

formulation process of a Development Plan, identification of the overall resources is a core

prerequisite for successful plan implementation. This entails costing a plan and coming up with

resource mobilization strategies for its financing.

Unlike processes for the Fifth and Sixth National Development Plans that took a

sectoral approach, the change to integrated development approach for the 7thNDP required re-

alignment of development cooperation to conform to the new approach. Changes were

expected in the structure of development cooperation in areas of policies, procedures and

practices that provide for internal government engagement and engagement with cooperating

partners and the existing Aid Policy and Strategy (Lupunga and Kayekesi, 2015).

Page 63: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 52

Stage Five – Programme and Project Appraisal

The development of the Public Investment Planning, Appraisal and Management

Framework in 2015 was one of the key aspects under the integrated planning and budgeting

component in the NPBP. Its eventual review in 2016 to the Public Investment Planning,

Appraisal and Management (PIPAM) Framework, incorporating guidelines and procedures,

not only provided a catalyst in the preparation process of the 7thNDP but a mechanism for

efficiency and effective Public Investment Management (PIM) in Zambia (Gumboh, 2016).

The framework, whereas advocating for robust institutional procedural approach to

public investment planning, appraisal and management, also placed strong emphasis on

creating opportunities for capacity building within the key infrastructure-linked institutions so

as to build the internal skills and understanding of the processes and procedures for effective

implementation of public investment. To this effect capacity building sessions on the PIPAM

for key technical persons were held as a strategy to enhance their capabilities to comprehend

public investment planning, appraisals and management techniques as part of the development

planning process (PIM Concept Note, 2015)

Stage Six – Alignment of District / Provincial Indicators to NDP Indicators

This stage mainly enhanced further stakeholder consultations on the plan structure and

strategic focus. It is the stage where provincial programmes and district indicators are re-

aligned to NDP indicators prior to being incorporated into the draft NDP.

Stage Seven – Draft Plan (With various Options)

Technically, the validation and technical finalization of the draft plan was supposed to

have been undertaken in the 2016 but this was not possible due to internal challenges. This

further delayed the transmission of the Draft NDP (with various lay out options) to Cabinet

approval. The result of the delay created another Implementation Gap in the process.

Page 64: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 53

Stage Eight – Draft NDP/Green Paper

Initial intention was to have the Draft plan and the Green Paper tabled before Cabinet

at the entry of 2017. A lot of internal challenges made the intention not to materialize. The

challenges were mainly on technical, financial and political aspects. The delay to approval of

the Plan prior to the start of the plan period created a further gap in implementation process.

Its eventual tabling and approval by Cabinet paved the way for its launch.

Stage Nine – NDP Launch

In line with the development stages specified in the NPBP, the Plan was finally

launched by the President on 21st June 2017. As per requirement, the Final plan will have to be

submitted to the National Assembly as part of the documentation to be used to support the first

budget fully prepared by the administration.

Attainment of the development outcomes contained in the Plan requires having in place

a robust coordination framework to provide guidance in the implementation of the Plan. In

addition, institutional arrangements need to be clarified together with assumptions upon which

the success of the Plan rests. Implementation and coordination of the Plan will equally be based

on the integrated approach with a view to ensure that sectors are not only well coordinated but

are mutually reinforcing each other in the process. The coordination and implementation

approach link the vision, priorities, people’s aspirations and the physical institutions. Through

an elaborate implementation and coordination framework, a system for accounting for

development results will be established to help in informed decision-making. This will shape

and guide the entire management of the 7th NDP involving the state and its institutions and

individual players in organizations or communities.

5.3 Implementation Framework of the 7th NDP

The 7th NDP will be implemented largely through the same institutional arrangements

as for the previous NDPs with the PDCCs and DDCCs continuing to perform their functions

Page 65: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 54

as earlier stated under the formulation process. There is only the inclusion of the Ward

Development Committees (WDCs) at the local level, while at sector level, Sector Advisory

Groups (SAGs) have been re-aligned to Cluster Advisory Groups (CAGs), which shall be an

assembly of sectors sharing common overall objectives. At the central level, the Cabinet

through the National Development Coordinating Committee (NDCC) will continue playing an

oversight role.

In addition to grouping advisory bodies (CAGs, PDCCs, and DDCCs) based on

development outcomes, institutions jointly addressing a particular development outcome will

come up with one integrated implementation plan. The Institutions are further expected to

elaborate inter- and intra-sectoral synergies that will result in complementary efforts towards

the implementation of various strategies under that development outcome. The relationships

among a host of institutions are to be clearly mapped and developed in a manner that promotes

reinforcement of outcomes by all the players.

In order to realize the aspirations of this Plan, the Government as part of the

implementation strategy will formulate a change management strategy to include change

management programmes aimed at bringing about mind-set change among all stakeholders,

including the general public. This is to involve packaging the integrated approach to planning

and implementing the 7th NDP and communicating the approach to stakeholders. Additionally,

relevant personnel are to be mobilized to work effectively with the coordinating entity, in an

effort to optimize technical benefits from the pool of knowledge and expertise available across

the Government to enrich the planning process.

5.4 Opportunities and Challenges

In the analysis for key objectives of the 7th NDP, there are number of opportunities that

the country can enhance its development planning processes in its effort to meet its national

aspirations.

Page 66: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 55

In the overall assessment of planning, budgeting and monitoring systems, challenges

and problems were identified which were detrimental to PFM efforts, budget credibility and

development results. These challenges were attributed to weak links between policy cycle and

financial cycle as a result of non-alignment of the budget planning, programming and

expenditure with NDPs and the Vision 2030. The assessment further revealed that in terms of

budget planning, the current set up of budget planning was not linked to any NPF.

There is therefore the opportunity to enhance the development of the NPF based on the

national strategic objectives that are defined from the national long-term Vision 2030. The

essence of the NPF is that it operationalizes the national long-term vision, by re-packaging long

term strategic objectives into the medium term. This is done by logically identifying and

interpreting the strategic objectives contained in the national long-term vision. In the absence

of the NPF, it is difficult to quantify and link outcomes and impact to Vision 2030. Even more

challenging is the difficulty to track implementation progress towards realizing objectives in

the Vision 2030. The development of the NPF is therefore expected to enhance policy cycle

and strategic vision through the establishment of a strong linkage between defined national

outcomes and key performance indicators in the NPF with NDP and the Vision 2030.

With regard to budget credibility, there is an opportunity to develop sector specific

performance frameworks (SPF) that will further enhance and improve alignment with the

MTEF, NDP and Vision 2030. What is of importance is the need for the government to fully

support the sectors to establish annual M&E plans based on SPF as this would contribute

towards systematic M&E of each sector strategic goals, objectives, programmes and projects.

The development of the annual M&E plans would help MPSAs to move away from activity-

based implementation and reporting to performance-based budget allocation, implementation

and tracking progress.

Page 67: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 56

There is also the opportunity for Government to consider Results Based Budgeting by

re-engineering the legacy systems so as to create the linkages between the policy and financial

cycle as well as planning and implementation which are fully aligned with NDP and Vision

2030.

There is greater opportunity for introducing evidence-based policy making19 approach

in the national development planning process in Zambia as this approach will further enhance

the identification of what would work by highlighting gaps where evidence of programme

effectiveness is lacking. This will enable policymakers to use evidence in making their

development and budget decisions.

Based on the fact that evidence-driven policy making relies much on systems to monitor

implementation and measure key outcomes, this will equally provide an opportunity for

government to enhance the development of a national M&E policy framework that would spell

out the M&E best practices, principles, processes, standards and procedures. These would be

underpinned by an implementation plan, M&E guidelines, manuals and tools for use or

adaption across government.

In order to enhance the process, there is opportunity for government to conduct capacity

development, training and sensitization across the sectors to institutionalize or embed adequate

utilization of M&E tools for Results Based Monitoring of the implementation process. What is

of importance is the need for the government to fully support the sectors to establish annual

M&E plans based on SPF as this would contribute towards systematic M&E of each sector

strategic goals, objectives, programmes and projects. The development of the annual M&E

plans would help MPSAs to move away from activity-based implementation and reporting to

performance-based budget allocation, implementation and tracking progress.

19 Evidence-based policymaking is a term often applied in multiple fields of public policy to refer to situations

whereby policy decisions are informed by rigorously established objective evidence.

Page 68: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 57

With regard to the “soft factors20” of monitoring and evaluation, there is an opportunity

for government to identify and appoint M&E-MIS champions every sector by instituting

change process and promotion of the paradigm shift from viewing M&E functions as policing

to being an important management tool geared towards promoting change and realizing

institutional and national goals and objectives.

Annex 5 provides the framework for evidence-based policy making in development

planning. The framework presents the five steps in Evidence –Based Policymaking based on

the Pew-MacArthur Results First Initiative. The framework suits well for governments to

follow to build and support a system of evidence –based policy making.

Regarding gender mainstreaming in the development planning processes, there are

opportunities for government to first assess the expected positive or negative impacts of gender

sensitive planning and budgeting, notwithstanding the possible impacts of such an initiative

before developing a framework for such purpose. Some of the possible impacts of gender

mainstreaming could include enhanced accountability of government to women’s rights,

increased transparency in planning and budgeting, enhanced participation and social control

over budget processes, policy effectiveness, cost-efficiency in programme implementation,

enhanced women’s empowerment and qualified participation in macroeconomic policy

debates. In addition to the envisaged positive impact, vis-a-vis, the enhancement of gender

mainstreaming, it would be important for government to undertake an assessment of the impact

of gender sensitive budgeting on the planning and budgeting process itself, including the legal

and institutional framework for budget and planning. Furthermore, it would be important to

20 Soft factors of Monitoring and Evaluation referred to psychological and latent elements (such as staff morale,

skills development and career progressions, motivation, commitment, respect for M&E leadership etc.) which

were observed to be generally lacking across the sectors though there were necessary factors for effective

functioning and implementation of M&E-MIS.

Page 69: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 58

indicate how the envisaged negative impact would be overcome or mitigated as envisaged in

the National Gender Policy of 2013.

With this paradigm shift in the development planning processes, there is also the

opportunity for the government to enhance good governance and a stable political environment

as these are necessary for sustainable development in that they promote an enabling business

environment, increased market confidence and attract foreign direct investment among others.

What is critical is for the Government to continue implementing policies that promote

transparency, accountability, citizen participation as well as strengthen governance institutions

as a stable political environment will give the country an opportunity to continue strengthening

its institutions to support growth and development and maximize the attainment of

development outcomes.

6.0 Conclusions and Recommendations

6.1 Key Issues

The study analyzed a number of key areas of development planning in Zambia. It

presented a chronological order of the status and progress made in enhancing development

planning processes with the view of providing opportunities for integrating accountability and

evidence-based policy making approaches in Zambia’s development planning processes.

Among the many issues identified in the report were those that bordered on strategic

formulation of macro-economic and fiscal frameworks and stakeholder consultations based on

communication strategies designed for the purpose. Also, there was the issue of the

development plan with a clear focus/ strategy to conform with the shift from sectoral approach

to Integrated or multi-sectoral meant to enhance the promotion of local participation in

development planning process. Another key issue identified in the development planning

processes was that of Development Cooperation. The development of the Public Investment

Page 70: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 59

Planning, Appraisal and Management Framework was also one of the key issues identified in

the development planning processes.

In terms of implementation strategy, the development of an integrated implementation

plan was one key issue identified. This pertained to the elaboration of inter- and intra-sectoral

synergies to complement efforts towards the implementation of various strategies under

development outcomes. The formulation of a change management strategy to include change

management programmes aims at bringing about mind-set change among all stakeholders,

including the general public was another key issue in the development processes.

With the planning and budgeting policy in place, the guidance provided makes it key

to the achievement of the Vision 2030 in that it specifically defines national measurement

framework to track implementation progress of the Vision 2030 for each sector by considering

the key result areas, key performance indicators and baseline and target values. Its enactment

into the National Planning and Budgeting legislation is anticipated to greatly enhance decision

making and efficiency in the development planning process.

6.2 Lessons Learnt

In the overall assessment of planning, budgeting and monitoring systems, lessons learnt

bordered on the challenges and problems detrimental to PFM efforts, budget credibility and

development results. In the Zambian case, it was clear that the challenges identified attributed

to weak links between policy cycle and financial cycle. This was due to failure to align the

budget planning, programming and expenditure with NDPs and the Vision 2030. This was

compounded further by the non-linkage of the of budget planning to the NPF. In the absence

of the NPF, it was learnt that quantifying and linking outcomes and impact to Vision 2030

could be difficult.

In the context, development of the NPF would therefore operationalize the national

long-term vision, by re-packaging long term strategic objectives into the medium term. This

Page 71: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 60

would be done by logically identifying and interpreting the strategic objectives contained in

the national long-term vision. In terms of tracking implementation progress towards realizing

objectives in the Vision 2030, the NPF would enhance policy cycle and strategic vision through

the establishment of a strong linkage between defined national outcomes and key performance

indicators in the NPF with NDP and the Vision 2030.

With regard to budget credibility, it was learnt that the development of sector specific

performance frameworks (SPF) would further enhance and improve the alignment of the NPF

with the MTEF, NDP and Vision 2030. This would be achieved by sectors establishing annual

M&E plans based on SPF. This would enhance the systematic M&E of each sector strategic

goals, objectives, programmes and projects.

It was further learnt that by re-engineering the legacy systems into Results Based

Budgeting, this would create linkages between the policy and financial cycle as well as

planning and implementation as aligned to the NDP and Vision 2030. The introduction of

evidence-based policy making approach in the national development planning process would

further enhance the identification of gaps where evidence of programme effectiveness is

lacking. With this strategy, policymakers would be enabled to use evidence in making

development and budget decisions.

With the understanding that evidence-driven policy making relies much on systems to

monitor implementation and measure key outcomes, this would enhance the development of a

national M&E policy framework that would spell out the M&E best practices, principles,

processes, standards and procedures. The underpinning factor would be the development of an

implementation plan, M&E guidelines, manuals and tools for use or adaption across

government.

6.3 Follow-up Actions and Recommendations

Page 72: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 61

In order to enhance accountability and evidence- based policy making in development

planning processes, it is therefore recommended that the development of the NPF be

heightened as this is expected to enhance policy cycle and strategic vision through

establishment of strong linkage between defined National Outcomes and Key Performance

Indicators in the NPF with those in NDP and the Vision 2030. Equally, the development of

Sector Performance Frameworks (SPF) should be heightened to improve the alignment of the

MTEF with the NDP and the Vision 2030.

In the understanding that M&E system is a key aspect to the provision of information

required for evidence-based development planning; transparent and accountable budgeting and

programme execution in the future, it is thus recommended that the National M&E Policy and

Master Plan be developed to guide implementation across Government levels, agencies and

sectors. There is also the need to support sectors to establish annual M&E Plans based on the

SPF. This would contribute to systematic M&E of every sector’s strategic goals, objectives,

programmes and projects. The annual M&E Plans would act as a catalyst to MPSAs to

proactively move away from activity-based implementation and reporting to performance-

based budget allocation, implementation and tracking of progress. The development of a

National M&E Policy framework is crucial in spelling out the best practices, principles,

processes, standards and procedures. This should be underpinned by an Implementation Plan,

M&E Guidelines / Manual and Tools for use or adaption across government.

It is crucial to ensure that resource mobilization, expenditure prudence, and donor

support coordination should be prioritized in all sectors to minimize and eliminate wasteful

duplication of investments and activities. This would be linked to the integrated approach as

envisaged for the 7th NDP.

It should be recommended that a strategy be developed to strengthen enhancement of

capacity (both human and institutional) across Government levels, agencies and sectors. This

Page 73: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 62

can be achieved by putting in place the necessary communication and motivational strategies,

incentives and rewards for best performing sectors as a mechanism to encourage and support

real change. Sectors should be able to identify and promote development champions to support

institutionalization of the necessary culture and desired mindset in their institutions. It is further

recommended that a comprehensive change management process be put in place by the change

champions, that is, institutions mandated to carry out such tasks on behalf of government such

as Cabinet Office, Public Service Management Division etc. In the context of the change

management process, two aspects need to be addressed namely communication and objectivity,

as key variables in the change management required.

The belief is that with the adoption of evidence-based policy making approach in the

development planning processes, this will reduce wasteful spending by identifying and

eliminating ineffective programmes. By implication, this would enable freeing up of budgets

for the expansion of innovative programmes as well as strengthening accountability in the

collection and reporting data on programmes operations and outcomes.

Page 74: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 63

References

African Union Commission, (2005), Agenda 2063 (https://au.int/en/agenda2063)

Chapagain, Dilip Kumar (2012), Approaches of Development planning (Presentation), NASC

Document Management System (dms.nasc.org.np. sites. files. Document)

Donge, Jan K, Henley David & Lewis Peter (2009), Tracking Development in Southern east

Asia and Sub-Saharan Africa - The Primacy of Policy (www.institutions-

africa.org/trackingdevelopment)

Gumboh, S (2012), Promotion of Appropriate Agricultural Technologies and the Management

of the Fertilizer Support Programme in Zambia: The Case of Small holder farmers, Lusaka

Gumboh, S, (2016), Formulation of the 7thNDP Presentation, Stakeholder Consultation on the

Development of the 7th NDP, Lusaka

Lupunga, P, (2016), Development Cooperation Presentation, Stakeholder Consultation on the

Development of the 7th NDP, Lusaka

Lupunga, P and Kayekesi, S (2015), Conceptualization of National Development Planning in

Zambia, Lusaka

Khor, Martin (2013), Reviving Economic Planning in Africa, Triple Crisis

(www.triplecrisis/reviving - economic-planning-in-africa)

Makinde, T (2005), Problems of Policy Implementation in Developing Nations; The Nigerian

Experience, in the Journal of Social Sciences, Vol.11, No 1, pp 63-69

Ministry of Community and Social Services (2013), National Gender Policy, Lusaka

Ministry of Development Planning and National Guidance (1965), First National Development

Plan, 1966-1970, Lusaka

Page 75: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 64

Ministry of Development Planning and National Guidance (1971), Second National

Development Plan, 1972-1976, Lusaka

Ministry of Finance and Economic Development (2000), Public Investment Programme,

(2000-2002), Lusaka

Ministry of Finance and National Planning (2002), Poverty Reduction Strategy Paper, Lusaka.

Ministry of Finance and National Planning (2002), Transitional National Development Plan,

(2002-2005), Lusaka

Ministry of Finance and National Planning (2002) Poverty Reduction Strategy Paper, Lusaka

Ministry of Finance and National Planning (2006), Fifth National Development Plan (2005-

2010). Lusaka

Ministry of Finance and National Planning (2012), Annual Progress Report - Sixth National

Development Plan. Lusaka

Ministry of Finance and National Planning (2011), Sixth National Development Plan, (2011 -

2015), Lusaka

Ministry of Finance and National Planning (2013), Revised Sixth National Development Plan

(2013-2016), Lusaka

Ministry of Finance and National Planning (2014), National Planning and Budgeting Policy,

Lusaka

Ministry of Finance and National Planning (2014), 2014 – 2016 Medium Term Expenditure

Framework Document, Lusaka

Ministry of Finance and National Planning (2015) MoF, Budget Call Circular, Lusaka

Ministry of Finance and National Planning (2013), Public Financial Management Reform

Strategy for Zambia, 2013-2015, Lusaka

Ministry of Local Government and Housing (2009), Decentralization Implementation Plan

2009-2013, Decentralization Secretariat, Lusaka

Ministry of National Development Planning (2015), M&E Inception and Synthesis Report for

Enhancing G-W- M&E Management Information System, Lusaka

Ministry of National Development Planning (2015), Public Investment Management Concept

Note, Lusaka

Ministry of National Development Planning (2015), Concept Paper on the National Integrated

Management Information System (2013 – 2018), Lusaka

Ministry of National Development Planning (2016), Concept Paper for the 7thNDP, (2017 -

2021), Lusaka

Page 76: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 65

Ministry of National Development Planning (2016), Seventh National Development Plan

(2017 -2021), Lusaka

Ministry of National Development Planning (2016), MoNDP, Re - Organization Report,

Lusaka

Ministry of National Development Planning (2015) Development Planning Report, Lusaka

Mudenda, S (2016), National Strategy on the Development of Statistics Presentation,

Stakeholder Consultation on the Development of the 7th NDP, Lusaka

Montather, R. Abd (2005), 5 Models of Strategic Planning, (www.linkedin.com/pulse/5-

models-of-strategic-planning)

Mulungushi, J.S (2007) Policy Development and Implementation in the Post Liberalization Era

in Zambia (1990s and Beyond): Towards a Participatory Planning and Economic Management

Model, Lusaka

Mwenda, J (2016), National Performance Framework Presentation, Stakeholder Consultation

on the Development of the 7th NDP, Lusaka

Office of the President (1964), Emergency Development Plan (1964-1965), Lusaka

Office of the President (1965), Transitional National Development Plan (1965-1966), Lusaka

Southern African Development Community, (2005), Regional Indicative Strategic

Development Plan (www.sadc.int/overview/strategic-pl/regional-indicative-strategic-

development-plan/)

United Nations (2010), UN News Centre (www.un.org/apps/news)

UNECA (2015), Planning for Africa’s Development ((www.un.org/stories/planningforafrica)

UNECA (2016), Strengthening of the Capacities of African Governments for Integrating

Accountability in Development Planning, 10th Tranche of the Development Account Project

Document, Addis Ababa

UNDP (2014), Programme Implementation and Project Appraisal Manual for Zambia,

Lusaka

UNDP (2015), Public Investment Planning, Appraisal Management Framework for Zambia,

Lusaka

Wikipedia, (2017), The Theory of Change Model (http://theoryofchange.org, 2017)

Page 77: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 66

Annex 1: Types of Plans, Timelines and Purpose

Level Plan Timeline Purpose

National /Sector National Vision 25-year

plan

Defining the long term national policy pronouncements

Outlining the long term national aspirations and goals

Defining long term national scenarios

Guiding long term and medium term sectoral planning

processes

Guiding the IDPs formulation processes

National

Development Plan

5-year

plan

Operationalizing the long-term vision

Providing medium term policy framework

Guiding sectoral planning processes

Guiding provincial and district planning processes

Sector Investment

Plans

10 to 20-

year plans

Operationalize the national vision

Outline long term sectoral investment programmes

Actualizing sector specific long-term targets

Sector plans 5-year

plans

Operationalize the national vision

Operationalizes the national development plan

Outline medium term sectoral development programmes

Actualizing sector specific medium targets

Provincial Provincial Growth

Development Plan

or

Provincial

Development Plan

5-year

plan

Identifying provincial potentials/

Comparative advantage

Enhancing multi-district initiatives

Aggregating / identification of programmes

District Integrated District

Plan

10-year

plan

Operationalize the national vision

Operationalize sector investment plans

Guiding district development plan processes

District Strategic

Development Plan

5-year

plan

Operationalize the IDP

Operationalize the NDP

Page 78: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 67

Actualize sector investment plans

Source: NPBP, 2014.

Annex 2: Institutional and Consultative Framework for Development Planning

Consultative Process Institutional Framework Output

National Vision

Ministry of National

Development Planning

National

Development

Coordinating

Committee

Five-Year National

Development Plan

Three-Year National

Development Implementation

Plan

Cabinet/

Cabinet

office

NDP

Policy

Guidance

Ministr

y of

Finance

MTEF and Annual

National Budget

Line Ministries

Planning Units

Sectoral

Development

Coordinating

Committee

Provincial Planning Units in

the office of the Permanent

Secretary Provincial

Administration

Provincial

Development

Coordinating

Committee

Institutional Strategic

Plans and

Implementation Plans

Page 79: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 68

Source: Author’s creation, 2017

Annex 3: National Performance Framework

District Planning Units in

the office of the District

Administration

District

Development

Coordinating

Committee

Page 80: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 69

Source: Ministry of National Development Planning 7th NDP Consultative Process Document,

2016

Annex 4: National Development Planning /Formulation Process

Year One - 2015

Year Three- 2017 Year Two - 2016

Evaluation Reports;

APRs; Government

Pronouncements

NDP Launched by

President and tabled

before National

Assembly for

implementation

Issues Paper & Concept Note,

Roadmap

Draft NDP/Green Paper tabled

before Cabinet

Commencement of Public

Consultations

Sectors, Provinces, Districts,

Private Sector, Interest

groups, Civil Society, Political

parties

Draft NDP with various lay out

options transmitted to Cabinet

Drafting of Zero Draft NDP

Taking into account issues

from Consultative process

Page 81: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 70

Source: 7th NDP Concept Note

Annex 5: The Five Steps in Evidence-Based Policymaking

Program assessment Systematically review available evidence on the effectiveness of public

programs.

Budget development (Planning) Incorporate evidence of program effectiveness into budget and policy decisions,

giving funding priority to those that deliver a high return on investment of public

funds.

Implementation oversight (Budget Execution) Ensure that programs are effectively delivered and are faithful to their

intended design.

Alignment of District /

Provincial Indictors to NDP

Indicators

Programme and Project

Appraisal

Page 82: The Zambian Case Study Progress and Status of Integrating ... Stephen Gumboh-Zambia Panning-revised.pdfPIM Public Investment Management PIP Public Investment Plan PIPA Programme Implementation

Page 71

Outcome monitoring Routinely measure and report outcome data to determine whether programs are

achieving desired results.

Targeted evaluation Conduct rigorous evaluations of new and untested programs to ensure that they

warrant continued funding.

Based upon the Pew-MacArthur Results First Initiative, who has developed a framework that

governments can follow to build and support a system of evidence-based policymaking.

Source: MoNDP, M&E Inception and Synthesis Report