Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Planning Act 2008 The Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009
Revision: Date: Description:
0 March 2016 Submission version
6.4.11 Volume 4: Environmental Statement Appendix 19.1: Draft CEMP
PINS Reference Number: EN010055Document Reference Number: 6.4.11Regulation Number: 5(2) (a)Lead Author: Atkins
The Wrexham(Gas Fired Power Station) Order
SEC6.4-ES Appendix TABS.indd 66 15/03/2016 11:15
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
i
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
ii
Contents
Executive summary
Chapter 1 u Introduction
Scheme Outline Purpose of the CEMP
Chapter 2 Planning and Legal Context
Legal Requirements, Standards and PoliciesDCO Requirement
Chapter 3 Implementation
Scheme Structure and REsponsibilities Training, Awareness and Competence Communication
Chapter 4 Environmental Monitoring and Auditing
Environmental Performance Indicators Inspections and Verifications Corrective and Preventative Action External Complaints PRocedure Emergency Preparedness and ResponseManagement Review Documents and Records
Chapter 5 Environmental Management
Environmental Risk Assessment Prevention of Nuisance and Pollution
Appendix A Tree Protection
Arboricultural protection method statementSite Meetings and Supervision Construction Exclusion Zone and Protective BarriersTree Works Sequence of Events Tree Protection Fencing Tree Monitoring Proforma
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Legal Requirements, Standards and Policies
Chapter 4 Environmental Monitoring and Auditing
Emergency Preparedness and Response
Chapter 5 Environmental Management
Arboricultural protection method statement
Construction Exclusion Zone and Protective Barriers
1
3
3
5
6
6
6
7
7
8
9
11
11
11
12
12
12
13
13
14
14
14
32
32
32 32
33
34
34
35
Glossary
Full Text Acronym
Above Ground Installation
AGI
AGI Site -
Above Ordnance Datum
AOD
Agricultural land classification
ALC
Air Cooled Condenser
Area of Outstanding Natural Beauty
AONB
Air Pollution Information System
APIS
Air Quality Limit Value Regulations 2010
Air Quality Management Area
AQMA
Air Quality Management Plan
AQMP
Air Quality Modelling and Assessment Unit
AQMAU
Air Quality Modelling and Risk Assessment Team
AQMRAT
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Notes
Compound where the infrastructure (pipes, valves and kiosk) is located which is required to connectGas Connection to the high pressure gas NationalTransmission System (‘NTS’).
The land on which the AGI will be located.
Height of land surface above sea level.
A nationally consistent and recognised method for assessing the potential productiveness of agricultural land.
A direct dry cooling system where the steam is condensed and returned condensate to the boiler without water loss. Situated within the Power Station Complex.
A landscape designation protected under the Countryside and Rights of Way Act, 2000
An information system that provides a comprehensive source of information on air pollution and the effects on habitats and species.
UK regulations to limit the levels of air borne pollutants emitted from industries.
An area designated by a local authority as being at risk of not meeting air quality standards
A plan developed to improve the air quality in the air quality management area.
An Environment Agency team that targets air quality related issues.
An NRW team that targets air quality related issues
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
iii
he infrastructure (pipes, valves and kiosk) is located which is required to connect the
high pressure gas National
A nationally consistent and recognised method for assessing the potential productiveness of agricultural
t dry cooling system where the steam is condensed and returned condensate to the boiler without water loss. Situated within the Power Station
A landscape designation protected under the
An information system that provides a comprehensive source of information on air pollution
it the levels of air borne
An area designated by a local authority as being at
e air quality in the air
An Environment Agency team that targets air quality
ity related issues
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
iv
Air Quality Strategy AQS The AQS for England, Scotland, Wales and Northern Ireland provides details of national air quality standards and objectives for a number of local air pollutants.
Air Quality Technical Advisory Group
AQTAG The jNatural Resource Wales group. AQTAG was established in 2000 by the agency’s Habitats Directive Project to provide technical guidance on the assessment of air emissions from IPC/IPPC processes.
Ancient Woodland - A woodland that has existed continuously since 1600 or before.
Annual Average Daily Traffic
AADT Measurement unit for the total volume of vehicle traffic to indicate how busy the road is.
Annual mean (Air Quality)
- The average of concentrations measupollutant for one year (usually a calendar year, from January to December). Sometimes it may be reported for a pollution year (April to March) which avoids splitting a winter season, useful for pollutants with higher concentrations during the wi
Application - The DCO application for the Power Station Complex Site made to the Secretary of State under the Planning Act 2008.
Applications: Prescribed Forms and Procedure Regulations
APFP The Infrastructure Planning Forms and Procedure)prescribe various matters in connection with the making of an application for development consent under the Planning Act 2008.
Asbestos Containing Material
ACM Any material containing more than 1% asbesto
Automatic Traffic Count
ATC Means of determining traffic levels in the vicinity.
Automatic Urban and Rural Network
AURN Air quality monitoring site.
Baseline - The conditions that exist without a proposed development at the time an assessment or suundertaken.
Bat Conservation BCT Voluntary organisation which provides advice and
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
The AQS for England, Scotland, Wales and Northern Ireland provides details of national air quality standards and objectives for a number of local air pollutants.
The joint Environment Agency, Natural England and Natural Resource Wales group. AQTAG was established in 2000 by the agency’s Habitats Directive Project to provide technical guidance on the assessment of air emissions from IPC/IPPC processes.
A woodland that has existed continuously since 1600 or before.
Measurement unit for the total volume of vehicle traffic to indicate how busy the road is.
The average of concentrations measured for a pollutant for one year (usually a calendar year, from January to December). Sometimes it may be reported for a pollution year (April to March) which avoids splitting a winter season, useful for pollutants with higher concentrations during the winter months.
The DCO application for the Power Station Complex Site made to the Secretary of State under the Planning Act 2008.
The Infrastructure Planning (Applications: PrescForms and Procedure) Regulations 2009 which prescribe various matters in connection with the making of an application for development consent under the Planning Act 2008.
Any material containing more than 1% asbesto
Means of determining traffic levels in the vicinity.
Air quality monitoring site.
The conditions that exist without a proposed development at the time an assessment or suundertaken.
Voluntary organisation which provides advice and
The AQS for England, Scotland, Wales and Northern Ireland provides details of national air quality standards and objectives for a number of local air
oint Environment Agency, Natural England and Natural Resource Wales group. AQTAG was established in 2000 by the agency’s Habitats Directive Project to provide technical guidance on the assessment of air emissions from IPC/IPPC processes.
A woodland that has existed continuously since 1600
Measurement unit for the total volume of vehicle
red for a pollutant for one year (usually a calendar year, from January to December). Sometimes it may be reported for a pollution year (April to March) which avoids splitting a winter season, useful for pollutants with
nter months.
The DCO application for the Power Station Complex Site made to the Secretary of State under the
(Applications: Prescribed Regulations 2009 which
prescribe various matters in connection with the making of an application for development consent
Any material containing more than 1% asbestos.
Means of determining traffic levels in the vicinity.
The conditions that exist without a proposed development at the time an assessment or survey is
Voluntary organisation which provides advice and
Trust
Below Ground Level Bgl
Best Available Technique
BAT
Best and most versatile
BMV
Biodiversity Action Plan
BAP
Best Practical Means BPM
British Geological Survey
BGS
British Society of Soil Science
BSSS
BS 4142 -
BS 8233 -
BS 5228 -
Cadw
CAoL Guidance -
Calculation of Road CRTN
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
guidance relating to bats.
A measure unit of distance below ground.
The most effective and advanced stagedevelopment of activities and their methods of operation which indicates the practical suitability of particular techniques for providing the basis for emission limit values and other permit conditions designed to prevent and, where that is not practicable, to reduce emissions and the impact on the environment as a whole.
Land in grades 1, 2 and 3a of the Agricultural Land Classification
Plan concerned with the protection of identified species and habitats.
Reasonably applied means that balance best practice against practical constraints.
The UK public body responsible for all aspects of geoscience.
A professional society that aims to advance the study of soil.
Method for Rating Industrial Noise Affecting Mixed Residential and Industrial Areas (2014).
Guidance on sound insulation and noise reduction for buildings (2014).
Code of Practice for Noise and Vibration Control on Construction and Open Sites 2009 (2009).
The Welsh Government's historic environment service. Cadw is a Welsh word meaning ‘to keep’ or ‘to protect’.
Department of Communities and Local Government guidance ‘Planning Act 2008: Guidance related to procedures for the compulsory acquisition of land’ (September 2013).
Department for Transport Memorandum, Calculation
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
v
The most effective and advanced stage in the development of activities and their methods of operation which indicates the practical suitability of particular techniques for providing the basis for emission limit values and other permit conditions designed to prevent and, where that is not
cticable, to reduce emissions and the impact on
Land in grades 1, 2 and 3a of the Agricultural Land
Plan concerned with the protection of identified
Reasonably applied means that balance best practice
The UK public body responsible for all aspects of
A professional society that aims to advance the study
Method for Rating Industrial Noise Affecting Mixed
Guidance on sound insulation and noise reduction for
Code of Practice for Noise and Vibration Control on
The Welsh Government's historic environment service. Cadw is a Welsh word meaning ‘to keep’ or
ies and Local Government guidance ‘Planning Act 2008: Guidance related to procedures for the compulsory acquisition of land’
Department for Transport Memorandum, Calculation
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
vi
Traffic Noise of Road Traffic Noise
Carbon Dioxide CO2 A primary greenhouse gas emitted through human activities as well as natural sources.
Carbon Monoxide CO One of the combustion products discharged by CCGT power stations.
Chamber of Commerce
CoC A network of businesses to represinterests.
Civil Aviation Authority
CAA A statutory corporation that oversees and regulates civil aviation in the UK.
Classified Turning Counts
CTC Measurement of vehicle traffic in particular at junctions.
Coal Authority - A nonoperations and coal reserves throughout the UK.
Construction Industry Research and Information Association
CIRIA A memberorganisation serving the construction industry
Code of Construction Practices
CoCP A guidance document that sets out standards and procedures for managing environmental impact of constructing major schemes.
Combined Cycle Gas Turbine
CCGT A form of power station that uses an efficient combination of gas and selectricity.
Combined Heat and Power
CHP A means of using waste heat generated by power station e.g. through a local heat distribution network.
Chartered Institute of Ecology and Environmental Management
CIEEM Professional body to chartership in 2013 the body was known as IEEM and publications refer to this.
Chartered Institution of Highways and Transportation
CIHT IHT is a professional body for transport professionals.
Commercial and Industrial waste
C&I Both commercial waste and industrial waste are defined by s75 of the Environmental Protection Act 1990. Commercial waste means "waste from premises … used wholly or mainly for the purposes of
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
of Road Traffic Noise 1988
A primary greenhouse gas emitted through human activities as well as natural sources.
One of the combustion products discharged by CCGT power stations.
A network of businesses to represent local business interests.
A statutory corporation that oversees and regulates civil aviation in the UK.
Measurement of vehicle traffic in particular at junctions.
A non-governmental body that manages coal mining operations and coal reserves throughout the UK.
A member-based research and information organisation serving the construction industry
A guidance document that sets out standards and procedures for managing environmental impact of constructing major schemes.
A form of power station that uses an efficient combination of gas and steam turbines to generate electricity.
A means of using waste heat generated by power station e.g. through a local heat distribution network.
Professional body governing ecology/ecologists prior to chartership in 2013 the body was known as IEEM and publications refer to this.
IHT is a professional body for transport professionals.
Both commercial waste and industrial waste are defined by s75 of the Environmental Protection Act 1990. Commercial waste means "waste from premises … used wholly or mainly for the purposes of
A primary greenhouse gas emitted through human
One of the combustion products discharged by CCGT
ent local business
A statutory corporation that oversees and regulates
Measurement of vehicle traffic in particular at
overnmental body that manages coal mining operations and coal reserves throughout the UK.
based research and information
A guidance document that sets out standards and procedures for managing environmental impact of
A form of power station that uses an efficient team turbines to generate
A means of using waste heat generated by power station e.g. through a local heat distribution network.
governing ecology/ecologists prior to chartership in 2013 the body was known as IEEM
IHT is a professional body for transport professionals.
Both commercial waste and industrial waste are defined by s75 of the Environmental Protection Act 1990. Commercial waste means "waste from premises … used wholly or mainly for the purposes of
Common Bird Census CBC
Construction, demolition and excavation waste
CDEW
Committee on the Medical Effects of Air Pollutants
COMEAP
Conceptual Site Model
CSM
Conservation Areas CA
Construction Stage -
Construction and Demolition Waste
C&D
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
a trade or business or the purposes of sport, recreation or entertainment excluding … household waste; …industrial waste and [waste prescribed as being excluded by the Secretary of State]". Industrial waste means "waste from any of the following premises - … any factory… any premises used for the purposes of, or in connection with, the provision to the public of transport services by land, water or air …any premises used for the purposes of, or in connection with, the supply to the public of gas, water or electricity or the provision of sewerage services… any premises used for the purposes of, or in connection with, the provision to the public of postal or telecommunications services; or … any mine or quarry or any premises used for agriculture within the meaning of the Agriculture Act 1947".
A standardised methodology to map breeding bird territories.
A type of construction waste as identified by the Natural Resource Wales
An advisory body that advises the UK government on all matters concerning the health effects of air pollutants.
A model that identifies the possible pathways by which a contaminant from a particular source can affect a particular receptor.
An area of special architectural and historic interest designated by the local planning authorityto the Planning (Listed Building and Conservation Areas) Act 1990.
The construction stage of the Scheme begins with enabling works, which will include site setgroundworks. Following this, construction of the Power Station Complex Site, and Gas Connection will be undertaken, followed by commissioning.
A type of construction waste.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
vii
a trade or business or the purposes of sport, creation or entertainment excluding … household
waste; …industrial waste and [waste prescribed as being excluded by the Secretary of State]". Industrial waste means "waste from any of the following
… any factory… any premises used for the es of, or in connection with, the provision to
the public of transport services by land, water or air …any premises used for the purposes of, or in connection with, the supply to the public of gas, water or electricity or the provision of sewerage
… any premises used for the purposes of, or in connection with, the provision to the public of postal or telecommunications services; or … any mine or quarry or any premises used for agriculture within the
A standardised methodology to map breeding bird
A type of construction waste as identified by the
An advisory body that advises the UK government on all matters concerning the health effects of air
A model that identifies the possible pathways by which a contaminant from a particular source can
An area of special architectural and historic interest designated by the local planning authority pursuant to the Planning (Listed Building and Conservation
e of the Scheme begins with enabling works, which will include site set-up and groundworks. Following this, construction of the Power Station Complex Site, and Gas Connection will be undertaken, followed by commissioning.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
viii
Construction Environmental Management Plan
CEMP A plan describing how the environmental impacts of the construction activities of a project will be minimised and mitigated relevant planning autho
Construction Traffic Management Plan
CTMP A plan for managing construction traffic that is submitted to the relevant Highway Authority for approval
dB(A) - Afrequency between 20 Hz and represents the way the human ear works.
Decibel dB Logarithmic scale for measuring sound levels.
Decommissioning Stage
- Following the end of its operational life, Station Complex would be decommissioned and will revertbe purged of gas and is likely to be left into avoid the adverse environmental effects associated with its removal.
Dee Valley Water A water supply company that covers North East Wales and the
Department for Education and Skills
DfES Government department responsible for education and children’s services.
Department of Energy and Climate Change
DECC Government department responsible for energy policy
Department for Environment, Food and Rural Affairs
DEFRA Government department responsible for environmental protection, food production and standards, agriculture, fisheries and rural communities.
Department for Transport
DfT Government department with responsibility fcertain areas of transport policy in Wales that have not been devolved.
Deposition - The main pathway for removing pollutants from the atmosphere, by settling on land.
Design Manual for Roads and Bridges
DMRB A suite of technical documents produced byHighways Agency (as was) that include guidance for environmental appraisal that are also used for nonhighways schemes and as such are commonly used in
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
A plan describing how the environmental impacts of the construction activities of a project will be minimised and mitigated that is submitted to the relevant planning authority for approval.
A plan for managing construction traffic that is submitted to the relevant Highway Authority for approval
A-weighted decibel – a correction applied to each frequency between 20 Hz and 20 kHz that effectively represents the way the human ear works.
Logarithmic scale for measuring sound levels.
Following the end of its operational life, the Power Station Complex would be decommissioned and will revert to open bare ground. The Gas Connection will be purged of gas and is likely to be left in-situ in order to avoid the adverse environmental effects associated with its removal.
A water supply company that covers North East Wales and the North West of England.
Government department responsible for education and children’s services.
Government department responsible for energy policy
Government department responsible for environmental protection, food production and standards, agriculture, fisheries and rural communities.
Government department with responsibility fcertain areas of transport policy in Wales that have not been devolved.
The main pathway for removing pollutants from the atmosphere, by settling on land.
A suite of technical documents produced byHighways Agency (as was) that include guidance for environmental appraisal that are also used for nonhighways schemes and as such are commonly used in
A plan describing how the environmental impacts of the construction activities of a project will be
that is submitted to the
A plan for managing construction traffic that is submitted to the relevant Highway Authority for
a correction applied to each 20 kHz that effectively
the Power Station Complex would be decommissioned and will
to open bare ground. The Gas Connection will situ in order
to avoid the adverse environmental effects associated
A water supply company that covers North East Wales
Government department responsible for education
Government department responsible for energy
Government department responsible for environmental protection, food production and standards, agriculture, fisheries and rural
Government department with responsibility for certain areas of transport policy in Wales that have
The main pathway for removing pollutants from the
A suite of technical documents produced by the Highways Agency (as was) that include guidance for environmental appraisal that are also used for non-highways schemes and as such are commonly used in
Determinand -
Development Consent Order
DCO
Electrical Connection -
Electricity Market Reform
EMR
Electric and Magnetic Fields
EMF
Emission -
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
EIA.
A substance or parameter that is determined analytically, e.g. arsenic concentration in soil, pH of water, concentration of a particular gas in air quality modelling.
An Order made under the Planning Act 2008 granting development consent for a Nationally Significant Infrastructure Project
The Electrical Connection is not part of the Application for the Scheme, but will be required for the export of electricity. A number of realistic assumptions have been made regarding the electrical connection works as set out below:
• The Electrical Connection is likely to consist of underground cabling between the Scheme’s electrical switchgear located within the Power Station Complex and the existing Marchwiel substation, located on Abbey Road on the Wrexham Industrial Estate.
• The wider existing electrical distribution network will also need upgrading to accommodate the new generation. This is likely to consist of works to the existing Marchwiel substation, re-stringing of existing pylons between Legacy and Wrexham substations, replacement of the existing portal frame towers between Legacy and Marchwiel substations, and laying of underground cables. Once completed the electrical network which currently serves the Wrexham Industrial Estate will have increased capacity and resilience from that which exists presently.
UK government's policy to reform the electricity market. The policy aims to deliver low carbon energy and reliable supplies for the UK, while minimising costs to consumers.
EMFs comprise electric and magnetic fields. Electric fields are the result of voltages applied to electrical conductors and equipment. Magnetic fields are produced by the flow of electric current.
The direct or indirect release of substances,
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
ix
A substance or parameter that is determined ation in soil, pH of
water, concentration of a particular gas in air quality
An Order made under the Planning Act 2008 granting development consent for a Nationally Significant
The Electrical Connection is not part of the Application for the Scheme, but will be required for
number of realistic assumptions have been made regarding the electrical
ectrical Connection is likely to consist of underground cabling between the Scheme’s electrical switchgear located within the Power Station Complex and the existing Marchwiel substation, located on Abbey Road on the Wrexham Industrial Estate.
existing electrical distribution network will also need upgrading to accommodate the new generation. This is likely to consist of works
stringing of existing pylons between Legacy and Wrexham
ent of the existing portal frame towers between Legacy and Marchwiel substations, and laying of underground cables. Once completed the electrical network which currently serves the Wrexham Industrial Estate will have increased
that which exists
UK government's policy to reform the electricity market. The policy aims to deliver low carbon energy and reliable supplies for the UK, while minimising
EMFs comprise electric and magnetic fields. Electric fields are the result of voltages applied to electrical conductors and equipment. Magnetic fields are
e of substances,
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
x
vibrations, heat or noise from individual or diffuse sources into air, water or onto land, e.g. pollution may be discharged into the atmosphere from a stack or vent.
Emission Limit Value ELV Legal enforcement limit on the physical, chemicbiological characteristics of a point source of emission to water or air.
Energy Efficiency Directive 2012
- Directive 2012/27/EU establishes a framework of measures for the promotion of energy efficiency within the European Union.
Environmental Health Officer
EHO A local authority health professional responsible for carrying out measures for protecting public health.
Environmental Impact Assessment
EIA The process of assessing the likely significant environmental impacts of a proposed project aof gaining planning consent.
Environmental Permit
EP A permit required in accordance with the Environmental Permitting Regulations.
Environmental Permitting Regulations
EPR The Environmental Permitting (England and Wales) Regulations 2010 regupollution potential through a permitting system.
Environmental Protection Act 1990
EPA The Act that covers, amongst other things, the regulation of contaminated land in the UK.
Environmental Protection UK
EPUK UK(NGO) working to improve the quality of the local environmen
Environmental Quality Standards
EQS The concentration of a particular pollutant or group of pollutants in water, sediment or biota which should not be exceeded in ohealth and the environment.
Environmental Statement
ES The document which reports the process, findings and recommendations of the EIA.
Environmentally Sensitive Area
ESA A designation for agricultural areas needing special protecthistorical value.
Flood Defence Consent
FDC A consent required by Natural Resources Wales, for construction or maintenance work on over, under or
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
vibrations, heat or noise from individual or diffuse sources into air, water or onto land, e.g. pollution may be discharged into the atmosphere from a stack or vent.
Legal enforcement limit on the physical, chemicbiological characteristics of a point source of emission to water or air.
Directive 2012/27/EU establishes a framework of measures for the promotion of energy efficiency within the European Union.
A local authority health professional responsible for carrying out measures for protecting public health.
The process of assessing the likely significant environmental impacts of a proposed project aof gaining planning consent.
A permit required in accordance with the Environmental Permitting Regulations.
The Environmental Permitting (England and Wales) Regulations 2010 regulate practices that have pollution potential through a permitting system.
The Act that covers, amongst other things, the regulation of contaminated land in the UK.
UK environmental Non-Governmental Organization (NGO) working to improve the quality of the local environment
The concentration of a particular pollutant or group of pollutants in water, sediment or biota which should not be exceeded in order to protect human health and the environment.
The document which reports the process, findings and recommendations of the EIA.
A designation for agricultural areas needing special protection by virtue of their landscape, wildlife or historical value.
A consent required by Natural Resources Wales, for construction or maintenance work on over, under or
vibrations, heat or noise from individual or diffuse sources into air, water or onto land, e.g. pollution may be discharged into the atmosphere from a stack
Legal enforcement limit on the physical, chemical or biological characteristics of a point source of emission
Directive 2012/27/EU establishes a framework of measures for the promotion of energy efficiency
A local authority health professional responsible for carrying out measures for protecting public health.
The process of assessing the likely significant environmental impacts of a proposed project as part
A permit required in accordance with the
The Environmental Permitting (England and Wales) late practices that have
pollution potential through a permitting system.
The Act that covers, amongst other things, the
Governmental Organization (NGO) working to improve the quality of the local
The concentration of a particular pollutant or group of pollutants in water, sediment or biota which
rder to protect human
The document which reports the process, findings
A designation for agricultural areas needing special ion by virtue of their landscape, wildlife or
A consent required by Natural Resources Wales, for construction or maintenance work on over, under or
Flood Risk Assessment or Flood Consequence Assessment
FRA or FCA
Full Time Equivalents FTE
Gas Connection -
Gas Connection Route
Gas Pipeline -
Gas Turbine GT
Great Crested Newt GCN
Greenhouse Gas GHG
Gross Value Added GVA
Ground Investigation GI
Groundwater GP3
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
near a main river (usually within 8-10 metres).
FRA or FCA An assessment that determines the risk of flooding to a proposed project.
The equivalent number of full time jobs provided by a project - e.g. two half-time jobs equates to one
This element comprises all the equipment required to connect the Power Station Complex to the National Transmission System, including the Gas Pipeline and the Above Ground Installation. This is being separately consented under the TCPA 1990 though it forms part of the Scheme that has been environmentally assessed through the EIA. The Gas Connection forms part of the Order Land.
The route within which the Gas Connection is situated together with the temporary construction working areas.
A continuously welded underground steel pipe with a nominal bore of up to 400mm.
A turbine driven by hot combustion gases at high temperature.
A species of newt protected by European Legislation.
An atmospheric gas such as carbon dioxide, methane, chlorofluorocarbon, nitrous oxide, ozone, or water vapour that slows the passage of re-radiated heat through the Earth’s atmosphere.
A measure of added value to the overall economy of each additional job created.
An intrusive or non-intrusive investigation, and subsequent testing, of surface and subsurface soil and conditions. This is undertaken to obtain information on the physical and chemical properties of the soil, rock, groundwater and gas regimes at and in the vicinity of a site.
A guidance published by the Environment Agency on
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xi
10 metres).
An assessment that determines the risk of flooding to
The equivalent number of full time jobs provided by a time jobs equates to one FTE.
This element comprises all the equipment required to connect the Power Station Complex to the National Transmission System, including the Gas Pipeline and the Above Ground Installation. This is being
TCPA 1990 though it forms part of the Scheme that has been environmentally assessed through the EIA. The Gas
The route within which the Gas Connection is situated construction working
A continuously welded underground steel pipe with a
A turbine driven by hot combustion gases at high
by European Legislation.
An atmospheric gas such as carbon dioxide, methane, chlorofluorocarbon, nitrous oxide, ozone, or water
radiated heat
easure of added value to the overall economy of
intrusive investigation, surface and
and conditions. This is undertaken to physical and chemical
properties of the soil, rock, groundwater and gas
A guidance published by the Environment Agency on
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xii
Protection: Principles and Practice
Groundwater protection.
Groundwater Source Protection Zone
GSPZ Areas around groundwater abstraction sources that are definefrom contamination.
Guidance for the Environmental Assessment of Road Traffic
GEART The IEMA guidance on the environmental assessment of road traffic.
Guidance on Transport Assessment
GTA Department for Transport2007 on the preparation of Transport Assessments as archived 22 October 2014 and replaced by NPPG “Transport evidence bases in plan making”
Guidelines for Landscape and Visual Impact Assessment, 3rd Edition
GLVIA Guidance produced bthe Institute for Environmental Management and Assessment dated 17 April 2013
Habitat - A place where an organism (e.g. human, animal, plant, microlive, characterised by its surroundings.
Habitat Regulations Assessment
HRA An assessment required under the European Directive 92/43/EEC.
Habitat Suitability Index
HSI A method for assessing the suitability of ponds for their potential to support Great Crested Newts.
Health and Safety Executive
HSE The nonfor workplace safety in the UK.
Heat Recovery Steam Generator
HRSG A means of recovering heat energy from hot exhaust gases in order to produce steam for driving a turbine.
Heavy Duty Vehicle HDV HGVs, buses and coaches.
Heavy Goods Vehicle HGV A truck that when laden has a total weight of more than 3500 kg.
Hectare ha 10,000m
Highway Authority HA The relevant highway authority responsible for the nonroads and motorways).
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Groundwater protection.
Areas around groundwater abstraction sources that are defined in order to help protect drinking water from contamination.
The IEMA guidance on the environmental assessment of road traffic.
Department for Transport guidance dated March 2007 on the preparation of Transport Assessments as archived 22 October 2014 and replaced by NPPG “Transport evidence bases in plan making”
Guidance produced by the Landscape Institute and the Institute for Environmental Management and Assessment dated 17 April 2013
A place where an organism (e.g. human, animal, plant, micro-organism) or population of organisms live, characterised by its surroundings.
An assessment required under the European Directive 92/43/EEC.
A method for assessing the suitability of ponds for their potential to support Great Crested Newts.
The non-departmental government body responsible for workplace safety in the UK.
A means of recovering heat energy from hot exhaust gases in order to produce steam for driving a turbine.
HGVs, buses and coaches.
A truck that when laden has a total weight of more than 3500 kg.
10,000m2 or 2.471 acres
The relevant highway authority responsible for the non-core road network (i.e. roads other than trunk roads and motorways).
Areas around groundwater abstraction sources that d in order to help protect drinking water
The IEMA guidance on the environmental assessment
guidance dated March 2007 on the preparation of Transport Assessments as archived 22 October 2014 and replaced by NPPG
y the Landscape Institute and the Institute for Environmental Management and
A place where an organism (e.g. human, animal, organism) or population of organisms
An assessment required under the European Directive
A method for assessing the suitability of ponds for their potential to support Great Crested Newts.
departmental government body responsible
A means of recovering heat energy from hot exhaust gases in order to produce steam for driving a turbine.
A truck that when laden has a total weight of more
The relevant highway authority responsible for the s other than trunk
Historic Environmental Record
HER
Hover -
Indices of Multiple Deprivation
IMD
Industrial Emissions Directive
IED
Industrial Estate Road (N)
Infrastructure Planning Commission
IPC
Institute of Acoustics IOA
Institute of Air Quality Management
IAQM
Institute of Environmental Management and Assessment
IEMA
Institute of Gas Engineers and Managers
IGEM
Integrated Pollution Prevention and Control Directive
IPPC
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
The record held by the local planning authority of known archaeological sites, buildings and landscapes of relevance to the historic environment.
An otter’s day nest or resting site.
An index to measure deprived areas in local councils.
EU Directive on industrial emissions that came into force in January 2011.
The new road which connects Wrexham Industrial Estate to the A534.
The public body that previously examined applications for development consent to build Nationally Significant Infrastructure Projects, abolished through the Localism Act 2011 with the role replaced by the Planning Inspectorate and decisions on whether or not to grant a DCO being made by the Secretary of State.
Professional body for Acoustics, Noise and Vibration professionals.
IAQM is a professional body for air quality professionals.
IEMA is a professional body for environmental professionals that provide industry guidance ontopics including EIA.
IGEM is a chartered professional body, licensed by the Engineering Council.
The EU Directive (2008/1/EC) incorporated intlaw by the Environmental Permitting Regulations on prevention and control of industrial emissions. The Directive aims to achieve a high level protection of the environment through measures to prevent or, where that is not practicable, to reduce emissiair, water and land from activities listed in Annex I of the Directive (e.g. energy industries, production and
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xiii
The record held by the local planning authority of known archaeological sites, buildings and landscapes
An index to measure deprived areas in local councils.
EU Directive on industrial emissions that came into
road which connects Wrexham Industrial
The public body that previously examined applications for development consent to build Nationally Significant Infrastructure Projects,
Localism Act 2011 with the role the Planning Inspectorate and decisions
on whether or not to grant a DCO being made by the
Professional body for Acoustics, Noise and Vibration
IAQM is a professional body for air quality
IEMA is a professional body for environmental professionals that provide industry guidance on many
IGEM is a chartered professional body, licensed by
The EU Directive (2008/1/EC) incorporated into UK law by the Environmental Permitting Regulations on prevention and control of industrial emissions. The Directive aims to achieve a high level protection of the environment through measures to prevent or, where that is not practicable, to reduce emissions to air, water and land from activities listed in Annex I of the Directive (e.g. energy industries, production and
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xiv
processing of metals, mineral industry, chemical industry, intensive pig and poultry farming, waste management, some food and drink indust
ISO 9613-2 - Acousticsoutdoors
Joint Nature Conservation Committee
JNCC The public body that advises the UK government and devolved administrations on UKinternational nature conservation.
Kilovolt kV A measure of electrical potential.
Kingmoor Park Access Road
- The road leading from Bryn Lane to the Power Station Complex Site numbered Work 5 on the Works Plan and in Schedule 1 to the Order
LA10 - Ameasurement period.
LA90 - Ameasurement period.
LAeq - A
LAmax - Ao
Local Air Quality Management
LAQM The mechanism by which the Government’s air quality objectives are to be achieved.
Landscape Character Area
LCA A area of defined landscape character in Wales.
Land Plans - The plans showing the to exercise powers of compulsory acquisition or a right to use land; land in relation to which it is proposed to extinguish or suspend existing easements, servitudes and other private rights and/or impose restrictive covenantApplication Document Reference
LANDMAP - A landscape characterisation and assessment system used across Wales.
Large Combustion Plant Directive
LCPD European legislation to reduce acidification, ground level ozone and particlcontrolling emissions of sulphur dioxide, nitrogen oxides and from large combustion plants in power
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
processing of metals, mineral industry, chemical industry, intensive pig and poultry farming, waste management, some food and drink industries etc.).
Acoustics- Attenuation of sound during propagation outdoors – Part 2: General method of calculation.
The public body that advises the UK government and devolved administrations on UK-wideinternational nature conservation.
A measure of electrical potential.
The road leading from Bryn Lane to the Power Station Complex Site numbered Work 5 on the Works Plan and in Schedule 1 to the Order
A-weighted noise level exceeded for 10% of the measurement period.
A-weighted noise level exceeded for 90% of the measurement period.
A-weighted equivalent continuous sound level.
A-weighted maximum sound pressure level recorded over a given period.
The mechanism by which the Government’s air quality objectives are to be achieved.
A area of defined landscape character in Wales.
The plans showing the land over which it is proposed to exercise powers of compulsory acquisition or a right to use land; land in relation to which it is proposed to extinguish or suspend existing easements, servitudes and other private rights and/or impose restrictive covenants (submitted with the Application Document Reference 2.2).
A landscape characterisation and assessment system used across Wales.
European legislation to reduce acidification, ground level ozone and particles throughout Europe by controlling emissions of sulphur dioxide, nitrogen oxides and from large combustion plants in power
processing of metals, mineral industry, chemical industry, intensive pig and poultry farming, waste
ries etc.).
Attenuation of sound during propagation Part 2: General method of calculation.
The public body that advises the UK government and wide and
The road leading from Bryn Lane to the Power Station Complex Site numbered Work 5 on the Works Plan
weighted noise level exceeded for 10% of the
weighted noise level exceeded for 90% of the
weighted equivalent continuous sound level.
weighted maximum sound pressure level recorded
The mechanism by which the Government’s air
A area of defined landscape character in Wales.
over which it is proposed to exercise powers of compulsory acquisition or a right to use land; land in relation to which it is proposed to extinguish or suspend existing easements, servitudes and other private rights and/or
s (submitted with the
A landscape characterisation and assessment system
European legislation to reduce acidification, ground es throughout Europe by
controlling emissions of sulphur dioxide, nitrogen oxides and from large combustion plants in power
Laydown Areas -
Lead Local Flood Authority
LLFA
Light Duty Vehicles LDV
Listed Building
Local Nature Reserve LNR
Local Wildlife Site LWS
Made Ground -
Maelor Gas Works -
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
stations.
The temporary (Work numbered 2A on the Works Plan) and temporary/permanent (Work numbered 2B on the Works Plans) laydown areas required for the Scheme.
The Laydown Area shown on the Works Plan and numbered Work 2A in Schedule 1 to the Order is located on the eastern side of the Power Station Complex and will be up to 3.6 ha in size. It will be used during construction of the Scheme only.
The Laydown Area shown on the Works Plan and numbered Work 2B in Schedule 1 to the Order is located adjacent to the south eastern corner of the Power Station Complex and will be up to 0.25 ha in size. It will be used during construction of the Scheme and for maintenance activities during operation.
The authority responsible for developing, maintaining and applying a strategy for local flood risk management in their areas and maintaining of flood risk assets.
Vehicles with a weight less than 3.5 tonnes (gross weight).
A building that has been placed on the statutory list of buildings of Special Architectural or Historic Interest and protected by the Planning (Listed Building and Conservation Areas) Act 1990.
Statutory designation for places with wildlife or geological features that are of special interest locally.
Wildlife rich sites selected for their local nature conservation value.
Man-made deposits artificially placed comprising a wide variety of material e.g. concrete, brick etc typical of previously developed sites.
An existing above ground installation which takes gas from the NTS and distributes it via existing infrastructure.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xv
The temporary (Work numbered 2A on the Works Plan) and temporary/permanent (Work numbered 2B
rks Plans) laydown areas required for the
The Laydown Area shown on the Works Plan and numbered Work 2A in Schedule 1 to the Order is located on the eastern side of the Power Station Complex and will be up to 3.6 ha in size. It will be
g construction of the Scheme only.
The Laydown Area shown on the Works Plan and numbered Work 2B in Schedule 1 to the Order is located adjacent to the south eastern corner of the Power Station Complex and will be up to 0.25 ha in
ng construction of the Scheme and for maintenance activities during operation.
The authority responsible for developing, maintaining and applying a strategy for local flood risk management in their areas and maintaining a register
Vehicles with a weight less than 3.5 tonnes (gross
A building that has been placed on the statutory list of buildings of Special Architectural or Historic
otected by the Planning (Listed Building and Conservation Areas) Act 1990.
Statutory designation for places with wildlife or geological features that are of special interest locally.
elected for their local nature
made deposits artificially placed comprising a wide variety of material e.g. concrete, brick etc -
stallation which takes gas from the NTS and distributes it via existing
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xvi
Maelor Gas Works Access Road
- The existing road and track between the B5130 and the Maelor Gas Works, which will be used to access the Gas Connection.
Maintenance or Maintain
- Includes to the extent assessed in the Environmental Statement, inspect, repair, adjust, alter, remove, refurbish, reconstruct, replace and improve any part, but not the whole, of the authorised development and “maintaining” is to be construe
Manual for Streets MfS The guidance produced by the Department for Transport and Department for Communities and Local Government on road layout and balancing the needs of different road users, with a focus on residential roads, dated 29 Marc
Megawatts of electrical power
MWe Measurement of electrical power.
Megawatts of thermal power
MWth Measurement of thermal power.
Milligrams per normal cubic metre
mg/ Nm3 Unit of concentration of emission limit values.
Multi Agency Geographical Information for the Countryside
MAGIC A webgeographical designations e.g. nature conservation sites, heritage sites.
Municipal Solid Waste
MSW Household waste.
National Cycle Network
NCN A network of signed and proacross the UK.
National Grid Company
NGC National Grid's principal operations are the ownership and operation of regulated electricity and gas infrastructure networks.
National Nature Reserve
NNR Statutory designations, where places wigeological features that are significant at a national level.
Natura 2000 sites - A network of European designated sites including Special Protection Areas (designated under Directive 2009/147/EC) and Special Conservation Areas as listed in
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
The existing road and track between the B5130 and the Maelor Gas Works, which will be used to access the Gas Connection.
Includes to the extent assessed in the Environmental Statement, inspect, repair, adjust, alter, remove, refurbish, reconstruct, replace and improve any part, but not the whole, of the authorised development and “maintaining” is to be construed accordingly
The guidance produced by the Department for Transport and Department for Communities and Local Government on road layout and balancing the needs of different road users, with a focus on residential roads, dated 29 March 2007.
Measurement of electrical power.
Measurement of thermal power.
Unit of concentration of emission limit values.
A web-based mapping browser showing various geographical designations e.g. nature conservation sites, heritage sites.
Household waste.
A network of signed and promoted cycle routes across the UK.
National Grid's principal operations are the ownership and operation of regulated electricity and gas infrastructure networks.
Statutory designations, where places with wildlife or geological features that are significant at a national level.
A network of European designated sites including Special Protection Areas (designated under Directive 2009/147/EC) and Special Conservation Areas as listed in Annex I and II of the EU Directive 92/43/EEC
The existing road and track between the B5130 and the Maelor Gas Works, which will be used to access
Includes to the extent assessed in the Environmental Statement, inspect, repair, adjust, alter, remove, refurbish, reconstruct, replace and improve any part, but not the whole, of the authorised development
d accordingly
The guidance produced by the Department for Transport and Department for Communities and Local Government on road layout and balancing the needs of different road users, with a focus on residential
based mapping browser showing various geographical designations e.g. nature conservation
moted cycle routes
National Grid's principal operations are the ownership and operation of regulated electricity and
th wildlife or geological features that are significant at a national
A network of European designated sites including Special Protection Areas (designated under Directive 2009/147/EC) and Special Conservation Areas as
Annex I and II of the EU Directive 92/43/EEC
Natural Resources Wales
NRW
National Policy Statements
NPS
National Transmission System
NTS
Nationally Significant Infrastructure Project
NSIP
National Air Traffic Control Services
NATS
Nitrate Vulnerable Zone
NVZ
Nitric Oxide NO
Nitrogen dioxide NO2
Oxides of nitrogen NOx
Noise Sensitive Receptor
NSR
Non-Road Mobile machinery
NRMM
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
(“Habitats Directive”)
NRW is a Welsh Government Sponsored Body, created in 2013, which took over the work of Countryside Council for Wales, Environment Agency Wales and Forestry Commission Wales.
Statement of planning policy concerning the consenting of NSIPs in the UK – designated under the Planning Act 2008. The Secretary of State must make his or her decision on an application for a DCO in accordance with a relevant NPS unless other considerations apply.
The strategic natural gas pipeline serving the UK.
As defined by the Planning Act 2008, which includes within the definition of an NSIP any onshore generating station in England and Wales of more than 50 MW.
The main air traffic control service provider within the UK.
A designated area where land drains into and contributes to nitrate found in nitratewaters.
Combustion product discharged by CCGT power station
Combustion product discharged by CCGT power station
Comprises mainly NO and NO2, combustion products discharged by CCGT power stations.
Receptors principally residential dwellings (existing or for which planning consent is being sought/ has been given) and any building used for long term rpurposes (such as a nursing home).
Construction vehicles or plant which are transported to site on low loaders as they are not suitable for driving on roads.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xvii
NRW is a Welsh Government Sponsored Body, created in 2013, which took over the work of Countryside Council for Wales, Environment Agency
Statement of planning policy concerning the designated under the
Planning Act 2008. The Secretary of State must make his or her decision on an application for a DCO in
ce with a relevant NPS unless other
The strategic natural gas pipeline serving the UK.
As defined by the Planning Act 2008, which includes e definition of an NSIP any onshore
generating station in England and Wales of more than
The main air traffic control service provider within the
and drains into and contributes to nitrate found in nitrate-polluted
Combustion product discharged by CCGT power
Combustion product discharged by CCGT power
, combustion products
Receptors principally residential dwellings (existing or for which planning consent is being sought/ has been given) and any building used for long term residential
Construction vehicles or plant which are transported to site on low loaders as they are not suitable for
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xviii
Non-Technical summary
NTS The nonStatement.
North & Mid Wales Trunk Road Agent
NMWTRA NMWTRA is responsible on behalf of Welsh Government for managing the strategic road network in North and Mid Wales
Okta - A unit used in expressing the extent of cloud cover, equal
Operation - The routine day to day functioning of the Scheme, including Maintenance activities.
Order - The Wrexham (Gas Fired Power Station) Order, being the Development Consent Order which has been applied to be made by theauthorising the Power Station Complex Site, a draft of which is submitted with the Application (Document Reference 3.1)
Order Land - The land as shown on the Land Plans (Document Reference 2.2) within which the Scheme may be carried
Order Limits - The limits shown on the Works Plans (Document Reference 2.3) within which the Power Station Complex Site may be carried out.
Ordnance Survey OS National mapping agency for Great Britain
Overhead Line OHL Network of overhead electrtransmission lines
Part II A - The section of EPA 1990 that deals with contaminated land.
Annual Average Flow Rate for surface water runoff
QBAR -
Particulate Matter PM Very small solid or liquid particles.
Pathway - The route bysource to a given receptor.
Peak Particle Velocity
PPV A term used to measure vibration through a solid surface. When a vibration is measured, the point at which the measurement takes place can be
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
The non-technical summary of the Environmental Statement.
NMWTRA is responsible on behalf of Welsh Government for managing the strategic road network in North and Mid Wales
A unit used in expressing the extent of cloud cover, equal to one eighth of the sky.
The routine day to day functioning of the Scheme, including Maintenance activities.
The Wrexham (Gas Fired Power Station) Order, being the Development Consent Order which has been applied to be made by the Secretary of State authorising the Power Station Complex Site, a draft of which is submitted with the Application (Document Reference 3.1)
The land as shown on the Land Plans (Document Reference 2.2) within which the Scheme may be carried out.
The limits shown on the Works Plans (Document Reference 2.3) within which the Power Station Complex Site may be carried out.
National mapping agency for Great Britain
Network of overhead electricity distribution and transmission lines
The section of EPA 1990 that deals with contaminated land.
-
Very small solid or liquid particles.
The route by which contamination moves from a source to a given receptor.
A term used to measure vibration through a solid surface. When a vibration is measured, the point at which the measurement takes place can be
f the Environmental
NMWTRA is responsible on behalf of Welsh Government for managing the strategic road network
A unit used in expressing the extent of cloud cover,
The routine day to day functioning of the Scheme,
The Wrexham (Gas Fired Power Station) Order, being the Development Consent Order which has been
Secretary of State authorising the Power Station Complex Site, a draft of which is submitted with the Application (Document
The land as shown on the Land Plans (Document Reference 2.2) within which the Scheme may be
The limits shown on the Works Plans (Document Reference 2.3) within which the Power Station
icity distribution and
The section of EPA 1990 that deals with contaminated
which contamination moves from a
A term used to measure vibration through a solid surface. When a vibration is measured, the point at which the measurement takes place can be
Percentage Heavy Goods Vehicles
%HGV
Percentile -
Permitted Development
-
Personal Protective Equipment
PPE
Pipeline Inspection Gauge
PIG
Planning Act 2008 PA 2008
Planning Inspectorate
PINS
Planning Policy Wales
PPW
Pollution Prevention Guidance
PPG
Potential Contaminant Linkages
PCL
Power Station -
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
considered to have a particle velocity.
Percentage of traffic that is classified as Heavy Goods Vehicles over a given period.
A value below which that percentage of data will either fall or equal. For instance, the 98thof values for a year is the value below which 98% of all of the data in the year will fall, or equal.
Development that is deemed under legislation to have planning consent without the need to obtain planning permission.
Equipment a person may wear to protect themselves from risks e.g. high-visibility jackets, gloves, steel toe capped boots.
Pipeline inspection and cleaning device.
England and Wales legislation which established the legal framework to apply for, examine and determine applications for Nationally Significant Infrastructure Projects.
Executive agency supported by the Department for Communities and Local Government which deals with planning appeals, national infrastructure, planning applications, examinations of local plans and other planning related and specialist casework in England and Wales.
Overarching land use planning policy for Wales, produced by the Welsh Government (edition 8, January 2016).
Environment Agency published guidance on pollution prevention and best practice
The existence of a contamination source and a receptor where a pathway is also present linking the two.
The power generating element of the Scheme
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xix
Percentage of traffic that is classified as Heavy Goods
A value below which that percentage of data will either fall or equal. For instance, the 98th percentile of values for a year is the value below which 98% of all of the data in the year will fall, or equal.
Development that is deemed under legislation to have planning consent without the need to obtain
Equipment a person may wear to protect themselves visibility jackets, gloves, steel toe
nd and Wales legislation which established the legal framework to apply for, examine and determine applications for Nationally Significant Infrastructure
Executive agency supported by the Department for d Local Government which deals with
planning appeals, national infrastructure, planning applications, examinations of local plans and other planning related and specialist casework in England
ning policy for Wales, (edition 8,
Environment Agency published guidance on pollution
contamination source and a receptor where a pathway is also present linking the
The power generating element of the Scheme
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xx
Complex including gas turbine building, Stack(s), HRSG(s), transformers, steam turbine building, admin/controbuilding, heat interface building, pressure regulation installation, water tanks, car parking, internal site roads, workshop, water treatment plant, switchyard, switchgear room and surface and foul water drainage (please refer to Works numbered 1A to 1GSchedule 1 to the Order).
Power Station Complex Site
The Power Station Complex, Laydown Areas, surface water drainage, landscaping and ecological mitigation,Schedule 1 to the Order and as shown on the Works Plan)
Preliminary Environmental Information Report
PEIR A report describing the preliminary environmental assessment during the preNSIP.
Pressure Regulating Installation
PRI Part of the Power Station Complex where the gas is receivconditions the gas before use in the gas turbine(s)
Previous Scheme The scheme proposed by WPL in 2011, for a power station with a generating capacity of up to detailed in the Previous Scoping Report and whibeen superseded by the Scheme which is the subject of the Application.
Previous Scoping Opinion
The Scoping Opinion issued by the Secretary of State in January 2013.
Previous Scoping Report
The Scoping Report submitted by WPL to the Secretary
Public Right of Way PRoW Paths on which the public have legally protected rights to pass.
Ramsar site A designation for wetlands of International importance.
Receptor - An identified aspect of the environment residwater etc as such, has been assessed as part of the EIA undertaken.
Registered Parks and Gardens and designed landscapes of special architectural and his
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
including gas turbine building, Stack(s), HRSG(s), transformers, steam turbine building, admin/controbuilding, heat interface building, pressure regulation installation, water tanks, car parking, internal site roads, workshop, water treatment plant, switchyard, switchgear room and surface and foul water drainage (please refer to Works numbered 1A to 1GSchedule 1 to the Order).
The Power Station Complex, Laydown Areas, surface water drainage, landscaping and ecological mitigation, (Works numbered 1, 2, 3, 4 and 5 in Schedule 1 to the Order and as shown on the Works Plan).
A report describing the preliminary environmental assessment during the pre-application process of an NSIP.
Part of the Power Station Complex where the gas is received from the Gas Connection. The PRI conditions the gas before use in the gas turbine(s)
The scheme proposed by WPL in 2011, for a power station with a generating capacity of up to 1,200 MWdetailed in the Previous Scoping Report and whibeen superseded by the Scheme which is the subject of the Application.
The Scoping Opinion issued by the Secretary of State in January 2013.
The Scoping Report submitted by WPL to the Secretary of State in November 2012.
Paths on which the public have legally protected rights to pass.
A designation for wetlands of International importance.
An identified aspect of the environment -resident, protected species, heritage asset, controlled water etc - that may be affected by the Scheme and, as such, has been assessed as part of the EIA undertaken.
Gardens and designed landscapes of special architectural and historic importance, placed on a
including gas turbine building, Stack(s), HRSG(s), transformers, steam turbine building, admin/control building, heat interface building, pressure regulation installation, water tanks, car parking, internal site roads, workshop, water treatment plant, switchyard, switchgear room and surface and foul water drainage (please refer to Works numbered 1A to 1G in
The Power Station Complex, Laydown Areas, surface water drainage, landscaping and ecological
(Works numbered 1, 2, 3, 4 and 5 in Schedule 1 to the Order and as shown on the Works
A report describing the preliminary environmental application process of an
Part of the Power Station Complex where the gas is ed from the Gas Connection. The PRI
conditions the gas before use in the gas turbine(s)
The scheme proposed by WPL in 2011, for a power 1,200 MWe
detailed in the Previous Scoping Report and which has been superseded by the Scheme which is the subject
The Scoping Opinion issued by the Secretary of State
The Scoping Report submitted by WPL to the
Paths on which the public have legally protected
A designation for wetlands of International
- e.g. a ent, protected species, heritage asset, controlled
that may be affected by the Scheme and, as such, has been assessed as part of the EIA
Gardens and designed landscapes of special toric importance, placed on a
Gardens
Remediation -
River Basin Management Plan
RBMP
Rochdale Envelope -
Scheduled Monument
SM
Scheme (also referred to as the "WEC")
-
Scoping Opinion -
ScottishPower Electricity Networks or SP Manweb plc
SPEN
Secretary of State SoS
Site (also referred to as the "WEC Site")
-
Site of Nature Conservation
SNCI
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
register by Cadw.
The clean-up of contaminated soil to make it suitable and safe for future use.
A management tool created by Natural Resources Wales to use for integrated water management.
The Rochdale cases provide the basis upon which a project can be described by a series of maximum extents – the ‘worst case’ scenario - allowing the detailed design of the scheme to vary within this ‘envelope’ without invalidating the corresponding EIA. This envelope has been assessed in the EIA for the Scheme.
A "nationally important" archaeological site or historic building, protected under the Ancient Monuments and Archaeological Areas Act 1979.
The construction, operation, maintenance and eventual decommissioning of the Power Station Complex Site (Work numbered 1-5 in Schedule 1 to the Order) and the Gas Connection.
The Scoping Opinion provided by the Secretary of State in May 2014 and included in the Appendices to the Environmental Statement (Document Reference 6.4, Appendix 5.1).
Company which operates the electrical distribution network in the North Wales and Cheshire area.
The decision maker for a NSIP application and head of the relevant government department. In the context of the Application the decision maker is the Secretary of State for Energy and Climate Change.
The area in which the Scheme will be constructed, operated and decommissioned as defined by the Order Land.
Non-statutory areas of local importance for nature conservation.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xxi
up of contaminated soil to make it suitable
A management tool created by Natural Resources resources
The Rochdale cases provide the basis upon which a project can be described by a series of maximum
allowing the detailed design of the scheme to vary within this
ithout invalidating the corresponding EIA. This envelope has been assessed in the EIA for
A "nationally important" archaeological site or historic building, protected under the Ancient
Act 1979.
The construction, operation, maintenance and eventual decommissioning of the Power Station
5 in Schedule 1 to
ng Opinion provided by the Secretary of State in May 2014 and included in the Appendices to the Environmental Statement (Document Reference
l distribution network in the North Wales and Cheshire area.
The decision maker for a NSIP application and head of the relevant government department. In the context of the Application the decision maker is the Secretary
The area in which the Scheme will be constructed, operated and decommissioned as defined by the
mportance for nature
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xxii
Interest
Site of Special Scientific Interest
SSSI A geological or biological conservation designation denoting a protected area in the UK.
Site Waste Management Plan
SWMP The strategic document dealing with the effective manageand the operation of the Scheme ensuring that waste is considered at all stages of the Scheme. will form part of the CEMP for the Scheme.
Spraint - Otter Faeces
Soil Framework Directive 2006
SFD Propopromote the sustainable use of soil and protect soil as a natural resource.
Sound Power Level SWL The Sound Energy flow per unit of time.
Sound Pressure Level SPL Logarithmic measure of the sound pressure ofsound relative to a reference value, the threshold of hearing.
Special Area of Conservation
SAC Area of protected habitats and species as defined in the European Union's Habitat Directive (92/43/EEC).
Special Landscape Areas
SLA Local designation to significant and attractive landscapes.
Special Protection Area
SPA A designated area for birds under the European Union Directive on the Conservation of Wild Birds (2009/147/EC)
Stack(s) - The structure by which the exhausheat from the Power Station Complex will be emitted to the atmosphere during Operation.
Statement of Community Consultation
SoCC A statement describing how an applicant proposes to consult the local community about a project.
SuDs Approval Body SAB -
Sulphur Oxides SOx One of the combustion products discharged by CCGT power stations.
Sustainable Drainage Systems
SuDS Water management practices and facilities that drain surface water more sustainably than the conventional practi
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
A geological or biological conservation designation denoting a protected area in the UK.
The strategic document dealing with the effective management of materials used for the construction and the operation of the Scheme ensuring that waste is considered at all stages of the Scheme. The SWMP will form part of the CEMP for the Scheme.
Otter Faeces
Proposed Directive (proposal withdrawn in 2014) to promote the sustainable use of soil and protect soil as a natural resource.
The Sound Energy flow per unit of time.
Logarithmic measure of the sound pressure ofsound relative to a reference value, the threshold of hearing.
Area of protected habitats and species as defined in the European Union's Habitat Directive (92/43/EEC).
Local designation to provide protection for locally significant and attractive landscapes.
A designated area for birds under the European Union Directive on the Conservation of Wild Birds (2009/147/EC)
The structure by which the exhaust gases and waste heat from the Power Station Complex will be emitted to the atmosphere during Operation.
A statement describing how an applicant proposes to consult the local community about a project.
-
One of the combustion products discharged by CCGT power stations.
Water management practices and facilities that drain surface water more sustainably than the conventional practice of routing run-off through a pipe to a
A geological or biological conservation designation
The strategic document dealing with the effective ment of materials used for the construction
and the operation of the Scheme ensuring that waste The SWMP
sed Directive (proposal withdrawn in 2014) to promote the sustainable use of soil and protect soil as
Logarithmic measure of the sound pressure of a sound relative to a reference value, the threshold of
Area of protected habitats and species as defined in the European Union's Habitat Directive (92/43/EEC).
provide protection for locally
A designated area for birds under the European Union Directive on the Conservation of Wild Birds
t gases and waste heat from the Power Station Complex will be emitted
A statement describing how an applicant proposes to
One of the combustion products discharged by CCGT
Water management practices and facilities that drain surface water more sustainably than the conventional
off through a pipe to a
Switchgear -
Technical Advice Notes
TAN
Tonnes per annum tpa
Town and Country Planning Act 1990
TCPA 1990
Transport Analysis Guidance
TAG
Tree Preservation Order
TPO
Urban Wastewater Treatment Directive
-
Waste (England & Wales) Regulations 2011
-
Waste Framework Directive
WaFD
Water Framework Directive
WFD
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
watercourse.
The combination of switches, fuses or circuit breakers used to control, protect and isolate electrical equipment. Can be air-insulated or gas-insulated.
Technical Advice Notes produced by the Welsh Government which provide detailed planning guidance on technical issues.
Unit for measuring waste produced.
TCPA 1990 The Act which consolidates certain enactments relating to town and country planning (excluding special controls in respect of buildings and areas of special architectural or historic interest and in respect of hazardous substances)
Guidance from the Department for Transport on how to assess transportation schemes first published on 29 October 2013 and last updated on 10 November 2014.
A written order made by the local authority which makes it an offence to intentionally damage orremove a tree protected by that order without the authority's permission.
A European Directive to protect the environment from the adverse effects of urban waste water.
Legislation for waste prevention, management and introduction of waste hierarchy.
The Waste Framework Directive is a European Union Directive which requires all EU states to take the necessary measures to ensure waste is recdisposed of without endangering human health or causing harm to the environment. It has been transposed to the Waste (England & Waste) Regulations in 2011.
The Water Framework Directive is a European Union directive which commits EU member states to achieve good qualitative and quantitative status of all
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xxiii
The combination of switches, fuses or circuit breakers used to control, protect and isolate electrical
insulated.
hnical Advice Notes produced by the Welsh Government which provide detailed planning
enactments relating to town and country planning (excluding special controls in respect of buildings and areas of special architectural or historic interest and in respect
nt for Transport on how to assess transportation schemes first published on 29 October 2013 and last updated on 10 November
A written order made by the local authority which makes it an offence to intentionally damage or remove a tree protected by that order without the
A European Directive to protect the environment from the adverse effects of urban waste water.
Legislation for waste prevention, management and
The Waste Framework Directive is a European Union Directive which requires all EU states to take the necessary measures to ensure waste is recovered or disposed of without endangering human health or causing harm to the environment. It has been transposed to the Waste (England & Waste)
The Water Framework Directive is a European Union e which commits EU member states to
achieve good qualitative and quantitative status of all
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xxiv
water bodies by 2015.
Water Resources Act 1991
WRA Legislation to prevent and minimise pollution of water.
Welsh Government - Welsh Government is the devolved GoWales with responsibility for the economy, education, health, planning, and other policy areas.
Welsh Water Supplies wastewater services within the Scheme area.
Weighted Sound Reduction Index
Rw Singleairborne sound insulation of a material or building element over a range of frequencies when tested in a laboratory.
Wildlife and Countryside Act 1981
Legislation which protects animals, plants and certain habitats in the UK.
Wrexham Energy Centre (also referred to as the "Scheme")
WEC The construction, operation, maintenance and eventual decommissioning of the Power Station Complex Site (Work numbered 1the Order) and the Gas Connection.
WEC Site (also referred to as the “Site”)
- The area in which the Scheme will be constructed, operated and decommissioned as defined by the Order Land.
Wrexham County Borough Council
WCBC The unitary authority area within which the Scheme is located
Wrexham Industrial Estate
WIE The substantiaWrexham within which the Power Station Complex Site will be located.
Wrexham Power Limited
WPL The applicant and developer of the Scheme.
World Health Organisation
WHO A United Nations agency concerned with public heal
Works Plan - The plan showing the the limits (and limits of deviations) within which the Power Station Complex Site may be carried out (Document Reference 2.3).
Zone of Theoretical Visibility
ZTV A computer generated of the surroundings within which a project could
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
water bodies by 2015.
Legislation to prevent and minimise pollution of water.
Welsh Government is the devolved Government for Wales with responsibility for the economy, education, health, planning, and other policy areas.
Supplies wastewater services within the Scheme area.
Single-number quantity which characterises airborne sound insulation of a material or building element over a range of frequencies when tested in a laboratory.
Legislation which protects animals, plants and certain habitats in the UK.
The construction, operation, maintenance and eventual decommissioning of the Power Station Complex Site (Work numbered 1-5 in Schedule 1 to the Order) and the Gas Connection.
The area in which the Scheme will be constructed, operated and decommissioned as defined by the Order Land.
The unitary authority area within which the Scheme is located
The substantial industrial estate to the east of Wrexham within which the Power Station Complex Site will be located.
The applicant and developer of the Scheme.
A United Nations agency concerned with public health.
The plan showing the Power Station Complex Site and the limits (and limits of deviations) within which the Power Station Complex Site may be carried out (Document Reference 2.3).
A computer generated plan showing a maximum area of the surroundings within which a project could
Legislation to prevent and minimise pollution of
vernment for Wales with responsibility for the economy, education,
Supplies wastewater services within the Scheme area.
number quantity which characterises the airborne sound insulation of a material or building element over a range of frequencies when tested in a
Legislation which protects animals, plants and certain
The construction, operation, maintenance and eventual decommissioning of the Power Station
5 in Schedule 1 to
The area in which the Scheme will be constructed, operated and decommissioned as defined by the
The unitary authority area within which the Scheme is
l industrial estate to the east of Wrexham within which the Power Station Complex
A United Nations agency concerned with public
Power Station Complex Site and the limits (and limits of deviations) within which the Power Station Complex Site may be carried out
plan showing a maximum area of the surroundings within which a project could
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
theoretically be viewed.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
xxv
I. Wrexham Power Limited (WPL) is proposing to construct, maintain and operate a gas-fired power station on land at Wrexham Industto the east of Wrexham.
II. The Scheme includes a Combined Cycle Gas Turbine (CCGT) Power Station. To operate, it will require a connection to the gas transmission network for importing the natural gas fuel, and a connection to the electrexport the power generated.
III. The Power Station Complex Site and the Gas Connection (together they are referred to as the Wrexham Energy Centre (‘WEC’) or the ‘Scheme’) have separate consenting requirements. However, the Environmental Sta(ES) assesses both elements in order to identify, insofar as possible, the likely significant environmental effects of the Scheme as a whole. As such, this CEMP also considers the Scheme as a whole.
IV. A description of the Scheme is provided in chapterStation Complex would be fuelled by natural gas and would have an electrical generation capacity of up to 299 megawatts (MWgenerated would be exported to the local 132kV electrical distribution network currently operated by Scottish Power Energy Networks (SPEN).
V. The location of the Scheme, which includes the Power Station Complex and Gas Connection (approximately 3.5 km in length) is shown in Figure below. The proposed Power Station Complex Site is situated immediate north-east of Wrexham Industrial Estate in an area dominated by industrial complexes, to the west and south, and by agricultural land, to the north and east. The Gas Connection Route runs through agricultural land to the south and east of Installation (AGI) adjacent to the Maelor Gas Works approximately 2.5 km to the south west.
VI. This draft CEMP describes the procedures and principles that will be implemented during the construction phase of themeasures that will be applied to mitigate potentially adverse effects on the environment from the construction of the Scheme. It is being submitted as an appendix to the Environmental Statement (ES) for the Scheme as part of the Application for the Order Connection and will be further developed with, and submitted for approval by Wrexham Countyauthority in advance of any construction
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
u Executive summary
Wrexham Power Limited (WPL) is proposing to construct, maintain and fired power station on land at Wrexham Industrial Estate (WIE),
to the east of Wrexham.
The Scheme includes a Combined Cycle Gas Turbine (CCGT) Power Station. To operate, it will require a connection to the gas transmission network for importing the natural gas fuel, and a connection to the electricity network to export the power generated.
The Power Station Complex Site and the Gas Connection (together they are referred to as the Wrexham Energy Centre (‘WEC’) or the ‘Scheme’) have separate consenting requirements. However, the Environmental Sta(ES) assesses both elements in order to identify, insofar as possible, the likely significant environmental effects of the Scheme as a whole. As such, this CEMP also considers the Scheme as a whole.
A description of the Scheme is provided in chapter 4 of the ES. Station Complex would be fuelled by natural gas and would have an electrical generation capacity of up to 299 megawatts (MWe). The electricity generated would be exported to the local 132kV electrical distribution
y operated by Scottish Power Energy Networks (SPEN).
The location of the Scheme, which includes the Power Station Complex and Gas Connection (approximately 3.5 km in length) is shown in Figure below. The proposed Power Station Complex Site is situated
east of Wrexham Industrial Estate in an area dominated by industrial complexes, to the west and south, and by agricultural land, to the north and east. The Gas Connection Route runs through agricultural land to the south and east of Wrexham Industrial Estate to the Above Ground Installation (AGI) adjacent to the Maelor Gas Works approximately 2.5 km to
This draft CEMP describes the procedures and principles that will be implemented during the construction phase of the Scheme, and the specific measures that will be applied to mitigate potentially adverse effects on the environment from the construction of the Scheme. It is being submitted as an appendix to the Environmental Statement (ES) for the Scheme as part of the
pplication for the Order and the TCPA 1990 application for the Gas and will be further developed with, and submitted for approval
Wrexham County Borough Council (WCBC) as the relevant planning authority in advance of any construction activity.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
1
summary
Wrexham Power Limited (WPL) is proposing to construct, maintain and rial Estate (WIE),
The Scheme includes a Combined Cycle Gas Turbine (CCGT) Power Station. To operate, it will require a connection to the gas transmission network for
icity network to
The Power Station Complex Site and the Gas Connection (together they are referred to as the Wrexham Energy Centre (‘WEC’) or the ‘Scheme’) have separate consenting requirements. However, the Environmental Statement (ES) assesses both elements in order to identify, insofar as possible, the likely significant environmental effects of the Scheme as a whole. As such, this
The Power Station Complex would be fuelled by natural gas and would have an electrical
The electricity generated would be exported to the local 132kV electrical distribution
y operated by Scottish Power Energy Networks (SPEN).
The location of the Scheme, which includes the Power Station Complex and Gas Connection (approximately 3.5 km in length) is shown in Figure 1.1 below. The proposed Power Station Complex Site is situated to the
east of Wrexham Industrial Estate in an area dominated by industrial complexes, to the west and south, and by agricultural land, to the north and east. The Gas Connection Route runs through agricultural land to
Wrexham Industrial Estate to the Above Ground Installation (AGI) adjacent to the Maelor Gas Works approximately 2.5 km to
This draft CEMP describes the procedures and principles that will be Scheme, and the specific
measures that will be applied to mitigate potentially adverse effects on the environment from the construction of the Scheme. It is being submitted as an appendix to the Environmental Statement (ES) for the Scheme as part of the
and the TCPA 1990 application for the Gas and will be further developed with, and submitted for approval
as the relevant planning
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
2
VII. The CEMP is Requirement not be commenced until the CEMP (such CEMP must be substantially in accordance with this draft CEMP) has been submitted to and approved by the relevant planning authority. Thebe constructed in accordance with the CEMPplanning authority.
VIII. The construction of the Scheme will require defined roles and responsibilities to ensure that required actions are undertaken; in padefined responsibilities for the seniorand senior environmental specialist (project environmentalthis, all construction personnel involved in the construction of the Scheme must understand the content and purpose of the CEMP and receive the necessary training to allowinternal communications, training and briefing.
IX. A community liaison developed for the Scheme. Responsibility for implementingthe project lead.
X. The environmental performance of the audited, with environmentalverifications undertaken.
XI. Management controls are described covering the environmental topics of nuisance and pollution,and water consumption.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Requirement 4 within Schedule 2 of the Order. The Schemenot be commenced until the CEMP (such CEMP must be substantially in
this draft CEMP) has been submitted to and approved by the relevant planning authority. The Requirement ensures that the Scheme will be constructed in accordance with the CEMP approved by the relevant
The construction of the Scheme will require defined roles and responsibilities required actions are undertaken; in particular there are
defined responsibilities for the senior construction manager (project lead) and senior environmental specialist (project environmental lead). Beyond this, all construction personnel involved in the construction of the Scheme
and the content and purpose of the CEMP and receive the necessary training to allow them to implement it. This will require robust internal communications, training and briefing.
A community liaison strategy, including a complaints procedure, oped for the Scheme. Responsibility for implementing this will be with
The environmental performance of the Scheme will be monitored and audited, with environmental performance indicators set and inspections and verifications undertaken.
Management controls are described covering the environmental topics of nuisance and pollution, ground conditions, waste, and energy, material use and water consumption.
The Scheme may not be commenced until the CEMP (such CEMP must be substantially in
this draft CEMP) has been submitted to and approved by the rement ensures that the Scheme will
approved by the relevant
The construction of the Scheme will require defined roles and responsibilities rticular there are
construction manager (project lead) lead). Beyond
this, all construction personnel involved in the construction of the Scheme and the content and purpose of the CEMP and receive the
them to implement it. This will require robust
strategy, including a complaints procedure, will be this will be with
cheme will be monitored and performance indicators set and inspections and
Management controls are described covering the environmental topics of ground conditions, waste, and energy, material use
SCHEME OUTLINE
1.1 Wrexham Power Limited (WPL) is proposing togas-fired power station on land at Wrexham Industrial Estate (WIE), to the east of Wrexham.
1.2 The Scheme includes a Combined Cycle Gas Turbine (CCGT) Power Station. To operate, it will require a connection to the gas trathe natural gas fuel, and a connection to the electricity network to export the power generated.
1.3 The Power Station Complex Site and the Gas Connection (together they are referred to as the Wrexham Energy Centre (‘WEC’) or requirements. However, the Environmental Statement (ES) assesses both elements in order to identify, insofar as possible, the likely significant environmental effects of the Scheme as a whole. As such, this CEMP also
1.4 The Power Station Complex would be fuelled by natural gas and would have an electrical generation capacity of up to 299 megawatts (MWgenerated would be exported to the local 132kV electrical distributicurrently operated by Scottish Power Energy Networks (SPEN).
1.5 The location of the Scheme, which includes the Power Station Complex and Gas Connection (approximately 3.5 km in length) is shown in Figure proposed Power Station CompleWrexham Industrial Estate in an area dominated by industrial complexes, to the west and south, and by agricultural land, to the north and east. The Gas Connection Route runs through agricultural land to thethe Above Ground Installation (AGI) adjacent to the Maelor Gas Works approximately 2.5 km to the south west.
1.6 Figure 1-1, below, shows the key features and environmental designationslocale of the Site.
1.7 The Scheme comprises:
• a combined cycle gas turbine (CCGT) power station (the "Power Station Complex") (work numbered 1 in Schedule 1 to the Order) which would be fuelled by natural gas and would have an electrical generation capto 299 megawatts (MWe);
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Chapter 1 u Introduction
Wrexham Power Limited (WPL) is proposing to construct, maintain and operate a fired power station on land at Wrexham Industrial Estate (WIE), to the east of
The Scheme includes a Combined Cycle Gas Turbine (CCGT) Power Station. To operate, it will require a connection to the gas transmission network for importing the natural gas fuel, and a connection to the electricity network to export the power
The Power Station Complex Site and the Gas Connection (together they are referred to as the Wrexham Energy Centre (‘WEC’) or the ‘Scheme’) have separate consenting requirements. However, the Environmental Statement (ES) assesses both elements in order to identify, insofar as possible, the likely significant environmental effects of the Scheme as a whole. As such, this CEMP also considers the Scheme as a whole.
The Power Station Complex would be fuelled by natural gas and would have an electrical generation capacity of up to 299 megawatts (MWe). The electricity generated would be exported to the local 132kV electrical distribution network currently operated by Scottish Power Energy Networks (SPEN).
The location of the Scheme, which includes the Power Station Complex and Gas Connection (approximately 3.5 km in length) is shown in Figure 1.1 below. The proposed Power Station Complex Site is situated to the immediate northWrexham Industrial Estate in an area dominated by industrial complexes, to the west and south, and by agricultural land, to the north and east. The Gas Connection Route runs through agricultural land to the south and east of Wrexham Industrial Estate to the Above Ground Installation (AGI) adjacent to the Maelor Gas Works approximately 2.5 km to the south west.
, below, shows the key features and environmental designations
a combined cycle gas turbine (CCGT) power station (the "Power Station Complex") (work numbered 1 in Schedule 1 to the Order) which would be fuelled by natural gas and would have an electrical generation capto 299 megawatts (MWe);
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
3
Introduction
construct, maintain and operate a fired power station on land at Wrexham Industrial Estate (WIE), to the east of
The Scheme includes a Combined Cycle Gas Turbine (CCGT) Power Station. To nsmission network for importing
the natural gas fuel, and a connection to the electricity network to export the power
The Power Station Complex Site and the Gas Connection (together they are referred the ‘Scheme’) have separate consenting
requirements. However, the Environmental Statement (ES) assesses both elements in order to identify, insofar as possible, the likely significant environmental effects of
considers the Scheme as a whole.
The Power Station Complex would be fuelled by natural gas and would have an The electricity
on network
The location of the Scheme, which includes the Power Station Complex and Gas below. The
x Site is situated to the immediate north-east of Wrexham Industrial Estate in an area dominated by industrial complexes, to the west and south, and by agricultural land, to the north and east. The Gas Connection Route
south and east of Wrexham Industrial Estate to the Above Ground Installation (AGI) adjacent to the Maelor Gas Works
, below, shows the key features and environmental designations in the
a combined cycle gas turbine (CCGT) power station (the "Power Station Complex") (work numbered 1 in Schedule 1 to the Order) which would be fuelled by natural gas and would have an electrical generation capacity of up
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
4
• the temporary and permanent Laydown Areas (works numbered 2A and 2B respectively in Schedule 1 to the Order);
• surface water drainage works (work numbered 3 in Schedule 1 to the Order);
• the landscaping and ecological mitiSchedule 1 to the Order);
• the alteration and use of the Kingmoor Park Access Road (work numbered 5 in Schedule 1 to the Order) (together the “Power Station Complex Site”);
• the gas connection and an Above Ground InstallationConnection").
1.8 A description of the Scheme is provided in chapters Statement (ES) (document reference 6.2).
1.9 This draft CEMP is an Appendix to c
Figure 1-1: The Scheme Setting and Key Features and Environmental Designations
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
the temporary and permanent Laydown Areas (works numbered 2A and 2B respectively in Schedule 1 to the Order);
surface water drainage works (work numbered 3 in Schedule 1 to the Order);
the landscaping and ecological mitigation works (work numbered 4 in Schedule 1 to the Order);
the alteration and use of the Kingmoor Park Access Road (work numbered 5 in Schedule 1 to the Order) (together the “Power Station Complex Site”);
the gas connection and an Above Ground Installation (AGI) (the "Gas
A description of the Scheme is provided in chapters 1and 4 of the Environmental (ES) (document reference 6.2).
is an Appendix to chapter 19 (mitigation summary) of the ES.
Setting and Key Features and Environmental Designations
the temporary and permanent Laydown Areas (works numbered 2A and 2B
surface water drainage works (work numbered 3 in Schedule 1 to the Order);
gation works (work numbered 4 in
the alteration and use of the Kingmoor Park Access Road (work numbered 5 in Schedule 1 to the Order) (together the “Power Station Complex Site”);
(AGI) (the "Gas
of the Environmental
on summary) of the ES.
PURPOSE OF THE CEMP
1.10 This draft CEMP describes the procedures and principles that will be implemented during the construction phase of the Scheme, and the specific measuresapplied to mitigate potentially adverse effects on the environment from the construction of the Scheme. It is being submitted as an appendix to the ES for the Scheme as part of the Application for the Order and Gas Connection and will be further developed with, and submitted for approval by WCBC as the relevant planning authority in advance of any construction activity on the WEC Site.
1.11 As detailed design of the Scheme progresses and an engineering procurement contract (EPC) contractor is engaged, a further version of the CEMP (substantially in accordance with this draft CEMP) will be submitted to the relevant planning authority for approval. The CEMP will have detail added to it, reflecting the increasing certainty of design and construction procedures for the Scheme. It will include detailed plans for specific topics, including:
• Site Waste Management Plan (SWMP);
• Nuisance management, including measures to avoid or minimise the impacts of construction works (coverin
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
This draft CEMP describes the procedures and principles that will be implemented during the construction phase of the Scheme, and the specific measures applied to mitigate potentially adverse effects on the environment from the construction of the Scheme. It is being submitted as an appendix to the ES for the Scheme as part of the Application for the Order and TCPA 1990 application for the
will be further developed with, and submitted for approval by as the relevant planning authority in advance of any construction activity on
As detailed design of the Scheme progresses and an engineering procurement ract (EPC) contractor is engaged, a further version of the CEMP (substantially in
accordance with this draft CEMP) will be submitted to the relevant planning authority for approval. The CEMP will have detail added to it, reflecting the
of design and construction procedures for the Scheme. It will include detailed plans for specific topics, including:
Site Waste Management Plan (SWMP);
Nuisance management, including measures to avoid or minimise the impacts of construction works (covering dust, lighting, noise and vibration).
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
5
This draft CEMP describes the procedures and principles that will be implemented that will be
applied to mitigate potentially adverse effects on the environment from the construction of the Scheme. It is being submitted as an appendix to the ES for the
TCPA 1990 application for the will be further developed with, and submitted for approval by
as the relevant planning authority in advance of any construction activity on
As detailed design of the Scheme progresses and an engineering procurement ract (EPC) contractor is engaged, a further version of the CEMP (substantially in
accordance with this draft CEMP) will be submitted to the relevant planning authority for approval. The CEMP will have detail added to it, reflecting the
of design and construction procedures for the Scheme. It will
Nuisance management, including measures to avoid or minimise the impacts of
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
6
Chapter 2
LEGAL REQUIREMENTS, STANDARDS AND POLICI
2.1 The construction phase of the Scheme will comply with all applicable legislation and regulations. All relevant permits and consents will be a(Other Consents and Licences (Implementation section below
2.2 The Scheme will have a register of legislation, which the ProjEnvironmental Lead (refer to Implementation section below) will be responsible for maintaining and updating the CEMP to take account of any changes in legislation or regulations. The register will also include standards and requirements from ostatutory authorities including
2.3 The Project Lead will also arrange for any such changes to be communicated to all relevant personnel through various means, such as environmental alnewsletters, briefings and toolbox talks. The register will be updated on a monthly basis, and revised as required to include
2.4 The Environmental Monitoring and Auditing how specific impacts have beenenvironment or receptors. Then the mitigationdiscussed along with the reduction in the potential risk of impact. Itpotential cumulative impacts with other schemes.
Construction (Design and Management) Regulations 2015 (CDM)
2.5 The construction of the Scheme will be compliant with the CDM Regulations. These regulations impose requirements on dutyholders to minimise risks to health and safety. These dutyholders include tcontractors, the client and individual workers.
DCO REQUIREMENT
2.6 The CEMP is Requirement 4 commenced until the CEMP (such CEMP must be substantially in accordancethis draft CEMP) has been submitted to and approved by the relevant planning authority. The Requirement ensures that the Scheme will be constructed in accordance with the CEMP approved by the relevant planning authority.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Chapter 2 u Planning and Legal Context
STANDARDS AND POLICIES
The construction phase of the Scheme will comply with all applicable legislation and regulations. All relevant permits and consents will be applied for and complied with
Licences (Document reference 5.6)). The Project Lead (refer to Implementation section below in chapter 3) has the responsibility to ensure this.
The Scheme will have a register of legislation, which the Project Lead and Environmental Lead (refer to Implementation section below) will be responsible for maintaining and updating the CEMP to take account of any changes in legislation or regulations. The register will also include standards and requirements from ostatutory authorities including WCBC, NRW and the Environment Agency,
The Project Lead will also arrange for any such changes to be communicated to all personnel through various means, such as environmental al
toolbox talks. The register will be updated on a monthly basis, and revised as required to include new aspects and impacts.
Monitoring and Auditing section below in chapter 4how specific impacts have been identified, and prioritised in terms of their risk to the environment or receptors. Then the mitigation measures to be employed are discussed along with the reduction in the potential risk of impact. It also considers potential cumulative impacts with other schemes.
Construction (Design and Management) Regulations 2015 (CDM)
The construction of the Scheme will be compliant with the CDM Regulations. These regulations impose requirements on dutyholders to minimise risks to health and safety. These dutyholders include the designer, principal contractor, other contractors, the client and individual workers.
4 within Schedule 2 of the Order. The Scheme may not be commenced until the CEMP (such CEMP must be substantially in accordancethis draft CEMP) has been submitted to and approved by the relevant planning authority. The Requirement ensures that the Scheme will be constructed in accordance with the CEMP approved by the relevant planning authority.
Planning and Legal Context
The construction phase of the Scheme will comply with all applicable legislation and pplied for and complied with
ocument reference 5.6)). The Project Lead (refer to ) has the responsibility to ensure this.
ect Lead and Environmental Lead (refer to Implementation section below) will be responsible for maintaining and updating the CEMP to take account of any changes in legislation or regulations. The register will also include standards and requirements from other
the Environment Agency, inter alia.
The Project Lead will also arrange for any such changes to be communicated to all personnel through various means, such as environmental alerts,
toolbox talks. The register will be updated on a monthly
in chapter 4 describes , and prioritised in terms of their risk to the
measures to be employed are also considers
The construction of the Scheme will be compliant with the CDM Regulations. These regulations impose requirements on dutyholders to minimise risks to health and
he designer, principal contractor, other
within Schedule 2 of the Order. The Scheme may not be commenced until the CEMP (such CEMP must be substantially in accordance with this draft CEMP) has been submitted to and approved by the relevant planning authority. The Requirement ensures that the Scheme will be constructed in
SCHEME STRUCTURE AND RESPONSIBIL
3.1 The construction of the Scheme will require a series of defined rolesdutyholders as defined in the CDM Regulationsindividuals will personally approve and support the CEMP, and be respimplementation
Project Lead
3.2 A senior construction manager (the Project Lead) will be responsible for implementing the work packages comprising the construction of the Scheme. The Project Lead's responsibilities will include:
• ensuring that construction is undertaken in accordance with the relevant Requirements in the Order;
• maintaining the CEMP;
• advising the project team on any changes to environmental requirements, programme or construction activities;
• specifying targets, environmental perfomeasures to be incorporated within the CEMP;
• ensuring the appointedaccordance with project
• signing off method statements ahead of any numbered work packaundertaken to ensure environmental compliance.
Project Environmental Lead
3.3 A senior environmental specialist (the Project Environmental Lead) responsible for managing the environmental aspects of the construction of the Scheme. The Project Environmental Lead's responsibilities will include:
• maintaining the CEMP in conjunction with Project Lead
• ensuring adequate monitoring, audit and inspection of EPIs and other environmental construction aspects and impacts;
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Chapter 3 u Implementation
TURE AND RESPONSIBILITIES
The construction of the Scheme will require a series of defined roles, in particular dutyholders as defined in the CDM Regulations. In particular, the following individuals will personally approve and support the CEMP, and be responsible for its
A senior construction manager (the Project Lead) will be responsible for implementing the work packages comprising the construction of the Scheme. The Project Lead's responsibilities will include:
onstruction is undertaken in accordance with the relevant Order;
advising the project team on any changes to environmental requirements, construction activities;
specifying targets, environmental performance indicators (EPIs) and mitigation be incorporated within the CEMP;
appointed EPC contractor and any subcontractors work in accordance with project procedures; and
signing off method statements ahead of any numbered work packaensure environmental compliance.
A senior environmental specialist (the Project Environmental Lead) responsible for environmental aspects of the construction of the Scheme. The Project
responsibilities will include:
in conjunction with Project Lead;
ensuring adequate monitoring, audit and inspection of EPIs and other construction aspects and impacts;
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
7
Implementation
, in particular . In particular, the following
onsible for its
A senior construction manager (the Project Lead) will be responsible for implementing the work packages comprising the construction of the Scheme. The
onstruction is undertaken in accordance with the relevant
advising the project team on any changes to environmental requirements,
rmance indicators (EPIs) and mitigation
EPC contractor and any subcontractors work in
signing off method statements ahead of any numbered work packages being
A senior environmental specialist (the Project Environmental Lead) responsible for environmental aspects of the construction of the Scheme. The Project
ensuring adequate monitoring, audit and inspection of EPIs and other
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
8
• ensuring that construction of the Schemrelevant, European and UK environmental regulations and legislation; and
• ensuring compliance with the Requirements in the Order (see Schedule 2 of the draft Order (Document reference 3.1)) and permits as required (Other Consents and reference 5.6)).
Environment, Health and Safety Function
3.4 This role supports the Project Environmental Lead and the Project Lead. responsible for all environmental andthe Scheme.
TRAINING, AWARENESS AND COMPETENCE
3.5 All construction personnel involved in the construction of the Scheme must understand the content and purpose of the CEMP and receive the necessary training to allow them to implement it. This training will vary, depending on roles and the level of control personnel have over matters that can affect environmental impact during construction.
3.6 Environmental training will be provided to all personnel working on the consof the Scheme. This will be appropriate to their level and role, and will include any subcontractors and the wider supply chain, as appropriate. Typical examples of training, and the participants at whom the training will be targeted, are shown below.
3.7 All WEC Site personnel (including all new starters):
• Company induction element
• Toolbox talks – spill prevention and cleanecological constraints and others as required.
3.8 Shift leaders, site management and environmental specialists:
• Relevant legislation and regulations;
• Roles and responsibilities for the protection of the environment;
• CEMP purpose and implementation;
• Environmental policies, procedures and systems;
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
ensuring that construction of the Scheme is undertaken in accordance with European and UK environmental regulations and legislation; and
ensuring compliance with the Requirements in the Order (see Schedule 2 of the ocument reference 3.1)) and other relevant consents, lic
(Other Consents and Licences document (D
Environment, Health and Safety Function
the Project Environmental Lead and the Project Lead. The tresponsible for all environmental and health and safety aspects of construction of
AND COMPETENCE
All construction personnel involved in the construction of the Scheme must understand the content and purpose of the CEMP and receive the necessary training
ow them to implement it. This training will vary, depending on roles and the level of control personnel have over matters that can affect environmental impact
Environmental training will be provided to all personnel working on the consof the Scheme. This will be appropriate to their level and role, and will include any subcontractors and the wider supply chain, as appropriate. Typical examples of training, and the participants at whom the training will be targeted, are shown
Site personnel (including all new starters):
Company induction element – environment and sustainability;
spill prevention and clean-up, noise prevention, dust prevention, ecological constraints and others as required.
ders, site management and environmental specialists:
Relevant legislation and regulations;
Roles and responsibilities for the protection of the environment;
CEMP purpose and implementation;
Environmental policies, procedures and systems;
e is undertaken in accordance with European and UK environmental regulations and legislation; and
ensuring compliance with the Requirements in the Order (see Schedule 2 of the ther relevant consents, licences and
document (Document
The team is health and safety aspects of construction of
All construction personnel involved in the construction of the Scheme must understand the content and purpose of the CEMP and receive the necessary training
ow them to implement it. This training will vary, depending on roles and the level of control personnel have over matters that can affect environmental impact
Environmental training will be provided to all personnel working on the construction of the Scheme. This will be appropriate to their level and role, and will include any subcontractors and the wider supply chain, as appropriate. Typical examples of training, and the participants at whom the training will be targeted, are shown
up, noise prevention, dust prevention,
• Potential environmental effects of their role, how to comply and risk of prosecution;
• Nuisance prevention and control (noise, dust, lighting) and complaint investigation;
• Emergency preparedness and response;
• Ecological protection, biosecurity
• Tree protection;
• Waste management certification;
• Emergency spill procedures; and
• Fire safety and response
COMMUNICATION
Internal Communication
3.9 Communication on environmental issues will be through a hierarchy of methods. At the highest level there will beProject Lead and including shift and discipline heads and representatives from the main subcontractors. This will have a dedicated environmental section. Issues to be covered will include:
• Relevant consents, applications and compliance;
• Complaints made, investigations and outcomes;
• Incidents, their causes and preventative measures to prevent recurrence;
• Monitoring and reporting against environmental performance indicators;
• Site audits and findings;
• Planned work and environmental risks;
• Ongoing or required public consultation; and
• Engagement with statutory authorities.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
ental effects of their role, how to comply and risk of
Nuisance prevention and control (noise, dust, lighting) and complaint
Emergency preparedness and response;
, biosecurity and protected species licences;
Waste management certification;
Emergency spill procedures; and
Fire safety and response
Communication on environmental issues will be through a hierarchy of methods. At the highest level there will be monthly project review meetings, chaired by the Project Lead and including shift and discipline heads and representatives from the main subcontractors. This will have a dedicated environmental section. Issues to be
applications and compliance;
Complaints made, investigations and outcomes;
Incidents, their causes and preventative measures to prevent recurrence;
Monitoring and reporting against environmental performance indicators;
rk and environmental risks;
Ongoing or required public consultation; and
Engagement with statutory authorities.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
9
ental effects of their role, how to comply and risk of
Nuisance prevention and control (noise, dust, lighting) and complaint
Communication on environmental issues will be through a hierarchy of methods. At monthly project review meetings, chaired by the
Project Lead and including shift and discipline heads and representatives from the main subcontractors. This will have a dedicated environmental section. Issues to be
Incidents, their causes and preventative measures to prevent recurrence;
Monitoring and reporting against environmental performance indicators;
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
10
3.10 Senior personnel will be designated as Environmental Project Lead and Project Lead (as indicated above). These will be individuals in charge othe most significant potential environmental impact. They will retain a copy of the CEMP.
3.11 Site noticeboards and newsletters will be used to communicate key headlines from project meetings. They will also be used to promote trainienvironmental awareness, discuss current themes or issues and to communicate with the wider community. Informal toolbox talks will focus on specific themes as required.
3.12 Project meetings and other internal communications will ensure active from all Scheme personnel, allowing for lessons to be learnt and delivering continual improvement.
External Communication
3.13 A community liaison strategy, including a complaints procedure,for the Scheme. Responsibility for impThis procedure will set out the forthcoming work packages for construction of the Scheme, how to inform those likely to be affected by the Scheme people and businesses) about the work to be undhow any potential impacts might be mitigated.
3.14 People likely to be captured by the community liaison procedure will include local residents, businesses and landowners. Examples of how communication may take place include:
• Presentations to residents’ groups, representatives and other interested parties;
• Advance notification of specific work packages likely to have more of an impact (e.g. piling and demolition activities such as existing slab removal) through newsletters and mail drops,
• Consultation with statutory bodies Environmental Health and Planning Departments,
3.15 Site management measures should include:
• displaying the name of accountable persons and or regional office information on the site boundary;
• recording all dust and air quality complaints, identify cause(s), take appropriate measures to reduce emissions in a timely manner, taken;
• making the complaints log available to the WCBC EHO as required; and
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Senior personnel will be designated as Environmental Project Lead and Project Lead (as indicated above). These will be individuals in charge of activities that can have the most significant potential environmental impact. They will retain a copy of the
Site noticeboards and newsletters will be used to communicate key headlines from project meetings. They will also be used to promote training and encourage environmental awareness, discuss current themes or issues and to communicate with the wider community. Informal toolbox talks will focus on specific themes as
Project meetings and other internal communications will ensure active participation personnel, allowing for lessons to be learnt and delivering continual
strategy, including a complaints procedure, will be developed for the Scheme. Responsibility for implementing this will be with the Project Lead. This procedure will set out the forthcoming work packages for construction of the Scheme, how to inform those likely to be affected by the Scheme (including local
about the work to be undertaken during construction, and how any potential impacts might be mitigated.
People likely to be captured by the community liaison procedure will include local residents, businesses and landowners. Examples of how communication may take
esentations to residents’ groups, representatives and other interested parties;
Advance notification of specific work packages likely to have more of an impact and demolition activities such as existing slab removal) through
il drops, presentations in community centres etc.; and
ultation with statutory bodies including Wrexham County Borough Council Environmental Health and Planning Departments, and Natural Resources Wales
Site management measures should include:
ng the name of accountable persons and the appointed contractor’s or regional office information on the site boundary;
recording all dust and air quality complaints, identify cause(s), take appropriate measures to reduce emissions in a timely manner, and record the measures
making the complaints log available to the WCBC EHO as required; and
Senior personnel will be designated as Environmental Project Lead and Project Lead f activities that can have
the most significant potential environmental impact. They will retain a copy of the
Site noticeboards and newsletters will be used to communicate key headlines from ng and encourage
environmental awareness, discuss current themes or issues and to communicate with the wider community. Informal toolbox talks will focus on specific themes as
participation personnel, allowing for lessons to be learnt and delivering continual
will be developed lementing this will be with the Project Lead.
This procedure will set out the forthcoming work packages for construction of the (including local
ertaken during construction, and
People likely to be captured by the community liaison procedure will include local residents, businesses and landowners. Examples of how communication may take
esentations to residents’ groups, representatives and other interested parties;
Advance notification of specific work packages likely to have more of an impact and demolition activities such as existing slab removal) through
presentations in community centres etc.; and
Wrexham County Borough Council and Natural Resources Wales.
ontractor’s head
recording all dust and air quality complaints, identify cause(s), take appropriate and record the measures
making the complaints log available to the WCBC EHO as required; and
• recording any exceptional incidents that cause dust and/or air emissionson- or off-site, and the action taken to resolve the situation in the log
Chapter 4 u Environmental Monitoring and Auditing
ENVIRONMENTAL PERFORMANCE INDICATORS
4.1 A set of Environmental Performance Indicators (EPIs) will be developed for the construction phase of the Scheme upon the aspects and impacts identified, and standards and policies. The EPIs will be measureable and will be communicated through regular project review meetings. They will be passed down through the supply chain. Reporting will be back uthrough the regular project review meetings.
INSPECTIONS AND VERIFICATIONS
4.2 The construction of the Scheme will be regularly inspected and evaluated against the defined EPIs. The inspections will be undertaken by theEnvironmental Specialist (as appropriate), and will focus on,
• Compliance with legislation and regulations;
• Nuisance management and prevention;
• Complaint investigation and resolution;
• Waste and materials storage and man
• Pollution controls and prevention of contaminated surface water runoff;
• Ecological protection measures
• Materials reuse on-site; and
• Off-site waste reuse and recycling.
4.3 Inspection records will be retairequired. The inspections will include verification that the correct systems and procedures have been followed. This will include,
• Checking that the correct permits, consents and licences have are being complied with;
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
recording any exceptional incidents that cause dust and/or air emissionssite, and the action taken to resolve the situation in the log book
Environmental Monitoring and Auditing
NCE INDICATORS
A set of Environmental Performance Indicators (EPIs) will be developed for the construction phase of the Scheme to be included in the CEMP. These will be based
ts and impacts identified, and WPL’s and its contractors’ own standards and policies. The EPIs will be measureable and will be communicated through regular project review meetings. They will be passed down through the supply chain. Reporting will be back up the supply chain and also communicated through the regular project review meetings.
The construction of the Scheme will be regularly inspected and evaluated against the defined EPIs. The inspections will be undertaken by the Project Lead or the Lead Environmental Specialist (as appropriate), and will focus on, inter alia:
Compliance with legislation and regulations;
Nuisance management and prevention;
Complaint investigation and resolution;
Waste and materials storage and management;
Pollution controls and prevention of contaminated surface water runoff;
Ecological protection measures in the form of an Ecological Compliance Audit
; and
ite waste reuse and recycling.
Inspection records will be retained in specific files, available for inspection as required. The inspections will include verification that the correct systems and procedures have been followed. This will include, inter alia:
Checking that the correct permits, consents and licences have been obtained and complied with;
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
11
recording any exceptional incidents that cause dust and/or air emissions, either book
Environmental Monitoring and Auditing
A set of Environmental Performance Indicators (EPIs) will be developed for the be included in the CEMP. These will be based
and its contractors’ own standards and policies. The EPIs will be measureable and will be communicated through regular project review meetings. They will be passed down through the
p the supply chain and also communicated
The construction of the Scheme will be regularly inspected and evaluated against the Project Lead or the Lead
Pollution controls and prevention of contaminated surface water runoff;
in the form of an Ecological Compliance Audit;
ned in specific files, available for inspection as required. The inspections will include verification that the correct systems and
been obtained and
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
12
• Checking activities against the environmental management system and procedures; and
• Checking that work is being undertaken according to this CEMP.
CORRECTIVE AND PREVENTATIVE ACTION
4.4 In the event that non-conformanidentified, or in the event of nonis observed, a corrective action procedure will be implemented. This will remedy non-compliance, and ensure that precurrence. Lessons learnt will then be communicated through the internal (and where required, external) communications procedures described above.
EXTERNAL COMPLAINTS PROCEDURE
4.5 A complaints procedure will be pconstruction process. Complaints will be logged centrally and allocated to aproject team member with environmental responsibility for further investigation. The outcome of that investigation will aland follow up with the complainant.
4.6 If required, the complaint investigation will be communicated to statutory agency (e.g. Natural Resources Walesremedial action taken to mitigate the consequences and to prevent recurrence.
EMERGENCY PREPAREDNESS AND RESPONSE
4.7 An environmental incident control plan (EICP) will be drafted for the Scheme. This will set out the steps to be taken in the event of an incident, and will co
• Pollution release to water;
• Pollution release to ground;
• Pollution release to air;
• Encountering evidence of cultural heritage;
• Encountering evidence of protected species;
• Encountering invasive non
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Checking activities against the environmental management system and
Checking that work is being undertaken according to this CEMP.
NTATIVE ACTION
conformances with the CEMP or any policies or procedures or identified, or in the event of non-compliance with legislation, regulations or permits is observed, a corrective action procedure will be implemented. This will remedy
compliance, and ensure that preventative action is put in place to prevent recurrence. Lessons learnt will then be communicated through the internal (and where required, external) communications procedures described above.
PROCEDURE
procedure will be put in place to track any complaints made about the construction process. Complaints will be logged centrally and allocated to aproject team member with environmental responsibility for further investigation. The outcome of that investigation will also be logged, along with the communication and follow up with the complainant.
If required, the complaint investigation will be communicated to WCBCstatutory agency (e.g. Natural Resources Wales (NRW)) as appropriate, along with
taken to mitigate the consequences and to prevent recurrence.
SS AND RESPONSE
An environmental incident control plan (EICP) will be drafted for the Scheme. This will set out the steps to be taken in the event of an incident, and will cover:
Pollution release to water;
Pollution release to ground;
Encountering evidence of cultural heritage;
Encountering evidence of protected species;
non-native species (INNS) and
Checking activities against the environmental management system and
ces with the CEMP or any policies or procedures or compliance with legislation, regulations or permits
is observed, a corrective action procedure will be implemented. This will remedy any reventative action is put in place to prevent
recurrence. Lessons learnt will then be communicated through the internal (and
ut in place to track any complaints made about the construction process. Complaints will be logged centrally and allocated to a named project team member with environmental responsibility for further investigation.
so be logged, along with the communication
CBC, or other as appropriate, along with
taken to mitigate the consequences and to prevent recurrence.
An environmental incident control plan (EICP) will be drafted for the Scheme. This ver:
• Encountering potential conta
4.8 A reporting form will be provided to ensure that the incident is reported to the Project and Environmental Leads, and that the correct procedures are followed as outlined in the EICP.
MANAGEMENT REVIEW
4.9 The Project Lead will undertake a high lincluding:
• Follow-ups from previous reviews;
• Results of internal audits;
• Evaluation of compliance with legislation and regulations;
• Evaluation of compliance with this CEMP;
• Extent to which EPIs have been met;
• Status of corrective actions, preventative actions and incident mitigation;
• Any external communications, either proactive or as a result of incidents, complaints or non-compliances;
• Changes in circumstances, either in the construction or the legal and otherrequirements placed on it; and
• Recommendations for continuous improvement.
4.10 The results of these reviews will be fed down tthe internal communications mechanisms described above.
DOCUMENTS AND RECORDS
4.11 This CEMP is the over-arching document for environmental control of the construction process. It defines policies, procedures, legislation and regulations concerning the main environmental issues affecting construction of the Scheme. The CEMP and all the associated policies aenvironmental management system for the construction of the Scheme. Responsibility for this will be with the Project and Environmental Leads.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Encountering potential contaminated land.
A reporting form will be provided to ensure that the incident is reported to the Project and Environmental Leads, and that the correct procedures are followed as
The Project Lead will undertake a high level review of the Scheme on a regular basis,
ups from previous reviews;
Results of internal audits;
Evaluation of compliance with legislation and regulations;
Evaluation of compliance with this CEMP;
Extent to which EPIs have been met;
tatus of corrective actions, preventative actions and incident mitigation;
Any external communications, either proactive or as a result of incidents, compliances;
Changes in circumstances, either in the construction or the legal and otherplaced on it; and
Recommendations for continuous improvement.
these reviews will be fed down to the construction workersthe internal communications mechanisms described above.
arching document for environmental control of the construction process. It defines policies, procedures, legislation and regulations concerning the main environmental issues affecting construction of the Scheme. The CEMP and all the associated policies and procedures described herein will form the environmental management system for the construction of the Scheme. Responsibility for this will be with the Project and Environmental Leads.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
13
A reporting form will be provided to ensure that the incident is reported to the Project and Environmental Leads, and that the correct procedures are followed as
evel review of the Scheme on a regular basis,
tatus of corrective actions, preventative actions and incident mitigation;
Any external communications, either proactive or as a result of incidents,
Changes in circumstances, either in the construction or the legal and other
construction workers through
arching document for environmental control of the construction process. It defines policies, procedures, legislation and regulations concerning the main environmental issues affecting construction of the Scheme. The
nd procedures described herein will form the environmental management system for the construction of the Scheme.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
14
Chapter 5
ENVIRONMENTAL RISK ASSESSMENT
5.1 An environmental impact assessment (EIA) has been undertaken to support the Application for the Scheme. The EIA has used the staged approach of scoping and assessment to identify the environmental aspects and impacts associated with the construction, operation (includThese aspects and impacts are those that form the basis of the project register described above. This then allows the relevant legislation and regulations, standards and obligations for each potential impact tactions and procedures for specific activities to be developed.
5.2 The aspects identified in the EIA for which there are potential impacts are:
• Socio-Economics;
• Transport and Traffic;
• Air Quality;
• Noise and Vibration;
• Landscape & Visual;
• Ecology;
• Historic Environment;
• Ground Conditions;
• Land Use
• Water Environment; and
• Waste.
5.3 Sustainable use of energy, materials and water
PREVENTION OF NUISANCE AND POLLUTION
5.4 The Scheme will be registered be managed according to the CCS requirements. The EIA (as presented in the main ES (document reference 6.2)) has highlighted potential environmental issues that are likely to have the potential to cause
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Chapter 5 u Environmental Management
SESSMENT
ntal impact assessment (EIA) has been undertaken to support the Application for the Scheme. The EIA has used the staged approach of scoping and assessment to identify the environmental aspects and impacts associated with the construction, operation (including maintenance) and demolition of the Scheme. These aspects and impacts are those that form the basis of the project register described above. This then allows the relevant legislation and regulations, standards and obligations for each potential impact to be identified and the relevant mitigation actions and procedures for specific activities to be developed.
The aspects identified in the EIA for which there are potential impacts are:
Water Environment; and
Sustainable use of energy, materials and water on-site will also be managed.
CE AND POLLUTION
will be registered to the Considerate Constructor Scheme (CCS), and will be managed according to the CCS requirements. The EIA (as presented in the main ES (document reference 6.2)) has highlighted potential environmental issues that are likely to have the potential to cause amenity or nuisance impact during construction.
Environmental Management
ntal impact assessment (EIA) has been undertaken to support the Application for the Scheme. The EIA has used the staged approach of scoping and assessment to identify the environmental aspects and impacts associated with the
ing maintenance) and demolition of the Scheme. These aspects and impacts are those that form the basis of the project register described above. This then allows the relevant legislation and regulations, standards
o be identified and the relevant mitigation
The aspects identified in the EIA for which there are potential impacts are:
will also be managed.
to the Considerate Constructor Scheme (CCS), and will be managed according to the CCS requirements. The EIA (as presented in the main ES (document reference 6.2)) has highlighted potential environmental issues that are
amenity or nuisance impact during construction.
Therefore, mitigation has been put in place in this CEMP to minimise risks of these impacts.
5.5 In conjunction with the monitoring, inspections and verifications and the internal and external communications plameasures described below willimpact being experienced by the local
Vermin and Pest Control
5.6 General good construction practices and housekeeping willvermin and pests are kept to a minimum. Welfare facilities, including toilets, showers, mess rooms, canteens, locker rooms etc., will be provided, and must be used. They will be cleaned daily and maintained in good condition. A licontainer will be provided for food and drink waste, which will be removed from the Scheme on a regular basis. Abuse of these facilities will be a disciplinary matter. Eating and drinking elsewhere encourages vermin and will be forbidden. Urinating ordefecating anywhere else on the Site will also be a disciplinary matter
Fire Control
5.7 The Scheme will be carried out in compliance with the Regulatory Reform (Fire Safety) Order 2005: “Joint Code of Construction Sites and Buildings Undergoing Renovation.” A Fire Safety Plan (FSP) will be defined and implemented in conjunction with third parties as required, defining roles and responsibilities and responsible people, and establishing procedures for fire prevention.
5.8 An initial fire risk assessment will be carried out, and updated as risks change over time. Weekly inspections will be undertaken, with findings recorded.
5.9 A Fire Safety Co-ordinator will be appointed to ensure that the FSP is complied with. This will include, inter alia:
• General housekeeping;
• Fire extinguishers, detection and alarms;
• Hot work permit scheme;
• Fire escapes and communications (including evacuation plans and procedures for calling the fire brigade);
• Fire brigade access;
• Fire drills and training;
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Therefore, mitigation has been put in place in this CEMP to minimise risks of these
In conjunction with the monitoring, inspections and verifications and the internal communications plans discussed above, the specific mitigation
measures described below will effectively prevent significant amenity or nuisance impact being experienced by the local community.
General good construction practices and housekeeping will ensure that the risks of vermin and pests are kept to a minimum. Welfare facilities, including toilets, showers, mess rooms, canteens, locker rooms etc., will be provided, and must be used. They will be cleaned daily and maintained in good condition. A licontainer will be provided for food and drink waste, which will be removed from the
on a regular basis. Abuse of these facilities will be a disciplinary matter. Eating and drinking elsewhere encourages vermin and will be forbidden. Urinating ordefecating anywhere else on the Site will also be a disciplinary matter.
The Scheme will be carried out in compliance with the Regulatory Reform (Fire Safety) Order 2005: “Joint Code of Practice on the Protection from Fire on
es and Buildings Undergoing Renovation.” A Fire Safety Plan (FSP) will be defined and implemented in conjunction with third parties as required, defining roles and responsibilities and responsible people, and establishing procedures for fire prevention.
initial fire risk assessment will be carried out, and updated as risks change over time. Weekly inspections will be undertaken, with findings recorded.
ordinator will be appointed to ensure that the FSP is complied with.
Fire extinguishers, detection and alarms;
Hot work permit scheme;
Fire escapes and communications (including evacuation plans and procedures for
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
15
Therefore, mitigation has been put in place in this CEMP to minimise risks of these
In conjunction with the monitoring, inspections and verifications and the internal ns discussed above, the specific mitigation
effectively prevent significant amenity or nuisance
ensure that the risks of vermin and pests are kept to a minimum. Welfare facilities, including toilets, showers, mess rooms, canteens, locker rooms etc., will be provided, and must be used. They will be cleaned daily and maintained in good condition. A lidded container will be provided for food and drink waste, which will be removed from the
on a regular basis. Abuse of these facilities will be a disciplinary matter. Eating and drinking elsewhere encourages vermin and will be forbidden. Urinating or
The Scheme will be carried out in compliance with the Regulatory Reform (Fire ractice on the Protection from Fire on
es and Buildings Undergoing Renovation.” A Fire Safety Plan (FSP) will be defined and implemented in conjunction with third parties as required, defining roles and responsibilities and responsible people, and establishing
initial fire risk assessment will be carried out, and updated as risks change over
ordinator will be appointed to ensure that the FSP is complied with.
Fire escapes and communications (including evacuation plans and procedures for
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
16
• Effective security to prevent arson; and
• Materials storage and waste management and control.
Air Quality
5.10 As a general principle, Best Practicable Means (BPM) will be employed to minimise risk of nuisance from dust emissions. The key construction dust risks enabling works and particularly the removal of existing
5.11 Preparing and maintaining the site should comprise:
• planning site layout so that machinery and dust causing activities are located away from receptors, as far as is pos
• erecting solid screens or barriers around dusty activities or the site boundary that are at least as high as any stockpiles
• avoiding site runoff of water or mud
5.12 Demolition (i.e. enabling works to remove existing structures and hardstandshould include:
• ensuring effective water suppression is used during demolition operations. Hand held sprays are more effective than hoses attached to equipment as the water can be directed to where it is needed. In addition high volume water suppressisystems, manually controlled, can produce fine water droplets that effectively bring the dust particles to the ground; and
• bagging and removing any biological debris or damp down such material before demolition.
5.13 Operations should consider:
• only using cutting, grinding or sawing equipment fitted or in conjunction with suitable dust suppression techniques such as water sprays or local extraction, e.g. suitable local exhaust ventilation systems;
• ensuring an adequate water supply on the site for effective dumatter suppression/mitigation, using nonappropriate;
• using enclosed chutes and conveyors and covered skips;
• minimising drop heights from conveyors, loading shovels, hoppers and other loading or handling equwherever appropriate; and
• avoiding bonfires and burning of waste materials.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
ffective security to prevent arson; and
Materials storage and waste management and control.
As a general principle, Best Practicable Means (BPM) will be employed to minimise nuisance from dust emissions. The key construction dust risks
particularly the removal of existing hard standing areas
Preparing and maintaining the site should comprise:
planning site layout so that machinery and dust causing activities are located away from receptors, as far as is possible;
erecting solid screens or barriers around dusty activities or the site boundary that are at least as high as any stockpiles on-site; and
avoiding site runoff of water or mud
Demolition (i.e. enabling works to remove existing structures and hardstand
ensuring effective water suppression is used during demolition operations. Hand held sprays are more effective than hoses attached to equipment as the water can be directed to where it is needed. In addition high volume water suppressisystems, manually controlled, can produce fine water droplets that effectively bring the dust particles to the ground; and
bagging and removing any biological debris or damp down such material before
Operations should consider:
tting, grinding or sawing equipment fitted or in conjunction with suitable dust suppression techniques such as water sprays or local extraction, e.g. suitable local exhaust ventilation systems;
ensuring an adequate water supply on the site for effective dust/particulate matter suppression/mitigation, using non-potable water where possible and
using enclosed chutes and conveyors and covered skips;
minimising drop heights from conveyors, loading shovels, hoppers and other loading or handling equipment and use fine water sprays on such equipment wherever appropriate; and
avoiding bonfires and burning of waste materials.
As a general principle, Best Practicable Means (BPM) will be employed to minimise nuisance from dust emissions. The key construction dust risks relate to
hard standing areas.
planning site layout so that machinery and dust causing activities are located
erecting solid screens or barriers around dusty activities or the site boundary that
Demolition (i.e. enabling works to remove existing structures and hardstanding)
ensuring effective water suppression is used during demolition operations. Hand held sprays are more effective than hoses attached to equipment as the water can be directed to where it is needed. In addition high volume water suppression systems, manually controlled, can produce fine water droplets that effectively
bagging and removing any biological debris or damp down such material before
tting, grinding or sawing equipment fitted or in conjunction with suitable dust suppression techniques such as water sprays or local extraction, e.g.
st/particulate potable water where possible and
minimising drop heights from conveyors, loading shovels, hoppers and other ipment and use fine water sprays on such equipment
5.14 Regular site inspections will be undertaken as part of the monitoring discussed in Inspections and Verifications swith the nuisance management measures described above.recorded and made available to frequency will increase when activities with a high potential to pbeing carried out, and during prolonged dry or windy conditions.
5.15 Mobile plant will be operated and permitted in accordance with the most recent version of DEFRA’s Process Guidance Note 3/16 for Mobile Crushing and Screening. It will be regulated under the Environmental Permitting (England and Wales) Regulations 2010 via an environmental permit issued by
5.16 Non-Road Mobile Machinery (NRMM)approved engine which meets the emission standards set in Machinery (Emission of Gaseous and Particulate Pollutants) Regulations 19991999/1053). The placement of diesel or petrol powered generators should consider proximity to nearby receptors and ensure that the exhaust discharges vertiis unimpeded.
5.17 If an on-site concrete batching is employed, such operations will be undertaken using enclosed plant and in accordance with DEFRA’s Process Guidance note 3/1 and permitted under the Environmental Permitting (England and Wales) Regul2010.
5.18 With regard to the control of emissions from vehicle/machinery and employees vehicles, the following measures will be implemented, via the CTMP:
• Ensuring the covering of HGVs entering and leaving the site as appropriate;
• The use of an on-site batching plant HGV vehicles requiring access to the Wfoundations for the Power Station Complex;
• Measures to ensure that arrivals and departures of HGV traffic is spread evenly over the course of the working day
• Ensuring all vehicles switch off engines when stationary
• Avoiding the use of diesel or petrol powered generators where mains electricity or battery powered equipment is practicable;
• Efficient loading of vehicles travelling to and from Site in order to minimise vehicle numbers(and hence emission levels); and
• Encourage vehicle sharing, use of public transport and walking/cyclingin the Construction Travel Plan (CTP)
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
ite inspections will be undertaken as part of the monitoring discussed in Inspections and Verifications section above in chapter 4), to monitor compliance with the nuisance management measures described above. Inspection results will be recorded and made available to WCBC and/or NRW on demand. Inspection frequency will increase when activities with a high potential to producebeing carried out, and during prolonged dry or windy conditions.
Mobile plant will be operated and permitted in accordance with the most recent of DEFRA’s Process Guidance Note 3/16 for Mobile Crushing and Screening. It
under the Environmental Permitting (England and Wales) environmental permit issued by WCBC.
achinery (NRMM) used on-site should be fitted with a type approved engine which meets the emission standards set in the Non-Road Mobile Machinery (Emission of Gaseous and Particulate Pollutants) Regulations 19991999/1053). The placement of diesel or petrol powered generators should consider proximity to nearby receptors and ensure that the exhaust discharges verti
ite concrete batching is employed, such operations will be undertaken using plant and in accordance with DEFRA’s Process Guidance note 3/1 and
Environmental Permitting (England and Wales) Regul
With regard to the control of emissions from vehicle/machinery and employees following measures will be implemented, via the CTMP:
Ensuring the covering of HGVs entering and leaving the site as appropriate;
batching plant may be considered to reduce the number of hicles requiring access to the WEC Site during construction of the
Power Station Complex;
Measures to ensure that arrivals and departures of HGV traffic is spread evenly course of the working day
Ensuring all vehicles switch off engines when stationary – no idling vehicles;
Avoiding the use of diesel or petrol powered generators where mains electricity powered equipment is practicable;
vehicles travelling to and from Site in order to minimise vehicle numbers(and hence emission levels); and
Encourage vehicle sharing, use of public transport and walking/cyclingin the Construction Travel Plan (CTP).
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
17
ite inspections will be undertaken as part of the monitoring discussed in the , to monitor compliance Inspection results will be on demand. Inspection
roduce dust are
Mobile plant will be operated and permitted in accordance with the most recent of DEFRA’s Process Guidance Note 3/16 for Mobile Crushing and Screening. It
under the Environmental Permitting (England and Wales)
should be fitted with a type Road Mobile
Machinery (Emission of Gaseous and Particulate Pollutants) Regulations 1999 (SI 1999/1053). The placement of diesel or petrol powered generators should consider proximity to nearby receptors and ensure that the exhaust discharges vertically and
ite concrete batching is employed, such operations will be undertaken using plant and in accordance with DEFRA’s Process Guidance note 3/1 and
Environmental Permitting (England and Wales) Regulations
With regard to the control of emissions from vehicle/machinery and employees
Ensuring the covering of HGVs entering and leaving the site as appropriate;
be considered to reduce the number of EC Site during construction of the
Measures to ensure that arrivals and departures of HGV traffic is spread evenly
no idling vehicles;
Avoiding the use of diesel or petrol powered generators where mains electricity
vehicles travelling to and from Site in order to minimise
Encourage vehicle sharing, use of public transport and walking/cycling as set out
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
18
• A specific individual will bincluding air quality and dust. All complaints or incidents will be recorded, identifying cause(s), and taking appropriatetimely manner, and recording the measures taken.will be made available for inspection as required.
Water Environment
5.19 Good practice will be employed to prevent contamination of surface water runoff from the Power Station Complexregulations and standards listed below:
• The Control of Pollution (Oil Storage) Regulations;
• Environment Agency Groundwater Protection: Principles and Practice; and
• All applicable Environment Agency Pollution Prevention Guidance.
5.20 In addition, the following specific mitigation measures will be implemented during construction and demolition of the Scheme:
• Bunding of potential contaminant sources such as tanks and excavated soils;
• Use of spill kits;
• Preparation of an Environmental
• Obtaining and complying with appropriate environmental permits for discharge to surface water;
• Capture of site runoff and attenuation of contaminants using sedimentation tanks prior to discharge to surface water;
• Use of appropriate care to avoid disturbancesuch as sewers, waste water pipes or fuel lines;
• laydown areas are situated within the Order Limits, which are entirely outside of zone designated as Principal Aquifers or SPZ1; and
• implementation of the Foul and Surfac
5.21 Regular monitoring of surface water will be undertaken as part of the monitoring discussed above (Inspections and Verifications), to ensure that pollution is not occurring. The inspection log will be made available to demand.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
A specific individual will be nominated to be accountable for nuisance issues, and dust. All complaints or incidents will be recorded,
identifying cause(s), and taking appropriate measures to reduce emissions in a timely manner, and recording the measures taken. This complaints / incidents log will be made available for inspection as required.
Good practice will be employed to prevent contamination of surface water runoff Power Station Complex Site during construction, in compliance wit
regulations and standards listed below:
The Control of Pollution (Oil Storage) Regulations;
Environment Agency Groundwater Protection: Principles and Practice; and
All applicable Environment Agency Pollution Prevention Guidance.
owing specific mitigation measures will be implemented during construction and demolition of the Scheme:
Bunding of potential contaminant sources such as tanks and excavated soils;
nvironmental Incident Control Plan;
btaining and complying with appropriate environmental permits for discharge
Capture of site runoff and attenuation of contaminants using sedimentation discharge to surface water;
Use of appropriate care to avoid disturbance or rupture of underground services sewers, waste water pipes or fuel lines;
laydown areas are situated within the Order Limits, which are entirely outside of zone designated as Principal Aquifers or SPZ1; and
Foul and Surface Water Drainage Strategy
Regular monitoring of surface water will be undertaken as part of the monitoring discussed above (Inspections and Verifications), to ensure that pollution is not occurring. The inspection log will be made available to WCBC and/or
e nominated to be accountable for nuisance issues, and dust. All complaints or incidents will be recorded,
measures to reduce emissions in a complaints / incidents log
Good practice will be employed to prevent contamination of surface water runoff Site during construction, in compliance with the
Environment Agency Groundwater Protection: Principles and Practice; and
owing specific mitigation measures will be implemented during
Bunding of potential contaminant sources such as tanks and excavated soils;
btaining and complying with appropriate environmental permits for discharge
Capture of site runoff and attenuation of contaminants using sedimentation
or rupture of underground services
laydown areas are situated within the Order Limits, which are entirely outside of
Regular monitoring of surface water will be undertaken as part of the monitoring discussed above (Inspections and Verifications), to ensure that pollution is not
and/or NRW on
Noise and Vibration
5.22 As a general principle, BPM will be employed to minimise risk of nuisance from noise and vibration emissions. As a minimum these will include the following measures:
• Restricted working hours during construction of between
• Selection and design of quieter plant and methods;
• Switching off plant when not in use, and regular plant maintenance;
• Increasing the distance between the plant and the nearest noisereceivers, where practicable;
• Use of silencers where practicable; and
• Use of standard acoustic enclosure, walls or building elements as screens where practicable.
5.23 A specific individual, the Environmental Lead (as described above) will be nominated to be accountable for nuisance issues, including air complaints or incidents will be recorded, identifying cause(s), and taking appropriate measures to reduce emissions in a timely manner, and recording the measures taken. This complaints / incidents log will be made available forequired.
Ecology
5.24 Adoption of industry working practices to avoid pollution, including the adoption of guidance found within the EA Pollution Prevention Guidance (PPG). pollution prevention measures described in this draft CEMPimpact on ecological receptors. This includes the nuisance management (including the measures to avoid or minimise the impacts of the construction works) and the use of BPM to minimise noise and air emissions. Lighting in the winpointed away from the ecological mitigation area and features including hedgerows and ponds
5.25 Undertake site inductions –the presence of and protection and the wider environment.
5.26 Mitigation measures aimed at protecting specific species or groups of species during construction are summarised below.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
As a general principle, BPM will be employed to minimise risk of nuisance from noise and vibration emissions. As a minimum these will include the following measures:
Restricted working hours during construction of between 07:00 and 19:00;
Selection and design of quieter plant and methods;
Switching off plant when not in use, and regular plant maintenance;
Increasing the distance between the plant and the nearest noisepracticable;
s where practicable; and
Use of standard acoustic enclosure, walls or building elements as screens where
A specific individual, the Environmental Lead (as described above) will be nominated to be accountable for nuisance issues, including air quality, light and dust. All complaints or incidents will be recorded, identifying cause(s), and taking appropriate measures to reduce emissions in a timely manner, and recording the measures taken. This complaints / incidents log will be made available for inspection as
Adoption of industry working practices to avoid pollution, including the adoption of guidance found within the EA Pollution Prevention Guidance (PPG). The general pollution prevention measures described in this draft CEMP will also help to prevent impact on ecological receptors. This includes the nuisance management (including the measures to avoid or minimise the impacts of the construction works) and the use of BPM to minimise noise and air emissions. Lighting in the winter months will be
the ecological mitigation area and potential foraging/commuting features including hedgerows and ponds.
– all construction personnel will receive briefings about the presence of and protection of ecological features present within the Order Land the wider environment.
Mitigation measures aimed at protecting specific species or groups of species during construction are summarised below.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
19
As a general principle, BPM will be employed to minimise risk of nuisance from noise and vibration emissions. As a minimum these will include the following measures:
07:00 and 19:00;
Increasing the distance between the plant and the nearest noise-sensitive
Use of standard acoustic enclosure, walls or building elements as screens where
A specific individual, the Environmental Lead (as described above) will be nominated quality, light and dust. All
complaints or incidents will be recorded, identifying cause(s), and taking appropriate measures to reduce emissions in a timely manner, and recording the measures
r inspection as
Adoption of industry working practices to avoid pollution, including the adoption of The general
will also help to prevent impact on ecological receptors. This includes the nuisance management (including the measures to avoid or minimise the impacts of the construction works) and the
ter months will be ing/commuting
all construction personnel will receive briefings about of ecological features present within the Order Land
Mitigation measures aimed at protecting specific species or groups of species during
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
20
Great Crested Newts
5.27 A licence issued by NRW, under RegulSpecies Regulations 2010, will be required to implement the mitigation strategy.
5.28 The mitigation strategy will be implemented prior to preliminary site clearance and other enabling works. It will comprise a captprogramme to avoid the disturbance, injury or killing of individual great crested newts within the Site. This mitigation strategy has been agreed in principle with NRW.
5.29 In summary, the mitigation strategy will inv
• A toolbox talk will be presented by the licensed ecologist to all the construction of the Power Station Complex and Gas Connection, in particular those involved in site clearance during the preliminary works stage. This will ensure that all personnel are aware of the presence of great crested newtsprotection afforded to great crested newtsstrategies that will be implemented and the appropriate action to take if a great crested newt is encountered
• The erection of ring-fencing around the pond which will be lost to the Scheme;
• The erection of temporary exclusion fencing around the perimeter of the Site to exclude great crested newts from the Power Station Complex footprint, the construction laydown area, the route of the gas pipeline and any area which will be subject to earthworks in order to implement the inherent landscape strategy (including the creation of new great crested newt ponds) and the drainage strategies;
• The provision of a recepaccess to three existing great crested newt ponds (the receptor area will not be subject to any construction or landscape activities);
• The erection of drift fencing within the Site to increase trappingwill be erected during the winter immediately prior to the spring trapping season;
• Pitfall trapping (in combination with the use of refuges) for a minimum of 30 days (with at least 5 ‘clear’ trapping days before the Site can be declaregreat crested newts), using a spacing of alternThe trapping array will be located either side of the ringand around the interior perimeter of the exclusion fencing;commence at the earliest opportunity during the spring migration to breeding ponds, i.e. February to May, and will be dependent on local weather conditions (trapping will not be undertaken when night air temperatures are below 5°C);
• The area required for the closs of an existing great crested newt pond) will be fenced and trapped first to
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
A licence issued by NRW, under Regulation 53 of the Conservation of Habitats an, will be required to implement the mitigation strategy.
The mitigation strategy will be implemented prior to preliminary site clearance and other enabling works. It will comprise a capture, small-scale relocation and exclusion programme to avoid the disturbance, injury or killing of individual great crested newts within the Site. This mitigation strategy has been agreed in principle with
In summary, the mitigation strategy will involve:
A toolbox talk will be presented by the licensed ecologist to all staff the construction of the Power Station Complex and Gas Connection, in particular
involved in site clearance during the preliminary works stage. This will that all personnel are aware of the presence of great crested newts
afforded to great crested newts under the legislation, the mitigation strategies that will be implemented and the appropriate action to take if a great
untered;
fencing around the pond which will be lost to the Scheme;
The erection of temporary exclusion fencing around the perimeter of the Site to exclude great crested newts from the Power Station Complex footprint, the
aydown area, the route of the gas pipeline and any area which will be subject to earthworks in order to implement the inherent landscape strategy (including the creation of new great crested newt ponds) and the drainage
The provision of a receptor area within the Site, allowing great crested newts access to three existing great crested newt ponds (the receptor area will not be subject to any construction or landscape activities);
The erection of drift fencing within the Site to increase trapping effort;will be erected during the winter immediately prior to the spring trapping
Pitfall trapping (in combination with the use of refuges) for a minimum of 30 days (with at least 5 ‘clear’ trapping days before the Site can be declaregreat crested newts), using a spacing of alternate traps and refuges every 5 m. The trapping array will be located either side of the ring-fencing and drift fencing and around the interior perimeter of the exclusion fencing; Trapping will
ence at the earliest opportunity during the spring migration to breeding ponds, i.e. February to May, and will be dependent on local weather conditions (trapping will not be undertaken when night air temperatures are below 5°C);
The area required for the creation of three new ponds (to compensate for the loss of an existing great crested newt pond) will be fenced and trapped first to
ation 53 of the Conservation of Habitats and , will be required to implement the mitigation strategy.
The mitigation strategy will be implemented prior to preliminary site clearance and scale relocation and exclusion
programme to avoid the disturbance, injury or killing of individual great crested newts within the Site. This mitigation strategy has been agreed in principle with
involved in the construction of the Power Station Complex and Gas Connection, in particular
involved in site clearance during the preliminary works stage. This will that all personnel are aware of the presence of great crested newts, the
, the mitigation strategies that will be implemented and the appropriate action to take if a great
fencing around the pond which will be lost to the Scheme;
The erection of temporary exclusion fencing around the perimeter of the Site to exclude great crested newts from the Power Station Complex footprint, the
aydown area, the route of the gas pipeline and any area which will be subject to earthworks in order to implement the inherent landscape strategy (including the creation of new great crested newt ponds) and the drainage
tor area within the Site, allowing great crested newts access to three existing great crested newt ponds (the receptor area will not be
effort; All fencing will be erected during the winter immediately prior to the spring trapping
Pitfall trapping (in combination with the use of refuges) for a minimum of 30 days (with at least 5 ‘clear’ trapping days before the Site can be declared ‘clear’ of
ate traps and refuges every 5 m. fencing and drift fencing
Trapping will ence at the earliest opportunity during the spring migration to breeding
ponds, i.e. February to May, and will be dependent on local weather conditions (trapping will not be undertaken when night air temperatures are below 5°C);
reation of three new ponds (to compensate for the loss of an existing great crested newt pond) will be fenced and trapped first to
ensure that the new ponds will be built and suitable for receiving great crested newts prior to the draining of the pond thatcompletion of the new ponds they will form part of the receptor areawill have appropriate shallow margins and the provision of suitable aquatic planting or artificial eggartificial egg-laying strips should be explored as this would reduce the risk of importing potentially harmful pathogens
• Relocation of captured great crested newts to the receptor area, allowing animals to access existing ponds and teSite;
• Following completion of trapping, the pond which will be lost to the Scheme will be drained down; netting and handgreat crested newts will be undertaken whilst t
• Provision of features to prevent the risk of great crested newts (and other reptiles, amphibians and small mammals) bring trapped in drainage structures such as gully pots and flow control chambers
• Maintenance of fencing via regul
5.30 A phased approach to the capture and relocation programme will be undertaken to allow preliminary site clearance and enabling works to commence as required (subject to areas being declared ‘clear’ of great crested newts.
5.31 Mitigation measures to avoid and reduce potential adverse effects on great crested newt ponds via pollution impacts on local air quality and on the local water environment are described elsewhere in this
Otters
5.32 A Precautionary Method of Working (PMW) will be implemenotters, comprising:
• A pre-construction survey of the within the working area;
• No external lighting of the
• The safe passage of otters through the works albe provided for throughout the works;
• Temporary accommodation and idling plant, machinery or traffic will be located as far away from the River Clywedog
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
ensure that the new ponds will be built and suitable for receiving great crested newts prior to the draining of the pond that will be lost to the Scheme. Upon completion of the new ponds they will form part of the receptor area. will have appropriate shallow margins and the provision of suitable aquatic planting or artificial egg-laying strips to provide egg-laying substrate. The use of
laying strips should be explored as this would reduce the risk of importing potentially harmful pathogens;
Relocation of captured great crested newts to the receptor area, allowing animals to access existing ponds and terrestrial habitat which remain within the
Following completion of trapping, the pond which will be lost to the Scheme will be drained down; netting and hand-searching through plants, debris and silt for great crested newts will be undertaken whilst the pond is being drained;
Provision of features to prevent the risk of great crested newts (and other reptiles, amphibians and small mammals) bring trapped in drainage structures such as gully pots and flow control chambers
Maintenance of fencing via regular inspections.
A phased approach to the capture and relocation programme will be undertaken to allow preliminary site clearance and enabling works to commence as required (subject to areas being declared ‘clear’ of great crested newts.
to avoid and reduce potential adverse effects on great crested newt ponds via pollution impacts on local air quality and on the local water
are described elsewhere in this CEMP.
A Precautionary Method of Working (PMW) will be implemented to avoid disturbing
construction survey of the River Clywedog to ensure no holts are present area;
No external lighting of the River Clywedog during the night;
The safe passage of otters through the works along at least one bank will always be provided for throughout the works;
Temporary accommodation and idling plant, machinery or traffic will be located River Clywedog as is reasonably practicable;
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
21
ensure that the new ponds will be built and suitable for receiving great crested will be lost to the Scheme. Upon
. The ponds will have appropriate shallow margins and the provision of suitable aquatic
bstrate. The use of laying strips should be explored as this would reduce the risk of
Relocation of captured great crested newts to the receptor area, allowing rrestrial habitat which remain within the
Following completion of trapping, the pond which will be lost to the Scheme will searching through plants, debris and silt for
he pond is being drained;
Provision of features to prevent the risk of great crested newts (and other reptiles, amphibians and small mammals) bring trapped in drainage structures
A phased approach to the capture and relocation programme will be undertaken to allow preliminary site clearance and enabling works to commence as required
to avoid and reduce potential adverse effects on great crested newt ponds via pollution impacts on local air quality and on the local water
ted to avoid disturbing
to ensure no holts are present
ong at least one bank will always
Temporary accommodation and idling plant, machinery or traffic will be located
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
22
• A toolbox talk to all relevant site perotter and the relevant legislation.
Breeding Birds
5.33 To ensure that no offences are committed under the Wi1981, any preliminary site clearance of vegetation suitable for supporting nestibirds will be undertaken outside of the nesting bird season (which is generally considered to be February to September inclusive, but is dependent on species and seasonal variation).
5.34 Should any clearance be required during the nesting bird season, a detinspection for nesting birds should be carried out, by a suitably experienced ecologist, no more than 24 hours prior to any clearance being undertaken. This minimises opportunities for nest building between the inspection and the start of any clearance. Any nest in use or being built during this inspection will need to be left in-situ, with an appropriate buffer of surrounding vegetation, until any young birds have fledged the nest and
Reptiles
5.35 To ensure that no offences are 1981, a Precautionary Method of Working (PMW) will be implemented to avoid or minimise the risk of injuring or killing reptiles during preliminary site clearance and enabling works.
5.36 In summary, the PMW will involve:
• The removal of any piles of wood, brash and rubble from the Power Station Complex footprint and construction laydown area by hand prior to preliminary site clearance and enabling works, with a suitably experienced ecologist onto provide advice and ideally not during the winter hibernating period for reptiles (November to February);
• Hand searching for reptiles by carefully checking within and underneath any potentially suitable refuges such as leaf piles around logs, tree trunks, bush stems and within coppice stools. Areas of dense vegetation may need to be strimmed/ cut by a contractor, with a suitably experienced ecologist onadvice, to approximately 150 mm height to enable the hand search to be undertaken;
• The removal of any refuge materials and cut vegetation from the power station complex footprint and construction laydown area;
• Any vegetation remaining within the Power Station Complex footprint and construction laydown area will be maintained at a height of less than 50 mmthroughout construction;
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
A toolbox talk to all relevant site personnel highlighting the potential impacts to otter and the relevant legislation.
To ensure that no offences are committed under the Wildlife and Countryside Act , any preliminary site clearance of vegetation suitable for supporting nesti
birds will be undertaken outside of the nesting bird season (which is generally considered to be February to September inclusive, but is dependent on species and
Should any clearance be required during the nesting bird season, a detinspection for nesting birds should be carried out, by a suitably experienced ecologist, no more than 24 hours prior to any clearance being undertaken. This minimises opportunities for nest building between the inspection and the start of
nce. Any nest in use or being built during this inspection will need to be situ, with an appropriate buffer of surrounding vegetation, until any young
birds have fledged the nest and it is no longer in use.
To ensure that no offences are committed under the Wildlife and Countryside Act , a Precautionary Method of Working (PMW) will be implemented to avoid or
minimise the risk of injuring or killing reptiles during preliminary site clearance and
involve:
The removal of any piles of wood, brash and rubble from the Power Station Complex footprint and construction laydown area by hand prior to preliminary site clearance and enabling works, with a suitably experienced ecologist on
ce and ideally not during the winter hibernating period for reptiles (November to February);
Hand searching for reptiles by carefully checking within and underneath any potentially suitable refuges such as leaf piles around logs, tree trunks, bush stems
d within coppice stools. Areas of dense vegetation may need to be strimmed/ cut by a contractor, with a suitably experienced ecologist on-hand to provide advice, to approximately 150 mm height to enable the hand search to be
refuge materials and cut vegetation from the power station complex footprint and construction laydown area;
Any vegetation remaining within the Power Station Complex footprint and construction laydown area will be maintained at a height of less than 50 mmthroughout construction;
sonnel highlighting the potential impacts to
ldlife and Countryside Act , any preliminary site clearance of vegetation suitable for supporting nesting
birds will be undertaken outside of the nesting bird season (which is generally considered to be February to September inclusive, but is dependent on species and
Should any clearance be required during the nesting bird season, a detailed inspection for nesting birds should be carried out, by a suitably experienced ecologist, no more than 24 hours prior to any clearance being undertaken. This minimises opportunities for nest building between the inspection and the start of
nce. Any nest in use or being built during this inspection will need to be situ, with an appropriate buffer of surrounding vegetation, until any young
committed under the Wildlife and Countryside Act , a Precautionary Method of Working (PMW) will be implemented to avoid or
minimise the risk of injuring or killing reptiles during preliminary site clearance and
The removal of any piles of wood, brash and rubble from the Power Station Complex footprint and construction laydown area by hand prior to preliminary site clearance and enabling works, with a suitably experienced ecologist on-hand
ce and ideally not during the winter hibernating period for reptiles
Hand searching for reptiles by carefully checking within and underneath any potentially suitable refuges such as leaf piles around logs, tree trunks, bush stems
d within coppice stools. Areas of dense vegetation may need to be strimmed/ hand to provide
advice, to approximately 150 mm height to enable the hand search to be
refuge materials and cut vegetation from the power station
Any vegetation remaining within the Power Station Complex footprint and construction laydown area will be maintained at a height of less than 50 mm
• A toolbox talk to all relevant site personnel highlighting the potential impacts to reptiles and the relevant legislation.
Badgers
5.37 No badger setts were found within 30 m of the WEC dispersal of badgers across the Gas Connection Route, all excavations will be covered or fenced off at night or left with a means of escape such as a plank of wood laid at a 45° angle. Appropriate measures will be implemented should it become evident that badgers are not navigating over the great crested newt exclusion fencing, such as timber ramps positioned either side of the fencing. These will ensure that badgers can disperse across the Gas Connection Route whilst avoiding damaging the exclusion fencing.
Bats
5.38 A licence issued by NRW, under Regulation 53 of the Conservation of Habitats and Species Regulations 2010, will be required to implement the mitigation strategy. The licence will be in effect for the duration of construction of the months, to ensure that any construction activities, do not result in the disturbance, injury or killing of bats.
5.39 The mitigation strategy will be implemented prior to any preliminary site clearance and other enabling works. It will comprise a Precautionary Method of Wo(PMW) for felling trees which have been assessed as having bat roost potential to avoid the injury or killing of any roosting bats, sensitive working methods to avoid potential disturbance or roosting bats in trees which are to be retained (includinginvestigation in to the use of appropriate sound barriers, particularly along the northern extents of the Power Station Complex disturbance of the confirmed and possible tree roosts to the north of the Power Station Complex).
5.40 In summary, the mitigation strategy will involve:
• A toolbox talk will be presented by the named ecologist or an accredited agent to all staff, in particular thosethe preliminary works stage. This will legislation afforded to bats and their roosts, the mitigation strategyappropriate action to take if a bat is encountered during the tree works and construction
• The erection of an array of bat boxes on suitabComplex Site prior to the commencement of the felling of any trees with bat roost potential to compensate for the loss of potential roosts and to provide alternative roosting habitat for any potentially displaced bats
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
A toolbox talk to all relevant site personnel highlighting the potential impacts to reptiles and the relevant legislation.
No badger setts were found within 30 m of the WEC Site. However, to allow the safe gers across the Gas Connection Route, all excavations will be covered
or fenced off at night or left with a means of escape such as a plank of wood laid at a 45° angle. Appropriate measures will be implemented should it become evident that
navigating over the great crested newt exclusion fencing, such as timber ramps positioned either side of the fencing. These will ensure that badgers can disperse across the Gas Connection Route whilst avoiding damaging the
issued by NRW, under Regulation 53 of the Conservation of Habitats and Species Regulations 2010, will be required to implement the mitigation strategy. The licence will be in effect for the duration of construction of the Scheme
e that any construction activities, do not result in the disturbance,
The mitigation strategy will be implemented prior to any preliminary site clearance and other enabling works. It will comprise a Precautionary Method of Wo(PMW) for felling trees which have been assessed as having bat roost potential to avoid the injury or killing of any roosting bats, sensitive working methods to avoid potential disturbance or roosting bats in trees which are to be retained (includinginvestigation in to the use of appropriate sound barriers, particularly along the northern extents of the Power Station Complex Site to avoid or reduce noise disturbance of the confirmed and possible tree roosts to the north of the Power
In summary, the mitigation strategy will involve:
A toolbox talk will be presented by the named ecologist or an accredited agent to those involved in the tree works and site clearance during
the preliminary works stage. This will ensure that all staff are aware of the legislation afforded to bats and their roosts, the mitigation strategyappropriate action to take if a bat is encountered during the tree works and
The erection of an array of bat boxes on suitable trees within the Power Station Complex Site prior to the commencement of the felling of any trees with bat roost potential to compensate for the loss of potential roosts and to provide alternative roosting habitat for any potentially displaced bats. Bat boxes must be
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
23
A toolbox talk to all relevant site personnel highlighting the potential impacts to
o allow the safe gers across the Gas Connection Route, all excavations will be covered
or fenced off at night or left with a means of escape such as a plank of wood laid at a 45° angle. Appropriate measures will be implemented should it become evident that
navigating over the great crested newt exclusion fencing, such as timber ramps positioned either side of the fencing. These will ensure that badgers can disperse across the Gas Connection Route whilst avoiding damaging the
issued by NRW, under Regulation 53 of the Conservation of Habitats and Species Regulations 2010, will be required to implement the mitigation strategy. The
Scheme, i.e. 36 e that any construction activities, do not result in the disturbance,
The mitigation strategy will be implemented prior to any preliminary site clearance and other enabling works. It will comprise a Precautionary Method of Working (PMW) for felling trees which have been assessed as having bat roost potential to avoid the injury or killing of any roosting bats, sensitive working methods to avoid potential disturbance or roosting bats in trees which are to be retained (including investigation in to the use of appropriate sound barriers, particularly along the
to avoid or reduce noise disturbance of the confirmed and possible tree roosts to the north of the Power
A toolbox talk will be presented by the named ecologist or an accredited agent to involved in the tree works and site clearance during
are aware of the legislation afforded to bats and their roosts, the mitigation strategy, and the appropriate action to take if a bat is encountered during the tree works and
le trees within the Power Station Complex Site prior to the commencement of the felling of any trees with bat roost potential to compensate for the loss of potential roosts and to provide
boxes must be
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
24
installed in areas not at risk of future developmentloss of roosting opportunities for the local bat population
• A PMW which will be employed during the treefelling tree inspections and soft
• The confirmed soprano pipistrelle day roost (see TN 61 on Figure 11.5 of the ES), which requires facilitation pruning, and all trees that have been assessed as having bat roost potential which require fellingpipistrelle day roost (see TN 26 on Figure 11.5 of the ES), will be subject to comprehensive, elevated external and internal inspections in order to establish the presence of, or evidence of, bats immediately prior to the t
• The careful removal by hand of any bats found during the course of the treefelling to the pre-erected bat boxes;
• Where possible, significant bat roost features within the trees to be felled will be carefully section-cut and strapped to existingComplex to encourage the Continued Ecological Functionality (CEF) of any such features
• Works in the Gas Connection Route identified as having bat roost potential. The identified trepotential will be marked out on site with an ecologist and an engineer to ensure the works do not encroach within 10m of these trees;
• Temporary accommodation and idling plant, machinery or traffic will be located as far away from any treereasonably practicable;
• Annual monitoring of the bat boxes during the construction phase of the Scheme and the first year its operation.
5.41 Noise management measures will be implemented to prevent disturbance odamage to trees with bat roost potentialup. A precautionary method of working document will be prepared by an ecologist and delivered to Project and Project Environmental Lead to ensure that these measures are implemented. Toolbox talks will also be provided
5.42 Lighting to be used during construction will be directed away from potential bat roost, foraging or commuting features (in particular the mature trees that are being retained and habitat within the Ecological Mitigation Area)months when bats may still be active moving between hibernating roostsexternal lighting of the Gas Connection route
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
installed in areas not at risk of future development to ensure there is no overall loss of roosting opportunities for the local bat population;
A PMW which will be employed during the tree-felling operations, involving prections and soft-fell techniques (if necessary);
The confirmed soprano pipistrelle day roost (see TN 61 on Figure 11.5 of the ES), which requires facilitation pruning, and all trees that have been assessed as having bat roost potential which require felling, including the possible soprano pipistrelle day roost (see TN 26 on Figure 11.5 of the ES), will be subject to comprehensive, elevated external and internal inspections in order to establish the presence of, or evidence of, bats immediately prior to the tree works
The careful removal by hand of any bats found during the course of the treeerected bat boxes;
Where possible, significant bat roost features within the trees to be felled will be cut and strapped to existing trees within the Power Station
Complex to encourage the Continued Ecological Functionality (CEF) of any such
in the Gas Connection Route will not involve the felling of any trees identified as having bat roost potential. The identified trees with bapotential will be marked out on site with an ecologist and an engineer to ensure the works do not encroach within 10m of these trees;
Temporary accommodation and idling plant, machinery or traffic will be located as far away from any trees identified as having bat roost potential as is
Annual monitoring of the bat boxes during the construction phase of the Scheme operation.
Noise management measures will be implemented to prevent disturbance otrees with bat roost potential. Root Protection Zones (RPZ’s) will be set
up. A precautionary method of working document will be prepared by an ecologist Project and Project Environmental Lead prior to works in this area
ure that these measures are implemented. Toolbox talks will also be provided
Lighting to be used during construction will be directed away from potential bat roost, foraging or commuting features (in particular the mature trees that are being
habitat within the Ecological Mitigation Area), particularly in winter months when bats may still be active moving between hibernating roostsexternal lighting of the Gas Connection route at night after 19:00 hours.
to ensure there is no overall
felling operations, involving pre-
The confirmed soprano pipistrelle day roost (see TN 61 on Figure 11.5 of the ES), which requires facilitation pruning, and all trees that have been assessed as
, including the possible soprano pipistrelle day roost (see TN 26 on Figure 11.5 of the ES), will be subject to comprehensive, elevated external and internal inspections in order to establish
ree works;
The careful removal by hand of any bats found during the course of the tree-
Where possible, significant bat roost features within the trees to be felled will be trees within the Power Station
Complex to encourage the Continued Ecological Functionality (CEF) of any such
will not involve the felling of any trees es with bat roost
potential will be marked out on site with an ecologist and an engineer to ensure
Temporary accommodation and idling plant, machinery or traffic will be located s identified as having bat roost potential as is
Annual monitoring of the bat boxes during the construction phase of the Scheme
Noise management measures will be implemented to prevent disturbance or ones (RPZ’s) will be set
up. A precautionary method of working document will be prepared by an ecologist prior to works in this area
ure that these measures are implemented. Toolbox talks will also be provided.
Lighting to be used during construction will be directed away from potential bat roost, foraging or commuting features (in particular the mature trees that are being
, particularly in winter months when bats may still be active moving between hibernating roosts. No
Invasive Plants
5.43 All invasive species within the WEC Site boundary will be identified and managed appropriately in accordance with best practice prior tomanagement plan for the ongoing identification and eradication of invasive species will be developed and implemJapanese knotweed Code of Practice.
General Biosecurity
5.44 In order to mitigate general biosecurity risks, good practice guidance from the Forestry Commission1 should be adhered to during construction anoperational maintenance works.
5.45 The Forestry Commission good practice guidance notes that for low risk sites and activities:
• Wear footwear and outerwear that be easily kept clean.
• Clean footwear and outerwear regularly; ensure they are visuallfree from soil and organic debris.
• Clean vehicles regularly; do not let mud and organic debris accumulate on tyres, wheels or under wheel arches.
• Restrict the equipment taken onto a site for the task.
• Ensure all tools and equipmeorganic debris.
5.46 In order to avoid the risk of Chalara dieback, Checks must be made for evidence of Phytophthora on all plant stocks to be used on site, prior to them leaving the nursery. In order to avoid the risk ofthat no evidence of Chalara was found on Site), ash trees should not be exported from site.
Hedgerows
5.47 To mitigate the short term seretained hedgerow arising’along the break in the hedgerow.
1 http://www.forestry.gov.uk/pdf/FCMS028
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
s within the WEC Site boundary will be identified and managed appropriately in accordance with best practice prior to and during construction. A management plan for the ongoing identification and eradication of invasive species will be developed and implemented should they exist on-site , paying heed to the EA Japanese knotweed Code of Practice.
In order to mitigate general biosecurity risks, good practice guidance from the should be adhered to during construction and appropriate
operational maintenance works.
The Forestry Commission good practice guidance notes that for low risk sites and
Wear footwear and outerwear that be easily kept clean.
Clean footwear and outerwear regularly; ensure they are visuallfree from soil and organic debris.
Clean vehicles regularly; do not let mud and organic debris accumulate on tyres, wheels or under wheel arches.
Restrict the equipment taken onto a site – on only what is needed
Ensure all tools and equipment are clean, serviceable and free from
In order to avoid the risk of Chalara dieback, Checks must be made for evidence of Phytophthora on all plant stocks to be used on site, prior to them leaving the nursery. In order to avoid the risk of Chalara dieback being exported (although note that no evidence of Chalara was found on Site), ash trees should not be exported
To mitigate the short term severance of hedgerows along the Gas Connection Rretained hedgerow arising’s will be placed in barrels of sand located at intervals along the break in the hedgerow.
http://www.forestry.gov.uk/pdf/FCMS028-guidance.pdf/$file/FCMS028-guidance.pdf
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
25
s within the WEC Site boundary will be identified and managed construction. A
management plan for the ongoing identification and eradication of invasive species , paying heed to the EA
In order to mitigate general biosecurity risks, good practice guidance from the d appropriate
The Forestry Commission good practice guidance notes that for low risk sites and
Clean footwear and outerwear regularly; ensure they are visually
on only what is needed
nt are clean, serviceable and free from
In order to avoid the risk of Chalara dieback, Checks must be made for evidence of Phytophthora on all plant stocks to be used on site, prior to them leaving the
Chalara dieback being exported (although note that no evidence of Chalara was found on Site), ash trees should not be exported
Connection Route s will be placed in barrels of sand located at intervals
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
26
Landscape and Visual Amenity
5.48 The following management practices will be secured:
• Implement tree protection fencing for retained vegetation prior to construction commencing and establish construction exclusion zones and methods of working adjacent to retained vegetation at tool box contractor talksAppendix A);
• Solid hoardings will be used to aid in visually screening the construction activity; and
• The construction site will be maintained in a clean and tidy manner, including covering of stockpiles
Transport and Traffic
5.49 As a general principle, construction traffic will be routed to minimise disruption on the network. The arrival of materials in the moperiods (07:30 – 09:00 and 16:30 Construction Traffic Management Plan (CTMP)based on the Draft CTMP provided in Appendix 7contractor that will detail the management of construction vehicle arrivals and departures, and will include the following specific measures as a minimum:
• An HGV booking/management system for vehicles 10 tonnes and larger which will allow drivers to book prepossibility of multiple HGVs causing congestion by smoothing out peaks in traffic. It will ensure that arrivals and departures are spread as evenly as possible over the course of the working day;
• All construction plant and vehicles will be parked onhighway;
• A system will be implemented for preabnormal loads to the authorities and the local community, and provide escorts where required;
• A wheel wash facility will be provided for all construction vehicles leaving the WEC Site. This will minimise the level of dust and dirt being transferred to the public highway. Site entrances and adjacent public highway will be and swept clear if required;
• A 24 hour contact number and a named member of staff (the community liaison manager) will be made available to the public to report any issues or concerns relating to construction traffic. This will allow nonroutes and inappropriate driving to be reported and addressed;
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
The following management practices will be secured:
Implement tree protection fencing for retained vegetation prior to construction ncing and establish construction exclusion zones and methods of working
adjacent to retained vegetation at tool box contractor talks (further details in
Solid hoardings will be used to aid in visually screening the construction activity;
he construction site will be maintained in a clean and tidy manner, including
As a general principle, construction traffic will be routed to minimise disruption on the network. The arrival of materials in the morning and afternoon highway peak
09:00 and 16:30 – 18:00) will be avoided as far as possible. A Construction Traffic Management Plan (CTMP) including a Construction Travel Planbased on the Draft CTMP provided in Appendix 7.5, will be prepared by the approved contractor that will detail the management of construction vehicle arrivals and departures, and will include the following specific measures as a minimum:
An HGV booking/management system for vehicles 10 tonnes and larger which drivers to book pre-determined time slots for deliveries to reduce the
possibility of multiple HGVs causing congestion by smoothing out peaks in traffic. It will ensure that arrivals and departures are spread as evenly as possible over
he working day;
All construction plant and vehicles will be parked on-site and not on the public
A system will be implemented for pre-notification of deliveries involving authorities and the local community, and provide
A wheel wash facility will be provided for all construction vehicles leaving the will minimise the level of dust and dirt being transferred to the
public highway. Site entrances and adjacent public highway will be and swept clear if required;
A 24 hour contact number and a named member of staff (the community liaison be made available to the public to report any issues or concerns
relating to construction traffic. This will allow non-compliance with agreed access routes and inappropriate driving to be reported and addressed;
Implement tree protection fencing for retained vegetation prior to construction ncing and establish construction exclusion zones and methods of working
(further details in
Solid hoardings will be used to aid in visually screening the construction activity;
he construction site will be maintained in a clean and tidy manner, including
As a general principle, construction traffic will be routed to minimise disruption on rning and afternoon highway peak
18:00) will be avoided as far as possible. A including a Construction Travel Plan,
pared by the approved contractor that will detail the management of construction vehicle arrivals and departures, and will include the following specific measures as a minimum:
An HGV booking/management system for vehicles 10 tonnes and larger which determined time slots for deliveries to reduce the
possibility of multiple HGVs causing congestion by smoothing out peaks in traffic. It will ensure that arrivals and departures are spread as evenly as possible over
site and not on the public
notification of deliveries involving authorities and the local community, and provide vehicle
A wheel wash facility will be provided for all construction vehicles leaving the will minimise the level of dust and dirt being transferred to the
public highway. Site entrances and adjacent public highway will be monitored
A 24 hour contact number and a named member of staff (the community liaison be made available to the public to report any issues or concerns
ce with agreed access
• Temporary signage will be installed to warn motorists of vehicles entering and exiting the site and to alert the construction traffic vehicles to the appropriate site access. The temporary site access points on Oak appropriate signage and temporary traffic management, while the field access points are in use.
• Consideration will be given to the use of onwould significantly reduce the number of HGV deliveries to the construction of the foundations (and will also help to reduce vehicle noise, air emissions and waste).
• Construction equipment and materials for the Gas Connection at the Power Station Complex or on the Gas Connection Route and transported along the route itself where suitable to minimize movements on the local highway network.
5.50 The construction working day will be arranged between 07:00 to stagger start and finish times. Further measures to be included in the CTMP may include:
• Information collection, to determine likely staff travel modes and patterns;
• Vehicle sharing
• Vehicle routing;
• Car parking provision;
• Public transport opportunities;
• Cycling; and
• Local recruitment policies (see also socio
Archaeology
5.51 A Written Scheme of Investigation will be agreed with the Local Authority and will include the following activities:
• Geophysical survey of the greenfield areas of the scheme
• Targeted archaeological investigation of anomalies identified by the geophysical surveys; and
• Archaeological watching brief
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Temporary signage will be installed to warn motorists of vehicles entering and exiting the site and to alert the construction traffic vehicles to the appropriate
ss. The temporary site access points on Oak Road will require appropriate signage and temporary traffic management, while the field access
Consideration will be given to the use of on-site concrete batching plant which y reduce the number of HGV deliveries to the WEC
construction of the foundations (and will also help to reduce vehicle noise, air
Construction equipment and materials for the Gas Connection shouldation Complex or on the Gas Connection Route and transported
along the route itself where suitable to minimize movements on the local
The construction working day will be arranged between 07:00 – 19:00, allowing staff finish times. Further measures to be included in the CTMP may
Information collection, to determine likely staff travel modes and patterns;
Public transport opportunities;
ecruitment policies (see also socio-economics).
A Written Scheme of Investigation will be agreed with the Local Authority and will include the following activities:
Geophysical survey of the greenfield areas of the scheme;
al investigation of anomalies identified by the geophysical
watching brief.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
27
Temporary signage will be installed to warn motorists of vehicles entering and exiting the site and to alert the construction traffic vehicles to the appropriate
will require appropriate signage and temporary traffic management, while the field access
site concrete batching plant which Site during
construction of the foundations (and will also help to reduce vehicle noise, air
should be stored ation Complex or on the Gas Connection Route and transported
along the route itself where suitable to minimize movements on the local
19:00, allowing staff finish times. Further measures to be included in the CTMP may
Information collection, to determine likely staff travel modes and patterns;
A Written Scheme of Investigation will be agreed with the Local Authority and will
al investigation of anomalies identified by the geophysical
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
28
Ground Conditions
5.52 Prior to construction, a ground investigationhelp define the extent and nature of contaminawill inform a quantitative land contamination assessment and remediation strategy (if necessary), and will also inform the final piling strategy and building design.
5.53 The results of the GI and subsequent risk assessments iCL:AIRE code of practice will inform how all excavated materials will be dealt with. For example excavated material may be:
• re-used on site if suitable for use without treatment;
• re-used on site if suitable for use after treatment;
• re-used on a separate site without treatment or following treatment; or
• removed from site as waste.
5.54 A verification plan and methodology will identify what remedial actions will be undertaken and how such actions will be validated and recorded if unexpected contamination is encountered during the works
5.55 In addition, the following specific mitigation measures will be implemented during construction:
• Implementation of appropriate dust suppression measures to prevent migration of contaminated dust as set out in tCEMP;
• Health and safety risk assessments, method statements and appropriate personal protective equipment (PPE) for the protection of construction workers when working in contaminated
• Working methods during conthe works or any stockpiles into adjacent surface watercourses does not cause pollution, in accordanceconstruction and demolition sites, PPG6);
• Piling strategy as per the EA guidance and implementation of piling techniques deemed appropriate by the strategy; and
• A methodology to address what remedial actions will be undertaken and how such actions will be validated and recorded if unsuspected contamination encountered during the works.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Prior to construction, a ground investigation (GI) will have been carried out that will help define the extent and nature of contaminated material on the WEC Site. This
quantitative land contamination assessment and remediation strategy inform the final piling strategy and building design.
and subsequent risk assessments in accordance with the CL:AIRE code of practice will inform how all excavated materials will be dealt with. For example excavated material may be:
used on site if suitable for use without treatment;
used on site if suitable for use after treatment;
used on a separate site without treatment or following treatment; or
removed from site as waste.
A verification plan and methodology will identify what remedial actions will be undertaken and how such actions will be validated and recorded if unexpected contamination is encountered during the works
In addition, the following specific mitigation measures will be implemented during
Implementation of appropriate dust suppression measures to prevent migration contaminated dust as set out in the nuisance management measures in the
Health and safety risk assessments, method statements and appropriate personal equipment (PPE) for the protection of construction workers when
working in contaminated areas;
Working methods during construction to ensure that surface water runany stockpiles into adjacent surface watercourses does not cause
pollution, in accordance with Pollution Prevention Guidelines (working at construction and demolition sites, PPG6);
ategy as per the EA guidance and implementation of piling techniques appropriate by the strategy; and
A methodology to address what remedial actions will be undertaken and how will be validated and recorded if unsuspected contamination
encountered during the works.
will have been carried out that will ted material on the WEC Site. This
quantitative land contamination assessment and remediation strategy inform the final piling strategy and building design.
n accordance with the CL:AIRE code of practice will inform how all excavated materials will be dealt with.
used on a separate site without treatment or following treatment; or
A verification plan and methodology will identify what remedial actions will be undertaken and how such actions will be validated and recorded if unexpected
In addition, the following specific mitigation measures will be implemented during
Implementation of appropriate dust suppression measures to prevent migration he nuisance management measures in the
Health and safety risk assessments, method statements and appropriate personal equipment (PPE) for the protection of construction workers when
struction to ensure that surface water run-off from any stockpiles into adjacent surface watercourses does not cause
with Pollution Prevention Guidelines (working at
ategy as per the EA guidance and implementation of piling techniques
A methodology to address what remedial actions will be undertaken and how will be validated and recorded if unsuspected contamination is
Land Use
5.56 The following measures will be implemented to minimise the effects on agriculturland:
• Observing best construction practice to control dust and weeds
• Disturbance to drains and water supplies to be restored as nec
• Soil handling and storage to follow best industry practiceto equivalent quality.
• Liaise with landowners and temporary crossings of the construction corridor
• Provide temporary water supplies during constructiondrains and water supplies on completion of work
• Provide temporary fencing during construction and restore permanent boundaries on completion of work
• Liaise with farmers about timing
• Liaise with landowners and farmers about timing of work in relation to game bird shoot and to replanting of game bird cover as appropriate
Waste
Excavation
5.57 Where excavated material (soil) is suitable for use from a contamigeotechnical perspective it will be reused across the
5.58 Hazardous materials will be treated onremoved off-site for disposal/treatment. An appropriately licensed contractor will be responsible for dealing with the waste. Records of waste movement will be maintained on-site and in line with legislative requirements and the SWMP.
Construction
5.59 Material will be recycled/reused indicators (within the Site Wappropriate levels. Hazardous materials will be removed disposal/treatment by an appropriately licensed contractor, who will be responsible
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
The following measures will be implemented to minimise the effects on agricultur
best construction practice to control dust and weeds
Disturbance to drains and water supplies to be restored as necessary
Soil handling and storage to follow best industry practice and land to be restored
landowners and farmers and provide alternative field accesses and temporary crossings of the construction corridor, if required.
ovide temporary water supplies during construction, if requireddrains and water supplies on completion of work
Provide temporary fencing during construction and restore permanent boundaries on completion of work
farmers about timing of work to minimise crop losses
Liaise with landowners and farmers about timing of work in relation to game bird shoot and to replanting of game bird cover as appropriate.
Where excavated material (soil) is suitable for use from a contamination and geotechnical perspective it will be reused across the Site.
Hazardous materials will be treated on-site where possible, or will otherwise be site for disposal/treatment. An appropriately licensed contractor will
ealing with the waste. Records of waste movement will be and in line with legislative requirements and the SWMP.
Material will be recycled/reused on-site where possible with key performance Waste Management Plan (SWMP)), set at challenging but
appropriate levels. Hazardous materials will be removed offdisposal/treatment by an appropriately licensed contractor, who will be responsible
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
29
The following measures will be implemented to minimise the effects on agricultural
and to be restored
farmers and provide alternative field accesses and
, if required. Restore
Provide temporary fencing during construction and restore permanent
Liaise with landowners and farmers about timing of work in relation to game bird
nation and
ite where possible, or will otherwise be site for disposal/treatment. An appropriately licensed contractor will
ealing with the waste. Records of waste movement will be and in line with legislative requirements and the SWMP.
erformance ), set at challenging but
off-site for disposal/treatment by an appropriately licensed contractor, who will be responsible
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
30
for dealing with the waste. All records of waste movemeline with legislative requirements.
5.60 Material removed from Site will be reused or recycled wherever possible. Where possible, the recycling/reuse of material with key performance indicpreferred option.
5.61 Where possible, the use of nonsought. The use of renewable materials, materials with low(er) environmental effects and towards components with high(er) proportions of recycled material to be utilised where possible.
5.62 The contractors will maintain the SWMP to identify responsibilities, waste streams and plan for efficient materials and waste handling.
5.63 A concrete batching plant may bless waste being produced, than if material is brought in ready mixed by
5.64 Hazardous materials will be treated removed off-site for disposal/treatment. An approresponsible for dealing with the waste. All records of waste movement will be kept on-site and in line with legislative requirements.
5.65 Recycling containers will be provided to reduce residual waste produced through all phases of the Scheme’s development. A number of bins will be provided around the site, specifically in the welfare areas to enable segregation of waste produced by the workers on-site. To this end:
• segregation of materials on-site and those requiring offrecycling and recovery); and
• Site materials will be quantified and categorised in order to identify options for recycling and reuse.
5.66 All waste will be removed from Site by an appropriately licensed contractor and sent to recycling/treatment facilities as appropriate.
5.67 Where required, excavated material can be used for backfilling and compacting of the gas trench. The remaining material will be suitable for othe
Energy, Material Use and Water Consumption
5.68 Waste prevention has been built into the design through reuse of existing materials on the WEC Site. Implementation of this CEMP and general good construction practice will ensure that materialleading to waste generation, wherever possible. Where waste generation is
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
for dealing with the waste. All records of waste movement will be kept online with legislative requirements.
Material removed from Site will be reused or recycled wherever possible. Where possible, the recycling/reuse of material on-site will be undertaken in accordance with key performance indicators identified in the SWMP. Reuse on-site
Where possible, the use of non-primary materials over primary materials will be sought. The use of renewable materials, materials with low(er) environmental effects
onents with high(er) proportions of recycled material to be
The contractors will maintain the SWMP to identify responsibilities, waste streams and plan for efficient materials and waste handling.
may be employed on-site and would potentially less waste being produced, than if material is brought in ready mixed by HGVs
Hazardous materials will be treated on-site where possible, otherwise it will be site for disposal/treatment. An appropriately licensed contractor will be
responsible for dealing with the waste. All records of waste movement will be kept and in line with legislative requirements.
Recycling containers will be provided to reduce residual waste produced through all hases of the Scheme’s development. A number of bins will be provided around the
site, specifically in the welfare areas to enable segregation of waste produced by the . To this end:
segregation of materials on-site will enable the allocation of materials for reuse and those requiring off-site treatment (involving decontamination,
recycling and recovery); and
ite materials will be quantified and categorised in order to identify options for
d from Site by an appropriately licensed contractor and sent to recycling/treatment facilities as appropriate.
Where required, excavated material can be used for backfilling and compacting of the gas trench. The remaining material will be suitable for other on-site purposes.
Energy, Material Use and Water Consumption
Waste prevention has been built into the design through reuse of existing materials on the WEC Site. Implementation of this CEMP and general good construction practice will ensure that material generated on-site is classified and reused without leading to waste generation, wherever possible. Where waste generation is
on-site and in
Material removed from Site will be reused or recycled wherever possible. Where will be undertaken in accordance
will be the
primary materials over primary materials will be sought. The use of renewable materials, materials with low(er) environmental effects
onents with high(er) proportions of recycled material to be
The contractors will maintain the SWMP to identify responsibilities, waste streams
potentially result in HGVs.
where possible, otherwise it will be priately licensed contractor will be
responsible for dealing with the waste. All records of waste movement will be kept
Recycling containers will be provided to reduce residual waste produced through all hases of the Scheme’s development. A number of bins will be provided around the
site, specifically in the welfare areas to enable segregation of waste produced by the
of materials for reuse site treatment (involving decontamination,
ite materials will be quantified and categorised in order to identify options for
d from Site by an appropriately licensed contractor and sent
Where required, excavated material can be used for backfilling and compacting of purposes.
Waste prevention has been built into the design through reuse of existing materials on the WEC Site. Implementation of this CEMP and general good construction
is classified and reused without leading to waste generation, wherever possible. Where waste generation is
unavoidable, it will be removed from the WEC Site by suitably licensed contractors, and sent for reuse or recycling wherever possisite reuse and recycling of waste material, will be monitored through the arrangements set out in the waste section above.
5.69 The construction methodology will ensure that energy and water use are minimised. Water consumption will be minimised by harvesting rainwater for use as far as practicable, ensuring all taps are turned off when not in use and that water used in damping operations, vehicle washing etc., is kept to the minimum amount required to be effective by use of water
5.70 Energy efficiency techniques will be employed, including switching vehicles, plant and machinery off when not in use and using low energy lighting where practicable.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
unavoidable, it will be removed from the WEC Site by suitably licensed contractors, and sent for reuse or recycling wherever possible. On-site materials reuse, and offsite reuse and recycling of waste material, will be monitored through the arrangements set out in the waste section above.
The construction methodology will ensure that energy and water use are minimised. tion will be minimised by harvesting rainwater for use as far as
practicable, ensuring all taps are turned off when not in use and that water used in damping operations, vehicle washing etc., is kept to the minimum amount required
water-efficient dust suppression techniques.
Energy efficiency techniques will be employed, including switching vehicles, plant and machinery off when not in use and using low energy lighting where practicable.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
31
unavoidable, it will be removed from the WEC Site by suitably licensed contractors, materials reuse, and off-
site reuse and recycling of waste material, will be monitored through the
The construction methodology will ensure that energy and water use are minimised. tion will be minimised by harvesting rainwater for use as far as
practicable, ensuring all taps are turned off when not in use and that water used in damping operations, vehicle washing etc., is kept to the minimum amount required
Energy efficiency techniques will be employed, including switching vehicles, plant and machinery off when not in use and using low energy lighting where practicable.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
32
ARBORICULTURAL PROTECTION METHOD STATEMENT
Site Meetings and Supervision
A.1 The appointed contractor shall undertake a preto construction operations commencing on supervising Arboriculturist, Wworks. This meeting is to raise awareness with the relevant parties of the trees on Site and to confirm individual responsibilities regarding trees. This meeting is also to confirm the specific site events requiring inputto ensure an auditable system of arboricultural site monitoring.
A.2 The appointed contractor shall undertake a postcompletion of the construction works onsupervising Arboriculturist or undertaking the works.
CONSTRUCTION EXCLUSION ZONE AND PROTECTI
Construction Exclusion Zone (CEZ)
A.3 For the purpose of the CEMP the CEZs can be defined asthe Root Protection Area (RPAareas behind the tree protection fencing. CEZs without consultation with an Arboriculturist include sequipment or materials, vehicular or plant access, washing down of vehicles or machinery, handling, discharge or spillage of any substances, including cement washings, actions likely to cause localised waterscraping or excavation shall be permitted in the CEZ and no earthworks or changes in the finished ground levels other than those agreed by an Arboriculturist.
Protective Barriers
A.4 The protective barriers are to be installed prior to any works commencing. Tlocation and setting out details for the fencing shall be confirmed during a precommencement site meeting. The barriers are to be erected to exclude construction activity in the RPAs or remaining RPAs of retained trees. The protective barrier is to comprise 2m tall welded mesh panels on rubber or concrete feet. The panels are to be joined together using a minimum of two anti
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Appendix A u Tree Protection
ON METHOD STATEMENT
contractor shall undertake a pre-commencement site meeting prior to construction operations commencing on Site. This meeting is to include the
pervising Arboriculturist, WCBC Tree Officer and the contractors undertaking the works. This meeting is to raise awareness with the relevant parties of the trees on
ite and to confirm individual responsibilities regarding trees. This meeting is also to confirm the specific site events requiring input or supervision from an Arboriculturist to ensure an auditable system of arboricultural site monitoring.
contractor shall undertake a post-construction site meeting on completion of the construction works on Site. This meeting is to include tsupervising Arboriculturist or WCBC Tree Officer and the appointed c
ON ZONE AND PROTECTIVE BARRIERS
(CEZ) Definition
For the purpose of the CEMP the CEZs can be defined as all the soft surfaces within RPA) of retained trees outside of the works areas and the
areas behind the tree protection fencing. Site operations are not permitted in the CEZs without consultation with an Arboriculturist include storage of plant, equipment or materials, vehicular or plant access, washing down of vehicles or machinery, handling, discharge or spillage of any substances, including cement washings, actions likely to cause localised water-logging, no mechanical digging,scraping or excavation shall be permitted in the CEZ and no earthworks or changes in the finished ground levels other than those agreed by an Arboriculturist.
The protective barriers are to be installed prior to any works commencing. Tlocation and setting out details for the fencing shall be confirmed during a precommencement site meeting. The barriers are to be erected to exclude construction activity in the RPAs or remaining RPAs of retained trees. The protective barrier is to
prise 2m tall welded mesh panels on rubber or concrete feet. The panels are to be joined together using a minimum of two anti-tamper couplers, installed so they
Tree Protection
commencement site meeting prior ite. This meeting is to include the
ontractors undertaking the works. This meeting is to raise awareness with the relevant parties of the trees on
ite and to confirm individual responsibilities regarding trees. This meeting is also to or supervision from an Arboriculturist
construction site meeting on ite. This meeting is to include the
appointed contractors
all the soft surfaces within of retained trees outside of the works areas and the
not permitted in the torage of plant,
equipment or materials, vehicular or plant access, washing down of vehicles or machinery, handling, discharge or spillage of any substances, including cement
logging, no mechanical digging, scraping or excavation shall be permitted in the CEZ and no earthworks or changes in
The protective barriers are to be installed prior to any works commencing. The location and setting out details for the fencing shall be confirmed during a pre-commencement site meeting. The barriers are to be erected to exclude construction activity in the RPAs or remaining RPAs of retained trees. The protective barrier is to
prise 2m tall welded mesh panels on rubber or concrete feet. The panels are to tamper couplers, installed so they
can only be removed from inside the fence. The distance between the fence coupleris to be at least 1m and is to be uniform throughout the fence; the panels are to be supported by inner side stabiliser struts attached to a base plate secured on a block tray.
A.5 The protected areas shall be seen as sacrosanct and once installed shall not be moved or altered without recommendation by the project Arboriculturist
Specific Tree Mitigation Measures
A.6 The British Standard relies heavily on the creation of a protected zone referred to as the RPA around each tree. This is the minimum area around a tree deemed tocontain sufficient roots and rooting volume to maintain the tree’s viability, and where the protection of the roots and soil structure is treated as a priority. These areas have influenced the layout of the different proposals to ensure the retention of trees on Site.
A.7 Where specific mitigation measures are required to protect trees during construction operations, e.g. hand excavations or root pruning, then these are to be agreed in writing with the supervising Arboriculturist or suitably qualified delegate
TREE WORKS
A.8 All tree works are to be undertaken in line with current recommendations in accordance with BS3998:2010 Tree work current Arboriculture and Forestry Advisory Group (AFAG) or applicable Forestry Industry Safety Accord advice published by the Health and Safety Executive (HSE) or FISA.
A.9 Tree works are to be planned to ensure protection of people, property and wildlife. If the works are to be undertaken during the bird nesting season then sought from an ecologist prior to undertaking tree works.
A.10 The appointed tree works contractor is to be made aware of the site access limitations. The appointed method statement for review by the works on Site.
Tree Works and Mitigation Schedule
A.11 A finalised tree works schedule shall be produced on completion of the precommencement site meeting.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
can only be removed from inside the fence. The distance between the fence couplerleast 1m and is to be uniform throughout the fence; the panels are to be
supported by inner side stabiliser struts attached to a base plate secured on a block
The protected areas shall be seen as sacrosanct and once installed shall not be tered without recommendation by the project Arboriculturist.
The British Standard relies heavily on the creation of a protected zone referred to as the RPA around each tree. This is the minimum area around a tree deemed tocontain sufficient roots and rooting volume to maintain the tree’s viability, and where the protection of the roots and soil structure is treated as a priority. These areas have influenced the layout of the different proposals to ensure the retention of
Where specific mitigation measures are required to protect trees during construction operations, e.g. hand excavations or root pruning, then these are to be agreed in writing with the supervising Arboriculturist or suitably qualified delegate.
All tree works are to be undertaken in line with current recommendations in accordance with BS3998:2010 Tree work – Recommendations and comply with the current Arboriculture and Forestry Advisory Group (AFAG) or applicable Forestry
fety Accord advice published by the Health and Safety Executive (HSE) or
Tree works are to be planned to ensure protection of people, property and wildlife. If the works are to be undertaken during the bird nesting season then advice is to be
cologist prior to undertaking tree works.
tree works contractor is to be made aware of the site access appointed contractor will have to submit a risk assessment and
method statement for review by the contractor or supervisor prior to commencing
Tree Works and Mitigation Schedule
A finalised tree works schedule shall be produced on completion of the precommencement site meeting.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
33
can only be removed from inside the fence. The distance between the fence couplers least 1m and is to be uniform throughout the fence; the panels are to be
supported by inner side stabiliser struts attached to a base plate secured on a block
The protected areas shall be seen as sacrosanct and once installed shall not be .
The British Standard relies heavily on the creation of a protected zone referred to as the RPA around each tree. This is the minimum area around a tree deemed to contain sufficient roots and rooting volume to maintain the tree’s viability, and where the protection of the roots and soil structure is treated as a priority. These areas have influenced the layout of the different proposals to ensure the retention of
Where specific mitigation measures are required to protect trees during construction operations, e.g. hand excavations or root pruning, then these are to be agreed in
All tree works are to be undertaken in line with current recommendations in Recommendations and comply with the
current Arboriculture and Forestry Advisory Group (AFAG) or applicable Forestry fety Accord advice published by the Health and Safety Executive (HSE) or
Tree works are to be planned to ensure protection of people, property and wildlife. If advice is to be
tree works contractor is to be made aware of the site access contractor will have to submit a risk assessment and
upervisor prior to commencing
A finalised tree works schedule shall be produced on completion of the pre-
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
34
SEQUENCE OF EVENTS
A.12 The works should comply with the following sequence;
1. Pre-commencement site meeting including the contractor and the supervising Arboriculturist;
2. Implementation of protective barriers by agreement with the Arboriculturist;
3. Construction operations, including any site specific measures requiring specificsupervision by an Arboriculturist, e.g. works in RPAs of trees;
4. Removal of protective barriers;
5. Tree planting;
6. Post-completion site meeting with all relevant stakeholders
TREE PROTECTION FENCING
A.13 The fencing specification will accord with either o
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
The works should comply with the following sequence;
commencement site meeting including the contractor and the supervising
2. Implementation of protective barriers by agreement with the Arboriculturist;
3. Construction operations, including any site specific measures requiring specificsupervision by an Arboriculturist, e.g. works in RPAs of trees;
completion site meeting with all relevant stakeholders
The fencing specification will accord with either of the layouts shown below.
commencement site meeting including the contractor and the supervising
3. Construction operations, including any site specific measures requiring specific
f the layouts shown below.
TREE MONITORING PROFORMA
A.14 The following proforma, or similar, should be used for tree monitoring.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
The following proforma, or similar, should be used for tree monitoring.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
35
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
36
Job Number: Revision: Purpose: Originated: Notice: Purpose of Monitoring Visit: Date of Visit: Observations: Recommended Actions:
A.15 Relevant photographs should be numbered and described.
WREXHAM ENERGY CENTRE ENVIRONMENTAL STATEMENT
Document Ref: Date:
Checked: Authorised:
sit:
Relevant photographs should be numbered and described.