Upload
jun-crisostomo
View
219
Download
0
Embed Size (px)
Citation preview
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 1/53
BUILDING COMMISSIONING:
The Value of Commissioning
CaGBC Building Advisor ProgramOctober, 2012John Kokko, P.Eng., CCP, LEED AP
[email protected] x2424
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 2/53
LEARNING OBJECTIVES
What is buildingcommissioning
What are the steps required byLEED
Why is it important
What results can we expect
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 3/53
NEW BUILDING CX
LEED Credits
EAp1 – Fundamental Cx (Prerequisite)
Deals mainly with construction and getting the building operating beforehand-over
EAc3 - Enhanced Cx (Credit)
Deals with design and post occupancy operation
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 4/53
WHAT IS NEW BUILD COMMISSIONING
Definition:
To bring a new project or facility on line
?
?
?
Hands over abuilding that gives the
owner what he paid for.
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 5/53
NAME FROM SHIP BUILDING
A commissioned ship is one deemed ready for service.
Must pass several milestones.
Equipment is installed and tested, problems are identified andcorrected, and staff are extensively trained.
A commissioned ship is one whose materials, systems, and staff havesuccessfully completed a thorough quality assurance process.
Commissioned ship is one ready to sail safely and reliably
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 6/53
VISION OF COMMISSIONING
Take the owner’s needs and wants
► Ensure requirements properly articulated
Through the minds of the consultants
► Ensure designs properly reflect OPR
Through the hands of suppliers and contractors
► Ensure building is properly built
Deliver a properly performing building
► Ensure all systems operate as intended
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 7/53
BUILDING Cx = QC FOR CARS?
Similar to a QC
process for cars Note similarities in:
Work area
Tools Assembly
techniques
Workers’
responsibilities
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 8/53
WHY IS COMMISSIONING NEEDED
Don’t the design and construction teams alreadydo this?
Everyone wants to do a good job. But two constrains:
1. Scope included with fees
2. Knowledge of the state-of-the-art Low price generally gets the job
Designers responsible for code
Site review for conformance to
drawings and specs
Not performance beyond obvious
faults and complaints after the fact
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 9/53
UP-TO-DATE KNOWLEDGE
Innovation moving extremely fast
Innovative equipment andsystems are relatively unfamiliarto designers, contractors,operators and even
manufacturers agents Energy efficiency, integrated
systems, imported designconcepts and computerization
have multiplied levels ofcomplexity
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 10/53
WHAT IS INNOVATIONMULTIPLE MARRIED TECHNOLOGIES
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 11/53
ADDED COMPLICATIONS
Radiant heating Radiant cooling Condensing boiler Water-side economizer Building automation systems
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 12/53
INNOVATION INCREASING EXPONENTIALLY
Direct and indirect evaporative cooling
Optimum start
Cascading PID loops
Stratified thermal storage
Daylighting control
LON and BACnet
Integration
And on and on and on ….
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 13/53
CONVENTIONAL COMMISSIONING
• Start-up and basic check out of equipment
• Testing, Adjusting and Balancing (TAB)
• Begins after systems in and ready forstart-up
• Verify individual components function ascomponents
• Performed by installing contractor ormanufacturers rep
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 14/53
TOTAL COMMISSIONING (LEED™)
A systematic quality assurance program
Starts at concept design and concludes at end of
warranty
Includes all phases concept design, detailed design,
construction, start-up, 1 year operation
Commissioning verifies energy performance and
comfort maintenance
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 15/53
TOTAL COMMISSIONING (LEED™)
Includes reviews
through all stages Includes participation
of consultants, trades,
O&M staff Includes detailed reviews
design, shop draw, install
Expanded installation
verification and start-up checks
O&M documentation more centralized
Whole system performance vs. component checks
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 16/53
COMMISSIONING COMPARISON
TOTAL COMMISSIONING
Concept Design Reviews
Detailed Design Reviews
Shop Drawing ReviewsSite Installation Verification
Equipment Start-Up Verification
Balancing Verif ication
Functional Performance Test
Documentation and Operator
Training
Trending and Seasonal FPT
Warranty and Occupant
concerns
TRADITIONAL COMMISSIONING
No Cx. Consultant self-checks.
No Cx. Consultant self-checks.
No Cx. Dwgs & specs met only.No Cx. Dwgs & specs met only.
Contractor or Manufacturer only. No
systems interoperability
No Cx. Contractor self-checks.
No Cx. Contractor self-checks.
No Cx. Contractor self-checks.
Owner verifies acceptabil ity.
Contractor seldom returns
No Cx. Respond to complaints only.
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 17/53
VALUE OF Cx
Largest study to date Mills, LBNL July 2009
http://cx.lbl.gov/2009-assessment.html
643 buildings, 26 US states 561 existing and 82 new buildings
37 Cx firms
99 M ft2, $2.2 B construct
90.4 M ft2 existing, 8.8 M ft2 new construction
$43 M Cx costs
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 18/53
NEW BUILDING Cx MEDIANS
Cx cost, $1.16/ft2 or 0.4% of overall construct cost($290/ft2) (Range $0.60 - $2.15)
Number of deficiencies identified, 3,528
(about 1/3 of projects reported deficiencies) Energy savings 13% (Range 9% - 29%)
Payback time, 4.2 years (Range 1.7 to 11.4 yrs)
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 19/53
AREAS OF BENEFIT
Construction Cost Savings Equipment downsizing and trade-offs
Energy Savings - $0.05 to $0.45/ft2
Peak demand reductions Maintenance and replacement costs reduced
Increased productivity and reduced liability Indoor environmental quality maintenance
Carbon emissions reductions
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 20/53
COMMISSIONING PROCESS OVERVIEW
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 21/53
LEED Cx OUTLINE
Design and Construction Phases EAp1 – Fundamental Cx EAc3 – Enhanced Cx
Design Owner documents OPR Before 50% CD Owner designatesCxA
Construction Documents Designers incorporate Cx specs intoConstruction Docs
CxA presents Cx Plan
50% CD CxA conducts 50% design review
Post Contract Award Owner designates CxACxA presents Cx Plan
CxA reviews shop drawings
Installation CxA performs/oversees installationverification
Start-up CxA performs/oversees functionaltesting
CxA reviews O&M ManualsCxA oversees staff training
Substantial Completion CxA prepares Draft Final Report CxA prepares Systems Manual
Post Construction CxA performs/oversees deferedtesting
Occupancy CxA delivers Final Report CxA provides Warranty andoccupant concerns review
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 22/53
OWNER & DESIGN TEAM DOCUMENTATION
Owners Project Requirements (OPR)► Owner and User requirements
► Environmental sustainability goals
► Energy efficiency goals
► Indoor environmental quality requirements► Equipment and systems expectations
► Building occupant & O&M personnel requirements
Basis of Design (BoD)
► Primary design assumptions
► Standards
► Narrative descriptions
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 23/53
Cx DURING DESIGN
Work with design team to define measurable energy andindoor environmental quality goals
Discuss alternatives to traditional design solutions
Provide support for unfamiliar technologies Review to verify design meets objectives and technologies
properly implemented
Review to verify equipment specified meets goals andobjectives
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 24/53
COMMON DESIGN ISSUES
No design target for energy use
Lighting power density not identified No heat recovery
Condensing boilers not considered
Variable speed pumps and fansECM motors not incorporated
20°F rather than 40°F design
temp drop design used Undersized piping and
ductwork
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 25/53
Cx PLAN
Overview of Cx Process
List of equipment and systems to be Cx
Cx Team and responsibilities Management, Communication and Reporting Overview
Cx Process Overview (Outline above)
List of deliverables
Milestones
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 26/53
Cx MEMBERS & RESPONSIBILITIES
COMMISSIONING AGENT
Owner’s rep leading commissioning Reviews and produces most paperwork Directs testing Ensures LEED™ requirements are met
OWNER
Provide support as required to ensure Cxproceeds smoothly
FM Staff?Consultants
Provide documentation as required for review Attend commissioning meetings as required
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 27/53
GENERAL CONTRACTOR
►Ensures contractors meet commissioningrequirements
M&E CONTRACTORS
►Completes start-up, installation verification lists►Operates equipment for Performance Testing►Produces O&M manuals, Provides owner training
CONTROLS CONTRACTOR►Operate controls for Performance Testing, produce
O&M materials for controls
Cx MEMBERS & RESPONSIBILITIES
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 28/53
Cx SPECIFICATIONS
Contractor responsibilities Submittal review process
Meetings
IVC process
Start-up process
Balancing reviews
FPT process
O&M manuals requirements
Training requirements
Warranty review
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 29/53
Cx DURING CONSTRUCTION
Verify equipment installed per drawings andspecs, manuf’rs requirements and proper
industry practice and standards
Verify equipment is, set-up, adjusted,balanced, controlled and operated to provide
expected comfort and energy performance
Provide owner complete systems O&M docs
Provide owner’s operating personneladequate training to understand, operate and
maintain equipment
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 30/53
COMMON INSTALLATION ISSUES
Coils piped backward
Maintenance access notprovided
Pumps with shaft oriented
improperly Thermostats located adjacent
to heating/cooling diffusers
Insulation missing Sensors improperly located
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 31/53
COMMON FUNCTIONAL TESTING ISSUES
Controls functions notmatching sequence
VFDs do not modulate
Outdoor damper minimumposition
Control valve action reversed
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 32/53
TRAINING TOPICS
General purpose of system Use of O&M manuals
Operation of systems under all conditions
Interaction with other systems
Adjustments and optimization for efficiency
Health and safety
Special maintenance and replacement resources
Occupant interaction
Controls training
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 33/53
SYSTEMS MANUAL
Final BoD System single line diagrams
As-Built sequences, set-points, etc.
System operating instructions Maintenance schedule
Retesting schedule
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 34/53
Cx AFTER OCCUPANCY
Follow trends on BAS to ensure ongoing operation
Completion of deficiencies remaining afterconstruction
Follow-up on warranty issues arising
Follow up on occupant concerns during warrantyand first year occupancy
Verify that issues are cleaned up by the end ofwarranty
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 35/53
FINAL REPORT
OPR
Design and shops review summary
Cx specifications IVC results
FPT results
O&M evaluation
Value achieved through Cx
Outstanding issues
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 36/53
MULTI-FUNTION AHU
DESIGN ISSUES Dehumidifying only
outdoor air reduces size ofequipment and increases
efficiency of equipment Using heat recovery to
reduce load on cooling coil Using indirect evaporative
cooler to increase HX eff’yhumidity carried outdoors
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 37/53
MULTI-FUNCTION AHU
INSTALLATION ISSUES
No radiation shield on sensor by flame
No maintenance access to somesensors
Installation of single point sensorwhere averaging required
Reset button set tight and vibrationcausing unit to cut out
Overloads not set properly
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 38/53
BOILERS
DESIGN ISSUES
No check valves wouldrequired both boilers operate in
parallel Independent controllers would
not have been coordinated Primary only loop with DHW
would have requiredcontinuous minimum 160F
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 39/53
BOILER
INSTALLATION ISSUES
Water treatment eliminated byaluminum boiler manufacturer. But
piping not protected OA reset not programmed
because tech believed it would notsave energy
Control sensor located in singleboiler supply rather than commonheader
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 40/53
RETIREMENT RESIDENCE
HVAC SYSTEM
Ground loop coupled distributed heat pumps withsupplemental gas-fired heating.
One AHU with heat recovery and HP htg/clg for fresh airdistribution to corridors and common areas
One AHU with WLHP htg/clg for Kitchen Individual HRVs for ventilation and WLHPs for htg/clg in
each room
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 41/53
RETIREMENT HOME
DESIGN ISSUES
Heat injection before rather
than after ground loop
Moved to eliminate boiler
heating ground
HX between building loop and
ground loop removed
Reduced capital cost and
increased efficiency
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 42/53
RETIREMENT HOME Cont’d
Dedicated DHW heaterssimplified boiler loop controls,allowed summer shutdownand allowed primary loop OA
reset and condensing Cascading different
temperature loops ensuredcold return water temps
40°F temp rise drop reducedpipe and pump sizing
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 43/53
SHOP DRAWING REVIEW FINDINGS
1. 3 re-submittals of heat wheel shop drawings requiredbefore a workable defrost strategy provided.
2. Shop drawing coil performance based on water whilesystem will used propylene glycol.
3. Coils have greater air-side and water-side pressuredrops than specified.
4. Controls sequences were carbon copy of engineer’s
general wording rather than converting to specifics thatcan be programmed.
Heat wheel, heating coil and cooling coils shall be
sequenced to provide energy efficient operation
AIR HANDLER
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 44/53
SERVICES and REPAIR BUILDING
HVAC SYSTEM
Ground Source Heat Pump
Radiant floor heating Dedicated outdoor air ventilation with heat recovery
Supplemental fan coils for cooling
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 45/53
SERVICE and REPAIR BUILDING
HVAC System
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 46/53
SMALL SERVICES BUILDING
Functional Testing
System relied on heat pump circulator but never
programmed to operate when heat pump off PID loops needed tuning to provide stable operation
Radiant floor valve found with wire not connected leavingvalve open and space overheating
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 47/53
SERVICE AND REPAIR BUILDING CASE STUDY
FUNCTIONAL TEST
Storage room hot, office cool. Found crossed floor loops. Officet’stat controlling floor heat in storage room. Loops not labelled
Heat pump constantly tripping. Supplier blamed system but did notmeasure any parameters. Cx measurements showed water flows
ok. Heat pump diagnostics finally found faulty TX valve and lowrefrigerant.
Controls are probably the single most important item in ensuringsuccessful system operation for comfort and energy savings.
CC programmed system heating water temps lower thanspecified because this works better
Improperly programmed 24 hr moving average outdoor tempcaused the system to flip-flop between heating and cooling
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 48/53
REAL PERFORMANCE
What is the energy use of typical buildings?
0
100
200
300
400
500
600
700
800
All Bldgs
(ON)
C&I Accom
(ON)
Offices
(ON)
Offices
(CAN)
GoG
Annual
Energy
ekWh/m2
All
data
(except
GoG)
from
NRCan
Survey
(CIBEUS,
2000).
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 49/53
RETIREMENT RESIDENCE A
Actual Performance
0
50
100
150
200
250
300
Dec '04 (SL) Nov '05 (SL) Nov '05 (CBIP) Jul '06 (Review) Apr '07 to Mar '08
Simulated
Actual
Annual
Energy
ekWh/m2
Floor Area = 5348 m2
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 50/53
0
50
100
150
200
250
Aug
'04
(SL) Feb
'06
(CBIP) Aug
'06
(Review) Aug
'07
to
Feb
'08
Simulated
Actual
RETIREMENT RESIDENCE B Actual Performance
Floor Area = 11702 m2
Annual
Energy
ekWh/m2
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 51/53
LABORATORY BUILDING
Actual Performance
Annual
Energy
ekWh/m2
0
100
200
300
400
500
Aug
'04
(SL) Aug
'06
(CBIP) Feb
'07
(Review) Dec
'07
to
Feb
'08 Mar
to
May
'08
Simulated
Actual
Floor Area = 9350 m2
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 52/53
COMPARISON
Annual
Energy
ekWh/m2
Actual energy use compared to typical buildings
0
100
200
300
400
500
600
700
800
All
Bldgs
(ON)
C&I
Accom
(ON)
Offices
(ON)
Offices
(CAN)
GoG VA SSJ KPHQ TRCABuilding
A
Building
B
Building
C
Building
D
7/25/2019 The Value of Building Commisioning
http://slidepdf.com/reader/full/the-value-of-building-commisioning 53/53
MMM Group Limited
100 Commerce Valley Drive West
Thornhill, ON Canada L3T 0A1
t: 905.882.1100 | f: 905.882.0055