Upload
hoanglien
View
216
Download
0
Embed Size (px)
Citation preview
Gabriel Penalba
2274 Mountain Dr.
Abbotsford, BC V3G1E5
May 6th, 2016
Chris B. McKesson, Ph.D., P.E., P.Eng.
Instructure of Naval Architecture and Marine Engineering
Department of Mechanical Engineering
The University of British Columbia | Point Grey Campus
2050 – 6250 Applied Science Lane, Vancouver, BC V6T 1Z4
Dear Dr. McKesson,
On behalf of Team Ferry, it is my distinct pleasure to present you with this capstone project report in
accordance with the requirements of the Naval Architecture and Marine Engineering program at UBC.
If you should require clarification or have any questions about our methodologies or results, please do
not hesitate to contact us.
Thank you for the magnificent opportunity to participate in this process of designing ships together.
Yours sincerely,
Gabriel Penalba, P.Eng.
SAVU SEA FERRY The design of a ROPAX ferry for Indonesia
Shaun Ren, Gabriel Penalba, Timothy Lee
Abstract Among the South-east Asian countries, Indonesia is known for its unsafe ferry practices. This
project seeks to find a safe, affordable, and yet innovative design for the Savu Sea in the province of East Nusa Tenggara. A steel catamaran with a length of 55 meters, a beam of 23.5 meters, and a draft of 2.8 meters at a full load displacement of 1010 tonnes is proposed. Although still in the
concept design phase, the solution proposed in this report manages to open up a new design space – a robust, safe, and economical ‘workhorse of the sea’ for the people of Indonesia.
Contents
1. LIST OF FIGURES 6
2. LIST OF TABLES 8
3. SUMMARY 10
3.1. Ship Placemat 10
4. INTRODUCTION 11
4.1. Why does this report exist? 11
4.2. Intended Audience 11
4.3. Who produced this report? 11
4.4. Overview of the ship design project 11
5. MISSION 11
5.1. Project Scope 11
5.1.1. Need 12
5.1.2. Goals 13
5.1.3. Objectives 13
5.1.4. Assumptions 13
5.1.5. Constraints 13
5.1.6. Budgets & Schedules 15
5.2. Mission Description 15
5.3. Concept of Operations 16
5.4. Owner’s Requirements 17
5.5. Critical Performance Parameters 18
6. HULL FORM & HYDRO 19
6.1. Summary of Hull Form Driving Considerations / Hull Form Development Rationale 19
6.2. Hull Geometry 23
6.2.1. Body Plan 26
6.2.2. Lines plan 28
6.2.3. Principal Dimensions and Coefficients Table 28
6.2.4. Future Hull Developments 28
6.3. Hydrostatics and Stability 29
6.3.1. Stability Criteria Used 29
6.3.2. Stability Results summary table 31
6.3.3. Limiting KG diagrams 32
6.3.4. Damaged stability Requirements 33
6.3.5. Damaged stability results 34
6.4. Hydrodynamics 35
6.4.1. Resistance and Powering 35
6.4.2. Ship Motions and Seakeeping 38
6.4.3. Ship Maneuverability 39
7. SHIP ARRANGEMENT 39
7.1. Arrangement Rationale 39
7.2. Arrangement Descriptions 42
7.2.1. Arrangement block drawings 42
7.2.2. Area/Volume Report 45
7.2.3. Future Improvements 48
8. SHIP STRUCTURE 49
8.1. Rule set and Methodology 49
8.1.1. Local Pressures 49
8.1.2. Vessel Loading 50
8.1.3. Global Loading 50
8.1.4. Material Selection 52
8.1.5. Plating Thickness 52
8.1.6. Stiffener Properties 53
8.1.7. Hull Girder Strength 54
8.2. Midship section drawing 58
8.2.1. Design Reservations and Recommendations 59
9. SHIP PROPULSION 59
9.1. Machinery plant description 59
9.1.1. Main Engine 59
9.1.2. Gearing and shafting 61
9.1.3. Rationale for Selection 61
9.1.4. Summary of Propulsor Comparison 64
9.2. Machinery Arrangement 70
9.2.1. Block diagram 70
9.2.2. Arrangement Rationale 70
9.3. Endurance fuel calculation 71
10. SHIP ELECTRICAL SYSTEM 71
10.1. Electric plant description 71
10.2. Generator Sizing and Selection Rationale 71
10.3. Electric plant block diagram 71
11. SHIP AUXILIARY AND CONTROL SYSTEMS 72
11.1. Description of systems 72
11.2. Simplified block or one-line diagrams 72
11.2.1. Control System 72
11.2.2. Bilge/fire System 73
11.2.3. Fuel Systems 73
11.2.4. Cooling System 75
11.2.5. Water systems 75
12. WEIGHT ENGINEERING 77
12.1. Margin Policy 77
12.1.1. Margins 77
12.1.2. Allowances 77
12.2. Master Equipment List 78
12.3. Weight & KG Estimate 79
13. COST ESTIMATE 81
13.1. Estimate of Acquisition Cost 81
13.1.1. PODAC Cost Estimate Methodology & Assumptions 81
13.1.2. Parametric Cost Estimate Methodology and Assumptions 83
13.2. Estimate of Operating Cost 86
13.3. ESTIMATE OF rEVENUE 88
14. Technical Risk Assessment 92
15. ISSUES REMAINING FOR NEXT PHASE 93
16. CONCLUSIONS 94
17. REFERENCES 94
18. APPENDICES 97
18.1. Appendix: Project Planning Documents for this Project 97
18.2. Appendix: Renderings 103
18.3. Appendix: General Arrangement Drawings 104
18.4. Appendix: Lines Plan 111
18.5. Appendix: Intact Stability Calculations 112
18.6. Appendix: Damaged Stability Calculations 117
18.6.1. A and B flooded: 118
18.6.2. B and C flooded: 119
18.6.3. C and D flooded: 120
18.6.4. D and E flooded: 122
18.6.5. E and F flooded: 123
18.6.6. F and G flooded: 124
18.7. Appendix: Resistance Calculations 126
18.7.1. NPL Resistance calcs 126
18.7.2. VWS Resistance calculations 128
18.7.3. Pram and Sahoo Resistance Calculations 129
18.8. Appendix: Structural Calculations 131
18.9. Appendix: Weight Estimate 143
18.9.1. Structural Weight 151
1. LIST OF FIGURES Figure 1 - Project Summary Placemat ......................................................................................................... 10
Figure 2 – Existing Passenger only Ferry Routes ......................................................................................... 12
Figure 3: Ramp Measurements ................................................................................................................... 15
Figure 4: Proposed Route ........................................................................................................................... 16
Figure 5: Overcrowding in Indonesian Ferries is typical ............................................................................. 19
Figure 6: Wave Piercing Catamaran Hull .................................................................................................... 20
Figure 7: Cars vs Vessel Length ................................................................................................................... 21
Figure 8: Medium speed CAT power ........................................................................................................... 22
Figure 9: Parent Ship - North Island Princess .............................................................................................. 23
Figure 10: Body Plans of NPL Models ......................................................................................................... 24
Figure 11: Residuary Resistance of NPL Models ......................................................................................... 24
Figure 12: Fat vs Slender Catamarans at Fn = 0.35 ..................................................................................... 25
Figure 13: Summary of Catamaran Target Particulars ................................................................................ 26
Figure 14: NPL Model 3b body plan ............................................................................................................ 27
Figure 15: VWS89 Body Plan ....................................................................................................................... 27
Figure 16: Savu Sea Ferry Demihull Body Plan ........................................................................................... 27
Figure 17: Savu Sea Ferry body plan with Cross Structure ......................................................................... 28
Figure 18: Severe Wind and rolling Criterion .............................................................................................. 30
Figure 19: Ship Fully Loaded Condition ....................................................................................................... 31
Figure 20: Orca Stability Results for Fully Loaded Departure. .................................................................... 32
Figure 21: Hull Subdivision .......................................................................................................................... 33
Figure 22: Example - Removing Buoyancy of Damaged Zones ................................................................... 34
Figure 23: Body Plans used by Pham and Sahoo ........................................................................................ 36
Figure 24: Resistance Predictions (design speed in Red) ............................................................................ 37
Figure 25: Kennell's data on the effect of slenderness ............................................................................... 38
Figure 26: Transport Factor for Similar ROPAX Catamarans ....................................................................... 38
Figure 27: Securing Points [23] ................................................................................................................... 41
Figure 28: Midship Arrangement ................................................................................................................ 42
Figure 29: Deck 5 - Pilot House and Officer Cabins ..................................................................................... 43
Figure 30: Deck 3 and 4 - PAX Accommodations and Seating .................................................................... 43
Figure 31: Deck 2 - Vehicle Deck ................................................................................................................. 44
Figure 32: MLC Space Requirements .......................................................................................................... 46
Figure 33: Vertical Wave Bending Moment ................................................................................................ 50
Figure 34: Twin-hull Bending Moment ....................................................................................................... 51
Figure 35: Twin-hull Torsional Moment ...................................................................................................... 51
Figure 36: Longitudinal Vertical Wave Bending Moment ........................................................................... 51
Figure 37: Simplified Hull form for Shear Stress Calculations ..................................................................... 55
Figure 38: Max Permissible Hull Shear Stress ............................................................................................. 55
Figure 39: Actual Hull Shear Stress ............................................................................................................. 56
Figure 40: Midship Section.......................................................................................................................... 58
Figure 41: NAV 550 Propulsion Unit ........................................................................................................... 60
Figure 42: Main Engine ............................................................................................................................... 61
Figure 43: Machinery Arrangement ............................................................................................................ 70
Figure 44: AC Power Estimate ..................................................................................................................... 71
Figure 45: Simplified Electric Diagram ........................................................................................................ 72
Figure 46: Control System ........................................................................................................................... 73
Figure 47: Bilge and Fi-Fi system ................................................................................................................. 73
Figure 48: Fuel Transfer System .................................................................................................................. 74
Figure 49: Fuel Supply system ..................................................................................................................... 74
Figure 50: Lube Oil System .......................................................................................................................... 75
Figure 51: Cooling System ........................................................................................................................... 75
Figure 52: Potable Water System ............................................................................................................... 76
Figure 53: Oily Water System...................................................................................................................... 76
Figure 54: Black Water System ................................................................................................................... 77
Figure 55: Ship Coordinate System ............................................................................................................. 79
Figure 56: Fully Loaded Weight .................................................................................................................. 79
Figure 57: Operating Trim, Fully Loaded ..................................................................................................... 80
Figure 58: Unloaded Weight ....................................................................................................................... 80
Figure 59: Operating Trim in the Unloaded Condition ............................................................................... 81
Figure 60: Capacity Value vs Salvage Price ................................................................................................. 84
Figure 61: Area Value for various Ferries .................................................................................................... 84
Figure 62: Ship Depreciation ....................................................................................................................... 85
Figure 63: Capacity Value ............................................................................................................................ 85
Figure 64: Annual Expense Pie Chart .......................................................................................................... 87
2. LIST OF TABLES Table 1: Weather Conditions ...................................................................................................................... 14
Table 2: Sea State Probabilities ................................................................................................................... 14
Table 3: Ferry Ramp Dimensional Findings ................................................................................................. 15
Table 4 - Loop around the Savu Sea ............................................................................................................ 16
Table 5: Owner's Requirements .................................................................................................................. 18
Table 6: Critical Performance Parameters .................................................................................................. 18
Table 7: Parametric Study of ROPAX Catamarans ...................................................................................... 21
Table 8: Preliminary Weight Estimate ........................................................................................................ 22
Table 9: Principle Particulars ....................................................................................................................... 28
Table 10: Tank Free Surface Effects ............................................................................................................ 31
Table 11: NPL Model Data compared to Ship Data .................................................................................... 36
Table 12: Local Design Pressures ................................................................................................................ 49
Table 13: Local Loads acting on Vessel ....................................................................................................... 50
Table 14: Hull Bending Moment, Torsional Moment, and Vertical Shear Force ........................................ 51
Table 15: Load Combinations for Cross Deck strength check ..................................................................... 52
Table 16: Minimum Plating Thickness Requirements ................................................................................. 53
Table 17: Sample Calculations of Stiffener Properties................................................................................ 54
Table 18: Maximum Permissible Hull Bending Stress ................................................................................. 55
Table 19: Hull Girder Strength at the Strength Deck .................................................................................. 55
Table 20: Max allowable Stress for the Cross-Deck Structure .................................................................... 56
Table 21: Cross-Deck Strength Criteria for Bending and Shear Stress ........................................................ 56
Table 22: Cross-deck Bending Strength Check ............................................................................................ 56
Table 23: Cross-Deck Shear Strength Check ............................................................................................... 57
Table 24: Propulsion Comparison Criteria .................................................................................................. 63
Table 25: Decision Indexes [26] .................................................................................................................. 63
Table 26: Criteria Weight ............................................................................................................................ 64
Table 27: Summary of Propulsor Comparisons........................................................................................... 65
Table 28: Propulsion Selection Overview ................................................................................................... 66
Table 29: Combined Weight Tables ............................................................................................................ 66
Table 30: ROI Comparisons ......................................................................................................................... 68
Table 31: Weight Allowances ...................................................................................................................... 78
Table 32: Master Equipment List ................................................................................................................ 78
Table 33: Cost Estimate Comparison .......................................................................................................... 81
Table 34: Cost Estimating Relationship Breakdown ................................................................................... 81
Table 35: PODAC Results ............................................................................................................................. 82
Table 36: Cost Estimation Rates.................................................................................................................. 82
Table 37: PODAC Based Cost Breakdown ................................................................................................... 82
Table 38: PODAC Cost Estimate Results...................................................................................................... 83
Table 39: Ticket Prices in the Operating Region ......................................................................................... 83
Table 40: Operating Cost Breakdown ......................................................................................................... 87
Table 41: Trips and Ticket Prices ................................................................................................................. 88
Table 42: Gross Revenue per Stop at 100% Capacity ................................................................................. 88
Table 43: Total Revenue per Year ............................................................................................................... 88
Table 44: Investment Metrics ..................................................................................................................... 89
Table 45: Revenue at Reduced Capacity ..................................................................................................... 90
3. SUMMARY
3.1. SHIP PLACEMAT
Figure 1 - Project Summary Placemat
4. INTRODUCTION
4.1. WHY DOES THIS REPORT EXIST? This report is the combined effort of a group of Naval Architecture and Marine engineering students at
UBC. The research, calculations, and drawings in this report was a powerful opportunity to allow their
knowledge of Naval Architecture and marine engineering to grow as well as fulfill graduation
requirements for the MEng NAME program at UBC.
4.2. INTENDED AUDIENCE Although this report is written to complete a class requirement, it’s also written with fellow students in
mind. Navigating through a large project can be difficult, and sometimes the only solid footing in the
vast sea of information on a topic is a method or reference used in another project. The team hopes that
some of the descriptions or techniques in this report is useful for future Naval Architecture students to
build upon.
4.3. WHO PRODUCED THIS REPORT? The project team includes Shaun Ren, Gabriel Penalba, and Timothy Lee. The team would like to thank
their professor, Dr. Chris McKesson as well as their Industry sponsor, Robert Allan, for their direction,
ideas, and encouragement.
4.4. OVERVIEW OF THE SHIP DESIGN PROJECT The idea for this project was initially conceived from the World Ferry Safety Association’s annual safe
and affordable ferry competition. The major focus of the design was to build a viable ferry concept for
Indonesia. This meant solving the challenges of safety and affordability through stability, capacity, and
ingenuity while meeting and exceeding regulatory requirements. Because of the wide scope and
complexity of the project, the design process took on the form of a spiral. The overall purpose of this
report is to present the design results and also present some of the data that supports the design
decisions. The design is a steel catamaran ferry with an overall length of 55 meters and a full load
displacement of 1010 tonnes.
5. MISSION
5.1. PROJECT SCOPE The aim of this project is to develop a concept level design for a safe and affordable roll-on roll-off
passenger ferry (ROPAX ferry) for the Worldwide Safe Ferry Association’s (WSFA) third annual design
competition. The scope of the competition and of this report is to develop a design at the concept level,
with work done on all the following areas:
ship particulars
general arrangements
outboard profile
mid-ship section
light ship weight
intact and damaged stability estimates
speed-power estimates
machinery arrangement plans
life-saving plans
cost estimate
We don’t expect to be able to cover everything in detail or have all the right answers. What we do
expect is to have gone around the design spiral a couple of times and fill in enough to gain a much
better sense of our design’s feasibility.
5.1.1. NEED Indonesia is currently the fourth most populous country after the United States of America and consists
of over 6,000 inhabited islands [1]. Despite being a country heavily influenced by the sea, the WFSA
reports that in the 14 years since 2000, 17% of the 21,574 lives lost due to ferry accidents in the world
are from Indonesia [2]. This competition is a response by the WFSA to encourage the development of
safe ferries that are affordable for the regions that are still overwhelmed with ferry tragedies.
East Nusa Tenggara (NTT, Nusa Tenggara Timur), a province of Indonesia, is particularly in need for safe
and affordable transportation. NTT is the poorest province in Indonesia with 15% inflation rates, 23%
interest rates and a stunning 30% unemployment rate [3]. A report on the problems and cost by the Asia
Foundation in this particular region indicates that a 10% reduction in transportation cost will reduce the
inflation rate by at least 1% [4]. Furthermore, ferry ticket accounts for about 77% of the inter-island
transportation costs and “entire journey time” (which increases truck crew costs). Consequently, an
improvement to the region’s ferry transportation is key to the region’s growth.
Figure 2 – Existing Passenger only Ferry Routes
5.1.2. GOALS The goal of this design project as students is to bring together what we have learn in the classroom with
the needs identified in NTT to advance the safety and affordability of ferry transportation. By
participating in this design project, we hope to learn about and share a few of the significant challenges
that ultimately affect ferry transport in NTT.
5.1.3. OBJECTIVES This project’s objective is to design a ferry concept tailored for NTT region’s needs. In particular for this
region, a ferry that addresses the common safety concerns present in this region such as fire safety,
storm-proofing and maneuverability while keeping the vessel affordable to potential owners.
5.1.4. ASSUMPTIONS Existing conditions are used as the baseline for current operating design parameters. These parameters
include fuel costs, transportation demands, social behaviors (such as overcrowding), and labor wages.
Furthermore, since the design requirements from WFSA have not specified a maximum cost nor a
maximum capacity for vehicles, the following assumptions were made prior to starting the project:
Maximize the vehicle capacity to increase revenue. The more vehicles the ferry can carry, the
better.
The acquisition cost should be kept as low as possible.
The ship is affordable if it can have a payback period that is equal to or less than 75% of its
expected life.
The ship’s operational life span is estimated to be 40 years based on various accounts describing
ferries in this region have an average age of 15-25 years [5].
5.1.5. CONSTRAINTS The environment of the region of operation constrains the design of the ship as much as the key
performance parameters. In fact, adverse weather contributes up to 53% of world ferry accidents
according to WFSA [6]. Some constraints were outlined in the owner’s requirements like depth
(maximum draft) and port constraints. Other constraints, like ramp constraints, were carefully
investigated to guarantee that the designed ROPAX ferry could berth at the designated ports to
successfully fulfill its mission of loading and unloading vehicles.
The tables below summarize the local weather conditions the ferry must withstand.
LOCATION FACTOR MIN HIGH UNIT CITATION
On route
Depth No restrictions m P3
Wind Speed 0 30 knots P3
Wind Direction N or SE
Sea Swelling 2 4 m P3
Wave Height 0 6 m
Dock
Depth (of ship) 6 m P3
Sea Swelling 4 5 m P3
Table 1: Weather Conditions
The designed ferry will have to satisfy these environmental conditions, as further detailed in the report
sections on hull form and structures. To verify that the owner’s specified maximum wind speed is
actually 30 knots the probability of the occurrence of 30 knot wind was computed (Note: 30 knots
sustained wind corresponds to Sea State 6 in NATO STANAG 4154 table for the North Atlantic
Ocean).The probability distribution of wind magnitudes is modeled as a Rayleigh Distribution just as
wave heights are modeled.
Equation 1: Exceedance Probability for Rayleigh Distribution [7]
“Q(r)” is the exceedance probability, “sigma” is the mode and “r” is the threshold of interest. From the
exceedance probability equation for a Rayleigh distribution, the probability of the wind exceeding 30
knots is 1.5*10^(-8). The low probability of exceeding 30 knots indicates that the statement made by the
owner is realistic. The most frequently seen (mode) wind speeds were obtained from inspecting the
maximum wind speed in the 2001 pilot charts for each month in the operating area. The table below
sums up the step by step results of the calculations.
WIND SPEED PROBABILITY SUSTAINED WIND SPEED
(KNOTS)
SIGNIFICANT WAVE HEIGHT
MODE (MOST SEEN BY
MARINERS – FROM THE PILOT
CHARTS)
10
SEA STATE 2
0.1-0.5 m
RMS (mode = 0.707*RMS)
14.14
SIGNIFICANT ~= MODE*2 20
SEA STATE 4
1.25-2.5 m
STANDARD DEVIATION
(SIGMA_N = 0.25 SIGNIFICANT) 5
EXCEEDANCE PROBABILITY
Q(R.) = 1.5*10^(-8)
30
SEA STATE 6
4 - 6 m
Table 2: Sea State Probabilities
Inquiry into the ferry piers show that they were designed for mono-hull ROPAX ferries that carry their
own stern and bow ramps; these ramps are located at the center-line of the ship. Since the hull form
chosen for this project is a catamaran, it was vital to determine how the ramps will be placed to ensure
compatibility with the existing piers.
Movable ramps in the region were measured to be generally over 5 m wide. Nevertheless, it is
recommended that the ramp be no more than 5 m to increase for tolerances as well as compatibility
with a wider range of ports. A Ferry Rehabilitation Project report [8] records that some of the purchased
movable “bridges” installed in Indonesia are of dimension as small as 19 x 5m.
Figure 3: Ramp Measurements
Most ferry piers have passenger walkways located on the starboard side of the ship from the
perspective of a ship unloading from the bow. The center of the ramp to the concrete dolphins or pier
side for passengers is about 3.9 m for the smallest pier in the designed route (Port of Savu/Sabu, the
smallest pier, uses a simple concrete ramp). If our ferry is to carry a bow or stern ramps, the center the
ramps is constraint to no more than 3.9m from the side of the ship.
SUMMARY OF FINDINGS ON FERRY PIER MOVABLE RAMPS
Physical Dimensions Dimension Range
Ramp Width 5.0 m 5.78 to 10m
Center of ramp to concrete dolphin 3.9 m 3.9 to 6.55m
Road width 4.5 m 4m to 6 m
Table 3: Ferry Ramp Dimensional Findings
5.1.6. BUDGETS & SCHEDULES
5.2. MISSION DESCRIPTION Within East Nusa Tenggara (NTT), the ferry is to operate in the region of the Savu Sea. This sea is
surrounded by five major islands. The ferry is to operate in a scheduled loop with five stops; stops are
located at major city ports of each island. The ROPAX Ferry will transport around 185 passengers, as well
as cars, and trucks that carry cargo. The proposed loop for the ferry is between the cities of Waingapu,
Ende, Tenau, Rote, and Savu, as shown in Table 1 and Figure 2 below.
Figure 4: Proposed Route
Mission Loop [Nm] Time in hours @15kn
Ende to Waingapu 99 6.6 Hr.
Waingapu to Sabu 110 7.3 Hr.
Sabu to Rote 88 5.9 Hr.
Rote to Tenau 32 2.1 Hr.
Tenau to Ende 139 9.3 Hr.
Total: 468 31.2 Hr.
[Nm] [hours, travelling] Table 4 - Loop around the Savu Sea
5.3. CONCEPT OF OPERATIONS A concept of operations informally describes how a system will be used in order to build consensus
among the stakeholders [9]. The following CONOPS describes, with broad strokes, the operational life of
the ferry.
Regular operating schedules will be created for the new ferry to operate among the five cities, Ende,
Waingapu, Savu, Rote, and Tenau. At 15 knots, the ferry will take about six days to one week to make a
complete loop based on average weather conditions. The crew will both live and work on the ferry.
Living accommodations including cabins, a mess room, a laundry room, and a galley will be provided.
Crew work spaces include the bridge and store areas as well as the various machinery spaces.
Passengers will begin boarding in the morning before it sets off. Cars, trucks, and passengers board from
the stern ramps. As passengers board, the crew will collect tickets.
Passengers climb the stairs from the deck to the 2nd deck, where the seating area is located. There is
premium and economy seating. Premium seats have the advantage of getting on and off the ferry first
as well as extra seating space. Accommodations are also available for passengers travelling on-board for
multiple nights on the Savu Sea loop or those who wish for a more comfortable and private ride. All
interior spaces will be ventilated and air conditioned, as the weather can get uncomfortably hot in
Indonesia. A kiosk to buy drinks, snacks or even basic groceries will be available behind the passenger
area. Stairs to the top deck allow passengers to enjoy the fresh air and scenery.
When the ferry is ready to leave port, the stern ramp is raised and then ferry will move out of the port.
The ferry will make a quick U-turn using the azimuth thrusters and head towards the destination port
city, gradually picking up speed to about 15 knots. The captain and the helmsman make use of the
navigation systems and will be on the lookout for obstacles. The longest trip will be a little over 9 hours
long; hence, the ship will arrive in the late afternoon. Tools such as GPS/chart plotters, advanced radar,
thermal imaging cameras, and night-vision scopes will be required if night-time navigation is desired.
Upon reaching the pier, the bow ramp will be lowered to disembark first class passengers and then the
general passengers and vehicles.
After the bustle of unloading, the crew cleans the vacant accommodations in preparation for the next
occupants of the following day. The janitor will obtain equipment from the janitor room to clean the
deck; the sewage tanks will be emptied and consumables such as store goods, food, fresh water, fuel,
and lube oil will be replenished.
Preparing for the next day’s loading from the stern ramp, the ferry will briefly pull out of its berth, turn
around and pull in from the stern ship.
When the ship’s engines are due for scheduled maintenance, a spare propulsion unit or engine unit will
be available at one of the piers for a quick swap out promptly ready for the next departure. The engine
swap will reduce significant amount of downtime by transferring on-board maintenance to the more
convenient on-shore maintenance.
In the case of a fire which is commonly caused by causes by the engine or trucks; automatic fire
sprinklers will be activated. Two separate fire-hoses also be accessible on the car deck. The well
ventilated deck feature of the ship also allows fire-fighting vessels to better put out fires as opposed to
the typical enclosed car decks. Well ventilated car deck are also known to have 90% less fire occurrences
[6].
5.4. OWNER’S REQUIREMENTS The owner’s requirements are defined in the Terms of Reference document of the “Student Design
Competition for Safe Affordable Ferries 2015” by the Worldwide Ferry Safety Association. The owner
specified that “the ferry must be affordable to construct, acquire, operate, maintain and repair” while
operating safety in its designed operations as description in section 9.2.
A summary of the requirements for passenger and crew comfort as specified in the MLC 2006,
International Conventions and the project’s Terms of Reference [10] is shown below in table.
Requirement Minimum Interpretation
Affordability Undefined by owner As good as or better than
investing in a conventional design
Passengers 70
Vehicles Undefined by owner Maximize
Passenger Cabins 20
Crew Cabins 7
Galley 1
Mess room 1
A/C environment Accommodation area
Design Speed 14 knots
Cruising Range 1000 Nm
Table 5: Owner's Requirements
The requirements for the number of vehicles is interpreted as an optimizing value since the other
revenue flow of passengers is limited to 185 passengers. Similarly, affordability of the ship is viewed
from an investment point of view of the owner. The owner’s next best alternative for their investment is
likely a conventional design or another student competition design.
5.5. CRITICAL PERFORMANCE PARAMETERS The key performance parameters, measurable system capabilities that must be met for operational
goals, are summarized in the table below.
Key Performance
Parameter
Minimum
Threshold
Maximum
Threshold
Designed Performance
Passenger Capacity 70 185 185
Vehicles unspecified to maximize 34 sedans, 10 trucks
Passenger Cabins 20 unspecified 20
Design Speed 14 18 15
Endurance 1000 Nm unspecified 1000 Nm
Sea Sate 6 unspecified 6 *
Table 6: Critical Performance Parameters
Additional miscellaneous requirements specified by the owner are: designing layouts to Maritime Labor
Convention (MLC) 2006 standards, providing specific crew spaces, and installing ventilation and air
conditioning for all accommodations areas.
6. HULL FORM & HYDRO
6.1. SUMMARY OF HULL FORM DRIVING CONSIDERATIONS / HULL FORM DEVELOPMENT RATIONALE With terms of reference as specific as is provided by the World ferry safety association including the
suggested maximum length of 50m (for alongside berthing), the design space of the ferry quickly started
to take shape. Many of the drivers that were considered in the hull design are summarized below.
Above all else, priority was given to safety. As has been previously mentioned, many ferries in Indonesia
are accidents waiting to happen. The number one cause of accidents in Indonesia is human error which
includes improper stowage of cargo, overcrowding, and misjudgment of weather conditions.
Overcrowding is very common in the area and should be expected.
Figure 5: Overcrowding in Indonesian Ferries is typical
Besides safety, cost is a prime consideration in this design. Indonesians will not easily invest in an
expensive hull form, no matter how efficient it is. For example, many recently built catamaran ferries of
similar length use a wave piercing hull, as shown in the next figure. Although this hull form has lower
overall resistance and improved sea-keeping characteristics due to its SWATH-like properties, it’s more
complex to both design and manufacture and so is not a prime candidate for this design.
Figure 6: Wave Piercing Catamaran Hull
Cost of the ship can be compensated by increasing the payload, which lowers the life-cycle cost and
lowers the payback period. This is reflected in the terms of reference from the WFSA that state that the
number of cars and trucks should be maximized. If a ship can make money, the owners are far more
likely to make the investment than to purchase a used ship and retrofit it as a ferry.
Choice of materials is also very important for this design. Aluminum is a third of the weight of steel and,
according to Davidson, an aluminum design is 53% the mass of its equivalent in steel [11]. With about
45% of a catamaran’s lightship weight due to hull structure, this would seem like an obvious choice.
However, aluminum is more expensive and results in a higher labor rate. According to our sponsor, a
fabricated cost (material and labor) of aluminum of about 7x the cost per tonne of steel. This cost can be
reduced over time with increased expertise and custom extrusions, as has is demonstrated by the
Australian Catamaran industry. Although the Indonesian ship building industry is growing, fueled by
changes like the Cabotage principles of 2008 [12], there are very few shipyards that will construct and
repair aluminum, and none in East Nusa Tenggara, the province the ship will be operating in. Lastly, it’s
important to mention that the amount of fire insulation required on an aluminum structure is
significantly more than on a steel vessel, somewhat offsetting the weight advantage of aluminum.
A review of ROPAX catamarans in operation shows that most of them are aluminum high speed craft.
This makes sense as the stability of the craft allows the demihulls to be very slender, providing less
resistance at high speed. Aluminum is used to increase the proportion of the ship’s displacement that is
payload: more of the displacement is making money, less is providing buoyancy and structure.
Connecting the dots of safety and cost, we’ve settled on a catamaran hull-form. A catamaran would
effectively counter the poor practices of ships being overloaded with people and potentially hazardous
materials while also maximizing deck space. Slender hulls spaced widely apart provides not only speed
and stability, but also dramatically increases the available deck area. This makes catamarans very well
suited for transport of high volume, low density cargo, which is exactly what we need. Simply put, a
catamaran satisfies the requirements of safety and affordability.
Medium speed, steel catamarans are uncommon. A number of parent vessels were collected to further
fill in the design space. The white rows below are medium speed, aluminum catamarans, and the green
rows are ROPAX catamarans with steel hulls. For posterity, the full list of catamarans and mono-hull
ferries used in the parametric analysis are included in the appendix.
Table 7: Parametric Study of ROPAX Catamarans
Some important parametric relationships that were developed with our list of similar ships include the #
of cars vs catamaran length and a parametric relationship for powering. The first serves to further
solidify our choice of a catamaran hull form; the second is a good initial power estimate.
Figure 7: Cars vs Vessel Length
Name Ref Type Materials Lightship Disp LOA LWL Beam BWL b Cb Draft
CATAMARANS [tonnes] [tonnes] [m] (overall) [m] [m] [m] [m]
Pentalina Sea Transport ROPAX CAT Aluminum 1137.2 68.9 62.01 20 19.5 6.50 0.55 2.5
Don Nasib Sea Transport ROPAX CAT Aluminum 966.6 61 54.9 20 19.5 6.50 0.55 2.4
Aurora V Sea Transport ROPAX CAT Aluminum 729.7 55.26 49.734 20 19.5 6.50 0.55 2
Don Nasib II Sea Transport ROPAX CAT Aluminum 729.7 55.26 49.734 20 19.5 6.50 0.55 2
Bigred Cat Sea Transport ROPAX CAT Aluminum 543.9 54 48.6 18 17.5 5.83 0.55 1.7
Fast CAT Sea Transport ROPAX CAT Aluminum 603.2 49.9 44.91 17.5 17 5.67 0.55 2.1
Ivete Sangalo Sea Transport ROPAX CAT Aluminum 424.7 49 44.1 16.5 16 5.33 0.55 1.6
Seascape Sea Transport ROPAX CAT All Aluminum 424.7 49 44.1 16.5 16 5.33 0.55 1.6
Island Navigator ROPAX CAT unknown… 413.0 38.5 34.65 13.7 13.2 4.40 0.55 2.4
Sealion 2000 Austral Ships ROPAX CAT Steel hull 685.2 48.8 47 16 15.5 5.17 0.55 2.5
CD551 Incat Crowther ROPAX CAT Steel Hull/Al Super 312.4 40 36.25 15.5 15 3.75 0.70 1.6
Sealink Sea Transport ROPAX CAT Steel Hull/Al Super 157.27 330.27 41 35 13 1.5
North Island Princess BC Ferries ROPAX CAT Steel Hull and Super 665.0 804.0 61.0 52.8 17.98 5.14 3.28
Starlite Ferry ROPAX CAT Steel Hull and Super 1029.5 41.4 39.8 15.90
0
50
100
150
200
250
0 20 40 60 80 100
# O
F C
AR
S
LENGTH
# OF CARS VS VESSEL LENGTH FOR MONOS AND CATS
Mono hulls
Cats
Linear (Mono hulls)
Linear (Cats)
Figure 8: Medium speed CAT power
The best parent ship available is the North Island Princess (NIP), a 61m long ROPAX catamaran
constructed from steel, with a lightship displacement of 665 tonnes. The NIP represents the only
accurate data point for displacement, so its lightship weight was used to make a rough estimate for the
full load displacement of our vessel. The following weight estimate, although very preliminary, tended to
fit in with later weight estimates. The DWT/displacement ratio from this estimate, at 0.3, is also quite
reasonable for ROPAX vessels.
Table 8: Preliminary Weight Estimate
y = 5.7363x - 1.8448
2
3
4
5
6
0.60 0.70 0.80 0.90 1.00 1.10 1.20
KW
/TO
NN
E
FN_V
MEDIUM SPEED CAT POWERING TRENDS
Figure 9: Parent Ship - North Island Princess
6.2. HULL GEOMETRY Hull geometry was developed in concert with a few different sources. The NPL round bilge displacement
series provided a systematic series to initially size the hulls and recommend a hull spacing. Dr. Max
Haase et al. [13] provided some very well documented advice on catamaran particulars for the medium
speeds around a Froude number of 0.35. The lines plan of the VWS89 series was used as a reference to
add a chine to the hull. Lastly, the expert advice of Chris McKesson and Robert Allan improved hull
iterations, lighting the way forward.
The NPL hull series are well organized for catamaran designs because they’re set up in incremental steps
of increasing Length/Displacement ratio (slenderness ratio). Molland calls the slenderness ratio the
predominant hull parameter, and for good reason. It is a major driver in demihulls design. According to
McKesson in [14], “The desire for slenderness is the very raison d’être for…the catamaran and
trimaran.” Assuming a waterline length of 50 meters and using our initial weight estimate of over 1000
tonnes in sea water, the closest NPL model is 3b, with a slenderness ratio of 6.27.
Figure 10: Body Plans of NPL Models
Examining the residuary resistance of the NPL ‘b’ models clearly shows a hollow in residuary resistance
at a Froude number of around 0.35. With a design speed of 14 to 18 knots as specified in the owner’s
requirements, a range of length between about 45 meters to 60 meters is possible.
Figure 11: Residuary Resistance of NPL Models
Longer ships are more slender and produce less wave-making resistance at Fn = 0.35 but will cost more
to manufacture and since they travel at a faster absolute speed, will require more power to reach the
desire Fn. Shorter ships make more waves, but travel slower and cost less. Put another way: Longer
ships are more efficient but you pay a premium for that efficiency. Figure 11 illustrates the constant
displacement line in the cloud of possible ship designs.
Because of the focus on the affordability of this design, shorter ships were favored. A selection was
made by prioritizing cost, tabulating all the required areas, and iterating over the resistance of possible
ships. A waterline length of 52.5 meters was settled on.
Figure 12: Fat vs Slender Catamarans at Fn = 0.35
Other principle dimensions and coefficients important to a catamaran design are prismatic coefficient,
block coefficient, transom depth, demihulls separation ratio, and cross structure height. Most of these
target particulars are covered very clearly in [15] with summarizing plots for medium speeds, which are
shown here in Figure 12.
A multihull’s prismatic coefficient has an affect much greater than that for a monohull, and should be at
most 0.6 if not lower. Block coefficient, especially for displacement (rather than planing) catamarans, is
of particular importance, and should range between 0.39 and 0.45, as is shown with the NPL models
which have a Cb of 0.39. Demihull separation ratio also has a great effect on catamaran resistance.
Separation ratio much be chosen correctly to avoid undesirable crossflow effects. Based on Haase,
Dubrovsky, and Molland, generally a wider separation is better, although a separation ratio (s/L) of 0.3
at a Froude number of 0.35 has been shown to reduce the wave-making resistance, as shown in Figure
12. This separation ratio is also fully documented in [16], which shows a marked drop in residuary
resistance at our design speed. Furthermore, the overall deck width created with s/L = 0.3 and LWL =
52.5 works well for a layout of standard car and truck lanes. These layouts will be covered more
thoroughly in the arrangements section of this report.
Figure 13: Summary of Catamaran Target Particulars
The tunnel height clearance chosen was 1.5 meters based on expert advice, which is a good first
estimate. Transom depth was chosen to ensure it stays dry – this occurs at a transom Froude number of
2.5. Solving for the transom depth at our design speed shows the transom depth must be less than
1meter.
Using these hull particulars, Orca’s hull assistant was used to generate an initial hull form. Dynamically
updating hydrostatics proved very useful. After 7 iterations through the hull assistant, the final touch
was to add more control points and move the LCB further aft to match the -6% midship LCB of NPL
models. Rebuilding the surface (RebuildUV in Rhino) to remove un-needed control point faired the hull,
greatly increasing its aesthetic appeal.
6.2.1. BODY PLAN The two body plans used to develop our hull were the NPL model 3b as well as the VWS89. They’re both
shown below along with the body plan of our hull for comparison.
Figure 14: NPL Model 3b body plan
Figure 15: VWS89 Body Plan
Figure 16: Savu Sea Ferry Demihull Body Plan
Figure 17: Savu Sea Ferry body plan with Cross Structure
6.2.2. LINES PLAN
6.2.3. PRINCIPAL DIMENSIONS AND COEFFICIENTS TABLE
Table 9: Principle Particulars
6.2.4. FUTURE HULL DEVELOPMENTS Although the hull was developed enough to provide a good start for arrangements, midship structure,
and weights, it’s far from being a finished product. Further iterations of this hull could include:
Widening the deck line forward to provide more flare, improving spray deflection and
seakeeping.
Increasing the slope from the chine to the wet deck, adding more reserve buoyancy.
Round out the bow so it ends in a nice radius instead of a point (perhaps 500mm)
Provide more of a transition from the demihull to the cross structure to match the midship
section drawing.
Lower the prismatic coefficient to more closely match the recommended value of 0.6.
6.3. HYDROSTATICS AND STABILITY
6.3.1. STABILITY CRITERIA USED SOLAS was used as the benchmark for safety, including intact stability requirements. Regulation 5, part
B-1 of SOLAS states that every passenger ship of length 24m and upwards shall at least comply with part
A of the 2008 IS Code. The 2008 IS Code clearly defines mandatory stability criteria, each to be applied
at the 4 conditions of loading defined for a passenger ship. As will be seen with the results, our ship is
incredibly stable and is able to easily satisfy all criteria. HSC Code (for high speed craft) has criteria
specific for multi-hull ships, and so it was considered worth reviewing. The purpose of HSC is to set
levels of safety equivalent to those of conventional ships. HSC Code applies to:
Passenger craft that do not proceed more than 4 hours at 90% max speed from a place of
refuge.
O At a speed of 15 knots, one leg of the Savu Sea loop will take the ship over 4.5 hours
away from a place of refuge.
‘HSC’ craft, as defined in HSC 2000 Chapter1.4: A craft capable of maximum speed in meters per
second, equal to or exceeding 3.7𝛁0.1667.
O At our design waterline, this amounts to 22.7 knots, which is far above our maximum
speed.
No enclosed sleeping berths for passengers are provided.
o We have over 50 passenger berths in our design.
Although we do not meet the requirements for all of HSC, some of the stability criteria shed light on
what is considered an “equivalent level of safety” for catamaran stability.
The stability criteria from IS 2008, including general criteria, severe wind and rolling criteria, as well as
special passenger ship criteria are as follows:
I. The area under the right lever curve (GZ Curve) is not to be less than 0.055 meter-radians (3.15
meter-degrees) up to a 30 degree angle of heel.
II. Area under GZ curve is not to be less than 0.09 meter-radians (5.16 meter-degrees) up to a 40
degree angle of heel.
III. Area under GZ curve is not to be less than 0.03 meter-radians (1.72 meter-degrees) from 30 to
40 degrees, or between 30 and the angle of down flooding.
IV. Right lever GZ shall be at least 0.2m at an angle of heel equal to or greater than 30 degrees.
V. The maximum righting lever shall occur at an angle of heel not less than 25 degrees. If this is not
practicable, alternative criteria based on an equivalent level of safety maybe applied.
VI. Initial metacentric height GM0 shall not be less than 0.15 meters.
VII. Under the severe wind and rolling criterion, area ‘b’ is to be greater than area ‘a’, as shown in
the following figure (See the appendix for a full calculation).
VIII. The angle of heel from crowding passengers, with passengers distributed to produce the most
unfavorable combination of passenger heeling moment and/or metacentric height, shall not
exceed 10 degrees.
IX. The angle of heel resulting from the steady wind heeling (𝛗0 ) should not exceed 16 degrees.
X. Angle of heel on account of turning shall not exceed 10 degrees, using the formula shown in IS,
part B, Chapter 3.1.2.
Figure 18: Severe Wind and rolling Criterion
The loading conditions include:
A. Fully loaded departure with cargo, full stores and fuel, and full number of passengers with their
luggage.
B. Fully loaded arrival condition, with cargo, full number of passengers and their luggage but with
only 10% stores and fuel remaining.
C. Ship without cargo, but with full stores and fuel and the full number of passengers and luggage.
D. Ship without cargo, but with only 10% stores and fuel remaining.
6.3.2. STABILITY RESULTS SUMMARY TABLE Part A, part 2.1.1 of IS Code states that free surface effects (FSE) have to be accounted for in all
conditions of loading. For simplicity, we’ve calculated the FSE for all large tanks for the worst case only –
the unloaded arrival case – and then applied this decrease in GM to all loading cases.
Table 10: Tank Free Surface Effects
Normally, the stability results should be calculated for all loading conditions. However, because of how
stable this catamaran is, only the worst case was considered (Fully loaded condition). Orca was used to
set the criteria limits and do all hydrostatic calculations.
Figure 19: Ship Fully Loaded Condition
Figure 20: Orca Stability Results for Fully Loaded Departure.
The one stability criteria that isn’t met is the angle where the maximum righting arm occurs. For an
equivalent level of safety, we can look at the parallel criteria in High Speed Craft code, which has a
similar criteria tailored for catamarans in HSC 2000 Annex 7. Here, the Maximum GZ value should occur
at an angle of at least 10 degrees. From this, we can conclude that the ship meets intact stability
requirements.
6.3.3. LIMITING KG DIAGRAMS As has been shown in the intact stability analysis, this catamaran ferry is very stable. Even with the
combined heeling moments of wind, overcrowding, and turning, the heeling angle was far below the
limit. Because of this, it was decided that a limiting KG diagram would not make a meaningful addition
to the ship’s stability analysis or proof of its ultimate safety.
6.3.4. DAMAGED STABILITY REQUIREMENTS SOLAS 2009 includes probabilistic methods to analyze subdivision and, in turn, damaged stability. This
newer method to assess stability opens up ship subdivision to a designer like never before, allowing for
all sorts of ship subdivision besides the traditional watertight transverse bulkheads. Rather than try to
solve for the optimal hull subdivision, this design subdivides using more traditional methods and then
uses deterministic methods based on SOLAS 1974 to assess damaged stability. It’s worthwhile noting
that a recent study on small ROPAX vessel stability (ship lengths ranging from 32m to 100m) shows that
vessels designed to SOLAS 90 requirements almost always meet the 2009 requirements [17]. All the
vessels in the study meet SOLAS 90 when their GM margins are considered.
Initial subdivision was done based on Table 3.4.1 of Lloyd’s Register rules and Regulations for the
Classification of Ships, Part 3, Chapter 3, Section 4. The total number of bulkheads for a ship of our
length is at least 3 with machinery aft, plus the addition of a collision bulkhead and after peak bulkhead.
We’ve exceeded these requirements by having a total of 6 watertight bulkheads.
For damaged stability criteria, SOLAS 2004 was used to define 2 compartment flooding. The criteria
evaluated were:
I. Righting lever curve shall have a minimum range of 15 degrees past equilibrium.
II. Area under the righting lever curve shall be at least 0.015m-radians (0.86 m-degrees) from
equilibrium to 27 degrees.
III. Residual GZ after damage to be heeling moment/displacement + 0.04, where the healing
moment is the greatest of crowding, launching survival craft, and wind pressure.
IV. A heel angle of 12 degrees is the maximum permitted after flooding.
V. The margin line should not be submerged in any case.
In order to do the analysis, a simplified ‘lost buoyancy’ method was used with Orca. Using ‘boolean
difference’ with solids, the volume of two compartments (A and B from the following figure, for
example) was removed. SOLAS defines the vertical extent of damage to be from the baseline up,
without limit, so the entire volume of the sections was removed, without regard to subdivision due to
tanks. Sections were then defined for the damaged hull and the righting arm curve was calculated to
evaluate stability criteria. A similar analysis could be done using the ‘added weight’ method by adding
‘Orca weight points’ to the hull representing the added weight of water taken on board after damage.
Figure 21: Hull Subdivision
Figure 22: Example - Removing Buoyancy of Damaged Zones
6.3.5. DAMAGED STABILITY RESULTS The following are stability criteria results for damage stability in the fully loaded departure condition.
6.4. HYDRODYNAMICS
6.4.1. RESISTANCE AND POWERING Resistance was calculated using three methods to approximate an upper envelope of effective power to
drive the ship at the design speed. All of these methods are summarized in [18]. The first is based on the
NPL series [16]. Molland reports resistance data for various models of the NPL round bilge series in both
monohull and catamaran configurations. Because the particulars of our hull do not fully match any one
model, resistance was calculated for our ship using the two closest models: Model 3b, which displaces
more if scaled to our ship, and model 4b, which displaces less. Residuary resistance was interpolated
between these two models for our ship, based on values of slenderness (L/V^1/3).
Freeboard At FreeEquil >= 0.076 meters 3.9198 0.076 1.7131 Pass
Angle At FreeEquil <= 12 deg 3.9198 12 3.9198 Pass
GZ At GZmax >= 0.29 meters 21.897 0.29 6.4237 Pass
Area Between FreeEquil and 27 >= 0.86
meters-deg
3.9198 27 0.86 107.7353 Pass
Angle Between FreeEquil and GZ0 >=
15 deg
3.9198 75.1032 15 71.1834 Pass
Name Angle 1 Angle 2 Required Actual Pass / Fail
Stability Criteria - SOLAS 2004, After Damage, compartments D and E
Freeboard At FreeEquil >= 0.076 meters 4.8345 0.076 1.1818 Pass
Angle At FreeEquil <= 12 deg 4.8345 12 4.8345 Pass
GZ At GZmax >= 0.29 meters 21.0658 0.29 4.5295 Pass
Area Between FreeEquil and 27 >= 0.86
meters-deg
4.8345 27 0.86 75.2789 Pass
Angle Between FreeEquil and GZ0 >=
15 deg
4.8345 70.4717 15 65.6372 Pass
Name Angle 1 Angle 2 Required Actual Pass / Fail
Stability Criteria - SOLAS 2004, After Damage, compartments F and G
Table 11: NPL Model Data compared to Ship Data
The next method that was used is a systematic series of 18 hard-chine demi-hulls [19]. Wave resistance
was calculated using SHIPFLOW, a hydrodynamics CFD software. After that, the data was analyzed and a
regression equation was developed. The authors admit that further research is needed to improve the
data, as the results deviate from other more established methods quite a bit. However, because of how
close the body plans used in this method match our body plan, it was included in this design. This
method predicts resistance in the Froude number range of 0.4 to 1.5, so the data was extrapolated
down to our design Froude number of 0.35.
The last method used in our resistance prediction is the VWS Hard Chine 89 Series Regression developed
by Zips [20]. This series covers a Length to demi-hull beam ratio of 7.55 to 13.55, an angle of dead rise
amidships of 16 to 38 degrees, and a transom wedge angle of 0 to 12 degrees. Our ship falls within these
parameters, but not within the speed range covered by the regression. The regression has data down to
a volumetric Froude number of 1. Like the last method, the available data was extrapolated down to the
design volumetric Froude number of 0.85.
Figure 23: Body Plans used by Pham and Sahoo
Figure 24: Resistance Predictions (design speed in Red)
The results above show that for a design speed of 15 knots, we can expect an effective power
requirement somewhere in the range of 700kW to 1650kW. Due to our lack of confidence in the Pham
and Sahoo method, we expect an effective power in the upper range of this estimate, from about 1300
to 1500kW.
The parametric relationship on powering, Figure 8 , can now be used to corroborate our powering
estimate. With an initial weight estimate of 1033 tonnes and a volumetric Froude number of 0.78 based
on a design speed of 15 knots, installed power is calculated to be 2620kW (using the relationship
KW/tonne = 5.7363*FN_v - 1.8448). Assuming a quasi-propulsive coefficient of 0.5 (this includes open
water efficiency, hull efficiency, and relative rotative efficiency), this brings right inside of the range of
our estimate of 1300 to 1500kW.
Another quick way to do a reality check is with Transport Factor (shown below), which has been
extensively written about in [14] for all ships and used in [15] to compare recently built high speed
catamarans. As recorded in [14], Kennell’s data on the effect of slenderness shows trend lines dropping
with decreasing slenderness away from the ‘State Of the Art’ curve. Plotting our table of similar ships in
the same way yields a trend that flows in the same direction as Kennell’s data. The best parent ship we
have, the NIP, has a transport factor of 34. Solving for the engine power using our initial weight estimate
and a design speed of 15 knots yields about 2400kW.
𝑇𝐹 =∆ × 𝑔 × 𝑈
𝑃𝑒𝑛𝑔𝑖𝑛𝑒
Figure 25: Kennell's data on the effect of slenderness
Figure 26: Transport Factor for Similar ROPAX Catamarans
6.4.2. SHIP MOTIONS AND SEAKEEPING Due to our divergence from the more common wave-piercing hull forms used on ferries today resulting
in a lack of sea-keeping data on our hull form, no further research into ship motions was done. It was
noted that the wave piercing hull form was developed as a response to the reduced resistance to
0
10
20
30
40
50
60
5 10 15 20 25 30 35 40
Tran
spo
rtat
ion
Fac
tor
Speed (kn)
Transportation Factor for Similar Ferries
pitching because of the slenderness of the catamaran hulls. Our hulls are at the lower end of catamaran
slenderness, so they may not benefit as much from the wave piercing form. It may be just as beneficial
to add more reserve buoyancy by adding more flare moving up towards the deck line.
6.4.3. SHIP MANEUVERABILITY Four azimuth thruster that can provide thrust in 360 degrees are included in the propulsion
arrangement. Due to the wide spacing and versatility of these thrusters, maneuverability was not seen
as a design constraint and was not further analyzed.
7. SHIP ARRANGEMENT
7.1. ARRANGEMENT RATIONALE The arrangement was carefully considered during the design process and is discussed below. There are
many factors that play off each other to achieve an arrangement that begins to be suitable such as
safety, mission, available space, weight, structural simplicity, and amenities. “Capacity, flow, and
passenger safety are the guiding principles…” [21]. For our purposes, these can be boiled down to
mission and safety.
Most of the area on the first deck of the ship is devoted to the temporary storage of vehicles. Cars and
trucks are located on the main deck with trucks placed in the center lanes for easy loading and
offloading. At 2.5 tonnes per lane-meter, trucks are the largest contributor to deadweight. Not only that,
trucks in Indonesia are often overloaded according to [22], on average up to 45% beyond their rated
capacity. For this reason, only the center lanes are high enough for trucks to travel under.
Cars and trucks are major drivers of the vessel’s beam. As shown in the arrangement drawings in the
next section, the midship’s beam is made up of 6 car lanes as well as space for a stair well and service
space on either side of the ship. According to [21], cars require from 2.2- 2.35m of lane width, and trucks
up to 3.2m of width. For our design, 2.6m wide lanes were used for cars, and 3.25m wide lanes for
trucks. From the resistance analysis, it was found that a demihull spacing to length ratio (s/L) of 0.3
resulted in low hull interference. Several combinations of car and truck lanes were calculated before the
current beam of 23.5 meters was settled on, which meets our minimum of 2.5m on each side for service
spaces and stairs. This 2.5m will include a stair and a walkway. This is based on the SOLAS requirement
of a minimum of 900mm open space, between railings, for a stair, plus space for bulkheads, framing,
and lining.
The locations of stairwells drove the longitudinal locations for the accommodations. Many possible
room and corridor configurations were drawn, but the team settled on the current arrangement of the
3rd and 4th decks (The stepped passenger area) for a few reasons, outlined below:
All cabins exceed minimum MLC requirements of 14.5m2 for a 4 berth room and 7.5m2 for a 2
berth room. Officer accommodations far exceed these minimums.
All the berths are placed longitudinally for increased passenger comfort. We found that adding
basic furnishings to the arrangement (Beds, sink, table) was key to generating a layout concept.
The size and direction of the beds and minimum spacing for passenger access greatly influenced
the size and arrangement of the rooms.
Sinks and toilets were placed close together to minimize plumbing. Plumbing routes were
visualized and roughed in to ensure feasibility.
A nominal 150mm was left between stairs and any structural bulkheads to allow for framing and
lining.
Premium rooms include a balcony on the starboard/port sides of the ship and economy rooms
are located in a block at the center of the ship. After several layout we found we had extra beam
that resulted in a clumsy central corridor. The best use of this corridor was to split it and move it
far to port/starboard as a balcony.
Although the containerized propulsion units include noise insulation, the passenger
accommodations are further insulated by bathrooms and corridors which are located abaft all
rooms. The ‘step’ in the hull described earlier is used in a clever way by creating a stepped
atrium hallway that allows light in. This serves to open up and lighten the accommodation area,
providing a more dynamic and live-able space. This runs in line with MLC 4.69, which requires
natural light in sleeping accommodations. Adding natural light also makes the cabins more
attractive to passengers.
An effort was made to line up structural bulkheads with the transverse frame spacing of
550mm. To match this, passageways in the accommodations block were made 1100mm wide.
Bulkheads that line up with frames include bathroom bulkheads, stair bulkheads, and the
bulkhead separating the accommodation from the seating area. Non-structural bulkheads, like
those found between accommodations, do not have to line up.
The arrangement lines up well with the structure at midships to minimize unnecessary moments
on columns that support the superstructure.
The safety of the passengers and crew is one of the prime considerations of this design. The safety of a
ship is not simply dependent on how seaworthy she is. The International Convention for the Safety of
Life at Sea (SOLAS) was consulted to select and place appropriate emergency equipment, define muster
stations, define fire zones and place ample means of escape.
The functional requirements of fire safety as described by SOLAS include the separation of
accommodation spaces by thermal and structural boundaries as well as the protection of the means of
escape. To address these, we’ve separated the entire accommodation area from the seating area by a
steel bulkhead. This bulkhead will be further insulated by A-60 rated fire insulation to isolate any fire in
its zone of origin. Access between the two sections will be by fire-rated doors on magnetic hold-backs.
The main stairwells have also been isolated from public areas by steel bulkheads and fire-rated doors to
guarantee a means of escape.
Safety equipment requirements are based on SOLAS, Chapter III, Part B, Section II, Regulation 21. This
regulation defines a short international voyage as one in which the last port of call in which the voyage
begins to the final port does not exceed 600 miles.
1 Fast Rescue Boat with a capacity of 15 people, including a slewing arm davit
1 Lifeboat with a capacity of 65 people, including a hydraulic davit.
8 throw-over, self-righting life-rafts, each with a capacity of 50 people. In preparation for vessel
overcrowding, twice the required capacity of life-rafts were added to the design. Pictures and
videos of Indonesian ferries in the region show a similar number of life-rafts on board.
Life Buoyant, spaced at about 5m intervals on all open decks.
440 Life Jackets, one under each seat and berth as well as 200 extra life jackets distributed close
to the muster stations for easy distribution.
Safety also extends to the safe stowage of cargo. IMO Resolution A.581 – Guidelines for Securing
Arrangements for the Transport of Road Vehicles on Ro-Ro Ships recommends securing points for road
vehicles along the deck, spaced not more than 2.5m apart. According to this resolution, a 25 tonne lorry
requires at least 3 securing points on each side.
Figure 27: Securing Points [23]
7.2. ARRANGEMENT DESCRIPTIONS
7.2.1. ARRANGEMENT BLOCK DRAWINGS
Figure 28: Midship Arrangement
7.2.1.1. DECK PLANS
Figure 29: Deck 5 - Pilot House and Officer Cabins
The top deck is primarily for crew. It includes the Pilot house, officer accommodations, a day room, and
an emergency generator room, as required by SOLAS. The rest of the area is open to the public and from
our research into the area will easily be crowded by passengers looking for a place to sit.
Figure 30: Deck 3 and 4 - PAX Accommodations and Seating
The stepped deck, decks 3 and 4, is the main passenger accommodations area. There are 4 vertical
stairways on this deck, providing ample means of escape. The cabins are in 2 and 4 berth
configurations, each including bunks, a desk, and a vanity unit with hot and cold running water. The 4
berth cabins include a door out to a small private balcony. Water closets are located towards the stern.
Each includes a sink, shower, and toilet.
Figure 31: Deck 2 - Vehicle Deck
Ample room has been provided for movement between cars to access the stairs to upper levels. Access
to these stairs is via small alcoves in the side structure so doors swinging open does not impede the flow
of traffic. The propulsion units are isolated from the rest of the main deck in a walled service space
located on the transom to give the ship’s engineer space to work and to keep the public safe.
7.2.1.2. INBOARD PROFILE
The Inboard profile cuts right through the centerline of the ship, hiding the step in the superstructure.
7.2.1.3. OUTBOARD PROFILE
The blue ‘speed line’ gives the ferry a sleek appearance while providing a structure to hide the generator
uptakes in. From this view, it’s also easy to see that the pilot has a good line of sight.
7.2.1.4. RENDERINGS
The rendering was made by composing a 3D model in Rhino based on the GA. The model is built up from
the hull from based extruded 3D shapes with materials applied.
7.2.2. AREA/VOLUME REPORT Areas and volumes were at first estimated from similar ships and recommendations from MLC and other
sources. Later, some of the areas were recorded from the GA to corroborate estimates and get better
accuracy for corridors and service spaces.
Figure 32: MLC Space Requirements
Dim 1, m Dim 2, m Area, m2 Notes
Minimum berth size 0.198 0.8
Minimum headspace 2.03
Single berth Sleeping area 4.5 All from MLC, 2006, pg 43 and 44
Two person sleeping room 7.5
Three person sleeping room 11.5
Four person sleeping room 14.5
More than 4 people 3.6 per person
Junior officer, single berth 7.5
Senior officer, single berth 8.5
Mess rooms 1.5 per person, Place close to the Galley
MLC REQUIREMENTS, minimum dimensions influencing facility areas
Public Accomodations - Frames 17 to 47
Name or use QTY Area each, m2 Height, m ∑ Area, m2 ∑ Vol, m3
PAX Cabin 4 single bunk 8 14.52 2.75 116.16 319.44
PAX Cabin 2 single bunk 12 7.36 2.75 88.32 242.88
***** Bunk bed size, min 200cm 90cm
Cabin Balconies 8 3.33 2.75 26.64 73.26
Cabin corridors 2.75 126 346.5
Women's Cabin Bathroom 2 7.68 2.75 15.36 42.24
Men's Cabin Bathroom 2 7.18 2.75 14.36 39.49
Total Passenger Berths 56 386.84 1063.81
Passenger Public Spaces - Frames 47 to 73
Name or use QTY # of PAX m2/PAX Height ∑ Area, m2 ∑ Vol, m3
Economy seating 1 128 1.11 2.75 141.9 390.115
Premium seating 1 44 2.17 2.75 95.5 262.57
Kiosks with drinks/snacks 1 2.75 24.5 67.4905
Outdoor viewing areas 1 2.75 12.8 35.2
Walkways 1 2.75 38.8 106.8
Public Women's Bathroom 1 185 0.05 2.75 9.6 26.5
***** # of toilets, women 2
*****# of sinks, women 2
Public Men's Bathroom 1 185 0.05 2.75 9.6 26.5
***** # of toilets, men 2
*****# of sinks, men 2
*****# Urinals 1
Total PAX public spaces 332.762 915.10
Crew Accomodations # of crew: 15
Name or use # Cabins Beds/cabin Size, m2 Height, m ∑ Area, m2 ∑ Vol, m3
Crew Cabin, Officer, private 4 1 7.5 2.75 30 82.5
Crew Cabin, Officers 2 2 7.5 2.75 15 41.25
Crew Cabin, Crew 2 4 14.5 2.75 29 79.75
Cabin Corridors, wall lining… use an extra::: 20% 2.75 14.8 40.7
Total Crew Cabins 8 16 88.8 203.55.92 m2/crew
Crew Spaces
Name or use #of Seats m2/seat m2/crew Height, m ∑ Area, m2 ∑ Vol, m3
Galley (kitchen) 5 2 1.00 2.75 15.0 41.3
Mess room 15 1.5 1.5 2.75 42.5 116.9
Laundry Area 2.75 8.0 22.0
Crew bridge head 2.75 6.8 18.6
Crew stores area 1.5 2.75 22.5 61.9
QTY Area Each
Crew single bathroom 2 4 2.75 8.0 22.0
***** # of toilets 1
*****# of sinks, men 1
Cabin corridors, wall lining… use an extra::: 10% 2.75 10.3 28.3
Total Crew Spaces 113.0 310.87.54 m2/crew
Service Spaces For all Crew + pax = 200
Name or use QTY m2/PAX Height ∑ Area, m2 ∑ Vol, m3
Garbage handling 1 0.05 2.75 5.0 13.8
Linen storage 1 0.1 2.75 5.0 13.8
Janitorial 2 2.75 10.0 27.5
Wheelhouse 1 2.75 18.0 49.5
Main Deck Service Spaces - 2.75 35.0 96.3
Total Service Spaces 73 200.75
Technical Spaces For installed engine power: 2984 kw
Name or use QTY area each m2/kW Height ∑ Area, m2 ∑ Vol, m3
Engine and thruster 2 26 3 52.0 156.0
pumps 1 3 100.0 300.0
Generator room 1 0.25 3 125.0 375.0
Switchboard rooms 1 0.005 3 2.5 7.5
Workshop + stores 1 0.01 3 29.8 89.5
Total Technical spaces 309.3 928.0
Deck Spaces
Name or use QTY m2/item Height ∑ Area, m2 ∑ Vol, m3
Staircase 2 10.5 8.75 21 183.75
Engine casing 2 8.8 5 17.6 88
funnel 1 3 5 3 15
Car spaces 34 13.5 2.75 459 1262.25
Truck spaces 10 31.5 4.25 315 1338.75
Storage space 2.75 145 398.75
Corridors, wall lining… use an extra::: 5% 48.03 164.325
Total Deck Spaces 1008.63 3450.83
7.2.3. FUTURE IMPROVEMENTS In many ways, the GA drove various other areas of the design, such as weight and structure. Through
the GA, we’re also able to communicate many of our design decisions in a very concise form. Because of
this, we spent a lot of time reviewing and refining it. Although it could be considered at the concept
design stage, we believe it’s far from where it should be to truly be a reflection of the viability of this
design. The next few improvements that
Add in allowances for framing, lining, and fire insulation on structural bulkheads as well as
allowances for non-structural bulkheads between accommodation areas.
Add in vertical trunks for wiring and plumbing, with thought of how these could be serviced
when necessary.
Make an evacuation plan, considering the number of passengers which would normally occupy
the spaces and where they would run to in the event of an emergency.
Tanks and Voids
Installed Engine Power 4977 kW
Cruising speed 15 kn
Total # of passengers and crew = 200 people
Name or use SG [t/m3]
Consump.
g/kWh Range, Nm
Days,
Endur. Margin factor ∑ Vol, m3
Fuel Oil 0.87 200 1000 2.8 0.6 45.8
Lube Oil 0.92 1.5 1000 2.8 4 2.2
l/pers/day
Potable Water 1.00 100 1000 1 1 20.0
Black water 1.00 150 1000 3 1 0.00
Grey Water 15.00
Used oil 0.50
Sludge 1.00
Oily Water 5.00
Voids… Extra ---> 25% 13.4
Total Tank space required 102.84
Name or use m2/pax Area, m2 Vol, m3
Crew facilities 201.8 514.3
Passenger facilities 719.6 1978.9
Service Spaces 73.0 200.8
Total Furnished Interior spaces (AC spaces) 994.4 2694.0
Total Machinery Spaces 309.3 928.0
Deck Car/truck Space 1008.63 3450.8
Tanks and Void Spaces 102.8
GROSS VOLUME 7175.66
GROSS TONNAGE 1988.50
System Design Summary
8. SHIP STRUCTURE
8.1. RULE SET AND METHODOLOGY The mid-ship section was designed to meet Lloyd’s Register Rules and Regulations for the Classification
of Special Service Craft, July 2011. Lloyd’s Register provides calculation procedures on the determination
of local design pressures, global loads, and associated scantling requirements. For the design of steel
catamarans, Part 5 and 6 within this rule set were mainly used.
The mid-ship structural design was performed based on the following design process and methodology.
First, the calculation was done for local design loads induced by environmental conditions, vessel
motion and impact loads such as hydrostatic, hydrodynamic pressure and impact pressures. Secondly,
global loading conditions including wave longitudinal moment, shear force, twin-hull transverse moment
and torsional moment were obtained. The scantlings were therefore determined based on the results of
design loads. The local design pressures were used to calculate the requirement of plating thickness,
sectional area and section modulus of each structural member, while the global loads were used to
check for the hull girder strength with the scantlings selected. It is noted that some of the fundamental
structural design decisions left for designers play very important role on the structural arrangement,
such as the type of framings for hull and deck, spacing of frames, type of keels and bottom to be used
for the vessel. The following sections provide the rationales on the design decisions for the vessel.
8.1.1. LOCAL PRESSURES The local design pressures were calculated using equations from Lloyd’s Register based mostly on the
vessel’s particulars and the environmental condition. The maximum values were selected for each type
of pressure to calculate the local loads exerted on the vessel. The results are summarized in the table
below, more detailed calculations on how the results were achieved can be found in Appendix.
hydrostatic pressure Ph 28.14
hydrodynamic pressure Pm 57.66
pitching pressure Pp 79.70
Impact pressure Pdh 64.74
deckhouse, superstructure pressure Pdhp 7.04
shell envelope pressure Ps 107.84
fore body impact pressure Pf 64.74
Impact pressure on cross-deck Ppc 22.76
pressure on weather deck Pwh 12.40
deck pressure for cargo Pcd 25.16
watertight bulkhead, plating Pbh, plating 28.25
watertight bulkhead, stiffener Pbh, stiffener 35.21
Table 12: Local Design Pressures
8.1.2. VESSEL LOADING The local load acting on vessel were found using the results from design pressures induced by
hydrostatic, hydrodynamic, impact pressures and etc. These loads were used to determine the plating
thickness and stiffening properties for the local members. The following table summarized the results of
the design load used for the vessel. The criteria from Lloyd’s Register and detailed calculations can be
found in Appendix.
bottom shell plating PBP 113.23
bottom shell stiffening PBF 56.61
side shell plating, outboard PSP, outboard 113.23
side shell stiffening, outboard PSF, outboard 56.61
side shell plating, inboard PSP, inboard 113.23
side shell stiffening, inboard PSF, inboard 56.61
cross-deck plating PCP 83.68
cross-deck stiffening PCF 41.84
weather deck plating PWDP 25.16
weather deck stiffening PWCDF 25.16
coach roof plating PCRP 13.02
coach roof stiffening PCRF 7.00
interior deck plating PIDP 25.16
interior deck stiffening PIDF 25.16
inner bottom plating PIBP 88.68
inner bottom stiffening PIBF 56.61
superstructure plating PDHP 7.39
superstructure stiffening PDHF 3.69
bulkhead plating PBHP 28.25
bulkhead stiffener PBHF 35.21
Table 13: Local Loads acting on Vessel
8.1.3. GLOBAL LOADING The global loads were calculated to check the hull strength. For catamarans, the major global loading
cases that need to be considered in addition to longitudinal vertical wave bending moment include:
twin-hull transverse bending moment, and twin-hull torsional connecting moment, as illustrated in the
figures below.
Figure 33: Vertical Wave Bending Moment
Figure 34: Twin-hull Bending Moment
Figure 35: Twin-hull Torsional Moment
The results of vertical wave bending moment along the length of the vessel, for both hogging and
sagging moment. Detailed calculations and table of results can be found in the Appendix.
Figure 36: Longitudinal Vertical Wave Bending Moment
The following tables show the results of twin-hull transverse bending moment, twin-hull torsional
moment, and vertical shear force at cross-deck centreline.
Twin hull transverse bending moment, kNm MB 26184
Twin hull torsional connecting moment MT 40389
Vertical shear force cross-deck centreline QT 1586
Table 14: Hull Bending Moment, Torsional Moment, and Vertical Shear Force
-30000
-20000
-10000
0
10000
20000
30000
40000
0% 25% 50% 75% 100%
Ver
tica
l wav
e b
end
ing
mo
men
t,
kNm
%Length
Vertical Wave Bending Moment
hogging
sagging
In addition, for multi-hull vessel, it is required to load the cross-deck subject to primary load
combinations depending on the heading of ship, including head sea, beam sea and quartering sea. These
load combinations were used to check the cross-deck strength against ductile failure modes. The results
of maximum values for each of operating conditions are summarized in the table below.
Vessel Heading Moment, kNm
Head sea 39215
Beam sea 37517
Quartering sea 56030
Table 15: Load Combinations for Cross Deck strength check
The results from global loads are to be used to check hull girder strength, as discussed in the following
sections.
8.1.4. MATERIAL SELECTION As mentioned in the previous section, one of the major design aspect from the owner’s requirement is
affordability, therefore steel was primarily chosen for the vessel to lower the construction as well as
overall lifetime cost. Furthermore, research on the infrastructure facilities in Indonesia also became one
of the driven factor as local shipyard has limited facilities and experience for aluminum vessel
construction, maintenance and repair. For structural design, Steel Grade A was selected with yielding
stress at 235MPa.
8.1.5. PLATING THICKNESS With the results obtained from local design pressures and the selected design frame spacing, the
minimum plating thickness requirements were calculated for all shell envelope, primary and secondary
stiffeners as well as plating on superstructure. First, the thickness of plating and stiffeners determined
by rule scantling requirement was calculated using the equation from Lloyd’s Register based on the local
design load, as shown here:
Equation 2: Thickness of Plating and Stiffeners
The results obtained from the equation were compared with the minimum thickness requirements for
shell envelope and each individual member set by the criteria table, which can be found in Appendix.
The overall thickness requirement of plating and stiffeners were therefore selected for the results
determined by both of the criteria, for whichever is larger. The results are summarized in the table
below. Detailed calculation and tables of results can be found in Appendix.
In addition, the plating thicknesses for the design were chosen, incorporating an optimized construction
practice, where common plating thicknesses were considered to reduce the complexity of structural
arrangement and ultimately construction cost. As a results, 10mm steel plate was selected for shell
envelope for hull and deck, and 8mm steel plate was chosen for the use of primary and secondary
stiffeners, while the plating for superstructure was 5mm. It is noted that potential weight reduction
might be achieved where extra plating thickness was selected. Further cost analysis is therefore
recommended for the trade-off.
Minimum thickness Design selection
Shell envelope
bottom shell plating 9.9 10
side shell plating 9.9 10
wet-deck plating 8.5 10
Single Bottom structure
centre girder web 6.7 8
floor webs 5.1 8
side girder webs 6.1 8
Bulkheads
watertight bulkhead plating 4.8 8
Deck plating and stiffeners
strength/main deck plating 8.5 10
lower deck/inside deckhouse 5.2 10
Superstructures and deckhouses
superstructure side plating 3.1 5
superstructure top plating 3.0 5
machinery casing side plating 3.0 5
Pillars
rectangular pillars 5.0 5
Table 16: Minimum Plating Thickness Requirements
8.1.6. STIFFENER PROPERTIES In addition to the plating thickness requirements, Lloyd’s Register requires calculations to be performed
on the minimum section modulus and moment of inertia for each of the individual structural members.
The sample calculation shown in this section is for the primary stiffener: The web frame for the cross-
deck structure. The procedure will be briefly described with these calculations.
Calculations were performed based on the equations provided by Lloyd’s Register, as shown below:
Equation 3: Required Section Modulus
Equation 4: Required Moment of Inertia
The stiffener properties of the design selection were calculated to check against the requirements. The
results are summarized in the following table.
Cross-deck Web Frame
load model a, b or c a
design pressure, [kPa] P 41.84
stiffener spacing, [mm] S 3300
effective span length, [m] Le 9.5
section modulus coefficient Φz, mid 0.04
inertia coefficient ΦI, mid 0.0026
web area coefficient ΦA, end 0.5
limiting bending stress coefficient fσ 0.65
limiting deflection coefficient fδ 1000
limiting shear stress coefficient fT 0.65
section modulus, [cm³] Z 3399
moment of inertia, [cm4] I 154144
web area, [cm²] Aw 74
section selection 1450x8
section modulus, [cm³] Z, selected 4205 OK
moment of inertia, [cm4] I, selected 203242 OK
web area, [cm²] Aw, selected 116 OK
Table 17: Sample Calculations of Stiffener Properties
Similar calculations were done for other structural members. Detailed calculations and complete tables
can be found in Appendix.
8.1.7. HULL GIRDER STRENGTH With the preliminary plating thicknesses selected for shell and deck plating, the hull girder strength of
the vessel was checked to meet the requirements. For multi-hull vessels over 40m, Lloyd’s Register
requires checking hull girder strength subject to wave bending moments and shear force for both
departure and arrival conditions. For the purposes of the concept design, only the fully-loaded condition
was considered based on the assumption that the vessel would be operating in full-loaded condition for
most of time due to the high local demand for ferry transportation services. The calculation procedure
and the summary of results are discussed in the following sections.
The hull girder longitudinal bending strength had to be checked for both the strength deck and keel
amidships. The section modulus for both the strength deck and keel were calculated - detailed
calculation can be found in Appendix. The bending stress subject to the global loading cases were
calculated using the following formulas provided by Lloyd’s Register:
Equation 5: Hull Girder Bending Stress at the Strength Deck
Equation 6: Hull Girder Bending Stress at the Keel
The calculated bending stresses were used to compare with the maximum permissible bending stress
based on material properties. The results are summarized in the following tables.
Hull Girder
Max permissible hull vertical bending stress, σp 169
Table 18: Maximum Permissible Hull Bending Stress
Actual section modulus at deck Zd 1.349
Hull girder bending stress at strength deck σd 24.1
check <σp? OK
Table 19: Hull Girder Strength at the Strength Deck
The equation used to calculate hull shear strength is shown below, using effective shear area as defined
by Lloyd’s Register:
Equation 7: Hull Sheer Strength
The transverse shear area was calculated by simplifying the hull form into rectangular boxes, where the
dimension of the boxes was based on the vessel particular, as shown in the figure below.
Figure 37: Simplified Hull form for Shear Stress Calculations
The complete table of total effective area calculation can be found in Appendix. The results of shear
stress check is summarized below.
Hull Girder
max permissible mean shear stress, τp 98
Figure 38: Max Permissible Hull Shear Stress
actual section modulus at keel Aτ 0.236
hull girder bending stress at keel QR/Aτ 5.7
check <τp? OK
Figure 39: Actual Hull Shear Stress
For catamarans, Lloyd’s Register requires checking the cross-deck structure strength against bending
moment and shear force. The bending and shear stress for cross-deck structure were calculated as a
function of vessel heading direction, namely Head Sea, Beam Sea and Quartering Sea. The results of
moment distribution for each heading direction can be found in Appendix. The maximum values of
bending and shear stress, along with the capacity check are included in this section.
The table below summarizes the results for the maximum permissible bending and shear stress for the
cross-deck structure based on the material properties.
Cross-deck Structure
max permissible hull vertical bending stress, σp 169
max permissible mean shear stress, τp 98
Table 20: Max allowable Stress for the Cross-Deck Structure
As per the requirement stated in Lloyd’s Register, the total bending and shear stress for the cross-deck
structure were calculated as sum of the stress induced by different global loading cases, including hull
girder stress, stress induced by twin-hull transverse bending moment and torsional connecting moment.
The criteria for multi-hull craft that was used in calculation is shown in the figure below.
Table 21: Cross-Deck Strength Criteria for Bending and Shear Stress
The results for checking the bending stress for the three major vessel heading directions are
summarized in the table below. Detailed calculations can be found in Appendix.
Head sea Beam sea Quartering sea
hull girder bending stress σd 24.1 2.4 9.7
stress induced by transverse bending σMB 4 39 4
stress induced by torsional moment σMT 5 10 48
total direct stress σP 32.8 50.6 61.6
check OK OK OK
Table 22: Cross-deck Bending Strength Check
Similarly, the required cross-deck shear stress was checked for the same heading direction, and the
results are summarized in the following table.
Head sea Beam sea Quartering sea
shear stress induced by vertical shear
force
τT 0.40 4.02 0.40
bending shear stress induced by
torsional moment
τMBT 2.07 4.14 20.69
shear stress induced by torsional
moment
τM 0.03 0.07 0.35
total shear stress τp 2.5 8.2 21.4
check OK OK OK
Table 23: Cross-Deck Shear Strength Check
Notice that the torsional stress calculation is not required by Lloyd’s Register for the type of vessel in
this project. Further studies and analysis for cross-deck structure torsional strength are recommended.
In general, it is noted that the proposed structure with design plating thickness provides sufficient hull
girder strength to meet the requirements as per Lloyd’s Register. The governing load case, therefore,
can be concluded to be the load design pressure that is discussed in the previous sections.
8.2. MIDSHIP SECTION DRAWING
Figure 40: Midship Section
A hybrid framing was selected considering the complexity of multi-hull structures and from parametric
studies. Note that transverse framing was selected for the demi-hull, while longitudinal framing was
chosen for the deck and cross-deck structure.
The spacing of frames was chosen to be fairly consistent for both longitudinal and transverse framing.
For a vessel with a length of 55m, the proposed 550m spacing was selected for the first design iteration.
One of the most important trade-offs for selection of the frame spacing is the overall steel weight, as
frame spacing essentially determines the plate thickness and the properties of stiffening members. The
maximum spacing of web frames is 3.3m taking into account the location of bulkheads. Further studies
on the specific location of frames, web frames and transverse bulkhead is recommended.
A double bottom was initially considered for the potential space reserved for use of fuel tanks, after
calibrating with general arrangement and discussing with the industry mentor. A single bottom was
chosen since the accommodation floor inside the hull performed the function of an isolation barrier for
grounding damage.
As transverse framing was selected for the hull, a number of five transverse bulkheads was selected for
each of the demi-hulls. This meets the Lloyd’s Register requirement where a minimum number of four
transverse bulkheads is needed.
Transverse framing was selected for the superstructure. The structural arrangement was to be designed
to be simple as possible for better stress flow consideration. As shown in the mid-ship section drawing,
the superstructure consists mostly of rectangular structures. A continuous column for the interior was
used to be the main structural support. It is also noted that the column was supported by the web
frames.
8.2.1. DESIGN RESERVATIONS AND RECOMMENDATIONS The above section describes the scope of the conceptual design for this project. It is recommended to
conduct further studies and analysis on structural design for the next design cycles. Some of the points
discussed below can be taken into considerations:
Finite element analysis is recommended to check overall vessel strength
Potential weight reduction could be achieved for optimal frame spacing
Properties of stiffening members should be further defined
Location of web frames and bulkheads should be specified along the length of the vessel
9. SHIP PROPULSION The propulsion system is the heart, fins and tails of a ship; hence, much attention has been put into its
selection and arrangement. The following section details the chosen machineries and the rationales for
their selections.
9.1. MACHINERY PLANT DESCRIPTION Two outboard power plants are placed on each of the catamaran’s demi-hulls. Each outboard plant
powers a Shottel rudder-propeller (azimuth thruster). The wide spacing between these pair of rudder-
propellers as well as the 360 degree rotations of the propellers provide the ferry with outstanding
maneuverability.
A maintenance feature of the Shottel rudder-propeller is the ability to hydraulically swing-up its
propellers for inspection and maintenance. The depth of the rudder-propellers can also be further
adjusted at the helm to prevent grounding or reducing drag when only two of the four propellers are
used.
9.1.1. MAIN ENGINE The outboard plant chosen for this project is the Schottel Navigator 550. The prime mover of the unit is
the Caterpillar 746 kW C32 ACERT engine. From the technical Specification:
An additional soundproof canopy is installed to lower the engine noise to 80 dB at a distance of one
meter [24]. This is lower than the 85dB level defined by the Code on Noise Levels on Board Ships. At
85dB, personnel are required to wear ear protection. The cabins are further insulated from the
propulsion units by several bulkheads and spaces. This should easily satisfy the limit of 60dB for
accommodation spaces. As the unit is closed, air is forced in via axial fans for cooling and combustion.
Figure 41: NAV 550 Propulsion Unit
“The SCHOTTEL Navigator is in principle a large-scale outboard plant
deck-mounted. A base frame, that is also capable of accommodating
the fuel day tank, serves to support the prime mover and provides all
necessary foundations as well as suspensions for the subsystems. A
canopy is mounted on top of the base frame. Bolted together, base
frame and canopy, they form a unit.”
Figure 42: Main Engine
9.1.2. GEARING AND SHAFTING The Nav500 includes an upper gearbox and a lower gearbox. The upper gearbox is connected to the
hydraulic clutch mounted to the engine housing by a cardan shaft. The lower gearbox connects the
vertical shaft with the propeller, completing the bottom portion of the ‘Z’ drive.
9.1.3. RATIONALE FOR SELECTION The five propulsion methods considered for this ferry were:
Drive shaft and rudder, hence forth called conventional propeller (assumed to be diesel
powered)
Voith Schneider Propulsion System
Outboard Azimuth Thruster
L-drive Thruster
Marine Waterjet
Marine waterjet propulsor was shortlisted early because of its costly maintenance and poor fuel
efficiency at slow speeds.
To best match the ideal propulsion type to the ferry’s mission, an Analytical Hierarchy Process (AHP) was
utilized. AHP decision making method helps compare unlike criteria.
The process of propulsion selection starts by relating the owner’s primary goals –safety and affordability
- with propulsion characteristic such as maintenance cost, fuel consumption, and maneuverability.
When utilizing AHP, it was helpful to define a relevant point of reference for each criteria and to
view the ship as an entire system rather than only the immediate outputs of the propulsion
system. The viewpoints for evaluating cost and maneuverability are as follows:
1. Calculating direct and indirect expenses (including opportunity cost) in terms of net
present value over the forty year lifespan of the ferry
2. Maneuverability of the ship is considered as a whole rather than just the propulsion
system ie. The effect of widely space propulsor on a catamaran.
CHALLENGES
Minimizing risk is another goal of this project. According to the recorded ferry accidents by the WSFA,
about 15% of all ferry accidents in Indonesia are related to collision [25]. The ongoing high risk that
exists in this region indicated that a minimum upgrade of maneuverability performance must be
attained over the propulsion systems and optimized as a commodity.
To avoid the dilemma of comparing and trading-off safety for costs benefits, it was known that the
maneuverability feature of motor-powered catamarans enables all five potential propulsion selections
and satisfies the minimum requirements for safe maneuvering. In fact, the ability to maneuver is vastly
increased due to the spacing of the propulsion units relative to mono-hull.
Commodity benefits of increasing maneuverability for the ROPAX ferry are:
minimizing the probability of small collisions that lead to increase maintenance costs
reduction in trip time due to faster docking and turnaround times
additional control at slow speeds while in harbor area (whereas rudders lose lift-force at slow
speeds)
The table below summarizes the computations performed to rank the four major propulsion
characteristics that affect the design goals.
For Propulsion
System
What was Compared Conclusion Major Assumptions
Affordability of
Propulsion
The cost of the
propulsion system to
the estimated cost of
the ship.
The propulsion system
is a big part of the
ship’s acquisition cost
if built in Indonesia
(about 30%)
The cost of different
propulsion can be
approximated linearly by
using parametric studies.
Fuel Efficiency
The net present day
value of fuel cost for
the lifetime of the ship
to the acquisition cost
of the ship
Fuel efficiency is
slightly more
important compared
to the ship’s
acquisition cost
The ship life is about 40
years
Cost of fuel remains
constant
The expect average
interest rate in 40 years is a
7.744%, the current rate
given by Indonesian
government for 10 year
bonds
Maneuverability The commodity
benefits of having
more maneuverability
than a catamaran with
twin-propellers such as
less down-time
Additional trip
performance and
safety features such
as better response
time is valued slightly
more than the
acquisition cost
15% calculated from World
Ferry Safety known data
The estimated payback
period for around 8 years
of a 40 year ship already
justifies the value or
affordability of the ferry
Maintenance/
Reliability
The effect of trading
off fuel efficiency for
up-time in net present
day value
The combined net
present value of
maintenance cost,
down-time and
revenue exceeds the
acquisition cost (see
section 18 for more)
Maintenance cost of our
ferry is assumed to be ¾
effect of Washington State
Ferry’s (WSF)’s cost
Washington State Ferry
(WSF) of ~$81.5/operating
hour
Fouling rates are higher in
Indonesia than in
Washington
Table 24: Propulsion Comparison Criteria
The evaluations in the table above is this transposed to index value as listed in the table below.
Table 25: Decision Indexes [26]
The pairwise comparison of propulsion system criteria outputs a criteria weight that ranks the
percentage of important out of 100%. The Consistency Ratio, a measure of the similarity of the
comparisons for the rows and columns, is found to be 1.7 %. Consistency Ratios are required to be
below 10% for AHP evaluations.
Table 26: Criteria Weight
Similar to pairwise comparison of criteria, four additional pairwise comparison of propulsion were
performed for each of the four criteria comparing the four different propulsion methods.
9.1.4. SUMMARY OF PROPULSOR COMPARISON Affordability
[$US/kW]
Fuel Efficiency
[compare to
conventional]
Maneuverability Maintenance/
Reliability
Outboard 1546
~15% less
By assuming a
number of gears
[27]
For hydraulic drive
~ 20% less [28]
Rotates at about
180 degrees per 12
seconds
[CITE SHOTTEL
SHEET]XXX
Can be lifted out
without dry-
docking
Modular, can be
swaps and
replaced quickly
Propulsor can be
hydraulically swung
out
L-drive 1304 One less gearbox
compared to Z-
drive (Outboard)
Cite *XXX*email
Likely the same
propulsor as the
outboard system
Likely between
outboard and
conventional in
terms of
serviceability
Voith Schneider 976
~25% less
Can almost
instantly change
thrust direction
“High maintenance
effort” according
to Voith [29] ;
Complex parts may
be expensive to
replace in
Indonesia
Conventional Require shaft
alignment, difficult
920 The reference
point in these
comparisons
Limited thrust
directions and
rudder loses lift-
force at slow
speeds
to access in
confined space;
taking apart entire
engine (commonly
done in Indonesia
as scheduled
maintenance [5]) is
a major task
Table 27: Summary of Propulsor Comparisons
EXPOUNDING ON THE PERFORMANCE INDEX OF PROPULSION SYSTEM
Performance Index of the propulsion system was assessed by calculating cost per kWh for each distinct
propulsion system. It was assumed that the cost per kWh of the propulsion systems can be reasonably
linearly interpolated. All of the propulsion systems above were evaluated as diesel engines. Since the
actual cost of propulsion units are proprietary and difficult to obtain, only one historic point was
establish for each of the four propulsion systems evaluated. The hydraulic outboard and L-drive unit
prices are quotes from Adam, a representative of the marine propulsion company -Thrustmaster. The
Voith Schneider propulsion cost was obtained from a budget approval request document for the Halifax
ferry in 2012 [5]. Conventional propulsion cost and characteristics were calculated from a science
vessel’s propulsion costs provided by Robert Allen; the dollars per kWh also closely matched Robert
Allen’s dollar per kWh rule of thumb for the cost of the conventional propulsion system.
EXPOUNDING ON THE MANEUVERAILITY OF PROPULSION SYSTEM
Differences in maneuverability for Z-drive and L-drive were assumed to be the same as they are both
azimuth propellers. Azimuth drives are much more maneuverable in wind conditions than conventional
shaft and rudder system but have a slight disadvantage in course keeping [6]. Voith Schneider
propulsion is “slightly” to “much better” than azimuth thrusters (Z and L-drives) as it can almost
instantly change the direction of thrust (thus faster crash stop), can be used for roll stabilization [7], and
is said to be much easier to learn. Conventional propulsion, in this case a twin-screw & rudder system, is
the least maneuverable of the four systems in terms of crash stopping and slow speed maneuverability.
Table 28: Propulsion Selection Overview
Combing all the weight tables above the following AHP decision was produced. Outboard propulsion is
ranked the most desirable propulsion method compared to the other three methods.
Table 29: Combined Weight Tables
This decision matrix should not be applied to other vessels as it was based on a custom scenario. Some
of the factors that effected the decision of this matrix include:
Service speed of 15 knots and length of ship of 55 m
Twin hull catamaran
Indonesia, an oil producing country with lower fuel costs
Steel RoPax Ferry carrying up to 40 vehicles and 185 passengers
Expected service life of around 40 years
Interest rates of about 7.74%
Low labor rates compare to North America
Region with high ferry accidents
Region with a trend of ship fire from engine and cargo
Ship assumed to be built in Indonesia
Tropical warm water climate
A fleet of these ferries can share the cost of spare propulsion units
Downtime mean loss in revenue and trust in ferry system
Downtime means additional cost of renting other service ships
THE IMPORTANCE OF MAINTENANCE IN THE SELECTION
A detailed cash flow analysis was done to compare outboard propulsion system with the conventional
twin-screw and rudder system. The conventional system is assumed to be 20% more efficient in terms of
fuel efficiency whereas the outboard unit is assumed to have an additional week of operations every
four month early in the ship’s life. The extra week is due to the scheduled dry-dock maintenance as seen
the Washington State ferry’s maintenance schedule [30]. The WSF ROPAX ferries are range in 5 to 40
years old and are good data points for early and late life maintenance rates. Older WSF ROPAX ferries
typical have a dry-docking time of one month in every four months (an assumption was made that the
limited four month maintenance schedule could be applied throughout the year). For our ferry designed
to use outboard propulsion system. It is designed that the propellers can be maintained without dry-
docking and any major engine problems or scheduled maintenance can be replace in a short period
without major interruptions to the ferry operations. The swapped out outboard unit is perceived to be
repair on land in the repair shop rather than onboard or in the dry dock.
In addition to opportunity costs of down-times, there is the cost of renting service ferries to substitute
the on-maintenance ferry. Assuming ship rentals are like car rentals, the owner will have to pay about
0.15% of the total ship’s original cost per day of rental.
To calculate the cost of operation and maintenance of the ship, an excel spreadsheet of the cash flow
table was constructed. The net present value, including ferry revenue, fuel cost, maintenance cost and
ship rental cost of the conventional and outboard propulsion systems are compared. The following
assumptions were made for the net present value calculations:
The ferry is assumed to be fully loaded with passengers and vehicles since overcrowding
problems means that capacity is less than demand
The ferry ticket rates are assumed to increase with the prevailing inflation rate of 6%
Cabin prices are assumed to be the same as a sedan ticket price
The interest rate for comparing future value remains the same, 7.744%
The outboard propulsion system is 20% less efficient than the conventional system; outboard
units probably do not increase as quickly since conventional engine systems are said to be
dismantled and replaced fairly often as ship ages in Indonesia [5]
Maintenance costs (which increase every year) are assumed to be the same for both systems;
this simplified the calculations as less variables need to be changed and further specific costs are
difficult to estimate.
The conventional system will have 1 week of dry-docking every 4 months T
The outboard scenario will have on-board inspections every four months and dry-docking yearly
during stormy seasons that are dangerous to operate in
When the ship reaches the age of 20, the conventional system scenario will increase its require
maintenance duration to 1 month of dry-docking every 4 months
The outboard propulsion system will require a purchase of a 1 to 2 outboard propulsion units at
after 5 and 20 years of service to keep up a steady supply of units for swap maintenance. The
cost of purchases are $500,000 US each time.
The net present value, payback period and rate of return results are as follows:
CONVENTIONAL PROPULSION
SYSTEM
OUTBOARD PROPULSION
SYSTEM
Net Present Value of 40
years of service at 100%
capacity
$ 16,555,000
$ 20,000,000
Payback Period
(not discounted)
100% Loaded
11.2 YEARS
11.2 YEARS
Payback Period
(not discounted)
at 90% capacity
13.8 YEARS
13.9 YEARS
Return on Investment
(ROI)
at 90% capacity
7.25%
7.20%
Table 30: ROI Comparisons
The results show that the trade-off is not significant. The cost of downtime due to maintenance is
comparable to fuel efficiency. Note that the conventional prolusion system has a slightly shorter
payback period even though it has a slightly less net present value. This is calculated by the simple
payback period which does not take into account future changes and discount rates.
Since both systems have a similar ROI, the outboard propulsion system rather than conventional
propulsion system has much higher present value. Other values not accounted for in the dollar values
are summarized below.
Having an outboard propulsion system that provides more uptime/reliability also suggests:
Better scheduled services for customers and a ferry system that can be trusted
More regular customers that use the ferry system rather than planes or cars
Reduction in safety risks of renting ferries to substitute for ferry downtimes
Better service to the community as an essential transport system - analogous to a bridge
Lower maintenance costs that were not accounted for in the calculations (maintenance cost
accounts for about ½ of the acquisition costs)
Open access to engines aids in the fight against engine fire
All the maneuverability benefits listed previously
OUTBOARD UNITS
Thrust master ODN 1500N and Schottel NAV 500 were compared and ultimately the NAV units were
chosen based on the following criteria:
Although the Thrust master unit is hydraulically driven with constant torque over a range of
speeds, we do not require high torque at low speeds.
The Thrust master power ratings do not match our estimated required power. The next size up
of power unit is much too heavy and expensive to seriously consider.
Schottel has over 50 years of production and is also advertised as a reliable and easy to maintain
propulsion unit.
When travelling at low speeds in harbor, 2 out of the 4 NAV 550 units could be used. In this way,
the engines would be run at their most fuel efficient loads.
One or even 2 engines could be disabled without the Ferry becoming stranded.
With 4 propellers, they will likely have access to cleaner flows as they can be placed out of the
hull shadow.
9.2. MACHINERY ARRANGEMENT
9.2.1. BLOCK DIAGRAM The machinery arrangement shown below is cropped closer to better show equipment locations.
FIGURE 43: MACHINERY ARRANGEMENT
9.2.2. ARRANGEMENT RATIONALE For a first order location estimates, block envelopes were used for each components. The arrangement
was largely based on placing items from the same systems close together. The catamaran hull and
separation of the main propulsion systems meant that some components had to be doubled up. For
example, with a tank in each hull, it makes sense to have a separate fuel pump, purifier, and day tank in
each hull. Other systems, like the bilge system, require having pumps in separate compartments. All
other things considered, reference ships were used when any further input was required.
9.3. ENDURANCE FUEL CALCULATION A require endurance of 1000 nautical miles is required by the owner. Using that average value fuel
consumption of 200g/kW-hour for the four Schottel engines and a diesel density of 0.832 kg/L, 49,000
liters of diesel fuel capacity is required for the required endurance. Further fuel capacity for hotel loads
such as lighting, laundry machine, air conditioning and control systems were not calculated in this
project due to resource constraints and focus on other systems.
10. SHIP ELECTRICAL SYSTEM For the purpose of this concept design, detailed electric load analysis is not included due to the limited
time constraint. A first order estimation was done to provide an approximation on the generator
selection mainly based on parametric studies and empirical equations for major electric load usage, as
discussed in the following sections. A complete electric load analysis for the vessel is therefore required
to be conducted in the future design iterations.
10.1. ELECTRIC PLANT DESCRIPTION
10.2. GENERATOR SIZING AND SELECTION RATIONALE One of the major electric loads came from the HAVC systems provided for passenger enclosed-spaces as
per owner’s requirement. The equation from [31] provides first-order electrical power estimation of Air
Conditioning system. The preliminary estimate of the required power for air conditioning was calculated
simply based off the vessel displacement using the equations as shown below.
Figure 44: AC Power Estimate
Based on our parametric study, the maximum total electric load was estimated to be around 450kW for
the vessel in the fully-loaded cruising condition.
10.3. ELECTRIC PLANT BLOCK DIAGRAM
Displacement 996 tonnes
AC BTU 1646835 BTU
AC power 275 kW
Figure 45: Simplified Electric Diagram
11. SHIP AUXILIARY AND CONTROL SYSTEMS
11.1. DESCRIPTION OF SYSTEMS The following on ship systems are required for ship operations:
Fuel System
Cooling System
Electrical System
Black Water System
Grey Water System
Fire Fighting System
Bilge System
11.2. SIMPLIFIED BLOCK OR ONE-LINE DIAGRAMS The diagrams below represent simplified systems indicative of what systems on the ferry could look like.
They are not to scale and are missing all of the details, but they are the product of our musings about
catamaran systems and helped in the development of a machinery arrangement.
11.2.1. CONTROL SYSTEM The propulsion system and its control is entirely supplied by Schottel. In case of an emergency, the
Schottel NAV 550 units have local control panels that can be activated at any time.
Figure 46: Control System
11.2.2. BILGE/FIRE SYSTEM The fire pumps act as backup bilge pumps in this system. The fire hydrants in this diagram represent
sprinklers that would be regularly placed throughout the superstructure and hoses that would be
located on deck to fight cargo fires.
Figure 47: Bilge and Fi-Fi system
11.2.3. FUEL SYSTEMS The fuel transfer system allows for easy filling on either side of the ship, and then transfer from one tank
to the other via the transfer pumps. The day tanks are located above deck, close to the propulsion units
(900 L day tanks are included in the Schottel package).
Figure 48: Fuel Transfer System
Figure 49: Fuel Supply system
Figure 50: Lube Oil System
11.2.4. COOLING SYSTEM The cooling system for the generators could be a ‘box cooler’ type of system, where the cooler tubes
plug right into the sea chest, or more of a remote cooler configuration as shown below.
Figure 51: Cooling System
11.2.5. WATER SYSTEMS Water Systems include potable water, oily water, black water, and grey water. For simplicity, it would be
possible to combine the grey and black water tanks together. They grey water system would be similar
to the black water system except that it would receive water from showers and sinks instead of from
toilets.
Figure 52: Potable Water System
Figure 53: Oily Water System
Figure 54: Black Water System
12. WEIGHT ENGINEERING
12.1. MARGIN POLICY
12.1.1. MARGINS A 5% margin was applied to lightship weight. As dead weight was calculated based on a fully loaded,
‘worst case’ scenario, no margin was applied to deadweight.
12.1.2. ALLOWANCES Wherever possible, weights were based on supplier information. This could come in the form of a per
unit weight, per area weight, or per volume weight. When supplier information was not available, a
weight allowance was used, based on other ships through ratiocination. In a few cases, a more
unmotivated allowance was made based on expert advice. These weight allowances account for just a
little over 12 percent of the light ship weight. Items that use allowances include:
Item Allowance
Bow and Stern Quarter Ramps 15,000 kg
Fuel Service System 2,000 kg
Lube oil System 300 kg
Ship Service Power Cable 15,500 kg
Switchgear and Panels 5000 kg
Lighting 4000 kg
Command and Control Systems 2000 kg
Navigation Systems 750 kg
Interior Communications 450 kg
Exterior Communications 200 kg
Ventilation System 3000 kg
Machinery Ventilation 2000 kg
Air Conditioning 6800 kg
Refrigeration System 4000 kg
Fire main and flushing 3000 kg
Potable Water 2000 kg
Mooring and Towing 2000 kg
Hull designating and Marking 150 kg
Painting 8000 kg
Cathodic Protection 300 kg
Workshops and test areas 2000 kg
Store rooms 1000 kg
TOTAL 79,450 kg
Table 31: Weight Allowances
12.2. MASTER EQUIPMENT LIST
Table 32: Master Equipment List
Item Qty
Sea Chest 2
Fire pump 2
Bilge pump 4
Bilge manifold 2
Black Water pump 1
Sewage Vaccuum 1
Lube oil pump 2
Sludge pump 1
Oily water pump 2
Oily water separator 1
Freshwater filtration 1
Water pump 2
Hot water pump 2
Fuel transfer pump 2
Fuel pumps 2
Fuel oil purifier 2
Machinery space Fans 2
Gensets 2
Main Switchboard 1
Emergency Genset 1
Emergency Switchboard 1
Distribution panels 12
Battery Box 1
Air Conditioning Units 5
AC Fan Coil Units 20
Master Equipment List
12.3. WEIGHT & KG ESTIMATE The weight and KG estimate is shown here for both the fully loaded departure condition as well as the
unloaded arrival conditions. These two conditions most widely reflect the different operating trims of
the ferry. Since this design does not include ballast tanks, the trim has been calculated for each
condition. As a quick check, the depth of the transom has also been calculated. The analysis shows that
as the ship lightens, the transom comes out of the water. For our project, we deem this as acceptable
since the ship will almost always be travelling with a full load. For future iterations however, adding an
aft bilge tank should be considered.
Figure 55: Ship Coordinate System
Figure 56: Fully Loaded Weight
Coordinate System
Axis Reference Positive Input
Direction Units
LCG Bow Aft m
VCG Baseline upwards m
TCG Centreline Port m
Ship in fully loaded departure condition: With Cargo, Full Stores, fuel, and all passengers
Full Load Displacement Summary Weight
(MT) LCG VCG TCG L.Mom V.Mom T.Mom
Consumables
Fuel (98%) 39.2 32.1 1.6 0.0 1258 64.3 0.0
Potable Water (98%) 19.6 25.5 1.6 8.3 500 32.1 161.7
Passengers, Crew, and Stores
Passengers + Crew 12.0 25.0 10.9 0.0 300 130.8 0.0
Crew Stores (15 crew) 0.8 22.8 4.0 -6.5 17 3.0 -4.9
Passenger stores (185 pax) 2.8 30.6 9.5 0.0 85 26.4 0.0
Misc. Liquids
Grey Water (10%) 1.5 24.5 2.0 0.0 37 3.0 0.0
Black Water (10%) 0.6 22.7 2.0 9.7 14 1.2 5.8
Lube Oil (98%) 1.8 38.3 2.2 0.0 69 3.9 0.0
Used Oil (10%) 0.0 38.3 2.2 0.0 2 0.1 0.0
Sludge (10%) 0.1 38.9 2.2 0.0 4 0.2 0.0
Oily Water (10%) 0.5 38.3 1.9 0.0 19 0.9 0.0
Mission Load
Cars, x 34 57.8 25.2 6.5 0.0 1457 376 0.0
Trucks (Fully loaded) x 10 200.0 27.8 6.6 0.0 5560 1320 0.0
Total Deadweight 336.7 27.69 5.83 0.48 9321 1962 163
Estimated Lightship Weight 671.7 31.1 6.0 0.0 20902.6 4008.9 9.9
LCG VCG TCG
Estimated FULL LOAD DISPLACEMENT 1008.3 29.974 5.921 0.171 30223 5971 173
LCB VCB TCB
29.979 1.888 0.188
Figure 57: Operating Trim, Fully Loaded
Figure 58: Unloaded Weight
Operating Trim, fully loaded
𝛁 = 986.73 m 3
T_LCF = 2.85 m Draft at the LCF
Trim lever = -0.03 m = LCG - LCB
TM = -26.29 tonne*m aplied trimming moment
Trim = -1.27 cm If negative, Trim by the bow.
If positive, Trim by the stern
dTf = 0.00 m Change in Draft Aft
T_transom = 0.80 m Design Transom Draft
T_tran_new = 0.80 m Static transom draft at current LCG!
Unloaded condition, with No cargo, full # of passengers and luggage, but only 10% stores and fuel
Unloaded arrival Weight
(MT) LCG VCG TCG L.Mom V.Mom T.Mom
Consumables
Fuel (98%) 4.0 32.1 1.6 0.0 128.4 6.6 0.0
Potable Water (98%) 2.0 25.5 1.6 8.3 51.0 3.3 16.5
Passengers, Crew, and Stores
Passengers + Crew 12.0 25.0 10.9 0.0 300.0 130.8 0.0
Crew Stores (15 crew) 0.8 22.8 4.0 -6.5 17.1 3.0 -4.9
Passenger stores (185 pax) 2.8 30.6 9.5 0.0 84.9 26.4 0.0
Misc. Liquids
Grey Water (10%) 14.7 24.5 2.0 0.0 359.6 29.4 0.0
Black Water (10%) 5.9 22.7 2.0 9.7 133.2 11.8 56.7
Lube Oil (98%) 0.2 38.3 2.2 0.0 7.1 0.4 0.0
Used Oil (10%) 0.5 38.3 2.2 0.0 17.3 1.0 0.0
Sludge (10%) 0.9 38.9 2.2 0.0 36.2 2.0 0.0
Oily Water (10%) 4.9 38.3 1.9 0.0 187.9 9.2 0.0
Mission Load
Cars, x 34 0.0 25.2 6.5 0.0 0.0 0.0 0.0
Trucks (Fully loaded) x 10 0.0 27.8 6.6 0.0 0.0 0.0 0.0
Total Deadweight 48.6 3.93 0.66 0.20 1323 224 68
Estimated Lightship Weight 671.7 31.1 6.0 0.0 20902.6 4008.9 9.9
LCG VCG TCG
Estimated UNLOADED DISPLACEMENT 720.2 22.042 4.198 0.078 22225 4233 78
Figure 59: Operating Trim in the Unloaded Condition
13. COST ESTIMATE Ship building cost was estimated in two ways, the Product-Oriented Design and Construction (PODAC)
cost model as well as the Parametric Cost Analysis using second hand ships prices on the market.
13.1. ESTIMATE OF ACQUISITION COST The table below compares the estimated acquisition cost by two methods.
Estimation Method
Bid Cost in USD, 2016
Parametric Cost Estimate $ 7,580,000
PODAC (1996) Cost Estimate $ 11,960,000
Table 33: Cost Estimate Comparison
13.1.1. PODAC COST ESTIMATE METHODOLOGY & ASSUMPTIONS The labor and material cost of the Ship Work Breakdown Structure (SWBS) groups 100 to 600 were
estimated using the Product-Oriented Design and Construction (PODAC) preliminary cost model. The
table below is extracted from the PODAC document [1] which contains the formulas to be used. By
applying these formulas, it is assumed that the prices of steel, manufacturing technologies, and methods
in Indonesia today are similar to those estimated in 1996. Since Indonesia is a developing country and
the shipbuilding industry is considered rather conservative, it is the assumptions seems to be a
reasonable.
Table 34: Cost Estimating Relationship Breakdown
Operating Trim, unloaded
𝛁 = 704.80 m 3
T_LCF = 2.04 m Draft at the LCF
Trim lever = -7.96 m = LCG - LCB
TM = -5731.67 tonne*m aplied trimming moment
Trim = -277.11 cm If negative, Trim by the bow.
If positive, Trim by the stern
dTf = -1.09 m Change in Draft Aft
T_transom = 0.80 m Design Transom Draft
T_tran_new = -0.29 m Static transom draft at current LCG!
Inputs Source
Ship Type Factor
1.25 From PODAC tables
Size Factor (SF)
2.31 = 32.47 x DISPL^(-0.3792)
Complexity Factor (CF)
2.89 = Ship Type Factor x Complexity Factor
Table 35: PODAC Results
“Ship Type Factor” for a ROPAX ferry in particular was not exactly available in the tables. From the three
similar ship types: Roll-on Roll-off Vessel, Ferry and Passenger Ship. The “Ferry” ship type was chosen as
it describes our ship and has values between the two. The table below summarize the values obtained
for the labor and material costs.
Table 36: Cost Estimation Rates
Using the assumed rates above, the ship costs were computed and tabulated in the following tables. An
interesting point is that the magnitude of the propulsion and electrical systems cost is about 63% of
total SWBS material cost, and as much as 43% of the grand total cost.
Table 37: PODAC Based Cost Breakdown
Table 38: PODAC Cost Estimate Results
The bid price from 1996 was projected to 2016 dollar value by using an average inflation rate of 2.1%.
13.1.2. PARAMETRIC COST ESTIMATE METHODOLOGY AND ASSUMPTIONS A method used to check whether the PODAC cost estimate of our ferry is affordable is to compare
second-hand ferry market prices. Price data was collected from used ferries because their prices were
easily accessible. Furthermore, because developing countries tend to buy more second hand ferries, it is
assumed to be a reasonable estimate for the owner’s minimal expected value of a ferry. The following
steps detail the calculations:
To compare all of the nine ROPAX ferries found on the market with lengths ranging from 37 m to 89 m
and speeds ranging from 10 knots to 18.5 knots, the following assumptions where made:
1. The key parameters of value are the capacity of people and vehicles
2. Cabins and vehicle capacities are worth 10 times more than a passenger seat space (this is based
on the calculated ticket price per area). Hallways and washroom areas for passengers were also
roughly accounted for as passenger area.
3. A ferry’s depreciation lifespan is around 22 years after which depreciation it no longer
depreciates and has a fixed salvage value
Table 39: Ticket Prices in the Operating Region
The following plot shows the Salvage Value (the value of a ship after full ~ 22 years of depreciation) vs
“Capacity Value” (a made-up term that relates the values of the space of cabins, cars and passengers)
Figure 60: Capacity Value vs Salvage Price
It is noted that the salvage prices of ROPAX ferries are relatively consistent between “capacity values” of
400 to 1200. The potential designs of this ferry also fit within this range of consistency. A closer look at
this range is in the table below.
Figure 61: Area Value for various Ferries
Assuming that ships retain a salvage value of 20% of the new build price [2], then the new build prices
for the seven ships older than twenty one years of age are as follows in yellow in figure 18.3-5. The
orange and grey data points are ferries that are less than twenty-two years old and have not full
depreciated.
Figure 62: Ship Depreciation
Figure 63: Capacity Value
Suppose that our ROPAX ferry were to carry 180 passenger, 20 cabins and 50 cars (sedans), the
“capacity value” would be;
Capacity Value = 180 + (50+20)*10 = 880
Using the linear curve fit equation of the new-build prices scaled up from salvage value price, the new-
build price is estimated to be:
New-Build Price = 6158.9*(880) - 381712 = $ 5,038,000.00 USD (22 years ago)
Then, taking inflation rates into account and assuming an inflation rate of 2.1% from the USA applies,
the purchase price of a mono-hull (since that data points were mainly mono-hull) ferry of this capacity is
around $7,580,000 US. Philip Koenig, Director of NAVSEA, commented that the idea of using salvage
price to estimate the price of a new-build ship price was doubtful because salvage prices fluctuates with
the market demand; nevertheless, the rough order of magnitude cost estimate was valuable in
comparing acquisition affordability.
An interesting data point found that helps gauge the affordability of our vessel was from a ferry
operator’s new sections. ASDP, an Indonesian ferry company, announced the procurement of five
passenger ferries of 2000 GT at $10,000,000 each [2]. Since our vessel’s gross tonnage was estimated to
be about 1800 GT, our vessel’s acquisition affordability can be compared to an Indonesia ferry operator
company.
The parametric cost estimate and future vessel procurement announcement affirms that cost estimated
from PODAC is likely to be within a reasonable price tag called affordable at acquisition.
13.2. ESTIMATE OF OPERATING COST Operating costs included in the estimate are:
1. Fuel Cost
2. Maintenance Cost
3. Crew Cost
4. Moorage Cost
5. Merchandise Cost
The table below summaries the methodology and costs per year of these expenses.
Cost (USD) Method Inputs
Fuel Cost
810,900
Utilized the CAT ACERT 32 engine’s fuel consumption rate and estimated trips per year to compute the fuel cost
USD 0.68 / liter of diesel as of date
CAT ACERT 32 consumes on average 200g/kWh
Assumed ship travels at designed speed, 15 knots
Maintenance Cost
166,870
Based on operational hours, Washington State Ferry’s (WSF) maintenance average and labor rates.
WSF estimates their maintenance rates to be USD 81.5/hour [32]
Since Indonesia has lower labor rates, the cost per hour was assumed to be 25% less
Crew Cost
155,000
Used labor rate cost estimate similar to shipyard cost estimate for a crew of twelve.
Crew was assumed to have a decent pay of USD 1.75 /hour with an 85% overhead rate to
account for miscellaneous ship expenses such as lighting
Administration/ Moorage Cost
77,500
Other unaccounted expense may include cost of using ports, and offices for the ferry operator. These costs were assumed to scale with maintenance costs as man-hours and operational hours are likely the main inputs
Based on BC Ferry Expense chart, their Administration costs is about half of the magnitude of the maintenance cost. [33]
Retail Goods Sold 6,680
A function of the number of good sold and the mark-up rate of the goods
Assumed:
A quarter of the passengers will spend a quarter of the value of their ticket price to buy refreshments or groceries
Mark-up rate of 200% like vending machines
Table 40: Operating Cost Breakdown
Figure 64: Annual Expense Pie Chart
13.3. ESTIMATE OF REVENUE Revenue of the ROPAX ferry was calculated using the designed ship capacity and ticket rates from table
18.3-1. A full load capacity was assumed because the issue of overcrowding, overloading, and long line
up queues suggest that demands currently exceed the capacity of passengers at this time. The yearly
revenue break-down results are tabulated in tables XX5-3. An inflation rate of 6% (based on 2000 to
2015 average) and 7.744% interest rate (based on government 10 year bond) was assumed in the cash
flow analyses.
Table 41: Trips and Ticket Prices
Table 42: Gross Revenue per Stop at 100% Capacity
Table 43: Total Revenue per Year
The performance of this investment, the ferry, is calculated using the cash flow analysis consisting of the
acquisition cost, annual revenue and future equipment purchase expenses. It was assumed that by
investing in spare propulsion units (estimated to be USD 250,000 each), the ship can transfer most of its
dry-dock maintenance to a repair shop at scheduled maintenance times. This maintenance plan is to
help increase operational time. The purchases in spare propulsion systems are assumed to happen at
year 5 and 20 of the vessel’s life when the vessel begins to require more maintenance. The full cash flow
is shown in table 18.5-6 and the summary of the investment performance in various performance
parameters are listed below. The salvage value was neglected for a conservative estimate.
Investment Performance Indicators
Net Present Value $20,017,050
Internal Rate of Return 14.76%
Return on Investment 9%
Simple Payback Period 11.19 years
Discounted Payback Period 13 years
Table 44: Investment Metrics
Table 18.5-5 below shows the non-ideal case where only 80% of the ship is full; the ship still has a
decent payback period of 19.3 years. At 67% load capacity, the ferry can just manage to pay itself back in
40 years if everything else remains the same. An audience during our final project presentation at UBC
pointed out that some ferry operators have revenue deficits and are government reimbursed. Perhaps
simply having an essential transportation that can pay itself back over its lifecycle is already considered
outstanding.
Table 45: Revenue at Reduced Capacity
14. TECHNICAL RISK ASSESSMENT An attempt was made to manage technical risk at the outset of the project by defining stakeholders and
team-mate roles and expectations. From there, requirements were collected and a work breakdown
structure was roughed out.
To begin the project, we made a Project Proposal using a standard template. For our project, this
proposal acts as the project charter, formally opening the project. It defines the name of the project
(Savu Sea ROPAX Ferry), the main stakeholder (Ferry Safety Association), our sponsor (Chris McKesson),
and our advisor (Robert Allan). It also touches on cost constraints and completion dates. Although we
did not formally obtain signatures on this document, our stakeholders, sponsor, and advisor all accepted
the project implicitly through their continued support.
Stakeholders are any individual or organization who may affect or be affected by the outcome of the
project (PMBOK pg 30). Some stakeholders influence the project (ie. Through expectations), such as our
professor Chris Mckesson, or the World Ferry Safety Organization. However, in our case, the people of
the Savu Sea are our “Unaware” stakeholder. Although they do not provide direct influence, we must
act on their behalf to predict their needs, and make a concerted effort to reach out and discover their
needs.
Stakeholder engagement is critical to success. From PMBOK, pg 403: C denotes current Engagement, D
indicates desired engagement. The size and structure of this project is simple, but it is apparent that
although difficult because of the distance and language barrier, it would be valuable to engage the end
users, the people of Indonesia.
Stakeholder Unaware Resistant Neutral Supportive Leading
Chris McKesson C,D
Rob Allan C,D
Ferry Safety As. C,D
End Users C D
With a project charter and stakeholders identified, we start to collect requirements. Many requirements
are laid out in the terms of reference provided by the World Ferry Safety Association, and are tabulated
in the appendix. Each requirement could further categorized by one of the following evaluation criteria,
taken from the terms of reference:
Safety (Fire safety is specified)
Affordability
Responsiveness
Inventiveness
Conceptual level design
Opportunities for Implementation (Whether Indonesians look favorably on the design and want
to build it)
Ease of repair
Our Scope initially had two distinct phases. The first was purely to meet the deliverables required by the
World Ferry Safety Organization. The second phase will took the form of a massive scope change after
the March 15 competition deadline to gear up to meet requirements for the NAME 591 report. Because
of unexpected project difficulties, the March 15 deadline was not met, which removed the need to have
a stepped scope.
The following describes some of the project management document used during the course of the
project. Most of them were initiated and assigned to a team-member to update, but most fell away as
team-mates preferred to have impromptu meetings and informally define their short term scope of
work, instead of formally recording progress.
Project Proposal: The proposal formally initiates the project, describing roles, deadlines,
sponsorship, and stakeholders.
Scope Spreadsheet: The spreadsheet includes all the scope definition inputs such as
requirements documentation, KPP’s, evaluation criteria, deliverables, RACI (acting as a WBS for
deliverables), assumptions, and the scope statement.
Rail Spreadsheet: This spreadsheet acts as the activity list for the project. This document is will
be updated at every project meeting by the project manager to ensure activities are done on
time.
Gantt chart: This chart acts as a top level schedule. An example of it is shown in the Appendix.
Risk Register: This spreadsheet contains all the identified risks or opportunities, like a SWOT
analysis spreadsheet, and serves to trouble shoot potential problems before they happen.
15. ISSUES REMAINING FOR NEXT PHASE With many of the major strokes of this design worked out, the next phase includes research into some
of the larger unknowns of this design to confirm feasibility.
Further research into the sea state and ship motions is required to confirm the tunnel height
and freeboard.
Improvements and fairing of the hull to improve its manufacturability and seakeeping
Work is required to hash out more detail on the fore and aft ramps and to improve compatibility
with current ferry ramps in the area of operation.
Another detailed pass on the arrangements to:
o Develop an evacuation plan and further meet SOLAS and FSS regulatory requirements
o Improve the flow of traffic on the main deck.
o Add allowances for bulkheads, piping, and wiring
Another detailed pass on weights to:
o Save weight on the structure
o Further refine the weight estimate
Complete a probabilistic damage assessment to confirm deterministic results.
16. CONCLUSIONS A new concept for a medium speed steel catamaran for Indonesia has been developed. This concept
deviates considerably from current ferries operating in the region, putting into question the enterprise
decisions that ferry operators in the region have taken. If safety and affordability are truly important to
the region, this report has shown that a steel catamaran ferry with outboard motors warrants another
look. Further work is required to paint in more details to prove out the concept.
17. REFERENCES
[1] "Notice of Competition 2015," WSFA, 2015.
[2] A. S. G. a. R. E. Weisbrod, "Trends, Causal Analysis, and Recommendations from 14 Years of Ferry
Accidents," 2016.
[3] "East Nusa Tenggara".
[4] "Transportation of Goods in East Nusa Tenggara: Problems and Costs," LPEM-FEUI and the Asia
Foundation, Jakarta, Indonesia, 2010.
[5] Liputan, "Si Tua yang Setia Seberangi Selat Sunda".
[6] J. Hemgard, "(mt) The Changing Ferry," SNAME, 2015.
[7] T. S. Sutulo, "Maritime Engineering and Technology," p. 233.
[8] "Indonesia Ferry Terminal in East Java and Bali Islands Urgent Rehabilitation Project," 2000.
[9] "The Mitre Corporation," [Online]. Available: http://www.mitre.org/publications/systems-
engineering-guide/se-lifecycle-building-blocks/concept-development/concept-of-operations.
[Accessed 2 Feb 2016].
[10] WSFA, "Student'Design'Competition' Safe Affordable Ferries 2015," 2015.
[11] G. Davidson, "Maximising Efficiency and Minimising Cost in High Speed Craft," in 11th International
Conference on Fast Sea Transportation, Honolulu, Hawaii, 2011.
[12] G. Yee and N. Din, "Clyde & Co," 4 March 2015. [Online]. Available:
http://www.clydeco.com/insight/updates/view/cabotage-and-its-impact-in-indonesia. [Accessed
15 04 2016].
[13] M. Haase and G. Davidson, "A Practical Design Approach and RANSE-based Resistance for Medium-
speed Catamarans," Australian maritime College, Tasmania, 2012.
[14] C. McKesson, "The Practical Design of AMV," US Office of Naval Research, New Orleans, 2009.
[15] M. Haase, J. Binns, T. Giles and N. Bose, "On the macro hydrodynamic design of highly efficient
medium-speed catamarans with minimum resistance," The International Jounral of maritime
Engineering, vol. September, 2012.
[16] A. Molland, W. J.F. and C. P.R., "Resistance Experimenets on a Systematic SEries of High Speed
Displacement Catamaran Forms: Variation of Length-Displacement Ratio and Breadth-Draught
Ratio," University of Southampton, 1994.
[17] H. Erichsen, "Small Ro/Pax Vessel Stability Study," in WMTC, 2015.
[18] P. Sahoo, M. Salas and A. Schwetz, "Practical evaluation of resistance of high-speed Catamaran hull
forms," Ships and Offshore Structures, pp. 307-324, 2007.
[19] X. Pham, K. Kantimahanthi and P. Sahoo, "Wave Resistance Prediction of Hard-Chine Catamarans
through Regression Analysis," Australian Maritime College, Launceston, Australia, 2006.
[20] J. Zips, "Numerical Resistance Prediction based on the Results of the VWS Hard Chine Catamaran
Hull Series '89," in FAST 95: Third International Conference on Fast Sea Transportation, Lubeck-
Travemunde, Germany, 1995.
[21] J. Knox, "Ferries," in Ship Design and Construction, Vol II, SNAME, 2004, pp. 38-7.
[22] N. McCulloch, "Asia Foundation," 23 April 2008. [Online]. Available: http://asiafoundation.org/in-
asia/2008/04/23/in-indonesia-keeping-trucks-moving/. [Accessed 16 February 2016].
[23] Freight Link Solutions, "Freightlink," 16 10 2014. [Online]. Available:
https://www.freightlink.co.uk/knowledge/articles/securing-load-ferry-winter. [Accessed 12 04 16].
[24] "Technical Specifications-Shottel Navigator-Type Nav550 Offshore," Shottel, 2016.
[25] A. Golden, "Ferry Fatalities MFA," 2015.
[26] "Geographic Information Technology Training Alliance - Weighting by Pairwise Comparision," 2013.
[Online]. Available: http://www.gitta.info/Suitability/en/html/Normalisatio_learningObject3.html.
[27] E. M. G. Parson, in Introduction to Marine Engineering, 2015, pp. Section 11-7.
[28] "Beta Marine Hydraulic Propulsion," [Online]. Available: http://betamarine.co.uk/portfolio-
item/hydraulic-propulsion/. [Accessed 2016].
[29] I. B. Dirk J, "Voith Turbo - Offshore Supply Vessels".
[30] "erry Service Impacts and Schedule Adjustments," Washington, 2016.
[31] D. Gerr, "BOAT MECHANICAL SYSTEMS HANDBOOK," International Marine/McGraw Hill, 2009.
[32] "Passenger-only Ferry Cost Analysis," Bellevue, 2006.
[33] "BCFS_AnnualReport_14_15," 2015.
18. APPENDICES
18.1. APPENDIX: PROJECT PLANNING DOCUMENTS FOR THIS PROJECT
RACI R - Responsible, A - Accountable, C - Consult, I - Inform
Template Activity Description Shaun Tim Gabriel
9 Project scope, mission, CONOPS, Parameters and KPP's I R A
11 Hull form and Hydro, Body Plan, hydrostatics and stability I I R
11.3 Hydrostatics and Stability, Intact Stability calcs I R A
11.4 Hydrodynamics: Resistance and Powering, ship motions, ship maneuverability R
12 Ship Arrangement and drawing I R
13 Ship Structure, loading cases, structural calculation R I
14 Ship Propulsion, machinery plant description, machinery arrangement A R
15 Ship electrical system, generator sizing, electric load estimate R I
16 Auxiliary and Control systems, Aux system diagrams R I
17 Weight Engineering (Weight estimate), master equipment list, KG estimate A R I
18 Cost Estimate, build strategy, cost through lifecycle R I
23.1 Project Planning documents, technical risk assessment R I R
23.1 Electric Plant Calculations R I
23.12 Areas and Volumes I R
23.4 Lines Plan and Renderings I R
23.6 Damaged Stability Calculations R I
23.7 Resistance Calculations I R
23.9 Propeller Calculations R
Names
A list of stakeholder requirements taken from the Terms of reference. These are used to drive scope and activities
Item # Requirement KPPs Scope Analysis Related Deliverable
1Ship must be safe to operate in the
conditions of the weather and
waterway – further specified
below.
Design is to be verified to meet specific
weather requirements, and will be
built according to Lloyd’s Register Rules
and Regulations as well as applicable
IMO conventions (SOLAS, MARPOL)
Scope should emphasize
seakeeping, weather, research
into he Indonesian waterway, as
well as class compliance Life-saving plans
2Ship must have a draft restriction
of 6 meters due to the depth of
some wharves.
The design will have a maximum draft
less then 6m, with a margin, possibly
4m
Keep draft restriction in mind
during hull sizing, this is a key
part of initial sizing and
parametrics. Table of particulars, GA
3Ship must be safe to operate in
wind speeds of up to 30 knots that
change direction seasonally:
Direction of wind NW and SE.
Consider wind resistance in powering
analysis as well as wind heeling
moment into the stability analysis. The
seasonal nature of the weather in this
region is to be studied for potential
impacts on the design.
Scope should, again, emphasisze
research into the waterway and
weather of the Savu Region to
determine impact on ship
(Seakeeping) Intact stability estimates
4Sea characteristics: Swells up to 2-
4m height, and 4-5 meters in
length.
Ensure ferry can operate safely within
sea state 4 to sea state 5, design to
International code on intact stability
(IS)
Scope needs to include
seakeeping and class compliance,
research into the region Intact stability estimates
5 Ship must be able to safely travel
in the day and overnight
Must have appropriate navigation
systems and lighting for overnight
travel.
Scope must include 24h
navigation Life-saving plans
6If alongside berthing, the vessel
length should not exceed 50m.
The maximum ship length should
probably not be much more than 50. A
survey of the ship berths will be
completed.
Scope must include both a local
survey of berths and a complete
parametric analysis.
Ship's particulars, outboard
profile, GA
7Fire safety must be carefully
addressed in the design.
Fire hazards will be mitigated according
to SOLAS. Look at the possibility of
having an open deck.
Scope must have a huge emphasis
on compliance to SOLAS as well as
a clear plan in place for fires. Life-saving plans
8 The ship must have a maximum
capacity of 185 with a crew of 15
Parametric analysis a part of
scope, as well as economic
analysis. GA
9Affordable to construct, acquire,
operate, maintain, and repair
Scope to include life-cycle costing
analysis. Cost estimates
10
The ship must have 20 cabins of
mixed configuration 2 and 4 bunks
each.
10 cabins with 4 bunks, 10 cabins with 2
bunks made to at least comply with
MLC 2006
Scope to include GA and
parametric analysis.
GA, cost estimates,
structural midship
11The ship must seat between 70
and 160 passengers
Scope to include GA and
parametric analysis. GA, cost estimates
15
All passenger compartments shall
be fitted with A/C. Also include all
standard customer comforts such
as toilets and showers. Include a
shop for groceries and soft drinks,
as well as a storage area for this
shop.
The ship will be designed according to
MLC 2006 for crew and passenger living
areas. The revenue from the shop
should be included in the cost analysis.
Include A/C for all compartments in the
electrical load analysis.
Scope to include GA, cost, and
electrical load analysis.
GA, cost estimates, speed-
power estimates
16Maximize the # of vehicles that the
ship can carry.
Maximize the deck area, and maximize
the possible Ro-Ro DWT in the design.
Scope to include a deadweight
calculation, and parametric
analysis to try to maximize
vehicle space GA, cost estimates
18
There must be Bow and Stern
loading for passengers and
vehicles, side loading for
passengers is acceptable. All ports
are equipped with moveable
ramps.
Scope to include a survey of the
region, assumptions made for
ramps, and how this influences
ferry dimensions.
19 The ship must be designed with a
design speed from 14 to 18 knots.
Design speed from 14 to 16 knots. Max
speed about 18 knots.
Scope to include parametric
analysis.
Speed-power estimates,
machinery arrangement
plans
21
Specific crew spaces are required.
(7 cabins, 4 single beds, 2 double
beds, 1 with 4 beds). Galley, mess
room, storage space,
toilets/showers
Include all required spaces, designed to
minimum requirements of MLC 2006,
include all spaces in a parametric
analysis.
Scope to include thorough
parametric analysis and class
compliance.
GA, outboard profile,
structural midship
Evaluation Criteria of the project, defined, with possible action items relating to the scope
Item Definition Scope Analysis Possible Actions
Safety
Safeguard loss of
life
Project scope should emphasis safety, including (but
not limited to) a complete safety analysis including
safety equipment list, plan and rationale for fire safety,
passenger evacuation plan, plan for securing vehicles,
and definition of compliance with SOLAS.
Research SOLAS. Use Lloyd's search
tool
Affordability and
Cost Analysis
Low cost across
lifecycle
Project Scope should include a comprehensive cost
analysis, including costs to construct, acquire, operate,
maintain, and repair.
Research how to do costing. Use
past student projects, similar ships,
SDAC (lamb), other references
Responsiveness Maneuverability
Scope should address maneuverability of the ship
quantitatively, with Lloyd's compliance Research what maneuverability is.
Inventiveness
Creative solutions
imbedded in the
design
Scope statement should describe an inventive solution
as being a key part of the project, and one that our
sponsor can provide insight into.
He probably already knows, but
mention this requirement to our
sponsor.
Conceptual
Design approach
Design at the right
depth; Even-
handed focus across
topics
Scope statement should describe the design as being
conceptual in nature, enough information to be able to
create interest in the design but not comprehensive
research into any area. Assumptions will have to be
made and clearly documented to save time.
Create a clear Scope statement and
a well defined WBS with
responsibilities mapped out. All
deliverales should be rudimentary
I nature.
Opportunities for
Implementation
Indonesian interest
in furthering the
design
The scope should lightly address finding some
connection with our Indonesian stakeholders, or at
least find some information to tailor the project to the
Savu sea, thus making it more attractive for actual
implementation.
Send out feelers (emails) to
possible Indonesian contacts.
Easy to Repair
and maintain
Limited repair
facilities available.
Project scope and scope statement should include an
emphasis on making the design easy to maintain and
repair across the ship. [Steel favored as a possible hull
material; Provide plenty of head clearance in machinery
spaces; Specify non-specialized mechanical and
electrical equipment.]
Create a list of how this was done
in example projects, both student
and commercial. Mention this to
our sponsor.
18.2. APPENDIX: RENDERINGS
18.3. APPENDIX: GENERAL ARRANGEMENT DRAWINGS
18.4. APPENDIX: LINES PLAN
18.5. APPENDIX: INTACT STABILITY CALCULATIONS
SEVERE WIND AND ROLLING CRITERION
P = 504 Pa Given
A = 544.72 m2 From GA
Z = 6.96 m From GA
Δ = 1008.3 tonnes @ the full load condition
g = 9.81 m/s^2
lw1 = 0.193 m Righting arm from a 504Pa wind
lw2 = 0.290 m
CB = 0.524
LWL = 52.493 m Waterline length
KG = 5.921 m @ the fully loaded condition
Draft = 2.85 m @ the fully loaded Draft
B = 23.476 m Moulded breadth of the ship
d = 2.81 m Moulded draft of the ship
B/d = 8.354 m
GM = 39.127 m Corrected for FSE
C = 0.543
T = 4.073 s Estimate of Rolling period
s = 0.100 We're out of the chart, our period is very short
OG = 3.111
r = 1.394
Ship in fully loaded departure condition: With Cargo, Full Stores, fuel, and all passengers
Full Load Displacement Summary Weight
(MT) LCG VCG TCG L.Mom V.Mom T.Mom
Total Deadweight 336.7 27.69 5.83 0.48 9321 1962 163
Estimated Lightship Weight 671.7 31.1 6.0 0.0 20902.6 4008.9 9.9
LCG VCG TCG
Estimated FULL LOAD DISPLACEMENT 1008.3 29.974 5.921 0.171 30223 5971 173
LCB VCB TCB
29.979 1.888 0.188
Trim Angle = 0.075 deg
LWL = 52.500 m
Trim = 0.069 m
Draft = 2.845 m
GM0 = 39.410 m
FSE = 0.283 m
GM1 = 39.127 m Corrected for FSE
X1 = 0.800 From the table, but we're off the chart.
X2 = 0.854 From a table, depending on Cb, interpolated
k = 0.700 For a ship with sharp bilges
φ0 = 0.03951712 degrees Interpolated from full load heeling results
φ1 = = 109 x k x X1 x X2 X sqrt(r x s)
19.46 degrees =
φ2 = 50 degrees = 0.873
ang of flooding, or 50 degrees, whichever less
φ0 - φ1 = -19.42 degrees = -0.34 rad -7 m
Angle at lw2 17 deg = 0.297 rad
Considering all passengers on the roof at once:
Lever Arm = 11.25 m
All passengers = 300
Weight, each = 75 kg
Total weight = 22500 kg
Heeling moment = 253125
Max Heeling arm = 0.25 m
Angle of heel with respect to turning:
v0 = 7.72 m/s service speed
LWL = 52.5 m
Displacement = 1008 tonnes
KG = 6.20 m Corrected for FSE
d = 2.81 m mean draft
MR = 1098 kNm
max heeling arm = 0.111 m
Worst case heeling arm:
Crowding + turning + wind gusts = 0.652 m
Stability Criteria - IS 2008, Open Water Criteria for Fully loaded departure
Name Angle 1 Angle 2 Required Actual Pass / Fail
GM At 0 > 0.15 meters 0 0.15 39.4186 Pass
GZ At 30 >= 0.2 meters 30 0.2 6.3479 Pass
Angle At GZmax > 25 deg 14.5197 25 14.5197 Fail
Area Between 0 and 30 > 3.15 meters-deg 0 30 3.15 175.2671 Pass
Area Between 0 and Flood > 5.15 meters-deg 0 22.6871 5.15 126.253 Pass
Area Between 30 and 40 > 1.72 meters-deg 30 40 1.72 57.8432 Pass
Stability Criteria - IS 2008, Severe Wind and Rolling_lw1, Wind Heeling_lw1
Name Angle 1 Angle 2 Required Actual Pass / Fail
Angle At SteadyEquil < 16 deg 0.032 16 0.032 Pass
Stability Criteria - IS 2008, Severe Wind and Rolling, lw2, Wind Heeling_lw2
Name Angle 1 Angle 2 Required Actual Pass / Fail
ResRatio Between SteadyEquil-19.45 deg and
50 >= 1
-19.277 50 1 2.6217 Pass
Stability Criteria - IS 2008, Passenger Crowding, Roof Overcrowding
Name Angle 1 Angle 2 Required Actual Pass / Fail
Angle At SteadyEquil <= 15 deg 0.1148 15 0.1148 Pass
Stability Criteria - IS 2008, Turning Criteria, Turning moment
Name Angle 1 Angle 2 Required Actual Pass / Fail
Angle At SteadyEquil <= 10 deg 0.1875 10 0.1875 Pass
Stability Criteria - IS 2008, Combined Wind + Overcrowding + turning, Combined Arms
Name Angle 1 Angle 2 Required Actual Pass / Fail
Angle At SteadyEquil <= 10 deg 0.6992 10 0.6992 Pass
USING SIMPSON’S RULE TO CORROBORATE ORCA RESULTS
step = 0.01
7 rads
0 to 40 0 to 30 30 to 40 Ar. b vs Ar. A
Heel Trim Righting Moment Heel
Righting Arm SM
SM*arm SM
SM*arm SM
SM*arm
SM
SM*arm
(deg)
(deg) (kgf-m) [rad] (m)
-40 1.28 -5022656 -0.70 -5.0
-39 1.26 -5143942 -0.68 -5.1
-38 1.23 -5263302 -0.66 -5.2
-37 1.21 -5380630 -0.65 -5.3
-36 1.18 -5496101 -0.63 -5.5
0.1.FULLY LOADED CONDITION
Area under the GZ curve not to be less than:
0.055 meter-radians up to 30 Deg angle of heel
Area from 0 to 30 = 3.102 >0.055 PASS
0.09 meter-radians up to 40 deg, or angle of downflooding
Area from 0 to 40 = 4.120 >0.09 PASS
Area under the GZ curve between 30 and 40, or 30 and downflooding angle
… shall not be less than 0.03 meter radians
Area, 30 to 40 = 1.018 >0.03 PASS
GZ shall be at least 0.2 m at an angle of heel equal to or greater than 30 deg
GZ @ 30 deg = 6.391 >0.2 PASS
The maximum righting lever shall occur at an angle of heel not less than 25 deg
*** This is not practical for our ship, see high speed craft code
Initial metacentric height GMo shall not be less than 0.15 m
Initial GM = 39.17m > 0.15m PASS
Max GZ is: 7.699 m
Which occurs at: 14.000 deg
-8.0
-6.0
-4.0
-2.0
0.0
2.0
4.0
6.0
8.0
-20 -15 -10 -5 0 5 10 15 20 25 30 35 40GZ (
m)
Heel (Degrees)
Righting Arm (m)
-35 1.16 -5609654 -0.61 -5.6
-34 1.13 -5720890 -0.59 -5.7
-33 1.11 -5830482 -0.58 -5.8
-32 1.09 -5937387 -0.56 -5.9
-31 1.06 -6042685 -0.54 -6.0
-30 1.04 -6145202 -0.52 -6.1
-29 1.02 -6245162 -0.51 -6.2
-28 1.00 -6342918 -0.49 -6.3
-27 0.98 -6437980 -0.47 -6.4
-26 0.97 -6530367 -0.45 -6.5
-25 0.95 -6620213 -0.44 -6.6
-24 0.94 -6707517 -0.42 -6.7
-23 0.93 -6792212 -0.40 -6.7
-22 0.92 -6874385 -0.38 -6.8
-21 0.92 -6954357 -0.37 -6.9
-20 0.92 -7031485 -0.35 -6.97
-19 0.91 -7107035 -
0.332 -7.05
-18 0.92 -7180288 -0.31 -7.1
-17 0.92 -7251193 -0.30 -7.2
-16 0.92 -7320616 -0.28 -7.3
-15 0.92 -7388084 -0.26 -7.3
-14 0.93 -7428595 -0.24 -7.4
-13 0.96 -7307016 -0.23 -7.2
-12 1.00 -7043833 -0.21 -7.0
-11 1.03 -6675040 -0.19 -6.6
-10 1.04 -6223625 -0.17 -6.2
-9 1.04 -5712120 -0.16 -5.7
-8 1.02 -5154780 -0.14 -5.1
-7 1.00 -4559302 -0.12 -4.5
-6 0.98 -3928508 -0.10 -3.9
-5 0.95 -3264389 -0.09 -3.2
-4 0.93 -2581813 -0.07 -2.6
-3 0.91 -1894456 -0.05 -1.9
-2 0.90 -1205816 -0.03 -1.2
-1 0.89 -516765 -0.02 -0.5
0 0.89 172419 0.00 0.171 1 0.2 1 0.2
1 0.89 861550 0.02 0.854 4 3.4 4 3.4
2 0.90 1550443 0.03 1.5 2 3.1 2 3.1
3 0.91 2238817 0.05 2.2 4 8.9 4 8.9
4 0.93 2925803 0.07 2.9 2 5.8 2 5.8
5 0.95 3607901 0.09 3.6 4 14.3 4 14.3
6 0.98 4271442 0.10 4.2 2 8.5 2 8.5
7 1.00 4901556 0.12 4.9 4 19.4 4 19.4
8 1.02 5496248 0.14 5.5 2 10.9 2 10.9
9 1.04 6052702 0.16 6.0 4 24.0 4 24.0
10 1.04 6563224 0.17 6.5 2 13.0 2 13.0
11 1.04 7013565 0.19 7.0 4 27.8 4 27.8
12 1.01 7381185 0.21 7.32 2 14.6 2 14.6
13 0.96 7643076 0.23 7.58 4 30.3 4 30.3
14 0.93 7763218 0.24 7.70 2 15.4 2 15.4
15 0.92 7721178 0.26 7.66 4 30.6 4 30.6
16 0.92 7652103 0.28 7.59 2 15.2 2 15.2
17 0.92 7580971 0.297 7.5 4 30.1 4 30.1 1 7.52
18 0.92 7508255 0.31 7.4 2 14.9 2 14.9 4 29.79
19 0.92 7433091 0.33 7.4 4 29.5 4 29.5 2 14.74
20 0.92 7355529 0.35 7.3 2 14.6 2 14.6 4 29.18
21 0.92 7276288 0.37 7.2 4 28.9 4 28.9 2 14.43
22 0.92 7194105 0.38 7.1 2 14.3 2 14.3 4 28.54
23 0.93 7109622 0.40 7.1 4 28.2 4 28.2 2 14.10
24 0.94 7022516 0.42 7.0 2 13.9 2 13.9 4 27.86
25 0.95 6932707 0.44 6.9 4 27.5 4 27.5 2 13.75
26 0.97 6840266 0.45 6.8 2 13.6 2 13.6 4 27.14
27 0.99 6745188 0.47 6.7 4 26.8 4 26.8 2 13.38
28 1.01 6647342 0.49 6.6 2 13.2 2 13.2 4 26.37
29 1.03 6546706 0.51 6.5 4 26.0 4 26.0 2 12.99
30 1.05 6443781 0.52 6.4 2 12.8 1 6.4 1 6.4 4 25.56
31 1.07 6338204 0.54 6.3 4 25.1 4 25.1 2 12.57
32 1.09 6229754 0.56 6.2 2 12.4 2 12.4 4 24.71
33 1.11 6119610 0.58 6.1 4 24.3 4 24.3 2 12.14
34 1.14 6006690 0.59 6.0 2 11.9 2 11.9 4 23.83
35 1.16 5892041 0.61 5.8 4 23.4 4 23.4 2 11.69
36 1.19 5774984 0.63 5.7 2 11.5 2 11.5 4 22.91
37 1.21 5655933 0.65 5.6 4 22.4 4 22.4 2 11.22
38 1.24 5534923 0.66 5.5 2 11.0 2 11.0 4 21.96
39 1.26 5411818 0.68 5.4 4 21.5 4 21.5 2 10.73
40 1.29 5286696 0.70 5.2 1 5.2 1 5.2 4 20.97
41 1.31 5159605 0.72 5.1 2 10.23
42 1.34 5030626 0.73 5.0 4 19.96
43 1.37 4899756 0.75 4.9 2 9.72
44 1.40 4767078 0.77 4.7 4 18.91
45 1.43 4632665 0.79 4.6 2 9.19
46 1.46 4496545 0.80 4.5 4 17.84
47 1.48 4358738 0.82 4.3 2 8.65
48 1.51 4219306 0.84 4.2 4 16.74
49 1.54 4078261 0.86 4.0 1 4.04
50 1.57 3935726 0.87 3.9
18.6. APPENDIX: DAMAGED STABILITY CALCULATIONS
18.6.1. A AND B FLOODED:
18.6.2. B AND C FLOODED:
Stability Criteria - SOLAS 2004, After Damage, compartments A and B flooded
Name Angle 1 Angle 2 Required Actual Pass / Fail
Angle Between FreeEquil and GZ0 >=
15 deg
0.3457 74.3977 15 74.052 Pass
Area Between FreeEquil and 27 >= 0.86
meters-deg
0.3457 27 0.86 145.389 Pass
GZ At GZmax >= 0.29 meters 17.7889 0.29 7.3066 Pass
Angle At FreeEquil <= 12 deg 0.3457 12 0.3457 Pass
Freeboard At FreeEquil >= 0.076 meters 0.3457 0.076 2.7204 Pass
18.6.3. C AND D FLOODED:
Stability Criteria - SOLAS 2004, After Damage, compartments B and C flooded
Name Angle 1 Angle 2 Required Actual Pass / Fail
Angle Between FreeEquil and GZ0 >=
15 deg
1.6092 74.5676 15 72.9583 Pass
Area Between FreeEquil and 27 >= 0.86
meters-deg
1.6092 27 0.86 125.8385 Pass
GZ At GZmax >= 0.29 meters 20.4644 0.29 6.6707 Pass
Angle At FreeEquil <= 12 deg 1.6092 12 1.6092 Pass
Freeboard At FreeEquil >= 0.076 meters 1.6092 0.076 2.146 Pass
Freeboard At FreeEquil >= 0.076 meters 3.3155 0.076 1.7779 Pass
Angle At FreeEquil <= 12 deg 3.3155 12 3.3155 Pass
GZ At GZmax >= 0.29 meters 21.6 0.29 6.0765 Pass
Area Between FreeEquil and 27 >= 0.86
meters-deg3.3155 27 0.86 107.3328 Pass
Angle Between FreeEquil and GZ0 >=
15 deg3.3155 74.8554 15 71.5399 Pass
Name Angle 1 Angle 2 Required Actual Pass / Fail
Stability Criteria - SOLAS 2004, After Damage, compartments C and D flooded
18.6.4. D AND E FLOODED:
18.6.5. E AND F FLOODED:
Freeboard At FreeEquil >= 0.076 meters 3.9198 0.076 1.7131 Pass
Angle At FreeEquil <= 12 deg 3.9198 12 3.9198 Pass
GZ At GZmax >= 0.29 meters 21.897 0.29 6.4237 Pass
Area Between FreeEquil and 27 >= 0.86
meters-deg
3.9198 27 0.86 107.7353 Pass
Angle Between FreeEquil and GZ0 >=
15 deg
3.9198 75.1032 15 71.1834 Pass
Name Angle 1 Angle 2 Required Actual Pass / Fail
Stability Criteria - SOLAS 2004, After Damage, compartments D and E
18.6.6. F AND G FLOODED:
Freeboard At FreeEquil >= 0.076 meters 3.5124 0.076 1.4749 Pass
Angle At FreeEquil <= 12 deg 3.5124 12 3.5124 Pass
GZ At GZmax >= 0.29 meters 21.0541 0.29 6.411 Pass
Area Between FreeEquil and 27 >= 0.86
meters-deg
3.5124 27 0.86 108.6101 Pass
Angle Between FreeEquil and GZ0 >=
15 deg
3.5124 74.2201 15 70.7077 Pass
Name Angle 1 Angle 2 Required Actual Pass / Fail
Stability Criteria - SOLAS 2004, After Damage, compartments E and F
Freeboard At FreeEquil >= 0.076 meters 4.8345 0.076 1.1818 Pass
Angle At FreeEquil <= 12 deg 4.8345 12 4.8345 Pass
GZ At GZmax >= 0.29 meters 21.0658 0.29 4.5295 Pass
Area Between FreeEquil and 27 >= 0.86
meters-deg
4.8345 27 0.86 75.2789 Pass
Angle Between FreeEquil and GZ0 >=
15 deg
4.8345 70.4717 15 65.6372 Pass
Name Angle 1 Angle 2 Required Actual Pass / Fail
Stability Criteria - SOLAS 2004, After Damage, compartments F and G
18.7. APPENDIX: RESISTANCE CALCULATIONS
18.7.1. NPL RESISTANCE CALCS
rho_sw 1021.88 kg/m 3 at 29.4 C rho_sw 1025 kg/m 3 at 15 C
v_sw 8.5975E-07 m2/sec at 29.4 C v_sw 8.5975E-07 m2/sec at 15 C
Ship Environment Model Environment
Model Data One hull
Name LWL L/B B/T L/V^(1/3) Cb Cp Cm S.A_wet LCB Form Factor
[m] [m2] % Midship (1 + Bk)
3b 1.6 7 2 6.27 0.397 0.693 0.565 0.434 -0.064 1.65
4a 1.6 10.4 1.5 7.4 0.397 0.693 0.565 0.348 -0.064 1.43
SavuFerry 52.50 8.02 2.33 6.67 0.50 0.73 0.39 872.00 -0.065 1.51
Resistance data for current ship design detailed above
s/L Fn C_TM Cr.model 1+Bk Cf.model V_model LWL_ship λ =
[m]
0.3 0.2 7.80E-03 3.21E-03 1.65 4.58E-03 0.79 52.50 32.81
0.3 0.25 8.10E-03 3.73E-03 1.65 4.37E-03 0.99 52.50 32.81
0.3 0.3 8.96E-03 4.75E-03 1.65 4.21E-03 1.19 52.50 32.81
0.3 0.35 1.00E-02 5.94E-03 1.65 4.08E-03 1.39 52.50 32.81
0.3 0.4 1.16E-02 7.65E-03 1.65 3.97E-03 1.58 52.50 32.81
0.3 0.45 1.64E-02 1.26E-02 1.65 3.88E-03 1.78 52.50 32.81
Resistance data for current ship design detailed above
s/L Fn C_TM Cr.model 1+Bk Cf.model V_model L_ship λ =
[m]
0.3 0.2 7.15E-03 2.56E-03 1.43 4.58E-03 0.79 52.50 32.81
0.3 0.25 7.69E-03 3.32E-03 1.43 4.37E-03 0.99 52.50 32.81
0.3 0.3 8.49E-03 4.28E-03 1.43 4.21E-03 1.19 52.50 32.81
0.3 0.35 8.65E-03 4.58E-03 1.43 4.08E-03 1.39 52.50 32.81
0.3 0.4 9.84E-03 5.87E-03 1.43 3.97E-03 1.58 52.50 32.81
0.3 0.45 1.18E-02 7.95E-03 1.43 3.88E-03 1.78 52.50 32.81
Approximated Ship resistance with interpolated residuary resistance
s/L Fn Cr.model 1+Bk Cf.model V_model L_ship λ =
[m]
0.3 0.2 2.79E-03 1.51 4.58E-03 0.79 52.50 32.81
0.3 0.25 3.46E-03 1.51 4.37E-03 0.99 52.50 32.81
0.3 0.3 4.45E-03 1.51 4.21E-03 1.19 52.50 32.81
0.3 0.35 5.06E-03 1.51 4.08E-03 1.39 52.50 32.81
0.3 0.4 6.50E-03 1.51 3.97E-03 1.58 52.50 32.81
0.3 0.45 9.59E-03 1.51 3.88E-03 1.78 52.50 32.81
Interpolated Values
SAVU SEA FERRY
MODEL 3B
MODEL 4B
Both Hulls
A_wet V_ship V_sh.kn Rn C_f.ship C_TS R_ship P_E PE
[m2] [m/s] [knots] ship [N] [W] [kW]
934.54 4.54 8.82 2.77E+08 1.81E-03 3.22E-03 31649.74 144E+3 143.65
934.54 5.67 11.03 3.46E+08 1.75E-03 3.78E-03 58090.36 330E+3 329.58
934.54 6.81 13.23 4.16E+08 1.71E-03 4.84E-03 107126.72 729E+3 729.35
934.54 7.94 15.44 4.85E+08 1.68E-03 6.06E-03 182606.90 1,450E+3 1450.44
934.54 9.08 17.65 5.54E+08 1.65E-03 7.79E-03 306492.29 2,782E+3 2782.23
934.54 10.21 19.85 6.24E+08 1.62E-03 1.27E-02 633903.99 6,474E+3 6473.66
A_wet V_ship V_sh.kn Rn C_f.ship C_TS R_ship P_E PE
[m2] [m/s] [knots] ship [N] [W] [kW]
749.36 4.54 8.82 2.77E+08 1.81E-03 3.18E-03 25065.59 114E+3 113.77
749.36 5.67 11.03 3.46E+08 1.75E-03 3.94E-03 48606.36 276E+3 275.77
749.36 6.81 13.23 4.16E+08 1.71E-03 4.92E-03 87352.85 595E+3 594.72
749.36 7.94 15.44 4.85E+08 1.68E-03 5.22E-03 126149.72 1,002E+3 1002.00
749.36 9.08 17.65 5.54E+08 1.65E-03 6.52E-03 205794.34 1,868E+3 1868.13
749.36 10.21 19.85 6.24E+08 1.62E-03 8.61E-03 343758.36 3,511E+3 3510.59
from model
A_wet V_ship V_sh.kn Rn C_f.ship C_TS R_ship P_E PE
[m2] [m/s] [knots] ship [N] [W] [kW]
855.46 4.54 8.82 2.77E+08 1.81E-03 3.19E-03 28741.11 130E+3 130.45
855.46 5.67 11.03 3.46E+08 1.75E-03 3.89E-03 54668.92 310E+3 310.17
855.46 6.81 13.23 4.16E+08 1.71E-03 4.89E-03 99133.37 675E+3 674.92
855.46 7.94 15.44 4.85E+08 1.68E-03 5.52E-03 152210.27 1,209E+3 1209.00
855.46 9.08 17.65 5.54E+08 1.65E-03 6.97E-03 251095.92 2,279E+3 2279.36
855.46 10.21 19.85 6.24E+08 1.62E-03 1.01E-02 458973.15 4,687E+3 4687.20
SAVU SEA FERRY
MODEL 3B
MODEL 4B
18.7.2. VWS RESISTANCE CALCULATIONS
"Numerical Resistance Prediction based on the Results of the VWS Hard Chine Catamaran Hull Series '89"
Jan M. Zips - presented at FAST '95 , Travemünde GE
The scope of the VWS 89 Chine hull series is:
1. Hull lengths from 20 to 80 m
2. displacement 25 to 1000 ts
3. Service speed 35 to 40 kn
4. Fn from 0.8 to 1.4
Inputs
LWL Waterline Length 52.49 m
BXDH Demihull Beam 6.55 m
LWL/BXDH 7.55 - 13.55 8.020
bM Deadrise Angle 16 - 38 deg 31 deg
dW Transom Wedge 0 - 12 deg 0 deg
D Displacement 996.1 tonnes For full ship, I assume…
Displaced volume 974.754 m3
r Sea water density 1021.88 kg m-3
n Sea water kinematic viscosity 8.5975E-07 m2 s
g Specific gravity force 9.807 m s-2
CA Correlation allowance 0.0004
Computed values
SW/2/3 Wetted surface coefficient 9.729520 SW = 957 m 2
LWL/(/2)1/3 Length-volume coefficient 6.410140
Fn/2 eR Rn CF RF v (m s-1) VK (kn) PE (kW) PE (hp)
1.00 0.030392325 515461109.1 0.00166468 77875.88 8.79 17.07 3292 4413
1.25 0.07165081 644326386.3 0.00161764 118908.33 10.98 21.33 8992 12054
1.50 0.076282926 773191663.6 0.00158066 168090.01 13.18 25.60 12035 16132
1.75 0.074679585 902056940.9 0.00155038 225291.20 15.37 29.87 14679 19677
2.00 0.077526059 1030922218 0.00152484 290405.52 17.57 34.13 18409 24677
2.50 0.087365591 1288652773 0.00148356 444026.55 21.96 42.66 28496 38198
3.00 0.097831239 1546383327 0.00145106 628365.99 26.36 51.20 41748 55962
3.50 0.092569908 1804113882 0.00142441 842961.63 30.75 59.73 53724 72016
18.7.3. PRAM AND SAHOO RESISTANCE CALCULATIONS
Practical Evaluation of Resistance of high-speed Catamaran hull forms
Extrapolated Data
Fn/2 v (m s-1) VK (kn) R_T (N) PE (kW) PE (hp)
0.55 4.83 9.39 29091 141 188
0.6 5.27 10.24 42108 222 298
0.65 5.71 11.09 59170 338 453
0.7 6.15 11.95 81075 499 668
0.75 6.59 12.80 108701 716 960
0.8 7.03 13.65 143006 1005 1347
0.85 7.47 14.51 185034 1382 1852
0.9 7.91 15.36 235913 1865 2500 Extrapolation form:
0.95 8.35 16.21 296857 2478 3321 R_T = k*V^x
0.975 8.57 16.64 331506 2839 3806 k = 36
1.00 8.79 17.07 374765 3292.34 4413.32 prediction: 952991.06
1.25 10.98 21.33 818835 8991.91 12053.50 exp = 4.25
Italic cells reference the table above
Fn alpha beta_1 beta_2 beta_3 beta_4 Cw_CAT V_ship V_sh.kn Rn C_f.ship (1+Bk) CT _cat R_ship P_E PE
[m/s] [knots] ship [N] [W] [kW]
0.4 2.507751 -2.25588 -1.819332 0.921796 -0.02667 0.002705 9.08 17.6 5.54E+08 1.65E-03 1.29 4.83E-03 177220.16 1.61E+06 1608.64
0.5 2.448887 -2.42472 -1.582805 0.861936 -0.2786 0.003203 11.35 22.1 6.93E+08 1.60E-03 1.29 5.27E-03 301998.75 3.43E+06 3426.58
0.6 2.231476 -2.44248 -1.528469 0.931836 -0.23256 0.002655 13.62 26.5 8.31E+08 1.57E-03 1.29 4.67E-03 385797.07 5.25E+06 5252.85
0.7 1.898569 -2.40299 -1.489982 0.961013 -0.12984 0.002195 15.88 30.9 9.70E+08 1.54E-03 1.29 4.17E-03 469007.61 7.45E+06 7450.12
0.8 1.543052 -2.3511 -1.442334 0.965683 -0.0469 0.001866 18.15 35.3 1.11E+09 1.51E-03 1.29 3.81E-03 559587.03 1.02E+07 10158.81
0.9 1.20842 -2.30869 -1.384697 0.96665 -0.00486 0.001592 20.42 39.7 1.25E+09 1.49E-03 1.29 3.51E-03 652110.80 1.33E+07 13318.31
1 0.911271 -2.27998 -1.317368 0.979194 0.004593 0.001323 22.69 44.1 1.39E+09 1.47E-03 1.29 3.21E-03 737576.99 1.67E+07 16737.58
1.1 0.063404 -2.25769 -1.24056 0.995197 -0.00438 0.000103 24.96 48.5 1.52E+09 1.45E-03 1.29 1.97E-03 547829.96 1.37E+07 13674.88
1.2 0.391235 -2.24274 -1.155136 1.021166 -0.01745 0.000702 27.23 52.9 1.66E+09 1.44E-03 1.29 2.55E-03 843486.31 2.30E+07 22969.13
1.3 0.162273 -2.23328 -1.050167 1.036256 -0.02771 0.000325 29.50 57.3 1.80E+09 1.42E-03 1.29 2.16E-03 836923.46 2.47E+07 24689.61
1.4 0.0027 -2.23505 -0.908676 1.119485 -0.03114 5.76E-06 31.77 61.8 1.94E+09 1.41E-03 1.29 1.82E-03 819740.54 2.60E+07 26042.92
1.5 -0.02858 -2.26839 -0.69293 1.32658 -0.03551 -6E-05 34.04 66.2 2.08E+09 1.40E-03 1.29 1.74E-03 899653.05 3.06E+07 30623.27
Calm water resistance of catamarans is in general attributed to two major components namely, viscous resistanceand calm water wave resistance. The former has been acceptably determined from ITTC-1957 lineusing a form factor component whilst the latter still remains to be a stimulating question to theresearchers.
Fn V_ship V_sh.kn R_ship P_E PE
[m/s] [knots] [N] [W] [kW]
0.15 3.40 6.62 2917.6 9931.078 9.9
0.2 4.54 8.82 9908.5 44970.19 45.0
0.25 5.67 11.03 25578.6 145111.7 145.1 Extrapolation form:
0.3 6.81 13.23 55513.3 377923.5 377.9 R_t = k*V x
0.35 7.94 15.44 106886.1 848935.2 848.9 k = 16
0.4 9.08 17.64 1.77E+05 1.61E+06 1608.64 prediction: 188532.9
0.5 11.35 22.06 3.02E+05 3.43E+06 3426.58 exp = 4.25
Italic cells reference the table above
Value Product
a0 0 0.000 0.00
a1 0.258 2.326 0.60
a2 2.505 6.670 16.71
a3 -150.791 0.300 -45.24
a4 4.932 1.450 7.15
a5 -1.446 15.514 -22.43
a6 68.628 0.698 47.89
a7 6.549 2.001 13.11
a8 -2.506 3.373 -8.45
a9 -2.432 9.672 -23.52
a10 100.173 0.435 43.58
a11 -1.636 4.654 -7.61
a12 1.417 22.496 31.88
a13 -43.355 1.012 -43.86
a14 -2.927 2.902 -8.49
1.29
(L/V 1/3)(s/L)
(B/T)(1+k)
(L/V 1/3)(1+k)
Regression Coefficients
(s/L)(1+k)
0
Coefficients
(L/V 1/3)(s/L)(1+k)
B/T
L/V 1/3
s/L
(1+k)
(B/T)(L/V 1/3)
(B/T)(s/L)
(B/T)(s/L)(1+k)
Regression Multiple
(B/T)(L/V 1/3)(s/L)
(B/T)(L/V 1/3)(1+k)
18.8. APPENDIX: STRUCTURAL CALCULATIONS
Factor Service group Range (NM)
0.5 G1 craft 0
0.6 G2 craft 20
0.7 G3 craft 150
0.8 G4 craft 250
1 G5 350
1 G6
Table. Vessel service group and factor
Local Design Load
Table. Vessel relative vertical motion
Table. Vessel vertical acceleration
% Lwl xwI xa Tx zk u kz Hrm
[%] [m] [m] [m] [m] [m]
0% 0.0 0.0 0.8 2.0 0.10 0.91 3.49
10% 5.2 5.2 1.5 1.4 0.17 0.84 2.99
20% 10.5 10.5 2.1 0.7 0.25 0.78 2.69
30% 15.7 15.7 2.5 0.3 0.30 0.74 2.57
40% 21.0 21.0 2.7 0.1 0.32 0.72 2.64
50% 26.2 26.2 2.8 0.0 0.34 0.71 2.89
60% 31.5 31.5 2.8 0.0 0.34 0.71 3.33
70% 36.7 36.7 2.8 0.0 0.34 0.71 3.96
80% 42.0 42.0 2.8 0.0 0.34 0.71 4.77
90% 47.2 47.2 2.4 0.4 0.29 0.75 5.77
100% 52.5 52.5 0.0 2.8 0.00 1.00 6.95
Distance from
aft end of Lwl
Distance from aft
end of Lwl
Relative vertical
motion
Distance from AP
along hull
Local draft to operating
waterline, above bottom hull
Vertical distance of
underside of keel
% Lwl xwI ax
[%] [m] [g]
0% 0.0 0.78
10% 5.2 0.76
20% 10.5 0.79
30% 15.7 0.85
40% 21.0 0.94
50% 26.2 1.08
60% 31.5 1.25
70% 36.7 1.46
80% 42.0 1.70
90% 47.2 1.99
100% 52.5 2.31
Distance from aft
end of Lwl
Distance from aft
end of Lwl
Vertical acc at xa
on static load
Table. Wave induced pressure calculation
Table. Wave induced pressure calculation (con’d)
Table. Wave induced pressure calculation (con’d)
xwI Pp Pw Hw fL E Pwh (Pd)
[m] [kPa] [kPa] [m] [kPa]
0.0 43.47 43.47 6.97 1.00 1.59 8.80
5.2 43.47 43.47 5.99 1.00 1.59 8.80
10.5 43.47 43.47 5.38 1.00 0 7.20
15.7 43.47 43.47 5.14 1.00 0 7.20
21.0 43.47 43.47 5.28 1.00 0 7.20
26.2 43.47 43.47 5.78 1.00 0 7.20
31.5 43.47 43.47 6.66 1.00 0 7.20
36.7 43.47 43.47 7.91 1.00 0 7.20
42.0 47.82 47.82 9.54 1.00 1.59 8.80
47.2 63.76 63.76 11.53 1.25 1.59 10.60
52.5 79.70 79.70 13.90 1.50 1.59 12.40
79.70 79.70 12.40
Hydrodynamic wave
pressure
Pressure on
deck
Hydrodynamic
pressure 2
Nominal wave
limit height
Location factor
weather/interior deck
deck
factor
Distance from aft
end of Lwl
xwI Φdh Pdh Pf Kpc ∇pc Ppc
[m] [kPa] [kPa] [kPa]
0.0 0 0.00 0 1.0 0.17 11.38
5.2 0 0.00 0 1.0 0.17 11.38
10.5 0 0.00 0 1.0 0.17 11.38
15.7 0 0.00 0 1.0 0.17 11.38
21.0 0 0.00 0 1.0 0.17 11.38
26.2 0 0.00 0 1.0 0.17 11.38
31.5 0.06 18.59 0 1.0 0.17 11.38
36.7 0.12 37.19 0 1.0 0.17 11.38
42.0 0.18 55.78 47.68 1.3 0.17 15.13
47.2 0.18 64.74 64.74 1.7 0.17 19.00
52.5 0.09 47.98 64.74 2.0 0.17 22.76
64.74 64.74 22.76
Impact
pressure,
Longitudinal
distribution factor
Cross-deck impact
factor
Bottom shell impact
pressure
Forebody impact
pressure
Distance from
aft end of Lwl
xwI C1 Pdhp Pcd
[m] [kPa] [kPa]
0.0 16.23
5.2 16.15
10.5 0.8 5.76 16.27
15.7 0.8 5.76 16.62
21.0 0.8 5.76 17.19
26.2 0.8 5.76 17.97
31.5 0.8 5.76 18.97
36.7 0.8 5.76 20.19
42.0 0.8 7.04 21.63
47.2 23.29
52.5 25.16
7.04 25.16
Design pressure for side plating
superstructureCargo deck design pressure
Distance from
aft end of Lwl
Pressure factor
superstructure side
Table. Hydrostatic pressure on shell plating
Table. Combined hydrostatic pressure on shell plating up to waterline
Table. Vertical distribution factor for hydrodynamic pressure
xwI
[m] 0.00 0.70 1.41 2.11 2.81
0.0 28.14 21.11 14.07 7.04 0.00
5.2 28.14 21.11 14.07 7.04 0.00
10.5 28.14 21.11 14.07 7.04 0.00
15.7 28.14 21.11 14.07 7.04 0.00
21.0 28.14 21.11 14.07 7.04 0.00
26.2 28.14 21.11 14.07 7.04 0.00
31.5 28.14 21.11 14.07 7.04 0.00
36.7 28.14 21.11 14.07 7.04 0.00
42.0 28.14 21.11 14.07 7.04 0.00
47.2 28.14 21.11 14.07 7.04 0.00
52.5 28.14 21.11 14.07 7.04 0.00
Hydrostatic pressure on shell plating, Ph [kPa]Distance from
aft end of Lwl
z [m]
28.14
xwI
[m] 0.00 0.70 1.41 2.11 2.81
0.0 71.61 64.58 57.54 50.51 43.47
5.2 71.61 64.58 57.54 50.51 43.47
10.5 71.61 64.58 57.54 50.51 43.47
15.7 71.61 64.58 57.54 50.51 43.47
21.0 71.61 64.58 57.54 50.51 43.47
26.2 71.61 64.58 57.54 50.51 43.47
31.5 71.61 64.58 57.54 50.51 43.47
36.7 71.61 64.58 57.54 50.51 43.47
42.0 75.96 68.92 61.89 54.85 47.82
47.2 91.90 84.86 77.83 70.79 63.76
52.5 107.84 100.80 93.77 86.73 79.70
Distance
from aft
107.84
Combined pressre distribution UP TO operating waterline, Ps [kPa]
z [m] < zk+Tx
xwI
[m] 0.00 0.70 1.41 2.11 2.81
0 0.68 0.76 0.84 0.92 1.00
5.2 0.69 0.77 0.85 0.92 1.00
10.5 0.70 0.78 0.85 0.93 1.00
15.7 0.71 0.78 0.85 0.93 1.00
21.0 0.71 0.78 0.86 0.93 1.00
26.2 0.71 0.79 0.86 0.93 1.00
31.5 0.71 0.79 0.86 0.93 1.00
36.7 0.71 0.79 0.86 0.93 1.00
42.0 0.71 0.79 0.86 0.93 1.00
47.2 0.71 0.78 0.85 0.93 1.00
52.5 - - - - -
z [m]
Vertical distribution factor, fzDistance from
aft end of Lwl
Table. Hydrodynamic pressure
Table. Design pressure for watertight bulkhead
Table. Summary of wave induced pressure
xwI [kPa]
[m] 0.00 0.70 1.41 2.11 2.81
0 23.66 26.46 29.26 32.06 34.85 34.85
5.2 20.69 23.00 25.32 27.63 29.94 29.94
10.5 18.87 20.88 22.88 24.89 26.90 26.90
15.7 18.22 20.09 21.96 23.84 25.71 25.71
21.0 18.79 20.69 22.58 24.48 26.38 26.38
26.2 20.65 22.71 24.78 26.85 28.91 28.91
31.5 23.80 26.18 28.55 30.93 33.31 33.31
36.7 28.27 31.09 33.92 36.74 39.57 39.57
42.0 34.07 37.47 40.88 44.28 47.68 47.68
47.2 40.79 45.00 49.22 53.44 57.66 57.66
52.5 - - - - - -
57.66
Hydrodynamic pressure 1, Pm [kPa]
z [m]
Max PmDistance
from aft
hb, [m] Pbh, plating hb Pbh, stiffener
4.89 35.21
1.97 14.183.92 28.25
Design pressure for watertight bulkhead, Pbh [kPa]
Plating Stiffeners
hydrostatic pressure Ph 28.14
hydrodynamic pressure Pm 57.66
pitching pressure Pp 79.70
Impact pressure Pdh 64.74
deckhouse, superstructure pressure Pdhp 7.04
shell envelope pressure Ps 107.84
forebody impact pressure Pf 64.74
Impact pressure on cross-deck Ppc 22.76
pressure on weather deck Pwh 12.40
deck pressure for cargo Pcd 25.16
watertight bulkhead, plating Pbh, plating 28.25
watertight bulkhead, stiffener Pbh, stiffener 35.21
Local Design Load Criteria for Craft Operating in Displacement Mode
Table. Design pressures criteria for displacement craft
Table. Summary of local design pressures
PBP Hf Sf Ps 113.23 PBF δf Hf Sf Ps 56.61
Hf Sf Gf Pdh 67.98 δf Hf Sf Gf Pd h 33.99
H f S f G f P f 67.98 δf H f S f G f P f 33.99
MAX 113.23 MAX 56.61
Outboard side shell PSP PBP 113.23 PSF δf P BP 56.61
inboard side shell PSP P BP 113.23 PSF δf P BP 56.61
1,6 P WDP at wet deck 40.26 1,9 P WDP at wet deck 47.81
MAX 113.23 MAX 56.61
wet deck PCP H f S f P p 83.68 PCF δf H f S f P p 41.84
H f S f P pc 23.89 δf H f S f P pc 11.95
MAX 83.68 MAX 41.84
weather deck PWDP H f S f G f P wh 13.02 PWDF δf H f S f G f P wh 6.51
P cd 25.16 P cd 25.16
(min) 7 7.00 (min) 7 7.00
MAX 25.16 MAX 25.16
coachroof PCRP H f S f G f P wh 13.02 PCRF δf H f S f G f P wh 6.51
7 7.00 7 7.00
MAX 13.02 MAX 7.00
interior deck PIDP H f S f P wh 13.02 PIDF δf H f S f P wh 6.51
Pcd 25.16 Pcd 25.16
3.5 3.50 3.5 3.50
MAX 25.16 MAX 25.16
deckhouse, superstructure PDHP H f S f G f P dhp 7.39 PDHF δf H f S f G f P dhp 3.69
inner bottom PIBP H f S f P m + P h 88.68 PIBF δf H f S f P s 56.61
10T 28.14 10T 28.14
MAX 88.68 MAX 56.61
watertight bulkhead PBHP P bh 28.25 PBHF P bh 35.21
Plating Stiffener
bottom shell, partially
submerged hulls
bottom shell plating PBP 113.23
bottom shell stiffening PBF 56.61
side shell plating, outboard PSP, outboard 113.23
side shell stiffening, outboard PSF, outboard 56.61
side shell plating, inboard PSP, inboard 113.23
side shell stiffening, inboard PSF, inboard 56.61
cross-deck plating PCP 83.68
cross-deck stiffening PCF 41.84
weachter deck plating PWDP 25.16
weather deck stiffening PWCDF 25.16
coachroof plating PCRP 13.02
coachroof stiffening PCRF 7.00
interior deck plating PIDP 25.16
interior deck stiffening PIDF 25.16
inner bottom plating PIBP 88.68
inner bottom stiffening PIBF 56.61
superstructure plating PDHP 7.39
supersturcture stiffening PDHF 3.69
bulkhead plating PBHP 28.25
bulkhead stiffener PBHF 35.21
Global Load and Design Criteria
Table. Vertical wave bending moment
Table. Vertical wave bending moment associated shear force
Table. Design load combination for multi-hull
% LR x Df MMW sagging MMW hogging
[%] [m] [kNm] [kNm]
0% 0.0 0.0 0 0
10% 5.1 0.3 -5087 8139
20% 10.2 0.5 -10174 16279
30% 15.3 0.8 -15262 24418
40% 20.4 1.0 -20349 32558
50% 25.5 1.0 -20349 32558
60% 30.6 1.0 -20349 32558
70% 35.6 0.9 -17442 27907
80% 40.7 0.6 -11628 18605
90% 45.8 0.3 -5814 9302
100% 50.9 0.0 0 0
Distance from aftDistance from
aft of LR
Vertical wave bending
moment, sagging
Vertical wave bending
moment, hogging
x Kf, positive Kf, negative QMW positive QMW negative
[m] [kN] [kN]
0.0 0.00 0.00 0.0 0.0
5.1 0.33 -0.46 638.0 -551.5
10.2 0.67 -0.92 1275.9 -1103.0
15.3 0.67 -0.92 1275.9 -1103.0
20.4 0.70 -0.70 1342.8 -839.2
25.5 0.70 -0.70 1342.8 -839.2
30.6 0.70 -0.70 1342.8 -839.2
35.6 1.00 -0.72 1918.3 -866.7
40.7 1.00 -0.72 1918.3 -866.7
45.8 0.67 -0.48 1278.8 -577.8
50.9 0.00 0.00 0.0 0.0
Distance from aft of LR Positve shear force
factor
Negative shear force
factor
Positive wave
shear force
Negative wave
shear force
x Sagging Hogging Sagging Hogging Sagging Hogging
[m] [kNm] [kNm] [kNm] [kNm] [kNm] [kNm]
0.0 6657 6657 34262 34262 43007 43007
5.1 1570 14797 33753 35076 40972 46263
10.2 -3517 22936 33244 35889 38937 49519
15.3 -8604 31076 32735 36703 36903 52775
20.4 -13691 39215 32227 37517 34868 56030
25.5 -13691 39215 32227 37517 34868 56030
30.6 -13691 39215 32227 37517 34868 56030
35.6 -10785 34564 32517 37052 36030 54170
40.7 -4971 25262 33099 36122 38356 50449
45.8 843 15960 33680 35192 40682 46728
50.9 6657 6657 34262 34262 43007 43007
Distance from aft
of LR Head sea Beam sea Quartering sea
Service group factor Gf for MB 1.5
Twin hull transverse bending moment, kNm MB 26184
Table. Twin-hull transverse bending moment
Service group factor Gf for MT 0.75
Twin hull torsional connecting moment, kNm MT 40389
Table. Twin-hull torsional connecting moment
Service group factor Gf for QT 1.5
Vertical shear force cross-deck
QT
1586
Table. Vertical shear force at cross-deck structure
Scantling Determination for Multi-hull Craft
Item Minimum thickness
[mm]
Shell envelope
bottom shell plating 4.85 ≥ 4 4.85
side shell plating 3.91 ≥ 3 3.91
wet-deck plating 3.91 ≥ 3 3.91
Single Bottom structure
centre girder web 6.71 ≥ 4 6.71
floor webs 5.08 ≥ 4 5.08
side girder webs 5.08 ≥ 4 5.08
Double bottom structure
centre girder:
(1) within 0.4LR amidships 6.71 ≥ 4 6.71
(2) outside 0.4LR amidships 5.99 ≥ 4 5.99
floors and side girders 5.08 ≥ 4 5.08
inner bottom plating 4.57 ≥ 3 4.57
Bulkheads
watertight bulkhead plating 3.35 ≥ 3 3.35
deep tank bulkhead plating 3.91 ≥ 3 3.91
Deck plating and stiffeners
strength/main deck plating 3.91 ≥ 3 3.91
lower deck/inside deckhouse 2.98 ≥ 2 2.98
Superstructures and deckhouses
superstructure side plating 3.14 ≥ 2 3.14
deckhouse front 1st tier 4.85 ≥ 3 4.85
deckhouse front upper tiers 4.30 ≥ 3 4.30
deckhouse aft 2.03 ≥ 2 2.03
Pillars
wall thickness of tubular pillars 5.00 5.00
wall thickness of rectangular pillars 5.00 5.00
Table. Minimum thickness requirement
Table. Bottom shell plating thickness
Table. Side shell plating thickness
Table. Wet deck plating thickness
Table. Cross-deck plating thickness
design pressure P 113.23
Stiffener spacing s 550
convex curvature correction factor γ 1.0
panel aspect ratio correction factor β 1.0
limiting bending stress coefficient fσ 0.75
minimum plate thickness tp 9.9
Bottom shell
outboard inboard
design pressure P 113.23 113.23
Stiffener spacing s 550 550
convex curvature correction factor γ 1.0 1.0
panel aspect ratio correction factor β 1.0 1.0
limiting bending stress coefficient fσ 0.75 0.75
minimum plate thickness tp 9.9 9.9
Side shell
design pressure P 83.68
Stiffener spacing s 550
convex curvature correction factor γ 1.0
panel aspect ratio correction factor β 1.0
limiting bending stress coefficient fσ 0.75
minimum plate thickness tp 8.5
Wet deck
design pressure P 83.68
Stiffener spacing s 550
convex curvature correction factor γ 1.0
panel aspect ratio correction factor β 1.0
limiting bending stress coefficient fσ 0.75
minimum plate thickness tp 8.5
Cross-deck
design pressure P 28.25
Stiffener spacing s 550
convex curvature correction factor γ 1.0
panel aspect ratio correction factor β 1.0
limiting bending stress coefficient fσ 1.0
minimum plate thickness tp 4.3
Watertight transverse
bulkhead
Table. Watertight bulkhead plating thickness
Table. Bar keel minimum requirement
Table. Centre girder minimum requirement
Table. Superstructure minimum plating thickness
Table. Stiffener minimum requirement bottom frame and web frame
Table. Stiffener minimum requirement side frame and web frame
bar keel cross-sectional area [cm²] Abk 38.2
bar keels thickness [mm] tbk 27.5
minimum bar keel depth [mm] depth 139
Bar keel
Centre girder
web thickness [mm] tw 5.1
overall web depth [mm] dw 630
design pressure P 7.39 7.39 7.39
Stiffener spacing s 550 550 550
convex curvature correction factor γ 1.0 1.0 1.0
panel aspect ratio correction factor β 1.0 1.0 1.0
limiting bending stress coefficient fσ 0.75 0.75 0.75
minimum plate thickness tp 2.5 2.5 2.5
Machinery casingHouse side House top peronnel loading
outboard inboard outboard inboard
load model a, b or c a a a a
design pressure P 56.61 56.61 56.61 56.61
stiffener spacing S 3300 3300 550 550
effective span length Le 1.9 1.9 1.9 1.9
section modulus coefficient Φz, mid 0.04 0.04 0.04 0.04
inertia coefficient ΦI, mid 0.0026 0.0026 0.0026 0.0026
web area coefficient ΦA, end 0.5 0.5 0.5 0.5
limiting bending stress coefficient fσ 0.65 0.65 0.65 0.65
limiting deflection coefficient fδ 1000 1000 1000 1000
limiting shear stress coefficient fT 0.65 0.65 0.65 0.65
section modulus Z 184 184 31 31
moment of inertia I 1669 1669 278 278
web area Aw 20 20 3 3
Bottom web frame Bottom transverse frame
outboard inboard outboard inboard
load model a, b or c a a a a
design pressure P 56.61 56.61 56.61 56.61
stiffener spacing S 3300 3300 550 550
effective span length Le 2.2 2.2 2.2 2.2
section modulus coefficient Φz, mid 0.04 0.04 0.04 0.04
inertia coefficient ΦI, mid 0.0026 0.0026 0.0026 0.0026
web area coefficient ΦA, end 0.5 0.5 0.5 0.5
limiting bending stress coefficient fσ 0.65 0.65 0.65 0.65
limiting deflection coefficient fδ 1000 1000 1000 1000
limiting shear stress coefficient fT 0.65 0.65 0.65 0.65
section modulus Z 247 247 41 41
moment of inertia I 2590 2590 432 432
web area Aw 23 23 4 4
Side web frame Side transverse frame
Table. Stiffener minimum requirement cross-deck structure
Table. Stiffener minimum requirement side stringer
Table. Stiffener minimum requirement wet deck
load model a, b or c a a
design pressure P 41.84 41.84
stiffener spacing S 3300 528
effective span length Le 9.5 3.2
section modulus coefficient Φz, mid 0.04 0.04
inertia coefficient ΦI, mid 0.0026 0.0026
web area coefficient ΦA, end 0.5 0.5
limiting bending stress coefficient fσ 0.65 0.65
limiting deflection coefficient fδ 1000 800
limiting shear stress coefficient fT 0.65 0.65
section modulus Z 3399 62
moment of inertia I 154144 754
web area Aw 74 4
Cross-deck longitudinalCross-deck web frame
outboard inboard
load model a, b or c b b
design pressure P 56.61 56.61
stiffener spacing s 2200 2200
effective span length Le 3.2 3.2
section modulus coefficient Φz, mid 0.10 0.10
inertia coefficient ΦI, mid 0.0035 0.0035
web area coefficient ΦA, end 0.5 0.5
limiting bending stress coefficient fσ 0.65 0.65
limiting deflection coefficient fδ 800 800
limiting shear stress coefficient fT 0.65 0.65
section modulus Z 835 835
moment of inertia I 5669 5669
web area Aw 23 23
Side stringer
load model a, b or c b
design pressure P 41.84
stiffener spacing S 671
effective span length Le 3.2
section modulus coefficient Φz, mid 0.10
inertia coefficient ΦI, mid 0.0035
web area coefficient ΦA, end 0.5
limiting bending stress coefficient fσ 0.65
limiting deflection coefficient fδ 800
limiting shear stress coefficient fT 0.65
section modulus Z 188
moment of inertia I 1278
web area Aw 5.1
Wet-deck longitudinal
Table. Stiffener minimum requirement superstructure
Hull Girder Strength
Table. Hull girder section modulus calculation
Table. Effective shear area calculation
Table. Load combination factor
load model a, b or c b b b
design pressure P 3.69 3.69 3.69
stiffener spacing s 550 550 550
effective span length Le 3.2 3.2 3.2
section modulus coefficient Φz, mid 0.10 0.10 0.10
inertia coefficient ΦI, mid 0.0035 0.0035 0.0035
web area coefficient ΦA, end 0.5 0.5 0.5
limiting bending stress coefficient fσ 0.75 0.6 0.75
limiting deflection coefficient fδ 600 800 600
limiting shear stress coefficient fT 0.75 0.6 0.75
section modulus Z 12 15 12
moment of inertia I 69 92 69
web area Aw 0.3 0.4 0.3
House side stiffener House top stiffener personnel
loadingCasing stiffener
scantlings scantlings a dn a*dn a*dn² h io
[mm] [mm] [mm²] [mm] [mm³] [mm4] [mm] [mm4]
main deck 23500 10 235000 5900 1386500000 8.18035E+12
wet deck 9500 10 95000 4450 422750000 1.88124E+12
side shell outboard 3900 10 39000 3700 144300000 5.3391E+11 3900 4.94E+10
side shell inboard 3900 10 39000 3700 144300000 5.3391E+11 3900 4.94E+10
side shell outboard 3900 10 39000 3700 144300000 5.3391E+11 3900 4.94E+10
side shell inboard 3900 10 39000 3700 144300000 5.3391E+11 3900 4.94E+10
bottom shell outboard 3000 10 30000 800 24000000 19200000000 2000 6.67E+09
bottom shell inboard 3000 10 30000 800 24000000 19200000000 2000 6.67E+09
bottom shell outboard 3000 10 30000 800 24000000 19200000000 2000 6.67E+09
bottom shell inboard 3000 10 30000 800 24000000 19200000000 2000 6.67E+09
center keel 150 40 6000 75 450000 33750000
center keel 150 40 6000 75 450000 33750000
SUM 618000 2483350000 1.22741E+13 2.24E+11
item
scantlings scantlings effective length effective shear area
[mm] [mm] [mm] [mm²]
side shell outboard 3900 10 3900 39000
side shell inboard 3900 10 3900 39000
side shell outboard 3900 10 3900 39000
side shell inboard 3900 10 3900 39000
bottom shell outboard 3000 10 2000 20000
bottom shell inboard 3000 10 2000 20000
bottom shell outboard 3000 10 2000 20000
bottom shell inboard 3000 10 2000 20000
SUM 236000
item
Head sea Beam sea Quartering sea
f MR1.0 0.1 0.4
f MB0.1 1.0 0.1
f MT0.1 0.2 1.0
18.9. APPENDIX: WEIGHT ESTIMATE
Vessel Particulars
LOA = 55.00 m
BOA = 23.50 m
Depth = 5.90 m
Cubic Number = 76.26
Coordinate System
Axis Reference Positive Input
Direction Units
LCG Bow Aft m
VCG Baseline upwards m
TCG Centreline Port m
Light Ship Summary Weight
(MT) LCG VCG TCG L.Mom V.Mom T.Mom
100 - Structure 434.1 30.1 5.6 0.0 13072678 2418781 0
200 - Propulsion 74.3 52.9 7.9 0.0 3929600 588100 0
300 - Electrical 31.0 34.2 6.8 0.0 1059600 209223 0
400 - Command 3.4 21.9 13.9 0.0 74325 47275 0
500 - Aux Equipment 44.8 24.5 8.4 0.0 1097640 374820 0
600 - Outfit 52.2 32.0 7.1 0.2 1668768 370710 9944
MARGIN (5%) 32.0
671.7 31.1 6.0 0.0 20903 4009 9.944
Full Load Displacement Summary Weight
(MT) LCG VCG TCG L.Mom V.Mom T.Mom
Consumables
Fuel (98%) 39 32 2 0 1258 64 0
Potable Water (98%) 20 26 2 8 500 32 162
Passengers, Crew, and Stores
Passengers + Crew 12 25 11 0 300 131 0
Crew Stores (15 crew) 1 23 4 -7 17 3 -5
Passenger stores (185 pax) 3 31 10 0 85 26 0
Misc. Liquids
Grey Water (10%) 2 24 2 0 37 3 0
Black Water (10%) 1 23 2 10 14 1 6
Lube Oil (98%) 2 38 2 0 69 4 0
Used Oil (10%) 0 38 2 0 2 0 0
Sludge (10%) 0 39 2 0 4 0 0
Oily Water (10%) 1 38 2 0 19 1 0
Mission Load
Cars, x 34 58 25 7 0 1457 376 0
Trucks x 10 200 28 7 0 5560 1320 0
Total Deadweight 337 28 6 0 9321 1962 163
Lightship Weight 671.7 31.1 6.0 0.0 20902.6 4008.9 9.9
LCG VCG TCG
Estimated FULL LOAD DISPLACEMENT 1008.3 30.0 5.9 0.2 30223 5971 173
SWBS # Section 100 Weight LCG VCG TCG L.Mom V.Mom T.Mom
100 HULL STRUCTURE, GENERAL 304957 30.52 3.52 0 9307287.64 1073448.64 0
150 DECK HOUSE STRUCTURE 114106 29.384 10.87 0 3352890.7 1240332.22 0
169 SPECIAL PURPOSE CLOSURES AND STRUCTURES 15000 27.5 7 0 412500 105000 0
TOTAL 434063 30 6 0 13072678 2418781 0
SWBS # Section 200 - Propulsion Equipment Weight LCG VCG TCG L.Mom V.Mom T.Mom
200 ENERGY GENERATING SYSTEM (NON-NUCLEAR) 72000 53.3 6.8 0 3837600 489600 0
261 FUEL SERVICE SYSTEM 2000 40 3.5 0 80000 7000 0
262 MAIN PROPULSION LUBE OIL SYSTEM 300 40 305 0 12000 91500 0
TOTAL 74300 53 8 0 3929600 588100 0
SWBS # Section 300 - Electrical Weight LCG VCG TCG L.Mom V.Mom T.Mom
311 SHIP SERVICE POWER GENERATION 4000 40 2.8 0 160000 11200 0
312 EMERGENCY GENERATORS 1750 35 13.25 0 61250 23187.5 0
313 BATTERIES AND SERVICE FACILITIES 700 40 2.8 0 28000 1960 0
321 SHIP SERVICE POWER CABLE 15500 31.3 8.25 0 485150 127875 0
324 SWITCHGEAR AND PANELS 5000 40 3 0 200000 15000 0
330 LIGHTING SYSTEM 4000 31.3 7.5 0 125200 30000 0
TOTAL 30950 34 7 0 1059600 209223 0
SWBS # Section 400 - Control and Nav Weight LCG VCG TCG L.Mom V.Mom T.Mom
410 COMMAND AND CONTROL SYSTEMS 2000 21 14.5 0 42000 29000 0
420 NAVIGATION SYSTEMS 750 21 14.5 0 15750 10875 0
430 INTERIOR COMMUNICATIONS 450 27.5 10 0 12375 4500 0
440 EXTERIOR COMMUNICATIONS 200 21 14.5 0 4200 2900 0
TOTAL 3400 22 14 0 74325 47275 0
SWBS # Section 500 - Auxiliary Equipment Weight LCG VCG TCG L.Mom V.Mom T.Mom
512 VENTILATION SYSTEM 3000 31.3 8.7 0 93900 26100 0
513 MACHINERY SPACE VENTILATION SYSTEM 2000 0 0 0 0 0 0
514 AIR CONDITIONING SYSTEM 6800 31.3 10.65 0 212840 72420 0
516 REFRIGERATION SYSTEM 4000 27.5 6 0 110000 24000 0
521 FIREMAIN & FLUSHING (SEA WATER) SYSTEM 3000 31.3 8.7 0 93900 26100 0
533 POTABLE WATER 2000 31.3 8.7 0 62600 17400 0
581 ANCHOR HANDLING AND STOWAGE SYSTEMS 10000 10 5.8 0 100000 58000 0
582 MOORING AND TOWING SYSTEMS 2000 10 5.8 0 20000 11600 0
583 BOATS, BOAT HANDLING & STOWAGE SYSTEMS 12000 33.7 11.6 0 404400 139200 0
TOTAL 44800 25 8 0 1097640 374820 0
SWBS # Section 600 - Outfit Weight LCG VCG TCG L.Mom V.Mom T.Mom
602 HULL DESIGNATING AND MARKING 150 29.5 5 0 4425 750 0
612 RAILS, STANCHIONS, AND LIFELINES 1938 36 11.6 0 69768 22480.8 0
620 HULL COMPARTMENTATION 11.96 33 8.7 0 394.68 104.052 0
631 PAINTING 8000 29.4 7.2 0 235200 57600 0
633 CATHODIC PROTECTION 300 32.5 2 0 9750 600 0
634 DECK COVERING 30000 33 7 0 990000 210000 0
638 REFRIGERATED SPACES 0 0 0 0 0 0 0
6411 OFFICER BERTHING SPACES 500 30.5 13.5 0 15250 6750 0
6412 OFFICER MESSING SPACES 0 0 0 0 0 0 0
643 ENLISTED PERSONNEL BERTHING AND MESSING
SPACES 2500 23 3.4 8 57500 8500 20000
644 SANITARY SPACES AND FIXTURES 4416 33 8.7 0 145728 38419.2 0
645 LEISURE AND COMMUNITY SPACES 200 31.5 3.4 8 6300 680 1600
655 LAUNDRY SPACES 640 21.8 3.4 -10.4 13952 2176 -6656
656 TRASH DISPOSAL SPACES 500 19 6.3 -10 9500 3150 -5000
665 WORKSHOPS, LABS, TEST AREAS (INCL PORTABLE
TOOLS, EQUIP) 2000 47 6.5 0 94000 13000 0
672 STOREROOMS AND ISSUE ROOMS 1000 17 6.5 0 17000 6500 0
TOTAL 52156 32 7 0 1668768 370710 9944
SW
BS
10
0: H
UL
L S
TR
UC
TU
RE
, G
EN
ER
AL
(show
ing a
ll of S
WB
S lvl
1,2
,3)
Item
Description
g/e
/sLength
Wid
thA
rea
Qty
U.
Wt
Weig
ht
LC
GV
CG
TC
GL.M
om
V.M
om
T.M
om
Note
s
mm
sq m
#U
kg/U
kg
mm
m
100
HU
LL
ST
RU
CT
UR
E,
GE
NE
RA
L
Fro
m P
are
nt
Sh
ip -
No
rth
Isl
an
d P
rin
ce
sse
304957
30.5
23.5
20
9307287.6
41073448.6
40
Centr
oid
of 3D
volu
me u
sed
110
SH
ELL A
ND
SU
PP
OR
TIN
G S
TR
UC
TU
RE
0
00
110
SH
ELL A
ND
SU
PP
OR
TIN
G S
TR
UC
TU
RE
0
00
111
SH
ELL P
LA
TIN
G,
SU
RF
AC
E S
HIP
AN
D S
UB
MA
RIN
E P
RE
SS
UR
E
HU
LL
00
0
112
SH
ELL P
LA
TIN
G,
SU
BM
AR
INE
NO
N-P
RE
SS
UR
E H
ULL
00
0
114
SH
ELL A
PP
EN
DA
GE
S
0
00
117
TR
AN
SV
. F
RA
MIN
G,
SU
RF
AC
E S
HIP
AN
D S
UB
MA
RIN
E P
RE
SS
UR
E
HU
LL
0
00
118
LO
NG
ITU
DIN
AL A
ND
TR
AN
SV
ER
SE
SU
BM
AR
INE
NO
N-P
RE
SS
UR
E
HU
LL
00
0
119
LIF
T S
YS
TE
M F
LE
XIB
LE
SK
IRTS
AN
D S
EA
LS
00
0
120
HU
LL S
TR
UC
TU
RA
L B
ULK
HE
AD
S
0
00
121
LO
NG
ITU
DIN
AL S
TR
UC
TU
RA
L B
ULK
HE
AD
S
0
00
122
TR
AN
SV
ER
SE
STR
UC
TU
RA
L B
ULK
HE
AD
S
00
0
123
TR
UN
KS
AN
D E
NC
LO
SU
RE
S
0
00
125
SU
BM
AR
INE
HA
RD
TA
NK
S
0
00
126
SU
BM
AR
INE
SO
FT T
AN
KS
00
0
130
HU
LL D
EC
KS
0
00
131
MA
IN D
EC
K
0
00
140
HU
LL P
LA
TF
OR
MS
AN
D F
LA
TS
00
0
141
1S
T P
LA
TF
OR
M
0
00
150
DE
CK
HO
US
E S
TR
UC
TU
RE
Ba
sed
on
Au
toC
AD
dra
win
ge
114106
29.3
84
10.8
70
3352890.7
1240332.2
20
151
DE
CK
HO
US
E S
TR
UC
TU
RE
TO
FIR
ST L
EV
EL
00
0
152
1S
T D
EC
KH
OU
SE
LE
VE
L
00
0
160
SP
EC
IAL S
TR
UC
TU
RE
S
00
0
161
STR
UC
TU
RA
L C
AS
TIN
GS
, F
OR
GIN
GS
, A
ND
EQ
UIV
. W
ELD
ME
NTS
0
00
163
SE
A C
HE
STS
0
00
164
BA
LLIS
TIC
PLA
TIN
G
0
00
165
SO
NA
R D
OM
ES
0
00
167
HU
LL S
TR
UC
TU
RA
L C
LO
SU
RE
S
0
00
168
DE
CK
HO
US
E S
TR
UC
TU
RA
L C
LO
SU
RE
S
0
00
169
SP
EC
IAL P
UR
PO
SE
CLO
SU
RE
S A
ND
STR
UC
TU
RE
S
Bo
w a
nd
ste
rn e
lectr
ic q
ua
rte
r ra
mp
sg
15000
27.5
70
412500
105000
0V
ery
rough g
uess
170
MA
STS
, K
ING
PO
STS
, A
ND
SE
RV
ICE
PLA
TF
OR
MS
0
00
171
MA
STS
, TO
WE
RS
, TE
TR
AP
OD
S
0
00
172
KIN
GP
OS
TS
AN
D S
UP
PO
RT F
RA
ME
S
0
00
180
FO
UN
DA
TIO
NS
0
00
184
CO
MM
AN
D A
ND
SU
RV
EIL
LA
NC
E F
OU
ND
ATIO
NS
00
0
190
SP
EC
IAL P
UR
PO
SE
SY
STE
MS
0
00
191
BA
LLA
ST,
FIX
ED
OR
FLU
ID,
AN
D B
UO
YA
NC
Y U
NIT
S
00
0
192
CO
MP
AR
TM
EN
T T
ES
TIN
G
00
0
199
HU
LL R
EP
AIR
PA
RTS
AN
D S
PE
CIA
L T
OO
LS
0
00
100 T
OTA
L:
434063
13072678.3
2418780.8
60
# o
f E
ntr
ies
3
SW
BS
#
g =
guess
e =
estim
ate
s =
supplie
r
SW
BS
20
0: P
RO
PU
LS
ION
PL
AN
T, G
EN
ER
AL
(show
ing a
ll of S
WB
S lvl
1,2
,3)
Item
Description
g/e
/sLength
Wid
thA
rea
Qty
U.
Wt
Weig
ht
LC
GV
CG
TC
GL.M
om
V.M
om
T.M
om
Note
s
mm
sq m
#U
kg/U
kg
mm
m
220
EN
ER
GY
GE
NE
RA
TIN
G S
YS
TE
M (
NO
N-N
UC
LE
AR
)
Schott
el N
AV
IGA
TO
R 5
50
s4
18000
72000
53.3
6.8
03837600
489600
0D
im t
o c
ente
r of conta
iner,
supplie
d D
RY
221
PR
OP
ULS
ION
BO
ILE
RS
0
00
223
MA
IN P
RO
PU
LS
ION
BA
TTE
RIE
S
0
00
223
PR
OP
ULS
ION
STE
AM
TU
RB
INE
S
0
00
223
PR
OP
ULS
ION
IN
TE
RN
AL C
OM
BU
STIO
N E
NG
INE
S
00
0
230
PR
OP
UL
SIO
N U
NIT
S
0
00
234
PR
OP
ULS
ION
GA
S T
UR
BIN
ES
0
00
235
ELE
CTR
IC P
RO
PU
LS
ION
0
00
237
AU
XIL
IAR
Y P
RO
PU
LS
ION
DE
VIC
ES
00
0
238
SE
CO
ND
AR
Y P
RO
PU
LS
ION
00
0
239
EM
ER
GE
NC
Y P
RO
PU
LS
ION
00
0
240
TR
AN
SM
ISS
ION
AN
D P
RO
PU
LS
OR
SY
ST
EM
S
s0
00
241
PR
OP
ULS
ION
RE
DU
CTIO
N G
EA
RS
0
00
242
PR
OP
ULS
ION
CLU
TC
HE
S A
ND
CO
UP
LIN
GS
00
0
243
PR
OP
ULS
ION
SH
AF
TIN
G
00
0
244
PR
OP
ULS
ION
SH
AF
T B
EA
RIN
GS
00
0
245
PR
OP
ULS
OR
S
00
0
246
PR
OP
ULS
OR
SH
RO
UD
S A
ND
DU
CTS
0
00
247
WA
TE
R J
ET P
RO
PU
LS
OR
S
0
00
248
LIF
T S
YS
TE
M F
AN
S A
ND
DU
CTIN
G
0
00
250
PR
OP
UL
SIO
N S
UP
PO
RT
SY
S.
(EX
CE
PT
FU
EL
AN
D L
UB
E
OIL
)
00
0
251
CO
MB
US
TIO
N A
IR S
YS
TE
M
0
00
252
PR
OP
ULS
ION
CO
NTR
OL S
YS
TE
M
0
00
need?
253
MA
IN S
TE
AM
PIP
ING
SY
STE
M
0
00
254
CO
ND
EN
SE
RS
AN
D A
IR E
JEC
TO
RS
0
00
255
FE
ED
AN
D C
ON
DE
NS
ATE
SY
STE
M
00
0
256
CIR
CU
LA
TIN
G A
ND
CO
OLIN
G S
EA
WA
TE
R S
YS
TE
M
0
00
257
Reserv
e F
eed a
nd T
ransfe
r S
yste
m
0
00
258
HP
STE
AM
DR
AIN
SY
STE
M
0
00
259
UP
TA
KE
S (
INN
ER
CA
SIN
G)
0
00
260
PR
OP
UL
SIO
N S
UP
PO
RT
SY
ST
EM
S (
FU
EL
AN
D L
UB
E
OIL
)
00
0need?
261
FU
EL S
ER
VIC
E S
YS
TE
M
Fuel pum
ps,
fuel handlin
ge
2000
40
3.5
080000
7000
0ra
cio
cin
ate
d,
does n
ot
inclu
de p
ipin
g
262
MA
IN P
RO
PU
LS
ION
LU
BE
OIL
SY
STE
M
300
40
305
012000
91500
0ra
cio
cin
ate
d
264
LU
BE
OIL
FIL
L,
TR
AN
SF
ER
, A
ND
PU
RIF
ICA
TIO
N
0
00
need?
29000
SP
EC
IAL
PU
RP
OS
E S
YS
TE
MS
0
00
299
PR
OP
ULS
ION
PLA
NT R
EP
AIR
PA
RTS
AN
D S
PE
CIA
L
TO
OLS
00
0need?
200 T
OTA
L:
74300
3929600
588100
0
# o
f E
ntr
ies
3
g =
guess
e =
estim
ate
s =
supplie
r
SW
BS
#
SW
BS
300:
Ele
ctr
ical
(show
ing a
ll of S
WB
S lvl
1,2
,3)
Item
Description
g/e
/sLength
Wid
thA
rea
Qty
U.
Wt
Weig
ht
LC
GV
CG
TC
GL.M
om
V.M
om
T.M
om
Note
s
mm
sq m
#U
kg/U
kg
mm
m
310
EL
EC
TR
IC P
OW
ER
GE
NE
RA
TIO
N
0
00
0
311
SH
IP S
ER
VIC
E P
OW
ER
GE
NE
RA
TIO
N
C
AT
C18,
450 e
kW
ma
xs
22000
4000
40
2.8
0160000
11200
0
312
EM
ER
GE
NC
Y G
EN
ER
ATO
RS
CA
T C
9,
250 e
kW
ma
xs
11750
1750
35
13.2
50
61250
23187.5
0
313
BA
TTE
RIE
S A
ND
SE
RV
ICE
FA
CIL
ITIE
S
S
tart
ing
Ba
tte
rie
sg
1700
700
40
2.8
028000
1960
0R
atiocin
ate
d
314
PO
WE
R C
ON
VE
RS
ION
EQ
UIP
ME
NT
00
00
320
PO
WE
R D
IST
RIB
UT
ION
SY
ST
EM
S
00
00
321
SH
IP S
ER
VIC
E P
OW
ER
CA
BLE
g1
15500
15500
31.3
8.2
50
485150
127875
0In
clu
des s
hore
pow
er
connection
322
EM
ER
GE
NC
Y P
OW
ER
CA
BLE
SY
STE
M
0
00
0
323
CA
SU
ALTY
PO
WE
R C
AB
LE
SY
STE
M
00
00
324
SW
ITC
HG
EA
R A
ND
PA
NE
LS
g1
5000
5000
40
30
200000
15000
0R
atiocin
ate
d
325
AR
C F
AU
LT D
ETE
CTO
R (
AF
D)
SY
STE
MS
00
00
330
LIG
HT
ING
SY
ST
EM
g
14000
4000
31.3
7.5
0125200
30000
0R
atiocin
ate
d
331
LIG
HTIN
G D
ISTR
IBU
TIO
N
0
00
0
332
LIG
HTIN
G F
IXTU
RE
S
0
00
0
340
PO
WE
R G
EN
ER
AT
ION
SU
PP
OR
T S
YS
TE
MS
00
00
341
SS
TG
LU
BE
OIL
00
00
342
DIE
SE
L S
UP
PO
RT S
YS
TE
MS
0
00
0
343
TU
RB
INE
SU
PP
OR
T S
YS
TE
MS
0
00
0
390
SP
EC
IAL
PU
RP
OS
E S
YS
TE
MS
0
00
0
399
ELE
CTR
IC P
LA
NT R
EP
AIR
PA
RTS
AN
D S
PE
CIA
L T
OO
LS
00
00
300 T
OT
AL
:30950
1059600
209222.5
0
g =
guess
e =
estim
ate
s =
supplie
r
SW
BS
#
SW
BS
400:
Com
mand a
nd s
urv
eill
ance,
Genera
l
(show
ing a
ll of S
WB
S lvl
1,2
,3)
Item
Description
g/e
/sLength
Wid
thA
rea
Qty
U.
Wt
Weig
ht
LC
GV
CG
TC
GL.M
om
V.M
om
T.M
om
Note
s
mm
sq m
#U
kg/U
kg
mm
m
400
CO
MM
AN
D A
ND
SU
RV
EIL
LA
NC
E,
GE
NE
RA
L
0
00
0
407
ELE
CTR
OM
AG
NE
TIC
IN
TE
RF
ER
EN
CE
RE
DU
CTIO
N (
EM
I)
0
00
0
410
CO
MM
AN
D A
ND
CO
NT
RO
L S
YS
TE
MS
g
2000
21
14.5
042000
29000
0ra
cio
cin
ate
d
4110
0
DA
TA
DIS
PLA
Y G
RO
UP
0
00
0
412
DA
TA
PR
OC
ES
SIN
G G
RO
UP
00
00
414
INTE
RF
AC
E E
QU
IPM
EN
T
00
00
415
DIG
ITA
L D
ATA
CO
MM
UN
ICA
TIO
NS
0
00
0
420
NA
VIG
AT
ION
SY
ST
EM
S
g750
21
14.5
015750
10875
0ra
cio
cin
ate
d
421
NO
N-E
LE
CTR
ICA
L/N
ON
-ELE
CTR
ON
IC N
AV
IGA
TIO
N A
IDS
00
00
422
ELE
CTR
ICA
L N
AV
IGA
TIO
N A
IDS
(IN
CL N
AV
IG.
LIG
HTS
)
0
00
0
423
ELE
CTR
ON
IC N
AV
IGA
TIO
N S
YS
TE
MS
00
00
424
ELE
CTR
ON
IC N
AV
IGA
TIO
N S
YS
TE
MS
, A
CO
US
TIC
AL
0
00
0
425
PE
RIS
CO
PE
S
00
00
426
ELE
CTR
ICA
L N
AV
IGA
TIO
N S
YS
TE
MS
00
00
427
INE
RTIA
L N
AV
IGA
TIO
N S
YS
TE
MS
0
00
0
428
NA
VIG
ATIO
N C
ON
TR
OL M
ON
ITO
RIN
G
0
00
0
430
INT
ER
IOR
CO
MM
UN
ICA
TIO
NS
g
450
27.5
10
012375
4500
0M
onitoring,
Ala
rm,
warn
ing s
yste
ms inclu
ded
431
SW
ITC
HB
OA
RD
S F
OR
IN
TE
RIO
R C
OM
MU
NIC
ATIO
N
SY
STE
MS
00
00
432
TE
LE
PH
ON
E S
YS
TE
MS
00
00
433
AN
NO
UN
CIN
G S
YS
TE
MS
0
00
0
434
EN
TE
RTA
INM
EN
T A
ND
TR
AIN
ING
SY
STE
MS
0
00
0
435
VO
ICE
TU
BE
S A
ND
ME
SS
AG
E P
AS
SIN
G S
YS
TE
MS
0
00
0
436
ALA
RM
, S
AF
ETY
, A
ND
WA
RN
ING
SY
STE
MS
0
00
0
437
IND
ICA
TIN
G,
OR
DE
R,
AN
D M
ETE
RIN
G S
YS
TE
MS
0
00
0
438
CO
NS
OLID
ATE
D C
ON
TR
OL A
ND
DIS
PLA
Y S
YS
TE
MS
00
00
439
RE
CO
RD
ING
AN
D T
ELE
VIS
ION
SY
STE
MS
00
00
440
EX
TE
RIO
R C
OM
MU
NIC
AT
ION
S
g200
21
14.5
04200
2900
0
441
RA
DIO
SY
STE
MS
00
00
442
UN
DE
RW
ATE
R S
YS
TE
MS
0
00
0
443
VIS
UA
L A
ND
AU
DIB
LE
CO
MM
UN
ICA
TIO
N S
YS
TE
MS
00
00
445
TE
LE
TY
PE
AN
D F
AC
SIM
ILE
SY
STE
MS
0
00
0
446
SE
CU
RIT
Y E
QU
IPM
EN
T S
YS
TE
MS
0
00
0
450
SU
RV
EIL
LA
NC
E S
YS
TE
MS
, S
UR
FA
CE
AN
D A
IR
0
00
0
451
SU
RF
AC
E S
UR
VE
ILLA
NC
E R
AD
AR
SY
STE
MS
0
00
0
452
2D
AIR
RA
DA
R S
YS
TE
MS
00
00
453
3D
AIR
RA
DA
R S
YS
TE
MS
00
00
454
AIR
CR
AF
T C
ON
TR
OL R
AD
AR
SY
STE
MS
0
00
0
455
IDE
NTIF
ICA
TIO
N S
YS
TE
MS
0
00
0
456
MU
LTI-F
UN
CTIO
N R
AD
AR
SY
STE
MS
00
00
457
INF
RA
RE
D S
UR
VE
ILLA
NC
E A
ND
TR
AC
KIN
G S
YS
TE
MS
0
00
0
458
AU
TO
MA
TIC
DE
TE
CTIO
N A
ND
TR
AC
KIN
G S
YS
TE
MS
00
00
460
SU
RV
EIL
LA
NC
E S
YS
TE
MS
(U
ND
ER
WA
TE
R)
0
00
0
470
CO
UN
TE
RM
EA
SU
RE
SY
ST
EM
S
00
00
480
FIR
E C
ON
TR
OL
SY
ST
EM
S
0
00
0
481
GU
N F
IRE
CO
NTR
OL S
YS
TE
MS
00
00
482
MIS
SIL
E F
IRE
CO
NTR
OL S
YS
TE
MS
00
00
483
UN
DE
RW
ATE
R F
IRE
CO
NTR
OL S
YS
TE
MS
0
00
0
484
INTE
GR
ATE
D F
IRE
CO
NTR
OL S
YS
TE
MS
0
00
0
489
WE
AP
ON
SY
STE
MS
SW
ITC
HB
OA
RD
S
00
00
490
SP
EC
IAL
PU
RP
OS
E S
YS
TE
MS
0
00
0
491
ELE
CTR
ON
IC T
ES
T,
CH
EC
KO
UT,
AN
D M
ON
ITO
RIN
G
EQ
UIP
ME
NT
00
00
492
FLIG
HT C
ON
TR
OL A
ND
IN
STR
UM
EN
T L
AN
DIN
G S
YS
TE
MS
00
00
493
AU
TO
MA
TE
D D
ATA
PR
OC
ES
SIN
G S
YS
TE
MS
(N
ON
-
CO
MB
AT)
00
00
494
ME
TE
OR
OLO
GIC
AL S
YS
TE
MS
0
00
0
495
SP
EC
IAL P
UR
PO
SE
IN
TE
LLIG
EN
CE
SY
STE
MS
00
00
499
CO
MM
AN
D A
ND
SU
RV
. R
EP
AIR
PA
RTS
AN
D S
PE
CIA
L
TO
OLS
00
00
00
00
500 T
OTA
L:
3400
74325
47275
0
g =
guess
e =
estim
ate
s =
supplie
r
SW
BS
#
SW
BS
500:
Auxili
ary
Syste
ms
g =
guess
e =
estim
ate
(show
ing a
ll of S
WB
S lvl
1,2
,3)
s =
supplie
r
Item
Description
g/e
/sLength
Wid
thA
rea
Qty
U.
Wt
Weig
ht
LC
GV
CG
TC
GL.M
om
V.M
om
T.M
om
Note
s
mm
sq m
#U
kg/U
kg
mm
m
500
AU
XIL
IAR
Y S
YS
TE
MS
, G
EN
ER
AL
0
00
0
508
TH
ER
MA
L IN
SU
LA
TIO
N F
OR
PIP
ING
AN
D M
AC
HIN
ER
Y
g0
00
0
510
CL
IMA
TE
CO
NT
RO
L
00
00
511
CO
MP
AR
TM
EN
T H
EA
TIN
G S
YS
TE
M
00
00
512
VE
NTIL
ATIO
N S
YS
TE
M
Fa
ns,
fil
ters
, d
ucts
, lo
uve
rs,
etc
.e
3000
31.3
8.7
093900
26100
0scale
d fro
m k
g/m
2 o
f S
cie
nce v
essel II
513
MA
CH
INE
RY
SP
AC
E V
EN
TIL
ATIO
N S
YS
TE
M
e2000
00
0ra
cio
cin
ate
d
514
AIR
CO
ND
ITIO
NIN
G S
YS
TE
M
AC
Un
its,
du
cts
, e
tce
6800
31.3
10.6
50
212840
72420
0scale
d fro
m k
g/m
2 o
f S
cie
nce v
essel II
515
AIR
RE
VIT
ALIZ
ATIO
N S
YS
TE
MS
(S
UB
MA
RIN
ES
)
0
00
0
516
RE
FR
IGE
RA
TIO
N S
YS
TE
M
C
om
pre
sso
r, c
on
de
nso
r, f
an
s, p
ipin
gg
4000
27.5
60
110000
24000
0m
inim
um
valu
e fro
m r
atiocin
ations,
for
a s
tora
ge r
oom
?
517
AU
XIL
IAR
Y B
OIL
ER
S A
ND
OTH
ER
HE
AT S
OU
RC
ES
00
00
00
00
520
SE
A W
AT
ER
SY
ST
EM
S
0
00
0
521
FIR
EM
AIN
AN
D F
LU
SH
ING
(S
EA
WA
TE
R)
SY
STE
M
e
3000
31.3
8.7
093900
26100
0In
clu
des
522
SP
RIN
KLE
R S
YS
TE
M
g
00
00
523
WA
SH
DO
WN
SY
STE
M
00
00
524
AU
XIL
IAR
Y S
EA
WA
TE
R S
YS
TE
M
00
00
526
SC
UP
PE
RS
AN
D D
EC
K D
RA
INS
00
00
528
PLU
MB
ING
DR
AIN
AG
E
0
00
0
529
DR
AIN
AG
E A
ND
BA
LLA
STIN
G S
YS
TE
M
00
00
00
00
530
FR
ES
H W
AT
ER
SY
ST
EM
S
00
00
531
DIS
TIL
LIN
G P
LA
NT
0
00
0
532
CO
OLIN
G W
ATE
R
0
00
0
533
PO
TA
BLE
WA
TE
R
e
2000
31.3
8.7
062600
17400
0ra
cio
cin
ate
d
534
AU
XIL
IAR
Y S
TE
AM
AN
D D
RA
INS
WIT
HIN
MA
CH
INE
RY
BO
X
00
00
535
AU
XIL
IAR
Y S
TE
AM
AN
D D
RA
INS
OU
TS
IDE
MA
CH
INE
RY
BO
X
00
00
536
AU
XIL
IAR
Y F
RE
SH
WA
TE
R C
OO
LIN
G
0
00
0
539
AU
XIL
IAR
Y F
RE
SH
WA
TE
R C
OO
LIN
G
0
00
0
00
00
540
FU
EL
S A
ND
LU
BR
ICA
NT
S,
HA
ND
LIN
G A
ND
ST
OR
AG
E
00
00
541
SH
IP F
UE
L A
ND
FU
EL C
OM
PE
NS
ATIN
G S
YS
TE
M
Pum
ps t
o m
ove
fuel betw
een t
anks
g0
00
0
542
AV
IATIO
N A
ND
GE
NE
RA
L P
UR
PO
SE
FU
ELS
0
00
0
543
AV
IATIO
N A
ND
GE
NE
RA
L P
UR
PO
SE
LU
BR
ICA
TIN
G O
IL
0
00
0
544
LIQ
UID
CA
RG
O
0
00
0
545
TA
NK
HE
ATIN
G
0
00
0
546
AU
XIL
IAR
Y L
UB
RIC
ATIO
N S
YS
TE
MS
00
00
00
00
550
AIR
, G
AS
, A
ND
MIS
CE
LL
AN
EO
US
FL
UID
SY
ST
EM
S
0
00
0
551
CO
MP
RE
SS
ED
AIR
SY
STE
MS
0
00
0
552
CO
MP
RE
SS
ED
GA
SE
S
0
00
0
553
O2 N
2 S
YS
TE
M
0
00
0
554
MA
IN B
ALLA
ST T
AN
K B
LO
W A
ND
LIS
T C
ON
TR
OL
SY
STE
M
00
00
555
FIR
E E
XTIN
GU
ISH
ING
SY
STE
MS
C
arb
on D
ioxid
e a
nd c
hem
ical fix
ed/p
ort
able
syste
ms
g0
00
0
556
HY
DR
AU
LIC
FLU
ID S
YS
TE
M
00
00
558
SP
EC
IAL P
IPIN
G S
YS
TE
MS
0
00
0
00
00
560
SH
IP C
ON
TR
OL
SY
ST
EM
S
0
00
0
561
STE
ER
ING
AN
D D
IVIN
G C
ON
TR
OL S
YS
TE
MS
0
00
0
562
RU
DD
ER
0
00
0
563
HO
VE
RIN
G A
ND
DE
PTH
CO
NTR
OL (
SU
BM
AR
INE
)
00
00
564
TR
IM A
ND
DR
AIN
SY
STE
MS
(S
UB
MA
RIN
ES
)
0
00
0
565
TR
IM A
ND
HE
EL S
YS
TE
MS
(S
UR
FA
CE
SH
IPS
)
00
00
566
DIV
ING
PLA
NE
S A
ND
STA
BIL
IZIN
G F
INS
(S
UB
MA
RIN
ES
)
0
00
0
567
STR
UT A
ND
FO
IL S
YS
TE
MS
0
00
0
568
MA
NE
UV
ER
ING
SY
STE
MS
0
00
0
00
00
570
RE
PL
EN
ISH
ME
NT
SY
ST
EM
S
0
00
0
570
RE
PLE
NIS
HM
EN
T S
YS
TE
MS
00
00
571
RE
PLE
NIS
HM
EN
T-A
T-S
EA
SY
STE
MS
00
00
572
SH
IP S
TO
RE
S A
ND
EQ
UIP
ME
NT H
AN
DLIN
G S
YS
TE
MS
0
00
0
573
CA
RG
O H
AN
DLIN
G S
YS
TE
MS
0
00
0
574
VE
RTIC
AL R
EP
LE
NIS
HM
EN
T S
YS
TE
MS
0
00
0
00
00
580
ME
CH
AN
ICA
L H
AN
DL
ING
SY
ST
EM
S
00
00
581
AN
CH
OR
HA
ND
LIN
G A
ND
STO
WA
GE
SY
STE
MS
In
clu
de
s th
e A
nch
or,
ro
de
, w
ind
lass
e10000
10
5.8
0100000
58000
0A
ssum
e v
ery
sim
ilar
to 4
5m
tug r
ef. 2
Anchors
not
req if 1 k
ept
in p
ort
582
MO
OR
ING
AN
D T
OW
ING
SY
STE
MS
C
ap
sta
ns,
mo
ori
ng
fit
tin
gs
an
d c
om
po
ne
nts
g2000
10
5.8
020000
11600
0
583
BO
ATS
, B
OA
T H
AN
DLIN
G A
ND
STO
WA
GE
SY
STE
MS
All
bo
ats
an
d r
igg
ing
, li
fesa
vin
g e
qu
ipm
en
tg
12000
33.7
11.6
0404400
139200
0
584
LA
ND
ING
CR
AF
T H
AN
DLIN
G A
ND
STO
WA
GE
SY
STE
MS
0
00
0
585
ELE
VA
TIN
G A
ND
RE
TR
AC
TIN
G G
EA
R
0
00
0
586
AIR
CR
AF
T R
EC
OV
ER
Y S
UP
PO
RT S
YS
TE
MS
00
00
587
AIR
CR
AF
T L
AU
NC
H S
UP
PO
RT S
YS
TE
MS
0
00
0
588
AIR
CR
AF
T H
AN
DLIN
G,
SE
RV
ICIN
G A
ND
STO
WA
GE
00
00
589
MIS
CE
LLA
NE
OU
S M
EC
HA
NIC
AL H
AN
DLIN
G S
YS
TE
MS
00
00
587
MIS
CE
LLA
NE
OU
S M
EC
HA
NIC
AL H
AN
DLIN
G S
YS
TE
MS
00
00
00
00
590
SP
EC
IAL
PU
RP
OS
E S
YS
TE
MS
0
00
0
592
SW
IMM
ER
AN
D D
IVE
R S
UP
PO
RT A
ND
PR
OTE
CTIO
N
SY
STE
MS
00
00
593
EN
VIR
ON
ME
NTA
L P
OLLU
TIO
N C
ON
TR
OL S
YS
TE
MS
0
00
0
594
SU
BM
AR
INE
RE
SC
UE
, S
ALV
AG
E,
AN
D S
UR
VIV
AL
SY
STE
MS
00
00
595
TO
WIN
G,
LA
UN
CH
ING
AN
D H
AN
DLIN
G F
OR
UN
DE
RW
ATE
R S
YS
.
00
00
597
SA
LV
AG
E S
UP
PO
RT S
YS
TE
MS
0
00
0
599
AU
XIL
IAR
Y S
YS
TE
MS
RE
PA
IR P
AR
TS
AN
D T
OO
LS
g0
00
0
500 T
OTA
L:
44800
1097640
374820
0
SW
BS
#
SW
BS
600:
Outfit a
nd F
urn
ishin
gs
(show
ing a
ll of S
WB
S lvl
1,2
,3)
Item
Description
g/e
/sLength
Wid
thA
rea
Qty
U.
Wt
Weig
ht
LC
GV
CG
TC
GL.M
om
V.M
om
T.M
om
Note
s
mm
sq m
#U
kg/U
kg
mm
m
600
OU
TF
IT A
ND
FU
RN
ISH
ING
S,
GE
NE
RA
L
00
00
602
HU
LL D
ES
IGN
ATIN
G A
ND
MA
RK
ING
Sh
ip's
na
me
, lo
go
, h
om
ep
ort
, o
the
r si
gn
ag
eg
150
29.5
50
4425
750
0A
ssum
e s
am
e a
s r
ef ve
ssel allo
wance
00
00
610
SH
IP F
ITT
ING
S
0
00
0
611
HU
LL F
ITTIN
GS
00
00
612
RA
ILS
, S
TA
NC
HIO
NS
, A
ND
LIF
ELIN
ES
e190
10.2
1938
36
11.6
069768
22480.8
0U
nit w
eig
ht
for
raili
ngs fro
m R
AL
613
RIG
GIN
G A
ND
CA
NV
AS
0
00
0
00
00
620
HU
LL
CO
MP
AR
TM
EN
TA
TIO
N
e
11.9
633
8.7
0394.6
8104.0
52
0calc
ula
ted b
ased o
n a
reas
621
NO
N-S
TR
UC
TU
RA
L B
ULK
HE
AD
S
0
00
0
622
FLO
OR
PLA
TE
S A
ND
GR
ATIN
GS
00
00
623
LA
DD
ER
S
00
00
624
NO
N-S
TR
UC
TU
RA
L C
LO
SU
RE
S
00
00
All
the n
on-s
tructu
ral doors
625
AIR
PO
RTS
, F
IXE
D P
OR
TLIG
HTS
, A
ND
WIN
DO
WS
0
00
0
00
00
630
PR
ES
ER
VA
TIV
ES
AN
D C
OV
ER
ING
S
00
00
630
PR
ES
ER
VA
TIV
ES
AN
D C
OV
ER
ING
S
00
00
631
PA
INTIN
G
e
8000
29.4
7.2
0235200
57600
0appro
x 2
% o
f gro
up 1
00 w
eig
ht
632
ZIN
C A
ND
ME
TA
LLIC
CO
ATIN
GS
0
00
0
633
CA
TH
OD
IC P
RO
TE
CTIO
N
g300
32.5
20
9750
600
0
634
DE
CK
CO
VE
RIN
G
e
30000
33
70
990000
210000
0calc
ula
ted b
ased o
n a
reas
635
HU
LL IN
SU
LA
TIO
N
00
00
636
HU
LL D
AM
PIN
G
0
00
0
637
SH
EA
TH
ING
00
00
638
RE
FR
IGE
RA
TE
D S
PA
CE
S
g0
00
0
639
RA
DIA
TIO
N S
HIE
LD
ING
0
00
0
00
00
640
LIV
ING
SP
AC
ES
00
00
641
OF
FIC
ER
BE
RTH
ING
AN
D M
ES
SIN
G S
PA
CE
S
00
00
6411
OF
FIC
ER
BE
RTH
ING
SP
AC
ES
Off
ice
r/P
ass
en
ge
r b
ert
hin
g o
utf
it/f
urn
ish
ing
sg
20
100
500
30.5
13.5
015250
6750
0
6412
OF
FIC
ER
ME
SS
ING
SP
AC
ES
Off
ice
r/p
ass
en
ge
r m
ess
ing
ou
tfit
/fu
rnis
hin
gs
g0
00
642
NO
NC
OM
MIS
SIO
NE
D O
FF
ICE
R B
ER
TH
ING
AN
D M
ES
SIN
G
SP
AC
ES
00
00
643
EN
LIS
TE
D P
ER
SO
NN
EL B
ER
TH
ING
AN
D M
ES
SIN
G
SP
AC
ES
Be
rth
ing
fo
r a
ll o
the
r cre
w +
me
ssin
g s
pa
ce
s2500
23
3.4
857500
8500
20000
Weig
ht
for
a m
ess fro
m r
efe
rence v
essels
, B
ert
h is 1
00 k
g
644
SA
NIT
AR
Y S
PA
CE
S A
ND
FIX
TU
RE
S
55.2
80
4416
33
8.7
0145728
38419.2
0C
oeffi
cie
nt
- "S
yste
m b
ased s
hip
desig
n"
645
LE
ISU
RE
AN
D C
OM
MU
NIT
Y S
PA
CE
S
D
ay R
oo
m f
or
cre
w200
31.5
3.4
86300
680
1600
00
00
650
SE
RV
ICE
SP
AC
ES
g
00
00
651
CO
MM
ISS
AR
Y S
PA
CE
S
0
00
0
652
ME
DIC
AL S
PA
CE
S
00
00
653
DE
NTA
L S
PA
CE
S
0
00
0
654
UTIL
ITY
SP
AC
ES
0
00
0
655
LA
UN
DR
Y S
PA
CE
S
La
un
dry
g4
160
640
21.8
3.4
-10.4
13952
2176
-6656
kg/m
2 first
appro
xim
ation fro
m "
syste
m b
ased s
hip
desig
n"
656
TR
AS
H D
ISP
OS
AL S
PA
CE
S
G
arb
ag
e h
an
dli
ng
sp
ace
g10
50
500
19
6.3
-10
9500
3150
-5000
kg/m
2 g
uess
00
00
660
WO
RK
ING
SP
AC
ES
g
00
00
661
OF
FIC
ES
0
00
0
662
MA
CH
INE
RY
CO
NTR
OL C
EN
TE
RS
FU
RN
ISH
ING
S
0
00
0
663
ELE
CTR
ON
ICS
CO
NTR
OL C
EN
TE
RS
FU
RN
ISH
ING
S
00
00
664
DA
MA
GE
CO
NTR
OL S
TA
TIO
NS
0
00
0
665
WO
RK
SH
OP
S,
LA
BS
, TE
ST A
RE
AS
(IN
CL P
OR
TA
BLE
TO
OLS
, E
QU
IP)
Wo
rksh
op
g20
100
2000
47
6.5
094000
13000
0kg/m
2 g
uess
00
00
670
ST
OW
AG
E S
PA
CE
S
g0
00
0
671
LO
CK
ER
S A
ND
SP
EC
IAL S
TO
WA
GE
0
00
0
672
STO
RE
RO
OM
S A
ND
IS
SU
E R
OO
MS
g
1000
17
6.5
017000
6500
0to
tally
a g
uess,
all
sto
re-r
oom
s o
n t
he s
hip
673
CA
RG
O S
TO
WA
GE
00
00
00
00
690
SP
EC
IAL
PU
RP
OS
E S
YS
TE
MS
0
00
0
699
OU
TF
IT A
ND
FU
RN
ISH
. R
EP
AIR
PA
RTS
AN
D S
PE
CIA
L
TO
OLS
00
00
600 T
OTA
L:
52,1
56
1668767.6
8370710.0
52
9944
g =
guess
e =
estim
ate
s =
supplie
r
SW
BS
#
18.9.1. STRUCTURAL WEIGHT
Legend
Input
Measured from drawing
Modified to OURSHIP
Not shown in NIP, designed for OURSHIP
SUMMARY
Deck Level Pax
Frame, ton Web, ton Frame, ton Web, ton Frame, ton Web, ton Frame, ton Web, ton
SUM 0.42 0.42 0.88 0.88 0.74 0.97 0.31 0.31
BridgeMid-Pax
SUMMARY
Frame, ton Web, ton
Components 1.14 3.30
Plating 2.21 2.21
SUM 3.35 5.51
HULL
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Forward Mid-ship ComponentsR Right longitudinals LONGS 152x102x18.3KG/M 9 18.3 90.6
R Right FB vert. cross LONGS 76x8 FB 8 610 5 FB 76 0.0018544 14.6
R Right T shape docking girder web (same as left) 8 305 1 2440 0.00244 10.5
R Right T shape docking girder flange(same as left) 9.5 102 1 969 0.000969 4.2
R Right L shape docking girder DOCKING GIRDER 254x102x8 FLANGED PLATE P&S 8 362 1 2896 0.002896 12.5
R Right FB keel floor 63.5x9.5 FB 9.5 381 1 FB 63.5 0.0002298 1.8
R Right web floor 381x8 WEB 8 3611 2 FB 381 -40856 0.021359 167.7
R Right FB on web floor 152x9.5 FB 9.5 3611 2 FB 152 0.0104286 81.9
R Right FB sitting on T docking girder (same as left) 415 1 FB 4.7 2.0
R Right hull floor beam FB (same as left) 6.3 4169 1 FB 63.5 0.0016678 13.1
R Right floor watertight flat 5 PLT 5 4315 1 21575 0.021575 93.2
R Right outboard web 254x8 WEB 8 2770 1 FB 254 0.0056286 44.2
R Right FB on outboard web 102x9.5 FB 9.5 2770 1 FB 102 0.0026841 21.1
R Right bump web 8 WEB SPACED 533 8 FB 87840 0.0007027 5.5
R Right web deck 762x8 WEB STRINGER 8 6994 1 FB 762 -149307.3325 0.041441 325.3
R Right Fb on web deck 152x9.5 FB 9.5 6994 1 FB 152 0.0100993 79.3
R Right web inboard 381x9.5 WEB 9.5 2770 1 FB 381 0.010026 78.7
R Right FB on web inboard 152x9.5 FB 9.5 2770 1 FB 152 0.0039999 31.4
MR Mid-Right Longitudinals web top LONGS 152x102x18.3KG/M 5 18.3 50.3
MR Mid-Right Longitudinals web bottomLONGS 152x89x14.6KG/M 5 14.6 40.2
MR Mid-Right FB vert. cross LONGS. 76x8 FB (TYPICAL) 8 483 5.5 FB 76 0.0016152 12.7
MR Mid-Right FB ring on web 102x12.7 FB RING 12.7 1197 1 FB 102 0.0015505 12.2 SUM
MR Mid-Right web (missing info, estimate) 8 4755 1 FB 1500 -114009 0.0561479 440.8 Web (per side)
MR Mid-Right web angle (missing info, estimate) 8 1 FB 243840 0.0019507 15.3 1.65
Item #
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Forward Mid-ship Plates
R Deck deck plating 8 0 1 0 0 0.0
R Outboard 1 side top plating 8 0 1 0 0 0.0
R Outboard 2 bump plating 12.7 0 1 0 0 0.0
R Outboard 3 side shell plating 8 0 1 0 0 0.0
R Keel kell plating 8 0 1 0 0 0.0
R Inboard inboard plating 8 0 1 0 0 0.0
MR Mid top (deck) mid top plating 8 0 1 0 0 0.0 SUM
MR Mid bottom 1 angle plating 8 0 1 0 0 0.0 Plating (per side)
MR Mid bottom 2 bottom flat plating 8 0 1 0 0 0.0 1.11
Item #
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Aft Mid-ship ComponentsL Left longitudinals LONGS 102x76x8.6KG/M 12 8.6 56.8
L Left outboard FB top 1 76x8 FB SPACED 533 8 762 0 FB 76 0 0.0
L Left FB attached to BKT with ring 63.5x8 FB 8 312 0 FB 63.5 0 0.0
L Left side frame on side shell SIDE FRAMES 102x76x10.7Kg/M SPACED 533 3970 1 FB 10.7 42.5
L Left keel floor outboard FLOOR 254 6.3 PLT 6.3 3611 1 FB 254 0.0057783 45.4
L Left keel floor inboard FLOOR 254 6.3 PLT 6.3 3611 1 FB 254 0.0057783 45.4
L Left keel floor FB outboard 76x6.3 FB 6.3 3611 1 FB 76 0.0017289 13.6
L Left keel floor FB inboard 76x6.3 FB 6.3 3611 1 FB 76 0.0017289 13.6
L Left hull floor beam FB BEAM SPACED 533 63.5X6.3 FB 6.3 6350 1 FB 63.5 0.0025403 19.9
L Left T shape docking girder web DOCKING GIRDER P&S CLEAR OF MACHINERY SEATS 305x8 WEB 102x9.5 FB8 305 3 7320 0.00732 31.6
L Left T shape docking girder flange DOCKING GIRDER P&S CLEAR OF MACHINERY SEATS 305x8 WEB 102x9.5 FB9.5 102 3 2907 0.002907 12.6
L Left FB sitting on T docking girder 51x51x4.7Kg/M E.A. 1480 1 FB 4.7 7.0
L Left FB sitting on T docking girder 51x51x4.7Kg/M E.A. 1480 1 FB 4.7 7.0
L Left L shape docking girder (same as right) 8 362 4 11584 0.011584 50.0
L Left inboard stiffeners STIFFENEARS 12x76x9.8Kg/M SPACED 533 3970 1 FB 9.8 38.9
L Left inboard stringer STRINGER305x8 FLGD 127 8 432 1 3456 0.003456 14.9
ML Mid-Left Longitudinals web top LONGS 152x102x18.3KG/M 8 18.3 80.5 SUM
ML Mid-Left Longitudinals web bottomLONGS 152x89x14.6KG/M 8 14.6 64.2 Frame (per side)
ML Mid-Left FB horizon. cross LONGS.76x9.5 FB 9.5 4755 1 FB 76 0.0034331 26.9 0.57
Item #
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Aft Mid-ship PlatesL Deck deck plating 8 6995 1 55960 0.05596 241.6
L Outboard 1 side top plating 8 0 0 0 0 0.0
L Outboard 2 bump plating 12.7 0 0 0 0 0.0
L Outboard 3 side shell plating upper 8 2190 1 17520 0.01752 75.6
L Outboard 4 side shell plating transition 8 1780 1 14240 0.01424 61.5
L Keel 1 keel plating outboard 8 3611 1 28888 0.028888 124.7
L Keel 2 Keel plating inboard 8 3611 1 28888 0.028888 124.7
L Inboard 1 inboard plating upper 8 2190 1 17520 0.01752 75.6
L Inboard 2 inboard plating transition 8 1780 1 14240 0.01424 61.5
ML Mid top (deck) mid top plating 8 4755 1 38040 0.03804 164.2 SUM
ML Mid bottom 1 angle plating 8 1372 1 10976 0.010976 47.4 Plating (per side)
ML Mid bottom 2 bottom flat plating 8 3714 1 29712 0.029712 128.3 1.11
Item #
Distance from Forward (m)
FROM TO FROM TO FROM TO FROM TO
15053 44069 20195 4801
3 20195 43219 2019
5 4161
3
Max area (midship) 33.30 m²
15.053
44.069 20.195
48.013
20.195
43.219
20.195
41.613
Superstructure
Stn#
Section
Location from
forward (m)
HULL Deck Level Pax Mid-Pax Bridge
Section full scale weight
Immersed Area (m^2)
Area factor
Hull weight (ton)
Moment
Weight
Moment Weight
Moment
Weight
Moment
Weight
Moment
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Forward Superstructure
Deck Level Components R Right casing outboard stiffeners STIFFENERS 76x51x4.6Kg/M SPACED 533 3350 1 FB 4.6 15.4
R Right casing inboard stiffeners STIFFENERS 76x51x4.6Kg/M SPACED 533 3350 1 FB 4.6 15.4
R Right outboard stays/railing STAYS 6.3 PLT Flanged 76 Spaced 1524 6.3 1 FB 196265 0.0012365 9.7
R Right H-shape column none(spaced on top of each web frame) 5 3350 0 FB 150 0 0.0
Deck Level Plating
R Casing outboard CASING SIDES 5 PLT 5 3350 1 16750 0.01675 72.3 SUM
R Casing inboard CASING SIDES 5 PLT 5 3350 1 16750 0.01675 72.3 Frame (per side)
R Deck rail bulwark BULWARK 5 5 1100 1 5500 0.0055 23.7 0.21
Item #
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Pax Level Components R Right pax deck floor beam BEAMS 76x51x6.1Kg/M SPACED 533 7250 1 FB 6.1 44.2
R Right pax outboard stiffener 76x6.3 FB SPACED 1524 6.3 2000 1 FB 76 0.0009576 7.5
R Right pax top stiffener 76x6.3 FB SPACED 1524 6.3 6250 1 FB 76 0.0029925 23.5
R Right pax outboard stays/railing STAYS 6.3 PLT Flanged 76 Spaced 1524 6.3 1 FB 106325 0.0006698 5.3
Pax Level Plating
R Pax floor DECK PL 5 5 7250 1 36250 0.03625 156.5
R Pax outboard PLATING 5 5 2000 1 10000 0.01 43.2 SUM
R Pax top PLATING 5 5 6250 1 31250 0.03125 134.9 Frame (per side)
R Pax level rail bulwark BULWARK 5 5 1100 1 5500 0.0055 23.7 0.44
Item #
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Mid Pax Level Components
R Mid-Right pax floor web (missing) 8 4500 1 FB 345 -49769.11082 0.0120218 94.4
R Mid-Right pax floor web corner (missing) 8 1 FB 782980 0.0062638 49.2
R Mid-Right outboard stiffener 76x6.3 FB SPACED 1524 6.3 3600 1 FB 76 0.0017237 13.5
R Officers deck beam BEAMS 76x63.5x7.3Kg/M SPACED 762 4500 1 FB 7.3 32.9
Mid Pax Level Plating
R Mid-Right floor DECK PL 5 5 4500 1 22500 0.0225 97.1 SUM
R Mid-Right outboard PLATING 5 5 3600 1 18000 0.018 77.7 Frame (per side)
R Officer deck DECK PL 6.3 6.3 4500 1 28350 0.02835 122.4 0.49
Item #
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Bridge Components
R Officers outboard stiffener 76x51x4.6Kg/M SPACED 762 2750 1 FB 4.6 12.7
R Officer top beam BEAMS 76x64x6.7Kg/M SPACED 762 3000 1 FB 6.7 20.1
Bridge Plating SUM
R Officer outboard PLATING 5 5 2750 1 13750 0.01375 59.4 Frame (per side)
R Officer top DECK PL 5 5 3000 1 15000 0.015 64.8 0.16
Item #
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Aft Superstructure
Deck Level Components L Left casing outboard stiffeners STIFFENERS 76x51x4.6Kg/M SPACED 533 3350 1 FB 4.6 15.4
L Left casing inboard stiffeners STIFFENERS 76x51x4.6Kg/M SPACED 533 3350 1 FB 4.6 15.4
L Left outboard stays/railing STAYS 6.3 PLT Flanged 76 Spaced 1524 6.3 1 FB 196265 0.0012365 9.7
L Left H-shape column none(spaced on top of each web frame) 5 3350 0 FB 150 0 0.0
Deck Level Plating
L Casing outboard CASING SIDES 5 PLT 5 3350 1 16750 0.01675 72.3 SUM
L Casing inboard CASING SIDES 5 PLT 5 3350 1 16750 0.01675 72.3 Frame (per side)
L Deck rail bulwark BULWARK 5 5 1100 1 5500 0.0055 23.7 0.21
Item #
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Pax Level Components L Left pax deck floor beam BEAMS 76x51x6.1Kg/M SPACED 533 7250 1 FB 6.1 44.2
L Left pax outboard stiffener 76x6.3 FB SPACED 1524 6.3 2000 1 FB 76 0.0009576 7.5
L Left pax top stiffener 76x6.3 FB SPACED 1524 6.3 6250 1 FB 76 0.0029925 23.5
L Left pax outboard stays/railing STAYS 6.3 PLT Flanged 76 Spaced 1524 6.3 1 FB 106325 0.0006698 5.3
Pax Level Plating
L Pax floor DECK PL 5 5 7250 1 36250 0.03625 156.5
L Pax outboard PLATING 5 5 2000 1 10000 0.01 43.2 SUM
L Pax level rail bulwark BULWARK 5 5 1100 1 5500 0.0055 23.7 Frame (per side)
L Pax top PLATING 5 5 6250 1 31250 0.03125 134.9 0.44
Item #
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Mid Pax Level Components L Mid-Left floor beam BEAMS 76x51x6.1Kg/M SPACED 533 4500 1 FB 6.1 27.5
L Mid-Left outboard stiffener 76x6.3 FB SPACED 1524 6.3 3600 1 FB 76 0.0017237 13.5
L Officers deck beam BEAMS 76x63.5x7.3Kg/M SPACED 762 4500 1 FB 7.3 32.9
Mid Pax Level Plating
L Mid-Left floor DECK PL 5 5 4500 1 22500 0.0225 97.1 SUM
L Mid-Left outboard PLATING 5 5 3600 1 18000 0.018 77.7 Frame (per side)
L Officer deck DECK PL 6.3 6.3 4500 1 28350 0.02835 122.4 0.37
Item #
Item Name Item Description thickness length Qty FB? width Area (less area)? kg/m given? Vol (m³) Weight (kg)
Bridge Components
L Left officers outboard stiffener 76x51x4.6Kg/M SPACED 762 2750 1 FB 4.6 12.7
L Left officer top beam BEAMS 76x64x6.7Kg/M SPACED 762 3000 1 FB 6.7 20.1
Bridge Plating SUM
L Officer outboard PLATING 5 5 2750 1 13750 0.01375 59.4 Frame (per side)
L Officer top DECK PL 5 5 3000 1 15000 0.015 64.8 0.16
Item #
0 b 0.57 5.51 0.1 0.00 0.02 0.0
1 f 1.12 3.35 0.6 0.02 0.06 0.1
2 f 1.67 3.35 1.3 0.04 0.13 0.2
3 f 2.22 3.35 2.2 0.07 0.22 0.5
4 f 2.77 3.35 3.3 0.10 0.34 0.9
5 f 3.32 3.35 4.6 0.14 0.47 1.5
6 f 3.87 3.35 6.0 0.18 0.61 2.3
7 f 4.42 3.35 7.5 0.22 0.75 3.3
8 f 4.97 3.35 9.0 0.27 0.91 4.5
9 b 5.52 5.51 10.5 0.32 1.74 9.6
10 f 6.07 3.35 12.1 0.36 1.22 7.4
11 f 6.62 3.35 13.6 0.41 1.37 9.1
12 f 7.17 3.35 15.1 0.45 1.52 10.9
13 f 7.72 3.35 16.6 0.50 1.67 12.9
14 w 8.27 5.51 18.0 0.54 2.98 24.6
15 f 8.82 3.35 19.4 0.58 1.95 17.2
16 f 9.37 3.35 20.7 0.62 2.09 19.5
17 f 9.92 3.35 22.0 0.66 2.21 21.9
18 f 10.47 3.35 23.2 0.70 2.33 24.4
19 w 11.02 5.51 24.3 0.73 4.02 44.2
20 f 11.57 3.35 25.3 0.76 2.55 29.5
21 f 12.12 3.35 26.3 0.79 2.64 32.0
22 f 12.67 3.35 27.1 0.82 2.73 34.6
23 f 13.22 3.35 27.9 0.84 2.81 37.2
24 f 13.77 3.35 28.7 0.86 2.89 39.7
25 b 14.32 5.51 29.3 0.88 4.85 69.4
26 f 14.87 3.35 29.9 0.90 3.01 44.8
27 f 15.42 3.35 30.4 0.91 3.06 47.2 0.42 6.44
28 f 15.97 3.35 30.9 0.93 3.11 49.7 0.42 6.7
29 w 16.52 5.51 31.3 0.94 5.18 85.6 0.42 6.9
30 f 17.07 3.35 31.7 0.95 3.19 54.4 0.42 7.1
31 f 17.62 3.35 32.0 0.96 3.22 56.7 0.42 7.4
32 f 18.17 3.35 32.3 0.97 3.25 59.0 0.42 7.6
33 f 18.72 3.35 32.5 0.98 3.27 61.2 0.42 7.8
34 b 19.27 5.51 32.7 0.98 5.40 104.1 0.42 8.0
35 f 19.82 3.35 32.8 0.99 3.30 65.5 0.42 8.3
36 f 20.37 3.35 32.9 0.99 3.32 67.5 0.42 8.5 0.88 17.87 0.74 15.11 0.31 6.39
37 f 20.92 3.35 33.0 0.99 3.33 69.6 0.42 8.7 0.88 18.4 0.74 15.5 0.31 6.6
38 f 21.47 3.35 33.1 0.99 3.33 71.6 0.42 9.0 0.88 18.8 0.74 15.9 0.31 6.7
39 w 22.02 5.51 33.2 1.00 5.49 120.8 0.42 9.2 0.88 19.3 0.97 21.5 0.31 6.9
40 f 22.57 3.35 33.2 1.00 3.34 75.5 0.42 9.4 0.88 19.8 0.74 16.7 0.31 7.1
41 f 23.12 3.35 33.3 1.00 3.35 77.4 0.42 9.7 0.88 20.3 0.74 17.2 0.31 7.3
42 f 23.67 3.35 33.3 1.00 3.35 79.3 0.42 9.9 0.88 20.8 0.74 17.6 0.31 7.4
43 f 24.22 3.35 33.3 1.00 3.35 81.2 0.42 10.1 0.88 21.3 0.74 18.0 0.31 7.6
44 f 24.77 3.35 33.3 1.00 3.35 83.0 0.42 10.3 0.88 21.7 0.74 18.4 0.31 7.8
45 b 25.32 5.51 33.3 1.00 5.51 139.4 0.42 10.6 0.88 22.2 0.97 24.7 0.31 7.9
46 f 25.87 3.35 33.3 1.00 3.35 86.6 0.42 10.8 0.88 22.7 0.74 19.2 0.31 8.1
47 f 26.42 3.35 33.2 1.00 3.35 88.4 0.42 11.0 0.88 23.2 0.74 19.6 0.31 8.3
48 f 26.97 3.35 33.2 1.00 3.34 90.2 0.42 11.3 0.88 23.7 0.74 20.0 0.31 8.5
49 f 27.52 3.35 33.2 1.00 3.34 91.9 0.42 11.5 0.88 24.1 0.74 20.4 0.31 8.6
50 f 28.07 3.35 33.1 0.99 3.33 93.6 0.42 11.7 0.88 24.6 0.74 20.8 0.31 8.8
51 w 28.62 5.51 33.1 0.99 5.47 156.5 0.42 12.0 0.88 25.1 0.97 27.9 0.31 9.0
52 f 29.17 3.35 33.0 0.99 3.32 96.9 0.42 12.2 0.88 25.6 0.74 21.6 0.31 9.2
53 f 29.72 3.35 32.9 0.99 3.32 98.5 0.42 12.4 0.88 26.1 0.74 22.1 0.31 9.3
54 f 30.27 3.35 32.9 0.99 3.31 100.2 0.42 12.6 0.88 26.6 0.74 22.5 0.31 9.5
55 f 30.82 3.35 32.8 0.99 3.30 101.8 0.42 12.9 0.88 27.0 0.74 22.9 0.31 9.7
56 f 31.37 3.35 32.7 0.98 3.29 103.3 0.42 13.1 0.88 27.5 0.74 23.3 0.31 9.8
57 b 31.92 5.51 32.7 0.98 5.40 172.4 0.42 13.3 0.88 28.0 0.97 31.1 0.31 10.0
58 f 32.47 3.35 32.6 0.98 3.28 106.4 0.42 13.6 0.88 28.5 0.74 24.1 0.31 10.2
59 f 33.02 3.35 32.5 0.98 3.27 108.0 0.42 13.8 0.88 29.0 0.74 24.5 0.31 10.4
60 f 33.57 3.35 32.4 0.97 3.26 109.5 0.42 14.0 0.88 29.5 0.74 24.9 0.31 10.5
61 f 34.12 3.35 32.3 0.97 3.25 111.0 0.42 14.3 0.88 29.9 0.74 25.3 0.31 10.7
62 f 34.67 3.35 32.2 0.97 3.24 112.5 0.42 14.5 0.88 30.4 0.74 25.7 0.31 10.9
63 w 35.22 5.51 32.1 0.97 5.32 187.2 0.42 14.7 0.88 30.9 0.97 34.3 0.31 11.0
64 f 35.77 3.35 32.1 0.96 3.23 115.4 0.42 14.9 0.88 31.4 0.74 26.5 0.31 11.2
65 f 36.32 3.35 32.0 0.96 3.22 116.8 0.42 15.2 0.88 31.9 0.74 27.0 0.31 11.4
66 f 36.87 3.35 31.9 0.96 3.21 118.2 0.42 15.4 0.88 32.4 0.74 27.4 0.31 11.6
67 f 37.42 3.35 31.8 0.95 3.20 119.6 0.42 15.6 0.88 32.8 0.74 27.8 0.31 11.7
68 b 37.97 5.51 31.7 0.95 5.24 198.8 0.42 15.9 0.88 33.3 0.97 37.0 0.31 11.9
69 f 38.52 3.35 31.5 0.95 3.18 122.3 0.42 16.1 0.88 33.8 0.74 28.6 0.31 12.1
70 f 39.07 3.35 31.4 0.94 3.16 123.6 0.42 16.3 0.88 34.3 0.74 29.0 0.31 12.3
71 f 39.62 3.35 31.3 0.94 3.15 124.8 0.42 16.6 0.88 34.8 0.74 29.4 0.31 12.4
72 w 40.17 5.51 31.2 0.94 5.16 207.2 0.42 16.8 0.88 35.3 0.97 39.1 0.31 12.6
73 f 40.72 3.35 31.0 0.93 3.13 127.3 0.42 17.0 0.88 35.7 0.74 30.2 0.31 12.8
74 f 41.27 3.35 30.9 0.93 3.11 128.4 0.42 17.2 0.88 36.2 0.74 30.6 0.31 12.9
75 f 41.82 3.35 30.8 0.92 3.10 129.5 0.42 17.5 0.88 36.7 0.74 31.0 0.31 13.12
76 f 42.37 3.35 30.6 0.92 3.08 130.5 0.42 17.7 0.88 37.2 0.74 31.4
77 f 42.92 3.35 30.4 0.91 3.06 131.5 0.42 17.9 0.88 37.7 0.74 31.9
78 w 43.47 5.51 30.3 0.91 5.01 217.6 0.42 18.2 0.88 38.1 0.97 42.35
79 f 44.02 3.35 30.1 0.90 3.03 133.3 0.42 18.39 0.88 38.6
80 f 44.57 3.35 29.9 0.90 3.01 134.1 0.88 39.1
81 f 45.12 3.35 29.7 0.89 2.99 134.9 0.88 39.6
82 b 45.67 5.51 29.5 0.89 4.88 222.8 0.88 40.1
83 f 46.22 3.35 29.3 0.88 2.95 136.2 0.88 40.6
84 f 46.77 3.35 29.0 0.87 2.92 136.7 0.88 41.0
85 f 47.32 3.35 28.8 0.87 2.90 137.2 0.88 41.5
86 w 47.87 5.51 28.6 0.86 4.73 226.2 0.88 42.0
87 f 48.42 3.35 28.3 0.85 2.85 138.0 0.88 42.49
88 f 48.97 3.35 28.1 0.84 2.82 138.3
89 f 49.52 3.35 27.8 0.83 2.80 138.5
90 f 50.07 3.35 27.5 0.83 2.77 138.6
91 b 50.62 5.51 27.2 0.82 4.50 227.9
92 f 51.17 3.35 26.9 0.81 2.71 138.7
93 f 51.72 3.35 26.6 0.80 2.68 138.6
94 f 52.27 3.35 26.3 0.79 2.65 138.4
95 f 52.82 3.35 26.0 0.78 2.62 138.2
96 w 53.37 5.51 25.7 0.77 4.25 226.7
97 f 53.92 3.35 25.3 0.76 2.55 137.6
98 f 54.47 3.35 25.0 0.75 2.52 137.1
99 b 55.00 5.51 24.7 0.74 4.08 224.5
TOTAL WEIGHTS
Hull Deck Level Pax Mid-Pax Bridge Total Superstructure
Weight 304.96 22.14 45.64 33.77 12.55 114.11
Moment 9399.67 658.03 1569.57 1080.00 390.19 3697.79
(from bow) LCG 30.82 29.72 34.39 31.98 31.09 32.41