146
THE SUCCESSFUL ONO F PROJECT MANAGEMENT IN A FMCG 1INIDUSTRY ILY MEANS OF A CONTEMPORARY SYSTEMS APPROACH BY SHAM VNHAL JAYRAM DISSERTATION submitted in compliance with the requirements for the MASTE ;": 'S DEG EE USINESS ADMINISTRATION 11 : offered by TECHNIK N WITWATERSRAND, MANAGEMENT UNIT and validated and conferred by the UNIVEm:SITY OF WALES SUPERVISOR: RWE VAN DE DATE OF SU tMISSION: JULY 2001 WAL

The successful implementation of project management in a

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

THE SUCCESSFUL ONO F

PROJECT MANAGEMENT IN A FMCG

1INIDUSTRY ILY MEANS OF A CONTEMPORARY

SYSTEMS APPROACH

BY

SHAM VNHAL JAYRAM

DISSERTATION

submitted in compliance with the requirements for the

MASTE ;": 'S DEG

EE USINESS ADMINISTRATION 11:

offered by

TECHNIK N WITWATERSRAND, MANAGEMENT

UNIT

and validated and conferred by the

UNIVEm:SITY OF WALES

SUPERVISOR: RWE VAN DE

DATE OF SU tMISSION: JULY 2001

WAL

:

LESLEE BOYD LiBRARY BIB No: G

ITEM No: I( j+ .3ge3e

ORDER No:

1 7 su:-

BRANCH/LOCATION: a I

SHELF No: 10 5 4O ./iy

LIBRARY STOCK

awl (2J

TE. .NIKON 'p rWATERSRAND TWR • IBRARIES - AUCKLAND PARK

Tei: 406•3640

This boo4 n renirned or renewed on Cr Cefore :re Cate stamped be;cw. fine wI be ca[c... , ,, ■ ed from the 1'11'51 Overdue Cay at 9.'00.

For teieoncmc re'. as please have your student numzer and the t ar ooze number of the readv..9..oc .. 3 in demand wilnot te renew ed. Only two renewals per COOS will be allowed

404 - 10- 1 •

2004 -12- 1 5

2005 -17:- 2 -ii3- 1 2

6\tci 2009 -07- 06

2010 -09- 3 0

2010 -11° 2

200/ii!- 16 2007 -11- 0 /

2012 -05- 6

NI4 7-* tr)

2008 -08- 3

2010 -08- 31

7`.e TWR reser,e3 :ne r ■ ynt recover r.e cost mm e 3,r. anculd ICC lest.

31C , •n. 3I CamageC fl lay way waIst :7:vote out aga ■ nat a uses name.

Technccon Wits Library

IIII1II1I llIIIIIllhII 1111 II

aliVyATERS,PAND

Deekrattion

I hereby declare that this Dissertation is my own unaided work. This Dissertation is

submitted in compliance with the requirements for the Master's Degree in Business

Administration offered by the Technikon Witwatersrand and validated and conferred

by the University of Wales. It has not been submitted before for any other degree or

any other examination at any other university.

Shahir Vishal Jayram

Monday, 30 July 2001

It

Dedication

To my Roving Dad, Motillan Jayram,

my friend and Guru,

who taught me weRD

the meaning of the words "pen -severance and persistence".

This has been a great honour to share this achievement with my Dade

iii

Nameste

Ac ut ement.

Thank you to all those individuals that provided assistance to myself in one form or

another, while I researched and wrote this dissertation.

iv

V

Table of Contents

Tableof Contents 000000.00000000000000000000000000.000.0000000000000000.000000v

Li Introduction 1

L2 1:: ac (ground to Project Management in a IFMCG ............ ........ ......... ......... ...... ............ 3

1.3 Aim 3

L4 Objective

1.5 teilning Concepts 4

1.6 Limitations 4

1.7 Vallue of Research 5

1 1 .8 Layout of eseareb Report 5 1.8.1 Chapter 1 5 1.8.2 Chapter 2 5 1.8.3 Chapter 3 6 1.8.4 Chapter 4 6 1.8.5 Chapter 5 6

1 1:

Ch pter 2 — Literature

review 0000000000000000000.000000000 ,000000000007

2.1 Ma agement functions 2.1.1 The Classicall/Traditional School 7 2.1.2 The Empirical School 7 2.1.3 The t ehaviouratll School 8 2.1.4 The Decision Theory School 8 2.1.5 The Management Systems School 8

2.2 Project 'life cycles 9 2.2.1 Kerzner's Five Stages of the Life Cycle 9 2.2.2 Shtub et all's Life cycle of a project 13 2.2.3 Turner's Project Life Cycles 17 2.2.4 Mayllor's Project Life cycles 118 2.2.5 Project Management tody of Knowledge's Project Life Cycle 21

vi

2.3 Life Cycle Leadership 24 2.3.11 Situational Leadership 24 2.3.11.1 Telling 25 2.3.1.2 Selling 26 2.3.1.3 Participating 26 2.3.1.5 Conclusion 27 2.3.2 Authority and I'' esponsnbnllntty 27

2.4 Planning, Organising, Controlling and Directing 31

2.4.1 IPilanning 31 2.4.1.1 Why plan? 311 2.4.11.5 Managing the planning process 42

2.4.2 Organising OOOOOO .0 OOOOOOOO OOOOOOOOOOOOOOOOO OOOOOOOOO .......... OOOOO .......43 2.4.11 The Need for Organising 43 2.4.2.2 Getting Organised 43 2.4.2.3 Matrix Irganisation 45 2.4.2.4 Advantages of a matrix organisational form 4$ 2.4.2.5 IPisadvantages of a matrix organisational form 49 2.4.2.6 Project Organising 50

2.4.3 Controlling 51 2.4.3.1 Task control! 52

Detailed functional objectives 52 Quality inspections 53 Work orders 53

2.4.4 Directing 54

2.5 Define the scope of work for the project 56

2.6 Commissioning 57

2.7 Takeover 58 2.7.1 Conclusions 60

2.8 Summation of Literature Study 61 2.8.1 Phase 1 Conceptual Design 61 2.8.2 Phase 2 tetailed Design 62 2.8.3 Phase 3 Production 63 2.8.4 Phase 4 4 perational 63 2.8.5 Phase 5 Divestment 64 2.8.6 Phase 6 Assessment 64 2.8.7 Planning Control 65

vii

2.8.8 Management Style 66

Chapter 3 Met lodollogy 000000000000000000.0.00000.00000000000000000.00.0067

3.1 Introduction 67

3.2 African Products Project Structure.......... ....... ............. .68

3.3 Reasons for choosing questionnaires 68

3.4 Criteria for selection of respondents 69

3.5 Questionnaires 70 3.5.1 Inexperienced Project Managers' Questionnaire 70 3.5.2 Experienced Project Managers' Questionnaire 71

3.6 Sampling 72

3.7 Data analysis 72

C lapter 4

esuilts 00.000.0000000000000.000000000.00.000000000000000000000000 74

4.1 Survey Results — Inexperienced Project Managers....... 74 4.1.1 Questions 74 4.1.2 Question 2 75 4.1.3 Question 3 76 4.1.4 Question 4 78 4.1.5 Question 5 79 4.1.6 Question 6 81 4.1.7 Question 7 82

4.2 S z rvey r':esults — Experienced Project Ma gers 84 4.2.1 Phase 1 Conceptual Design 84 4.2.2 Phase 2 letailed esign $6 4.2.3 Phase 3 Production Phase $8 4.2.4 hase 4 Operational 89 4.2.5 Phase 5 rlbivestment 90 4.2.6 Phase 6 Assessment 92 4.2.7 Planning & Controlling 93 4.2.8 Management Style 95

Chapter 5 Conclitutsften

ecommerrndations000.0000.000.0.0.98

5.1 Conclusion of Surveys 98

viii

5.2 Recommendations 103

60

fiblliography 0000000000000000000000000000000000000000000000000000000000000 11 04

'70 Appendfices00000000.0.0000000000000.00.0000.000.000000.000.0000.000000000.001[07

Appendix A 107 Appendix 126

Table of Figures

Figure 1.1 Constraints of Project Management 2

Figure 2.1 Shtub et al's Phases of a Project 13

Figure 2.2 Deming's PDAC 18

Figure 2.3 (a) and (b) Maylor's Project Life Cycle 19

Figure 2.4 Typical Project Life Cycle — PMBOK 22

Figure 2.5 Construction Project Life Cycle - PMBOK 22

Figure 2.6 Hersey & Blanchard Leadership Styles 24

Figure 2.7 The Project Planning and Control System 34

Figure 2.8 Typical Matrix Organisation 46

TECHNIKON WITINKIERSRAND

Table of Tablies

LIBRARY

Table 2.1 Turner's Project Life Cycles 17-18

Table 2.2 Maylor's Project life Cycles 20

Table 2.3 Concerns of Functional and Project Managers 47

Table 4.1 Responses to Question 1 74

Table 4.2 Various Phases of a Project 75

Table 4.3 Utilisation of the Contemporary Systems Approach to Project

Management 77

Table 4.4 Pitfalls to using the Contemporary Systems Approach to Project

Management 78

Table 4.5 The Importance of Planning and Control 80

Table 4.6 Responses to Deviations 81

Table 4.7 Preference of Management Style 82

Table 4.8 Responses to Phase 1 84

Table 4.9 Responses to Phase 2 86

Table 4.10 Responses to Phase 3 88

Table 4.11 Responses to Phase 4 89

Table 4.12 Responses to Phase 5 90

Table 4.13 Responses to Phase 6 92

Table 4.14 Responses to Planning 93

Table 4.15 responses to Controlling 94

Table 4.16 Responses to Management Style 96

ix

Chapter R

1

It a e .&ground

Li ffntroduction

"Project management provides one with the tools, knowledge and techniques for

managing, defining, planning, organising, controlling and closing a project. A project has

a defined start and stop date. Certain steps must be performed in a logical sequence, not

randomly as it is subject to a series of constraints imposed upon it, such as cost, budget

and schedule" (Kliem et al, 1997:2-3).

"Projects are composed of a unique set of activities established to realize a given set of

objectives in limited time span. The non-routine nature of projects activities places a set

demands on the project manager that are different in many respects from those the

manager of more routine operations activities experiences, both in planning and

coordinating the work and in human problems encountered" (Stevenson, 1999:792).

Kerzner's (1998:6) definition of project management: "Project management is planning,

organizing, directing and controlling of company resources for a relatively short-term

objective that has been established to complete specific goals and objectives." Figure 1.1

is pictorial representation of project management.

Figure 1.1: Constraints of Project Management

The objective of Figure 1.1 is to show that project management is designed to manage or

control company resources on a give activity, within cost, time and performance. Time,

cost and performance are the constraints of the project (Kerzner, 1998: 6).

It may be argued that the solution to many of corporate problems involves obtaining

better control and utilization of existing corporate resources, with emphasis on internal

forces. Large-scale industry is making the migration towards project-based work,

whereby the three main functional areas, operations, marketing and finance synergise

efforts such that overall departmental goals are in alignment with the corporate strategy.

In a fast moving consumable good (FMCG) industry, project management is not a core

competency, but has transformed into a key performance area. Project management has

to be internally managed as the cost of consultants are expensive, also, when projects are

completed and there are queries, it is a mammoth task to get hold of the project manager,

even if you successful in tracking him down, will he remember anything usually not.

In today's globally competitive markets, one has to manage projects internally as this

protects intellectual property, retains staff and gives the competitive edge to be a leader

rather than be a follower.

2

1.2 tackground to Project Management in a FMCG

ffndustry

In a FMCG based industry it is imperative that market forecasts are accurate, especially

when venturing into new business opportunities. Marketing will conduct a SWOT

analysis complimented with the target market segmentation with specific demand

analysis. The demand strategy is usually one of level capacity. This information is then

forwarded to operations; more specifically technical support whom together with finance

then conducts a feasibility study and initial design (African Products, NBD Procedure).

Once the design has been finalised, a capital application for financing is done. The return

on investment and payback time must be known before the capital application is made.

When the board of directors has approved the capital, a suitable process engineer is

appointed to manage the project to termination.

The project manager will manage the project by (Kerzner, 1998:5):

Planning

Organising

Controlling

Directing

As the project is executed internally, there is no project office, hence resources are shared

between projects and day-to-day functions. The project manager will request for specific

staff, but the final decision of what resources are committed rests with the line managers.

This concept of management is known as the matrix organisation.

1.3 Aim

To determine what management skills newly appointed project managers should have to

successfully implement project management.

3

1.4 Objective

The illustration of successful project management will be achieved by discussing the

following:

Determination of management functions by literature study

Develop a model based on the outcome of objective a.

Evaluate the model generated in b. by means of surveying expert project

managers and new employees entering the project management arena

1.5 Defining Concepts

Project — a group of activities that have to be performed in a logical sequence to meet

preset objectives outlined by the client (Burke, 1995:9).

Project management — deals with the one time effort to achieve a focused objective

(Shtub et al, 1994:5)

Management functions — modern practitioners identify management responsibilities and

skills in terms of (Kerzner, 1998:226):

Planning

Organising

Controlling

Directing

4

1.6 Limitations

This research will be limited to African Products (Pty) Ltd only.

1.7 ValIan of Research

This research will provide valuable and important background information on current

trends of project management strategies. Such information could be used to re-examine

existing practices and strategic intentions. In African Products it will also provide useful

information that could be used when injecting technology into an organisation.

1.8 Layout of Research Report

1.8.1 Chapter 1

Chapter 1 discusses the function of project management in a fast moving consumable

good industry (FMCG). Also, project is defined and the constraints of project

management are explained.

The Aim, Objective, Limitation and Value of Research are stated in this chapter.

1.8.2 Chapter 2

A comprehensive literature review has been undertaken in order to establish the

management functions in project management. These are planning, organising,

controlling and directing.

A project has a logical sequence of stages, this is known as a project life cycle.

Upon completion of the literature review a model for project management is

postulated.

5

Objectives a. and b. are achieved in this chapter.

1.8.3 Chapter 3

Chapter 3 elaborates the research methodology used in validating the model presented

at the end of Chapter 2.

Questionnaires were used to get responses from experienced and inexperienced

project managers. There was a criterion for selecting respondents, this is discussed.

The sampling and data analysis techniques are explained.

1.8.4 Chapter 4

This presents the results of the surveys conducted on experienced and in experienced

project managers.

Objective c. is achieved in this chapter.

Responses to each question is presented in tabulated form and a discussion follows

directly.

1.8.5 Chapter 5

This chapter discusses the findings in Chapter 4. There is unanimous support for

postulated model.

Five recommendations are made at the end of this chapter. This is improve the

postulated model and to practically test it, upon success can be incorporated into

company operating procedures.

6

(Chapter 2 — literature Review

2.1 Management functions

The difficult aspect of the project management environment in African Products is

that individuals at the project-functional level interface must report to two bosses.

Functional manager and project managers, by virtue of their different authority levels

and responsibility, treat their people in different fashions depending on their

"management school" philosophies. There are five management schools (Kerzner,

1998: 225-226).

2.1.1 The Classical/Traditional School

Management is the process of getting things done (i.e., possibly achieving objectives) by

working both with and through people operating in organised groups. Emphasis is placed

on the end-item or objective, with little regard for the people involved. This type of

management is the ends justify the means, people are consumables in this management

function.

2.1.2 The Empirical School

Managerial capabilities can be developed by studying the experiences other managers,

whether or the situations are similar or not. A clever man learns from experience and

wise man learns from others mistakes.

7

2.1.3 The Behavioural School

Two classrooms are considered within this school. First, there is the human relations

classroom in which the emphasis is on the interpersonal relationship between individuals

and their work. The second classroom includes the social system of the individual.

Management is considered to be a system of cultural relationships involving social

change.

2.1.4 The Decision Theory School

The decision theory school: Management is a rational approach to decision making using

a system of mathematical models and processes, such as operations research management

science.

2.1.5 The Management Systems School

The management systems school: Management is the development of a systems

model, characterised by input, processing and output, and directly identifies flow of

resources (money, equipment facilities personnel, information and material) necessary

to obtain some objective by either maximising or minimising the some objective

function. The management systems school also includes contingency theory, which

stresses that each situation is unique and must be optimised separately within the

constraints of the system.

In a project environment, functional managers are generally practitioners of the first three

schools of management, whereas the project managers utilize the last two (Kerzner, 1998:

226).

8

2.2 Project life cycles

To fully understand what project management is, project life cycles will be examined first

as this will give a indication as to what management functions are required by new

employees to successfully complete objectives set in the project.

2.2.1 Kerzner's Five Stages of the Life Cycle

Kerzner (1998) developed five stages that indicate the work activity for each stage. The

five stages from initiation to termination are shown below:

2.2.1.1 Conceptual

Kerzner (1998:74) stated that this is the preliminary evaluation of the idea. Preliminary

analysis of risk, resulting impact on time, cost, quality and potential impact on company

resources. This is includes the feasibility study.

Determine existing needs or potential deficiencies of existing systems

Establish system concepts that provide initial strategic guidance to overcome

existing or potential deficiencies

Determine initial technical, environmental and economic feasibility and

practically of the system

Examine alternative ways of accomplishing the system objective

Provide initial answers to the following questions:

What will the system cost?

When will the system be available?

What will the system do?

How will the system be integrated into the existing systems?

9

Identify the human and non-human resources required to support the system

Select the initial system designs that will satisfy the system objectives

Determine initial system interfaces

Establish a system organisation.

2.2.1.2 Definition

Kerzner (1998:75) stated that definition is a refinement of the elements described under

the conceptual phase. Firms' identification of required resources and establishment of

realistic time, cost and quality parameters. Includes the initial preparation of all

documentation necessary to the support system. Conduct cost benefit analysis, i.e.

payback time.

Firm identification of human and non-human resources required

Preparation of the final system performance

Preparation of detailed plans required supporting the system

Determination of realistic cost, schedule and performance requirements

Identification of those areas of the system where high risk and uncertainty exist,

and outline plans for further exploration of these areas

Definition of intersystem and intrasystem interface

Determination of necessary support subsystems

Identification and initial preparation of the documents to support the system, such

as policies, procedures, job descriptions budget, and funding papers, letters and

memoranda.

10

2.2.1.3 Production

Production is predominantly a testing and final standardisation effort so operations can

begin. Almost all documentation must be completed in this phase.

Updating of detailed plans conceived and defined during the preceding phases

Identification and management of resources required to facilitate the production

processes, such as inventory supplies, labour funds and so on

Verification of system production specifications

o Beginning of production, construction and installation

Final preparation and dissemination of policy and procedural documents

Performance of final testing to determine adequacy of the system to do the things

it was intended to do

Development of technical manuals and affiliated documentation describing how

the system is intended to operate

Development of plans to support the system during its operational phase

(Kerzner, 1998:77).

2.2.1.4 Operational

Operational is the integrating of the project's product or service into the existing

organisation. This may involve further life cycles such as introduction, growth,

maturity and deterioration of a marketable product (Kerzner, 1998:77).

Use of the system results by the intended user or customer

Actual integrating of the project's product or service into existing

organisational systems

Evaluation of the technical, social and economic sufficiency of the project to

meet actual operating conditions

Provision of feedback to organisational planners concerned with developing

new projects and systems

Evaluation of the adequacy of supporting systems.

2.2.1.5 Divestment

Divestment evaluates the efforts of the total system and serves as input to conceptual

phases for new projects and systems. This final phase also has an impact on other

ongoing projects with regard to priority identification. Includes the real location of

resources and "where should they be reassigned?" (Kerzner, 1998:78).

System phase down

Development of plans transferring responsibility to supporting organisations

Divestment or transfer of resource to other systems

Development "of lessons learnt" for inclusion in qualitative/quantitative database

to include:

Assessment of images by the customer

Major problems encountered and their solution

Technological advances

Advancement in knowledge relative to department strategic objectives

New or improved management techniques

Recommendation for future research and development

Recommendations for the management of future programs, including

interfaces with associate contractors

Other major lessons learnt during the course of the system.

12

13

2.2.2 Shtub et al's Life cycle of a project

Because of the degree to which projects differ in their attributes, such as length, cost, type

of technology used, and sources of uncertainty, it is difficult to generalise the operational

and technical issues they each face. It is possible, however, to discuss some strategic and

tactical issues that are relevant to many types of projects. The framework for the

discussion is the project life cycle or the major phases through which a "typical" project

progresses. An outline is depicted below in Figure 2.1 and elaborated on by Cleland and

Johnson and King (1983) as shown in Shtub et al, who identify the long range (strategic)

and medium-range (tactical) issues that management must consider. A synopsis follows

(Shtub et al, 1994:24):

Fig.2.1: Shtub et al's Phases of a Project

Phase 1

Conceptual design

Phase 2

Advanced development

Phase 3

Detailed design

Phase 4

Production

Phase S

Termination

Goals Plan Responsibility Manage Closeout Scope Budget definition Measure Document Baseline Schedule Team Control Suggest Requirements Bid proposal Organizational Update and improvements

Feasibility Management structure replan Transit

Desirability commitment Detailed plan Problem Reassign Kickoff solving Dissolve team

2.2.2.1 Conceptual design phase

In this phase (Shtub et al, 1994:24), an organisation (client, contractor, sub-contractor)

initiates the project and evaluates potential alternatives. A client organisation may start

identifying a need or deficiency in existing operations an issuing a request for proposal,

also see Figure 2.1.

The selection of projects at the conceptual phase is a strategic decision based on the

established goals of the organisation, needs, ongoing projects, and long term

commitments and objectives. In this phase, expected benefits from alternatives projects,

assessment of costs and risks, and estimates of required resources are some of the factors

weighed. Important action items include the initial "make or buy" decisions for

components and equipment, the development of contingency plans for high-risk areas,

and the preliminary selection of subcontractors and other team members that will

participate in the project.

In addition, upper management must consider the technological aspects such as

availability and maturity of the required technology, its performance, and expected usage

in subsequent projects. Environmental factors related to government regulations,

potential markets and competition must also be analysed.

The selection of projects is based on a variety of goals and performance measures,

including expected cost, profitability, risk and potential for follow-on assignments. Once

a project is selected and its conceptual design is approved, work begins on the second

phase, where many of the details are ironed out.

2.2.2.2 Advanced development phase

In this phase (Shtub et al, 1994:25) weighing the tactical advantages and disadvantages of

each possible arrangement forms the organisational structure of the project. Once a

decision is made, lines of communication and procedures for work authorisation and

performance reporting are established. This leads to the framework in which the project

is executed.

14

2.2.2.3 Detailed design phase

This is the phase (Shtub et al, 1994:25) in a project's life cycle where comprehensive

plans are prepared. These plans consist of:

Product and process design

Final performance requirements

Detailed break down of work structure

Scheduling information

Blueprints for cost and resource management

Detailed contingency plans for high-risk activities

Budgets

Expected cash flows

In addition and most important, procedures and tools for executing, controlling and

correcting the project are developed. When this phase is completed, implementation can

begin since various plans should cover all aspects of the project in sufficient detail to

support work authorisation and execution.

The success of a project is highly correlated with the quality and depth of the plans

prepared during this phase. A detailed design review of each plan and each aspect of the

project is therefore conducted prior to approval. A sensitivity analysis of environmental

factors that contribute to uncertainty may also be needed. This analysis is typically

performed as part of "what if' studies using expert opinions and simulations as

supporting mechanisms.

In most situations, the resources committed to the project are defined during the initial

phases of its life cycle. Although these resources are used later, the strategic issues of

how much to spend and at what rate are addressed here.

2.2.2.4 Production phase

The fourth life-cycle phase (Shtub et al, 1994:26) involves the execution of plans and in

most projects dominates the others efforts and duration. The critical strategic issue here

15

relates to maintaining top management support, while the critical tactical issues centre on

the flows of communications within and among the participating organisations. At this

level the focus is on actual performance and changes on the original plans. Modifications

can take different forms — in the extreme case, a project may be cancelled. More likely,

though, the scope of work, schedule and budget will be adjusted as the situation dictates.

Throughout this phase, management's task is to assign work to the participating parties,

to monitor actual progress, and to compare it to the baseline plans. The establishment

and operation of a well-designed communications and control system are therefore

necessary.

Support of the product or system throughout its entire life (logistic support) requires

management attention in most engineering projects where an operational phase is

scheduled to follow implementation. The preparation for logistic support includes

documentation, personnel training, maintenance and initial acquisition of spare parts.

Neglecting this activity or giving it only cursory attention can doom an otherwise

successful venture.

2.2.2.5 Termination phase

In this phase (Shtub et al, 1994:26), management's goal is to consolidate what it has

learned and translate this knowledge into ongoing improvements in the process. Current

lessons and experience serve as the basis for improved practice. But while successful

projects can provide valuable insights, failures can teach us even more. Unless we learn

form our mistakes we are bound to repeat them making the task of continuous

improvement little more than an empty exercise. Databases that store and support the

retrieval of information on cost, schedules, resource utilisation and so on, are assets of an

organisation. Readily available, accurate information is a key factor on the success of

future projects.

16

2.2.3 Turner's Project Life Cycles

Turner's (1993:23-24) view of project life cycles is a four-stage process. The four-stage

process is shown in Table 2.1:

Table 2.1: Turner's Project Life Cycles

Stage Name Management objectives

Germination Proposal and initiation Project definition

Scope and business objectives

Functional design

Feasibility

Initial estimates approx. 30%

Go/no go decision

Growth Design and appraisal Systems design for sanction

Planning and resourcing

Sanctions estimates approx. 10%

Baseline

Sanction

Maturity Execution and control Education and communication

Detail planning and design

Control estimate to 5%

Work allocation

Progress monitoring

Forecasting completion

Control and recovery

17

project

execution

Plan: formulation and revision

-17 of intended

activity

Check/study: ovaluate

performance

of all phases

Fig 2.2: Deming's PDAC

Death Finalisation and close

out

Completion of work

Use of product

Achieving of benefits

Disbanding/rewarding the team

Audit and review

Historical records

Turner 1993:23 has the view that people tend to jump from perceiving a problem to

choosing a solution, or worse, to implementing a solution. Similarly, they go straight to

the execution stage of a project, without first determining whether the proposal is

worthwhile or how it is to be achieved. If one chooses a solution without going through

the decision making process, the solution tends to cure symptoms but does not get to the

cause of the problem.

2.2.4 Maylor's Project Life cycles

Maylor (1996:25) uses Deming's Planning, Doing, Checking, and Acting in the

project environment with the objective of continuous improvement, Figure 2.2. The

generic lifecycle for a project involves the consideration of how the level of activity

varies with time. This is illustrated in the Figure 2.3 and shows how the level of

activity is relatively low during the planning phase, increases through the doing phase,

and decreases through check and act phases.

18

Act:

make changes in all phases

to provide for

improvement

Plan

Do Check Act

Leve

l of d

eli

Cum

ula

tive

exp

end i

ture

Time

(a)

Check. Act

Plan

Time

(b)

19

Fig 2.3: Maylor's Project Life Cycle

This pattern is reflected in the graph of cumulative expenditure Figure 2.3 (b) against

time. Outgoings are generally low in the early stages, but grow rapidly during execution

phase. The Figure 2.3 (a) also demonstrates why the check and act phases are so vital —

by the time the majority of the doing phase is completed, the probability is that in excess

of 98% of the total project will have incurred. The last two phases are the time when the

project team themselves can benefit from the process and ensure that lessons (good and

bad) are applied in the future (Maylor, 1996:26).

20

The life cycle may be further broken down as shown in Table 2.2:

Table 2.2: Maylor's Project Life Cycles

Stage in life cycle Activity Description

Planning Conceptualisation Generate explicit statement of needs

Analysis Identify what has to be provided to

meet those needs

Proposal Show how those needs will be met

through the project activities

Justification Prepare and evaluate financial costs

and benefits from the project

Agreement Point at which go-ahead is agreed by

project sponsor

Doing Start up Gathering of resources, assemble

project teams

Execution Carry out defined activities

Completion Time/money constraint reached or

activity series completed

Handover Output of project passed to client

Checking Review Identify the outcomes for all

shareholders

Acting Feedback Put in place improvements to

procedures, fill gaps in knowledge,

document lessons learnt for the

future

(Maylor, 1996:26)

From the above it is seen that Maylor breaks down the into four major sections namely

based on Deming:

Planning

Doing

Checking

Acting

Each of the above sections is subdivided into different tasks as shown in Table 2.2. The

Maylor model of Project Life Cycles involves eleven activities from conceptualisation

(initial idea) to feedback (lessons learnt). The eleven activities make up the four major

sections of Deming's Planning, Doing, Checking and Acting. Maylor's objective in the

aboVe model is to achieve continuous improvement.

2.2.5 Project Management Body of Knowledge's Project Life Cycle

The time frame for the project management process encompasses two sequential steps

of planning and accomplishment. This subdivision was further divided into four

• distinct phases, which are typical of most areas of project application. The project life

cycle may be defined as "The four sequential phases in time through which any

project passes, namely: concept, development, implementation and termination"

(PMBOK Vol.1, 1991: III-1).

For practical purposes in the management of most projects, these four sequential

phases need to be broken down into greater detail. That is, each phase may be made

up of one or more stages and, for purposes of scheduling the actual work involved,

each stage id further developed into a number of activities or tasks (PMBOK Vol. 1,

1991: III-1).

From the various project life cycles offered by the Project Management Body of

Knowledge (PMBOK), the typical and construction life cycles are applicable to a

FMCG industry. These life cycles are shown in the figures below:

21

Plan

Total Project Life Cycle TIME

Accomplish

Phase 1

CONCEPT

Conceive ( C)

Gather data Identify need Establish:

- goals, objectives - basic economics,

feasibility - stakeholders - risk level - strategy - potential team Guesstimate

resources Identify alternatives Present proposal Obtain approval for

next phase

Phase 2 DEVELOPMENT

Develop

(D)

- Appoint key team members

- Conduct studies - Develop scope

baseline: - end product(s) - quality standards - resources - activities

- Establish: - master plan - budget. cash flow - VVBS - policies &

procedures - Assess risks

Confirm justification - Present project brief

Ootain approval to proceed

Phase 3 IMPLEMENTATION

Execute

(E)

- Setup:- organization

- communications - Motivate team - Detail technical

requirements - Establish:

work packages - detailed schedule - information

control systems - Procure goods &

se rvices Execute work packages

- Direct/monitor/ torecasVcontrol:

- scope - quality - time -lost

- Resolve problems

Phase 4 TERMINATION

Finish (F)

Finalize product(s) Review & accept Settle final a/c's Transfer product

responsibility Evaluate project Document results Release/redirect resources

Reassign project team

Fig. 2.4 Typical Project Life Cycle - PMBOK (Vol.!, 1991: E[1-2)

22

Total Project Lite Cycle TIME

<4 Plan

D-

Accomplish

Phase 1 CONCEPT Conceive

C)

Phase 2 DEVELOPMENT

Develop (D)

Phase 3 IMPLEMENTATION

Execute (E)

Phase 4 TERMINATION

Finish (F)

Identify need Develop: Set up organization - Train operators

Establish leastrility: - Plan - Working drawings - Transfer materials

- program, process - block diagrams and specifications - Document results

schematics - sketches - Design reviews - Transfer

- sketches & out- - standards - Procure equipment responsibility

line drawings Conduct studies - Procure construc- Release resources - basic budget & Select equipment tion services Re-assign project

schedule Reconfinn - Produce physical learn - project team economics entity - financing Develop:- - Quality assurance Identity alternatives -budget - Verity performance Present proposal - schedule - Modify as required Obtain approval to

proceed - cash flow prepare & submit

Protect Brief Obtain approval to

implement

Fig. 2.5 Construction Project Life Cycle - PMBOK (Vol.], 1991: 1111!-3)

By breaking up the project down into manageable phases is attractive as it enables the

same standard approach to applied throughout (PMBOK Vol.1, 1991: 111-2).

From Fig. 2.4 and Fig. 2.5 it can be seen that there is a great deal of similarity between

PMBOK, Kernzner, Shtub, Maylor and Turner.

Both project life cycles presented are applicable to the FMCG industry as most

projects have a construction (i.e. erection of buildings) component.

A consolidation of Kerzner, Shtub, Turner, Maylor and PMBOK is presented in 2.8

Summation of Literature Study.

23

HIGH

M4

MODERATE LOW

M2 M3 M1

2.3 Life Cveile Leadership

2.3.1 Situational Leadership

The type of leadership style that is best applicable to project management is situational

leadership: a contingency theory that focuses on follower readiness (Robbins 1998:358).

Therefore, Hersey and Blanchard have developed the best model for a project

management leadership style. The model is shown below in Figure 2.6 (Hersey &

Blanchard, 1982:152): STYLE OF LEADER

PARTICIPAfFING High Relationship Low Task

&

§3

SELIJNG High High

S2

Task & Relationship

Lovy LoW

DELEGATING EGATING Relationship & Task

TELLING High Task 8{ Low Relationship

Si

(LOW) <

TASK BEHAVIOUR

> (HIGH)

MATURITY OF FOLLOWER(S)

24

RE

LATI

ON

SH

IP

EL)

2

Figure 2.6 Hersey & Blanchard Leadership Styles

The attempt (Hersey & Blanchard, 1982:152) in Figure 2.6 is to portray the relationship

between task-relevant maturity and the appropriate leadership style to be used as

followers move from immaturity to maturity. The appropriate leadership style (style of

leader) for given levels of follower maturity is portrayed by the prescriptive curve going

through the four leadership quadrants. This bell shaped curve is called the prescriptive

curve because it shows the appropriate leadership style directly above the corresponding

level of maturity.

Each of the four-leadership styles- telling, selling, participating and delegating identified

in Figure 2.6 above, is a combination of task relationship behaviour.

Relationship behaviour is the extent to which a leader engages in two-way

communication with people: providing support, encouragement, and "psychological

strokes" and facilitating behaviours. It means actively listening to people and supporting

their efforts (Hersey & Blanchard, 1982:152).

The maturity of followers is a question of degree. As can be seen in Figure 2.6, some

benchmarks of maturity are provided for determining appropriate leadership style by

dividing the maturity continuum below the leadership model into four levels: low (M1),

low to moderate (M2), moderate to high (M3) and high (M4).

2.3.1.1 Telling

"Telling" is for low maturity. People who are both unable and unwilling (M1) to take

responsibility to do something are not competent or confident. In many cases, their

unwillingness is a result of their insecurity regarding the necessary task. Thus, a directive

"telling" style (Si) that provides clear, specific directions and supervision has the highest

probability of being effective with individuals of this maturity level. This style is called

"telling" because it is characterised by the leader defining roles and telling people what,

how, when and where to do various tasks. It emphasizes direct behaviour. Too much

supportive behaviour with people at this maturity level may be seen as permissive, easy

25

and most importantly as rewarding for poor performance. This task involves high task

behaviour and low relationship behaviour (Hersey & Blanchard, 1982:153).

2.3.1.2 Selling

"Selling" is low to moderate maturity. People who are unable but willing (M2) to take

responsibility are confident but lack skills at this time. Thus, a "selling" style (S2) that

provides directive behaviour, because of their lack of ability, but also supportive

behaviour to reinforce their willingness and enthusiasm appears to be most appropriate

with individuals at this maturity level. This style is called "selling" because of the

direction is still provided by the leader. Yet, through two-way communication and

explanation, the leader tries to get followers psychologically to "buy in" desired

behaviours. Followers at this maturity level will usually go along with a decision if they

understand the reason for the decision and if their leader also offers some help and

direction. This style involves high task behaviour and high relationship behaviour

(Hersey & Blanchard, 1982:153).

2.3.1.3 Participating

" Participating" is for moderate to high maturity. People at this maturity level are able

but unwilling (M3) to do what their leader wants. Their unwillingness is often a function

of their lack of confidence or insecurity. If, however, they are competent but unwilling,

their reluctance to perform is more of a motivational problem than a security problem. In

either case, the leader needs to open the door (two-way communication and active

listening) to support the follower's efforts to use the ability he has. Thus, supportive,

nondirective, "participating" style (S3) has the highest probability of being effective with

individuals of this maturity level. This style is called "participating" because the leader

and follower share in decision making, with the main role of the leaser being facilitating

and communicating. This style involves high relationship and low task behaviour

(Hersey & Blanchard, 1982:153).

26

2.3.1.4 Delegating

"Delegating" is for high maturity. People at this maturity level are both able and willing

or confidant, to take responsibility. Thus, a low profile "delegating" style (S4) that

provides little direction or support has the highest probability of being effective with

individuals at this maturity level. Even though the leader may still identify the problem,

the responsibility for carrying out plans is given to these mature followers. They are

permitted to run the show and decide on the how, when and where. At the same time,

they are psychologically mature and therefore so need above average amounts of two-way

communication or supportive behaviour. This style involves low relationship behaviour

and low task behaviour (Hersey & Blanchard, 1982:154).

2.3.1.5 Conclusion

It should be clear that the appropriate leadership style for all four of the maturity

designations — low maturity (M1), low to moderate maturity (M2), moderate to high

maturity (M3) and high maturity (M4)- correspond to the following leadership style

designations: telling (S1), selling (S2), participating (S3) and delegating (S4). That is,

low maturity a telling style, low to moderate maturity needs a selling style and so on

(Hersey & Blanchard, 1982:154).

2.3.2 Authority and Responsibility

Several key factors affect the delegation of authority and responsibility both from upper

level management to project management, and from project management to functional

management. These key factors include (Kerzner, 1998:579):

The maturity of the project management function

The size, nature and business base of the company

The size and nature of the project

The life cycle of the project

The capabilities of management at all levels

27

28

Once agreement has been reached on the project manager's authority and responsibility,

the results may be documented to delineate that role regarding (Kerzner, 1998:579):

Focal position

Conflict between the project manager and functional managers

Influence to cut across functional and organization lines

Participation in major management and technical decisions

Collaboration in staffing the project

Control over allocation and expenditure of funds TECHNIKON WITWATERSRAND

Selection of contractors LIBRARY Rights in resolving conflicts

Input in maintaining the integrity of the project team

Establishment of project plans

Provisions for a cost-effective information system for control

Provisions for leadership in preparing operational requirements

Maintenance of prime customer liaison and contact

Promotion of technological and managerial improvements

Establishment project organization for the duration

Eliminate red tape

Documenting the project manager's authority (Kerzner, 1998:579) is necessary in some

situations because:

All interfacing must be kept as simple as possible

The project manager must have the authority to "force" functional managers to

depart from existing standards and possibly incur risk

Gaining authority over those elements of programs that are not under the project

manager's control essential. This is normally achieved by earning the respect of

the individuals concerned.

The project manager should not attempt to fully describe the exact authority and

responsibilities of the project office personnel or team members. Problem solving

rather than role definition should be encouraged.

Although documenting project authority is undesirable, it may be a necessary

prerequisite, especially if project initiation and planning require a formal project chart.

Power and authority are often discussed as though they go hand in hand. Authority

comes from people above you, perhaps by delegation, whereas power comes from people

below you. You can have authority without power or power without authority. In most

companies the project manager has authority from senior management and powered by

the members of the project team. For a project manager, expert power, legitimate and

expert powers are required to complete a project. Also, quite often most project teams

are not static in that a project team is made from different individuals from various

departments — this is called the matrix structure. This clearly shows that a project

manager can have no power as individuals only report to him on a progressive basis, i.e.

movement towards the goal of the project.

In a traditional organisational structure, most individuals maintain position power. The

higher up you sit, the more power you should have. But in project management, the

reporting level of the project might be irrelevant, especially if a project sponsor exists. In

project management, the project manager's power base emanates from his (Kerzner,

1998:580):

Expertise

Credibility with employees

Sound decision-making ability

The last item is usually preferred. If the project manager is regarded as a sound decision

maker, then the employees normally give the project manager a great deal or power over

them.

Leadership styles refer to the interpersonal influence modes that a project manager can

use. Project managers may have to use different leadership styles, depending on the make

up of the project personnel (Kerzner, 1998:579). The best model that depicts an

appropriate leadership style is the Hersey & Blanchard situational leadership model as

29

discussed in 2.3 Life Cycle Leadership. In terms of situational leadership for the project

manager this means that he delegates to competent team members who possess a very

high maturity level. Since team members are assumed to be competent there is a low task

and low relationship between the project manager and team members.

Conflict management is important because if the project manager can predict what

conflicts will occur and when they are most likely to occur, he may be able to plan for the

resolution of the conflicts through project administration (Kerzner, 1998: 579).

Finally, project, line and executive management must analyse other internal and external

variables before finalizing these schedules. A partial listing of these variables includes

(Kerzner, 1998:581):

Introduction or acceptance of the product in the market place

Present or planned manpower

Economic constraints

Degree of technical difficulty

Manpower availability

Available of personnel training

Priority of the project

30

2A Planning, Organising, Controlling and Directing

Kerzner (1998:5) states that a project manager will manage a project by: Planning,

Organising, Controlling and Directing. These form the core of project management.

Each of these core functions is included in the phase management of Kerzner (2.3.1),

Shtub et al (2.3.2), Turner (2.3.3) and Maylor (2.3.4).

The four core functions of management are now discussed. In order to complete a project

life cycle, i.e. from initiation to completion, there has to be planning, organising,

controlling and directing.

2.4.1 Planning

2.4.1.1 Why plan?

The answer according to Ruskin & Estes (1994: 43-44) is that the project definition or

proposal plan is incomplete and too superficial to serve as a project management plan. It

is typically prepared to sell the project and does not address many elements needed to

manage the project. And it may be a success orientated plan, which is hardly protection

against mishaps or a means of contending with them. There are other additional reasons

for planning (Ruskin & Estes, 1994:43-44):

The plan is a simulation of prospective project work, which allows flaws to be

identified in time to be corrected

The plan is a vehicle for discussing each person's role and responsibilities,

thereby helping direct and control the work of the project

The plan shows how the parts fit together, which essential for coordinating related

activities

31

o The plan is a point of reference for any changes of scope, thereby helping project

managers deal with their customers

o The plan helps everyone know when the objectives have been reached and

therefore when to stop.

2.4.1.2 Planning in action

The most important responsibilities of a project manager are planning, integrating and

executing plans. Almost all projects, because of their relatively short duration and often-

prioritised control of resources, require formal detailed planning. Planning generally can

be best described as the function of selecting the enterprise and objectives and selecting

policies, procedures and programmes necessary to achieve them (Kerzner, 1998:519).

The project manager is facilitator in the project who through the assistance of resources

achieves the goals of the project. The success of a project hinges on detailed planning

with built in contingencies if anything were to go wrong.

Project planning can be viewed as setting a predetermined course of action within the

constraints of time, cost and budget. One has to know what is happening when,

conducted by who, why and how. Therefore, it is imperative that milestones be set so

that the progress of the project can be monitored. If the project manager cannot commit

because milestones are unrealistic, the project manager may have to develop alternatives,

one of which may be to move the milestones, planning is required management function

to facilitate the comprehension of complex problems involving interacting factors

(Kerzner, 1998:519).

Nothing builds more confidence in a project manager than the knowledge that the various

alternatives, courses of action and suggestions have been considered and weighed in the

development of a plan (Blanchard, 1990:27).

The project manager is instrumental in the successful planning of a project. Planning on

behalf of the project is easier when the project manager is involved from conception.

Project planning must be systematic, flexible enough to handle unique activities,

disciplined through reviews and capable of accepting multifunctional inputs. Planning is

32

an ongoing activity in the life of a project, even the termination of the project is planned,

otherwise how does one close a project and determine whether the project was a failure or

success (Kerzner, 1998:520).

According to Kerzner (1998:520), one of the objectives of project planning is to

completely define all work required (possibly through a Gantt chart) so that it can be

readily identifiable to each project participant. This is a necessity in a project

environment because:

If the task is well understood prior to being performed, much of the work can be

pre-planned

If the task is not understood, then during the actual task execution more

knowledge is gained, in turn, leads to changes in resource allocations, schedules

and priorities

The more uncertain the task, the greater the amount of information that must be

processed in order to ensure effective performance

The aforementioned points apply to all projects requiring a variety of resources but

functioning under the constraints of time, cost and budget with little margin for error.

Figure 2.7 identifies the type project planning required to establish an effective

monitoring and controlling system (Kerzner, 1998:520):

The boxes in the upper portion of the curve represent the planning activities, and the

lower portion identifies the "tracking" or monitoring of the planned activities.

33

9 U)

Mi

0

Fig

. 2.

7: T

he P

roje

ct P

lan

nin

g an

d C

on

tro

l Sy

stem

(K

ern

zer,

199

8:52

1)

2

8 U

0

MO

U ts

GO

AL

S/O

BJE

CTI

VE

S

SY

ST

IZO

LEV

EL

0 C

OO

PA

NY

LIE

VE

L

0 x

3

O

O SAA

2

3 Mi

4 2

4

SYS

TEM

RE

POR

TS

"I I IT IiitJ a

FEE

DB

AC

K

35

According to Kerzner (1998:520) poor planning will lead to:

Project initiation, demographics not understood

Wild enthusiasm, no plan, free to act on own will — no coordination

Disillusionment, employee or customer dissatisfaction

Chaos, everybody doing what they see fit

Search for the guilty, head hunting to make an example

Punishment for the innocent

Promotion for non-participants

Definition of the requirements

There are four basic reasons for project planning (Kerzner, 1998:520):

To eliminate uncertainty, i.e. fully understand the requirement/objective, the objective is what

must be achieved, planning is how to get there.

To improve efficiency of the operation, this ensures that tasks have continuity and are carried out

in an ordered objective manner.

To obtain better understanding of the objective, deliver what is expected rather supposed

To provide a basis for monitoring and controlling work, progress can be readily assessed

The above links to Ruskin & Estes (1994) Why Plan? 2.4.1.1 in that a project proposal is a mere

marketing tool to sell the project and therefore does not address any elements to manage the project.

From the above it is clearly seen that one has to protect against mishaps or a means of contending with

them.

Also as stated in Planning in Action 2.4.1.2 the most important responsibilities of a project manager are

planning, integrating and executing plans.

36

2.4.1.3 Total project planning

The difference between the good project manager and poor project manager is often described in one

word: planning. Unfortunately, people have poor definition of what project planning actually involves.

Project planning involves for Kerzner (1998: 577-579):

Schedule development

Budget development

Project administration

Leadership styles

Conflict management

The first two items involve the quantitative aspects of planning.

Although each project manager has the authority and responsibility to establish project policies and

procedures, they must fall within the general guidelines established by top management. Guidelines can

also be established from planning, scheduling, controlling and communications.

2.4.1.4 Subplans: A check list for major plan elements

When thinking of a plan, it natural to think mainly in terms of performance or work accomplishment.

This is indeed the central part of any plan, but it is seldom the whole plan JRuskin & Estes, 1994:60).

a. Staffing plans

The staffing plan (Ruskin &Estes, 1994:61) shows that who will be responsible for each part of the work

break down structure (WBS). Attaching a personal name to each element in the WBS, thereby creating a

basic organisation chart, easily represents this plan. Basic charts may be augmented to include staff

positions for selected basic positions for e.g. a secretary as staff to the project manager.

37

The project organisation shows reporting relationships for the project and should not be confused with

the company's organisation chart. Also, the project organisation chart is not a status chart. Thus a

senior individual who is responsible for a detailed portion of a project may report on a project to junior

person who integrates the senior person's work with the work of others (Ruskin & Estes, 1994:62).

Nor is the project organisation chart a device for aggregating the work to be done by individuals. Thus,

the chart should not gather together different responsibilities for a single individual in order to have the

individual's name appear just once on the chart. To do so would obliterate the project's hierarchical

relationships, relationships, which are exactly what is intended to show.

While project organisation charts show project reporting relationships, they do not represent all project

communication lines. Indeed, well functioning projects have a spider web of such lines. However,

project organisation charts do identify the arbitrators of any conflicts that may arise: the individual who

occupies the lowest-lying project organization chart node that spans the conflicting parties is the

arbitrator.

Significant negotiations are often required to obtain commitments of personnel necessary to fulfil the

staffing plan. The project manager can plan for this negotiation by sketching out a tentative plan,

including estimates of the efforts required for each key participant. Prospective project members should

make these estimates whenever possible (Ruskin & Estes, 1994:62).

Some project managers try to economise on the effort needed to staff their projects by assigning

individuals to two hierarchically related WBS elements. This arrangement, however, should be avoided

if possible, for two reasons. First, individuals either tend to become engrossed in the details of their

lower level WBS element and slight their coordination responsibilities at the higher levels, or they tend

to focus on their higher level responsibilities and slight their lower level responsibilities ones. When

coordination responsibilities are slighted, interface problems are likely to be ignored or neglected when

they are small and easy to resolve, which allows them to grow until they are larger and more difficult to

resolve.

38

When lower level responsibilities are slighted, their neglect is likely to be unnoticed or unattended

because individuals are in effect supervising themselves. In either case, slippage and inefficiencies are

likely to result instead of economies.

The second reason an individual should not WBS elements at two levels is that doing so creates

difficulty for other lower level managers. Since the manager of a higher-level WBS element arbitrates

conflicts among managers at the next lower level, an individual responsible for two levels is both

advocate of a lower level element and arbitrator of conflicts at that level. What should another

individual at the lower level make of this duality? Is the two level individual a peer or a boss? Can the

two level individual be both a strong advocate for the lower level element and an objective arbitrator?

These questions are so vexing that those two levels of responsibility for a given individual should be

avoided, if possible (Ruskin & Estes, 1994:62).

To avoid two level assignments, individuals can be assigned to two different projects (or sub projects)

instead, perhaps in highly technical capacity on one hand and in more managerial capacity in another.

While such project require interproject planning, they can be arranged when the organization has

concurrent projects and attention is paid across the organization to avoiding two level assignments.

Interproject staff planning will not only minimize two level assignments problems, it will help optimise

staffing situations overall, and it is strongly recommended. In addition, it will promote cross-

fertilization and thereby minimize redundant efforts.

The decisions and negotiations that are needed to complete a staffing plan are significant, and the project

overall budget and schedule should provide for them accordingly (Ruskin & Estes, 1994:63).

b. Quality control plans

The quality control plan contains the scheme for assuring that the project will produce a good product.

Thus, it tells who is going to check what, when the check will be done, and at what time and resources

required. It may range from a trained pair of eyes that checks the product before it goes out the door to

39

an elaborate and thorough check and cross check of everything done.

The quality control plan should be well known to the entire project staff If one person is to be

responsible for assuring quality, that person should prepare the plan, consulting with those who will do

the work that will be checked and with checkers, as well as the project manager, so that no one will be

surprised (Ruskin & Estes, 1994:63-64).

Equipment and material] plans

The equipment and materials plan pertains to the physical resources needed to accomplish the project. It

begins with a list of items needed, the dates that are needed, suggested sources of supply, and the lead

times necessary to obtain items, including time to obtain price quotations, shipping time, and time to

clear customs if applicable. This information, together with knowledge of the organisation procurement

practices, is then used to establish the sequence of activities and the milestones for specifying and

ordering every piece of equipment, material and any necessary physical installations, including plumbing

and electrical hook-ups needed for the project.

Task leaders prepare equipment and material plans for their respective parts of the overall plan. The

project manager should check these plans to be sure that overall project objectives, particularly schedule

objectives, will still be met. Serious slippages commonly occur because of inadequate provision for

equipment and material lead times (Ruskin & Estes, 1994:64).

Work authorisation plans

The work authorisation plan is the projects manager's scheme for approving successive stages of work.

It consists of periodic reviews and evaluations to establish the readiness and appropriateness of each task

to proceed and a means of authorising each task leader to proceed when appropriate.

A primary virtue of work authorisation plans is that they enable the project manager to revise individual

task plans in order to reallocate resources among tasks as overall project needs change. While a project

40

manager can conceivably retrieve that were once assigned to task leaders, it is psychologically difficult

to do. An easier approach is to release resources incrementally from time to time. This way, the task

leaders are less likely to feel abused when they are required to revise their individual plans as a means of

optimising attainment of overall project objectives.

Sometimes the project manager's customer also authorises work in increments, which are then typically

called phases. The customer's motivation is the same, namely to be able to examine the re sults .of early

work before setting the course and approving work later (Ruskin & Estes, 1994: 64-65).

e. Cost control plans

Cost control is based upon cost expectations (i.e., task budgets) cost measurements, budget-

measurement comparisons and revisions of plans and budgets to achieve budget objective -s when

discrepancies are detected. The cost control plan therefore specifies what budgetary are-needed, what

costs will be measured and what comparisons will be made. It also specifies what techniques will be

used to collect and process the information and review it in a timely way so that suitable corrective

actions may be taken. These activities require resources and time that must be provided in the overall

cost plan (Ruskin & Estes, 1994: 65).

ff. Schedule control plans

Schedule control plans is based on expectations (i.e., performance schedules), measurements of

performance versus time, expectation-measurement comparisons, and revisions of performance plans as

needed to achieve performance and schedule objectives. Thus they resemble cost control plans in form.

The schedule control plan accordingly specifies what performance details will be monitored, when they

will be monitored and by whom. Provisions for these activities must be included in the overall project

plan (Ruskin & Estes, 1994: 65-66).

41

2. Reporting plans

Every project manager will want to know what is going on all the time. And the customer will want to

know on a periodic basis. Thus every project needs a reporting plan that identifies who reports to whom,

what is reported, how often reports are made and how widely the information is distributed.

In order to make overall project reporting as efficient as possible, internal reports (i.e. for those who

work on the project) should be coordinated with reports to the customer. Information should be detailed

and organised to serve multiple users, without recalculation or reformatting whenever possible. Since

satisfying customer needs are of paramount importance, there reporting needs should be determined

before establishing internal reporting requirements.

As in the case of the other sub plans, time and resources must be provided for reporting in the overall

project plan (Ruskin & Estes, 1994: 66).

h. Risk plans

To plan for risk is to consciously search out potentially important adverse occurrences and then

determine how they can be:

Accommodated as if they should happen

First reduced then accommodate

Eliminate or avoid altogether

Thus, risk planning goes beyond merely having overall contingency allowances in the case something

goes wrong. Rather, risk planning involves detailed consideration of adverse occurrences and an action

plan that promises the best cost/benefit results given the resources available (Ruskin & Estes, 1994: 66).

42

2.4.1.5 Managing the planning process

Maylor (1996:49) states that most projects of low complexity will bias the ratio of planning: action

heavily towards the action. As complexity increases, so does the necessity for a formalised plan. This

is both a systematic analysis of the project (which provides its own set of benefits) and an opportunity to

show that the project manager has been systematic in the planning process (by showing the level of

consideration that the project manager has given to issues). 'Traceability' has become a major issue in

many companies — allowing products to be tracked back to records of their constituent parts. The same

is required of a project plan. In the event of an unsatisfactory result, for whatever reason, a good plan

can show that the planner took every possible precaution to ensure that result was positive. Conversely,

should the project go particularly well, you would have an assignable cause for this — namely planning

(Maylor, 1996:48).

The benefits of using a systematic methodology (Maylor, 1996:49) in planning include:

Breaking down complex activities into manageable chunks, i.e. WBS

Determining logical sequences of activities, i.e. CPM

Providing an input to subsequent project management processes, including estimating the time

and resources required for the project

Providing a logical basis for making decisions

Showing effects on other systems

Filtering frivolous ideas and activities

Providing a framework for the assessment of programmes (the post-project review process relies

on comparing the achieved result with the original plan, particularly for the purpose of

improving the planning process)

Being essential for the revision/refinement process

Allowing lessons to be learnt from practice

Facilitating communication of ideas in a logical form to others .

43

The above benefits of being systematic are clearly desirable, though the route to achieving them requires

that a planning sequence be followed (Maylor, 1996:50).

2.4.2 Organising

2.4.2.11 The Need for Organising

To carry out a project involving a large number of people, there must be a clear indication of who has to

do what and, if something goes wrong, who to report to. This applies to situations ranging from an

office where various administrative functions are performed to an engineering project involving several

departments (Van Der Waldt & Knipe, 1998:184).

The organisational structure should give project team members a clear idea if their responsibilities, the

authority they have and the person to whom they must report. Without this basic form of organisation,

the project team is unlikely to achieve its objectives (Van Der Waldt & Knipe, 1998:184).

The organisation process in a project team refers to the division of functions and their assignment to the

project team members. Several methods can be used for this, for the purpose of this study a matrix

organisation is used (you need to put this in) (Van Der Waldt & Knipe, 1998: 1 84).

2.4.2.2 Getting Organised

There are four essential steps in getting a project team organised (Lewis, 1995:99)

Decide what must be done, using WBS, problem definitions and other planning tools

Determine the staffing required accomplishing the steps identified above.

Recruit members for the project team.

Complete your project plan through the participation of team members.

44

Some of the criteria by which team members should be selected include (Lewis, 1995:99):

The candidate should possess the necessary skills to perform the required work at the speed

needed to meet deadlines.

The candidate should have his needs met through the participation in the project.

The applicant should have the temperament to fit in with other team members who have already

been recruited, as well as with the project manager and other key players.

The person should not object to overtime requirements, tight timetables, or other project

requirements.

45

2.4.2.3 Matrix Organisation

A matrix organisation is defined as "one in which there is dual or multiple managerial accountability and

responsibility" (Stuckenbruck, 1996:69). However, the term matrix means quite different things to

different people and in different industries. In a matrix there are usually two chains of command, one

along functional lines and the other along project, product or client lines. Other chains of command

such as geographic location are also possible. The matrix organisational form may vary from one in

which the project mangers holds a very strong managerial position to one in which only a coordinating

role is played (Stuckenbruck, 1996:69).

The primary reason for adopting the matrix in a large organisation can be pinpointed in the fact that

functions and skills are fragmented throughout the organisational structure. Individual functional

departments have great difficulty in solving very large problems because of a failure to view the total

system a tendency to sub-optimise or solve the problem within their particular discipline (Stuckenbruck,

1996:71).

Hence arose the need to form a project team that was complimented by each department, which has

limited expertise that contributed to the total solution.

A hybrid structure known as a matrix organisation provides a sound basis for balancing the use of

human resources and skills as people are shifted from one project to another. The matrix organisation

can be viewed as a project organisation superimposed on a functional organisation with well-defines

interfaces between project teams and functional elements. In the matrix organisation, duplication of

functional units is eliminated by assigning specific resources of each functional unit to each project.

Figure 2.8 depicts an organisation that is performing several projects concurrently. Each project has a

manager who must secure the required resources from the functional groups.

46

President

Vice-president engineering

Vice-president manufacturing

Vice-p -esident marketing

Manager project

ib Mons° I Bob

Gary

Vice-president projects

Manager project 2

Latnrctte Don

Jon Sigmond Tammy Manager project n

Fig 2.8: A Typical Matrix Organisation

Technical support, for example, is obtained from the engineering department and marketing provides

sales estimates. The project manager's request for support is handled by the appropriate functional

manager, who assigns resources based on availability and the project's relative level of need (Shtub at el,

1994:216).

Table 2.3 shows the concerns of both project and functional managers within a matrix organisation

(Shtub et al, 1994:216).

47

Table 2.3: Concerns of Project and Functional Managers

Project Manager Functional Manager

What is to be done? How will the task be done?

What is the importance of the task? Where will the task be done?

When will the task be done? Who will do the task?

How much money is available to do the task? How well has the functional input been

integrated into the project?

How well has the total project been done?

The two must act as partners to coordinate operations and the use of resources. It is the project manager,

though, who is ultimately responsible for the success or failure of the project (Shtub, 1994:216).

Project management is a "coordinative" function, whereas matrix management is collaborative function

division of project management. In the coordinative or project organisation, work is generally assigned

to specific people or units who "do their own thing". In the collaborative or matrix organisation,

information sharing is may be mandatory, and several people may be required for the same piece of

work. In a project organisation, authority for decision-making and direction rests with the project leader,

whereas in a matrix it rests with the team. Certain ground rules for exist for matrix development

(Kerzner, 1998:111):

Participants must spend full time on the project; this ensures a degree of loyalty

Horizontal as well as vertical channels must exist for making commitments

There must be quick and effective methods for conflict resolution

There must be good communication channels and free access between managers

All managers must have input into the planning process

Both horizontally and vertically orientated managers must be willing to negotiate resources

48

The horizontal line must be permitted to operate as a separate entity except for administrative

purposes.

These rules simply state some the ideal conditions that matrix structures should possess. The basis for

the matrix approach is an attempt to create synergism through shared responsibility between project and

functional management. Yet this is easier said than done. No two working environments are the same,

therefore, no two companies will have the same matrix design (Kerzner, 1998:111).

2.4.2.4 Advantages of a matrix organisational form

The following are the advantages of a matrix organisational form (Kerzner, 1998:115):

The project manager maintains maximum project control (through line managers) overall

resources, including cost and personnel

Policies and procedures can be set up independently for each project, provided that do not

contradict company policy and procedures

The project manager has the authority to commit resources, provided that scheduling does not

cause conflicts with other projects

Rapid responses are possible to changes, conflict resolution, and project needs (as technology or

schedule)

The functional organisations exist primarily as support for the project

Each person has "home" after project completion. People are susceptible to motivation and end-

item identification. Each person can be shown a career path.

Because key people can be shared, the program cost can be minimised. People can work on a

variety of problems, that is, better people control is possible.

A strong technical base be developed, and much more time can be devoted to complex problems

solving. Knowledge is available for all projects on an equal basis

Conflicts are minimal, and those requiring hierarchical referrals are more easily resolved

There is better balance between time, cost and performance

49

Rapid development of specialists and generalists occurs

Authority and responsibility are shared

Stress is distributed among the team (and the functional managers).

2.4.2.5 Disadvantages of a matrix organisational form

The following are the disadvantages of a matrix organisational form (Kerzner, 1998:116):

Multidimensional information flow

Multidimensional work flow

Dual reporting

Continuously changing priorities

Management goals different from project goals

Potential for continuous conflict and resolution

Difficulty in monitoring and control

Company-wide, the organisational structure is cost-effective because more people than necessary

are required, primarily administrative

Each project organisation operates independently. Care must be taken that the duplication of

efforts does not occur

More effort and time are needed initially to define policies and procedures, compared to

traditional form

Functional managers may be biased according to their set of priorities

Balance of power between functional and project organisations must be watched

Balance of time, cost and performance must be monitored

Although rapid response time is possible for individual problem resolution, the reaction time can

become quite slow

Employees and managers are more susceptible to role ambiguity than in traditional form

Conflicts and their resolutions may be a continuous process (possibly requiring support from an

50

organisational development specialist)

People do not feel that they have any control over their own destiny when continuously reporting

to multiple managers.

2.4.2.6 Project Organising

A single function may predominate, or the project may require a composite of skills in order to achieve

the objective. The scope of the project will determine the breadth of its organisational structure.

Corporate culture will influence the authorities and the responsibilities assigned to it. Given these

parameters, the project manager can then form his team using the following steps (Blanchard, 1990:70-

71).

Divide the objectives into individual tasks. If the project is large, it may be necessary to establish sub

objectives to permit greater divisibility. This is commonly called the work break down structure (WBS).

It is important to differentiate between the WBS and the structure. Tasks fall into to different

categories: those dependent on each other in a sequential fashion and those, which have commonality of

skills, required to perform them.

Determine those tasks, which have common skill factors, complexity, and priority and performance

durations. The result of this exercise is determination of the number and abilities of the individuals

needed to perform the tasks.

Determine the qualifications of the personnel required to perform each of the tasks and note any

special skills needed.

Examine the whole and make adjustments as required to match the results of step immediately

above. This may require moving people from one group to another, combining or breaking

down tasks, and adding or subtracting individuals.

51

Group the individuals in such a way as to reduce the initial project to one of several projects that

minimize dependency on one another. The maximum of dependency between individuals should

occur within own work group.

Supervision is chosen to link the groups through a system of interdependence, which considers

skill requirements and time factors. As with the main project, the groups should perform their

respective tasks, then go out of business. Shifting individuals whose skills are required in later

groups can retain continuity.

2.4.3 Controffing

Controlling is a three-step process of measuring progress toward an objective, evaluating what remains

to be done, and taking the necessary corrective action to achieve or exceed the objective or the

objectives. These three steps — measuring, evaluating and correcting — are defined as follows (Kerzner,

1998: 227):

Measuring: determining through formal and informal reports the degree to which progress

toward objectives is being made.

Evaluating: determining cause of and possible ways to act on significant deviations from planned

performance.

Correcting: taking control to correct an unfavourable trend or to take advantage of an unusually

favourable trend.

Ruskin & Estes (1994: 88) adds a fourth objective:

Timely corrective actions designed to meet the objectives, schedule or budget.

52

The project manager is responsible for ensuring the accomplishment of group and organisational goals

and objectives, e.g. compliance to 1S09002. 1S09002 is a model for quality assurance introduction,

installation and servicing as prescribed by the South African Bureau of Standards (SABS), (SABS

1S09000, 1994:8). To this effect, the project manager must have a thorough knowledge of standards

and control policies and procedures so that a comparison is possible between operating results and pre-

established standards. The project manager must then take the necessary corrective actions (Kerzner,

1998:227).

The process of control can be devised into the following categories (Ruskin & Estes, 1994:92-96):

Task control: Task control consists of assuring that the work itself is accomplished according to

plan (without regard to schedule or budget, which are handled separately).

Schedule control: schedule control of assuring that the work is accomplished according to the

planned timetable. Generally, there is little concern if the work is accomplished early, so

attention is usually focused on preventing slippage. However, if premature accomplishment

would result in cash flow problems or excessive interest charges, project manager should keep

major activities from occurring until they are needed.

Cost control: Cost control consists of assuring that work elements are accomplished within their

respective budgets. Because of their differing characteristics, it is useful to have three separate

budgets for each work element: direct labour, support services and purchased services,

equipment and materials.

2.4.3.1 Task control

a. Detailed functional objectives

Task control is based first of all upon detailed functional objectives for the elements in the WBS. Each

objective should have a detailed statement of work so that they can be accomplished unambiguously.

53

The increments of work should be no greater than the schedule and budgetary contingency allowances

available to fix any mistakes that are found, and preferably much less. Then, if a particular increment of

work is found deficient, it can be done within available allowances and not thwart the attainment of the

project's overall objectives, schedule and budget.

By monitoring in increments that are relatively small compared to whichever of the schedule and

budgetary contingency allowances for the segment is more stringent, correction of a single deficiency

will not exhaust a major part of the allowance. This will leave some allowance for correcting other

increments that might be later found deficient. As a rule of thumb, monitoring increments that are 5% to

10% of available allowances have proven successful (Ruskin & Estes, 1994: 92).

Quality inspections

Inspections of work quality are a important aspect of task control and go hand in hand with detailed

functional objectives. Each work increment, no matter simple, needs to be checked at some level to

assure that it is satisfactory. Project managers dare not find that a trivial item, such as late delivery,

wrong specification, inadequate access, incorrect size, faulty instrument, lack of suitable personnel and

so forth, is precluding a successful project. And, certainly, no major task can go unchecked. Thus,

project managers must arrange for timely and appropriate reviews or inspections to confirm either that

the work is being done according to plan or that a deficiency exists that must either be corrected or

accommodated by changing the plan (Ruskin & Estes, 1994: 93).

Work orders

Another element in task control is the use of work orders to authorise work increments or packages. By

using work orders, the project manager can force personnel working on parts of the project to coordinate

their efforts: they may not proceed until authorised or the authorisation will be given only when the

project manager is satisfied that their interactions are properly reflected in their respective efforts. This

approach minimizes the chance of having to redo a portion of the work because of overlooking

interactions of related activities (Ruskin & Estes, 1994: 93).

54

Work orders also prevent flexibility for major revisions, which may be necessary if contingency

allowances are fully consumed. When an original contingency is used up, the only way the project

manager can provide for still other possible deficiencies and unforeseen events are to rescope some or all

of the remaining work. While it is theoretically possible to cancel work already authorised, it is time-

consuming and costly to do so. On the other hand, if most of the future work is yet to be authorised,

some of it can easily be cancelled, simply by not authorising it. Thus, using work orders makes it easier

for the project manager to rescope future work in light of the total situation and thereby better meet their

overall project goals (Ruskin & Estes, 1994:94).

2.4.4 Directing

Directing (Kerzner, 1998:227) is the implementing and'carrying out (through others) of those approved

plans that are necessary to achieve or exceed objectives. Directing involves such steps as:

Staffing: seeing that a qualified person is selected for each position.

Training: teaching individuals and groups how to fulfil their duties and responsibilities.

Supervising: giving others day-to-day instruction, guidance and discipline as required so that can

fulfil their duties and responsibilities.

Delegating: assigning work, responsibility and authority so others can make maximum utilisation

of their abilities.

Motivating: encouraging others to perform by fulfilling or appealing to their needs.

Counselling: holding private discussions with one another about how he/she might do better

work, solve a personal problem or realise his/her ambitions.

Coordinating: seeing that activities are carried out in relation to their importance and with a

minimum of conflict.

55

Directing subordinates in a project environment is not an easy task because of both the short time

duration of the project and the fact that employees might still be assigned to a functional manager while

temporary assigned to your effort. The possibility of "getting to know" one's efforts may not be possible

in a project environment.

Directives should be written with one simple and clear objective so that subordinates can work

effectively and get things done first time right. Oral orders and directives must be and should be

disguised as suggestions and requests. The requester should ask the receiver to repeat the oral order so

that there is no misunderstanding (Kerzner, 1998:228).

Project managers must understand human behaviour, perhaps more so than functional managers. The

reason for this is that the project manager must continually motivate people toward successful

accomplishment of project objectives. Motivation cannot be accomplished without at least a

fundamental knowledge of human behaviour.

Kerzner uses organisational behaviour model, Theory X and Theory Y by McGregor. The model is best

described Robbins (1998 170):

Douglas McGregor proposed two distinct views of human beings: one basically negative labelled Theory

X, and the other basically positive, labelled Theory Y. McGregor concluded that manager's view of the

nature of human beings is based on certain grouping of assumptions and that he tends to mould his

behaviour toward subordinates according to these assumptions.

Under Theory X, the four assumptions are held by managers are:

Employees inherently dislike work and, whenever possible, will attempt to avoid it

Since employees dislike work, they must be coerced, controlled, or threatened with punishment

to achieve goals

Employees will avoid responsibilities and seek formal direction whenever possible

56

Most workers place security above all other factors associated with work and will display little

ambition

In contrast to these four negative views about the nature of human beings, McGregor listed four positive

assumptions that he called Theory Y:

Employees can view work as being as natural as rest or play

People will exercise self-direction and self control if they are committed to the objectives

The person can learn to accept, even seek responsibility

The ability to make innovative decisions is widely dispersed throughout the population and is

not necessarily the sole province of those in management positions

What are the motivational implications if one accepts McGregor's analysis? The answer is best

expressed in the framework presented by Maslow. The Theory X assumes that lower order needs

dominate individuals. McGregor himself held to the belief that Theory Y assumptions were more valid

than Theory X. Therefore, he proposed such ideas as participative decision-making, responsible and

challenging jobs and good relations as approaches that would maximize an employee's job motivation.

This proposition links to Hersey & Blanchard's Model of Situational Leadership, which is explained

later.

25 ll effine the scope of work for the prof ect

The failure to define and agree on the scope of work prior to starting a project is one of the most

frequent causes of cost overruns and schedule delays. There are a number of reasons for this, such as the

common perception that time is short and everyone understands what has to be done anyway. Another is

the feeling that, if the full scope of work is revealed, the project may not be approved. Even when

design specifications are prepared in detail, experience shows that contractors will often encounter many

unforeseen problems. All if this is often due to the inherent difficulty in defining the scope of the small

project due to its revamp nature (Westney, 1985:39).

57

When a project is complete? Does a project scope include start up and commissioning of all systems?

Does it include final revisions of all drawings? Does it include all punch list items? The answer is, it all

depends. Some projects include these items and others do not (Westney, 1985:39).

If a clear definition of the technical and planning scope of work cannot be easily obtained, the project

manager should clearly document his assumptions, and thereby set the basis for discussing changes if the

assumptions turn out to be incorrect.

2.6 Commissionitng

The commissioning stage is deceptive to the uninitiated. If start up were as simple pressing a button or a

switch, everyone would be delighted but this is rarely the case. To examine this stage in some detail the

following subdivisions may be discerned (not necessarily in strict chronological order) (Snowdon,

1977:27):

Verification that the work has been completed to the approved design. This is an overlap of the

construction activity and needs to be done once thoroughly and not twice partially.

Performance testing to acceptable standards. Methodical verification is required and should

achieve high degree of confidence.

Dummy runs.

Operator training may have already have begun during construction but will be remembered that

the end of the commissioning stage is routine operation.

Stage-wise operation may be necessary in a multistage project or process. It may also be

necessary to try out latter processes first to pave the way for subsequent successful operation of

the earlier stages. Stage-wise activity mat also be necessary to achieve quality checks at

58

intermediate places in production lines.

o Planning and programming of all these activities is obviously necessary particularly as the

pressures will be very severe with the majority of the capital spent and a great anxiety to achieve

some return with all possible speed.

2.7 Takeover

Most authors make mention of project takeover, but do not delve into the subject. Takeover marks the

beginning of the end of the project, where the customer takes over the functional aspect of the new

operation. This has to be preceded by successful commissioning, this means that the objective has been

achieved. Whittaker (1995:358-359) states the following:

It is usual for commissioning to be carried out under the supervision of the owner of the technology: the

contractor, a third party or the employer himself. If the employer is responsible for commissioning, then

this may be managed by the receiving works, rather than by the employer's project manager. In any

case, the bulk of the staff concerned in the commissioning will be provided by the employer, and will be

composed of experienced operating staff who must work closely with design, construction and the

works, and many of them will go on to operate and maintain the plant on a permanent basis. The first

members of commissioning team to be appointed will be the works representatives on the employer's

project team. The assembly and necessary training of the rest team will need to commence some months

before the first part of the completed plant is to be handed over. Plant operating instructions and

emergency procedures must be produced. At the same time the commissioning plan must be developed

to detail with that of construction, fleshing out the bare outlines that were included in the project

program at the sanction stage.

The construction management will be concerned to agree the timing of takeover and the required

condition of the plant at the time. Both the size of the commissioning task and its nature require that it

be carried out in a phased way: it is not practical to start up everything at once even if resources

permitted. The possibility of overlapping construction and commissioning therefore arises, and this is

59

commonly done. However, the way in which the construction of a process plant is most efficiently

organized does not match the requirements of a phased commissioning program. Systems that are made

live will run through areas where construction is still proceeding. High safety standards, and rigorous

clearance and permit to work procedures will be required. Both construction and commissioning labour

forces will need to be experienced, well trained and disciplined. Where this is not the case, the extent of

overlap must be reduced.

The take over of a major process plant from construction to the commissioning team is a complicated

business. The work that follows erection — cleaning, inspection, testing and generally confirming that

the plant is in fit state to start up — is extensive. If not properly managed there can be a good deal of

duplication of effort by the construction and commissioning teams. It is therefore important that both

should be clear about what is required and who is responsible. Proper budgeting and allocation of costs

is also desirable. The various responsibilities might be as follows:

o Construction

Erection: complete to design and specifications. Defects rectified, cleaning, flushing and

pressure testing complete. Construction equipment, rubbish and debris to be removed.

Conditioning: including air and steam blowing of lines, leak tests, any further water

flushing required, service tests and acid washing. Oil changed in gearboxes, motors run

to confirm direction of rotation. Instruments loop checked and calibrated, checked.

o Takeover

The customer takes over functional aspect of the operation, preceded by successful

commissioning. Start incorporating project into existing works.

60

o Commissioning:

o Pre-commissioning: including water trials, trials of rotating equipment.

o Commissioning: chemicals introduced into the plant.

2.7.1 Conclusions

Although the conditioning work is the responsibility of construction, the definition of what needs to

done and the commissioning team would lay down the final standards of acceptance, who must monitor

what is done. The nature of the conditioning work is such that an individual sub-contractor is unlikely to

agree to its inclusion in the program for which he accepts liability.

Mechanical completion and takeover by the commissioning team may be separated by the conditioning

stage (Whittaker, 1995:360).

Takeover should not be confused with handover, the difference between the two being:

Takeover: operation start to incorporate the project into existing works, but operating rates need to be

achieved.

Handover: when operating has been achieved and the plant is in a suitable state, the handover and

divestment of the project team can begin. Operations are now fully responsible for the project.

61

2.8 Summation of Literature Study

Life cycle management, the basis being Kerzner and Shtub et al, best implements the process of project

management. Therefore, management will be situational, hence the model developed by Hersey and

Blanchard is best suited. The core function of management is planning, organising, directing and

controlling (Kerzner, 1998:5).

The model shown below is called the Contemporary Systems Approach to Project Management.

2.8.1 Phase 1 Conceptual Design

Determine goals (2.2.2.1) and (2.2.5)

Establish system concepts to provide initial strategic guidance to overcome existing or potential

difficulties (2.2.1.1)

Show project needs will be met through project activities e.g. conduct technology search, if

technology does not exist in-house, develop R&D program or bring in consultancy's (2.2.4) and

(2.2.2.1)

Examine alternative ways of achieving goals (2.2.1.1) and (2.2.5)

Determine environmental and economic feasibility (2.2.1.1) and (2.2.5)

Provide answers for (2.2.1.1):

What will the system cost?

When will the system be ready?

What will the system do?

How will the system be integrated into the existing systems?

What resources are required?

Generate scope (2.2.3)

Select initial system design that will best satisfy the project goals (2.2.2.1)

62

Liase with the customer to check if the work requirement or project goal is properly understood

(2.2.3)

Go/no decision (2.2.3) and (2.2.4)

2.8.2 Phase 2 Detailed Design

Select the appropriate project manager (2.2.2.2) and (2.2.5)

Commitment from senior management (2.2.2.2) and (2.2.4)

Refine the elements under the conceptual phase (2.2.1.2)

Select the "best" system for achieving the goal (2.2.1.2) and (2.2.5)

Reach agreement on system design and then generate the following (2.2.2.3) and (2.2.5):

Freeze project scope

Project planning

Project Budget

Project Schedule

Determine the extra resources required and for what duration (2.2.1.1)

Identify areas of risk and uncertainty and outline plans for further exploration of these areas

(2.2.2.3)

Conduct a HAZOP (hazardous operation study), operation to be intrinsically safe in all

respects/disciplines of engineering and operations (2.2.2.3)

Start documentation process such as policies, procedures, job descriptions and etc (2.2.1.2)

Can the system still be afforded, i.e. after final costing is it economically viable (payback)

(2.2.3)?

Detailed contingency plans for areas of risk: Can enter into technological agreements to share or

brokerage of information (2.2.2.3)

Develop procedures for work authorization, performance reporting (2.2.2.3)

Develop training manuals (2.2.1.2)

63

2.8.3 Phase 3 Production

Updating of detailed plans conceived and defined during the preceding phases (2.2.1.3), (2.2.3)

and (2.2.5)

Maintain top management support and flow of communications within and among the

participating organizations (2.2.2.4) and (2.2.5)

Verification of system production specifications (2.2.1.3)

Update change of scope register (2.2.2.4) and (2.2.5)

Beginning of production, construction and installation (2.2.1.3)

Monitor actual progress and compare to baseline plans, i.e. critical path and network diagrams

and WBS (2.2.2.4), (2.2.3) and (2.2.5)

Final preparation and dissemination of policy and procedural documents (2.2.1.3)

Performance of final testing to determine adequacy of the system to do the things it is intended

to do, if so, hand over document to be signed, this if process can generate some profit, but not

target profit (2.2.1.3)

Training of operators (2.2.1.3) and (2.2.5)

Development of technical manuals and affiliated documentation describing how the system

intended to work (2.2.1.3) and (2.2.5)

Develop systems to support the system during its operational phase (2.2.1.3)

2.8.4 Phase 4 Operational

Acceptance of final results by customer (2.2.4)

Check competency of operators (2.2.3) and (2.2.2.3)

Evaluation of technical, social and economic sufficiency of the project to meet actual operational

conditions (2.2.3) and (2.2.5)

Use of the system results by the intended user or customer (2.2.1.4) and (2.2.3)

Start to prepare handover documentation (2.2.2.5) and (2.2.3)

64

Actual integration of the project's product or service into existing organizational systems

(2.2.1.4)

Provide feedback to organizational planners concerned with developing new projects and

systems (2.2.1.4)

Evaluation of the adequacy of supporting systems (2.2.1.4)

2.8.5 Phase 5 Divestment

Develop plans for transferring responsibility to supporting organizations, i.e. handover (2.2.1.5)

and (2.2.5)

Divestment or transfer of resources to other systems (2.2.1.5) and (2.2.3)

2.8.6 Phase 6 Assessment

Development of "lessons learnt from system" for inclusion in quantitative-qualitative database to

include:

Assessment of image by the customer (2.2.15) and (2.2.5)

Major problems encountered and their solutions (2.2.1.5)

Technological advances (2.2.1.5)

New or improved management techniques (2.2.1.5)

Recommendations for future research and development (2.2.1.5)

Recommendations for management of future programs, including interfaces with associate

contractors (2.2.1.5)

Other major lessons learned during the course of the system (2.2.3)

65

2.8.7 Planning & Control

Through each of the steps mentioned in the phases of project management, planning and control must be

practiced to a high degree.

The steps that must be followed during planning are as follows:

Understand exactly what is required by the client, sign a contracted scope of work, this to be

used as a "live" document for the service rendered. The scope should include the objective and

termination dates (2.4.1.1).

Establish a basis of a planning network (CPM), identifying key milestones. Plan to do detail

planning for each phase only when necessary. Conduct a hazardous operation and environmental

impact studies (2.4.1.5)

Assess time and resource requirements and provide slack time (i.e. overruns) (2.4.1.1).

Confirm staff allocations via organizational matrix (2.4.2.3).

Make allocation for staff training (2.4.1.5).

Project authority should be clearly defined (2.4.1.3).

The steps to be followed during the controlling are as follows:

Establish communication systems, both within the project and senior management (2.4.3).

Hold fortnightly meetings to monitor progress with the client. Informal communication channels

should be established (2.4.3.1c).

Use Deming's PDAC to project plan in check (2.3.4).

Monitor quality in all regards, workmanship, service rendered and received (2.4.3.1 b).

Maintain a scope change register (2.4.3).

Track actual costs to forecasts (2.4.5.1a).

Record reasons for slippage, inform management/client and move termination date accordingly

(2.4.3.1a) and (2.4.3.1c).

66

8) Does the project management procedure comply with IS09002 (2.4.3)?

2.8.8 Management Style

The management style to be adopted is the Hersey & Blanchard S4/M4 relationship (2.3) by work is

delegated and there are low management relationships. It is assumed that team members are willing and

able. The manager should also have the ability to motivate (McGregor Theory X &Y and Maslow

Theory of Needs) the project.

67

clua ger 3 Method&logy

3.1 l[ntroduction

The methodology that was adopted is an integral part of the understanding of the basic concepts of

this research. Project management, as with any other professional trait needs to be developed. One

of the final objectives in project management are lessons learnt, so, does one need to go through a

life span to gain the necessary experience, NO. There is no point in wasting time to learn from one's

own mistakes — a clever man learns from his own mistakes, an intelligent man learns from others'

mistakes. TECHNIKON WITWATERSRAND LIBRARY

Questionnaires for both experienced and inexperienced project managers were drawn up. The primary

reason for this is to determine whether experienced project managers support the model described in 2.8

Contemporary Systems Approach to Project Management. Secondly, to determine what inexperienced

perceive project management to be and would the use of the stated model assist them in the execution of

a project they are responsible for.

The model in 2.8 is summation of various authors' works. For the above reasons structured surveys

were prepared for both experienced and inexperienced project managers.

This research was conducted at African Products, a corn wet milling company producing starch, glucose

and animal feeds in South Africa. There are four sites country wide: one plant in Germiston -

Johannesburg, one plant in Alberton - Johannesburg, one plant in Meyerton — Meyerton, one plant in

Belleville — Cape Town and a head office in Meadowdale - Germiston.

lo 33

68

3.2 African Products Project Structure

One of the strategic objectives of African Products is to be world class — this is demonstrated in

attracting and retaining the best employees. Therefore, there are always opportunities develop.

The current human resource grading system is the Patterson system. The project structure is based

on the organisational matrix. This creates an excellent training field for the inexperienced project

manager.

easons for choosing (questionnaires

A questionnaire is a printed list of questions which respondents are asked to answer. (Mellville &

Goddard, 1996:43). The questionnaire must be an effective one. This requires planning before hand to

ensure that the data can be objectively analysed afterwards.

The main reason for opting of for the questionnaire is that the researcher knows what precisely what

information is required to validate the model presented in 2.8.

Closed (or structured) are used in large-scale data collection. Here respondents choose from alternatives

(e.g. true/false) or assign numerical score or ranking (Mellville & Goddard, 1996:43). The questionnaire

used in this study is based on a five-point scale, which allows for a neutral answer.

69

A good questionnaire:

Is complete: gets you all the data you need

Is short: don't abuse the respondents time or concentration

Asks only relevant questions

Gives clear instructions

Has precise, unambiguous and understandable questions

Has objective answers, don't suggest answers

Starts with general questions

Has appropriate questions: if you have to ask sensitive questions, put these at the end

Uses commonly closed questions, often with a 4-point scale.

(Mellville & Goddard, 1996:43-44)

The above was taken into consideration when drawing up the two questionnaires in this study.

Some of the advantages of using a questionnaire are:

Helps the researcher to obtain data fairly easily

Information from questionnaires are easily coded

Benefits the scientific community if the measures are well validated and are reliable

Often is a catharsis for respondents.

3A Criteria for seliection of respondents

The researcher was of the opinion that the criterion for respondent selection should be:

70

0 Inexperienced project manager: a person with less than two years of experience in this field,

i.e. managing projects. The premise for choosing two years is based is that the projects team

in African Products is relatively young in terms of employees' ages, hence experience is not

vastly available.

o Experienced project manager: a person with more than two years experience in this field.

This was based on the premise that this person has managed projects for greater than two

years. Most long-term projects have a duration of a year, for this reason the researcher that

this calibre of person was ideal an experienced project manager. Also, it is rare or never that

a large project is managed by an inexperienced project manager.

33 Questaionnaires

Questionnaires were forwarded to both in/experienced and experienced project managers, each

questionnaire is discussed in 3.5.1 and 3.5.2 respectively.

In Appendix A, the two types of questionnaires are shown.

3.5.1 Inexperienced Project Managers' Questionnaire

An inexperienced project manager is defined as someone who has less than two years experience as a

project manager. In African Products this type of person is given first hand training being part of project

team, as time progresses the responsibility of decision-making is increased.

Since most inexperienced project managers are recent graduates or diplomats their knowledge is limited

both practically and theoretically. As time is spent working on project, the future project manager

begins to gras.p the knowledge of executing a project to completion within the parameters of time, cost,

resources and technology. Also, how the matrix structure works.

71

The following are the questions posed to the inexperienced project managers:

What are the most important management functions in project management?

Can project be broken down into phases, if so state?

Would the model presented in 2.8 make project management easier?

What are the pitfalls of using such model as presented in 2.8?

How and why is planning and controlling important?

How should one deal with deviations from plans?

What management style is preferred (by the project manager)?

3.5.2 Experienced Project Managers' Questionnaire

An experienced project manager is defined as someone who an excess of two years experience working

in project teams and managed project independently. These project managers have both practical and

theoretical knowledge of project management.

The experienced project manager was asked to comment on each phase of the model presented in 2.8.

They had the following in terms of answering the questions, five-point scale:

Strongly agree

Agree

Indifferent

Disagree

Strongly disagree

Recommendations

Recommendations gave the opportunity to express a personal view point be positive or negative.

In addition, outlines of planning, controlling and the Hersey & Blanchard S4/M4 situational

72

management model were also surveyed with the experienced project managers. Again, they had the

aforementioned options in answering the questions.

3.6 Samphing

The target population for the purpose of this study were people that involved in project management at

African Products.

Due to the size of the company few people are involved in project management. For this reason only

nine inexperienced and ten experienced project managers were sampled. The focus for inexperienced

project managers firstly on determining the level of understanding in terms of project management and

secondly would the respondent gain from utilising the model presented in 2.10. The focus on

experienced project managers was determine if the these respondents accepted the model presented in

2.8.

3,7 Data atfiallysis

The data obtained from the questionnaires sent out has been coded and has been input into a computer

spreadsheet program to assist in analysis. According to Emory & Cooper (1994:381) "Coding involves

assigning numbers to the answers so that the response can be grouped into a limited number of classes or

categories." This was the method used for analysing the responses for both experienced and

inexperienced project managers.

The objective of descriptive research can be seen as the portraying of an accurate profile on events or

situations and may be the forerunner to, or the extension of exploratory research. It can be described

as "to have a clear picture of the phenomena on which you wish to collect data prior to the collection

of the data (Saunders et al, 1977:79).

The descriptive research in this study will take the form of the systematic collection information on

assessment of the model proposed in 2.10 in terms of acceptance, this by both experienced and

73

inexperienced project managers. The data obtained can be used to assess the knowledge of

inexperienced project managers and acceptance by experienced project managers together with

recommendations.

74

Cm ter 4 Resullts

401 Survey Results — Inexperienced Proiect Managers

The questionnaire is given as Appendix A.

4.1.1 Question!

Inexperienced project managers were asked in their opinion what are the most important management

functions in project management. Table 4.1 shows the response to this question.

Table 4.1: Responses to Question1

Planning Organising Controlling Directing

Personl * * *

Person2 * * * *

Person3 * *

Person4 * * *

Person5 * * *

Person6 * * *

Person? * *

Person8 * *

Person9 * * *

The following terms were classified as synonyms by the researcher:

Directing = People management

Organising = Achieving objectives, delegating, scheduling

Coordinating = Planning

75

Planning, Organising, Controlling and Directing is defined by Kerzner (1998:5) as the main management

functions in project management.

From Table 4.1 it can be seen that five people agreed as to the most important functions of project

management. This represents 56% of those surveyed. Some people could not state the functions of

project management explicitly. This is clear indication that the functions are project management are

not clear, this is due receiving little or no training at all. Most peoples' general perception of a project —

a goal to be met in a limited time and money and also non-repetitive. Beyond this there is very little that

is understood...

4.1.2 Question 2

In Question 2 the sample was asked if a project could be broken down into phases and if so, requested to

state them. Table 4.2 shows the response to this question.

Table 4.2: Various Phases of a Project

Phase Conceptual Detailed Production Operational Divestment Assessment

Breakdown Design Design

Personl Yes * * *

Person2 Yes * * * *

Person3 Yes * * * *

Person4 Yes * * * *

Person5 Yes * * * *

Person6 Yes * * * * * *

Person? Yes * * * * *

Person8 Yes * * * *

Person9 Yes * * * * *

The following terms were classified as synonyms by the researcher:

76

Conceptual = Evaluation of idea, idea

Detailed design = Final design

Production = Build, erect, implementation, execution, supply

Operational = Performance test, commission, benefit of idea

Divestment = Commercialisation, hand over

Assessment = Project evaluation, customer satisfaction

Table 4.2 indicates that 22% of the respondents correctly identified the phases of project management.

The remaining 78% could identify four to five the phases in project management, the phases referred to

the model presented in 2.10 — Contemporary Systems Approach to Project Management. Four

respondents, 44% were able to categorise five of the six phases. This indicates that they have some idea

what the phases of project management is, hence the need for training in applying the postulated model.

4.1.3 Question 3

Question 3 enquired if a model as postulated in 2.10 — Contemporary Systems Approach to Project

Management was made available, would this make project management easier, i.e., systematic. The

answer to this question is depicted in Table 4.3.

77

Table 4.3: Utilisation of Contemporary Systems Approach to Project Management

Yes No

Person] *

Person2 *

Person3 *

Person4 *

Person5 *

Person6 *

Person? *

Person8 *

Person9

The comments are summarised as follows by the researcher:

Good base to operate from

Clearly outlines activities to be performed, can be modified to suit predicament

Work not compromised

Can be used a tool for project tracking/performance

Better planning and control

The model may not always work in a crisis situation

Using such a model will promote sameness and ease of documentation and future additions

A very definite path to follow, which leads to professional management of the process

As shown in Table 4.3, there is 100% support for the Contemporary Systems Approach to Project

Management. This clearly shows the Contemporary Systems Approach to Project Management will be

valuable tool in the execution of the project.

78

It is true that postulated Model cannot be used in a fast track project. Something that overcomes this

hurdle, fast track projects is always managed by experienced project managers. A strong technical base

usually compliments such projects, i.e. experienced operators and engineers.

4.1.4 Question 4

This question pondered if there were any pitfalls in using as postulated in 2.10 — Contemporary Systems

Approach to Project Management. The replies to Question 4 are shown in Table 4.4.

Table 4.4: Pitfalls to using the Contemporary Systems Approach to Project Management

one Commented

Personi *

Person2 *

Person3 Commented

Person4 *

Person5 *

Person6 Commented

Person? Commented

Person8 Commented

Person9 *

The comments received to Question 4 are shown below:

People have their own preferences and may not accept the Model

Frequent use would lead to greater acceptance

Model may be industry specific

If you not planning, you planning to fail

79

o No two projects are the same

o Adhering to all aspects of the model at all times can take time. Not all projects are big enough

for full project management.

As can seen from the above comments there are valid points raised as pitfalls, also in a fast track project

a lot steps in the project management procedure will be omitted, i.e. tailored to the situation. Also,

people tend to develop comfort zones, that is, set ways in doing things, convincing such people to

change is a project in itself — you cannot teach an old dog new tricks. Therefore, if this model is

implemented at grass roots level, it must be implemented in the full, unless the project is being fast

tracked, otherwise the natural flow of project management will not be realised. Respondents that

indicated that there were no pitfalls to the utilisation of the model were 56%. This can be viewed as

enthusiasm for using such a model. Gauging the response to Question 4, it obvious that the use of the

model will definitely benefit inexperienced project managers.

4.1.5 Question 5

Question 5 prompted inexperienced project managers to answer why planning and control are important

in project management. The replies to this question are shown Table 4.5.

80

Table 4.5: The Importance of Planning and Control

Replies

Person 1 To maintain overall control and enables proper management

Person 2 Communicates objectives to be achieved within the constraints of time and

money

Person 3 Focus on objective and know when end point is reached

Person 4 If you don't plan, you planning to fail

Person 5 Eliminate overlaps and saves time and money

Person 6 Establish milestones and overall performance can be compared to forecasts

Person 7 Need set objectives and show how objectives are to achieved

Person 8 Lack of planning and control leads to overspending and under/over utilisation

of resources, which in turn makes an unhappy customer and low profit

margins.

Person 9 To make sure the right product is delivered at the right price at the right place.

All of the replies to Question 5 are correct. The objective of a project is to achieve the set objective

within the constraints of time, technology and resources — resources being mainly finances and people.

Also, a project is a non-repetitive task. Therefore, to be successful at project management one requires

planning and controlling such that the customers needs can be satisfied. Planning and control is required

in each phase of the Contemporary Systems Approach to Project Management.

If there is no plan, there is no way one can know where one is going. This will be Chaos even the Chaos

Theory will be of no use! As one the respondents stated "If you not planning, you planning to fail."

81

4.1.6 Question 6

In Question 6 respondents were asked how should one deal with deviations from plans. Table 4.6 shows

the answers to this question.

Table 4.6: Responses to Deviations

Contingency

Planning

Personl *

Person2 *

Person3

Person4 *

Person5 *

Person6 *

Person?

Person8 *

Person9 *

Person 8 comments:

o Change /amend plans such that it has the least impact on the critical path, minimum penalties

with a happy customer. In no way alter the end goal.

This is true, and more importantly the quality of the goal must not be compromised.

In essence, one has to plan for unexpected. As Murphy's Law states: If something can go wrong, it will.

All responses to this are question is considered correct.

82

4.1.7 Question 7

Question 7 probed what type of management style did the inexperienced project managers prefer. This

was based on the Hersey & Blanchard Model of Situational Leadership. Table 4.7 illustrates the

management style preferred.

Table 4.7: Preference of Management Style

Delegative Participative Participative

To Delegative

Personl *

Person2 *

Person3 *

Person4 *

Person5

Person6 *

Person? *

Person8

Person9 *

Some people chose participative to delegative mainly due to joint decision making by virtue of the lack

of experience. All the inexperienced project managers viewed this as a learning field. The reason for

this is that in a participative structure there is joint decision making, hence the Manager bears some of

the responsibility with regards to decision. The manager must mentor is such a way that when decision

is reached, the project team member must view it as though he/she has reached that decision by

himself/herself. Furthermore, this will boost the confidence of the inexperienced project manager.

Respondents that chose the delegative management style were 30%. People that responded in manner

are specialists in their fields, e.g. software programming. Their work forms part of the final product but

83

is dependent on others' outputs. As the quoted example, software programming is a specialised field, it

is highly unlikely that a project manager will have the knowledge to perform such work activities. This

is the advantage of the organisational matrix, specialised skills are sourced from other departments.

Respondents choosing a participative to delegative style were 56% this mainly due to inexperience. It is

assumed that with practice this will develop to delegative management style.

84

402 Survey Resulits — Experienced Proiect Mangers

The questionnaire is given at the end of Appendix A.

4.2.1 Phase 1 Conceptual Design

The break down of tasks for Phase I as shown in 2.8 was presented to experienced project managers to

solicit their opinions. The responses are represented in Table 4.8.

Table 4.8: Responses to Phase 1

Phase 1

Strongly

Agree Agree Indifferent Disagree

Strongly

Disagree

Person 1 *

Person 2 *

Person 3 *

Person 4 *

Person 5 *

Person 6 *

Person 7 *

Person 8 *

Person 9

Person 10 *

The percentage of respondents in agreement with Phase 1 is 100% (tally of strongly agree and agree).

85

Person 6 commented that having an agreed scope of work is one of the most important points in this

phase. Also, as stated by Person 6 and 8, resourcing from the client is important in that there is someone

on the project team to make decisions on behalf on the client as quickly as possible with the knowledge

of what is happening on the project at that time. This is particularly important for customer satisfaction

and hence will make the Assessment Phase easier.

Person 9 raised an important concern of highlighting legal issues and/or requirements, e.g. compliance to

air pollution limits. If this is not done a whole project can be aborted or raise project costs to

unattractive returns. The process of ascertaining legal compliance is achieved by conducting an

environmental impact assessment, this is shown in Appendix B.

86

4.2.2 Phase 2 Detailed Design

The break down tasks of Phase 2 was presented to experienced project managers, this as shown in 2.8.

The results are shown in Table 4.9.

Table 4.9: Responses to Phase 2

Phase 2

Strongly

Agree Agree Indifferent Disagree

Strongly

Disagree

Person 1 *

Person 2 *

Person 3

Person 4 *

Person 5 *

Person 6

Person 7 *

Person 8 *

Person 9 *

Person 10 *

As can be seen from Table 4.9 there is 100% agreement to Phase 2.

Person 1 commented that the project manager must train/mentor future project managers, hence this is

further extrapolated that it is vital that inexperienced project managers form part of the project team.

Persons 4 and 5 commented that a scope change register is maintained to record any changes. The client

must approve any additional expenses.

87

Person 8 stated some managers might not support the project and therefore will not make resources

available for the project. This does make the execution of the project extremely difficult, therefore it is

imperative to have signed commitment of resources for the project.

88

4.2.3 Phase 3 Production Phase

Phase 3 as explained in 2.8 was presented to experienced project managers to solicit their opinions. The

results are depicted in Table 4.10.

Table 4.10: Responses to Phase 3 TECHNIKON WITVvA IEHSRAND

LIBRARY

Phase 3

Strongly

Agree Agree Indifferent Disagree

Strongly

Disagree

Person 1 *

Person 2 *

Person 3 *

Person 4 *

Person 5 *

Person 6 *

Person 7 *

Person 8 *

Person 9 *

Person 10 *

As can be seen from Table 4.10 there is 100% agreement to aspects of Phase 3.

Person 1 and 9 commented that punch listing should be included in this phase. Punch listing is an

activity whereby the quality of work is inspected by the client and defects recorded. These defects have

to be remedied before the divestment phase of the project. An e.g. of a punch list item: leaking roof or

doors not shutting properly. Defects can be minor or major, this highly dependent on the client's

expectation. The punch listing activity will be included in Phase 3.

89

Person 8 and 10 highlighted the importance of the CPM method, one needs to be realistic in time

allocations for the different tasks.

4.2.4 Phase 4 Operational

Phase 4 as outlined in 2.8 was presented to experienced project managers in order to solicit their

opinions about the tasks that make up this phase. The results are depicted in Table 4.11.

Table 4.11: Responses to Phase 4

Phase 4

Strongly

Agree Agree Indifferent Disagree

Strongly

Disagree

Person 1 *

Person 2 *

Person 3

Person 4 *

Person 5 *

Person 6 *

Person 7 *

Person 8 *

Person 9 *

Person 10 *

As can be seen from Table 4.11 there is 100% agreement to Phase 4.

Person 6's comment best outlines the importance of this phase "this is usually an aspect that is not

90

handled that well, but can carry a lot of negative emotions and feedback if not properly done."

Person 8 suggested that takeover should take place once the project is commercially viable, i.e. client

reaps financial benefit. This does make sense but removes a lot responsibility from the service provider,

hence not all items are completed and leads to customer dissatisfaction.

4.2.5 Phase 5 Divestment

Phase 5 as outlined in 2.8 was presented to experienced project managers to solicit their opinions about

the tasks in this phase. The results are shown in Table 4.12.

Table 4.12: Responses to Phase 5

Phase 5

Strongly

Agree Agree Indifferent Disagree

Strongly

Disagree

Person 1 *

Person 2 *

Person 3 *

Person 4 *

Person 5 *

Person 6 *

Person 7 *

Person 8 *

Person 9 *

Person 10 *

As can be seen from Table 4.12 there is 90% agreement with Phase 5.

91

Person 6 commented that care should be taken when the project team is broken up as people may have

formed strong working relations. The matrix organisation ensures that people always have a home to go

to.

Person 7 justified his indifferent opinion by stating, "divestment is valid and suitable for in house project

department." This is not true, as the service provider cannot be expected to baby-sit the project beyond

the end point, for this reason it shouldn't have been a project in first place. Divestment is necessary for

the client to take ownership of the project.

92

4.2.6 Phase 6 Assessment

Phase 6 as outlined in 2.8 was presented to experienced project managers to solicit their opinions with

regards to the tasks in this phase. The results are shown in Table 4.13.

Table 4.13: Responses to Phase 6

Phase 6

Strongly

Agree Agree Indifferent Disagree

Strongly

Disagree

Person I *

Person 2 *

Person 3 *

Person 4 *

Person 5 *

Person 6 *

Person 7 *

Person 8 *

Person 9

Person 10 *

As can be seen from Table 4.13 there is 100% agreement with Phase 6.

Persons 1, 5 and 8 commented that lessons learnt not shared organisationally. This is a major

disadvantage, as the company will as pay for the same mistakes rather than learn from them. Also, there

is little time spent between projects, as one is being terminated the next project is beginning.

93

Person 10 raised an interesting point: could the project be designed better. This would be extremely

valuable if the project were to be repeated.

4.2.7 Planning & Controlling

In this question people were asked what was their opinion about the points mentioned in 2.11 under the

heading of Planning & Controlling. Planning & Controlling were surveyed separately and results shown

in Table 4.14 and Table 4.15 respectively.

Table 4.14: Responses to Planning

Planning

Strongly

Agree Agree Indifferent Disagree

Strongly

Disagree

Person 1 *

Person 2 *

Person 3 *

Person 4 *

Person 5 *

Person 6 *

Person 7 *

Person 8 *

Person 9 *

Person 10 *

As can be seen from Table 4.14 there is 90% agreement with regard to the steps outlined in Planning.

94

Person 5 commented that the project manager should get signed commitment for personnel for duration

of project, i.e. team members priorities must not change during the project, a valid point indeed. This is

negotiated in Phase 2, 4.2.2.

Person 7 stated that the scope should change from being "live" to frozen at some point during the

project's life and late changes are often done at very high cost. If one has scoped properly and the scope

is used a point of reference for changes, hence the referral of being "live", the client signs a contracted

scope. This is regarded as "frozen scope".

Person 8 added that allocations should be made for the training of future project managers.

Table 4.15: Responses to Controlling

Controlling

Strongly

Agree Agree Indifferent Disagree

Strongly

Disagree

Person 1

Person 2 *

Person 3 *

Person 4 *

Person 5 *

Person 6 *

Person 7 *

Person 8 *

Person 9 *

Person 10

95

As can be seen from Table 4.15 there is 100% agreement with regards to the steps outlines in the

controlling of a project.

Person 1 commented that feedback should be both formal and informal.

Person 6 commented, "If the steps were executed well it will make a big impact."

Person 10 made an interesting remark, "Finishing on time but above budget is better than late and on

budget — you can never recover lost income by late delivery."

4.2.8 Management Style

The suggested management style of Hersey & Blanchard M4/S4 relationship was presented. In this

management style the work is delegated thereby transferring decision-making power to the subordinate.

Also, it assumed that followers are willing and able to execute the delegated tasks. In addition, the

manager should be able to motivate personnel via McGregor's Theory X & Y and Maslow's Theory of

Needs. The experienced project manager's were asked their sentiments about this. The results are

shown in Table 4.16.

96

Table 4.16: Responses to Management Style

ManagementAgree

Strongly

Agree Indifferent Disagree

Strongly

Disagree

Style

Person 1

Person 2 *

Person 3 *

Person 4 *

Person 5 *

Person 6 *

Person 7 *

Person 8 *

Person 9 *

Person 10

As can be seen from Table 4.16 there is 80% support for the suggested management style. The

remaining 20% was made as 10% indifference and 10% disagreement.

The persons that agreed stated that this is an ideal management style. In reality one often has to manage

a diverse group of people with different levels of experience, hence may also require individual

attention. This takes up time, instead of directing the project manager is now executing, this is not

supposed to his function unless this is viewed as part of training.

Person 5 commented that some project managers are ignorant of this management style and both

managers and team members should be educated in this regard.

Person 3 took an indifferent stance, he stated that the beginning of project is S2 (selling) and S3

97

(participating). This is true when negotiating with the client to win the contract, but not so managing the

project team. Therefore, this statement is disregarded on the basis that the question was not fully

understood.

Person 7 chose to disagree with the suggested management style. His feeling was that team members

tend to focus on the tasks/items rather than overall progress, the project manager should constantly drive

the critical path items to deliver the project on time. This is what is intended in the suggested

management style, again, this is a case where the question as not properly understood.

98

Chapter 5 (Co>rnc s mii & Recommendations

501 Concilusiton of Surveys

The topic for this dissertation was a Contemporary Systems Approach to Project Management. Very

often inexperienced employees are dropped into the deep end where they have to manage a project. At

best, some have had an introductory class during the course of their studies.

Project management involves different phases. Each phase requires planning, controlling, directing and

organising. The goal of the project must be delivered within three crucial parameters:

Within time

Within resources (people and finances)

Within technology

At times, time is no friend, as friends between the project and time, they're out of time..In this case, it is

better to deliver the project on time and over budget rather than late and within budget. Lost time cannot

be made up, but money can. Hence, it is imperative in being goal focussed, and manage by objective.

After all, projects will always have an objective.

Any new project endeavoured will bring about change this may be in terms of management style,

technology and methods. A project therefore:

Involves new and unknown tasks

Leads to change in people's daily work or living conditions

Requires the right people at the right time, but staff of different backgrounds who are not

used to working together

Is subject to a strict deadline

99

A project implements change, which is difficult in itself. The change is occurring in a stated period of

time. It is an unknown task for many of those involved. Resources will be that in many cases are not

available or belong to other managers, organisationally speaking (Anderson et al, 1999:28-29).

Therefore, the project requires the establishment of an organisational structure as explained in 2.7.2, and

that the work in this structure be managed with the assistance of specific methods and tools. For this

purpose, it recommended to utilise the Contemporary Systems Approach to Project Management as a

tool for the effective execution of a project.

The special conditions associated with project management require special knowledge and methods.

Anderson et al (1999:29) include the following subsidiary tasks in project management:

Planning

Organising

Controlling

Directing (Kerzner, 1998:5)

Each of these management functions are integrated into the life cycle of project management. This is

demonstrated in the developed model of this study: Contemporary System Approach to Project

Management (2.8).

100

The following outcomes from Chapter 4 will be discussed with regard to:

The need for training

Acceptance of the Contemporary Systems Approach to Project Management

Risks of using the Contemporary Systems Approach to Project Management

Planning and controlling

Management style for a project

The need for training

Most of the inexperienced project managers could not mention the four management activities and the

different phases involved in project management, there is a need to train/educate these people in

managing a project. Also, there is great support for utilising the Contemporary Systems Approach to

Project Management, this will require further training in respect of applying the Model (2.8).

Each project must be staffed such that an inexperienced project manager is given the opportunity to gain

hands on experience. The project manager should take on the role as mentor. If possible, transfer some

decision making power to the prodigy, this will boost his/her confidence and reinforce the team concept.

Acceptance of the Contemporary Systems Approach to Project Management

Both, experienced and inexperienced project unanimously approved the Contemporary Systems

Approach to Project Management model. The philosophy being that there will be a manual at one's

disposal as a reference.

The model can be incorporated in company procedures hence become an official protocol. This ensures

that there is sameness and continuity in projects. Project tracking then becomes easier and will have

similar document controls.

The premise of the Model shown in 2.9 is that the quality of work is not compromised. This provides a

101

logical sequence of events, which is relatively easy to understand.

o Risks of using the Contemporary Systems Approach to Project Management

The risks are considered as being the down side of implementing the Contemporary Systems Approach

to Project Management.

People are naturally resistant to change, hence it will take some effort in winning their support. Prior to

doing so, the Model has to be proven practically. Theoretically, both inexperienced and experienced

project managers have approved of the Model.

The Model assumes that the right people are available at the right time, but in reality this may not be the

case. People may be tied up with other projects, on vacation or not released to the project by relevant

managers. This poses a serious problem as the constraints of time and money need to be met, this if

technology is proven or approved by the customer. For this reason, it may necessary to outsource certain

tasks, e.g. civil engineer to oversee the erection of a building).

Some people may not fancy endeavouring all the steps in the postulated Model (2.9), as this may be time

consuming. Omitting certain steps is acceptable given out of normal circumstances, e.g. fast track

project.

102

0 Planning and controlling

One needs to plan and control a project so that the objective is met within the stated constraints of time,

money and resources. In planning milestones must be set so that actual progress can be compared to

forecasts. This will immediately indicate whether the project can be delivered on time. Lack of

planning and control leads to overspending and under/over utilisation of resources, which in turn makes

an unhappy customer and low profit margins.

One has to plan such that the project is delivered at the right time at the right price. Once the plan has

been established, one initiates activities and controls/monitors them keeping the time target in mind.

In order to meet customer expectation it is vital that the customer makes someone available to the

project. This person will be the liaison between the project team and the customer. He/she shall be

charged with the responsibility of acting on behalf of the client.

After all as one respondent stated, "If you not planning you're planning to fail".

0 Management style for a project

Theoretically the preferred management style is the S4/M4 task and relationship based upon the Model

of Situational Leadership by Hersey & Blanchard. The inexperienced project managers preferred a

participative to delegative style due to the lack of experience — joint decision making. Therefore, it is

vital that inexperienced project manager be part of the project team for development purposes.

The project manager's duty is to manage and complete the project while also mentoring inexperienced

project managers.

Incapable people cannot staff the project as this would delay the project and cost substantially more.

Over/under staffing the project will also have adverse effects, e.g. costs.

103

The company has to use the organisational matrix to full effect. This ensures that competent people

make the project team. The major problem in this structure is the availability of staff.

There will be times when the project manager will adopt telling, selling, participating management

styles, this depending of the nature of work on hand. For the technical and professional tasks, this must

be delegated to able people. The project manager must not become involved in knit picking the design,

as this will cause compromise the goal. After all, that is why one delegates. Empower people to make

decisions in the best interest of the project, if in doubt then consulting should take place.

5.2 Recommendations

The environmental impact assessment should be included in Phase 1 of the proposed model.

This was recommended by the electrical engineering manager who is responsible for the

electrical installations on projects. The reason including the environmental impact study in

Phase 1 is that non-compliance to environmental policy could lead to the abandoning or

increasing the cost of the project. If forgotten, the project could be completed but may be

regarded as an illegal installation. In doing so, time, effort and money will be saved.

The model must be proven practically, then it can become part of the company's operating

procedures.

The model illustrated should be used to train inexperienced project managers.

The model should be used for future projects as this will make document controls the same.

104

11► ibililography

African Products (Pty) Ltd, New Business Development Procedures

Anderson ES, Grude KV, Haug T, Goal Directed Project Management, Second Edition,

1999,Kogan Page Limited, Great Britain

Blanchard FL, Engineering Project Development, 1990, Marcel Dekker, USA

Burk R, Project Management: Planning and Control, 1995, Second Edition

Emory CW, Cooper DR, Business Research Methods, 4 th Edition, 1994Irwin, Boston

Hersey & Blanchard, Organizational Behaviour Utilising Human Resource, 1982, 4 th Edition,

Prentice Hall, USA

Kerzner H, Project Management: A systems approach to planning, scheduling and controlling,

1998, Sixth Edition, John Wiley & Sons, New York, USA

Kliem RL, Ludin IS, Robertson KL, Project Management Methodology, 1997, Marcel Dekker,

New York, USA

Lewis JP, Fundamentals of Project Management, 1995, AMACON, New York

Maylor H, Project Management, 1996, Great Britain, Pitman Publishing

Melville S, Goddard W, Research Methodology, 1996, Creda Press, Cape Town

Robbins PS, Organisational Behaviour, 8 th Edition, 1998, Prentice-Hall, Inc., New Jersey

105

Ruskin AM & Estes WE, What Every Engineer Should Know About Project Management, 1994,

Marcel Dekker Inc., USA

Saunders M, Lewis P, Thornhill A, Research Methods for Business Students, 1997, Pitman

Publishing, London

Shtub et al, Project Management, Engineering, Technology and Implementation, 1994, Prentince

Hall, USA

Snowdon M, Management of Engineering Projects, 1977, Great Britain, Butterworth and

Company

South African Bureau of Standards, IS09000, 1994,South Africa

Stevenson WJ, Production Operations Management, 1999, Sixth Edition

Stuckenbruck LC, The Implementation of Project Management, 1996, Addison-Wesley

Publishing Company, Massachusetts

Turner RJ, The Handbook of Project Based Management, 1993, McGrawhill, UK

Van Der Waldt G & Knipe A, Project Management, 1998, International Thomson Publishing,

South Africa

106

Westney RE, Managing the Engineering and Construction of Small Projects, 1985, Marcel

Dekker, USA

Wideman Max R., A Framework for Project and Program Management Integration, 1991,

Project Management Institute, USA

Whittaker R, Project Management the Process Industries, 1995, John Wiley & Sons, New York,

USA

Wysocki KW, Beck R Jr., Crane DB, Effective Project Management, 1995, John Wiley & Sons,

Inc., USA

107

psr ___Klices

Appendix A

'Inexperienced project manager questionnaire

Project Management Questionnaire

This is survey to determine whether the opinion of inexperienced project managers in terms the

management functions to be carried out.

Title: Date

Questions for inexperienced Project Managers

1) In your opinion what are the most important management functions involved in project

management?

108

Can a project be broken down into phases, if so please state?

If a model was made available that outlined the series of events in the phases of a project,

would this make project management easier? Also, state reason for using such a model.

Model attached after question 7.

If any, what do think the pitfalls would be if such a model were utilized?

109

How and why is planning and controlling important?

,

No matter how good the controlling deviations will occur. How should one deal with this?

Being part of project team, what type of management style would you prefer? Also, state

why.

Proposed Project Management Modell

Phase 1 Conceptual Design

Determine goals

Conduct a feasibility

Establish system concepts to provide initial strategic guidance to overcome existing or

potential difficulties

Conduct technology search, if technology does not exist in-house, develop research and

development program or bring in consultants

Examine alternative ways of achieving goals

Determine environmental and economic feasibility

Provide answers for:

What will the system cost, within 25% accuracy?

When will the system be ready?

What will the system do?

How will the system be integrated into the existing systems?

What resources are required?

Generate scope

Select initial system design that will best satisfy the project goals

Liaise with the customer to check if the work requirement or project goal is properly

understood

Go/no decision

110

111

Phase 2 Detailed Design

Select the appropriate project manager

Commitment from senior management

Refine the elements under the conceptual phase

Select the "best" system for achieving the goal

Reach agreement on system design and then generate the following:

Freeze project scope

Project planning

Project Budget

Project Schedule

Determine the extra resources required and for what duration

Identify areas of risk and uncertainty and outline plans for further exploration of these areas

Conduct a HAZOP (hazardous operation study), operation to be intrinsically safe in all

respects/disciplines of engineering and operations

Start documentation process such as policies, procedures, job descriptions and etc.

Can the system still be afforded, i.e. after final costing is it economically viable (payback)?

Detailed contingency plans for areas of risk: Can enter into technological agreements to share

or brokerage of information

Develop procedures for work authorization, performance reporting

Develop training manuals

Phase 3 Production

Updating of detailed plans conceived and defined during the preceding phases

Maintain top management support and flow of communications within and among the

participating organizations

Verification of system production specifications

112

Update change of scope register

Beginning of production, construction and installation

Monitor actual progress and compare to baseline plans, i.e. critical path and network

diagrams and WBS

Final preparation and dissemination of policy and procedural documents

Performance of final testing to determine adequacy of the system to do the things it is

intended to do, if so, hand over document to be signed, this if process can generate some

profit, but not target profit

Training of operators

Development of technical manuals and affiliated documentation describing how the system

intended to work

Develop systems to support the system during its operational phase

Phase 4 Operational

I. Acceptance of final results by customer

Check competency of operators

Evaluation of technical, social and economic sufficiency of the project to meet actual

operational conditions

Use of the system results by the intended user or customer

Start to prepare handover documentation

Actual integration of the project's product or service into existing organizational systems

Provide feedback to organizational planners concerned with developing new projects and

systems

Evaluation of the adequacy of supporting systems

113

Phase 5 Divestment

Develop plans for transferring responsibility to supporting organizations, i.e. handover

Divestment or transfer of resources to other systems

Phase 6 Assessment

Development of "lessons learnt from system" for inclusion in quantitative-qualitative database to

include:

Assessment of image by the customer

Major problems encountered and their solutions

Technological advances

New or improved management techniques

Recommendations for future research and development

Recommendations for management of future programs, including interfaces with associate

contractors

Other major lessons learned during the course of the system

Planning & Control

Through each of the steps mentioned in the phases of project management, planning and control

must be practiced to a high degree.

The steps that must be followed during planning are as follows:

1. Understand exactly what is required by the client, sign a contracted scope of work, this to be

used as a "live" document for the service rendered. The scope should include the objective

and termination dates.

114

Establish a basis of a planning network (CPM), identifying key milestones. Plan to do detail

planning for each phase only when necessary. Conduct a hazardous operation and

environmental impact studies.

Assess time and resource requirements and provide slack time (i.e. overruns).

Confirm staff allocations via organizational matrix.

Make allocation for staff training.

Project authority should be clearly defined.

The steps to be followed during the controlling are as follows:

Establish communication systems, both within the project and senior management.

Hold fortnightly meetings to monitor progress with the client. Informal communication

channels should be established.

Use Deming's PDAC to project plan in check.

Monitor quality in all regards, workmanship, service rendered and received.

Maintain a scope change register.

Track actual costs to forecasts.

Record reasons for slippage, inform management/client and move termination date

accordingly.

Does the project management procedure comply with IS014002.

Management Style

The management style to be adopted is the Hersey & Blanchard S4/M4 relationship whereby work is

delegated and there are low management relationships. It is assumed that team members are willing

and able. The manager should also have the ability to motivate (McGregor Theory X &Y and

Maslow Theory of Needs) the project.

115

Experienced project manager questionnaire

Proieet Management Questionnaire

Questions for experienced Project Managers

This is survey to determine whether the project management model presented herewith is of

validation. Various authors' works were consulted to develop the model. The model concentrates

on the management functions in project management.

The model presented is subdivided into six phases. Each phase is further broken into a series of

activities. Each phase has five possibilities in terms of answers. Please tick the appropriate box and

make recommendations where applicable.

Also, an ideal management style is postulated, this being the Hersey&Blanchard S4/M4 relationship

where subordinates are thought-to be willing and able. The steps of planning and controlling are

also surveyed as this is viewed as a vital part f any project.

Thank you kindly.

Title- Date-

116

Phases of Project Management

Phase 1 Conceptual design

Determine goals

Conduct a feasibility

Establish system concepts to provide initial strategic guidance to overcome existing or

potential difficulties

Conduct technology search, if technology does not exist in-house, develop research and

development program or bring in consultants

Examine alternative ways of achieving goals

Determine environmental and economic feasibility

Provide answers for:

What will the system cost, within 25% accuracy?

When will the system be ready?

What will the system do?

How will the system be integrated into the existing systems?

What resources are required?

Generate scope

Select initial system design that will best satisfy the project goals

Liaise with the customer to check if the work requirement or project goal is properly

understood

Go/no decision

117

Strongly agree Agree Indifferent Disagree Strongly

disagree

Recommendations

Phase 2 detailed design

Select the appropriate project manager

Commitment from senior management

Refine the elements under the conceptual phase

Select the "best" system for achieving the goal

Reach agreement on system design and then generate the following:

Freeze project scope

Project planning

Project Budget

Project Schedule

6. Determine the extra resources required and for what duration

118

Identify areas of risk and uncertainty and outline plans for further exploration of these areas

Conduct a HAZOP (hazardous operation study), operation to be intrinsically safe in all

respects/disciplines of engineering and operations

Start documentation process such as policies, procedures, job descriptions and etc.

Can the system still be afforded, i.e. after final costing is it economically viable (payback)?

Detailed contingency plans for areas of risk: Can enter into technological agreements to share

or brokerage of information

Develop procedures for work authorization, performance reporting

Develop training manuals

Strongly agree Agree Indifferent Disagree Strongly

disagree

Recommendations

Phase 3 production phase

Updating of detailed plans conceived and defined during the preceding phases

Maintain top management support and flow of communications within and among the

participating organizations

Verification of system production specifications

Update change of scope register

119

Beginning of production, construction and installation

Monitor actual progress and compare to baseline plans, i.e. critical path and network

diagrams and WBS

Final preparation and dissemination of policy and procedural documents

Performance of final testing to determine adequacy of the system to do the things it is

intended to do, if so, hand over document to be signed, this if process can generate some

profit, but not target profit

Training of operators

Development of technical manuals and affiliated documentation describing how the system

intended to work

Develop systems to support the system during its operational phase

Strongly agree Agree Indifferent Disagree Strongly

disagree

Recommendations

120

Phase 4 Operational

Acceptance of final results by customer

Check competency of operators

Evaluation of technical, social and economic sufficiency of the project to meet actual

operational conditions

Use of the system results by the intended user or customer

Start to prepare handover documentation

Actual integration of the project's product or service into existing organizational systems

Provide feedback to organizational planners concerned with developing new projects and

systems

Evaluation of the adequacy of supporting systems

Strongly agree Agree Indifferent Disagree Strongly

disagree

Recommendations

121

Phase 5 Divestment

Develop plans for transferring responsibility to supporting organizations, i.e. handover

Divestment or transfer of resources to other systems

Strongly agree Agree )indifferent Disagree Strongly

disagree

Recommendations

Phase 6 Assessment

Development of "lessons learnt from system" for inclusion in quantitative-qualitative database to

include:

Assessment of image by the customer

Major problems encountered and their solutions

Technological advances

New or improved management techniques

Recommendations for future research and development

Recommendations for management of future programs, including interfaces with associate

122

contractors

o Other major lessons learned during the course of the system

Strongly agree Agree Indifferent Disagree Strongly

disagree

Recommendations

Planning & Control

Through each of the steps mentioned in the phases of project management, planning and control

must be practiced to a high degree.

The steps that must be followed during planning are as follows:

I. Understand exactly what is required by the client, sign a contracted scope of work, this to be

used as a "live" document for the service rendered. The scope should include the objective

and termination dates.

2. Establish a basis of a planning network (CPM), identifying key milestones. Plan to do detail

planning for each phase only when necessary. Conduct a hazardous operation and

environmental impact studies.

123

Assess time and resource requirements and provide slack time (i.e. overruns).

Confirm staff allocations via organizational matrix.

Make allocation for staff training.

Project authority should be clearly defined.

Strongly agree Agree Indifferent Disagree Strongly

disagree

Recommendations

124

The steps to be followed during the controlling are as follows:

I. Establish communication systems, both within the project and senior management.

Hold fortnightly meetings to monitor progress with the client. Informal communication

channels should be established.

Use Deming's PDAC to project plan in check.

Monitor quality in all regards, workmanship, service rendered and received.

Maintain a scope change register.

Track actual costs to forecasts.

Record reasons for slippage, inform management/client and move termination date

accordingly.

Strongly agree Agree ]Indifferent Disagree Strongly

disagree

Recommendations

125

Management Style

The management style to be adopted is the Hersey & Blanchard S4/M4 relationship whereby work is

delegated and there are low management relationships. It is assumed that team members are willing

and able. The manager should also have the ability to motivate (McGregor Theory X &Y and

Maslow Theory of Needs) the project.

Strongly agree Agree Indifferent Disagree Strongly

disagree

Recommendations

126

Appendix B

PURPOSE:

The environmental impact assessment is intended to identify the potential influences a proposed process will have on employees, the public and the environment.

It is intended to provide information on:

which plant designs should be implemented and

which contingency plans should be formulated,

in order to reduce the possible negative impact of the development.

SCOPE:

All major projects e.g. New Greenfields Plant All capacity expansion projects All process improvement/replacement projects All minor projects that could have an environmental effect.

For major projects, the EIA should establish currently known potential hazards or environmental impacts upfront. This will allow these aspects to be addressed in the detailed design.

After completion of the detailed engineering, the EIA study should be reviewed to finalize the assessment.

Complete the following ENVIRONMENTAL IMPACT ASSESSMENT where applicable:

Note:

All minor projects that could have an environmental effect, only complete items marked (*).

127 ENVIRONMENTAL IMPACT ASSESSMENT

1.1 PROJECT (*)

Project Name & Number:

1.2 Proposed Project commencement:

1.3 Proposed Project completion:

1.4 EIA completion:

1.5 Final EIA review:

(Prior to scope being frozen)

2.1

THE PROJECT & PROCESS (*)

Project Description:

2.2 Process Description:

2.3 Alternatives considered:

2.4 Previous environmental incidents known to have occurred with the

same/similar processes:

3.1 MATERIAL HAZARD DATA

(List all process materials — excluding maintenance materials — to be

handled on site)

Materials list

Raw Materials:

128

Finished Products:

Solid Wastes:

3 . 2 Effluents

(Quantity & Composition of Effluent)

3 . 3 Hazard Sheets

(Provide details for all materials as per Chemical Hazard data

sheets — Table 1)

4.

4.1

4.1.1

ENVIRONMENTAL ASPECTS

(*)

Air pollution

(See tables 2 & 3 for standards/guidelines)

Is the proposed process classified as a scheduled process?

If so, has approval been obtained? Provide details of approval.

4.1.2 Block flow diagram of air pollutants (identify quantity and composition of

streams, e.g. boiler stack, drier discharges, cooling tower vapours, see also

4.1.3.

(*)

4.1.3 Description of processes: (for example)

SO2 Generation:

Steam Generation: (S02/smoke)

129

Feed Drying: (Odour)

Product Drying/Conveying: (Dust)

Effluent Treatment:

4.1.4 Equipment to be used to purify air streams? (1

4.1.5 Stack Heights: (where applicable)

4.1.6 Cooling Towers:

4.1.7 Sensitivity of surrounding vegetation to air pollutants:

4.1.8 Are background measurements of expected pollutants available?

4.1.9 Proposed monitoring programme:

4.1.10 Is any open incineration or burning contemplated?

4.1.11 Is any solid or liquid effluent generated from air purification equipment? (1

4.2

4.2.1

Water pollution

( )

(See tables 4 & 5 for standards/guidelines)

Effluent block flow diagram:

130

4.2.2 Has an application for water/effluent permit been processed?

(Provide details of permit approval)

4.2.3 Detailed drainage paths from site and catchments areas:

4.2.4 Describe receiving body for effluent discharges:

4.2.5 Provide data on depth, quality and usage of underground water.

4.2.6 Quality of existing streams entering/leaving the site:

4.2.7 What control measures will be utilised on effluent arising from the process? (*)

4.2.8 What effluent treatment system(s) will be utilised? (*)

4.2.9 Where/how will domestic sewage be treated?

4.2.10 What system is proposed to monitor potential off-site pollution? •

131

4 . 3

4.3.1

Solid Waste Disposal

(1

Solid wastes should preferably be disposed of on an off-site dump, managed

by an outside concern. Proper contracts to cover liabilities from dump

pollution should be drawn up.

Describe site where solid wastes are to be dumped:

4.3.2 Will waste give rise to leachate?

4.3.3 Will leachate meet standards?

4.4

4.4.1

Noise

(*)

(See attached Table 6 for guidelines)

Description of existing background noise:

4.4.2 Has a pre-project boundary noise survey been carried out?

4.4.3 Identify critical noise receptors near site:

4.4.4 Describe anticipated noise sources: (1

4.4.5 Steps proposed to eliminate/reduce noise: (*)

4.4.6 Noise associated with plant shut down:

132

4.4.7 What system will be used to monitor future noise level?

4.5 Aesthetics

4.5.1 Will the development of the site create visual/aesthetic disruption?

4.5.2 List sizes of visually prominent equipment/dumps:

4.5.3 List sources of light or glare:

4.5.4 Plant/Structure appearance from site boundaries:

5.

5.1 TRANSPORTATION AND SITE DATA (Only applicable to MAJOR

Projects)

Identify access routes to the proposed site:

5.2 Is dust on roadways a potential problem?

5.3 Define quantities of materials transported to and from site:

133

Rail:

Road:

5.4 Effect on existing road traffic:

5.5 Describe proposed site:

Location:

Size:

5.6 Provide distance, direction to nearest residential/public area:

5.7 Describe surrounding vegetative cover:

5.8 Describe surrounding topography and soil:

5.9 Describe existing pollution sources.

(Air; water; noise; dust)

5.10 Provide available climatologically data: (Maximum; Minimum; Average)

0 Temperature

0 Humidity

0 Rainfall

0 Wind direction; speed

0 Sunshine

0 Evaporation

0 Frequency of inversion

6. WATER SUPPLY (Only applicable to MAJOR Projects) 6.1 Where will process water be sourced from? _

134

6.2 Where will domestic/ablution water be sourced from?

6.3 Will any of these water sources require additional treatment before use?

6.4 Indicate daily and annual average/maximum usage levels.

6.5 Has a water permit been approved?

(Provide details)

CONSULTATION WITH EXTERNAL AUTHORITIES 7

.1 List external authorities that need to provide approvals.

(Contact person(s) needs to be identified)

7.2 List consent levels that have to be complied with to obtain approval.

(Also provide expected operating levels)

EMERGENCY FACILITIES 8.1 Describe any emergency procedures that will be in effect on the site.

135

8.2

List facilities on site to cater for emergencies.

9. CONSTRUCTION PHASE 9.1 What steps will be taken to minimum/reduce interference/impact of

construction activities on:

Current site activities:

Neighbouring sites:

9 . 2 Materials 9.2

.1 Are specific areas available for receiving/storing construction

materials? (building materials; plant equipment; piping; cabling; etc)

9 . 2 . 2 Is an area available for accumulation (if required) of rubble,

excavation materials & wastage?

9.2.3 What is the proposed frequency of site cleaning?

9.3 Pollution

9.3.1 Are adequate ablution facilities available on site for construction

workforce?

136

9.3.2 What steps will be taken to limit/reduce noise arising from

construction activities?

9.4

9 . 4 . 1

Aesthetics

Identify and list sizes of visually prominent equipment/dumps during

construction.

9.4.2 Is any sensitive ecological/vegetative area being affected by the

construction (project)? (Have the necessary discussions been

held/acceptance been obtained?)

9.4.3 What steps will be taken to reinstate environmental impacts of

construction? (e.g. excavations; damage to vegetation)

9.5

9 . 5 . 1

Safety/Housekeeping

Have all contractors on site attended Afprod's Safety &

Environmental Induction Programme?

9 . 5 . 2 Have all contractors accepted responsibility for daily cleaning of

site?