The Stability Graph Method for Qpen-Stope Design (1)

  • Upload
    lou721

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

  • 8/17/2019 The Stability Graph Method for Qpen-Stope Design (1)

    1/8

    C H A P T E R 5 9

    The Stability Graph Method for Qpen-Stope Design

    Yves Po tvi rt * and John H ad j i geo rg io i s t

    60* 1 INTRODUCTION

    In the late 1970s to early 1980s, the underground metal-mining

    industry shifted its extraction strategy from highly selective

    ent ry methods, such as cut-and-fill, to non -entry methods

    such as open stoping. A review of Canadian practice has shown

    that 90% of the total production of underground metal mines,

    based on reported tonnage, rely on open-stope mining methods

    (Poulin et al. 1995). The popularity of open-stope operations can

    be attributed to the higher productions levels achieved by

    employing larger excavations and using mechanised equipment.

    Considering the high cost of developing each stope, there is

    a significant incentive to produce a smaller number of large open

    stopes. The consequences, however, of exceeding the maximum

    critical stable dimensions of a stope can be disastrous. Instability

    around open stopes may require large remedial costs for ground

    rehabilitation, production delays, mining equipment loss, ore

    reserves loss, and, at the extreme, injuries or fatalities to mine

    workers.

    Pakalnis (1986) reports that in a survey of 15 Canadian

    mines, almost half (47%) of the open-stope mines had more than

    20% dilution with one fifth suffering excessive dilution of over

    35%. Based on field data from 34 Canadian mines, Potvin (1988)

    demonstrated that open-stope design was based on past experi-

    ence of mine operators in similar mining conditions and on trial

    and error. Consequently, it can be argued that the reported high

    dilution rates in the early 1980s could be attributed to the

    absence of comprehensive engineering design tools. It follows

    that there are significant economic gains to be made by

    improving open-stope stability.

    @Q

    d

    2 EXC AVATIO N STABIL ITY

    Evaluating the stability of a non -entry excav ation such as a stope

    can be subjective. Unlike entry excavations in which mine

    workers have access, isolated rock falls in stopes are generally of

    no consequence, providing that they can be handled by mucking

    units. Therefo re, a stope can be considered to be stable if it yields

    low dilution (less than 5%) and if there are no ground-fall-

    related operational problems. It has been argued (Pakalnis,

    Poulin, and Hadjigeorgiou 1995) that there is a unique accept-

    able dilution rate for every mine operation. This is defined as a

    function of ore gra de, costs, grade of dilution material, and metal

    prices. Consequently, provided the operation remains safe and

    economical, it is possible to tolerate a level of dilution and a

    degree of instability for every stope. Open stopes that display

    excessive dilution and/or unmanageable stability problems are

    often referred to as caved. In this context, the term cave d indi-

    cates major stability problems and should not be confused with

    the cave mining interpretation where it refers to orebody failure

    (cavings) after undercutting. This overlap of terminology has,

    from time to time, been the source of confusion amongst people

    not familiar with open-stope mining.

    There are multiple and interrelated factors that potentially

    contribute to the instability of excavations. For convenience, they

    can be divided into two groups: the ones related to the in-situ

    conditions prevailing before mining, and the factors related to

    the disturbance of these cond itions induced by min ing.

    The premining conditions can be characterised by rock-mass

    classification schemes and supplemented with structural geology

    data and an estimation of the in-situ stress field. The major

    factors related to mining are the size, shape, and orientation of

    excavations as well as the ground support used (including back-

    fill). Blast damage and the effect of time in highly convergent

    rock may also affect the stability of excavations.

    S 0 a 3 D E S C R I P T I O N O F T H E S TA B S L I T Y -

    m A P U ¡1 E T O 0 O

    The stability-graph method is an empirical m ethod fo r open-stope

    design (non-entry ex cavations). It aims to account for and quantify

    the major factors influencing the stability of open stopes. A stability

    index for each stope surface is subsequently traced against its

    dimensions. A series of empirically derived guidelines allow for

    predictions on the overall stability of a stope. Since its introduction

    (Mathew s et al. 1981), it has gained wide acceptance and is used

    world wide as a design tool. There are documented case studies of

    the method being used in Africa, Europe, and the United States,

    and extensive databases of case studies in Canada and Au stralia. In

    practice, the stability graph can be employed during three distinct

    mining stages. Its primary use is during the feasibility stage but it

    has also been found useful during individual stope planning.

    Finally, through the use of back analysis, it provides an index of

    stope performance and allows the mine operation to develop reme-

    dial strategies where warranted.

    The method traces its origin to the recognition that tradi-

    tional rock-mass classification and design tools were based on

    tunnelling case studies. A review of some case studies and engi-

    neering judgement resulted in the first version of the method,

    whereby a stability number (N) was traced against the hydraulic

    radius of a stope surface.

    The stability-graph method uses the NGI tunnelling index Q

    (Barton, Lien, and Lunde 1974) as a basis for estimating rock-

    mass quality.

    where:

    Q = NGI tunnelling index with

    RQ D  = rock quality designation

    * Australian Center for Geomechanics, Nedlands, WA, Australia,

    t Laval University, Quebec City, Quebec, Canada.

    5 1 3

  • 8/17/2019 The Stability Graph Method for Qpen-Stope Design (1)

    2/8

    5 1 4

    F o u n d a t i o n s f o r D e s i g n i

    1000

    1 0 1 5

    H y d r a u l i c r a d i o s ( m )

    1 0 1 5

    H y d r a u l i c r a d i u s ( m )

    F IG U R E S O 1 S ta b i l i t y g r a p h , a f t e r M a t h e w s e t a l . (1 9 8 1 )

    F I GU R E 6 0 . 2 S t a b i l i t y g r a p h a f t e r P o t v i n (1 9 9 8 )

    J'

    r

      = joint roughness number

    J

    w

      = joint water reduction number

    J

    n

      = joint set number

    J

    a

      =  joint alteration number

    SR F  = stress reduction factor

    Using S RF equal to 1 is a departure fro m the original system

    (Barton, Lien, and Lunde 1974). This modified tunnelling index,

    Q, is further adjusted to account for stress, rock defect orienta-

    tion, and design-surface orientation factors to arrive at a stability

    number N.  The stability number was plotted against the hydraulic

    radius (surface area/perimeter) of the studied surface of an exca-

    vation (Mathews et al. 1981). Three zones of potentially stable,

    unstable, and caving were proposed with reference to the

    predicted stability of an excavation (see Figure 6 0.1).

    In its early days, a major shortcoming of the method was

    that it was backed by limited field data—26 case studies from

    three mines. Once the database was expand ed to 175 cases from

    34 mines and the stability graph modified (Potvin 1988), the

    method rapidly gained wide acceptance in the Canadian mining

    industry. The transition z one fr om stable to unstable was reduced

    significantly, thus removing some of the subjectivity in using the

    design chart (see Figure 60.2). It should be noted that in the

    Potvin database, the adjustment factors were differen t than those

    proposed by Mathews et al. (1981). This resulted in what is

    commonly referred to as the modified stability-graph method

    using a stab ility index AT.

    N' = Q'xAxBxC

    where:

    AT = stability num ber

    Q ' = mod ified tunnelling quality index (NG I)

    A =  stress factor

    B  = joint orientation factor

    C  = gravity factor

    A Factor

    The A-factor is used to account for the resulting

    induced stress in the investigated stope surface. A series of charts

    that provided preliminary estimates of induced stresses for

    1.0

    0 .8

    0 .6

    42

    i

    0 .4

    W

    0 .2

    0.1

    0

    1

    Gc/Oi

  • 8/17/2019 The Stability Graph Method for Qpen-Stope Design (1)

    3/8

    T h e S t a b i l i t y G r a p h M e t h o d f o r © p e s i -S t o p e D e s i g n

    5 1 5

    1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 0

    R e l a t iv e d i f f e r e n c e i n d i p b e t w e e n

    t h e c r i t i c a l Jo i n t a n d s l o p e s u r f a c e

    F I G U R E 6 0 A

    ( 1 9 8 8 )

    D e t e r m i n a t i o n o f t h e O r i e n t a t i o n F a c t o r , a f t e r P o t v i n

    1 1 l

    30 40 50

    i n c l i n a t i o n o f

     :

    F I GU R E 6 0 . 5 I n f l u e n c e o f g r a v i t y f o r s l a b b i n g a n d g r a v i t y f a ll m o d e s

    o f f a i l u r e

    © 0 = 4 D I S C U S S I O N O F T H E I N P U T F A C T O R S

    As a result of wide dissemination in a number of textbooks

    (Hoek, Kaiser, and Bawden 1995, Hutchinson and Diederichs

    1996) the input factors for the calculation of N' described above

    have now gained broad acceptance from practitioners and

    researchers. The applicability of the input methodology on a

    case-by-case analysis was reviewed and, with the exception of the

    minor modifications to the C factor shown in Figure 60.6, were

    found to be appropriate (Hadjigeorgiou, Leclair, and Potvin

    1995). On the other hand, some authors (Stewart and Forsyth

    1995; Trueman et al. 2000) have indicated their preference for

    the formulation of the input factors as originally proposed

    (Mathew s et al. 1981).

    critical joint > F W

    i 1 1 — n r

    10 20 30 40 50

    I n c l i n a t i o n o f c r i t i c a l j o i n t

    F I G U R E 6 0   I n f l u e n c e o f g r a v i t y f o r s l i d i n g m o d e o f f a i l u r e , a f t e r

    H a d j i g e o r g i o u L e c l a i r a n d P o t v i n ( 1 9 9 5 )

    Several other modifications to the stability graph have been

    proposed during the last decade. The following offers a brief

    historical review. It should be noted that most of these proposals

    have not yet been extensively tested by case studies nor are they

    wide ly employed by practitioners.

    Scoble and Moss (1994) suggested that there was merit in

    adding tw o further adjustment factors, D for blasting and E for

    sublevel interval rating with some tentative factors proposed. A

    fault factor was been deve loped that can be incorporated into the

    stability factor (Suorineni, Tannant, and Kaiser 1999). This fault

    factor accounts for the angles between fault and stope surface

    and the position where the fault intersects the stope surface. The

    fault factor was derived based on modelling and demonstrated

    that it could be critical for a series of documented case studies in

    Canada and Africa. At the G olden Giant Mine in Ontario, Canada,

    it was shown that under high-stress environments the introduc-

    tion of a stress-damage factor merited attention (Sprott et al.

    1999). Based on 3-D numerical modelling, they used the extra

    stress deviato r, the uniaxial resistance of the rock, and the

    hydraulic radius to define a stress-damage factor. It has been

    argued that the stability predictions of the stability-graph method

    may prove inaccurate due to the influence of rock-mass degrada-

    tion and relaxation (Kaiser et al. 1997). It was recommend ed that

    stope sequencing be used as a tool to minimise stress-induced

    rock-mass degradation and to minimise stress relaxation. In their

    work, they defined rock-mass relaxation as stress reduction

    parallel to the excavation wall—not to stress reductions in the

    radial or a reduction in confinement. Rock-mass degradation was

    quan tified as loss of rock-mass strength.

    S 0

    o

    S H Y D R A U L I C R A D I U S

    Th e term hydraulic radius has been used in the past to charac-

    terise the size and shape of stope surfaces (Laubscher 1977). This

    is the area over the perimeter of a given stope surface. It has also

    been demonstrated that, despite the advantages of hydraulic

    radius over span, it still has important limitations (Milne,

    Pakalnis, and Felderer 1996). In particular, when applied to

    irregularly shaped stope surfaces, it is possible to arrive at the

  • 8/17/2019 The Stability Graph Method for Qpen-Stope Design (1)

    4/8

    5 1 6

    F o u n d a t i o n s f o r D e s i g n i

    F I G UR E 6 0 . 7 D e t e r m i n a t i o n o f t h e r a d i u s f a c t o r , a f t e r M i l n e e t a t .

    ( 1 9 9 6 )

    same hydraulic radius. It has been put forward that a better way

    to describe the geometry of an irregularly shaped excavation is

    the radius factor (see F igure 60.7 ). This is determined by identi-

    fying the centre of any excavation and by taking distance

    measurements to abutments at small regular increments:

    RF = °

    5

    I y n = i i

    n ^ Q r

    0

    where

    re = distance fro m the surface centre to the abutm ents at

    angle q

    n  = number of rays measured to the surface edge

    In principle, the radius factor can be determined at any

    point on a surface. If the centre cannot be determined, a series of

    calculations are possible with the maximum value assumed to be

    the radius factor. Despite its somewhat cumbersome definition,

    the radius factor can easily be calculated by a routine integrated

    into a computerised design package.

    8©oS B E B i m c h a r t s

    In reviewing the proposed chart, Figure 60.1 (Mathews et al.

    1981), it can be seen that the developed guidelines were some-

    what vague for design purposes. This was because there was

    insufficient data to provide more accurate zone definition. As

    more case studies became available, a narrower transition zone

    and a support requirement zone were defined (Potvin 1988).

    This has allowed for a calibrated and m ore versatile design tool

    (Figure 60.2). A more comprehensive statistical analysis further

    mod ified the support zones by introducing lines indicating wh ere

    cable bolting could be used (see Figure 60.8) (Nickson 1992). A

    review of a larger database (Hadjigeorgiou, Leclair and Potvin

    1995) confirmed the general validity of previous work (Potvin

    1988, Nickson 1992) within statistical limits.

    It should be noted that the work of Hadjigeorgiou et al.

    (1995) demonstrated that, for larger stopes with a hydraulic

    radius greater than 15, the design curve was in fact flatter (see

    Figure 60.9). M ore recent work in the United Kingdom by Pascoe

    et al. (1998) and in Australia by Trueman et al. (2000) has

    confirmed the same trends.

    A series of design guidelines were proposed (Stewart and

    Forsyth 1995) that allowed for a finer definition of the types of

    F I G UR E 6 0 . 8 S t a b i l i t y g r a p h , a f t e r N i c k s o n ( 1 9 9 2 )

    F I GU R E 6 0 . 9 S t a b i l i t y g r a p h d e s i g n li n e s a s d e v e l o p e d b y

    H a d j i g e o r g i o u s e t a l . ( 1 9 9 5 )

    stope failure, distinguishing between potentially unstable, poten-

    tially major, and caving failure separated by transition zones (see

    Figure 60.10). In their experience, the boundary between stable

    and unstable is clear cut, while the transition between unstable

    and major failure is not as well defined. It is of interest that the

    transition between a potentially stable zon e and a potentially

    unstable zon e is identical to Potvin's transition zone. In practice,

    it could be argued that, for open-stope design purposes, it is

    somewh at irrelevant to subdivide the area de fining stope failure

    into three zo nes as the objective is to design stable stopes.

    Cavity monitoring laser surveys have been employed to back-

    analyse the resulting volumetric measurements of overbreak/

  • 8/17/2019 The Stability Graph Method for Qpen-Stope Design (1)

    5/8

    T h e S t a b i l i t y G r a p h M e t h o d f o r © p e s i -S t o p e D e s i g n

    5 1 7

    1000

    1

    5 1 0 1 5

    H y a r a u l i c r d i u ( m )

    1 0 1 5

    H y d r a u l i c r a d i u s ( m )

    F I GU R E 6 0 = 1 0 S t a b i l i t y g r a p h a f t e r S t e w r t & F o r s yt h ( 1 9 9 3 )

    F I GU R E 6 0 . 1 2 E s t i m a t i o n o f o v e r b r e a k / s l o u g h f o r n o n s u p p o r t e d

    h a n g i n g w a l l s a n d f o o t w a l l s , a f t e r Cl a r k a n d P a k a l n i s 1 9 9 7

    S t o p e

    „ W i d t h

    s?

    s*

    ¡ 4 I C r o s s - S e c t i o n s

    G e n e r a t e d f r o m

    I M S S u r v e y

    L e n g t h j . y . . G ì

    l/\ \

    E q u i v a l e n t L i n e a r

    O v e r b re a k / S l o u g h

    ( E x p r e s s e d i n M e t e r s

    E l

      S l o u g h f r o m S t o p e W a i l s

    I E q u i v a l e n t l i n e a r o v e r b r e a k / S l o u g h

    F I GU R E 6 0 . 1 1 S c h e m a t i c d e f i n i t i o n o f t h e E L OS p a r a m e t e r , a f t e r

    C l a r k a n d P a k a l n i s 1 9 9 7

    slough and underbreak, and a new index has been prop osed (Clark

    and Pakalnis 1997) (see Figure 60.11):

    ELOS

    equivalent linear overbreak

    slough

    volume of slough from stope surface

    stope height x wa ll strike length

    In Figure 60.12, ELOS has been integrated in the stability

    graph, providing a series of design zones (Clark and Pakalnis

    1997). Although this data presentation does not account for the

    influence of support, it provides a useful back-analysis tool for

    hanging walls and footwalls in a low- or relaxed-stress state and

    with parallel geological structure being present.

    All of the above graphs rely on arbitrarily drawn design

    curves. The first comprehensive statistical analysis of the then-

    available field data (Nickson 1992) clearly demonstrated the

    applicability of the modified stability graph (Potvin 1988) and

    laid the foundations for further statistical work (Hadjigeorgiou,

    Leclair, and Potvin 1995, Pascoe et al. 1998, and Suorineni

    1998).

    Successful applications of the stability graph recognise that

    the method remains subjective. Despite using quantifiable values,

    the precise degree of inherent conservatism is not known. It

    reflects current and past practice, which m ay have been influ-

    enced by legislation, local practices, or geologic al peculiarities, and

    does not necessarily constitute an optimum design meth odology.

    8 0 . 7 ¡R IS K A N A L Y S I S

    It has been argued that the design of non-entry excavations lends

    itself to risk analysis much more than the design of access ways

    where worker safety is the major concern (Pine et al. 1996,

    Pascoe et al. 1998, Diederichs and Kaiser 1996). There are two

    basic elements in risk analysis. The first one deals with input vari-

    ability and the second deals with calibration uncertainty. For

    practical purposes, the major challenge lies in defin ing ho w much

    risk is acceptable for design purposes. Using risk probability

    procedures for fine-tuning or calibrating site-specific design

    guidelines, while attractive, is hindered in that site-specific cali-

    brated guidelines will be validated only towards the end of mine

    life. At that time, their impact will be limited to p roviding a b etter

    understanding of particular field conditions, but it may be too

    late to implement m ajor design changes.

    6 0 . 8 S U P P O R T R E C OI V I I VS E N D A TS O N S

    Potvin (1988) first addressed the influence of support on the

    stability of open stopes. The area of the graph that could success-

    fully be supported by cable bolts was refined , and a series of design

    recommendations made on cable-bolting patterns (Nickson 1992).

    The basic concept is that there is a zone where support cannot be

    effectively used to stabilise the excavation. It has been shown

    (Hadjigeorgiou, Leclair, and Potvin 1995) that the actual support-

    able zone was smaller than predicted (Nickson 1992).

    A design chart is available to select a suitable cable-bolt

    density as a function of relative block size  (RQD/J

    n

    )  and the

    hydraulic radius (Potvin and Milne 1992). This graph, slightly

    modified in Figure 60.13, is most appropriate for stope backs. It

    has also been employed for hanging-wall reinforcement design,

    provided a systematic and regular cable-bolt pattern is used.

  • 8/17/2019 The Stability Graph Method for Qpen-Stope Design (1)

    6/8

    5 1 8

    Foyo i ida tBOin is fo r Des ign

    ( R Q D / J n )

    H y d r a u l i c r a d i u s

    F I GU R E 6 0 . 1 3 D e t e r m i n a t i o n o f c a b l e b o l t d e n s i t y

    At the time when the design curves for cable reinforcement

    were developed, support often consisted of single plain-strand

    cables. Recent years have seen a shift towards double-strand and

    modified-geometry cables as they provide higher support

    capacity. This is achieved in the presence of sufficiently high

    ground deformation whereby the strength of the steel is being

    mobilized. In other words, pattern reinforcement is designed to

    help the rock support itself and not necessarily to support the

    dead weight of the rock. A series of semi-empirical design charts

    to determine the design spacing for both single- and double-

    strand cable bolts has been proposed (Diederichs, Hutchinson,

    and Kaiser 1999). It should be noted, how ever, that there are no

    documented case studies confirming their application.

    SQ 3

      L I M I T A T I O N S © F T i H E S T A B I L I T Y

      QiRAPU

    All empirical methods are limited in their application to cases

    that are similar to the one used in the developmental database.

    Therefore, the stability graph is inappropriate in severe rock-

    bursting conditions, in highly deformable (creeping) rock mass,

    and for entry methods. Since its introduction, the stability graph

    method has been the subject of extensive efforts to expand its

    applicability to better account for the presence of faults, blast

    damage, and stress damag e. Unfortunately, some of the proposed

    modifications are not supported by field data. Furthermore, when

    merging databases from diverse sources, it is necessary to verify

    the quality of collected data. In particular, the practice of using

    empirical correlations to convert from one rock-mass classifica-

    tion system to another should only be used as a last resort and

    even then with great caution.

    For all practical purposes, the stability graph can be used

    during the feasibility stage, during individual stope planning, and

    for stope reconciliation or back analyses.

    e ®

    D

    1 0 D E S D G N C O N S I D E R A T I O N S

    T H E F E A S I B I L I T Y S T A © E

    The determination of adequate stope dimension is one of the

    most critical decisions to be made at the feasibility study stage of

    a mine. The profitability of an operation is directly linked to

    productivity, which in turn, is influenced by stope dimensions.

    Validation of stope-design methodology can begin once the first

    stope is extracted. By this time, however, the mine infrastructure

    is already in place, allowing for no or only minor m odifications to

    design stope dimensions. This emphasizes the importance of

    developing a reliable stope-design methodology at the earliest

    possible stage.

    Many practitioners have reported on the reliability of the

    stability-graph method during the last 12 years (Reschke and

    Romanowski 1993, Bawden 1993, Pascoe et al. 1998, Dunne et al.

    1996, and Goel and Wezenberg 1999). When properly used, the

    meth od provides a goo d ball park estimate of stable stope dimen-

    sions under different conditions. The major limitation at the feasi-

    bility study stage is the availability of quality geotechnical data.

    This is a concern fo r all design m ethods. C onsequently, it is essen-

    tial to optimise all available data while being fully aware of any

    limitations. The following guidelines can facilitate the estimation

    of realistic stability numbers during the feasibility stage.

    An integral part of the stability method is the quantification of

    rock-mass quality based on the Q system. At the green f ield stage,

    the majority of geomechanical data are derived from boreholes.

    Consequently, it is possible to develop a comprehensive database

    of  RQ D  readings, which can easily be integrated into geological

    models easily accessed by both planning and rock mechanics. It is

    strongly suggested that the number of joint sets be determined by

    using oriented diamond-drill cores in the orebody.

    There are several case studies where core data were used to

    derive representative Q readings for underground mines (Milne,

    Germain and Potvin 1992, Germain, Hadjigeorgiou, and Lessard

    1996). This has included a simplified approach to determine joint

    alteration, J

    a

    .  If the joint cannot be scratched with a knife, J

    a

      is

    assumed to be equal to 0.75, and if it is possible to scratch, it

    varies from 1.0 to 1.5. Whe n a joint feels slippery to touch and

    can scratched with a fingernail, J

    a

      is equal to 2; and when it is

    possible to indent with a fingernail,  J

    a

      is equal to 4. The joint

    roughness parameter (J

    r

    ) is more difficult to assess on a small

    exposed surface of a core. How ever, in most cases, it is possible to

    estimate whether the surface is smooth or rough . In the absence

    of reliable data, joints are assumed to be planar. This allows for J

    r

    values of 0.5 for slickenslide planar, 1.0 for smooth planar, and

    1.5 for rough planar joints.

    Factor A can generally be assumed to be equal to 1 for all

    stope walls, unless mining is to proceed very deep (say 1,000 m

    and deeper). As a first-pass estimation, the stress induced in

    stope backs could be assumed to be around 1.5 times the pre-

    mining horizontal stress for transversal mining (mining across

    the strike of the orebody). In longitudinal mining (mining along

    strike), a rough estimate of the induced stress in the back can be

    obtained by doubling the premining horizontal stress perpendic-

    ular to the orebod y strike. The prem ining stress can be measured

    if underground access is available or otherw ise based on regional

    data. The uniaxial compressive strength of rock is easily obtained

    by standard laboratory tests on cored rock. A larger database of

    UCS values can also be gathered at low cost using a standard

    point load test. When at least some oriented core is available,

    Factor B can be estimated. In the absence of joint orientation

    data, a minimum value of 0.2 is assumed. The estimation of

    factor C is independent of ground conditions and is, therefore,

    straightforward to determine, eve n at the feasibility stage.

    A good methodology for the construction of a geomechan-

    ical model and the application of the stability graph method for

    mine feasibility assessment exists (Nickson et al. 1995). Stability

    numbers are calculated for back and walls and displayed on m ine

    sections. For each stability number (N ), a hydraulic radius (S ) is

    determined from the stability graph in Figure 60.14, using the

    upper section of the transition zone. The option of increasing

    stope dimensions exists if a systematic pattern of cable-bolt

    support is to be used. This can be assessed using Figure 6 0.8.

    Unless the ground conditions are consistent throughout the

    orebody, a number of stable hydraulic radii will be produced,

    which can be grouped into domains and displayed on a longitu-

    dinal section. Because most mines employ systematic layouts, a

  • 8/17/2019 The Stability Graph Method for Qpen-Stope Design (1)

    7/8

    T h e St a b i l i t y G r a p h M e t h o d f o r © p e s i -S t o p e D e s i g n

    5 1 9

    3CQQ EL

    F I G UR E 6 0 . 1 4 A c a s e s t u d y d u r in g t h e f e a s i b i l i t y s t a g e , a f t e r

    N i c k s o n e t a i . 1 9 9 5

    unique stope dimension is usually determined for each mine

    domain. Engineering judgement must be used in selecting the

    appropriate hydraulic radius. Selecting the smallest hydraulic

    radius would ensure that all stopes would be stable, but would

    not likely be the most economical option. Notwithstanding the

    value of ore, the impact of dilution, acceptable risks, and the

    operating philosophy, a good starting point for selecting a mean

    hydraulic radius for an entire domain would be to ensure that

    approximately 80% of the stopes are stable. The remaining 20%

    or so can then be dealt with individually using specific ground

    support or different extraction strategies.

    The stope height, length, and width within each domain can

    be determined from the mean hydraulic radii (roof and walls).

    The orebody geometry obviously has an important influence on

    the determination of the stope geometry. In many cases, there

    will be an economic advantage to maximising the stope height as

    it has a major influence on the sublevel interval, and therefore,

    on the mine infrastructure cost.

    As more and more operations integrate backfill in the

    extraction process, its impact on stope stability must be

    accounted for. The main function of mine backfill is to limit the

    exposure of stope surfaces during extraction by filling adjacent

    mined-out stopes. Provided a good quality-control program is

    followed, it can reasonably be assumed that backfill provides

    adequate support of adjacent mined out stopes. Consequently,

    the stability-graph method treats backfill as a rock material when

    calculating stope-wall dimensions. In practice, however, it is rare

    that a tight fill can be established against a stope back. As a

    result, in stope-back analysis, the influence of backfill is assumed

    to be minimal and ignored.

    @© „ 1 ± D E S I G N C O N S I D E R A T I O N S F O R

    I N D I V I D U A L S T O P E P L A N N I N G

    It is good engineering practice to employ the stability graph at the

    plannin g stage to evaluate the stability of each stop e. At this stage

    of development, there is usually underground access that allows

    for a revaluation of the rock-mass data collected during the feasi-

    bil ity study. Direct underground mapping can provide more

    reliable information than diamond-drill hole data. Another

    advantage of underground observations is that it can reveal early

    signs of stress. This can be complemented by stress measure-

    ments allowing for a better assessment of stress influence on the

    stopes. At this point, it is possible to integrate numerical model-

    ling to investigate optimum sequencing.

    Access to more quality data can allow fo r greater confidence

    in stope stability estimates than allowed during the feasibility

    study. Consequently, it is possible to consider modifications or

    fine-tuning to the ground support and extraction strategies. At

    this stage, it is also important to assess the influence on stope

    stability of some of the factors not well accounted-for in the

    stability-graph method. These can include faulting, shear zones,

    or areas susceptible to rock bursts.

    One o f the great bene fits of using such a meth od at the plan-

    ning stage is that it brings geomechanical considerations into

    stope design and increases the awareness of mine planners to

    ground-control issues. Modern stope designs require the close

    cooperation of geology, mine p lanning, and rock mechanics.

    6 0 1 2 S T O P E R E C O N C I L I A T I O N

    Using the stability graph to assess and document stope perfor-

    mance is useful to build site-specific empirical knowledge that

    can be used in future design. Once a sufficient number of case

    histories have been collected, it may even be possible to refine the

    stability graph for a given site or extend its predictive capability

    to dilution (Pakalnis, Poulin, and Hadjigeorgiou 1995) or to

    quantify the probability of failure (D iederichs and Kaiser 1996).

    A major aid in stope reconciliation has been the introduction of

    cavity-monitoring systems.

    These refinements are interesting and contribute to a better

    understanding of stope behaviour. However, the value added to

    operations from this effort remains limited in many cases because

    the initial stages of mining are completed, the mine infrastruc-

    ture is in place, and opportunities for modifying stopes layout are

    restricted.

    6 0 , 1 3 D I S C U S S I O N A N D C O N C L U S I O N

    By definition, empirical design is based on observation and expe-

    rience. The stability-graph method owes its popularity in its ease

    of  use its application at early stages of minin g, and the fac t that it

    can provide a reference for stope performance. Invariably, it

    cannot provide a successful prediction for every stope at every

    operation because the complexity of ground conditions and oper-

    ating practices can influence stope performance.

    It has been argued in the past that the method only reaches

    its full potentia l wh en it is site-calibrated . Th e basic assumption

    is that, as more data become available, the design recommenda-

    tions can be modified through back analysis. Obviously, this is an

    important step in better understanding the site conditions. If the

    reconciliation exercise is done rigorously, it can reveal important

    information on the efficiency of mine practices such as blasting,

    prereinforcement, and sequencing.

    However, this should not detract from the main ob jective of

    the method as a design tool at the feasibility stage when no such

    data is available, but when the critical decision must be made.

    The extensive calibration of the method worldwide makes it

    very robust and ideal for designing open-stope dimension at the

    z

    o

    Q

    HW ROD

    Q

    :

     = 1 0

    A  = 1

    B = 0 .3

    C = 3 .5

    N' =  10 5

    3 = 6

    > = 0 %

    S   > =   20%

    l i   > =   40%

    El

     >

     =   60%

    a > = 7 5 %

  • 8/17/2019 The Stability Graph Method for Qpen-Stope Design (1)

    8/8

    5 2 0

    F o u n d a t i o n s f o r D e s i g n i

    feasibility-assessment stage. The added value of a very refined

    site-specific graph towards the end of a mine life can only be

    limited.

    Over the years, there has been a proliferation of design

    charts aiming to refine the m ethod or expand on its applicability.

    Design charts that are not backed by field data have limited use.

    Similarly, modifications that rely on limited sites should be

    viewed with caution.

    Complex charts bring new and interesting ideas, but one

    should keep in mind that the method can be no better than the

    quality of input data available. This is particularly true at the

    feasibility stage where data are limited by access.

    Introducing many zones to the graph has limited application

    at the design stage because the designer has to come up with a

    hydraulic radius number for each domain. The transition

    between stable and unstable and the potential for increasing

    dimensions b y using pattern cable bolts rema in the basis for stope

    design

    S O „ 1 4 R E F E R E N C E S

    Barton, N., R. Lien, and J. Lunde. (1974). E ngineering classification of

    rock masses for the design of tunnel support.

     Rock Mechanics

    Vol. 6.

    No. 4, pp. 189-236.

    Bawden , W.F., J. Nantel, and D. Sprott. (19 89). Practical rock eng ineering

    in the optimisation o f stope dimensions—Applications and cost

    effectiveness.

     CIM Bulletin,

     82 (92 6), pp. 63-70.

    Bawde n, W.F. (1993). Th e use of rock mechanics principles in Canadian

    underground hard-rock mine design. Comprehensive

     Rock Engi-

    neering.

     Chapter 11, Vol. 5, pp. 2 47-29 0.

    Clark, L.M., and R.C. Pakalnis. (1997 ). An empirical design approach fo r

    estimating unplanned dilution from open stope hangingwalls and

    footwalls.

     99th CIM-AGM,

     Vancouver, published on CD-ROM.

    Diederichs, M., D.J. Hutchinson, and P.K. Kaiser. (199 9). Cable-bolt

    layouts using the modified stability graph.

     CIM Bulletin

      November/

    December, pp. 81-85.

    Diederichs, M ., and P.K. Kaiser. (1996 ). Rock instability and risk in open

    stope design.

     Can.

     Geotech.

     J .,

     Vol. 33, pp. 431-439.

    Dunne, K. and R.C. Pakalnis. (19 96). D ilution aspects of a sub-level

    retreat stope at Detour Lake Mine.

     Proc. 2nd HARM S Rock

     Mechanics

    Symp. On Rock Mechanics Toob and

     Techniques Montreal, Balkema,

    Vol. 1, pp. 305-313.

    Dunne, K., R. Pakalnis, S. Mah, and S. Vongpaisal. (1996 ). Design anal-

    ysis of an open stope at Detour Lake Mine.

     98th CIM-AGM,

    Edmonton.

    Germa in, P, J. Hadjigeorg iou, and J.F. Lessard. (1996 ). On the relation-

    ship between stability prediction and observed stope overbreak.

    Proc. 2nd HARMS, Rock Mechanics

     Symp.

     on Rock Mechanics Tools

    and

     Techniques Vol. 1, pp. 227-283.

    Goel, S.C., and U. Wez enbe rg. (199 9). Stability of open stopes at Ashanti

    Goldfields-Obuasi Betriebe 1999.

     Hinth International

      Congress

     on

    Rock Mechanics.

     Vol 1, pp. 101 -106.

    Had jigeorgio u, J., J.G. Leclair, and Y. Potvin. (1 995). A n update of the

    stability graph method for open stope design.

     97th CIM-AGM, Rock

    Mechanics and Strata Control

     Session Halifax, Nova Scotia.

    Hutchinson, D.J. and M. Diederichs. (19 96). Cable

     bolting in Underground

    Mines.

     BiTech Publishers, Richmon d, 406 pp.

    Hoek , E., P.K. Kaiser, and W.F. Bawden . (1 995).

     Support of Underground

    Excavations in Hard Rock.

     Rotterda m: A .A. Balkema, 1995, 215 pp.

    Kaiser, P.K, V. Falmagne, F.T. Suorineni, M.S. Diederichs, and D .D.

    Tannant. (1997). Incorporation of rock-mass relaxation and degra-

    dation into empirical stope design.

     CIM-AGM,

      Vancouver.

    Laubscher, D.H. (19 77). Geom echanics classification of jointe d rock

    masses-mining applications. Transactions Institute of Mining and

    Metallurgy, Section A . Vol. 86, pp. A1-A7.

    Mathe ws K.E., E. Hoek, D .C. Wy llie, and S.B.V. Stewart. (19 81). Predic-

    tion of stable excavation spans for mining at depths below 1,000 m

    in hard rock mines. Canmet Report DSS Serial No.  OSQ8O OOO8I.

    Milne, D.,  P. Germain, and Y. Ponan. (1992). Measurement of rock mass

    properties for mine design, Proceedings

     o f

     the

     ISRM-Eurock S ympo-

    sium on Rock Characterization,

     A.A . Balkema, Chester, England.

    Milne, D., R.C. Pakalnis, and M. Felderer. (1996) Surface geometry

    assessment for open stope design.

     Proc. Horth Americam Rock

    Mechanics Symposium, Montreal,

     Balkema, pp. 315-322.

    Nickson, S.D. (1992). Cable support guidelines for underground hard

    rock mine ope rations. M.A.Sc. Thesis, The University o f British

    Columbia., 223 p.

    Pakalnis, RC. (1986). E mpirical stope design at Ruttan Min e. Ph.D.

    Thesis. The Un iversity of British Colum bia.

    Pakalnis R., R. Poulin, and  J. Hadjigeorgiou. (1995 ). Quantifying the cost of

    dilution in underground

     mines

    .

     Mining

     Engineering: pp. 1136-1141.

    Pascoe D.M., N. Powell, J.S. Coggan, K. Atkinson, and M. Ow en. (1998 ).

    Methodology for underground risk analysis using the Canadian

    stability graph method.

     Mine Planning and Equipment Selection.

    pp.199-205.

    Pine R.J., K. J. Ross, P. Arno ld, and M. Hodgs on. (1995 ). A probabilistic

    risk assessment approach to hanging wa ll design.

     IMM

     Conference

    on Health Safety in Mining Metallurgy,

     London.

    Potvin, Y. (1988). Empirical open stope design in Canada. Ph.D. Thesis.

    The University of British Columbia p. 350.

    Potvin, Y. and D. Milne. (1992 ). Empirical cable bolt support design.

    Proceedings of

     the

     International S ymposium on Rock Support,

    P. Kaiser and D. McCreath, Eds. Sudbury, Ontario, pp. 269 -275.

    Poulin R., R. Pakalnis, D.A. Peterson, and J.C. Kalynchuk. (19 95). Evalua-

    tion of cable bolt applications for Canadian underground mines.

    CIM Bulletin,

     Vol. 88, No. 989 pp. 55-58 .

    Reschke A.E. and J. Roman owski. (1993 ). The success and limitations of

    Mathe ws analysis for open stope design at HBMS, Flin Flon opera-

    tions.

     95th CIM-AGM,

      Calgary.

    Scoble, M.J., and A. Moss. (199 4). A. dilution in underground bulk

    mining: implications for production management, mineral resource

    evaluation II: methods and case histories.

     Geological Society

     Special

    Publication

      no. 79,1994, p. 95-108.

    Sprott, D.L., M.A. Toppi, X. Yi., and W.F. Bawden. (1999 ). The incorpora-

    tion of stress damage fac tor into Mathew's stability graph. Canadian

    Institute of Mining Annual General Meeting, Calgary, published on

    CD-ROM.

    Stewart, S.B.V., and W.W. Forsyth. (1993). The Mathew s method for open

    stope design.

     CIM Bull,

      Vol. 88 (99 2), 1995, pp. 45-53.

    Suorineni, F.T. (1999 ). Effects

     o f Faults and

     Stress

     on O pen Stope Design.

    Ph.D. Thesis, Department of Earth Sciences, University of Wa terloo,

    Waterloo, Canada, 345 pp.

    Suorineni, F.T., D.D. Tannant, and P.K. Kaiser. (199 9). Fault factor for the

    stability graph method of open stope design.

     Trans. Instn. Min.

    Metall.

      (Sect. A: Min. Industry) 108, pp. A92-A 104.

    Trueman R ., P. Mikula, C. Mawde sley, and N. Harries. (2000 ). Experience

    in Australia with the application of the Mathews method for open

    stope design.

     CIM B ulletin,

     Vol. 93, No . 1036, pp. 162-167.