The San Xavier Mine - Hoist Commissioning

Embed Size (px)

Citation preview

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    1/103

    THE

    SAN XAVIER

    MINE:

    HOIST

    COMMISSIONING

    By

    DANA

    IONET

    SPECHT

    A

    Thesis

    Submitted

    to the

    Honors College

    In Partial

    Fulfillment

    of

    the

    Bachelors

    of

    Science

    degree

    With

    Honors

    in

    Mining

    Engineering

    THE

    UNTVERSITY

    OF

    ARIZONA

    MAY 2OI1

    Dr

    Mary Poulton

    DeparEnent

    of

    Mining

    and Geologrcal

    Engineering

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    2/103

    STATEMENT

    BYAUTHOR

    This

    thesis has

    bee4

    submitted in

    partial

    fulfilknent of

    requirements

    for

    a

    degree

    at The

    University

    of Arizona

    and

    is

    deposited

    in the

    University Library

    to be

    made

    available

    to

    boriowers

    under rules

    of

    the Library

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    3/103

    Statement of Individual Work

    Dana Specht: Mine Leader. San Xavier Mine Manger.

    Responsible for coordinating the project with the mine.Also responsible for coordinating and delegating team

    duties at the San Xavier Mine.

    Scott Shields: Contracting Leader. San Xavier Associate

    Engineer. Responsible for coordinating with contractors

    and setting up meetings.

    Stephenie Mirka:

    Responsible for following project

    requirements and insuring all research and team

    deadlines were met.

    Andrew Swazey: Responsible for technical data and

    visual imaging.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    4/103

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    5/103

    iii

    Contents

    Executive Summary ......................................................................................................................... 1

    Introduction .................................................................................................................................... 2Scope of Work ................................................................................................................................. 3

    Background ..................................................................................................................................... 4

    Mine History ................................................................................................................................ 4

    Hoist History ................................................................................................................................ 5

    Current Hoist ........................................................................................................................... 5

    Refurbished Hoist .................................................................................................................... 7

    Usage ........................................................................................................................................... 8Communication ........................................................................................................................... 9

    San Xavier Hoisting Emergency Procedures .......................................................................... 10

    RopeRanger Autonomous System .......................................................................................... 11

    Rope .......................................................................................................................................... 11

    Cameras ..................................................................................................................................... 12

    Utilities ...................................................................................................................................... 13

    Schedule ........................................................................................................................................ 13Fall Schedule .......................................................................................................................... 14

    Spring Schedule ..................................................................................................................... 14

    Implementation Schedule ..................................................................................................... 15

    Budget ........................................................................................................................................... 16

    Hoist Upgrade Costs .................................................................................................................. 16

    Commissioning Costs................................................................................................................. 17

    Design ............................................................................................................................................ 18Risk Assessment ........................................................................................................................ 18

    Opportunities and Challenges ................................................................................................... 20

    Hoisting calculations ................................................................................................................. 22

    Implementation ......................................................................................................................... 23

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    6/103

    iv

    San Xavier Hoist Operating Hardware Manual ............................................................................. 23

    Future Work .................................................................................................................................. 23

    Conclusion ..................................................................................................................................... 24

    References .................................................................................................................................... 27

    Appendix A - San Xavier Mine Operating Procedures .................................................................. 28

    Appendix B - Existing and Proposed Electrical Loads ................................................................... 30

    Appendix C - Schedule and Budget ............................................................................................... 32

    Appendix D - Risk Analysis ............................................................................................................ 35

    Appendix E - Applicable MSHA Regulations ................................................................................. 37

    Appendix F - Applicable OSHA Regulations .................................................................................. 44

    Appendix G - Applicable Arizona Mining Regulations .................................................................. 46

    Appendix H - Stantec Proposal ..................................................................................................... 47

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    7/103

    1

    Executive Summary

    The San Xavier Mining Laboratory (SX) outside of Tucson, Arizona, is a one-of-a-kind venue,

    partly due to its working shaft. The SX has provided many mining engineering students with

    vital experience before moving forward with their career. Capital has been raised to improve

    the shafts hoisting system, and that capital will go towards the implementation of newly placed

    hoisting equipment. This implementation will improve the functionality and safety of the hoist

    system.

    The project consists of three major parts: implementation and engineering verification of the

    physical hoist system, implementation of automated hoist controls, and installation of a skip

    viewing system. Besides the main project team, the project will include coordination with three

    outside groups. The groups involved include Stantec Consulting Services for engineering

    verification, SafeHoist representatives to assist with software implementation, and CCT &

    Associates to assist with camera system installation. Implementation of the tangible pieces of

    the project is to commence following administrative contract verification and signing. A budget

    of approximately $15,900 has been estimated for the project. A general implementation

    schedule was developed apart from the overarching project schedule to allow for any

    unexpected administrative delays out of the project teams control.

    At the time of this writing, the newly installed hoist is scheduled to be wound and attached to

    the skip. This piece of the project was recently authorized and will be completed by the project

    team.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    8/103

    2 | P a g e

    Introduction

    In any industry, safety should come first. The mining industry is no different. A lack of safety

    will inhibit the amount of production that operating mines possess. Similarly, a research and

    learning facility needs to operate in the same manner, in order to fulfill its purpose of

    education. The SX, owned by the University of Arizona, utilizes the No. 6 shaft to train mining

    engineering students in removing equipment, muck, and injured persons in the case of an

    emergency. Although safe practices may be part of the culture within a mine site, hazards can

    still exist. Undeniably, mine shafts and hoists are inherently dangerous if a malfunction were to

    occur.

    With the advancement of new technology, it is now possible to reduce the risks that hoisting

    presents. The SafeHoist RopeRanger system can provide sensors and detectors to improve

    the safety of working hoisting equipment. These sensors are installed on the hoist rope. The

    detectors report the acceleration, oscillation, and tension of the rope. Additionally, this system

    allows the operator to monitor any possible slack in the rope and ensures that the safety factor

    remains constant. Shaft changes can be detected, as well.

    Prior to installation of the SafeHoist system, a newly purchased hoist rope will be wound by a

    team of undergraduate, design students at the San Xavier Mining Laboratory. This team has

    developed a project management plan to refurbish the existing hoist by proposing safety

    enhancements and automated hoisting controls. In addition to the installation of the

    RopeRanger, a Lily Simplex Overspeed and Overwind hoist controller will be implemented.

    Finally, the team has proposed that previously donated cameras be installed along the depth of

    the shaft, in order to monitor the skip by a use of a BARCO multiple I/O port Central Processing

    Unit (CPU).

    These components of the proposed refurbishment require outside engineering professionals to

    monitor the installation of said components, as well as ensure their reliability. The entirety of

    this project will be performed with funds which have been allocated from the Universitys

    Mining Engineering Department. Upon completion, the mines currently working shaft will

    further accentuate the unique qualities of this underground, research facility. It will provide

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    9/103

    3 | P a g e

    students and other visitors the opportunity to obtain knowledge about a mine shaft and hoist,

    while working with improved safety conditions and advanced technological systems.

    Scope of WorkThe SX utilizes a shaft and hoisting system to both lower and raise mining and research equipment,

    to remove earthen material from two lower levels, and to provide emergency rescue hoisting if

    necessary. Currently, the operating system consists of a pneumatically driven drum and is manually

    operated from an outdoor station.

    The project team proposes safety enhancements and automated hoisting controls for the San Xavier

    mine. The project will include hoist engineering calculations, system integration and component

    compatibility investigations, and implementation of three systems:

    1.) A donated SafeHoist RopeRanger autonomous system.

    2.) An existing Lily Simplex Overspeed and Overwind Hoist Controller.

    3.) Installation of a skip viewing system along the depth of the shaft.

    Figure 1: San Xavier Hoist Commissioning

    A newly purchased hoist rope would be wound as part of the refurbishment. Creation of an

    operating manual and training procedure would also be within the scope of the proposed project.

    The timeline for completion is two months, and will require approximately $15,900 in funding.

    External sources of engineering and hoisting expertise are required to complete this project. All

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    10/103

    4 | P a g e

    safety calculations will be reviewed by licensed engineers prior to making in-field modifications to

    the existing system.

    An electrical engineer will be required to confirm if the existing electrical system will be sufficient

    and to ensure compatibility with the safe hoist system. A refurbished Lily Simplex Controller has

    been installed at the mine; however, it has not been placed into service. A Safetronics field

    representative will be required to integrate the SafeHoist system and to aid in the removal of the

    current hoisting components upon commissioning of the system. A professional hoisting engineer

    will be necessary to oversee the hoist rope winding and to approve all hoisting calculations

    completed under the scope of the project.

    Donated camera system components will be integrated with a BARCO multiple I/O port CPU and

    screen to increase skip monitoring capabilities. Project team members will be required to install the

    cameras and monitoring system. A CCT & Associates representative will be required for system

    programming and camera integration with the CPU.

    In order to decrease the workload of outside engineers and personnel, the project team will

    calculate hoist engineering data, coordinate planned work, and complete installation of the various

    hoist system components. The project team will also produce an operating manual and implement a

    training plan for new hoist operators.

    Background

    Mine History

    The San Xavier Mining Laboratory is a unique resource that allows students to gain leadership

    and problem solving skills with hands-on experience running a fully operational, underground

    mine. The University of Arizona Department of Mining and Geological Engineering has

    operated the mine since 1958. In 1975, the University of Arizona assumed full ownership of the

    zinc, lead, silver, and copper operation from Anamax Mining Company. The property is

    comprised of over 90 acres, featuring a mine training and operations facility, a hoist house and

    headframe, and work and lay down areas. Located approximately 23 miles south of Tucson,

    Arizona, the mine is part of a closed network of mine workings surrounding the No. 6 Shaft.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    11/103

    5 | P a g e

    Figure 2: San Xavier Mine, 1978

    The SX is currently the only mining laboratory in the United States with a working vertical shaft.

    Three underground levels are currently operational, including an adit level and two working

    levels at depths of 100 feet and 150 feet accessible from the shaft. Primarily a drill-blast-muck

    operation, the mine is maintained by university students. This future workforce is heavily

    involved in the operations of the SX as student leaders and volunteers spend weekly eight hour

    shifts developing the mine and their skill-set. The facility is used for course work from many

    different disciplines of education at the University of Arizona and also provides research

    opportunities for educational, private, and commercial partners. For these reasons, the SX has

    been recognized by the International Society of Mine Professionals for its dedication to

    advancing safety and health in the mining industry.

    Hoist History

    Current HoistThe hoist currently in use at the SX consists of a small, pneumatically powered, Gardner-Denver

    air tugger and a 3/8 inch rope, as shown in Figure 2. At optimum conditions, the air tugger

    maintains a 1.5 ton load capacity. This capacity has gradually been reduced due to infrequent

    maintenance and constant exposure to the elements. Although normal production

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    12/103

    6 | P a g e

    requirements do not exceed this capacity, the hoist is occasionally required to lift an Eimco 12B

    tracked overshot mucker. The downward acceleration of the overshot mucker exceeds the

    rated capacity by several hundred pounds and cannot be controlled by the brake alone. Thus,

    lowering the overshot mucker requires the operator to simultaneously employ the break and

    the upward hoisting controls to accommodate the weight.

    In addition to the inadequacy of the air tugger, the 3/8 inch cable rope is not designed for

    hoisting. When lowering the skip to the 150 foot level, the rope permits nearly 4 inches of

    stretch, creating a hazard when miners below are on-loading ore carts or equipment. Many

    time-consuming incidents have occurred in which ore carts have been tipped onto the skip,

    spilling ore and requiring extensive energy to re-right.

    Another cause for concern is the noise interference when operating the hoist. Located outside

    in close proximity to the air compressor, the hoist operator is unable to hear directions. For this

    reason, the hoist operator typically requires an assistant to listen to the bells and relay

    directions. This often causes confusion and is potentially dangerous in emergency situations. All

    factors considered, the current hoisting system is well below the MSHA required factor of

    safety.

    Figure 3: Existing Hoist

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    13/103

    7 | P a g e

    Refurbished Hoist

    The hoist to be commissioned at the SX was installed as a senior capstone project in 2008. The

    hoist and original AC drive were donated from the Silver Valley Mining District of Idaho. A

    comparable DC drive motor and 6:2 planetary gear reducer were donated by The National

    Institute of Occupational Safety and Health (NIOSH). Additionally, US Gypsum provided the

    electrical distribution consoles and the Program Language Controller (PLC). Prior to installation,

    the 2008 senior team designed and poured a hoist foundation with a safety factor of 11. During

    this time, the hoist components were remachined, while new drum bearings were installed, the

    planetary gear reducer and the DC motor were attached to the hoist base, and an emergency

    break operated by air pressure was mounted to the hoist. A SafeHoist system and a Lily

    Simplex controller with location indicator were attached to the hoist and PLC for future

    automation of the hoist. In addition to the hoist, a 5/8 inch, 18 strand cable rope was

    purchased. It is important to note that MSHA requires all hoisting components to meet a

    minimum safety factor of 7 for hoisting miners. Although the shaft is currently dedicated to

    production, the system exceeds the requirements and would be capable of hoisting people in

    the future.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    14/103

    8 | P a g e

    Figure 4: Refurbished Hoist

    Usage

    The hoist at the SX is dedicated purely to

    materials handling. As students spend weekly

    shifts at the mine drilling, blasting, and

    mucking, they rely on an operator to hoist the

    muck to the surface for dumping. Each level

    maintains two ore carts, each weighing 1.6

    tons when loaded. Other items commonly

    hoisted include jack-leg drills, drill steels, rail,

    booster fans, air and water lines, and

    miscellaneous tools. Without the hoist and a

    sufficient operator, advancement underground would not be possible at the mine.

    Figure 5: Student Mucking Underground

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    15/103

    9 | P a g e

    Communication

    At the SX, a miners undergroundphone system and a bell system for signaling the hoist

    operator are the only means of communications between underground personnel and hoisting

    operator or engineers. Shaft bells are used as a method of communication between the hoist

    engineer and personnel operating the cages and does not require use of the phone if

    communications have been made clearly and with complete comprehension. The moving

    location of the skip is unavailable and notification of delivery to desired location is made

    through the use of the bell system.

    Although this works very sufficiently, a need for improvement was recognized as latency occurs

    during this communication and the resulting stop or go signal if altered by the attention of the

    operator running the current air-tugger system. Adding to the latency of system operation, the

    existing operating station is located away from and inside the hoist house. The essential

    feature in any signaling system is that the signals be fully understood by both the engineer and

    the bell ringer. Any person authorized to use shaft bells must realize that complete and

    thorough cooperation is required between the bell ringer and the hoist engineer. If at any time

    a signal is misunderstood or understood fully, the operator shall make contact via the phone

    system prior to moving the skip. Mine operators must set the brake on the air tugger and walk

    to the mine phone system to achieve communications currently. A secondary visual alarm

    system has been added to the traditional bell system, because at times the ambient noise of

    the air compressor and operating the air-tugger makes hearing the bell almost impossible. The

    potential for missing either bell rings or light alarm signals exist while operating the system.

    During these circumstances, it is imperative the operator of the hoist make contact with the

    requesting bell ringer to ensure accurate and complete communications were made. After

    receiving confirmation, the hoist operator could return to the air-tugger and make the

    requested skip movements. Once fully commissioned, the mine phone will be located next to

    the indoor operation station and will eliminate much of the time lag currently occurring.

    Position location of the skip will be made available via a physical location depth gauge and level

    indicator, and visual display through the RopeRanger hoisting graphical user interface (GUI).

    Electric switches will be located at collar locations to identify skip location and to provide motor

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    16/103

    10 | P a g e

    control commands. A touch screen display will provide location of the skip as well as numerous

    other hoist monitoring functions.

    San Xavier Hoisting Emergency Procedures

    Currently, the only emergency hoisting procedure identified for an operator of the hoist or forrequesting mine operations personnel, is a 7-Bellemergency alarm signal. Upon the

    identification of a hazard, potential hazard, or accident during hoisting operations, mine

    personnel must ring the bell seven times in succession. The hoist operator should immediately

    set the break on the air-tugger halting all further movement of the skip, proceed to the Mine

    Phone System and ascertain further information. The existing air tugger system has a single

    brake that can be applied while the newly refurbished system will have multiple brakes upon

    completion of the installation.

    In total, three braking systems are available for normal and emergency operations. A manual

    hand assist brake, a fail-safe air/electric dual caliber brake, and the Lily Overspeed Controller.

    The Lilly Overspeed Controller will serve as the operating braking system and is controlled via

    the SafeHoist operating control panel or via an emergency stop push button. The manual

    hand assist braking lever shall only be used in the event of complete failure to either the air

    brake or the Lily Overspeed Controller. Its primary function is to be a parking brake and is to be

    engaged when the skip is to remain at a set location for extended time periods. The newly

    installed hoist now has a fail-safe air brake installed on the drum and will be the primary

    braking component during an emergency. The primary brake is pneumatically and

    electronically controlled. During the event of either a power loss to the motor, a loss of air in

    the compressed lines, or from a general all stop called for by an operator during emergency

    shut down scenarios, a dual caliber brake pad will cease movement of the drum. In the event

    of over-travel, protection to the hoist and skip will be provided by an electric switch installed on

    the head frame and at defined stations in the shaft.

    Once the system is complete, all controls for the hoist operation including shaft location

    dispatch will occur via the SafeHoist operator station controller. Until this work has been

    completed, a manual operation mode is also available for use during hoisting events and can be

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    17/103

    11 | P a g e

    engaged for raising and lowering of the skip. Controls for manual operation are located on the

    controller station panel display. Braking during manual operation is achieved by the

    engagement of the caliper brake pads via the all stop emergency button. Speed of the hoist

    must be monitored closely by an authorized user and special attention must be paid to

    eliminate overpowering of the brake. To perform manual movement operations, the SafeHoist

    control panel, motor controller, and main power supply to the hoist must be energized.

    RopeRanger Autonomous System

    The RopeRanger hoist monitoring system is

    a start of the art multi-sensor monitoring system

    used to track critical operational and safety

    components during mine hoisting. Monitoring is

    obtained real time and can be displayed on a touch

    screen operator SafeHoist display and control

    station. The system is self contained and

    environmentally protected against dust and

    contamination during use. It uses a 16 bit analog to digital converter while monitoring rope

    tension, vibration, acceleration, speed, slack, overload and over-distance parameters. To ease

    requirements for installation, the system utilizes wireless radios as to not interfere with existing

    wire rope hardware and equipment. The RopeRanger system monitors tension sensitivity to

    approximately 0.001% and is well suited for the 5/8 inch cable installed on the refurbished hoist

    and drum assembly.

    Rope

    The 5/8 inch, 18 cable rope purchased by the San Xavier mine

    must be wound by a licensed hoisting engineer. As shown in

    Figure 7, the placement of the hoist drum was located to

    maintain a rope fleet angle less than 1.5 degrees. The current

    setup utilizes a 1.3 degree fleet angle to the sheave wheel.

    This design factor is important in maintaining the integrity of Figure 7: Fleet Angle

    Figure 6: RopeRanger Monitoring Screen

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    18/103

    12 | P a g e

    the drum throughout its operating life. Angles exceeding 1.5 degrees can cause premature wear

    and will not utilize the full length of the drum. This new rope has a capacity of 22.5 tons and a

    safety factor of 8. All other design factors are shown in Table 1.

    Table 1: Rope Specifications

    Dead windings 10

    Max fleet angle 1.5 degrees

    Length 432.3 feet

    Minimum strength 40868.1 Lb

    Max diameter 5/8 in

    Lays/drum width 38.4

    Length/wrap 5.9 ft

    Layers 1.5

    Max tension 5108.5 Lb

    Rope angle from horizontal 73.0 degrees

    Cameras

    A series of Intec wide angle cameras will be installed in the shaft for skip monitoring

    capabilities. The cameras have multiple sealed injection cast alloy enclosures and use a Mil-

    spec connector to eliminate potential shorting caused in the event of water exposure in the

    shaft. There are enough units to place one camera at the collar and a unit at each of the lower

    level shaft stations at the 100 foot and 150 foot levels. The hoist operator will now have the

    capability to adjust skip position to ensure an appropriate loading platform based upon

    visibility. A BARCO multiple I/O port CPU and touch screen display will allow the operator of

    the hoist to have multiple views simultaneously or to have a single isolated but larger screen

    when necessary. Installation of the cameras will occur after the limit switches for hoist

    operation have been installed. CCT & Associates are providing technical expertise for the

    installation of the touch screen CPU and for potential integration with the hoist operator

    monitoring station.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    19/103

    13 | P a g e

    Figure 8: Intec Wide Angle Camera and Features

    Utilities

    Power is supplied to the hoist house via an underground duct bank and terminated in panels

    located in the hoist control room. As a result of previous investigations into the connected

    versus demand load schedules of supplied power feed and utilization at the SX,

    recommendations have been made to upgrade the system in total capacity. It is also

    recommended that careful consideration be paid to live current demand when starting motors

    at the SX, as a potential for overdraw may exist.

    Currently, the mine is supplied with a 200A 3 Phase power feed source; however, it is rated for

    400A according to Trico Power. In recent years this system was evaluated by other project

    teams. A proposal for ideal power supply was made based upon the following calculations from

    recommended electrical feed. An electrical engineer has determined the installation of the

    electrical feed sources to the main control panels and PLC cabinets have been installedcorrectly, however, verification of this conclusion could not be ascertained by this project team.

    As a result, Stantec Engineering will provide an electrical engineer to perform a job site audit to

    ensure there are no hazards to staff and personnel working in the hoist house and hoist control

    room. The electrical engineer will also determine the demand versus connected load. These

    determinations will ensure the existing power system is capable of handling the startup and

    safe operation of the rebuilt hoist.

    Schedule

    The time table for this project has been an integral part of moving the project forward. While

    scheduling setbacks have occurred, reporting and presentation deadlines have remained

    unchanged. The project has progressed over an academic year, so the project time table was

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    20/103

    14 | P a g e

    split into two semester schedules. Very little work was completed in the break between the

    semesters, due to conflicting personal schedules. The semester time tables can be found in

    Appendix A. While work on preparation for the physical implementation of the project has been

    mentioned in the schedule, the time table of the physical implementation has been developed

    to be independent of the academic schedule.

    Fall Schedule

    The fall work schedule was used for some parts of the project, but unexpected events caused

    problems in completing some of the items on schedule. Additionally, some of the items on the

    schedule were not completed due to changes in how the physical implementation would occur.

    Changes to the schedule were driven by clarifications in the scope and changes in applicable

    Stantec personnel. For administrative reasons, the scope changed from design and

    implementation to designing an implementation plan to be executed when time permitted. This

    change was due in part to Stantecs loss of Clyde Peppin, the former project mentor. The loss of

    Mr. Peppin caused issues with coordination and communication with Stantec representatives,

    delaying the implementation process. As a result of those unexpected events, no items

    associated with system verification or physical implementation occurred in the fall. Despite

    changes to the implementation and design items of the schedule, the project reports and

    presentations were able to continue as planned. Initial project outlines and proposals were

    completed on schedule, but were later revised as the project scope was clarified. Resource

    requirements were defined, allowing for a budget to be created. The resource requirements

    remained largely unchanged, but the budget was revised as the roles of the various groups

    involved were redefined.

    Spring Schedule

    Changes in the fall schedule led to the need for revisions in the spring schedule.

    Implementation of the project was moved to spring, pending full administrative approval for

    the execution of the project. Dates for implementation are included in the spring schedule, but

    have been delayed and are subject to further change pending complete final approval. Due to

    the revised scope of the project, only one direct meeting with the new main project consultant,

    Ed Thomas, was necessary. Ongoing telecommunication was used as necessary instead of direct

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    21/103

    15 | P a g e

    meetings due to a revised and limited scope on the part of Stantec and the fact that Stantec

    engineers are located in Phoenix, Arizona. Unlike the variability in timing available for

    implementation, reports and presentation elements are to be completed on schedule.

    Implementation Schedule

    The implementation schedule has been developed to be separable from the academic schedule

    due to administrative uncertainty and uncertainty with outside vendor representative

    availability. Representative availability is a severely limiting factor in the implementation

    process, so the implementation process has been divided into an order of events that must take

    place to complete the project. This order of events is shown in Table 2. It is important to note

    that the camera implementation process is separate from the hoist implementation process.

    Table 2: Implementation Order

    Description Order Groups Involved

    Hoist Implementation

    Electrical review 1 Stantec

    Hoisting calculations 2 Stantec, Design Team

    Engineering review 3 Stantec

    Hoist rope change out 4 Stantec, Design Team

    Software implementation 5 SafeHoist, Design Team

    Operating manual

    documentation

    6 Design Team

    Camera Implementation

    Placement design 1 Design Team

    Wiring and installation 2 Design Team

    System setup and software

    implementation

    3 CCT & Associates,

    Design Team

    Having an implementation order instead of a dated schedule is of great benefit for this project.

    Due to the small budget of the project when compared to large commercial mines and the fact

    that time spent is an in-kind donation by a University partner, the outside company

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    22/103

    16 | P a g e

    representatives will likely be working on this project only in their spare time. Work will likely

    commence on weekends when the groups involved are available, meaning the implementation

    will occur in fragments over an extended period of time.

    Budget

    Hoist Upgrade Costs

    Prior to the completion of this hoist upgrade project, other hoist improvement projects have

    commenced to that have lead to the final commissioning of the refurbished hoisting system.

    Necessary previous projects have included construction of a hoist mounting base, rewiring the

    hoist room to accommodate a large hoist motor, and refurbishing and installing the hoist used

    in the proposed project. The cost for the rewire project is not included in the report for that

    project, therefore the cost for that piece of the overall project is unknown. However, the costs

    for the 2008 San Xavier Hoist Upgrade project are known. These costs should be considered

    when considering the overall costs sunk into the overarching hoisting system upgrade. The

    costs for the 2008 San Xavier Hoist Upgrade project are shown in Table 3.

    Table 3Project Costs

    Item Cost

    Machine Work $9,000

    Epoxy $120

    Bolts $140 (Shipping, Bolts donated)

    Wire Rope $1,200

    Electrical $800

    Grease $150

    Gantry Crane $700

    Miscellaneous Equipment Rental $400

    Total $12,510

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    23/103

    17 | P a g e

    Commissioning Costs

    Project cost is an important piece in overall project management progression, so a cost

    schedule has been developed for the hoist upgrade. This cost schedule has been developed on

    an all-inclusive basis, taking into account all known major costs from initiation to completion of

    the hoist upgrade process.

    The project includes coordinating with three major outside sources and winding the hoist rope.

    Outside sources consulted in this project include Stantec Consulting Services, who provide

    engineering consulting services, SafeHoist, the manufacturers of the hoist controller system,

    and CCT & Associates, a solutions consulting group familiar with the camera functionality and

    construction. A generalized breakdown of the project costs is listed in Table 4. A full breakdown

    of the associated costs can be found in Appendix A.

    Table 4General Costs

    Description Cost

    Stantec

    Project Management, Controls $1,353

    Site Visit $4,364

    Historical Document Review $1,361

    Electrical Design Review $1,913

    UA Report Review $308

    Miscellaneous Fees $3,901

    SafeHoist

    Site Visit $700

    CCT & Associates

    Site Visit $1,000

    Equipment

    Rope Attachments $500

    Camera Installation Equipment $500

    Total $15,900

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    24/103

    18 | P a g e

    The majority of the costs are associated with consultation with the outside sources, but there

    are some equipment costs as well. Costs associated with Stantec are primarily for engineering

    services to oversee hoist implementation and verify calculations associated with the hoist

    system. The costs associated with SafeHoist are for a company representative to visit the hoist

    and assist with the SafeHoist RopeRanger system setup and implementation. Similarly,

    representatives of CCT & Associates will need to visit the SX as well to assist in the setup and

    installation of the camera system and potential integration with SafeHoist operating systems.

    Cost estimates for the CCT and SafeHoist representatives are for flights and hotels only; time

    spent working on the project by these representatives will be an in-kind donation. Additional

    costs will be associated with winding the hoist rope and the camera installation. The hoist rope

    equipment and camera equipment costs have been roughly estimated, but are unlikely to

    exceed the costs listed. Costs for winding the rope include the purchase of cable clamps,

    thimble, clevis, and safety latch devices.

    Considering all the elements of the implementation plan, the estimated cost to complete the

    project is $15,900. Financing for the project will be from the University of Arizona Mining

    Department budget as funded by the Science Foundation Arizona program. This cost estimate is

    lower than the actual value, due to in-kind and other donations by the outside sources

    involved. SafeHoist and CCT & Associates are giving in-kind donations by sending

    representatives to assist with their respective systems. Services provided by Stantec will not be

    donated, but Stantecs cost estimate does include a fifteen percent preferred customer

    discount.

    Design

    Risk AssessmentPrior to project initialization, a Job Safety Analysis was performed on February 12, 2011 to

    ensure the teams awareness of all safety hazards present at the San Xavier Mine. This item is

    included in the appendix for further reference.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    25/103

    19 | P a g e

    During the completion of this analysis, both behavioral and hazard checks were made. An

    examination of the required documentation and Lock Out/Tag Out/Try Out (LOTOTO)

    procedure was completed during this analysis. Also, emergency equipment, such as fire

    extinguisher and eyewash station, was located. Several factors were incorporated into the

    behavioral analysis. These include positioning all personnel away from moving objects,

    ensuring visibility in the area, establishing that no lifting will be required, and making certain

    that communication during the project will be properly coordinated. An overview of Personal

    Protective Equipment (PPE) that must be worn while in the mining laboratory was discussed.

    On the other hand, a hazard check was comprised of identifying other concurrent jobs on-site,

    weather issues, and proper lifting equipment, as well as a number of other hazard inspections.

    Additionally, a hoist risk analysis was performed in order to assess any risks that could affect

    personnel involved in the project. Hazards within the project can affect the maintenance,

    construction, and operation of the equipment.

    Both mechanical and electrical problems can disrupt the maintenance of the hoisting system.

    Many critical tasks exist for reducing these risks. For example, the hoist, sheaves, and rope all

    possess the potential for the following mechanical problems. In order to minimize any

    potential risks, suspended loads, sources of energy, rotating equipment, and pinch points need

    to be identified. Also, other dangers may arise mechanically, in the form of slips, trips, falls,

    falls from a height, noise exposure, chemical exposure, falling objects, lack of ventilation,

    moving equipment, and flammable substances. In addition to the previously listed risks,

    conveyances from the haulage level also includes the possibility of falls from a height in the

    shaft, falling rocks in the excavation, and falling items in the shaft. In order to minimize the last

    hazard, fall protection should be in place above and below the station.

    Electrical maintenance problems may arise through the main power, main drive, control power

    and voltage, safety interlocks, and compensation sheaves. Issues with the main power can be

    identified as originating from any sources of energy, suspended loads, pinch points, slips, trips,

    and falls, falling objects, and falls from heights, as well as noise and chemical exposure.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    26/103

    20 | P a g e

    Flammable substances, moving equipment, lack of communication, lack of ventilation, security,

    and arch flashes are also included in these possible sources of danger.

    Hoisting hazards can also impact the construction during the project. Mechanical and electrical

    risks include suspended and moving heavy or large loads, sources of energy, rotating

    equipment, pinch points, slips, trips, and falls, and falls from heights. In addition, any chemical

    exposure, noise exposure, flammable substances, lack of ventilation, falling objects, and mobile

    equipment may pose a problem. Finally, workers lacking task-specific skills can affect the

    construction that will take place on the hoisting system. Civil hazards consist of the prior issues,

    as well as any excavation blasting in the foundation.

    Finally, this project may impact the operation of the system. In order to mitigate any hazards

    that will affect the operation of the hoist, several resources can be provided on site. Adequate

    emergency planning, proper guards on moving equipment, as well as sufficient transportation

    for personnel, material, and equipment can minimize any hazards. Also, environmental risks

    and ergonomics must be taken into consideration. The design team should ensure that proper

    access is available for all equipment and personnel in the working areas.

    Opportunities and Challenges

    This project has required a solid project management plan to ensure timelines are met and the

    project reaches completion by May 2011. It commenced with the knowledge that several risks

    would be present. These risks have evolved into challenges over the course of the project

    timeline.

    Primarily, an unexpected setback occurred during the latter part of January. The project teams

    original mentor, Clyde Peppin, left Stantec to pursue opportunities elsewhere. As a result,

    Edward Thomas (also from Stantec) became the new Project Manager. Mr. Thomas knowledge

    of the hoisting upgrade project was limited at the time. This required him to take time to read

    the teams project proposal, as well as find time to travel out to the project site.

    In addition, a risk to the completion date has been identified as consultant availability and

    engineering support. While the project has an established budget, much of the effort devoted

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    27/103

    21 | P a g e

    to this project comes in the form of donated time and services. All three previously mentioned

    external resource requirements have been or are donating time to the project with an

    understood agreement of availability to perform. For example, Mr. Thomas is involved in other

    various projects for Stantec, which has required him to fit the UA project into his schedule.

    Since his office is located in Phoenix, Arizona, it was difficult for him to find time to travel down

    to make a preliminary site visit to the San Xavier Mine. This conflict with time resulted in a

    delay in Stantec drafting a project proposal for Mr. Ros Hill, the Director of San Xavier Mining,

    to approve. This delay in Stantecs work has consequently postponed SafeHoists visit to the

    San Xavier Mine. SafeHoist is unable to install their equipment until the rope is wound on the

    hoist drum.

    Additionally, time commitment for student team members has proved to be a challenge. Since

    all four members are enrolled in their final year of their undergraduate career, it has been

    difficult to fit meetings into their schedules. The members have commitments with work and

    school, and two hold leadership positions at the San Xavier Mine. These demanding schedules

    have created difficulties in the organization of team meetings and site visits. Also, as of

    December 2010, the academic schedules of the team changed, in accordance with the

    Universitys policies. This created further problems when attempting to find agreement among

    their schedules. In order to complete the required work by the project deadline, a project

    management plan was developed by the team of students. This plan has allowed for some

    deviation to the proposed schedule.

    During the engineering analysis of existing and proposed hardware, details for compatibility

    and capacity will either show compliance or the need for further infrastructure development.

    Due to the postponement of many of the projects phases, it has been determined that the

    project management plan will be passed on to other students in May 2011, in order that the

    project can be completed in the fall semester of 2011.

    Just as there are risks that may cause delays, there are also opportunities to expedite the

    project in the future. With the involvement of vendors that are engineering professionals as

    well as product suppliers, projections for time commitments and for necessary resource

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    28/103

    22 | P a g e

    involvement may become reduced. Stantec engineers are well versed in safe hoisting

    techniques and will recognize potential pitfalls, unidentified by the student team. SafeHoist

    professionals have installed similar systems globally and could sufficiently reduce the time

    requirements for installation. Experts may also recommend colleagues from their past

    experiences to assist with the San Xavier Hoist Upgrade Project. One of the positive outcomes

    from our change in mentor is that Mr. Thomas is a University of Arizona graduate. As a student

    working at the San Xavier Mine, he helped construct the headframe. This has proved to be an

    asset, as far as knowledge and time is concerned, since Mr. Thomas is aware of the background

    of the mining laboratory.

    Another opportunity for success came in the form of donations to the Mining and Geological

    Engineering Department. Time, effort, and equipment have already been donated to the San

    Xavier mine to enhance the hands-on learning environment. Additional hardware and time

    commitments donated to the mine could decrease the amount of external and internal

    resources required for successful project completion.

    Hoisting calculations

    The San Xavier Mine has attempted to upgrade its hoisting system since 1978 when the current

    headframe was erected. Since then, multiple hoisting calculations have been conducted to find

    an optimum solution in ore handling. The unique situation encountered in 2008 was the

    inability to choose the perfect hoist, but instead to optimize the hoist donated to the mine.

    Using all calculations with current knowledge enabled the team to accurately confirm or

    recalculate the necessary information pertaining to this hoist. Pertinent information regarding

    the hoist can be found in Table 5. All correct calculations performed within the last ten years

    are available in Appendix G. Through the research and calculations performed by this team, all

    components of the hoisting system exceed the minimum factor of safety of 7 set forth by

    MSHA.

    Table 5Hoist Specifications

    Hoist Type Single Drum

    Hoist Drum 22.5 in. Diameter

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    29/103

    23 | P a g e

    Hoist Gear 48.0 in. Diameter

    Drum Width 24 In.

    Drive Gear 4.0 in. Diameter

    Dist to sheave H 46.5 Ft.

    Dist to sheave V 40.1 Ft.

    Lifting on Hoist 4885.4 Lb.Drum RPM 17.0 rpm

    Implementation

    Once all contracts have been signed and authorization from the University of Arizona

    Contracting Services has been given, actual physical implementation of the hoist improvement

    project will occur. Primarily, a safety audit and electrical review will be conducted by a small

    group of engineers from Stantec. Upon completion of these mandatory items, they willsupervise the student project team in winding the newly purchased rope on the hoist drum,

    safely and securely. Subsequently, Mr. Mike Beus from SafeHoist Inc. will install the

    RopeRanger and Lily Simplex Controller systems. He will also aid in the removal of the current

    hoisting components. Ultimately, volunteers at the student mine will install the cameras along

    the shaft, as well as the monitoring system. A representative from CCT & Associates will be

    required in order to program the system and integrate the cameras with the CPU.

    San Xavier Hoist Operating Hardware Manual

    Accompanying this report is an operating manual for the combined components of the

    SafeHoist and RopeRanger operating systems. This manual is tailored specifically for the San

    Xavier Hoist and will serve as a training guide outlining the safe operating procedures.

    Future Work

    This project advances the functionality of the hoist greatly, but further work could improve the

    functionality of the hoist. These improvements are beyond the scope of this project, but further

    projects could bring the hoist systems abilities forward.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    30/103

    24 | P a g e

    One goal for the hoist system is to become man-rated. Man-rating the hoist would involve two

    major projects, re-lining the shaft with non-flammable materials, and changing out the skip for

    a man-rated cage. The existing cribbing and guide rails for the skip are all wooden, but law

    dictates that shaft lining and guide rails in a man shaft are non-flammable. Another project that

    would be required before man-rating is installation of a man cage. The current skip does not

    have a surrounding cage, and is not man-rated. To prepare the hoist system for man-rating,

    future work would include re-lining the shaft with steel cribbing and installing a steel man cage.

    Another goal for the hoist system is to eventually service the entire shaft. Due to problems on

    the 250 foot level, the serviced shaft stations only include the 100 foot and 150 foot levels. This

    project allows the hoist to reach the 250 level, but the condition of that level is not fully

    understood. In order to reach the 250 level, inspection and rehabilitation of the shaft between

    the 150 and 250 levels would be required. Additionally, the shaft station would need to be

    rehabilitated and have communications extended to that level.

    As far as this shaft is concerned, the future projects listed would essentially complete the

    functionality of the hoist. The future work mentioned would allow the hoist to carry any normal

    load, human or otherwise, and hoist along the entire length of the shaft. Absent sinking the

    shaft further or any other type of earthwork, the shaft would be advanced to its maximum

    functionality.

    Conclusion

    The San Xavier Hoist Improvement project, proposed by Team SevenStephenie Mirka, Scott

    Shields, Dana Specht, and Andrew Swazey, was a tremendous learning experience. The project

    quickly evolved from what we initially perceived to be an engineering design assignment to

    what was really a project management learning experience. Throughout the two semester

    terms, our mentors Mr. John Fenn and Mr. David Naccarati continually reminded us our

    ultimate goal is to manage our work such that if an immediate need to pass on responsibilities

    for completion of the project occurred, another qualified team could resume work and

    successfully finish the job.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    31/103

    25 | P a g e

    A major change to our project was the deviation from an engineering design to commissioning.

    Initial perspectives of the work was that our team would be required to investigate current

    hoisting conditions, calculate hoist and load parameters, and implement changes as required.

    Although this is true in respects, we quickly realized much forethought and work to accomplish

    these goals had already culminated.

    Much of the time we spent developing this project was investigating what had been done

    before we assumed responsibility for completing the hoist improvements. Other work crews in

    years passed had culminated their design projects by completing not only technical reports, but

    also providing a product. Unfortunately, the data and the respective final reports were not

    stored in locations available to our team. Many hours were spent tracking down data from the

    past 30 years that are essential for the completion of our specific goals. Not only would our

    investigations require tracking down this information on site at the SX Laboratory and the

    University of Arizona Mining and Geological Engineering Department, our search spanned to

    Idaho, Nevada, Montana, California, and Washington. The resulting finds of material were

    astounding in that Team Seven realized our project was beginning a transition from design to

    commission.

    A major challenge to this project has been the continual timeline setbacks as a result of

    commitment and coordination with consulting engineers. Although design work for the hoist

    change-out had already been completed by students, this information had to be transferred to

    professionals and reviewed for safety. The cause for delay throughout the past seven months

    has been a unique series of events including a change in mentor, waiting time for the right

    person to be available when needed, and the extended wait while project proposals are

    reviewed, revised, and ultimately approved. Once completed, the potential contract then had

    to be processed through the University of Arizona Contracting Services group. At this time we

    are still waiting for a signed contract to be delivered so that the design work can be completed

    safely and efficiently. In addition, commitments to perform much of the outside consulting

    work under in-kind donations places our priority below money making jobs. As an industry

    partner and a friend to the University, these companies are doing as much as possible to help.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    32/103

    26 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    33/103

    27 | P a g e

    References

    Birbeck, Scott, Philip Requadt, and Erron Winsor. SX Hoist Upgrade: Replacing the Hoist at the

    San Xavier Student Mine and Research Laboratory. Rep. 2008. Print.Brokenshire, Peter, and Susan Andersen, eds. Hoist and Haul 2010 Proceedings of the

    International Conference on Hoisting and Hauling.Littleton: Society for Mining

    Metallurgy, 2010. Print.

    Code of Federal Regulations, Mineral Resources, National Archives and Records Administration

    30 (1997). Print.

    "Crosby Clips: Warnings and Application Instructions for Wire Ropes." 2008. The Crosby Group,

    Inc.Featherston, John, Steven Bastian, and Tim George. The San Xavier Re-Wire Project. Rep. 2006.

    Print.

    Featherston, John. The San Xavier Re-Wire Project. Rep. 2005. Print.

    Hartman, Howard L., ed. SME Mining Engineering Handbook. 2nd ed. Vol. 2. Littleton: Society

    for Mining, Metallurgy, and Exploration, 1992. Print.

    Peppin, Clyde. "Hoist Risk Review Notes." 1 Oct. 2010. E-mail.

    Phelps Dodge Corporation, Copper Queen Branch, Mechanical Department. Code of Safe

    Practice for Hoist Engineers(1969). Print.

    San Xavier Mining Laboratory. SX Safety Manual. The University of Arizona.

    Walker, Jr., W. Dan, and R. W. Stahl. "Recommended Procedures for Mine Hoist and Shaft

    Installation, Inspection, and Maintenance." Bureau of Mines Information Circular8031

    (1961). Print.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    34/103

    28 | P a g e

    Appendix A - San Xavier Mine Operating Procedures

    Safe Hoist Operating Procedures

    1. Only authorized persons shall be in hoist rooms or hoist cabs.

    2. Personnel shall not ride loaded skip decks, cage decks, or buckets with muck, supplies,materials, or tools other than small hand tools.

    3. When a manually operated hoist is used, a qualified hoist operator shall remain within

    hearing of the telephone or signal device at all times while any person dependent on

    that hoist is in the mine.

    4. Only experienced hoist operators shall operate a hoist except in case of emergency and

    when new operators are being trained.

    5. When personnel are hoisted in buckets, rope speed shall not exceed 500 ft/min andshall not exceed 200 ft/min when approaching the intended station or stopping point.

    ***Note: The hoistman shall respond to call signals for a cage, before presenting the cage to a

    person on a level. Until the hoistman has responded to a signal, thereby acknowledging the

    receipt of that signal, no person will attempt to signal on the shaft bell system, nor shall any

    person attempt to load a cage until the hoistman has acknowledged the receipt on the

    squawker.

    Hoist Bell Signals - Hoist Operators Guide

    Cage Position Adjustment Signals:

    Slow Bells Mean Move Cage Slowly

    1 Bell - Stop Immediately

    2 Bells - Lower Cage

    3 Bells - Raise Cage

    General Communication Signals:

    5 Bells - Turn Air On/Off

    7 Bells - Go to Mine Phone Immediately - Possible Emergency

    Surface Cage Dispatching Signals:

    1 Long Bell + 1 Bell + 1 Bell - Send Cage to Shaft Collar

    1 Long Bell + 1 Bell + 2 Bells - Send Cage to 100 Level

    1 Long Bell + 1 Bell + 3 Bells - Send Cage to 150 Level

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    35/103

    29 | P a g e

    1 Long Bell + 1 Bell + 4 Bells - Cage Released from Collar

    100 Level Cage Dispatching Signals:

    1 Long Bell + 2 Bells + 1 Bell - Send Cage to Shaft Collar

    1 Long Bell + 2 Bells + 2 Bells - Send Cage to 100 Level1 Long Bell + 2 Bells + 3 Bells - Send Cage to 150 Level

    1 Long Bell + 2 Bells + 4 Bells - Cage Released from 100 Level

    150 Level Cage Dispatching Signals:

    1 Long Bell + 3 Bells + 1 Bell - Send Cage to Shaft Collar

    1 Long Bell + 3 Bells + 2 Bells - Send Cage to 100 Level

    1 Long Bell + 3 Bells + 3 Bells - Send Cage to 150 Level

    1 Long Bell + 3 Bells + 4 Bells - Cage Released from 150 Level

    ***Note: Hoist Operator will not move cage unless all bell signals are understood and a signal

    has been received from both the sending and receiving shaft stations.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    36/103

    30 | P a g e

    Appendix B - Existing and Proposed Electrical Loads

    Existing Electrical Capacities:

    Entire Property 480V, 3, 200A

    Hoist House 480V, 3, 100A

    Surface Substation 480V, 3, 100A

    Existing Electrical Loads:

    Hoist House

    Operation Volts (V) Phase () Full Load Amperage (A)

    Welder 480 3 Rated 50A

    Grinder 110/120 1 15

    Drill Press 110/120 1 15

    Band Saw 110/120 1 5

    Cap Lamp Chargers 220/240 1 30

    General Receptacles 110/120 1 Rated 60A (20A X 3 circuits)

    General Lighting 110/120 1 Rated 15A

    Underground Circuit 110/120 1 Rated 20A

    (Bells, Lighting, Outlets)

    Security Light 110/120 1 15

    Radio 110/120 1 1

    Total Full Load Amps 131

    Surface Substation

    Operation Volts (V) Phase () Full Load Amperage (A)

    100' & 150' Ventilation 480 3 15

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    37/103

    31 | P a g e

    Adit Level Ventilation 480 3 15

    100' Level 3 Electrical 480 3 15

    Adit Level Electrical 480 3 15

    Total Full Load Amps 60

    Existing Total Full Load Amps (Entire Property) 191

    Proposed Electrical (Rating) Amperages:

    Operation Volts (V) Phase () Full Load Amperage (A)

    Change Room / Office 480 3 200

    Electric Compressor 480 3 125

    Decline Ventilation Fan 480 3 125

    Adit Level 480 3 60

    100' Level 480 3 60

    150' Level 480 3 60

    Hoisting System 480 3 125

    Total Proposed (Rating) Amperage 755

    453

    (Figure on 60% of full load at any given time)

    Total Needed Electrical Capacity 567.6 600A

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    38/103

    32 | P a g e

    Appendix C - Schedule and Budget

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    39/103

    33 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    40/103

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    41/103

    35 | P a g e

    Appendix D - Risk Analysis

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    42/103

    36 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    43/103

    37 | P a g e

    Appendix E - Applicable MSHA Regulations

    30 CFR 57.16011 - Riding hoisted loads or on the hoist hook.

    Persons shall not ride on loads being moved by cranes or derricks, nor shall they ride the

    hoisting hooks unless such method eliminates a greater hazard.

    30 CFR 57.16017 - Hoisting heavy equipment or material.

    Where the stretching or contraction of a hoist rope could create a hazard, chairs or other

    suitable blocking shall be used to support conveyances at shaft landings before heavy

    equipment or material is loaded or unloaded.

    30 CFR 57.19000 - Application.

    (a) The hoisting standards in this subpart apply to those hoists and appurtenances used for

    hoisting persons. However, where persons may be endangered by hoists and appurtenances

    used solely for handling ore, rock, and materials, the appropriate standards should be applied.

    (b) Standards 57.19021 through 57.19028 shall apply to wire ropes in service used to hoist--(1) Persons in shafts and slopes underground;

    (2) Persons with an incline hoist on the surface; or

    (3) Loads in shaft or slope development when persons work below suspended loads.

    (4) These standards do not apply to wire ropes used for elevators.

    (c) Emergency hoisting facilities should conform to the extent possible to safety requirements

    for other hoists, and should be adequate to remove the persons from the mine with a minimum

    of delay.

    30 CFR 57.19001 - Rated capacities.

    Hoists shall have rated capacities consistent with the loads handled and the recommended

    safety factors of the ropes used.

    30 CFR 57.19002 - Anchoring.

    Hoists shall be anchored securely.

    30 CFR 57.19003 - Driving mechanism connections.

    Belt, rope, or chains shall not be used to connect driving mechanisms to man hoists.

    30 CFR 57.19004 - Brakes.

    Any hoist used to hoist persons shall be equipped with a brake or brakes which shall be capableof holding its fully loaded cage, skip, or bucket at any point in the shaft

    30 CFR 57.19005 - Locking mechanism for clutch.

    The operating mechanism of the clutch of every man-hoist drum shall be provided with a

    locking mechanism, or interlocked electrically or mechanically with the brake to prevent

    accidental withdrawal of the clutch.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    44/103

    38 | P a g e

    30 CFR 57.19006 - Automatic hoist braking devices.

    Automatic hoists shall be provided with devices that automatically apply the brakes in the

    event of power failure.

    30 CFR 57.19007 - Overtravel and overspeed devices.

    All man hoists shall be provided with devices to prevent overtravel. When utilized in shafts

    exceeding 100 feet in depth, such hoists shall also be provided with overspeed devices.

    30 CFR 57.19008 - Friction hoist synchronizing mechanisms.

    Where creep or slip may alter the effective position of safety devices, friction hoists shall be

    equipped with synchronizing mechanisms that recalibrate the overtravel devices and position

    indicators.

    30 CFR 57.19009 - Position indicator.

    An accurate and reliable indicator of the position of the cage, skip, bucket, or cars in the shaft

    shall be provided.

    30 CFR 57.19010 - Location of hoist controls.

    Hoist controls shall be placed or housed so that the noise from machinery or other sources will

    not prevent hoistmen from hearing signals.

    30 CFR 57.19011 - Drum flanges.

    Flanges on drums shall extend radially a minimum of 4 inches or three rope diameters beyond

    the last wrap, whichever is the lesser.

    30 CFR 57.19012 - Grooved drums.Where grooved drums are used, the grooves shall be of suitable size and pitch for the ropes

    used.

    30 CFR 57.19014 - Friction hoist overtravel protection.

    In a friction hoist installation, tapered guides or other approved devices shall be installed above

    and below the limits of regular travel of the conveyance and arranged to prevent overtravel in

    the event of failure of other devices.

    30 CFR 57.19017 - Emergency braking for electric hoists.

    Each electric hoist shall be equipped with a manually-operable switch that will initiate

    emergency braking action to bring the conveyance and the counterbalance safely to rest. This

    switch shall be located within reach of the hoistman in case the manual controls of the hoist

    fail.

    30 CFR 57.19018 - Overtravel by-pass switches.

    When an overtravel by-pass switch is installed, the switch shall function so as to allow the

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    45/103

    39 | P a g e

    conveyance to be moved through the overtravel position when the switch is held in the closed

    position by the hoistman. The overtravel by-pass switch shall return automatically to the open

    position when released by the hoistman.

    30 CFR 57.19021 - Minimum rope strength.

    At installation, the nominal strength (manufacturer's published catalog strength) of wire ropes

    used for hoisting shall meet the minimum rope strength values obtained by the following

    formulas in which "L" equals the maximum suspended rope length in feet:

    (a) Winding drum ropes (all constructions, including rotation resistant).

    For rope lengths less than 3,000 feet: Minimum Value=Static Load x (7.0--0.001L)

    For rope lengths 3,000 feet or greater: Minimum Value=Static Load x 4.0.

    (b) Friction drum ropes.

    For rope lengths less than 4,000 feet: Minimum Value=Static Load x (7.0--0.0005L)

    For rope lengths 4,000 feet or greater: Minimum Value=Static Load x 5.0.

    (c) Tail ropes (balance ropes).

    Minimum Value=Weight of Rope x 7.0

    30 CFR 57.19022 - Initial measurement.

    After initial rope stretch but before visible wear occurs, the rope diameter of newly installed

    wire ropes shall be measured at least once in every third interval of active length and the

    measurements averaged to establish a baseline for subsequent measurements. A record of the

    measurements and the date shall be made by the person taking the measurements. This record

    shall be retained until the rope is retired from service.

    30 CFR 57.19023 - Examinations.

    (a) At least once every fourteen calendar days, each wire rope in service shall be visually

    examined along its entire active length for visible structural damage, corrosion, and improper

    lubrication or dressing. In addition, visual examination for wear and broken wires shall be made

    at stress points, including the area near attachments, where the rope rests on sheaves, where

    the rope leaves the drum, at drum crossovers, and at change-of-layer regions. When any visible

    condition that results in a reduction of rope strength is present, the affected portion of the

    rope shall be examined on a daily basis.

    (b) Before any person is hoisted with a newly installed wire rope or any wire rope that has not

    been examined in the previous fourteen calendar days, the wire rope shall be examined in

    accordance with paragraph (a) of this section.

    (c) At least once every six months, nondestructive tests shall be conducted of the active length

    of the rope, or rope diameter measurements shall be made--

    (c)(1) Wherever wear is evident;

    (c)(2) Where the hoist rope rests on sheaves at regular stopping points;

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    46/103

    40 | P a g e

    (c)(3) Where the hoist rope leaves the drum at regular stopping points; and

    (c)(4) At drum crossover and change-of-layer regions.

    (d) At the completion of each examination required by paragraph (a) of this section, the person

    making the examination shall certify, by signature and date, that the examination has been

    made. If any condition listed in paragraph (a) of this section is present, the person conductingthe examination shall make a record of the condition and the date. Certifications and records of

    examinations shall be retained for one year.

    (e) The person making the measurements or nondestructive tests as required by paragraph (c)

    of this section shall record the measurements or test results and the date. This record shall be

    retained until the rope is retired from service.

    30 CFR 57.19024 - Retirement criteria.

    Unless damage or deterioration is removed by cutoff, wire ropes shall be removed from service

    when any of the following conditions occurs:

    (a) The number of broken wires within a rope lay length, excluding filler wires, exceeds either--

    (a)(1) Five percent of the total number of wires; or

    (a)(2) Fifteen percent of the total number of wires within any strand.

    (b) On a regular lay rope, more than one broken wire in the valley between strands in one rope

    lay length.

    (c) A loss of more than one-third of the original diameter of the outer wires.

    (d) Rope deterioration from corrosion.

    (e) Distortion of the rope structure.

    (f) Heat damage from any source.

    (g) Diameter reduction due to wear that exceeds six percent of the baseline diametermeasurement.

    (h) Loss of more than ten percent of rope strength as determined by nondestructive testing.

    30 CFR 57.19025 - Load end attachments.

    (a) Wire rope shall be attached to the load by a method that develops at least 80 percent of the

    nominal strength of the rope.

    (b) Except for terminations where use of other materials is a design feature, zinc (spelter) shall

    be used for socketing wire ropes. Design feature means either the manufacturer's original

    design or a design approved by a registered professional engineer

    (c) Load end attachment methods using splices are prohibited.

    30 CFR 57.19026 - Drum end attachment.

    (a) For drum end attachment, wire rope shall be attached--

    (1) Securely by clips after making one full turn around the drum spoke;

    (2) Securely by clips after making one full turn around the shaft, if the drum is fixed to the shaft;

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    47/103

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    48/103

    42 | P a g e

    Man cages and skips used for hoisting or lowering employees or other persons in any vertical

    shaft or any incline shaft with an angle of inclination of forty-five degrees from the horizontal,

    shall be covered with a metal bonnet.

    30 CFR 57.19055 - Availability of hoist operator for manual hoists.

    HOISTING PROCEDURES

    When a manually operated hoist is used, a qualified hoistman shall remain within hearing of the

    telephone or signal device at all times while any person is underground.

    30 CFR 57.19056 - Availability of hoist operator for automatic hoists.

    When automatic hoisting is used, a competent operator of the hoist shall be readily available at

    or near the hoisting device while any person is underground.

    30 CFR 57.19057 - Hoist operator's physical fitness.

    No person shall operate a hoist unless within the preceding 12 months he has had a medical

    examination by a qualified, licensed physician who shall certify his fitness to perform this duty.

    Such certification shall be available at the mine.

    30 CFR 57.19058 - Experienced hoist operators.

    Only experienced hoistmen shall operate the hoist except in cases of emergency and in the

    training of new hoistmen.

    30 CFR 57.19061 - Maximum hoisting speeds.

    The safe speed for hoisting persons shall be determined for each shaft, and this speed shall not

    be exceeded. Persons shall not be hoisted at a speed faster than 2,500 feet per minute, except

    in an emergency.

    30 CFR 57.19062 - Maximum acceleration and deceleration.

    Maximum normal operating acceleration and deceleration shall not exceed 6 feet per second

    per second. During emergency braking, the deceleration shall not exceed 16 feet per second

    per second.

    30 CFR 57.19063 - Persons allowed in hoist room.

    Only authorized persons shall be in hoist rooms.

    30 CFR 57.19080 - Hoisting tools, timbers, and other materials.

    When tools, timbers, or other materials are being lowered or raised in a shaft by means of a

    bucket, skip, or cage, they shall be secured or so placed that they will not strike the sides of the

    shaft.

    30 CFR 57.19081 - Conveyances not in use.

    When conveyances controlled by a hoist operator are not in use, they shall be released and the

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    49/103

    43 | P a g e

    conveyances shall be raised or lowered a suitable distance to prevent persons from boarding or

    loading the conveyances.

    30 CFR 57.19083 - Overtravel backout device.

    A manually operated device shall be installed on each electric hoist that will allow the

    conveyance or counterbalance to be removed from an overtravel position. Such device shall not

    release the brake, or brakes, holding the overtravelled conveyance or counterbalance until

    sufficient drive motor torque has been developed to assure movement of the conveyance or

    counterbalance in the correct direction only.

    30 CFR 57.19090 - Dual signaling systems.

    There shall be at least two effective approved methods of signaling between each of the shaft

    stations and the hoist room, one of which shall be a telephone or speaking tube.

    30 CFR 57.19091 - Signaling instructions to hoist operator.

    Hoist operators shall accept hoisting instructions only by the regular signaling system unless it is

    out of order. In such an event, and during other emergencies, the hoist operator shall accept

    instructions to direct movement of the conveyances only from authorized persons.

    30 CFR 57.19093 - Standard signal code.

    A standard code of hoisting signals shall be adopted and used at each mine. The movement of a

    shaft conveyance on a "one bell" signal is prohibited.

    30 CFR 57.19094 - Posting signal code.

    A legible signal code shall be posted prominently in the hoist house within easy view of the

    hoistmen, and at each place where signals are given or received.

    30 CFR 57.6204 - Hoists.

    (a) Before explosive material is transported in hoist conveyances--

    (1) The hoist operator shall be notified; and

    (2) Hoisting in adjacent shaft compartments, except for empty conveyances or counterweights,

    shall be stopped until transportation of the explosive material is completed.

    (b) Explosive material transported in hoist conveyances shall be placed within a container which

    prevents shifting of the cargo that could cause detonation of the container by impact or by

    sparks. The manufacturer's container may be used if secured to a nonconductive pallet. Whenexplosives are transported, they shall be secured so as not to contact any sparking material.

    (c) No explosive material shall be transported during a mantrip.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    50/103

    44 | P a g e

    Appendix F - Applicable OSHA Regulations

    1926.251(c)

    Wire rope.

    1926.251(c)(1)

    Tables H-3 through H-14 shall be used to determine the safe working loads of various sizes and

    classifications of improved plow steel wire rope and wire rope slings with various types ofterminals. For sizes, classifications, and grades not included in these tables, the safe working

    load recommended by the manufacturer for specific, identifiable products shall be followed,

    provided that a safety factor of not less than 5 is maintained.

    1926.251(c)(2)

    Protruding ends of strands in splices on slings and bridles shall be covered or blunted.

    1926.251(c)(3)

    Wire rope shall not be secured by knots, except on haul back lines on scrapers.

    1926.251(c)(4)(i)

    An eye splice made in any wire rope shall have not less than three full tucks. However, this

    requirement shall not operate to preclude the use of another form of splice or connectionwhich can be shown to be as efficient and which is not otherwise prohibited.

    1926.251(c)(4)(ii)

    Except for eye splices in the ends of wires and for endless rope slings, each wire rope used in

    hoisting or lowering, or in pulling loads, shall consist of one continuous piece without knot or

    splice.

    1926.251(c)(4)(iii)

    Eyes in wire rope bridles, slings, or bull wires shall not be formed by wire rope clips or knots.

    1926.251(c)(4)(iv)

    Wire rope shall not be used if, in any length of eight diameters, the total number of visible

    broken wires exceeds 10 percent of the total number of wires, or if the rope shows other signs

    of excessive wear, corrosion, or defect.

    1926.251(c)(5)

    When U-bolt wire rope clips are used to form eyes, Table H-20 shall be used to determine the

    number and spacing of clips.

    http://www.osha.gov/pls/oshaweb/owalink.query_links?src_doc_type=STANDARDS&src_unique_file=1926_0251&src_anchor_name=1926.251(c)http://www.osha.gov/pls/oshaweb/owalink.query_links?src_doc_type=STANDARDS&src_unique_file=1926_0251&src_anchor_name=1926.251(c)(3)http://www.osha.gov/pls/oshaweb/owalink.query_links?src_doc_type=STANDARDS&src_unique_file=1926_0251&src_anchor_name=1926.251(c)(4)(iii)http://www.osha.gov/pls/oshaweb/owalink.query_links?src_doc_type=STANDARDS&src_unique_file=1926_0251&src_anchor_name=1926.251(c)(4)(iii)http://www.osha.gov/pls/oshaweb/owalink.query_links?src_doc_type=STANDARDS&src_unique_file=1926_0251&src_anchor_name=1926.251(c)(3)http://www.osha.gov/pls/oshaweb/owalink.query_links?src_doc_type=STANDARDS&src_unique_file=1926_0251&src_anchor_name=1926.251(c)
  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    51/103

    45 | P a g e

    Table H-20:

    1926.251(c)(5)(i)

    When used for eye splices, the U-bolt shall be applied so that the "U" section is in contact with

    the dead end of the rope.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    52/103

    46 | P a g e

    Appendix G - Applicable Arizona Mining Regulations

    27-348. Shaft stations

    Stations or levels shall have a passageway around the working shaft so that crossing over the

    hoisting compartments may be avoided. Sumps shall be securely covered. At shaft stations a

    gate or guard rail shall be provided and kept in place across the shaft, except when a cage, skip

    or bucket is being loaded, but may be temporarily removed for repairs or other operations ifproper precaution is taken to prevent danger to persons. The top of the shaft shall be protected

    by a substantial gate or guard rail.

    27-351. Hoists; operator; indicator

    A. No person addicted to intoxicating liquors or drugs, or under eighteen years of age shall be

    employed as a hoisting engineer.

    B. All power hoisting machinery used in hoisting from or lowering employees and materials into

    mines, except for prospect shafts not exceeding three hundred feet in depth, shall be equipped

    with an indicator placed near and in clear view or hearing of the engineer. The indicator shall be

    in addition to marks on the rope, cable or drum.C. It is unlawful to hoist or lower persons from or into a mine at a speed greater than fifteen

    hundred feet per minute, but the inspector may designate a lesser speed than fifteen hundred

    feet per minute in a shaft, if in his opinion a greater speed is unsafe, or a greater speed if in his

    opinion particular shafts and hoist conditions so warrant.

    27-352. Inspection and construction of hoists

    A. Hoisting machinery, cables and sheaves shall be inspected once every twenty-four hours by a

    competent person appointed by the operator for that purpose, and the person making the

    inspection shall immediately report in writing to the operator all defects found.

    B. Ropes or cables used for hoisting purposes shall be of approved quality and manufacture. In

    shafts and winzes over two hundred feet deep, wire ropes or cables only shall be used for

    hoisting purposes.

    C. Head frames where persons are hoisted at a speed of over two hundred fifty feet per minute

    and where more than twenty-five persons are employed shall be constructed to allow at least

    twenty-five feet above the hoist landing stage in which the cage, skip or bucket can travel freely

    in case of an overwind.

    27-358. Signaling apparatus

    A. Every shaft and each compartment thereof used for hoisting which exceeds fifty feet in

    depth, and not exempted in writing by the inspector, shall be provided with an efficient means

    of interchanging distinct and definite signals between the top of the shaft and the lowest levelfrom which hoisting is being done, and the various intermediate levels for the time they are in

    use.

    B. The signaling apparatus shall be either wire or cable actuating a bell, whistle, speaking tube,

    telephone, electric or electronic system, or two or more of them.

    C. Only those employees and supervisors authorized by the operator shall be permitted to ring

    any shaft or station bells.

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    53/103

    47 | P a g e

    Appendix H - Stantec Proposal

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    54/103

    48 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    55/103

    49 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    56/103

    50 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    57/103

    51 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    58/103

    52 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    59/103

    53 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    60/103

    54 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    61/103

    55 | P a g e

  • 7/25/2019 The San Xavier Mine - Hoist Commissioning

    62