12
Bheri Babai Diversion Multipurpose Project (BBDMP) Presented by Jim Clark, Projects Manager India The Robbins Company More than 50 years of innovation and experience, More than 900 Employees worldwide Annual sales exceeding $300 million We hold almost 90% of TBM tunneling world production records Company Facts THE ROBBINS COMPANY Front of office building SOLON, OHIO, USA Solon, Ohio, USA Facilities include: Administration USA Equipment production Engineering staff Field service staff Headquarters THE ROBBINS COMPANY

The Robbins Company - icid.org · ROBBINS EXPERIENCE IN INDIA •2 x 10.0 m Diameter double shield TBMs •Length 43.5 km. •Longest tunnel in the world without intermediate access

  • Upload
    vulien

  • View
    217

  • Download
    1

Embed Size (px)

Citation preview

Bheri Babai Diversion Multipurpose Project (BBDMP)

Presented by Jim Clark, Projects Manager IndiaThe Robbins Company

• More than 50 years of innovation and experience,

• More than 900 Employees worldwide

• Annual sales exceeding $300 million

• We hold almost 90% of TBM tunneling world production records

Company Facts

THE ROBBINS COMPANY

Front of office building

SOLON, OHIO, USA

Solon, Ohio, USA

Facilities include:

• Administration

• USA Equipment production

• Engineering staff

• Field service staff

Headquarters

THE ROBBINS COMPANY

• Robbins Europa -- Italy

• Roboretec -- Romania

• Robbins China -- Shanghai

• Robbins China -- Guangzhou

• Robbins Asia Pacific

• Hong Kong

• Brisbane

• Robbins GmbH -- Germany

• Robbins India – New Delhi

• Robbins España – Madrid

• Robbins Mexico – Mexico City

• Robbins TBM Korea – Seoul

• Representatives in

35 countries

Facilities in 11 Countries Worldwide

THE ROBBINS COMPANY

Robbins Experience in

India

• Almost 70 km of tunnels bored to date

• Metro

• Water Transfer

• Hydro Electric Power

• 300 Employees

• 25 expats

ROBBINS EXPERIENCE IN INDIA

AMR Water tunnel

ROBBINS EXPERIENCE IN INDIA

• 2 x 10.0 m Diameter double shield TBMs

• Length 43.5 km.

• Longest tunnel in the world without intermediate access.

• Granite & Quartzite, UCS up to 300 MPa

• Robbins responsible for all TBM related activities

Alimineti Madhava Reddy Water Tunnel

Mumbai Water tunnel

ROBBINS EXPERIENCE IN INDIA

• Tunnel length 8.3 Km

• 6.25 m Open Gripper machine

• Shaft depth 109 m

• Continuous conveyor system

• Vertical conveyor system

Mumbai Water tunnel

ROBBINS EXPERIENCE IN INDIA

Mumbai Water tunnel

• Bored over 8 km in 18 months

• Over 60 m bored in 24 hours

• Indian record of 870 meters in a month

Jaipur Metro

ROBBINS EXPERIENCE IN INDIA

Jaipur Metro

• TBM’s bored beneath heritage structures

• Only 5 m of cover

• Robbins provided key personnel & operators

• Took full responsibility for boring beneath the gate

ROBBINS EXPERIENCE IN INDIA

Chandpole gate

• Foundations made up of irregular size stone blocks

• Limited resistance to settlement

• Lime mortar joints in poor condition

• Riddled with cavities

• Contract limit of 4 mm settlement

ROBBINS EXPERIENCE IN INDIA

Jaipur Metro “whoever destroys, injures, mutilates, defaces, alters, removes,

disperses, misuses, imperils or allows to fall into decay a

protected monument, or removes from a protected monument

any sculpture, carving image, bas-relief, inscription or other like

object, shall be punishable with imprisonment for a term which

may extend to six months with a fine which may extend to five

thousand rupees or with both”

BBDMP TBM Selection

TBM SELECTION

Geology and overburden

• Mostly sandstone & Mudstone

• Some conglomerate

• Two thrust/shear zones

• Babai thrust (100m from portal)

• Bheri thrust (5,800m from portal)

• Up to 800m overburden

• Shielded machine best suited to geology

TBM SELECTION

Construction Schedule

• Necessity to finish the project in 54 months

• Absence of intermediate adits

• boring and lining must proceed concurrently

• High Performance Double Shield TBM is required

TBM SELECTION

Benefits of Double shield TBM

• Rapid tunnel and lining progress

• Secure the immediate stabilization of the tunnel walls

• Act as a final lining, not requiring any further working phase

• Immediately reducing any water inflow into the tunnel

TBM SELECTION

TBM Specifications

TBM Manufacturing, Delivery and Assembly

TBM MANUFACTURING, DELIVERY & ASSEMBLY

Manufacturing & Assembly

• Critical components are manufactured in the USA and Europe

• Shipped to Robbins facility in Shanghai for assembly

TBM MANUFACTURING , DELIVERY & ASSEMBLY

Testing, Disassembly & Shipping

• Full factory testing of machine (FAT)

• Machine then disassembled and shipped by sea to Kolkata

• Then 1,300 km overland from Kolkata to the project site

TBM MANUFACTURING , DELIVERY & ASSEMBLY

Site Assembly

• Machine arrived on site the first week of September 2017

• Assembly of the TBM commenced 10th September

• 6 weeks taken to complete assembly, commissioning and push machine to the face of the starter tunnel

TBM MANUFACTURING , DELIVERY & ASSEMBLY

Site Assembly

Production to Date

Learning curve

PRODUCTION TO DATE

• A learning curve is factored into all production predictions for TBM driven tunnels.

• Prediction for this tunnel was a learning curve of 3 months at 250m production per month (750m total)

• Boring commenced Early November 2017

• TBM completed 330m of boring in November

• By Mid December after only 6 weeks of tunneling the TBM passed the 750m in 3 months learning curve target.

• Excellent achievement by any standards.

First 6 months

PRODUCTION TO DATE

• The machine has completed almost 4 km during the first 6 months of boring

• Best 24 hours 52.9m

• Best week 285m

• Best month/30 day period

1057 m

Challenges Ahead ?

Main Areas of Concern

CHALLENGES AHEAD

• Squeezing ground

• Slabbing/Spalling ground

• Jointed and blocky rock

• Water ingress

• Bheri thrust/shear zone estimated to be 400m wide

Inundation

CHALLENGES AHEAD

Probe Drilling/Ground Treatment

PROBE DRILLING/GROUND TREATMENT

Probe Drill

• The probe drill is used for probe and grout holes

• It can also be used to relieve hydrostatic pressure at the face

• By drilling relief holes through the segmental lining behind the machine

PROBE DRILLING/GROUND TREATMENT

Grout Packers

• Mechanical packer

Can be inserted to approx 4-5m. May not be long enough to prevent grout return into bored tunnel in fractured rock

• Inflatable packer

Can be extended and inserted up to 10m+. Can be placed ahead of the tunnel face to prevent grout return.

PROBE DRILLING/GROUND TREATMENT

• Primary holes drilled first

• Packers inserted into holes

• Pressure gauge is connected to the packer in any hole thatshows water ingress.

• Water pressure is measured

• Injections begins from lowest holes

• Injection pressure is dictated by hydrostatic pressure

Operations carried out in 2 separate phases

PROBE DRILLING/GROUND TREATMENT

• Secondary or control holes drilled.

• Experienced geologist must monitor the drilling

• Observe the effects of the primary injection

• Packers inserted in selected holes if required

• Injection sequence repeated

Secondary phase begins once primary phase completed

Squeezing Ground

SQUEEZING GROUND

TBM Shields becoming trapped

• CHD Diameter 5,060 mm -Diameter of Front/ Telescopic Shield 4,990 mm (70 mm clearance)

• Diameter of Gripper Shield/ Tail Shield 4,910 mm (80 mm clearance)

• 35 mm of radial overcut is also available

SQUEEZING GROUND

TBM Shields becoming trapped

• Single shield mode

• TBM gripper shoes are retracted

• Main thrust cylinders closed up

• Auxiliary thrust cylinders are utilized to push machine

• By thrusting off the segmental lining

• 40% additional thrust

• 38,475 kN

Bursting and Spalling Ground

BURSTING and SPALLING GROUND

Shield Design

• Designed to deal with bursting or spalling ground

• Cope with extreme loading

• Protect the tunnel personnel

• Provide support to the ground continually

• Up until erection of segmental lining

BURSTING and SPALLING GROUND

Cutterhead design

• Low profile muck buckets

• Reduce possibility of “pulling in” loose rock

• Large capacity and smooth throat

• Able to handle the large amount of broken rock produced in high speed production.

BBDMP Summary

SUMMARY

• Selected correct Machine for the Job

• Initial 500m excavated by Robbins plus training

• Experienced contractor

• Good site set up

• Experienced project team

• Production to date is very good

• Caution required when approaching Bheri thrust Zone

• First TBM project in Nepal has exceeded target

• Now expected to be huge success

• TBM can be refurbished and utilized on other projects.

Questions?