77
THE REGIONAL MUNICIPALITY OF NIAGARA TENDER 2017-T-104 (RN 17-04) Regional Municipality of Niagara South Side Low Lift Sewage Pumping Station Upgrades City of Niagara Falls A D D E N D U M N O. (1) I DIRECTIVE This addendum shall form an integral part of the plans and specifications for the above project and shall be read in conjunction therewith. This addendum shall, however, take precedence over all requirements of the previously issued drawings and specifications with which it may prove to be at variance, unless otherwise clarified by the Engineer. This addendum must be signed by the Tenderer in the appropriate space and must be attached to the back of the Form of Tender and placed in the Envelope for submission at the time of tendering. Tenders not including this addendum signed as requested shall be rejected as informal. II REVISIONS 1. Special Instructions to Bidders, Item 2. Tender Procedure (c) (iii), page SIB-4 Update first bullet and replace ‘Pages FT-Error! Bookmark not defined through FT- 3 (Form of Tender)to read Pages FT-1 through FT-3 (Form of Tender)”. Update and replace ‘Refer to SIB Item 34, “Error! Reference Source not found.” to read ‘Refer to SIB Item 34, “48 Hour Breakdown Schedule of Tender Prices”. 2. Form of Tender Please find attached a Reissued Form of Tender page FT-10. Failure to utilize REVISED Form of Tender page shall result in disqualification. III CLARIFICATIONS Niagara Region has adopted a new Commissioning Process to ensure consistency in the commissioning requirements for Water and Wastewater facilities. Attached to this addendum is the Niagara Region Water and Wastewater Services Commissioning Guideline. This guideline is to be read in conjunction with Specification 01810 and the Commissioning Plan included in the tender documents. IV QUESTIONS Q1 Regarding the above mentioned tender, specification 13911 appears to be missing from the contract documents altogether. Please provide a copy of this specification. A1 Specification 13911 is attached as part of this addendum.

THE REGIONAL MUNICIPALITY OF NIAGARA

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

THE REGIONAL MUNICIPALITY OF NIAGARA

TENDER 2017-T-104 (RN 17-04)

Regional Municipality of Niagara

South Side Low Lift Sewage Pumping Station Upgrades

City of Niagara Falls

A D D E N D U M N O. (1)

I DIRECTIVE

This addendum shall form an integral part of the plans and specifications for the above project and

shall be read in conjunction therewith. This addendum shall, however, take precedence over all

requirements of the previously issued drawings and specifications with which it may prove to be at

variance, unless otherwise clarified by the Engineer.

This addendum must be signed by the Tenderer in the appropriate space and must be attached to

the back of the Form of Tender and placed in the Envelope for submission at the time of tendering.

Tenders not including this addendum signed as requested shall be rejected as informal.

II REVISIONS

1. Special Instructions to Bidders, Item 2. Tender Procedure (c) (iii), page SIB-4

Update first bullet and replace ‘Pages FT-Error! Bookmark not defined through FT- 3

(Form of Tender)” to read ‘Pages FT-1 through FT-3 (Form of Tender)”.

Update and replace ‘Refer to SIB Item 34, “Error! Reference Source not found.” to read

‘Refer to SIB Item 34, “48 Hour Breakdown Schedule of Tender Prices”.

2. Form of Tender

Please find attached a Reissued Form of Tender page FT-10.

Failure to utilize REVISED Form of Tender page shall result in disqualification.

III CLARIFICATIONS

Niagara Region has adopted a new Commissioning Process to ensure consistency in the

commissioning requirements for Water and Wastewater facilities. Attached to this addendum

is the Niagara Region Water and Wastewater Services Commissioning Guideline. This

guideline is to be read in conjunction with Specification 01810 and the Commissioning Plan

included in the tender documents.

IV QUESTIONS

Q1 Regarding the above mentioned tender, specification 13911 appears to be missing from

the contract documents altogether. Please provide a copy of this specification.

A1 Specification 13911 is attached as part of this addendum.

2017-T-104 (RN 17-04)

Addendum No. 1

Page 2 of 2

Q2 It is also not clear if the PLC Programming and SCADA integration is to be done by the

Contractor, please confirm. If so, please confirm the list of Region approved SCADA

integrators able to bid on this portion of the scope of work.

A2 PLC Programming and SCADA Integration is not the responsibility of the

Contractor under this contract.

Q3 Please provide a list of contractors that were present at the non-mandatory Tender

meeting held on site March 27th

, 2017 at 10:00.

A3 The list of contractors that attended the Tender site meeting is as follows:

Baseline

BGL Contracting

Sheridan Electric

Century Group Inc. Constructors

Romag

The Becc Construction Group

Genrep

T.R. Hinan

Matheson Construction

Procon

Sona

Q4 Please clarify the lighting scope on the first floor of the pump station. Is the lighting to

be replaced or remain?

A4 The previous contractor has installed 10 new “Style B” (Drawing E210) light

fixtures. These fixtures are to remain. The contractor is responsible for providing

and installing any remaining fixtures indicated on the contract drawings.

END OF ADDENDUM NO. 1

NO. OF PAGES: 2

Date Issued: March 27, 2017

Signature: Vicki Lafford-Field

Purchasing Agent

THE TENDERER SHALL ADJUST HIS BID PRICE ACCORDING TO THE

CHANGES SPECIFIED IN THIS ADDENDUM.

Name of Company:

Tenderer's Signature:

Date: ___________________

CONTRACT NO. 2017-T-104

RN 17-04

South Side Low Lift SPS Upgrades in the City of Niagara Falls

SCHEDULE OF TENDER PRICES

TO BE SUBMITTED AS PART OF THE 48 HOUR BREAKDOWN

All line items in the Schedule of Tender Prices must be completed with a dollar value.

Failure to comply will result in an incomplete bid

Rev 4, 2016-06 REVISED FT - 10

Item Spec No. Description Unit Total Price

Protection (excluding HST)

Division 8 – Doors and Windows

9.1 08255 FRP Doors and Frames L.S.

9.2 08330 Coiling Doors L.S.

9.3 08700 Finish Hardware L.S.

9.4 All Other Division 8

Requirements

L.S.

Sub-total Division 8 – Doors

and Windows (excluding

HST)

Division 11 – Equipment

10.1 11350 Photoionization Odour Control

Unit

L.S.

10.2 11425 Screw Centrifugal Pumps L.S.

10.3 11430 Fuel Oil Supply Pumps L.S.

10.4 11900 Aboveground Fuel Storage

Tanks

L.S.

10.5 11901 Fuel Oil Day Tanks L.S.

10.6 All Other Division 11 L.S.

Water and Wastewater Services

Commissioning Guideline

Commissioning Guideline Region of Niagara

Rev 00

Page 2

Commissioning Guideline

Revision Date Description of Revisions 00 2017-01-19 First Edition of the Commissioning Guideline

Commissioning Guideline Region of Niagara

Rev 00

Page i

Table of Contents Introduction ................................................................................................................................... 1

Scope .............................................................................................................................................. 1

Commissioning Handbook ........................................................................................................... 1

1. Definitions ......................................................................................................................................................... 1 2. Commissioning Process ................................................................................................................................. 4 3. Commissioning Responsibilities, Roles and Processes ........................................................................... 4 4. Commissioning Meetings............................................................................................................................... 4 5. Submission Requirements ........................................................................................................................... 10 6. Equipment or Process In-service ............................................................................................................... 10

Commissioning Plan Outline ..................................................................................................... 12

Part 1. Administration and Project Overview .......................................................................................... 12 1.1. Revisions .............................................................................................................................................. 12 1.2. Administration and Management ................................................................................................... 12 1.3. Commissioning Team ....................................................................................................................... 12 1.4. Project Summary ................................................................................................................................ 12 1.5. Equipment / Process to be Commissioned ................................................................................. 12

Part 2. Commissioning Plan .......................................................................................................................... 13 2.1. Commissioning Sequence ................................................................................................................ 13 2.2. Summary of Testing and Commissioning Activities ................................................................... 13 2.3. Commissioning Requirements ........................................................................................................ 13

2.3.1. Equipment / Process .............................................................................................................. 13 2.3.1.1. Relevant Specifications .................................................................................................... 13 2.3.1.2. Pre-requisites .................................................................................................................... 13 2.3.1.3. Disinfection and Bacteriological Testing ..................................................................... 14 2.3.1.4. Relevant Forms ................................................................................................................. 14 2.3.1.5. Test Highlights .................................................................................................................. 14

2.4. Site Acceptance Testing Tracking .................................................................................................. 15 2.5. Training ................................................................................................................................................ 15 2.6. SCADA Software SAT ...................................................................................................................... 15 2.7. Functional Run Tests ......................................................................................................................... 15 2.8. Commissioning Schedule ................................................................................................................. 15 2.9. Commissioning Linear Infrastructure ........................................................................................... 16 2.10. In-service Date ................................................................................................................................... 16

Part 3. Forms .................................................................................................................................................... 16 List of Appendices Appendix A – Commissioning Plan Example Appendix B - Forms

Commissioning Guideline Region of Niagara

Rev 00

Page 1

Introduction The start-up, testing, and commissioning of Water-Wastewater facilities (W-WW), services, and equipment is a complex process that varies significantly between projects. Commissioning requirements for W-WW infrastructure must be considered on a case-by-case basis according to the type, scope, and complexity of the project in question. A customized commissioning procedure must be developed for each W-WW capital works project, including but not limited to those projects involving treatment plants, pumping stations, meter chambers, storage tanks, reservoirs, odour control facilities, and hauled waste receiving facilities. For each capital works project, it is the Project Consultant’s responsibility to prepare and document the commissioning procedure. All applicable Niagara quality management system (QMS) procedures need to be adhered to during commissioning to ensure that all requirements of external stakeholders, regulatory requirements, and legal instruments (MDWL, DWWP, ECA, etc.) are met and maintained. Niagara Region’s capital works projects are governed in part by the Niagara Peninsula Standard Contract Documents; where the requirements of this Commissioning Guideline conflict with the Contract Documents, the more stringent of the requirements shall be applied. The Project Consultant is required to identify any deviations from the Contract Documents or the Commissioning Guideline and shall provide written documentation and reasoning for said deviations. Any submissions from other Project Contractors must be reviewed and approved by the Project Consultant before they are submitted to Niagara Region. Scope This Commissioning Procedure Guideline provides guidance for Niagara Region W-WW Services’ staff, Project Consultants, and Contractors in the development and execution of these commissioning procedures. Commissioning Handbook 1. Definitions

Term Definition

Calibration The action of configuring equipment to function as intended with respect to a system’s desired process parameters.

Care The responsibility for maintenance or repair of equipment or processes that have been placed in service. New equipment or processes placed into service shall be under the care of the Contractor until the facility is deemed Commissioned and the project is substantially performed. The Region shall notify the Contractor of run times to ensure preventative maintenance can be completed by the Contractor. Existing equipment shall be under the care of the Region until that equipment or process is removed from service.

Commissioned Means the successful completion of the Facility Functional Run Test with documented sign-off dates from the Region and Consultant representatives,

Commissioning Guideline Region of Niagara

Rev 00

Page 2

Term Definition

and the submission of all contractual deliverables (i.e. Operations and Maintenance Manuals, Single Line Drawings, etc.).

Commissioning Manager

A representative from both the Consultant and Contractor responsible for working together to ensure the successful completion of the Commissioning process.

Commissioning Plan A step-by-step procedure to detail the systematic testing of all of the specific equipment and processes installed under the contract. The plan shall include copies of all the supporting quality control checklists, forms, and process shutdown/bypass plans that shall be used to record the results of the tests in accordance with the Region’s commissioning sequencing process. The Commissioning Plan is initially prepared by the Consultant based on the construction sequencing suggested in the specifications. The Commissioning Plan is updated by the Contractor based on the construction schedule, final sequencing of construction, and any modifications made to the design during construction.

Commissioning Process

A process initiated by the preparation of the Commissioning Plan by the Consultant, and finalized by the successful completion of the Facility Functional Run Test, as stipulated by the Region’s Commissioning Procedure and all associated definitions.

Consultant The Engineering Consulting firm contracted with the Region to undertake the design of Regional infrastructure, and who will act as the Contract Administrator.

Contingency Plan Submitted as part of the 80% commissioning plan, and finalized by the Contractor for the 100% submission. Describes the Contractor’s back-up plan should equipment and/or systems malfunction as they are brought online or offline, and during shutdowns/bypasses in an operating facility to ensure continued safe operation.

Contract Documents Compiled engineering specifications, drawings, and any other identified documentation pertinent to the construction/execution of a specific project.

Contractor The Construction firm contracted with the Region that undertakes construction of Regional infrastructure in accordance with the Contract Documents.

Control The responsibility to operate equipment or processes which are accepted by the Region and Consultant, and have been placed into service.

EAM Niagara Region’s Enterprise Asset Management system commonly referred to as CMMS (Computerized Maintenance Management System).

Equipment Maintenance Manual

A manual that identifies and describes all required maintenance activities for all facility equipment, and includes equipment spec sheets, shop drawings, etc. The Maintenance Manual is subject to review and approval by Regional staff prior to acceptance.

Commissioning Guideline Region of Niagara

Rev 00

Page 3

Term Definition

Facility Entire horizontal and/or vertical infrastructure including all individual unit processes.

Facility Functional Run Test

A Functional Run Test completed at the end of the Commissioning process to ensure that all new or modified equipment or processes, controls, and programming successfully function within overall facility operation.

Factory Acceptance Testing (FAT)

Testing performed on specified equipment at the manufacturer’s facility prior to shipment. No equipment can be shipped without FAT approval by the Consultant. The Region and Consultant may elect to participate in the FAT process if deemed necessary.

Functional Run Test Testing over a specified duration the operation of each piece of equipment, or process, installed or modified as a part of the project, to determine whether it functions as required.

In-service In-service refers to equipment or a process being operational within the facility’s entirety, and used for its intended final purpose(s), and under the Region’s control.

Network Testing Cable acceptance testing, network closets SAT, basic network connectivity tests, and link acceptance tests. Region and Consultant may elect to participate in the Network Testing process if deemed necessary.

Operations Manual A manual that highlights the operation of the facility, describing the function of the facility and all associated processes. The Operations Manual is subject to review and approval by Regional staff prior to acceptance.

Process A unit within the overall operation of the facility that performs a specific function.

Process Control Narrative

Also described as SCADA Process Narrative this is an updated Process Narrative identifying the operation of the facility and the degree of automation. It identifies the actions that are to be completed by an operator, and the semi-automatic and/or automatic actions of the facility SCADA System. 80% version produced by the Consultant during design. 100% version produced by the Contractor’s SCADA integrator, and shall include a SCADA software requirements document describing the specific algorithms and content required in the RPU and SCADA computer programs.

Process Narrative A written description of key items and procedures of a specific process prepared by the Consultant. The Process Narrative outlines the sequence of operations in Normal, Maintenance, and Emergency conditions, each in manual and automatic modes of control.

Red-line Drawings Drawing sets marked up in red and submitted by the contractor to reflect all changes made in the specifications and working drawings during the construction process, and show the exact dimensions, geometry, and location of all elements of the work completed under the contract.

Site Acceptance A test, or tests, performed after start-up on individual pieces of equipment,

Commissioning Guideline Region of Niagara

Rev 00

Page 4

Term Definition

Testing (SAT) processes, or software/program to demonstrate and confirm that the equipment, process, or software/program meet the specified operational performance requirements. The SAT shall be carried out in the presence of the Contractor, Supplier/Manufacturer, Consultant and the Region.

Start-up The Contractor, in conjunction with manufacturers / suppliers, ensuring that specific equipment or processes are: as specified; installed correctly; calibrated, and certified. Start-up will be witnessed, documented and signed-off by the manufacturer/supplier. No sign-off requirement from the Consultant or Region. The Region and Consultant may elect to participate in the Start-up process if deemed necessary.

Training Site / class instruction of Regional staff on the operation and maintenance of the new equipment/process. Training is to occur following the SAT and prior to the Functional Run Test. Contractor / SCADA Integrator are responsible for scheduling and facilitating equipment and SCADA training. Consultant is responsible for scheduling and facilitating process training.

2. Commissioning Process Figure 1 outlines the overall Commissioning Process that is to be followed when preparing a project specific Commissioning Plan 3. Commissioning Responsibilities, Roles and Processes Table 1 details the requirements and roles / responsibilities for each task within the Commissioning Process. 4. Commissioning Meetings The Consultant will meet with Niagara Region’s Project team to review and finalize the plan prior to tendering, based on the Consultant’s suggested construction sequencing and Niagara Region’s operational constraints. Commissioning Plan Review Meeting(s) during construction will be held between the Niagara Region, Contract Administrator, and Contractor Project Teams to discuss and finalize the Commissioning Plan based on final construction sequencing, schedule, and operational constraints.

Commissioning Guideline Region of Niagara

Rev 00

Page 1

Commissioning Guideline Region of Niagara

Rev 00

Page 2

Table 1

Task ID Description Responsibility

Region Consultant Contractor

1. Process Start

Project is awarded to the Consultant. As the suggested construction sequencing develops with the design, the framework for the commissioning plan begins to be established.

Ensuring that all forms related to the Commissioning Process are up to date

-

2. Consultant Prepares Commissioning Plan

The Consultant shall prepare a Commissioning Plan that will be considered 80% complete. The Commissioning Plan is based on the suggested construction sequencing, and confirm the applicability of commissioning tasks identified in the following outline with respect to the specific project. All pre-commissioning, commissioning, and post-commissioning submittals are to be provided in accordance with the commissioning checklists.

Review and accept commissioning plan

Prepare and submit commissioning plan

-

3. Project Tendered

Final tender-ready project design package inclusive of the 80% commissioning plan is released for tender through the Region’s purchasing department.

Release tender Incorporate Commissioning Plan into tender package

-

Commissioning Guideline Region of Niagara

Rev 00

Page 3

Task ID Description Responsibility

Region Consultant Contractor

4. Contractor Finalizes Commissioning Plan

The commissioning plan is finalized based on actual construction sequencing, schedule, and Input from Sub-contractors and Suppliers, including an update to all items noted as part of the 80% Commissioning plan including all relevant checklists, where applicable, as well as the following at a minimum: • Functional testing schedule • Factory Acceptance Test (FAT) reports for SCADA

equipment • FAT reports for process equipment • Calibration certificates for all instruments • Certification of calibration for testing equipment

(including certification and credentials of laboratory) • Copies of manufacturer’s certificates of proper installation • Copies of manufacturer’s certificate of successful

operation • Copies of manufacturer’s start-up procedures for all

equipment • Copies of manufacturer’s start-up log sheets • Copies of specification sections from individual equipment

manuals • The Contractor’s 24-hour emergency response plan

during the commissioning period. The plan shall be completed with a daytime staffing plan and names, qualifications and telephone numbers of those assigned to off-hour standby duty

• Performance testing schedule • Operational testing schedule • Contingency plan • System Integrator Software Test Plans and Schedules

Review and provide comment on Commissioning Plan submitted by Contractor Attend Review meeting / workshop

Review Contractor’s finalized commissioning plan and distribute to the Region for review Work with Contractor’s Commissioning Manager to facilitate review meetings and/or workshops to provide input into the plan.

Finalize Commissioning Plan Work with Consultant’s Commissioning Manger to facilitate review meetings and/or workshops to provide input into the plan. Submit Commissioning Plan 3 weeks prior to the commissioning meeting/workshop. Finalize the Commissioning Plan based on comments received.

Commissioning Guideline Region of Niagara

Rev 00

Page 4

Task ID Description Responsibility

Region Consultant Contractor

5. Region Accepts Final Commissioning Plan

The commissioning plan as finalized by the project team will be considered as accepted by the Region.

Review and accept final Commissioning Plan

- Keep and maintain all forms related to the Commissioning Process maintain a master set of all forms and documents on site -

6. Draft O&M Manuals, Red-Line As-Built and Single Line Drawings

Submission of 70% complete Operations Manual and Maintenance Manual, and red-line as-built and single line drawings.

Review and accept draft submissions.

Submit draft Operation Manuals, Review red-line as-built and Single Line drawings

Submit draft Maintenance manuals. Submit red-line as-built and Single Line Drawings

7. Swabbing, flushing and/or Pressure Testing if Required

Depending on the commissioning requirements, swabbing, flushing and pressure testing is undertaken as required by the Contractor in accordance with the Contract Documents.

- Witness swabbing, flushing and pressure testing operation

Coordinate and undertake swabbing, flushing and/or pressure testing

8. Update EAM Database for equipment/ process

Updating of EAM database to reflect equipment removed, and inputting of all equipment information to ensure the EAM is up to date with all equipment brought online during the commissioning process.

Update Regional EAM version based on Consultant’s web based EAM update

Update the web-based EAM for all equipment brought into service

Provide equipment complete nameplate and technical information to Consultant

Commissioning Guideline Region of Niagara

Rev 00

Page 5

Task ID Description Responsibility

Region Consultant Contractor

9. Disinfection of Equipment/ Material if Required

Depending on the commissioning requirements, disinfection of equipment/material is undertaken as required by the Contractor in accordance with the Contract Documents.

Take bacteriological samples and have them analyzed

Coordinate and undertake disinfection operations

10. Authorization to Proceed

Depending on the results of the swabbing, pressure testing, and/or disinfection processes where applicable, the Region’s Overall Responsibility Officer (ORO), or Area Operations Manager, will decide whether or not to permit the commissioning process to proceed to the next commissioning phase.

ORO or Area Operations Manager signs off on the appropriate checklist

- -

11. Start-up With approval from the ORO granted, Contractor can now start-up equipment or systems slated for commissioning in accordance with the Contract Documents in the presence of manufactures as required. Prior to start-up the Contractor shall ensure that all non-operating functions required to bring Work to a state of readiness for placing systems into service are completed

Attend and participate in equipment Start-up process if deemed necessary

Attend and participate in equipment Start-up process if deemed necessary

Power/Start-up equipment to be commissioned in the presence of the manufacturer or supplier

Commissioning Guideline Region of Niagara

Rev 00

Page 6

Task ID Description Responsibility

Region Consultant Contractor

12. SAT Equipment testing is undertaken by the Contractor, manufacturer, and/or supplier in the presence of the Region and Consultant,

Attend testing session Assume control of the equipment/process if integrated into the overall facility.

Complete relevant equipment/ process testing checklists with the assistance of the Contractor Witness and confirm successful completion of the SAT

Undertake testing of equipment/ process with the manufacturer or supplier. Assist in the completion of relevant checklists

13. Training Niagara Region staff are trained by the Contractor on the operation and maintenance of equipment/processes, and SCADA as required, in accordance with the Contract requirements. The Consultant will train Niagara Region staff on the overall operation of the process / facility

Niagara Region staff participation in training

Attend Contractor training session and prepare sign in sheet. Schedule, coordinate and provide in class and field process training

Schedule, coordinate and provide in class and field training .

Commissioning Guideline Region of Niagara

Rev 00

Page 7

Task ID Description Responsibility

Region Consultant Contractor

14. Notice of Equipment in Service

Identification of the exact dates when equipment/processes are integrated into the normal facility operations.

Project Manager will notify Compliance Technologist that equipment is in service. Compliance Technologist to notify the MOECC that equipment is in service

Notify Niagara Region PM when equipment has been or will be placed in service.

Provide Consultant and Niagara Region one weeks’ notice of equipment being integrated into the existing operation (i.e. SAT or Functional Run Test)

15. Functional Run Test

Functional run tests carried out on individual pieces of equipment in accordance with the Contract Documents.

Assume control of the equipment/process if integrated into the overall facility Identify any operation issues that occur during the test and notify Consultant

Track the success of the functional run tests

Undertake functional run tests of individual equipment manually (independent of SCADA network)

Commissioning Guideline Region of Niagara

Rev 00

Page 8

Task ID Description Responsibility

Region Consultant Contractor

16. Software SAT and Training

Completion of required test(s) on software/program to demonstrate and confirm that the software/program meet the specified operational performance requirements as dictated by the Contract Documents. Software / SCADA training of Niagara Region staff is completed.

Witness operation of equipment via SCADA network (Integrated Systems)

Witness operation of equipment via SCADA network

Undertake functional run tests of equipment via SCADA network. Provide training on SCADA system updates.

17. Facility Functional Run Test

A Functional Run Test completed at the end of the Commissioning Process to ensure that all new or modified equipment or processes, controls, and programming successfully function within overall facility operation.

Assume control of the equipment/process if integrated into the overall facility Identify any operation issues that occur during the test and notify Consultant

Track the success of the facility functional run test

Undertake functional run test of equipment/ processes within the overall facility operation as per the contract requirements

Commissioning Guideline Region of Niagara

Rev 00

Page 9

Task ID Description Responsibility

Region Consultant Contractor

18. Final O&M, EAM, Red-line As-Built drawings, and Mounted Single Line Diagram Drawing

The Operations Manual, Maintenance Manual, EAM database, and red-line as-built drawings are updated / finalized to reflect the results of, or changes made during, the Facility Functional Run Test. The final Single Line Diagram drawing is to be mounted as per the contract requirements.

Accept Operations Manual and Maintenance Manual Upload the web based EAM entries into the Niagara database.

Update and submit final Operations Manual Update EAM Provide final as-built Single line Diagram drawing to Contractor

Update and submit final Maintenance Manual Update red-line as built drawings Mount final Single Line Drawing

19. Region assumes Care of the Facility

The Region assumes responsibility for care of equipment or processes which have been placed into service Warranty issues are the responsibility of Contractor for the duration of the warranty.

Assume care of equipment and notify Consultant of any warranty issues

Coordinate warranty repairs with Contractor

Address warranty issues

Commissioning Guideline Region of Niagara

Rev 00

Page 10

5. Submission Requirements As part of the Commissioning Process, both the Consultant and the Contractor are required to submit documents at various stages throughout the process. The Consultant will provide a draft copy of the Commissioning Plan, and the Operations Manual or Update, to Niagara Region for review as part of the Detailed Engineering Design Review submission. Comments / edits received from Niagara Region will be incorporated into each document prior to the project being tendered. The Contractor will provide a draft copy of the final Commissioning Plan to the Contract Administrator’s Commissioning Manager for review by the Contract Administrator and Niagara Region. Comments / edits received during review meetings will be incorporated into the final Commissioning Plan. This process may require multiple submissions before the Plan is accepted. Prior to the start of the Commissioning Process testing stage(s) the Contractor must ensure that the following is submitted or complete:

a) Final Commissioning Plan is accepted; b) All asset information for the equipment, process, or facility is entered into Niagara Region’s

EAM; c) Draft Maintenance Manual is accepted by Contract Administrator and Niagara Region, and is

available on-site; d) Red-line as-built drawings are up to date; and e) Red-line as-built Single Line Diagram is completed and available on-site.

Prior to Niagara Region accepting full care and control of the facility, and the Commissioning Process deemed complete, the Consultant and the Contractor must ensure that submitted or completed:

a) Asset information changed during the testing stage(s) is updated in EAM; b) Final red-line as-built drawings are provided to the Consultant; c) Final Single Line Diagram as-built is completed and mounted as per the specifications; and d) Final Operations Manual and Maintenance Manual provided to Niagara Region as per the

specifications. Keeping in mind that some submissions may have multiple iterations before being finalized, the Consultant and Contractor should allow sufficient time for multiple reviews and meetings in their schedules. 6. Equipment or Process In-service It is crucial for compliance purposes that the in-service date for all equipment and/or processes is recorded. The in-service milestone may vary and is dependent on test requirement (i.e. does the equipment or process need to be online to test?). Prior to being placed in-service the Region’s Area Operations Manager will sign-off indicating approval for the equipment or process to be placed in service. The in-service date must reflect the first day that the equipment or process is operational within the facility’s entirety, and used for its intended final purpose(s), and under the Region’s control.

Commissioning Guideline Region of Niagara

Rev 00

Page 11

Distribute updated forms to the identified commissioning team members as each piece of equipment and / or process is placed in-service.

Commissioning Guideline Region of Niagara

Rev 00

Page 12

Commissioning Plan Outline The following sections outline the minimum requirements for inclusion in a Commissioning Plan, including sections to be discussed and their associated requirements (submittals and checklists) associated with a testing and commissioning plan to assist Consultant’s and Contractors with developing the Commissioning Plans for Regional facility infrastructure. Each part of the Commissioning Plan shall be separated using appropriately labeled tab separators. Part 1. Administration and Project Overview 1.1. Revisions Standard revision block table indicating the version of the commissioning plan, submittal date, approver, approval date, and reason for commissioning plan iterations. Commissioning Plan Version

Developed By

Revision Date

Approver Approval Date

Reason for Subsequent Versions

1.2. Administration and Management Identify Commissioning Plan recipients and how the plan will be transmitted to the recipient.

Recipient Name Recipient Organization Distribution Method 1.3. Commissioning Team Identify the Project Commissioning Team including. names, roles and responsibilities, organization, contact information, and any additional comments for all members (Region, Consultant, Contractor, Manufacturer, etc.).

Name Role and Responsibility Organization Contact Information Comments

1.4. Project Summary Provide a brief explanation of the project scope and purpose and all systems to be commissioned in accordance with final facility operational goals as stipulated in the project’s contract documents. Project Component Required Scope •

1.5. Equipment / Process to be Commissioned List all equipment and/or processes being commissioned under the Commissioning Plan

Commissioning Guideline Region of Niagara

Rev 00

Page 13

Equipment / Process Equipment Tag(s)

Part 2. Commissioning Plan 2.1. Commissioning Sequence Based on the Commissioning Process requirements identified in Section 3.2, and the suggested construction sequencing identified in the contract specifications, provide a brief sequence of the equipment / process commissioning (i.e. what equipment process will be commissioned when). 2.2. Summary of Testing and Commissioning Activities Develop a table which provides a high level summary of testing and commissioning activities arranged in a table format, noting the system/equipment to be commissioned, test/commissioning title, test purpose, how the test will be undertaken, party member responsibilities, and forms and tables to use.

Test Objective Procedure Responsibilities Region Consultant Contractor

2.3. Commissioning Requirements The specific commissioning requirements for individual pieces of equipment or processes shall be identified under this section. Each individual piece of equipment or process shall be identified separately, and shall identify the following: 2.3.1. Equipment / Process Identify the specific equipment or process to be commissioned. 2.3.1.1. Relevant Specifications List all relevant specifications to be referenced when completing the Commissioning Process for the equipment or process

Specification Number Title

2.3.1.2. Pre-requisites Identify all activities/tasks required to be completed prior to undertaking the Commissioning Process for specific equipment or processes. This can include commissioning of other equipment or processes. Identify any disinfection and bacteriological testing requirements for the equipment / process.

Commissioning Guideline Region of Niagara

Rev 00

Page 14

Prerequisite Equipment/Systems Date Completed

1

2.3.1.3. Disinfection and Bacteriological Testing Identify all necessary steps to properly disinfect the equipment / process as per current AWWA and Niagara Region requirements. Information to be provided shall include as a minimum:

1. Source water; 2. Backflow prevention requirements; 3. Filling of equipment / process with source water; 4. Hypochlorite concentration; 5. Hypochlorite injection point; 6. Contact time; 7. Flushing / emptying requirements including water disposal and dechlorination; 8. Bacteriological testing sample locations and requirements; and 9. Responsibilities.

Utilize the appropriate Niagara Region disinfection form. 2.3.1.4. Relevant Forms Identify all Regional forms and additional forms from the contract documents that are relevant to the stage. Use the following numbering format for forms that do not have a pre-set number: Format: Y-#####-X-ZZ#

Equipment Tag / Area Designator Sequential number for forms under the specification Specification Number Discipline (P-Process; M-Mechanical; E-Electrical; I-Instrumentation; Y-Yard Piping)

Example – P-11213-01-LL1 (Low Lift Pump 1) The Manufacturer’s authorized representatives will provide and complete their own commissioning / inspection forms as required for each testing stage. These forms are to be included as part of the overall commissioning package, and will be approved by the Contract Administrator’s Commissioning Manager prior to use.

Stage / Test Form ID Form Title Additional Notes 2.3.1.5. Test Highlights Identify key tasks to be completed as part of the equipment / process testing during the identified stage.

Commissioning Guideline Region of Niagara

Rev 00

Page 15

System Stage / Test Task

2.4. Site Acceptance Testing Tracking Complete Form G-05 identifying all equipment / processes. Attach forms to Part 3 as a separate section. 2.5. Training Complete Form G-06 for each day of training and/or for each process. Attach forms to Part 3 as a separate section. Based on the training activities identified in the schedule the Region’s Project Manager will issue meeting invitations to the Project Team Individuals identified for Operations, Maintenance, and Integrated Systems. Those individuals will in turn schedule staff for the training on the scheduled day. 2.6. SCADA Software SAT The SCADA Software SAT should follow the requirements identified in Volume 4 of the “Regional Municipality of Niagara Integrated SCADA Standards Manual” The Consultant shall prepare forms for the Software SAT based on the testing requirements outlined. The Contract 2.7. Functional Run Tests Complete Form G-07 identifying each piece of equipment / process that will undergo a Functional Run Test. Attach forms to Part 3 as a separate section. If the Functional Run Test fails during the allotted test period the deficiencies identified will be logged using Form G-04. 2.8. Commissioning Schedule Prepare an overall schedule identifying timing of all commissioning activities. The Consultant shall identify in general terms the expected duration of each activity. The General Contractor shall finalize the schedule based on the overall construction schedule, and availability of representatives from Manufacturers and Suppliers. The Schedule shall be in calendar for as identified below. The Contractor shall update the schedule on a regular basis to reflect changes in the overall project schedule.

Commissioning Guideline Region of Niagara

Rev 00

Page 16

Month

Sunday Monday Tuesday Wednesday Thursday Friday Saturday 1 2 3 4 5 6 7

8 9 10 11 12 13 14

15 16 17 18 19 20 21

22 23 24 25 26 27 28

29 30 31

2.9. Commissioning Linear Infrastructure Commissioning Plans for linear infrastructure shall comply with the requirements of this document and the contract specifications. The Consultant shall prepare a Connection Sequencing Plan that will allow the linear asset to be commissioned and brought into service with the least disruption to the existing system.

Connection Sequencing Plan

Connect Sequence Size Location Valves to

Close

Affected Residents or Businesses

Mains in service

Mains not in Service

Source Water

Location Comments

2.10. In-service Date Complete Form G-10 for each piece of equipment or process placed into service. This form is also to be completed indicating the date that Niagara Region becomes responsible for care of the equipment or process. This form is to be used for linear and facility work. Part 3. Forms Attach all forms to this section separated by equipment or process

Page A-1

Appendix A Commissioning Plan Example

Commissioning Guideline Region of Niagara

Rev 00 Appendix A

Page A-1

Part 1. Administration and Project Overview

1.1. Revisions

Commissioning Plan Version

Developed By

Revision Date

Approver Approval Date

Reason for Subsequent Versions

Rev01 Consultant 2016-06-29 Niagara Region PM

2016-07-29 Updated comments

1.2. Administration and Management

Recipient Name Recipient Organization Distribution Method

Niagara PM Niagara Region electronic Niagara OM Niagara Region electronic Niagara CO Niagara Region electronic Niagara MM Niagara Region electronic Consultant PM ABC Consulting electronic Consultant FI ABC Consulting electronic Consultant CM ABC Consulting electronic Contractor PM General Contractor Electronic Contractor SS General Contractor Electronic Contractor CM General Contractor Electronic

1.3. Commissioning Team

Name Role and Responsibility Organization Contact Information Comments

Niagara PM Project Manager

Niagara Region

(905) 980-6000 [email protected]

Niagara OM Operations Manager

Niagara Region

(905) 980-6000 [email protected]

Niagara CO Chief Operator Niagara Region

(905) 980-6000 [email protected]

Niagara MM Maintenance Manager

Niagara Region

(905) 980-6000 [email protected]

Consultant PM Project Manager

ABC Consulting

(905) 555-5555 [email protected]

Consultant FI Field Inspector ABC Consulting

(905) 555-5555 [email protected]

Consultant Commissioning Manager

Commissioning Manager

ABC Consulting

(905) 555-5555 [email protected]

Contractor PM Project Manager

Gen Contracting

(905) 555-1212 [email protected]

Contractor SS Site Supervisor Gen Contracting

(905) 555-1212 [email protected]

Commissioning Guideline Region of Niagara

Rev 00 Appendix A

Page A-2

Name Role and Responsibility Organization Contact Information Comments

Contractor CM

Commissioning Manager

Gen Contracting

(905) 555-1212 [email protected]

1.4. Project Summary The objective of the project is to upgrade the Niagara WTP with respect to civil, electrical, mechanical, instrumentation and control improvements to meet current Region and industry standards. The following table identifies the overall scope of the project. Project Component Required Scope

Low Lift Pumping Station

• Replace four (4) low lift pumps (LL1, LL2, LL3, and LL4) • Replace all control instruments, analyzers, and control panels • Replace both MCCs and associated electrical equipment • Replace both travelling screens • Remove interior stairs and replace exterior stairs • Upgrade existing building mechanical and electrical systems

Filtration • Replace (2) backwash pumps • Install new air scour blower and associated valves, piping, and

appurtenances • Replace influent and backwash gate actuators • Replace Wheeler bottom underdrains with plastic, dual parallel

underdrains and integrated air scour • Replace filter media

High Lift Pumping • Replace the west treated water flow meter with • Replace (4) high lift pumps with (5) new pumps (HL1, HL2, HL3, HL4,

and HL5) • Replace existing vacuum priming system and associated valves and

appurtenances 1.5. Equipment / Processes to be Commissioned

Equipment / Process Equipment Tag(s)

Low Lift Pumps LLP-1, LLP-2, LLP-3

High Lift Pumps HLP-1, HLP-2, HLP-3, HLP-4, HLP-5

Commissioning Guideline Region of Niagara

Rev 00 Appendix A

Page A-3

Part 2. Commissioning Plan 2.1. Commissioning Sequence The following equipment / process sequence is anticipated to be undertaken as part of this project. It can be expected that some of the tasks may occur concurrently based on the overall construction schedule • Remove Existing Low Lift Pump (LL)1 and associated piping. • Install new LL1 and associated piping. • Update EAM for LL1. • Complete start-up testing, SAT, training, and functional run test on LL1. • Repeat above steps for LL2 and LL3. • Remove Existing High Lift Pump (HL) 1 and associated piping. • Install new HL1 and associated piping. • Update EAM for HL1. • Disinfect HL1 and associated piping (refer to section 2.3.2.3 for a detailed procedure). • Upon satisfactory bacteriological results and sign-off from the Overall Responsible Operator, or

designate, complete start-up testing, SAT, training, and functional run test on HL1. • Repeat above steps for HL2, HL3, HL4 and HL5. • Carry out software SAT. • Upon a successful software SAT carry out Facility Functional Run Test • Finalize EAM data input for all equipment.

Commissioning Guideline Region of Niagara

Rev 00 Appendix A

Page A-4

2.2. Summary of Testing and Commissioning Activities

Test Objective Procedure Responsibilities Region Consultant Contractor

Pre-requisites (Non-operating functions)

Confirm that equipment / processes are installed and connected correctly.

• Conduct: cleaning, leakage and pressure testing; cold alignment checks; disinfection; system flushing; lubrication of mechanical equipment; rotation checks; and wiring lop checks inspections of all components

• Arrange for equipment manufacturers/suppliers to undertake installation inspections

• Prepare deficiency lists and take corrective actions to complete work in accordance with Contract Documents

• Obtain/complete and submit installation certification forms for each piece of equipment, in accordance with the Contract Documents

Overall Responsibility Officer (ORO) shall give permission to proceed to the next stage of Commissioning

Conduct inspections of all components and sub-components Arrange for equipment installation inspections by manufacturer or supplier

Start-up With approval from the ORO granted, Contractor can now start-up equipment or systems slated for commissioning to ensure that the equipment / processes run correctly in accordance with the Contract Documents. Prior to start-up the Contractor shall ensure that all non-operating functions required to bring Work to a state of readiness for placing systems into service are completed

• Undertake/facilitate manual testing (i.e. testing of equipment in manual/hand mode) of equipment as required by the Contract Documents, and as recommended by the equipment manufacturer.

• Prepare deficiency lists and correct identified deficiencies.

• Retest as required until successful test is obtained.

• Obtain/complete and submit start-up certification forms for each piece of equipment, in accordance with the Contract Documents.

Attend and participate in equipment Start-up process if deemed necessary

Attend and participate in equipment Start-up process if deemed necessary

Power/Start-up equipment to be commissioned in the presence of the manufacturer or supplier

SAT Equipment testing is undertaken by the Contractor, manufacturer / supplier, in the presence of the Region and Consultant, to demonstrate the successful operation of new equipment and/or systems

• Undertake testing/demonstrations for Owner and Consultant

• Coordinate with manufacturer as required for testing/demonstrations

• Provide notice of testing/demonstration dates and times

Attend testing session Assume control of the equipment / process if integrated into the overall facility.

Complete relevant equipment/ process testing checklists with the assistance of the Contractor

Undertake testing of equipment/ process with the manufacturer or supplier. Assist in the

Commissioning Guideline Region of Niagara

Rev 00 Appendix A

Page A-5

Test Objective Procedure Responsibilities Region Consultant Contractor

• Submit completed SAT documentation Witness and confirm successful completion of the SAT

completion of relevant checklists

Training Region staff are trained by the Contractor on the operation and maintenance of equipment/processes, and SCADA as required, in accordance with the Contract requirements. The Consultant will train Niagara Region staff on the overall operation of the process / facility

• Schedule and coordinate training sessions in accordance with Contract Documents

• Submit training documents in advance of sessions • Verify that all necessary training has taken place

Niagara Region staff participation in training

Attend Contractor training session and prepare sign in sheet. Schedule, coordinate and provide in class and field process training

Schedule, coordinate and provide in class and field training.

Functional Run Test

Functional run tests carried out on individual pieces of equipment in accordance with the Contract Documents.

• Commence functional run test for equipment and systems

• Prepare and submit documentation for functional run tests

Assume control of the equipment / process if integrated into the overall facility Identify any operation issues that occur during the test and notify Consultant

Track the success of the functional run tests

Place individual equipment / process on-line. Undertake functional run tests of individual equipment manually (independent of SCADA network) Maintain care of equipment throughout the tests Provide full time trades techs, materials, supplies, fuel, etc. for length of the test.

Software SAT and Training

Completion of required test(s) on software/program to demonstrate and confirm that the software/program meet the specified operational performance requirements as dictated

• Complete SCADA programming and SAT. This includes testing in automatic control mode (PLC control mode).

Witness operation of equipment via SCADA network (Integrated Systems)

Witness operation of equipment via SCADA network

Undertake functional run tests of equipment via SCADA network.

Commissioning Guideline Region of Niagara

Rev 00 Appendix A

Page A-6

Test Objective Procedure Responsibilities Region Consultant Contractor

by the Contract Documents. Software / SCADA training of Niagara Region staff is completed.

Provide training on SCADA system updates.

Facility Functional Run Test

A Functional Run Test completed at the end of the Commissioning Process to ensure that all new or modified equipment or processes, controls, and programming successfully function within overall facility operation. This test cannot begin until the functional run test for the individual pieces of equipment have been completed to the satisfaction of the Owner and Consultant

• Put all equipment and systems, installed into the overall facility operation, in service locally and remotely.

• Prepare and submit documentation for functional run tests

• The SCADA system is intended to be live during the system functional run test.

Assume control of the equipment / process if integrated into the overall facility Identify any operation issues that occur during the test and notify Consultant

Track the success of the facility functional run test

Place all equipment / process on-line. Undertake functional run test of equipment/ processes within the overall facility operation as per the contract requirements Maintain care of equipment throughout the tests Provide full time trades techs, materials, supplies, fuel, etc. for length of the test.

Commissioning Guideline Region of Niagara

Rev 00 Appendix A

Page A-7

2.3. Commissioning Requirements 2.3.1. Low Lift Pumps The following are the requirements for ensuring the satisfactory commissioning of the Low Lift Pumps. 2.3.1.1. Relevant Specifications The following specification sections are to be referenced when completing the Commissioning process for this equipment:

Specification Number Title

Construction Sequencing Plan

01650 Commissioning of the Works

11000 Equipment General Requirements

11005 Electric Motors

11213 Vertical Turbine Pumps 2.3.1.2. Pre-requisites The following are pre-requisite activities/tasks that must be completed prior to beginning the commissioning process. • Submission of draft O&M data. • Equipment training to be scheduled and training materials to be submitted. • All associated equipment to have undergone commissioning, as outlined in the Table below:

Prerequisite Equipment/Systems Date Completed

1 Switch Gear

2 Pump Starters

3 Suction and discharge valves and actuators

4 Pipe and valve/equipment supports

5 PLC control system

6 Associated instrumentation

2.3.1.3. Disinfection and Bacteriological Testing Not Applicable

Commissioning Guideline Region of Niagara

Rev 00 Appendix A

Page A-8

2.3.1.4. Relevant Forms

Stage / Test Form ID Form Title Additional Notes Start-up G-01 Safety Compliance Form

G-02 Notification of Testing G-03 List of Attendees G-04 Deficiency List

P-11213-01-LL1 Equipment Start-up and SAT Form

Form completed during Start-up phase will be updated during SAT

P-11213-02-LL2 Equipment Start-up and SAT Form

Form completed during Start-up phase will be updated during SAT

P-11213-03-PR1 Room Start-up and SAT Form Low Lift Pump Room

Manufacturer’s commissioning forms

SAT P-11213-01-LL1 Equipment Start-up and SAT Form

Update form started under Start-up

P-11213-02-LL2 Equipment Start-up and SAT Form

Update form started under Start-up

Field Input/Output Test Report

Panel Test Report G-04 Deficiency List

G-05 Site Acceptance Testing Tracking

Training G-06 Equipment / Process Training Form

Functional Run Test

G-07 Functional Run Test G-04 Deficiency List

2.3.1.5. Test Highlights

Commissioning Guideline Region of Niagara

Rev 00 Appendix A

Page A-9

System Stage / Test Task

Low Lift Pumps

Start-up Equipment and piping flushing disinfection Pressure testing of suction and discharge piping Manufacturer’s installation inspection and tests as outlined in specification and as recommended Testing with service fluid (i.e. water) Testing of alarms and shutdowns Pump performance (flow & pressure) testing Testing with manual/hand controls Vibration testing Other Manufacturer required testing Manufacturer / Supplier Certification

SAT Contractor to complete equipment testing and demonstrations in presence of Owner and Consultant. Instrument testing, including I/O demonstrations for any equipment connected to the control panel. Alarm and shutdown testing for equipment Submit documentation including test forms, SAT documents, etc

Training Manufacturer / Supplier to provide (1) training session, (1) hour duration. Software SAT Completion of SCADA programming and SAT as it pertains to this

equipment. Functional Run Test

Region notifies MOECC that equipment is entering service. Testing under automatic (PLC) control. 7 day uninterrupted run-test for pumping system, as outlined in specifications including pumps and associated electrical and instrumentation systems. Submission of final O&M documentation and EAM data.

2.4. Site Acceptance Testing Tracking Refer to Form G-05 under Part 3 2.5. Training Training activities for equipment / processes are identified in the Commissioning Schedule. The Region’s Project Manager will issue meeting invitations to the Project Team Individuals identified for Operations, Maintenance, and Integrated Systems. Refer to Form G-06 under Part 3 for training requirements. This form will be completed for each training day and/or each process. Niagara Region staff attending training sessions will sign the form indicating that they received the necessary training . 2.6. SCADA Software SAT Refer to Part 3 for forms related to SCADA Software SAT 2.7. Facility Functional Run Test

Commissioning Guideline Region of Niagara

Rev 00 Appendix A

Page A-10

Refer to Form G-07 under Part 3 2.8. Commissioning Schedule Month Rev. Date

Sunday Monday Tuesday Wednesday Thursday Friday Saturday 1 2 3 4 5 6 7

Disinfection of Equipment Bacteriological Testing & Authorization to Proceed

8 9 10 11 12 13 14

Start-up of Equipment Region Witnessed Testing Equipment Training

15 16 17 18 19 20 21

Training Functional Run Test of Individual Equipment Software SAT

22 23 24 25 26 27 28 Software SAT Functional Run Test of System (Defined Test Period – e.g. 5 days)

29 30 31 Final O&M, EAM, As-Builts, and Mounted Single Line Drawing

Region Care and Control

2.9. In-service Date Refer to Form G-10 under Part 3 As each piece of equipment or process is placed into service the form will be distributed to all Commissioning Team members identified in Section 1.3

Appendix B Forms

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-1

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-2

Form G-01

Safety Compliance Form Contract Title Contract No. Date Test Duration Test 1. In order to ensure the safety of personnel during testing, Commissioning Manager(s) need to acknowledge, initial, and date this announcement.

Construction and Testing Safety rules must be followed. 2. Commissioning Manager(s) shall relay the announcement to all involved manufacturer representatives and sub-contractors, and ensure that they

acknowledge the test and safety rules. 3. Commissioning Manager is to complete this form prior to proceeding with testing.

Test Reference Description

Acknowledgement Comments Company/

Discipline Representative Initial Date

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-3

Form G-02

Notification of Testing Contract Title Contract No.

The following test is scheduled as shown

System/Test Test Date Test Duration

Organization Subcontractor/ Supplier Details Name Attending Comments Initial

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-4

Form G-03 List of Attendees

Contract Title Contract No System / Test Date

Attendee Supplier/Rep Name Role Date Completed Comments Sign-Off

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-5

Form G-04

Deficiency List Contract Title Contract No System Test Stage

No. Reference Description Date Completed Comments Sign-Off

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-6

Form G-05

SAT Tracking Form Contract Title Contract No Equipment / Process

Tag / Identification Components Included Spec

No. P & ID

No. Location Size (mm)

SAT Form Completed Date Sign-Off Comments

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-7

Form G-06

Equipment / Process Training Form Contract Title Contract No Date In-class � On-site �

Equipment / Process

1. 10. 2. 11. 3. 12. 4. 13. 5. 14. 6. 15. 7. 16. 8. 17. 9. 18.

Name (Print) Signature W & WW Section

Contractor’s Commissioning Manager

Signature

Contractor Administrator’s Commissioning Manager

Signature

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-8

Form G-07 Functional Run Test Tracking

Contract Title Contract No

Equipment / Process Tag

Test Duration

Test Start Date

Successful Completion Test Re-start

Date

Test Completion Date

Sign-off Comments Yes No

Note: For a Facility Functional Run Test input “Facility” in Column 1 If a test is to be re-started input as a separate line and indicate in the comments section the reason for the test failure

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-9

Form G-08

Field Input / Output Test Report Contract Title Contract No.

Contract Administrator’s Commissioning Manager

(Signature) (Date) Contract Administrator’s Commissioning

Manager

(Signature) (Date)

Niagara Region Representative (Signature) (Date)

Description I/O Tag I/O Address RR/SS/PP

Installation Checklist Documentation Review

Acc

epte

d Y/

N

Comments

Fiel

d D

evic

e D

efic

ienc

y A

ddre

ssed

Inst

alle

d at

cor

rect

I/O

Poi

nt

Inst

alla

tion

Acc

epta

ble

Cor

rect

Vol

tage

and

Pol

arity

Cor

rect

ly W

ired

N.O

. and

N.C

.

Cor

rect

On/

Off

or O

pen/

Clo

se

Stat

us

Cor

rect

DO

sta

rt/S

top

or

Ope

n/C

lose

Sta

tus

Cor

rect

Ana

log

Inpu

t/O

utpu

t Ra

nge

All

Labe

ls In

stal

led

SCA

DA

PLC

/PC

Inst

alla

tion

Acc

epte

d Y/

N

Fiel

d W

irin

g Sc

hem

atic

Cal

libra

tion

Repo

rt

Fina

lized

Sho

p D

raw

ing

Prov

ided

Oth

er

Mee

ts S

CA

DA

Sta

ndar

ds

Doc

umen

tatio

n A

ccep

ted

Y/N

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-10

Form G-09

Panel Test Report Contract Title Contract No.

Contract Administrator’s Commissioning Manager

(Signature) (Date)

Contract Administrator’s Commissioning Manager

(Signature) (Date)

Niagara Region Representative (Signature) (Date)

Panel Name Panel Tag

Installation Checklist Documentation Review

Acc

epte

d Y/

N

Comments

Pane

l FA

T D

efic

ienc

ies

Add

ress

ed

Inst

alla

tion

Acc

epta

ble

Func

tions

Cor

rect

ly

Pow

er W

irin

g In

stal

latio

n C

orre

ct

Fiel

d W

ire

Col

ours

mee

t Re

gion

al

Stan

dard

s

Fiel

d I/O

Wir

ing

Inst

alle

d C

orre

ctly

Fiel

d W

ire

Pass

es P

ull T

est

Net

wor

k Eq

uipm

ent

Inst

alla

tion

Spar

e Pa

rts

Prov

ided

Inst

alla

tion

Acc

epte

d Y/

N

Inst

alla

tion

Det

ails

Dra

win

g

Fiel

d W

irin

g Sc

hem

atic

Fina

lized

Sho

p D

raw

ing

Prov

ided

WA

N IP

Add

ress

Rec

orde

d

Cle

an o

f all

Deb

ris,

etc.

Doc

umen

tatio

n A

ccep

ted

Y/N

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-11

Form G-10

In-service Date and Care Assumption Date Tracking Form Contract Title Contract No Equipment / Process

Equipment / Process Tag Test Stage

Previous Test Req.

Complete

Area Operations

Manager (Initials)

In-service Date

CA Commission

Manager (Initials)

Date NR Assumes

Care Comments

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-12

Equipment Start-up and Site Acceptance Testing (SAT) Form Project Name: Contract No.:

Form No.: Equipment:

Equipment Details:

Type:

Location:

Tag No.:

Make and Model No.:

Serial No.:

Size:

Service:

Material:

Applicable Shop Drawing No(s):

Applicable Specification(s): Applicable Contract Drawing No(s):

START-UP This section is to be completed by the Contract Administrator’s Commissioning Manager. All demonstrations are to be completed by the Contractor. All forms required for start-up will be provided by the manufacturer / supplier and approved by the Contract Administrator’s Commissioning Manager. All completed forms are to be submitted to the Contract Administrator prior to setting Site Acceptance Testing dates

Item Reviewed for Completeness Date Status / Comments

Matches Shop Drawing

Matches Specification

Matches Contract Drawing

Reports Start-up report from manufacturer / supplier attached

Certificate of Site Acceptance by Manufacturer’s

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-13

representative

Testing by Manufacturer’s representative

Factory Acceptance Test Report attached

Equipment / Process disinfection completed successfully, and Bacteriological tests (if required) passed

Checks:

Setpoints:

Item Reviewed for Completeness Date Status / Comments

Equipment / process meets minimum and maximum design requirements as per the specifications

All required forms for start-up of the equipment / process have been completed and attached

Comments:

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-14

Start-up Sign-off (to be signed on site)

Manufacturer Date Consultant’s Commissioning

Manager Date

Contractor’s Commissioning Manager

Date Region Project Manager Date

Contract Administrator (Approval to Proceed to next stage)

Date

SITE ACCEPTANCE TESTING

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-15

(Site Acceptance Testing for specific equipment / process can only proceed once all the prerequisites for the equipment / process, including start-up, have been completed).

Item Reviewed for Completeness Date Status / Comments

All Start-up items have been successfully completed / addressed.

Matches Specification

Matches Contract Drawing

Reports Equipment SAT completed by Manufacturer / Supplier

SAT Report attached Certificate of Site Acceptance by Manufacturer’s representative

Factory Acceptance Test Report attached

Checks:

Setpoints:

Item Reviewed for Completeness Date Status / Comments

All required forms for the

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-16

equipment / process SAT have been completed and attached

Comments:

Site Acceptance Testing Sign-off (to be signed on site)

Manufacturer Date Consultant’s Commissioning

Manager Date

Contractor’s Commissioning Manager

Date Region Project Manager Date

Contract Administrator (Approval to Proceed to next stage)

Date

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-17

Room / Location Start-up and Site Acceptance Testing (SAT) Form Project Name: Contract No.:

Form No.:

Room / Location:

Chemicals Stored in Room

Room Hazard Classification

Applicable Shop Drawing No(s):

Applicable Specification No(s): Applicable Contract Drawing No(s):

Applicable Start-up and SAT Forms (attached)

This form is to be used for: spill containment; plumbing; low voltage electrical; access and egress; and general safety systems, and does not replace Process, Mechanical, Electrical, HVAC System or other Specialized Equipment or System Forms.

START-UP This section is to be completed by the Contract Administrator’s Commissioning Manager. All demonstrations are to be completed by the Contractor. All forms required for start-up will be provided by the manufacturer / supplier and approved by the Contract Administrator’s Commissioning Manager. All completed forms are to be submitted to the Contract Administrator prior to setting Site Acceptance Testing dates

Item Reviewed for Completeness Date Status / Comments

Chemical feed system is complete for this room / location

HVAC Start-up form is complete

Complies with Plumbing Shop Drawing(s)

Complies with Plumbing Specification(s)

Complies with Plumbing Contract Drawing(s)

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-18

Complies with Low Voltage Electrical Shop Drawing(s)

Complies with Low Voltage Electrical Specification(s)

Complies with Low Voltage Electrical Contract Drawing(s)

Complies with Electrical Shop Drawing(s)

Complies with Electrical Specification(s)

Complies with Electrical Contract Drawing(s)

Complies with Door Hardware Shop Drawing(s)

Complies with Door hardware Specification(s)

Complies with Door Hardware Contract Drawing(s)

Complies with Signage Shop Drawing(s)

Complies with Signage Specification(s)

Complies with Signage Contract Drawing(s)

Floor Drainage – Type, and floor slopes to drain and outside of containment

Cabinet and/or Shelving Work

Finishes – Floor, Wall, Ceiling

Windows and Doors (type), and Hardware

Labeling Safety Systems (Fire, Eyewash / Shower, Emergency Lighting, Alarms, etc.

Insect Screens Chemical Containment Tanks

Single Line Diagram As-built mounted as per specifications

All required forms for

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-19

Start-up of this location have been completed and attached

Comments

Start-up Sign-off (to be signed on site)

Manufacturer Date Consultant’s Commissioning

Manager Date

Contractor’s Commissioning Manager

Date Region Project Manager Date

Contract Administrator (Approval to Proceed to next stage)

Date

SITE ACCEPTANCE TESTING

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-20

(Site Acceptance Testing for specific equipment / process can only proceed once all the prerequisites for the equipment / process, including start-up, have been completed)

Item Reviewed for Completeness Date Status / Comments

All requirements for Start-up have been addressed / completed

All required forms for equipment / process SAT have been completed and attached

Comments:

Site Acceptance Testing Sign-off (to be signed on site)

Manufacturer Date Consultant’s Commissioning

Manager Date

Contractor’s Commissioning Manager

Date Region Project Manager Date

Contract Administrator (Approval to Proceed to next stage)

Date

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-21

Yard Piping Start-up and Site Acceptance Testing (SAT) Form

Project Name: Contract No.:

Form No.: Pipe Function:

Details:

Material:

Location:

Size:

Applicable Shop Drawing No(s):

Applicable Specification(s): Applicable Contract Drawing No(s):

START-UP This section is to be completed by the Contract Administrator’s Commissioning Manager. All demonstrations are to be completed by the Contractor. All forms required for start-up will be provided by the manufacturer / supplier and approved by the Contract Administrator’s Commissioning Manager. All completed forms are to be submitted to the Contract Administrator prior to setting Site Acceptance Testing dates

Item Reviewed for Completeness Date Status / Comments

Pipe Matches Shop Drawing

Pipe Matches Specification Pipe Matches Contract Drawing

Hydrostatic Pressure test successfully completed as per specifications

Swabbing successfully completed

Disinfection successfully completed

Bacteriological tests passed Authorization to connect provided by ORO

Chamber installation complies with specifications

Chamber installation complies with contract

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-22

drawings

Chambers comply with Shop Drawings

CCTV Inspection of sewers completed successfully

Deflection testing of sewer completed successfully

Pipe support complies with specifications

Tracer wire installed and continuity testing successful

Equipment / process meets minimum and maximum design requirements as per the specifications

All required forms for start-up of the equipment / process have been completed and attached

Comments:

Start-up Sign-off (to be signed on site)

Manufacturer Date Consultant’s Commissioning

Manager Date

Contractor’s Commissioning Manager

Date Region Project Manager Date

Contract Administrator (Approval to Proceed to next stage)

Date

SITE ACCEPTANCE TESTING

Commissioning Guideline Region of Niagara

Rev 00 Appendix B

Page B-23

(Site Acceptance Testing for specific equipment / process can only proceed once all the prerequisites for the equipment / process, including start-up, have been completed)

Item Reviewed for Completeness Date Status / Comments

All requirements for Start-up have been addressed / completed

All required forms for equipment / process SAT have been completed and attached

Comments:

Site Acceptance Testing Sign-off (to be signed on site)

Manufacturer Date Consultant’s Commissioning

Manager Date

Contractor’s Commissioning Manager

Date Region Project Manager Date

Contract Administrator (Approval to Proceed to next stage)

Date

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 1 of 16

GENERAL

1.1. Contractor Scope of Work

1.1.1. Contractor is responsible to provide a complete and functional Control System,

and the integration of this Control System into the existing SCADA WAN to

meet the Niagara SCADA standard. The scope of work is (but not limited) to

provide, install, wire, commission and start-up the following:

.1 Field instruments and transmitters, refer to specs section 13105

.2 PLC (RPU) Control Panel, refer to specs section 13911 and contract

drawings.

.3 New SCADA Network connection commission

.4 Wiring between field equipments and all Control Panels (including

Control Panels parts of equipment packages).

.5 Factory Acceptance Test (FAT)

.6 Site Acceptance Test (SAT) for hardware and software.

.7 Complete coordination with the Region’s SCADA System Integrator

(The Region’s SCADA System Integrator will be responsible for the

PLC and SCADA Node View computer programming and shall

participate and perform with Contractor the software SAT.)

1.1.2. During the construction phase Communication system down time is to be kept to

a minimum. Contractor to inform Region, and Operating Authority of

communication shutdowns, forty-eight (48) hours prior to any shutdown. Unless

otherwise agreed to by operations staff and Region the communication system

and control systems are to remain functional at all times. The Region and/or

Engineer reserves the right to deny, restrict (including time of day), and limit the

number and duration of permitted shutdowns.

1.1.3. SCADA System Integrator

.1 As a part of Contract, the SCADA System Integrator has to supply,

install, test, and commission the required programming for pump

station PLC (RPU), SCADA Node View Computer and new SCADA

screens at the Niagara Falls WWTP Station. The work shall be in

compliance with the process narratives and with the Region of Niagara

SCADA Standards (most actual version).

.2 The SCADA System Integrator Scope of supply work shall include

programming of the following systems:

a) Migrate the existing SCADApack and HMIprogram to new

PLC (RPU) and HMI’s installed within the new Electrical

room.

b) Complete the new programming associated with new pump

upgrading

c) New Screens for the SCADA,

d) The SCADA System Integrator must provide programming in

compliance with the process narratives and with the Region of

Niagara SCADA Standards (most actual version).

e) Develop, test, start-up and commission Compact Logix

software for the new PLC and HMI, iFix software for the new

SCADA network..

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 2 of 16

f) Develop, test start-up and commission the HMI software for

the pump station and SCADA, including alarming, historical

data collection and graphical displays.

g) PLC and SCADA Screens FAT testing.

h) PLC and SCADA Screens SAT testing.

i) Provide complete documentation (SCADA manual) at

completion of the project.

j) Supply twelve (12) hours of SCADA system training for the

Region staff.

k) Supply SCADA operation manuals (Qty.: 6), containing the

following sections:

1. Network Diagram

2. Process Control Narrative. This document will be

provided to Contractor by SCADA System

Integrator, end of the commissioning and start-up.

3. SCADA Node View Computer Operation including

screen shots

l) Provide and update the process control narrative in co-

operation with Consultant and the Region.

m) All other items remain the responsibility of the Contractor.

.3 Region’s SCADA System Integrator:

a) Hatch Ltd.

.4 All programs and applications created under the WWTP upgrades will

be owned by the Region of Niagara, with the following items:

a) The SCADA System Integrator shall not affix any copyrights

to any works. All licenses for software and applications to be

registered to the Region of Niagara.

b) The SCADA System Integrator must use the tools inherently

provided within the SCADA network, HMI and Compact

Logix programming software.

c) Programming to be based on functional block techniques,

ladder logic programming will not be accepted.

d) All configuration files and raw source files must remain intact.

e) The SCADA network PLC’s, HMI,s and Compact Logix

programs and applications must remain 100% editable by

Region staff using the programs native programming tools at

the conclusion of the contract.

f) Failure to meet all of the above requirements will result in

Substantial Completion being withheld.

1.2. Shop Drawings

1.2.1. Submit shop drawings within two (2) weeks of award of contract in accordance

with Division 16 and Contract Specifications.

1.2.2. Include:

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 3 of 16

.1 Schematic

.2 Wiring

.3 Interconnection Diagrams

.4 Network Architecture

a) Indicate patch panels, connect blocks, jacks, network cabling

and patch cords.

b) All communication equipment. Indicate models and part

numbers.

.5 Network Integration Plan

1.2.3. Additional Requirements:

.1 For devices containing dip switches, jumpers or programming keypads:

a) Functional description.

b) Performance data.

c) Physical, electrical and environmental requirements.

d) Location drawing.

e) Equipment descriptive literature.

f) Wiring details.

.2 For programmable equipment, communication links and networks,

submit bill of materials. Include in bill of materials hardware

documentation.

a) For hardware items include and clearly identify: Description,

make, model, part number and serial number.

b) For documentation include: Title and publisher for each item.

.3 For Programmable Equipment Hardware:

a) Product description for each item including:

1. Wiring and installation instructions.

2. Functional description.

3. Performance data.

4. Physical, electrical and environmental requirements.

5. Adapters and controllers.

b) Equipment layout drawings showing location of hardware,

boards, jacks, cables and terminals.

c) Related field tag numbers and wire numbers and module tag

assignment, to follow the Region of Niagara Tagging

standards.

d) Location and identifier and pin assignment of plugs, jacks, and

cables.

e) Switch settings and addresses, firmware.

f) Interconnection Diagrams including wiring, cables, jacks

between internal and external components, power supplies,

processors, communications modules, racks, I/O modules and

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 4 of 16

peripherals. Label terminals, jacks and pins. Show settings for

jumpers and switches. Show address for each hardware

module and point.

1.3. Related Work

1.3.1. Divisions 11 and 16 of the Contract Specifications.

1.4. Warranty

1.4.1. During the warranty period, as specified under contract documents, hardware

service shall be provided by factory trained service representative who shall be

on-site within 8 hours of a service request, 24 hours/day, 7 days/week, including

weekends and holidays.

1.4.2. The service representative shall be equipped with all necessary tools, testing

equipment, spare parts, and expertise to perform the service in one visit.

1.4.3. For each service call submit a report giving the following information:

.1 Part numbers, description for items replaced.

.2 Revised hardcopy listings of program or date changes.

.3 Hours worked by maintenance personnel, itemized by Specification

item number.

.4 Reason for the service call, and whether preventative, unscheduled or

corrective maintenance was carried out.

.5 Name of Region’s technician present during repairs.

.6 Explanation of the problem and solutions to the Region’s technician(s).

.7 Description of problem as discovered on arrival at site and itemized

report of activities performed to isolate and correct problem.

.8 Identification of any required actions to prevent similar future

occurrence.

.9 Name of attending maintenance representative, time of call and time of

arrival on site.

1.4.4. A single contact point shall be provided for all hardware such that the Region

need only call a single phone number irrespective of which hardware had failed.

1.4.5. The Region’s technician(s) may be present during repairs. Explain the problem

and solutions to the Region’s technician(s).

1.4.6. Free telephone support shall be provided for the total system and all parts

thereof during the warranty period

1.4.7. Spare Parts / Firmware & Software Upgrades:

.1. The Supplier should have access to a dedicated spare parts inventory

for each component provided. Parts shall be available within 4 hours of

a service parts request, 24 hours/day 7 days/week.

.2. Include key spare parts which are not normally available immediately

from stock, in the Recommended Spare Parts List.

.3. Provide, install, test and place in operation any firmware upgrades

issued by manufacturers to address shortcomings in delivered products

during the warranty period at no cost to the Region.

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 5 of 16

.4. Advise the Region/Engineer of software upgrades and new versions

which become available that would benefit or enhance the installed

system.

2. PRODUCTS

2.1. PLC Control Panel

2.1.1. Supply, install, test, and commission fully functional Allen Bradley Compact

Logix process automation controller, associated I/O modules and ancillary

equipment. The SCADA upgrade programming to be done by the SCADA

System Integrator (named by Consultant) under a separate contract..

2.1.2. Allow a minimum of four (8) weeks for programming of the Compact Logix

PLC, HMI and SCADA screens, following hardware delivery by the contractor.

2.1.3. Provide all interconnecting cables between PLC and other networking

components as required for a complete system.

2.1.4. Provide all RS-232, RS-485, and Ethernet cables, and any other required

communication cable as required for a complete network.

2.1.5. Allen Bradley COMPACT LOGIX components (minimum quantities), and

communication equipment.

.1 Contractor is responsible for verifying the quantities contained in the

following table, and for all additional components, cables, etc. required

to complete the work as defined in the specifications and on the

drawings. Quantities listed in a list/table (as the above sample) to

include all COMPACT LOGIX components to be installed in this

application.

.2 Allow 20% spare I/O points for each signal type. Unless otherwise

noted in the Contract Drawings the PLC I/O rack shall be 80% full,

leaving 20% spare.

.3 If the second additional bank of I/O is required, provide an other 1769-

PA4 power supply and the corresponding Expansion Cable and End

Cap.

.4 All hardware not specifically identified in Section 2.1 remains the

responsibility of the contractor, including but not limited to network

and interconnecting cabling, network jacks, patch cords, couplers,

adapters to provide a fully functional control system.

2.2. Control Devices

2.2.1. AC Control Relays (Qty.: As Required)

.1 Universal pole type: electrically held with 3 poles, convertible from NO

to NC by changing wiring connections. Coil rating: 120 V, 3 VA.

Contact rating: 120 V, 10 A.

.2 Manufacturers:

a) Allen-Bradley 700HA,

b) Omron

c) Potter & Brumfield

d) Square D.

2.2.2. Solid State Timing Relays (Qty: As Required)

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 6 of 16

.1 Construction: AC operated electronic timing relay with solid-state

timing circuit to operate output contact. Timing circuit and output

contact completely encapsulated to protect against vibration, humidity

and atmospheric contaminants.

.2 Operation: on-delay or off-delay, as indicated on drawings.

.3 Potentiometer: self contained to provide time interval adjustment.

.4 Supply Voltage: 120 Vac, 60 Hz.

.5 Temperature range: minus 20º C to 60º C.

.6 Output contact rating: maximum Voltage 120 VAC or dc. Current:

EEMAC B300.

.7 Timing ranges: minimum 1.0 s, maximum 60 s, unless otherwise

specified.

.8 Manufacturer:

a) Allen-Bradley 700HA,

b) Omron

c) Potter & Brumfield

d) Square D.

2.2.3. Interposing PLC Panel Relays (Qty: As Required)

.1 Entrelec. Din-Rail mounted.

120 VAC relays

a) Rated Voltage: 120VAC.

b) Power: 1VA.

c) Rated Current: 9mA.

d) Drop-out Voltage: 20VAC.

e) RB121AR2, P/N: 010 168.01.

24VDC Relays:

f) Rated Voltage: 24VDC.

g) Power: 0.31W.

h) Rated Current: 13mA.

i) Drop-out Voltage: 2.4VDC.

j) RB122, P/N: 010 159.07

2.2.4. Pushbuttons (Qty.: As Required)

.1 Oil tight. Operator extend type 30mm diameter. Black with NO and

NC 120 V contacts rated at 720 VA ac, labels as indicated. Stop

pushbuttons coloured red. Start pushbuttons coloured green. Reset

buttons coloured black.

.2 Manufacturers:

a) Allen-Bradley 800T,

b) Cutler Hammer,

c) Square D.

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 7 of 16

2.2.5. Selector Switches (Qty: As Required)

.1 Maintained unless otherwise indicated, labeled as indicated, heavy

duty, 30mm diameter oil-tight standard operators, contact arrangement

as indicated, rated 120 V, 720 VA ac.

.2 Provide number of positions as shown on the drawings.

.3 HAND-OFF-AUTO switches to be break-before-make.

.4 LOCAL-REMOTE switches to be make-before-break.

.5 Allen-Bradley 800T, Cutler Hammer, Square D.

2.2.6. Indicating Lights (Qty: As Required)

.1 Oil-tight, transformer type, 30mm diameter, lens colour: as indicated,

supply Voltage: 120V, labels as indicated. Push-to-test function on all

pilot lights. Provide LED-style lamps for CP-01.

.2 Manufacturers:

a) Allen-Bradley 800T,

b) Cutler Hammer,

c) Square D.

2.3. Control and Relay Panels

2.3.1. Manufactured Units.

.1 Control panels: Complete working system with instruments, meters,

indication lights, alarm annunicators, protection and control relays,

programmable logic controllers, transducers, contractors, switches,

auxiliary devices and similar items.

.2 Arrangement of instruments and devices (face-mounted as well as rear-

of-panel mounted): Allow sufficient access for maintenance.

.3 Mounting Height: Indicating devices, controls and instruments between

1000 mm and 2000 mm above finished floor. Allow for housekeeping

pads, pedestals and similar items.

.4 Side or back face mounted devices: On removable backplate. Direct

mounted devices will not be accepted.

.5 Nameplates: Removable, lamacoid, to identify panel and equipment

function, letters minimum 6 mm, fasten with stainless steel screws.

Grind screws flush on inside of panel so no sharp edges protrude.

.6 Supply panels complete with wiring and header piping connections.

2.3.2. Enclosure

.1 Dry areas: Rigid, dead front, 2 mm steel sheet, NEMA/EEMAC 12

unless otherwise noted.

.2 Wet and damp and process areas: Rigid, dead front, 2 mm, 304

stainless steel sheet, NEMA/EEMC 4X, with stainless steel hardware.

.3 Corrosive areas: Rigid, dead front, moulded fibreglass reinforced

polyester, NEMA/EEMAC 4X.

.4 Hazardous areas: Assembly and components suitable for application in

specific areas indicated.

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 8 of 16

.5 Visible welding seams: Not acceptable.

.6 Back plate: 2.7 mm stainless steel sheet mounted on four 10 mm collar

studs minimum with stainless steel hardware.

.7 Doors: Removable, continuous piano type hinges, three point latching,

lockable handle, keyed alike.

.8 Print pocket: On inside of door, rigid, for storing manual, layout

drawings and wiring diagrams.

.9 Finish: Steel sheet, phosphatize, zinc chromate prime, baked enamel

epoxy coated inside and outside, matte white interior and ANSI 61 grey

exterior. Follow the Region of Niagara standard requirements.

2.3.3. Internal Assembly.

.1 Internal component and equipment mounting: On hinged sub-chasses,

racks and back plates, arranged for ease of access and removal.

.2 Pans and rails: For mounting terminal blocks, relays, contactors, wiring

and similar devices.

.3 Luminaire: For floor mounted panels, fluorescent, guarded, with light

switch..

.4 Receptacle: For floor mounted panels, 120 V AC, 14 A, duplex, U

ground type, complying with Specifications.

.5 Power supply disconnecting devices: Moulded case circuit breakers,

5,000 A symmetrical interrupting capacity for each instrument

requiring 120 VAC supply.

.6 Instrument disconnecting devices: To disconnect incoming power

supply sources and individual feeder circuit supplies, moulded case

circuit breakers.

.7 Identification: Identify switches, circuit breakers, components, terminal

blocks, power supplies, relays, wiring and similar devices.

.8 Warning signs: Identify sources of supply. Comply with Specifications.

.9 Wiring ducts: Maximum 50% fill, minimum 75mm wide, 100mm high,

with snap-on cover, by Panduit Canada.

2.3.4. Terminal Blocks

.1 Terminal blocks: Modular, rated 600 V 25 A minimum, tubular clamp

type, 35 mm DIN rail mounted, individually removable, with

removable insulating covers on exposed terminals carrying above 50 V,

SAK Series by Weidmuller Ltd., UL Series by Phoenix Terminal

Blocks Ltd., WK/4 Series by Wieland Electric Ltd. And Entrelec.

.2 Mounting: 150 mm minimum wiring space between rows of terminal

blocks.

.3 Arrangement: Separate terminals and wiring by class of signal. Comply

with Section 16120.

.4 Field instrument connections to SCADA/RPU/I/O: Terminal blocks,

type SAKC4 complete with test sockets both sides and type PS 2.3 test

plug by Weidmuller Ltd.

.5 Spares: Minimum 20% spare terminals for each signal class.

2.3.5. Instrument Grounding

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 9 of 16

.1 Ground: Full length tin plated copper ground bus or ground stud with

tin plated copper lugs at ends, suitable for minimum #4 AWG ground

wire.

.2 Instrument cable shields and equipment ground conductors

connections: With screws and clamp washers.

2.3.6. Insulating Barriers

.1 Barriers: Covering exposed terminals and terminal blocks against

inadvertent contact.

.2 Warning labels: Lamacoid with 3 mm white letters on red background,

on front of compartments where multiple power sources are present.

2.3.7. Internal Wiring

.1 Comply with Specifications.

.2 To control or eliminate electrical noise in wiring systems, group wires

of compatible signal or power levels together and run separately or

electromagnetically isolated from wires of incompatible signal or

power level.

.3 Install low level analogue signals, 50 V DC maximum or 4-20 mA, and

digital signal operating at 50 V AC or DC maximum, in raceway

electromagnetically isolated from high power or signal wiring. Comply

with wiring separation and isolation guidelines recommended by

instrument and RPU equipment manufacturers.

.4 Wiring type: except shielded instrumentation wiring, copper, 600 V,

single conductor, seven strands minimum, heat and flame-retardant

type insulation. #14 AWG minimum for control circuits, #12 AWG

minimum for power circuits and #10 AWG minimum for current

transformer circuits.

.5 Wiring devices on hinged doors or panels: Extra flexible, forty-nine

strands minimum, harnessed nylon cable ties.

.6 Instrumentation Wiring:

.7 Comply with Specifications.

.8 Wiring ducts: Maximum 50 % fill, with snap-on cover, by Panduit

Canada.

.9 Identify each conductor, including spares, with a unique alphanumeric

designation to facilitate troubleshooting and maintenance.

.10 Identify PLC/RPU wiring at terminal blocks and connection points

with PLC terminal (I/O) address numbers. Comply with Regional

Standards

.11 Wire markers: Identify wiring at both ends with heat shrink type,

indelible machine printed wire markers. Electrovert Type Z or

approved equal and comply with Regional Standards.

.12 Wiring terminations: On terminal blocks only.

.13 Spare I/O points: Terminate on terminal blocks.

.14 Spare terminal blocks: Minimum 20 % spare terminals for each signal

class.

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 10 of 16

.15 Maximum number of conductors under one terminals for each signal

class.

.16 Insulating barriers: Covering exposed terminals and terminal blocks

against inadvertent contact.

2.3.8. Acceptable Manufacturers:

.1 Hammond,

.2 Ralston,

.3 Rittal.

2.4. Control Circuit Breakers

2.4.1. Quantity: as required

2.4.2. Rail mounted, thermomagnetic, toggle operated.

2.4.3. Manufacturers:

.1 Entrelec,

.2 Weidmuller,

.3 Phoenix.

.4 Westinghouse

2.5. Uninterruptible Power Supply

.1 Provide one Uninterruptible Power Supply (UPS) suitable for powering

and protection of COMPACT LOGIX PLC, instruments, and

communication equipment during the main power source outage.

.2 UPS shall be on-line, no-break, batteries continuously in circuit with

static bypass loads. Minimum rating 1500 VA, 120 VAC, 60 Hz and

minimum 15 minutes run time, unless otherwise specified.

.3 Surge protection shall comply with Category B, ANSI/IEEE C62.41

and 45 and shall have automatic low and high Voltage protection.

.4 Battery: sealed, maintenance free, minimum 6 years life and LED

warning light for battery replacement.

.5 UPS to be supplied with one alarm card with following alarm contacts

a) UPS fault,

b) UPS low batteries,

c) UPS not powered.

.6 Contractor to use UPS to power communication equipment.

.7 Manufacturers:

a) Eaton PW 9130L1500T-XL (c/w alarm relay interface card)

2.6. General Purpose Receptacle

2.6.1. Specification grade, 15 A, 125 Vac, duplex, flush, brown or black,

2.6.2. Manufacturers:

.1 Hubbell 5252-BLB

.2 Or equal.

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 11 of 16

2.7. VDC Power Supply

.1 Input: 120 VAC, 60 Hz (fused).

.2 Output: 24 VDC, 5A.

.3 Protections: short circuit, overload.

.4 Quantity: as required

.5 Manufacturers:

a) Hammond

b) Weidmueller

2.8. Communication System

2.8.1. All equipment for a fully functional system is to be supplied by the contractor

unless otherwise specified.

2.8.2. Contractor to supply, install, test, and commission the cable between the new

PLC Control Panel and the existing Ethernet Hub (Core Switch). Provide Surge

protection, as required.

2.9. Software and Licenses

2.9.1. All licenses provided by contractor and shall be registered to the Region of

Niagara.

2.10. Isolated Ground

2.10.1. Provide a separate ground system for the instrumentation circuits, isolated from

the main 120VAC power system ground.

2.10.2. Provide a #2/0 AWG insulated green with yellow tracer TWH conductor,

connection from the electrical system ground grid to the isolated ground buss in

PLC panel.

3. EXECUTION

3.1. Installation

3.1.1. Supply, install, test, and commission PLC, communication equipment, and

associated equipment to ensure functionality of complete network and control

system at the Niagara Falls WWTP and Pumping Station. Report all

construction defects which will affect the progress of the work to the Region and

Engineer immediately.

3.1.2. The drawings have been developed on a conceptual basis. Provide devices,

components and accessory items necessary for the operation of the control

system. Install communication jacks and associated components as required for

a fully functional network at the Niagara Falls WWTP.

3.1.3. The network architecture design is to be submitted for review to the Engineer,

two (2) weeks after the award of contract.

.1 Submit all product data and panel layouts for review.

3.1.4. Existing water distribution systems to remain functional at all times. Shut down

of any of the existing equipment or system only to be performed under the

direction of the Region and Engineer.

3.1.5. Delays due to lack of coordination will not be accepted.

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 12 of 16

3.1.6. All replaced or extra equipment to be delivered to the Region upon project

completion.

3.1.7. Communication system and PLC Panels to be completed, tested, and operational

prior to Site Acceptance Testing and commissioning.

3.2. Testing

3.2.1. Contractors testing Requirements

.1 Contractor to complete an I/O checkout with I&C contractor and

Engineer present.

.2 Contractor to complete a Site Acceptance Test (SAT) with the SCADA

System Integrator in the presence of the Client and the Engineer

.3 Contractor to commission station with the SCADA-SI, Engineer and

the Client.

3.2.2. SCADA System Testing Requirements

.1 Contractor to complete an I/O checkout with the SCADA System

Integrator and Engineer present.

.2 I&C-SI to complete a Factory Acceptance Test (FAT) with the Client

and the Engineer present.

.3 I&C-SI and SCADA-SI to perform the SAT (hardware and software,

including the communication to WWTP plant in presence of the

Engineer and the Client.

3.3. Wiring and Cabling Standards

3.3.1. General Wiring

.1 Wires and cables shall always be installed in such a manner as to

reduce EMI interference and crosstalk between conductors resulting in

clean signals and accurate transfer of data and information through the

SCADA system.

.2 Wires that contain different types of signals and signal levels shall be

separated to reduce noise problems. In order to minimize crosstalk,

cables carrying different signal levels shall not be mixed in the same

conduit or cable tray. Where runs must cross perpendicular, the runs

shall be separated by a minimum distance of 75mm.

.3 High voltage power feeds of 600V and above shall be separated from

signal wiring and low voltage control wiring by running in a separate

conduit. If signal wires must run parallel with high voltage wires, at

least 300mm shall separate the runs. Signal wires shall be in rigid PVC

or metallic conduits and not in a cable tray anytime the path must run

parallel with high voltage wires. Runs which cross high voltage cables

shall be at 90° to reduce EMI interference generated by the high

voltage cables.

.4 Instrumentation signal and thermocouple extension wires shall be

installed in separate raceways and conduits from power and control

wiring. Instrumentation and control wiring conduits shall be separated

from power lines carrying more than 100VAC by a minimum distance

of 300mm for parallel runs. All analog signals in one cable or conduit

shall be of the same signal type.

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 13 of 16

.5 As far as is practicable, all wiring shall be continuous form origin to

panel termination without splices in intermediate pull boxes or splicing

chambers. All spare external wire shall be labeled and terminated on

terminal blocks. Field device wiring shall not be directly connected to

I/O modules.

3.3.2. AC Power Wiring

.1 All AC power wiring is to be a minimum #12 AWG multi-stranded

copper. The connection to the common supply, typically though a

circuit breaker, for each individual field device circuit shall be wired

through a fuse to ensure that a wiring fault of one field device does not

adversely affect the operation of other devices sharing the same power

supply.

.2 The colour convention for AC power wiring shall be as follows.

a) 600VAC, 3 phase:

1. Phase 1: Red

2. Phase 2: Black

3. Phase 3: Blue

b) 208VAC, 3 phase:

4. Phase 1: Red

5. Phase 2: Black

6. Phase 3: Blue

c) 240VAC, 3 wire:

7. Hot: Black

8. Hot: Red

9. Neutral: White

d) 120VAC:

10. Hot: Black

11. Neutral: White

12. Ground conductor: Green, always.

.3 The conductor designation is that green conductors are always at

ground.

.4 AC power wiring shall be of the following characteristics, or otherwise

approved by the Region of Niagara.

a) Cable Type: T90

b) Description: Multi-stranded bare copper, flame retardant PVC

compound, overall nylon covering

c) Application: Exposed or concealed wiring in raceways (except

cable troughs) in dry or damp locations

d) Gauge: #12 AWG (minimum)

e) Spec: CSA Spec. 22.2, No.75; UL Spec. No.83

f) Temperature: -10°C to +90°C dry, +75°C wet, +60°C exposed

to oil

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 14 of 16

3.3.3. AC Digital Signals

.1 The 120VAC digital I/O field cabling is to be a minimum #14 AWG

stranded copper. The connection to a common 120VAC supply,

typically though a circuit breaker, for each individual field device

circuit shall be wired through a fuse to ensure that a wiring fault of one

field device does not adversely affect the operation of other devices

sharing the same power supply.

.2 Whenever AC digital signals are transmitted between two controllers,

interposing relays shall be used to provide a dry contact interface. The

topology of solid state output to solid state input and/or the use of pull

up or pull down resistors is to be avoided.

.3 The colour convention for AC control wiring shall be as follows.

a) Control: Red

b) Neutral: White

c) Hot: Black

d) Ground: Green

.4 The conductor designation is that green conductors are always at

ground.

.5 AC digital signal wiring shall be of the following characteristics, or

otherwise approved by the Region of Niagara.

a) Cable Type: T90

b) Description: Multi-stranded bare copper, flame retardant PVC

compound, overall nylon covering

c) Application: Exposed or concealed wiring in raceways (except

cable troughs) in dry or damp locations

d) Gauge: #14 AWG

e) Spec: CSA Spec. 22.2, No.75; UL Spec. No.83

f) Temperature: -10°C to +90°C dry, +75°C wet, +60°C exposed

to oil

3.3.4. DC Digital Signals

.1 General

a) Low voltage DC digital signals are typically from remote

isolated contact closures conducting less than 10mA at

48VDC. DC signals are to be installed with multi-stranded

copper wire minimum #16 AWG. Device change of state shall

be actuated by powering and un-powering the positive side of

the 24VDC circuit. All of the negative connections of the

circuit shall be tied together. Switching elements on the return

circuit is not permitted.

b) The power supply connection for each individual field device

circuit shall be wired through a fuse to ensure that a wiring

fault of one field device does not adversely affect the

operation of other devices sharing the same power supply.

Whenever DC digital signals are transmitted between two

controllers, interposing relays shall be used to provide a dry

contact interface. The topology of solid state output to solid

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 15 of 16

state input and/or the use of pull up or pull down resistors is to

be avoided.

.2 Colour Coding

a) The colour coding for digital control wiring in the field shall

be as follows.

1. Control: Dark Blue (+); Light Blue (common)

b) The colour coding for DC control wiring inside panels shall be

as follows.

1. Control: Brown (+); Yellow (common)

3.3.5. Analog Field Device Wiring

.1 Analog signals are typically 4-20mA inputs received from remote

devices and 4-20mA outputs transmitted to remote control elements.

Analog signal wiring is to be twisted pair shielded wire. Individual

signal conductors shall be multi-stranded copper wire. When multi-pair

cabling is provided, each pair must be individually shielded and an

over-all cable shield must be included. Shield shall be continuous foil,

providing 100% coverage including a drain wire in continuous contact

with the shield. The drain wire shall not be used as a control signal

conductor.

.2 Each pair is to consist of one white and one black conductor. The

colour convention shall be as follows.

a) Positive: White

b) Negative: Black

.3 Each pair’s shield drain wiring shall be terminated to the isolated DC

ground point which shall be the only electrical connection to the shield.

The shield must retain its electrical isolation though junction boxes, etc.

by the use of insulating sleeves and dedicated terminal block

assignments. At the field device, the shield must be insulated and left

floating. Signal wiring shall be segregated from control power wiring

and functionally grouped together. Low-level analog signals of 100mV

or less shall not be combined with digital input or control output wiring

nor shall they be intermixed in the same bundle. All DC signal wiring

shall always be segregated from AC wiring by a minimum of 300mm

clearance between conduits. Analog field shall be wired such that there

is only one series pathway for the signal. Field devices shall include

electrical isolation as necessary to ensure accurate signal transmission

from/to the field device to/from the field controller.

.4 The power supply connection for each individual field device circuit

shall be wired through a fuse to ensure that a wiring fault of one field

device does not adversely affect the operation of other devices sharing

the same power supply. DC analog field device wiring shall be of the

following characteristics, or otherwise approved by the Region of

Niagara.

a) Manufacturer and P/N: Belden #8719

b) Description: Twisted shielded pair

c) Gauge: #16 AWG

d) Rating: 600V, 80°C

Regional Municipality of Niagara Division 13

South Side Low Lift SPS Upgrades PLC Control Panels and Communication

Contract RN #17-04 Section 13911

Hatch Ltd. Page 16 of 16

e) Conductors: 16-stranded copper

f) Shield: Beldfoil aluminum-polyester shield

g) Drain wire: Bare #18AWG copper drain wire

3.3.6. Wiring Identification and Labeling

.1 Wiring identification and labeling is to be implemented in order to

clearly identify each conductor installed within the Region of Niagara

SCADA system with the goal to facilitate troubleshooting and

maintenance. All conductors, including spares, are to be identified at

each end and at any connection, termination, junction box, pull box or

intermediate manhole with the Region of Niagara labels. Labels shall

be identified by machine printed labels. Hand printed labels are not

acceptable. Labels shall be oriented for easy readability. Each

conductor originating at the RPU shall be defined with a unique

alphanumeric label as defined in the Region of Niagara Field Wiring

Tagging standards.

.2 Each conductor originating at control panels and lighting panels shall

be defined with a unique alphanumeric label as defined in the Region

of Niagara Field Wiring Tagging standards. Wiring markers and labels

shall be of the following characteristics, or otherwise approved by

Region of Niagara.

a) Manufacturer and P/N: Thomas & Betts, E-Z-Code

b) Description: Printable self-laminating, self-adhesive markers

c) Colour: White background with black lettering

d) Material: Vinyl plastic or polyester film suitable to

environment

.3 Each wire marker shall be sleeved with clear heatshrink tubing

ensuring maximum protection of the label against oils, grease, water,

chemicals and other foreign matter.

3.4. FIELD QUALITY CONTROL

3.4.1. Perform tests in accordance with Divisions 13 and 16.

3.4.2. Depending upon magnitude and complexity, divide control system into

convenient sections, energize one section at a time and check out operation of

section.

3.4.3. Upon completion of sectional test, undertake group testing.

3.4.4. Check out complete system for operation sequencing.

3.4.5. Submit to Engineer one (1) copy of test results.

3.4.6. Provide a written list of all passwords, keywords, serial numbers, and

configurations that are encountered during the installation of the operating

system and application software.

3.4.7. Assign all warranties, licenses and product registration to the Region

(Contractor to confirm Region’s contact information for product registration).

3.4.8. Turn over to the Region all installation software, user manuals, accessory cables,

calibration units, or any other material accompanying the installed equipment.

END OF SECTION