Page 1: The project manager is responsible for the serial product cost

1 Itzhak Ben-Levy LEAN Expert ©

The project manager is

responsible for the serial

product cost

Itzhak Ben Levy - LEAN Expert

972-523579166

[email protected]

www.benlevy.co.il

June 2012

Page 2: The project manager is responsible for the serial product cost

2 Itzhak Ben-Levy LEAN Expert ©

The 2 customers of the

Project manager

• The external customer - determines

– Performance

– Time schedule

– …

• The internal customer, (CEO) - determines

– Cost

– Quality

– …..

Page 3: The project manager is responsible for the serial product cost

3 Itzhak Ben-Levy LEAN Expert ©

ONCE

PRICE = PROFIT +COST

What the

customer

pays

"by product "

of the design

Determined

by the

corporate

Page 4: The project manager is responsible for the serial product cost

4 Itzhak Ben-Levy LEAN Expert ©

NOW

COST = PROFIT - PRICE

Determined

by the

corporate

Determined

by the

competitors Determined

to the project

manager

Page 5: The project manager is responsible for the serial product cost

5 Itzhak Ben-Levy LEAN Expert ©

The Traditional way

I cant assemble it

Too many parts It is

expensive Nobody gave me

The target cost

The requirements

were changed

Page 6: The project manager is responsible for the serial product cost

6 Itzhak Ben-Levy LEAN Expert ©

Who has the Biggest Effect on Costs

production

Development

Page 7: The project manager is responsible for the serial product cost

7 Itzhak Ben-Levy LEAN Expert ©

How the engineer know

how to design?

Casting Welding

Machining Forging

Sub

contracting Riveting

The cost target determines it

Page 8: The project manager is responsible for the serial product cost

8 Itzhak Ben-Levy LEAN Expert ©

Design to Cost

Conceptual

Design

Target

cost

Target

cost

Preliminary Design

DRR

Changing

concept,

Architecture

PDR

NO

NO

Changing

Preliminary

Design

Page 9: The project manager is responsible for the serial product cost

9 Itzhak Ben-Levy LEAN Expert ©

Cost Reduction workshop

Project

manager

DFMA Tools Facilitator

Challenge the design

Multidisciplinary

Team

• Requirements

• Architecture

• Technology

• Assembly

• Reuse

• COTS

• Standards

• Symmetry

• Tolerances

• No. of Parts

• Tests

• Commonality

Page 10: The project manager is responsible for the serial product cost

10 Itzhak Ben-Levy LEAN Expert ©

Not

important

Important

Low High

Requirements

(QFD)

Accept all

Consider to

delete delete

challenge

Implementation

Cost

(DTC)

Reduce requirements And cost

Page 11: The project manager is responsible for the serial product cost

11 Itzhak Ben-Levy LEAN Expert ©

Engineering

Requirements Reduction Cost Reduction

Supplier

Suppliers costs reduction

Costs drivers

Requirements

Priorities

Page 12: The project manager is responsible for the serial product cost

12 Itzhak Ben-Levy LEAN Expert ©

Description$hr

1sliding tube material 100

2sliding tube assy, 14

3INER BODY 130

4GLEND120

5NUT8012

6ORIFICE CAP80

7DOWEL 4804

8SPACER2007

9RING80

10tests300

11

total117037

How to integrate the production and

procurement into development process

The project manager should require

a real cost status in each gate

Multidisciplinary

Team