Click here to load reader
Upload
jack-wallace
View
216
Download
3
Embed Size (px)
Citation preview
22 renewable energy focus January/February 2009
Wind/Operation & Maintenance
The problem with O&MFRANK MASTIAUX, CEO OF E.ON CLIMATE AND RENEWABLES
RECENTLY SAID THAT IF COMPANIES SUCH AS E.ON ARE TO REALISE
THEIR PROJECT PIPELINES AND GET MW ON THE GROUND, THE
WIND INDUSTRY HAS TO MOVE FROM “BOUTIQUE TO TRULY
INDUSTRIAL LEVELS OF OUTPUT”. BUT AS THIS HAPPENS AT AN EVER
INCREASING RATE CREDIT CRUNCH OR NO CREDIT CRUNCH, HOW
CAN PROJECT DEVELOPERS AND TURBINE MANUFACTURERS ENSURE
THAT THE TWIN DEMONS OF POOR TURBINE RELIABILITY AND HIGH
COSTS OF O&M BOTH WELL DOCUMENTED DO NOT CONSPIRE
TO REDUCE THE POTENTIAL SCALE OF WIND POWER?
renewable energy focus January/February 2009 23
Wind/Operation & Maintenance
Over the next few issues In a new, regular, column, Renewable Energy Focus
will look at various aspects of O&M.
In the first installment, Matthew Jackson and Stephen Rogers from the Arthur
D. Little consultancy suggest how Offshore wind can overcome its various
obstacles (see pages 24-27).
But first, Jack Wallace, wind turbine technical advisor with US-based Frontier
Pro Services, asks whether extended periods of downtime might not just be a
problem of faulty turbines, but rather on occasion be down to the lack of exper-
tise – and poor attitude – of the O&M teams themselves…
Downtime and your O&M team – turbine availability begins at home
With all the various and uncontrollable causes of turbine downtime that
wind park owners and operators are all too familiar with, there remains a
frequently overlooked, entirely manageable cause of turbine downtime:
the operations and maintenance (O&M) team.
The most important issue for any wind park operator is to ensure the
turbines are available when the wind is on. As wind parks proliferate and
turbine technology becomes increasingly complicated, the shortage of
qualified wind energy technicians is taking a significant toll on downtime.
The stress on O&M that leads to turbine downtime takes many forms.
Insufficient training, poor employee motivation, engineering problems,
over-complicated and over-controlled procedures, lack of a sense of
urgency, as well as the O&M team’s failure to apply an appropriate atten-
tion to detail.
The most important success factor for any wind park operator is turbine
availability – when the wind is blowing, the blades must be turning. The
cost of downtime from O&M inefficiencies can be difficult to calculate.
The difference is often hidden; meaning that many days of wind can hide
one day of a turbine being off line.
However, these outages add up to significant lost revenue when averaged
over the course of a year or the lifetime of the wind park. Wind parks that
deliver superior financial returns typically have well-trained, highly moti-
vated O&M teams that are driven by incentives crafted to ensure the
blades will turn whenever the wind is blowing.
As a wind technician and field consultant for more than 20 years, I have
heard and seen some mind-boggling and maddening things. Once a few
years ago, I was discussing a customer’s O&M challenges with him, and he
told me in all sincerity that “wind is our enemy.” That was as backward and
disheartening a thought as I could imagine!
So, I began to talk with him and his team further to understand what had
them all so frustrated. I discovered that they were understaffed or staffed
with unqualified people, and that the O&M team’s efforts were unappreci-
ated insofar as their often times extraordinary service efforts were not
acknowledged or recognised in anyway.
Unrecognised for their work to keep the turbines up (or down!), their
motivation to answer middle of the night calls to reset faults was clearly
waning – and wind had become the enemy.
It is true that a good portion of downtime on wind parks is related to the
engineering of the wind turbine. Major component failures are usually not
the fault of an O&M team. If a wind turbine component is poorly engi-
neered, it will make itself known very quickly to those in the wind industry.
About the only area of design that allows field efforts to affect reliability
is in the control system. Today’s wind turbine control systems can be over
stacked with complexity. The turbine controllers are over protective,
complicated and not user-friendly. Such controllers make troubleshooting
difficult, especially if the wind turbine’s theory of operation is not made
bluntly evident.
But if you have a specific wind turbine, or wind park, then that is what you
get. That decision is a 20-50 year decision. It is final. In all probability no one
is going to be replacing that turbine with another design anytime soon. So,
the wind park operator needs to change his mindset from the list of prob-
lems inherent in the turbine’s design to creating a best-in-class operations
plan for keeping the turbines running. Eventually the engineering problems
will be worked out, and all that will be left to fix will be up to you.
For years I drove past a wind park that always had many machines off. I
assumed that the turbine had a bad design and that that was the reason
for such poor operations. Ten years later, and I am now running that wind
park with a team of my technicians. The problem was not design. It was
operator motivation. The operator did not try very hard. Today, that same
wind park is now operating in its 23rd year, and running well.
Maybe the manufacturer will help you get the machines running, maybe
they won’t. Regardless, the reputation of your wind park is up to you. You
know if you are trying or not, and so do your co-workers. Making the
machines run is priority one. Yes, it’s challenging work; but it is the work
of the O&M team. We are not talking wind turbine efficiency here. We are
talking about reliability and run time. If you can keep them running in
wind then you are doing your job. All incentives, recognition, processes
and procedures must be in line with this fundamental objective: the wind
turbines must be available when the wind is on.
As far as efficiency problems go, they are engineering problems and have
to be built in. If you find yourself with time to worry about efficiency – that
is icing on the cake. The bulk of the problem, though, is ensuring the
turbines are running.
I have worked with many different types of wind turbines. The number one
cause of nuisance faults causing downtime are controller issues. Once you
have the controllers working properly, then the next most common cause
of downtime is technician-related.
“Wind parks that deliver superior financial
returns typically have well-trained, highly
motivated O&M teams that are driven by
incentives crafted to ensure the blades will
turn whenever the wind is blowing.”
Jack Wallace, Frontier Pro Services
24 renewable energy focus January/February 2009
Wind/Operation & Maintenance
Controllers for wind turbines are becoming major technical innovations.
Turbines are using controllers with thousands of parameters. Any little burp
causes the entire machine to shut off requiring a reset, either remotely or
an onsite reset. If it is the end of the day, windy, and a turbine is off, you
need your technicians to go out and look at the machine. This is the differ-
ence between the turbine being off for 1 hour or overnight for 15 hours.
More and more wind park O&M teams are not accepting the responsi-
bility for ensuring that the turbines are running. As wind parks go main-
stream and qualified technicians become scarce, a proud and elite
profession is adopting very mainstream problems including low motiva-
tion, selfishness, lack of ambition, laziness, carelessness, “just a job” atti-
tude, all of which are very dangerous in an industry that services
massive machinery.
The best run wind parks do not necessarily have the best machines, they
just have the best motivated technicians with incentives aligned with the
primary objective: keeping the turbines running.
We all hear the grumbling from technicians about poorly designed
machines. However, the machines you have are the machines you have.
That’s it. It’s all you get. If you want other types of machines to work on,
then by all means move to another wind park. But I guarantee, if turbine
problems make you grumble, you’ll be grumbling at any wind park. The
best technicians accept the challenges, and just work the problems they
know they have – and keep the turbines running!
Jack Wallace Jr., Frontier Pro Services
Offshore wind –
how can it overcome the O&M obstacles?
The offshore wind market is a small but growing part of the world energy
market. Total capacity reached 1 GW in 2007 (around 0.01% of global energy
capacity) and is set to increase sevenfold over the next five years. Activity is
currently confined to Europe. The lack of take up in other major markets such
as the USA and China is due to the abundance of available land in these
countries, meaning that Governments have little incentive to subsidise
offshore developments.
Offshore wind project update
The UK’s Thanet offshore wind farm has been saved by Vattenfall’s £35m purchase of the project. ScottishPower had been due to purchase the project, but pulled out late into negotiations. Onshore construction work had already begun on the project, with foundation installation due to start before the end of 2008. Foundations will now go in starting in February 2009, using A2Sea’s vessel Sea Jack. Installation of the 100 Vestas V90 turbines will take place in 2010 and will be performed by Marine Projects International. Commissioning on the £780m project is due by the end of 2010. Vestas is supplying 100 turbines with total capacity of 300MW.
The high cost of the Thanet project and other forthcoming projects is cause for concern. Major developers such as Centrica have previously expressed concern. For the UK, the falling value of the pound against the euro is exacerbating fears, as is the overall economic slowdown. There is a risk that some of the more expensive projects will be postponed or cancelled. Developers may attempt to bring in new project partners to help share costs on the large offshore wind farms.
Supply chain constraints will be an additional factor on projects due post 2010, with an increasing number of projects competing for resources each year.
Late last year, the jack-up Titan-1 was lost at sea during transportation from the US to the UK. The jack-up was being moved from Pascagoula, Mississippi, to Liverpool ahead of starting an 817-day contract in the North Sea. The job would have covered the installation, servicing and maintenance of wind turbines off Denmark and the UK. The first project was aiding with installation at the 90 MW Rhyl Flats project off north Wales.
Despite this loss, the Rhyl project is on schedule for completion in summer 2009. Other UK activity ongoing includes the 172 MW Gunfleet Sands project (consisting of the Round 1 and Round 2 projects combined), due for completion in autumn 2009. Installation work at Robin Rigg is well progressed, albeit behind schedule, with completion of the 180 MW site due in 2009.
In Scotland, the bidding process for the Crown Estate’s separate
licensing process saw 23 projects put forward from 14 companies or joint ventures, a higher response than first anticipated. It is hoped that the first of these projects would enter construction around 2016. The actual permitting process these projects would be subject to has yet to be determined.
Denmark’s Horns Rev II project is well underway, with foundations all installed and cable installation taking place at present. Turbine installation will begin in March and is to be undertaken by A2Sea. The project remains on schedule for completion at the end of 2009. This will be the first offshore completion in Denmark since the first Nysted project was built in 2003.
The other major current project off Denmark is an extension to the Nysted wind farm. The Nysted II project will see gravity base foundation installation start in February. Turbine installation and commissioning of the 207 MW project, which uses 2.3 MW Siemens turbines, will take place in 2010.
A new 400 MW project is to be built between Djursland and the island of Anholt. The Danish Energy Authority has arranged environmental assessments of the site, the cable route and also geotechnical investigations. After an expression of interest early in 2009, full bids are expected by summer 2010. The Danish Energy Authority want the project to come online by the end of 2012. Eon, Dong and Vattenfall are expected to bid.
continued on c1, page 26
“For years I drove past a wind park that
always had many machines off. I assumed
that the turbine had a bad design and
that that was the reason for such poor
operations. Ten years later, and I am now
running that wind park with a team of my
technicians. The problem was not design. It
was operator motivation.”
Jack Wallace, Frontier Pro Services
renewable energy focus January/February 2009 25
Wind/Operation & Maintenance
The problem
Theoretically, offshore wind should be a low risk investment, in that fixed
costs represent a high proportion of overall costs. This provides a level of
certainty which, combined with guaranteed tariffs, makes it particularly
attractive during times of volatility. But offshore installation is roughly
50% more expensive than for onshore, and O&M costs are roughly twice
as much.
In this regard, technical problems present the biggest potential risk to the
future of the industry. Technical failure rates in offshore wind can be high
compared to onshore, and offshore failures are difficult and expensive to fix.
This is underlined by an analysis of maintenance records, which shows
that while service teams for offshore wind farms are supposed to make
two scheduled maintenance visits every year, unscheduled visits to many
installations are made 20 times a year.
Why do turbines fail?
The heart of the problem is that the technology being used offshore is
generally onshore technology that has not been modified sufficiently to
meet the different demands of an offshore environment.
The classic example of this is the disaster at the Horns Rev wind farm in
2005, following which Vestas is reported to have removed and repaired
80 of its V90 models, designed for offshore use, owing to the effect of
salty water and air on the generators and gearboxes, which became
corrupt after only two years. A similar procedure has been reported this
year, with Vestas’ 30 turbines requiring a change of rotor bearings, at an
estimated cost of €30m.
Failures are also harder to repair because they tend to happen in stormy
conditions, and are often not dealt with when they happen, but on an
aggregated basis at intervals. That means it can be as long as three
months before a turbine failure is repaired. The contrast with onshore
reliability is dramatic, and availability levels of 97% are regularly
achieved.
As sites move further offshore, these problems are likely to get worse.
That could mean offshore developments in deepwater areas will be seen
as unviable. For example, all the potential sites in the German North Sea
have been allocated, but it is uncertain as to whether investment
will follow.
The gearbox
The main area of concern in the industry surrounds the gearbox. The
reason for gearbox failure is currently not a matter of universal agree-
ment. Data indicates that gearbox failures onshore are in line with
industry averages. Offshore, it appears that gearboxes in fact perform
better than other parts of the turbine. The problem with offshore turbines
is that conditions are more extreme, and the downtime which results
from the replacement of a gearbox has a greater effect on availability
compared with, for example, the failure of a generator. The technology of
offshore gearboxes therefore needs to improve, and when it does, this will
have a dramatic effect on availability levels (nb: in next month’s issue the
O&M column will cover the Gearbox – ed).
26 renewable energy focus January/February 2009
Wind/Operation & Maintenance
The direct-drive system, pioneered by Enercon, and which bypasses the
need for a gearbox, could be held up as a solution to this issue. The initial
higher costs would be repaid by lower maintenance costs and higher
uptime levels. Siemens Wind Power is another organisation currently
testing a Direct Drive model.
Realistically, the step-change required in the manufacturing facilities of
the other main suppliers of turbines, all of whom use gearboxes, would
be too great, and we are unlikely to see the disappearance of the gearbox
in offshore installations, particularly considering the huge weight of the
direct-drive system (up to 500 tonnes).
Less rigorous testing is required for onshore turbine components, as they
can be replaced with relative ease, on a ‘fire-fighting’ basis, whereas with
offshore this is not feasible. For gearboxes, then, better testing will be a
key requirement as part of – and in addition to – the development of the
technology. Offshore blades are currently tested very thoroughly, and
perform relatively well considering that they receive the bulk of the
torque to which the turbine is subjected. Generators are not tested as
rigorously, and do not perform as well offshore.
Improved testing for gearboxes might involve breaking prototypes rather
than subjecting them to limited loads as is common now. Suggestions for
improving the design itself include making the gear case more flexible,
and possibly reducing the size of the gearbox, to two stages rather than
three.
Another solution that is not currently being considered is the possibility
of complete nacelle testing. Currently the first time the components work
together is when they are part of a live turbine.
The bottom line for technical difficulties is that they have the potential
to cripple returns, and thus the risk profile of projects is increased and
their economics more dependent on generous Government support –
not a sustainable model for the future of an industry that aspires to be
a key source of world renewable energy.
What is needed?
The change needed for the industry to secure its long-term future is for
the technology to become more robust and reliable:
■ Better design of individual components (i.e. smaller, two-stage gear-
boxes); the drive train (smarter integration of key components) and
foundations;
■ Increased levels of R&D – not only in design, but also access and
maintenance methods;
■ More thorough certification testing so components really can with-
stand the offshore environment.
Analysis from Arthur D. Little shows that testing is probably the crucial
element that will stimulate work in the other two areas. To date, testing
has clearly been inadequate. Manufacturers have claimed it is possible to
test onshore without the expense of offshore testing. However, there is
clear evidence that, while it may be possible to test individual compo-
nents onshore, running a turbine in real offshore conditions for at least a
year would bring to light many key problems and save considerable
amounts of money.
Such testing has already been shown possible, albeit with Government
support. In Germany, for example, offshore testing is already taking place
at Alpha Ventus (albeit on a partly commercial basis).
Marine project update
Atlantis Resources Corp., has signed a Memorandum of Understanding with the CLP Group which lays the foundation for Atlantis to collaborate with CLP in the development of commercial-scale tidal current renewable energy generation projects across Asia-Pacific. This, together with agreements with partners in other regions, will bring Atlantis’ total electricity generating project pipeline to over 800MW. Sites under investigation span Asia-Pacific, Australia, the UK and North America, positioning Atlantis as a genuine pioneer in global tidal energy generation.
Atlantis recently completed trials of its Solon tidal current turbine and the commercial launch of a 2MW Solon turbine is expected in summer 2009. Last month, the company announced plans to build a tidal energy-powered data centre near Scotland’s Pentland Firth.
Aquamarine Power Ltd has appointed ABB to complete the electrical engineering design and construct the electrical generating system for Aquamarine’s Neptune tidal stream device. With a contract worth over £2million, ABB will also install and commission the system at the European Marine Energy Centre
(EMEC) in Orkney, where Aquamarine will demonstrate the first full-scale Neptune device.
Marine Current Turbines Ltd (MCT) has agreed a partnership with Canada’s Minas Basin Pulp and Power Company Ltd (MBPP) to demonstrate and develop tidal power technology and facilities in Canada’s Bay of Fundy, Nova Scotia. MBPP of Hantsport, Nova Scotia is a sustainable energy and resources company. Working in partnership with MBPP, MCT will participate in the tidal power demonstration centre established by the Province of Nova Scotia. MBPP and MCT intend to deploy a 1.5MW tidal generator when the in-stream tidal energy centre enters full operation and is connected to the Nova Scotia grid.
The Scottish Government has granted consent for the Siadar wave energy project on the Scottish island of Lewis. npower renewables, a UK-subsidiary of RWE Innogy will be the operator of the planned facility with Wavegen, the Scottish subsidiary of Voith Siemens
Hydro Power Generation, the technology partner for the wave power units. Both npower renewables and Wavegen have been working together on the project since 2006.
Adam Westwood, Douglas-Westwood Ltd.
Another solution that is not currently being
considered is the possibility of complete
nacelle testing [for offshore wind turbines].
Currently the first time the components
work together is when they are part of a
live turbine.
renewable energy focus January/February 2009 27
Wind/Operation & Maintenance
All this work will need to be underpinned by collaboration. To date, the
industry has been characterised by a general atmosphere of secrecy and
suspicion and, as a result, there has been fragmentation of knowledge
and lack of research progress.
The catalyst for change will come from a shift in the balance of power
away from the wind turbine manufacturers towards bigger and more
experienced customers.
These customers will have the knowledge as well as the muscle to make
specific demands for improvements in testing and development in a way
that was impossible for small wind farm owners. These higher standards
will filter all the way down the supply chain and are likely to result not
only in better design, but also better type testing of components and
integrated systems during the production process.
At the moment, individual company research into the causes of
mechanical failures or ways of improving access and maintenance may
be prohibitively expensive. Collaboration can reduce those costs
significantly. In terms of testing, greater openness would facilitate the
testing of integrated drive trains. Independent testing facilities – such as
the New and Renewable Energy Centre (NaREC), in Blyth, UK – should
continue to be used as a neutral location for such tests to be carried out
without compromising secrecy. It is true that such shared schemes have
been tried before and not succeeded, but in a changing climate these
options will need to be considered again.
This kind of collaboration is not unusual in the energy sector. In offshore oil
and gas, for example, E&P companies have collaborated for years on access
and maintenance issues, and the results have benefited the entire industry.
This shows that there is a clear model to follow.
Action is therefore needed from offshore wind farm owners and developers
to apply pressure on turbine suppliers to ensure they invest in rigorous
component testing and robust offshore-specific R&D; apply pressure on
turbine and component manufacturers to take a long-term view and invest
to secure a sustainable future for the offshore wind market; and finally help
is needed from Governments to free up funding for public R&D centres, and
projects that can act as catalysts for industry collaboration and ‘open research’.
What should particularly concentrate minds in the offshore wind industry
is the clear message that without collaboration, the offshore wind industry
will not mature or progress.
About the authors:
Downtime and your O&M team – turbine availability begins at home
Jack Wallace Jr., is a wind turbine technical advisor with Frontier Pro Services
+1 951-849-3194
Offshore wind – how can it overcome the O&M obstacles?
Matthew Jackson is a business analyst in Arthur D. Little’s Energy and Utilities practice.
Stephen Rogers is a director in Arthur D. Little’s London office.