The new Renewable Energy Sources Act in Poland An opportunity or a threat? Copenhagen, 19.04.2012 1

The new Renewable Energy Sources Act in Poland An opportunity or a threat ?

  • Upload
    iram

  • View
    21

  • Download
    1

Embed Size (px)

DESCRIPTION

The new Renewable Energy Sources Act in Poland An opportunity or a threat ?. Copenhagen , 1 9 .04.2012. - PowerPoint PPT Presentation

Citation preview

Page 1: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

The new Renewable Energy Sources Act in Poland

An opportunity or a threat?

Copenhagen, 19.04.2012

1

Page 2: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Polish Wind Energy Association

a non-governmental organisation, acting since 1999having more than 100 member companies

a member of:

European Wind Energy Association,

Global Wind Energy Council.

2

Page 3: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

1. Wind power development in Poland – plans vs. the reality.

2. Key reservations and conclusions from public consultations of the draft RES Act of 22 December 2011.

3. The industry’s expectations towards the new draft.4. Summary.

Agenda

3

Page 4: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Wind installed capacity in the 2010-2020 period in accordance with the National Renewable Energy Action Plan (NREAP)

Source: Ministry of Economy

Small wind installations [MW]Onshore wind [MW]Offshore wind [MW]

4

Page 5: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

RES-E sector by technology in 2020 in accordance with the NREAP

Source: Ministry of Economy

HydroWind

GeothermalSolid biomass

PVBiogas

5

Page 6: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Wind power slowdown – 2011 growth rates lower than before and less than expected

Source: PWEA own study on the basis of ERO data

Installed capacity in particular years, 2003-2011

Year

Growth rate [%]

Installed capacity [MW]

Installed capacity [MW] Growth rate [%]

6

Page 7: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Electricity production (MWh) by particular RES technologies, 2005 – 2010

Source: PWEA own study on the basis of ERO data

Biogas

Biomass

Wind

Hydro

Co-firing

2005 2006 2007 2008 2009 2010

7

Page 8: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Draft of 22 December 2011

Draft v. 2.0 after public and interdepartmental consultations

Final draft

The draft RES Act

8

Page 9: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Modyfikacja systemu bez zachowania przepisów przejściowych

Key reservations of the wind power sector to the draft RES Act of 22 December 2011

No ensured stability of the support scheme

Insufficient support period (15 years) and variability of coefficients during the green certificates acquisition period

Modification of the support scheme without transitory provisions; decreased support levels

No guarantee of purchase of electricity from RES at a predefined price

9

Page 10: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

• A support scheme without an element guaranteeing the purchase of electricity from RES would not lead to the increase in new capacity in Poland.

• A significant slowdown to wind power development.• Incapacity to achieve the targets laid down in the

NREAP.• No protection for completed investments and

investments in progress – bankruptcy of companies and compensatory claims towards the State Treasury.

• Investors’ abandonment of most projects.

Conclusions from public consultations

10

Page 11: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

• Non-specification of correction factors precludes the making of investment decisions.

• Specification of correction factors in a Regulation increases investment risk.

• Sudden changes to the support scheme result in lack of investors’ confidence in the state’s legal system, hence in the increase of investment costs.

• Uncertainty as to the level of revenues during validity periods of subsequent factors.

• A risk of collapse of the green certificates system.

Conclusions from public consultations

11

Page 12: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Expectations towards the new draft RES Act

Expectations towards the new draft RES Act

• Full implementation of Directive 28.• Implementation of clear and transparent rules

supporting RES development.• Development of new support rules that do not

result in doubt together with the RES sector on the basis of economic analyses and expert knowledge.

• Clear specification of the schedule of works on the draft RES Act together with specification of a transitory period.

12

Page 13: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

A comparison of both versions of the draft RES Act A comparison of both versions of the draft RES Act

Support schemeversion 1.0 of 22 December 2011• No guarantee of purchase

of electricity from RES at a predefined price.

Support schemeversion 2.0 of the draft Act• Return to the mandatory

purchase of energy from RES by a „designated vendor” concept

• Purchase of energy from RES at the average electricity sales price on the competitve market in year 2011 (annual indexation).

13

Page 14: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Factors version 1.0

• A fixed factor, acquisition of green certificates by a RES installation for a period of 15 years.

• Specification of the first correction factors directly in the Act, further in a Regulation.

• Support for RES installations for 15 years, variability of factors during the green certificates acquisition period.

• Specification of correction factors in a Regulation to the Act.

Factors version 2.0

A comparison of both versions of the draft RES Act A comparison of both versions of the draft RES Act

14

Page 15: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Transitory provisions version 1.0

• Certificates of origin for RES commissioned before effective date of the Act together with a fixed correction factor of 1 may be received for a period of 15 subsequent years.

• No protection for completed investments and investments in progress.

• The planned modification to the support scheme could be deemed expropriation (the so-called regulatory or indirect expropriation).

Transitory provisions version 2.0

A comparison of both versions of the draft RES Act A comparison of both versions of the draft RES Act

15

Page 16: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Substitution fee version 1.0

• Modification of the substitution fee calculation concept

• Substitution fee (base) value: 286.74 PLN/ MWh

• Annual indexation with consumer price index

• The substitution fee calculation algorithm assumes the unit substation fee Ozj= 470 PLN/MWh.

• The value of green certificates constitutes the difference between the proposed unit substitution fee and the average energy price on the competitive market.

Substitution fee version 2.0

A comparison of both versions of the draft RES Act A comparison of both versions of the draft RES Act

16

Page 17: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Oversupply of certificatesversion 1.0

Oversupply of certificates version 2.0

• No regulations preventing oversupply of green certificates.

• Implementation of a scheme reducing the risk of oversupply of certificates of origin.

• A subject managing a commodity exchange shall monitor the sale prices of proprietary itnerest stemming from certificates of origin on the exchange.

• Reporting to the Minister for Economy.

• Increased share of electricity in the so-called RES Regulation.

A comparison of both versions of the draft RES Act A comparison of both versions of the draft RES Act

17

Page 18: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Grid connection version 1.0

• Priority connection of RES installations to the power grid compared to installations other than renewable energy sources, if:– grid connection is technically

feasible and economically legitimate,

– the applicant accepts connection conditions.

• No regulations ensuring priority in connection of RES installations to the power grid.

Grid connection version 2.0

A comparison of both versions of the draft RES Act A comparison of both versions of the draft RES Act

18

Page 19: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

• Lack of regulations ensuring grid connection of RES

Grid connection version 1.0

• The President of the ERO concludes regulatory agreements with the TSO and DSOs ensuring increase of new connection capacity of renewable energy sources at least to the extent estimated in the National Renewable Energy Action Plan.

Grid connection version 2.0

A comparison of both versions of the draft RES Act A comparison of both versions of the draft RES Act

19

Page 20: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

• Ambiguous terms and fully discretional assessment of connection applications.

• Lack of any objective, defined criteria for assessment of connection applications.

Grid connection version 1.0

• Definition of economic conditions for connection.• The connection conditions shall specify:

– connection schedule,– implementation schedule of

an investment task (RES installation);

– detailed valuation of costs related to the connection divided into actual connection costs and the costs of necessary grid extension or modernisation.

Grid connection version 2.0

A comparison of both versions of the draft RES Act A comparison of both versions of the draft RES Act

20

Page 21: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

• The new draft of RES should be published on May 2012. Ministry of Economy expects that new law can be implemented by the end of 2012.

• Department of Renewable Energy at Ministry of Economy has accepted most important remarks submitted by PWEA at the consultation period.

• PWEA has built strong coalition of organisations and created PA and PR campaign to continue its activities to support decision makers to implement good law for renewable energy market development.

SummarySummary

21

Page 22: The  new Renewable Energy Sources Act in  Poland An opportunity or  a threat ?

Thank you for attention!

Arkadiusz SekscinskiPolish Wind Energy Association

www.psew.pl 22