40
THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia December 16, 2003 National Energy Technology Laboratory

THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Embed Size (px)

Citation preview

Page 1: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

THE MATERIALS JOINING EXPERTS

Inspection of Fusion Joints in Plastic Pipe

Delivery Reliability ProgramProject Kick-Off Meeting

Morgantown, West VirginiaDecember 16, 2003

National Energy Technology Laboratory

Page 2: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary– Background– Problem Statement– Technical Objective– Benefits– Project Team

Technical Overview

Project Plan

Schedule

Milestones

Page 3: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary– Background– Problem Statement– Technical Objective– Benefits– Project Team

Technical Overview

Project Plan

Schedule

Milestones

Page 4: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

• Plastic pipe has been used successfully for 30 yrs by natural gas industry

• Butt fusion is one of the two most common processes used for joining the pipe.– It utilizes a hot plate which is inserted

between two pipes butted together and heated to temperature. The plate is removed and the pipes are forced together.

• Electro-fusion methods are typically employed for joining tees and branches.

Executive Summary - Background

Page 5: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary– Background– Problem Statement– Technical Objective– Benefits– Project Team

Technical Overview

Project Plan

Schedule

Milestones

Page 6: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary - Problem Statement

• Pipeline and environmental damage• Risk of fire or explosion• Risk of human personnel (user and service)• Interrupted service• Significant loss of revenue

Although infrequent, polyethylene pipe butt fusion joint failure could result in:

Page 7: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary– Background– Problem Statement– Technical Objective– Benefits– Project Team

Technical Overview

Project Plan

Schedule

Milestones

Page 8: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary - Technical Objective

This project will develop, demonstrate and validate an in-situ non-destructive method for butt fusion joints inspection in plastic gas distribution pipelines

Page 9: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary– Background– Problem Statement– Technical Objective– Benefits– Project Team

Technical Overview

Project Plan

Schedule

Milestones

Page 10: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary - Benefits

• Eliminate operator bias• Improved reliability and safety• Reduction in costly destructive QA

testing• Increased confidence in plastic pipe

use

Page 11: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary– Background– Problem Statement– Technical Objective– Benefits– Project Team

Technical Overview

Project Plan

Schedule

Milestones

Page 12: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary - Project Team

NYSEARCHAngelo Fabiano

EWI Connie Reichert

Project DirectorAlex Savitski

Project ManagementJohn Coffey

Accounting/ContractAntoinette Kerins

Page 13: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary– Background– Problem Statement– Technical Objective– Benefits– Project Team

Technical Overview

Project Plan

Schedule

Milestones

Page 14: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Technical Overview

• Visual characteristic review• Initial conclusions• Initial characteristic correlation• Cross-section and surface

comparison• Demonstration unit

Page 15: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Technical Overview

Acceptable welds made under standard conditions

Page 16: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Technical Overview

Insufficient interfacial pressure – unacceptable weld

50% nominal interfacial pressure (tolerant resin) – weld acceptable

Page 17: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Technical Overview

Excessive interfacial pressure – good weld

Page 18: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Inspection of Fusion Joints in Plastic Pipe

Excessive temperature Insufficient heating

Page 19: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Initial Conclusions from Previous Work:

• Bond line appearance in the weld zone always correlated with the reduction of the joint’s mechanical properties

• The sensitivity of the Weld Zone Inspection Method (WZIM) was verified by industry-accepted destructive testing

• WZIM was successful in differentiating between welds made under standard and non-standard conditions

• WZIM was demonstrated to be a simple and accurate testing technique for assessing butt-fusion joint quality

Technical Overview

Page 20: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Conclusions (continued)

• The method is easy to use.

• No expensive testing equipment is required.

• It is less costly than common destructive testing methods (labor).

• A database of cross-sectional images representing typical standard and non-standard joints and their interpretations for selected PE pipes was developed.

Technical Overview

Page 21: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

. Acceptable

• No visible bond line

• Proper double roll-back

• Sufficient melt

• Sufficient pressure

Technical Overview

Page 22: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Unacceptable

• Visible bond line

• Incomplete double roll-back (too small)

• Insufficient melt

• Sufficient pressure

Probable procedure violation – insufficient heating

Technical Overview

Page 23: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Technical Overview

Unacceptable

• Visible bond line

• Double roll-back (excessive)

• Excessive melt

• Disproportionately rounded outlines

Probable procedure violation – excessive temperature

Page 24: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Development of nondestructive procedure for PE butt-fusion joints assessment

• Transforming a destructive inspection method into a nondestructive technique was proved experimentally

• The correlation between the cross-sectional and pipe surface images (after the bead removal) was studied and analyzed

• Several “blind” tests were conducted on the joints independently prepared by gas companies

• Joints were fused under standard and non-standard conditions, and 88% were correctly assessed

Technical Overview

Page 25: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Driscopipe 8100 - Standard Welding Conditions

Cross-sectional image Pipe surface image

Technical Overview

Page 26: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Technical Overview

Cross-sectional image Pipe surface image

Driscopipe 8100 – Excessive Heating Temperature

Page 27: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Technical Overview

Cross-sectional image Pipe surface image

Driscopipe 8100 – Insufficient Interfacial Pressure

Page 28: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Demonstration unit for Weld Zone Inspection Method

Technical Overview

• EWI proprietary image recognition system

• Laser-based

• Automatically generate and interpret images

• Assign pass/fail rating

Page 29: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Conclusions and Recommendations

• The WZIM has the potential to become a quality-assessment field method to nondestructively identify lesser quality non-standard fusion joints.

• Evaluated results can be recorded, stored and documented for QA auditing and process mapping

Technical Overview

Page 30: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary– Background– Problem Statement– Technical Objective– Benefits– Project Team

Technical Overview

Project Plan

Schedule

Milestones

Page 31: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Area I and II Tasks

• Task 1: Research Management Plan• Summary of technical objectives and technical

approach

• Task 2: Technology Status Assessment• Describe current state-of-the-art of plastic pipe

inspection

• Task 3: Validation of Inspection Method and Testing Procedure Optimization

• Correlation between the WZIM joint image and mechanical joint strength by using short-term destructive mechanical tests

Project Plan

Page 32: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Area I and II Tasks ( continued)

• Task 4: Method Verification using Long Term Destructive Testing

• Determine if a detrimental affect occurs on a quality weld by performing local reheating

• Task 5: Specification of User Requirements• Define requirements for assigning pass/fail rating

• Task 6: Development of Image Recognition Inspection System

• Develop hardware

• Refine software

• Integrate and calibrate components

Project Plan

Page 33: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Area III Tasks

• Task 7: Development of Field Test Program• Test matrix of conditions, type, materials and sizes

to be tested during field operations

• Task 8: Field Test Preparation• Inspection parameters will be optimized based on

Task 7 test matrix

• Operator training

• Task 9: Field Testing• Cover a representative range of materials and sizes

Project Plan

Page 34: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Area III Tasks (continued)

• Task 10: Data Analysis, Specification Optimization and Inspection Guidelines

• Next step towards technology commercialization

• Task 11: Reporting• Final technical report

• Comprehensive operation and maintenance manual

Project Plan

Page 35: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

• Overall Project Budget• $373,005 (includes $93,000 cost match)

• Area I and II (Task 1 – 6) $243,330• DOE funding $170,330

• Cost share $73,000

• Area III (Task 7-11) $129,675• DOE funding $109,675

• Cost share $20,000

Note: Decision point will not be reached based on DOE obligated funds of $132,000.

Project Plan - Funding

Page 36: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary– Background– Problem Statement– Technical Objective– Benefits– Project Team

Technical Overview

Project Plan

Schedule

Milestones

Page 37: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Project Schedule

ID % Complete Task Name Start Finish

1 5% Inspection of Fusion Joints in Plastic Pipe 10/1/03 9/29/05

2 6% Area I and II 10/1/03 9/2/04

3 100% Task 1.0 Research Management Plan 10/8/03 11/28/03

7 100% Task 2.0 Technology StatusAssessment

10/27/03 1/16/04

15 0% Task 3.0 Validation of InspectionMethod and Optimization of Testing

10/1/03 5/3/04

22 0% Task 4.0 Method Verification usingLong Term Destructive Testing

10/1/03 5/3/04

26 0% Task 5.0 Specification of UserRequirements for Prototype Image

11/17/03 12/26/03

29 0% Task 6.0 Development of ImageRecognition Inspection System

10/8/03 9/2/04

34

35 0% Decision Point 9/2/04 9/2/04

36

37 0% Area III 10/1/03 9/29/05

38 0% Task 7.0 Development of Field TestProgram

9/3/04 9/30/04

40 0% Task 8.0 Field Test Preparation 10/1/03 2/17/05

44 0% Task 9.0 Prototype Field Testing 2/18/05 5/12/05

46 0% Task 10.0 Field Data Analysis,Development of NDT SystemSpecifications and Inspection

5/13/05 8/4/05

49 0% Task 11.0 Final Reporting 8/5/05 9/29/05

9/2

Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 12003 2004 2005 2006

Page 38: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Executive Summary– Background– Problem Statement– Technical Objective– Benefits– Project Team

Technical Overview

Project Plan

Schedule

Milestones

Page 39: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Milestone Responsibility Milestone DescriptionApproximate

Submission Date

M1 EWI Hazardous Substance Plan 10/31/2003

M2 EWI Research Management Plan - Draft 10/31/2003

M3 NETLDOE Input Received for Research

Management Plan 11/20/2003

M4 EWITechnology Status Assessment

Report - Draft 11/30/2003

M5 NETL

DOE Input Received for Technology Status Assessment Report 12/19/2003

M6 EWI User Requirements Defined 12/26/2003

M7 EWILaser Based Inspection Hardware

Developed 5/4/2004

M8 EWILaser Based Inspection Software

Developed 5/4/2004

M9 EWI Integrated Inspection System 9/2/2004

M10 NETLWritten approval from DOE COR to

proceed beyond Task 6 9/2/2004

Project Schedule – Phase I

Page 40: THE MATERIALS JOINING EXPERTS Inspection of Fusion Joints in Plastic Pipe Delivery Reliability Program Project Kick-Off Meeting Morgantown, West Virginia

Milestone Responsibility Milestone DescriptionApproximate

Submission Date

M11 EWI Developed Field Test Matrix 9/30/2004

M12 EWI

One Day Training Course on the Fundamentals of WZIM Inspection System 2/17/2005

M13 NETL Final Technical Report 10/28/2005

M14 EWIComprehensive Operation and

Maintenance Manual Developed 10/28/2005

M15 EWI Hazardous Waste Report 10/1/2005

M16 EWIReport of Termination or Completion

Inventory 10/1/2005

M17 EWI Semi-Annual Report 1 4/30/2004

M18 EWI Semi-Annual Report 2 10/31/2004

M19 EWI Semi-Annual Report 3 4/30/2005

Project Schedule – Phase II