Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
The market and economics of (mobile) port-based
Ballast Water Treatment solutions
@BluePortS Meeting - Lisbon, 15 May 2019
@BluePortS Meeting - Lisbon May 15th, 2019
The Regulatory Framework • IMO - BWM Convention
• US: not acceded to the IMO BWM Convention • has instead adopted its own ballast water management requirements• California’s ballast water management regulations are codified in the
Marine Invasive Species Act (“MISA”)
• EU: No Direct EU law• EU Regulation 1143/2014 on Invasive Alien Species entered into force
on 1 January 2015 • recognizes the IMO BWMC as one of the possible management
measures
@BluePortS Meeting - Lisbon May 15th, 2019
The Regulatory Framework: IMO
• entered into force globally on 8 September 2017
• The BWMC applies to all vessels, either flying the flag of a Party or operating under the authority of a Party, other than:
1) ships not designed to use ballast water; 2) warships or Naval auxiliary vessels; 3) vessels only on non-commercial voyages; and 4) vessels with permanent sealed ballast.
@BluePortS Meeting - Lisbon May 15th, 2019
Ratification
• ships registered under a flag• Ships operating in waters under the authority of a Party
which hasn’t ratified the BWM Convention?
Number of Contracting States: 80(80.94% of the gross tonnage of the world’s merchant fleet) (as of 2019)
@BluePortS Meeting - Lisbon May 15th, 2019
Ratification - Shortsea shippingI. SIGNATORIES
• Netherlands - Subject to approval
• Spain - Subject to ratification
II. Contracting States
• France (accession)1 24 September 2008 8 September 2017
• Greece (accession) 26 June 2017 26 September 2017
• Cyprus (accession) 8 August 2018 8 November 2018
• Portugal (accession) 19 October 2017 19 January 2018
• Spain (ratification) 14 September 2005 8 September 2017
• Morocco (accession) 23 November 2015 8 September 2017
• Tunisia, Algeria ?
• Italy ?
• The UK has yet to ratify the Convention
@BluePortS Meeting - Lisbon May 15th, 2019
Shipowners’ view (limited sample):
• Exemption• Not accept voyage• Internal transfer of ballast
ComplianceThe Market
@BluePortS Meeting - Lisbon May 15th, 2019
Com
plia
nce
with
the
IM
O C
onve
ntio
n
Exemption eg under the Same Risk Area (SRA) approach – G7
Ballast Water Exchange – G11
On-board system – G3
containerised BWTS
regular BWTS
Mobile port/shore based
barge
containerised mobile BWTS (e.g on a truck)
Fixed port/shore based
treatment facilities (PRF)
containerised BWTS
Deckhouse solution for tankers
Alfa Laval has developed standard deckhouses to fit Alfa Laval PureBallast 3 Ex ballast water treatment systems. Each deckhouse is delivered as a pre-assembled solution, including the PureBallast 3 Ex system and all piping inside the deckhouse, for easy integration into the vessel.
For PureBallast 3 Ex system details, please refer to the Alfa Laval PureBallast 3 product leaflet.
ApplicationA large portion of the world’s tanker fleet uses submersible pumps, e.g. Framo pumps or the equivalent, to eliminate the need for a pump room and maximize space for the trans-port of product. This poses challenges when installing a bal-last water treatment system, as it means there is no internal space available. A deckhouse for PureBallast 3 Ex offers a solution when the pump room is lacking or offers too little space for the installation.
Benefits• Pre-assembled PureBallast 3 Ex system in standardized
deckhouse• Durable construction with marine-approved steel (Grade
A with 3.2 certificates)• Climate regulation through integrated HVAC
Deckhouse for Alfa Laval PureBallast 3 Ex
• DNV-GL type approval covering both deckhouse and treatment system
• Possibility to transport the deckhouse in a pallet-wide high cube container (40’/20’/10’)
• Full backing from Alfa Laval’s global service organization
ConfigurationThe flow-related components of the PureBallast 3 Ex sys-tem (UV reactor, filter and CIP unit) are contained within the deckhouse, while the lamp drive cabinet and control cabinet are installed outside the deckhouse and within the vessel’s safe zone.
Safety classificationAll components and wiring inside the deckhouse are classi-fied for use in hazardous areas in accordance with the IEC 60079 series of standards: • Zone 1• Explosion group IIC• Temperature class T4 (135°)
Type approvalThe standard deckhouse configuration, including the PureBallast 3 Ex system, is type approved by DNV-GL.
Photos: InvaSave 300 (up) - Alfa Laval PureBallast 3 Ex (down)
Mobile Port/Shore based
@BluePortS Meeting - Lisbon May 15th, 2019
Comp
lianc
e with
the
IMO
Con
vent
ion
Exemption eg under the Same Risk Area (SRA) approach – G7
Ballast Water Exchange – G11
On-board system – G3
containerised BWTS
regular BWTS
Mobile port/shore based
barge
containerised mobile BWTS (e.g on a truck)
Fixed port/shore based
treatment facilities (PRF)
containerised BWTS
Shore-Based Ballast Water Treatment in California 23 April 2018 Task 15a: Summary Report 33 Job 15086.01, Rev A
from the data available but is estimated at <1 per year in waters between 0 and 24 nautical miles offshore.
Based on this conclusion, this study proposes that underway discharges be planned in advance to the extent practicable and, whenever they cannot be practically avoided or conducted outside 24 nautical miles, conducted in port at designated anchorages or “Deep Water Service Stations” (DWSS).
Ballast water capture and treatment operations at a DWSS would be virtually equivalent to bunkering operations at anchor, as shown in the below figure. Barges would be dispatched to vessels at pre-arranged times and secured alongside in the same manner as for vessels at berth. The processes for connection, capture, and treatment of ballast would also be similar.
Figure 10 Open-hatch gantry ship, Star Florida engaged in bunkering operations in Vancouver Harbor,
British Columbia.
If implemented for each zone, DWSS would provide a suitable and practical means of eliminating current underway discharge practices in California, both for inbound and outbound vessels. The few vessels requiring this practice would experience schedule impacts, but the system would not cause disruptions to normal operations at marine terminals, or appreciably contribute to marine traffic in port or other port congestion issues.
It should be noted that planning and conducting ballasting operations at specified locations may result in unintended or undesirable outcomes. These outcomes may include vessels sailing in a less-than-optimal loading condition during transits from offshore waters to port (or vice versa), or vessel schedule delays associated with conducting ballasting operations in port that had previously been conducted while underway.
The barge-based system proposed herein will not prevent those few discharges that must be conducted immediately for the safety of the vessel and crew. In these instances, the capabilities
Source: https://magazine.damen.com/green/retrofit-port-and-mobile-bwt-solutions/
Fixed Port/Shore based
@BluePortS Meeting - Lisbon May 15th, 2019
Com
plian
ce w
ith th
e IM
O C
onve
ntio
n
Exemption eg under the Same Risk Area (SRA) approach – G7
Ballast Water Exchange – G11
On-board system – G3
containerised BWTS
regular BWTS
Mobile port/shore based
barge
containerised mobile BWTS (e.g on a truck)
Fixed port/shore based
treatment facilities (PRF)
containerised BWTS
Shore-Based Ballast Water Treatment in California 20 February 2018 Task 3: Assessment of Retrofitting of Ports and Wharves 15 Job 15086.01, Rev -
2.2.2 Marine Vessel Support Requirements
The above design basis identifies the support requirements for marine vessels calling at this terminal. These requirements consider the 95% case of ballast operations for vessels that called between 2014 and 2015. In addition, the ports and wharves modifications consider the containership identified in the Task 2 report, Reference 2.
A 6,300 TEU containership was used for ship geometry inputs. This size vessel is large, though not uncommon, in terms of likely ship calls at this terminal, and as such is considered representative, with some conservatism. The assumed point of discharge for the ballast water from the ship is on the main deck, and assumed to be located approximately 20 meters above the waterline of the ship’s highest point above the water.
The assumed discharge rate from the ship is 750 m3/hr. The assumed pressure at the point of discharge is zero MPA. This pressure from the ship’s presentation flange is adequate to prime the ship to shore connection, but not adequate to lift the received ballast water to the storage and treatment plant. As such, intermediate dockside lift stations are required to complete the transfer to the point of storage and/or treatment. The booster pump/lift station will be located in the container yard approximately 50 m landside of the ship.
2.2.3 Terminal Operations
2.2.3.1 General Arrangement Plan
The general arrangement plan for the TraPac terminal (Figure 13) identifies the overall geometry of the terminal along with the anticipated ship location, points of connection, wharf piping, booster pump/lift station location, piping between the booster pump/lift station and the treatment facility.
Figure 13 General arrangement plan
Fixed Port/Shore based
@BluePortS Meeting - Lisbon May 15th, 2019
OIC Harbour Authority Ballast Water Management Policy for Scapa Flow 10 December 2013
Orkney Marine Environmental Protection Committee 29 April 2014 and 29 November 2017
1
ORKNEY ISLANDS COUNCIL
HARBOUR AUTHORITY
BALLAST WATER MANAGEMENT POLICY
FOR
SCAPA FLOW
OIC Harbour Authority Ballast Water Management Policy for Scapa Flow 10 December 2013
Orkney Marine Environmental Protection Committee 29 April 2014 and 29 November 2017
21
Map.1. Locations of monitoring sites in Scapa Flow.
NOTES
• Port Reception Facilities :• Covered by Guidelines• Port-based (unless on a barge) BWMS may be subject to different regulations• Municipal Waste Management
• Ballast Water Management Plan• specific to each ship• Requires new Plan • New G8 guidelines
@BluePortS Meeting - Lisbon May 15th, 2019
The EconomicsPorts
@BluePortS Meeting - Lisbon May 15th, 2019
Shore-Based Ballast Water Treatment in California 20 February 2018 Task 3: Assessment of Retrofitting of Ports and Wharves 2 Job 15086.01, Rev -
Port/Terminal Name Details El Segundo – Chevron Offshore Marine Terminal
Port/Terminal Description: offshore mooring for load and discharge of liquid bulk (petroleum) products Primary Vessel Type(s): tankers and ATBs Primary Cargo Type(s): crude oil and refined fuels Annual Discharge Volume (m3) (2015 data): 203,900 Number of Discharge Events (2015): 49 90th Percentile Discharge Volume (m3) (2015): 32,000 Approx. Period per Discharge (days): 1 Approx. Discharge Rate (m3/hr): 3,400
Port of LA/Long Beach – Long Beach Cruise Terminal
Port/Terminal Description: dedicated cruise ship terminal Primary Vessel Type(s): passenger cruise ships Primary Cargo Type(s): passengers and stores Annual Discharge Volume (m3) (2015 data): 165,900 Number of Discharge Events (2015): 256 90th Percentile Discharge Volume (m3) (2015): 1,500 Approx. Period per Discharge (days): 1 Approx. Discharge Rate (m3/hr): 400
Port of LA/Long Beach – SA Recycling, Terminal Is.
Port/Terminal Description: bulk export Primary Vessel Type(s): bulk carriers Primary Cargo Type(s): scrap steel Annual Discharge Volume (m3) (2015 data): 257,300 Number of Discharge Events (2015): 17 90th Percentile Discharge Volume (m3) (2015): 18,000 Approx. Period per Discharge (days): 5 Approx. Discharge Rate (m3/hr): 1,400
1.1 Methods Each of the subject terminals and ports were researched for available vacant space and location for ballast water storage and/or treatment facilities selected to match the vessels that frequently discharge ballast water and the frequency of their discharges in case study ports. Potential locations for the storage and treatment of ballast water were communicated to the team preparing the Task 4 and 5 reports. Reported vessel discharge data was then examined to estimate the practicality and cost of any new infrastructure required on-shore. In general, this included:
Shore-Based Ballast Water Treatment in California 20 February 2018 Task 3: Assessment of Retrofitting of Ports and Wharves 1 Job 15086.01, Rev -
Executive Summary
This report is part of an overall coordinated study evaluating the feasibility of using shore-based mobile or permanent ballast water treatment facilities to meet California’s Interim Ballast Water Discharge Performance Standards (CA Interim Standards). Tasks 2 through 5 are submitted together to discuss the practical necessities for shore-based treatment system implementation, from the modifications onboard vessels to the treatment technologies used in the facilities.
This Task 3 report considers the modifications to ports and wharves that are required to receive ballast water from the vessels that call on each case study terminal. Table 1 Case study ports/terminals
Port/Terminal Name Details Port of Stockton – East Complex
Port/Terminal Description: bulk import/export Primary Vessel Type(s): bulk carriers, tank vessels Primary Cargo Type(s): bulk cement, sand, tire chips, liquid fertilizer, anhydrous ammonia, food grade oil, molasses, bagged magnesium, project cargo. Annual Discharge Volume (m3) (2015 data): 1,194,000 Number of Discharge Events (2015): 59 90th Percentile Discharge Volume (m3) (2015): 29,500 Approx. Period per Discharge (days): 1 Approx. Discharge Rate (m3/hr): 2,800
Port of Oakland – TraPac Terminal
Port/Terminal Description: container import/export Primary Vessel Type(s): containerships only Primary Cargo Type(s): containers only Annual Discharge Volume (m3) (2015 data): 7,200 Number of Discharge Events (2015): 2 90th Percentile Discharge Volume (m3) (2015): 7,500 Approx. Period per Discharge (days): 1 Approx. Discharge Rate (m3/hr): 750
Port of Hueneme – North, South & Joint-use Terminals
Port/Terminal Description: auto import and bulk import/export Primary Vessel Type(s): reefer ships, general cargo, ro-ro Primary Cargo Type(s): autos, break-bulk agricultural products (e.g. bananas and other fresh fruit), liquid fertilizer, oil, containers, fish, project cargo) Annual Discharge Volume (m3) (2015 data): 4,800 Number of Discharge Events (2015): 4 90th Percentile Discharge Volume (m3) (2015): 4,000 Approx. Period per Discharge (days): 1 Approx. Discharge Rate (m3/hr): 350
Shore-Based Ballast Water Treatment in California 20 February 2018 Task 3: Assessment of Retrofitting of Ports and Wharves 13 Job 15086.01, Rev -
Table 2 Summary of Port of Stockton Berths 5 and 6 wharf modification cost estimate
Location Ballast Capacity (m3) Modification Cost
Port of Stockton 34,000 Wharf Modifications (Berths 5 & 6) $50,000 Piping between wharf and lift station $510,000
Purchase of modification of yard equipment for the movement of piping connection from the wharf to the ship
$500,000
Regulatory Review $250,000 Engineering $110,000 Contingency of 20% $230,000 Total $1,650,000
2.2 Port of Oakland – Berth 30-33, Tra Pac Terminal
2.2.1 Summary of Port TraPac, Oakland is a dedicated container-only terminal located in the Port of Oakland, Outer Harbor Channel at Berth 30 and 32. Presently, TraPac handles four to five vessel calls per week (Reference 8), mostly Panamax-sized.
Figure 11 Location of TraPac Terminal
The terminal area encompasses approximately 66 acres. The berth area is 2,100 feet long and has six working lanes beneath four post-Panamax container gantry cranes. Currently, the yard is set up to accommodate a combination of wheeled and grounded operations, but is designed to allow for conversion to higher density grounding if required.
Ballasting operations at TraPac are typical of container terminals that see a net import of cargo. The vessel offloads cargo, and takes on ballast water to compensate for weight changes. In the TraPac case, there were only five ballast water discharges over a 24-month period that saw an estimated 500 vessel calls (one ballast discharge per 100 vessel calls). Discharges are indicated by Figure 12 below.
Waste Water Treatment Facility
Re-use of BW:Mass balance between ballast water that is taken up and discharged in the same location
Glosten (2018) Prepared for Delta Stewardship Council, California
The EconomicsVessels
@BluePortS Meeting - Lisbon May 15th, 2019
Shore-Based Ballast Water Treatment in California 20 February 2018 Task 2: Assessment of Retrofitting and Outfitting of Vessels 6 Job 15086.01, Rev -
(1) Port of Stockton ballast discharges are tightly linked to cargo discharge rates, which are occur daily and in high volumes. Due to this tight pattern of consistent high rates and volumes, the design basis is set at the maximum rates with a small margin. Often, there are multiple consecutive days with high volume discharges, resulting in as much as 98,000 tons in a single seven-day period.
(2) Port of Oakland Trapac facility parameters are used to develop a baseline design reception from ship to shore and intermediate storage. The adjoining facility details are then used for sizing transfer station pumps and piping. The total for processing plant considers the rate and total of ballast water to the centralized processing plant. The totals provided use Trapac specific as well as port wide historic ballast water discharge volumes and rates.
(3) Hueneme sees discharges from multiple vessel types, but car carriers provide a reasonable design basis for presentation flange pressure and dimensions. The discharge rates and volumes vary significantly, and there is more than one approach. The design rate is based on slowing down some of the larger vessels discharge rates, but allowing typical discharge volumes to be offloaded in less than eight hours. There are various ways to consider the volume period and amounts. The design basis here is based uses a 20-day period for the ballasting cycle, i.e. how many vessels and ballast discharge volumes per 20-day period. This approach is based on 12 years of data, showing that such a 20-day period will see no more than 4,000 tons of ballast discharge. For the rare, every five years, higher volumes additional barge or other means would be required.
(4) El Segundo vessel discharges are strictly governed by cargo loading rates, which are impractical to slow for all but extreme cases. The discharge volumes and rates are based on typical highest discharges, noting that one vessel called in last several years with higher rates and volumes. That case will require additional time, split discharge, or other special accommodation.
(5) POLA/SA Recycling processes cargo on weekly basis, seeing ballast discharges of as much as 22,000 tons per week. Although ship discharge rates are as high as 2,800 m3/hr, it is reasonable to slow this rate significantly during port collection, as the amount of ballast water to be discharged on a daily basis is no more than 6,000 metric tons. This reduced rate, over an eight-hour period would be only 750 m3/hr. However, it is important to not stress ship's pumps by running at too slow of a rate, i.e. less than 50% of rated. As such, design rate for port reception is 1,400 m3/hr, 50% of ship pumps.
(6) POLB cruise terminal discharges have seen only three vessels routinely discharging over the last several years. That noted, these vessels are typical of the industry in terms of volume discharges and rates, discharging less than 2,000 tons of ballast water in a 4-hour period. That noted, the design basis provides some margin to holding capacity, to account for some growth given newer cruise ships having larger capacities, based on analysis of other cruiseship discharges at other ports. The rate is increased to 400 m3/hr to correspond to 6-hour processing of larger volumes.
(7) Hose sizing follows OCIMF guidance, generally keeping less than 12 meters per second velocity. Actual size considers the available head from the vessels pumps at the presentation flange, and assumes 70 kPa suction lift from the receiving facility (lift station). Hose is assumed to be smooth bore with Hazen Williams friction factor of 140 or less, and total length between 30 and 50 meters. In hose velocities are a special case, where in pipe velocities use the much slower rate of 3 meters per second (10 feet per second) as a guideline.
1.5 Summary of Findings Cost estimates were developed to inform the economic feasibility of modifying vessels for shore-based treatment, and are summarized below.
Table 4 Modification costs by vessel type and size
Vessel Type Case Study Discharge Rate (m3/hr)
Modification Cost
Articulated tug-barge El Segundo 1,700 $151,400 Containership Oakland – TraPac 750 $152,600 Bulk carrier Stockton/SA Recycling 2,800/1,400 $308,900 Oil tanker El Segundo 3,400 $425,900 Passenger cruise ship Long Beach Cruise Terminal 400 $297,300 Automobile carrier Hueneme 350 $297,300
Operations:Certain vessel conduct ballasting operations to offset cargo operations, in order to maintain stability and reduce hull stresses. As cargo is loaded, ballast water must be discharged at the same time. Typical: bulk carriers, oil tankers, ATBs, and some containerships.
A deck manifold connection is the more obvious location for oil tankers, bulk carriers, containerships, and ATBs. A side port connection is likely for car carriers and passenger cruise ships that already use such locations for fuel oil bunkering operations.
• NO universal connection standard for ballast water discharge• SOLAS (above 500GT) specifies an international shore connection
standard for connecting with a vessel’s firemain for firefighting purposes
Shore-Based Ballast Water Treatment in California 20 February 2018 Task 2: Assessment of Retrofitting and Outfitting of Vessels 19 Job 15086.01, Rev -
Section 4 General Modifications This section describes the general vessel modifications that would be required for any marine vessel that would transfer ballast water to a shore-based or marine vessel-based treatment system.
4.1 Ship Connection Options Connection between a vessel’s ballast system and shore-based treatment facilities can be made in several manners as outlined in below table. These same connections might be considered for either a ship-to-shore or a ship-to-ship connection. Table 8 Ship connection options
Representative Image Concept
Concept Locations for Connection This image, repeated from the Summary section, identifies
possible locations for capturing ballast water discharges from marine vessels.
A deck manifold connection is the more obvious location for oil tankers, bulk carriers, containerships, and ATBs.
A side port connection is likely for car carriers and passenger cruise ships that already use such locations for fuel oil bunkering operations.
The direct use of existing hull fittings has been considered for capturing ballast water, avoiding the need to modify the marine vessels.
Deck Manifold – Mechanical Loading Arm This image shows a mechanical loading arm connected
between a dock and a marine vessel. It would be very unusual for a marine vessel to already be
outfitted with a ballast water deck fitting. The rare exceptions would be very old tank ships that are still outfitted with non-segregated ballast water. It is also possible that some vessels will have their ballast water crossed over to the fire main, which would have a main deck connection. However, that connection would be DIN100, and unlikely to support needed ballast water discharge rates.
Mechanical loading arms have many advantages, in particular that they avoid interferences with mooring lines, and readily adjust for changes in tides. They are also flexible in size, and very useful for handling high flow rates and pressures.
Glosten (2018) Prepared for Delta Stewardship Council, California
Pricing the service : The ProviderPort/Terminal Operator: Charge a fee per visit and/or per volumePRF – Service provider: Charge a fee per visit and/or per volume
Port Authority / National Port Association : same as above But CAPEX maybe recovered (subsidized by State) or paid by membersShipowners Association: fee per usageBut CAPEX maybe recovered (subsidized by State) or paid by members- Subsidized if mandatory as a contingency measure- Investment Banks
Unless mandatory or subsidized: PRICE = (CAPEX+OPEX) + Profit marginAlternatives : pricing under competition, maximum Willigness to Pay
@BluePortS Meeting - Lisbon May 15th, 2019
Pricing the service : The CostCAPEX: capital expensesannual equivalent of the capital cost
initial cost (C) will be paid back in equal instalments over the N-year period at an interest rate of I
N: 8-12 yearsi: average of 5%
@BluePortS Meeting - Lisbon May 15th, 2019
OPEX: operating expensesUSAGE: 20 - 80 hrs per week, mean: 60 hours (1mil. c.m. per year)
10 hrs = 3,000
FUEL PRICE : 300 €/ton and a maximum of 650 €/ton
Fuel/Energy cost(Diesel generator, electricity grid, Renewable energy…)
incl. spare parts for main and support equipment, consumable materials (lubrication, coolant, grease), certification for engine and ballast water compliance, average repair costs
TRANSPORTATION/REPOSITIONING COSTS ?PERSONNEL COST ?
0.23212
0.27504
0.27758
0.28439
0.28975
0.29515
0.43279
0.33218
0.31535
0.31705
0.30554
0.30860
Baseline = 0.30087
0.20
0.25
0.30
0.35
0.40
0.45
Usage (hrs per week)
N of years
interest rate
CAPEX (€)
Fuel price (€/mt)
Other Costs
CAPEX+ OPEX (€/c.m)
CAPEX+ OPEX (€/c.m)Inputs Ranked By Effect on Output Mean
Input High
Input Low
Pricing the service : The Cost
@BluePortS Meeting - Lisbon May 15th, 2019
RESULTS
OPEX: 0.1€ per c.m
CAPEX+OPEX:0.23-0.43 € per c.m
Pricing the service : The Cost
@BluePortS Meeting - Lisbon May 15th, 2019
OPEX: operating expensesUSAGE: 20 - 80 hrs per week, mean: 60 hours (1mil. c.m. per year)
0.23212
0.27504
0.27758
0.28439
0.28975
0.29515
0.43279
0.33218
0.31535
0.31705
0.30554
0.30860
Baseline = 0.30087
0.20
0.25
0.30
0.35
0.40
0.45
Usage (hrs per week)
N of years
interest rate
CAPEX (€)
Fuel price (€/mt)
Other Costs
CAPEX+ OPEX (€/c.m)
CAPEX+ OPEX (€/c.m)Inputs Ranked By Effect on Output Mean
Input High
Input LowTable 4 – The ballast volume discharged from different types of vessels per year.
Average vessel
Containership Bulker Tanker Passenger RoRo Other
Ballast water discharges per year
259 223 375 570 167 10 210
Volume per discharge in m3 6,840 3,680 15,313 10,605 816 853 9,771
Source: Adapted from Glosten (2018)
Is it realistic ?• Information online on 4-6 similar concepts • MEPC 65/2/20 22 March 2013 - Ballast Water Treatment Boat (BWTBoat) by India
• MEPC 71/INF.30 28 April 2017 - Experience with contingency measures by IMarEST
• MEPC 71/4/13 19 April 2017 - Contingency planning for ballast water management, port solution by the Netherlands
• MEPC 74/INF.21 7 March 2019 - Statement of Compliance with Guidelines (G5) of the BawatTM BWMS Mk2 Mobile Treatment Unit by Denmark
@BluePortS Meeting - Lisbon May 15th, 2019
MEPC 71/INF.30 Page 3
I:\MEPC\71\MEPC 71-INF-30.docx
Development progress 10 The Global Industry Alliance (GIA) held the 2nd Expert Workshop on Port-Based BWM Contingency Measures in October 2013 in Busan, Republic of Korea. This was attended by experts representing all stakeholders in ballast water management. The workshop concluded: "the level of "need" was still unknown and was dependent on uncertainties in the ultimate demand and regulatory requirements". There have been no further GIA workshops on contingency measures since. There has, however, been significant progress on several of the projects as discussed below. 11 The BWTBoat concept, presented by the Indian Register of Shipping, has continued development. This system, in concept design, would deliver and receive ballast water at a network of ports throughout various trading areas. In this manner, a ship could be loaded with treated ballast water for future compliant discharge. Alternatively, a ship could discharge untreated ballast water to the BWTBoat, for treatment. 12 The Top Water Flow mobile concept, developed by a private company in Norway, uses a barge-based treatment system. This system is in the concept phase. The barge connects to the ship's hull at the ballast water discharge pipe using an electromagnetic tip with a rubber seal. 13 The Damen InvaSave system allows placement of any number of InvaSave treatment containers on board a barge, truck, dock, or other suitable platform. The ship then pumps ballast water off to the treatment modules for treatment. This is a commercially offered product, is in full-scale demonstration in a Netherlands port and has been certified to meet the D-2 treatment discharge standard. 14 The Glosten inResponse system is a mobile kit that is deployed on board a ship. The system lowers a device into the ballast water tanks where an Active Substance is mixed into the ballast water, a hold time recorded, and a neutralizing agent then applied. This system is continuing full-scale prototype demonstration trials.
Table 1: Summary of contingency measures development efforts
BWTBoat Top water flow InvaSave inResponse Description Network of ships
to provide treated ballast, or receive untreated ballast
Mobile barge based treatment plant, with hose connecting to ship's hull at ballast discharge pipe
Treatment container that can process discharged ballast water. Locate on barge, truck, shore, etc.
Mobile treatment system brought onto the ship, treating ballast water in-tank
Efficacy Assumed to meet D-2, not yet developed
Assumed to meet D-2, testing data not available
Demonstrated to meet D-2, certified
Mixed results, meeting D-2 when there is good tank access, and short of D-2 when tank access is difficult
Development phase
Concept design Concept design Commercially available, working prototype
Working prototype, with ongoing trials
Limitations Requires deck connection for ballast transfer
Requires special connection to ship's hull
Requires deck connection for ballast transfer
Requires access to ballast water tank hatch/manhole
MEPC 74/INF.21 Annex, page 1
I:\MEPC\74\MEPC 74-INF.21.docx
ANNEX
___________
Is it realistic ? “why are there no other systems ?”
• There are indeed other companies working on the concept
(54-57 BWMS approved, 4-5 containerized BWMS concepts + INVASAVE)
• “Shooting ourselves on the foot” (Manager Business Development and Marketing)
• $30 billion - 56,000 vessels (approx. 10,000 sold)
• BWTS which will be installed (i.e. delivered on board a vessel) prior to Oct. 28th 2020,
should be certified either with the existing G8 or the revised.
@BluePortS Meeting - Lisbon May 15th, 2019
Operators’ experience (ABS,2019)
ABS Best Practices for Operations of Ballast Water Management Systems Report 8
2018 BWMS Operational Experience Survey Results ABS received responses from more than 60 shipowners and operators worldwide covering 483 BWMS installations for seven BWMS treatment technologies and a wide range of vessel types including bulk carriers, container ships, gas carriers, general cargo carriers, heavy load carriers, LNG carriers, product carriers, tankers, and vehicle carriers.
The results from the questionnaires were imported into an Excel spreadsheet with the quantifiable information such as dates and sizes, and the information was refined to support sorting for analysis. If not initially indicated, the descriptive sections were deciphered and interpreted to support more comprehensive analysis. Depending on the categorization, data was pulled into numerical terms and presented graphically. The aggregated results allowed for the identification of common issues, challenges, and best practices. The following figures summarize a few of the survey results. A more detailed analysis can be found in Appendix A.
Figure 1 BWMS Operability
Figure 2 BWMS Overall Experience (Positive Feedback)
34%
40%
22%26%
0%5%
10%15%20%25%30%35%40%45%
Reliability User Friendliness OPEX Will Use Again
@BluePortS Meeting - Lisbon May 15th, 2019
American Bureau of Shipping - March 2019 - 2019 Best Practices for Operations of Ballast Water Management Systems Report
60 shipowners and operators worldwide covering 483 BWMS installations for seven BWMS treatment technologies
ABS Best Practices for Operations of Ballast Water Management Systems Report 8
2018 BWMS Operational Experience Survey Results ABS received responses from more than 60 shipowners and operators worldwide covering 483 BWMS installations for seven BWMS treatment technologies and a wide range of vessel types including bulk carriers, container ships, gas carriers, general cargo carriers, heavy load carriers, LNG carriers, product carriers, tankers, and vehicle carriers.
The results from the questionnaires were imported into an Excel spreadsheet with the quantifiable information such as dates and sizes, and the information was refined to support sorting for analysis. If not initially indicated, the descriptive sections were deciphered and interpreted to support more comprehensive analysis. Depending on the categorization, data was pulled into numerical terms and presented graphically. The aggregated results allowed for the identification of common issues, challenges, and best practices. The following figures summarize a few of the survey results. A more detailed analysis can be found in Appendix A.
Figure 1 BWMS Operability
Figure 2 BWMS Overall Experience (Positive Feedback)
34%
40%
22%26%
0%5%
10%15%20%25%30%35%40%45%
Reliability User Friendliness OPEX Will Use Again
BWMS Overall Experience (Positive Feedback) BWMS Operability
Operators’ experience (ABS,2019)
@BluePortS Meeting - Lisbon May 15th, 2019
American Bureau of Shipping - March 2019 - 2019 Best Practices for Operations of Ballast Water Management Systems Report
Frequent outages and replacement of UV lamps and clogging of filters that require frequent or continuous back-flushing operations
control system software faults and hardware failures that caused unexplained alarms interrupting continuous operations
effective crew training to allow proper operations, maintenance, troubleshooting, and repairs was problematic
ABS Best Practices for Operations of Ballast Water Management Systems Report 9
Figure 3 BWMS Overall Experience-Treatment Technologies (Positive Feedback)
Figure 4 In-Operation Concerns Reported
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Filtration +Chlorination via
chemical addition(5.0%)
Filtration +Deoxygenation
(0.2%)
Filtration + FullFlow (In-line) EC +
Neutralization(17.8%)
Filtration + Side-stream EC +
Neutralization(29.0%)
Filtration + UVTreatment
(20.7%)
Full Flow (In-line)EC (7.5%)
Ozone Treatment+ Neutralization
(19.9%)
Reliability User Friendliness OPEX Will Use Again
95%
89%
65%
17%
4%
36%
78%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Filtration +Chlorination via
chemical addition(5.0%)
Filtration +Deoxygenation
(0.2%)
Filtration + FullFlow (In-line) EC +
Neutralization(17.8%)
Filtration + Side-stream EC +
Neutralization(29.0%)
Filtration + UVTreatment
(20.7%)
Full Flow (In-line)EC (7.5%)
Ozone Treatment+ Neutralization
(19.9%)
Hardware Failure Software Failure Human Error
Health and Safety Issues Impact on Ballast Coating of Piping Reduction in Ballast Rate
Other Issues and Challenges
@BluePortS Meeting - Lisbon May 15th, 2019
ABS Best Practices for Operations of Ballast Water Management Systems Report 30
6 Contingency Measures
Well planned BWM contingency measures allow shipowners, operators and crew to identify, practice and implement the BWM strategy and be prepared for unexpected circumstances (i.e., inoperable BWMS, equipment failures, etc.). This could avoid unnecessary downtime for the vessel (i.e., delay at berths or ports, inability to continue cargo operations, etc.) and help avoid economic and/or commercial impacts.
The BWM methods used should be well understood by the vessel’s crew. These should be incorporated as part of the training program and documented in the ship-specific BWMP to allow proper operation and maintenance of the BWMS.
With the increasing number of owners experiencing problematic operations as a result of system design limitations, a considerable amount of time during the workshops was used to review practical and feasible contingency measures.
“Alternate Compliant Methods • Mobile facilities that come alongside to
receive and treat ballast water for vessels or shore- based treatment facilities may be (or become) available in the future.
• In anticipation of these facilities becoming available, the vessel could be provided with a method to connect to shore or shipboard reception facilities to obtain compliant ballast water. However, the responsibility for preventing discharging non-compliant ballast water would be the responsibility of the owner.
• For discharges to U.S. waters inside 12 NM, the use of U.S. public water system (PWS) may be an option. Shore connections provided during the BWMS retrofit could better facilitate ballasting the ship with U.S. PWS if necessary.”
Selection of the best alternative IC
ompl
ianc
e w
ith t
he
IMO
Con
vent
ion
Exemption eg under the Same Risk Area (SRA) approach – G7
Ballast Water Exchange – G11
On-board system – G3
containerised BWTS
regular BWTS
Mobile port/shore based
barge
containerised mobile BWTS (e.g on a truck)
Fixed port/shore based
treatment facilities (PRF)
containerised BWTS
Questionnaire under preparation to be sent to stakeholders
WeightingRanking of alternatives
@BluePortS Meeting - Lisbon May 15th, 2019
Selection of the best alternative II
@BluePortS Meeting - Lisbon May 15th, 2019
Thank you !
Christos Kontovas M.Eng, PhD | Dr.-Ing. Naval Architect and Marine Engineer Senior Lecturer Department of Maritime and Mechanical Engineering James Parsons Building, Byrom Street, Liverpool, L3 3AF e: [email protected] Office: 1.30
www.linkedin.com/in/xkontovas/
@BluePortS Meeting - Lisbon May 15th, 2019