The lesson learnt for Piping and Mechanical:
There are some conflicts in specification which furnished by client. But these differences
could not be found by during checking before award and during preparation of drawings.
This mistake affected to engineering as well as construction so much. .. . . So we
have to study carefully all specification and incorporate between disciplines in project.
During checking P!D" we should pay more attention to #$ote% below. These can affect
to &T'" specification" drawings (or e)ample" the length of fle)ible hose was
determined in datasheet. *owever the connection from where to where usually noted in
P!D. Based on these notes" the length of fle)ible hose can be changed in comparison
with the length shown in data sheets. Sometimes the length too short or too long is also
suitable for installation and operation.
During checking !sometric from client" we should update the modifications and changes
in to + common P!D in order to control easily.
The performance &T' was no so good. There was still some Top,up &T' due to low
contingency" wrong &T'" the changes lesson learnt for the ne)t project by many
ways- ascending the contingency" the bulk material shall be /0 and add more /0 for
*12 line" and more 3 D* lines as contingency" and add more gaskets for swing spool
!n the design stage" we have to take care to ensure the hydro test can be done later. The
spool shall have the vent- drain 4flageolet and blind flange5 at the pocket where water can
be trapped.
(or bolts at the joints where have insulation gasket or T67 should be longer than the
length as normally case. !n the !sometric drawings" the bolts" nut and gaskets should be
put on *12 lines at tie in point between onshore and offshore in order to avoid missing
material during fabrication onshore lines.
During review and incorporate vendor data" the orientation of jack up rig shall be
considered in order to avoid clashing to the e8uipment" instrument such as fire water
monitor" eye wash and shower" lighting 7lso pay more attention for SP items. The
space around corrosion coupon has to be enough to connect 9etrieving Tool. (or
2ontinuous Drainers Trap" :e need do check carefully the direction of flow for model inPD&S and installation correctly. (lame 7rrestor location should be near the end of vent
boom to arrest the flame as soon as possible. (or manual valves" e8uipment" the space
around them shall ade8uate for operation and maintenance.
:hen we establish the hydro test package register" to make sure all of lines included in
this list. ;esson learn is the lines which connect to riser 4behind shutdown valve5 to be
8/13/2019 The Lesson Learnt for Piping and Mechanical
2/3
performed hydro test onshore despite of *12 lines name to ensure one golden weld joint
only.
The connection joint inside e8uipment" especially is where storing pressure" the flange
type must be used" no threaded type which is difficult for repairing and replacement. The
self contain eye wash and shower is an e)ample. The leaking found at many threadedconnection joints. !t takes time to repair it.
The e8uipment lifting procedures were submitted late lead to comments from client.
These procedures should be approved by client minimum one day before lifting
e8uipment.
.
+. (or /? packages which scope supply of *;@'2 handover to P
8/13/2019 The Lesson Learnt for Piping and Mechanical
3/3
be a Standard item" and only 8ualified material used for the Test. ;esson ;earnt for this is
before any hold point" all material and e8uipment are used for the Test shall be reviewed
carefully and with all precondition.
. (or Pedestal 2rane PackageA This package is free issued by *;@'2. This package
delayed one month that effected to construction at P