The Incremental Commitment Model process patterns for rapid‐fielding projects PhD Qualifying Examination Proposal Supannika Koolmanojwong November 2009 Viterbi School of Engineering University of Southern California

The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

  • Upload
    vutu

  • View
    215

  • Download
    1

Embed Size (px)

Citation preview

Page 1: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

  

The Incremental Commitment Model process patterns for rapid‐fielding 

projects 

 

 

PhD Qualifying Examination Proposal 

Supannika Koolmanojwong 

 

 

 

November 2009 

 

Viterbi School of Engineering 

University of Southern California 

   

Page 2: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

  

Table of Contents 

List of Figures ................................................................................................................................................ 3 

List of Tables ................................................................................................................................................. 4 

Abstract ......................................................................................................................................................... 1 

Chapter 1 Introduction ................................................................................................................................. 2 

1.1.  Motivation ..................................................................................................................................... 2 

1.2.  Research Questions....................................................................................................................... 4 

1.3.  Intended Research Contribution ................................................................................................... 4 

Chapter 2 Background and Related Work .................................................................................................... 5 

2.1.  The Incremental Commitment Model (ICM) ................................................................................ 5 

2.2.  Software Development Processes ................................................................................................ 6 

2.3.  Process Patterns of Software Development Project ..................................................................... 8 

2.4.  USC Software Engineering Course .............................................................................................. 11 

Chapter 3 Proposed Methodology .............................................................................................................. 12 

3.1.  Design of Empirical Experiment .................................................................................................. 12 

3.2.  The Incremental Commitment Model – Electronic Process Guide (ICM EPG) ........................... 13 

3.3.  Process Decision Drivers ............................................................................................................. 14 

3.4.  Hypothesis ................................................................................................................................... 15 

3.5.  Data Collection and Analysis ....................................................................................................... 16 

3.6.  Threats to Validity ....................................................................................................................... 18 

Chapter 4 Research Plan ............................................................................................................................. 19 

4.1.  Overall of Research Plan ............................................................................................................. 19 

4.2.  Progress of the ICM Electronic Process Guide (EPG) .................................................................. 19 

4.3.  Status of Data Collection ............................................................................................................. 21 

References .................................................................................................................................................. 22 

Appendix A‐ Survey form ............................................................................................................................ 25 

Appendix B‐ Effort Category ....................................................................................................................... 29 

Appendix C‐ ICM EPG: Roles, Activities, Work products, and Delivery Process ......................................... 30 

Appendix D‐ Example of Decision driver ..................................................................................................... 34 

Appendix E‐ CSCI 577 projects .................................................................................................................... 37 

Appendix F‐ Client Feedback Form ............................................................................................................. 38 

Appendix G – Qualitative Interview Form .................................................................................................. 43 

 

Page 3: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

  

List of Figures 

Figure 1. Net Centric Services Usage in Software Development Projects in USC Software Engineering Class .............................................................................................................................................................. 3 Figure 2. Statistics about Mashup created and listed at ProgrammableWeb.com (accessed 11/9/09) ...... 3 Figure 3. Overview of the Incremental Commitment Model ....................................................................... 6 Figure 4. Different Risk Patterns yield Different Processes ........................................................................ 10 Figure 5. The Incremental Commitment Model Electronic Process Guide (EPG) ....................................... 13 Figure 6. An Example of Using Decision Drivers to map with an NDI‐Intensive Project ............................. 15 Figure 7. Research Timeline ........................................................................................................................ 19 Figure 8. Student Background Information Survey ‐ Page 1 ....................................................................... 25 Figure 9. Student Background Information Survey ‐ Page 2 ....................................................................... 26 Figure 10. Student Background Information Survey ‐ Page 3 ..................................................................... 27 Figure 11. Student Background Information Survey ‐ Page 4 ..................................................................... 28 Figure 12. Welcome Page of ICM EPG ........................................................................................................ 30 Figure 13. List of Roles in ICM EPG ............................................................................................................. 30 Figure 14. List of Practices in ICM EPG ........................................................................................................ 31 Figure 15. Practice Page in ICM EPG ........................................................................................................... 31 Figure 16. A task page in ICM EPG .............................................................................................................. 32 Figure 17. A role and responsibilities page in ICM EPG .............................................................................. 32 Figure 18. A delivery process page in ICM EPG ........................................................................................... 33 Figure 19. list of work products in ICM EPG ............................................................................................... 33 Figure 20. An Architected Agile team project status with the Architected Agile Decision Pattern ........... 34 Figure 21. An Architected Agile team project status with the Use Single NDI Decision Pattern ................ 34 Figure 22. An Architected Agile team project status with the NDI‐Intensive Decision Pattern ................. 34 Figure 23. An Architected Agile team project status with the Services‐Intensive Decision Pattern .......... 34 Figure 24. An Services‐intensive team project status with the Services‐Intensive Decision Pattern ......... 35 Figure 25. An Services‐intensive team project status with the Architected Agile Decision Pattern .......... 35 Figure 26. An Services‐intensive team project status with the Use Single NDI Decision Pattern .............. 35 Figure 27. An Services‐intensive team project status with the NDI‐Intensive Decision Pattern ................ 35 Figure 28. An NDI‐intensive team project status with the NDI‐Intensive  Decision Pattern ...................... 36 Figure 29. An NDI‐intensive team project status with the Architected Agile  Decision Pattern ................ 36 Figure 30. An NDI‐intensive team project status with the Use Single NDI  Decision Pattern .................... 36 Figure 31.An NDI‐intensive team project status with the Services‐Intensive  Decision Pattern ................ 36     

Page 4: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

  

List of Tables 

Table 1. Differences between NDI and Net‐Centric Services ........................................................................ 7 Table 2. Differences between NDI and NCS .................................................................................................. 8 Table 3. Characteristics of the Risk‐Driven Process Patterns of the ICM ..................................................... 9 Table 4. Process Decision Drivers ............................................................................................................... 14 Table 5. Status of Process Guidelines used in USC Software Engineering class ......................................... 20 Table 6. Status of Data Collection ............................................................................................................... 21 Table 7. Effort Categories in Effort Reporting System ................................................................................ 29 Table 8. List of Projects and their process in Fall 2008 ‐ Spring 2009 ......................................................... 37 Table 9. List of Projects and their process in Fall 2009 ‐ Spring 2010 ......................................................... 37  

Page 5: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

1  

Abstract 

To provide better services to customer and not to be left behind in a competitive business environment,  

wide variety of ready‐to‐use software and technologies are available for one to grab and go and build up 

software system  in a very  fast pace. Rapid  fielding comes  to play a major role  in developing software 

system to provide a quick response to the organization. This research  investigates the appropriateness 

of  current  software  development  processes  and  develops  new  software  development  process 

guidelines,  focusing  on  four  process  patterns: Use  single NDI, NDI‐intensive,  Services‐intensive,  and 

Architected Agile. Currently, there  is no single software development process model that  is applicable 

to  all  four  process  patterns,  but  the  Incremental  Commitment Model  (ICM)  can  help  a  new  project 

converge on a process that fits their process scenario. The output of this research will be implemented 

as an Electronic Process Guide for USC Software Engineering students to use as a guideline to develop 

real‐client  Software  Engineering  course  projects.  An  empirical  study will  be  conducted  to  verify  the 

suitability of the newly developed process as compared to results data from previous course projects.  

 

Page 6: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

2  

Chapter 1 Introduction 

1.1. Motivation 

The growing diversity of software systems  (requirements‐driven, NDI‐driven, services‐driven,  learning‐

driven,  qualities‐driven,  systems  of  systems)  has  made  it  clear  that  there  are  no  one‐size‐fits‐all 

processes for the full range of software systems. Some process models are being developed that provide 

specific evidence‐based and risk‐based decision points. One of the most thoroughly elaborated of these 

models is the Incremental Commitment Model (ICM). The ICM with its risk‐driven nature and its process 

decision  table  can  help  new  projects  converge  on  a  process  that  fits  their  process  drivers  and 

circumstances. To select and follow the appropriate process pattern helps the development to finish the 

project  faster  and more  efficient.   A  set  of  decision  criteria  and  the  ICM  decision  points  have  been 

defined on a general‐experience basis. Quantitative evidence  is  lacking on the ability of the criteria to 

produce a viable process decision early in the life cycle. 

The USC real‐client MS‐level team projects provide a significant number of projects that are suitable to 

four  of  the  ICM  process  patterns:  Architected  Agile,  Use  Single  NDI,  NDI‐intensive,  and  Services‐

intensive.  The  research will  test  the  hypothesis  that  the  decision  criteria  are  usable  to  determine  a 

viable process during  the  first  stage of  the  life  cycle. Architected Agile exemplifies a  scalable balance 

between plan‐driven and agile‐driven approaches  [Boehm and Turner 2004]. NDI  is an alternative  for 

software  developers  to  reduce  development  time  and  cost  while  increasing  software  quality  and 

productivity via software reuse [Basili and Boehm 2001; Li et.al 2006]. Use single NDI provides an option 

of a ready‐to‐use product either as a complete project solution or as a partial development solution.  

Page 7: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

3  

 

Figure 1. Net Centric Services Usage in Software Development Projects in USC Software Engineering Class 

For  Services‐intensive  project,  based  on  projects  from  at USC’s  Software  Engineering  Class,  Figure  1 

shows an increasing trend in using net centric services in real‐client software development projects. Not 

only in the academic environment, 80% of the world economy provides services in various forms [CMMI 

for Services 2009]. As shown  in Figure 2,  in each day, there are about 3 new mashups or web service 

extensions created and listed at programmableweb.com [Programmableweb.com 2009]. The users who 

are  consuming  these  services  need  to  know  how  to  select  the  right  service  and  utilize  the  service 

properly. Moreover, based on our preliminary study from Fall’08‐Spring’09 projects, we found that for 

some projects, a pure COTS‐Based Development process does not fit well for Net‐Centric Services case.  

 

Figure 2. Statistics about Mashup created and listed at ProgrammableWeb.com (accessed 11/9/09) 

 

Page 8: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

4  

This research mainly experiments with new software development processes for Architected Agile and 

Services‐Intensive  and  extends  Yang  and  Boehm’s  COTS‐Based  Application  Development  guidelines 

(CBD)  [Yang  2006]  by  using  the  risk‐driven  approach  of  the  Incremental  Commitment  Model  and 

incorporating  feedback  from  Bhuta’s  empirical  analysis  on  COTS  interoperability  assessment  [Bhuta 

2007].  

1.2. Research Questions 

Research questions are developed around the concepts of process modeling and process improvement.  

RQ 1. How does the Incremental Commitment Model fit in each process pattern? 

RQ 2. What are the decision criteria that branch a project to each process pattern? 

RQ 3. What activities, roles, responsibilities, and work products should exist for each process pattern? 

RQ 4. In what ways do the process patterns improve project outcomes?  

RQ 5. In what ways could the process patterns be improved? 

 

1.3. Intended Research Contribution 

 

The research is intended to provide the following contributions:  

• Current Software Development Process Investigation and Analysis 

• Decision Criteria of Process Deployment 

• Software Development Process Guidelines for 4 process patterns 

• The ICM Electronic Process Guide 

 

 

Page 9: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

5  

Chapter 2 Background and Related Work 

2.1. The Incremental Commitment Model (ICM) 

The ICM [Boehm and Lane 2007; Pew and Mavor 2007] is a new generation process model.  ICM covers 

the full system development life cycle consisting of the Exploration phase, Valuation phase, Foundations 

phase, Development phase, and Operation phase.  ICM has been evaluated  to be a  reasonably  robust 

framework  for  system  development.  The  core  concepts  of  the  ICM  include  1)  commitment  and 

accountability of system sponsors, 2)  success‐critical stakeholder satisficing, 3) incremental growth of 

system definition and stakeholder commitment, 4) concurrent engineering, 5)  iterative development 

cycles, and 6) risk‐based activity levels and milestones. One of the main focuses of the ICM is feasibility 

analysis; evidence must be provided by the developer and validated by  independent experts. The  ICM 

combines the strengths of various current process models and limits their weaknesses. The ICM, like the 

V‐Model  [V‐Model  2009],  emphasizes  early  verification  and  validation,  but  allows  for  multiple‐

incremental  interpretation  and  alleviates  on  sequential  development.  Compared  to  the  Spiral Model 

[Boehm 1988], the ICM also focuses on risk‐driven activity prioritization, but offers an improvement by 

adding  well‐defined  in‐process  milestones.  While  ICM,  RUP,  and  MBASE  [Boehm  1996]  perform 

concurrent  engineering  that  stabilizes  the  process  at  anchor  point  milestones,  ICM  also  supports 

integrated  hardware‐software‐human  factors  oriented  development.  Comparing with  Agile methods 

[Agile 2009], ICM embraces adaptability to unexpected change perspective and at the same time allows 

scalability.  

Page 10: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

6  

 

Figure 3. Overview of the Incremental Commitment Model 

2.2. Software Development Processes 

The proposed process patterns of software development processes in ICM are developed by combining 

strengths  from  several  development  processes.  The  Architected  Agile  case  balances  a  plan‐driven 

approach  in building up  the  steady architecture and an agile‐driven approach  in  iterative  incremental 

and  frequent delivery as practice  in Scrum  [Rising 2000] or Agile Unified Process  [Ambler 2009]. The 

Software  Engineering  Institute  (SEI)  CMMI‐COTS  [CMMI‐COTS  2009]  and  USC‐CSSE  COTS‐Based 

Development  (CBD) Guidelines  [Yang 2007] provide  strong  foundations  for Use NDI, NDI‐Intensive or 

COTS‐Based  systems  (CBS). Regarding  Services‐Intensive, most of  the processes,  including CMMI‐SVC 

[CMMI‐SVC 2009], cover only the process of how to develop and maintain web services. None of them 

are able to pick, choose and use available online services. Although the Services‐Intensive case is similar 

to the NDI‐intensive case, we found that the differences between NDI and NCS shown in Table 1 and  

Page 11: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

7  

Table 2 below make  the CBD guidelines an  imperfect  fit with a Services‐Based development process. 

Having properly defined software process models is essential, but the ability to effectively communicate 

those models  to  the  software engineers  is also  important. At USC‐CSSE, we have been using  the  IBM 

Rational Method Composer to develop an Electronic Process Guide (EPG) for the ICM. Currently, the ICM 

EPG covers the guidelines for all four process patterns. 

Table 1. Differences between NDI and Net‐Centric Services 

Category  Non‐Developmental Item [ includes open source, customer‐furnished software] 

Net‐Centric Services 

Payment  • Non‐commercial  items  usually  have  no  monetary cost 

• Expensive  initial  costs,  moderate  recurring  fee, training fee, licensing arrangement‐dependent 

• Not all services are free, mostly pay per transaction • Low  initial  costs, moderate marginal  cost,  duration 

depending license 

Platform  • Specific and limited to specific platform / language • Generally  supported  on  a  subset  of  platforms  or 

multiple platforms but with different editions 

• Platform and language independent • Server and client can work on different platform • Interaction between machines over a network 

Integration  • Generally more tightly coupled • Not  very  flexible  on  existing  legacy  systems  when 

proprietary standard is used • Difficult  when  it  is  a  platform  dependent  and 

different technologies involved in it. • detailed  documentation  and  on‐site  extensive 

support  

• Generally more loosely coupled • Common web standards, flexible, easy to integrate • Requires internet access • Support forums and API documentation available • This  integration  could  be  done  merely  in  code, 

without  additional  installation  of  external components 

Changes  • Able to freeze the version, under user control • Designed for specific use so costly for customization 

and change • Change on server side doesn’t impact the client side • Major releases once in while • Requires end user intervention to upgrade  

• Changes are out of developers’ control  • Not easy to predict change, cannot avoid upgrade • The end‐user has the latest version of the service • Change  on  the  server  side  can  result  in  the  client 

side • Minor releases frequently (through patching) • Does not require end user intervention 

Extensions  • Only if source is provided and the license permits • Extension must  be  delivered  to  and  performed  at 

the end‐user’s site • Custom extensions may not be portable across COTS 

or compatible with future releases 

• Extension  is  limited  to  data  provided  by  the  web services 

• In‐house extension such as wrapper or mashup • Little control over performance overhead 

Evaluation 

Criteria 

• Maintenance,  extensibility,  scalability,  reliability, cost,  support,  usability,  dependency,  ease  of implementation,  maintainability,  upgrades,  size, Access to source and code‐escrow considerations 

• Upfront costs opposed to subscription • Platform compatibility; Feature controllability 

• Reliability,  Availability,  Cost,  Available  Support, Speed,  Predicted  longevity  of  the  service  provider, release cycle, Bandwidth 

• Recurring  costs  to  use  of  the  service  and  future functionality offered 

• Standards compatibility; Feature‐ data controllability Support 

Services 

• Vendor  support  for  integration,  training  and tailoring/modification sometimes available for a fee 

• Help  topics  or  FAQs  would  likely  not  be  updated after installation 

• Upgrades/Patches and data migration support • Sometimes can be customized for specific user • Upgrade  through  purchasing  new  releases,  self‐

install 

• Support for tailoring/modification, training generally not available 

• Help  topics would generally be  frequently updated; self‐learning 

• Usually not customized for specific user • Patching on service provider’s side; mostly does not 

require installation on client side 

Page 12: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

8  

Data  • Data  often  stored  locally.  Backups  generally  the responsibility of the user 

• Data access is generally fast  • Possible variety of proprietary formats • May be inflexible for change but more secure • Platform‐dependent data format • Can process data offline 

• Data stored on service host’s servers. Backups by the provider. Introduces privacy and data‐retention  

• Data access could be slower since it is internet based • Common XML using web standard protocols • Data  from different web  services  can be used by a 

single client program  • Process data online 

 

 

Table 2. Differences between NDI and NCS 

Characteristics   NDI  NCS  Platform Independent   Yes / No  Yes  Required Internet Access   Yes / No  Yes  Common Standard   No Yes  Option of rejecting next release Yes  No  Change / upgrade control   Client /Server’s site  Server’s site  End user has the latest version  Yes / No  Yes  Database Ownership   Yes  Yes/No  

 

2.3. Process Patterns of Software Development Project 

Given  a  project  description,  one  may  not  know  that  it  should  follow  a  general  waterfall  or  agile 

development process or if it needs to adopt different development process. As shown in Table 3, in the 

exploration  phase, with  the  known  initial  scoping,  project  risks,  and  project’s  nature,  the  following 

process drivers generally help make an appropriate decision whether the project should follow one of 

several process pattern  development processes:  system’s  size  and  complexity;  its  rate of  change;  its 

mission  criticality;  the extent of NDI  support  for desired  capabilities; and  the available organizational 

and personnel capability for developing the system.  

Page 13: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

9  

Table 3. Characteristics of the Risk‐Driven Process Patterns of the ICM 

Process patterns  Example 

Size, Com

plexity

 

Change Rate (%

/Mon

th) 

Criticality 

NDI Sup

port 

Organizational and

 

Person

nel Capability 

Time/Bu

ild; Tim

e/Increm

ent 

Architected Agile  Business  data processing 

Med  1‐10  Med‐High 

Good;  most  in place 

Agile‐ready Med‐high 

2‐4 wks;  2‐6 months  

Use single NDI  Small accounting        Complete     NDI‐ intensive  Supply  chain 

management Med‐High 

0.3‐3  Med‐Very High 

NDI‐driven architecture 

NDI‐ experienced; med‐high 

SW:1‐4 weeks; Systems:  6‐18 months 

Services‐intensive  Community Services  or  Special Interest Group 

Low‐Med 

0.3‐3  Low‐Med 

Tailorable service elements 

NDI‐ experienced 

<= 1 day; 6‐12 months 

 

Moreover,  as  shown  in  Figure  4,  different  risk  patterns  for  each  project  yields  different  software 

processes. For example, in the second example, when in the Exploration phase, the developers spent a 

good  amount  of  effort  to  explore  and  find  a  perfect  NDI  that  satisfied  all  the  win  conditions,  the 

development team could skip the Valuation phase and Foundations phase.  In the third and the fourth 

example,  if the development team found possible NDIs/NCSs  in the Exploration phase, the team could 

spend  more  effort  and  time  evaluating  the  NDIs/NCSs,  prioritizing  their  win‐conditions  or  their 

constraints. On the other hand, since NDIs/NCSs will provide a majority of the end product features, the 

development team could spend less time in Foundations and Development‐related efforts. Processes in 

the NDI and NCS cases might look similar, but the differences are in the details as mentioned in Table 3.  

Page 14: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

10  

 

Figure 4. Different Risk Patterns yield Different Processes 

For the small e‐services projects developed in our project course, four of the 12 process patterns of the 

ICM [Boehm et.al 2009] predominate: 

Architected Agile ‐ For less than 80 agile‐ready‐people team size and a fairly mature technology project, 

agile methods can be scaled up using an Architected Agile approach emphasizing early  investment  in a 

change‐prescient  architecture  and  all  success‐critical‐stakeholders  team  building  [Boehm  and  Turner 

2004]. The Valuation phase and Foundations phases can be brief. A scrum of Scrums approach can be 

used in the Development phase.  

Use NDI – When an appropriate NDI  (COTS, open  source,  reuse  library,  customer‐furnished package) 

solution is available, it is an option to either use the NDI or develop perhaps a better version by oneself 

or  outsource  such  a  development  which  generally  incurs more  expense  and  takes  longer  to  begin 

capitalizing on  its benefits. On  the other hand,  an NDI may  come with high  volatility,  complexity, or 

incompatibility. Major effort will then be spent on appraising the NDI.   

Page 15: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

11  

NDI‐Intensive –NDI‐Intensive system is a system where 30% of end‐user functionality is provided by NDI 

[Yang 2006].  A great deal of attention goes into appraising the functionality and interoperability of NDI, 

effort spent on NDI  tailoring and  Integration, and NDI upgrade synchronization and evolution  [Li et.al 

2006; Morisio et.al. 2000].  

Services‐Intensive  –Net  Centric  Services  support  community  service  organizations  in  their  online 

information  processing  services  such  as  donation,  communication  or  their  special  interest  group 

activities such as discussion boards, file sharing, and cloud computing. Similar to NDI‐Intensive, the focus 

goes to appraising the functionality of the available services and tailoring to meet needs.  

 

2.4. USC Software Engineering Course 

In  the keystone  two‐semester  team project graduate  software engineering  course  sequence CS577ab 

[USC CSCI577 2008] at USC, students  learn through experience how to use good software engineering 

practices to develop software systems from the Exploration Phase to the Operation Phase, all within a 

24‐week schedule. Six on‐campus and two off‐campus students team up to develop real‐client software 

system products. Based on the nature of the course projects, all teams will follow the ICM Exploration 

Phase  guidelines  to  determine  their  most  appropriate  process  pattern.  Most  of  the  clients  are 

neighborhood non‐profit organizations, small businesses or USC departments. Examples of the projects 

are an accounting system, an art gallery web portal, a theatre script online database, and an EBay search 

bot. Because of  the  semester break between  Fall  and  Spring  semester,  for  the  Software Engineering 

class, we added a short Rebaselined Foundations phase to accommodate the possible changes.  

Page 16: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

12  

Chapter 3 Proposed Methodology 

3.1. Design of Empirical Experiment 

Experiment Preparation:  I applied  the  ICM process  to  itself by  first exploring  the problems of current 

processes and opportunities to  improve them. Besides an extensive  literature review,  I collected data, 

feedback and  input from the CSCI 577‐ software engineering class  in Fall 2008‐Spring 2009, where the 

first version of the ICM EPG for Architected Agile and USC‐CSSE CBD guidelines were used. The collected 

data are a) student’s individual critiques which is mainly focused on process improvement; b) Effort; c) 

Weekly  risk  report;  d)  Grades;  e)  Interview  of  service‐based  development  teams  that  used  CBD 

guidelines  and CBD  teams  regarding  feedback of  the  guidelines  and  criteria or  incidents of decisions 

changed to process pattern project, and f) feedback from clients. This data is being analyzed and will be 

used as feedback and input to develop the EPG for 4 process patterns.  

Pre‐experiment:  Before  the  project  starts,  there will  be  a  questionnaire  to  collect  students’  general 

information and appraise their knowledge about general software engineering, NDI and NCS.  

Experiment: The experiment will be started once the students form their teams and select the projects. 

Teams  will  follow  the  ICM  Exploration  phase  process  to  determine  their most  appropriate  process 

patterns. Tutorials, lectures, assignments, and extra readings will help students come up with a software 

engineering learning curve and will be similar to previous years. In addition, they will use material on the 

four process patterns. During  the experiment,  the  following  tools and activities will be used  to collect 

data  and  to  ensure  project  success:  the  ICM  EPG,  effort  reporting  system,  risk  analysis  tool,  NDI‐

Interoperability assessment  tool  [Bhuta 2007], architecture  review board, verification & validation by 

off‐campus students, teaching staff, and team mentor by Software Engineering PhD students.  

Page 17: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

13  

Post‐Experiment:  After  the  experiment,  the  following  information will  be  collected  and  analyzed  a) 

follow‐up questionnaires; b) individual critiques; c) clients’ feedback; d) effort; e) risk items; f) Incidence 

of direction changes at reviews relative to outcomes; and g) team performance based on team grading. 

3.2. The Incremental Commitment Model – Electronic Process Guide (ICM EPG) 

Effectively communicating the software process model to the software engineers is essential in enabling 

them  to understand  the overall process as well as  specific areas of  focus. To  satisfy  the objective of 

helping  students  learn  the  software processes,  the  ICM  EPG  is developed by using  the  IBM Rational 

Method Composer (RMC) [IBM RMC 2008]. The  ICM EPG as shown  in Figure 5, describes the software 

development  process  by  providing  guidance  in multiple‐view  representations,  which  are  role‐based 

representation,  activity‐based  representation,  chronological  event‐based  representation,  and  artifact‐

based  representation. Moreover,  additional  artifact  templates  and  supplementary  guides  have  been 

demonstrated  to  speed up  the users’  learning  curve and  support  them  in  their development process 

[Koolmanojwong 2007; Phongpaibul 2007]. Samples of the ICM EPG can be found in Appendix C.  

 

Figure 5. The Incremental Commitment Model Electronic Process Guide (EPG) 

Page 18: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

14  

3.3.  Process Decision Drivers  

In order to select the appropriate process pattern, the development team will use the decision drivers 

presented in Table 4. The development team will use 16 decision drivers to evaluate the project status 

and map it with the possible maximum‐minimum boundary range of each possible process pattern.  

Table 4. Process Decision Drivers 

Decision Criteria  Importance Architected 

Agile Use NDI 

NDI‐Intensive 

Services‐Intensive 

Alternatives More than 30% of features available in NDI/NCS      0 – 1  2 – 3   3 – 4  3 – 4 

Has a single NDI/NCS that satisfies a complete solution      0 – 1  4  2 – 3  2 – 3 

Very unique/ inflexible business process     2 – 4  0 – 1  0 – 1  0 – 1 

Life Cycle 

Need control over upgrade / maintenance      2 – 4  0 – 1  0 – 1  0 – 1 

Rapid Deployment; Faster time to market     0 – 1  4  2‐ 4  2 – 3 

Architecture 

Critical on compatibility      2 – 4  3 – 4  1 – 3  2 – 4 

Internet Connection Independence      0 – 4  0 – 4   0 – 4  0 

Need high level of services / performance      0 – 4  0 – 3  0 – 3  0 – 2 

Need high security      2 – 4  0  ‐ 4  0 – 4  0 – 2 

Asynchronous Communication    0 – 4  0 – 4  0 – 4  0 

Access Data anywhere      0 – 4  0 – 4  0 – 4  4 

Resources 

Critical mass schedule constraints      0 – 1  3 – 4  2 – 3  2 – 4 

Lack of Personnel Capability      0 – 2  3 – 4  2 – 4  2 – 3 

Little to no upfront costs (hardware and software)      0 – 2  2 – 4  2 – 4  3 – 4 

Low total cost of ownership    0 – 1  0 – 3  0 – 3  2 – 4 

Not‐so‐powerful local machines     1 – 4  1 – 3  0 – 4  3 – 4 

 

The  “Importance”  attribute, whose  values  are  1‐Low,  2‐Medium,  3‐High, will  act  as  a  tie  breaker  to 

support decision making in selecting the best fit process pattern. The value of project status ranges from 

0‐Very Low, 1‐Low, 2‐Moderate, 3‐High, and 4‐Very High. Figure 6 shows an example of a team that  is 

developing a simple website. The team found a possible content management system NDI, but  it does 

not satisfy all of the capability win conditions. The team rates the project status based on 16 decision 

drivers, the result is shown in the blue line. The background block diagram is the max‐min boundary of 

Page 19: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

15  

NDI‐Intensive  project.  The  red  underline  represents  High  Importance  level,  while  green  dashed 

underline represents Low  Importance  level. As a result, the decision driver shows that this team could 

follow the NDI‐intensive software development process. More examples can be found in Appendix D.  

 

Figure 6. An Example of Using Decision Drivers to map with an NDI‐Intensive Project 

3.4. Hypothesis 

The ICM characteristics in each process pattern 

• H1a: Commitment and Accountability exist in each process pattern 

• H1b: Success‐critical stakeholder satisficing exists in each process pattern 

• H1c: Incremental growth of system definition and stakeholder commitment exists in each process 

pattern 

• H1d: Concurrent engineering exists in each process pattern 

• H1e: Iterative development cycles exists in each process pattern 

• H1f: Risk‐based activity levels and milestones exists in each process pattern  

Decision driver and each process pattern 

Page 20: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

16  

• H2a: if Evaluating Alternative is part of the decision criteria, the development team can effectively 

select the appropriate process pattern  

• H2b: if Control Over Project Life Cycle is part of the decision criteria, the development team can 

effectively select the appropriate process pattern  

• H2c: if Architectural Performance is part of the decision criteria, the development team can 

effectively select the appropriate process pattern  

• H2e: if Project Resources is part of the decision criteria, the development team can effectively select 

the appropriate process pattern 

 

Project outcome improvement 

• H3: The development teams following the correct process pattern would outperform others using 

traditional processes 

 

Process patterns improvement 

• H4: The development teams following the correct process pattern would outperform others using 

traditional processes 

  

3.5. Data Collection and Analysis 

Data collection process will be done to answer the research questions.  

RQ 1. How does the Incremental Commitment Model fit in each process pattern? 

 The  6  key  concepts  of  the  ICM  are  Commitment  and  accountability,  Success‐critical  stakeholder 

satisficing,  Incremental  growth  of  system  definition  and  stakeholder  commitment,  Concurrent 

engineering,  Iterative development cycles, and Risk‐based activity  levels and milestones. The empirical 

Page 21: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

17  

analysis  will  be  performed  to  verify  which  each  key  concept  is  contained  in  each  process  pattern. 

Validation will use concrete examples.  

RQ 2. What are the decision criteria that branch a project to each process pattern? 

The  initial  decision  criteria  or  decision  drivers  have  been  developed  based  on  experience  and  the 

literature review. The development teams are currently using the decision driver to help them select the 

appropriate process. Qualitative interviews and the incidence of direction changes will be used to refine 

the decision criteria.  

RQ 3. What activities, roles, responsibilities, and work products should be there for each process 

pattern? 

Based on the current CBD guidelines [Yang 2007] and various literature reviews, activities, roles, 

responsibilities, and work products will be defined and developed into the ICM Electronic Process Guide. 

At the end of the semester, qualitative interview and students’ individual critique will be used as a main 

source of process guidelines improvement.  

RQ 4. In what ways do the process patterns improve project outcomes?  

The following measurements will be used to identify whether the proposed process patterns have 

improve the project outcomes:  

‐ Personnel Effort 

‐ Number of Defect 

‐ Team performance 

‐ Client Satisfaction 

RQ 5. In what ways could the process patterns be improved? 

Based on the results from RQ3 and RQ4, the gap will be identified for further improvement.  

   

Page 22: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

18  

3.6. Threats to Validity 

This section discusses possible validity threats and ways in which the threats could be reduced.  

‐ Inconsistent Effort Reporting:  It  is possible  that  there might be  inaccurate efforts  reported,  so 2 

forms  of  effort  reporting will  be  used,  classroom  effort  reporting  system  and  a  post‐experiment 

questionnaire.  

‐ Non‐representativeness  of  subjects:  Based  on  the  history  of  the  software  engineering  class,  the 

participants, with average of not more than 2 years of industrial experience and an average 12‐hour, 

non‐collocated work week, are not representative of a software engineer in the industry.  However, 

the clients and off‐campus students are full‐time working professionals. 

‐ Learning Curve:  The possibility of  an  imbalanced  team  and  the  threat of  learning  curve  in using 

these process models could be overcome by providing tutorials and discussion sessions  in order to 

build the foundations for all participants.  

‐ Non‐representativeness  of  projects:  Although  the  target  projects  need  to  conform  to  fixed 

semester schedules, this  is to some degree representative of fixed‐schedule  industry projects. The 

projects  are  small  e‐services  applications,  but  will  be  developed  for  real  clients  with  diverse 

domains, and will use the same COTS or services that are used  in  industry projects. Moreover, the 

process guidelines and decision drivers will be cross checked with experts in the field for enterprise‐

level compatibility.  

 

Page 23: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

19  

Chapter 4 Research Plan 

4.1. Overall of Research Plan 

Figure 7 shows the overall picture of the research timeline starting from 2007. The first group painted in 

pink  represents  time  line of  the CSCI 577 Software Engineering class. The green bars  represent works 

involved  in  this  research.  The blue bar  represents  a  related work which  is  the use of USC CSSE CBD 

guidelines [Yang and Boehm 2007]. The red markings represent the dissertation milestones. 

 

 Figure 7. Research Timeline 

4.2. Progress of the ICM Electronic Process Guide (EPG) 

One of the main contributions of this research is the ICM EPG. In Fall 2005 – Spring 2008, there were 2 

kinds  of  software  development  process  guidelines,  LeanMBASE  guidelines  for  Non‐COTS‐Based 

Page 24: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

20  

Development project and USC CSSE CBA guidelines  for COTS‐Based Development project.  In  summer 

2008,  the  IBM Rational Method Composer was selected as a  tool  to  implement  the EPG. At  the same 

time,  the  Incremental Commitment Model was  selected  to  replace  the  LeanMBASE  approach.  In  Fall 

2008, the first version of ICM EPG for the Architected Agile team was available for developers to follow. 

For NDI/NCS teams, they followed the USC CSSE CBA guidelines. Based on feedback of the first version 

of  ICM  EPG  for  Architect  Agile  from  Fall  2008  –  Spring  2009  and  discrepancies  and  outdated  data 

observed  in USC CSSE CBA guidelines  for NDI/NCS teams,  in summer 2009, the second version of  ICM 

EPG  for  Architected  Agile  process  and  the  first  version  of  ICM  EPG  for  NDI/NCS  were  developed. 

Currently,  4  available  process  guidelines  for  4  different  process  patterns  are  being  used  by  the 

development teams in CSCI577 Software Engineering class. The summary of progress of the ICM EPG is 

shown in Table 5.  

 

Table 5. Status of Process Guidelines used in USC Software Engineering class 

Process  Pattern  / Semester 

Fall ’05‐ Spring ‘08  Summer ‘08 Fall ‘08 

Spring ‘09 

Summer ‘09 Fall ‘09 

Spring’10 

Architected Agile Use LeanMBASE 

Guidelines Develop 

ICM EPG : AA V1 Deploy 

ICM EPG : AA V1 Revise V2  Deploy V2 

NDI‐Intensive 

Use USC CSSE COTS‐Based Application Guidelines 

Develop ICM EPG : NDI‐ intensive V1 

Deploy V1 

Services‐Intensive Develop ICM EPG : 

Services‐intensive V1 Deploy V1 

Use NDI Develop ICM EPG : Use single NDI V1 

Deploy V1 

 

   

Page 25: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

21  

4.3. Status of Data Collection 

Currently  the experiment  is  running  at  the USC CSCI577  Software  Engineering Class.  Table 6  shows  the projects’  important 

milestones and key dates for data collection.  

 Table 6. Status of Data Collection 

Schedule  Activities Fall 2009   

October 19‐23  First project milestone review November 30 – December 4  Second project milestone review December 7  Follow up questionnaire December 9  Client Feedback, Individual Critique 

Spring 2010   February 10‐11  Third project milestone review April 14‐15  Fourth project milestone review May 7  Project deliverables May  Interview, Client Feedback, Individual Critique 

Page 26: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

22  

References 

Agile, Principles behind the agile manifesto, http://agilemanifesto.org/principles.html. accessed on 8/4/2009. 

Amazon Payment Services, https://payments.amazon.com/sdui/sdui/index.htm 

Ambler, S.W., Agile Unified Process, http://www.ambysoft.com/unifiedprocess/agileUP.html Accessed 8/4/2009 

Basili, V., Boehm, B., "COTS‐Based Systems Top 10 List," Computer, Volume 34, Number 5, May, 2001, pp. 91‐93 

Bhuta, J., “A Framework for Intelligent Assessment and Resolution of Commercial‐Off‐The‐Shelf Product Incompatibilities” PhD Dissertation, Department of Computer Science, University of Southern California, August 2007 

Boehm B, "A Spiral Model of Software Development and Enhancement", IEEE Computer, 21(5):61‐72, May 1988 

Boehm B, Anchoring the Software Process, IEEE Software, v.13 n.4, p.73‐82, July 1996 

Boehm, B. and Bhuta, J., "Balancing Opportunities and Risks in Component‐Based Software Development," IEEE Software, November‐December 2008, Volume 15, Issue 6, pp. 56‐63 

Boehm, B. and Lane, J., “Using the Incremental Commitment Model to Integrate Systems Acquisition, Systems Engineering, and Software Engineering,” “Cross Talk, October 2007, pp.4‐9 

Boehm, B. and Lane, J., "Guide for Using the Incremental Commitment Model (ICM) for Systems Engineering of DoD Projects" USC CSSE Tech Report 2009‐500 

Boehm, B., Lane, J. and Koolmanojwong, S. "A Risk‐Driven Process Decision Table to Guide System Development Rigor," Proceedings of the 19 th International Conference on Software Engineering, Singapore, July, 2009. 

Boehm, B. and Turner, R. 2004. Balancing agility and discipline:  a guide for the perplexed. Addison‐Wesley, Boston. 

CMMI for COTS‐based Systems, http://www.sei.cmu.edu/publications/documents/03.reports/03tr022.html 

CMMI for Services Version1.2, ftp://ftp.sei.cmu.edu/pub/documents/09.reports/09tr001.doc 

CMMI for Services flyer, www.sei.cmu.edu/cmmi/models/CMMI‐for‐Services‐one‐pager‐20090320.doc 

Page 27: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

23  

CrossTalk, The Journal of Defense Software Engineering, http://www.stsc.hill.af.mil/index.html, accessed 08/24/09 

DOD 5000.02 Operation of the Defense Acquisition System [ACC] http://www.dtic.mil/whs/directives/corres/pdf/500002p.pdf accessed 09/11/09 

Google Map, http://maps.google.com/ 

IBM Rational Method Composer http://www‐01.ibm.com/software/awdtools/rmc/ 

Instructional ICM‐Software Electronic Process Guide, http://greenbay.usc.edu/IICMSw/index.htm 

Koolmanojwong, S., et.al, "Comparative Experiences with Software Process Modeling Tools for the Incremental Commitment Model" USC CSSE Technical Report 2007‐824 

Koolmanojwong, S., et.al, "Incremental Commitment Model Process Guidelines for Software Engineering Class", USC CSSE Technical Report 2008‐832 

Lenth, R. V., “Some practical guidelines for effective sample size determination”,  American Statistician, 2001, 55, 187‐193. 

Li, J., et al., “An empirical study of variations in COTS‐Based Software Development Processes in Norwegian IT industry,” Journal of Empirical Software Engineering vol. 11, no.3, 2006, pp 433‐461 

Morisio, M., C. B. Seaman , A. T. Parra , V. R. Basili , S. E. Kraft , S. E. Condon, Investigating and improving a COTS‐based software development, Proceedings of the 22nd international conference on Software engineering, p.32‐41, June 04‐11, 2000, Limerick, Ireland 

Ning, http://www.ning.com/, accessed 08/24/08 

Pew, R. W., and Mavor, A. S. , “Human‐System Integration in the System Development Process:  A New Look”. 2007, National Academy Press. 

Phongpaibul, M., Koolmanojwong, S., Lam, A., and Boehm, B. "Comparative Experiences with Electronic Process Guide Generator Tools," ICSP 2007, pp. 61‐72 

ProgrammableWeb http://www.programmableweb.com/mashups accessed on 11/9/2009 

Rising, L., & Janoff, N. The Scrum Software Development Process for Small Teams. IEEE Software, July/August 2000 

Scaffidi, C.,” Topes: Enabling End‐User Programmers to Validate and Reformat Data”, PhD Dissertation, Technical Report CMU‐ISR‐09‐105, Institute for Software Research (ISR), Carnegie Mellon University, May 2009. 

USC – CSCI577 Software Engineering Class I Website, http://greenbay.usc.edu/csci577/fall2008/site/index.html accessed on 08/24/08 

V‐Model Lifecycle Process Model http://www.v‐modell.iabg.de/kurzb/vm/k_vm_e.doc accessed on 10/9/2009 

Page 28: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

24  

Yahoo Developer Network, http://developer.yahoo.com/ 

Yang, Y., "Composable Risk‐Driven Processes for Developing Software Systems from Commercial‐Off‐The‐Shelf (COTS) Products," PhD Dissertation, Department of Computer Science, University of Southern California, December 2006 

Yang Y. and Boehm B., COTS‐Based Development Process guidelines,   http://greenbay.usc.edu/csci577/spring2007/site/guidelines/CBA‐AssessmentIntensive.pdf Accessed 08/24/07 

   

Page 29: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

25  

Appendix A­ Survey form 

 Figure 8. Student Background Information Survey ‐ Page 1 

 

Page 30: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

26  

 Figure 9. Student Background Information Survey ‐ Page 2 

   

Page 31: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

27  

 Figure 10. Student Background Information Survey ‐ Page 3 

   

Page 32: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

28  

 Figure 11. Student Background Information Survey ‐ Page 4 

Page 33: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

29  

Appendix B­ Effort Category 

Table 7. Effort Categories in Effort Reporting System Operational Concept Development   Implementation Analyze Current System  Explore and evaluate  alternatives Identify Shared Vision  Analyze and prioritize capabilities to prototype Establish New Operational Concept  Acquire  NDI/ServicesIdentify System Transformation  Prepare development / operational environment Identify Organizational and Operational Transformation Develop prototype Identify Objectives, Contraints and Priorities  Develop componentAssess Operational Concept  Assess Prototype / componentDocumenting of OCD  Tailor NDI/ ServicesSystem and Software Requirements Development   Integrate ComponentsSet up WinWin negotiation context  Transition the systemNegotiate (during meeting)  Develop Transition PlanNegotiation using WikiWinWin tool (after meeting)   Develop Support PlanIdentify win conditions    Provide TrainingIdentify issues    Develop User ManualNegotiate options    Documenting of PrototypingDevelop Requirements Definition  Testing Assess requirements definition  Identify Test CasesDocumenting of SSRD  Identify Test PlanDocumenting of WinWin Negotiation Report  Identify Test ProceduresSystem and Software Architecture Development  Record Test ResultsAnalyze the Proposed System  Identify Regression Test Package Define Technology‐Independent Architecture  Documenting Test‐related documents Define Technology‐Dependent Architecture  Perform custom component test Specify Architecture Styles, Patterns and Frameworks Perform NDI/service component test Assess System Architecture  perforn Integration testDocumenting of SSAD  perform acceptance test

Life Cycle Planning   perform regression test Identify Milestones and Products perform unit testIdentify Responsibilities and Skills  Project Administration (currently not in ICM EPG) Identify Life Cycle Management Approach  Create and maintain project website Estimate Project Effort and Schedule using COCOMO II Interact with ClientsEstimate Project Effort and Schedule using COCOTS  Interact between team members Assess Life Cycle Content  Learn about Incremental Commitment Model Detail Project Plan  Learn about Application domain Record Project Progress  Prepare transition siteRecord Project Individual Effort  Manage Code configurationIdentify Development Iteration  Attend ARBAssess Development Iteration  Planning and controlPerform Core Capabilities Drive‐Through  Control Project PerformanceDocumenting of LCP  Quality Management Documenting Iteration‐related cocuments  Gather DefinitionsTrack problem and report closure  Construct Traceability MatrixFeasibility Evidence Description   Identify Configuration Management Strategy Analyze Business Case  Identify Quality Management Strategy Identify, assess, and manage risks  Verify and Validate Work Products Provide Architecture Feasibility Evidence  Assess Quality Management Strategy Provide Process Feasibility Evidence  Documenting of QMPAssess Feasibility Evidence  Documenting of SIDAssess/Evaluate NDI/Services Candidate  Documenting of review‐related document Check components Interoperability Documenting of FED 

 

Page 34: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

30  

Appendix C­ ICM EPG: Roles, Activities, Work products, and Delivery Process 

  

Figure 12. Welcome Page of ICM EPG 

 Figure 13. List of Roles in ICM EPG 

Page 35: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

31  

 Figure 14. List of Practices in ICM EPG 

 

 Figure 15. Practice Page in ICM EPG 

 

Page 36: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

32  

 Figure 16. A task page in ICM EPG 

  

 Figure 17. A role and responsibilities page in ICM EPG 

  

Page 37: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

33  

 Figure 18. A delivery process page in ICM EPG 

 

 Figure 19. list of work products in ICM EPG 

Page 38: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

34  

Appendix D­ Example of Decision driver 

 Figure 20. An Architected Agile team project status with the Architected Agile Decision Pattern 

 

 Figure 21. An Architected Agile team project status with the Use Single NDI Decision Pattern 

 Figure 22. An Architected Agile team project status with the NDI‐Intensive Decision Pattern 

 Figure 23. An Architected Agile team project status with the Services‐Intensive Decision Pattern 

   

Page 39: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

35  

 Figure 24. An Services‐intensive team project status with the Services‐Intensive Decision Pattern 

 Figure 25. An Services‐intensive team project status with the Architected Agile Decision Pattern 

 Figure 26. An Services‐intensive team project status with the Use Single NDI Decision Pattern 

 

 Figure 27. An Services‐intensive team project status with the NDI‐Intensive Decision Pattern 

   

Page 40: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

36  

 Figure 28. An NDI‐intensive team project status with the NDI‐Intensive  Decision Pattern 

 Figure 29. An NDI‐intensive team project status with the Architected Agile  Decision Pattern 

 Figure 30. An NDI‐intensive team project status with the Use Single NDI  Decision Pattern 

 Figure 31.An NDI‐intensive team project status with the Services‐Intensive  Decision Pattern 

Page 41: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

37  

Appendix E­ CSCI 577 projects 

Table 8. List of Projects and their process in Fall 2008 ‐ Spring 2009 

#  Project Name  Process Followed P1  Master Pattern  Architected Agile P2  Housing Application Tracking System  Architected Agile P3  Revamping Proyecto Pastoral  Architected Agile P4  UNO Web Tool  Architected Agile P5  Hunter‐gatherer interactive research database  Architected Agile P6  The IGM On‐Line Art Gallery  COTS‐Based Development P7  EZBay  Architected Agile P8  AAA Petal Pushers Remote R&D  Architected Agile P9  Information Organization System  COTS‐Based Development P10  The Roots of Inspiration web site  Architected Agile P11  Web‐based Service for TPC Foundation  COTS‐Based Development P12  Online Peer Review System for Writing Program  Architected Agile P13  Acme Research Engine for USC‐WB Archives  Architected Agile P14  The Virtual Assistant Living and Education Program  Architected Agile P15  Data Base for III, Inc.  COTS‐Based Development P16  Theatre Script Online Database  Architected Agile   

Table 9. List of Projects and their process in Fall 2009 ‐ Spring 2010 

#  Project Name  Process Followed P1  Online DB support for CSCI 511  Architected Agile  P2  SHIELDS for Family  Architected Agile  P3  Theater Stage Manager Program  Architected Agile  P4  Growing Great Online  Services‐Intensive  P5  SPC Website Automation Enhancement  NDI‐Intensive  P6  VALE Information Management System  Services‐Intensive  P7  LANI D‐Base  Architected Agile  P8  Freehelplist.org  Services‐Intensive  P9  Early Medieval East Asian Timeline  Architected Agile  P10  BHCC Website Development  Architected Agile  P11  AI Client Case Management Database  Architected Agile  P12  AI Website Development  Services‐Intensive  P13  Healthcare The Rightway  Services‐Intensive  

P14  AROHE Web Development  Architected Agile       

Page 42: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

38  

Appendix F­ Client Feedback Form 

Appendix F1‐Client Feedback Form – CSCI577a   Project Name: __________________________________________ Team # _______  Please provide a ranking where indicated. Use a 1 ‐ 5 scale where 1 is low and 5 is high. Where comments are requested,  please  include  any  descriptive  statements  you  wish  to  add. FOR  THE  FIRST  TWO  ITEMS,  consult  your  team's  Development  Commitment  Package  documentation  by  clicking  on  the  project  name  in  the  table  shown  on  the  course  webpage http://greenbay.usc.edu/csci577/fall2008/site/projects/index.html  1.  Operational Concept Description (especially Sections: 2. Shared Vision; 3. System Transformation). How well did the team capture your ideas of what the new system should do?  Ranking: (1‐5)     Comments:   2.  Team helpfulness Did the team suggest new idea about your project? Did the team support you in any project complexity?   Ranking : (1‐5)     Comments:  FOR THE NEXT ITEMS, base your responses on your interactions with the project team and their product.  3.  Team Responsiveness: Was the team responsive to you and to your requirements? Did the team answer any questions you might have had? How successful was the requirements negotiation between you and your team?  Ranking : (1‐5)  Comment:    4.  Project Results: How satisfied are you with the prototype? How well does the proposed system meet the need identified by your project?  Ranking: (1‐5)  Comment:     5. Project Future: Do you think this project should be carried forward for development in CS577b? Has the team adequately  identified  and managed  the  potential  risks  and  complications  associated with  the  project? Do  you foresee difficulties in transitioning this project into the development and implementation phase?  Ranking : (1‐5)     Comment:   6. Team Communication: How effective was the team  in communicating with you? Do you feel you had enough meetings with  them? Did  the  team make effective use of your  time and expertise? What means did you use  to communicate? 

Page 43: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

39  

 Ranking : (1‐5)  Comment:  7. Tools: Regarding software tools students used in the class  7a. Did the team share WinWin negotiation results with you? If so, how?  Comment  7b. Did the team mention or describe any other software engineering tools? Comment:    8. Your  Learning: Did  you  gain  a better understanding of  software  engineering  and  information  technology by participating  in  this  project?  Please  provide  specifics  where  possible.  Ranking : (1‐5)  Comment:     9. Suggestions about the course processes from your (a client's) perspective.  Comment:    10. Overall Value: Did  you  feel  your participation was worthwhile? Would  you participate  again? Did  you  find participation  valuable  as  either  a  teaching  or  research  activity?  Ranking : (1‐5)  Comment:     If you have any other comments that you would like to offer, please feel free.  We may get back to you in the future on these for clarification.      

Page 44: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

40  

Appendix F1‐Client Feedback Form – CSCI577b  577B Client Evaluation Team # _______________________ Project ______________________  The items listed below will ask for either a ranking or a yes/no response. For rankings, use a 1‐5 scale where 1 is low and 5  is high. For yes/no  items, p[lease  indicate your  choice. Additional  comments will be very helpful  for evaluation and planning purposes. Please use the questions in parenthesis as starting points for your comments.  Documentation  1. User Manual: Rank your level of satisfaction with the User Manual. (Is it well written? Will it reasonably answer both user and administrator questions? Did your team ask you to evaluate the User Manual? Did they incorporate your comments?)  Ranking: (1 to 5) Comments:   2. System Documents: Rank your level of satisfaction with the As Built system documents.  Ranking: (1 to 5) Comments:    Team Interaction  3. Team Responsiveness: How responsive was the team to your needs as a client? Did they address your project objectives and concerns? Ranking:  (1 to 5)  Comments:   4. Team Communication: How satisfied were you with the team’s communication with you? (Did they tell you what you needed  to  know when  you needed  to  know  it? Did  they explain  their work/the  issues  in  terms  you  could understand?) Ranking: (1 to 5)  Comments:  System Preparation and Testing  5. How effective were the students at installing the software and providing any necessary set‐up and configuration support  to enable  you  to get  started?  (Had  they anticipated and prepared  for any  set‐up  issues or problems?) Were  the  students  responsive  and  effective  in  handling  any  configuration  adjustments  that might  have  been needed once you began using the system?  Ranking: (1 to 5) Comments:   6. Did the students help to adequately prepare you to handle ongoing support and maintenance of the system? Yes/No:  Comments:  7. Training: Did the team provide appropriate training on how to use the system? (How was this done?) Yes/No:  Comments:    

Page 45: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

41  

8.  Training  Quality:  (Answer  only  if  you  received  training  for  the  system)  –  How  adequate  was  your  system training? Ranking: (1 to 5) Comments:  9A. Software Testing: Did the team ask you to test the final product? Yes/No:   9B. Software Testing: If yes, did you test all of the system’s features? Yes/No:    9C. Software Testing: How much time did you spend doing system testing?    10.  Software  Test  Results:  (Answer  only  if  you  participated  in  software  testing)  –  Please  rate  how  close  the functions you used came to meeting your expectations. Did they work as you expected? Ranking: (1 to 5)  Comments:  Implementation  11.  Is the system up and running  in full release? or  in a beta release?  Is any additional programming required to achieve sufficient basic functionality for public release? Yes/No:  Comments:   12. Hardware & Software: Do you need additional hardware and/or software to implement the system? Yes/No:  Comments:  13. Other  implementation  issues: Are  there  any  other  issues which  impact whether or  not  the  system  can  be implemented? Yes/No:   Comments:   Overall Value  14. Rate how successful the product is, as delivered, at achieving your objectives and desired functionality. Has the team made the right choices and trade‐offs? Ranking: (1 to 5)  Comments:    15.  Rate  the  value  /  anticipated  benefits  of  the  product  you’ve  received.  Is  it  a worth  the  time  you’ve  spent working with  the  team over  the past 2 semesters? Will  the product provide sufficient utility? Does  it have  long term potential or applicability beyond the need outlined in your original proposal? Ranking:  (1 to 5)  Comments:  Summary  16. Your Learning: Did you learn anything new this semester? Yes/No:   Comments:  

Page 46: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

42  

 17. Teaching: Did you feel you made a contribution to the education of graduate CSCI students at USC? Yes/No:   Comments:   18. Research: Did you feel you made a research contribution by participating in this project? Yes/No:   Comments:  19. Recommendation for Others: Would you recommend participation in future projects to your colleagues? (Are there specific projects, either your own or projects of your colleagues, which you would  recommend  for  future courses?) Comments:    20. Feel free to provide any other comments or suggestions for future course improvement.       

Page 47: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

43  

Appendix G – Qualitative Interview Form 

Part 1: Information about COTS/ Services in your project Section 1: General info about your project 1. Name, team: 2. What is your client’s computer technology level 

[  ] Low    [  ] Medium      [  ] High   3. What is your client’s role in this project (check all that apply) 

[  ] End user  [  ] Maintainer/ Administrator    [ ] Policy Planner   [  ] Acquirer [  ] Other,  4. What are the COTS/ Services you finally selected?  5. What are the functionalities of your selected COTS/Service? 6. What were on your choices? 7. What are the cost(s) of the selected C/S? 8. Does your selected C/S satisfy all the project goals? 9. If not, what are the part(s) that is left to develop? 10. Who introduced these C/Ss? 

[  ] Client               [  ] Development Team        [  ] Other, ___________________________ 11. If client was not the one who introduced the C/S, what was his/her first reaction?  

[  ] Oppose   [  ] Hesitate  [  ] Support  [ ] Other, ___________________________________ 12. When did you introduce your C/S? 

[  ] Exploration Phase           [  ] Valuation Phase      [  ] Foundations Phase 13. When did you finalize your C/S? 

[  ] Exploration Phase           [  ] Valuation Phase      [  ] Foundations Phase 14. What were the process / steps in finalizing the C/S selection?  Section 2: Criteria in selecting COTS/ Services 1. What kind of information you used to select the COTS/ Services?  [  ] Core capabilities in OCD     [ ] Business workflow in OCD     [ ] Requirements in SSRD          [  ] Use case in SSAD [  ] Current system infrastructure    [  ] Proposed system infrastructure      [  ] Prototype  [  ] Business Case Analysis  Anything else? 3. Where did you get information about these COTS/ Services?  Section 3: Activities in each phase  Section 3.1 Exploration Phase 1. Was C/S part of the project proposal? a. If yes, what did your client have any specific C/S in mind at the beginning?  b. If no, did you plan to develop everything from scratch at the beginning, why?  2. When you read the project proposal, did you know that there is/ are possible C/Ss available for this project?  3. Any problem regarding C/S in this phase?  Section 3.2 Valuation Phase 1. In this phase, did you switch to C/S team or still follow the traditional development guidelines?  2. Did you prioritize or reprioritize your criteria? 3. Did you build any prototype?  4. If your C/S is selected, did you tailor the C/S? 5. If your C/S is selected, did you write any glue code for the C/S?  Section 3.3 Foundations Phase 1. In this phase, did you switch to C/S team or still follow the traditional development guidelines?  

Page 48: The Incremental Commitment Model process patterns for rapid‐fielding projectscsse.usc.edu/TECHRPTS/2009/usc-csse-2009-526/usc-… ·  · 2010-08-13The Incremental Commitment Model

44  

2. Did you reprioritize your criteria? 3. Did you drop any criteria? 4. Did you build any prototype?  5. If your C/S is selected, did you tailor the C/S? 6. If your C/S is selected, did you write any glue code for the C/S?  Section 4: Hypothetical Situations    Part 2: EPG for COTS/Services 1. Are there any activities/tasks that you perform but they are not listed/ explained in CBA Guidelines? 2. Is there any role(s) that should be added? 3. Is there any work product(s) that should be added? 4. Is there any guideline(s) that should be added?