Upload
rosemary-beasley
View
215
Download
1
Embed Size (px)
Citation preview
The Future of Infrastructure Investments
Carter H. Strickland, Jr.
Commissioner, New York City Department of Environmental Protection
March 7, 2013
2
Hurricane Sandy
3
Hurricane Sandy Flooding Area
4
Monthly Maximum Water Levels at the Battery
Courtesy AECOM
Nor
th A
mer
ican
Ver
tical
Dat
um 1
988
(fee
t)15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
-1
1920 1930 1940 1950 1960 1970 1980 1990 2000 2010 2020
Years
Monthly High Water
Previous Record
March 1962December
1992Hurricane
Irene
Sandy
-2
9:24 PM – Manhattan Battery
• 13.88 feetMean Lower Low Water
• 11.10 feet North American Vertical Datum 1988
5
Sandy Impacts on Pumping Stations
6
Manhattan Pump Station
Con Edison Substation
Manhattan Pump Station
7
Sandy Impacts on Wastewater Treatment Plants
8
Oakwood Beach Wastewater Treatment Plant
9
Wastewater Response
26th Ward WWTP
Coney Island WWTP
49th Street Pumping Station
10
Climate Change Planning at DEP
11
10-Year Capital Plan
• $14.4 billion 10 Year Capital Budget
o $3.3 billion for Wastewater Treatment Plant Upgrades
o $2.4 billion for Sewer Construction
o $1.8 billion for State of Good Repair Programs
o $730 million for Green Infrastructure
12
• Initiate Staten Island Siphon construction ($250M)
• Complete sewer connections in Queens ($396M) and Staten Island ($380M)
• Bring Bluebelts to southeast Queens to naturally control stormwater ($29M)
• Complete connections to City Water Tunnel No. 3 ($898M)
• Initiate Green Infrastructure related projects ($187M)
• Complete repairs to the Manhattan Pump Station ($227M)
• Continue planning for Delaware Aqueduct repair – Water for the Future ($1.7B*)
DEP’s Capital Priorities 2012-2016
Shaft Connections for Delaware Tunnel Repair – Water for the Future
Staten Island Bluebelt Connections to Water Tunnel No. 3
* $1.7 B is the total projected cost for Water for the Future, including design and construction, as well as alternative sources and conservation measures
13
Grey Infrastructure Investments
Newtown Creek WWTP Paerdegat Basin CSO Facility
More than $10 billion in wastewater investments since 2002
• $5 billion – Newtown Creek Wastewater Treatment Plant upgrade
• $437 million – Paerdegat Basin CSO Facility
• $500 million – Hunts Point Wastewater Treatment Plant upgrade and nutrient removal
• $100 million – Nitrogen control upgrades at 26th Ward, Coney Island, and Rockaway wastewater treatment plants
14
Climate Change Impacts on NYC
Source: New York City Panel on Climate Change
Baseline1971–2000 2020s 2050s 2080s
Air Temperature 55°F + 1.5 to 3°F + 3 to 5°F + 4 to 7.5°F
Precipitation 46.5 in + 0 to 5% + 0 to 10% + 5 to 10%
Sea Level Rise NA + 2 to 5 in + 7 to 12 in + 12 to 23 in
Rapid Ice-Melt Sea
Level RiseNA + 5 to 10 in + 19 to 29 in + 41 to 55 in
15
Green Infrastructure
15
Blue RoofGreen Roof
Bioswale Porous Pavement
16
$2.9 $2.9
$1.5
$0.9
$0.03
$3.9
$-
$1.0
$2.0
$3.0
$4.0
$5.0
$6.0
$7.0
$8.0
Green Strategy Grey Strategy
Potential Tanks, Tunnels, & Expansions Optimize Existing System
Green Infrastructure - Private Investment Green Infrastructure - Public Investment
Reduced Flow Cost-Effective Grey Investments
$6.8
$5.3
$2.4
The Green Strategy Costs Less
17
Right of Way Bioswale
18
Area-Wide Approach
19
For more information visit www.nyc.gov/dep
Follow us on facebook at www.facebook.com/nycwater