Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 0
The Facts in the Recovery Process of
Fukushima Nuclear Accident
March 21, 2012
@IAEA IEM, Vienna
Akira Kawano
Tokyo Electric Power Company
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 1
What I will present
1.How the Earthquake and the Tsunami affected
the Power Supply at 1F and 2F sites ?
2.How the Accident Developed and was Stabilized
at 1F and 2F Sites ?
3.How We Responded to the Accident at 1F and
2F Sites ?
4.Summary
5.Reference
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 2
1.How the Earthquake and the Tsunami Affected
the Power Supply at 1F and 2F Sites ?
Unit 6 Unit 5 Unit 1
Unit 2 Unit 3
Unit 4 Unit 1
Unit 2 Unit 3
Unit 4
Fukushma Daiichi(1F) Fukushma Daini(2F)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 3
Overview of Fukushima Daiichi NPS (1F)
and Fukushima Daini NPS (2F)
Plant Unit
In
Operation
Since
Plant
Type
Power
Output
(MWe)
Main
Contractor Pre-earthquake Status
1F
1 1971.3 BWR-3 460 GE Operating
2 1974.7 BWR-4 784 GE/Toshiba Operating
3 1976.3 BWR-4 784 Toshiba Operating
4 1978.10 BWR-4 784 Hitachi
Shutdown for maintenance
Full core offloaded to spent fuel pool
5 1978.4 BWR-4 784 Toshiba Shutdown for maintenance
6 1979.10 BWR-5 1100 GE/Toshiba Shutdown for maintenance
2F
1 1982.4 BWR-5 1100 Toshiba Operating
2 1984.2 BWR-5 1100 Hitachi Operating
3 1985.6 BWR-5 1100 Toshiba Operating
4 1987.8 BWR-5 1100 Toshiba Operating
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 4
4A 4B
4D 4C
4E
D/G
4B
D/G
4A
D/G
3B
D/G
3A D/G
2B
D/G
2A
D/G
1B
D/G
1A
3A 3B
3C 3D
3SA 3SB
2A 2B
2C 2D
2E
2SA 2SB
1A 1B
1C 1D
1S
Shutdown by earthquake
Shutdown by Tsunami
Power supply of Unit 1-4 @ 1F after Tsunami
The DG lost the function due to either “M/C failure,” “loss of
sea water system,” or “DG main unit failure.”
Okuma Line 1L, 2L: Receiving circuit breaker damaged in earthquake
Okuma Line 3L: Renovation work in progress
Okuma Line 4L: Circuit breaker shutdown by protection relay activation
Ohkuma
4L
Ohkuma
3L
Ohkuma
2L
Ohkuma
1L
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 5
双葉線1L
双葉線2L
5A
5C
5B
5D
D/G
5A
D/G
5B
D/G
HPCS
D/G
6A
D/G
6B
5SA-1 5SA-2 5SB-2 5SB-1 6A-1 6A-2
HPCS 6C
6B-1 6B-2
6D
Shutdown by earthquake
Shutdown by Tsunami
Survived after tsunami
Power supply of Unit 5/6 @ 1F after Tsunami
Futaba
1L
Futaba
2L
Yonomori 2L Yonomori 1L
For transmitting
power
For transmitting
power
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 6
Damages of transmission line
& Shinfukushima substation by earthquake
500kV Disconnector 275kV Circuit Breaker
- About 10 km away from both 1F and 2F site
- Important switchgear station from which electricity of 1F & 2F is transmitted to Tokyo area
Transmission tower collapse
Collapse (C)GeoEye
Collapse of filled soil & sand
Tower collapse
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 7
6.9kV 6.9kV
2F Offsite Power was secured after the Tsunami Offsite Power
500kV 66kV
H STr
Unit #1, 2 STr Unit #3, 4 STr
D/G
Emergency
Power for Unit #1
D/G
1H 1A 1B
6.9kV
D/G D/G
2H 2A 2B
D/G
3H 3A 3B
6.9kV
D/G D/G
4H 4A 4B
One 500 kV line was available.
66 kV lines were outage because of scheduled
maintenance and substation trouble but recovered.
Many power centers and motors were damaged
because of the flooding.
P P P P
Emergency
Power for Unit #2 Emergency
Power for Unit #3 Emergency
Power for Unit #4
D/G
P : Cooling Pumps
D/G : Diesel Generator
D/G
P D/G
P D/G
P D/G
P
Tomioka Line Iwaido Line
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 8
Integrity of Power Supply System After the Tsunami at 1F and 2F
*1 functionality lost due to inundation of power panels *2 functionality lost due to the damage of sea water system
Power panelCan/cannot beused
Power panelCan/cannot beused
Power panelCan/cannot beused
Power panelCan/cannot beused
Power panelCan/cannot beused
Power panelCan/cannot beused
Power panelCan/cannot beused
Power panelCan/cannot beused
Power panelCan/cannot beused
Power panelCan/cannot beused
DG 1A × DG 2A × DG 3A × DG 4A × DG 5A(*2) × DG 6A ×(*2) DG 1A × DG 2A ×(*2) DG 3A ×(*2) DG 4A ×(*2)
DG 1B ×DG 2B
(air-cooled)×(*1) DG 3B ×
DG 4B(air-cooled)
×(*1) DG 5B(*2) ×DG 6B
(air-cooled)○ DG 1B × DG 2B ×(*2) DG 3B ○ DG 4B ×(*2)
- - - - - - - - - - HPCS DG ×(*2) DG 1H × DG 2H ×(*2) DG 3H ○ DG 4H ○
M/C 1C × M/C 2C × M/C 3C × M/C 4C × M/C 5C × M/C 6C ○ M/C 1C × M/C 2C ○ M/C 3C ○ M/C 4C ○
M/C 1D × M/C 2D × M/C 3D × M/C 4D × M/C 5D × M/C 6D ○ M/C 1D ○ M/C 2D ○ M/C 3D ○ M/C 4D ○
- - M/C 2E × - - M/C 4E × - -HPCS DG
M/C○ M/C 1H × M/C 2H ○ M/C 3H ○ M/C 4H ○
M/C 6A-1 × M/C 1A-1 ○ M/C 2A-1 ○ M/C 3A-1 ○ M/C 4A-1 ○
M/C 6A-2 × M/C 1A-2 ○ M/C 2A-2 ○ M/C 3A-2 ○ M/C 4A-2 ○
M/C 6B-1 × M/C 1B-1 ○ M/C 2B-1 ○ M/C 3B-1 ○ M/C 4B-1 ○
M/C 6B-2 × M/C 1B-2 ○ M/C 2B-2 ○ M/C 3B-2 ○ M/C 4B-2 ○
M/C 5SA-1 × M/C 1SA-1 ○ M/C 3SA-1 ○
M/C 5SA-2 × M/C 1SA-2 ○ M/C 3SA-2 ○
M/C 5SB-1 × M/C 1SB-1 ○ M/C 3SB-1 ○
M/C 5SB-2 × M/C 1SB-2 ○ M/C 3SB-2 ○
P/C 1C × P/C 2C ○ P/C 3C × P/C 4C ○ P/C 5C × P/C 6C ○ P/C 1C-1 × P/C 2C-1 ○ P/C 3C-1 ○ P/C 4C-1 ○
P/C 1D × P/C 2D ○ P/C 3D × P/C 4D ○ P/C 5D × P/C 6D ○ P/C 1C-2 × P/C 2C-2 × P/C 3C-2 × P/C 4C-2 ×
- - P/C 2E × - - P/C 4E × - - P/C 6E ○ P/C 1D-1 ○ P/C 2D-1 ○ P/C 3D-1 ○ P/C 4D-1 ○
P/C 2A ○ P/C 3A × P/C 4A ○ P/C 5A × P/C 6A-1 × P/C 1D-2 × P/C 2D-2 × P/C 3D-2 ○ P/C 4D-2 ×
P/C 2A-1 × - - - - P/C 5A-1 ○ P/C 6A-2 × P/C 1A-1 ○ P/C 2A-1 ○ P/C 3A-1 ○ P/C 4A-1 ○
P/C 1B × P/C 2B ○ P/C 3B × P/C 4B ○ P/C 5B × P/C 6B-1 × P/C 1A-2 ○ P/C 2A-2 ○ P/C 3A-2 ○ P/C 4A-2 ○
- - - - - - - - P/C 5B-1 ○ P/C 6B-2 × P/C 1B-1 ○ P/C 2B-1 ○ P/C 3B-1 ○ P/C 4B-1 ○
P/C 1S × - - P/C 3SA × - - P/C 5SA × - - P/C 1B-2 ○ P/C 2B-2 ○ P/C 3B-2 ○ P/C 4B-2 ○
- - - - - - - - P/C 5SA-1 × - - P/C 1SA ○ P/C 3SA ○
- - P/C 2SB × P/C 3SB × - - P/C 5SB × - - P/C 1SB ○ P/C 3SB ○
DC125V mainbus panel A
×DC125V P/C
2A×
DC125V mainbus panel 3A
○DC125V mainbus panel 4A
×DC125V P/C
5A○
DC125V DISTCENTER 6A
○DC125V mainbus panel A
○DC125V mainbus panel A
○DC125V mainbus panel A
○DC125V mainbus panel A
○
DC125V mainbus panel B
×DC125V P/C
2B×
DC125V mainbus panel 3B
○DC125V mainbus panel 4B
×DC125V P/C
5B○
DC125V DISTCENTER 6B
○DC125V mainbus panel B
○DC125V mainbus panel B
○DC125V mainbus panel B
○DC125V mainbus panel B
○
A RHRS A × RHRS A × RHRS A × RHRS A × RHRS A × RHRS A × RHRS A × RHRS A × RHRS A ×
B RHRS B × RHRS B × RHRS B × RHRS B × RHRS B × RHRS B × RHRS B × RHRS B ○ RHRS B ×
SW ×
- -
Regu
lar use
P/C
P/C 1A ×
-
Sea w
ater
system
DC
pow
er
supply
125V
DC
Em
erge
ncy D
GM
/C
-
Regu
lar use
Em
erge
ncy
use
M/C 2SB
M/C 2SA
×
×
×
× M/C 3SA
M/C 3SB
M/C 2B
M/C 3A
×M/C 5BM/C 4B
M/C 5AM/C 4A ×××
××× M/C 3B
M/C 1S ×
M/C 1B ×
×M/C 2A
Em
erge
ncy u
se
M/C 1A ×
Unit 3 Unit 5Unit 4 Unit 6
- -
Fukushima DaiichiUnit 1 Unit 2
Fukushima DainiUnit 1 Unit 2 Unit 3 Unit 4
1F:No off-site power available 2F:Off-site power survived
DG
6
.9K
V M
/C
480V
PC
D
C
O: operable X: damaged Sea Water System
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 9
2. How the accident developed
and was stabilized at 1F & 2F
Sites?
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 10
Fukushima Daiichi Units 1 - 4 Fukushima Daiichi Units 5 & 6 Fukushima Daini Units 1 - 4
Progress made by each plant towards cold shutdown (outline)
Units 1-3 in operation
Unit 4: outage in progress
[Power supply] Total loss of off-site
power supply and DG
[Sea water system] Total loss
Water injection using IC, RCIC,
HPCI
PCV Venting, SRV operation
& Sea water injection
Switch to freshwater
・Heat removal route has been
continuously improved
・Currently the closed cycle
cooling is in function
Sea water was initially injected into
the spent fuel pool; currently
injecting freshwater
Outage in progress
[Power supply] Emergency DG 6B
start up
[Sea water system] Total loss
3/19
Alternative RHRS was
started and the spent fuel
pool and reactor were cooled
Increase in spent fuel pool
temperature to near 70°C
3/20
Units 5, 6 cold shutdown
Installation of temporary RHRS
Installation of temporary power
supply
In operation
[Power supply] One off-site power
supply system secured
[Sea water system] Total loss apart
from Unit 3
3/12
Unit 3 cold
shutdown
Units 1, 2, 4
Water injection using MUWC
3/14
RHR startup
Water injection using RCIC
3/14 Units 1, 2 cold shutdown
3/15 Unit 4 cold shutdown
RHRC motor was replaced
Installation of temporary power
supply
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 11
-1000
1000
3000
5000
7000
3/1112:00
3/1118:00
3/120:00
3/126:00
3/1212:00
3/1218:00
3/130:00
3/136:00
3/1312:00
3/1318:00
3/140:00
3/146:00
3/1412:00
3/1418:00
3/150:00
3/156:00
3/1512:00
3/1518:00
3/160:00
0.00
2.00
4.006.00
8.00
10.00
3/1112:00
3/1118:00
3/120:00
3/126:00
3/1212:00
3/1218:00
3/130:00
3/136:00
3/1312:00
3/1318:00
3/140:00
3/146:00
3/1412:00
3/1418:00
3/150:00
3/156:00
3/1512:00
3/1518:00
3/160:00
逃がし弁機能(7.47,7.54,7.61MPa abs)
設計圧力(8.7MPa abs)
運転圧力(7.0MPa abs)
0.000
0.200
0.400
0.600
0.800
1.000
3/1112:00
3/1118:00
3/120:00
3/126:00
3/1212:00
3/1218:00
3/130:00
3/136:00
3/1312:00
3/1318:00
3/140:00
3/146:00
3/1412:00
3/1418:00
3/150:00
3/156:00
3/1512:00
3/1518:00
3/160:00
設計圧力(0.38MPa abs)
ベント実施圧力(0.723MPa abs)
R
x W
ate
r
Level [m
m]
RCIC
HPCS No Operation( Inoperative due to submersion of power source and inoperative auxiliary cooling system)
SRV
MUWC
RHR
PCV Vent
● S/C Pressure (MPa)
● D/W Pressure (MPa)
Earthquake (14:46)
Tunami (15:23)
Rx P
ressu
re
[MP
a]
D/W
&
S/C
Pre
ssu
re [M
Pa
]
0(TAF)
(3:50 ~ )Depressurization Pressure Control
(0:00 ~ )
(3:45 ~ )
▼(18:30) Vent Line Configuration Completed
Cold Shut Down(14:46)
Overscale
Restoration of RHR system
2F Unit 1 Plant Parameter and Operation
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 12
• Operator’s initial response
– MSIVs closed manually, and reactor
pressure controlled by SRVs.
– RCIC actuated manually to maintain
reactor water level. RCIC repeated
automatic trip due to high water level
signal and manual restart.
– MUWC actuated for alternative
water injection measure introduced
for Accident Management, as stated
in EOP manual for seamless water
injection.
– Reactor depressurized and RCIC
stopped due to steam pressure
decrease.
– Water level maintained by MUWC.
Sea
Steam
Water
Condensat
e Storage
Tank
RPV
Reactor Building
Heat Exchanger Building
Heat rejection by
opening SRVs
Temperature
increase
Tsunami flooding Inoperable by
flooding
Equipment cooling system was not
available.
RHRC Pump
RHRS Pump
RHR Pump
RCIC MUWC
MSIV
Suppression
Chamber
(S/C)
Response at Main Control Room and TSC
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 13
0
1
2
3
4
5
6
7
8
3/11 3/12 3/13 3/14 3/15
(MPa [gage])
3/11 16:15 Reactor depressurization
started (SRV automatically opened)
3/14 10:05~
LPCI and S/C
cooling and spray
by RHR(B)
3/14 13:40
Cold shutdown3/12 0:00
MUWC started
3/11 15:36 - 3/12 4:58
RCIC Operation
(intermittent)
-1000
-500
0
500
1000
1500
3/11 3/12 3/13 3/14 3/15
(mm)
Out of measurement range
3/11 16:15
Reactor depressurization started
(SRV automatically opened)
Successful Reactor Cooling during Transient
Reactor Pressure (Unit 1) Reactor Water Level (Unit
1)
Securing uninterrupted water injection throughout the
depressurization process with RCIC at high pressure condition and
MUWC at low pressure condition was a critical factor for successful
reactor cooling.
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 14
0
20
40
60
80
100
120
140
3/11 3/13 3/15 3/17 3/19
(℃)
3/12 06:20~07:47S/C injection by FCS(A)3/12 07:10 D/W spray3/12 07:37 S/C spray
3/1311:32~13:26 14:29~14:37D/W spray
0
50
100
150
200
250
300
3/11 3/13 3/15 3/17 3/19
(kPa[gage])
0
20
40
60
80
100
120
140
3/11 3/13 3/15 3/17 3/19
3/14 01:24RHR(B) started withS/C cooling mode
3/17 20:03~20:20Water transfer fromCondenser to S/C viaCST to monitorCondenser water level
3/1311:32~13:2614:29~14:37D/W spray
3/12 06:20~07:45S/C injection by FCS(A)3/12 07:10 D/W spray3/12 07:37 S/C spray
Variation of major parameters【2F-1】(from March 11 to 19)
S/C Temperature (Unit 1) S/C Pressure (Unit 1)
S/C water temperature reached 100ºC (212F).
It eventually increased up to about 130ºC (266F).
Water injected to S/C through Hydrogen Recombiner cooler discharge line in order
to mitigate temperature and pressure increases.
Alternative injection to reactor using MUWC switched to D/W spray, then S/C spray.
S/C temperature decreased after restoration of RHR.
EOP includes an alternative water injection measures employing MUWC .
Flexible approach to cool S/C using Hydrogen Recombiner worked well.
Efforts to Control Temperature and Pressure in PCV
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 15
Preparation for Venting
PCIS and SGTS actuated to secure isolation of the PCV and
maintained negative pressure of the reactor building.
Judging from the increasing PCV pressure trend and projected
restoration time, as a back-up plan, TSC decided to make PCV vent
line up ready.
PCV pressure went up to about 280 kPa [gage] before restoration of
RHR, but did not reach its design maximum pressure 310 kPa [gage].
PCV vent line up was made ready as a back-up plan.
This would enable feed and breed cooling to avoid potential
core damage.
(As restoration of cooling capability was successful and cold
shutdown was achieved, venting was not conducted actually.)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 16
0.000
0.200
0.400
0.600
0.800
1.000
3/11 12:00
3/11 18:00
3/12 0:00
3/12 6:00
3/12 12:00
3/12 18:00
3/13 0:00
設計圧力
(0.53MPa abs)
ベント実施圧力
(0.954MPa abs)
0.00
2.00
4.006.00
8.00
10.00
3/11 12:00
3/11 18:00
3/12 0:00
3/12 6:00
3/12 12:00
3/12 18:00
3/13 0:00
逃がし弁機能(7.28,7.35,7.41MPa abs)
設計圧力(8.7MPa abs)
運転圧力(7.0MPa abs)
-3000
-1000
1000
3000
5000
3/11 12:00
3/11 18:00
3/12 0:00
3/12 6:00
3/12 12:00
3/12 18:00
3/13 0:00
原子炉水位(燃料域)(A)(mm)
原子炉水位(燃料域)(B)(mm)
In Operation(Over Scale)
Rx W
ate
r
Le
ve
l [m
m]
IC
HPCI No Operation
SRV No Operation
FP/Fire Engine
PCV Vent
● Fuel Range (A) (mm)
● Fuel Range (B) (mm)
● Rx Pressure (A) (MPa)
● Rx Pressure (B) (MPa)
● S/C Pressure (A) (MPa)
● D/W Pressure (B) (MPa)
(19:04)Sea Water
Order for Vent Preparation (0:06) ▼
(4:00) Fresh Water [80t] (14:53)
(18:18 - 25) (21:30)
(14:52)
Earthquake (14:46)
Tunami (15:27)
Operation Unclear
Order for Vent ▼ (8:03) (14:30) D/W Pr decrease confirmed
Unit 1 R/B Explosion (15:36)
Core Damage Started due to MAAP Analysis
Rx P
ressu
re
[MP
a]
D/W
&
S/C
Pre
ssu
re [M
Pa
]
1F Unit 1 Plant Parameter and Operation
0(TAF)
Rx water level data revealed incorrect afterward
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 17
-4000
-2000
0
2000
4000
6000
3/1112:00
3/1118:00
3/120:00
3/126:00
3/1212:00
3/1218:00
3/130:00
3/136:00
3/1312:00
3/1318:00
3/140:00
3/146:00
3/1412:00
3/1418:00
3/150:00
3/156:00
3/1512:00
3/1518:00
3/160:00
0
2
4
6
8
10
In Operation (Over Scale)
0.00
2.00
4.006.00
8.00
10.00
3/1112:00
3/1118:00
3/120:00
3/126:00
3/1212:00
3/1218:00
3/130:00
3/136:00
3/1312:00
3/1318:00
3/140:00
3/146:00
3/1412:00
3/1418:00
3/150:00
3/156:00
3/1512:00
3/1518:00
3/160:00
逃がし弁機能(7.44,7.51,7.58MPa abs)設計圧力(8.7MPa abs)
運転圧力(7.0MPa abs)
0.000
0.200
0.400
0.600
0.800
1.000
3/1112:00
3/1118:00
3/120:00
3/126:00
3/1212:00
3/1218:00
3/130:00
3/136:00
3/1312:00
3/1318:00
3/140:00
3/146:00
3/1412:00
3/1418:00
3/150:00
3/156:00
3/1512:00
3/1518:00
3/160:00
設計圧力(0.53MPa abs)
ベント実施圧力(0.954MPa abs)
Rx W
ate
r
Le
ve
l [m
m]
RCIC
HPCI No Operation
SRV
FP/Fire Engine
PCV Vent
● Fuel Range (A) (mm)
● Fuel Range (B) (mm)
○ CAMS D/W(A)(Sv/h) ○ CAMS S/C(A)(Sv/h)
● Rx Pressure (A) (MPa)
● Rx Pressure (B) (MPa)
● S/C Pressure (MPa)
● D/W Pressure (MPa)
(19:54)Sea Water
Order for Vent Preparation ▼ (17:30)
Depressurization (~18:00)
Earthquake (14:46) Tunami
(15:27)
▼(2:55) Operation confirmed
▼(11:00) Vent Line Configuration Completed
Unit1 R/B Explosion (15:36)
Core Damage Started due to MAAP Analysis
Rx P
ressu
re
[MP
a]
D/W
&
S/C
Pre
ssu
re [M
Pa
]
1F Unit 2 Plant Parameter and Operation Unit3 R/B Explosion (11:01)
Impact sound (6:00-6:10)
Valve Condition Unclear
Order for Sea Water Injection Preparation (12:05)▼
2Valves Open
Small Vent Valves Opened
(13:25)Out of Service Judged
0(TAF)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 18
0.000
0.200
0.400
0.600
0.800
1.000
3/1112:00
3/1118:00
3/120:00
3/126:00
3/1212:00
3/1218:00
3/130:00
3/136:00
3/1312:00
3/1318:00
3/140:00
3/146:00
3/1412:00
3/1418:00
3/150:00
3/156:00
3/1512:00
3/1518:00
3/160:00
設計圧力(0.53MPa
abs)
ベント実施圧力(0.954MPa
0.00
2.00
4.006.00
8.00
10.00
3/1112:00
3/1118:00
3/120:00
3/126:00
3/1212:00
3/1218:00
3/130:00
3/136:00
3/1312:00
3/1318:00
3/140:00
3/146:00
3/1412:00
3/1418:00
3/150:00
3/156:00
3/1512:00
3/1518:00
3/160:00
逃がし弁機能(7.44MPa,7.51MPa,7.58MPa)設計圧力(8.7MPa)
運転圧力(7.0MPa)
-4000
-2000
0
2000
4000
6000
3/1112:00
3/1118:00
3/120:00
3/126:00
3/1212:00
3/1218:00
3/130:00
3/136:00
3/1312:00
3/1318:00
3/140:00
3/146:00
3/1412:00
3/1418:00
3/150:00
3/156:00
3/1512:00
3/1518:00
3/160:00
I n Ope ratio n (Ove r Sc ale )
R
x W
ate
r
Le
ve
l [m
m]
RCIC
HPCI
SRV
D/D-FP
FP/Fire Engine
PCV Vent
● Fuel Range (A) (mm)
● Fuel Range (B) (mm)
● Fuel Range (mm)
○ Wide Range (mm)
● Rx Pressure (A) (MPa)
● Rx Pressure (B) (MPa)
● S/C Pressure (MPa)
● D/W Pressure (MPa)
(16:30)Sea Water
Order for Vent Preparation ▼ (17:30)
Earthquake (14:46) Tunami
(15:27)
Unit1 R/B Explosion (15:36)
Core Damage Started due to MAAP Analysis
Rx P
ressu
re
[MP
a]
D/W
&
S/C
Pre
ssu
re [M
Pa
]
1F Unit 3 Plant Parameter and Operation Unit3 R/B Explosion (11:01)
Order for Preparation ▼(17:12)
0(TAF)
(11:36) Trip
Automatic Start (12:35)
(16:03)
(2:42) Stop
(13:12)Sea Water Fresh Water (9:25)
▼(8:41) Vent Line Configuration Completed
(~9:08)Depressurization
(22:15) Stop due to running out of fuel
After HPCI shut down, water injection
using D/D FP was implemented, however
not possible due to high reactor pressure
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 19
3. How We Responded to the
Accident at 1F & 2F Sites?
- What difficulties existed
- What were effectively utilized
- How the difficulties were overcome
- Testimonies
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 20
Establishing an alternative method to inject water into the
reactor pressure vessel (RPV)
Venting of the primary containment vessel (PCV)
Recovery of the most important instrumentations:
reactor water level
reactor pressure
drywell pressure
wet-well (suppression chamber: S/C) pressure
Recovery of the lights in the control rooms and other power
supply sources
What 1F site focused on during March 11-15
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 21
Activities were done in complete darkness due to lack of power sources.
Work in complete darkness
In the service building. Many
scattered objects were also
on the floor.
Temporary power supply
Connect temporary
batteries to recover
instrumentations.
Major Activities at Fukushima Daiichi Unit 1
~Factors disturbing the recovery work (inside the building) ~
Scram
response
Preparations
for water
injection
Preparations
for venting
Water
injection
started
Venting
Deteriorating
operability
due to the
tsunami
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 22
Image of a power supply cart
Used batteries taken from cars for recovery of important
instrumentations.
Put Engine-Generators to provide power for the control room
lightings and PCV vent valve actuation.
Tried to connect a mobile power supply vehicle to P/C 2C/4D
with temporary cable. The hydrogen explosion of Unit 1&3
caused damage of the temporary cable.
Scram
response
Preparations
for water
injection
Preparations
for venting
Water
injection
started
Venting
Deteriorated
operability
due to the
tsunami
Major Activities at 1F
~Factors disturbing initial recovery of instrumentations and power supply ~
Hurdles for the work:
Darkness and suspensions due
to aftershocks, tsunami alarms,
Puddles, openings of manholes,
debris and other obstacles
caused by the tsunami,
Influence of the hydrogen
explosions
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 23
Number of Aftershocks Greater than M 5.0
3/11 Dates (from March 11, 2011 to Dec. 5th, 2011)
12/5 4/1
Da
ily N
um
be
r of A
fters
ho
cks G
reate
r th
an
M 5
.0
Cum
ula
tive N
um
ber
of A
fters
hocks G
reate
r th
an M
5.0
On March 11th alone
155 times > M 5.0
37 times > M6.0
3 times > M7.0
Total during first week
358 times > M 5.0
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 24
Instruments were monitored wearing a full face mask with a flashlight in
complete darkness
Supervising (2)
Supervising at a deputy
supervisor’s desk wearing
a full face mask in
complete darkness
Supervising (1)
Check indicated values only
with a flashlight in complete
darkness
Major Activities at Fukushima Daiichi Unit 1
~Factors disturbing the recovery work (inside the buildings) ~
Scram
response
Deteriorating
operability
due to the
tsunami
Water
injection
started
Venting
Preparations
for water
injection
Preparations
for venting
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 25
• Many obstacles on access routes disturbed access to the field.
• Vehicles had to avoid passing over fire protection hoses laid in the field.
• Most of the prepared communication tools between the ERC and the
control room were unavailable.
Scram
response
Deteriorating
operability
due to the
tsunami
Water
injection
started
Venting
Preparations
for water
injection
Preparations
for venting
Major Activities at 1F Unit 1 <factors disturbing recovery work (outside the building) >
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 26
Scram
response
Deteriorating
operability
due to the
tsunami
Water
injection
started
Venting
Major Activities at Fukushima Daiichi Unit 1
~Containment Vessel Venting Operation (1) ~
Self-contained
breathing apparatus
Two valves, a PCV vent valve (MO valve) and a S/C vent valve (AO valve: small) were selected
as the target for manual PCV venting operation .
Manual valve operation were planned to be conducted by 3 teams with 2 shift workers per team
(one worker per team would be difficult due to the total darkness) and shift supervisors and vice-
supervisors were selected to the team members.
Equipment for the teams included fire-resistant clothing, self-contained breathing apparatus,
APD, survey meter and flash light.
At 9:03, it was confirmed that evacuation from the vicinity of south side of the NPS completed.
At 9:04, the team members headed to the site for the venting operation.
72
AO
ボンベ
210
MO ラプチャーディスク排気筒
1AO
ボンベ
閉
閉
83
AO閉
閉90
AO
0.549MPabsで破壊
RPV
D/W
RPVRPV
D/W
IA
IA
D/W最高使用圧力0.528MPabs
ベント実施圧力0.954MPabs
電磁弁
電磁弁
213
AO
Shift workers operation to
manually open
valve
MO
AO
AO
AO
AO
MO
Exhaust
stack
Closed
Closed
Closed
Closed
Solenoid
valve
Solenoid valve
Cylin
de
r
Cylin
de
r
D/W maximum
operating pressure:
0.528MPaabs
Ruptured
disc Broke at
0.549MPabs
Venting
pressure:
0.954MPaabs
Preparations
for water
injection
Preparations
for venting
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 27
Water
injection
started
Venting
Major Activities at Fukushima Daiichi Unit 1
~Containment Vessel Venting Operation (2) ~
72
AO
ボンベ
210
MO ラプチャーディスク排気筒
1AO
ボンベ
閉
閉
83
AO閉
閉90
AO
0.549MPabsで破壊
RPV
D/W
RPVRPV
D/W
IA
IA
D/W最高使用圧力0.528MPabs
ベント実施圧力0.954MPabs
電磁弁
電磁弁
213
AO
(25%開)
1st team proceeded to site to operate
PCV vent valve (MO valve) on the
2nd level of the R/B, and implemented
operation to open the valve manually.
R/B 2nd level R/B 1st level
South-side
double door
To 2nd level by
southeast stairs PCV vent valve
(MO valve)
North-side
double door
Operation to open PCV vent
valve (MO valve) successful
Access route to PCV vent valve (MO valve)
Manual
opening
operation
successful
MO
MO
AO
AO
AO
AO
Ruptured disc
Broke at 0.549MPabs
Air stack
Closed
Closed
Closed
Solenoid valve
Solenoid valve
Cylin
der
Cylin
der
D/W maximum operating pressure
Venting pressure
Closed
(25% open)
Operation to manually open
PCV vent valve (MO valve) Scram
response
Deteriorating
operability
due to the
tsunami
Preparations
for water
injection
Preparations
for venting
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 28
Water
injection
started
Venting
Major Activities at Fukushima Daiichi Unit 1
~Containment Vessel Venting Operation (3) ~
72
AO
ボンベ
210
MO ラプチャーディスク排気筒
1AO
ボンベ
閉
閉
83
AO閉
閉90
AO
0.549MPabsで破壊
RPV
D/W
RPVRPV
D/W
IA
IA
D/W最高使用圧力0.528MPabs
ベント実施圧力0.954MPabs
電磁弁
電磁弁
213
AO
(25%開)
2nd team entered the torus room (R/B B1F), but the valve was located at a direction of 180 degrees from where the team entered the torus room.
The survey meter rose up to the limit on the way, and the team members returned.
R/B 1st floor R/B B1F
S/C vent
valve
(AO valve)
Dose at the
north-side
double
door was
high, and
south-
bound
course was
selected
Manual operation was abandoned and another means were selected
Access route to S/C vent valve (AO valve)
Manual opening
operation
successful
AO
AO
Manual opening
operation abandoned
due to high dose
AO
AO MO
MO Ruptured disc
Broke at 0.549MPabs
Air stack
Closed
Closed
Closed
Solenoid valve
Solenoid valve
Cylin
der
Cylin
der
D/W maximum operating pressure
Venting
pressure
Closed
(25% open)
Operation to manually open S/C
vent valve (AO valve) valves
South-side
double door
North-side
double door
Deteriorating
operability
due to the
tsunami
Scram
response
Preparations
for water
injection
Preparations
for venting
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 29
What were available for the recovery work after the tsunami?
There were only the following limited number of
devices and tools available !
Fire Engines: only a few people knew how
to operate them.
Flashlights
Cable
Tools (screwdrivers, etc.)
Batteries taken from cars
Engine driven Generators*
Engine driven Air Compressors*
*They were in the warehouses
of the affiliated companies and
difficult to find.
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 30
System Status after the Tsunami at 2F
○ ; secure (power, pump and motor all working)
× ; loss of function (power, pump or motor inoperable)
△ ; malfunction (inoperable due to factor other than power, pump or motor)
RHR(A) ×inoperable due to the
loss of power source
and cooling system
△inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system
RHRC/RCRS(A,C) ×inoperable due to the
submerge of power
source and motor
×inoperable due to the
submerge of power
source and motor
×inoperable due to the
submerge of power
source and motor
×inoperable due to the
submerge of power
source and motor
EECW(A) ×inoperable due to the
submerge of power
source and motor
×inoperable due to the
submerge of power
source and motor
×inoperable due to the
submerge of power
source and motor
×inoperable due to the
submerge of power
source and motor
×inoperable due to the
loss of power source
and cooling system
△inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system
×inoperable due to
submerge△
inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system
RHR(B) △inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system○ stand-by △
inoperable due to the
loss of cooling system
RHRC/RCRS(B,D) ×inoperable due to the
submerge of power
source and motor
×inoperable due to the
submerge of power
source
○ stand-by ×inoperable due to the
submerge of power
source and motor
EECW(B) ×inoperable due to the
submerge of power
source and motor
×inoperable due to the
submerge of power
source
○ operation ×inoperable due to the
submerge of power
source
△inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system○ stand-by △
inoperable due to the
loss of cooling system
×inoperable due to
submerge△
inoperable due to the
loss of cooling system○ operation △
inoperable due to the
loss of cooling system
△inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system△
inoperable due to the
loss of cooling system
MUWC
(alternative water injection)MUWC(B) ○ stand-by ○ stand-by ○ stand-by ○ stand-by
○ stand-by ○ stand-by ○ stand-by ○ stand-by
RHR(C )
EDG(B)
RWCU
RCIC
Unit 4Unit 3Unit 2Unit 1System
RHR(A)
including cooling
systems
RHR(B)
including cooling
systems
LPCS
EDG(A)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 31
Field Walkdown
• Challenges in conducting field walkdown
– Under continuous tsunami alerts, walkdown must be done in the field where a
lot of debris, openings and flooding areas existed in the dark.
– Preparation for emergency evacuation in case of further tsunami and other
safety measures for personnel going out to the field.
– Successful access to the field was 6 hours after the tsunami flooding.
• Field walkdown after the tsunami
– Plant equipment status checked / component
functionality verified.
– Results were summarized and shared at TSC.
– TSC set priorities on recovery of RHR (B) cooling
systems by replacing motors and supplying power
from survived electrical buses and mobile power
vehicles through temporary cable.
In order to establish a well-prioritized restoration strategy, degree of damage and possibility of short-term restoration must be understood through walkdown.
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 32
Logistics in Emergency Situation • Procurement and transportation of Materials and Equipment
– Emergency procurement of motors, cable, mobile power vehicles, fuel oil and
mobile transformers with close cooperation between site TSC and corporate ERC.
– Rated output of some motors were not the same as that of the original motors.
TSC determined to install them based on the evaluation of actual load conditions.
• Difficulties experienced in logistics
– Motors were transported from Toshiba by a chopper of SDF and from Kashiwazaki
Kariwa NPP by trucks.
– Securing redundant communication measures were critically important when major
highway was damaged and public cell phone services were disrupted.
Mobile Power Vehicles Fuel oil delivery to the site Necessary materials and
equipment prioritized and listed
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 33
Emergency Restoration Efforts in the Field
• Pumps of RHR cooling systems (RHRC, RHRS, EECW) were inspected.
• Motors were replaced for pumps in RHRC and EECW.
• In order to restore the inundated electrical buses, temporary cable and
high voltage mobile power vehicles were deployed.
• Temporary cable was laid from survived power cubicles in Rad-Waste
Building and Unit 3 Heat Exchanger Building.
Drawing made at TSC for temporary cable laying
Motor replacement
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 34
Recovering Electricity
• Temporary cable of 9 km length was laid by about 200 personnel within a day.
Usually this size of cable laying requires 20 personnel and more than 1 month period.
• After the pumps for RHR cooling systems were restored and temporary cable was laid,
RHR (B) of Unit 1 started up at 1:24 on March 14 and other units followed.
• Finally at 15:42 on March 14
with the start up of Unit 4 RHR,
RHR of all four reactors of
Fukushima Daini started
operation.
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 35
Temporary Power Supply and Motor Replacement at 2F
Unit #3
Hx
Building
Unit #1
Reactor
Rad-Waste
Building
TSC
Main Office
Unit #4
Turbine
Unit #2
Hx
Building
Unit #1
Hx
Building
Unit #4
Hx
Building
Unit #2
Reactor Unit #3
Reactor
Unit #4
Reactor
Unit #3
Turbine
Unit #1
Turbine
Unit #2
Turbine
Mobile Power Supply Truck (500kVA)
Temporary Cables
Mobile Power Supply Truck (500kVA)
6.6kV/480V Transformer
6.6kV/480V Transformer
About 9 km of temporary cables
were laid and motors were
replaced.
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 36
System Status after Emergency Restoration at 2F
○ ; secure (power, pump and motor all working)
× ; loss of function (power, pump or motor inoperable)
△ ; malfunction (inoperable due to factor other than power, pump or motor)
RHR(A) ×inoperable due to
loss of power source
and cooling system
△
inoperable due to
loss of cooling
system
△
inoperable due to
loss of cooling
system
△
inoperable due to
loss of cooling
system
RHRC/RCRS(A,C) ×inoperable due to
submerge of power
source and motor
×inoperable due to
submerge of power
source and motor
×inoperable due to
submerge of power
source and motor
×inoperable due to
submerge of power
source and motor
EECW(A) ×inoperable due to
submerge of power
source and motor
×inoperable due to
submerge of power
source and motor
×inoperable due to
submerge of power
source and motor
×inoperable due to
submerge of power
source and motor
×inoperable due to
loss of power source
and cooling system
△
inoperable due to
loss of cooling
system
△
inoperable due to
loss of cooling
system
△
inoperable due to
loss of cooling
system
×inoperable due to
submerge△
inoperable due to
loss of cooling
system
△
inoperable due to
loss of cooling
system
△
inoperable due to
loss of cooling
system
RHR(B) ○ operation ○ operation ○ operation ○ operation
RHRC/RCRS(B,D) ○ operation ○ operation ○ operation ○ operation
EECW(B) ○ operation ○ operation ○ operation ○ operation
○ stand-by ○ stand-by ○ stand-by ○ stand-by
△operable using tie-line
from unit #2○ stand-by ○ stand-by ○ stand-by
△inoperable due to the
loss of purge line△
inoperable due to the
loss of purge line△
inoperable due to the
loss of purge line△
inoperable due to the
loss of purge line
MUWC
(alternative water injection)MUWC(B) ○ stand-by ○ stand-by ○ stand-by ○ operation
×inoperable for loss of
core pressure×
inoperable for loss of
core pressure×
inoperable for loss of
core pressure×
inoperable for loss of
core pressureRCIC
RWCU
EDG(B)
RHR(C )
Unit 2 Unit 3 Unit 4System
RHR(A)
including cooling
systems
RHR(B)
including cooling
systems
Unit 1
LPCS
EDG(A)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 37
Overview of the 10-Unit Simultaneous Accidents
Date 1F 2F
1 2 3 4 5 6 1 2 3 4
3/11
3/12
3/13
3/14
3/15
3/16-19
3/20
3/14 17:00
3/14 1:24
RHR 3/14 7:13
RHR
3/14 15:42
RHR
3/14 18:00
3/15 7:15
3/12 12:15
3/20 14:30
3/19 22:14
RHR
3/12 8:13
D/G-6B
3/22 10:35
P/C-4D
3/22 10:36
P/C-4D
3/20 15:46
P/C-2C
3/20 15:46
P/C-2C
3/19 5:00
RHR
3/20 14:30
Station Black-Out
Loss of Ultimate Heat Sink
Cold Shutdown
3/12 15:36 Unit 1 Explosion
3/15 6:00-6:10 Unit 4 Explosion (?)
3/14 11:01 Unit 3 Explosion
3/11 15:27 1st Tsunami, 15:35 2nd Tsunami 3/11 15:22~ Tsunamis
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 38
Testimonies from the Field (Operators)
―In an attempt to check the status of Unit 4 D/G, I was
trapped inside the security gate compartment. Soon the
tsunami came and I was a few minutes before drowning,
when my colleague smash opened the window and saved
my life.‖
―In total darkness, I could hear the unearthly sound of SRV
dumping steam into the torus. I stepped on the torus to
open the S/C spray valve, and my rubber boot melted.‖
―The radiation level in the main control room was
increasing 0.01 mSv (1 mrem) every 3 seconds but I
couldn’t leave—I felt this was the end of my life.‖
―I asked for volunteers to manually open the vent valves.
Young operators raised their hands as well; I was
overwhelmed.‖
―Unit 3 could explode anytime soon, but it was my turn to
go to the main control room. I called my dad and asked
him to take good care of my wife and kids should I die.‖
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 39
Testimonies from the Field (Maintenance Persons)
―We saw our car crashed by the explosion of the Unit 3. If
we had gotten on the car a few minutes earlier, all of us
would have been dead.‖
We were replacing fire hoses when the explosion of Unit 3
occurred. We felt almost dying since many large rubbles
were falling down to us. I urgently ran underneath a nearby
fire engine. One of my colleagues got injuries in his leg and
stomach.‖
―There were so many manholes opened by the tsunami. In
order to lay cables, we had to proceed step by step
carefully checking safety in the complete darkness.‖
―We were working in the Unit 3/4 control room when the
explosion occurred. I was resigned to my fate. Dose rate
was going up in the room after the explosion and we
desperately tried to find places with lower dose rate.‖
―After replacing an air cylinder for the PCV ventilation of
Unit 3, I heard sound of steam and saw white mist around
us. I got into a panic for a while.‖
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 40
4. Summary
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 41
The 1F accident was caused by the simultaneous loss of multiple safety
functions due to far beyond design basis of tsunami. The main factors of the
accident are “the simultaneous loss of total AC power and DC power for
a extended period of time” and “the loss of the heat removal function of
the emergency seawater system for a extended period of time.”
Preparations had been previously made to receive power from neighboring
units in the event that AC power and DC power were not available. During the
accident, direct tsunami damage was so widespread that the neighboring
units were all in the same condition.
Summary of Lessons Learned
―Carefully consider the robustness of current design of
nuclear power plants and emergency preparedness
against beyond design basis events that could lead to
common cause failures regardless of their assumed
probability demonstrating a continuous learning
organization.‖
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 42
Success path regarding Cooling and Heat Removal from the Reactor
1)Promptly initiate core injection
methods using high-pressure cooling
water injection equipment
2)Initiate depressurization methods before losing
of high-pressure cooling water injection function
3)Stable low-pressure cooling water injection methods
should be available during the depressurization stage
4)Provide reliable PCV venting methods (heat removal
through the atmospheric discharge of heat)
5)Provide measures to restore the
cooling function using sea water
6)Provide measures which enable necessary monitoring for those operation
and plant conditions.
It is inevitable to maintain water injection and core cooling function thoroughly
and continuously even in poor environmental conditions.
Technical Lessons Learned
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 43
2F Key Success Factors
Accident mitigation by applying EOP and AMG
Prioritized restoration strategy based on Field Walkdown
Prompt restoration with success of emergency
procurement for materials and equipment
Logistics for long term emergency response
Organizational integrity: Leadership, Communication,
Accountability, Professionalism
Organization and Management Features
Design/Engineering Features
Availability of most of M/C, P/C and Battery
Availability of off-site power
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 44
Website Information
TEPCO English website http://www.tepco.co.jp/en/nu/fukushima-np/index-e.html
Internal Investigation Committee Interim Report (Dec. 2nd, 2011) http://www.tepco.co.jp/en/press/corp-com/release/11120205-e.html
Report on initial responses to the accident (Dec. 22nd,2011)
The Latest version of accident Timeline (Dec.22nd, 2011) English version will be on the following website soon.
http://www.tepco.co.jp/en/press/corp-com/release/11122208-e.html
INPO—Special Report on Fukushima Daiichi Nuclear Power Station http://www.nei.org/resourcesandstats/documentlibrary/safetyandsecurity/reports/special-report-
on-the-nuclear-accident-at-the-fukushima-daiichi-nuclear-power-station
EPRI—Fukushima Daini Independent Review and Walkdown http://my.epri.com/portal/server.pt?Abstract_id=000000000001023422
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 45
Thank you for your attention!
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 46
5. References
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 47 47
Intensity of the earthquake at the power stations
*: The records were stopped approximately 130-150 seconds after recording started.
Observation Point
(The lowest basement of
reactor buildings)
Observed Data Maximum Response Acceleration
against Basic Earthquake Ground
Motion (Gal) Maximum Response
Acceleration (gal)
Horizontal
(N-S)
Horizontal
(E-W) Vertical
Horizontal
(N-S)
Horizontal
(E-W) Vertical
Fukushima
Daiichi
Unit 1 460* 447* 258* 487 489 412
Unit 2 348* 550* 302* 441 438 420
Unit 3 322* 507* 231* 449 441 429
Unit 4 281* 319* 200* 447 445 422
Unit 5 311* 548* 256* 452 452 427
Unit 6 298* 444* 244 445 448 415
Fukushima
Daini
Unit 1 254 230* 305 434 434 512
Unit 2 243 196* 232* 428 429 504
Unit 3 277* 216* 208* 428 430 504
Unit 4 210* 205* 288* 415 415 504
In Fukushima Daiichi the observed data partially exceeded the maximum response acceleration with respect to the
design-basis earthquake, however most data was below the baseline
Note) Standard ground motion Ss: Seismic motion that was newly established to evaluate seismic safety, taking into account the
earthquakes, etc., that could occur around the power station, based on the revised seismic design review guidelines.
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 48
In Fukushima daiich observation record partially exceeded the design-basis earthquake
ground motion, however it was confirmed to be almost the same level
0.02 0.05 0.1 0.2 0.5 1 2 50
1000
2000
3000
周 期(秒)
加
速
度
(Gal)
Res_1FZ2011031114462R2_EW.wazRes_1f2_Ss-1_mat_EW.wazRes_1f2_Ss-2_mat_EW.wazRes_1f2_Ss-3_mat_EW.waz
(h=0.05)
0.02 0.05 0.1 0.2 0.5 1 2 50
1000
2000
3000
周 期(秒)
加
速
度
(Gal)
2FZ2011031114463R2_NS2F3_mat_Ss-1H_NS2F3_mat_Ss-2H_NS2F3_mat_Ss-3H_NS
(h=0.05)
Fukushima daiich
period(s) period(s)
0 50 100 150-800
-400
0
400
800
時間(秒)
加速
度(G
al)
550
0 50 100 150-800
-400
0
400
800
時間(秒)
加速
度(G
al)
277
Fukushima daini
0.02 0.05 0.1 0.2 0.5 1 2 50
500
1000
1500
2000
周 期(秒)
加
速
度
(Gal)
Res_1FZ2011031114461R2_EW.wazRes_1f1_Ss-1_mat_EW.wazRes_1f1_Ss-2_mat_EW.wazRes_1f1_Ss-3_mat_EW.waz
(h=0.05)
Observation records Design-basis seismic ground motion Ss-1H Design-basis seismic ground motion Ss-2H Design-basis seismic ground motion Ss-3H
0.02 0.05 0.1 0.2 0.5 1 2 50
500
1000
1500
2000
周 期(秒)
加
速
度
(Gal)
Res_1FZ2011031114461R2_EW.wazRes_1f1_Ss-1_mat_EW.wazRes_1f1_Ss-2_mat_EW.wazRes_1f1_Ss-3_mat_EW.waz
(h=0.05)
Observation records Design-basis seismic ground motion Ss-1H Design-basis seismic ground motion Ss-2H Design-basis seismic ground motion Ss-3H
Unit 2(W-E) Unit 3(N-S)
time(s) time(s)
Acce
lera
tion
(Gal
)
Acce
lera
tion
(Gal
)
550 277
Acce
lera
tion
(Gal
)
Acce
lera
tion
(Gal
)
Intensity of the earthquake at the power stations
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 49
(C)GeoEye
Inundated Areas at 1F
Inundation throughout almost all areas where main buildings sited Units 1~4: Inundation height in areas where principal buildings sited:
OP approx. 11.5m~15.5m
(Localized inundation height in southwest area: OP approx. 16m~17m)
Unit 5 & 6: Inundation height in areas where principal buildings sited: OP approx.
13m~14.5m
Almost whole area was flooded Fukushima
Daiichi
Unit
1 Unit
2
Unit
3
Unit
4 Unit
6
Unit
5
Radwaste
Processing
building
Elevation of major
Unit-1-4 buildings:
O.P.10m
Elevation of major
Unit-5,6 buildings:
O.P.13m
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 50
1 号機 2 号機 3 号機 4 号機
運用補助共用建屋
6 号機 5 号機
6 号機D G 建屋
O.P.+1 3 m
O .P.+1 0 m
O .P.+4 m
O .P.+4 m
原子炉建屋
タ ービン建屋
3u Emergency D/G
air inlet louver
Location of Openings from which Sea Water
could Flow into Main Buildings (Fukushima Daiichi Nuclear Power Station)
Turbine
building
Reactor
building
Unit 6 D/G building
Unit 5 Unit 6
Unit 1 Unit 2 Unit 3 Unit 4
▼:Openings at the ground level from
which sea water could flow into buildings
▼:Openings connected to underground
trenches/ducts where sea water could flow
into buildings
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 51
Inundated Areas at 2F
Inundation occurred throughout all areas along the sea, but it was not observed to
have inundated over the slope and into areas where major buildings are sited.
Run up of tsunami centered on the south side of Unit 1 Inundation height in sea side area: OP approx. +7.0~7.5m
Inundation height in areas where principal buildings sited: OP approx. 12~14.5m
Inundation height in area south of Unit 1: OP approx. + 15~16m
Limited area was flooded
Inflowed
intensively
(C)GeoEye
Unit 2 Unit 1 Unit 3 Unit 4
Elevation of major
Unit-1-4 buildings:
O.P.12m
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 52 52
Location of Openings from which Sea Water
could flow into Main Buildings (Fukushima Daini Nuclear Power Station)
Inside Unit 1 heat exchanger building Units 3 & 4
Sea side of turbine building
▼:Openings at the ground level from which sea water could flow into buildings
▼:Openings connected to underground trenches/ducts where sea water could flow into buildings
Heat exchanger
building
Turbine
building
Reactor
building
Unit
1
Unit
2
Unit
3
Unit
4
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 53
Base level O.P.0m
Reactor building
Ocean-side area Main building area
breakwater
Design basis tsunami height O.P.+5.2m
Site level O.P. +12m
Water intake
Inundation height apx. O.P. +6.5 - 7m Safety measures has taken
against 5.2m Tsunami height
Site level O.P. +4m
Turbine building
Tsunami Height @1F v.s. 2F
4月9日記者発表
• The new design basis Tsunami height for 1F & 2F were evaluated based on the JSCE Tsunami assessment
methodology. (1F: O.P.+5.7m, 2 F: O.P.+5.2m)
• The countermeasures were implemented at both NPSs, such as pump motor elevation raised @1F and
openings sealed @2F, that were all equivalent from the viewpoint of resistance against Tsunami hazard.
• The 15m class Tsunami caused by M9.0 class earthquake that accidentally attacked 1F was far beyond design
basis and whatever evaluation and whatever countermeasures did not matter at this time.
1F
2F
O.P.:Onahama Point
Hx building
Assumed highest tsunami water level
O.P. +5.7m
Base level O.P. 0m
-
-
-
- Assumed highest
tsunami water levelO.P. +5.7m
Base levelO.P. 0m
Site levelO.P. +10m(Units 1-4*)
* Site level on Units 5 and 6 is O.P. +13m
Turbine building
Reactor buildingInundation heightapx. O.P. +14-15m
Ocean-side area
Main building area
Water intake
Site level O.P. +4m
Safety measures has taken against 5.7m
Tsunami height
breakwater
Water
Pump
Assumed highest tsunami water level
O.P. +5.7m
Base levelO.P. 0m
Site levelO.P. +10m(Units 1-4*)
* Site level on Units 5 and 6 is O.P. +13m
Turbine building
Reactor buildingInundation heightapx. O.P. +14-15m
Ocean-side area
Main building area
Water intake
Site level O.P. +4m
Safety measures has taken against 5.7m
Tsunami height
breakwater
Water
Pump
Design basis
tsunami height
O.P.+5.7m
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 54 54
Differences in Tsunami that hit Fukushima Daiichi
and Daini NPSs
1050
100150
福島第二
福島第一0
2
4
6
8
10
12
14
水深[m]Sea floor
displacement
[m]
Fukushim
a
Da
iich
i
Fu
ku
sh
ima
Dain
i
Ma
xim
um
tsu
na
mi h
eig
ht
[m
]
Peaks coinciding
↓
Tsunami height: High
Peaks not coinciding
↓
Tsunami height: Low
①
②
③
Same amplification rate
Water level
fluctuation from
each block Time T
Warm colored blocks
generated massive
tsunami wave heights
③
②
①
Tsunami of various magnitudes at a depth of
around 150m were amplified at the same rate
and struck at each nuclear power station
Water depth [m]
①
+
②
+
③
Postulated Tsunami Model
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 55
Permitted Design Basis(1)… Tsunami assessment
Tsunami assessment in construction permit
Fukushima NPSs
•Historical tsunamis of Iwate and Miyagi coast were larger than that of Fukushima
•Approved design basis at Fukushima NPS was 3.1-3.7m
Fukushima NPSs
3.11.2011 tsunami heights (m) Historical tsunami heights (m)
Preliminary results by The 2011 Tohoku Earthquake Tsunami Joint Survey Group( http://www.coastal.jp/ttjt/) 07 May 2011
Inundation
Run-up
Unit Ground Level Tsunami Height〔m〕
R/B,Tb/B
〔m〕
Pumps
〔m〕
Design Basis Modified in
2002 (2009)
11 march
2011
1F 1-4 10.2 4 3.1 5.7 (6.1) 14-15
1F 5-6 13.2 4 3.1
2F1-4 12 7 3.7 5.2 7-7.5
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 56
Permitted Design Basis(2)… Tsunami assessment
Earthquake Magnitude Earthquake
#1 8.2 1952 Nemuro-oki
#2 8.4 1968 Tokachi-oki
#3 8.3 1896 Meiji-Sanriku
#4 8.6 1611 Keicho-Sanriku
#5 8.2 1793 Miyagi-oki
#6 7.7 1978 Miyagi-oki
#7 7.9 1938 Fukushima-oki
#8 8.1 1677 Enpo-Bousou
(http://outreach.eri.u-tokyo.ac.jp/eqvolc/201103_tohoku/#Inversion 2011/3/18) 2011/3/11 source area
English edition
http://www.jsce.or.jp/committee/ceofnp/Tsunami/eng/tsuna
mi_eng.html
In JSCE- 2002, assumed 8 earthquakes individually. March
11 Earthquake occurred over several areas simultaneously.
Tsunami Assessment was revised based on the JSCE (Japan
Society of Civil Engineers) Method,2002
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 57
Unit 1 Unit 2
Equipm
ent
Installed
building
Installe
d floor
Possi
bility
of
use
Status Equipme
nt
Installed
location
Installed
floor
Pos
sibili
ty of
use
Status
DG
DG 1A T/B B1FL × Submerged DG 2A T/B B1FL × Submerged
DG 1B T/B B1FL × Submerged DG 2B Shared
pool 1FL ×
M/C
submerged
cannot be
used
- - - - - - - - - -
(M/C)
Emerge
ncy
high
voltage
switchb
oard
M/C 1C T/B 1FL × Water
damage M/C 2C T/B B1FL × Submerged
M/C 1D T/B 1FL × Water
damage M/C 2D T/B B1FL × Submerged
- - - - - M/C 2E Shared
pool B1FL × Submerged
Damage Status of Unit 1 & 2 Emergency DG and Emergency High
Voltage Switchboard (Immediately after the Tsunami)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 58
Unit 3 Unit 4
Equipme
nt
Installed
location
Installe
d floor
Possi
bility
of
use
Status Equipme
nt
Installed
location
Install
ed
floor
Pos
sibili
ty of
use
Status
DG
DG 3A T/B B1FL × Submerge
d DG 4A T/B B1FL × Submerged
(Construction
in progress)
DG 3B T/B B1FL × Submerge
d DG 4B Shared
pool 1FL ×
M/C
submerged
cannot be
used
- - - - - - - - - -
(M/C)
Emerge
ncy
high
voltage
switch
board
M/C 3C T/B B1FL × Submerge
d M/C 4C T/B B1FL ×
Submerged
(Inspection
in progress)
M/C 3D T/B B1FL × Submerge
d M/C 4D T/B B1FL × Submerged
- - - - - M/C 4E Shared
pool B1FL × Submerged
Damage Status of Unit 3 & 4 Emergency DG and Emergency High
Voltage Switchboard (Immediately after the Tsunami)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 59
Unit 5 Unit 6
Equipme
nt
Installed
location
Install
ed
floor
Po
ssi
bilit
y of
use
Status Equipment Installed
location
Install
ed
floor
Pos
sibili
ty of
use
Status
DG
DG 5A T/B B1FL ×
Related
equipment
Water
damage
DG 6A R/B B1FL ×
Related
equipment
Water
damage
DG 5B T/B B1FL ×
Related
equipment
Water
damage
DG 6B DG
building 1FL ○ -
- - - - - HPCSD/G R/B B1FL ×
Related
equipment
Water
damage
(M/C)
Emerge
ncy
high
voltage
switchb
oard
M/C 5C T/B B1FL × Submerged M/C 6C R/B B2FL ○ -
M/C 5D T/B B1FL × Submerged M/C 6D R/B B1FL ○ -
- - - - - HPCS
DG M/C R/B 1FL ○ -
Damage Status of Unit 5 & 6 Emergency DG and Emergency High
Voltage Switchboard (Immediately after the Tsunami)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 60
Fukushima Daiichi: DG System Outline
All function
was lost after
the tsunami
Power was
secured in
Unit 6 (B)
only
[Fukushima Daini: DG System Outline]
Power was
secured in
Unit 3
(B)(H) and
Unit 4 (H)
only
Sea water-cooled DG (10)
Unit 1 (A)(B), Unit 2 (A), Unit 3 (A)(B), Unit 4 (A), Unit 5 (A)(B), Unit 6 (A)(H)
Air-cooled DG (3)
Unit 2 (B), Unit 4 (B), Unit 6(B)
Sea water-cooled DG (12)
Unit 1 to Unit 4(A)(B)(H)
Sea water
pump
D/G Heat
exchanger
Sea
~ ~
~ ~
~ ~ ~ ~
Outside air
Air cooler D/G
Cooling water pump
Heat
exchanger
Sea water
pump Heat
exchanger
Cooling water
pump
D/G Sea
~ ~ ~ ~
~ ~ ~ ~
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 61
Power Access/Restoration Status Immediately
after 1F-1,2 Shutdown
Date Operation and Restoration Status
March 11 Temporary MCR lighting on (Temporary small engine generator)
March 12
Power source for Unit 1 Instrument restored (Temporary small
engine generator)
Power source for Unit 1 Instrument restored (power source cart)
Temporary small engine generator destroyed by H2 explosion
Temporary MCR lighting on (another temporary small engine
generator)
March 19 Backup transformer ~ Unit 1 & 2 temporary M/C (A) cable laid
March 20 Off-site power restored (P/C2C power received)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 62
Power Access/Restoration Status Immediately
after 1F-3,4 Shutdown
Date Operation and Restoration Status
March 11 Temporary MCR lighting on (Temporary small engine generator)
March 13 P/C 4D restored (power source cart)
March 14
Yonomori Line 1L step-down transformer cart (66/6.9kW)
connected to the Shin-Fukushima Substation
Yonomori Line 1L ~ Okuma Line 3L connected
Power source for Unit 1 Instrument restored (power source cart)
The power source cart destroyed by H2 explosion
March 18 Unit 3 & 4 MC, Switch installation location
March 22 Off-site power restored (P/C4D power received)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 63
Power Access/Restoration Status Immediately
after 1F-6 Shutdown
Date Operation and Restoration Status
March 11
DG6B startup (6A and 6H were shut down by the tsunami,
6B is an air-cooled type)
SGTS(B) startup, DC125V/250V (B system) restoration
March 12 DC125V/250V (A system) restoration
March 13 MUWC(B) startup
March 19
RHR 6B startup, temporary RHRS alternative pump startup
(power source cart)
DG6A startup (March 21 shutdown)
March 20 Cold shutdown condition
March 22 Off-site power restored (M/C6C, 6D power received)
March 23 Temporary RHRS alternative pump switched to off-site
power
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 64
Date Operation and Restoration Status
March 12 DC125V/250 restoration
March 13 MUWC(A), SGTS(A) startup
March 18 Temporary RHRS alternative pump startup (power source cart)
March 19 RHR 5C startup
March 20 Cold shutdown condition
March 22 Off-site power restored (M/C6C, 6D power received)
March 23 Temporary RHRS alternative pump switched to off-site power
Power Access/Restoration Status Immediately
after 1F-5 Shutdown
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 65
Recovery Process of I&C equipments @1F (1/2)
● After tsunami → Total loss of instrumentations due to loss
of offsite power and DC 125V
● March 11-14: to install temporary batteries to important
instrumentations, such as reactor water level, reactor
pressure, D/W pressure, S/C pressure etc. (1F-1-3: March 11,
1F-5/6: March 14) and to start to obtain plant data
● March 22-25: to recover AC 120V bus for I&C (1F1: March
23, 1F2: March 25, 1F3/4: March 22)
● ~Present: to prioritize the recovery of redundant
instrumentations for their reliability and to change step by step
from temporary battery to original power source
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 66
Recovery Process of I&C equipments @1F (2/2)
● May 9: to go into R/B to calibrate the D/W pressure
instrument @1F1
● May 10-12: to calibrate the fuel zone reactor water level
instrument @1F1
- water level assumed as lower than -500cm of TAF
● June 3-4: to install the temporary reactor pressure and
Δpressure instrument at the test line of fuel zone reactor
water level instrument @1F1, to obtain more precise data on
reactor pressure and water level
● June 22-24: to install the temporary reactor pressure and
Δpressure instrument at the test line of fuel zone reactor
water level instrument @1F2
- not successful due to rapid evaporation of water inside instrumentation line by
high PCV temperature
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 67
Current status of important instrumentations @1F
Paramete
r/unit 1F1 1F2 1F3 1F4 1F5 1F6
Reactor
water level
A:◎
B:△
A:△
B:△
A:△
B:△ N/A ○ ○
Reactor
pressure A:◎ A:○
A:△
B:△ N/A ○ ○
Reactor
water temp. Not sampled Not sampled Not sampled N/A ○ ○
Temperatur
e around
RPV
○ ○ ○ N/A N/A N/A
D/W
pressure ◎ △ ○ N/A N/A N/A
S/C
pressure ○ × ○ N/A N/A N/A
CAMS rad
monitor D/W:×
S/C:○
D/W:○
S/C:○
D/W:○
S/C:○ N/A N/A N/A
S/C
temparature ○ ○ ○ - - -
◎:calibrated, ○:assumed to be intact, △:under continuous observation, ×:failure
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 68
Unit 1 Isolation Condenser
R
PV
Primary Containment
Open to the Air
Fire protection system Pure water make up system
MO
B system A system Isolation
Condensor
1B
10A 10B
3A
3B
PLR P’P
MO
MO
MO
MO
MO
MO
MO MO
MO
1A
2B 2A
4A
4B
①Initiating system by
opening the valve
② Reactor steam is cooled by Isolation condenser coolant tank
④Condensate water return
back to RPV driven by
natural convection force
③Heated water in the tank
released to the open air
MSIV
Function of the Isolation condenser
○Depressurization of the reactor by steam condensation during reactor Isolation
(MSIV closure condition)
○Redundancy design(2 systems)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 69
1F Unit 1 Schematic System Diagram (After Tsunami )
Sea
Tb
Condenser
H/W
Gen
CST
Filtrated Water Tank
SLC
Stac
k
Sea
CCS
D/G CCSW
SRV
CRD
HPCI
CP RFP
CWP
CS MUWC
DD FP
IC
S/C vent valve
D/W vent valve
RP
V
from CST&H/W
Sea
:Operable
:Inoperative due to power loss
: Briefly Operative
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 70
The automatic isolation interlock of the IC was actuated due to the loss of power
caused by the tsunami and then lost its function. Afterwards, the reactor water
level decreased in a short period of time and the core was exposed (Dropped to
TAF), leading to the core damage. During this time, it was difficult to understand
plant status due to the loss of power.
Based on the analysis results, it is evaluated that the core would have been
damaged regardless of the continuation of the operation of the IC after 18:18.
When the water level gauge was temporarily restored using a temporary power
source after 21:00 on March 11, a reading was obtained showing that the reactor
water level was above TAF. However at this point, there was not enough
information to comprehensively determine that this reading was erroneous. At the
Emergency Response Headquarters on the site and the Head Office, it was not
deemed at this point that the IC had stopped. The possibility of the core damage
was recognized due to the increase in dose rate in front of the double doors of the
reactor building at around 23:00 on March 11 and the unusually high reading for
the dry well pressure that was obtained for the first time at around 0:00 on March
12.
Summary of the Plant Behavior in Unit 1 (1/2)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 71
On March 12 at around 3:00, the reactor pressure decreased, although reactor
depressurization operation was not conducted. This implies that damage to the
reactor cooling water pressure boundary had occurred due to core damage. This
implies that core damage might have progressed to a considerable extent in a
short period of time.
Based on the results using the accident analysis codes, it took about 3 hours to
drop to TAF after the earthquake and about 4 hours until core damage began,
which indicates the rapid event progress to the core damage. This result is
consistent with the events actually observed.
Summary of the Plant Behavior in Unit 1 (2/2)
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 72
1F Unit 2 Schematic System Diagram (After Tsunami)
Sea
Tb
Condenser
H/W
Gen
CST
Filtrated Water Tank
SLC
Stac
k
Sea
RHR
D/G RHRS
SRV
CRD
HPCI
LPCP MD-RFP
CWP
CS
MUWC DD FP
S/C vent valve
D/W vent valve
:Operable
:Inoperative due to power loss
RP
V
TD-RFP
from CST&H/W
CST
RCIC
HPCP
Sea
:Inoperative
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 73
As the RCIC of Unit 2 functioned for a relatively long period of time, the core
decay heat was lower than immediately after shutdown. However as the high-
pressure systems (RCIC) lost its function, decrease in the reactor water level
started.
About 1 hour and 20 minutes later after the RCIC shutdown, the fire engine’s
pump was started up and preparations for low-pressure water injection were
ready. However the SRV did not immediately operate during reactor
depressurization.
It is considered that core damage occurred because low-pressure water injection
did not function immediately after the SRV was activated and reactor
depressurization was achieved. Because of the rapid decrease in the retained
water due to the outflow of steam to the S/C associated with reactor
depressurization, cooling function degraded furthermore.
According to the analysis by using the MAAP code, it is evaluated that core
damage started due to the decrease in reactor water level followed by
degradation of the function of the RCIC.
Summary of the Plant Behavior in Unit 2
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 74
1F Unit 3 Schematic System Diagram (After Tsunami)
Sea
Tb
Condenser
H/W
Gen
CST
Filtrated Water Tank
SLC
Stac
k
Sea
RHR
D/G RHRS
SRV
CRD
HPCI
LPCP MD-RFP
CWP
CS
MUWC DD FP
S/C vent valve
D/W vent valve
RP
V
TD-RFP
from CST&H/W
CST
RCIC
HPCP
Sea
:Operable
:Inoperative due to power loss
:Inoperative
All Rights Reserved ©2011The Tokyo Electric Power Company, Inc. 75
In Unit 3, preparations for low-pressure water injection were performed by
activating the diesel-driven fire pump. However, because the reactor pressure
was higher than the water injection pressure, switching to low-pressure water
injection was not immediately successful after shutdown of the high-pressure
systems (HPCI). This caused degradation of cooling and thus leading to core
damage.
S/C venting was conducted and repeated several times. The monitoring car
reading near the main gate increased temporarily. However no large increase in
the background level was observed.
In addition, the hydrogen that was generated following the core damage was not
completely retained in the PCV and leaked into the reactor building, and is
considered to have caused the explosion of the reactor building.
Summary of the Plant Behavior in Unit 3