Upload
hubert-erik-blankenship
View
216
Download
2
Tags:
Embed Size (px)
Citation preview
The Efficiency of Flexible Solar Panels and Changes in the Earth’s Magnetic Field at Altitude
Vehicle Summary
• Total length of 116.5 inches
• 4.0” Airframe (3.9” Inside diameter)
• BlueTube 2.0
• Separates into three sections
TopNoseconePayload
Flip-Out Rotor Blades
MiddleDrogue Parachute
AltimetersHousing for Rotor Blades
BottomMain ParachuteMotor (Plugged)
Fins
Payload Summary
• Studying the efficiency of flexible solar panels, and changes in power output
• Also investigating changes in the earth’s magnetic field
• Housed in the Modular Payload System (explained later)
Vehicle Changes
• Recent delays in funding have delayed parts orders and some parts have gone out of stock– Aerotech K700 motor now Aerotech K828– Aerospace composite fins now fiberglass covered
birch plywood– Ejection canisters will be made and not bought– Piston removed on drogue parachute compartment
• Design changes from subscale problems– Ejection charge holders have been added– Vertical Wind Turbine has been replaced with flip out
rotor blades
Payload Changes
• The LabPro data logger does not support a data trigger
• Exchanged for a custom built LabQuest data logger from Vernier at no charge
• The proper amount of resistance has been researched and verified by manufacturer– 77 Ohms of resistance instead of previous 40
Ohms
Motor Selection
• Aerotech K828 FJ
• 54/2560 mm casing
• Change was made because K700 Motor was out of stock from multiple vendors
Motor ManufacturerTotal Impulse (N-
sec)Max Thrust (Newtons)
Burn Time (s)
Average Thrust (Newtons)
Thrust to Weight Ratio
K828 AeroTech 2120.0 1,303.8 N 2.50 828 8.64
Estimated Rocket Performance
• Estimating a coefficient of drag of around 0.60• Estimated dry weight of 16.37 pounds
Note: Simulations calculated with 5 mph winds
Motor Thrust Curve
Rocket Flight Stability Margin
• Center of gravity 73.4 inches from nose
• Center of pressure 87.5 inches from nose
• Stability margin of 3.50 calipers
• Stability of 4.86 calipers after burnout
CG Position: 73.4 inches from noseCP Position: 87.5 inches from nose
Stability Margin: 3.50
Thrust to Weight Ratio
• Thrust to weight ratio is 8.64 to 1
• High acceleration of approx. 459 m/s2 (14 g’s)
Acceleration (ft/s2) vs. Time (s)
Rail exit velocity
• 8 ft Rail = 75.0 ft/s
• 10 ft Rail = 83.3 ft/s
• 12 ft Rail = 90.8 ft/s
• Planned to launch using a 10 ft rail
• Lugs compatible with Standard 1” Black Sky Rails
Parachute Sizes and Descent Rates
• Drogue parachute: 24 inch diameter TAC-1• Four flat strap nylon suspension lines• Deploys at Apogee (backup charge 2 seconds
later)• Estimated descent rate of 82 ft/s• Swivels are attached to each parachute• Additional swivel attached to drogue mount
Parachute Sizes and Descent Rates
• Main parachute: 84 inch diameter TAC-1• Four flat strap nylon suspension lines• Deploys at 700 feet (backup charge at 500 feet)
• Estimated descent rate of 19 – 20 ft/s• Drift in 5 mph= 500 feet• Drift in 10 mph= 900 feet• Drift in 15 mph= 1800 feet
Large Margin of Error
Test Plans and Procedures
• BlueTube airframe was able to withstand 300 pounds of force of compression without signs of failure
• 350 degrees for 30 minutes = ⅛” increase in circumference
• Freezer for 30 minutes = No notable change• Underwater for 30 minutes = Tube began to
wrinkle• 2 hours in sun = 1/16th inch bend across 4 feet
Test Plans and Procedures
• A 3/16th inch birch plywood bulkplate withstood 200 pounds of force before test was stopped– Force was applied by stepping on exposed plate– Plate was permanently warped 1/8th inch across
diameter
Birch Plate
Clamp
Force
Test Plans and Procedures
• All sensors for payload have been verified and function as planned– Sensors must be zeroed before use for best results
• Accelerometer– Held up for 5 seconds, down for 5, shook, then hit against palm
• The magnetic field sensor was rotated clockwise to check functionality
• Peak readings when pointed to magnetic south (geo graphic north) as expected
• Does not appear to be affected by other sensors
Test Plans and Procedures
• Solar panel, current probe, and voltage probes have been tested– Test was done in evening sun– Not optimal power output– Solar panel was 50% covered, then roughly 90% bcovered, then
fully covered
Test Plans and Procedures
• Remaining tests:– Ejection charge deployment test
• Procedure explained later
– Solar panel test in full sun• With 77 ohms of resistance, current and voltage
probes
– Fin strength test• Identical to bulkplate test
Test Plans and Procedures
Scale Model Flight Test • Two half-scale flights have been
conducted• One ejection charge test before flight• Aerotech H180 • 3.5 Stability margin
• Two straight flights without any wobble• Set up for dual deployment
Scale Model Flight Test
• First launch reached 2403 feet• Second launch reached 2313 feet• After launch conditions were put into Rocksim• Estimated drag coefficient of 0.45
Scale Model Problems
• First launch blew a hole in the main airframe (no main parachute)– Cause due to no ejection
charge canister support
• Second launch separated for main parachute, but parachute did not deploy
-Cause due to use of Pyrodex/ not enough black powder-Extensive ground testing will be completed with 4F black powder for full-scale
Scale Model Problems
• First launch carried a vertical wind turbine– Slow, inconsistent spin
• Second launch carried flip out rotor blades– Fast consistent spin, but shock cord caught
under blade and twisted
Scale Model Problems
• Rotor blade cracked– Higher grade propeller will be used for full scale
• Shock cord heavily twisted– Shock cords will be better packed use a rubber
band to contain cords for organization
Dual Deployment Avionics Test
• Completed on Monday, December 13th
• Altimeters placed in a vacuum chamber• Both altimeters showed a drogue and main deployment
Ejection Charge Amount test
• Status: In planning
• Calculated 3.1 grams for main, 2.3 for drogue
• Calculating for 300 pounds of force or 23.9 psi
• Plenty of force to break three 2.5 mm styrene shear pins
• 6 total ground tests will be performed
Ejection Charge Amount Test
• Start test with ejection charges sized below calculated amount
• Rocket will be mounted horizontally
• Ballast will be used to simulate actual weights
• Test must clearly eject and pull out parachutes
Payload Integration Feasibility • All sensors and data logger are made by Vernier
Software and Technology• Data logger is also power source for all sensors• LabQuest has been modified by Vernier to fit
into the payload airframe• To retrieve data the data logger unit must be
retrieved
Payload Integration Feasibility
• All units contained in the Modular Payload System (MPS)
• Constructed out of birch plywood• Two ¼” threaded steel rods for structural integrity• Excess wiring will be coiled and stored in bottom section
of MPS• Slots cut in bulkplates to allow for wiring to pass from
one section to another• Must be installed facing specific direction to slide over
solar panel wiring
Modular Payload System
Removal of the MPS
• Nosecone must be removed• A strap will be connected to the two stainless
steel rods the can be used to pull out the MPS• When the mid section is exposed the wires from
solar panel are disconnected• The entire unit is taken to computer for data
retrieval via USB cable
Educational Engagement Plan Status
• “To Apogee and Beyond” Project currently in progress• High schools students will learn about the basics of
rocketry– Will design and make fins for a partially designed rocket in
Rocksim– Working in groups of 2 or 3, they will assemble their rocket
• Large scale launch day on February 27th where the 200+ students will launch their rockets
• Launch site at Local ranch: Tate Farms
Educational Engagement Plan Status
• Visiting the local middle school’s aeronautics class – Status: Scheduled for first week of February
• Visiting local elementary school’s science night and will give presentation– Status: In development
Questions?