The City University of New York Report to the Board of Trustees Committee on Facilities Planning and Management October 30, 2000 2001-2002 Capital Budget Request 2001 2001 - - 2002 Capital Budget Request 2002 Capital Budget Request

The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

The City University of New York

Report to the Board of Trustees

Committee on Facilities Planning and ManagementOctober 30, 2000

2001-2002 Capital Budget Request20012001--2002 Capital Budget Request2002 Capital Budget Request

Page 2: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

The Capital Building Program provides facilities appropriate to house the University’s educational programs and to create effective environments conducive to learning.

Objective:Objective:Objective:

Page 3: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

The Capital Building Program was developed by the Colleges and the Central Office with broad participation by administrators, faculty, staff and students.

Methodology:Methodology:Methodology:

Page 4: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

CAPITAL BUDGETOverview of State Approved Five-Year ProgramCAPITAL BUDGETCAPITAL BUDGETOverview of State Approved FiveOverview of State Approved Five--Year ProgramYear Program

FY2001/2002 is the fourth year of the five-year State capital budget program enacted in FY1998/1999.

The entire five-year program (FY1998/99-2002/03) totals approximately $1 billion in bonded projects and $25 million in minor rehabilitation projects.

Page 5: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2001/2002 Request:FY2001/2002 RequestFY2001/2002 Request::

$322 million for bonded projects

$7 million for minor rehabilitation projects

Page 6: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

CAPITAL BUDGETOverview of State Approved Five-Year ProgramCAPITAL BUDGETCAPITAL BUDGETOverview of State Approved FiveOverview of State Approved Five--Year ProgramYear Program

Capital funding in the previous three years of the $1 billion five-year plan have totaled approximately $535 million.

The remaining funds for the final year of the $1 billion five-year plan total approximately $223 million and will be requested in FY2002/03.

Page 7: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

The City University of New York2001-2002 Capital Budget RequestThe City University of New YorkThe City University of New York20012001--2002 Capital Budget Request2002 Capital Budget Request

PROJECTCATEGORIES OBJECTIVES

Health & Safety Address campus health, safety & security needs

Facility Preservation Maintain appropriate conditions in existing buildings

Comply w/Code requirements & legal statutesADA/Asbestos

Technology Upgrades Improve technology infrastructure & information systems

Energy Conservation Reduce Energy consumption and achieve savings

Renovations Upgrade facilities to support programmatic initiatives

New Construction Provide new space to correct existing deficiencies

Page 8: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

THE CITY UNIVERSITY OF NEW YORKFACILITY AGE PROFILETHE CITY UNIVERSITY OF NEW YORKTHE CITY UNIVERSITY OF NEW YORKFACILITY AGE PROFILEFACILITY AGE PROFILE

4.6 Million GSF

3.4 Million GSF

9.8 Million GSF

2.8 Million GSF 6.2 Million GSF

1980-1999 1900-1919

1920-1939

1940-1959

1960-1979

36%

23% 10%13%

17%

Total: 26.8 Million Gross Square Feet

Page 9: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of
Page 10: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of
Page 11: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2001/2002 RequestFY2001/2002 RequestFY2001/2002 RequestCUNY-Wide Senior College Projects:CUNY-Wide Senior College Projects:

• Health & Safety/Facilities Preserv. $32,900,000

• Network Infrastructure/Telecomm. $9,500,000

• Educational Technology Phase IV $3,000,000

• Energy Conservation $4,845,000

• Science & Technology Equipment $3,750,000

Page 12: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2001/2002 RequestFY2001/2002 RequestFY2001/2002 Request

• Brooklyn - West Quad Building $52,066,000Senior College Projects:Senior College Projects:

Page 13: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of
Page 14: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2001/2002 RequestFY2001/2002 RequestFY2001/2002 Request

• John Jay - Phase II $112,825,000

• Brooklyn - West Quad Building $52,066,000Senior College Projects:Senior College Projects:

Page 15: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of
Page 16: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2001/2002 RequestFY2001/2002 RequestFY2001/2002 Request

•• Lehman - Consolidated Computer Ctr $10,073,000

• John Jay - Phase II $112,825,000

• Brooklyn - West Quad Building $52,066,000Senior College Projects:Senior College Projects:

Page 17: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of
Page 18: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2001/2002 RequestFY2001/2002 RequestFY2001/2002 Request

•• Lehman - Consolidated Computer Ctr $10,073,000

• John Jay - Phase II $112,825,000

• Brooklyn - West Quad Building $52,066,000Senior College Projects:Senior College Projects:

•• Staten Island - 2M Renov. Phs I $318,000

•• Hunter - Renovate Thomas Hunter Hall $1,486,000

Page 19: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2001/2002 RequestFY2001/2002 RequestFY2001/2002 Request

• Health & Safety/Facilities Preserv. $8,900,000

• Network Infrastructure/Telecomm. $6,500,000

• Educational Technology Phase III $3,300,000

• Energy Conservation $2,000,000

CUNY-Wide Community College ProjectsCUNY-Wide Community College Projects

Page 20: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2000/2001 RequestFY2000/2001 RequestFY2000/2001 RequestCommunity College & Medgar Evers ProjectsCommunity College & Medgar Evers Projects

• Medgar Evers – Academic Building I $32,462,000

Page 21: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of
Page 22: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2000/2001 RequestFY2000/2001 RequestFY2000/2001 RequestCommunity College & Medgar Evers ProjectsCommunity College & Medgar Evers Projects

• Medgar Evers – Academic Building I $32,465,000• Medgar Evers – Academic Building I $32,465,000• LaGuardia - Design of Center 3 $11,000,000

Page 23: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of
Page 24: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2000/2001 RequestFY2000/2001 RequestFY2000/2001 RequestCommunity College & Medgar Evers ProjectsCommunity College & Medgar Evers Projects

• Medgar Evers – Academic Building I $32,465,000• LaGuardia - Design of Center 3 $11,000,000

• Bronx - N. Instructional Bldg $6,000,000

Page 25: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of
Page 26: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

FY2000/2001 RequestFY2000/2001 RequestFY2000/2001 RequestCommunity College & Medgar Evers ProjectsCommunity College & Medgar Evers Projects

• Medgar Evers – Academic Building I $32,465,000• LaGuardia - Design of Center 3 $11,000,000

• Bronx - N. Instructional Bldg $6,000,000• BMCC - Chambers St. Renovation $11,000,000

• Hostos - Clinical Science Facility $7,333,000

• Queensborough - Instructional Bldg $2,000,000

Page 27: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of

Overview of FiveOverview of Five--Year Capital Budget RequestYear Capital Budget RequestFY2001/02FY2001/02--FY2005/06 FY2005/06 (costs in thousands)

SeniorColleges

CommunityColleges* Total

2001/2002 $236 $92 $3292002/2003 $175 $97 $2722003/2004 $302 $83 $3852004/2005 $221 $89 $3112005/2006 $286 $108 $394Totals $1,221 $470 $1,691

3 Remaining Years of CurrentFive-Year Program

First 3 Years of NextFive-Year Program

*State/City required match for bonded and minor rehabilitation projects

Page 28: The City University of New York · 2002/2003 $175 $97 $272 2003/2004 $302 $83 $385 2004/2005 $221 $89 $311 2005/2006 $286 $108 $394 Totals $1,221 $470 $1,691 3 Remaining Years of