  • The City of New York

    Capital Commitment PlanFiscal Year 2012

    Volume 2February 2012

    Michael R. Bloomberg, Mayor Office of Management and BudgetMark Page, Director

  • February 2012 Capital Commitment Plan Agency Index

    Department No. Department Name Volume Page 125 Aging, Department for the (AG) .......................................................................................... 1 1

    801 Business Services, Department of Economic Development, Office of (ED) ................................................................ 1 112

    068 Children’s Services, Administration for (CS) ...................................................................... 1 67 042 City University of New York (HN) ...................................................................................... 2 468 856 Citywide Administrative Services, Department of Courts (CO) ............................................................................................................ 1 48 Equipment and Miscellaneous (PU) ....................................................................... 3 1004 Public Buildings (PW) ........................................................................................... 3 1308 Real Property (RE) ................................................................................................. 3 1437 072 Correction, Department of (C).............................................................................................. 1 26 126 Cultural Affairs, Department of (PV) ................................................................................... 3 1038 858 Department of Information Technology & Telecommunications (DP) ................................ 1 86 040 Education, Department of (E) ............................................................................................... 1 97 826 Environmental Protection, Department of Equipment (EP) ...................................................................................................... 1 163 Sewers (SE) ............................................................................................................ 3 1468 Water Mains, Sources and Treatment (WM) ......................................................... 3 1593 Water Pollution Control (WP) ................................................................................ 3 1652 Water Supply (W) .................................................................................................. 3 1585 057 Fire Department (F) .............................................................................................................. 1 178 816 Health, Department of (HL) ................................................................................................. 2 404 819 Health and Hospitals Corporation (HO) ............................................................................... 2 508

  • February 2012 Capital Commitment Plan Agency Index

    Department No. Department Name Volume Page 071 Homeless Services, Department of (HH) ............................................................................. 1 392 806 Housing Preservation and Development Housing Authority (HA) ........................................................................................ 1 206 Housing Preservation and Development (HD) ....................................................... 1 299 096 Human Resources Administration (HR) ............................................................................... 2 531 130 Juvenile Justice, Department of (JJ) ..................................................................................... 2 655 Libraries 035 New York Research (L) ......................................................................................... 2 659 038 Brooklyn Public (LB) ............................................................................................. 2 665 037 New York Public (LN) ........................................................................................... 2 676 039 Queens Borough Public (LQ) ................................................................................. 2 701 846 Parks and Recreation, Department of (P) ............................................................................. 2 715 056 Police Department (PO) ....................................................................................................... 3 971 827 Sanitation, Department of (S) ............................................................................................... 3 1440 998 Transit Authority MTA Bus Company (MT)………………………………………………………... 2 713 Staten Island Rapid Transit (ST) ............................................................................ 3 1539 Transit Authority (T) .............................................................................................. 3 1542 841 Transportation, Department of Bridges, Highway (HB) ......................................................................................... 1 225 Bridges, Waterway (BR) ........................................................................................ 1 19 Equipment (TD) ..................................................................................................... 3 1549 Ferries and Aviation (FA) ...................................................................................... 1 198 Highways (HW) ..................................................................................................... 2 547 Traffic (TF) ............................................................................................................ 3 1553

  • VIII..

    2012-2015AppropriationsandCommitmentswith2012PlanandForecast,andActualsthroughNovember,IncludingDetailedProjectStatusInformations,byBudgetLine

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 404WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN014 FMS #: 816 A00 ALBERT EINSTEIN COLLEGE OF MEDICINEAVAILABLE BALANCE AS OF: 11/30/11 $2,550,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $1,901.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $2,035,099.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 1,000 * * * * (C)* 4,550 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 4,550 * 4,550FORCST(C)* * * * * * * * * * * * 4,550 * 4,550ACTUAL(C)* * * * 2,000 * * * * * * * * * 2,000

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    801 HL82ALB Albert Einstein College of MedicineCONS 002 CONSTRUCTION 1,000 0 06/12

    801 HL99AECOM AECOM-DIABETES MOBILE TESTING UNIT & EQUIPMENTEQFN 003 EQUIPMENT AND FURNITURE 1,000 0 06/12

    816 HL99ALEIN ALBERT EINSTEIN COLLEGE OF MEDICINEEQFN 002 EQUIPMENT AND FURNITURE 500 0 06/12EQFN 003 EQUIPMENT AND FURNITURE 2,050 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 405WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN020 FMS #: 816 A01 AMERICAN CANCER SOCIETYAVAILABLE BALANCE AS OF: 11/30/11 $318,720.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $465.20 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $1,180,814.80 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 319 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 319 * 319FORCST(C)* * * * * * * * * * * * 319 * 319ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL99AMCAN AMERICAN CANCER SOCIETY, EASTERN DIVISIONCONS 002 CONSTRUCTION 319 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN023 FMS #: 816 A02 AMERICAN RED CROSS IN GREATER NEW YORKAVAILABLE BALANCE AS OF: 11/30/11 $154,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 154 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 154 * 154FORCST(C)* * * * * * * * * * * * 154 * 154ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL99AMRC AMERICAN RED CROSS IN GREATER NEW YORK - COMMUNICATION EQUIPEQFN 002 EQUIPMENT AND FURNITURE 154 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 406WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN036 FMS #: 816 A05 ASSOCIATION FOR THE ADVANCEMENT OF THE BLIND AND RETARDEDAVAILABLE BALANCE AS OF: 11/30/11 $200,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 200 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 200 * 200FORCST(C)* * * * * * * * * * * * 200 * 200ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL99AABRT ASSOC. FOR THE ADVANCEMENT OF THE BLIND & RETARDEDEQFN 001 EQUIPMENT AND FURNITURE 200 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN041 FMS #: 816 A06 BAILYSTOCKER CENTERAVAILABLE BALANCE AS OF: 11/30/11 $835,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 835 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 835 * 835FORCST(C)* * * * * * * * * * * * 835 * 835ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    850 HL99BIALY BAILYSTOKER CENTER - CAPITAL IMPROVEMENTS FOR EQUIPMENTEQFN 001 EQUIPMENT AND FURNITURE 835 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 407WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN045 FMS #: 816 A07 BEDFORD STUYVESANT FAMILY HEALTH CENTER INCAVAILABLE BALANCE AS OF: 11/30/11 $2,013,790.72 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $1,233,207.46 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $559,237.43 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 2,014 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 2,014 * 2,014FORCST(C)* * * * * * * * * * * * 2,014 * 2,014ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    801 HLBSFHC BEDFORD STUYVESANT FAMILY HEALTH CENTEREQFN 003 EQUIPMENT AND FURNITURE 2,000 0 06/12

    801 HL99BEDFC FA - Construction of Bed-Stuy Family Health Center DSGN 12/04 12/05CONS 010 CONSTRUCTION 14 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN049 FMS #: 816 A08 NYU SCHOOL OF MEDICINEAVAILABLE BALANCE AS OF: 11/30/11 $200,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 200 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 200 * 200FORCST(C)* * * * * * * * * * * * 200 * 200ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL99NYUS2 BELLEVUE - NYU SCHOOL OF MEDICINEEQFN 001 EQUIPMENT AND FURNITURE 200 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 408WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN050 FMS #: 816 A09 BETH ISRAEL MEDICALCENTER- KINGS HIGHWAY DIVISIONAVAILABLE BALANCE AS OF: 11/30/11 $1,069,682.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $1,644,318.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1,070 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1,070 * 1,070FORCST(C)* * * * * * * * * * * * 1,070 * 1,070ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL98BETH BETH ISRAEL KINGS HWY HOSPITAL EQFNEQFN 007 EQUIPMENT AND FURNITURE 250 0 06/12EQFN 008 EQUIPMENT AND FURNITURE 138 0 06/12EQFN 009 EQUIPMENT AND FURNITURE 682 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN084 FMS #: 816 A13 CALLEN-LORDE COMMUNITY HEALTH CENTERAVAILABLE BALANCE AS OF: 11/30/11 $2,274,101.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $56,241.41 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $479,657.59 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 759 * * * * (C)* 2,224 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 2,224 * 2,224FORCST(C)* * * * * * * * * * * * 2,224 * 2,224ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    850 HL82CLORD CALLEN LORDE HEALTH CENTER - VARIOUS EQUIPMENT PROJSTRT 07/08 07/08CONS 008 CONSTRUCTION 2,017 0 06/12

    CO#: BL CONS 008 CONSTRUCTION 207 0 06/12CO#: 02 IFSP 012 IFA CONSTRUCTION SUPERVIS 200 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 409WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN107 FMS #: 816 A16 COBBLE HILL HEALTH CENTERAVAILABLE BALANCE AS OF: 11/30/11 $1,500,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1,493 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1,493 * 1,493FORCST(C)* * * * * * * * * * * * 1,493 * 1,493ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    850 HL99CHHC COBBLE HILL HEALTH CENTER - RENOVATE RESIDENTIAL SENIOR HEALCONS 001 CONSTRUCTION 480 0 06/12EQFN 002 EQUIPMENT AND FURNITURE 263 0 06/12CONS 003 CONSTRUCTION 750 0 06/12IFSP 010 IFA CONSTRUCTION SUPERVIS 7 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN108 FMS #: 816 A17 COLUMBIA UNIVERSITY MEDICAL CENTERAVAILABLE BALANCE AS OF: 11/30/11 $165,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $250,000.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 165 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 165 * 165FORCST(C)* * * * * * * * * * * * 165 * 165ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    801 HL99CUMC COLUMBIA UNIVERSITY Pediatric Dental ClinicEQFN 002 EQUIPMENT AND FURNITURE 165 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 410WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN133 FMS #: 816 A18 DR. BETTY SHABAZZ HEALTH CENTERAVAILABLE BALANCE AS OF: 11/30/11 $1,042,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $40,000.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1,042 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1,042 * 1,042FORCST(C)* * * * * * * * * * * * 1,042 * 1,042ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    850 HL99CHN COMMUNITY HEALTHCARE NETWORK DR. BETTY SHABAZZ HLTH CTR RENV PROJSTRT 02/07 02/07CONS 004 CONSTRUCTION 1,042 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN135 FMS #: 816 A20 EAST HARLEM HEALTH CENTERAVAILABLE BALANCE AS OF: 11/30/11 $75,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 75 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 75 * 75FORCST(C)* * * * * * * * * * * * 75 * 75ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82HRAMP SECURITY SYSTEMS FOR DOHMH HEALTH CENTERS IN HARLEMCONS 004 CONSTRUCTION 75 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 411WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN136 FMS #: 816 A84 EPISCOPAL HEALTH SERVICES INC.AVAILABLE BALANCE AS OF: 11/30/11 $1,612,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1,612 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1,612 * 1,612FORCST(C)* * * * * * * * * * * * 1,612 * 1,612ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82SJONE Saint John Episcopal - EquipmentEQFN 003 EQUIPMENT AND FURNITURE 1,612 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN146 FMS #: 816 A85 NEW ALTERNATIVES FOR CHILDREN (NAC) INC.AVAILABLE BALANCE AS OF: 11/30/11 $46,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 46 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 46 * 46FORCST(C)* * * * * * * * * * * * 46 * 46ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82NACH NEW ALTERNATIVES FOR CHILDRENCONS 001 CONSTRUCTION 46 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 412WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN163 FMS #: 816 A88 SINERGIAAVAILABLE BALANCE AS OF: 11/30/11 $175,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 175 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 175 * 175FORCST(C)* * * * * * * * * * * * 175 * 175ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82SINER SINERGIA- INITIAL OUTFITTINGEQFN 001 EQUIPMENT AND FURNITURE 175 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN164 FMS #: 816 A89 WILLIAM F. RYAN COMMUNITY HEALTH CENTERAVAILABLE BALANCE AS OF: 11/30/11 $290,500.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $487,500.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 82 * * * * (C)* 778 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 778 * 778FORCST(C)* * * * * * * * * * * * 778 * 778ACTUAL(C)* * * * 488 * * * * * * * * * 488

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HLWFRCHC William F. Ryan Community Health CtrEQFN 001 EQUIPMENT AND FURNITURE 82 0 06/12

    816 HL82WFRY WILLIAM RYAN COMMUNITY HEALTH CENTER - INITIAL OUTFITTINGEQFN 001 EQUIPMENT AND FURNITURE 500 0 06/12EQFN 002 EQUIPMENT AND FURNITURE 196 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 413WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN189 FMS #: 816 A25 HOSPITAL FOR SPECIAL SURGERYAVAILABLE BALANCE AS OF: 11/30/11 $4,215,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 629 * * * * (C)* 4,215 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 4,215 * 4,215FORCST(C)* * * * * * * * * * * * 4,215 * 4,215ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HLHSS HOSPITAL FOR SPECIAL SURGERY - X-ray systemsEQFN 001 EQUIPMENT AND FURNITURE 629 0 06/12

    816 HL82HSS1 EQFN FOR THE HOSPITAL OF SPECIAL SURGERY - CC$$EQFN 002 EQUIPMENT AND FURNITURE 310 0 06/12

    816 HL82HSS2 HOSPITAL FOR SPECIAL SURGERYEQFN 001 EQUIPMENT AND FURNITURE 533 0 06/12EQFN 002 EQUIPMENT AND FURNITURE 613 0 06/12

    816 HL98HSS HOSPITAL FOR SPECIAL SURGERY -EQUIPMENTEQFN 002 EQUIPMENT AND FURNITURE 2,130 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 414WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN192 FMS #: 816 A26 INTERFAITH MEDICAL CENTERAVAILABLE BALANCE AS OF: 11/30/11 $500,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 500 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 500 * 500FORCST(C)* * * * * * * * * * * * 500 * 500ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL99IFMC INTERFAITH MEDICAL CENTEREQFN 001 EQUIPMENT AND FURNITURE 250 0 06/12EQFN 003 EQUIPMENT AND FURNITURE 250 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN201 FMS #: 816 A91 NEW YORK BLOOD CENTERAVAILABLE BALANCE AS OF: 11/30/11 $986,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 515 * * * * (C)* 986 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 986 * 986FORCST(C)* * * * * * * * * * * * 986 * 986ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HLNYBC New York Blood Center -Vans and blood drive equipmentEQFN 001 EQUIPMENT AND FURNITURE 515 0 06/12

    816 HL82NYBC NEW YORK BLOOD CENTER- MOBILE MUSEUMEQVH 001 EQUIPMENT - VEHICLES 185 0 06/12EQVH 002 EQUIPMENT - VEHICLES 286 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 415WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN202 FMS #: 816 A27 JAMAICA HOSPITAL MEDICAL CENTERAVAILABLE BALANCE AS OF: 11/30/11 $2,529,085.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $713.50 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $41,201.50 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1,775 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1,775 * 1,775FORCST(C)* * * * * * * * * * * * 1,775 * 1,775ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL99JHMC JAMAICA HOSPITAL MEDICAL CENTEREQFN 005 EQUIPMENT AND FURNITURE 1,775 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN228 FMS #: 816 A28 KINGSBROOK JEWISH MEDICAL CENTERAVAILABLE BALANCE AS OF: 11/30/11 $5,709,021.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $2,972,979.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 1,195 * * * * (C)* 9,436 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 9,436 * 9,436FORCST(C)* * * * * * * * * * * * 9,436 * 9,436ACTUAL(C)* * * * 2,973 * * * * * * * * * 2,973

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82KJMED KINGSBROOK JEWISH MEDICAL CENTEREQFN 001 EQUIPMENT AND FURNITURE 1,700 0 06/12EQFN 002 EQUIPMENT AND FURNITURE 1,691 0 06/12

    816 HL82KNJSW KINGSBROOK JEWISH MEDICAL CENTER: SURGICAL TABLEEQFN 002 EQUIPMENT AND FURNITURE 1,195 0 06/12

    816 HL98KJMC KINGSBROOK JEWISH MED CTR -CAT SCANNEREQFN 002 EQUIPMENT AND FURNITURE 1,850 0 06/12EQFN 004 EQUIPMENT AND FURNITURE 3,000 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 416WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN244 FMS #: 816 A30 LONG ISLAND COLLEGE HOSPITALAVAILABLE BALANCE AS OF: 11/30/11 $400,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 400 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 400 * 400FORCST(C)* * * * * * * * * * * * 400 * 400ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82LICH2 LICH - RADIOLOGY & RADIATION EQUIPMENTEQFN 001 EQUIPMENT AND FURNITURE 400 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN252 FMS #: 816 A31 LUTHERAN MEDICAL CENTERAVAILABLE BALANCE AS OF: 11/30/11 $7,043,604.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $981,396.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 1,400 * * * * (C)* 7,044 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 7,044 * 7,044FORCST(C)* * * * * * * * * * * * 7,044 * 7,044ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HLLUTHR LUTHERAN MEDICAL CENTEREQFN 001 EQUIPMENT AND FURNITURE 1,400 0 06/12

    816 HL82HLLMC Lutheran Medical CenterCONS 001 CONSTRUCTION 1,668 0 06/12CONS 002 CONSTRUCTION 2,000 0 06/12

    816 HL82LUTHR LUTHERAN MEDICAL CENTER - PATIENT MGMT SYSTEM - CC$$EQFN 004 EQUIPMENT AND FURNITURE 219 0 06/12EQFN 005 EQUIPMENT AND FURNITURE 1,757 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 417WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN254 FMS #: 816 A32 MAIMONIDES MEDICAL CENTERAVAILABLE BALANCE AS OF: 11/30/11 $7,151,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $2,650,000.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 850 * * * * (C)* 7,151 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 7,151 * 7,151FORCST(C)* * * * * * * * * * * * 7,151 * 7,151ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82MAIMC MAIMONIDES MEDICAL CENTEREQFN 001 EQUIPMENT AND FURNITURE 1,800 0 06/12

    816 HL82MIDES MAIMONIDES MEDICAL CENTER: PURCHASE 2 AMBULANCESEQFN 002 EQUIPMENT AND FURNITURE 850 0 06/12

    816 HL99MAIMO CONSTRUCT A NEW CANCER CENTER AT MAIMONIDES HOSPITALEQFN 008 EQUIPMENT AND FURNITURE 1,001 0 06/12EQFN 009 EQUIPMENT AND FURNITURE 1,800 0 06/12EQFN 012 EQUIPMENT AND FURNITURE 500 0 06/12EQFN 013 EQUIPMENT AND FURNITURE 1,200 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 418WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN269 FMS #: 816 A34 MORRIS HEIGHTS HEALTH CENTERAVAILABLE BALANCE AS OF: 11/30/11 $2,117,592.36 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $8,650,000.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $503,407.64 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 2,071 * * * * (C)* 2,118 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 2,118 * 2,118FORCST(C)* * * * * * * * * * * * 2,118 * 2,118ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    801 HL82MORR Morris Heights Health CenterCONS 001 CONSTRUCTION 2,071 0 06/12

    801 HL82MORRH FA - Morris Heights Health Facility DSGN 01/04 01/05CONS 008 CONSTRUCTION 47 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN271 FMS #: 816 A35 MOUNT SINAI ADOLESCENT HEALTH CENTERAVAILABLE BALANCE AS OF: 11/30/11 $1,685,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1,685 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1,685 * 1,685FORCST(C)* * * * * * * * * * * * 1,685 * 1,685ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    850 HL82SINAM MOUNT SINAI HOSPITAL - RENOVATIONCONS 001 CONSTRUCTION 1,475 0 06/12

    850 HL82SINDC MOUNT SINAI ADOLESCENT HEALTH CENTEREQFN 001 EQUIPMENT AND FURNITURE 210 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 419WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN273 FMS #: 816 A36 MOUNT SINAI HOSPITAL OF QUEENSAVAILABLE BALANCE AS OF: 11/30/11 $2,998,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 253 * * * * (C)* 2,998 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 2,998 * 2,998FORCST(C)* * * * * * * * * * * * 2,998 * 2,998ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HLMTSIN MOUNT SINAI HOSPITAL,QUEENS CAMPUSEQFN 001 EQUIPMENT AND FURNITURE 253 0 06/12

    816 HL99SINAI MT. SINAI QUEENS HOSPITAL -NEW CANCER CENTEREQFN 004 EQUIPMENT AND FURNITURE 2,745 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN275 FMS #: 816 A92 METROPOLITAN JEWISH HOME CARE, INC.AVAILABLE BALANCE AS OF: 11/30/11 $.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * 237 * * * (C)* * 237 * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * *FORCST(C)* * * * * * * * * * * * *ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82MJHC METROPOLITAN JEWISH HOMECARE INCEQFN 002 EQUIPMENT AND FURNITURE 237 0 06/13

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 420WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN295 FMS #: 816 A38 NEW YORK ACADEMY OF MEDICINEAVAILABLE BALANCE AS OF: 11/30/11 $1,012,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $4,766,305.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 512 * * * * (C)* 1,002 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1,002 * 1,002FORCST(C)* * * * * * * * * * * * 1,002 * 1,002ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    801 HL82MED NY Academy of MedicineCONS WW 001 CONSTRUCTION WINDOWS 512 0 06/12

    850 HL82NYAM3 New York Academy of medecine- BoilerEQFN 001 EQUIPMENT AND FURNITURE 490 0 06/12IFSP 005 IFA CONSTRUCTION SUPERVIS 10 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN299 FMS #: 816 A44 NEW YORK DOWNTOWN HOSPITALAVAILABLE BALANCE AS OF: 11/30/11 $814,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 814 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 814 * 814FORCST(C)* * * * * * * * * * * * 814 * 814ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82NYDW NEW YORK DOWNTOWN HOSPITALEQFN 001 EQUIPMENT AND FURNITURE 235 0 06/12

    816 HL82NYU NYU DOWNTOWN HOSPITAL - EMERGENCY AND CRITICAL CARE EQFNEQFN 013 EQUIPMENT AND FURNITURE 500 0 06/12EQFN 014 EQUIPMENT AND FURNITURE 79 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 421WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN300 FMS #: 816 A40 NEW YORK EYE AND EAR INFIRMARYAVAILABLE BALANCE AS OF: 11/30/11 $1,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1 * 1FORCST(C)* * * * * * * * * * * * 1 * 1ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL99NYEEI NEW YORK EYE & EAR INFIRMARYEQFN 001 EQUIPMENT AND FURNITURE 1 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN305 FMS #: 816 A42 NEW YORK HOSPITAL QUEENSAVAILABLE BALANCE AS OF: 11/30/11 $820,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1,320 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * 500 * * * * 820 * 1,320FORCST(C)* * * * * * * * 500 * * * * 820 * 1,320ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82NYHCQ NEW YORK HOSPITAL MEDICAL CENTER OF QUEENSEQFN 002 EQUIPMENT AND FURNITURE 820 0 06/12

    816 HL99NYHQ NEW YORK HOSPITAL QUEENSEQFN 001 EQUIPMENT AND FURNITURE 500 0 02/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 422WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN308 FMS #: 816 A43 NEW YORK UNIVERSITY COLLEGE OF DENTISTRYAVAILABLE BALANCE AS OF: 11/30/11 $1,285,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $300,000.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 535 * * * * (C)* 1,285 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1,285 * 1,285FORCST(C)* * * * * * * * * * * * 1,285 * 1,285ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HLNYUD NEW YORK UNIVERSITY COLLEGE OF DENTISITRYEQFN 001 EQUIPMENT AND FURNITURE 535 0 06/12

    816 HL98NYUD NYU COLLEGE OF DENTISTRY -DENTAL CLINIC EQEQFN 008 EQUIPMENT AND FURNITURE 750 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN316 FMS #: 816 A45 NEW YORK FAMILIES FOR AUTISTIC CHILDRENAVAILABLE BALANCE AS OF: 11/30/11 $2,265,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $235,000.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 2,250 * * * * (C)* 2,265 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 2,265 * 2,265FORCST(C)* * * * * * * * * * * * 2,265 * 2,265ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    801 HL99AUTSM NY FAMILIES FOR AUTISTIC CHILDRENCONS 004 CONSTRUCTION 2,250 0 06/12CONS 005 CONSTRUCTION 15 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 423WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN324 FMS #: 816 A47 PENINSULA HOSPITAL CENTERAVAILABLE BALANCE AS OF: 11/30/11 $3,723,700.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $551,300.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 3,724 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 3,724 * 3,724FORCST(C)* * * * * * * * * * * * 3,724 * 3,724ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82PENIN PENINSULA HOSPITAL CENTER - REHAB WITH CC$$EQFN 003 EQUIPMENT AND FURNITURE 500 0 06/12EQFN 005 EQUIPMENT AND FURNITURE 2,130 0 06/12EQFN 007 EQUIPMENT AND FURNITURE 249 0 06/12

    816 HL99PENI2 PENINSULA HOSPITAL CENTER - CONSTRUCTION & RELOCATECONS 001 CONSTRUCTION 845 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN328 FMS #: 816 A48 PLANNED PARENTHOOD OF NEW YORK CITYAVAILABLE BALANCE AS OF: 11/30/11 $129,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $4,592.29 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $375,407.71 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 129 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 129 * 129FORCST(C)* * * * * * * * * * * * 129 * 129ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82PPNY2 PLANNED PARENTHOOD OF NYCEQFN 001 EQUIPMENT AND FURNITURE 36 0 06/12EQFN 004 EQUIPMENT AND FURNITURE 93 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 424WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN336 FMS #: 816 B02 PROJECT RENEWALAVAILABLE BALANCE AS OF: 11/30/11 $359,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 359 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 359 * 359FORCST(C)* * * * * * * * * * * * 359 * 359ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82PCRHL PROJECT RENEWALEQFN 001 EQUIPMENT AND FURNITURE 359 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN346 FMS #: 816 A52 RICHMOND UNIVERSITY MEDICAL CENTERAVAILABLE BALANCE AS OF: 11/30/11 $1,544,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $250,000.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $953,000.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1,544 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1,544 * 1,544FORCST(C)* * * * * * * * * * * * 1,544 * 1,544ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82RCHD RICHMOND UNIVERSITY MEDICAL CENTER-ANGIOGRAPHY & CTEQFN 003 EQUIPMENT AND FURNITURE 250 0 06/12EQFN 004 EQUIPMENT AND FURNITURE 458 0 06/12EQFN 005 EQUIPMENT AND FURNITURE 86 0 06/12

    816 HL82RCHU Richmond University Hospital - Purchase Medical EquipmentEQFN 008 EQUIPMENT AND FURNITURE 750 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 425WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN357 FMS #: 816 A53 RUSK INSTITUTE OF REHABILITATION MEDICINEAVAILABLE BALANCE AS OF: 11/30/11 $375,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 375 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 375 * 375FORCST(C)* * * * * * * * * * * * 375 * 375ACTUAL(C)* * * * * * * * * * * * *

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL99NYURI NYU HOSPITAL CENTER - THE RUSK INSTITUTE - EQUIPMENTEQFN 001 EQUIPMENT AND FURNITURE 375 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN359 FMS #: 816 A54 RYAN/CHELSEA-CLINTON COMMUNITY HEALTH CENTERAVAILABLE BALANCE AS OF: 11/30/11 $1,132,094.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $297,906.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1,130 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 1,130 * 1,130FORCST(C)* * * * * * * * * * * * 1,130 * 1,130ACTUAL(C)* * 2-* * * * * * * * * * * 2-

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL98RCCCH RYAN CHELSEA-CLINTON COMM - PURCHASE FULL SERVICE MED VANCO#: 00 EQVH 001 EQUIPMENT - VEHICLES 1,130 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    SOLIMAR SOLASC JL132 NONE

    X::PDF(F)PX(S)MT(MAIN)

  • FY 2012 AUTHORIZED COMMITMENT PLAN PAGE: 426WITH FY 2012 PLAN AND FORECAST AND ACTUALS

    ($ IN THOUSANDS / COMMITMENT TOTALS EXCLUSIVE OF IFA)

    BUDGET LINE: HL-DN363 FMS #: 816 A56 SAINT BARNABAS HOSPITALAVAILABLE BALANCE AS OF: 11/30/11 $1,159,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $500,000.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* * * * * (C)* 1,659 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* 500 * * * * * * * * * * * 1,159 * 1,659FORCST(C)* * * * * * * * * * * * 1,659 * 1,659ACTUAL(C)* 500 * * * * * * * * * * * * 500

    * * * * * * * * * * * * *PLAN (N)* * * * * * * * * * * * *FORCST(N)* * * * * * * * * * * * *ACTUAL(N)* * * * * * * * * * * * *____________________________________________________________________________________________________________________________________

    MGN PROJECT CITY NC PLAN CURRENT MILESTONEAGY ID NO DESCRIPTION COST COST COMM DATE MILESTONE START END____________________________________________________________________________________________________________________________________

    816 HL82SBARN ST. BARNABAS HOSPITAL - PURCHASEEQFN 001 EQUIPMENT AND FURNITURE 159 0 06/12

    816 HL99SBARN ST BARNABAS HOSPITAL DIAGNOSTIC IMAGING SYSTEMEQFN 002 EQUIPMENT AND FURNITURE 500 0 07/11EQVH 003 EQUIPMENT - VEHICLES 1,000 0 06/12

    ------------------------------------------------------------------------------------------------------------------------------------

    BUDGET LINE: HL-DN367 FMS #: 816 A58 ST. MARY'S HEALTHCARE SYSTEM FOR CHILDRENAVAILABLE BALANCE AS OF: 11/30/11 $4,927,000.00 (CITY) $.00 (NON-CITY)CONTRACT LIABILITY: $.00 (CITY) $.00 (NON-CITY)ITD EXPENDITURES: $.00 (CITY) $.00 (NON-CITY)

    * FY 12 * FY 13 * FY 14 * FY 15 * * FY 12 * FY 13 * FY 14 * FY 15 *____________________________________________________________________________________________________________________________________ADOPTED (C)* 2,775 * * * * (C)* 4,927 * * * *APPROPRIATIONS COMMITMENT PLAN

    (N)* * * * * (N)* * * * *____________________________________________________________________________________________________________________________________FY 2012

    JULY AUG SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE FY 12____________________________________________________________________________________________________________________________________PLAN (C)* * * * * * * * * * * * 4,927 * 4,927FORCST(C)* * * * * * * * * * * * 4,927 * 4,927ACTUAL(C)* * * * * * * * * * * * *