Physical Development – Half-yearly Progress Report
For the Period Ended 30th June 2018
This half-yearly report covers the progress of Capital, Alteration, Addition & Improvement (AA&I) and major spatial / interior
enhancement projects delivered by Campus Development Office (CDO) from January to June 2018. The progress of several
special projects with sizable areas and funding, namely the CUHK Medical Centre, six new student hostels under
Government’s Hostel Development Fund, new Teaching–Research Complex in Area 39 for Faculty of Medicine,
Redevelopment of Prince of Wales Hospital by the Hospital Authority and associated CUHK facilities / buildings to be funded
by the Government.
New Capital Projects
(A) UGC Funding (about HK$2,000 mil) (a) For the new capital project of Jockey Club Postgraduate Halls 2 & 3 – Superstructure of both towers was topped
out in January 2018, followed by the internal partitioning, finishes and M/E works carried out in full swing.
Statutory inspections by Building Authority and Fire Services Department had been commenced in 2nd Quarter
2018. The project was targeted for completion in 4th Quarter 2018; in parallel, some existing facilities have been
deployed to accommodate student intake in August 2018. (b) With the approval by the Development Bureau on the revised Technical Feasibility Statement of the Centralized
General Research Laboratory Complex (Block 2) in Area 39, detailed design was resumed for the proposed
expanded scope (to build the originally phased future expansion in one go) and adjustment of the site location as
per Education Bureau’s direction. Consultancy fee adjustment for expanded scope was supported by UGC in June
2018. Submission to CWRAE for B+ selection and construction funding approval would be in 2019/20 the
earliest with tentative completion in 2023/24. Regular meetings with consultant were held and the Building
Committee was re-activated to oversee the project design, budget and progress.
(B) UGC Hostel Development Fund (HDF) (about HK$1,800 mil) Hostel Development Fund proposal was announced by the Chief Executive in 2017 Policy Address to expedite student
hostel development. After close co-ordination with the UGC regarding the shortfall and entitlement of new hostel
places, a Master Hostel Development Plan (MHDP) for the University was developed with the Management and
stakeholders for submission. Under the MHDP, proposed hostels and sites, special site constraints and construction
programme etc. were submitted to UGC in June 2018 for vetting and processing. Subsequently, the Finance
Committee of the Legislative Council has endorsed the HDF paper to support the new funding arrangement for meeting
the hostel shortfalls and the proposed hostel projects. Meanwhile, close liaison was also made with UGC to finalize
the details of Service Agreement of the new HDF Scheme; the granting of the funding was targeted in early 2019. The six student hostel projects supported by UGC to be completed in phases in the following eight years were: (a) 300-place Student Hostel at New Asia Campus
(b) 250-place Student Hostel at United Campus
(c) 300-place Student Hostel at Shaw Campus
(d) 300-place Student Hostel at Chung Chi Campus
(e) 250-place Student Hostel at Wu Yee Sun Campus
(f) 394-place Student Hostel in Area 39
(C) Government Funding - Food and Health Bureau (FHB) (about HK$7,900 mil) (a) With FHB’s support, planning for a new Teaching–Research Complex in Area 39 for Faculty of Medicine was in
progress. Master planning, schematic layout, programme and preliminary budget were being studied. To apply
funding for the engagement of consultants to carry out the Detailed Design, Draft Technical Feasibility Studies
(TFS) was under preparation for circulation to all relevant Government Departments for their comments/
endorsement. FHB also clarified that those areas to support the needy expansion of medical and nurse training
would not be accountable under the UGC space inventory. (b) Regarding the Redevelopment of Prince of Wales Hospital (PWH) and the re-provision of associated University
facilities by Hospital Authority (HA), Schedule of Accommodation for University space in PWH was worked out
by Faculty of Medicine and submitted to HA for their incorporation. In addition, scheme design proposals for the
Faculty’s proposed new developments in the PWH Campus was under study for HA and FHB’s consideration.
香 港 中 文 大 學
校 園 發 展 處
THE CHINESE UNIVERSITY OF HONG KONG
Campus Development Office
P. 2 of 17
Physical Development – Half-yearly Progress Report
For the Period Ended 30th June 2018
New Capital Projects (cont’d)
(D) Private Funding (a) For the privately-funded CUHK Medical Centre (CUHKMC), good progress was registered during the report
period. After the execution of the lease modification and award of the Design and Construction Contract in late
2016, piling works for the building was completed in June 2017. The Project Management Team was working
closely with the Contractor and users for design development / approval and construction supervision.
Superstructure works was in steady progress and topping out was targeted by end 2018. Completion was
scheduled in phases starting from 1st Quarter 2020.
(b) For the privately-funded Redevelopment of Block D & G to Staff Quarters and Student Community Complex in
Chung Chi Campus, detailed design was underway. Antiquities and Monuments Office (AMO) had assessed
the Block D & G to be ‘Nil’ grading. Hoarding works was under preparation to facilitate the commencement of
demolition works in late 2018. Upon the approval of the General Building Plan by the Building Authority,
drawings and specifications for the main–superstructure contract were being prepared for tender calling in
November 2018. Project completion was scheduled in 3rd Quarter 2021.
Alteration, Addition and Improvement (AA&I) Projects and Urgent Works (about HK$277 mil)
Sizable funding has also been secured on an annual basis for the delivery of Alteration, Addition and Improvement (AA&I)
and urgent works, the progress was summarized as follows:
(A) HK$57.8 mil was secured under UGC’s Block Allocation 2016/17 in March 2016 for the following proposals to address
the University’s needs of the animal facilities for teaching and research activities and initiatives on sustainability works:
Upgrading and Improvement Works of Shanghai Fraternity Association Research Services Centre (addition of
one storey to the existing annex). Site works were in steady progress. The new roof extension work was
scheduled to be completed by end 2018 while the upgrading works for existing floors would be completed by 1st
Quarter 2019.
Various works contracts for upgrading of air-conditioning, roof greening, lifts replacement and slope safety
works were at construction stage.
(B) HK$72.0 mil was secured under UGC’s Block Allocation 2017/18 in March 2017 to address the University’s new
initiatives and users’ needs in research laboratory space and sports facilities. User committees have been set up to
monitor the project design and implementation:
Extension to Roof of Mong Man Wai Building and 1/F of William M.W. Mong Engineering Building to create
new laboratory space for teaching and research activities – Consultancy services was awarded. Detailed design
was in progress.
Extension to University Sports Centre and associated external works to create new space for sports facilities -
Consultancy services was awarded. Detailed design was in progress.
Track Improvement Works at the Sir Philip Haddon-Cave Sports Centre enhancing and upgrading of the sports
track facilities – Works commenced in April 2018. Completion date was rescheduled to 3rd Quarter 2018 due to
the inclement weather.
(C) HK$57.4 mil was secured under UGC’s Block Allocation 2018/19 in March 2018 to address the University’s needs of
upgrading the IT infrastructure facilities and users’ imminent needs in research laboratory space:
Upgrading of Information Technology Infrastructure for Next Generation Campus Network – Outline design was
completed. Detailed design work was in progress.
Provisions of New Laboratory Space –
(i) Spatial Reorganisation of 5/F Mong Man Wai Building and Lady Shaw Building – Detailed design for the
new office / workshop on 2LG of Lady Shaw Building was underway.
(ii) Extension on 2/F of Ho Sin-Hang Engineering Building - Tender for consultancy services were underway.
(D) Feasibility studies have been carried out by CDO together with the University stakeholders and management, and a new
round of proposals (of about HK$180 mil) was submitted to the UGC in May 2018 to bid for the UGC AA&I Block
Allocation 2019/20. These proposals in their order of priority included :
(1) Space Addition and Re-organization at G/F of Lady Shaw Building for office / teaching laboratory;
(2) Infrastructure and Safety Enhancement Works (a) Stabilization Works for Slope behind University Residence No. 16
& No. 17; and (b) Construction of New Dangerous Goods Stores for teaching and research activities;
(3) Accessibility Improvement Works for Barrier Free Access (i) Replacement of Lift at Chan Chun Ha Hall and
Inter-University Hall, (ii) New Lifts at Adam Schall Residence; and (iii) Improvement Works to Lift Lobby at
Elisabeth Luce Moore Library;
P. 3 of 17
Physical Development – Half-yearly Progress Report
For the Period Ended 30th June 2018
Alteration, Addition and Improvement (AA&I) Projects and Urgent Works (cont’d)
(D) (4) Bus Stop Shelter at Sir Run Run Shaw Hall and C.W. Chu College;
(5) Spatial Re-organization and Improvement Works at University MTR Station Piazza;
(6) Spatial Re-organization and Laboratory Conversion Works for 3/F & 4/F of Mong Man Wai Building; and
(7) Additional projects under 2018-19 Block Allocation: Spatial Re-organization and Improvement Works for
Dissecting Laboratories on LG/F of Choh-Ming Li Basic Medical Sciences Building.
UGC visited the campus in May 2018 to review the proposed items and detailed project estimates were submitted for
UGC/ArchSD’s vetting. The outcome of the proposed projects under Block Allocation under 2018/19 and 2019/20
would be known around September 2018 and March 2019 respectively.
Miscellaneous Studies and Works
During the report period, about HK$23 mil of spatial reorganization / interior fitting-out / minor works were completed by
CDO to accommodate the University’s amenities, teaching and learning initiatives; these included e.g. Alumni Corner at John
Fulton Centre, various off campus learning centres for School of Continuing and Professional Studies, laboratory renovation
works at Hong Kong Institute of Biotechnology, Lady Shaw Building & Prince of Wales Hospital, etc. About HK$118 mil of
works were also under construction on campus as well as in Prince of Wales Hospital including new Academic Conference
Centre at Cheng Yu Tung Building, spatial re-organisation works at Wu Chung Multi-media Library and Elisabeth Luce
Moore Library, I-House 1 & 2 and laboratory conversion / renovation works at various buildings on campus and PWH etc.
Feasibility studies were also conducted continuously by CDO in relation to space conversion / addition / renovation etc.; new
initiatives included e.g. laboratory renovation works for Department of Biomedical Engineering, conversion work of
Inter-University Hall to InnoHub, spatial reorganization works for Guest House facilities, interactive classrooms in various
academic buildings and possible development collaborations with The Hong Kong Science Park, etc.
UGC was preparing to revisit the formulae and standards for arriving at the space requirements of UGC-funded Universities.
Close collaborations with UGC’s consultant was commenced in March 2018 to carry out the first stage of review, including
e.g. exchange of views on the study, collection and update of space inventories, on-site space audit and utilization survey etc.
Meanwhile, room / area data and layouts were uploaded regularly to the University’s new on-line Space Inventory Updating
System to maintain an updated space inventory for management information and improving the efficiency of building
utilizations.
Description January February March
Cumulative Total for the Fiscal Year
2017-18
Cumulative Total for the Fiscal Years
2016-17/2015-16
Expenditures on Capital and AA&I Works, inclusive of private funds
$40.952m $32.836m $36.827m $339.377m $120.720m/$76.709m
Expenditures on Minor Works (supported by Minor Works vote, Hostel Funds and others)
$7.553m $2.382m $5.754m $126.616m $91.010m/$60.612m
Description April May June
Cumulative Total for the Fiscal Year
2018-19
Cumulative Total for the Fiscal Years
2017-18/2016-17
Expenditures on Capital and AA&I Works, inclusive of private funds
$45.177m $48.997m $37.664m $131.838m $57.670m/$22.223m
Expenditures on Minor Works (supported by Minor Works vote, Hostel Funds and others)
$6.410m $3.832m $4.703m $14.495m $37.280m/$20.741m
Note: Fiscal year - 1st April 2018 to 31st March 2019
Report Period - 1st January 2018 to 30th June 2018
P. 4 of 17
Physical Development – Half-yearly Progress Report
For the Period Ended 30th June 2018
Section Content Page
I. MAJOR CAPITAL PROGRAMME ON UGC FUNDING 6 - 7
1. Jockey Club Postgraduate Halls 2 & 3
(previously named 2x338-place Student Hostels (Block A3 & A4) on Northern Campus)
2. New Student Hostels under Hostel Development Fund (HDF)
(a) 300-place Student Hostel at New Asia Campus
(b) 250-place Student Hostel at United Campus
(c) 300-place Student Hostel at Shaw Campus
(d) 300-place Student Hostel at Chung Chi Campus
(e) 250-place Student Hostel at Wu Yee Sun Campus
(f) 394-place Student Hostel in Area 39
3. Centralised General Research Lab Complex Block 2 in Area 39
4. Final Accounts of 3+3+4 Capital and New College Project
II. AA&I WORKS ON UGC BLOCK ALLOCATION 8 - 11
A. 2018-2019 Block Allocation
1. Upgrading of Information Technology Infrastructure for Next Generation Campus Network
2. Provisions of New Laboratory Space –
(a) Spatial Reorganisation of 5/F Mong Man Wai Building and Lady Shaw Building
(b) Extension on 2/F of Ho Sin-Hang Engineering Building
B. 2017-2018 Block Allocation
1. Extension on roof of Mong Man Wai Building and 1/F of William M.W. Mong Engineering
Building for new laboratory space
2. Extension of University Sports Centre
3. Track improvement works at Sir Philip Haddon-Cave Sports Field
C. 2016-2017 Block Allocation
1. Upgrading and Improvement Works of Shanghai Fraternity Association Research Services
Centre
2. Energy Saving and Safety Enhancement Works on Campus
D. 2015-16 Block Allocation
1. Spatial Re-organization and Improvement Works for Sui Loong Pao Building
2. Spatial Re-organization and Improvement Works for Academic Building No. 1
3. Upgrading of Central Air Conditioning Plants in Seven Buildings including Esther Lee Building, Mong Man Wai Building and University Sports Centre
III. OTHER CAPITAL PROJECTS AND AA&I WORKS 12 - 13
1. CUHK Medical Centre
2. Teaching-Research Complex in Area 39
3. Redevelopment of Prince of Wales Hospital and Associated University Facilities in Prince of
Wales Hospital by Hospital Authority
4. Block D&G at Chung Chi College
5. Lee Shu Pui Hall at Chung Chi College
6. (a)
(b)
2x300-place Student Hostel at Wu Yee Sun College
300-place Student Hostel at C.W. Chu College
7. Other Minor Projects Being or Having Been Put Forth to the UGC for
AA&I Funding Consideration
IV. MINOR WORKS 14 - 17
Appendix – Selected Projects Images
P. 5 of 17
Physical Development – Half-yearly Progress Report
For the Period Ended 30th June 2018
Key Legend:
P: Project: M: Amount of Contract/Sub-contract:
AP Authorized Person $A Air-conditioning Installation
PA Project Architect/Architectural Consultant $AV Audio-visual System
PB Building Services Consultant $C Construction Works
PD Project Designer $E Electrical Installation
PG Geotechnical Consultant $F Fire Services Installation
PLA Landscape Architect $F&E Major Equipment Installation
PM Project Manager $FO Fitting-out Works
PQ Quantity Surveyor/Building Surveyor $L Lifts Installation
PS Structural Consultant $LF Laboratory Furniture Installation
TBA To be Appointed $M Building Construction / Main Contract Works
$R Foundation / Sub-structure
$S Site Investigation/Slopes/External Works
$T Telephone System
C: Contract/Sub-contract:
CA Air-conditioning Installation
CAV Audio-visual System
CD&B Design & Build D: Date:
CE Electrical Installation D/AIP Date accorded AIP
CF Fire Services Installation D/C Date for Commencement
CF&E Furniture & Equipment Installation DC/E Date for Completion with Anticipated EOT
CFO Fitting-out Works D/FA Date accorded Full Approval
CL Lifts Installation D/PC Date of Practical Completion
CLF Laboratory Furniture Installation D/TC Date for Targeted Completion
CM Building Main Contractor
CR Substructural
CS Site Investigation/Slopes/External Works
CT Telephone System
GI Ground Investigation
TS Topographic Survey
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 6 of 17
I. Major Capital Programme on UGC Funding:
Project Title
Percentage
of Works
Completed
Description
Jun
I. 1. Jockey Club Postgraduate Halls 2 & 3
(previously named 2x338-place Student Hostels
(Block A3 & A4) on Northern Campus)
PM – Stephen Ho AP/PA – Andrew Lee King Fun & Associates Architects Ltd. PS/PG – Meinhardt (C&S) Ltd. PLA – ACLA Ltd. PB – Parsons Brinckerhoff (Asia) Ltd. PQ – Rider Levett Bucknall Ltd. CM – Chinney Construction Co. Ltd. D/FA – July 2015 D/C – November 2016 (CM) D/TC – 4th Quarter 2018
(a) Outline Proposal / Schematic Design 100% Foundation work was completed in November 2016 and
preparation of final account is in progress.
Superstructure of blocks topped out in January 2018. Main
contract work commenced on 30 November 2016 and
statutory inspection by WSD, FSD, and BD were in progress.
Regular site progress meetings were conducted to review the
materials and equipment submissions, site coordination
works.
(b) Detailed Design 100%
(c) Tendering 100%
(d)
(e)
Foundation Works
Site Works
100%
91%
Nominated sub-contract for lift installation was awarded and
work was substantially completed.
Direct contract for FF&E were awarded and work in progress.
I. 2.
New Student Hostels under Hostel Development Fund
(HDF)
(a) 300-place Student Hostel at New Asia Campus PM – Stephen Leung
PA – Spence Robinson Ltd.
PQ – K.C. Tang Consultants Ltd.
D/FA – May 2015
D/C – January 2019
D/TC – 2nd Quarter 2022
(i) Outline Proposal / Schematic Design
(ii) Detailed Design
100%
95%
Detailed design was mostly completed and the tender
documentation was under preparation.
This project is now under Government’s Hostel Development
Fund to expedite the design and construction progress.
(b) 250-place Student Hostel at United Campus
(c) 300-place Student Hostel at Shaw Campus
(d) 300-place Student Hostel at Chung Chi
Campus
Undergoing planning and preliminary design
(e) 250-place Student Hostel at Wu Yee Sun
Campus
(f) 394-place Student Hostel in Area 39
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 7 of 17
I. Major Capital Programme on UGC Funding (cont’d):
Project Title
Percentage
of Works
Completed
Description
Jun
I. 3. Centralized General Research Laboratories Complex
(Block 2) in Area 39
PM – S.C. Li / Thomas Yuen AP/PA – Andrew Lee King Fun & Associates Architects Ltd. PS/PG – Meinhardt (C&S) Ltd. PLA – Urbis Ltd. PB – WSP Hong Kong Ltd. PQ – Rider Levett Bucknall Ltd.
D/FA – September 2017
D/C – May 2020
D/TC – July 2023
Technical feasibility of extending the scope for a larger lab
building with more net operational floor area and better
utilization of land resources without going into phase
development was made, and revised Project Definition
Statement (PDS) / Technical Feasibility Statement (TFS) for
the expanded scope was submitted in September 2013. The
proposed Lab Block 2 location was also adjusted in response
to UGC / Education Bureau’s comment conveyed in the
process of their project vetting. A revised TFS for the
relocated scope was submitted in December 2014.
The revised TFS was approved by the Development Bureau in
September 2017. The Government has re-selected this
project under the 2017 CWRAE to Category B- for the
expanded and relocated version. Detailed design was
resumed accordingly after the adjustment of consultancy fee
was supported by UGC in June, 2018.
Regular design meeting with the Consultant was held and new
Building Committee was formed to oversee the project and
formulate the users’ requirements.
I. 4. Final Accounts of 3+3+4 Capital and New College
Projects
(a) Centralized General Research Laboratories
Complex (Block 1) at Area 39
Assessment of bills of variations and preparation of final
account of works contracts for project close out with the UGC
were in progress. The project final accounts are anticipated
to be completed progressively.
(b) 1,500-place Student Hostels
Site A: Morningside College & S.H. Ho College
Site B: Lee Woo Sing College
(c) Extension to Existing University Library 100%
(d) Student Amenity Centre
(e) An Integrated Teaching Building
(f) Two-Integrated Teaching Buildings
- Yasumoto International Academic Park (YIA)
- Wu Ho Man Yuen Building (WMY)
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 8 of 17
II. AA&I Works on UGC Block Allocation:
A) 2018-19 Block Allocation
Project Title
Percentage
of Works
Completed
Description
Jun
II.A.1. Upgrading of Information Technology Infrastructure
for Next Generation Campus Network
(Approved Project Estimate: HK$30 Mil)
D/FA – March 2018
D/C – March 2019
D/TC – December 2020
(a)
(b)
Outline Proposal / Schematic Design
Detailed design
100%
40%
Schematic design for the information technology
infrastructure was completed. Detailed design was
underway. The site works was scheduled to commence in
1st Quarter 2019.
II.A.2.
Provisions of New Laboratory Space
(Approved Project Estimate: HK$27Mil)
(a)
Spatial Reorganisation of 5/F Mong Man Wai
Building and Lady Shaw Building
PM – Mabel Lam
D/FA – March 2018
D/C – September 2018
D/TC – December 2020
i) Outline Proposal / Schematic Design
ii) Detailed Design
50%
40%
Detailed design for the new office / workshop at Lady Shaw
Building was underway. Tender would be issued in July
2018 for works commencement in September 2018.
(b) Extension on 2/F of Ho Sin-Hang Engineering
Building
PM – Becky Luk
D/FA – March 2018
D/C – March 2019
D/TC – December 2020
i) Consultancy Appointment 50%
Tender for consultancy services was under preparation for
appointment of consultant to commence detailed design.
B) 2017-18 Block Allocation
II.B.1. (a) Extension on roof of Mong Man Wai Building
for New laboratory space
(Approved Project Estimate: HK$27Mil) PM – Thomas Yuen D/FA – March 2017 D/C – January 2019 D/TC – December 2019
i) Consultancy Appointment
ii) Outline Proposal / Schematic Design
iii) Statutory Submission
100% 50% 20%
General building plans submission was approved by
Buildings Department. User Committee was formed and the
Lead Architectural Consultant was appointed in January
2018. Updated general building plans and structural plans
submissions were under preparation.
(b) Extension on 1/F of William M.W. Mong
Engineering Building for new laboratory space
PM – Thomas Yuen
D/FA – March 2017
D/C – January 2019
D/TC – December 2019
i) Consultancy Appointment
ii) Outline Proposal / Schematic Design
iii) Statutory Submission
iv) Detailed Design
100%
80%
50%
20%
General building plans submission was approved by
Buildings Department. User Committee was formed and the
Lead Architectural Consultant was appointed in January
2018. Updated general building plans and structural plans
were under preparation.
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 9 of 17
II. AA&I Works on UGC Block Allocation:
B) 2017-18 Block Allocation (cont’d)
Project Title
Percentage
of Works
Completed
Description
Jun
II.B.2. Extension of University Sports Centre (Approved Project Estimate: HK$30Mil)
PM – Thomas Yuen D/FA – March 2017 D/C – January 2019 D/TC – August 2020
(a)
(b)
(c)
Consultancy Appointment
Outline Proposal / Schematic Design
Statutory Submission
100% 80% 20%
User Committee was formed and the Lead Architectural
Consultant was appointed in January 2018. Schematic
design and general plans submissions were under preparation.
II.B.3. Track Improvement Works at Sir Hadden-Cave
Sports Field (Approved Project Estimate: HK$12Mil)
D/FA – March 2017 D/C – January 2018 D/TC – October 2018
(a)
(b)
(c)
Detailed Design
Tendering
Site Work
100% 100% 85%
Detailed design was completed. Works were commenced in
April 2018. Completion was rescheduled to October 2018
due to inclement weather.
C) 2016-17 Block Allocation
II.C.1.
Upgrading and improvement works of Shanghai
Fraternity Association Research Services Centre
(Approved Project Estimate: HK$30Mil)
PM – S.C. Li / Thomas Yuen
AP/PA – Compass Studio Ltd. PS – K.C. Wong & Associates Ltd. PB – Thomas Anderson & Partners Consulting Engineers Ltd. PQ – Beria Consultants Ltd. CM – Wah Cheong Construction Co. Ltd.
D/FA – March 2016
D/C – February 2018
D/TC – End 2018 for Phase I; March 2019 for Phase II
(a) Consultancy Appointment 100% User Committee was formed to collect the users’ requirement
for the design planning and development. Detailed design
was completed and Main Contract was awarded in December
2017 for works commencement. Phase I works were
scheduled to be completed by end 2018 while Phase II works
would be completed by March 2019.
(b) Outline Proposal / Schematic Design 100%
(c) Detailed Design 100%
(d) Tendering 100%
(e)
Construction for Phase 1 80%
II.C.2.
Energy Saving and Safety Enhancement Works on
Campus
(Approved Project Estimate: HK$27.8Mil)
PM – Boris Lau
(a) Upgrading of Central Air-conditioning Plants for
High Efficiency Water Cooled Chillers at
University Science Centre (SC)
Centralized Optimization System for Central
Chiller Plant at Run Run Shaw Science
Building (RRSSB)
PB – PKL Consultants Ltd.
PS – CT & Associates (HK) Ltd.
CA – Krueger Engineering (Asia) Ltd.
D/FA – March 2016
D/C – December 2016
D/TC – 4th Quarter 2018
i) Consultancy Appointment 100% As scheduled, the site work was commenced in February
2018. 2 out of 3 existing chillers in SC were replaced by
high efficiency type. Prior to replacement of the remaining
chiller, two weeks trial run period was allowed to ensure
stability and reliability of the new chillers. The whole
replacement and upgrading works for SC are expected to be
substantially completed in August 2018. Upgrading of the
centralized system for RRSSB was carried out in parallel and
is expected to be completed by October 2018.
ii) Detailed Design 100%
iii) Tendering 100%
iv) Site Works 75%
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 10 of 17
II. AA&I Works on UGC Block Allocation:
C) 2016-17 Block Allocation (cont’d)
Project Title
Percentage
of Works
Completed
Description
Jun
II.C.2. Energy Saving and Safety Enhancement Works on
Campus (cont’d)
(b) Roof greening for Carbon Recovery and
Accessibility Improvement works at various
Buildings on Campus
PM – Stephen Ho
i) Consultancy Appointment 100% Lead Landscape Consultant was appointed to carry out
detailed design. Tender award for the proposed green roof
at 3/F Choh-Ming Li Basic Medical Sciences Building would
be by September 2018 with targeted completion by January
2019.
ii)
iii)
iv)
Detailed Design
Tendering
Site Work
20%
40%
0%
(c)
(d)
Replacement of lifts for Barrier Free Access at
Leung Kau Kui Building, John Fulton Centre,
Ch’ien Mu Library
i) Detailed Design
ii) Tendering
iii) Construction C
Safety Enhancement for Slope Inspection and
Maintenance
i) Consultancy Appointment
ii) Detailed Design
100%
100%
100%
100%
60%
Works were completed in December 2017.
PS – Wong & Cheng Consulting Engineers Ltd.
Statutory submission for railing and maintenance access for
slope was submitted to Buildings Department for approval.
Detailed design are underway.
D) 2015-16 Block Allocation
II.D.1.
Spatial Re-organization and Improvement Works for Sui Loong Pao Building (Approved Project Estimate: HK$30Mil)
PM – Stephen Ho AP/PA – Meta4 Design Forum Ltd. PS – Paul Wong Consulting Engineers Ltd. PB – Far East Consulting Engineers Ltd. PQ – Beria Consultants Ltd. CM – PacificPlan Interiors Ltd.
D/FA – March 2015 D/C – June 2016 D/TC – January 2018
(a) Consultancy Appointment 100% Spatial re-organization and improvement works were
completed and handed over to users starting from October
2017 with Indoor Air Quality of excellent class and
BeamPlus Interior Assessment of Platinum rating. Final
account was in progress.
(b) Detailed Design 100% (c) Tendering 100% (d) Site Works 100%
II.D.2. Spatial Re-organization and Improvement Works for Academic Building No. 1 (Approved Project Estimate: HK$30Mil)
PM – Mabel Lam
AP/PA – Seniorman Design Ltd. PS – Wong Cheng Consulting Engineers Ltd. PB – PKL Consultants Ltd. PQ – TLS & Associates Ltd.
CM – Evergreen Engineering & Construction Co. Ltd. D/FA – March 2015 D/C – June 2016 D/TC – 4th Quarter 2018
(a) Consultancy Appointment 100% Construction works would be completed by end of September
2018.
FSD inspection is scheduled in September 2018 and OP
inspection will be carried out in October 2018 accordingly.
(b) Detailed Design 100% (c) Tendering 100% (d) Site Works 90%
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 11 of 17
II. AA&I Works on UGC Block Allocation:
D) 2015-16 Block Allocation (cont’d)
Project Title
Percentage
of Works
Completed
Description
Jun II.D.3. Upgrading of Central Air Conditioning Plants in
Seven Buildings (Approved Project Estimate: HK$30Mil) - Esther Lee Building (ELB) - Mong Man Wai Building (MMW) - University Sports Centre (USC) - William M.W. Mong Engineering Building - Ho Sin-Hang Engineering Building
PM – Boris Lau PB – PKL Consultants Ltd. PS – CT & Associates (HK) Ltd. CA – Shun Hing E&M Engineering Ltd. D/FA – March 2015 D/C – December 2015 D/TC – 3rd Quarter 2018
- Choh-Ming Li Basic Medical Sciences Building - Lady Shaw Building
(a) (b) (c) (d)
Consultancy Appointment Detailed Design Tendering Site Works
100% 100% 100% 90%
Upgrading of chiller plant for USC was completed and put into operation on time to meet the vacancy schedule in summer 2016. Report completion to the government authorities were conducted and approvals obtained.
All site works for ELB were completed and the new plant was put into full operation in August 2017. Report completion to the government authorities were in progress.
Revised working details for MMW were confirmed to suit the site constrains and difficulties. The contractor/ consultant were asked to make amendment submission to BD for approval and site works will be carried out accordingly. The upgrading control and monitoring works for other remaining buildings were completed.
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 12 of 17
III. Other Capital Projects and Major Alterations, Additions and Improvement (AA&I) Works:
(on private funds or seeking UGC’s support)
Project Title
Percentage
of Works
Completed
Description
Jun
III. 1. CUHK Medical Centre
(previously named Private Teaching Hospital)
Managed and executed by the CUHKMC Ltd. and CUHKMC
Planning Office. PQ – Rider Levett Bucknall Ltd. (RLB) Project Management – Ove Arup & Partners Hong Kong Ltd.
(OAP)
D&B Contractor – China State Construction Engineering
(Hong Kong) Ltd. (CSC)
D/C – 1st Quarter 2014 D/TC – 1st Quarter 2020
(a)
(b)
(c)
(d)
(e)
Lease Modification
Consultancy Appointment
Brief
Tendering
Construction
100%
100%
100%
100%
40%
Superstructure works were in steady progress targeting for
completion in December 2018.
Completion was scheduled in phases starting from 1st Quarter
2020.
III. 2. New Teaching–Research Complex in Area 39 Planning for a new Teaching–Research Complex in Area 39
for Faculty of Medicine was in progress. Master planning,
schematic layout, programming and project cost estimate was
being prepared and studied. Draft Technical Feasibility
Studies was under preparation and would be circulated to
relevant Government Departments for their comments.
III. 3. Redevelopment of Prince of Wales Hospital (PWH)
and the associated University Facilities in Prince of
Wales Hospital by Hospital Authority (HA)
Schedule of Accommodation for University space in the HA’s
area were worked out by Faculty of Medicine and was
submitted to HA for their planning and design. In addition,
various scheme proposals for the University’s new
development in PWH Campus was under study and
preparation for HA’s consideration.
III. 4.
Redevelopment of Block D&G for Chung Chi College
PM – Stephen Leung
PA – Leigh & Orange Ltd.
PQ – K.C. Tang Consultants Ltd.
D/FA – October 2017
D/C - March 2018
D/TC – 3rd Quarter 2021
(a) Consultancy Appointment (Feasibility Stage) 100% Planning and detailed design for redevelopment of Block D
and G to staff quarters and student community complex was
underway. General Building Plan was approved by Buildings
Department.
Antiquities and Monuments Office (AMO) has assessed
Block D and G to a ‘Nil’ grading. Demolition contract was
awarded in April 2018 for commencement of hoarding works.
(b) Feasibility Study 100%
(c) Detailed Design 30%
III. 5. Renovation of Lee Shu Pui Hall for Chung Chi College
(a) Detailed Design
(b) Tendering
(c) Site work
100%
100%
100%
PM – Stephen Leung
PA – Arch Design Architects Ltd.
PQ – Currie & Brown (China) Ltd.
CM – YBL Ltd.
D/FA – April 2017
D/C – May 2017
D/TC – September 2017
Outstanding work of fence wall in laundry area was
completed in March 2018. Final account was under
preparation.
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 13 of 17
III. Other Capital Projects and Major Alterations, Additions and Improvement (AA&I) Works: (cont’d)
(on private funds or seeking UGC’s support)
Project Title
Percentage
of Works
Completed
Description
Jun
III. 6. (a) 2x300-place Student Hostel at Wu Yee Sun
College
100% (a) The final account was completed and signed by the
contractor.
(b) 300-place Student Hostel at C.W. Chu College 100% (b) Final account was assessed and agreed amongst the
project team and contractor.
III. 7. Other Minor Projects Being or Having Been Put
Forth to the UGC for AA&I Funding Consideration
Projects submitted to UGC for consideration in
May 2018 under 2019/2020 Block Allocation
(1)
Space Addition and Re-organization at G/F of Lady
Shaw Building for Office / Teaching Laboratory
(Estimated Cost: HK$30Mil)
(2) Infrastructure and Safety Enhancement Works
a) Stabilization Works for Slope behind University
Residence No. 16 & No. 17 (7NE-C/C65 and
Adjacent Natural Terrain)
b) Construction of New Dangerous Goods Stores for
Compressed Gases on Campus
(Estimated Cost: HK$30Mil)
(3) Accessibility Improvement Works for Barrier Free Access
a) Replacement of Lift at Chan Chun Ha Hall and
Inter-University Hall
b) New Lifts at Adam Schall Residence
c) Improvement Works to Lift Lobby at Elisabeth Luce
Moore Library
(Estimate Cost : HK$20Mil)
(4) Bus Stop Shelter at Sir Run Run Shaw Hall and C.W. Chu
College
(Estimated Cost: HK$12Mil)
(5) Spatial Re-organisation and Improvement Works at
University MTR Station Piazza
(Estimated Cost: HK$30Mil)
(6) Spatial Re-organization and Laboratory Conversion
Works for 3/F & 4/F of Mong Man Wai Building
(Estimated Cost: HK$30Mil)
Additional Project under 2018-19 Block Allocation
(7) Spatial Re-organization and Improvement Works for
Dissecting Laboratories on LG/F of Choh-Ming Li Basic
Medical Sciences Building
(Estimated Cost: HK$30Mil)
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 14 of 17
IV. Minor Works: (Jan – Jun 2018)
A. The following minor works have been completed during the period of report: (Project Cost: HK$23Mil)
(1) Fitting Out Work at Room 601, 6/F, Tin Ka Ping Building for University Archives of University Library
(2) Renovation Works for Rooms 313-318, 3/F, Pi Chiu Building for Internal Audit Office
(3) Fitting Out Works at Room G22, G/F, Lady Shaw Building for Department of Statistics
(4) Renovation of Room 138 & 144, 1/F, Lady Shaw Building for Department of Biomedical Engineering
(5) Renovation Work of Alumni Corner at Room G01, G/F, John Fulton Centre for Alumni Affairs Office
(6) Design and Build Feature Wall at G/F of Run Run Shaw Science Building
(7) Fitting Out Works to Rooms 538 & 539, 5/F, Sino Building for Faculty of Social Science
(8) Improvement of Acoustic Door at Room 1206A, 12/F, Yasumoto International Academic Park for Office of
Admissions and Financial Aid
(9) Renovation Works at Rooms 234, 236, 238 & 240, 2/F, Hong Kong Institute of Biotechnology for joint
inter-faculty translational biomedicine laboratory
(10) Renovation of Room UG09, UG/F, Wu Yee Sun College
(11) Fitting Out Works to School of Continuing and Professional Studies
Room 100 and 112, 1/F, Bank of America Tower at Central
Room 802 & 1403 at Oriental Centre at Tsim Sha Tsui
(12) Renovation Works for Faculty of Medicine at Prince of Wales Hospital :
(a) Lui Che Woo Clinical Sciences Building
Room 34086 (Haematology Laboratory), 1/F, for Department of Anatomical and Cellular Pathology
Room 34180 (Office), 1/F, for Department of Anatomical & Cellular Pathology
Room 94026 to 94033 (BioBank), 7/F, for Faculty and Planning Office
(b) Special Block (Block F)
Room 21 (Laboratory), 9/F, for Department of Obstetrics and Gynaecology
B. The following minor works are at different stages of construction or implementation: (Project Cost: HK$118Mil)
(1) University Conference Centre at L1 & L2 of Cheng Yu Tung Building – (October 2018)
(2) Renovation Works at Hong Kong Institute of Biotechnology
Rooms 230 & 230A for Department of Medicine and Therapeutics - (August 2018)
Rooms 216, 216A, 220 & 220A for AoE Centre for Genomic Studies on Plant-Environment Interaction for
Sustainable Agriculture and Food Security – (October 2018)
(3) Elisabeth Luce Moore Library
Renovation Works at 1/F and 2/F – (August 2018)
Application for Extension of Temporary Occupation Permit & Temporary Building Permit of temporary
structure on roof – application was under process by Buildings Department
(4) Spatial Re-organization for Wu Chung Multimedia Library – (August 2018)
(5) Modification Work of Room 215 of Language Lab for Department of Translation at Humanities Building –
(September 2018)
(6) Fitting Out Works at Room 126, 1/F, Art Museum West Wing – (September 2018)
(7) Renovation of Room 332 at Pi Chiu Building for Office of Research and Knowledge Transfer Services –
(August 2018)
(8) Foyer Enhancement Work at Choh-Ming Li Basic Medical Sciences Building – (September 2018)
Remarks: ( ) denotes scheduled completion date
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 15 of 17
IV. Minor Works: (Jan – Jun 2018)
B. The following minor works are at different stages of construction or implementation: (cont’d)
(9) Fitting Out Works at Room 239 & 240B, Lady Shaw Building for Department of Mathematics –
(September 2018)
(10) Renovation of Staff Associations at 3/F of John Fulton Centre – (December 2018)
(11) Alternation & Addition Works at LG1 & LG4 at North Block of Lee Woo Sing College – (August 2018)
(12) 3D printing for campus model and directory at University Entrance at Tai Po Road – (September 2018)
(13) Fitting Out Works to School of Continuing and Professional Studies:
Room 1300 & 1305 at Oriental Centre, Tsim Sha Tsui – (August 2018)
Room B105, East Ocean Centre, Tsim Sha Tsui – (August 2018)
Room 104 & 105 at Bank of America Tower, Central – (November 2018)
(14) Interior Renovation Works of I-house 1 & 2 for Office of Student Affairs – (June 2019)
(15) Improvement Works at 1/F Lobby, Li Wai Chun Building – (August 2018)
(16) Fitting out Works at Rooms 522, 522A, 526A & 538A, Sino Building for Faculty of Social Science –
(September 2018)
(17) Fitting out Works to Room 527 of Sino Building for Department of Psychology – (July 2018)
(18) Renovation Works for Theology Building – (August 2018)
(19) Renovation Works for Faculty of Medicine at Prince of Wales Hospital:
(a) Lui Che Woo Clinical Sciences Building
Room 33030, 1/F for Department of Chemical Pathology – (October 2018)
Room 34033, 1/F for Office for Department of Anatomical and Cellular Pathology – (September 2018)
Room 38008 & 38012A, 1/F for Department of Microbiology – (October 2018)
Rooms 84026 to 84031, 6/F for Department of Otorhinolaryngology, Head and Neck Surgery - pending
funding approval
Room 84008, 6/F for Faculty and Planning Office – (August 2018)
Room 84046, 6/F for Department of Paediatrics – (August 2018)
Room 124010, 10/F for Li Ka Shing Institute of Health Sciences – Pending Hospital Authority’s approval
(b) Special Block E & F
Rooms 41016 to 41019 (Conference Room), 2/F for Faculty and Planning Office – (August 2018).
(c) Li Ka Shing Specialist Clinics, North Wing
Orthopaedic Learning Centre, 1/F for Department of Orthopaedics and Traumatology - pending Hospital
Authority’s approval
Room 14, 1/F for Department of Orthopaedics and Traumatology – (August 2018)
Surgical Skill Lab, 3/F for CUHK Jockey Club Minimally Invasive Surgical Skills Centre – (January
2019)
(d) The Jockey Club School of Public Health and Primary Care
Room 104 & 104A (Seminar Room), 1/F for Faculty and Planning Office – (November 2018)
Room 327 (Student Common Room), 3/F for Faculty and Planning Office – (September 2018)
(e) Madam S.H. Ho Hostel for Medical Students
Warden quarter, G/F for Student Hostel – (October 2018)
Remarks: ( ) denotes scheduled completion date
Physical Development – Half-yearly Progress Report for the Period Ended 30th June 2018
P. 16 of 17
IV. Minor Works: (Jan – Jun 2018)
C. The following minor works are at different stages of feasibility studies, design or tender:
(1) Feasibility studies were being carried out for space conversion or addition at various buildings and potential sites to
address new initiates and space demand on Campus:
(a) Proposed Alteration and Addition for a University Shop near the MTR entrance piazza.
(b) Proposed Alteration and Major Renovations to convert Inter-University Hall into an InnoHub.
(2) Proposed alteration and addition works for Yali Guest House, Chan Kwan Tung Inter-University Hall and Chiangs
Building – Consultant was appointed and detailed design was in progress.
(3) Spatial Re-organisation of 10/F and 11/F of William M. W. Mong Engineering Building for Department of
Biomedical Engineering - Consultants were appointed and detailed design was in progress.
(4) Renovation of Room C4 & C5 at Lady Shaw Building for Interactive Classroom – detailed design was in progress.
(5) Proposed alteration and addition works for converting language laboratories into multi-purpose classrooms at Lee
Shau Kee Building and Yasumoto International Academic Park for Registry - Conceptual design and funding
application are in progress; site works are expected to commence in December 2018 and June 2019 respectively.
(6) Campus Landscape Master Plan – Tree compensatory discussion report was circulated among Campus
Landscaping Enhancement Committee (CLEC) members and finalized. The University would communicate with
District Lands Office or related government department if necessary.
(7) GIS based Slope Information System and Engineer Inspection for Maintenance – Draft reports of Engineer
Inspection and Maintenance Manual for 75 features were submitted. Comments for individual reports were given
and the final reports are expected to be completed in October 2018. Specification of the GIS software for
tendering is being prepared by the project consultant.
(8) Fitting out Works at 6/F Railway Plaza, Tsim Sha Tsui for School of Continuing and Professional Studies - detailed
design was underway and tender would be issued in August 2018.
(9) University Administration Building
(a) Fitting out works at Room LG12A, LG/F South Block – detailed design is in progress and tender would be
issued in July 2018.
(b) Proposed fitting out works at Room LG12B, LG/F South Block - Conceptual design are in progress.
(10) Choh-Ming Li Basic Medical Sciences Building
(a) Spatial Re-organization for LG1/F – Appointment of consultants are in progress and waiting for funding
approval.
(b) Addition of Glass house / Marquee at proposed green roof at 3/F – detailed design was completed, tender was
returned and the cost are under reconciliation.
(11) Fitting Out Works at 2/F, International House 5 for Office of Student Affairs - conceptual design was completed
and pending for funding approval.
(12) Improvement works for Master Lodge at LG1 of Morningside College - Construction work would be commenced
in September 2018 and expected to be completed in November 2018.
(13) Alteration and addition work for new passenger lift at G/F to LG4/F of Lee Woo Sing College – Statutory
submission was approved and tender would be issued in September 2018.
Appendix - Capital Projects
Jockey Club Postgraduate Halls 2 & 3 on Northern Campus
Two multi-storey hostel blocks with a total of 676 student hostel places, including accommodation for wardens,tutors and attendants; common and supporting facilities
CFA : 15,980 sqm
Project cost : HK$675.2 mil
Status : Superstructure completed and preparing application ofOccupation Permit in August 2018
Completion : 4th Quarter 2018
Physical Development –
Half-yearly Progress Report
Period ended 30th June 2018
Proposed Centralized General Research Lab Complex Block 2 in Area 39 (Expanded and relocated version )
A multi-storey research laboratory building in Area 39, including research laboratories, seminar rooms, offices, DG stores, car parking facilities
CFA : 21,820 sqm
Preliminary Estimate : HK$1,400 mil @ 3rd Quarter 2017
Status : Revised Technical Feasibility Study (TFS) of the proposed expansion and site
adjustment version was approved by Development Bureau. The project was
re-selected to Cat. B- in 2017 CWRAE. Fee adjustment by Consultants to cover
the expanded scope and relocated site was supported by UGC. Detailed design was commenced.
Completion : 2023 - 2024
Proposed Lab Block 2Revised TFS
approved
Proposed A2 & A5 HostelsTFS approved
Existing Lab Block 1
A3 & A4 Hostelsunder construction
P. 1 of 10
New Student Hostels under Hostel Development Fund (HDF) - 300-place Student Hostel, New Asia Campus
Appendix - Capital Projects
Multi-storey 300-place student hostel on New Asia Campus with multi-purpose hall and related facilities
CFA : 5,920 sqm
Project Estimate : HK$270 mil @3rd Quarter 2017
Status : Hostel Development Fund was approved and agreement was being prepared by UGC. Main Contract and Foundation tender was under preparation. Tender calling in 4th Quarter 2018, contract award upon receipt of UGC funding; tentatively inJan 2019.
Completion : 2nd Quarter 2022
New Student Hostels under Hostel Development Fund (HDF) - 250-place Student Hostel, United Campus
Multi-storey 250-place hostel with accommodation for wardens, tutors and supporting facilities
CFA : 5,100 sqm
Preliminary Estimate : HK$248 mil @ 3rd Quarter 2017
Status : Hostel Development Fund was approved and pending formal agreement with UGC in 4th Quarter 2018. Building Committee formulation in progress; procurementof consultants to commence Detailed Design in 2019.
Completion : 2022/2023
P. 2 of 10
Appendix - Capital Projects
Conceptual Image Redevelopment of Block D & G for Chung Chi College
Proposed Lab Block 2Revised TFS
approved
Proposed A2 & A5 HostelsTFS approved
Redevelopment of existing Block D & G to Staff Quarters and Student Community Complex
CFA : 4,420 sqm
Project Estimate : HK$210 mil @ 3rd Quarter 2016
Status : Detailed design is underway. Antiquities and Monuments Office had assessed Nil grading
to the existing Block D&G. Ground Breaking Ceremony was held on 28th May 2018.
Hoarding works to be commenced in 3rd Quarter 2018 followed by demolition works. Tendering for Main - Superstructure and Foundation Contract scheduled in 4th Quarter 2018.
Completion : 3rd Quarter 2021
Appendix - Special Projects
CUHK Medical Centre
Pile Cap works were commenced in October 2017 for completion in January 2018. Superstructure work is in steady progress and topping out is scheduled by end 2018.
Completion: in phases 1st Quarter 2020 and onward
P. 3 of 10
Upgrading and Improvement Works of Shanghai Fraternity Association Research Services Centre
Extension of University Sports Centre
A new extension block of single floor fitness centre next to the existing University Sports Centre with roof garden on top.
CFA : 445 sqm
Project Cost : HK$30 mil
Status : User Committee was formed and the Lead Architectural Consultant was appointed inJanuary 2018. Schematic design and general plans submission are under preparation.
Completion : 3rd Quarter 2020
Appendix - Selected AA&I Projects
Roof top extension to provide new animal holding facilities and research laboratories for research animals; and upgrading of the existing ventilation systems
CFA : 2,180 sqm
Project Cost : HK$30 mil
Status : Main Contract was awarded, works in steady progress. Roof top extension would be
completed by end 2018.
Completion : End 2018 Roof top extension
March 2019 Upgrading works on existing floorsP. 4 of 10
Provision of New Laboratory Space on Roof Extension of Mong Man Wai Building
Roof top extension to provide new wet/ teaching laboratories for research activities
CFA : 500 sqm
Project Cost : HK$20 mil
Status : User Committee was formed and the Lead Architectural Consultant was appointed inJanuary 2018. General building plans and structural plans submissions are underpreparation.
Completion : December 2019
Provision of New Laboratory Space at 1/F of William M W Mong Engineering Building
Extension on existing 1/F flat roof to provide new teaching laboratories for research activities
CFA : 190 sqm
Project Cost : HK$10 mil
Status : User Committee was formed and the Lead Architectural Consultant was appointed inJanuary 2018. General building plans and structural plans submissions are underpreparation.
Completion : December 2019
Appendix - Selected AA&I Projects
P. 5 of 10
Appendix - Selected AA&I Projects
Spatial Reorganization and Improvement Works for Academic Building No. 1
Construction of an extension block and spatial reorganization of G/F to 3/F for Engineering Faculty research laboratories, offices and classroom
CFA : 1,818 sqm
Project Cost : HK$30 mil
Status : Construction in progress
Completion : 4th Quarter 2018
New Lift at Lee Woo Sing College
New lift with glass enclosure from LG4/F to G/F at Lee Woo Sing College
CFA : 50 sqm
Project Cost : HK$10 mil
Status : Detailed design
Completion : 4th Quarter 2019
P. 6 of 10
CFA: Approx 600 sqmProject Cost: HK$1.5 milStatus: Detail design
Tender preparation Completion: December 2018
Appendix – Selected Fitting Out / Interior Projects
New Headquarter Office for CUSCS - School of Continuing and Professional Studies 6/F Railway Plaza, Tsim Sha Tsui
Appendix - Selected Minor Works Projects
Fitting Out Works of Room 100 & 112, 1/F Bank of America Tower
Refurbishment and Upgrading of Existing Lecture Theatre and Classroom Spaces
CFA : 292 sqmProject Cost : HK$4.9 milStatus : Works in progressCompletion : July 2018
P. 7 of 10
Enhancement of Study Spaces to existing library at 1/F
CFA : 1,200 sqm
Project Cost : HK$6 mil
Status : Works in progress
Completion : August 2018
Shelving Area
Study Area
Compact Filing
Group Study Room
Fitting Out Works at 1/F Elisabeth Luce Moore Library, Chung Chi College
Appendix – Selected Minor Works Projects
Spatial Re-organization of existing Learning Spaces and Refurbishment of Shelving Areas from LG/F to 2/F
CFA : 3,000 sqm
Project Cost : HK$18 mil
Status : Works in progress
Completion : August 2018
Remodeling of Wu Chung Multimedia Library, United College
P. 8 of 10
Appendix - Selected Minor Works Projects
Renovation Works of Alumni Corner at Room G01, G/F John Fulton Centre
Fitting-out for Amenity Space at John Fulton Centre
CFA : 172 sqm
Project Cost : HK$3.5 mil
Status : Completed
Completion : June 2018
University Conference Centre at L1 & L2 of Cheng Yu Tung Building
Renovation Works for University Conference Centre at Cheng Yu Tung Building
CFA : 2532 sqm
Project Cost : HK$27 mil
Status : Work in Progress
Completion : October 2018
P. 9 of 10
Appendix - Selected Energy & Infrastructure Enhancement Projects
Upgrading of Central Air-Conditioning Plants
Completion : Dec 2017 ( HK$ 24 mil)
Completion : Jun 2018 (HK$ 10 mil)
Upgrading of central air-conditioning plants from air-cooled to high efficiency water-cooled chillers for energy saving
Status : Construction in progress
Esther Lee Building
University Sports Centre