The Challenges and Lessons Learned Related to the
Qualification, Selection and Monitoring of Site
Contractors
Tom Mudge31st Energy & Environmental
ConferenceSeptember 2004Orlando, Florida
LEARNING OBJECTIVES
• UNDERSTANDING RISKS
• KEYS TO SUCCESS
• EVALUATION METHODS
• COMPENSATORY ACTIONS
RISK ASSESSMENT
PROBLEMS ATTRIBUTED TO INADEQUATE PERFORMANCE OF
CONTRACTORS CAN BE AS MUCH AS 60% OF THE OVERALL QUALITY
PROBLEMS ON A PROJECT.
BIG BUCKS $$$$$
RISK ASSESSMENT
• NATURE OF ACTIVITY
• CRITICALITY OF MISSION
• CONSEQUENCES OF FAILURE
NATURE OF ACTIVITY
• TYPE OF ACTIVITY• WHAT CAN GO WRONG?• PROBABILITY • PREVIOUS EXPERIENCE
TYPE OF ACTIVITIES
•REINFORCED CONCRETE
•STRUCTURAL STEEL
•PIPING
•HVAC•CARPENTRY•PAINTING• I&C /
ELECTRICAL
CRITICALITY OF MISSION
• RESIDENTIAL HOUSING• PUBLIC FACILITY Buildings Rail Highway• INDUSTRIAL Chemical / Nuclear
CONSEQUENCES OF FAILURE
• LOSS OF LIFE AND LIMB• REPAIR / REWORK• SCHEDULE DELAYS• CONTRACT TERMINATION• CUSTOMER SATISFACTION• DAMAGED REPUTATION
COMPENSATORY ACTIONS
•SURVEILLANCE / AUDIT•WITNESS / HOLD POINTS•CONTINUOUS OVERSIGHT - INSPECTION - TESTING
ATLANTIC CITY GARAGE COLLAPSE
• INADEQUATE REBAR INSTALLATION
- Quantity - Connections• NO CYLINDER TESTING• NO BRACING• SCHEDULE PRESSURE
KEYS TO SUCCESS
• MANAGEMENT SYSTEM - Organization• PROJECT TEAM PERSONNEL - Technical Background - Work Experience - Team• MANAGEMENT’S ROLE
HUMAN SIDE OF QUALITY
PRIDE
LOYALTY / COMMITMENT
EGO / POWER
INTEGRITY
“ME”
DON’T UNDERESTIMATE THE HUMAN SIDE
OF QUALITY.
ORGANIZATION
• INDEPENDENCE
• MANAGEMENT INVOLVEMENT - AWARENESS - RESPONSE
Contractor Characteristics
Contractor A Contractor B Contractor C Contractor D
Type Local Local National National
Supervision Long Term Long Term Long Term Short Term
Work Force Long Term Short Term Short Term Short Term
Team Experience
Yes No Yes No
Management Involvement
Close Intermittent Intermittent Intermittent
EVALUATION METHODS
• REVIEW QA MANUAL• REVIEW RESUMES• FACILITY SURVEY• QUESTIONNAIRES• PREVIOUS CUSTOMERS• MANAGEMENT OVERVIEW
INVEST IN THE EVALUATION PROCESS
THE COST OF THE EVALUATION PROCESS IS
MINOR COMPARED TO THE COST OF FAILURE –NOW AND THE FUTURE
SELECT THE BEST
All companies will occasionally
experience quality problems on their
projects.
What sets the good
contractor apart, however, is their ability to
understand why the problem occurred and implement effective
corrective action to prevent recurrence in the future