Upload
others
View
72
Download
7
Embed Size (px)
Citation preview
The API RBI Tank Module & Examples of Tank RBI
Assessments
The Equity Engineering Group, Inc. March, 2010
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
2
Presentation Overview
• Introduction & General RBI Background • Storage Tank RBI Overview • API RBI Tank Module • Two Case Studies
– Tank Inspection Variance – Tank Inspection Prioritization
• Summary & Conclusions
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
3
Introduction
• RBI provisions added to API 653 in late 1990s
• Current API 653 includes inspection intervals that account for RBI assessment (and similar service; use of RPB’s, CP, etc.)
• Significant enhancements were made to the API RBI Tank Module in Version 8 released in 2007 Cop
yrigh
t © 20
10 E
²G | T
he E
quity
Eng
ineeri
ng G
roup,
Inc. A
ll Righ
ts Res
erved
.
4
General RBI Background
• API 580 Risk Based Inspection – provides guidance on developing an RBI program – What is RBI – What are the key elements of an RBI program – How to implement an RBI program
• API 581 Risk Based Inspection Technology –
provides details of an RBI program that complies with API 580 – API RBI software based on API 581 methodology – A quantitative approach – Detailed procedures and calculations
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
5
General RBI Background
• In general, Risk is the product of probability of failure and consequence of failure
• POF is a function of time since many damage
mechanisms (fatigue, thinning, cracking, creep, etc.) can be functions of time – so, Risk is time-dependent
• In API RBI, the COF is assumed to be independent of time, so:
( ) ( )R t POF t COF= ⋅
( ) ( )( ) ( )
R t POF t CA for Area Based RiskR t POF t FC for Financial Based Risk
= ⋅ −= ⋅ −
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
6
Probability of Failure
• The time dependency of probability of failure is the basis of using RBI for inspection planning
• The probability of failure used in API RBI is a function of three terms:
( ) ( )
( )
( )
:
f MS
f
MS
POF t gff D t Fwhere
POF t the probability of failure as a function of timegff generic failure frequencyD t damage factor as a function of timeF management systems factor
= ⋅ ⋅
−
−
−
−Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
7
API RBI Generic Failure Frequency
• From API 581 – Part 2 Table 4.1:
• GFF are based on statistical analysis of best available data and experience of the API RBI Sponsor Group
Table 4.1 – Suggested Component Generic Failure Frequencies ( )[1 thru 8]
Equipment Type Component Type as a Function of Hole Size (failures/yr)
(failures/yr) Small Medium Large Rupture
Compressor COMPC 8.00E-06 2.00E-05 2.00E-06 0 3.00E-05 Compressor COMPR 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Heat Exchanger HEXSS 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Heat Exchanger HEXTS 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Heat Exchanger HEXTUBE 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Pipe PIPE-1 2.80E-05 0 0 2.60E-06 3.06E-05 Pipe PIPE-2 2.80E-05 0 0 2.60E-06 3.06E-05 Pipe PIPE-4 8.00E-06 2.00E-05 0 2.60E-06 3.06E-05 Pipe PIPE-6 8.00E-06 2.00E-05 0 2.60E-06 3.06E-05 Pipe PIPE-8 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Pipe PIPE-10 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Pipe PIPE-12 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Pipe PIPE-16 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Pipe PIPEGT16 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Pump PUMP2S 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Pump PUMPR 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Pump PUMP1S 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Tank650 TANKBOTTOM 7.20E-04 0 0 2.00E-06 7.20E-04 Tank650 COURSE-1 7.00E-05 2.50E-05 5.00E-06 1.00E-07 1.00E-04 Tank650 COURSE-2 7.00E-05 2.50E-05 5.00E-06 1.00E-07 1.00E-04 Tank650 COURSE-3 7.00E-05 2.50E-05 5.00E-06 1.00E-07 1.00E-04 Tank650 COURSE-4 7.00E-05 2.50E-05 5.00E-06 1.00E-07 1.00E-04 Tank650 COURSE-5 7.00E-05 2.50E-05 5.00E-06 1.00E-07 1.00E-04 Tank650 COURSE-6 7.00E-05 2.50E-05 5.00E-06 1.00E-07 1.00E-04 Tank650 COURSE-7 7.00E-05 2.50E-05 5.00E-06 1.00E-07 1.00E-04 Tank650 COURSE-8 7.00E-05 2.50E-05 5.00E-06 1.00E-07 1.00E-04 Tank650 COURSE-9 7.00E-05 2.50E-05 5.00E-06 1.00E-07 1.00E-04 Tank650 COURSE-10 7.00E-05 2.50E-05 5.00E-06 1.00E-07 1.00E-04 Vessel/FinFan KODRUM 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Vessel/FinFan COLBTM 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Vessel/FinFan FINFAN 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Vessel/FinFan FILTER 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Vessel/FinFan DRUM 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Vessel/FinFan REACTOR 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Vessel/FinFan COLTOP 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Vessel/FinFan COLMID 8.00E-06 2.00E-05 2.00E-06 6.00E-07 3.06E-05 Note: See references [1] through [8] for discussion of failure frequencies for equipment
gffgfftotalgff
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
8
Tank Failure – What is Impacted
Subsurface Soil
Surface Water
OnsiteOffsite
1
Ground Water
Tank
Dike Area
6
32
4
5
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
9
Tank RBI – API RBI • Consequences from component damage, product loss
and environmental costs are considered - Level 1 consequence determination only in API RBI Tank Module
• Result is in financial risk terms
• Tank Modeled as several components - Tank Bottom; Shell Courses
• When safety consequences need to be considered in addition to financial model a tank shell a pressure vessel shell, as well Cop
yrigh
t © 20
10 E
²G | T
he E
quity
Eng
ineeri
ng G
roup,
Inc. A
ll Righ
ts Res
erved
.
10
Tank RBI – API RBI
Table 7.1 – Fluids and Fluid Properties for Atmospheric storage Tank Consequence Analysis
Fluid
Level 1 Consequence
Analysis Representative
Fluid
Molecular Weight Liquid Density (lb/ft3)
Liquid Dynamic Viscosity (lbf-s/ft2)
Gasoline C6-C8 100 42.702 8.383E-5
Light Diesel Oil C9-C12 149 45.823 2.169E-5
Heavy Diesel Oil C13-C16 205 47.728 5.129E-5
Fuel Oil C17-C25 280 48.383 7.706E-4
Crude Oil C17-C25 280 48.383 7.706E-4
Heavy Fuel Oil C25+ 422 56.187 9.600E-4
Heavy Crude Oil C25+ 422 56.187 9.600E-4
• Fluid properties determined by fluid selection • Hydraulic conductivity and fluid seepage velocity
determined from density and viscosity
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
11
Tank RBI – API RBI
Table 7.2 – Soil Types and Properties for Atmospheric storage Tank Consequence Analysis
Soil Type
Hydraulic Conductivity for Water Lower
Bound (in/sec)
Hydraulic Conductivity for Water Upper
Bound (in/sec)
Soil Porosity
Coarse Sand 3.94E-2 3.94E-3 0.33
Fine Sand 3.94E-3 3.94E-4 0.33
Very Fine Sand 3.94E-4 3.94E-6 0.33
Silt 3.94E-6 3.94E-7 0.41
Sandy Clay 3.94E-7 3.94E-8 0.45
Clay 3.94E-8 3.94E-9 0.50
Concrete-Asphalt 3.94E-11 3.94E-12 0.99
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
12
Tank RBI – API RBI
• Release Rate Calculation – Liquid head is assumed to be constant (maximum) with
time – Leak into ground is treated as a continuous porous media;
based on the soil porosity given for the tank subgrade – Product leakage flow rate through a small hole is a function
of the soil and fluid properties as well as liquid head – Bernoulli or Girard equation used depending on hydraulic
conductivity
• API Tank RBI modules uses a Financial Risk Target
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
13
Tank RBI – API RBI
• Financial environmental cost from shell course leakage
• Financial environmental cost for a shell course rupture
• Total financial environmental cost for shell courses
leak leakindike indike ss onsite ss oniteleak
environ leak leakss offsite ss offite water water
Bbl C Bbl CFC
Bbl C Bbl C− −
− −
⋅ + ⋅ += ⋅ + ⋅
rupture ruptureindike indike ss onsite ss oniterupture
environ rupture rupturess offsite ss offite water water
Bbl C Bbl CFC
Bbl C Bbl C− −
− −
⋅ + ⋅ += ⋅ + ⋅
leak ruptureenviron environ environFC FC FC= +
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
14
Tank RBI – API RBI • Component damage cost for shell courses
• Outage Days and the cost of business interruption
• Financial Consequence for shell courses
• A similar consequence calculation is done for the tank
floor
total environ cmd prodFC FC FC FC= + +
4
1n n
ncmd
total
gff holecostFC matcost
gff=
⋅ = ⋅
∑
( )( )prod cmd affaFC Outage Outage prodcost= +
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
15
API RBI - Risk Targets
• When a risk target is exceeded in API RBI, an inspection is recommended to reduce uncertainty
• Fixed equipment primarily uses an Area Risk Target: 27-40 ft2/yr target is typical (from experience, case studies)
• Tank RBI uses a Financial risk target. No well defined case studies for Tank RBI Risk Targets: - Typically determined with client input to be in the $15,000 to
$50,000/yr range; inspection costs and production interruption are considered Cop
yrigh
t © 20
10 E
²G | T
he E
quity
Eng
ineeri
ng G
roup,
Inc. A
ll Righ
ts Res
erved
.
16
API RBI - Key Inputs
• Operating conditions – Height, Temperature, SG • Foundation – Design, Release Prevention, Soil Type • Containment Information (dike, possibility of off-site
contamination) • Production Impact • Environmental Impact • Previous inspections
– Corrosion rates – Damage to insulation – Overall condition
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
17
API RBI Inspection Effectiveness
• Grade Inspections – (A through E)
• API 581 – Part 2 Tables in Section 5 – Based on type of damage that is of concern
• Typically, an intrusive and non-intrusive method of inspection is listed
Table 5.10 – Guidelines for Assigning Inspection Effectiveness – Tank Bottoms
Inspection Category
Inspection Effectiveness
Category Soil Side Product Side
A Highly Effective
a. Floor scan 90+% & UT follow-up b. Include welds if warranted from
the results on the plate scanning c. Hand scan of the critical zone
Commercial blast Effective supplementary light Visual 100% (API 653) Pit depth gauge 100% vacuum box testing of suspect welded joints Coating or Liner: a. Sponge test 100% b. Adhesion test c. Scrape test
B Usually Effective
a. Floor scan 50+% & UT follow-up OR a. EVA or other statistical method
with Floor scan follow-up if warranted by the result
a. Brush blast b. Effective supplementary light c. Visual 100% (API 653) d. Pit depth gauge Coating or Liner: a. Sponge test >75% b. Adhesion test c. Scrape test
C Fairly Effective
a. Floor scan 5-10+% plates; supplement with scanning near Shell & UT follow-up; Scan circle and X pattern
b. Progressively increase if damage found during scanning
c. Helium/Argon test d. Hammer test e. Cut coupons
a. Broom swept b. Effective supplementary light c. Visual 100% d. Pit depth gauge Coating or Liner: a. Sponge test 50 – 75% b. Adhesion test c. Scrape test
D Poorly Effective a. Spot UT b. Flood test
a. Broom swept b. No effective supplementary lighting c. Visual 25-50% Coating or Liner: Sponge test <50
E Ineffective None None Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
18
API RBI – Tank Damage Mechanisms
• Tank Bottom Corrosion – Product Side – Soil Side
• Shell Thinning Damage
• Shell External Damage (CUI)
• Often, no other mechanisms:
– Fatigue – Creep – Cracking
Cop
yrigh
t © 20
10 E
²G | T
he E
quity
Eng
ineeri
ng G
roup,
Inc. A
ll Righ
ts Res
erved
.
19
API RBI – Typical Input (Bottom)
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
20
API RBI - Typical Input (Shell)
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
21
API RBI – Typical Input (Thinning)
Tank 1 – Tank Bottom
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
22
Case Study 1
• Two refinery AST – RBI used to defer the inspections – variance from jurisdiction
• A similar service argument was used for other tanks
very close to these tanks
• Similar Service argument was not accepted by the regulators for these two tanks
• Both were last inspected in the early 1990’s
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
23
Tank Descriptions
• Tank 1 – Diesel Product Tank – Installed in the late 50’s, floor replaced in early 90’s – 30’ diameter, 40’ tall – Sits on a ring wall with no release prevention – No internal inspection since floor replacement
• Tank 2
– Heavy Gas Oil Tank – Installed in early 90’s – 120’ diameter, 48’ tall – Sits on a graded concrete slab – No internal inspection since installation
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
24
Thinning Damage
Component Component Type Base Metal Measured Rate (mpy)*
Base Metal Calculated Rate (mpy)
TANK 1-BTM TANKBOTTOM - 9.5
TANK 1-Course 2 COURSE-1 0 -
TANK 1-Course 3 COURSE-2 0 -
TANK 1-Course 4 COURSE-3 0 -
TANK 1-Course 4 COURSE-4 0 -
TANK 1-Pressure Vessel DRUM 0 -
TANK 2-BTM TANKBOTTOM - 11.0
TANK 2-Course 1 COURSE-1 0 -
TANK 2-Course 2 COURSE-2 0 -
TANK 2-Course 3 COURSE-3 0 -
TANK 2-Course 4 COURSE-4 0 -
TANK 2-Course 5 COURSE-5 5.0 -
TANK 2-Presusre Vessel DRUM 5.0 -
* Measured rates came from provided UT data Cop
yrigh
t © 20
10 E
²G | T
he E
quity
Eng
ineeri
ng G
roup,
Inc. A
ll Righ
ts Res
erved
.
25
External Damage
Component Component Type Insulation Type External Environment
Base Material Calculated Rate (mpy)
TANK 1-Course 1 COURSE-1 Mineral Wool Marine 8.4
TANK 1-Course 2 COURSE-2 Mineral Wool Marine 8.4
TANK 1-Course 3 COURSE-3 Mineral Wool Marine 8.4
TANK 1-Course 4 COURSE-4 Mineral Wool Marine 8.4
TANK 1-Pressure Vessel DRUM Mineral Wool Marine 8.4
TANK 2-Course 1 COURSE-1 Fiberglass Marine 10.9
TANK 2-Course 2 COURSE-2 Fiberglass Marine 10.9
TANK 2-Course 3 COURSE-3 Fiberglass Marine 10.9
TANK 2-Course 4 COURSE-4 Fiberglass Marine 10.9
TANK 2-Course 5 COURSE-5 Fiberglass Marine 10.9
TANK 2-Presusre Vessel DRUM Fiberglass Marine 8.4
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
26
RBI Results
Component Component Description
Component Type
Thinning Inspection Category
Cracking Inspection Category
External Damage
Inspection Category
RBI Inspection
Date
TANK 1-BTM TANK 1-Bottom TANKBOTTOM C 2015-02-01
TANK 1-Shell TANK 1-Shell DRUM C 2015-10-24
TANK 2-BTM TANK 2-Bottom TANKBOTTOM C 2017-03-15
• Inspection Planning
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
27
RBI Results - Inspection Plans
• TANK 1 Bottom – C-level bottom thinning inspection by early 2015. – Scanning of 5 to 10+% of the floor plates while supplementing scanning near
the shell and the floor – 100% visual inspection of the floor – Scanning should progressively increase if damage is found.
• TANK 2 Bottom – C-level bottom thinning by March of 2017.
• TANK 1 Shell – C-level external shell inspection by fall 2015.
– 95 to 100% external visual inspection of the insulation – Follow-up with profile or real time radiography of 33 to 65% of suspect areas – Follow-up of corroded areas with 95 to 100% visual inspection of the exposed
surface with UT, RT or pit gauge. – This inspection in non-intrusive.
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
28
Results
• A request/report was written to the jurisdiction to request a variance to extend the inspection intervals
• Meeting was held with the jurisdiction to present
the results, answer questions, provide general education on API 580/581 and the API RBI methodology.
• Variance was subsequently approved
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
29
Case Study 2 • RBI used to prioritize tank inspections and determine
level of inspection for each tank
• Tank farm in a refinery with about 25 AST in variety of services: – Slop Tanks – Fuel Oil – Diesel – Gasoline – Jet Fuel – Alkylate – Reformate – Additives
• Range of typical tank sizes and details
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
30
RBI Results – Inspection Plan • Inspection Planning (selected examples)
Component Component Description
Thinning Inspection Category
Cracking Inspection Category
External Damage
Inspection Category
RBI Inspection
Date
TANK 1-BTM Slop Tank-Bottom A 2013-02-21
TANK 1-BTM Slop Tank-Shell C A 2021-06-07
TANK 2-BTM Slop Tank-Bottom A 2009-09-21
TANK 3-BTM Gasoline-Bottom A 2022-03-22
TANK 3-BTM Gasoline-Bottom A 2012-02-17
TANK 4-BTM Jet Fuel-Course 2 C A 2016-07-02
TANK 4-BTM Jet Fuel-Course 3 C A 2023-06-28
TANK 5-BTM Marine Diesel-Bottom A 2009-09-21
TANK 6-BTM Fuel Oil-Course 1 C A 2011-10-30
TANK 6-BTM Fuel Oil-Course 2 B 2011-12-29
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
31
Results
• 20-plus tanks included about 170 “components”
• About 50 components (30%) had recommended inspections in the plan period (before 2025); a couple had recommendations for inspection in the short term
• About half the tanks had recommended bottom inspections (typically considered intrusive) in the plan period
• The timing and required level of inspections were
defined for these tank components – resources allocated in an effective way
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
32
Results
• Frequently, RBI results for larger populations of equipment are presented in a Risk Matrix format – Provides a look at
multiple components relative ranking
• Matrix not done for
either of these two case studies, but as an example:
2 4
3
1 11
3
7
5
2
3
4
12 16 13 7 2
7 0.14
6
6
11
19
8
50
5
16 0.32
17 0.34
10 0.20
Unit X
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
33
Tank RBI - Summary
• Uses of API RBI include: – Evaluating internal inspection interval variances – Prioritizing, determination of critical components – Determining needed level of inspection
• Jurisdiction/regulatory issue:
– Get early project involvement; educate, as needed – Seek examples of preferred reporting format/content
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
34
Tank RBI - Summary • API RBI documents are undergoing revision:
– API 580 and 581 re-writes, some of this is related to tank sections
– API 653 section on inspection intervals and RBI is undergoing a review and further revision
• Continued enhancements to API RBI software: – Addition of fluid modeler used for other fixed equipment
– unlimited fluid capabilities – Level 2 consequence analyses will be available for tanks – Area (Safety) Risk will be available – API 620 allowable stresses/calculations – Settlement as a damage mechanism – Impact of annular ring and additional foundation/design
details
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.
35
Thank You!
Questions
Copyri
ght ©
2010
E²G
| The
Equ
ity E
ngine
ering
Grou
p, Inc
. All R
ights
Reserv
ed.