Upload
erick-bruce
View
240
Download
0
Tags:
Embed Size (px)
Citation preview
The 4S Reactor Project The 4S Reactor Project The 4S Reactor Project The 4S Reactor Project
30 Years of Power30 Years of Power30 Years of Power30 Years of Power
2
4S Reactor Project4S Reactor Project
Toshiba and CRIEPI Project Super Safe, Small & Simple & Secure Sodium-cooled, metallic fueled, small reactor Key features
• Fuel costs are set for 30 years
• Operates without the need for grid or backup power
• Higher temperature increases efficiency of hydrogen and oxygen production
• Negative heat coefficient
Toshiba and CRIEPI Project Super Safe, Small & Simple & Secure Sodium-cooled, metallic fueled, small reactor Key features
• Fuel costs are set for 30 years
• Operates without the need for grid or backup power
• Higher temperature increases efficiency of hydrogen and oxygen production
• Negative heat coefficient
3
ElectricityElectricity
Hydrogen generationHydrogen generation
District HeatingDistrict Heating
DesalinationDesalination
4S Reactor Features4S Reactor Features
Transportable No refueling for 30 years Reasonable cost of power Cogeneration of H2 Passive safety Proliferation resistant
Transportable No refueling for 30 years Reasonable cost of power Cogeneration of H2 Passive safety Proliferation resistant
4
Steam generator Secondary
cooling loop
Reactor top dome
Reactor Vessel & Guard Vessel
Seismic isolators
Turbine
GeneratorCondenser
Shielding Plug
Reactor Core
4S Cross Section4S Cross Section
5
äCè„ÇÃóAëóäCè„ÇÃóAëóMarine transport
Barge
Designed for shop fabrication and mass production
Steel beam and autoclaved lightweight concrete
Steel plate reinforced concrete
TransportationTransportation
Approximate dimensions: 90’ x 68’ x 120’Approximate shipping weight: 3000 tons
6
Electric Grid on the YukonElectric Grid on the Yukon
In 2004 the Department of Energy paid for a Study of the Galena Electrical Alternatives.
The Nuclear Power alternative was found to be most desirable both because of cost and because it causes less pollution.
In 2004 the Department of Energy paid for a Study of the Galena Electrical Alternatives.
The Nuclear Power alternative was found to be most desirable both because of cost and because it causes less pollution.
7
Galena Electric Power –a Situational Analysis Advisory
Advisory Group Meeting July 21, 2004Outline Purpose Approach System OptionsSummaryEconomic Analysis Environmental Issues Conclusions
8
Galena Electric Power –a Situational AnalysisGalena Electric Power –a Situational Analysis
Nuclear: Possible Uses of Extra Power
•Hydrogen Production •Greenhouses •Aquaculture •Galena as a test-bed •Transmission to Neighboring Villages Increased use by consumers
Nuclear: Possible Uses of Extra Power
•Hydrogen Production •Greenhouses •Aquaculture •Galena as a test-bed •Transmission to Neighboring Villages Increased use by consumers
9
Mohamed ElBaradeiMohamed ElBaradei
Nobel laureate Mohamed ElBaradei, director general of the International Atomic Energy Agency, gave this year's David J. Rose Lecture on "Nuclear Technology in a Changing World: Have We Reached a Turning Point?" Photo / Donna Coveney
One potential strategy is to construct hundreds of mini-nuclear power plants that would each serve a single village, said ElBaradei. These plants would be less expensive than their full-size counterparts and could be set up without a need for an extensive power grid. In addition, the small-scale plants could be made with sufficient safety features to prevent meltdown and theft. This includes a passive cooling system that works even if power is shut down, said researchers this summer at Argonne National Laboratory. The reactors could also run for 30 years without the need to refuel, and any theft would require the use of large and conspicuous gear that could be visible by satellite, according to Argonne's senor technical advisor David Wade.
10
GNEPGNEP
President George BushPresident George Bush
11
GNEP Element Demonstrate SmaII Scale ReactorsGNEP Element Demonstrate SmaII Scale Reactors
In order to expand the use of nuclear energy in these small electricity markets, a small reactor is preferred for small electricity grids. These reactors will be safe, simple to operate, more proliferation-resistant, and highly secure.
How the reactors would work
Small, more proliferation-resistant reactors could incorporate features that would … include fuel designs that offer very long-life fuel loads (that last the entire life of the reactor); effective… safeguards … to promote non-proliferation; potential for district heating and potable water production; fully passive safety systems; simple operation that requires minimal in-country nuclear infrastructure; use of as much existing licensed or certified technology as possible; and use of advanced manufacturing techniques.
In order to expand the use of nuclear energy in these small electricity markets, a small reactor is preferred for small electricity grids. These reactors will be safe, simple to operate, more proliferation-resistant, and highly secure.
How the reactors would work
Small, more proliferation-resistant reactors could incorporate features that would … include fuel designs that offer very long-life fuel loads (that last the entire life of the reactor); effective… safeguards … to promote non-proliferation; potential for district heating and potable water production; fully passive safety systems; simple operation that requires minimal in-country nuclear infrastructure; use of as much existing licensed or certified technology as possible; and use of advanced manufacturing techniques.
12
Pre-Application ReviewPre-Application Review
NRC recommends a Pre-Application Review before the reactor manufacturer files the application for Design Certification
Pre-Application Review identifies issues for:
• Compliance with generic NRC policy guidance
• Staff technical resolution before design certification gets underway
• Applicant follow-up to develop necessary design changes
Pre-Application Review allows reactor manufacturer to make an early decision on whether to proceed with certification
NRC recommends a Pre-Application Review before the reactor manufacturer files the application for Design Certification
Pre-Application Review identifies issues for:
• Compliance with generic NRC policy guidance
• Staff technical resolution before design certification gets underway
• Applicant follow-up to develop necessary design changes
Pre-Application Review allows reactor manufacturer to make an early decision on whether to proceed with certification
13
4S Pre-Application4S Pre-Application
A Pre-Application Review for the 4S should take about one year
Intend to take advantage of the work that the NRC has already done in reviewing similar designs:
• Sodium Advanced Fast Reactor (SAFR)
• Power Reactor Innovative Small Module (PRISM) liquid metal reactor
• Fast Breeder Reactor (FBR)
• Argonne’s Integral Fast Reactor (IFR) and Experimental Breeder Reactor (EBR-II)
• Fast Flux Test Reactor (FFTR)
Address issues in the prior NRC design reviews
14
Study and Document Preparation (TSB)
Submittal of Preliminary Safety Information Document (PSID) (TSB)
Meetings with NRC and NRC technical reviews (TSB, NRC)
NRC Questions to and Requests for Additional Information (NRC)
Development and Submittal of New or Modified Documents (TSB)
Initial Meeting with NRC Staff(TSB, NRC)
NRC Referral to Advisory Committee on Reactor Safeguards/ ACRS letter
Issuance of PSER (NRC)
Summary of Pre-Application ProcessSummary of Pre-Application Process
15
4S Preliminary Cost Estimate4S Preliminary Cost Estimate
50MWe (135MWt) : Commercial plant (mass
production phase)
• Plant Construction: $ 2,500-$3,000/KWe
• Busbar Cost: $.065 mills-$.070 /KW-hr*
*8% house load factor is assumed
16
O2
Ele
ctro
lyte
Cat
ho
de
An
od
e H2O
H2
O2-e-e-
(Solid OxideElectrolyte Cell)
Hydrogen ProductionHydrogen Production
High temperature steam electrolyser
Hydrogen production from the 50 MWe
• ~15,000 Nm3/h
• ~10M gal/yr of diesel equivalent
• ~10,000 people in rural areas
• Production can be shared with district heating, desalination and electricity
High temperature steam electrolyser
Hydrogen production from the 50 MWe
• ~15,000 Nm3/h
• ~10M gal/yr of diesel equivalent
• ~10,000 people in rural areas
• Production can be shared with district heating, desalination and electricity
17
Sample Commodity Costs –10 Megawatts of Electricity Equivalent
Sample Commodity Costs –10 Megawatts of Electricity Equivalent
Commodity Production Rate
10 MWe Yields:
Comments
Electricity 10 MW 240,000 KW/day
Oxygen 567 scf/min 817,071 scf/day
Assume electrolysis process using Teledyne Titan HP generator
Hydrogen 1134 scf/min
1,634,143 scf/day
Assumes electrolysis process using Teledyne Titan HP generator
Desalinated Water
6,381 gpm 9,188,522 gpd
Assumes Salt Water Reverse Osmosis process with 35,000 ppm TDS input and producing 350 ppm TDS output
18
Construction PeriodConstruction Period
Month
Excavation
Waterproofing, lower mat, MMR (Man-Made Rock)
Seismic isolator
Transport rail for module
Module transport, rail dismantlement
Concrete curing of upper mat
Reactor room
Reactor
Start-up test
14 15 1610 11 12 136 7 8 92 3 4 5-3 -2 -1 1
rock inspectionÅ@ŧ
RV insertionŧ
Module settingÅ@Å@ŧ
ŧFuel load
19
White PapersWhite Papers
The City obtained a legislative grant of $500,000 to get additional insight into the safety of the 4s reactor. This is being accomplished through a series of White papers. Each white paper is about 30 pages long and is available for review at www.roe.com.
Work on the papers is being done by Burns & Roe, a nuclear engineering firm in conjunction with PWSP, a large Washington DC law firm. There will a total of 7 White papers written. The topics are as follows:
The City obtained a legislative grant of $500,000 to get additional insight into the safety of the 4s reactor. This is being accomplished through a series of White papers. Each white paper is about 30 pages long and is available for review at www.roe.com.
Work on the papers is being done by Burns & Roe, a nuclear engineering firm in conjunction with PWSP, a large Washington DC law firm. There will a total of 7 White papers written. The topics are as follows:
20
Overview White Paper Overview White Paper
All of the Whitepapers include a narrative on the
conditions that we deal with to produce power in rural Alaska. Also, they chronicle what steps the City council has taken on this project.
The Overview White Paper explains the mechanics of the reactor and the process required to get a reactor licensed by the Nuclear Regulatory Commission.
All of the Whitepapers include a narrative on the
conditions that we deal with to produce power in rural Alaska. Also, they chronicle what steps the City council has taken on this project.
The Overview White Paper explains the mechanics of the reactor and the process required to get a reactor licensed by the Nuclear Regulatory Commission.
21
Nuclear Liability Nuclear Liability
This white paper provides background on the regulations
regarding liability insurance for Nuclear Power plants.
It then compares the 4s at 10 MGW to traditional nuclear plants at 1000 MGW.
Based on the smaller size and the passive safety features the paper requests that the NRC consider the lower range of the insurance requirements.
This white paper provides background on the regulations
regarding liability insurance for Nuclear Power plants.
It then compares the 4s at 10 MGW to traditional nuclear plants at 1000 MGW.
Based on the smaller size and the passive safety features the paper requests that the NRC consider the lower range of the insurance requirements.
22
Physical Security Physical Security
This paper set forth the general physical security for
nuclear power plants, such as how many guards and fencing etc.
The paper explains the inherent safety features of the 4s
design. Then provides a conceptual overview of the physical security requirements in Galena and identifies the staffing levels that would be needed.
This paper set forth the general physical security for
nuclear power plants, such as how many guards and fencing etc.
The paper explains the inherent safety features of the 4s
design. Then provides a conceptual overview of the physical security requirements in Galena and identifies the staffing levels that would be needed.
23
Emergency Planning Emergency Planning
This paper addresses two components of emergency planning. First is the plan to deal with onsite radiological emergencies and the second is to prepare offsite plans to provide responses to an emergency in the area surrounding the plant.
The paper recommends a clear zone of 800 meters or a half mile around the facility. This is the distance that would need to be evacuated in the case of an emergency at the plant.
State regulations will deal with the risk associated with offsite plumes.
This paper addresses two components of emergency planning. First is the plan to deal with onsite radiological emergencies and the second is to prepare offsite plans to provide responses to an emergency in the area surrounding the plant.
The paper recommends a clear zone of 800 meters or a half mile around the facility. This is the distance that would need to be evacuated in the case of an emergency at the plant.
State regulations will deal with the risk associated with offsite plumes.
24
DecommissioningDecommissioning
This paper describes the planning for the 3 major areas of decommissioning.
1. selecting the appropriate disposal method at the end of the useful life; disposing of the spent fuel, the sodium and returning the site to it’s natural state,
2. estimating the cost of decommissioning and 3. establishing a mechanism for funding the decommissioning.
Decommissioning includes disposal of the spent fuel, the primary sodium and the carrier vessel.
This paper describes the planning for the 3 major areas of decommissioning.
1. selecting the appropriate disposal method at the end of the useful life; disposing of the spent fuel, the sodium and returning the site to it’s natural state,
2. estimating the cost of decommissioning and 3. establishing a mechanism for funding the decommissioning.
Decommissioning includes disposal of the spent fuel, the primary sodium and the carrier vessel.
25
Seismic ConsiderationsSeismic Considerations
The Seismic White Paper discusses the relevant siting issues including the historical characteristics of the region and the pertinent design features of the 4s reactor.
The Seismic White Paper discusses the relevant siting issues including the historical characteristics of the region and the pertinent design features of the 4s reactor.
26
ContainmentContainment
The Containment white paper is a summary of the reactor vessel and other containment systems.
The paper includes a general plant description, with extra attention to those systems responsible for containment of the core in the event of a severe accident.
The system is designed so that a sodium leak will not leave the core uncovered.
The Containment white paper is a summary of the reactor vessel and other containment systems.
The paper includes a general plant description, with extra attention to those systems responsible for containment of the core in the event of a severe accident.
The system is designed so that a sodium leak will not leave the core uncovered.
27
Next Steps: Ownership Next Steps: Ownership
A small Municipality such as Galena will not be the owner of the 4s Nuclear Plant. Issues include:
• Liability
• Financing
• Long term sustainability
A small Municipality such as Galena will not be the owner of the 4s Nuclear Plant. Issues include:
• Liability
• Financing
• Long term sustainability
28
Ownership ContinuedOwnership Continued
Ownership will most likely be an LLC. Potential scenarios with pro’s & con’s are:
1. State of Alaska – AIDEA
Pro: Access to bond funds, loan guarantees,
Control determination on siting & location
could become owner/distributor/franchisee
Increased credibility at Toshiba, NRC, DOE
Con: AEA prohibited for nuclear projects
Educating the politicians to understand the viability of the operations,
no state commitment to become involved.
Ownership will most likely be an LLC. Potential scenarios with pro’s & con’s are:
1. State of Alaska – AIDEA
Pro: Access to bond funds, loan guarantees,
Control determination on siting & location
could become owner/distributor/franchisee
Increased credibility at Toshiba, NRC, DOE
Con: AEA prohibited for nuclear projects
Educating the politicians to understand the viability of the operations,
no state commitment to become involved.
29
Ownership ContinuedOwnership Continued
2. Private corporations.
Pro: Access to capital
Faster decision making
Other energy facilities
Con: most likely not Alaska specific
Profitability primary decision making toolCherry picking
2. Private corporations.
Pro: Access to capital
Faster decision making
Other energy facilities
Con: most likely not Alaska specific
Profitability primary decision making toolCherry picking
30
Alaskan DemandAlaskan Demand
1. Communities
Several communities have already expressed interest in this energy source
Any community or group of communities with a combined load of 5 MGW or more would also benefit
2. Industry Remote or off grid mining companies need an alternative to the high
cost and transportation issues associated with diesel The size is also appropriate for some of the pipeline pump stations
1. Communities
Several communities have already expressed interest in this energy source
Any community or group of communities with a combined load of 5 MGW or more would also benefit
2. Industry Remote or off grid mining companies need an alternative to the high
cost and transportation issues associated with diesel The size is also appropriate for some of the pipeline pump stations
31
Prerequisites for DeploymentPrerequisites for Deployment
1. NRC approval of the 4s plant
2. Owner & Operations alternatives settled
3. Plant production schedules set
4. Predictable construction schedules
5. Funding for R & D
1. NRC approval of the 4s plant
2. Owner & Operations alternatives settled
3. Plant production schedules set
4. Predictable construction schedules
5. Funding for R & D