TFN Updates 8/8/03 Fiber Status • Backbone Fiber Status – Backbone all segments completed and tested except Athens to Columbus – Regen Hut in Lancaster pending 9/5/03 • Integration Engineering – Cleveland Integration complete • Toledo, Columbus, Youngstown, AFS - Pending Projects Akron, Cincinnati, Columbus, Dayton, Toledo, Youngstown

TFN Updates 8/8/03 Fiber Status Backbone Fiber Status –Backbone all segments completed and tested except Athens to Columbus –Regen Hut in Lancaster pending

Embed Size (px)

Citation preview

Page 1: TFN Updates 8/8/03 Fiber Status Backbone Fiber Status –Backbone all segments completed and tested except Athens to Columbus –Regen Hut in Lancaster pending

TFN Updates 8/8/03Fiber Status

• Backbone Fiber Status– Backbone all segments completed and tested

except Athens to Columbus– Regen Hut in Lancaster pending 9/5/03

• Integration Engineering– Cleveland Integration complete

• Toledo, Columbus, Youngstown, AFS

- Pending Projects Akron, Cincinnati, Columbus, Dayton, Toledo, Youngstown

Page 2: TFN Updates 8/8/03 Fiber Status Backbone Fiber Status –Backbone all segments completed and tested except Athens to Columbus –Regen Hut in Lancaster pending

TFN Updates 8/8/03Committee Updates

• Lighting and Architecture Committee– Unanimously approved Physical and Logical design

(see website for designs) 7/26/03– Optical/IP based network utilizing MPLS –fast reroute

Layer 3 protection (non-Sonet based network)– Approved Equipment selections

• Optical CISCO 15454• Router CISCO 12000

– Installation plan - SBC to install OARnet team to assist

Page 3: TFN Updates 8/8/03 Fiber Status Backbone Fiber Status –Backbone all segments completed and tested except Athens to Columbus –Regen Hut in Lancaster pending

TFN Updates 7/31/03Committee Updates

• Pricing Committee– Approved pricing model for the network 8/7/03– Components to include:

• membership dues• Ohio Connection fee• Internet 1 fee• Internet 2 fee• Service fee

– Model has been submitted to OSTEER Finance Committee for review

– Final model and fees to be determined by Finance Committee

Page 4: TFN Updates 8/8/03 Fiber Status Backbone Fiber Status –Backbone all segments completed and tested except Athens to Columbus –Regen Hut in Lancaster pending

TFN Updates 7/31/03Committee Updates

• Last Mile Committee– Completed review of the RFP– Reviewed by OSU Purchasing – RFP on hold pending OTA meeting and final

mailing list– RFP expected to be released by 8/25/03– Key changes:

• Added all K-12 sites• Approved vendor list

Page 5: TFN Updates 8/8/03 Fiber Status Backbone Fiber Status –Backbone all segments completed and tested except Athens to Columbus –Regen Hut in Lancaster pending

TFN Updates 7/31/03Committee Updates

• Implementation Committee– Key Milestones for Installation

• Completion of the Bill of Materials 8/5/03• Completion of the fiber Integration projects 9/29/03• Complete On-site visits Points of Presence (POPs) and Re-gen Sites

10/31/03• Complete pre-site preparation 10/31/03• Complete fiber characterization 10/31/03• Delivery of Equipment to the Staging Center 10/20/03• Complete Testing and burn-in at Staging Center 11/30/03• Complete on-site installation 1/30/04

– First Installation Team Meeting 7/31/03 SBC/CISCO/ODE/Schoolnet/OARnet

Page 6: TFN Updates 8/8/03 Fiber Status Backbone Fiber Status –Backbone all segments completed and tested except Athens to Columbus –Regen Hut in Lancaster pending

TFN Updates 7/31/03Committee Updates

• Implementation Committee– Key Milestones for Conversion

• Secure fiber connectivity between current POPs and new POPs 10/31/03

• Install 3750s to link from current POPs to the new 12000 routers 1/31/04

• Disconnect connect current leased backbone and convert service to TFN backbone 1/31/04

Page 7: TFN Updates 8/8/03 Fiber Status Backbone Fiber Status –Backbone all segments completed and tested except Athens to Columbus –Regen Hut in Lancaster pending

TFN Updates 7/31/03Committee Updates

• Implementation Committee– Conversion Objectives to expedite

• Elimination of the current leased backbone cost ($4,000 per day)

• Conversion from ATM service to IP

• Transitions of all Schools to the new backbone

Page 8: TFN Updates 8/8/03 Fiber Status Backbone Fiber Status –Backbone all segments completed and tested except Athens to Columbus –Regen Hut in Lancaster pending

TFN Updates 7/31/03Administrative Updates

• Ohio Telecom Association Meeting– To address open issues regarding TFN– Focus on Research, Education and Service– Not Competing with Telecos for services– Improve communications– Opportunities to participate– Share Policies

Page 9: TFN Updates 8/8/03 Fiber Status Backbone Fiber Status –Backbone all segments completed and tested except Athens to Columbus –Regen Hut in Lancaster pending

TFN Updates 8/8/03Administrative Updates

• Funding – Obtained Controlling Board Approval to purchase

equipment– Obtained BOR approval to transfer funds to OSUFocus

on Research, Education and Service– Obtained Schoolnet Funding for their Phase 1 Last

Mile sites– Seeking grant funding for Central State, Wilberforce,

Cedarville Last Mile– Seeking $5M funding from PUCO to expand POPs to

reduce Last Mile Costs