11
TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 [email protected] Engineering Operations April 2003

TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 [email protected] Engineering Operations April

Embed Size (px)

Citation preview

Page 1: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

TF Joint Testing Data Acquisition Special Test Equipment

Hans Schneiderwith Robert Marsala

(609) [email protected] Operations

April 2003

Page 2: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

Hans SchneiderEngineering Operations

2

Resistance Measurement PlanPrototype & Insitu Joints

• Mechanical Prototype Testing

• Electrical Prototype Testing

• Maintenance Insitu Testing

• Commissioning Insitu Testing

Page 3: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

Hans SchneiderEngineering Operations

4

Resistance Measurement PlanMechanical TF Joint Test System

• Mechanical Prototype Testing– Cyclical Mechanical Loads Applied to Prototype Joint

– Measure Joint Voltage Drop with 100 Amperes Applied

– Voltage Measured at Two Joint Locations

– Automated Test Stand Control & Data Acquisition

Page 4: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

Hans SchneiderEngineering Operations

5

Resistance Measurement PlanMechanical TF Joint Test System

• Mechanical Prototype Testing– Cyclical Mechanical Loads Applied to Prototype Joint

– Measure Joint Voltage Drop with 100 Amperes Applied

– Voltage Measured at Two Joint Locations

– Automated Test Stand Control & Data Acquisition

• Joint Voltage Drop Accuracy Factors– Limited by Cycle Time

– Initial Investigation Indicates 0.5% Should be Possible

– Cycle Dwells Could Increase Accuracy to 0.2% or Better

Page 5: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

Hans SchneiderEngineering Operations

8

Resistance Measurement PlanElectrical TF Joint Test System

• Electrical Prototype Testing– Cyclical Electrical Loads Applied to Prototype Joint

– Measure Joint Voltage Drop with > 70,000 Amperes Applied

– Voltage Measured at Up to Eight Joint Locations

– Remote Control of Automated Data Acquisition System

Page 6: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

Hans SchneiderEngineering Operations

9

Resistance Measurement PlanElectrical TF Joint Test System

• Electrical Prototype Testing– Cyclical Electrical Loads Applied to Prototype Joint

– Measure Joint Voltage Drop with > 70,000 Amperes Applied

– Voltage Measured at Up to Eight Joint Locations

– Remote Control of Automated Data Acquisition System

• Joint Voltage Drop Accuracy Factors– TF Power Supply Current Measurement Accuracy

– Magnetic Field Influences on Measurement Leads & System

– Unknown Accuracy at This Time

Page 7: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

Hans SchneiderEngineering Operations

12

Resistance Measurement PlanInsitu Maintenance Test System

• Maintenance Insitu Testing– Permanent Test Cell Installation

– Measure Joint Voltage Drop with +/-200 Amperes Applied

– Each of 48 Joints Measured at One Joint Location

– Automated Test Cell Data Acquisition System

Page 8: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

Hans SchneiderEngineering Operations

13

Resistance Measurement PlanInsitu Maintenance Test System

• Maintenance Insitu Testing– Permanent Test Cell Installation

– Measure Joint Voltage Drop with +/-200 Amperes Applied

– Each of 48 Joints Measured at One Joint Location

– Automated Test Cell Data Acquisition System

• Joint Voltage Drop Accuracy Factors– “Ambient” Electrical Noise & Long Joint Cable Leads

– Combat with DC Current Reversal & Long Integration Times

– Unknown Accuracy at This Time

Page 9: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

Hans SchneiderEngineering Operations

15

Resistance Measurement Plan Insitu Commissioning Test System

• Commissioning Insitu Testing– Utilizes Maintenance System Wiring

– Measure Joint Voltage Drop with Up to 72,000 Amperes

– Instrument One, Possibly Two TF Flag Joints

– Data Collected via 908 or 3232 Transient Digitizer

Page 10: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

Hans SchneiderEngineering Operations

16

Resistance Measurement Plan Insitu Commissioning Test System

• Commissioning Insitu Testing– Utilizes Maintenance System Wiring

– Measure Joint Voltage Drop with Up to 72,000 Amperes

– Instrument One, Possibly Two TF Flag Joints

– Data Collected via 908 or 3232 Transient Digitizer

• Joint Voltage Drop Accuracy Factors– TF Power Supply Current Measurement Accuracy

– Magnetic Field Influences on Measurement Leads & System

– Unknown Accuracy at This Time

Page 11: TF Joint Testing Data Acquisition Special Test Equipment Hans Schneider with Robert Marsala (609) 243-2017 hschneid@pppl.gov Engineering Operations April

Hans SchneiderEngineering Operations

21

Resistance Measurement PlanPrototype & Insitu Joints

• Mechanical Prototype Testing

• Electrical Prototype Testing

• Maintenance Insitu Testing

• Commissioning Insitu Testing