Testing and Commissioning Procedure for Motors _ EEP

Embed Size (px)

Citation preview

  • 8/10/2019 Testing and Commissioning Procedure for Motors _ EEP

    1/7

    12/1/13 Testing and Commissioning Procedure For Motors | EEP

    electrical-engineering-portal.com/testing-and-commissioning-procedure-for-motors 1/7

    Testing and Commissioning Procedure For

    Motors

    Testing and Commissioning Procedure For Motors // Photo by TECO Middle East (TME)

    Scope Of Motor Testing

    It should be noted that the scope of motor testing depends upon the motor type and size, this being

    indicated on the inspection forms.

    Motor vibration shall be measured in a tri-axial direction, i.e.:

    Point x axis side of bearing housing at shaft height

    Point y axis top of bearing housing

    Point z axis axial of bearing housing at shaft height

    http://electrical-engineering-portal.com/testing-and-commissioning-procedure-for-motorshttp://electrical-engineering-portal.com/7-most-common-motor-enclosure-types-defined-by-nema-standardshttp://electrical-engineering-portal.com/testing-and-commissioning-procedure-for-motors
  • 8/10/2019 Testing and Commissioning Procedure for Motors _ EEP

    2/7

    12/1/13 Testing and Commissioning Procedure For Motors | EEP

    electrical-engineering-portal.com/testing-and-commissioning-procedure-for-motors 2/7

    The measurements shall be carried out with an instrument conforming to ISO 2954 (10-1000

    Hz frequency range). With the motor at normal operating temperature, the vibration velocity shall not

    exceed 2.8 mm/s RMS, or 4 mm/s PEAK, in any direction.

    For bearings fitted with proximity probes, the unfiltered peak-to-peak value of vibration (including shaft

    run-out) at any load between no load and full load, shall not exceed the following values:

    50 m for two-pole motors60 m for four-pole motors

    75 m for six-pole or higher motors

    Motor bearing (photo by CCLW INTERNATIONAL)

    Bearing temperature rise limits following a heat run of 3.5 4 hours are as follows:

    Rolling bearings:

    Outer ring measurement max. 90 C

    Temperature rise from ambient max. 50 C

    Sleeve bearings:

    Oil temperature max. 90 C

    Bearing temperature rise by RTD max. 50 CLub. oil temperature rise from ambient max. 30 C (for forced lub. oil systems).

    When commissioning or re-commissioning motors, precautions shall be taken to avoid excessive

    http://www.iso.org/iso/catalogue_detail.htm?csnumber=21835
  • 8/10/2019 Testing and Commissioning Procedure for Motors _ EEP

    3/7

    12/1/13 Testing and Commissioning Procedure For Motors | EEP

    electrical-engineering-portal.com/testing-and-commissioning-procedure-for-motors 3/7

    vibrationcaused by the phenomenon known as soft foot; i.e. feet which do not have solid flat contact

    with the base prior to the tightening of the holding-down bolts.

    This may be measured and rectified during installation or detected during running by the loosening of

    each holding-down bolt in turn while measuring motor vibration.

    Motor Soft Foot Condition

    Soft feet are those which do not have solid flat contact with the base prior to the tightening of the

    holding-down bolts; one or more feet may be soft as shown in Figures 1 to 3.

    The profile of the foot contact area may be as shown in Figures 4 to 6.

    The profile of the foot contact area (Figures 1, 2 and 3)

    Figure 1- Machine resting on 3 feet, foot 4 is raised or soft

    Figure 2 - Machine resting on diagonal formed by feet 3 and 4, feet 1 and 4 are soft

    Figure 3 - Bottoms of all 4 feet are not parallel with base, feet 3 and 4 are soft

    Profile of 'soft foot' contact area

    NOTE:Re-machining of rotor feet is required in Figures 4 and 5; temporary use of wedge-shaped

    shims may be acceptable (maintenance).

    Advertisement

    http://electrical-engineering-portal.com/advertisementhttp://electrical-engineering-portal.com/selection-of-crane-duty-motors-part-2
  • 8/10/2019 Testing and Commissioning Procedure for Motors _ EEP

    4/7

    12/1/13 Testing and Commissioning Procedure For Motors | EEP

    electrical-engineering-portal.com/testing-and-commissioning-procedure-for-motors 4/7

    Forms

    Form 14 Inspection of electric motor Cage-induction type(incl. control unit)

    Inspection of electric motor cage-induction type (including control unit)

    http://electrical-engineering-portal.com/direct-starting-of-squirrel-cage-induction-motors
  • 8/10/2019 Testing and Commissioning Procedure for Motors _ EEP

    5/7

    12/1/13 Testing and Commissioning Procedure For Motors | EEP

    electrical-engineering-portal.com/testing-and-commissioning-procedure-for-motors 5/7

    Form 4 Inspection of Switching Units HV Switchgear

    Inspection of Switching Units - HV Switchgear

    Form 11 Inspection Of Outgoing Unit LV Switchboard

  • 8/10/2019 Testing and Commissioning Procedure for Motors _ EEP

    6/7

    12/1/13 Testing and Commissioning Procedure For Motors | EEP

    electrical-engineering-portal.com/testing-and-commissioning-procedure-for-motors 6/7

    Inspection Of Outgoing Unit - LV Switchboard

    Reference:Field Commissioning and Maintenance Of Electrical Installations and Equipment Manual

    Recommended EE articles

  • 8/10/2019 Testing and Commissioning Procedure for Motors _ EEP

    7/7

    12/1/13 Testing and Commissioning Procedure For Motors | EEP

    electrical-engineering-portal.com/testing-and-commissioning-procedure-for-motors 7/7

    2013 EEP - Electrical Engineering Portal. All Rights Reserved | Privacy Policy| 40 queries in 0.668

    seconds.

    Powered by CsanyiGroup

    Edvard- Electrical engineer, programmer and founder of EEP. Highly specialized for

    design of LV high power busbar trunking (