ABUDHABI FUTURE SCHOOL PROGRAME PHASE 2 PACKAGE 4 AL-FALAH AND AL-BAHYA Method Statement for Testing of GRP WATER TANK Project Name: ADEC Future School Phase 2 Package 4 @ Al-Falah and Al-Bahya Document No. : ASEM-MTST-PL-01 Revision : 00 Dated : 14/08/2013

Testing and Commissioning of Grp Water Tank

Embed Size (px)

DESCRIPTION

Testing and Commissioning of Grp Water Tank

Citation preview

Page 1: Testing and Commissioning of Grp Water Tank

ABUDHABI FUTURE SCHOOL PROGRAME PHASE 2 PACKAGE 4AL-FALAH AND AL-BAHYA

Method Statement for

Testing of

GRP WATER TANK

Project Name: ADEC Future School Phase 2 Package 4 @ Al-Falah and Al-Bahya

Document No. : ASEM-MTST-PL-01

Revision : 00

Dated : 14/08/2013

Page 2: Testing and Commissioning of Grp Water Tank

ABUDHABI FUTURE SCHOOL PROGRAME PHASE 2 PACKAGE 4AL-FALAH AND AL-BAHYA

INDEX

1:- DEFINITIONS

2:- INTRODUCTION

3:- PURPOSE

4:- SCOPE

5:- REFERENCES

6:- QUALITY CONTROL

7:- MATERIAL, TOOLS, EQUIPMENTS, HOUSE KEEPING & PPE

8:- PRE COMMISSIONING PROCEDURE

9:- COMMISSIONING PROCEDURE

10:- PROJECT CONTROLS

11:- TEST REPORT

Page 3: Testing and Commissioning of Grp Water Tank

ABUDHABI FUTURE SCHOOL PROGRAME PHASE 2 PACKAGE 4AL-FALAH AND AL-BAHYA

1.0- DEFINITIONS

Consultant : M/s. Dewan

Main Contractor : M/s. United Engineering Construction

MEP Sub Contractor : M/s. Al Sabbah Electromechanical Co.

The Project : ADEC Future School Phase 2 Package 4 @ Al-Falah and Al-Bahya

2.0- INTRODUCTIONGRP water tank Method statement for Testing for the project - ADEC Future School, Phase 4 Package

2 @ Al-Falah and Al-Bahya

3.0- PURPOSE

This Work Method Statement (WMS) is to describe the method of which the testing of GRP water tank is

carried out for this project.

The aim and /or benefits of complying with this WMS include: Program Compliance, Health, Safety, and

Quality and Environmental company policy compliance.

4.0- SCOPE

The method of testing for GRP water tank for the project- ADEC Future School, Phase 4 Package 2

5.0- REFERENCES

Project Specification

Contract drawings

Approved Shop Drawings

Approved material submittal

Project Safety Plan

Project Quality Plan

6.0- QUALITY CONTROL

Page 4: Testing and Commissioning of Grp Water Tank

ABUDHABI FUTURE SCHOOL PROGRAME PHASE 2 PACKAGE 4AL-FALAH AND AL-BAHYA

Quality control on site will be expedited through the project team using qualified and experienced

Foreman with Engineers verifying their works and hold point approval by the QC Engineer.

The QC engineer will carry out the inspection in line with the documentation referenced in ITP.

7.0- MATERIALS, TOOLS, EQUIPMENT AND PPE

7.1- MATERIALSFor the purposes of this method statement it is considered that all materials to be used for the tasks

mentioned, will have been though the materials submission/ approval process and also will have been

inspected on arrival to site for technical and material compliance by the relevant parties in accordance

with the approved project Quality Management plan.

7.2/7.3- TOOLS & EQUIPMENTLadder, torch, screw wrench, mechanical tools

7.4- HOUSE KEEPING

All work places where personnel are working will be cleaned from the scrap materials derived from their works, ensuring clean and healthy work environment as well as to maintain free access and egress in the event of emergency.

7.5- PPEHard Hat, High Vis Vest, Safety Boots (mandatory)

Eye Protection (mandatory)

Safety harness to be provided while working at height

8.0 - PRE COMMISSIONING PROCEDURE

8.1 Visual Inspection Prior to perform the Test of GRP water tank, the following visual Inspection shall be checked:

a) Check for approved make and recommended materials by the manufacturer / supplier are used at site.

b) Check all the tank is installed according to the approved shop Drawings.

c) Visual check of the system.

9.0 - TESTING PROCEDURE

Page 5: Testing and Commissioning of Grp Water Tank

ABUDHABI FUTURE SCHOOL PROGRAME PHASE 2 PACKAGE 4AL-FALAH AND AL-BAHYA

The following are to be checked prior to handover of the Fire Sprinkler System to the Clients/ End Users.

1. Fill the tank with water.2. Close the valves of outgoing network.3. Leave the water for at least 05 hours.4. Check for any leaks from tank.

10.0 PROJECT CONTROLS

Quality Controls

Project specific Inspection & test plan (ITP) relating to the works

Project specific QA/QC checklist relating to these works

These works will be managed in accordance with the Quality Plan structure and the Project wide audit program.

Safety Controls

All operatives must have undertaken the Main Contractors & Hastie Internationals safety induction prior to commencing any works on site.

Pressure testing area will be cordoned off.

Adequate signage will be provided and unauthorized entry will be restricted to the premises.

Pre-start check will be done on all equipments.(fittings, gauges ,etc).

Pressure testing will be notified to concerned people.

Material Safety Data Sheet (MSDS) will be provided for all hazardous materials

Proper lighting arrangements to be provided during installation services.

Full and correct safety induction to be carried out by the safety officer to all the people before going to the site.

Tool box talks (TBT) will be carried out on applicable subjects prior to commencing works. TBT records will be maintained, included in the monthly statistics and a record will be provided to the Main Contractor within 24 hours of the TBT being conducted.

Any trenches must be made safe by the Main Contractor prior to Hastie International employees entering the trench using a safe method i.e. shoring. Prior to any works commencing in trenches a PTW must be obtained from the Main Contractor. A thorough inspection must be made of any trench by both the Main Contractor’s supervisor and the Hastie International supervisor prior to entering the trench. If there is any doubt by the operatives or supervision carrying out the work with regard to safety then the work shall not proceed. All trenches must be thoroughly inspected following any adverse weather conditions and if required the senior management / safety department may be consulted to ensure that trenches are safe to work in.

All power tools must be 110V, if higher voltage power tools are required to be used then special permission must be applied for from the main Contractor via a permit to work system.

Page 6: Testing and Commissioning of Grp Water Tank

ABUDHABI FUTURE SCHOOL PROGRAME PHASE 2 PACKAGE 4AL-FALAH AND AL-BAHYA

11:- TEST REPORT