Term Project: Waste Transfer Station Part II

Embed Size (px)

Citation preview

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    1/31

    Term Project:Waste Transfer Station

    P t II

    MIDDLE EAST TECHNICAL UNIVERSITY

    I E 3 7 2 S I M U L A T I O N

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    2/31

    P t II

    Table of Contents

    Page

    Table of Contents 1

    1. INTRODUCTION.... 2

    2. OUTPUT ANALYSIS...................................................................................................... 2

    2.1. Performance Measures.............................................................................................. 2

    2.2. Alternative Scenarios..................................................................................... 4

    2.3. Output Analysis................................................................................................. 7

    2.3.1 Eliminating Initial Bias for Alternative 1. 7

    2.3.2 Eliminating Initial Bias for Alternative 2 10

    2.4. Estimations on Alternative Scenarios.. 12

    2.4.1. Estimations on Primary Performance Measures.......................... 13

    2 4 2 E ti ti S d P f M...................... 14

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    3/31

    1. INTRODUCTION

    In the first part of this project, the given waste management system is modeled and

    some alternative scenarios are generated as initial thoughts. The aim of the second part of the

    project is to analyze these alternatives by modifying the model constructed in the previous

    part and interpreting the outputs of these models. At the end of this project, the modified

    simulation model which is satisfying the goals of the manager will be suggested as

    recommendations. Since this is a simulation based project, this suggested model will not

    necessarily be the optimal configuration; however it will be compared with the all other

    options and the one which fits to objectives best will be suggested. In addition, numerical

    results of implementing this suggestion will be provided in detail throughout the report. The

    model which is used throughout this report is thefirst simulation model which is shared as the

    answer of the Project Part 1.

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    4/31

    3

    Port Crane ConveyorMetal

    Gatherer

    Manual

    Process

    Area

    Worker

    Group 1

    Worker

    Group 2Notes

    First Step 39,39 34,68 99,90 60,84 99,35 99,79 39,58

    Iteration 1

    Iteration 2 38,39 67,31 99,80 39,18 99,89 96,87 77,671 "Manual Process Area", 1 "Worker Group 1"

    and 2 "Metal Gatherer" added

    Iteration 3 40,59 69,41 99,73 40,43 99,89 99,88 80,12 1 "Manual Process Area" added

    Iteration 4 38,97 84,86 99,29 49,39 99,83 81,46 97,97 1 "Worker Group 1" added

    Iteration 5 38,78 95,07 96,32 55,51 99,73 91,29 54,69 1 "Worker Group 2" added

    Iteration 6 40,09 47,35 99,87 55,29 99,33 90,91 54,50 2 "Crane" added

    Iteration 7 38,84 51,54 99,99 60,15 99,60 98,93 59,39 1 "Manual Process Area" added

    Iteration 8 39,45 59,24 99,79 69,07 97,87 85,29 68,34 1 "Worker Group 1" added

    Iteration 9 39,99 65,02 99,51 75,69 94,79 93,62 75,07 1 "Manual Process Area" added

    Iteration 10 39,73 66,13 99,40 77,12 93,33 95,19 76,29 1 "Manual Process Area" added

    Alternative 1 40,13 44,57 98,28 78,01 80,44 74,35 76,951 "Worker Group 1" added # of workers in

    Worker Group 1 =11. Worker Group 2 =10

    Final

    numbers:2,00 3,00 1 3 7 5 2 Resource levels of Alternative 1

    Alternative 2 38,55 42,84 97,72 74,95 85,69 55,09 77,092 more "Worker Group 1" # of workers in

    Worker Group 1 = 9. Worker Group 2 = 9Final

    numbers:2 3 1 3 7 7 2 Resource levels of Alternative 2

    Table 2.2.1: Utilizations of iterations and alternatives (All values in percentages) (Gathered from related ARENA Simulation Outputs)

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    5/31

    2.2. Alternative Scenarios

    In order to decide on the alternative scenarios, the given model is run, statistics are

    collected and the bottlenecks are tried to be found. To reach a feasible solution that satisfies

    the goals of the manager, a step by step approach is used. In order to see the bottlenecks of

    each step easier, the utilization of the resources are tabulated as can be seen in Table 2.2.1 on

    previous page.

    In this step-by-step approach, utilization statistics are collected at each run and the

    bottlenecks are shown by highlighting in the table above. Bottlenecks are thought as the

    resources with the highest true utilization level and dependency of these utilizations are also

    considered such as worker groups and manual process areas. Iterations are proceed until there

    is a configuration which concludes remaining waste flow time less than 180 minutes as

    averages of a number of replication averages. At each iteration, if the utilization levels are

    close to each other and maximum level, cost of making these investments are taken into

    consideration as:

    I i th b f t $900 000 d $15 000 ll

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    6/31

    Resource Number

    Port 2

    Crane 3

    Conveyor 1

    Metal Gatherer 3

    Manual Process Area 7

    Worker 5 x First Group (x 11) + 2 x Second Group (x 10) = 75

    Table 2.2.2 : Alternative 1 configuration

    In Alternative 1, when the given configuration in the Table 2.2.2 above concluded that

    the simulation model reaches a remaining waste flow time less than 180 minutes when

    average of replication averages are checked. ARENA Simulation output for this alternative

    which shows that the remaining waste flow time is less than 180 minutes and satisfies the goal

    of manager can found from Appendix 4.1. For this configuration, annual operation,

    investment and total costs are calculated in the Table 2.2.3 below.

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    7/31

    As tabulated in Table 2.2.3, Alternative 1 yields a total cost of $ 6.088.000 for two

    years when all annual operation, investment cost and monthly wages of workers are taken into

    consideration.

    In Alternative 2, configuration only changes for the number of worker groups and

    number of workers in these groups. Configuration of Alternative 2 is presented in the Table

    2.2.4 below:

    Resource Number

    Port 2

    Crane 3

    Conveyor 1

    Metal Gatherer 3

    Manual Process Area 7

    Worker 7 x First Group (x 9) + 2 x Second Group (x 9) = 81Table 2.2.4 : Alternative 2 configuration

    The effect of this change in configuration on the cost figures can be seen from the

    Table 2.2.5 below. As presented, Alternative 2 yields a total cost of $ 6.304.000 for two years

    when all related cost items are taken into consideration. ARENA Simulation Output of this

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    8/31

    When these two alternative models are run for three months, the final value of the

    total revenues tally is found to be nearly one fourth of the total cost for two years. So it is

    thought that both alternatives will achieve the profit goal of the manager. Since these two last

    alternatives satisfy all objectives and both are the result of step-by-step increase from scratch,

    they will be regarded as best possible suggestions and will be studied as main alternative

    options in the rest of this report.

    2.3. Output Analysis

    In this part, since this station works continuously and simulation model is constructed

    to start from zero, this effect of the initializing will be eliminated. In order to achieve this, for

    each two alternatives, moving averages of primary performance measures will be plotted and

    the time where the line starts to stabilize approximately will be taken as the truncation point.

    Considering these truncation points, a relatively long replication length will be chosen to

    eliminate effects of this initial bias.

    2.3.1 Eliminating Initial Bias for Alternative 1

    C id i h i f hi h h b f l i

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    9/31

    Graph 2.3.1.2: Flow time of remaining waste versus time (Moving average)

    In order to eliminate effect of initial bias, we need to find a point where these two

    plots are get stabilized thereafter. Therefore, by observing the plots, approximately 30000

    i t i l t d f t ti i t I dditi i d t li i t ff t f thi t

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    10/31

    Summary 2.3.1.2: Confidence interval for remaining waste flow time (3 replications - Alternative 1)

    In order to decide number of replications, target half-width is calculated by multiplying

    the outputs mean and determined precision; then it is compared with the half-width level

    gathered from output. Since target half-width (156 x 0.08 = 12.48) is less than what is

    gathered for the 3 replications (18.3), required number of replications is calculated according

    to the formula given in lecture notes and found to be 8.

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    11/31

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    12/31

    Graph 2.3.2.2: Flow time of remaining waste versus time (Moving average)

    With the same approach used in the last part, by observing the plots, approximately

    30000 minutes is selected for truncation point. In addition, in order to eliminate effects of this

    h h l i i li i l h i l d b l i l l h 30000

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    13/31

    Summary 2.3.2.2: Confidence interval for remaining waste flow time (3 replications - Alternative 2)

    In order to decide sufficient number of replications, target half-width is calculated

    (177.74 x 0.08 = 14.24) and compared with the half-width gathered from summary output

    above. Since target level is less than what is calculated for the 3 replications (17), required

    number of replications is calculated according to the formula given in lecture notes and found

    to be 5.

    Therefore, in order to reduce variance, 5 replications with truncating first 30000 minutes

    and with a replication length of at least 3 months will be used in the next parts of the report.

    With this approach, ARENA Simulation Report of the last replication is given in the

    A di 4 4 ARENA O f Al i 2 (T d) Al i b i d

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    14/31

    Summary 2.3.2.3: Confidence interval for remaining waste flow time (5 replicationsAlternative 2)

    2.4. Estimations on Alternative Scenarios

    While estimating the performance measures, 3-month replication period after

    truncation and five replications are used for both of the alternatives to compare them with the

    similar conditions. Averages of replication averages are used to estimate mean; and sample

    variance of the replications is used to estimate the standard deviation. The formulas used are

    i d

    2

    i i )

    2

    M h i d i d

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    15/31

    As can be seen from the tables above, Alternative 1 has higher revenue estimation

    than the Alternative 2. In addition, when estimations of remaining waste flow time taken into

    consideration, Alternative 1 also has a better (in that sense, smaller) flow time. When standard

    deviation estimations are checked, it shows that Alternative 2 has higher diversity than

    Alternative 1 which is not desirable.

    (Actually there are 8 replications for Alternative-1, but only five of them are presented

    here)

    2.4.2. Estimations on Secondary Performance Measures

    Since secondary performance measures are only checked to diagnose any problems of

    system, their calculations are provided for any further investigation in Appendix 4.5 -

    Estimations of Secondary Performance Measures. The only point to mention about these

    measures that although the second alternative seems to use all resources a little bit more

    efficient than the first alternative, its crane queue storage has a higher level and its standard

    deviation estimation shows that this level is not so precise because standard deviation

    estimation is very close to the mean estimation.

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    16/31

    This output shows that, for 2 years Alternative 1 has an expected revenue level of $

    13.266.800 and with 99 % confidence this level will not be dropped less than $ 13.159.0007.

    Considering high precision level and low variations from minimum and maximum levels of

    interval, this alternative can be regarded as a reliable alternative in monetary issues. For

    further analysis, output of the last replication of 2 year-run for this alternative is provided in

    Appendix 4.6 - ARENA Output of Alternative 1 (2-year-run)

    2.5.2. Cost Benefit Analysis for Alternative 1

    According to the study conducted, Alternative 1s revenue within two year is

    approximately $13,266,800 and the cost of investment is $3,210,000 which reveals that the

    revenue is far sufficient to cover the investment. Moreover, if the investment costs considered

    with the total operation costs during this time period which is $6,088,000, revenues even

    sufficient to cover such cost and the profit of the company would be near $7,178,800.

    2.5.3 Confidence Interval Construction for Alternative 2

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    17/31

    with other measures, it can be directly said that this high difference of maximum and

    minimum of confidence interval can create problems in business environment. For further

    investigation, output of the last replication of 2 year-run for this alternative is provided in

    Appendix 4.7 - ARENA Output of Alternative 2 (2-year-run)

    2.5.4. Cost Benefit Analysis for Alternative 2

    As for the Alternative 2s revenues within two year, it is approximately $12,817,500

    although the cost of investment is the same $3,210,000. However, the revenue is still far

    sufficient to cover the investment. Moreover, if the investment costs considered with the total

    operation costs during this time period is $6,304,000, which is increased; but, revenues even

    sufficient to cover such cost and the profit of the company would be near $7,178,800.

    However, flow time of remaining waste is increased although the operation cost is increased.

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    18/31

    3. CONCLUSIONS

    To conclude, both alternative systems have same investment costs; however they

    differ in operation costs. Moreover, they both could cover their overall costs by far at the end

    of two year time period. However, Alternative-1 has both lower operation cost and better

    remaining waste flow time in terms of both length of the average flow time and reliability of

    this average flow time. As a result, the proper suggestion for the company is Alternative-1.

    Conducting this project, there are mainly two difficulties which are faced by this

    group. The first one is that the model which is given as the solution of Part I is a little more

    professional than the ones covered in the lectures and recitations. For example, there are

    differentblocks in model and different approaches of modeling like using While blocks to

    model conditional situations. Although it was not so difficult to understand how the model

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    19/31

    18

    4. APPENDIX

    4.1. ARENA Output of Alternative 1

    ARENA Simulation ResultsDepartment of Industrial EngineeringSummary for Replication 1 of 1

    Project: Unnamed Project Run execution date : 5/27/2011Analyst: Department of Industrial Engineering Model revision date: 5/27/2011

    Replication ended at time : 129600.0 MinutesBase Time Units: Minutes

    TALLY VARIABLES

    Identifier Average Half Width Minimum Maximum Observations___________________________________________________________________________________________________

    plasticFlowTime 159.91 15.699 33.625 539.08 86613glassFlowTime 196.75 15.328 32.255 592.47 86559paperFlowTime 140.23 16.028 32.160 516.27 86635glassTruckTally 1006.5 .23043 1000.0 1016.4 1079compostFlowTime 2018.2 31.892 1465.2 2605.8 10196remainingFlowTime 155.69 15.786 35.127 523.18 86627plasticTruckTally 1016.7 .36196 1000.0 1037.6 2820

    organicFlowTime 1095.7 (Corr) 61.979 2553.6 76439metalFlowTime 133.31 15.996 24.991 510.16 86634

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    20/31

    19

    DISCRETE-CHANGE VARIABLES

    Identifier Average Half Width Minimum Maximum Final Value___________________________________________________________________________________________________

    Crane True Utilization 133.71 3.3314 .00000 300.00 300.00metalRevenue+plasticRevenue+glassRevenue+o 8.3192E+05 (Corr) .00000 1.6687E+06 1.6687E+06Number in Crane Queue 53.747 9.1323 .00000 361.00 19.000Crane Utilization 251.12 7.1549 .00000 300.00 300.00metalRevenue 3.3147E+05 (Corr) .00000 6.6376E+05 6.6376E+05Worker Group 2 Utilization 153.90 3.8044 .00000 200.00 .00000Number in Port Queue .09205 .01290 .00000 6.0000 .00000Port Utilization 40.126 1.1541 .00000 100.00 50.000Metal Gatherer Utilization 256.18 6.6050 .00000 300.00 .00000organicRevenue 73785. (Insuf) .00000 1.5075E+05 1.5075E+05NR(conveyor) 9.8278 .02484 .00000 10.000 9.0000landfillCost 1.5125E+05 (Corr) .00000 3.0289E+05 3.0289E+05

    Worker Group 1 Utilization 371.76 9.3105 .00000 500.00 .00000Metal Gatherer True Utilization 234.02 6.0144 .00000 300.00 .00000paperRevenue 88102. (Corr) .00000 1.7646E+05 1.7646E+05NR(workerArea) 5.6309 .13965 .00000 7.0000 .00000compostRevenue 6041.1 (Insuf) .00000 11885. 11885.NUMENT 855.50 27.346 1.0000 2072.0 142.00glassRevenue 4.1221E+05 (Corr) .00000 8.2538E+05 8.2538E+05Number in Conveyor 8.9983 (Corr) .00000 9.0000 9.0000plasticRevenue 71571. (Corr) .00000 1.4336E+05 1.4336E+05

    Simulation run time: 1.68 minutes.Simulation run complete.

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    21/31

    20

    4.2. ARENA Output of Alternative 2

    This output shows that the Alternative 2 has remaining waste flow time less than 180 minutes.

    ARENA Simulation ResultsDepartment of Industrial EngineeringSummary for Replication 1 of 1

    Project: project Run execution date : 5/26/2011Analyst: aykutKerem Model revision date: 5/26/2011

    Replication ended at time : 129600.0 MinutesBase Time Units: Minutes

    TALLY VARIABLES

    Identifier Average Half Width Minimum Maximum Observations___________________________________________________________________________________________________

    plasticFlowTime 148.68 10.265 34.055 452.99 83244glassFlowTime 189.33 9.5605 33.464 521.92 83197paperFlowTime 128.42 10.794 31.783 427.80 83266glassTruckTally 1006.2 .30893 1000.0 1015.4 993compostFlowTime 2001.0 25.035 1482.3 2429.4 9495remainingFlowTime 141.84 10.555 36.105 449.07 83255plasticTruckTally 1016.0 .37176 1000.0 1037.0 2677organicFlowTime 1113.5 31.757 44.730 2415.6 73771metalFlowTime 120.63 10.756 24.671 420.09 83265

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    22/31

    21

    DISCRETE-CHANGE VARIABLES

    Identifier Average Half Width Minimum Maximum Final Value___________________________________________________________________________________________________

    Crane True Utilization 128.51 (Corr) .00000 300.00 .00000

    metalRevenue+plasticRevenue+glassRevenue+o 7.4940E+05 (Corr) .00000 1.5071E+06 1.5071E+06Number in Crane Queue 43.566 (Corr) .00000 292.00 .00000Crane Utilization 235.04 (Corr) .00000 300.00 .00000metalRevenue 3.1709E+05 (Corr) .00000 6.3680E+05 6.3680E+05Worker Group 2 Utilization 154.17 (Corr) .00000 200.00 .00000Number in Port Queue .08515 .01151 .00000 5.0000 .00000Port Utilization 38.553 (Corr) .00000 100.00 50.000Metal Gatherer Utilization 241.12 (Corr) .00000 300.00 .00000organicRevenue 70767. (Insuf) .00000 1.4468E+05 1.4468E+05NR(conveyor) 9.7716 (Corr) .00000 10.000 9.0000landfillCost 1.7409E+05 (Corr) .00000 3.4947E+05 3.4947E+05Worker Group 1 Utilization 385.64 (Corr) .00000 700.00 .00000

    Metal Gatherer True Utilization 224.85 (Corr) .00000 300.00 .00000paperRevenue 84119. (Corr) .00000 1.6883E+05 1.6883E+05NR(Zipper) .08150 (Corr) .00000 1.0000 .00000NR(workerArea) 5.9981 (Corr) .00000 8.0000 .00000compostRevenue 5407.9 (Insuf) .00000 10928. 10928.NUMENT 832.04 30.377 1.0000 1992.0 116.00glassRevenue 3.7838E+05 (Corr) .00000 7.5936E+05 7.5936E+05Number in Conveyor 8.9983 (Corr) .00000 9.0000 9.0000plasticRevenue 67723. (Corr) .00000 1.3600E+05 1.3600E+05

    Simulation run time: 2.12 minutes.Simulation run complete.

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    23/31

    22

    4.3. ARENA Output of Alternative 1 (Truncated)

    ARENA Simulation ResultsDepartment of Industrial Engineering

    Summary for Replication 8 of 8

    Project: project Run execution date : 5/27/2011Analyst: aykutKerem Model revision date: 5/27/2011

    Replication ended at time : 129600.0 MinutesStatistics were cleared at time: 30000.0 Minutes (Thursday, June 16, 2011, 20:00:00)Statistics accumulated for time: 99600.0 MinutesBase Time Units: Minutes

    TALLY VARIABLES

    Identifier Average Half Width Minimum Maximum Observations

    ___________________________________________________________________________________________________

    plasticFlowTime 160.94 19.071 34.323 602.93 64282glassFlowTime 199.49 18.254 34.216 678.51 64260paperFlowTime 140.63 19.606 33.175 597.29 64287glassTruckTally 1006.4 .29059 1000.0 1015.8 801compostFlowTime 2033.0 30.539 1570.0 2472.7 8044remainingFlowTime 156.33 19.211 36.091 607.74 64290plasticTruckTally 1016.8 .44104 1000.0 1037.3 2092organicFlowTime 1097.3 32.944 44.494 2500.9 57737metalFlowTime 133.76 19.617 25.783 589.26 64284

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    24/31

    23

    DISCRETE-CHANGE VARIABLES

    Identifier Average Half Width Minimum Maximum Final Value___________________________________________________________________________________________________

    Crane True Utilization 129.07 5.0369 .00000 300.00 .00000metalRevenue+plasticRevenue+glassRevenue+o 9.9191E+05 (Corr) 3.7094E+05 1.6110E+06 1.6110E+06Number in Crane Queue 51.892 15.073 .00000 406.00 .00000Crane Utilization 241.11 10.648 .00000 300.00 .00000metalRevenue 3.9470E+05 (Corr) 1.4828E+05 6.3991E+05 6.3991E+05Worker Group 2 Utilization 148.56 5.8113 .00000 200.00 200.00Number in Port Queue .09077 .02221 .00000 5.0000 .00000Port Utilization 38.651 1.7442 .00000 100.00 50.000Metal Gatherer Utilization 247.11 9.8440 .00000 300.00 .00000organicRevenue 88337. (Insuf) 31194. 1.4517E+05 1.4517E+05NR(conveyor) 9.7942 .03694 9.0000 10.000 9.0000landfillCost 1.8041E+05 (Corr) 67934. 2.9269E+05 2.9269E+05

    Worker Group 1 Utilization 358.85 14.043 .00000 500.00 100.00Metal Gatherer True Utilization 225.83 8.7806 .00000 300.00 .00000paperRevenue 1.0506E+05 (Corr) 39611. 1.7034E+05 1.7034E+05NR(workerArea) 5.4375 .21357 .00000 7.0000 4.0000compostRevenue 7287.0 (Insuf) 2558.9 11921. 11921.NUMENT 834.07 35.249 45.000 1994.0 100.00glassRevenue 4.9159E+05 (Corr) 1.8513E+05 7.9785E+05 7.9785E+05Number in Conveyor 9.0000 .00000 8.0000 9.0000 9.0000plasticRevenue 85340. (Corr) 32132. 1.3849E+05 1.3849E+05

    Simulation run time: 6.27 minutes.

    Simulation run complete.

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    25/31

    24

    4.4. ARENA Output of Alternative 2 (Truncated)

    ARENA Simulation ResultsDepartment of Industrial EngineeringSummary for Replication 5 of 5

    Project: project Run execution date : 5/27/2011Analyst: aykutKerem Model revision date: 5/27/2011

    Replication ended at time : 129600.0 MinutesStatistics were cleared at time: 30000.0 Minutes (Thursday, June 16, 2011, 20:00:00)Statistics accumulated for time: 99600.0 MinutesBase Time Units: Minutes

    TALLY VARIABLES

    Identifier Average Half Width Minimum Maximum Observations___________________________________________________________________________________________________

    plasticFlowTime 183.88 18.895 34.738 586.94 65939glassFlowTime 224.13 17.511 34.761 651.15 66012paperFlowTime 164.24 19.554 34.621 578.94 65942glassTruckTally 1006.1 (Corr) 1000.0 1015.4 787compostFlowTime 2010.6 27.531 1473.3 2485.1 8017remainingFlowTime 177.45 19.233 38.276 591.77 65939plasticTruckTally 1016.2 .54106 1000.0 1037.2 2119

    organicFlowTime 1136.0 40.792 36.584 2437.7 58987metalFlowTime 156.84 19.548 26.135 572.38 65940

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    26/31

    25

    DISCRETE-CHANGE VARIABLES

    Identifier Average Half Width Minimum Maximum Final Value___________________________________________________________________________________________________

    Crane True Utilization 132.41 4.3247 .00000 300.00 200.00

    metalRevenue+plasticRevenue+glassRevenue+o 9.4963E+05 (Corr) 3.4954E+05 1.5461E+06 1.5461E+06Number in Crane Queue 68.844 14.825 .00000 388.00 41.000Crane Utilization 259.24 9.6276 .00000 300.00 300.00metalRevenue 4.0267E+05 (Corr) 1.4917E+05 6.5437E+05 6.5437E+05Worker Group 2 Utilization 158.69 5.2198 .00000 200.00 200.00Number in Port Queue .08230 .01264 .00000 5.0000 .00000Port Utilization 39.721 1.2428 .00000 100.00 50.000Metal Gatherer Utilization 263.41 8.8116 .00000 300.00 300.00organicRevenue 88412. (Insuf) 31171. 1.4657E+05 1.4657E+05NR(conveyor) 9.8589 .03320 9.0000 10.000 10.000landfillCost 2.2037E+05 (Corr) 81601. 3.5809E+05 3.5809E+05Worker Group 1 Utilization 397.11 13.017 .00000 700.00 500.00

    Metal Gatherer True Utilization 231.69 7.5515 .00000 300.00 300.00paperRevenue 1.0671E+05 (Corr) 39544. 1.7336E+05 1.7336E+05NR(workerArea) 5.9039 .19485 .00000 7.0000 7.0000compostRevenue 7674.1 (Insuf) 2861.0 12063. 12063.NUMENT 873.06 37.968 37.000 1968.0 112.00glassRevenue 4.7871E+05 (Corr) 1.7663E+05 7.7842E+05 7.7842E+05Number in Conveyor 9.0000 .00000 8.0000 9.0000 9.0000plasticRevenue 85812. (Corr) 31763. 1.3943E+05 1.3943E+05

    Simulation run time: 6.03 minutes.Simulation run complete.

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    27/31

    26

    4.5. Estimations of Secondary Performance Measures

    Alternative 1

    Replications Port Crane Conveyor Metal Gatherer Manual Process Area Worker Group 1 Worker Group 2 Number in crane queue

    1 40,14 44,62 98,31 78,16 80,51 74,45 77,01 51,14

    2 40,06 44,57 90,89 77,84 80,46 74,35 76,94 59,21

    3 39,08 43,40 98,05 75,96 78,35 72,36 75,02 49,24

    4 39,91 44,45 98,27 77,71 80,29 74,17 76,80 52,26

    5 38,65 43,02 97,94 75,28 77,68 71,77 74,28 51,89

    6 40,44 44,67 98,39 78,33 81,14 74,80 77,68 72,63

    7 39,33 43,72 98,09 76,51 78,86 72,91 75,59 45,75

    8 40,93 45,35 98,48 79,40 81,86 75,66 78,34 68,50

    39,57 44,01 96,69 76,99 79,46 73,42 76,01 52,75

    0,44 0,56 10,54 1,65 1,80 1,59 1,62 14,40

    Alternative 2

    Replications Port Crane Conveyor Metal Gatherer Manual Process Area Worker Group 1 Worker Group 2 Number in crane queue

    1 40,47 44,99 98,76 78,68 86,05 80,99 81,05 72,55

    2 39,41 43,76 98,47 76,44 83,68 78,71 78,83 62,68

    3 40,52 45,03 98,76 78,71 86,02 81,04 80,98 73,66

    4 38,94 43,16 98,31 75,42 82,46 77,65 77,60 56,54

    5 39,72 44,14 98,59 77,23 84,34 79,42 79,35 68,84

    39,81 44,22 98,58 77,30 84,51 79,56 79,56 66,86

    0,47 0,65 0,04 2,04 2,39 2,16 2,16 51,65

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    28/31

    27

    4.6. ARENA Output of Alternative 1 (2-year-run)

    ARENA Simulation ResultsDepartment of Industrial Engineering

    Summary for Replication 8 of 8

    Project: project Run execution date : 5/30/2011Analyst: aykutKerem Model revision date: 5/30/2011

    Replication ended at time : 1036800.0 MinutesStatistics were cleared at time: 30000.0 Minutes (Sunday, June 19, 2011, 20:00:00)Statistics accumulated for time: 1006800.0 MinutesBase Time Units: Minutes

    TALLY VARIABLES

    Identifier Average Half Width Minimum Maximum Observations___________________________________________________________________________________________________

    plasticFlowTime 171.22 9.4151 31.653 839.74 667369glassFlowTime 208.56 9.0488 31.445 905.18 667367paperFlowTime 151.55 9.6370 31.806 808.60 667362glassTruckTally 1006.5 .07688 1000.0 1016.6 8319compostFlowTime 2037.3 14.247 1448.6 2887.9 82745remainingFlowTime 167.02 9.4921 35.425 830.18 667373plasticTruckTally 1016.8 .11798 1000.0 1037.7 21720organicFlowTime 1116.2 7.2051 41.419 2761.3 586111metalFlowTime 144.63 9.6221 23.694 800.38 667362

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    29/31

    28

    DISCRETE-CHANGE VARIABLES

    Identifier Average Half Width Minimum Maximum Final Value___________________________________________________________________________________________________

    Crane True Utilization 132.57 1.7522 .00000 300.00 100.00

    metalRevenue+plasticRevenue+glassRevenue+o 6.7988E+06 (Corr) 3.7094E+05 1.3222E+07 1.3222E+07Number in Crane Queue 60.847 8.1264 .00000 587.00 69.000Crane Utilization 248.95 3.7817 .00000 300.00 300.00metalRevenue 2.7008E+06 (Corr) 1.4828E+05 5.2513E+06 5.2513E+06Worker Group 2 Utilization 152.75 2.0550 .00000 200.00 100.00Number in Port Queue .08936 .00553 .00000 7.0000 .00000Port Utilization 39.767 .52525 .00000 100.00 .00000Metal Gatherer Utilization 254.02 3.4643 .00000 300.00 300.00organicRevenue 6.1089E+05 (Corr) 31194. 1.1893E+06 1.1893E+06NR(conveyor) 9.8219 .01315 9.0000 10.000 10.000landfillCost 1.2352E+06 (Corr) 67934. 2.4017E+06 2.4017E+06Worker Group 1 Utilization 368.56 4.8443 .00000 500.00 400.00

    Metal Gatherer True Utilization 231.96 3.0598 .00000 300.00 300.00paperRevenue 7.1931E+05 (Corr) 39611. 1.3988E+06 1.3988E+06NR(workerArea) 5.5865 .07467 .00000 7.0000 5.0000compostRevenue 50554. (Corr) 2558.9 98909. 98909.NUMENT 866.08 16.766 30.000 2362.0 118.00glassRevenue 3.3681E+06 (Corr) 1.8513E+05 6.5488E+06 6.5488E+06Number in Conveyor 9.0000 .00000 8.0000 9.0000 9.0000plasticRevenue 5.8439E+05 (Corr) 32132. 1.1364E+06 1.1364E+06

    Simulation run time: 3.88 minutes.Simulation run complete.

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    30/31

    29

    4.7. ARENA Output of Alternative 2 (2-year-run)

    ARENA Simulation Results

    Department of Industrial Engineering

    Summary for Replication 5 of 5

    Project: project Run execution date : 5/30/2011Analyst: aykutKerem Model revision date: 5/30/2011

    Replication ended at time : 1066800.0 MinutesStatistics were cleared at time: 30000.0 Minutes (Sunday, June 19, 2011, 20:00:00)Statistics accumulated for time: 1036800.0 MinutesBase Time Units: Minutes

    TALLY VARIABLES

    Identifier Average Half Width Minimum Maximum Observations___________________________________________________________________________________________________

    plasticFlowTime 202.79 14.661 31.578 1047.0 693732glassFlowTime 242.42 14.424 33.208 1116.8 693739paperFlowTime 183.25 14.774 31.574 1030.8 693733glassTruckTally 1006.2 (Corr) 1000.0 1015.9 8272compostFlowTime 2061.8 21.406 1444.2 3082.4 92460remainingFlowTime 196.33 14.717 33.798 1043.1 693732plasticTruckTally 1016.3 .09228 1000.0 1037.2 22298

    organicFlowTime 1142.0 10.992 36.584 2748.0 601112metalFlowTime 175.82 14.769 23.332 1024.9 693732

  • 7/31/2019 Term Project: Waste Transfer Station Part II

    31/31

    30

    DISCRETE-CHANGE VARIABLES

    Identifier Average Half Width Minimum Maximum Final Value___________________________________________________________________________________________________

    Crane True Utilization 133.82 1.3229 .00000 300.00 100.00metalRevenue+plasticRevenue+glassRevenue+o 6.6140E+06 (Corr) 3.4954E+05 1.2900E+07 1.2900E+07Number in Crane Queue 82.184 9.9270 .00000 729.00 80.000Crane Utilization 262.19 3.0067 .00000 300.00 300.00metalRevenue 2.7980E+06 (Corr) 1.4917E+05 5.4578E+06 5.4578E+06Worker Group 2 Utilization 160.58 1.5997 .00000 200.00 200.00Number in Port Queue .08964 (Corr) .00000 6.0000 .00000Port Utilization 40.149 .39599 .00000 100.00 50.000Metal Gatherer Utilization 266.28 2.7032 .00000 300.00 300.00organicRevenue 6.2090E+05 (Corr) 31171. 1.2094E+06 1.2094E+06NR(conveyor) 9.8685 .01045 9.0000 10.000 10.000landfillCost 1.5342E+06 (Corr) 81601. 2.9921E+06 2.9921E+06

    Worker Group 1 Utilization 401.47 3.9821 .00000 700.00 400.00Metal Gatherer True Utilization 234.25 2.2731 .00000 300.00 200.00paperRevenue 7.4226E+05 (Corr) 39544. 1.4476E+06 1.4476E+06NR(workerArea) 5.9692 .05940 .00000 7.0000 7.0000compostRevenue 55460. (Corr) 2861.0 1.0937E+05 1.0937E+05NUMENT 897.26 16.777 25.000 2218.0 1435.0glassRevenue 3.3342E+06 (Corr) 1.7663E+05 6.5028E+06 6.5028E+06Number in Conveyor 9.0000 .00000 8.0000 9.0000 9.0000plasticRevenue 5.9734E+05 (Corr) 31763. 1.1649E+06 1.1649E+06

    Simulation run time: 2.85 minutes.

    Simulation run complete.