TENTATIVE FIVE YEAR WORK PROGRAMFISCAL YEARS 2020-2024
FLORIDA DEPARTMENT OF TRANSPORTATION - DISTRICT ONE
COLLIER COUNTY
MISSION STATEMENTThe Department will provide a safe, interconnected statewide transportation system for Florida's citizens and visitors that ensures the mobility of people and goods, while enhancing economic prosperity and sustaining the quality of our environment.
Zachary Burch Gov. Affairs & Comm. Manager Southwest Area Office 10041 Daniels Parkway Fort Myers, FL 33913 (239) 225-1950
Brian Rick Gov. Affairs & Comm. Manager District 1 Headquarters 801 North Broadway Avenue Bartow, FL 33830 (863) 519-2828
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 1 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
ACNP ADVANCE CONSTRUCTION NHPP
ACSA ADVANCE CONSTRUCTION (SA)
ACSS ADVANCE CONSTRUCTION (SS,HSP)
ACSU ADVANCE CONSTRUCTION (SU)
ACTU ADVANCE CONSTRUCTION TALU
BNIR INTRASTATE R/W & BRIDGE BONDS
BRRP STATE BRIDGE REPAIR & REHAB
CIGP COUNTY INCENTIVE GRANT PROGRAM
D UNRESTRICTED STATE PRIMARY
DDR DISTRICT DEDICATED REVENUE
DI ST. - S/W INTER/INTRASTATE HWY
DIH STATE IN-HOUSE PRODUCT SUPPORT
DPTO STATE - PTO
DS STATE PRIMARY HIGHWAYS & PTO
DSB2 EVERGLADES PKY/ALLIGATOR ALLEY
DU STATE PRIMARY/FEDERAL REIMB
EM19 GAA EARMARKS FY 2019
FAA FEDERAL AVIATION ADMIN
FTA FEDERAL TRANSIT ADMINISTRATION
FTAT FHWA TRANSFER TO FTA (NON-BUD)
HSP SAFETY (HIWAY SAFETY PROGRAM)
LF LOCAL FUNDS
LFP LOCAL FUNDS FOR PARTICIPATING
PL METRO PLAN (85% FA; 15% OTHER)
REPE REPURPOSED FEDERAL EARMARKS
SA STP, ANY AREA
SR2T SAFE ROUTES - TRANSFER
SU STP, URBAN AREAS > 200K
TALT TRANSPORTATION ALTS- ANY AREA
TALU TRANSPORTATION ALTS- >200K
CURRENTLY REPORTED ACTIVE FUND CODES
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 2 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
TRIP TRANS REGIONAL INCENTIVE PROGM
TRWR 2015 SB2514A-TRAN REG INCT PRG
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 3 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FLP: TRANSIT
FPN : 4101131 Project/Location : COLLIER COUNTY MPO TRANSIT PLANNING FTA SECTION 5305 (D)
Desc: MODAL SYSTEMS PLANNING Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
PLN DPTO $9,720 $9,877 $9,877 $9,877 $9,877PLN DU $77,760 $79,010 $79,010 $79,010 $79,010PLN LF $9,720 $9,877 $9,877 $9,877 $9,877Project Total: $97,200 $98,764 $98,764 $98,764 $98,764
FPN : 4101201 Project/Location : COLLIER COUNTY FTA SECTION 5311 OPERATING ASSISTANCE
Desc: OPERATING/ADMIN. ASSISTANCE Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
OPS DU $404,500 $366,460 $364,222 $404,525 $379,787OPS LF $404,500 $366,460 $364,222 $404,525 $379,787Project Total: $809,000 $732,920 $728,444 $809,050 $759,574
FPN : 4101391 Project/Location : COLLIER COUNTY STATE TRANSIT BLOCK GRANT OPERATING ASSISTANCE
Desc: OPERATING FOR FIXED ROUTE Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
OPS DDR $0 $0 $0 $906,623 $0OPS DPTO $982,792 $1,031,948 $1,083,545 $228,574 $1,194,608OPS LF $982,792 $1,031,948 $1,083,545 $1,135,197 $1,194,608Project Total: $1,965,584 $2,063,896 $2,167,090 $2,270,394 $2,389,216
FPN : 4101461 Project/Location : COLLIER COUNTY FTA SECTION 5307 CAPITAL ASSISTANCE
Desc: CAPITAL FOR FIXED ROUTE Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP FTA $2,313,830 $2,348,065 $2,643,559 $2,061,778 $1,782,420CAP LF $578,458 $587,016 $660,890 $515,445 $445,605Project Total: $2,892,288 $2,935,081 $3,304,449 $2,577,223 $2,228,025
FPN : 4101462 Project/Location : COLLIER COUNTY FTA SECTION 5307 OPERATING ASSISTANCE
Desc: OPERATING FOR FIXED ROUTE Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
OPS FTA $574,297 $500,000 $100,000 $408,000 $0OPS LF $574,297 $500,000 $100,000 $408,000 $0Project Total: $1,148,594 $1,000,000 $200,000 $816,000 $0
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 4 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4340301 Project/Location : COLLIER CO./BONITA SPRINGS UZA FTA SECTION 5339 CAPITAL ASSISTANCE
Desc: CAPITAL FOR FIXED ROUTE Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP FTA $365,428 $347,686 $299,327 $299,889 $411,466CAP LF $91,357 $86,922 $74,382 $74,972 $102,867Project Total: $456,785 $434,608 $373,709 $374,861 $514,333
FPN : 4350292 Project/Location : US 41 FROM CR 846 (111TH AVE) TO NORTH OF 91ST AVE
Desc: PUBLIC TRANSPORTATION SHELTER Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP FTAT $51,600 $0 $0 $0 $0CAP SU $51,600 $0 $0 $0 $0Project Total: $103,200 $0 $0 $0 $0
FLP: TRANSIT TOTAL 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
$7,472,651 $7,265,269 $6,872,456 $6,946,292 $5,989,912
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 5 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FLP:AVIATION
FPN : 4443941 Project/Location : EVERGLADES AIRPARK SEAPLANE BASE DESIGN AND CONSTRUCT
Desc: AVIATION CAPACITY PROJECT Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP DDR $630,000 $0 $0 $0 $0CAP LF $157,500 $0 $0 $0 $0Project Total: $787,500 $0 $0 $0 $0
FPN : 4336321 Project/Location : IMMOKALEE REGIONAL AIRPORT SECURITY ENHANCEMENTS
Desc: AVIATION SECURITY PROJECT Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP DPTO $480,000 $0 $0 $0 $0CAP LF $120,000 $0 $0 $0 $0Project Total: $600,000 $0 $0 $0 $0
FPN : 4417831 Project/Location : IMMOKALEE ARPT TAXIWAY C EXTENSION
Desc: AVIATION PRESERVATION PROJECT Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP DDR $0 $150,000 $0 $0 $0CAP DPTO $12,500 $0 $0 $0 $0CAP FAA $225,000 $2,700,000 $0 $0 $0CAP LF $12,500 $150,000 $0 $0 $0Project Total: $250,000 $3,000,000 $0 $0 $0
FPN : 4417841 Project/Location : IMMOKALEE ARPT ENVIRONMENTAL STUDY FOR RUNWAY 9/27 EXTENSION
Desc: AVIATION ENVIRONMENTAL PROJECTProject Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP DDR $0 $0 $10,000 $0 $0CAP FAA $0 $0 $180,000 $0 $0CAP LF $0 $0 $10,000 $0 $0Project Total: $0 $0 $200,000 $0 $0
FPN : 4389771 Project/Location : IMMOKALEE REGIONAL ARPT REHABILITATE RUNWAY 18/36
Desc: AVIATION PRESERVATION PROJECT Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP DDR $1,074,000 $4,706,000 $400,000 $0 $0CAP LF $268,500 $1,176,500 $100,000 $0 $0Project Total: $1,342,500 $5,882,500 $500,000 $0 $0
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 6 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4370631 Project/Location : MARCO ISLAND APT NEW TERMINAL BUILDING
Desc: AVIATION CAPACITY PROJECT Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP DDR $3,599,620 $0 $0 $0 $0CAP LF $899,905 $0 $0 $0 $0Project Total: $4,499,525 $0 $0 $0 $0
FPN : 4416751 Project/Location : NAPLES MUNICIPAL AIRPORT SECURITY UPGRADES
Desc: AVIATION SECURITY PROJECT Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP DDR $0 $0 $0 $0 $800,000CAP LF $0 $0 $0 $0 $200,000Project Total: $0 $0 $0 $0 $1,000,000
FPN : 4417651 Project/Location : NAPLES MUNICIPAL AIRPORT RUNWAY 5-23 DRAINAGE SWALE IMPROVEMENTS
Desc: AVIATION PRESERVATION PROJECT Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CAP DDR $150,000 $0 $0 $0 $0CAP FAA $2,700,000 $0 $0 $0 $0CAP LF $150,000 $0 $0 $0 $0Project Total: $3,000,000 $0 $0 $0 $0
FLP:AVIATION TOTAL 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
$10,479,525 $8,882,500 $700,000 $0 $1,000,000
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 7 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
HIGHWAYS
FPN : 4318953 Project/Location : 16TH ST BRIDGE NE FROM GOLDEN GATE BLVD TO RANDALL BLVD
Desc: NEW BRIDGE CONSTRUCTION Project Length : 3.212 Begin Mile Post : 0.000 End Mile Post: 3.212Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SA $0 $0 $1,132,944 $0 $0CST SU $0 $0 $3,801,000 $0 $0Project Total: $0 $0 $4,933,944 $0 $0
FPN : 4418461 Project/Location : 111TH AVE NORTH FROM BLUEBILL AVE BRIDGE TO 7TH ST NORTH
Desc: BIKE LANE/SIDEWALK Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $553,410 $0 $0 $0Project Total: $0 $553,410 $0 $0 $0
FPN : 4404411 Project/Location : AIRPORT PULLING RD FROM VANDERBILT RD TO IMMOKALEE RD
Desc: ADD THRU LANE(S) Project Length : 1.970 Begin Mile Post : 0.000 End Mile Post: 1.970Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST LF $0 $0 $0 $4,928,100 $0CST CIGP $0 $0 $0 $4,928,100 $0PE CIGP $0 $1,500,000 $0 $0 $0PE LF $0 $1,500,000 $0 $0 $0
Project Total: $0 $3,000,000 $0 $9,856,200 $0
FPN : 4418781 Project/Location : BALD EAGLE DRIVE FROM COLLIER BLVD TO OLD MARCO LN
Desc: SIDEWALK Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $509,685 $0 $0 $0Project Total: $0 $509,685 $0 $0 $0
FPN : 4433753 Project/Location : COLLIER COUNTY LAKE TRAFFORD ROAD SIDEWALK AND BIKE LANES
Desc: SIDEWALK Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $800,460 $0 $0 $0Project Total: $0 $800,460 $0 $0 $0
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 8 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4433754 Project/Location : COLLIER COUNTY LAKE TRAFFORD ROAD SIDEWALK AND BIKE LANES
Desc: SIDEWALK Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $572,675 $0 $0 $0Project Total: $0 $572,675 $0 $0 $0
FPN : 4380911 Project/Location : COUNTY BARN ROAD FROM RATTLESNAKE HAMMOCK TO SR 84(DAVIS BLVD)
Desc: BIKE PATH/TRAIL Project Length : 2.045 Begin Mile Post : 0.000 End Mile Post: 2.045Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SA $0 $0 $0 $50,000 $0CST SU $0 $0 $0 $1,829,376 $0PE SU $0 $176,000 $0 $0 $0
Project Total: $0 $176,000 $0 $1,879,376 $0
FPN : 4380921 Project/Location : CR 901/VANDERBILT DR FROM VANDERBILT BEACH RD TO 109TH AVENUE N
Desc: SIDEWALK Project Length : 1.214 Begin Mile Post : 0.000 End Mile Post: 1.214Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $0 $0 $709,075 $0PE SU $0 $151,000 $0 $0 $0
Project Total: $0 $151,000 $0 $709,075 $0
FPN : 4404351 Project/Location : COLLIER COUNTY TRAFFIC SIGNAL TIMING OPTIMIZATION AT VARIOUS LOCATIONS
Desc: TRAFFIC SIGNAL UPDATE Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $0 $0 $50,000 $0PE SU $0 $0 $351,000 $0 $0
Project Total: $0 $0 $351,000 $50,000 $0
FPN : 4350431 Project/Location : COLLIER COUNTY SCOUR COUNTERMEASURE AT VARIOUS LOCATIONS
Desc: BRIDGE-REPAIR/REHABILITATION Project Length : 0.074 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST BRRP $0 $0 $151,340 $0 $920,920CST DIH $0 $0 $54,050 $0 $0PE BRRP $0 $0 $0 $200,000 $0
Project Total: $0 $0 $205,390 $200,000 $920,920
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 9 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4369701 Project/Location : CR 92 (SAN MARCO RD) FROM S BARFIELD DRIVE TO 400 FT E OF VINTAGE BAY
Desc: BIKE PATH/TRAIL Project Length : 1.417 Begin Mile Post : 2.027 End Mile Post: 3.444Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $1,330,114 $0 $0 $0 $0Project Total: $1,330,114 $0 $0 $0 $0
FPN : 4371031 Project/Location : COLLIER TMC OPS FUND COUNTY WIDE
Desc: OTHER ITS Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
OPS DS $81,000 $81,000 $81,000 $81,000 $81,000Project Total: $81,000 $81,000 $81,000 $81,000 $81,000
FPN : 4051061 Project/Location : COLLIER MPO IDENTIFIED OPERATIONAL IMPROVEMENTS FUNDING
Desc: TRAFFIC OPS IMPROVEMENT Project Length : Begin Mile Post : End Mile Post: Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $1,506,518 $163,287 $0 $1,061,033 $1,900,117Project Total: $1,506,518 $163,287 $0 $1,061,033 $1,900,117
FPN : 4126661 Project/Location : COLLIER COUNTY TRAFFIC SIGNALS REIMBURSEMENT
Desc: TRAFFIC SIGNALS Project Length : 12.814 Begin Mile Post : 1.299 End Mile Post: 14.113Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
OPS DDR $331,017 $339,661 $348,971 $358,843 $369,348Project Total: $331,017 $339,661 $348,971 $358,843 $369,348
FPN : 4414801 Project/Location : EDEN PARK ELEMENTARY
Desc: SIDEWALK Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SR2T $0 $0 $663,333 $0 $0Project Total: $0 $0 $663,333 $0 $0
FPN : 4380931 Project/Location : GREEN BLVD FROM SANTA BARBARA BLVD TO SUNSHINE BLVD
Desc: BIKE LANE/SIDEWALK Project Length : 1.040 Begin Mile Post : 0.000 End Mile Post: 1.040Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $0 $0 $1,084,670 $0PE SU $0 $226,000 $0 $0 $0
Project Total: $0 $226,000 $0 $1,084,670 $0
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 10 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4385841 Project/Location : I-75/ALLIGATOR ALLEY TOLL BOOTH LANDSCAPING
Desc: LANDSCAPING Project Length : 0.001 Begin Mile Post : 49.250 End Mile Post: 49.251Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DDR $0 $0 $0 $0 $0CST DIH $0 $0 $0 $0 $0PE DIH $0 $10,000 $0 $0 $0PE DDR $0 $200,000 $0 $0 $0
Project Total: $0 $210,000 $0 $0 $0
FPN : 4411281 Project/Location : I-75 (SR 93) AT CR 886 (GOLDEN GATE PKWY)
Desc: LANDSCAPING Project Length : 0.900 Begin Mile Post : 53.300 End Mile Post: 54.200Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DIH $0 $0 $0 $0 $0CST DDR $0 $0 $0 $0 $0PE DDR $0 $200,000 $0 $0 $0PE DIH $0 $10,000 $0 $0 $0
Project Total: $0 $210,000 $0 $0 $0
FPN : 4258432 Project/Location : I-75 AT SR 951
Desc: INTERCHANGE IMPROVEMENT Project Length : 0.651 Begin Mile Post : 50.096 End Mile Post: 50.747Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DIH $0 $0 $0 $55,550 $0CST DSB2 $0 $46,974 $0 $0 $0CST LF $0 $0 $0 $138,875 $0CST DI $0 $0 $0 $83,039,028 $0ENV DDR $0 $0 $0 $125,000 $0PE DDR $0 $0 $0 $1,087,990 $0
ROW DI $6,174,000 $0 $0 $1,323,000 $0RRU DI $0 $0 $0 $2,651,000 $0RRU LF $0 $0 $0 $1,100,000 $0Project Total: $6,174,000 $46,974 $0 $89,520,443 $0
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 11 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4440081 Project/Location : I-75 (SR 93) FROM BROWARD COUNTY LINE TO TOLL BOOTH
Desc: RESURFACING Project Length : 78.304 Begin Mile Post : 0.063 End Mile Post: 49.102Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DS $0 $0 $1,734,504 $0 $0CST DSB2 $0 $0 $91,886,954 $0 $0PE DSB2 $4,942,900 $0 $0 $0 $0
Project Total: $4,942,900 $0 $93,621,458 $0 $0
FPN : 4418791 Project/Location : INLET DRIVE FROM ADDISON CT TO TRAVIDA TERRACE
Desc: SIDEWALK Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $411,781 $0 $0 $0Project Total: $0 $411,781 $0 $0 $0
FPN : 4404361 Project/Location : MANDARIN GREENWAY SIDEWALKS AT VARIOUS LOCATIONS
Desc: BIKE LANE/SIDEWALK Project Length : 10.360 Begin Mile Post : 0.000 End Mile Post: 10.320Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DDR $0 $0 $17,478 $0 $0CST SU $0 $0 $331,929 $0 $0PE TALU $45,311 $0 $0 $0 $0
Project Total: $45,311 $0 $349,407 $0 $0
FPN : 4331891 Project/Location : N COLLIER BLVD FROM E ELKCAM CIRCLE TO BUTTONWOOD COURT
Desc: SIDEWALK Project Length : 0.658 Begin Mile Post : 1.727 End Mile Post: 2.385Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST LFP $105,146 $0 $0 $0 $0CST SU $656,579 $0 $0 $0 $0Project Total: $761,725 $0 $0 $0 $0
FPN : 4371041 Project/Location : NAPLES TMC OPERATIONS FUNDING CITY WIDE
Desc: OTHER ITS Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
OPS DDR $50,000 $0 $0 $0 $0OPS DS $30,000 $30,000 $30,000 $30,000 $30,000Project Total: $80,000 $30,000 $30,000 $30,000 $30,000
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 12 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4371851 Project/Location : NAPLES BEACH ACCESS SIDEWALKS AT VARIOUS LOCATIONS
Desc: SIDEWALK Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $1,118,682 $0 $0 $0 $0Project Total: $1,118,682 $0 $0 $0 $0
FPN : 4136271 Project/Location : NAPLES TRAFFIC SIGNALS REIMBURSEMENT
Desc: TRAFFIC SIGNALS Project Length : 12.814 Begin Mile Post : 1.299 End Mile Post: 14.113Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
OPS DDR $122,010 $125,194 $128,621 $132,249 $136,117Project Total: $122,010 $125,194 $128,621 $132,249 $136,117
FPN : 4404251 Project/Location : PINE RIDGE RD FROM WHIPPOORWILL LANE TO NAPA BLVD
Desc: SIDEWALK Project Length : 3.810 Begin Mile Post : 0.000 End Mile Post: 3.810Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $0 $0 $0 $1,315,273PE SU $0 $0 $229,418 $0 $0
Project Total: $0 $0 $229,418 $0 $1,315,273
FPN : 4175402 Project/Location : SR 29 FROM OIL WELL ROAD TO SUNNILAND NURSERY ROAD
Desc: ADD LANES & RECONSTRUCT Project Length : 4.762 Begin Mile Post : 27.209 End Mile Post: 31.971Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
ENV DI $0 $0 $0 $0 $885,000PE DI $0 $0 $0 $0 $6,140,000PE ACNP $0 $0 $0 $0 $1,250,000
Project Total: $0 $0 $0 $0 $8,275,000
FPN : 4175403 Project/Location : SR 29 FROM SUNNILAND NURSERY ROAD TO S OF AGRICULTURE WAY
Desc: ADD LANES & RECONSTRUCT Project Length : 2.548 Begin Mile Post : 31.971 End Mile Post: 34.519Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
ENV DDR $0 $0 $0 $500,000 $0Project Total: $0 $0 $0 $500,000 $0
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 13 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4175404 Project/Location : SR 29 FROM S OF AGRICULTURE WAY TO CR 846 E
Desc: ADD LANES & RECONSTRUCT Project Length : 2.251 Begin Mile Post : 34.519 End Mile Post: 36.770Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
ENV DDR $0 $0 $0 $270,000 $0Project Total: $0 $0 $0 $270,000 $0
FPN : 4175405 Project/Location : SR 29 FROM CR 846 E TO N OF NEW MARKET ROAD N
Desc: ADD LANES & RECONSTRUCT Project Length : 3.484 Begin Mile Post : 36.770 End Mile Post: 40.254Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
ROW ACNP $0 $0 $0 $0 $1,022,228ROW DI $0 $0 $0 $0 $0Project Total: $0 $0 $0 $0 $1,022,228
FPN : 4175406 Project/Location : SR 29 FROM N OF NEW MARKET RD N ROAD TO SR 82
Desc: ADD LANES & RECONSTRUCT Project Length : 3.037 Begin Mile Post : 39.761 End Mile Post: 42.798Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
ENV DDR $0 $0 $0 $380,000 $0ROW ACNP $0 $0 $0 $0 $1,122,707Project Total: $0 $0 $0 $380,000 $1,122,707
FPN : 4178784 Project/Location : SR 29 FROM SR 82 TO HENDRY C/L
Desc: ADD LANES & RECONSTRUCT Project Length : 1.869 Begin Mile Post : 42.844 End Mile Post: 44.713Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST ACNP $0 $0 $0 $9,753,761 $0CST DI $0 $0 $0 $166,650 $0ENV DI $0 $15,000 $0 $0 $0ENV ACNP $400,000 $0 $0 $50,000 $0INC DDR $0 $0 $0 $0 $475,000
ROW ACNP $0 $1,258,822 $0 $0 $0Project Total: $400,000 $1,273,822 $0 $9,970,411 $475,000
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 14 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4370961 Project/Location : SIDEWALKS EVERGLADES CITY AT VARIOUS LOCATIONS
Desc: SIDEWALK Project Length : 0.200 Begin Mile Post : 0.000 End Mile Post: 0.200Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST TALT $0 $0 $84,692 $0 $0CST TALU $0 $0 $372,940 $0 $0ENV TALT $0 $20,000 $40,000 $0 $0PE TALT $150,000 $0 $0 $0 $0PE TALU $185,000 $0 $0 $0 $0
Project Total: $335,000 $20,000 $497,632 $0 $0
FPN : 4351112 Project/Location : SR 951 FROM MANATEE RD TO N OF TOWER RD
Desc: ADD LANES & REHABILITATE PVMNTProject Length : 0.350 Begin Mile Post : 8.615 End Mile Post: 8.965Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
ROW DDR $3,812,751 $0 $0 $0 $0Project Total: $3,812,751 $0 $0 $0 $0
FPN : 4348571 Project/Location : SR 951 OVER BIG MARCO PASS(JUDGE JOLLY MEMORIAL BRIDGE)
Desc: BRIDGE-REPAIR/REHABILITATION Project Length : 0.302 Begin Mile Post : 2.606 End Mile Post: 2.908Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DIH $0 $21,060 $0 $0 $0CST BRRP $0 $2,393,322 $0 $0 $0ENV BRRP $10,000 $0 $0 $0 $0PE BRRP $250,000 $0 $0 $0 $0PE DIH $20,000 $0 $0 $0 $0
Project Total: $280,000 $2,414,382 $0 $0 $0
FPN : 4308481 Project/Location : SR 82 FROM HENDRY COUNTY LINE TO GATOR SLOUGH LANE
Desc: ADD LANES & RECONSTRUCT Project Length : 4.022 Begin Mile Post : 0.000 End Mile Post: 4.022Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DI $0 $0 $0 $44,744,273 $0CST DIH $0 $0 $0 $59,967 $0ENV DDR $0 $0 $20,000 $50,000 $0INC DDR $0 $0 $0 $0 $0
ROW BNIR $2,496,116 $0 $0 $0 $0RRU DDR $0 $0 $0 $500,000 $0Project Total: $2,496,116 $0 $20,000 $45,354,240 $0
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 15 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4404371 Project/Location : SOUTH GOLF DR FROM GULF SHORE BLVD TO W US 41
Desc: BIKE LANE/SIDEWALK Project Length : 2.537 Begin Mile Post : 0.000 End Mile Post: 2.537Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SA $0 $0 $0 $1,976,749 $0Project Total: $0 $0 $0 $1,976,749 $0
FPN : 4404381 Project/Location : SAN MARCO RD FROM VINTAGE BAY DRIVE TO GOODLAND RD
Desc: BIKE PATH/TRAIL Project Length : 1.440 Begin Mile Post : 3.440 End Mile Post: 4.880Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $650,062 $0 $0 $0Project Total: $0 $650,062 $0 $0 $0
FPN : 4379251 Project/Location : SIGNAL TIMING COUNTY ROADS AT VARIOUS LOCATIONS
Desc: TRAFFIC SIGNAL UPDATE Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SA $0 $0 $452,560 $0 $0Project Total: $0 $0 $452,560 $0 $0
FPN : 4379261 Project/Location : SIGNAL TIMING US41 FROM SR951/COLLIER BLVD TO OLD US41
Desc: TRAFFIC SIGNAL UPDATE Project Length : 19.960 Begin Mile Post : 1.300 End Mile Post: 20.200Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SU $0 $516,200 $0 $0 $0Project Total: $0 $516,200 $0 $0 $0
FPN : 4390021 Project/Location : SR 29 FROM NORTH 1ST STREET TO NORTH 9TH STREET
Desc: PEDESTRIAN SAFETY IMPROVEMENT Project Length : 0.502 Begin Mile Post : 37.309 End Mile Post: 37.811Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DDR $1,857,125 $0 $0 $0 $0CST DS $750,012 $0 $0 $0 $0Project Total: $2,607,137 $0 $0 $0 $0
FPN : 4395551 Project/Location : SR 951 FROM JUDGE JOLLEY BRIDGE TO FIDDLERS CREEK PARKWAY
Desc: RESURFACING Project Length : 3.031 Begin Mile Post : 3.152 End Mile Post: 6.183Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
ENV DDR $50,000 $0 $0 $0 $0Project Total: $50,000 $0 $0 $0 $0
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 16 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4415611 Project/Location : SR 90 FROM WHISTLER'S COVE TO COLLIER BLVD
Desc: RESURFACING Project Length : 1.380 Begin Mile Post : 18.883 End Mile Post: 20.263Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DDR $0 $0 $5,517,342 $0 $0CST DIH $0 $0 $43,240 $0 $0CST DS $0 $0 $682,936 $0 $0ENV DDR $0 $25,000 $50,000 $0 $0Project Total: $0 $25,000 $6,293,518 $0 $0
FPN : 4379241 Project/Location : TRAVEL TIME DATA COLLECTION COLLIER COUNTY ITS ARCH ATMS
Desc: OTHER ITS Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST SA $0 $0 $441,000 $0 $0Project Total: $0 $0 $441,000 $0 $0
FPN : 4415121 Project/Location : US 41 (SR 45) FROM S OF DUNRUSS CREEK TO S OF GULF PARK DR
Desc: RESURFACING Project Length : 4.735 Begin Mile Post : 1.175 End Mile Post: 5.910Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DDR $0 $0 $0 $2,198,388 $0CST DS $0 $0 $0 $858,317 $0CST SA $0 $0 $0 $7,864,025 $0CST TRIP $0 $0 $0 $2,076,166 $0CST TRWR $0 $0 $0 $2,299,513 $0Project Total: $0 $0 $0 $15,296,409 $0
FPN : 4380591 Project/Location : US41(SR 90) TAMIAMI TRL FM E OF SR84(DAVIS BLVD) TO COURTHOUSE SHADOWS
Desc: RESURFACING Project Length : 1.346 Begin Mile Post : 13.039 End Mile Post: 14.385Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST ACSS $0 $1,496,440 $0 $0 $0CST DDR $0 $6,052,058 $0 $0 $0CST SA $0 $1,105,650 $0 $0 $0ENV DDR $30,000 $75,000 $0 $0 $0Project Total: $30,000 $8,729,148 $0 $0 $0
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 17 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
FPN : 4439891 Project/Location : US41(SR90) FROM SR951(COLLIER BLVD) TO GREENWAY ROAD
Desc: LANDSCAPING Project Length : 7.529 Begin Mile Post : 6.908 End Mile Post: 23.668Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DS $0 $1,978,000 $0 $0 $0Project Total: $0 $1,978,000 $0 $0 $0
FPN : 4419751 Project/Location : US 41 (SR 90) AT OASIS VISITOR CENTER
Desc: ADD LEFT TURN LANE(S) Project Length : 0.276 Begin Mile Post : 21.000 End Mile Post: 21.276Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
CST DDR $0 $0 $0 $509,442 $0CST DIH $0 $0 $0 $16,665 $0ENV DDR $0 $15,000 $30,000 $0 $0PE DDR $150,000 $0 $0 $0 $0PE DIH $10,000 $0 $0 $0 $0
Project Total: $160,000 $15,000 $30,000 $526,107 $0
HIGHWAYS TOTAL 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
$26,664,281 $23,228,741 $108,677,252 $179,236,805 $15,647,710
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 18 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT
TRANSPORTATION PLANNING
FPN : 4393142 Project/Location : COLLIER COUNTY MPO FY 2018/2019-2019/2020 UPWP
Desc: TRANSPORTATION PLANNING Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
PLN PL $546,564 $0 $0 $0 $0Project Total: $546,564 $0 $0 $0 $0
FPN : 4393143 Project/Location : COLLIER COUNTY MPO FY 2020/2021-2021/2022 UPWP
Desc: TRANSPORTATION PLANNING Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
PLN PL $0 $546,564 $546,564 $0 $0Project Total: $0 $546,564 $546,564 $0 $0
FPN : 4393144 Project/Location : COLLIER COUNTY MPO FY 2022/2023-2023/2024 UPWP
Desc: TRANSPORTATION PLANNING Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
PLN PL $0 $0 $0 $546,564 $0Project Total: $0 $0 $0 $546,564 $0
TRANSPORTATION PLANNING TOTAL 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024
$546,564 $546,564 $546,564 $546,564 $0
COLLIER COUNTY TOTALS
Phase Fund 2019/ 2020 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 Total
COUNTY Total : $45,163,021 $39,923,074 $116,796,272 $186,729,661 $22,637,622 $411,249,650
PHASE CODES
ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities
Page: 19 Run Date:11/19/2018 SnapShot Date: 11/14/2018
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT
July 1, 2019 Through June 30, 2024 COLLIER COUNTY
DRAFT