41
Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct Project Request to Implement Prefiling APPENDIX C Examples of Consultation Letters

Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Tennessee Gas Pipeline Company, L.L.C.

Northeast Energy Direct Project

Request to Implement Prefiling

APPENDIX C

Examples of Consultation Letters

Page 2: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Dr. Brian Jones

State Archaeologist

2019 Hillside Road, Unit 1023

Storrs, CT 06269-1023

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Dr. Jones,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Page 3: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Hillsborough, NH 8.37

Page 4: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 5: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Victor T. Mastone

Chief Archaeologist

251 Causeway Street, Suite 800

Boston, MA 02114

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Mr. Mastone,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Page 6: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Hillsborough, NH 8.37

Page 7: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 8: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Elizabeth Muzzey

Department of Cultural Resources

19 Pillsbury Street, 2nd

Floor

Concord, NH 03301

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Ms. Muzzey,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Page 9: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Hillsborough, NH 8.37

Page 10: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 11: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Jennifer Anderson

NOAA Fisheries

55 Great Republic Drive

Gloucester, MA 01930

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Ms. Anderson,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Page 12: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Hillsborough, NH 8.37

Page 13: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 14: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Matthew Brower

New York State Department of Agriculture & Markets

Agricultural Resource Specialist

10B Airline Drive

Albany, NY 12235-001

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Mr. Brower,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Page 15: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Hillsborough, NH 8.37

Page 16: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 17: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Daniel Naylor

Pennsylvania Department of Agriculture

Region 3

Route 92 South

PO Box C

Tunkhannock, PA 18657

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Mr. Naylor,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Page 18: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Page 19: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Hillsborough, NH 8.37

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 20: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Andrew Dehoff

Susquehanna River Basin Commission

Executive Director

4423 N. Front Street

Harrisburg, PA 17110

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Mr. Dehoff,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Page 21: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Hillsborough, NH 8.37

Page 22: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 23: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Wade Chandler

USACE – Baltimore District

Chief of Pennsylvania Section

10 S. Howard Street

PO Box 1715

Baltimore, MD 21203-1715

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Mr. Chandler,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Page 24: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Page 25: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Hillsborough, NH 8.37

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 26: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Curt Spalding

USEPA – Region 1

EPA Regional Administrator

5 Post Office Square

Mail Code: ORA

Boston, MA 02109-3912

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Mr. Spalding,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Page 27: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Page 28: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Hillsborough, NH 8.37

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 29: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Tom Chapman

USFWS

New England Field Office

70 Commercial Street, Suite 300

Concord, NH 03301

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Mr. Chapman,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Page 30: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Hillsborough, NH 8.37

Page 31: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 32: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Dennis Reidenbach

National Park Service

Regional Director

200 Chestnut Street, 5th Floor

Philadelphia, PA 19106

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Mr. Reidenbach,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Page 33: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Hillsborough, NH 8.37

Page 34: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 35: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

August 29, 2014

Abenaki Nation of New Hampshire

Charles True

Speaker

262 Lancaster Road

Whitefield, NH 03598

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Mr. True,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Page 36: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

2

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Hillsborough, NH 8.37

Page 37: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Z:\KM-NED 60328763\300-Communications\330 External\Pre-File\Pre-File Letters Sent\CTArch letter 082214 prefile notification template.docx

3

Proposed NED Project Pipeline Facilities

County, State Mileage

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 38: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

4

August 29, 2014

Jackie Colburn

Rivers Management and Protection Program

Rivers Coordinator

29 Hazen Drive

Concord, NH 03302

Subject: Federal Energy Regulatory Commission Pre-Filing Participation Request

Northeast Energy Direct Project

Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire

Dear Ms. Colburn,

Tennessee Gas Pipeline Company, L.L.C. (TGP) proposes the Northeast Energy Direct (NED) Project to expand and modify its existing pipeline system in Pennsylvania, New York, Massachusetts, Connecticut, and New Hampshire. The NED Project, as described in more detail below, is being developed to meet the increased demand in the Northeast United States for transportation capacity of natural gas. Natural gas is a clean, environmentally friendly energy source that is produced domestically.

TGP respectfully requests your participation in the Federal Energy Regulatory Commission’s

(FERC) National Energy Policy Act pre-filing process for the NED Project. The FERC’s pre-filing

process involves the review by the FERC of the draft Environmental Report (ER) prepared for the

Project (drafts of the ER are expected to be submitted in Spring 2015). In addition, the pre-filing

process entails the solicitation of comments and identification of concerns regarding the Project by

federal, state, and local agencies, landowners, environmental groups, and other stakeholders for

inclusion into the ER prior to the formal submittal of the Natural Gas Act Section 7(c) certificate

application for the Project, which application will include a final ER. More information regarding the

FERC’s pre-filing process may be found in Section 157.21 of the FERC’s regulations, 18 C.F.R. §

157.21 (2014). TGP anticipates that it will file a letter with the FERC requesting approval to use the

FERC’s pre-filing process for the NED Project in mid-September 2014.

The NED Project will provide up to 2.2 billion cubic feet per day (bcfd) of new firm natural gas

transportation capacity into northeast markets. The proposed Project involves the following

facilities:

Approximately 50 miles of looping of the existing TGP 300 Line in Pennsylvania;

Approximately 117 miles of new (greenfield) pipeline in Pennsylvania and New York (extending from TGP’s existing 300 Line to Wright, New York);

Approximately 50 miles of pipeline co-located with the existing TGP 200 Line in New York and Massachusetts;

Approximately 129 miles of new (greenfield) pipeline in Massachusetts (extending to Dracut, Massachusetts);

Various laterals and pipeline looping segments in Massachusetts, Connecticut, and New Hampshire to serve local markets;

Page 39: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

5

Construction of new compressor stations and meter stations and modifications to existing compressor and meter stations throughout the Project area; and

Construction of minor appurtenant facilities, including mainline valves, cathodic protection, and pig launcher/receivers throughout the Project area.

The table below summarizes the proposed pipeline mileage within each county and state crossed

by the Project. In addition, an overall map depicting the approximate locations of the Project

facilities is included with this letter for reference.

Proposed NED Project Pipeline Facilities

County, State Mileage

Bradford, PA 27.73

Susquehanna, PA 44.11

Pennsylvania Subtotal 71.84

Broome, NY 16.17

Chenango, NY 2.45

Delaware, NY 45.59

Schoharie, NY 34.80

Albany, NY 24.18

Rensselaer, NY 11.10

Columbia, NY 10.87

New York Subtotal 145.16

Berkshire, MA 28.15

Hampshire, MA 5.56

Franklin, MA 37.96

Worcester, MA 38.10

Middlesex, MA 49.35

Essex, MA 13.95

Massachusetts Subtotal 173.07

Fairfield, CT 1.51

Hartford, CT 14.57

Connecticut Subtotal 16.08

Hillsborough, NH 8.37

Rockingham, NH 2.13

New Hampshire Subtotal 10.50

Project Total 416.65

The proposed facilities are subject to change, and the final scope will be reflected in the certificate

application anticipated to be filed with FERC in the fourth quarter of 2015. TGP will be seeking the

Page 40: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

6

issuance of a certificate of public convenience and necessity from the FERC for the NED Project by

the fourth quarter of 2016.

TGP will provide documentation of the participating agencies to FERC and would appreciate a

formal response letter or email confirming or declining agency participation in the pre-filing process.

Should you have any questions regarding the Project, please do not hesitate to contact me at 713-

420-5360 or via email at [email protected]. Thank you for your consideration.

Yours sincerely,

Michael Letson

Environmental Lead, Tennessee Gas Pipeline Company, L.L.C

cc: Allen Fore, Tennessee Gas Pipeline Company, L.L.C

Jacquelyne Rocan, Tennessee Gas Pipeline Company, L.L.C

Richard Siegel, Tennessee Gas Pipeline Company, L.L.C

Mark Gardella, AECOM

Attachment: Project Location Map

Page 41: Tennessee Gas Pipeline Company, L.L.C. Northeast Energy Direct … · 2014-12-10 · formal response letter or email confirming or declining agency participation in the pre-filing

Beverly

STA.323

STA.265A

STA 266A

STA. 267

STA. 264STA. 261

STA. 325

STA. 321

STA. 254

STA. 249

STA. 245

STA. 319STA. 317

STA. 315STA. 313

STA. 241STA. 237STA. 233

Wright Dracut

New York

Pennsylvania

Maryland

Vermont

New Jersey

Massachusetts

New Hampshire

Connecticut

Delaware

Rhode Island

District of Columbia

Suffolk

York

Lewis

Essex

Grafton

Hamilton

York

Ulster

Jefferson

Wayne

Oneida

HerkimerOswego

Worcester

Delaware

Carroll

Berks

Otsego Essex

Bradford

Ocean

Barnstable

Warren

Pike

Sullivan

Rutland

Plymouth

Windsor

Tioga

Cayuga

Orange

Bristol

Luzerne

Wayne

Litchfield

Fairfield

Lycoming

Cumberland

Berkshire

Bucks

Lancaster

OrangeAddison

Tioga

Saratoga

Chester

Merrimack

Hartford

Franklin

Broome

Greene

Dutchess

Chenango

Fulton

Windham

Middlesex

Cheshire

Schuylkill

Cecil

Monroe

Madison

Atlantic

Burlington

Albany

Onondaga

Oxford

Dukes

Morris

New Haven

Washington

Hillsborough

Sussex

Sullivan

Columbia

Carroll

Hampden

Dauphin

Rockingham

Harford

Schoharie

Steuben

Monmouth

Yates

New London

Bennington

Susquehanna

Cortland

Perry

Rensselaer

Belknap

Tolland

Nassau

Norfolk

Sullivan

Salem

Washington

Windham

Tompkins

Seneca

Carbon

Columbia

Union

Lehigh

Hampshire

Warren

Adams

Strafford

Middlesex

Wyoming

Chemung

Snyder

Ontario

Hunterdon

Kent

Lebanon

Westchester

Schuyler

New Castle

Providence

Montgomery

NewportLackawanna

Bergen

Montgomery

Mercer

St. Lawrence

Putnam

MiddlesexSomerset

Gloucester

Nantucket

Northumberland

Baltimore County

Northampton

Cumberland

Camden

Androscoggin

Passaic

Cumberland

Queens

WashingtonFranklin

Rockland

Essex

Delaware

Suffolk

Union Kings

Schenectady

Juniata

Montour

Frederick

Kent

Philadelphia

Richmond

Bronx

Clinton

Coos

Bristol

KennebecCaledonia

LegendLaterals/LoopsPA to WrightWright to DracutExisting TGPProposed Compressor StationExisting Compressor Station

5

8

2

21

22

23 24

25

26

28

27

9

29

3

12

13

11 10

1

20

FOR INFORMATION ONLYSUBJECT TO CHANGE

3433

32

31

38

Essex

Middlesex

Hillsborough

Rockingham

2

1

SEE INSET

436

30

NOTICEKINDER MORGAN, INC.

PRIVILEGED OR CONFIDENTIAL INFORMATION

PLEASE FIND KINDER MORGAN GIS DATA SPECIFIC TO THIS PROJECT. A NEW DATA REQUEST WILL NEED TO BE MADE FOR ANY FUTURE OR SUBSEQUENT PROJECTS. THIS DATA IS INTENDED SOLELY FOR INTERNAL USE BY YOUR BUSINESS FOR THAT PURPOSE. YOU MAY NOT

DISCLOSE, PUBLISH, SELL, ASSIGN OR TRANSFER THIS DATA TO ANY OTHER PARTY.ALTHOUGH EFFORTS HAVE BEEN MADE TO ENSURE THAT THE DATA IS CORRECT AND RELIABLE, ERRORS ARE POSSIBLE. KINDER MORGAN DOES NOT GUARANTEE OR WARRANT THE ACCURACY OR QUALITY OF THIS DATA. THIS DATA SHOULD NOT BE USED FOR EXCAVATION OR

CONSTRUCTION PURPOSES. YOU ARE REQUIRED UNDER APPLICABLE STATE LAWS TO ACTIVATE THE ONE CALL PROCESS TO FACILITATE ANY LINE LOCATING REQUIREMENTS.

Created By: BWR

Date: August 11, 2014

[email protected]

Northeast Energy Direct (NED)Project Location Map

30 0 3015

Miles

Document Name: GISMS-556_Aug112014_FERC

7

NED Pipeline MAOP MOP State Dia Length (mi)1 Haverhill Lateral 1460 1460 MA/NH 16" 7.362 Lynnfield Lateral 1460 1460 MA 20" 16.593 West Nashua Lateral 1460 1460 MA/NH 12" 12.184 Fitchburg Lateral Extension 1460 1460 MA 12" 5.205 North Worcester Lateral 1460 750 MA 12" 14.437 300 Line CT Loop 800 800 CT 24" 14.578 Stamford Loop 1460 719 CT 12" 1.959 Pittsfield Lateral 1460 1460 MA 12" 1.5710 Loop 319-3 1200 1170 PA 36" 9.0511 Loop 317-3 1200 1170 PA 36" 22.9512 PA to Wright 1460* 1460* PA/NY 30" 134.8313 Wright to Dracut 1460 1460 NY/MA 36" 179.60

*MAOP/MOP between Troy to Wright Tail Station & Wright is 1600

35

37

38

Competitor Pipelines20 Hub Line21 M&NP22 M&NP & PNGTS Joint Facilities23 PNGTS24 M&NP25 Iroquois26 Constitution27 Millennium28 Dominion29 Algonquin

30 Station 319 Upgrades31 PA to Wright Head Station 32,000 HP32 PA to Wright Mid Station 20,500 HP33 PA to Wright Tail Station 30,000 HP34 Wright to Dracut Head Station 20,000 HP35 Wright to Dracut Mid Station 1 120,000 HP36 Wright to Dracut Mid Station 2 120,000 HP37 Wright to Dracut Mid Station 3 120,000 HP38 Wright to Dracut Tail Station 23,000 HP

Compressor Station