Upload
mou777
View
233
Download
3
Embed Size (px)
Citation preview
7/30/2019 Tendering Procedures
1/26
Ahmed Saleh Mokhtar, PMP1
1-1-Establishment of Project StrategyEstablishment of Project Strategy
2- Pre-qualification processes2- Pre-qualification processes
3- Obtaining Tenders3- Obtaining Tenders
4- Opening of Tenders4- Opening of Tenders
5- Evaluation of Tenders5- Evaluation of Tenders
6- Award of Contract6- Award of Contract
TENDERING PROCEDURAL FLOWCHARTS ACCORDING TO FIDIC
7/30/2019 Tendering Procedures
2/26
Ahmed Saleh Mokhtar, PMP2
Establishing procurement StrategyEstablishing procurement Strategy
Requirements definition!
1.0
ESTABLISHMENT OF
PROJECT STRATEGY
Establish project strategy comprising:
procurement method
form of tendering / Contracting
time schedules
Establish project strategy comprising:
procurement method form of tendering / Contracting
time schedules
SECTION EMPLOYER/ENGINEER CONTRACTORS
7/30/2019 Tendering Procedures
3/26
Ahmed Saleh Mokhtar, PMP3
Procurement Strategy
Whether to procure?
make or buy?, Break-even analysis.
Procurement planning is the process of identifying which
project needs can be best met by procuring products or
services outside the project organization and should beaccomplished during the scope definition effort. It involves
consideration of whether to procure, how to procure, what to
procure, how much to procure, and when to procure.
7/30/2019 Tendering Procedures
4/26
Ahmed Saleh Mokhtar, PMP4
Break - even AnalysisBreak - even Analysis
No.
of
Units
Cost
Buy
MakeBreak-even Point
7/30/2019 Tendering Procedures
5/26
Ahmed Saleh Mokhtar, PMP5
Procurement StrategyProcurement StrategyWhat, How, WhenWhat, How, When
How much to procure?
Work packages (E&M works, Finishing, etc)
Phases: Design, Construction, Testing (Design-Build, etc)
Project incl. Finance (BOT),
What to procure? Goods (Material and Equipment),
Services, combination of them.
When to procure? Master time schedule, long lead items,
market conditions (inflation, etc)
7/30/2019 Tendering Procedures
6/26
Ahmed Saleh Mokhtar, PMP6
How to procure: Bidding TypesHow to procure: Bidding Types
How to procure?
Bidding and Contract type selection.
Tenders: open, restricted and local tenders
Bidding Type:
Negotiations: open, restricted and local negotiations
Direct orders: special cases
7/30/2019 Tendering Procedures
7/26Ahmed Saleh Mokhtar, PMP7
How? Broad categories of contractsHow? Broad categories of contracts
Fixed-price or lump-sum contracts: involve a fixed total price for a well-
defined product. They may include incentives for meeting or exceeding
selected project objectives.
Cost-reimbursable contracts: involves payment (reimbursement) to the seller
for its actual costs, plus typically a fee representing seller profit. They often
include incentives for meeting or exceeding selected project objectives.
Re-measured contracts: are a hybrid type of contractual arrangement thatcontains aspects of both cost-reimbursable and fixed-price-type
arrangements. e.g. Fixed unit rates + variable quantities)
Incentive contracts: add to other types of contracts
7/30/2019 Tendering Procedures
8/26Ahmed Saleh Mokhtar, PMP8
Fixed Price / Lump sum ContractsFixed Price / Lump sum Contracts
Advantages Disadvantages
Firm assurance of cost Control of changes /
delays Min. Buyer follow up Quick completionincentive
Must have clearrequirements Delayed solicitation
documents High bidding costs Increased prices tocover Sel ler risks(contingencies)
Fixed total price for a well defined product
7/30/2019 Tendering Procedures
9/26Ahmed Saleh Mokhtar, PMP9
Cost Reimbursable ContractsCost Reimbursable Contracts
Advantages Disadvantages
Max. Flexibility to Buyer Min. Profit to Seller Min. Negotiations Min. Preliminary Specscosts
Min. Start time(Early completion)
Min. Risk of not qualifiedBidders with lowest price
No assurance of actualcost No financia l incentive Excessive changes indesign and (high) specs by
Buyer staff = more cost +time Auditing by Buyerrequired
Payment to the seller for its actual cost (direct and indirect) + fee
7/30/2019 Tendering Procedures
10/26Ahmed Saleh Mokhtar, PMP10
Incentive ContractsIncentive Contracts
Fixed-Price-Incentive-Fee
(FPIF)
Cost-Plus-Incentive- Fee
(CPIF) Final Price is guaranteedbe Seller (loss is possible) If actual cost < TargetCost, savings are shared
according to formula. If actual cost > TargetCost, Sellers Target fee is
reduced. Point of total assumption
Seller is reimbursed 100% ofcosts (loss is not possible) BUT a max. and min. feeexists If actual cost < Target Cost,savings are shared according to
formula. If actual cost > Target Cost,Sellers target fee is reduced.
7/30/2019 Tendering Procedures
11/26Ahmed Saleh Mokhtar, PMP11
Guaranteed max.-Share savingsGuaranteed max.-Share savings
Advantages Disadvantages
Firm assurance of costControl of changes / delaysMin. Buyer follow upQuick completion incentiveBuyer and Seller share risksPossible cooperation in furtherprojects
Clear requirementsComplete auditing b y Buyer
required
7/30/2019 Tendering Procedures
12/26Ahmed Saleh Mokhtar, PMP12
2.1
PREPARATION OF PRE-
QUALIFICATION
DOCUMENTS
Prepare pre- qualificationdocuments comprising:
letter of invitation
information about
prequalificationprocedure
project information
prequalification application
Prepare pre- qualificationdocuments comprising:
letter of invitation
information about
prequalification
procedure
project information
prequalification application
SECTION EMPLOYER/ENGINEER CONTRACTORS
2- Pre-qualification processes
RECOMMENDED PROCEDURE FOR THERECOMMENDED PROCEDURE FOR THE
PRE-QUALIFICATION FOR TENDERERS (1PRE-QUALIFICATION FOR TENDERERS (1))
7/30/2019 Tendering Procedures
13/26Ahmed Saleh Mokhtar, PMP13
2.2
INVITATION TO
PREQUALIFY
PREPARE PRE-QUALIFICATION
ADVERTISEMENT IN PRESS,EMBASSIES
ETC. AS APPROPRIATE STATING:
employer & Engineer
outline of project (scope, location,
programme, source of finance)
dates for issue of tender documents& submission of tenders
instructions for applying for pre-qualification
minimum requirements for pre-qualification
submission date for contractors pre-ualification
PREPARE PRE-QUALIFICATION
ADVERTISEMENT IN PRESS,EMBASSIES
ETC. AS APPROPRIATE STATING:
employer & Engineer
outline of project (scope, location,
programme, source of finance)
dates for issue of tender documents
& submission of tenders
instructions for applying for pre-qualification
minimum requirements for pre-qualification
submission date for contractors pre-qualification
SECTION EMPLOYER/ENGINEER CONTRACTORS
RECOMMENDED PROCEDURE FOR THE PRE-RECOMMENDED PROCEDURE FOR THE PRE-
QUALIFICATION FOR TENDERERS (2)QUALIFICATION FOR TENDERERS (2)
7/30/2019 Tendering Procedures
14/26Ahmed Saleh Mokhtar, PMP14
2.3
ISSUE & SUBMISSION
OF PREQUALIFICATION
DOCUMENTS
Issue prequalification documents &
questionnaires requesting from each
company/joint venture:
organisation & structure
experience in the intended type of
work & the region
resources:
- Managerial
- Technical
- Labour
- Plant
financial statements
current contract commitments
litigation history
Issue prequalification documents &
questionnaires requesting from each
company/joint venture:
organisation & structure
experience in the intended type of
work & the region
resources:
- Managerial
- Technical
- Labour
- Plant
financial statements
current contract commitments
litigation history
Acknowledge receipt
Acknowledge receipt
Complete & submit PQ documents
& questionnaires
Complete & submit PQ documents
& questionnaires
SECTION EMPLOYER/ENGINEER CONTRACTORS
Request Prequalification documentsRequest Prequalification documents
RECOMMENDED PROCEDURE FOR THE PRE-RECOMMENDED PROCEDURE FOR THE PRE-
QUALIFICATION FOR TENDERERS (3)QUALIFICATION FOR TENDERERS (3)
7/30/2019 Tendering Procedures
15/26Ahmed Saleh Mokhtar, PMP15
2.4
ANALYSIS OF
PREQUALIFICATION
APPLICATIONS
Analyse Prequalification data:
- company/joint venture structure
- experience
- resources- financial capailty
- general suitablity
Analyse Prequalification data:
- company/joint venture structure
- experience
- resources- financial capailty
- general suitablity
2.5
SELECTION OF
TENDERERSPrepare list of tenderersPrepare list of tenderers
SECTION EMPLOYER/ENGINEER CONTRACTORS
2.6
NOTIFICATION OF
APPLICANTS
Notify all selected tenderersNotify all selected tenderersAcknowledge & confirm
intention to submit tender
Acknowledge & confirm
intention to submit tender
SHORT LIST
RECOMMENDED PROCEDURE FOR THERECOMMENDED PROCEDURE FOR THE
PRE-QUALIFICATION FOR TENDERERS (4)PRE-QUALIFICATION FOR TENDERERS (4)
7/30/2019 Tendering Procedures
16/26Ahmed Saleh Mokhtar, PMP16
RECOMMENDED PROCEDURE FOR OBTAININGRECOMMENDED PROCEDURE FOR OBTAINING
TENDERS (1)TENDERS (1)
3.1
PREPARATION OF
TENDER DOCUMENTS
Prepare tender documents:
Letter of invitation to tender
Instructions to tenderers
General and special Conditions
of contract
Form of tender
Drawings and specifications
Bill of quantities
Additional information
Prepare tender documents:
Letter of invitation to tender Instructions to tenderers
General and special Conditions
of contract
Form of tender
Drawings and specifications
Bill of quantities
Additional information
SECTION EMPLOYER/ENGINEER TENDERERS
3- Obtaining Tenders3- Obtaining Tenders
7/30/2019 Tendering Procedures
17/26Ahmed Saleh Mokhtar, PMP17
Types of SpecificationsTypes of Specifications
Design Specs: What is to be done in terms of
physical characteristics, Riskon the Buyer.
Performance Specs: Measurable capabilities in
terms ofoperational characteristics of the end
product, Riskon the Seller. Functional Specs: The Seller describes the end
use of the product, Riskon the Seller.
7/30/2019 Tendering Procedures
18/26Ahmed Saleh Mokhtar, PMP18
3.3
VISIT TO SITE BY
TENDERERS
Arrange date and time
for visit site
Arrange date and time
for visit siteApply for visit to site if
required
Apply for visit to site if
required
Visit(s) to site by tenderers accompanied by
employer/engineer
Visit(s) to site by tenderers accompanied by
employer/engineer
Issue tender documents to
contractors on list of
tenderers
Issue tender documents to
contractors on list of
tenderers
Acknowledge receiptAcknowledge receipt
3.2
ISSUE OF TENDER
DOCUMENTS
RECOMMENDED PROCEDURE FOR OBTAININGRECOMMENDED PROCEDURE FOR OBTAINING
TENDERS (2)TENDERS (2)
SECTION EMPLOYER/ENGINEER TENDERERS
To 3.5To 3.5
7/30/2019 Tendering Procedures
19/26Ahmed Saleh Mokhtar, PMP19
3.4
TENDERERS
QUERIES
A) Correspondence
Method
B) Tenderers
Conference
Method
A) Prepare repliesA) Prepare replies
Submit queries in
writing by given date
Submit queries in
writing by given date
B) Inform tenderers present of queries and replies submitted
in writing. Replies to queries raised at conference
B) Inform tenderers present of queries and replies submitted
in writing. Replies to queries raised at conference
RECOMMENDED PROCEDURE FOR OBTAININGRECOMMENDED PROCEDURE FOR OBTAINING
TENDERS (3)TENDERS (3)
SECTION EMPLOYER/ENGINEER TENDERERS
Send minutes to alltenderers
Send minutes to alltenderers
Acknowledgereceipt
Acknowledgereceipt
Issue addenda including
replies to queries to all
tenderers
Issue addenda including
replies to queries to all
tenderers
Acknowledge
receipt
Acknowledge
receipt
3.5
ADDENDA TO
TENDER
DOCUMENTS
FORM 3.2FORM 3.2
7/30/2019 Tendering Procedures
20/26Ahmed Saleh Mokhtar, PMP20
3.6
SUBMISSION ANDRECEIPT OF TENDERS
Record date and time of
receipt
Record date and time of
receipt
Submit tenders
Acknowledge receipt or
return unopened tendersreceived late
Acknowledge receipt or
return unopened tenders
received late
RECOMMENDED PROCEDURE FOR OBTAININGRECOMMENDED PROCEDURE FOR OBTAINING
TENDERS (4)TENDERS (4)
SECTION EMPLOYER/ENGINEER TENDERERS
LIST OF TENDERERS
7/30/2019 Tendering Procedures
21/26Ahmed Saleh Mokhtar, PMP21
RECOMMENDED PROCEDURERECOMMENDED PROCEDURE
FOR THE OPENING OF TENDERSFOR THE OPENING OF TENDERS
4.1
OPENING OF
TENDERS
Tender opening by public or
restricted opening: announce and record the names of
tenderers and prices, including
prices for alternative tenders if
appropriate announce and record names of
tenderers (if any) disqualified due
to late or non-arrival of tenders
Tender opening by public or
restricted opening: announce and record the names of
tenderers and prices, including
prices for alternative tenders if
appropriate announce and record names of
tenderers (if any) disqualified dueto late or non-arrival of tenders
SECTION EMPLOYER/ENGINEER TENDERERS/CONTRACTOR
Attend public/
restricted openingif desired
Attend public/
restricted openingif desired
4- Opening of Tenders4- Opening of Tenders
7/30/2019 Tendering Procedures
22/26Ahmed Saleh Mokhtar, PMP22
RECOMMENDED PROCEDURE FORRECOMMENDED PROCEDURE FOR
THE EVALUATION OF TENDERS (1)THE EVALUATION OF TENDERS (1)
5.2 TENDERS
CONTAINING
DEVIATIONS
Evaluate deviations, seek clarification &
rank tenders as evaluated
Evaluate deviations, seek clarification &
rank tenders as evaluated
5.3
ADJUDICATIONOF TENDERS
5.4
REJECTION OF
ALL TENDERS
Assess tenders in accordance with
evaluation criteria Raise further points requiring
clarification, if any complete evaluation check with funding agency
Reject non-conforming tenders &advise tenderer(s) concerned
Assess tenders in accordance with
evaluation criteria Raise further points requiring
clarification, if any complete evaluation check with funding agency Reject non-conforming tenders &
advise tenderer(s) concerned
SECTION EMPLOYER/ENGINEER TENDERERS/CONTRACTOR
Provide clarificationProvide clarification
Provide clarificationProvide clarification
5.1
REVIEW OF
TENDERS
Establish conformity and completeness
of tenders, reject substantially
unresponsive tenders
Establish conformity and completeness
of tenders, reject substantially
unresponsive tenders
5- Evaluation of Tenders:5- Evaluation of Tenders:
7/30/2019 Tendering Procedures
23/26Ahmed Saleh Mokhtar, PMP23
Evaluation CriteriaEvaluation Criteria
Sample criteria:
Subjective and Objective Criteria
Often part of procurement documents, Why?
Overall life cycle cost: present value of purchasing, O&M, other costs.
Technical and managerial capabilities
Past experience
Financial capacity
7/30/2019 Tendering Procedures
24/26
Ahmed Saleh Mokhtar, PMP24
RECOMMENDED PROCEDURE FORRECOMMENDED PROCEDURE FOR
THE AWARD OF CONTRACTTHE AWARD OF CONTRACT
6.0
AWARD OF
CONTRACT
6.1
ISSUE LETTER OF
ACCEPTANCE
6.2
PERFORMANCE
SECURITY
Decide on contract
award, if necessary after
pre-award discussions
Decide on contract
award, if necessary after
pre-award discussions
SECTION EMPLOYER/ENGINEER TENDERERS/CONTRACTOR
Attend pre-award
discussions, if
required
Attend pre-award
discussions, if
required
Issue letter of acceptance Issue letter of acceptanceAcknowledge
receipt
Acknowledge
receipt
Obtain performance
security from contractor
Obtain performance
security from contractorProvide performance
security
Provide performance
security
7/30/2019 Tendering Procedures
25/26
Ahmed Saleh Mokhtar, PMP25
RECOMMENDED PROCEDURE FOR THE OPENING ANDRECOMMENDED PROCEDURE FOR THE OPENING AND
EVALUATION OF TENDERS (3)EVALUATION OF TENDERS (3)
6.3
PREPARATION
OF CONTRACTAGREEMENT
6.4
NOTIFICATIONOF
UNSUCCESSFUL
TENDERERS
SECTION EMPLOYER/ENGINEER TENDERERS/CONTRACTOR
Prepare contract documents
Signing of contract
Prepare contract documents
Signing of contract Signing of contractSigning of contract
Advise unsuccessfultenderers and return tender
security (if provided)
Advise unsuccessfultenderers and return tender
security (if provided)
Unsuccessfultenderers
acknowledge receipt
Unsuccessfultenderers
acknowledge receipt
7/30/2019 Tendering Procedures
26/26
Contract DefinitionContract Definition
A contract is a mutually binding agreement that
obligates the seller to provide the specified product
and obligates the buyer to pay for it. A contract is alegal relationship subject to remedy in the courts .
Contracts may be called, among other names, a
contract, an agreement , a subcontract, a purchase
order, or a memorandum of understanding.