Tendering (CONS6811) Lara Tookey TENDERING #4

TENDERING #4 - Weebly

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

TENDERING #4

Page 2: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Session FOUR

Face 2 Face (4 hours)• Stage 2 – Project

appreciation & enquiries

• Introduction to subcontracting

• Why does a MC need subbies?

• How is the work split between the various parties?

Self-directed (6 hours)

• Read before the session:

• Weebly• eBook• CIOB overview of

subcontracting

Page 3: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

ACTIVITY (20 MIN) Working with your peers

• Working with those around you, please evaluate the three samples provided in order to determine a BID / NO BID decision.

• Please keep a note of your queries / assumptions made for further discussion.

• Feedback will be requested.

Page 4: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Page 5: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Page 6: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Page 7: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Page 8: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Detailed Examination of Docs

• Adequacy of information in tender documents;

• Onerous or unusual conditions noted;• Discrepancies;• Specifications;

– Do they match the drawings?– Could be main contract document (if no Schedule of Quantities)

• Constructional problems.

Page 9: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

What kind of documents are we talking about?• The Contract – ‘rules’ NZS 3910/5/6:2013• Schedule of Prices / Quantities• Specifications• Drawings• Appendices i.e. consents; geotechnical

reports

Page 10: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Project Appreciation

• View Drawings• Visit Site & Locality:

• Visit site & prepare site report;• Take photos (demolition, alterations, additions);• Photograph surroundings i.e. buildings, fences,

paths etc.• Determine construction methods• Prepare Preliminary Programme

Page 11: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

CAN WE (THE MC) DO ALL THE WORK ON OUR OWN?

Page 12: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

What work with the MC do?

• Do it all within the contracting organisation!!

• Subcontract it all• Construction Management approach

• Combination of own work & subcontract work packages

• Generally • 30% own work• 70% subcontracted

• Project & Contractor specific• Most common approach

Aka Packaging Options

Page 13: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Objective of Packaging Strategies

• Obtaining competitive advantage through work package optimisation.

• Work packaging is the grouping of similar types of work processes to be carried out by one entity.

• Work Breakdown Structure (WBS)• Trade Based packaging

Page 14: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Work packages

• Each work package should consist of work that would be done by a specific class of subcontractor.

Page 15: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Remember!!

• Increasing the number of subcontractors on the job reduces financial risk to MC but increases communication complexity and cash flow problems for the project team

• Decision to subcontract versus retain works is a risk/return optimization problem

• Retained work has potential for greater reward, but carries more risk

• Retained is less risky when you have long-term trades people and well-understood market

Page 16: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Page 17: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Enquiries to Subcontractors

• Which trade packages will require subcontract quotations – send docs to sub-contractors;

• Include all relevant info to enable technically accurate quotations;• Terms & conditions detailed;• Identify ‘unique’ materials;

• Essential to indicate approximate time when goods / services required on site.

Page 18: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

WHAT DO WE MEAN BY SUB CONTACTING?

Page 19: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

• A subcontractor is a construction specialist that generally contracts with the MC (using a contract called a subcontract) to perform some aspect of the MC’s work (a particular portion / work package of the project)

Page 20: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

WHAT LEAD TO THE DEVELOPMENT OF SUB CONTRACTING?

Page 21: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Just a few issues

Transaction costs

Employee Training

Work RestructuringSafety and Health

Nature of the industry

Technological Change

Page 22: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

General pressures

• Different types of projects - different skills required.

• Increasing technical complexity / diverse skillbase requires increasing numbers of specialist inputs

• Perceived threat posed by trade unions.

Page 23: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Nature of Construction Industry

• Sites are geographically dispersed, some workers better placed for some sites than others.

• Traveling distances – more inclined to employ from local workers.

Page 24: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

• Non-wage cost (transaction) of employment i.e. training, pension rights, sick pay, redundancy payments;

• If price of using SC’s exceeds cost of internal utilisation of resources, firm will in-source.

• If, however, cost of in-house production exceeds that of contracting out work, firm will opt for outsourcing.

Page 25: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Advantages of using subbies

• Efficient and economical in the use of available resources.

• The prime contractor can obtain workers with the requisite skills when they are needed, without the necessity of maintaining an unwieldy and inefficient full-time labor force.

Page 26: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Advantages of using subbies

• Qualified subcontractors are usually able to perform their work more quickly and at lesser cost than can the main contractor.

• Many construction specialties have specific licensing, bonding, and insurance requirements that would be costly for the main contractor to secure for irregular use.

Page 27: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

ACTIVITY (10 MIN) Working with your peers

So, what do you think the disadvantages of subcontracting are?

Page 28: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Issues related to dealing with SC’s

• Job spiking. • Occurs when a SC signs up for more work than he

can handle & then starts a little bit of each project to secure the work.

• The MC is left with a SC who simply does not have motivation or capabilities to pursue work in a timely manner.

• SC do not understand / care about the domino effect their non-performance causes.

Page 29: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

• Extensive subcontracting can seriously complicate the overall scheduling of job operations, lead to a serious division of project authority, fragmentize responsibility, make the coordination of construction activities difficult, weaken communication between management and the field, foster disputes, and be generally detrimental to job efficiency.

Page 30: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

• The MC remains responsible under its contract with the owner for any faulty performance by the subcontractor.

• The MC assumes complete responsibility to the owner for the direction and accomplishment of the total work including the responsibility of coordination and supervision of the subcontractors.

Page 31: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

ACTIVITY (10 MIN) Working with your peers

Identify and explain the difference

between the various types of

subcontractors.

Page 32: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Types of Sub-contractors

• Domestic• Selected and appointed by the MC.• MC responsibility to ensure delivery, quality,

progress etc.• Supply & fix all labour, plant & material.

Page 33: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Types of Sub-contractors

• Nominated• Selected by Client• Client negotiates a price with nominated subbie

and then instructs MC to appoint them for that work.

• MC may make ‘reasonable objection’• MC will include price as a prime cost sum, to

which they can add overheads, profit and attendance.

• Declining practice

Page 34: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Types of Sub-contractors

• Named• Subbie for a particular package selected from a

list of acceptable subbies provided by the client.• Allowed for in the tender docs by means of

provisional sums for which the MC makes allowance for profit, attendance and programme within it’s tender offer.

Page 35: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

• Named cont.• Once appointed, the MC seeks tenders for the

package from the named subbies, places a sub-contract with successful tenderer, and provisional sum is replaced with tendered figure.

• MC responsible for performance • Delays, performance etc

• MC also completes payment certificates.

Page 36: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Types of Sub-contractors

• Labour-only / Labour & plant only• Materials provided by MC.

• Eg brickwork & concreting gangs; reinforcement steel SC.

• Selected & engaged as per Domestic SC.• MC responsible for delivery, quality, progress etc

Page 37: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Subcontractor selection process

Page 38: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Three Stage Process

• Preparation phase• Determine a bid list

• ‘Public’ call or select

• Implementation phase• Notification

• Analysis / tender phase• Receive bids• Evaluate the bids• Choose the best SC• Inform all bidders of results.

Page 39: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Preparation Phase -Determine a Bid List

• Most MC’s maintain comprehensive records concerning suppliers & sub-contractors.

• History of past performance;• Aka track record• Perceptions of quality• Financial stability

• Extent of geographical operation;• Size & type of contract on which previously

used;• Information concerning contracts.

Page 40: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Implementation PhaseNotification

• Provide info required by tenderers:• Contract documents• Tender information

• Tender format & submission date & time.• Contact for further information• Updates• Clarifications

Page 41: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Page 42: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Method of Construction

• Alternative methods of construction, sequencing of work and site layouts need to be evaluated.

• Requirements for labour, plant & site facilities determined.

• Technical risks:– Define construction methods before costing the

work.– If cost of failure high in relation to value of project –

insure against possible loss, or increase control.

Page 43: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Programme & Temp works design

• Done by specialists.• You will need to work closely with them in

order to develop your P&G costs.

Page 44: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Page 45: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Site Report

• Description of site

• Description of access to site

• Topographical details of the site

• Description of restrictions to / on site

Page 46: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

• Description of ground conditions

• Position of existing services

• Any problems related to security of the site• Facilities for disposal / storage of soil• Location of site amenities.

Page 47: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

• Description of any demolition work

• Description of temporary works

• Assessment of availability of labour

Page 48: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

• Identify• Local Statutory Authorities• Building surveyors• City engineers• Emergency services

Page 49: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Page 50: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Page 51: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Page 52: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

Session FIVE – Chris Prigg

Face 2 Face (4 hours)

• Stage 3 – Resource & Preparation of the Estimate

• Pricing

Self-directed (6 hours)

Page 53: TENDERING #4 - Weebly

Tendering (CONS6811) Lara Tookey

YOUR ASSESSMENTS

Q&A