BHARAT HEAVY ELECTRICALS LIMITED (A Govt Of India Undertaking) POWER SECTOR – EASTERN REGION PLOT – DJ 9/1, SECTOR II, SALT LAKE KOLKATA – 700 091 TENDER NO PSER:SCT:SRG-M1576:14 VOLUME II SCOPE, TECHNICAL SPECIFICATION JOB Design, engineering, supply, erection & commissioning of Elevator Package for 2x660 MW Super Critical TPS, Stage-V, RRVUNL,Suratgarh, Rajasthan. CAPACITY 2x660 MW, PROJECT Suratgarh Super Critical TPS, Rajasthan. Stage-V, Unit # 7 & 8.

TENDER PSER:SCT:SRG-M1576:14 NO VOLUME II … · bharat heavy electricals limited (a govt of india undertaking) power sector – eastern region plot – dj 9/1, sector ii, salt lake

  • Upload
    dangbao

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

  • BHARAT HEAVY ELECTRICALS LIMITED (A Govt Of India Undertaking)

    POWER SECTOR EASTERN REGION PLOT DJ 9/1, SECTOR II, SALT LAKE

    KOLKATA 700 091

    TENDER NO

    PSER:SCT:SRG-M1576:14

    VOLUME II SCOPE, TECHNICAL SPECIFICATION

    JOB Design, engineering, supply, erection & commissioning of Elevator Package for 2x660 MW Super Critical TPS, Stage-V, RRVUNL,Suratgarh, Rajasthan.

    CAPACITY 2x660 MW, PROJECT Suratgarh Super Critical TPS, Rajasthan. Stage-V,

    Unit # 7 & 8.

  • RAJSTHAN RAJAY VIOYUT UTPADAN NIGAM LTD.

    (RRVUNL) JAIPUR.

    2X660 MW SURATGARH SCTPS SATGE-V. (Unit# 7 & 8)

    VOLUME - II B & III

    TECHNICAL SPECIFICATION

    FOR

    ELEVATOR

    SPECIFICATION NO. PE-TS-392-502 -AOOI

    BHARA T HEAVY ELECTRICALS LIMITED

    (A Govt. of India Undertaking)

    POWER SECTOR

    PROJECT ENGINEERING MANAGEMENT

    NOIDA, U.P

    INDIA

  • TITLE

    TECHNICAL SPECIFICA liON

    FOR

    ELEVATOR PREAMBLE

    SPECIFICATION NO. PE -TS - 392 - 502- A001

    VOLUME III

    SECTION

    REV o I DATE 23.12.2013 SHEET OF

    1.0 The tender document contains three (3) volumes. The bidder shall meet the requirements of these documents.

    VOLUME-I Condition of Contract: This consists of four parts as below: Volume-IA: This part contains instructions to bidder for making bid to BHEL. Volume-IB: This part contains general commercial conditions of the tender and includes provision that

    Vendor shall be responsible for the quality of item supplied by their sub-vendors. Volume-IC: This part contains special condition of contract. Volume-ID: This part contains commercial condition for erection and commissioning site work, as

    applicable.

    VOLUME-II Technical Specification

    Volume-IIA: General technical conditions. Volume-liB: Technical specification including drawings, if any. This volume is subdivided in to following

    sections. (SH 1-113) Section-A: This section out lines scope of enquiry. (SH 2-3) Section-B: This section provides project information. (SH 4-7) Section-C: This section indicates technical requirements specific to the contract not covered in to

    section-D. This section is subdivided in following subsections. (8 -113) Sub-section C 1 : Specific technical requirements (Mechanical) (SH 09-37) Sub-section C2: Specific technical requirements (Electrical) (SH 38-107)

    ANNEXURE-A: List of Mandatory Spares: (SH 108-109) Section-D: This section comprises of technical specifications of equipment's complete with data

    sheet A. Data sheet-A: TG Building, Service and Administrative building elevator (SH 110-113)

    VOLUME-III (SH 114 -130)

    1. Compliance cum confirmation certificate (SH 116-117) 2. Schedule of technical deviation (SH118) 3. Specific confirmation. (SH 119-120) 4. Technical schedules I Data sheets B (SH 121-124) 5. Performance guarantee & weight & dimension (SH125-126) 6. Checklist for bidder of elevator (SH 128) 7. Main drawing List (SH 129) 8. Drawing documents submission schedule (SH 130)

  • 0)

    II TITLE

    TECHNICAL SPECIFICATION

    FOR

    ELEVATOR

    SPEC. NO. PE

    VOLUME

    SECTION

    REV

    SHEET

    TS - 392 - 502 - A001

    II

    D

    IDATE0 23 -12 - 13 OF

    VOL -II B

  • 02 TITLE I SPEC. NO. PE - TS -392 - 502 - A001

    Ii TECHNICAL SPECIFICATION VOLUME liB FOR SECTION A ELEVATOR REV 0 IDATE 23-12 -13

    SHEET OF

    SECTION -A

    SCOPE OF ENQUIRY

  • ill TITLE

    TECHNICAL SPECIFICATION

    FOR

    ELEVATOR

    SPECIFICATION NO. PE - TS -392 - 502 - A001

    VOLUME liB

    SECTION B

    REV 0 I DATE 23 -12 - 13 SHEET OF

    SECTION - B

    PROJECT INFORMATION

  • oS-

    SPEC,NO. VOLUME II

    TATA CONSULTING ENGINEERS LIMITED TCE.S7S0A-H-SOO-OO1 SECTION-B

    RRVUNL, 2 x 660 MW, Super-Critical TPS, Stage-V, SHEET 10F 3Unit # 7 &8 at Suratgarh, Rajasthan

    GENERAL PROJECT INFORMATION

    1.0 Owner Rajasthan Rajya Vidyut Utpadan Nigam Ltd., Jaipur

    2.0 Consulting Engineer TATA Consulting Engineers Ltd. 73/1, St. Marks Road, Bangalore - 560 001

    Tel : 080 - 6622 6000 Fax: 080 - 22274874

    3.0 Location of the plant Prabat Nagar, Suratgarh Sriganganagar district, Rajasthan.

    4.0 Latitude and long itude Latitude : 29 deg. 10 min. N Longitude: 74 deg.01 min. E

    5.0 Elevation above mean sea level 186 m (approximate)

    6.0

    i 6.1

    Climatic conditions

    Temperatures: Monthly basis

    Mean of daily max. Mean of daily min.

    32.8 deg.C (in the month of May) 17.6 deg.C (in the month of Jan)

    6.2 Temperatures: Annual basis

    Mean of daily max. Mean of daily min.

    32.3 deg.C 19.6 deg.C

    Highest temperature recorded 50 deg.C

    Lowest temperature recorded Design Ambient Temperature for Electrical Equipment design

    (-) 2.8 deg.C 50 deg C

    6.3 Relative humidity Varies between 21 % and 81 %

    6.4 Annual average rain fall 312 mm

    6.5 7.0

    i Annual mean wind speed: Wind load

    4 km I hr.

    ISSUE

    RI

    FORM NO. 329 R5

  • 06 SPEC.NO. VOLUME II

    TAT A CONSUL TING ENGINEERS LIMITED TCE.S7S0A-H-SOO-OO1 SECTION-B

    RRVUNL, 2 x 660 MW, Super-Critical TPS, Stage-V, SHEET 20F 3Unit # 7 & 8 at Suratgarh, Rajasthan

    GENERAL PROJECT INFORMATION

    I Calculations for wind effect shall be in accordance with IS:875-1987(Part-3) taking into account the following:

    8.0

    a) Basic wind speed =47 m/sec b) Factor K1 =1.07 c) Category of terrain =Category 2 d) K3 as per IS 875 Seismic data (As per IS: 1893 latest issue)

    a) Zone Zone II

    Designs & design coefficients shall be based on IS 1893:2002

    Design condenser cooling water inlet temperature

    33 Deg C

    9.0 Auxiliary power supply:

    Auxiliary electrical equipment to be supplied against this specification shall be suitable for operation on the following system:

    a) For motors rated 160 kW and below.

    415V AC, earthed.

    3-phase, 3-wire effectively

    b) For motors rated above 160 kW

    and up to 1500 kW

    6600V AC, 3-phase, 3-wire, 50 Hz, non-effectively earthed

    c)

    d)

    e)

    For motors rated above 1500kW

    ~IUl\' r control centres

    IIIULUI ~tarters, DC solenoids,

    11000V AC, 3-phase, 3-wire, 50 Hz, non-effectively earthed

    415V AC, 3-phase, 3/4-wire effectively earthed.

    220 V DC, 2-wire unearthed ;:'C cucu III control and protection

    f) AC control & protective devices 110 V 1 phase, 50Hz, 2 wire AC supply. The single phase 110V AC supply shall be derived by VENDOR by providing 415V / 11 0 V Control transformers of adequate rating with MCCB / MCB on both the primary and secondary sides.

    g) Uninterrupted power supply 230 V, 1-phase, 50 Hz, 2-wire, AC

    ISSUE

    RI

    FORM NO. 329 R5

  • 01 SPEC.NO. VOLUME II

    TATA CONSULTING ENGINEERS LIMITED TCE.5750A-H-500-001 SECTION-B

    RRVUNL, 2 x 660 MW, Super-Criticar TPS" Stage-V, SHEET 30F 3Unit # 7 & 8 at Suratgarh, Rajasthan

    GENERAL PROJECT INFORMATION

    supply (For all instrumentation and control system equipment and solenoid valves)

    g)

    h)

    Lighting 'fixtures and space heaters

    Construction supply

    240 V, 1 phase, 2 wire, 50Hz,solidly earthed system 415 V, 3 phase, 4 wire, 50Hz AC supply with neutral lead solidly earthed.

    i) The above voltages may vary as follows:

    All devices shall be suitable for continuous operation over the entire range of voltage and frequency indicated below without any change in their performance.

    AC supply Voltage variation 10% Frequency variation 5%

    j) DC supply For instrument and control system of steam generator and steam turbine generator.

    Combined voltage & frequency variation 10% Voltage variation +10% ,-15% 230 V 5% AC UPS, 1-phase, 50 Hz, 2-wire. The 24 V DC required for control system shall be generated from this UPS.

    10.0 All the electrical equipment shall be designed for 50 C reference ambient temperature.

    ISSUE

    Rl

    FORM NO. 329 R5

  • TITLE:

    TECHNICAL SPECIFICATION FOR

    ELEVATORS

    SPEC. NO. PE-TS-392-502-AOOI

    VOLUME lIB

    SECTION C I SUB-SECTION

    REV. 00 I DATE: 23/12/2013

    SHEET 1 OF 13

    SECTION - C SPECIFIC TECHNICAL

    REQUIREMENTS

  • 09

    Ii TITLE

    TECHNICAL SPECIFICATION

    FOR

    ELEVATOR

    SPEC. NO. PE TS 392 - 502 - A001

    VOLUME liB

    SECTION C

    I REV 23-12-13

    SHEET OF

    SECTION - C1 Specifics Technical Requirements (Mechanical)

  • 10

    1.0

    2.0

    2.0.1

    SI. no 1.

    2

    3

    2.0.2

    1)

    2)

    3)

    4)

    5)

    6)

    TITLE: TECHNICAL SPECIFICATION

    FOR ELEVATORS

    SPEC. NO. PE-TS-392-502-AOOI

    VOLUME lIB

    SECTION C I SUB-SECTION

    REV. 00 IDATE: 23/12/2013 SHEET 2 OF 13

    Introduction

    Passenger elevator shall be provided for access to various operating floors I platforms in TG building, Service building and Administrativebuilding for 2x660 MW SURATGARH STPP Project to facilitate movement of operating and maintenance personnel.

    Scope of equipment supply and services

    Design, Engineering, Manufacture, Inspection & Testing at manufacturer's works or at their sub-vendor's works, Painting at manufacturer's or at their subvendor's works, duly packed for transportation to site, delivery to site, storage and handling at site, Erection & Commissioning, carrying out trial run and Acceptance I Functional Tests at site & finaJ painting of Passenger Elevators for 2 x 660 MW SURATGARH STPP as listed below:

    Building No. of Capacity No. of Total Type Speed elevators landings rise

    TG Building I 1 No. 680 Kg O.Om, 3.5M, 28M Conventional 1.0 m/s Station building 8.5m, 12.0m (Passenger

    ,17.0m, 24.0m, Elevator)

    and last landing at 28.0m. (Seven including ground)

    Service 1 No. 1360 Kg O.Om, 4.25m, 17.0M Conventional 0.75 building 8.5m, 12.75 and (Passenger m/s

    last landing at cum goods 17.0m. (Five Elevator) including ground)

    Admin Building 1 No. 884 Kg l.Om, 5.5m, and 9.0M Conventional 1.0 m/s last landing at (Passenger 1O.Om, (Three Elevator) including ground)

    Elevator shall include but shall not be limited to the following:

    Elevator car.

    Guide rails for car and counterweights.

    Counterweight.

    DCEM brakes.

    Spring buffer for car and counterweight.

    Driving arrangement including motor, gear box, sheaves etc.

  • 1 ,

    7)

    8)

    9)

    10)

    11)

    12)

    13)

    14)

    15)

    16)

    17)

    18)

    19)

    20)

    21)

    22)

    23)

    24)

    25)

    TITLE: TECHNICAL SPECIFICATION

    FOR ELEVATORS

    SPEC. NO. PE-TS-392-502-AOOI

    VOLUME liB

    SECTION C I SUB-SECTION REV. 00 I DATE: 2311212013 SHEET 3 OF 13

    All electrical equipment including power cable, control cable, controller panel, safety devices including push buttons, limit switches, safety switches, indicators etc.

    Car doors and hoist way doors.

    Car operating panel, digital control, car position indicator at all 'noors, luminous hall buttons, auto door operating mechanism, alarm bell, car light & car fan.

    Intercom connection.

    Ropes for hoisting.

    Circuit breaker, switch fuse unit etc. in machine room for terminating the power supply cable (power supply cable provided by purchaser up to machine room level), other power/control and trailing cabling and equipment earthling.

    Ladder in pits.

    Emergency light with rechargeable battery.

    All fixing materials require fixing rails, brackets, equipment including nuts and bolts.

    Facia plates (750 mm minimum) & sill angels.

    Full length infra-red Curtain safety feature in door along with pressure limiter as an extra mechanical safety.

    ELCB if required as per statutory requirement.

    Any other equipment required to meet the requirement of local statuary and regulatory body and prevailing lift etc.

    Car lighting, recessed nuorescent light fittings for illumination level of 100 lux on car floor.

    Mirror.

    Floor announcement cum music system to be provided.

    List of mandatory spares in terms of numbers/ sets shall be furnished by the bidder along with the offer.

    Recommended spares for three (3) years of trouble operation. Bidder to furnish un-priced list along with the offer.

    Three (3) sided SS- mirror finish hand railing at suitable height.

  • 12 TITLE:

    TECHNICAL SPECIFICATION FOR

    ELEVATORS

    SPEC. NO. PE-TS-392-502-AOOI

    VOLUME lIB

    SECTION C I SUB-SECTION

    REV. 00 I DATE: 23/12/2013 SHEET 4 OF 13

    26)

    27) 2B)

    29.

    30.

    31.

    32.

    33.

    34.

    35

    36

    37

    Maintenance tools and tackles along with un-priced list with the offer.

    Minor civil work required during installation of elevator. Automatic rescue device with battery drive - Modern advanced electronic drive system of rescuing passenger trapped in an elevator shall be provided.

    Emergency safety devices - The lift shall be provided with safety device attached to the lift car frame and sustaining the lift car up at governor tripping speed with full rated load in car.

    All steel embedment for fixing landing doors 1 indicators etc. to the elevator well shaft and fascia plate shall be supplied by the bidder

    Guide rails complete with supporting brackets for the car and counter weights.

    Elevator drive machines complete with electric motor, reduction gear unit, suspension ropes, buffers for the cars and the counter weights and other drives and control mechanism. All foundation anchor bolts, sleeves, anchoring steels and any item required to complete the job satisfactorily shall be provided by the bidder. The bidder shall also provide for the grouting of anchor bolts, sleeves, anchoring steel etc. and other anchorages. Bidder shall provide hoist and hoisting beam in the machine room ceiling.

    Any other steel works as well as all other accessories 1 components not specified in the technical specification but necessary for making the elevator complete.

    All minor building works including the supply of steel items, associated with installations of equipments in the machine room hoist way, hoist way door, frames and elevator pit, shall form part of bidder's scope of supply, BHEL 1 customer will provide the elevator well complete with foundation and brick walls around the lift well together with overhead machine room. The machine room will be provided with RCC floor slab with necessary pockets for anchor bolts and slots. Window 1 split type air conditioner (min 2T) in the machine room which includes fans, air 'filter and accessories to prevent dust ingress in the machine room 1/2 Kg C02/suitabie type Fire extinguisher in bidder scope. Fixing arrangement shall be provided in Car accordingly Scope demarcation:S. No Civil scope Electrical Scope Remarks 1) BHEL / customer Elevator Shaft, Pit and Car lighting by bidder as

    except minor civil M/c room lighting by per electrical specification. like grouting etc bidder as per electrical which shall be in specification bidder's scope

    3B. Please also refer enclosed customer specification vide Volume-IV section D14, PART-B, and for mandatory spares vide Volume-II, Section CB.

  • NOTES:

    TITLE: TECHNICAL SPECIFICATION

    FOR ELEVATORS

    SPEC. NO. PE-TS-392-502-AOOI

    VOLUME lIB

    SECTION C I SUB-SECTION REV. 00 I DATE: 23/12/2013

    SHEET 5 OF 13

    1) Flooring for all passenger type elevators shall be PVC tile as indicated in the Data sheet except for Passenger cum Goods elevators which shall be MS chequered plate.

    2) Bidder shall submit the type and capacity of air conditioner required for machine room in the technical bid. However, successful bidder shall furnish the heat load calculation and capacity of air conditioner after considering all actual heat loads of m/c room during detait engineering stage for BHEL's reference and record.

    3) Functional Guarantee test shall be carried out at site for over speed test and over load test, travel and hoist speed checks as per IS: 14665 (Latest).

    4) Car, landing door and car ceiling shall be of SS-304 sheet with thickness (min) 1.5 mm.

    5) Bidder shall fill the electrical load data for project as per the format provided in the specification along with bidder offer.

    6) Min dimensions as specified in applicable IS 14665 (all five parts) shall be considered I provided for lift shaft I pit I car I M/c Room. Safety requirement shall be as per IS 14665 (Relevant part).

    7) All Equipment's I facilities needed for erection commissioning of elevator shall be in bidder's scope.

    8) Bidder to note that all L T Power cables (Fixed power and control cables etc), Trailing cable and instrument I signal cable for elevator shall be in bidder's scope as per electrical specification. Trailing cable shall be FRLS type (with strain bearing member). Detailed cable specification shall as per cable specification attached in electrical portion specification.

    9) Make of various bought out items & QAP shall subject to approval of BHEL I Customer during detail engineering stage.

    10) Bidder shall provide all required spares during E & C without any commercial implication.

    11) Car frame and structure (guide brackets, supports etc) shall be painted with epoxy based paint for all elevators.

    12) Protection class for motor shall be IP 54 and main control panel shall be min IP 21 and elevator control shall be VVVF type. Push buttons, Car operating Panel, Landing Operating Panel, Landing door motor and other equipment shall be I P54.

    13) Factor of safety for rope shall be 12 (min).

  • 14)

    15)

    16)

    17)

    a) b) c) d) e)

    18)

    19)

    20)

    21)

    22)

    23)

    24)

    i) ii) iii)

    TITLE: TECHNICAL SPECIFICATION

    FOR ELEVATORS

    SPEC. NO. PE-TS-392-502-A001

    VOLUME lIB

    SECTION C I SUB-SECTION REV. 00 I DATE: 23/1212013 SHEET 6 OF 13

    All Landing door shall be fire rated for at min 1 hour or as per latest IS.

    Motor shall be S4 duty with insulation class F & temp rise limited to class B.

    Full length infra-red Curtain safety feature in door along with pressure limiter as an extra mechanical safety.

    Bidder shall submit the following documents (min) for BHEL/customer approval during detail engineering stage:

    General arrangement of Elevator Technical data sheet of elevator Technical data sheet of motor along with power, control and trailing cable details Wiring schematic diagram MQP for elevator along with test procedure of various components.

    Bidder shall comply to the quality requirements as enclosed with specification. Quality plan shall be submitted by the successful bidder for approval during detail engineering.

    Bidder shall provide equipment as per requirements indicated in this specification, statutory and regulatory requirements, and prevailing local lift act requirements.

    Bidder shall confirm that supply, installation and commissioning of elevator shall be completed within project schedule as indicated elsewhere from placement of intent I letter of intent.

    Bidder shall be responsible for obtaining all necessary approval from statutory and regulatory body and lift inspector. However, purchaser will furnish required information time to time basis, if required.

    Bidder shall include scaffoldings required in their scope of work.

    Elevator shall be provided with AC VWF type drive control system.

    All eqUipment shall be treated with anti corrosive paint I zinc plating.

    Bidder shall furnish the following documents onlv during tender stage as a part of technical bid. Any other technical documents furnished by bidder shall not be considered as the part ofoffer :

    Electrical load list for each elevator Deviation schedule (if any) GA of elevator with Pit, shaft, M/c room details and motor power calculation for all types and capacities of elevator

  • III iv) v) vi)

    3.0

    1)

    2)

    3)

    4)

    5)

    6)

    7)

    8)

    9)

    10)

    4.0 1)

    2)

    3)

    4)

    TITLE: TECHNICAL SPECIFICATION

    FOR ELEVATORS

    SPEC. NO. PE-TS-392-502-A001

    VOLUME lIB

    SECTION C I SUB-SECTION REV. 00 I DATE: 23/12/2013 SHEET 7 OF 13

    Signed and stamped copy of Electrical scope matrix and electrical specification Signed and stamped copy of Specific confirmation sheet (Annexure II). Capacity of air conditioner for machine room and hoist

    Note: In case bidder fails to furnish any document specified above, bidder's offer shall be treated as incomplete and shall liable to be rejected.

    SCOPE OF SERVICES Scope of services will broadly include the followings:

    Complete erection, testing and commissioning including all testing and commissioning materials, consumables and other tools and tackles required for erection of complete elevator package.

    Painting of all equipments I items within the battery limit.

    Unloading, storage, handling and transportation at site for all items of elevator.

    Minor civil and structural works

    Necessary consumables and instrumentation as required for inspection and testing at works as well as at site including pre-commissioning activities, if any, shall be arranged by the successful bidder at their own cost.

    PG testing of complete elevator package.

    Preparation of civil input drawings including elevator pit, shaft, machine room etc.

    Preparation of all necessary drawings I data sheets I documents I calculations as required for obtaining necessary local administration permits I approval from statutory authority and make arrangements for inspection and tests required thereby for necessary approval on behalf of the customer. Fees as required for obtaining approval from statutory bodies shall also be included in the scope of work of the bidder.

    Any other service as required for making the installation complete in all respect and satisfactory erection and commissioning of the system.

    Relevant requirements as per GTR, GCC, ECC & SCC.

    Exclusion

    Complete civil works for hoist way, machine room, pit complete with the side enclosure (brick I RCC), interconnecting platform (if any) and monorail beam. Manual hoist with travelling trolley of 3T capacity to facilitate handling of equipment in the machine room.

    Power supply cable (AC 415 V, 3 Ph, 50 Hz) up to machine room level. Further cabling (all cables including power, control and instrumentation) shall be provided by the bidder.

    Electrical exclusion as per separate scope sheet attached in the specification.

  • 'ZI TITLE:

    TECHNICAL SPECIFICATION FOR

    ELEVATORS

    SPEC. NO. PE-TS-392-502-AOOI

    VOLUME lIB

    SECTION C I SUB-SECTION REV. 00 I DATE: 23112/2013 SHEET 8 OF 13

    5.0

    a)

    b)

    c)

    d)

    e)

    f)

    g)

    h)

    i)

    j)

    k)

    Operation

    Elevator shall have provision to meet followings operational reqlJirements:

    Selective simplex collective, automatic operation with or without attendant through illuminated push button station located inside the lift car.

    Door operating shall be automatic. Infrared curtain type electronic door protection system for opening I closing of car & landing doors and shall be provided so that in case there is any obstruction in its path while the door is closing, car & landing door shall return to open position.

    Bidder shall provide car operating panel with luminous buttons, car position indication in car (both visual and audio) combined with direction arrows, overload warning indicator, battery operated alarm bell and emergency light and fan and hands free speaker telephone set with suitable battery, charger and controls.

    Every passenger lift shall be provided with an overloaded devise, which will prevent the lift from starting in case the lift car is loaded to 110 % of the rated capacity of the lift or more. Lift shall remain stationary with door open. Audio and visual warning device shall be provided to alert the passengers in case of overload.

    An electric contact for the car door shall be provided which shall prevent elevator movement away from the landing unless the door is in the closed position. The mechanical interlock with auxiliary's door closing device shall be provided so that elevator can be operated only after the interlock circuit is established.

    Bidder shall provide emergency indicator to indicate the location of elevator in case of elevator being stuck up between the floors through automatic flashers (both audio and vislJal).

    Bidder shall provide electronic door detector (infrared curtain type).

    Two (2) push buttons, one for upward movement and the other for downward movement at each intermediate landing and one (1) push button at each terminal landing shall be provided in order to call the car. Digital hall position indicator at all floors, tell lights at all floors shall also be provided by the bidder.

    All fixtures shall be in stainless steel face plates.

    Push buttons shall be fixed in the car for holding the door open for any length of time required. Power supply mains shall be lockable as per requirements of IS: 1860

  • 17 SPEC. NO. PE-TS-392-502-AOOI TITLE:

    TECHNICAL SPECIFICATION VOLUME lIB FOR SECTION C I SUB-SECTION

    ELEVATORSWi,j' REV. 00 I DATE: 23112/2013 SHEET 9 OF 13

    I) With each lift bidder shall supply a maintenance tool kit which shall be kept in machine room.

    m) All other safety / protection / operation interlocks as required by IS - 14665 (all parts) latest edition.

    n) Operating devices and indicating devices shall be as per table given below.

    Ogerating devices

    In the car In the landing In the m/c room On top of the car UP push button (PB)

    UpP.B UpP.B Up

    Down PB Down PB Down PB Down Number PBs for each landing

    Bell - stop

    Bell PB, Phone Lift PB Stop PB 240 V 1 Ph Non- stop PB Door open PB Door close P B Alarm PB Key operated selector for attendant operation.

    - - -

    I ndicating devices.

    In the car On the landing Up direction of travel Up direction of travel Down direction of travel Down direction of travel Floor position indicator Car position indicator with direction Illuminated numeral for each landing (illuminated numeral for each landing) Landing car registering unit (with buzzer & registration cancelling unit & lamp test push button)

    Call registered 'Up' indicator

    Call registered 'down' indicator Lift out of order

    6.0 Electric Motor The driving motors shall conform to IS 325 and suitable for variable voltage variable frequency (VWF) application. All motors shall be squirrel cage induction type, suitable for operation at 415 V (+/- 10% variation), 3 Phase, 3 wire, 50 Hz (+5% to -5% variation) supply. Motors shall be provided with class F insulation & temp rise limited to class B.

    7.0 Controls

    The control shall be variable voltage and variable frequency type and shall provide smooth and constant acceleration and retardation under all conditions of

  • 18 SPEC. NO. PE-TS-392-502-AOOITITLE:

    TECHNICAL SPECIFICATION VOLUME liB FOR SECTION C I SUB-SECTION

    ELEVATORS REV. 00 I DATE: 23/12/2013

    SHEET 10 OF 13

    operation. Suitable control panels shall be provided in the machine room. The lift will be automatically stopped by upper and lower terminal switches. The elevators will have an emergency stop switch, limit switches and other safety devices according to statutory rule.

    8.0 Cables and wirings

    The cables used in the elevator installations shall conform to the latest edition of IS 4289(Please also refer electrical portion specification - cables and carries system at running). All wiring I cabling between the equipments in the lift machine room and that between the machine room and equipment in the lift well and at the landing shall be wired in HOP conduits I galvanised steel conduits to be supplied by the bidder. Alternatively, armoured cables may be used. However, bidder shall refer detailed specification of cables I wirings elsewhere in the specification.

    9.0 Earthing

    The elevator structures and all electrical equipments, including metal conduits shall be effectively earthed with the earth conductors provided in the machine room as per IS 3043. (Please also refer electrical portion specification - Earthing and lighting protection system.)

    10.0 DESIGN CRITERIA The design criteria and equipment specification will be as follows:

    i) The rated speed will be one (1) m/sec for passenger elevator and 0.75 m/sec for passenger cum goods elevator. Proper allowance will be made for impact and wear and the factor of safety for rope shall not be less than twelve (12) or as per IS 14665 (all parts). The suspension wire rope will confirm to IS-14665 or approved equivalent international standard.

    ii) The lift will be providing with automatic travelling device which will take care of overrun and under run of the car and rope stretch that the car floor is within 6.0 mm from the landing level at the floors while in operation.

    iii) The lift will be equipped with upper and lower terminal switches arranged to stop the car automatically within the limit of the top car clearance and bottom run-by, from the any normal operating speed.

    iv) The elevator car shall be provided with SS-304 sheet fabricated, bright finished to approved shade (including landing doors of the car). Vitrified ceramic tile of matt finish flooring as indicated in the data sheet - A, concealed fan and indirect lighting, emergency lighting, intercom, car position and travel direction indicator.

    v) As the elevator is to provide service in a power station, it is necessary for the equipment to be specially coated (painted). This will include application of

  • vi)

    vii)

    viii)

    11.0

    1)

    2)

    3)

    4)

    5)

    6)

    7)

    8)

    9)

    TITLE: TECHNICAL SPECIFICATION

    FOR ELEVATORS

    SPEC. NO. PE-TS-392-502-AOOI

    VOLUME lIB

    SECTION C

    REV. 00 I DATE: 23/12/2013 SHEET 11 OF 13

    anticorrosive paint as applicable. The electrical equipment will have enclosures meeting degree of protection as covered under electrical specification.

    The elevator as a whole will comply with relevant Indian Standard i.e. 14665 or approved international standard. The outline dimensions of electric lift shall meet the requirements of IS 14665 (latest edition).

    The elevator shall be provided with AC VWF type drive control system.

    Doors are automatic, center opening with emergency key opening at all landings, horizontal sliding type for car as well as for hoist way. Trap door shall be provided as per IS-14665 (latest edition).

    Other Technical Requirements

    Characteristic curves of all motors shall be furnished by the bidder during detail engineering stage for approval showing torque, speed, current and voltage.

    Electrical requirements shall be as per requirements enclosed elsewhere in the specification.

    C&I requirements shall be as per requirements enclosed elsewhere in the specification.

    Dealers are not acceptable for any item of the package. Bidder shall procure all items from BHEL I customer approved sub vendor only. No argument on this account shall be entertained.

    Complete elevator installation shall be in accordance with the requirements of concerned approving authority.

    Minor civil and structural works shall be carried out by the bidder if required at site for which no additional commercial implication shall be entertained by BHEL.

    In case of any contradictory requirement amongst the various clauses within the speCification and clarifications not having been sought by the bidders, the most stringent requirement as per interpretation of BHEL's engineer shall be final and binding on the bidder for which BHEL will not entertain any commercial implication.

    Data sheets of various items shall be prepared by the bidder and shall be submitted to BHEL I customer I consultant for approval after placement of order and any changes required by BHEL I customer I consultant for the same shall be incorporated and adhered by the bidder without any commercial implications.

    GA drawing indicating design data, material of construction etc. shall be prepared by the bidder during detail engineering stage based on speCification I

  • 20 TITLE:

    TECHNICAL SPECIFICATION FOR

    ELEVATORS

    SPEC. NO. PE-TS-392-502-A001

    VOLUME lIB

    SECTION C I SUB-SECTION

    REV. 00 IDATE: 23/12/2013 SHEET 12 OF 13

    10)

    11)

    12)

    13)

    14)

    15)

    16)

    a)

    b)

    c)

    d)

    contractual requirement and there should be no commerdal implication on account of finalization of the drawings and documents.

    0 & M manual shall be furnished to BHEL I customer I consultant for approval during detailed engineering stage.

    Field quality plan I quality assurance plan I check list shall be prepared by the bidder for each item of elevator and shall be submitted to BHEL I customer I consultant for approval after placement of order and any changes required by BHEL I customer I consultant for the same shall be incorporated and adhered by the bidder without any commercial implications.

    All possible efforts shall be made by the bidder to get the approval of drawings and documents from BHEL I customer I conSUltant at the earliest and the documents prepared I generated by them or their sub-vendors shall be checked by their competent authority before submission to BHEL.

    Revision made by the bidder in any drawings and documents shall be highlighted by indicating the no. of revisions in a triangle without fail so that the minimum time is required by BHEL to review the drawings and documents.

    Bidder to note that all the drawings shall be prepared in Auto Cad - 2010 version and required number of hardcopies and soft copies shall be furnished to BHEL during detailed engineering stage. Exact requirement of number of hard copies and soft copies of all drawings and documents as required by BHEL I customer I consultant shall be informed to the successful bidder during detail engineering stage and bidder to furnish the same for which no additional cost shall be entertained.

    21 days time is required by BHEL to offer their comments on the drawings and documents being submitted by the bidder (during detailed engineering stage in the event of L.O.l being placed) from the date of receipt.

    Civil works will be provided by BHEL I customer. Hence, bidder has to furnish the civil inputs in time. Bidder has to carry out the rectification in the civil works in the event of any changes in the civil input data furnished by them or delay in submission of input data by them. Bidder to furnish the civil foundation drawing along with the loading data for approval during detailed engineering stage showing I indicating the followings :

    Scope of work by BHEL and bidder shall be indicated with different legend or in the form of note.

    Recommended locations of earthing pads.

    Civil loads along with detailed calculation of loading

    Details of pockets I cut outs as required for anchor bolts.

  • 21 SPEC. NO. PE-TS-392-502-AOOITITLE:

    TECHNICAL SPECIFICATION VOLUME lIB FOR SECTION C I SUB-SECTION

    ELEVATORS REV. 00 I DATE: 23112/2013 SHEET 13 OF 13

    17) Bidder to depute competent designer (s) at BHEL's office during detailed engineering stage to disclJss drawings and other technical documents as and when required by BHEL. However, minimum seven (7) days' notice shall be served for the same.

    18) All the drawings which are required to be furnished to BHEL during detailed engineering stage shall include technical parameters, details of paints, BOa I BOM etc in tabular form indicating all components including bought out items and their quantity, material of construction indicating its applicable code I standard, weight, make etc.

    19) All drawings and documents including general arrangement drawing, data sheet, calculation etc. shall be furnished to BHEL during detailed engineering stage and shall include I indicate the following details for clarity W.r.t. inspection, construction, erection and maintenance etc.:

    a) All drawings and documents shall bear BHEL's title block and drawing I document number. However, BHEL's drawing I document numbering scheme shall be furnished to the successful bidder after the placement of L. 0.1.

    b) All drawings and documents shall indicate the list of all reference drawings including general arrangement.

    c) All drawings shall include I show plan, elevation, side view, cross - section, skin section, blow - up view, all major self manufactured and bought out items shall be labeled and included in BOa I BOM in tabular form.

    d) Specification I schedule of painting shall be made as a part of general arrangement drawing of each item indicating at least 3 make.

    20) Bidder to assess the capability of their sub-vendors in terms of preparation of drawings, calculations, documents, quality assurance, supply of material etc. as per project schedule before placing the order on them. No deviations shall be entertained.

    21) Bidder to furnish prices and unit price of each item of proposed system as per BHEL's price format only along with the final price bid.

    22) Bidder shall check that specifications of all the items are available in the NIT specification. However, in the event of absence of specification for any item, bidder will approach BHEL to furnish the specification of missing items and new specification will be adhered by the bidder for which no commercial implication shall be entertained by BHEL.

    23) Bar chart, list of drawings and documents including data sheet, manual calculation, quality plan, field quality plan, PG test procedure, list of sub vendors (mechanical, C & I and erection and commissioning), technical

  • 22

    vitI

    24)

    25)

    26)

    27)

    28)

    29)

    30)

    TITLE: TECHNICAL SPECIFICATION

    FOR ELEVATORS

    SPEC. NO. PE-TS-392-502-AOOI

    VOLUME lIB

    SECTION C I SUB-SECTION

    REV. 00 I DATE: 23/12/2013 SHEET 14 OF 13

    specification and material of construction, painting specification / schedule, dispatch schedule etc. of various items as required by SHEL / customer / consultant shall be submitted to SHEL / customer / consultant during detail engineering stage for approval and the approved drawings / documents shall be adhered by the bidder without any commercial implication.

    List of Mandatory spares and list of tools and tackles in terms of numbers shall be furnished by the bidder along with the offer. List of commissioning spares and list of tools and tackles in terms of numbers shall be furnished by the bidder along with the offer.

    "Technical deviations" shall be clearly indicated in bidder's offer in "Technical deviation format" only.

    All drawings shall be prepared as per SHELls title block and bear SHELls drawing No. and customer / consultant's drawing no; which will be forwarded to the successful bidder during detail engineering stage.

    The General Technical Requirements shall be as per GTR enclosed elsewhere in the specification.

    Commercial implication includes price implication as well as delivery implication.

    Dummy landing/s, as required in case travel between two consecutive landings is more than 10 m, shall be considered by bidder in his offer.

  • 23

    VOLUME IVSPEC.NO.

    TATA CONSULTING ENGINEERS LIMITED SECTION: D14 TCE.S7S0A-H-SOO-001

    RRVUNL, 2 x 660 MW, Super-critical TPS, StageV, Units 7 & 8 at Suratgarh, Rajasthan

    PARTB SHEET 1 OF 3 ELEVATORS

    1.0 LIFTS

    Contractor shall provide the following lifts lelevators.

    1.1 Gns (1) passsngsr cum goods lift of capacity 1360 kg and speed of 0.75 mlsec shall be proided in eaoh steam generator area (Le. Total 2 nos.).

    1.2 One (1) Passenger Elevator of capaci 600 kg and speed of 1 m/sec shall be provided in Station building. 1680 Kg

    1.3 One (1) passenger-cum-goods lift of capacity of 1360 kg and speed of 0.75 m/sec shall be provided in the service building.

    1.4 Olle(1) passemger cun i goods lift of capacity 1360kg & speed of O.75m/see shall be provided in tAe bunker bay fer each unit (i.e total 2 nos)

    1.5 The platforms to be served shall be decided during detailed engineering stage.

    2.0 SPECIFIC REQUIREMENTS

    2.1 Design, fabrication and supply of lift complete with all devices as are necessary to complete the installation in accordance with this specification.

    2.2 The capacity of the lift for the boiler shall be 1360 kg and if the heaviest piece of equipment to be lifted to boiler platform is heavier than this weight, the rated capacity of the lift shall be suitably increased later.

    2.3 Any code, statutory requirements, specific requirements at the place of installation shall be complied with in all respects.

    2.4 Lift shall be weatherproof and the degree of protection shall be IP55 for all except for the Service building lift which shall be IP54.

    2.5 For description/requirement of Rack & pinion clmfator refer seotion D24.

    2.6 The A.C motors of the lift shall comply with Section D13 of this specification.

    2.7 Landing, operating and indicating devices in boiler area shall be weatherproof and rain proof.

    2.8 Special care and precaution shall be taken regarding handling of lift cable loops between the points of suspension as the loops are prone to twist I distortion.

    2.9 An electric contact for the car door shall be provided which shall prevent elevator movement away from the landing unless the door is in the closed position. The mechanical interlock with auxiliary door closing device shall be provided so that the elevator can be operated only after the interlock circuit is established.

    2.10 The car door shall be provided with a non contact type protective device extending to the full height and shall be so arranged that any obstruction in its path while the door is closing, it shall automatically cause the car door and hoist way door to return to open position.

    ISSUE

    R1

    TCE FORM 329 RSFILE NAME: F329RS.DOC

  • SPEC.NO. VOLUME IV

    TCE.S7S0A-H-SOO-OO1 TATA CONSULTING ENGINEERS LIMITED SECTION: D14

    RRVUNL, 2 x 660 MW, Super-critical TPS, Stage-V, Units 7 & 8 at Suratgarh, Rajasthan

    PART B SHEET 2 OF 3 ELEVATORS

    2.11 An emergency switch shall be provided to stop the elevator at a particular landing, cancelling all the registered calls.

    2.12 Power supply mains shall be lockable as per requirements of IS 1860.

    2.13 ' With each lift the Vendor shall supply a maintenance tool kit which shall be kept in machine room.

    2.14 Refer section D28 for codes & standards.

    2.15 The following operating devices I indications shall be provided in the car I on the landing I in the machine room as indicated below:

    2.15.1 Operating devices.

    In the car In the landing In the mlc room . car

    Up push button (PB) Up P.B Up PB Up

    Down PB Down PB Down PB Down

    Number PB s for each Bell Hand cranking Stop landing device

    Bell PB, Phone Lift PB Stop PB 240 V 1~ receptacle

    Non-stop PB - -Door open PB - - -Door close PB - - -Alarm PB - - -Emergency stop PB - - -Key operated selector for - - -

    attendant operation

    2.15.2 Indicating devices.

    In the car On the landing

    Up direction of travel Up direction of travel

    Down direction of travel Down direction of travel

    Floor position indicator Car position indicator with direction

    (Illuminated numeral for each landing) (Illuminated numeral for each landing)

    Landing car registering unit Call registered 'Up' indicator

    Call registered 'Down' indicator

    ISSUE

    R1

    TCE FORM 329 RSFILE NAME: F329RS.DOC

  • 25

    SPEC. NO.

    TCE.S7S0A-H-SOO-OO 1 TATA CONSULTING ENGINEERS LIMITED

    VOLUME IV

    SECTION: D14

    PARTS

    RRVUNL, 2 x 660 MW, Super-critical TPS, StageV, Units 7 & 8 at Suratgarh, Rajasthan

    ELEVATORS SHEET 3 OF 3

    2.15.3 Additional requirement

    Car ventilation fan with switch

    Fire extinguisher

    Levelling accuracy shall be +/- 5mm

    Energy saving device

    In built hands free telephone in car

    Overload device

    3.0 For technical particulars refer datasheet-A.

    ISSUE

    R1

    TCE FORM 329 RSFILE NAME: F329RS.DOC

  • 26

    SPEC. NO.

    TCE.S7S0A-H-SOO-001 TATA CONSULTING ENGINEERS LIMITED VOLUME IV

    SECTION: 014

    PART B

    RRVUNL, 2 x 660 MW, Super-critical TPS, Stage-V, Units 7 &8 at Suratgarh, Rajasthan

    DATA SHEET-A

    ELEVATOR

    SHEET 1 OF 4

    Sr. Description unit Client specification

    No.

    1.0 Name of manufacturer *

    2.0 Make of lift *

    3.0 Lift category Goods cum Passenger

    3.1. Quantity

    L~\ 0",:1", .. 'C:~\ """'... ') \ .., \ " , (b) Station Building Nos 1

    (c) Service building Nos 1

    '''''\ h, , ... 1,,,.. h ...." I .. ,.., ,...., ......... n ..............~ 'IIV~ L. 3.2. Rated Load

    I-::J.\ C:~ , iff. 11.(",.. o1'lCn \ ...., -~ -"" '~ --(b) Station building Kg 600

    (c) Service building Kg 1360 (rn RllnL-QI" h-::J.\1 Iv,.. ... ')~n , , ",I '~ IvVV

    3.3. Rated Speed L'"1\ C:r"' I :.u 1 ......... 1 ... "',.. n 7e:.\-, -- ....,,,. """',",,,, U. 'V (b) Station building m/sec 1

    (c) Service building m/sec 0.75 L.J\ n ,I L

    1 ......... 1 ... "',.. n 7c:.\Uj ""YIII'~1 1J

  • 27

    SPEC. NO.

    TCE.S7S0A-H-SOO-001 TATA CONSULTING ENGINEERS LIMITED VOLUME IV

    SECTION: D14

    PARTB

    RRVUNL, 2 x 660 MW, Super-critical TPS, Stage-V, Units 7 & 8 at Suratgarh, Rajasthan

    DATA SHEET-A SHEET 2 OF 4

    ELEVATOR

    Sr.

    No.

    3.8.

    3.9.

    3.10.

    3.11.

    3.12.

    3.13.

    Description

    No of door in car

    Type of control

    Operation

    Automatic operation type

    Operating devices

    Indicating devices

    unit Client specification

    One, Centre opening sliding

    By Bidder

    Automatic without attendant

    Selective Collective

    As listed in write up

    In the car Yes to be provided

    (a) Up Direction of Travel

    (b) Down Direction of Travel

    (c) Floor position Indicator (illuminated numeral for each landing)

    (d) Landing call registering unit (with buzzer & registration cancelling unit & lamp test push button)

    In the landing Yes to be provided

    (a) Up direction of travel

    (b) Down Direction of travel

    (c) Car position indicator (illuminated numeral Top of landing door for each landing)

    (d) Location of the position indicator

    (e) Call registered indicator

    (f) Call registered up indicator

    (g) Call registered down indicator

    (h) lift out of order

    REV. NO. RO R1 JOB NO. r-------r-------+-------------~

    I__P_PD_._B_Y_:~U-M------+-S-K----------~TCE-CKD. BY : MSVM MSVM S7S0A

    CLlENT:RRVUNL

    DATE NOV'2009 JUN'2012 PROJECT: 2 x 660 MW, Super-critical TPS, Stage-V, Units 7 & 8 at Suratgarh, Rajasthan

    TCE FORM NO. 329 RS

  • 28

    SPEC. NO.

    T C E.5750A-H-500-00 1 TATA CONSULTING ENGINEERS LIMITED VOLUME IV

    SECTION: D14

    PARTB

    RRVUNL, 2 x 660 MW, Super-critical TPS, Stage-V, Units 7 & 8 at Suratgarh, Rajasthan

    DATA SHEET-A

    ELEVATOR

    SHEET 3 OF 4

    Sr.

    No.

    Description unit Client specification

    3.14. Miscellaneous devices

    (a) Car lighting

    (b) Car ventilation fan with manual and automatic switch through selector

    (c) Decor inside the car

    (d) Enclosure for electrical equipment located outside the MIC room

    (e) Emergency Exit

    (f) Provision for opening the landing door in case of emergency

    (g) Emergency device 220V DC operated

    3.15. Car accessories

    3.16. Special requirements and notes

    a) Inching control

    b) Stop blocked in floors

    c) Fire extinguisher

    d) Facia plates

    e) Material of the list rope

    Fluorescent tube

    Yes

    Yes

    Dust & water tight (IP55)

    Yes

    Yes

    Yes

    Following accessories to be provided in addition to those mentioned in the write LIP

    a) Hand rail

    b) PVC 'Hooring

    c) Emergency DC light

    a) yes

    b) yes

    c) yes

    d) yes

    e) Steel

    ~R_EV~.~N~O~.~R~0~____~R_1__________~JOBNO. I~P~PD~.~B~Y~:~U~M~____~S~K~________~TCE-

    CKD. BY: MSVM MSVM 5750A

    DATE NOV'2009 JUN'2012

    CLlENT:RRVUNL

    PROJECT: 2 x 660 MW, Super-critical TPS, Stage-V, Units 7 & 8 at Suratgarh, Rajasthan

    TCE FORM NO. 329 R5

  • 29

    SPEC. NO.

    TCE.S7S0A-H-SOO-001 TATA CONSULTING ENGINEERS LIMITED VOLUME IV

    SECTION: D14

    PARTB

    RRVUNL, 2 x 660 MW, Super-critical TPS, Stage-V, Units 7 & 8 at Suratgarh, Rajasthan

    DATA SHEET-A SHEET 4 OF 4

    ELEVATOR

    Sr. Description unit Client specification

    No.

    3.17. Landing details

    ~\-, ~r, lift ,..... -' +,.." ... ....

    b) Station building All floors

    c) Service building All floors

    ..1\...., C ' ... I,"r h ...." ............................., Rirlrlor t" .J '.J .

    REV. NO. RO R1 I----------r-------+-------------~ I ____P_PD_._B_Y_:-+--U_M____+-S_K__________~

    JOB NO. TCE

    CLlENT:RRVUNL

    CKD. BY : MSVM MSVM S7S0A

    DATE NOV'2009 JUN'2012 PROJECT: 2 x 660 MW, SlJper-critical TPS, Stage-V, Units 7 & 8 at SlJratgarh, Rajasthan

    TCE FORM NO. 329 RS

  • 30

    VOLUME IV SPEC. NO. T ATA CONSULTING ENGINEERS LIMITED TCE.5750A-H-500-001 SECTION: D 14

    RRVUNL, 2 x 660 MW, Super-critical TPS, Stage-V,

    Units 7 & 8 at Suratgarh, Rajasthan

    PARTB SHEET 1 OF 1 DATASHEET-C

    ELEVATORS

    DATA TO BE FURNISHED BY BIDDER AFTER AWARD OF CONTRACT

    1. Final dimensions of the lift car & machine room.

    1.1 Any modification required.

    2. Largest Package for Transport and storage at site.

    Dimensions :

    Weight

    3. DRAWINGS

    VENDOR shall furnish the following drawings. The schedule of submission of drawings shall be furnished:

    3.1 Dimensioned Drawings of Lift and accessories.

    3.2 Layout of machine room.

    3.3 General arrangement drawing of control panels.

    3.4 Wiring diagram and schematic diagrams of control panels.

    3.5 Braking load on guides.

    3.6 Fixing detail of side guides.

    3.7 Reaction of buffers or lift pit.

    ISSUE R1

    FILE NAME: F329R5.DOC TCE FORM NO. 329 R5

  • 31

    1.0 a)

    b)

    c)

    d)

    e)

    1.1

    1.2

    TITLE SPEC. NO. PE-TS-392-502-A001

    TECHNICAL SPECIFICATION of VWF drive for VOLUME 11-8

    Elevator SECTION - C

    DATE 23-12-13 I SUB SECTION SHEET 1 OF 5

    General This part of the specification describes the general requirements for the Variable Voltage Variable frequency Drives, herein referred to as AC Drives, for use with standard IEC design AC squirrel cage induction motors. The nominal values, the standard documents and the drive's minimum performance are defined in this part. To avoid any mismatch between the motor and its control equipment, the AC Drive shall be capable of auto adjustment by automatic measurement of the motor parameters with/without motor rotation. Inverter construction and related devices:

    Construction shall be divided in 3 broad sections. Section one converts AC Supply into DC supply. Section 2 Converts and controls DC supply into AC Supply with regulation. Section 3 shall be used for braking action of the motor and Dynamic Braking Unit (DBU) can be inbuilt or external depending upon the drive capacity. VVVF can be used in open loop (without external speed feed back) like in Travel motions or close loop (With external speed feed back) like in Hoist motions. Like all other electronic I electric devices VVVF drives are also protected by MCB I MCCB I Fuses. VVVF drives are sensitive to temperature and hence drive internal as well as external cooling fans are provided. Programming of VVVF Drives.

    VVVF drives shall be programmable and for that purpose detachable digital Operator display unit shall be supplied along with the VVVF having required buttons for setting the user constant, functions etc. The VVVF drive is to be fine tuned by matching the motor parameters and setting the parameters on full load.

    VVVF drives shall be connected with power supply and these drives generate their own low voltage control supply. Potential free contacts shall be connected to this control supply and few programmable control terminals. Starting I stopping I set speeds operations of VVVF drive shall be achieved by above control connection.

    VVVF shall give smooth control over acceleration and deceleration making the motion jerk free and using Variable voltage variable frequency limits the inrush current to the squirrel cage motors. VVVF provides controlled torque to the motor due to which elevator operations are jerk free.

    Experience

    The Frequency Converter Manufacturer shall have adequate experience in frequency converter manufacturing and have adequate business volume in order to provide credibility in his commitments and a capability of long term support.

    Local support

    The Supplier shall have a permanent representative office with a trained and skilled support staff, in the country where the goods are delivered, in order to prove his commitment for local support and to provide a channel for communication.

  • 32.

    SPEC. NO. PE-TS-392-502-AOO1 TITLE

    VOLUME 11- BTECHNICAL SPECIFICATION of VWF drive for

    SECTION - C ElevatorIii DATE 23-12-13 SUB SECTIONI

    SHEET 2 OF 5

    The engineers employed by the Supplier's regional office shall be certified by the Manufacturer and provide start-up service including physical inspection of the drive, connected wiring and final adjustments, to ensure that the AC Drive meets the required performance.

    The Supplier shall be able to give basic drives training to the Customer's engineers, preferably on the site. The training shall, as a minimum, include system concepts and basic troubleshooting.

    2.0 Basic requirements for the AC Drives

    2.1 General requirements

    The AC Drive shall comply with National (country of origin) and International standards and the recommendations for electrical industrial control devices (IEC, EN, UL, NFC, and VDE).

    The AC Drive shall be of the most modern design, yet user friendly and be simple to install commission and maintain. The AC Drive shall be able to start and control the speed of a standard squirrel cage induction AC motor. The AC Drives shall be: CE marked, conforming to European Low Voltage (73/23/CEE and 93/68/CEE) and EMC (89/336/CEE) Directives, UUCSA marked according to UL S08C.

    The AC Drives have to be built to comply with the IEC standards.

    The AC Drive shall be a digitally controlled drive, using, at least, the Pulse Width Modulation (PWM) with flux vector control open loop (for travel) and closed loop (for hoist). It shall have diodes / thyristors in rectifier and IGBT's in the inverter section in their entire power range, and it shall have the following minimum specifications.

    Rated Input Voltages 380V to 480V (-100/0 to +100/0 variation), three-phase

    Rated Input Frequency SOHz +S % to - S%

    Output Voltage 0- Input voltage, three-phase

    Output Frequency Range oto 400 Hz

    Acceleration / Deceleration Time 0.01 - 999s, adjustable, linear, with S, with U or customised shapes

    Overload capability (Constant Torque) 1S00/0 of nominal current for 1 min.

    Operating ambient Temperature -10C up to SOC(shall be de-rated suitably if not rated at SOC)

    Storage ambient Temperature -2SoC up to 70C

  • TITLE SPEC. NO. PE-TS-392-502-A001

    TECHNICAL SPECIFICATION of WVF drive for

    Elevator

    VOLUME II - B r---------------------------~

    I SECTION - C r-------------~------------~

    I DATE 23-12-13 I SUB SECTION SHEET 3 oF5

    ~ng altitude 1000 m without de-rating, 1000 ... 3000 (shall be de-rated suitably)

    Max. Relative Humidity 95 0/0, without condensation and dripping water.

    Main Protections Over current, short circuit between phase, short circuit between phase and ground, input phase loss, output phase loss, motor overload, over speed, over voltage, under voltage, drive over temperature

    The AC Drive shall be able to give a 100 % output current continuously in the above specified conditions. In order to ensure that the drive can provide the required output current in the specified ambient conditions, the Manufacturer shall inform the required de-rating, if the ambient ternperature given in the project-specific specification is higher than rated ambient of the drive or if the installation altitude is more than 1000 m above the sea level. The de-rating factor shall be specified so that neither the lifetime of the AC Drive nor the unit's performance, overload capability included, nor the reliability of the AC Drive shall suffer.

    Suitable encoder shall be provided for main hoist motion.

    3.0 User interface

    3.1 General

    The user interface shall be identical throughout the power range and type to avoid confusion amongst the users and need for training in several different units.

    3.2 Inputs and outputs

    A. At least, the following standard Inputs and Outputs shall be provided, to be used in interface with the control system: Analogue Inputs 1 x Programmable differential voltage input 10V,

    1 x Programmable current input 0(4) - 20mA 1 x Programmable voltage input 0 - 10V

    Analogue Output 1 x Programmable analogue outputs 0(4) - 20mA or 0 10V Logic inputs 6 x Programmable logic Inputs isolated from the mains Relay Outputs 2 x Programmable Digital outputs with a changeover dry contact

    All the control terminals shall be clearly marked.

    B. At least, it shall be possible to assigned the following functions to the I/0s:

  • 34

    3.4

    A.

    B.

    C.

    D.

    i) ii) iii) iv) v) vi)

    TITLE SPEC. NO. PE-TS-392-502-A001

    TECHNICAL SPECIFICATION ofVWF drive for VOLUME 11- B

    Elevator SECTION -C

    DATE 23-12-13 I SUB SECTION

    Analogue input Speed reference Summing reference

    Logic input Forward Reverse Jog Preset speeds Reference switching Ramp switching Parameter sets selection Fast stop Freewheel stop + speed - speed External fault

    Programming terminal

    SHEET

    Analogue outputs Motor current Motor frequency "Motor torque Motor power

    4 OF 5

    Relay or logic outputs (open collector) Ready Drive running High speed attained Drive fault Frequency threshold attained Motor thermal state attained Torque or current limitation attained Brake control

    The AC drive shall have a keypad /display for programming and controlling purposes. An IP54 or IP65 remote mounting shall be possible at a distance of 10m.

    Password protection shall be provided to avoid unauthorized tampering with the set parameters.

    The programming terminal shall be able to display the com~ercial reference of the AC drive and of the options, the software version, the serial number

    Direct keypad entry shall be provided to observe the following actual parameters. Any one of the following parameters or actual values shall be selected to be always displayed:

    Input Voltage Input Frequency Output Frequency Output Power Output Current Motor Speed

    The following parameters shall always be displayed during normal operation:

    i) Drive Status

    The following drive control functions at least shall be available from the keypad:i) Run

  • 35

    ii) iii) iv) v) vi) vii)

    3.5

    3.6

    4.0

    A.

    B.

    5.

    TITLE SPEC. NO. PE-TS-392-502-A001

    TECHNICAL SPECIFICATION ofVWF drive for VOLUME II-B

    Elevator SECTION - C

    DATE 23-12-13 I SUB SECTION SHEET 5 OF 5

    Stop Local/ Remote selection. Forward/Reverse (if function enabled) Accelerate Decelerate Parameter setting

    Application programming

    The AC Drive shall be designed for both simple and the most complicated applications, yet it shall be user friendly. It shall be possible to reset the parameter settings back to the original factory settings through the keypad.

    PC Tools

    The AC Drive Supplier shall have Windows based PC software available for monitoring and controlling the AC Drives, and the software shall be offered as an option. The software shall be supplied with the necessary hardware and a provision for connecting a PC with the AC Drives. It shall be possible to set and modify parameters, control the drive, read actual values and make trend analysis using the software.

    Software features

    Restart

    In the event of a fault trip due to over voltage, over current or loss of analogue signal, the AC DRIVE shall be programmable to attempt an automatic restart. For safety reasons, the maximum number of attempts shall be within a selectable time. If the fault does not clear after the attempts, the drive shall lock out.

    Brake logiC control

    The AC Drive shall have a built-in function to control a mechanical brake in order to move the load in a smooth and safe way. The brake logic control shall be adapted to the different movements: hOisting, travel, orientation.

    Preferred makes:

    Schneider Electric, L&T-YASKAWA, Siemens, ABB, Allen Bradley (Rockwell Automation).

  • 36

    im TITLE SPEC. NO. PE - TS - 392 - 502 - A001

    TECHNICAL SPECIFICATION VOLUME liB

    FOR SECTION

    ELEVATOR REV 0 I DATE 22-12-2013 SHEET OF

    ANNEXURE - II

    Drawings I documents distribution schedule

    DRAWINGS AND DOCUMENTS REQUIREMENT

    S.NO. DESCRIPTION OF MANUALS NO. OF NO. OF CD PRINTS (SETS)

    1 PLANT DEFINITION MANUAL 3 2 DRAWINGS FOR APPROVAL 9 3 3 DRAWINGS FOR INFORMATION 9 3 4 FINAL DRAWINGS 15 3 5 AS BUILT DRAWINGS 15 3 6 DATA SHEETS, DESIGN CALCULATIONS, PURCHASE

    SPECIFICATIONS AND OTHER TYPE OF DOCUMENTS

    6.1 FOR APPROVAL 9 3 6.2 FINAL 15 3 6.3 ANALYSIS REPORT OF EQUIPMENTS I PIPING I

    STRUCTURES I SYSTEMS EMPLOYING SOFTWARE PACKAGES AS DETAILED IN SPECIFICATION

    6.3.1 INPUT 9 3 6.3.2 OUTPUT 9 3 6.3.3 DRAWING I SKETCHES 9 3

    7 ERECTION MANUAL - FINAL 3 8 OPERATIONS AND MAINTENANCE MANUAL - FINAL 3 9 PLANT HAND BOOK - FINAL 3 10 COMMISSIONING AND PERFORMANCE PROCEDURE 3

    MANUAL - FINAL 11 PERFORMANCE AND FUNCTIONAL 9 3 12 PROGRESS REPORTS 9 3 13 PROJECT COMPLETION REPORT 15 3 14 QA PROGRAMME INCLUDING ORGANIZATION FOR 1 1

    IMPLEMENTATION AND QA SYSTEM MANUAL 15 VENDOR DETAILS IN RESPECT OF PROPOSED 1 1

    VENDORS INCLUDING CONTRACT EVALUATION REPORT

    16 MQP AND FIELD QPs, FIELD WELDING SCHEDULES AND THEIR REFERENCE DOCUMENTS LIKE TEST PROCEDURES, WPS, POR ETC.

    16.1 FOR REVIEW I COMMENTS 3 1 16.2 FOR FINAL APPROVAL 4 1 17 WELDING MANUAL, HEAT TREATMENT MANUAL,

    STORAGE AND PERSERVATION MANUALS 17.1 DRAFT 4 17.2 FINAL 4 2 18 MONTHLY VENDOR APPROVAL AND QP APPROVAL 2 1

    STATUS 19 QP DOCUMENTATION PACKAGE FOR ITEMS I 2 2

    EQUIPMENTS MANUFACTURED AND DEPATCHED TO SITE

    20 QA DOCUMENTATION PACKAGE FOR FIELD ACTIVITIES 2 2 ON EQUIPMENT I SYSTEMS AT SITE

  • 37 TITLE SPEC. NO. PE - TS - 392 - 502 - A001

    TECHNICAL SPECIFICATION VOLUME liB

    FOR SECTION

    ELEVATOR I REV o IDATE 22-12-2013

    SHEET OF

    NOTE: THE ABOVE ARE THE MINIMUM QUANTITY OF DRAWINGS/DOCUMENTS REQUIRED.THE EXACT REQUIREMENT SHALL BE INFORMED TO THE SUCCESSFUL BIDDER DURING DETAIL ENGINEERING SATGE FOR WHICH NO COMMERCIAL IMPLICATION SHALL BE ENTERTAINED BY BHEL.

  • 38 TITLE NO. PE - TS - 392 - 502 - A001

    TECHNICAL SPECIFICATION E " SECTION DFOR

    REV o DATE 23 -12 -13 SHEET OF

    ELEVATOR

    VOL-liB

    ELECTRICAL

  • 39

    TITLE SPEC. NO.PE TS 392 - 502 - A001

    II TECHNICAL SPECIFICATION VOLUME liB FOR SECTION C ELEVATOR IDATE 23 - 12- 13 REV 0

    SHEET OF

    SECTION - C2 Specifics Technical Requirements (Electrical)

  • 4-0

    RAJASTHAN RAJYA VIDYUT UTPADAN NIGAM LTD. 2 x 660 MW SURATGARH SUPER CRITICAL TPS

    UNIT # 7 & 8

    ELEVATORS

    TECHNICAL SPECIFICATION (ELECTRICAL PORTION)

    BHARAT HEAVY ELECTRICALS LIMITED POWER SECTOR

    PROJECT ENGINEERING MANAGEMENTNOIDA, UTTAR PRADESH,

    INDIA

  • 4-1

    IifiLE:

    ELECTRICAL EQUIPMENT SPECIFICATION FOR

    ELEVATORS

    2 X 660 MW SUARTGARH STPS

    ~PECIFICAllON NO.

    VOLUME NO. : II-B ~ECTION: C REV NO. : 00 DATE: 21.12.2013 ~HEET: 1 OF 1

    SECTION

    C

    C

    C

    C

    C

    D

    D

    D

    D

    D

    D

    D

    CONTENTS

    TITLE NO OF SHEETS

    SPECIFIC TECHNICAL REQUIREMENTS 1

    ELECTRICAL SCOPE BETWEEN BHEL & VENDOR 1

    ELECTRICAL LOAD DATA FORMAT 1

    DATASHEET-A & ANNEXURE-I 3

    TECHNICAL SPEORCAllON FOR MOTORS 14

    GENERAL TECHNICAL REQUIREMENTS FOR LV MOTORS 5

    MOTOR DATASHEET-C 7

    CABLES AND CARRIES SYSTEM 10

    EARTHING AND UGHTNING PROTECTION SYSTEM 8

    QUALITY PLAN (FOR MOTORS BELOW 55 KW) 2

    QUALITY PLAN (FOR MOTORS ABOVE & 55 KW) 9

    QUALITY PLAN FOR CABLE TRAYS AND ACCESSORIES 4

  • 4-2t,41i ~LE: ELECTRICAL EQUIPMENT SPECIFICATION FOR ELEVATORS

    2 X 660 MW SUARTGARH srps

    SPECIFICATION NO.

    VOLUME NO. = II-B

    SECTION: C ,REV NO. : 01 DATE: 26.12.2013 SHEET: 1 OF 1

    SPECIFIC TECHNICAL REOUIREMENTS: ELECTRICAL

    1.0 EQUIPMENT &. SERVICES TO BE PROVIDED BY BIDDER: a) Services and equipment as per "Electrical Scope between BHEL and Vendor". b) Any item/work either supply of equipment or erection material which have not been

    specifically mentioned but are necessary to complete the work for trouble free and efficient operation of the plant shall be deemed to be included within the scope of this specification. The bidder without any extra charge shall provide the same.

    c) Supply of mandatory spares as specified in the specifications of mechanical eqUipment's. d) Erection and commissioning spares. e) Erection & Maintenance tools & tackles. f) Electrical load requirement for ELEVATORS. g) All equipment shall be suitable for the power supply fault levels and other climatic conditions

    mentioned in the enclosed project information. h) Bidder to furnish list of makes for each equipment at contract stage, which shall be subject

    to customer /BHEL approval without any commercial and delivery implications to BHEL. i) Various drawings, data sheet as per required format, quality plans, calculations, Type test &

    Routine test reports & certificates, operation and maintenance manuals, complete technical literature with catalogues etc. shall be furnished as specified at contract stage. All documents shall be subject to customer /BHEL approval without any commercial implications to BHEL.

    j) The sub-vendor list for various electrical equipment! items in the scope of bidder shall be subject to BHEL/Customer approval without any technical, commercial and delivery implications.

    k) All electrical equipment shall be suitable for the power supplies, fault levels (mentioned in the customer specification for motor & actuator) and climatic conditions indicated in project information with the speCification.

    I) Clause 1.2 of motor spec. (customer spec) to be read as: Efficiency class IE2 as per latest revision of IS 12615 along with amendments (II revision, 2011 as on date).

    m) Following shall superseed the reqUirements mentioned anywhere in the technical spec: "Bidder shall furnish all AC as well as DC loads required for the system at different voltage levels (e.g. 415V AC, 240 VAC, 220V DC etc.) of all types, such as motor feeders, supply feeders in PEM format along with the offer. However AC supply provided by BHEl shall be 3hase, 3wire only. Any requirements of 3phase, 4 wire or 1 phase, 1wire shall be derived by vendor using BHEl supply of 3hase, 3wire".

    2.0 EQUIPMENT &. SERVICES TO BE PROVIDED BY PURCHASER FOR ELECTRICAL &. TERM:[NAL POINTS: Refer "Electrical Scope between BHEL and Vendor".

    3.0 DOCUMENTS TO BE SUBMITTED ALONG WITH BID 3.1 Bidder shall confirm total compliance to the electrical speCification without any deviation

    from the technical/ quality assurance requirements stipulated. In line with this, the bidder as technical offer shall furnish two signed and stamped copies of the following: a) A copy of this sheet "Electrical Equipment Specification for ELEVATORS and sheet

    "Electrical Scope between BHEL and Vendor" with bidder's signature and company stamp.

    b) List of Erection and Commissioning spares, c) List of Erection & Maintenance tools & tackles. d) Electrical load requirement.

  • +3

    r/~91 ~LE: ELECTRICAL EQUIPMENT SPECIFICATION FOR ELEVATORS

    ~PECIFICAnON NO.

    ~OLUME NO.: 11-8

    2 X 660 MW SUARTGARH STPS SECTION: C REV NO. : 01 DATE: 26.12.2013 SHEET: 1 OF 1

    e) If there is any conflict, customer motor specification will prevail over BHEL motor specification.

    3.2 No technical submittal such as copies of data sheets, drawings, write-up, quality plans, type test certificates, technical literature, etc. is required during tender stage. Any such submission even if made, shall not be considered as part of offer.

    4.0 LIST OF ENCLOSURES 4.1 Electrical scope between BHEL & vendor. 4.2 Technical specification for Electric Motors. 4.3 Motor data sheet-Co 4.4 Quality Plan for motors. 4.5 Load data format.

  • REV: 01A DATE: 27.12.13 ANNEXURE -I TO SECTION - C: STANDARD ELECTRICAL SCOPE BETWEEN BHEL AND VENDOR

    PACKAGE: ELEVATORS PROJECT 2X660 MW SURATGARH STPS

    S.NO DETAILS SCOPE SUPPLY

    SCOPE E&C REMARKS

    1 415V Local Starter Panel Vendor Vendor BHEL will provide two number 415 V supply feeders in Machine Room for elevators. Any requirements of 3phase, 4 wire or 1phase, 1wire shall be derived by vendor using BHEL supply of 3hase, 3wire.

    2 Power cables, control cables, screened control cables and any special cables (if required) between equipment supplied by vendor.

    Vendor Vendor

    3 Cabling material (cable trays, accessories, cable tray supporting system, conduits etc).

    Vendor Vendor

    4 Equipment Earthing Vendor Vendor All equipments metallic enclosures I frames, metal structure etc. shall be grounded at two points each to the nearest grounding points I risers provided by BHEL I customer.

    5 Motors Vendor Vendor 6 Cable glands and lugs for equipment supplied by vendor Vendor Vendor 1. Double compression Ni-Cr plated brass cable glands

    2. Solder less crimping type tinned copper heavy duty lugs for power cables.

    3 solderless crimping type heavy duty copper lugs for control cables.

    7 a) Input cable schedules (C &I) b) Cable interconnection details for above c) Cable block diagram

    Vendor Vendor

    Vendor

    ---

    Cable listing for C&I systems for vendor supplied equipment shall be furnished during detail engineering by vendor in soft copies in the BHEL cable schedule format.

    8 Equipment layout drawings Vendor -9 Electrical Equipment GA drawing Vendor - For necessary interface review.

    NOTE: - 1. Above is applicable if motor starters are part of starter cum control panel & control is relay based. 2. If motor starters are provided in main MCC then customer will provide power &control cable including supply, laying &termination.

    + ~

    http:27.12.13

  • LOAD TITLE

    trG HALL ELEVATOR

    ELEVATOR MOTOR

    2 T AlC FOR TG HALL M/C ROOM AND LIGHTING FOR ELEVATOR M/C ROOM & SHAFT)

    SERVICE BUILDING ELEVATOR

    ELEVATOR MOTOR

    2 T AlC FOR SERVICE BUILDING ELEVATOR M/C ROOM AND LIGHTING FOR ELEVATOR M/C ROOM & SHAFT)

    IADMIN BUILDING ELEVATOR

    ELEVATOR MOTOR

    2 TAlC FOR ADMIN BUILDING ELEVATOR M/C ROOM AND LIGHTING FOR ELEVATOR M/C ROOM & SHAFT)

    RATING (KW) 1_ Nos. Lu : I):L---,...------1. U) 0 W _

    - 0 0

    NAME PLATE

    ZOO MAX. t;", > w 0

    - '-" al (!) 0:::CONT. S' ~ 0 LL

    o

  • 4-6

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

    11.0

    12.0

    13.0

    14.0

    15.0

    16.0

    17.0

    18.0

    TITLE

    LV MOTORS

    DATA SHEET-A

    Design ambient temperature

    Maximum acceptable kW rating of LV motor:

    Installation (Indoors/ Outdoors)

    Degree Of Protection

    Cooling

    Details of supply system

    a) b) c) d) e)

    f)

    Rated voltage (with variation) Rated frequency (with variation) Combined voltage & freq. variation System fault level at rated voltage Short time rating for terminal box LV System grounding

    Class of insulation

    Minimum voltage for starting (As percentage of rated voltage)

    Power cables data

    Earth Conductor Size & Material

    Space heater supply(30KW & ABOVE)

    Rating up to which Single phase motor

    TYPE OF STARTER PROVIDED IN MCC

    Locked rotor current a) Limit as percentage of FLC b) Permissible tolerance, if any

    Additional tests

    Flame-proof motor a) Enclosure suitable (As per IS:2148) b) Classification of Hazardous area

    (As per IS: 5572 part-I) c) Degree of protection

    Makes

    Terminal box

    SPECIFICATION NO.

    VOLUME II B

    SECTION ID REV NO. 00 DATE 09/09/2013

    SHEET 1 OF 1

  • 4-7

    TITLE SPECIFICATION NO.

    LV MOTORS VOLUME liB SECTION ID

    DATA SHEET-A REV NO. 00 DATE 09/09/2013

    SHEET 2 OF 1

    19.0 Paint shade Shade 631 of IS-5

    All LT motors shall be controlled as follows: a) Up to 50kW: - MPCB + Contactor (MPCB shall be with adjustable SIC and OIL protection). b) 50kW to 90kW shall have MCCB+ contactor+ bimetallic relay. c) 90Kw to 160kW shall have ACB +motor protection relay (MPR).

  • ANNEXURE-I

    SUB-VENDOR LIST

    The list of approved make of the L T Motors are as mentioned below:

    S.No. LIST OF LT MOTORS

    1. BHARAT BIJLEE LTD. 2. CROMPTON GREAVES 3. ASEA BROWN BOVERI

    4. KIRLOSKAR ELECTRIC CO LTD.

    5. NGEF

    6. SIEMENS

    7. MARATHON

    8. GE-POWER

    9. I RAJINDRA ELECT INDUSTRIES

    10. LAXMI HYDRAULICS PVT. LTD

    However, the final list of makes for the L T Motors is subjected to BHEL/Customer approval, during contract stage, without any commercial implications.

  • 4-9

    TECHNICAL SPECIFICATION FOR MOTORS

    ELEVATORS (ELECTRICAL PORTION)

    2x 660 MW SURATGARH TPS

    MOTORS

  • !So

    VOLUME IVSPEC.NO. TATA CONSULTING ENGINEERS LIMITED SECTION: D13TCE.S7SOA-H-SOO-OO 1

    RRVUNL, 2 x 660 MW, Super-Critical TPS, Stage

    V, Units 7 & 8, at Suratgarh, Rajasthan

    PARTS SHEET 1 OF 7 MOTOR & ACTUATOR

    1.0 AC & DC MOTORS

    1.1. HT motors of rating above 1500kW shall be suitable for 11 kV, 3 phase, 50Hz power supply. Motors above 160kW and up to 1500kW shall be suitable for 6.6kV, 3 phase, 50Hz. Motors rated 160kW and below shall be suitable for 415V, 3 phase, 50 Hz power supply.

    1.2. All L T motors shall be energy efficient class - I in line with IS: 12615. However, the starting current shall be limited to 600% (inclusive of 20% tolerance) of full load current.

    1.3. The motor rating shall be arrived at considering 15% margin over the duty point input or 10% over the maximum demand of the driven equipment, whichever is higher, considering highest system frequency. Motors shall be capable of starting and accelerating the load with the applicable method of starting without exceeding acceptable winding temperatures when supply voltage is 80% of the rated voltage for HT motors and 85% for LV motors. HT motors shall also be capable of satisfactory operation at full load at a supply voltage of 80% of the rated voltage for 5 min. commencing from hot condition. DC motors shall be suitable for the DC system voltage of 220V. Motor shall be capable of starting and accelerating the load with the applicable method of starting, without exceeding acceptable winding temperatures, when the supply voltage is in the range of 85% to 110% of rated motor voltage.

    1.4. Motors shall be capable of running for one second if the supply voltage drops to 70% of the rated voltage. If such operation is envisaged for a period of one second, the pull out torque of the motor shall be at least 205% of full load torque.

    1.5. Motors shall withstand for 1 second the voltage and torque stresses developed due to the vector difference between the motor residual voltage and the incoming supply voltage equal to 150% of the rated voltage during fast changeover of buses.

    1.6. Locked rotor current of the HT motors rated 1500 kW and below shall be limited to 600% (inclusive of 20% tolerance) of the full load current of the motors and motor rated above 1500 kW shall be limited to 450% (inclusive of 20% tolerance) of full load current of the motor.

    1.7. The locked rotor withstand time under hot condition at 110% rated voltage shall be more than the starting time at minimum permissible voltage specified above by at least three seconds or 15% of the accelerating time whichever is greater. Provision of speed switch shall be avoided to the extent possible.

    These motors shall be designed to withstand at least 5% harmonics in the supply voltage.

    1.8. The degree of protection for the motor enclosure (including terminal box) shall be IP-55 for outdoor. For single core cable termination, gland plates shall be of nonmagnetic material. All motors located in hazardous area shall have flame proof enclosure.

    ISSUE R1

    TCE FORM 329 RSFILE NAME: F329RS.DOC

  • 51

    VOLUME IVSPEC.NO. TATA CONSULTING ENGINEERS LIMITED SECTION: D13 TCE.5750A-H-500-001

    RRVUNL, 2 x 660 MW, Super-Critical TPS, StageV, Units 7 & 8, at Suratgarh, Rajasthan

    PARTS SHEET 2 OF 7 MOTOR & ACTUATOR

    1.9. All HT motors shall be provided with vibration pads for mounting vibration detectors. Vibration monitoring devices shall be provided on DE and NDE side in X &Y direction with remote DCS monitoring, alarms and tripping

    1.10. Motors rated 1000kW and above shall be provided with differential protection. These motors shall be provided with star connected stator windings. The 3 nos. current transformers, one for each phase shall be mounted in a separate compartment in the neutral side terminal box. The three phases shall be connected to form the star point after they pass through the CTs. The CTs shall be of relay accuracy and the CT characteristics shall be compatible with the differential relay. The additional 3 nos. CTs of identical characteristics shall be provided in the 11 kV/6.6 kV switchgear panel.

    1.11. The terminal box of motor shall be of suitable size, suitable to terminate and maintain the cables easily. Terminal box shall be suitable to rotate at 90 degrees.

    1.12. The ring oiling system shall be adequate for starting and continuous operation of the motor for at least one half hour without pressure oiling system in operation.

    1.13. For 11 kV & 6.6 kV motors, 6-nos. duplex RTD s for winding shall be provided for remote monitoring, alarm and tripping at DCS. Each bearing shall be provided with one duplex RTD for temperature remote monitoring, alarm and tripping at DCS. 6 nos. spare RTDs shall be provided for winding in HT motors.

    1.14. The maximum double amplitude vibrations for motors shall be as per IS 12075.

    1.15. Maximum noise level measured at a distance of 1.5 meter from the outer surface of the motor shall not exceed 85 db (A).

    1.16. Cable boxes of all 11 kV & 6.6 kV motors shall be Phase segregated & shall be provided with quick disconnecting type terminal connectors to facilitate easy disconnection and removal of the motors without requiring unsealing or otherwise disturbing the external cable connections and leaving the phase segregated terminal box intact. The terminal boxes shall have fault withstand capacity equal to at least rated short circuit level of system voltage for 0.25 sec. The terminal boxes shall be reversible to suit cable entry from top or bottom and suitable for termination of FRLS, XLPE armoured cables.

    1.17. The star connection side terminal box should have sufficient capacity to accommodate CT's for differential protection for motor above 1000kW.

    1.18. The insulation system for 11000 V AC & 6600 V AC motors shall withstand the negative or positive 0.3 / 3.0 microsecond wave (2.7 pu rated peak line to earth operating voltage) switching surges originating from non-effectively earthed power system. All 11000V AC & 6600 V AC motors shall have BIL and power frequency withstand voltage as per relevant standards.

    1.19. Motor bearing shall be insulated wherever required.

    1.20. All HT motors shall be with VPI insulation or beUer

    ISSUE R1

    TCE FORM 329 R5 FILE NAME: F329R5.DOC

  • 52.

    VOLUME IVSPEC.NO. TATA CONSULTING ENGINEERS LIMITED SECTION: D13 TCE.S7S0A-H-SOO-001

    RRVUNL, 2 x 660 MW, Super-Critical TPS, Stage

    V, Units 7 & 8, at Suratgarh, Rajasthan

    PART B SHEET 3 OF 7 MOTOR &ACTUATOR

    1.21. All HT motors / L T motors 15 kW and above shall be provided with external greasing arrangement

    1.22. CACW motor shall be provided with water leakage detector with remote alarms and tripping.

    1.23. All HT motors / L T motors 30 kW and above shall be provided with space heaters using 240 V AC supply. However, for all the actuators, irrespective of its rating, space heaters shall be provided using 240V AC supply.

    1.24. All motors below 15 kW shall be provided with sealed ZZ bearings

    1.25. Each motor shall have two earthing terminals.

    1.26. All motors for outdoor duty shall have detachable metal canopy.

    1.27. HT motors shall be designed for operation as follows:

    a) Upto 1 OOOkW - Vacuum circuit breakers/SF6.

    b) Above 1000kW-Vacuum circuit breakers/SF6.

    c) All motors shall be suitable for DOL starting.

    1.28. Separate terminal boxes to be provided for space heater, RTDs for windings/bearings, vibration monitors etc. All terminal boxes shall be provided with two earth studs for termination of protective earth conductor. Double compression type brass cable glands and crimping type copper lugs shall be provided for termination.

    1.29. Provision shall be made at DCS to monitor, integrate running hours, nos. of starts and stop recording for all motors.

    1.30. The terminals of all motors shall be suitable for terminating Aluminium conductor, XLPE insulated, armoured cables, the sizes of which will be intimated by the Purchaser.

    2.0 ACTUATOR

    2.1. GENERAL TECHNICAL REQUIREMENT

    2.1.1. Actuator shall be weatherproof type with enclosure conforming to IP-64 degree of protection. It should be suitable for out-door use without the need for canopy. If the IP-68 degree of protection is required due to occasional submergence, the purchaser shall specify the depth and duration of such submergence.

    2.1.2. The actuator shall be suitable for installation in any position without lubrication leakage or other operational difficulty.

    2.1.3. All actuators shall be supplied with non integral starters for open & close. The main gearbox of the actuator shall be special grease filled.

    2.1.4. Each actuator should have a hand wheel for emergency manual operation. Clockwise operation of hand wheel shall cause clockwise movement of the

    ISSUE R1

    TCE FORM 329 RSFILE NAME: F329RS.DOC

  • VOLUME IVSPEC.NO. TATA CONSULTING ENGINEERS LIMITED SECTION: D13TCE.5750A-H-500-001

    RRVUNL, 2 x 660 MW, Super-Critical TPS, Stage

    V, Units 7 & 8, at Suratgarh, Rajasthan

    PARTB SHEET 4 OF 7 MOTOR & ACTUATOR

    output drive. The hand wheel shall be clearly marked with an arrow and the word CLOSE.

    2.1.5. The hand wheel shall automatically disengage when the power to the motor is restored i.e. power drive shall have a preference over manual drive.

    2.1.6. The manual effort should not exceed 400 N (push I pull). A top bevel gear set (side mounted hand wheel) shall be employed to reduce the manual effort.

    2.1.7. Each actuator shall have a local mechanical position indicator. It should be suitable to indicate 0 - 100% position of the valve (continuous type).

    2.1.8. In order to minimise the amount of spare parts required, parts and subassemblies limit I torque switches, limit switch counter gear assembly, torque switch drive assembly, mechanical position indicator assembly etc. individually interchangeable I replaceable throughout the models selected.

    2.1.9. The actuator shall be painted with corrosion resistant epoxy resin paint. Paint shade shall be Grey (Shade 631) as per IS-5.

    2.1.10. In order to prevent condensation, a space heater shall be provided in the switch compartment, suitable for continuous operation. Actuator mounting dimensions shall be according to ISO-5210. For rising stem applications, the design must allow the removal of actuator from the output drive without disturbing the function of valve.

    2.2. LIMIT AND TORQUE SWITCHES

    2.2.1. Independent torque and limit switches shall be provided in the actuator. A minimum of two position limit switches and two torque switches, one each for each direction of travel, having 4 NO + 4 NC potential free contacts, shall be supplied. If called for in the data sheet, two additional limit switches shall be provided for intermediate positions.

    2.2.2. Torque switch dial shall be graduated directly in "kg-mil for easy setting to desired value within the range specified. Separate dials shall be provided for CLOSE and OPEN torque switches.

    2.2.3. Two additional limit switches with 2NO + 2NC contacts, each adjustable at any intermediate position. shall be provided in the actuator.

    2.2.4. The rating of both torque and limit switches shall be 240 V AC, 5 Amps. The switches shall individually be enclosed to a minimum of IP-64 protection class.

    2.2.5. Torque and limit switches shall have only stainless steel flaps for better protection against environmental condition.

    2.2.6. Limit switches shall be operated by gear driven cams, which are mechanically linked to the driving devices. The counter gear used for counting and tripping the limit switches shall be of metallic construction lik