Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
1
Bid Document,
VOLUME – II OF II Clause
No. 1.6
Page 6 of
167
TYPE OF COMPRESSOR BLOCK
Lubricated or non lubricated two throw Balanced opposed
reciprocating Compressor with lube oil system and cooling system
(console type) as required.
Burckhardt Compression (India) Pvt. Ltd.(BCIN) Trunk Piston
Design compressor are best suited for CNG
applications as they offer Zero Gas Loss and are suitable for
frequent start stop ,do not require nitrogen purging etc .
BCIN trunk piston design compressor have clocked 4 Million
operating hours at sites of IGL and other CGD
companies such as AGL,BGL ,TNGL etc.
All Burckhardt Compression make CNG packages are
currently in operation at Aavantika Gas Limited of Trunk
Piston design model.
Request you to please approve Burckhardt Compression
Trunk Piston Design.
Bidder may supply the package with their proprietary design.
2
Bid Document,
VOLUME – II OF II Clause
No. 4.10.1
Page 14 of
167
GAS ENGINE
Gas fired 4-stroke; spark ignited
type.
We request to please confirm the acceptable make of
Gas Engine Tender Condition Prevails
3
Bid Document,
VOLUME – II OF II Clause
No. 4.10.10
Page 15 of
167
CPCB COMPLIANCE
Yes, Engine shall meet the latest
MP state/central pollution control
board rules & regulations.
Currently there are no norms applicable on emissions
from gas engine powering compressors. Also
central/state pollution control board do not undertake
testing & certification of emissions at site. They are
governing bodies and their scope is limited to publishing of
standards.
Testing of engines at site is carried out by agencies
authorised by state/central pollution control boards.
We request AGL to advice on applicable CPCB norms.
Bidder shall submit a certificate approved/accepted by MP State Pollution Control Board
for the installed gas engine during Site Acceptance Test / Performance Test.
OR
Bidder shall meet the CPCB norms on Genset run on dedicated Natural Gas mentioned
in the environment (protection) rules - 1986, in Schedule-I,Serial No - 95A after issued a
notification on 07/03/16 by Ministry of Environment ,Forest & Climate Change.
4
Bid Document,
VOLUME – II OF II Clause
No. 7.1
Page 29 of
167
Compressor Capacity
DESIGN SUCTION PRESSURELOCATION: COMPRESSOR
BLOCK OR PACKAGE INLET
Package Inlet (Bidder to note that the suction pressure and
temperature shall be measured at vendor’s boundary limit and not
at compressor cylinder)
We understand that pressure drop across suction filter
and PRV and flow meter are to be accounted for while
designing the package.
Please confirm if our understanding is correct.
Also please confirm the placement location of suction
filters ( within the package or outside the package) In case
the suction filters are placed outside the package then the
design is to be done considering 16 bar in at the inlet of
suction flow meter or the package.
In case placement of Suction Filters is permitted
outside the package then please confirm if the package
design is to be done considering 16 Kg/CM2 at the inlet
of the suction filter or after the suction filter.
Yes, your understanding is correct. The location of the suction filters are either inside
or outside of the package. In both the cases, the compressor package shall be designed
considering 16kg/cm2 at the inlet of the suction filter.
5
Bid Document,
VOLUME – II OF II Clause
No. 1.6.3
Page 6 of
167
MASS FLOW METER FOR VENT
The mass flow meter shall be W&M approved only
We understand that weights & measures approval is
applicable only for suction, discharge, engine flow
meter.
Vent flow meter is thermal mass flow meter type &
weight and measures approval is not required.
Please confirm if our understanding is correct.
For Vent Mass Flow Meter , Certifications on the par to national / international standards
to be submitted.
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
Page 1 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
6
Bid Document,
VOLUME – II OF II Clause
No. 4.11.3
Page 15 of
167
IP RATING OF ENCLOSURE
Enclosure shall be provide with a degree of protection…….IP 54
The compressor enclosure is equipped with large
suction and discharge hoods open to atmosphere.
Under the circumstances it is not possible to certify the
enclosures as IP 54 compliant.
We request for waiver of this clause.
Enclosure shall be flameproof , weatherproof with adequate ventillation system.
7
Bid Document,
VOLUME – II OF II Clause
No. 14.0
Page 43 of
167
NOISE LEVEL OF ENCLOSURE
72+/- 3 dBA at 1.0m distance
Gas engine driven packages have noise level in the
range of 78dBA +/ - 3 dBA.
We request AGL to accept the same.
Tender Condition Prevails
8
Bid Document,
VOLUME – II OF II Clause
No. 1.6.15 & 4.11.1
Page 6 &
15 of 167
TEMPERATURE DIFF. BETWEEN AMBIENT AND INSIDE OF
ENCLOSURE
Exhaust fan in the enclosure in addition………………..heat
exchanger. Maximum allowed temperature within the enclosure
shall be 8 deg. C above ambient temperature.
Requirement of exhaust fan is mentioned on page no 6
point 15, but of this page it is mentioned (In case the
ventilation fan is mounted inside the canopy then no
separate ventilation fan required provided this meet
the required temperature.)
Our Radiator Fan and the ventilation fan are engine
driven. Under the circumstances we shall not be
providing a separate electric motor driven fan.
Please refer reply to Sr. No. 26
9
Bid Document,
VOLUME – II OF II Clause
No. 5.3
Page 20 of
167
HMI
HMI shall be ………….Touch Screen with 10” graphic display.
Preferred make – Siemens & Schneider and Display shall be
weather proof to IP 65.
7” Touch Screen is an Industry standard. We offer Siemens
PLC with 7 “ touch screen. Siemens does not supply 10”
screen.
We request AGL to accept 7 inch touch screen as it is a
standard in City gas
Tender Condition Prevails
10
Bid Document,
VOLUME – II OF II Clause
No. 2.1.2
Page 9 of
167
AIR COMPRESSOR
3.7 kW 16kg/cm2 discharge with PRV. Preferred make
IR/KPCL/ELgi/CP. 1000 water litre capacity air receiver also
required.
Kindly approve the Iwata Motherson make as we are
supplying the same to all CGD companies. Tender Condition Prevails
11
Bid Document,
VOLUME – II OF IIClause
No. 5.6.11(n)
Page 23 of
167
SS TUBE FITTINGS
All high pressure fittings need to be of double ferrule type and SS
material only. Makes: M/s Swagelok (USA) / M/s Parker
(USA)/HYLOK/DK- LOK/SSP/HOKE/HAMLET/ M/S BMT Korea
We request approval towards Voss make fittings as
Burckhardt packages are factory supplied with Voss din rated
fittings. The same are in use at all city gas
companies and have successfully completed over 4
million hours of operations in India.
We can provide a certification towards successful use
of Voss fittings in Burckhardt package from prestigious
City Gas end user.
Tender Condition Prevails
12
Bid Document,
VOLUME – II OF II Clause
No. 5.6.11(s)
Page 23 of
167
PREFERRED MAKES of cooler
GEI Hamon Ind. Ltd, GEA India, Patel Air temp, Process
equipment Karad / M/s KPCL, M/s CP.
We request approval towards Chintamni make gas
coolers as Burckhardt packages are factory supplied
with Chintamani cooler. The same are in use at all city
gas companies and have successfully completed over 4
million hours of operations in India.
We can provide a certification towards successful use
of Chintamani gas cooler in Burckhardt package from
prestigious City Gas end user.
Tender Condition Prevails
Page 2 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
13
Bid Document,
VOLUME – II OF II Clause
No. 4.2.3
Page 11 of
167
Compressor maximum vibrations at cylinders and at frame shall
not exceed 10 mm /sec. And 5 mm/s respectively unfiltered peak
velocity
These may be applicable to API618 / ISO13631 compliant
compressor block.
These may not have any interlink with performance in field as
these are related with design.
We supply our field proven trunk piston design
compressor in CNG industries. These parameters are not
applicable to Trunk Piston Design.
We suggest that these being design parameters,
proprietary to each manufacturer, may kindly be dealt
accordingly.
Vendor may supply the package with their proprietary design, subject to fulfillment of
Tender requirement. However, the same design must have been supplied in the past
and approved by PESO.
14
Bid Document,
VOLUME – II OF II Clause
No. 5.2.2
Page 17 of
167
Control Philosophy
PLC architecture
We understand that 100% redundancy in CPU and power
supply is required for bump less changeover.Yes, your understanding is correct.
15
Bid Document,
VOLUME – II OF II Clause
No. 6.3
Page 113
of 167
MECHANICAL STRING TEST
Mechanical String Test of complete package for 4 hrs shall
be performed at packager’s shop before dispatch in
presence of Purchaser/Consultant. This test can be clubbed
up with the Mechanical Run Test of compressor as specified
above, provided the job driver, lube Oil system is used f or
the test. All parameters including discharge pressure shall
be demonstrated. String test at unload condition is not
acceptable.
Since we test the machines on natural gas in our plant.
We request to combine and allow MST and PAT at
packager’s work.
Tender Condition Prevails
16
Bid Document,
VOLUME – II OF II Clause
No. 6.4
Page 114
of 167
PACKAGE PERFORMANCE TEST (PT)
Bidder shall assemble the complete package including
auxiliary systems, instrumentation, safety dev ices within
the enclosure at his shop and dispatch. Duration of PG test
shall be min 4 hours continuously. Complete package
including gas engine shall be performance tested as a
module along with electric motor driven air compressor.
Bidder shall demonstrate all controls, shutdown, trips &
alarm s etc. Pressure and temperature of gas shall be
considered at purchaser’s boundary limit and supplier shall
install necessary pressure and temp measuring devices.
Necessary spool piece shall be provided in discharge tubing
of the com pressor. All instrument duly calibrated, tools &
tackles, any modification required for conducting PT shall
be in the scope of supplier.
We request that Performance Acceptance Test be
conducted for full 04 hours, on load, prior to dispatch at
the premises of packager itself. This methodology is
better as due to variation in loads and frequent auto
shutoff, it is not possible to carry out PAT seamlessly at
site
Tender Condition Prevails
17Bid Document,
VOLUME – I OF II SOR
Page 141
of 142
As mentioned in SOR
1) Supply of CNG Compressor – 3 QTY
2) String Test of package @ packager’s Factory– 3 QTY
3) Supply of Special tools and tackles – 3 QTY
4) Supply of Air Compressor with Air Receiver Vessel – 3 QTY
5) E&C and PAT at Site – 3 Qty
6) O&M for 1 st to 5th year – 3 QTY for each year
Our packaging plant is fully equipped to test the
package on design parameter continuously for 4 hours
on Natural Gas.
We request AGL to accept Performance Acceptance test at
factory.
Tender Condition Prevails
Page 3 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
18
Bid Document,
VOLUME – I OF II Clause
No. 26.1.1
Page 67 of
142
PRICE REDUCTION SCHEDULE
0.5% per week or part thereof of the delayed deliver value
maximum up to 5% of total delivery order value. The total value of
PO considered for applying PRS shall be excluding of all Taxes
and Duties.
We request that 0.5% value of PRS be applicable upon
completion of the complete week.
Please refer clause no. 33 "PRICE REDUCTION SCHEDULE (PRS)" of GCC-Goods
Section V of Tender Vol I of II.
19
Bid Document,
VOLUME – I OF II Clause
No. 1.A
Page 32 of
142
FOR SUPPLY 1)
85% of supply valve including string test – within 15 days
All Prominent City Gas Companies allow payment to
domestic bidders against Inland Letter of Credit.
Similarly, we request to release 85% payment through
Inland letter of credit.
This shall help us to offer better price.
Tender Conditions Prevail
We understand that 1200 SCMH machines are expected
to operate for approximately 2.5 hours daily. (13000
hours/15 years as per tender clause) We humbly submit that
the Machine Size Vs Loading and Penalty do not match and
submit as below :
1. Economic Lifecycle of CNG package is considered
as 73000 Hours. ( Reference tender of Progressive
City Gas Entities ) In case AGL has assumed total
operational life of the machine as 13000 hours then a 1200
SCMH Machine will compress Approx 11.7 Million Kg of CNG
in lifecycle which is 1/6th Capacity of a 1200
SCMH Machine ( as 1200 SCMH machine is procured to
compress approx 70 Million KG of CNG in Lifecycle)
To compress 11.7 Million over lifecycle a 250 SCMH machine
is sufficient. With a margin of 100 % also a 400 SCMH
capacity is more than sufficient (13000hours x 1200 SCMH /
73000 hours of life cycle = 213 SCMH)
A 1200 SCMH machine for the purpose is significantly over
sized proposition. It may also be noted that an over sized
machine has many other associated factors also contribute
towards inefficiency and thus increase loses. Some of the
factors are summarised as below.
Tender Condition Prevails
2. All API 618 standard Machines, by virtue of Design
require Nitrogen Purging Or have to forcibly Vent Gas into
the atmosphere to prevent air from entering the crankcase.
3. Under the circumstances an API 618 Machine
cannot be Zero Gas Loss Machine. Machines lose
Gas while in operation as well as in idling.
4. Loss is excessive in case of idling in comparison to
operation because flooding of Air in Crankcase is not
permitted & venting of Gas in open environment is the
necessity to prevent formation of explosive mixture. In our
opinion, Natural Gas being potent Greenhouse Gas should
not be vented in the atmosphere as it exists in environment
for more than 100 years & depletes
the Ozone layer.
Purchase of 1200 SCMH machine and almost 80 % idling
will lead to massive financial loss to Ex-Chequer and will
also pollute the environment . Hence AGL is requested to
reconsider decision to purchase 1200 SCMH machine and
instead opt for 250 SCMH as it will save millions of rupees in
Capex and OPEX and also safeguard the environment . All
Progressive CGD companies evaluate the bid after
considering the following:
▪ It is requested that lifecycle ownership and
operating cost should be considered while evaluating
bids
▪ The following may kindly be considered in
evaluation:
• Cost of equipment and auxiliaries including insurance,
freight and taxes
• Energy cost for 73000 hours of operation •
Gas Loss for 73000 hours of operation
• Operation & maintenance cost
• E&C, PAT, FAT charges We request to confirm the same.
Bid Document,
VOLUME – II OF II Clause
No. 7.2.1 (i)
20Page 30 of
167
PRICE LOADING FOR FUEL CONSUMPTION
F = (G-Q) * hours * Nop *N
Where,
F = Loading amount in Rs.
G = Guaranteed fuel consumption
in Kg/Hr for every 873 kg (1200
SCMH) of CNG Compressed for
bidder under evaluation.
H =Cost of NG= Rs. 44/ Kg
Nop = 13000 Hrs *
N =No. of Compressors
* This has been considered on
present running hours, expected
running hours for next 15 years
and NPV of Investment.
Tender Condition Prevails
Page 4 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
21
Bid Document,
VOLUME – II OF II Clause
No. 7.2.2(ii) - Vol II -
Page 31 of
167
Penalty during performance test towards gas loss
Bidders are to ensure that the package loss (excluding Engine
consumption) should not exceed 1.0%of the capacity of the
machine. If package loss is quoted more than 1 %of the capacity
of the machine, then bid shall be rejected. In case the above loss
exceeds 0.5% of the capacity of the machine (established in PT),
the purchaser shall be compensated @ Rs 65/- per kg for 5 years
for the gas leakage. The amount will be deducted from O&M
monthly running bill. It is bidder’s responsibility to demonstrate
during PT that the gas leakage is within the limit of 0.5% of the
capacity of the machine. All the provisions such as Flow Meter
(for low flow application) at common vent line suitable for the
application required for this shall be provided by bidder at his own
cost.
From the tender terms we understand that a machine
with gas loss of upto 1% is acceptable.
We understand that even as 13000 hours of operation
and 873kg/hr production the machine make cause a gas
loss of 1.13 lac kgs or in financial terms a loss of approx. 50
lacs.
It is requested that AGL consider taking declaration of
gas loss from bidder and load the bid price during
evaluation.
Tender Condition Prevails
22
Bid Document,
VOLUME – II OF II Clause
No. 13.14.1 & 13.14.2 & 1.3
-
Page 41 &
42 & 166 of
167
All spares, consumables, lubricants, lubricating oil, coolant,
sealant etc. required for carrying out the Operation and
maintenance of the complete compressor package during the
warranty period, including periodic, breakdown maintenance for
continuous and uninterrupted operation of the compressor
packages shall be in scope of the Bidder and shall be kept in
stock. If any equipment got fire or broken due to accident the
same shall be replaced or rectified by the bidder.
Insurance towards fire, theft & accident of the compressor
package shall be in PURCHASER’s Scope. Tender Condition Prevails
23
Bid Document,
VOLUME – II OF II Clause
No. 4.0
Page 4 of
167Delivery shall be………………..
Please note that we shall be transporting the package
either to storage/store or site (place to be confirmed by
client during despatch instructions).Further loading,
retransportation and unloading of the package store to site
will not be in our scope.
Re-transportation of the package from the store to the actual site/station including
transit insurance is in bidder's scope.
2. All API 618 standard Machines, by virtue of Design
require Nitrogen Purging Or have to forcibly Vent Gas into
the atmosphere to prevent air from entering the crankcase.
3. Under the circumstances an API 618 Machine
cannot be Zero Gas Loss Machine. Machines lose
Gas while in operation as well as in idling.
4. Loss is excessive in case of idling in comparison to
operation because flooding of Air in Crankcase is not
permitted & venting of Gas in open environment is the
necessity to prevent formation of explosive mixture. In our
opinion, Natural Gas being potent Greenhouse Gas should
not be vented in the atmosphere as it exists in environment
for more than 100 years & depletes
the Ozone layer.
Purchase of 1200 SCMH machine and almost 80 % idling
will lead to massive financial loss to Ex-Chequer and will
also pollute the environment . Hence AGL is requested to
reconsider decision to purchase 1200 SCMH machine and
instead opt for 250 SCMH as it will save millions of rupees in
Capex and OPEX and also safeguard the environment . All
Progressive CGD companies evaluate the bid after
considering the following:
▪ It is requested that lifecycle ownership and
operating cost should be considered while evaluating
bids
▪ The following may kindly be considered in
evaluation:
• Cost of equipment and auxiliaries including insurance,
freight and taxes
• Energy cost for 73000 hours of operation •
Gas Loss for 73000 hours of operation
• Operation & maintenance cost
• E&C, PAT, FAT charges We request to confirm the same.
Bid Document,
VOLUME – II OF II Clause
No. 7.2.1 (i)
20Page 30 of
167
PRICE LOADING FOR FUEL CONSUMPTION
F = (G-Q) * hours * Nop *N
Where,
F = Loading amount in Rs.
G = Guaranteed fuel consumption
in Kg/Hr for every 873 kg (1200
SCMH) of CNG Compressed for
bidder under evaluation.
H =Cost of NG= Rs. 44/ Kg
Nop = 13000 Hrs *
N =No. of Compressors
* This has been considered on
present running hours, expected
running hours for next 15 years
and NPV of Investment.
Tender Condition Prevails
Page 5 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
24
Bid Document,
VOLUME – II OF II Clause
1.6
Page 6 of
167Separate Junction Boxes..... For interfacing to local panel
Please note that we will not be providing separate junction
boxes for different signals. As per our standard practice all
cables run directly up to PLC panel. Kindly confirm
Accepted
25
Bid Document,
VOLUME – II OF II Clause
1.6
Page 6 of
167
Blow Down vessel shall be located preferably on top of the
package to facilitate periodic testing of pressure vessel.
Blow down vessel shall be mounted on the common
structural skid for compressor, gas engine and other auxiliary
components. This is our proprietary design approved by
PESO.
Bidder may supply the package with their proprietary design. BDV on the top of the
package shall be preferable.
26
Bid Document,
VOLUME – II OF II Clause
1.6
Page 6 of
167
Exhaust fan in the enclosure in addition to the cooling fan of the
heat exchanger.
The ACHE is forced draft and the hot air inside the package
is blown out by the fan. Thus, ventilation fans are not
envisaged.
Our aim is there should be sufficient ventillation for heat dissipation of coolers. Bidder
is required to assess the requirement of additional ventilation fan for the
same.Compressor shall not be tripped on account of rise of temperature inside
compressor package.
27
Bid Document,
VOLUME – II OF II Clause
1.6
Page 7 of
167Separate accoustic enclosure....... UV detectors in each enclosure
We would like to inform you that our compressor package
design having single accoustic enclosure without partition is
approved by PESO. Hence we will not provide a separate
enclosure with a set of GD and FD in each enclosure.
Tender Condition Prevails
28
Bid Document,
VOLUME – II OF II Clause
1.6
Page 7 of
167
O&M charges (post warrantee period) with spares, consumables,
man power and lubricants including complete overhauling of
compressor & engine, if required.
Top and Major Overhauling of Engine is not inlcuded in our
scope.Tender Condition Prevails
29
Bid Document,
VOLUME – II OF II Clause
2.1.2
Page 10 of
167
Manual drains and automatic moisture traps shall be provided in
the system.
Moisture trap not provided by KPCL on reservoir .We are
providing moisture separator cum regulator in the system.Please refer clause no 1.6, Page no 91 of 167, Vol II of II of tender document.
30
Bid Document,
VOLUME – II OF II Clause
2.1.7
Page 10 of
167For running the Air compressor…...... requirement in the offer.
Please specify the distance of PDB from the location where
the compressor package is going to be installed so that cost
of necessary power cable can be considered.
Distance between the PDB and compressor package will be depending on the site
condition. However, distance between them is not more than 40 meters.
31
Bid Document,
VOLUME – II OF II Note
4.8.2
Page 13 of
167
For Calculating the surface area of the air cooler the ambient
temperature of 42 deg C and 80% R.H.
Please confirm the ambient air temperature required for
calculating the area of air cooler. In Datasheet of Heat
exchanger it is stated that exchanger should be designed
with air side temperature of 44 deg C.
The ambient temperature of 44 deg C is considered for designing of ACHE.
32
Bid Document,
VOLUME – II OF II Note
4.9.3
Page 13 of
167
Scrubber service class- B shall be used for interstage/ discharge
scrubbers.
The proposed CNG package has suction volume bottle at
each stage and discharge volume bottle at final stage
discharge only. The volume bottles at suction are connected
to condensate drain system through auto-drain valves. These
volume bottles shall act as scrubbers/ condensate removal
system. No separate KODs shall be supplied. Isolation valve
is mounted in upstream of auto drain valve. Please let us
know your acceptance.
Bidder may supply the package with their proprietary design.
33
Bid Document,
VOLUME – II OF II Note
4.10.10
Page 15 of
167
Engine shall meet all the latest MP State / Central Pollution
Control Board rules & regulations. Bidder shall submit a certificate
approved/accepted by MP State Pollution Control Board for the
installed gas engine during Site Acceptance Test / Performance
Test.
CPCB norms are not applicable as CPCB scope is limited to
Natural Gas Engines for genset applications. However, we
will submit OEM certificate indicating emission values of
offered engine
Please refer reply to Sr. No. 3
34
Bid Document,
VOLUME – II OF II Note
4.11.1
Page 15 of
167
Adequate ventilation fans shall be provided to account for heat
dissipation of coolers.
Please note that Gas engine, compressor and ACHE are in
line and all the hot air inside the package is blown out by the
fan itself due to forced draft. Thus, ventilation fans are not
envisaged.
Please refer reply to Sr.no. 26
Page 6 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
35
Bid Document,
VOLUME – II OF II Note
4.11.3
Page 15 of
167
Enclosures shall be provide with a degree of protection equivalent
to IP 54 as defined in AS 1939, shall be flame proof and provided
with ventilation system. The enclosures shall have doors for
normal access and removable wall panels for ease of
maintenance.
Please note that we will be offering weather proof canopy and
manufacturer's compliance will be given for the degree of
protection. Please confirm the acceptance. Also removable
wall panels will not be provided as all components are easily
accessible without removing wall panels.
Please refer reply to Sr. No. 6.
36
Bid Document,
VOLUME – II OF II Note
4.13
Page 15 of
167
V -Belt drive upto 150 KW gas engine rating is acceptable. Direct
driv e shall be offered by the Bidder if power requirement is > 150
KW.Gear drive is not acceptable. V -Belt driv e >= 150 KW gas
engine rating is also acceptable but the same design must be
approved by PESO.
According to International standards API 618 V-Belt drive is
not suitable for power requirement greater than 150 kW. V-
belt drives are also not accepted by consultants such as
MECON, etc. We would like to point out that PESO only
approves electrical components of the package. From
mechanical point of view belt drive is not suitable.
In case of Belt drive, Bidder shall meet the requirements as per API 618. For more
details please refer clause no 7.4 (Belt Drive) of API 618.
37
Bid Document,
VOLUME – II OF II Note
5.6.11
Page 22 of
167Preferred Makes
We wish to add some other makes as per our market
availabilty:
Switches/Fuses/Contactors: Technik
SS tube, Tube fittings: SSP / Ratnamani
Ball/Needle Valve: SSP
For SS tube & Fittings/On-Off Valve/ NRV : Refer clause no 5.6.11 (n) , Vol II of II of the
tender document.
38
Bid Document,
VOLUME – II OF II Note
5.7.10
Page 25 of
167
Pressure transmitters shall be fixed range type with 2 wire 4 to 20
mA transmitter of piezoresisitive suitable for CNG applications
except at suction and discharge
Please note that all PTs will be piezoresistive. Noted
39
Bid Document,
VOLUME – II OF II Note
5.7.13
Page 25 of
167
Two nos. Of RS 485/RS232 Serial Communication Ports shall be
provided for Hooking Up the PLC to SCADA ..............for
accessing the PLC, HMI and mass flow meter through owner
supplied Laptop PC or laptop supplied by the bidder.
Please note that we shall include one set of license software
for accessing PLC, HMI and Mass flowmeter common for 3
nos of compressor packges. Laptop will not be in our scope.
Accepted
40
Bid Document,
VOLUME – II OF II Note
5.7.14
Page 25 of
167Vendor shall submit test certicates and test reports. Certificates will be submitted as per our standard QAP. Tender Condition Prevails
41
Bid Document,
VOLUME – II OF II Clause
1.6
Page 90 of
167Separate accoustic enclosure....... UV detectors in each enclosure
We would like to inform you that our compressor package
design having single accoustic enclosure without partition is
approved by PESO. Hence we will not provide a separate
enclosure with a set of GD and FD in each enclosure.
Tender Condition Prevails
42
Bid Document,
Sec V- Special conditions of
Contract
Item No. 7.3
Page 82 of
142
Defects liability period) twelve months period of liability from the
date of issue of completion certificate:
Defect liability should be 12 months from commissioning or
18/24 months from supply which ever is earlier.Refer Clause no. 7 of GCC-Works Section VI. Tender Conditions Prevail
43
Bid Document,
Sec V- Special conditions of
Contract
Item No. 6
Page 82 of
142
Contractor will also be responsible for taking
delivery of free issue material from Owner’s store and
Transportation to place of work
including its coverage for transit insurance.
Please note that we shall be transporting the packages either
to storage/store or site (place to be confirmed by client
during despatch instructions). Further loading. Re-
transportation and unloading of the package from store to
site will not be in our scope.
Please refer reply to Sr.no. 23
44
Bid Document,
Sec VI- Special conditions
of Contract
Item No. 1.4
Page 37 of
142
All arrangements and temporary construction if any, within
allocated area for adequate storage and safe custody of all goods
received against the order and for all other allied activities of the
Bidder, shall be done entirely by the bidder at their own cost.
Please note that contractor shall only be responsible for safe
custody of all supplies. Storage (watch and guard) and
preservation to be considered in Purchaser's scope.
Tender Condition Prevails
Page 7 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
B) 5% payment: On completion of erection, alignment & commissioning of each
compressor units. However, if, erection is not started within 90 days after supply due to
non-availability of site/gas, payment against erection and commissioning shall be
released to the successful bidder against receipt of bank guarantee of the said amount
to remain valid for a period of 1 year after completion of 90 days; i.e. 15 months from
the date of FOT site (actual).
REVISED PAYMENT TERMS• In case Erection and Commissioning is delayed beyond 3 Months for the Reason not
attributable to Vendor:
In case erection and commissioning is delayed beyond 3 months from receipt of
package at site, then 5% payment will be released to the vendor after 90 Days (3 months)
of receipt of package at site against submission of security deposit equivalent to 5%
value in form of Bank Guarantee for the period of Twenty-Four (24) Months (warrantee
period) and renewable till the commencement of AMC period (maximum validity 7
years).
1.2 In case the Testing and Field Performance Test could not be executed within 90
days from the date of completion of Erection and commissioning due to reason directly
attributable to the owner.
OR
Erection could not be taken up within 105 days from the date of delivery of material at
site due to reasons directly attributable to the owner; the balance 10% of supply value
as per 1.1 (C) shall be released after deduction against PRS clause if any and on
submission of Bank Guarantee of equivalent amount which shall remain valid for a
period of 1 year after completion of 90 days; i.e. 15 months from the date of FOT site
(actual).
REVISED PAYMENT TERMS• In case the Testing and Field Performance Test could not be executed within 90 days
from the date of completion of Erection and commissioning due to reason not
attributable to Vendor OR Erection could not be taken up within 105 days from the date
of delivery of material at site due to reasons not attributable to Vendor:
Testing and Field Performance Test could not be executed within 90 days from the date
of completion of Erection and commissioning at site or erection could not be taken up
within 105 days from the date of delivery of material at site, then 10% payment for
testing & field performance test can be released against submission of Security Deposit
equivalent to 10% of remaining value in form of Bank Guarantee for the period of
Twenty Four (24) Months (warrantee period) and renewable till the commencement of
AMC period (maximum validity 7 years).
45
Bid Document,
Sec III- Terms of PaymentPage 32 of
142
5% payment: On completion of installation, erection, allignment &
commissioning..... Validity of BG
Please note that if Erection & Commissioning has started but
not completed due to reasons attributable to the owner, this
payment will be put on hold. Hence we request you to accept
the following ammendment in the backstop of this payment
milestone:
However, if erection has started but not completed within 90
days after supply due to reasons not attributable to supplier,
the payment against Erection & Commissioning shall be
released against bank guarantee of the said amount. The
bank guarantee shall be valid for a period of 1 year after
completion of 90 days and validity of this BG shall not be
extended further.
Please note that if Erection & Commissioning has started but
not completed due to reasons attributable to the owner, this
payment will be put on hold. Hence we request you to accept
the following ammendment in the backstop of this payment
milestone: Installation/ Erection
has started but not completed within 105 days from the date
of delivery of material at site due to reasons directly
attributable to the owner; the balance 10% of supply value as
per 1.1.1 (C) or 1.1.2 (C) shall be released after deduction
against PRS clause if any and on submission of Bank
Guarantee of equivalent amount which shall initially remain
valid for a period of 1 year after completion of 90 days and
vaildity of this BG shall not be extended further.
10% payment: In case the testing and PG test could not be
executed within 90 days from date of completion of Erection &
Commissioning.... Validity of BG
Page 32 of
142
Bid Document,
Sec III- Terms of Payment
46
Page 8 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
• Regarding Payment Terms during AMC period after expiry of Warranty Period:
Firm commissioning date cannot be given at that time as it depends upon the site
conditions. However, the AMC rate will be valid upto the period of 7 years (2 years
Warranty period + 5 years AMC period) from the date of Supply. For example – If
Compressor is commissioned in 4th year from the date of supply then AMC period
should be considered for the balance period from 4th year to 7th year at the same rate
quoted by bidder.
Definition of Balance period = (Two Year Warranty period + Five Year AMC Period) –
(Time Elapsed due to delay in Commissioning from the date of supply)
For example:
i) If Compressor is commissioned within Warranty period of 24 months from the date of
supply:
if a Compressor delivered on 15.05.2020 and commissioned on 16.07.2021, then AMC
period will commence for balance period as per following formula:
Balance Period = {(warranty period (15.05.2020 to 16.07.2021) + Five year AMC period} -
{Time Elapsed due to delay in Commissioning from the date of supply (15.05.2020 to
16.07.2021)}
AMC period will commence for Balance period = From 17.07.2021 to 16.07.2026.
i) If Compressor is commissioned beyond Warranty period of 24 months from the date
of supply:
if a Compressor delivered on 15.05.2020 and commissioned on 25.08.2023, then AMC
period will commence for balance period as per following formula:
Balance Period = {(warranty period (15.05.2020 to 14.05.2022) + Five year AMC period
(15.05.2022 to 14.05.2027)} - {Time Elapsed due to delay in Commissioning from the
date of supply (15.05.2020 to 25.08.2023)}
AMC period will commence for Balance period = From 25.08.2023 to 14.05.2027
46
Page 9 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
47
Bid Document,
Sec VI- Special conditions
of Contract
Item No. 33
Page 48 of
142PRICE REDUCTION SCHEDULE (PRS)
We request you to accept below price reduction schedule:
0.5% per week or part thereof of the delayed delivery value
maximum up to 5% of Undelivered portion Order value
(Excluding Taxes and Duties).
Please refer clause no. 33 "PRICE REDUCTION SCHEDULE (PRS)" of GCC-Goods
Section V of Tender Vol I of II.
48
Bid Document,
Sec VI- Special conditions
of Contract
Item No. 18.1
Page 44 of
142
Insurance: Insurance cover shall be applicable during entire
tenure contractor's custody till the material is handed over to the
Owner at site in a manner defined in tender documents.
Please note that complete Insurance cover will be excluded
from our scope. We shall only bear the transit Insurance till
site.
Tender Conditions Prevail
49Installation, testing & Commissioning of CNG compressor
package.
Please note that our E&C charges shall be valid till warranty
periodE&C charges shall be valid for 24 months from the supply of Compressor at Site/store
50
Bid Document,
VOLUME – II OF II Clause
No. 1.2
Codes & Standards
The following National & International Codes & Standards of
Latest editions shall be applicable.
OISD 179, NFPA-52: 1995 or equivalent
NFPA – 37
NFPA – 12- CO2 Flooding system
IS: 325/ IEC or International standards. – Standards for electric
Motor
IS: 6382
Applicable ANSI, ASTM, NEC, NEMA code. API – 618
API – 11P 2nd edition
API – 661 Specifications for Air cooled exchangers
ASME Section – VIII Div – 1/2 Design codes for pressure vessels.
Gas Cylinder Rules 2016.
Standard Specifications of Bureau of Indian Standards (BIS).
Specifications/Recommendations of IEC.
Indian Electricity Rules.
Indian Explosives Act.
TEMA – C - Water cooled heat exchangers
ASME / ANSI – B-31.3 Code for Process Piping
51
Bid Document,
VOLUME – II OF II Clause
No. 1.3
Precedence
3. International standards/codes as applicable
4. Indian Standards / codes applicable
52
Bid Document,
VOLUME – II OF II Clause
No. 4.4.1
All oil wiper intermediate gas cylinder pressure packing shall be a
segmental ring with stainless steel garter springs. The pressure
packing case shall be provided with a common vent and drain
below the piston rod tube to the outside of the Package enclosure.
Pressurized crankcase and hence not applicable Please refer clause no 4.4.4, Vol II of II of the tender document.
53
Bid Document,
VOLUME – II OF II Clause
No. 4.4.2
ERW / seamless steel tubing conforming to ASTM A-192 or series
300 SS tubing conforming to ASTM A-269 with minim um
thickness as specified in Cl. 7.11 of API-11P shall be used for
vent piping.
Pressurized crankcase and hence not applicable
Please refer clause no 4.4.4, Vol II of II of the tender document.
54
Bid Document,
VOLUME – II OF II Clause
No. 4.4.3
Packing vent piping inside of the distance piece shall be designed
for the maximum operating pressure of the cylinder.
Pressurized crankcase and hence not applicable
Please refer clause no 4.4.4, Vol II of II of the tender document.
55
Bid Document,
VOLUME – II OF II Clause
No. 4.5.3, 4.12.8 & 4.12.11
All lube oil piping after oil filter shall be 300 series stainless steel
conforming to ASTM A269.
All lube oil piping down stream of filter shall be series 300
Stainless Steel
All piping after coalescent filter at compressor discharge shall be
of SS 316.
After oil filter inbuilt oil galleries are provided. Standard Brass
NRV provided at forced lubrication point.
Tender Condition Prevails
3 x 1200 SCMH AT 16 KG/CM2G , 3 STAGE- 16-19-MOTOR
The compressor design is derived from
API618/11P/equivalent industry standards. However, the
design is enhanced to meet specific CNG application such as
pressurized crankcase to avoid gas vent loss etc.
Tender Condition Prevails
Page 10 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
56
Bid Document,
VOLUME – II OF II Clause
No. 4.6.1 & 4.6.2
Distance Pieces
Distance piece as per API-11P with cylinder side compartment
vented to safe location is specified.
Distance pieces shall be provided with gasket, solid covers and
shall be suitable for a minimum differential compartment pressure
of 1.75 kg/cm²g.
Distance piece will be as per manufacturer's design
standard.
Tender Condition Prevails
57
Bid Document,
VOLUME – II OF II Clause
No. 4.7.1
Single plunger per point force feed mechanical lubricator / divider
Block type shall provide lubrication to compressor cylinders.
Divider block type with Common indicator will be provided &
Brass NRV provided. Please refer clause no 4.7.3, Vol II of II of the tender document.
58
Bid Document,
VOLUME – II OF II Clause
No. 4.7.3
Lubricators shall have a sight flow indicator for each lubricator
point and a stainless steel double ball check valve shall be
provided at each lubrication point. Common sight glass is also
acceptable . Divider block lubrication system to compressor
cylinders shall also be accepted.
Common indicator is provided & Brass NRV provided. Please refer clause no 4.7.3, Vol II of II of the tender document.
59
Bid Document,
VOLUME – II OF II Clause
No. 4.7.4
Digital no flow timer shall be provided to stop the compressor in
case of loss of cylinder lubrication.
Common Digital No Flow Switch (time based) will be
provided.
- When there is no – pulse ( from cylinder lubrication -
divider block) for certain time interval, the switch toggles &
the compressor is tripped on lubrication fault.
Accepted
60
Bid Document,
VOLUME – II OF II Clause
No. 4.8.2
Inter / After Gas Coolers
Air-cooled inter-stage and final stage discharge coolers shall be
provided which shall limit the gas temperature after the cooler to
50 degree C (Or the discharge temperature after aftercooler =
Ambient + 10 deg C). For calculating the surface area of the air
cooler the ambient air temperature of 42oC and 80% RH shall be
considered. Cooler design shall be on the basis of 20% excess
capacity than required corresponding to suction PR of 16 kg/cm2
Gas sections of coolers shall be designed as per API-661
requirements; however gas section shall be inspected by
approved third party inspection agency and may not be “U” code
stamped. Vibration switch shall be provided on the heat exchanger
to trip the compressor on high vibration limit. Bidder shall indicate
vibration level in the offer.
For cooling of the Heat Exchangers a cooling fan to be provided
inside the enclosure(s).
Cooling system shall be preferably installed on the same skid as
the compressor due to space constraints. Bidder shall submit
cooler sizing calculation for review.
- The approach above ambient would be 10°C. (max.
discharge temp. 42°C + 10°C = 52°C).
- The required inputs would be given in the Heat Exchanger
datasheet.
-Cooler design shall be on the basis of 10% excess
-Design shall be manufacturer standard.
-TPI not considered.
-We shall be suplying package with concrete filled frame,
vibration s/w on cooler frame is not envisaged
1. The dicharge temp after the cooler = 42°C + 10°C = maximum 52°C.
2. For the rest points : Tender Condition Prevails.
Page 11 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
62
Bid Document,
VOLUME – II OF II Clause
No. 8.4
The headers of air-cooled exchanger shall be zinc sprayed.The headers of air-cooled exchanger shall be with heat
resistant paint. Tender Condition Prevails
63
Bid Document,
VOLUME – II OF II Clause
No. 1.6
3 nos. mass flow meters to measure the Natural Gas consumption
at packages inlet, package discharge (both Coriolis type) and
package loss / venting (thermal type) with online test
arrangement. Mass flow meter (Model CNG 50 & F Series with
integral local display) based on Coriolis principle of Micro motion,
USA CNG 50 with 2700 transmitter at Compressor discharge, F-
series with 1700 transmitter at compressor suction. Installation
and manufacturing of mass flow meter shall be as per as per AGA-
11. While installing special care shall be taken to isolate the m
ass flow meter from piping vibration. Mass flow meter shall be
provided in package vent for measuring vent losses. The mass
flow meter at the suction & discharge of compressor shall be
W&M approved only. The flowmeters should be enabled with
MODBUS/RS 485 communications
-As we are offering block with pressurised crankcase, there
is no vent loss. Thermal MFM is not evisaged and hence not
considered.
-Custody transfer for suction MFM not considered.
Tender Condition Prevails
64
Bid Document,
VOLUME – II OF II Clause
No. 1.6
Common structural steel skid for the compressor- Motor
combination and for all auxiliary systems
All auxiliary systems (Air compressor , CO2 flooding etc)
shall be supplied loose and to be mounted apart from
pacakge.
Only CO2 flooding , Air Compressor with Dryer , Air Receiver to be mounted apart from
the package. Suction Filter shall be inside or outside of the package.
MRT will be carried out as per manufacturer's standards. Tender Condition Prevails61
Mechanical running test (MRT)
The MRT for the each compressors shall be carried out by
tenderer with job or shop driver including complete job driving
system i.e., job driven V-belt, job pulleys etc., for 4 hours
continuously at shop of compressor manufacturer. The
compressor need not be pressure loaded for MRT test. During
this test following shall be recorded at agreed intervals.
• Vibration levels measured on cylinders and frame
• Bearing temperature
• Oil cooler inlet and outlet tem p
• Sound level
Subsequent to satisfactory run the compressor shall be examined
as per standard procedure & following shall be examined as
minimum:
Strip test is limited to open Crank Case cover, X-Hd guide &
Dist.pc. Cover and opening of bore & other parts, piston, one
valve per cylinder. Visual examination of position rod If any of part
found damaged, all similar components shall be stripped for
inspection. The MRT test shall be repeated after replacement of
such parts. All the interlocking and performance of the
instrumentation system will be verified during the MRT.
Bid Document,
VOLUME – II OF II Clause
No. 6.2.1
Page 12 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
65
Bid Document,
VOLUME – II OF II Clause
No. 1.6
Separate junction boxes for different type of signals like
intrinsically safe signals, alarm, shutdowns, thermocouples, RTDs
etc. for interfacing to local panel
LCP (With PLC) is mounted on package itself hence
separate JB's are not required (With PLC) is mounted on
package itself & also separate gauge box will be used for
intrinsically safe signals.
Please refer reply to Sr. No. 24.
66
Bid Document,
VOLUME – II OF II Clause
No. 1.6
Separate acoustic enclosure, seprated with a partition wall of
minimum 3 mm thickness and fabricated in such fashion that it is
completely sealed so that gas or fire should not travel from one
enclosure to another, for both Compressor and motor as
specified, with two number L.E.L detector and two UV detectors in
each enclosure.
Practically 100% sealing is not possible as mentioned in the
tender document clause. PESO has approved non
compartmentalized enclosures. Adequate safeties are
provided in the enclosures to avoid any uneventful incident.
Kindly consider non - compartment type enclosure.
Tender Condition Prevails
67
Bid Document,
VOLUME – II OF II Clause
No. 1.6
Separator/ Knockout drums/volume drums with solenoid valve
operated auto & manual drains as required. Moisture separator
cum regulator in the system shall also be accepted. Bypass
valves for automatic drain system shall be as per manufacturer’s
recommendation.
Considering safety hazards manual drains for KOD not
considered also as drain shall be normally open hence
requirement on manual drain is not evisaged.
For final oil drain from blowdown vessel manual and
automatic drain shall be provided.
Compressor package shall be capable to drain out from Seperators/KOD in case of
automatic system fails.
68
Bid Document,
VOLUME – II OF II Clause
No. 2.1.2
Bidder shall make his own provision for Instrument air if required
with an electric motor driven air compressor with a suitably sized
receiver & Refrigerant type air drier system. Air Compressor motor
should be 415 V squirrel cage motor DOL / star delta starter
having overload protection, single phase preventer. A Rain guard
of MOC carbon steel minimum thickness of 2 mm should be
provided over the air compressor.
Pl confirm if air compressor supply is in bidder's scope ? Please refer clause no 2.1.1, Vol II of II of the tender document.
69
Bid Document,
VOLUME – II OF II Clause
No. 2..2.4
UPS and Non UPS power shall be made available from power
distribution board (PDB) in the electrical room. Supply, Erection
and termination of all cables and accessories from feeder in
electrical room shall be in the bidder’s scope
Pl confirm if UPS is in bidder's scope ? Cable lengths to be
defined properly.
Please refer clause no 2.1.6, Vol II of II of the tender document.However the distance
between PDB and compressor package is not more than 40 meters.
70
Bid Document,
VOLUME – II OF II Clause
No. 4.9.1
Carbon Steel separators/KOD at auto and manual drain system
shall be prov ided for the capacity as required.
Considering safety hazards manual drains for KOD not
considered also as drain shall be normally open hence
requirement on manual drain is not evisaged.
For final oil drain from blowdown vessel manual and
automatic drain shall be provided.
Please refer reply to Sr. No. 67.
71
Bid Document,
VOLUME – II OF II Clause
No. 4.9.3
Scrubber service class - B shall be used f or Inter-stage /
discharge scrubbers. Service Class - C
shall be used f or su ction scrubber. (Refer API -11P)
Manufacturer standard , spinner type seperator shall be
provided instead of scrubber type seperator.Please refer reply to Sr.No. 32
Page 13 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
72
Bid Document,
VOLUME – II OF II Clause
No. 4.9.3
All v essels including pulsation dam pers shall be fully (100 %)
radio graphed as per ASME VIII UW (a) or equiv alent.
All vessels will be fully (100%) radio-graphed as per ASME
VIII, however U stamping not considered.Tender Condition Prevails
73
Bid Document,
VOLUME – II OF II Clause
No. 4.9.4
Gas recovery system
Suction damper and gas recovery vessel shall be combined
as per manufacturer std practice hence as per tender specs
PRV between blowdown vessel and compressor suction is
not considered.
Please refer clause no 4.9.4, Vol II of II of tender document.
74
Bid Document,
VOLUME – II OF II Clause
No. 4.9.7
Coalescent super fine filters (preferably two stages) with CE m
ark/ third party inspected for rem oval of liquid (e.g. water & oil)
and solid particles down to 0.1 microns out of com pressed natural
gas shall be provided. Residual Oil Contents shall be less than 1
PPM. Manual drains with isolation valves with oil collecting pot
shall be provided. The filter should be sized to flow for 200% of
flow corresponding to flow at suction pressure of 19 kg/cm2g .
However mechanical design shall be based on safety set
pressure.
Filters with 100% of flow capacity are sufficient. CE / TPI
markings are not necessary since filetrs shall be from
approved makes.
Tender Condition Prevails
75
Bid Document,
VOLUME – II OF II Clause
No. 4.9.8
Pulsation, Vibration Control and Analog Study Not feasible to be provided since design data is proprietary. Accepted
76
Bid Document,
VOLUME – II OF II Clause
No. 4.11.5
All the pressure, tem perature, lube oil pressure, coolant
temperature, coolant lev el indicators shall be visible from outside
of enclosures.
Cooler level indicator of engine radiator shall not visible from
outide however can be easily check Accepted
77
Bid Document,
VOLUME – II OF II Clause
No. 4.12
Piping
Gas piping/ tubing at 3rd stage discharge will only be in SS-
316, with SS fittings,
Rest all piping /tubing will be Combination of Flanged &
screwed connections with CS material (pipes, Fittings &
Flanges ) as per application requirement & standard design.
This is as per manufacturing standard design.
Instrument Air Tubing will be in SS-304.
A) For CS Piping ,Please refer clause no 4.12.2, Vol II of II of tender document.
B) For Instrument Air Piping ,Please refer clause no 4.12.5, Vol II of II of tender
document.
78
Bid Document,
VOLUME – II OF II Clause
No. 4.12.5
The instrument air tubing material shall be SS316 as per ASTM
A269.Impulse air tubing for actuator operation shall be SS-304. Please refer reply to Sr.No. 77 (B).
79
Bid Document,
VOLUME – II OF II Clause
No. 4.12.9
External drain & v ent piping shall be Carbon Steel and not less
than 1" nominal sizeExternal drain connection shall be-1/2" Tender Condition Prevails
80
Bid Document,
VOLUME – II OF II Clause
No. 4.12.9
Following certificates have to be submitted for piping fabricated at
Site / shopElectrode qualification test results not considered Please refer clause no 4.12.14, Point no .11 (C) Vol II of II of tender document.
81 Makes Pressure Transmitter Please approve GIC Tender Condition Prevails
82
Bid Document,
VOLUME – II OF II Clause
No.5.7.4 & 5.7.15
Electrical instrumentation shall be certified by a recognized
authority such as BASEEFA, PTB, LCIE, CESI, INIEX, CMRS or
any agency approved by Indian Gov ernm ent.
CCOE or its equivalent certificate (FM, CSA , ATEX, UL,
CMRI) whichever applicable & available will be provided.Accepted
83
Bid Document,
VOLUME – II OF II Clause
No. 5.7.4 & 5.7.15
For online Calibration of MFM; Vendor to provide suitable
arrangement to connect Master Mass flow meter (Prover) with
Compressor Suction & Compressor Discharge flow meter for
calibration purpose.
For online calibration of suction MFM loose pipe arrangement
shall be provided and for discharge MFM provision for
calibration shall be available on P&ID
Tender Condition Prevails
84
Bid Document,
VOLUME – II OF II Clause
No. 5.7.14
Offered m ass flow m eter shall be necessary f or Custody
Transfer application but not exceeding
0.5% of span. Type of approval certificate from W&M India is
required.
0.5% accuracy considered but custody tranfer application for
suction MFM not consideredTender Condition Prevails
Page 14 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
85
Bid Document,
VOLUME – II OF II Clause
No. 6.4
Pressure and temperature of gas shall be considered at
purchaser’s boundary limit and supplier shall install necessary
pressure and temp measuring devices. Necessary spool piece
shall be provided in discharge tubing of the com pressor. All
instrum ent duly calibrated, tools & tackles, any modification
required f or conducting PT shall be in the scope of supplier.
Pressure and temperature shall be considered at compressor
block suction during performance test.Tender Condition Prevails
HYDROTEST OF-CYLINDER HEADS Not feasible hence not considered Tender Condition Prevails
LEAK PROOF T EST OF PRESSURIZED CRANK CASE (4 Hours
wit h k erosene)
Hydrotest for crankacase considered.
Customer inspection not considered as it will lead to major
delivery time adder
Tender Condition Prevails
ULTRASONIC TEST OF-CRANK SHAFT , CONNECTING ROD.,
PIST ON R O DUltrasonic test for crank shaft not considered Tender Condition Prevails
RADIOGRAPH Y AS APPLICABLE-PRESSURE VESSELS, HEAT
EXCHANGER, G AS PIPINGAs welding not involved in heat exchanger Tender Condition Prevails
BARRING OVER TO CHECK CYLINDER END CLEARANCE
AND PISTON ROD RUNOUTPiston rod runnot not considered as not feasible to check. Tender Condition Prevails
NO LOAD MECHANICAL RUN T EST OF THE COMPR. W IT H
RAT ED (OR MORE) SPEED AND SHOP DRIVER (4 HRS. Minim
um .)
Customer witness not considered Tender Condition Prevails
STRIP CHECK AND INTERNAL INSPECTION AFTER " NLMRT"
OF ALL C O MPRESSO RS ; - Routine test c ertif icat e by v
endors
Customer witness not considered Tender Condition Prevails
88
Bid Document,
VOLUME – II OF II Clause
No. 1.3
Precedence
3. International standards/codes as applicable
4. Indian Standards / codes applicable
Bid Document,
VOLUME – II OF II Clause
No.20-QAP
3x 1200 SCMH AT 16 KG/CM2G , 3 STAGE- 16-19-ENGINE
86
Bid Document,
VOLUME – II OF II Clause
No. 1.2
87
Please refer reply to Sr.No.50
The compressor design is derived from
API618/11P/equivalent industry standards. However, the
design is enhanced to meet specific CNG application such as
pressurized crankcase to avoid gas vent loss etc.
Codes & Standards
The design, construction, manufacture, supply, testing and other
general requirements of the compressor package equipment shall
be strictly in accordance with the data sheets, applicable API
codes, and shall comply fully with relevant National/ International
standards, Indian Electricity Act, Indian Electricity Rules,
regulations of Insurance Association of India and Factories Act
while carrying out work as per this specification.
Any modification suggested by the statutory bodies either during
drawing approval or during inspection, if any, shall be carried out
by the Bidder without any additional cost and delivery implications.
The following codes and standards (versions/ revisions valid on
the date of order) are referenced to & made part of specification:
API-11P, Second edition, API 618,
ISO 13631-2002,
NFPA-37, OISD 179, NFPA-52: 2006, NFPA-496, NFPA-68, NFPA-
70
ANSI, ASTM, NEC, NEMA
Indian Electricity Rules, Indian Explosives Act, Gas cylinder rules,
codes for SS tube & forged fittings.
Page 15 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
89
Bid Document,
VOLUME – II OF II Clause
No. 4.10.10
Engine shall meet all the latest MP State / Central Pollution
Control Board rules & regulations. Also, Bidder shall submit a
certificate approved/accepted by MP State Pollution Control Board
for the installed gas engine during Site Acceptance Test /
Performance Test. All the requisite fees for this test shall be borne
by Bidder. Performance Test will be considered to be final
thereafter only.
Provision of emmissionized gas engine with catalytic
convertor shall only be in the scope of bidder. Certification of
any sort from MP Pollution control board will not be provided
by bidder. This is primarily the responsibility of the CGD Gas
Company.
Please refer reply to Sr.No.3
90
Bid Document,
VOLUME – II OF II Clause
No. 4.4.1
All oil wiper intermediate gas cylinder pressure packing shall be a
segmental ring with stainless steel garter springs. The pressure
packing case shall be provided with a common vent and drain
below the piston rod tube to the outside of the Package enclosure.
Pressurized crankcase and hence not applicable Please refer reply to Sr.No.52
91
Bid Document,
VOLUME – II OF II Clause
No. 4.4.2
ERW / seamless steel tubing conforming to ASTM A-192 or series
300 SS tubing conforming to ASTM A-269 with minimum thickness
as specified in Cl. 7.11 of API-11P shall be used for vent piping.
Pressurized crankcase and hence not applicable
Please refer reply to Sr.No.53
92
Bid Document,
VOLUME – II OF II Clause
No. 4.4.3
Packing vent piping inside of the distance piece shall be designed
for the maximum operating pressure of the cylinder.
Pressurized crankcase and hence not applicable
Please refer reply to Sr.No.54
93
Bid Document,
VOLUME – II OF II Clause
No. 4.5.3, 4.12.8 & 4.12.11
All lube oil piping after oil filter shall be 300 series stainless steel
conforming to ASTM A269.
All lube oil piping down stream of filter shall be series 300
Stainless Steel
All piping after coalescent filter at compressor discharge shall be
of SS 316.
After oil filter inbuilt oil galleries are provided. Standard Brass
NRV provided at forced lubrication point.
Please refer reply to Sr.No.55
94
Bid Document,
VOLUME – II OF II Clause
No. 4.6.1 & 4.6.2
Distance Pieces
Distance piece as per API-11P with cylinder side compartment
vented to safe location is specified.
Distance pieces shall be provided with gasket, solid covers and
shall be suitable for a minimum differential compartment pressure
of 1.75 kg/cm ²g.
Distance piece will be as per manufacturer's design
standard.
Please refer reply to Sr.No.56
95
Bid Document,
VOLUME – II OF II Clause
No. 4.7.1
Single plunger per point force feed mechanical lubricator / divider
Block type shall provide lubrication to compressor cylinders.
Divider block type with Common indicator will be provided &
Brass NRV provided. Please refer reply to Sr.No.57
96
Bid Document,
VOLUME – II OF II Clause
No. 4.7.3
Lubricators shall have a sight flow indicator for each lubricator
point and a stainless steel double ball check valve shall be
provided at each lubrication point. Common sight glass is also
acceptable. Divider block lubrication system to compressor
cylinders shall also be accepted.
Common indicator is provided & Brass NRV provided. Please refer reply to Sr.No.58
97
Bid Document,
VOLUME – II OF II Clause
No. 4.7.4
Digital no flow timer shall be provided to stop the compressor in
case of loss of cylinder lubrication.
Common Digital No Flow Switch (time based) will be
provided.
- When there is no – pulse ( from cylinder lubrication -
divider block) for certain time interval, the switch toggles &
the compressor is tripped on lubrication fault.
Please refer reply to Sr.No.59
Page 16 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
98
Bid Document,
VOLUME – II OF II Clause
No. 4.8.2
Inter / After Gas Coolers
Air-cooled inter-stage and final stage discharge coolers shall be
provided which shall limit the gas temperature after the cooler to
50 degree C (Or the discharge temperature after aftercooler =
Ambient + 10 deg C). For calculating the surface area of the air
cooler the ambient air temperature of 42°C and 80% RH shall be
considered. Cooler design shall be on the basis of 20% excess
capacity than required corresponding to suction PR of 16 kg/cm2
Gas sections of coolers shall be designed as per API-661
requirements; however gas section shall be inspected by
approved third party inspection agency and may not be “U” code
stamped. Vibration switch shall be provided on the heat exchanger
to trip the compressor on high vibration limit. Bidder shall indicate
vibration lev el in the offer.
- The approach above ambient would be 10°C. (max.
discharge temp. 42°C + 10°C = 52°C).
- The required inputs would be given in the Heat Exchanger
datasheet.
-Cooler design shall be on the basis of 10% excess
-Design shall be manufacturer standard.
-TPI not considered.
-We shall be suplying package with concrete filled frame,
vibration s/w on cooler frame is not envisaged
Please refer reply to Sr.No.60
100
Bid Document,
VOLUME – II OF II Clause
No. 8.4
The headers of air-cooled exchanger shall be zinc sprayed. Shall be with heat resistant paint Please refer reply to Sr.No.62
101
Bid Document,
VOLUME – II OF II Clause
No. 1.6.3
Electrical instrumentation shall be certified by a recognized
authority such as BASEEFA, PTB, LCIE, CESI, INIEX, CMRS or
any agency approved by Indian Gov ernm ent.
PESO approved Please refer reply to Sr.No.63
102
Bid Document,
VOLUME – II OF II Clause
No. 1.6.6
Separate junction boxes f or different type of signals like analog,
digital signals, alarm, shutdowns, and thermocouples, RTDs etc. f
or interfacing to FLP local panel.
LCP (With PLC) is mounted on package itself hence
separate JB's are not required (With PLC) is mounted on
package itself & also separate gauge box will be used for
intrinsically safe signals.
Please refer reply to Sr.No.24
MRT will be carried out as per manufacturer's standard
procedures.99
Mechanical running test (MRT)
The MRT for the each compressors shall be carried out by
tenderer with job or shop driver including complete job driving
system i.e., job driven V-belt, job pulleys etc., for 4 hours
continuously at shop of compressor manufacturer. The
compressor need not be pressure loaded for MRT test. During
this test following shall be recorded at agreed intervals.
• Vibration levels measured on cylinders and frame
• Bearing temperature
• Oil cooler inlet and outlet temp
• Sound level
Subsequent to satisfactory run the compressor shall be examined
as per standard procedure & following shall be examined as
minimum:
Strip test is limited to open Crank Case cover, X-Hd guide &
Dist.pc. Cover and opening of bore & other parts, piston, one
valve per cylinder. Visual examination of position rod If any of part
found damaged, all similar components shall be stripped for
inspection. The MRT test shall be repeated after replacement of
such parts. All the interlocking and performance of the
instrumentation system will be verified during the MRT.
Bid Document,
VOLUME – II OF II Clause
No. 6.2.1
Please refer reply to Sr.No.61
Page 17 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
103
Bid Document,
VOLUME – II OF II Clause
No. 1.6.7
Main incoming cable from owner PDB to main control panel of the
com pressor through Conduit/trenches. Cable from owners
electronic earth pit (EE) f or electronic circuit in control Panel,
cables f rom owners m ain earthing ring to control panel body
earth and all interconnecting Cables including com plete erection
accessories like double compression cable, FLP gland, cable
tags, Lugs etc. as required. Conduit from PDB to Flam e control
panel shall be m ade av ailable by supplier & from Control panel to
diff erent accessories / ESD /units shall be in supplier scope
Define proper cable lengths. Please refer reply to Sr.No.30
104
Bid Document,
VOLUME – II OF II Clause
No. 1.6.9
Blow down vessel shall be located preferably on top of the
package to facilitate periodic testing of pressure vessel.
Blowdown vessel shall be monted on base of the pacakge.
This is as per proven manufacturer design.Please refer reply to Sr.No.25
105
Bid Document,
VOLUME – II OF II Clause
No. 1.6.13
Shed Structure (Galvanized corrugated sheet) of 10’ x 8’ ov er the
Control panel to the Operator for operating the com pressor. Total
structure setup, fabrication & finishing shall be in bidder’s scope.
The shed over the control penal is also for operator to operating
the compressor
Control panel shall be mounted inside the pacakge canopy
hence additional shed is not required. Tender Condition Prevails
106
Bid Document,
VOLUME – II OF II Clause
No. 1.6.17 & 4.9.1
Separator/ Knockout drums/volume drums with solenoid valve
operated auto & manual drains as required. Moisture separator
cum regulator in the system shall also be accepted. Bypass
valves for automatic drain system shall be as per manufacturer’s
recommendation
Considering safety hazards manual drains for KOD not
considered also as drain shall be normally open hence
requirement on manual drain is not evisaged.
For final oil drain from blowdown vessel manual and
automatic drain shall be provided.
Please refer reply to Sr.No.67
107
Bid Document,
VOLUME – II OF II Clause
No. 1.6.24
Separate acoustic enclosure, seprated with a partition wall of
minimum 3 mm thickness and fabricated in such fashion
that it is completely sealed so that gas or fire should not
travel from one enclosure to another, for both Compressor
and Engine as specified, with two number L.E.L detector and
two UV detectors in each enclosure.
Practically 100% sealing is not possible as mentioned in the
tender document clause. PESO has approved non
compartmentalized enclosures. Adequate safeties are
provided in the enclosures to avoid any uneventful incident.
Kindly consider non - compartment type enclosure.
Please refer reply to Sr.No.66
108
Bid Document,
VOLUME – II OF II Clause
No. 4.9.1
Carbon Steel separators/KOD at auto and manual drain system
shall be prov ided for the capacity as required.
Considering safety hazards manual drains for KOD not
considered also as drain shall be normally open hence
requirement on manual drain is not evisaged.
For final oil drain from blowdown vessel manual and
automatic drain shall be provided.
Please refer reply to Sr.No.67
109
Bid Document,
VOLUME – II OF II Clause
No. 4.9.3
Scrubber service class - B shall be used f or Inter-stage /
discharge scrubbers. Service Class - C
shall be used f or su ction scrubber. (Refer API -11P)
Manufacturer standard , spinner type seperator shall be
provided instead of scrubber type seperator.Please refer reply to Sr.No. 32
110
Bid Document,
VOLUME – II OF II Clause
No. 4.9.3
All v essels including pulsation dam pers shall be fully (100 %)
radio graphed as per ASME VIII UW (a) or equiv alent.
All vessels will be fully (100%) radio-graphed as per ASME
VIII, however U stamping not considered.Please refer reply to Sr.No. 72
111
Bid Document,
VOLUME – II OF II Clause
No. 4.9.4
Gas recovery system
Suction damper and gas recovery vessel shall be combined
as per manufacturer std practice hence as per tender specs
PRV between blowdown vessel and compressor suction on
considerd
Please refer reply to Sr.No. 73
112
Bid Document,
VOLUME – II OF II Clause
No. 4.9.7
Coalescent super fine filters (preferably two stages) with CE m
ark/ third party inspected for rem oval of liquid (e.g. water & oil)
and solid particles down to 0.1 microns out of com pressed natural
gas shall be provided. Residual Oil Contents shall be less than 1
PPM. Manual drains with isolation valves with oil collecting pot
shall be provided. The filter should be sized to flow for 200% of
flow corresponding to flow at suction pressure of 19 kg/cm2g .
However mechanical design shall be based on safety set
pressure.
Filters with 100% of flow capacity are sufficient. CE / TPI
markings are not necessary since filetrs shall be from
approved makes.
Please refer reply to Sr.No. 74
Page 18 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
113
Bid Document,
VOLUME – II OF II Clause
No. 4.9.8
Pulsation, Vibration Control and Analog Study Not feasible due to proprietary design details. Please refer reply to Sr.No. 75
114
Bid Document,
VOLUME – II OF II Clause
No. 4.1
Gas Engine We shall consider Cummins GTA855 gas engine. Please refer reply to Sr.No. 2
115
Bid Document,
VOLUME – II OF II Clause
No. 4.11.5
All the pressure, tem perature, lube oil pressure, coolant
temperature, coolant lev el indicators shall be visible from outside
of enclosures.
Cooler level indicator of engine radiator shall not visible from
outide however can be easily check Please refer reply to Sr.No. 76
116
Bid Document,
VOLUME – II OF II Clause
No. 4.11.8
Suitable gradients shall be provided on the enclosure roof f or rain
drainage and to av oid water pockets.
As exhaust silencer will be mounted on top gradients not
considered.Please refer clause no 4.10.7, Page no 14 of 167, Vol II of II of tender document.
117
Bid Document,
VOLUME – II OF II Clause
No. 4.12
Piping
Gas piping/ tubing at 3rd stage discharge will only be in SS-
316, with SS fittings,
Rest all piping /tubing will be Combination of Flanged &
screwed connections with CS material (pipes, Fittings &
Flanges ) as per application requirement & standard design.
This is as per manufacturing standard design.
Instrument Air Tubing will be in SS-304.
Please refer reply to Sr.No. 77
118
Bid Document,
VOLUME – II OF II Clause
No. 4.12.5
The instrument air tubing material shall be SS316 as per ASTM
A269.Impulse air tubing for actuator operation shall be SS-304. Please refer reply to Sr.No. 78
119
Bid Document,
VOLUME – II OF II Clause
No. 4.12.9
External drain & v ent piping shall be Carbon Steel and not less
than 1" nominal sizeExternal drain connection shall be-1/2" Please refer reply to Sr.No. 79
120
Bid Document,
VOLUME – II OF II Clause
No. 4.12.9
Following certificates have to be submitted for piping fabricated at
Site / shopElectrode qualification test results not considered Please refer reply to Sr.No. 80
121 Mkes Pressure Transmitter Please approve GIC Please refer reply to Sr.No. 81
122
Bid Document,
VOLUME – II OF II Clause
No. 5.7.4 & 5.7.15
Electrical instrumentation shall be certified by a recognized
authority such as BASEEFA, PTB, LCIE, CESI, INIEX, CMRS or
any agency approved by Indian Gov ernm ent.
CCOE or its equivalent certificate (FM, CSA , ATEX, UL,
CMRI) whichever applicable & available will be provided.Please refer reply to Sr.No. 82
123
Bid Document,
VOLUME – II OF II Clause
No. 5.7.14
For online Calibration of MFM; Vendor to provide suitable
arrangement to connect Master Mass flow meter (Prover) with
Compressor Suction & Compressor Discharge flow meter for
calibration purpose.
For online calibration of suction MFM loose pipe arrangement
shall be provided and for discharge MFM provision for
calibration shall be available on P&ID
Please refer reply to Sr.No. 83
124
Bid Document,
VOLUME – II OF II Clause
5.7.14
Offered m ass flow m eter shall be necessary f or Custody
Transfer application but not exceeding
0.5% of span. Type of approval certificate from W&M India is
required.
0.5% accuracy considered but custody tranfer application for
suction MFM not consideredPlease refer reply to Sr.No. 84
125
Bid Document,
VOLUME – II OF II Clause
6.4
Pressure and temperature of gas shall be considered at
purchaser’s boundary limit and supplier shall install necessary
pressure and temp measuring devices. Necessary spool piece
shall be provided in discharge tubing of the com pressor. All
instrum ent duly calibrated, tools & tackles, any modification
required f or conducting PT shall be in the scope of supplier.
Pressure and temperature shall be considered at compressor
block suction during performance test.Please refer reply to Sr.No. 85
Page 19 of 20
Sr.no. Clause No./Document No. Page no. Query Description Bidder's Query AGL Reply/Remarks
Corrigendum-1
TENDER NO_AGL/0304/TO/CNG COMPRESOOR/05-19
Techno-commercial Query
HYDROTEST OF-CYLINDER HEADS Not feasible hence not considered
LEAK PROOF T EST OF PRESSURIZED CRANK CASE (4 Hours
wit h k erosene)
Hydrotest for crankacase considered.
Customer inspection not considered as it will lead to major
delivery time adder
ULTRASONIC TEST OF-CRANK SHAFT , CONNECTING ROD.,
PIST ON R O DUltrasonic test for crank shaft not considered
RADIOGRAPH Y AS APPLICABLE-PRESSURE VESSELS, HEAT
EXCHANGER, G AS PIPINGAs welding not involved in heat exchanger
BARRING OVER TO CHECK CYLINDER END CLEARANCE
AND PISTON ROD RUNOUTPiston rod runnot not considered as not feasible to check.
NO LOAD MECHANICAL RUN T EST OF THE COMPR. W IT H
RAT ED (OR MORE) SPEED AND SHOP DRIVER (4 HRS. Minim
um .)
Customer witness not considered
STRIP CHECK AND INTERNAL INSPECTION AFTER " NLMRT"
OF ALL C O MPRESSO RS ; - Routine test c ertif icat e by v
endors
Customer witness not considered
126
This Corrigendum-1 forms an integral part of the Tender Document No.: AGL/0304/TO/CNG COMPRESOOR/05-19 and a copy (duly signed and stamped) of the same is to be submitted along with the Bid.
Please refer reply to Sr.No. 86
Bid Document,
VOLUME – II OF II Clause
20-QAP
Page 20 of 20