October 16, 2018
Tender No. 423/981/17
For Selecting the Project Designer for the Light Railway Project in the
Haifa Metropolitan Area between Haifa and Nazareth
Pursuant to the Invitation to Bid for the tender published on June 28, 2018, Cross Israel
Highway Ltd. (the "Company") hereby publishes the Company’s response for requests to
clarifications that were addressed to it by the Participants in the said Tender. The
Company’s response is attached as Annex "1".
In addition, the Company hereby announces that the Submission Date has been
postponed until November 7, 2018 no later than 16:00 (Israel time).
1. It is hereby clarified that the language of the questions listed below is not necessarily
identical to the language used by those who referred to the Company and that not all
of the questions were necessarily answered by the Company.
2. In addition, some questions may have been asked by more than one Participant, and,
therefore, the company’s response below may refer to one version of the said
questions.
3. This document, including the updates and clarifications appearing herein, constitutes
an integral part of the Tender Documents and must be attached to the Proposal of the
Participant. Each page shall be duly signed by the person duly empowered and
authorized to sign on behalf of the Participant, in accordance with the provisions of
the Tender Documents.
Sincerely,
Cross Israel Highway Company Ltd.
Annex "1"
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the revised Annex “E”.
General Invitation to Bid 1.
The Company is not expected to
hold a conference.
The Company was requested to clarify
whether a conference of Participant will be
convened?
Tender Documents General Invitation to Bid
2.
Participants are required to
check the company's website on
a timely basis. For the
convenience of the Participants,
each updated version of the
Tender Documents shall be
marked as such.
The Company was requested to clarify how
the Participants can tell if a document has
been updated?
Tender Documents General Invitation to Bid
3.
The Company clarifies that the
provision Services is expected to
commence immediately upon
signature of the Project Designer
Agreement and the Management
Tender agreement.
The Company was requested to provide an
approximate date for the commencement of
the provision of the Services.
Schedule 1.5 Invitation to Bid
4.
The request is rejected. The Company was requested to re-publish
all so far published documents (uploaded
on the Company’s website) as well as any
further documents/addenda on English as
well.
Provision of documents
on English
2. Rules and
Procedures
2.9 Language
Invitation to Bid
5.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that
Participants are not required to
include such agreement as part
of their proposals.
According to clause 3.1.4, a JV has to be
created by means of an agreement between
its members. However, it is not clear
whether such agreement should be included
in the proposal, since it is not mentioned in
clause 4.1.2 (contents of Envelope 1).
Please clarify.
Agreement between JV
members
3.General
Provisions
Relating to
Participants
3.1.4
and
4. Contents of
the Proposal
4.1.2 (Envelope
1)
Invitation to Bid
6.
The request is rejected.
Participants’ attention is drawn
to the provisions of Section 1.1
of Annex D”2” (Threshold
Requirements for the Local
Design Firm) to the Invitation to
Bid.
The Company was requested to amend the
Tender Document so that a participant can
be an unincorporated, special purpose JV
made up of two international companies.
Participant requirements 3
3.1
Invitation to Bid
7.
The Company clarifies that the
Participant may present the same
individual as a candidate
covering two different functions,
except for the functions of the
Chief Designer and/or the
Deputy Chief Designer.
In addition, participants’
attention is drawn to the
The Company was requested to clarify
whether the Participant can present the
same individual as a candidate covering
two different positions of those specified
under sections 3.5 - 3.10.
General provisions
relating to Participants
3 Invitation to Bid
8.
Response Clarification/Question Subject Section Document Name No.
amendments to the provisions of
Sections 2.5 of Annex H to the
Agreement.
The request is rejected.
Participants’ attention is drawn
to provision of section 3.11 of
the Invitation to Bid.
The Company was requested to clarify
whether the Local Design Firm may submit
offers with two foreign companies
separately?
Participation 3.1 Invitation to Bid
9.
Participants’ attention is drawn
to the provisions of Annex H
(Office Holders in the Project
Designer) and section 9 of
Annex “B” (The Services) to the
Agreement.
The Company was requested to clarify
whether the bidding only covers the system,
track, rolling stock, operation and
maintenance? Please clarify if there are
civil works which are not covered?
General provisions
relating to Participants
3.2—3.10 Invitation to Bid
10.
Participants’ attention is drawn
to the provisions of Sections
3.5-3.6 of the Agreement.
The Company was requested to clarify the
Project Designer’s responsibility for its own
interpretation of the data and information
which mention in this Section.
Data and information 3.5 Invitation to Bid
11.
The request is rejected.
Participant are required to
strictly follow attach the
provisions of the Invitation to
Bid only as to the content of
their submissions.
we would like to add our methodological
approach to the Quality Proposal as part of
Envelope 3. Please clarify whether this
would be accepted.
Attachments to Envelopes 4.
Invitation to Bid
12.
Participants’ attention is drawn
to the provision of Section 5.4 of
the Invitation to Bid. For the
avoidance of doubt, the
According to the Invitation to Bid (clause
4.1.2), the agreement with its corresponding
appendices should be included in the
proposal and located in Envelope 1.
Signature on the
agreement on behalf the
Project Designer
Project
Designer
Agreement
Project Designer
Agreement
13.
Response Clarification/Question Subject Section Document Name No.
authorized signatory on behalf
of the Participant shall sign the
Agreement.
(a) Should the Agreement be signed and
authenticated or only initialized and
on each page?
(b) who signs the agreement on behalf the
Participant?
Please clarify the above mentioned.
Invitation to
Bid
4.1.2 - Contents
of the Proposal:
General
The request is rejected. The Company was requested to amend the
Tender Documents so that the Project
Designer will be entitled to receive
compensation due to any change of any
applicable law.
legal requirements. 4.2 Invitation to Bid
14.
The Company confirms as
requested.
The Company was requested to confirm
whether documents that are bound with
wire binding could be sign on the first and
last pages.
Signature on binders 5. Method of
Submission
5.4 Signing of
the Proposal
Invitation to Bid
15.
The Company confirms as
requested.
The Company was requested to confirm
that certification of the signatures by a Non-
Israeli attorney will be acceptable.
Signature by an Attorney 5. Method of
Submission
5.5
Authorization
of Signature by
an Attorney
Invitation to Bid
16.
The Company clarifies that
according to section 5.4.3 of the
Invitation to Bid, in the event a
It is not clear how the proposal should be
signed. As per clause 5.4.1 each page has to
be signed and stamped, but as per clause
Signing the proposal 5.4 Signing of
the Proposal
Invitation to Bid
17.
Response Clarification/Question Subject Section Document Name No.
document or set of documents
constituting part of the Proposal
are set in binders, the Participant
is only required to sign the first
and last page of each of the
binders.
5.4.3 only the first and last page should be
signed. Please clarify.
All Tender Forms will be
published at the Company
website as MS - Word version,
locked from editing, except for
the fields required to be filled by
the Participants, prior to
Submission Date.
The Company was requested to provide all
tender forms in doc/docx format in order to
fill them by typing in all required data.
Score allocation tables in
editable format
Clause 5.6.2 of
the Invitation to
Bid
Invitation to Bid
18.
Participants’ attention is drawn
to the following example:
PPSi = [(20% – PPi)/40%] *100
If the proposed discount rate is
eighteen percent (18%) then the
calculation of the PPSi will be
as follow:
PPSi = [(20% – (–18))/40%]
*100
In such case, the PPSi will be
equal 95.
The Company was requested to clarify the
formula to calculate PPi discount/addition
rate
Pricing evaluation 6.5 Invitation to Bid
19.
Response Clarification/Question Subject Section Document Name No.
The Tender Documents remain
unchanged. Participants’
attention is drawn to the
provisions of Sections 8.4. of the
Invitation to Bid.
Any question or clarification
regarding the industrial
cooperation obligation should be
addressed directly to the
Industrial Cooperation Authority
at the Ministry of Economy and
Industry
The Company was requested to confirm
that all the payments made from the Lead
Design Firm to the Local Design Firm will
be considered for the percentage of the
Industrial cooperation commitment of the
JV.
Industrial Cooperation
payments
8.4.6 Invitation to Bid
20.
The request is rejected. The Company was requested to provide
design documents in English.
Reference Design
Documents
Annex “B” Invitation to Bid 21.
Participants are asked to ignore
this document which was
accidentally attached as part of
Annex “B’.
We downloaded all the Reference Design
Documents listed in Annex “B” and found
under INTERURBAN ROADS section a cost
estimate (an EXCEL file in Hebrew) for this
component. However, we failed to locate a
parallel cost estimate for the urban section.
Please clarify whether such an estimate
exists and where it can be derived from.
Cost estimate for urban
roads
Annex B
“Reference
Design
Documents”
Invitation to Bid –
22.
The request is rejected.
The Company was requested to clarify what
is the valid (most recent) source of the costs
assessment for the LRT line in subject?
Costs Estimations Annex “B” Invitation to Bid
23.
Participants’ attention is drawn
to the provisions of Section 3.1
of Annex B (The Services) to
The Company was requested to clarify
whether the Project Designer is authorized
to amend the design criteria during the
Amending the design
criteria
Annex “B” Invitation to Bid
24.
Response Clarification/Question Subject Section Document Name No.
the Agreement. Preliminary Design phase for optimization
or crosschecking purpose?
The Company clarifies that there
are no sections that require the
design of Heavy Railway
Tracks.
The Company was requested to clarify
whether there are any sections that require
the design of Heavy Railway Tracks?
Heavy railway tracks Annex “B” Invitation to Bid
25.
The Company clarifies that
streams must be treated, to the
extent required according to the
provisions of the Tender
Documents and as may be
required by any Relevant
Authorities. Participants’
attention is drawn to the
provisions of National
Infrastructure Plan No. 56. and
Annex “B” (The Services) to the
Agreement, including sections
3.10.5 and 4.2.10. of Annex “B”
(The Services) to the
Agreement.
The Company was requested to clarify
whether it is necessary to treat streams in
the project area?
Streams Annex “B” Invitation to Bid
26.
Participants’ attention is drawn
to Annex “C” (Preliminary
Schedule) to the Agreement.
The Company was requested to clarify the
reference to Annex “C”.
Annex “C” 2.16.1 Invitation to Bid
27.
The Company so clarifies.
For the avoidance of doubt the
length is calculated from end to
We understand that the term rail has the
meaning of track. Please confirm.
Term "rail" Annex D(1):
2.1.1
Annex D(2):
2.1.2
Invitation to Bid
28.
Response Clarification/Question Subject Section Document Name No.
end of the project, regardless of
the number of trucks.
Annex D(3):
2.1.3
Annex D(4):
2.1.3
Annex D(5):
2.1.2.1
Annex D(6):
2.1.3.1
Annex D(8):
2.1.3
Annex E
The Company so clarifies. Forms B”1-8” and C”1-8” as included in
the Tender Documents allow a presentation
of 2-3 projects.
Is it permitted to extend each corresponding
table by appending a copy of it in
continuation of the first one to allow
presentation of more projects than the given
format originally allows?
Threshold and score
allocation tables
Annexes D and
E Threshold
Requirements
and Quality
Proposal
Invitation to Bid
29.
All Tender forms will be
uploaded to the Company’s
website in word format prior to
Submission Date.
We ask you to provide all the forms starting
from Form A1 up to Form D in doc/docx
format in order to fill them by typing in all
required data.
Score allocation tables in
editable format
Annexes D and
E Threshold
and Quality
Proposal
requirements
Clause 5.6.2
Invitation to Bid
30.
The Company clarifies that the
Participants are not required to
The Company was requested to clarify
whether there is a need to list the full
Professional Staff Annex D1-D8 –
Threshold
Invitation to Bid 31.
Response Clarification/Question Subject Section Document Name No.
attach such list to their
proposals.
professional staff as part of the proposal. Requirements
for Core Design
Team
The Company clarifies that the
Participants can present
engineers with certification from
other countries, provided
however that such certificates
are corresponding to the
certificates mentioned under
these annexes.
The Company was requested to clarify
whether it will be possible to present
engineers which holds certification from
other countries in addition to the certificates
that are stated within the threshold
requirements.
Engineer's certificate Annex D1-D8 Invitation to Bid
32.
The request is rejected. The Company was requested to amend the
threshold requirements for the Local Design
Firm.
Threshold Requirements
for the Local Design Firm
Annex “D(1)” Invitation to Bid
33.
The request is rejected.
The Company was requested to amend
clause 2.1.5.2 so it will allows considering
design projects with Detailed or
Preliminary/Final levels as “Design”.
Professional threshold
requirements
Annex D(1) –
2.1.5.2
Invitation to Bid
34.
Participants’ attention is drawn
to the revised Section 2.1.5.10
of Annex D”1” to the invitation
to Bid.
For the avoidance of doubt,
railway systems, such as Tram
or Tram-Train, which comply
with all the provisions of the
definition of the term “Light
The Company was requested to consider
additional railway systems as equivalent to
LRT for the purposes of evaluating the
Participant design experience.
Light Rail Train -
Definition
Annex D”1”:
Section 2.1.5.10
Section 2.1.5.11
Invitation to Bid
35.
Response Clarification/Question Subject Section Document Name No.
Rail Train” shall be deemed
“Light Rail Train” for the
purposes of the threshold
requirements and the quality
proposal.
The term “ENTSI” shall mean:
European Norm (EN) Technical
Specifications for
Interoperability (TSI)
The Company was requested to clarify the
definition of the term ENTSI.
ENTSI Standard Annex “D(1)”
Form B“1”
Invitation to Bid
36.
The request is accepted.
Participants’ attention is drawn
to the revised Section 3 of
Annex D”1” to the invitation to
Bid.
The Company was requested to reduce the
amount of the average annual turnover that
was required from the Lead Design Firm, in
accordance with the provisions of Annex
D”1”.
Annex “D"(1)
Threshold requirements
for the lead design firm
Appendices to
the Invitation to
Bid
Invitation to Bid
37.
The request is rejected. The Company was requested to amend the
Tender Documents so that projects which
were designed for early design will be
acceptable.
Threshold Requirements
for the Local Design Firm
Annex D2-
Threshhold
Requirements
for the local
Design Firm
2.1.3.1
Invitation to Bid
38.
The request is rejected.
The Tender Documents remain
unchanged.
The Company was requested to amend the
Tender Documents so that DB projects
which were prepared and slated for tender
yet not published still acceptable for
threshold requirements?
Threshold Requirements
for the Local Design Firm
Annex D2-
Threshhold
Requirements
for the local
Design Firm
2.1.3.1
Invitation to Bid
39.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the revised Form B“3”.
The Company was requested to confirm
that the Participants must consider the
requirement for 20 years of experience.
Chief Designer
experience
Annex “D(3)”
Form B“3”
Invitation to Bid
40.
The Company clarifies that for
the purposes of the Threshold
Requirements and the Quality
Proposal, the term “Vehicle”
shall mean a single train unit
capable of operating as a service
train.
The Company was requested to define what
type of vehicles will be accepted for with
respect to the requirement to present a
project which included a fleet of 20
vehicles.
Rolling Stock Annex D6 -
Threshold
Requirements
for Systems
Engineer
Invitation to Bid
41.
The Company clarifies that this
condition listed under Annex
D”6” because the System
Engineer has interfaces with the
vehicles.
The Tender Documents remain
unchanged.
The Company was requested to clarify why
this condition listed here and not just with
the Rolling Stock Engineer.
Rolling Stock Annex D6 -
Threshold
Requirements
for Systems
Engineer
Invitation to Bid
42.
The term “Vehicle” shall mean:
a single train unit capable of
operating as a service train.
The Company was requested to clarify the
meaning of the term “vehicle” for the
Project.
Rolling Stock Engineer
Requirements
Annex “E” Invitation to Bid
43.
The request is rejected. The Company was requested to add "Small
Project" to the scoring of the Deputy Chief
Designer.
3. Content and Criteria for
scoring the Quality
Proposals
3.1. The Lead Design
Firm
Annex “E”
Invitation to Bid
44.
Response Clarification/Question Subject Section Document Name No.
The request is rejected. The Company was requested to amend the
Tender Document so that railway stations
projects will be accepted for points.
The Quality Proposal for
Local Design Firm
Annex E-
Quality
Proposal - 3.2
Invitation to Bid
45.
The request is rejected. The Company was requested to amend the
Tender Document so that points will be
allocated to projects which are less than
6km in length.
The Quality Proposal for
Local Design Firm
Annex E-
Quality
Proposal - 3.2
Invitation to Bid
46.
The request is rejected. The Company was requested to amend the
Tender Document so that BRT projects will
be acceptable for points
The Quality Proposal for
Local Design Firm
Annex E-
Quality
Proposal - 3.2
Invitation to Bid
47.
Participants’ attention is drawn
to the revised Annex “E” to the
Invitation to Bid.
The Company was requested to provide a
breakdown of the evaluation score of the
interview.
Interview Score Annex “E”
Section 3.9
Invitation to Bid
48.
The request is rejected.
The Company was requested to amend the
tender documents so that it will be allowed
to repeat the same references for different
Key Staff members both in the Threshold
and Quality proposal forms
Quality Proposal Projects Annex E
2. “Display of
the Data”
Invitation to Bid
49.
The Company so confirms.
The Company was requested to confirm
that it is possible to use the same set of
references presented for example for one
Key Expert for the purposes of the
Thresholds Requirements and for the other
Key Expert for the purposes of the Quality
Proposal evaluations (while his set of
Quality Proposal Projects Annex E
2. “Display of
the Data”
Invitation to Bid
50.
Response Clarification/Question Subject Section Document Name No.
references for the Thresholds differs)?
The Company clarifies that the
methodology should be specific
for the Project.
According to the provisions of Annex “E”
is it expected to present the “methodology
for shortening the time for completion” as a
case study (e.g. as a presentation in ppt
format) based on the Participant’s
experience and references or as a general
approach for the assignment in subject?
Interview Annex E
3.9. Interview
3.9.8 + 3.9.9
Invitation to Bid
51.
Any question or clarification
regarding the industrial
cooperation obligation should be
addressed directly to the
Industrial Cooperation Authority
at the Ministry of Economy and
Industry
The Company was requested to clarify
which kind of guarantee shall be issued as
the additional Instrument Guarantee for the
implementation of the Binding Undertaking
in case is requested by ICA.
Industrial Cooperation Annex “F” Invitation to Bid
52.
Any question or clarification
regarding the industrial
cooperation obligation should be
addressed directly to the
Industrial Cooperation Authority
at the Ministry of Economy and
Industry
There is a requirement for foreign suppliers
to engage local subcontractor. We
understand that by incorporating a local
Israeli design firm in our JV in the
approximate share of the contract value of
49%, we fulfill the requirements as
stipulated in the aforementioned Annex F.
Please confirm and/ or comment.
Engagement of local
subcontractors by foreign
suppliers
Annex “F” -
ICA Appendix
Item 1
Invitation to Bid
53.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that said
forms should be signed by the
authorized signatory of the Lead
Design Firm.
It is not clear who should sign the required
forms in the name of the Participant:
(a) The Authorized Representative
nominated as per Form A”2”.
(b) An authorized signatory of the Lead
Design Firm.
Please clarify the above mentioned.
Signatory / Signatories Invitation forms Invitation to Bid
54.
The Company clarifies that
Participants should attach the
required attachments (as
applicable) as detailed under the
Invitation to Bid.
The Company was requested to clarify the
necessity of the “attachments”.
Meaning of the term
“attachments”
Forms B and C
for the
Threshold and
Quality
Proposal
3.
Miscellaneous
Invitation to Bid
55.
Participants’ attention is drawn
to the amended Tender Forms.
The Company was requested to clarify
whether it would be possible for the
Authorized Representative to sign this
document instead of the CEO or the CFO?
Threshold Requirements
for the Lead Design Firm
Invitation Form
B “1”
Invitation to Bid
56.
Participants’ attention is drawn
to the revised Form B”4” to the
Invitation to Bid.
The Company was requested to clarify
whether the Deputy Chief Designer may be
employed by the Local Design Firm or
entered into agreement with the Local
Design Firm.
Threshold conditions for
the Deputy Chief
Designer
Form B“4” - 1.4 Invitation to Bid
57.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that the
table can be appended in
continuation.
The table included in the Quality Proposal
Form for the Lead Design Firm experience
limits presentation of the experience to
three projects only. However, section 3.1.4
quotes that the score “…shall not exceed 17
points.”
Can the table be appended in continuation?
Reaching full score of
17%
Form C”1”
Invitation to Bid
58.
The Company clarifies that such
hard copies, printing and
binding of documents, report,
drawings are included in the
Contract Price.
Please confirm that all hard copies, printing
and binding of documents, report, drawings
etc. for submissions, coordination, and
permitting of works, surveys or buildings
are excluded from the Project Designer’s
price proposal.
Printing & Hard-copies From “D” Invitation to Bid
59.
The attention of all Participant is
drawn to the provisions of
Section 2.15 of the Invitation to
Bid.
Is the price based on the design drawings in
annex B to the Invitation to Bid?
design drawings Form D Invitation to Bid
60.
With respect to the (i) - the
Company so clarifies.
With respect to (ii) - the
Company clarifies that
translation costs will not be
reimbursed. Participants’
attention is drawn to the
provision of Section 2.4 of
Annex B (The Services) to the
Agreement.
The Company was requested to clarify (i)
whether the Project Designer will be
responsible for obtaining all the data,
information, drawings and documents that
may be required for the performance of the
Services and (ii) whether translations cost
for obtained documents will be reimbursed.
Gathering of data /
Translations
General
Project Designer
Agreement
61.
Response Clarification/Question Subject Section Document Name No.
The Company so clarifies.
The Company was requested to clarify
whether the National Infrastructure Plan
No. 56 was approved and published.
Statutory Plan Status General
Project Designer
Agreement 62.
Participants’ attention is drawn
to the provisions of the revised
Section 2.4.1 of the
Agreement.
According to this clause the Project
Designer is requested to confirm within 30
days following Signature Date that it has
obtained all Approvals, including working
permits. According to our experience it
takes as a minimum 90 days to obtain a
working permit. Therefore, please consider
to either exclude working permits from
such requirement or to extend the period to
120 days following signature date.
Obtainment of Approvals 2.4.1
Project Designer
Agreement
63.
The Company clarifies that these
approvals are required for the
provision of the Services only.
The Company was requested to confirm
that approvals referred to in this clause and
would not include such approvals, consents
or permits which may have to be requested
and obtained as part of the Services.
Obtainment of Approvals 2.4.1
Project Designer
Agreement
64.
The request is rejected.
The Company was requested to amend the
provisions so that to the extent changes in
law result in additional cost for the Project
Designer the Project Designer it will be
entitled to receive respective compensation.
Changes in law 4.2
Project Designer
Agreement
65.
Response Clarification/Question Subject Section Document Name No.
The request is rejected.
Participants’ attention is drawn
to the provisions of Section 9.5
of Annex “B” (The Services) to
the Agreement.
The Company was requested to add a
Company’s obligation to provide response
to any submission of material or request
from the Project Designer within 14
calendar days of the presented issue.
Company response time
to submissions
5 Project Designer
Agreement
66.
The request is rejected. The Company was requested to specify
justified circumstances for replacement of
Team Members
Justified circumstances
for replacement of team
members
6. Team
Members
6.4.
Replacement of
Team members
Project Designer
Agreement
67.
Participants’ attention is drawn
to the provisions of Section 5.2
of Annex B (The Services) to
the Agreement.
The Company was requested to clarify what
will be the Company’s timeline for reviews
comments and consideration of documents
submitted by the Project Designer
We did not find any
timeline for such reviews
comments and
consideration in the
contract documents.
68. The
Services'
Concept,
Scope and
Schedule
7.2. Scope of
Services
Project Designer
Agreement
69.
Participants’ attention is drawn
to the amendments to the
provisions of Section 8.2.3 of
the Agreement.
The Company was requested to clarify the
time period within which the company is
willing to give a first answer?
Time period for
company’s answer in
8.2.3 following
preliminary estimate from
the project designer.
8. Prerogatives
of the Company
and Variation
8.2. Variation
Project Designer
Agreement
70.
Response Clarification/Question Subject Section Document Name No.
The request is rejected. The Company was requested to clarify what
are the circumstances upon the Company
will be entitled to exercise its right in
accordance with the provision of section 8.3
of the Agreement.
Rate of Progress 8. Prerogatives
of the Company
and Variation
8.3. Rate of
Progress
Project Designer
Agreement
71.
The Company clarifies that
Section 8.2.3 refers to
Preliminary Estimate while
Section 8.2.4 refers to an
Amended Estimate.
In clause 8.2.3 it is mentioned that the
Project Designer is to provide response to
variation within 21 days while in clause
8.2.4 it is intentioned 5 days.
Please explain.
Response time to
variations
8.2.4-8.2.3 Project Designer
Agreement
72.
Participants’ attention is drawn
to the amendments to the
provisions of Section 9 of the
Agreement.
The Company was requested to clarify the
provision of Section 9.2. of the Agreement.
Project Designer’s
Liability
9. Project
Designer’s
Liability
9.2. Damages or
loss
Project Designer
Agreement
73.
Participants’ attention is drawn
to the amendments to the
provisions of Section 9 of the
Agreement.
The Company was requested to clarify
whether there is any limit to the Project
Designer’s contractual liability.
Project Designer’s
Liability
9 Project Designer
Agreement 74.
Participants’ attention is drawn
to the amendments to the
provisions of Section 9 of the
Agreement.
The Company was requested to clarify
whether the Project Designer’s contractual
liability will be limited to direct damages or
otherwise the Project Designer shall also be
liable to the Company for loss of profit and/
or indirect or consequential damages.
Project Designer’s
Liability related to 16.7.3
9 Project Designer
Agreement
75.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the amendments to the
provisions of Section 9 of the
Agreement.
The Company was requested to add at the
end of the paragraph the following
provision:
"The Company is obliged to notify the
Project Designer promptly following such
claim being made and to permit the Project
Designer to defend itself against it".
Project Designer’s
Liability
9.2 Project Designer
Agreement
76.
Participants’ attention is drawn
to the amendments to the
provisions of Section 1.5.5 of
Annex D (Service Price) to the
Agreement.
The Company was requested to clarify
whether each member of the Joint Venture
will be allowed to submit an invoice
separately and to be paid separately in the
event the Contract is awarded to an (un-
incorporated) Joint Venture.
Invoice 11. Project Designer
Agreement
77.
Participants’ attention is drawn
to the provisions of Section
1.5.5 of Annex D (Service Price)
to the Agreement.
The Company was requested to confirm
that all the payments to the Project
Designer, shall be invoiced by the Lead
Design Firm in case of JV.
Payments to the JV 11 Project Designer
Agreement 78.
The Company clarify that there
is no limitation on the amounts
of liquidated damages according
to Section 12 of the Agreement.
The Company was requested to clarify
whether there is any limitation on the
amount of liquidated damages applicable to
the Project Designer.
Liquidated damages 11 Project Designer
Agreement 79.
Participants’ attention is drawn
to the provision of section 11.3
of the Agreement.
The Company was requested to clarify the
conditions for the release of the Retention
Amount.
Payment 11.3 Project Designer
Agreement 80.
The Company so confirms. It is assumed that the requirement to furnish
the Company with Letters of Undertaking
Non-Conflict of Interest
Undertaking
14.2
Project Designer
Agreement 81.
Response Clarification/Question Subject Section Document Name No.
from employees prior to their employment
only applies to such employees which
might be employed by the Project Designer
after contract award but not the ones
employed already at the time of contract
award.
Please confirm.
The request is rejected. The Company was requested to clarify the
compensation mechanisms (if any)
according to section 15.4. of the Agreement
Prior notice periods 15. Suspension Project Designer
Agreement 82.
The Company clarifies that no
inconsistence was found in the
Tender Documents, and that the
information in Figure 9 is
correct.
The Company was requested to provide a
list of stops included in the project because
to the opinion of the participant there is
some inconsistencies in the number and
names of stops along the alignment
Figure 9 - Stops in the
Project
Annex B Project Designer
Agreement
83.
The Company clarifies that the
Project Designer will be
required to prepare its design
based on the existing conditions,
provided, however, that any
modifications or adjustments to
the design prepared by the
Project Designer due to the
Hamovil Intersection design
and/or construction or any
additional coordination required,
are included in the Scope of
The Company was requested to clarify what
is required from the Project Designer in
Hamovil Intersection, in order to ensure full
separation between LRT and road,
including the required road infrastructure
design and the utilities design of the main
water line of Israel (המוביל הארצי).
HaMovil Intersection Annex B Project Designer
Agreement
84.
Response Clarification/Question Subject Section Document Name No.
Work without any entitlement to
adjustment of the Service Price
or the Project schedule.
The Tender Documents remain
unchanged.
The attention of all Participant is
drawn to the provisions of
Section 2.15 of the Invitation to
Bid and Section 3.6.2.5 of
Annex B (The Services) to the
Agreement.
The Company was requested to clarify the
lack of voltage level and connection style of
the Medium-voltage network.
preliminary design files Annex B Project Designer
Agreement
85.
Participants’ attention is drawn
to the provisions of Annex “B”
(The Services) to the
Agreement.
The Company was requested to clarify
which type of supercapacitor will be
adopted for vehicle?
Track Annex B Project Designer
Agreement
86.
The request is rejected. The Company was requested to amend the
Tender Document so that Chinese standards
may be adopted for the design.
Track Annex B Project Designer
Agreement
87.
Participants’ attention is drawn
to the provisions of section 3.1
and 3.4.7 Annex “B” (The
Services) to the Agreement.
Please make clear the bid stage of the
project. Whether the station site of the line
and the vehicle system standard have been
determined?
Please make clear the design standard for
station architecture and the problems on
drawing file standard.
preliminary design files Annex B Project Designer
Agreement
88.
Response Clarification/Question Subject Section Document Name No.
The Tender Documents remain
unchanged.
The attention of all Participant is
drawn to the provisions of
Section 2.15 of the Invitation to
Bid and Annex B (The Services)
to the Agreement.
The following basic information is not
provided
1. Train grouping, motor car weight,
trailer car weight, passenger-
carrying weight, maximum
operating speed of train, traveling
speed of train, unit power
consumption of train, maximum
starting current of train, capacity of
auxiliary power supply, maximum
acceleration and maximum braking
acceleration.
2. Information about traction
calculation:Traction - speed
curve, braking force - speed curve,
traction current - speed curve,
braking current - speed curve and
train resistance formula.
preliminary design files Annex B Project Designer
Agreement
89.
Participants’ attention is drawn
to the amended Section 2.4. of
Annex “B” (The Services) to the
Agreement.
Does the Company supply the mentioned
information or is the Project Designer
required to perform it?
Topographic, Cadaster
and Utilities survey
Annex B Project Designer
Agreement
90.
Participants’ attention is drawn
to the provisions of the Price
Matrix under Annex “D”
(Service Price) to the
In the provided drawings this section is
shown as at Grade level. Please clarify that
should this section be required to be
designed as an underground section, it shall
Road 781 Annex B Project Designer
Agreement
91.
Response Clarification/Question Subject Section Document Name No.
Agreement.
The Company clarifies that the
main road will be at grade level,
while connections and under
paths may be underground. In
such case, the Project Designer
will be entitled to receive
compensation based on the price
for such design, as detailed
under the Price Matrix.
be subject to a variation order to the Project
Designer.
The Company clarifies that the
term permit refers, inter alia, to
both building permits and
authorization permits.
Participants’ attention is drawn
to the provisions of sections
2.4.5, 4.2.2 and 4.3.4 of Annex
“B” (The Services) to the
Agreement.
Please clarify if the permit required will be
a Building Permit )היתר בניה( or an
Authorization Permit )הרשאה למבני דרך(
Building Permit and
Building Authorization
Annex B Project Designer
Agreement
92.
Participants’ attention is drawn
to the amended Section 3.2. of
Annex “B” (The Services) to the
Agreement.
In case of a need to relocate Major Utilities
such as: Super High Voltage of IEC,
Mekorot water pipes, National Water line,
Gas Lines, Petrol Lines we request your
clarification that the cost and consequences
of such major event including the design of
the change, shall not be within the Project
Designer responsibility.
Major Utilities Annex B Project Designer
Agreement
93.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the map that was attached to
the Invitation to Bid as part of
Annex B (Reference Design
Documents) to the Invitation to
Bid.
The Company was requested to clarify the
limits of the Project's lateral design (the
width) and to provide updated plans and
files of the design area.
Road 781 Annex B Project Designer
Agreement
94.
The request is rejected.
The Company was requested to provide a
full list of adjacent works and projects not
in the LRT strip.
Adjacent Projects
Annex B Project Designer
Agreement
95.
The Company clarifies that the
Project Designer will be
required to prepare its design
based on the existing conditions,
provided, however, that any
modifications or adjustments to
the design prepared by the
Project Designer due to the
Somech Intersection design
and/or construction or any
additional coordination required,
are included in the Scope of
Work without any entitlement to
adjustment of the Service Price
or the Project schedule.
The Company was requested to clarify to
which design will the LRT be integrated to.
To the opinion of the participant, the
clarification is required because in the
current stage there are two junctions in this
section and the future design includes a full
intersection with ramps.
Somech Intersection Annex B Project Designer
Agreement
96.
The Company clarifies that the
part of Taufik Ziad street that is
partly covered is included in the
The Company was requested to advise
whether the Taufik Ziad street in Nazareth
is included in the SoW or not.
Taufik Ziad Street Annex B Project Designer
Agreement
97.
Response Clarification/Question Subject Section Document Name No.
Project Designer Scope of
Work, in accordance with the
provisions of Annex B (The
Services).
The Company clarifies that
Yiftachel Intersection is
designed by a third party and
therefore the Company has no
further information on said
works.
Without this being an
undertaking by the Company,
Yiftachel Intersection is
intended to be executed on a
parallel schedule with the
project.
If Yiftachel Intersection will not
execute on time and such non-
execution will require additional
design, such design will be
included within the Project
Designer Scope of Work
without any entitlement to
adjustment of the Service Price
or the Project schedule.
The Company was requested to clarify the
construction schedule of the Yiftachel
Intersection in 784 roads, and whether the
loop designed in the HaMovil Intersection
is part of the SoW.
Road 784 & Yiftachel
Intersection
Annex B Project Designer
Agreement
98.
Response Clarification/Question Subject Section Document Name No.
With respect to the loop in
HaMovil Intersection, the design
of the loop is not included
within the Project Designer
Scope of Work.
The Company clarifies that in
any case where the issuance of
permits will be required by the
Relevant Authorities, the Project
Designer will be responsible to
obtain such permits.
The Company was requested to clarify
whether an EMC permitting would be
required for the TTRs and/or any other
elements in the project.
EMC/EMI Permitting Annex B Project Designer
Agreement
99.
The request is rejected.
The Company clarifies that this
task is included within the
Project Designer Scope of
Work.
The Company was requested to provide all
drainage plans of the project.
Drainage Drawings Annex B Project Designer
Agreement
100.
The Company clarifies that the
Project Designer will be
required to design the LRT
according to the existing
conditions.
The Company was requested to clarify to
which stage will the LRT be designed
within Somech Intersection, as part of the
Project Designer's Scope of Work.
Somech Intersection Annex B Project Designer
Agreement
101.
The Company clarifies that
green construction will be
implemented. The green
construction elements to be
taken into account as part of the
design will be determined by the
Company, at a later stage.
The Company was requested to clarify
whether green construction elements such
as micro climate will be taken into
consideration for LRT stop design?
Green construction
elements
Annex B Project Designer
Agreement
102.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
section 3.1. of Annex “B” (The
Services) to the Agreement.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
Annex “B” (The Services) to the
Agreement, including section
3.4.7. of Annex “B” (The
Services) to the Agreement.
The Company was requested to clarify
whether there is a requirement for “park
and ride” parking lots along the LRT’s
route?
Park and ride Annex B Project Designer
Agreement
103.
The Company clarifies that the
final location of TTR structures
will be determined by the
Company and will be considered
as included in the Project
Designer scope of work without
any entitlement to adjustment of
the Service Price or the Project
schedule.
Participants’ attention is drawn
to the Company response to the
request for clarification number
218 below and to the provisions
of National Infrastructure Plan
TATAL plans has Technical Structures
symbol but it is unclear whether the
TATAL allows implementing of those on
the relevant area cells.
TATAL Annex B Project Designer
Agreement
104.
Response Clarification/Question Subject Section Document Name No.
No. 56. and Annex “B” (The
Services) to the Agreement
including, section 3.6.2. of
Annex “B” (The Services) to the
Agreement.
The Company clarifies that the
final typical of the TTR
structure will be determined by
the Company and will be
considered as included in the
Project Designer scope of work
without any entitlement to
adjustment of the Service Price
or the Project schedule.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
Annex “B” (The Services) to the
Agreement, including section
3.3.3. of Annex “B” (The
Services) to the Agreement.
The Company was requested to clarify if
there are plans for typical TTR structure?
TTR structure Annex B Project Designer
Agreement
105.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
Annex “B” (The Services) to the
Agreement, including section
4.2.29. of Annex “B” (The
The Company was requested to clarify
whether there is a requirement for planning
traffic lights electronic systems?
Traffic lights electronic
systems
Annex B Project Designer
Agreement
106.
Response Clarification/Question Subject Section Document Name No.
Services) to the Agreement.
The final determination
regarding the requirement for
the design of security and safety
cameras along the LRT’s route
will be determined by the
Company and will be considered
as included in the Project
Designer scope of work without
any entitlement to adjustment of
the Service Price or the Project
schedule.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
of Annex “B” (The Services) to
the Agreement, including
sections 3.6.5. and 4.2.32 of
Annex “B” (The Services) to the
Agreement.
The Company was requested to clarify
whether there is a requirement for planning
security and safety cameras along LRT’s
route?
Security and safety
cameras
Annex B Project Designer
Agreement
107.
Response Clarification/Question Subject Section Document Name No.
The final determination
regarding the requirement for
the design of special elements
due to electromagnetic current
will be determined by the
Company and will be considered
as included in the Project
Designer scope of work without
any entitlement to adjustment of
the Service Price or the Project
schedule.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
sections 3.6.2.-5.2.3. of Annex
“B” (The Services) to the
Agreement.
The Company was requested to clarify
whether there is a requirement for planning
special elements due to electromagnetic
current?
Electromagnetic current Annex B Project Designer
Agreement
108.
The Company clarifies that the
final determination regarding the
requirement for the design of
active or passive mechanism to
prevent stray currents will be
determined by the Company and
will be considered as included in
the Project Designer scope of
work without any entitlement to
adjustment of the Service Price
The Company was requested to clarify
whether there is a requirement for design an
active or passive mechanism to prevent
stray currents?
Active or passive
mechanism to prevent
stray currents
Annex B Project Designer
Agreement
109.
Response Clarification/Question Subject Section Document Name No.
or the Project schedule.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
section 5.2.3. of Annex “B”
(The Services) to the
Agreement.
The Company clarifies that the
there is a requirement for the
design of traffic impact plans.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
Annex “B” (The Services) to the
Agreement, including section
3.5. of Annex “B” (The
Services) to the Agreement.
The Company was requested to clarify
whether there is a requirement for traffic
impact planning?
Traffic impact planning Annex B Project Designer
Agreement
110.
The Project Designer must
provide any Person who will be
required for the provisions of the
Services, without any
entitlement to adjustment of the
Service Price or the Project
schedule, all as specified under
the Tender Documents.
The Company was requested to clarify the
content of the consultants required for the
project.
Staff Annex B Project Designer
Agreement
111.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
Annex “B” (The Services) to the
Agreement, including sections
3.2. and 4.2.19-4.2.25 of Annex
“B” (The Services) to the
Agreement.
The Company was requested to clarify
whether there are any gas and fuel utilities
on the project and if there is a requirement
to relocate/place HHV grids?
Basic planning
information
Annex B Project Designer
Agreement
112.
The Company clarifies that it
shall not provide any additional
background information or
surveys and reports.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
sections 2.4.5., 3.4. and 4.2.4.-
4.2.6. of Annex “B” (The
Services) to the Agreement.
The Company was requested to clarify
whether it shall provide the required
background materials such as detailed
survey, utilities detection, hydrology report,
structure survey, traffic and passengers
predictions etc.
Basic planning
information
Annex B Project Designer
Agreement
113.
The Company clarifies that as of
this date, said documents do not
exist. Participants’ attention is
drawn to the provisions of
section 3.4. of Annex “B” (The
Services) to the Agreement.
The Company was requested to clarify
whether there is a DSM Document for LRT
planning specified for the project’s rolling
stock?
Content Annex B Project Designer
Agreement
114.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the provisions of National
Infrastructure Plan No. 56. and
Annex “B” (The Services) to the
Agreement, including sections
3.3.3.-3.4.7. of Annex “B” (The
Services) to the Agreement.
For the avoidance of doubt, the
final structure will be
determined by the Company and
will be considered as included in
the Project Designer scope of
work without any entitlement to
adjustment of the Service Price
or the Project schedule.
The Company was requested to clarify
whether there is a typical structure for
Urban / InterUrban LRT stations?
typical structure for
Urban / InterUrban LRT
stations
Annex B Project Designer
Agreement
115.
Participants’ attention is drawn
to the provisions of Section 2.4.
of Annex “B” (The Services) to
the Agreement.
The Company was requested to clarify
whether the borders of the design are the
Blue Line of the TATAL 56 Statutory Plan
Border of design Annex B Project Designer
Agreement
116.
The Company clarifies that the
Project Designer will be
required to perform all the tasks
specified under the provisions of
section 8 of Annex “B” (The
Services) to the Agreement
throughout the Agreement
In Annex B of the Scope of Work for Infra
2, tasks for the Supreme Supervision
package include the following:
review and approval of the
detailed design of the PPP
Contractor’s Designer,
CSD’s and SEM’s,
Payments to the Project
Designer, the documents
do not match to each
other
Annex B
Cost
assessment, 5.
Transport
System
Investment
Project Designer
Agreement
117.
Response Clarification/Question Subject Section Document Name No.
Period.
The Project Designer will be
required to do supreme
supervision only over execution
of works the design components
at a Detailed Design level
prepared thereby.
which is substantially bigger part and
workload required in comparison to the
INFRA 1 Supreme Supervision Works.
In our understanding the review and
approval of the PPP Contractor’s Design
should be done by the Independent
Checking Engineer and preparation of the
final CSDs and SEMs for the Final Design
should be also done by the PPP Contractors
Designer (checked and approved by the On-
Site Supervision).
Costs
Annex D,
Service Price,
Price Matrix
The Project Designer will be
required to do supreme
supervision only over the design
components at a Detailed
Design level prepared thereby.
In the Price Matrix Supreme Supervision
for INFRA 1 and for INFRA 2 tasks both
show approximately the same percentage
(12,10 % vs 12,90% respectively).
According the cost assessments pdf
document: the investment cost for the
systems (Infra 2) are much higher than the
costs for civil structures (Infra 1).
Taking a cognizance of the above stated,
efforts and workload for the
implementation of the systems should be
also reflected as such in the Price Matrix
under the Supreme Supervision parts:
percentage of the INFRA 2 part should be
higher in comparison to the INFRA 1
(amounting still in total to ca.25%).
Payments to the Project
Designer, the documents
do not match to each
other
Annex B
Cost
assessment, 5.
Transport
System
Investment
Costs
Annex D,
Service Price,
Price Matrix
Project Designer
Agreement
118.
Response Clarification/Question Subject Section Document Name No.
The Project Designer will be
required to do supreme
supervision only over the design
components at a Detailed
Design level prepared thereby.
The cost assessment shows an allocation
ratio of the investment cost of 1 (Infra 1) to
4,7 (Infra 2) for the basic scenario without
take into account the cost for the rolling
stock.
In our assumption Infra 1 includes
surfacing, civil works for stations and
buildings, utilities, road and parking areas
for the depot. This ratio is not reflected in
the Price Matrix / or nor in costs
assumption (cross-checked).
Please clarify and/or comment accordingly.
Payments to the Project
Designer, the documents
do not match to each
other
Annex B
Cost
assessment, 5.
Transport
System
Investment
Costs
Annex D,
Service Price,
Price Matrix
Project Designer
Agreement
119.
The Project Designer will be
required to make an updated
estimate of the quantities and
prices for its design.
Costs estimation given in the file name
“Cost assessment.pdf” (page 8) are based
on assumptions which for us are not
retraceable. See the example below and the
taken costs assumptions:
Please advise what cost estimate values
should be considered by the participant and
explain their input assumptions.
Costs estimations from
various sources do not
match to each other
Annex B
Cost
assessment, 5.
Transport
System
Investment
Costs
Annex D,
Service Price,
Price Matrix
Project Designer
Agreement
120.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the provisions of the Price
Matrix (Annex “D” to the
Agreement) and to the
provisions of Section 4.2. of
Annex “B” (The Services) to the
Agreement.
Does the scope of work include Priority
Traffic Lights? If yes, how many?
Priority Traffic Lights Annex B Project Designer
Agreement
121.
The Company clarifies that it
will contract with drilling
contractors at its own expense.
Participants’ attention is drawn
to the provisions of Section
2.4.10 of Annex “B” (The
Services) to the Agreement.
The Company was requested to clarify
whether the drilling contractor is hired and
paid by the Company and what is the scope
of the Project Designer.
Soil Investigation and
Drilling boreholes
Annex B Project Designer
Agreement
122.
The Company clarifies that there
is no definite division.
Participants’ attention is drawn
to the provisions of Annex B
and Annex H to the Agreement.
The Company was requested to clarify
whether there are any requirements or
descriptions of how the tasks listed in the
scope of works should be divided between
the Lead Design Company and the Local
Design Firm.
Division of Tasks
between the Lead Design
Firm and the Local Firm
Annex B Project Designer
Agreement
123.
Participants’ attention is drawn
to provision of section 1.10 of
Annex B (The Services) to the
Agreement.
The Company was requested to clarify the
scope of works at each station.
Design works at Stations Annex B Project Designer
Agreement
124.
Participants’ attention is drawn
to provision of sections 3.4.1
and 4.2.4 of Annex B (The
The Company was requested to clarify
whether there will be a need to make
orthophotos (aerial photographs) for the
Orthophoto Annex B Project Designer
Agreement
125.
Response Clarification/Question Subject Section Document Name No.
Services) to the Agreement. work and if so at the expense of the Project
Designer or at the expense of the Company.
The Company clarifies that it
shall not pay the expenses for
copies, preparation of plans,
presentations and drawings that
are required for the purpose of
promoting coordination of the
design and its various stages
between the Project Designer
and its sub- designers.
However, the Company shall
pay for Copies, preparation of
plans and drawings that are
intended for the use of the
Company or any person acting
on its behalf, provided that the
Project Designer has performed
the required work through the
Company’s service provider for
this purpose.
The Company was requested to clarify
whether the printing costs for drawings and
reports are at the expense of the Project
Designer or at the expense of the Company.
Copies/Printing Costs Annex B Project Designer
Agreement
126.
The Company clarifies that there
is no Depot in Nazareth.
We could not find drawings and
information concerning the Depot marked
in Nazareth, as was provided for the Depot
in Kyriat Ata. Is Nazareth Depot included
in the scope of work?
Nazareth Depot Annex B Project Designer
Agreement
127.
Response Clarification/Question Subject Section Document Name No.
The request is rejected.
Participants’ attention is drawn
to the Tender Documents,
including Annex B (The
Services) to the Agreement.
The Company was requested to provide
more data regarding the scope of work for:
1) Bridge works
2) Tunneling works
3) Road Works
4) Traffic Design
Details regarding scope of
work
Annex B Project Designer
Agreement
128.
The request is rejected. The Company was requested to provide a
specified list of the design elements such as
buildings, technical rooms and other
buildings types, parking lots and terminals.
List of design elements Annex B Project Designer
Agreement
129.
The Company clarifies that the
design will be signed by Israeli
qualified professionals
(including engineers), as
required under applicable law.
The Company was requested to clarify
whether the design need to be signed by an
Israeli authorized designer?
Details regarding scope of
work
Annex B Project Designer
Agreement
130.
The Company will be
responsible to respond to third
party requests, while the Project
Designer will provide the
information and input to the
Company as required so to
enable the Company to respond,
according to the provisions of
Section 2.4.1. of Annex “B”
(The Services) to the
Agreement.
A lot of development and designs of
adjacent and crossing projects and utilities
are expected. The extent and intensity are
not known. We request that response to any
requests of such interested parties shall be
given by the Company and if the Project
Designer inputs are necessary, those will be
recognized as tasks outside the scope of
design work.
Adjacent and crossing
projects
Annex B Project Designer
Agreement
131.
Response Clarification/Question Subject Section Document Name No.
It is clarified that all deliverables
must meet all the requirements
of the applicable laws, standards
and criteria set for the Project,
including the signature by Israeli
qualified professionals
(including engineers), where
required under applicable law.
Participants’ attention is drawn
to the provisions of Annex “B”
(The Services) to the
Agreement.
Do design documents submitted by foreign
consultants need to meet Israeli Standards?
Is the Local Design Company responsible
for the submission and approval of design
documents submitted by foreign
consultants?
Foreign Consultant
Submissions
Annex B Project Designer
Agreement
132.
The design of the vehicle is one
of the Project Designer’s tasks.
The Company was requested to clarify
whether the LRT vehicle layout will be a
double-unit vehicle or it will be only
defined as a result of the Preliminary
Design?
Vehicle layout Annex B - 1.4.3 Project Designer
Agreement
133.
The Company clarifies that at
this stage it has no additional
information with respect to the
high level of passengers entering
the LRT system at the Reineh-
Mashad station/stop. Additional
information will be provided to
the Project Designer at a later
stage, during the Agreement
In relation to the Figure 7 (page 11) there is
no explanation provided for the high level
of passengers entering the LRT system at
the Reineh-Mashad station/stop (increment
of the passenger numbers from that station).
The Company was requested to clarify the
above described issue.
Figure 7 Annex B - 1.8.
Project Designer
Agreement
134.
Response Clarification/Question Subject Section Document Name No.
Period.
Participants’ attention is drawn
to the provisions of Section 2.15
of the Invitation to Bid.
The Company so clarifies. Please confirm that AB Traffic Model (of
Yefe-Nof) will be made available to the
Successful Participant (to be contracted as
the Project Designer).
AB Traffic Model (by
Yefe Nof) + demand flow
analysis results
Annex B – 1.8.
Project Designer
Agreement 135.
The Company clarifies that one
of the Project Designer’s tasks is
to suggest the type of signaling
system or elements to be used in
the different sections. The
Company will make its
determination at a later stage
during the Agreement Period.
The Company was requested to indicate the
type of signaling system/elements to be
used (LOSD, ATP/ATO/ATS, AVLS etc.)
in the different sections (inter-urban/urban)
and/or elements (AG, tunnels, etc.).
Signaling System Annex B - 1.9.1 Project Designer
Agreement
136.
The Company clarifies that the
Project Designer will be
required to provide the
Company with all the tasks
mentioned in the request for
clarification.
The Company was requested to clarify what
will be required from the Project Designer
in terms of tunnels, including:
a) Tunnel locations
b) Tunnel and Portals dimension
(lengths, Spans)
c) Construction methods
SoW of the Project’s Designer in terms of
tunneling works – geotechnical, Building
Condition Surveys/ZOI, etc.
Tunnels Annex B -
1.9.2
2.2.3.21
3.6.3.1.2
Project Designer
Agreement
137.
Response Clarification/Question Subject Section Document Name No.
The length of the route is
approximately 41 kilometers,
but the Company expected that
the Detailed Design will be
required for 43 kilometers.
In any event, the Project
Designer will be entitled to
receive the Service Price
according to the actual
quantities.
Please clarify, how long is the project: 41
km or 43 km?
Length of the project Annex B -
1.9.6.
Project Designer
Agreement
138.
The request is rejected.
The Tender Documents remain
unchanged.
There is a discrepancy with the provided
“proposed parking places” and the
“proposed at-grade parking” for Tal and
Yiftahel stations/stops.
The Company was requested to provide the
updated / consistent number of the required
parking places or clarify the deviation
accordingly.
Proposed parking places
vs Proposed at-grade
parking
Annex B - 1.10.
and 1.10.13
Project Designer
Agreement
139.
The company clarifies that there
is a possibility for a second floor
and this option can be exercised.
The Company was requested to clarify the
term "Provisions for 2nd
level" in the
column "Comments".
Proposed parking places
vs Proposed at-grade
parking
Annex B - 1.10.
and 1.10.13
Project Designer
Agreement 140.
The request is rejected.
The Project Designer is required
to follow the provisions of
National Infrastructure Plan No.
56.
The Company was requested to clarify what
is the purpose of the area marked in the
statutory plan next to Ziad stop/station
(parking compound, specific infrastructure,
etc.).
Ziad Stop/Station Annex B –
1.10.13
1.10.24
Project Designer
Agreement
141.
Response Clarification/Question Subject Section Document Name No.
The Company shall provide the
Project Designer with the
updated forecasts for the Design
of the Project during the
Agreement Period.
The passengers’ boarding figures in the
afternoon in Haifa would be the important
figures.
The company was requested to provide
these figures accordingly or provide an
indication who will be responsible to
provide this data.
Morning Peak in terminal
in Haifa validity for the
demand analysis
Annex B - 1.10.
Stations and
Stops / Lev
Hamifratz/1.10.
19
Project Designer
Agreement
142.
The Company clarifies that this
section does not concern
security issues.
In this section it is stated that all stops will
be unmanned operation.
Is this term valid also to security issues?
Stops security Annex B -
1.10.2
Project Designer
Agreement
143.
The Company clarifies that the
Project Designer’s scope of
work may cover the re-design of
all the parking facilities, as shall
be required by the Relevant
Authorities.
The Company was requested to clarify
whether the scope of the Project Designer
covers the re-design of all the parking
facilities set in clauses 1.10.10-14.
Parking facilities Annex B -
1.10.10-14
Project Designer
Agreement
144.
The Company clarifies that the
design of this station is included
within the Project Designer
Scope of Work.
The Company was requested to clarify
whether the Government City station in
Nazareth is completely an underground
facility or if it is as a trench station
connected by walkways.
Stations / Government
City, Nazareth
Annex B -
1.10.22
Project Designer
Agreement
145.
The Company clarifies that the
design of the stations are
included within the Project
Designer Scope of Work.
The Company was requested to specify if
there is any other station along the route
conceived as an underground space and if
so, to clarify whether “shelter” security
Stations / Government
City, Nazareth
-
LRT Stations and Park &
Annex B -
1.10.22,
3.4.7.1, 3.4.10
Project Designer
Agreement 146.
Response Clarification/Question Subject Section Document Name No.
requirements shall be applied for these
structures.
Ride Facilities
-
Civil works / Buildings-
Special Stations
The request is rejected.
The Company was requested to provide a
list of structures under the Designer’s SoW
and their details, in English.
SoW – Project’s
Structures
Annex B - 2 Project Designer
Agreement 147.
The Company clarifies that land
acquisition and expropriation are
not under the Project Designer
scope of work.
The Company was requested to clarify
whether the Project Designer will be
required to prepare drawings/designs for
land acquisition and expropriation.
Land acquisition and
expropriation
Annex B – The
Services
2.1
Project Designer
Agreement 148.
The Company clarifies that at
this stage a definite division
between Infra 1 and Infra 2 has
not been established.
The level of the design is
determined according to the
relevant discipline, and the
deliverables are determined
according to the relevant level of
design, as specified in the Scope
of Work.
The Company was requested to confirm
that:
a) Infra 1 tender(s) will include
preparation of the road and LRT
strip, including temporary filling
b) Infra 2 tender will include all LRT-
strip elements, including all layers
and Trackbed, Multitubular, and
OCS poles and its foundations, as
well as all stops (platforms and its
equipment).
Infra1-Infra2 Division -
the LRT strip
Annex B - 2.1.1 Project Designer
Agreement
149.
The Company clarifies that the
Project Designer is required to
design the TTR structure at a
Detailed Design level, regardless
Please specify whether the TTR structures
will be tendered through Infra 1 (BOQ) or
Infra 2 (PPP) tender.
Infra1-Infra2 Division -
TTRs
Annex B - 2.1.1 Project Designer
Agreement 150.
Response Clarification/Question Subject Section Document Name No.
of the division between Infra 1
and Infra 2.
The Company clarifies that the
OCC and Depot are both part of
the systems design and will be
designed at a Final Design level
by the Project Designer.
The Detailed Design of the OCC
and the Depot will be done by
Infra 2 Contractor.
The OCC will be located in the
Depot site.
The Company was requested to clarify:
a) what is under “…OCC and depot
site preparatory works”
b) whether the Depot structures and/or
OCC structures will be tendered
through Infra 1 (BOQ) or Infra 2
(PPP) tender
c) whether OCC will be inside the
depot
Infra1-Infra2 Division -
Depot
Annex B -
2.2.2.1
Project Designer
Agreement
151.
The Company clarifies that
parking areas and/or structures
will be tendered through Infra 1.
The Company was requested to clarify
whether the parking areas/structures will be
tendered through Infra 1 (BOQ) or Infra 2
(PPP) tender
Infra1-Infra2 Division –
Parking Areas
Annex B
2.2.2.1
Project Designer
Agreement 152.
The Company clarifies that all
said systems will be designed by
the Project Designer.
The Company was requested to clarify
whether the Parking areas/compounds
would include parking management or
other systems, and if so – who will be the
design said systems.
Infra1-Infra2 Division –
Parking Areas
Annex B
2.2.2.1
Project Designer
Agreement
153.
The Tender Documents remain
unchanged.
Usually a PPP tender includes deliverables
in a final design level. Accordingly, please
clarify the detailed design necessity and
Detailed Design Annex B - 2.2,
4.2
Project Designer
Agreement 154.
Response Clarification/Question Subject Section Document Name No.
deliverables for the following:
a) Track elements
b) OCS, Traction and Power
c) Signaling
d) Traffic lights – priority
e) Fire-fighting and detection
f) Cyber security
Participants’ attention is drawn
to the provisions of the
Agreement, including section
5.2 of Annex “B” (The Services)
to the Agreement.
The Company clarifies that the
division will be based on the
design components and not
between Infra 1 and Infra 2.
For "The Designer shall undertake
Preliminary Design and Final Design for all
LRT works (both Infra 1 Works and Infra 2
Works" mentioned in 2.2.1 of Appendix B,
please make clear whether it means as
follows: design function is not contained in
PPP implementation object in infra2
Works, and the participant is responsible
for the design of infra 1 Works and infra 2
Works.
Scope of work Annex B - 2.2.1 Project Designer
Agreement
155.
The Project Designer is required
to design all the systems
required for the Project.
Participants’ attention is drawn
to provision of section 2.1.3. of
Annex B (The Services) to the
Agreement.
Please provide a list of systems to be
designed as part of the Project Designer’s
SoW.
LV Systems Annex B - 2.2.3 Project Designer
Agreement
156.
Response Clarification/Question Subject Section Document Name No.
The Project Designer is required
to design all the systems
required for the Project.
Participants’ attention is drawn
to provision of section 2.1.3. of
Annex B (The Services) to the
Agreement.
Please explicitly list all the systems within
the scope of the Project Designer to avoid
all potential ambiguities created by the term
“including for and in respect of but not
limited…”.
Scope of Services Annex B - 2.2 /
2.2.3
Project Designer
Agreement
157.
Participants’ attention is drawn
to the Agreement, including
Section 2.2.3. of Annex “B”
(The Services) to the
Agreement.
The Company was requested to confirm
that the Rolling Stock Engineer is required
to do the design itself for the rolling stock
(including the simulator).
Rolling stock (including
simulator)
Annex B - 2.2
and 2.2.3.11
Project Designer
Agreement
158.
Participants’ attention is drawn
to the provisions of the
Agreement, including Sections
3.9. and 5.2.12 of Annex “B”
(The Services) to the
Agreement.
It is our understanding that at the design
stage it can be only written / developed on
the basis of the high-level assumptions as
far the operation and maintenance planning
depend on the systems to be implemented
by the PPP Contractor/O&M Operator.
Please confirm the above stated and/or
comment accordingly.
Operation and
maintenance planning and
specifications
Annex B -
2.2.3.12
Project Designer
Agreement
159.
The Company clarifies that the
Project Designer is responsible
to design the Detailed Design of
all Civil Engineering works,
regardless of the division
between Infra 1 and Infra 2.
The Company was requested to clarify
whether Participants should consider that
the civil works with road and roadside
development related works are rather part
of the INFRA 1 package of services?
Civil Engineering works
and road and roadside
equipment
Annex B -
2.2.3.17
Project Designer
Agreement
160.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that the
Project will include LRT and
vehicles tunnels only, and that
payment for tunnel design will
be determined pursuant to the
applicable item of Annex D
(Service Price) to the
Agreement.
The Company was requested to define the
type (e.g. only utility tunnel or LRT tunnel)
of the tunnels together with their quantities
to be taken within the Project Designer’s
scope.
Tunnel MEP Annex B -
2.2.3.21
Project Designer
Agreement
161.
Participants’ attention is drawn
to the Agreement, including
Sections 3.8, 4.2.3.1, and 5.2.8-
5.29 of Annex “B” (The
Services) to the Agreement.
Depot Management System at the design
stage can be only defined as high level
specifications based on assumptions as far
the operation and maintenance planning
depends on the systems to be implemented
by the PPP Contractor/O&M operator.
Can the Company confirm this assumption
or comment accordingly?
Depot Management
System
Annex B -
2.2.3.23
Project Designer
Agreement
162.
The Company clarifies that
Safety Specifications relate to
RAMS.
The Company was requested to clarify
whether Safety Specifications relate to
RAMS or security.
Scope of services – Safety
Specifications
Annex B -/
2.2.3.24
Project Designer
Agreement 163.
The Company clarifies that
construction documents include
all the documents required for
the construction of the Project.
The Company was requested to define the
term “construction documents” and list the
required documents to be produced by the
Project Designer in that regard.
“Construction
Documents”
Annex B -
2.2.3.27
Project Designer
Agreement 164.
Response Clarification/Question Subject Section Document Name No.
The Project Designer is required
to design all the systems
required for the Project,
including those mentioned
within this request for
clarification.
The Company was requested to define
which systems, facilities and activities are
within the scope of the Project Designer.
There are number of systems, facilities and
design/design-implementation activities
which could be provided by the PPP
Contractor and the future O&M Operator.
The listing does not make a distinction
between railway/tram systems and typical
building systems (MEP). A number of
systems are missing, or not separately
listed, e.g. lifts and escalators, earthing and
bonding, traction power supply, stray
current control, digital mobile radio system,
W-Lan system, central clock system,
recording system, advertising system and
all the management systems related to the
future operations and maintenance.
….for and in respect of
but not limited to the
following systems,
facilities and
activities….scope
definition
Annex B -
2.2.3.
Project Designer
Agreement
165.
The Company so confirms.
The Company was requested to confirm
that the Gilam intersection is excluded from
the Project’s Designer SoW.
Gilam Intersection Annex B - 2.3.2 Project Designer
Agreement 166.
The Company clarifies that as of
this date, there is no requirement
for extending the LRT to the
south and to the town of
Nazareth Illit.
The Company was requested to clarify
whether there is any preliminary plan or
guidelines for extending the LRT to the
south and to the town of Nazareth Illit?
Possible extension of the
LRT to the south
Annex B - 2.4.4
Project Designer
Agreement
167.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the provisions of Sections
2.4.10 of Annex B (The
Services) to the Agreement.
The Company was requested to clarify
whether the actual geological tests and soil
sampling are at the expense of the Project
Designer or at the expense of the Company.
The scope of works defines that geological
geotechnical studies are part of the scope of
work.
Geological Geotechnical
Studies
Annex B –
2.4.5
Project Designer
Agreement
168.
Participants’ attention is drawn
to provision of section 2.4.5. of
Annex B (The Services) to the
Agreement.
The Company was requested to clarify
whether the actual surveying of the
topographical surveys will be at the
expense of the Project Designer or at the
expense of the Company?
Topographical Surveys Annex B –
2.4.5
Project Designer
Agreement
169.
The Company clarifies that the
authorized body under
applicable law will be
responsible to approve the traffic
lights prioritizing along the
entire route.
The Company was requested to clarify who
is responsible to approve the traffic lights
prioritizing along the entire route under the
scope of the project.
Priority Lights Annex B -
2.4.5.4
Project Designer
Agreement
170.
The Company clarifies that
insofar as the request refers to
priority traffic lights,
participants’ attention is drawn
to the provisions of clause 3.5 of
Annex “D” to the Agreement.
Insofar as the request refers to
impacted traffic lights, whether
inside or outside the Limit of
The Company was requested to clarify how
the participants should price the design of
traffic lights outside of the Limit of Works
of the project.
Traffic Lights Annex B –
2.4.5.4
Annex D
Project Designer
Agreement
171.
Response Clarification/Question Subject Section Document Name No.
Works of the Project, all
impacted traffic lights are
deemed included in clause 3 of
Annex “D” to the Agreement.
The Company clarifies that
locating priority elements and is
included within the Project
Designer Scope of Work.
The Company was requested to provide a
list of signalized junctions and/or elements
to be designed in terms of priority.
LRT Priority Annex B -
2.4.5.4
4.2.29.2
Project Designer
Agreement 172.
The request is rejected.
In addition, the identity of the
operator and maintainer of the
road traffic lights is unknown at
this satge.
The Company was requested to provide a
description of the interface regarding
priority lights and clarify on who shall be
the traffic authority (רשות תמרור) along the
alignment.
In addition, the Company was requested to
clarify on who shall be the operator and
maintainer of the road traffic lights, and
what shall be the design boundary in terms
of system/operation design.
LRT Priority Annex B -
2.4.5.4
4.2.29.2
Project Designer
Agreement
173.
The request is rejected.
The Company was requested to define the
term “undertake” in regard to the Project
Designer’s responsibility, accountability
and provide a precise definition / list of
tasks to be executed by the Project
Designer.
Designer’s responsibility
to undertake items listed
under 2.4.5.1-2.4.5.7
Annex B - 2.4
Project Designer
Agreement
174.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that said
sections deals with the
underpass link to Government
City station in Nazareth
Annex “B” (The Services) mentions design
of all civil engineering works and the list
mentions “tunnels”. Where in the project
are there tunnels?
Tunnels Annex B -
2.2.2.1
3.4.1.4
Project Designer
Agreement
175.
With respect to item a - as
detailed in the Tender
Documents
With respect to item b -
The Project Designer will
undertake all assignments
regarding the geotechnical
surveys, except for the Drilling
contractor and Laboratory
services that will be contracted
by the Company. Participants’
attention is drawn to the
provisions of clause 2.4.10 of
Annex B
With respect to item c -
It is under the Company’s
responsibility
Usually for such projects the land survey
and geotechnical surveys are done by the
Employer, with the designer coordinating
the interfacing tasks only.
Please specify what will be provided by the
company and what exactly is under the
scope of work of the Designer.
Please specifically refer to all related
activities such as:
a) For surveyor:
1. Photogrammetry
2. Detailed land survey for design
3. Survey for registration (TAZAR)
4. Survey for Expropriations
5. Additional surveyor activities
(utilities, trees, etc.)
b) Drilling campaign:
1. Utility coordination for the drilling
campaign
2. Design of traffic arrangements for
drilling campaign
3. Permitting for the drilling
campaign, including technical
Surveys Annex B –
2.4.5.1
3.4
4.2.5
Project Designer
Agreement
176.
Response Clarification/Question Subject Section Document Name No.
permit (היתר הנדסי) in the
municipalities and traffic permit
in the municipalities (היתר תנועתי)
and police
4. The drilling, boreholes and other
works by the drilling contractor
5. Any required supervision by utility
owners
6. The traffic arrangements including
supervision and traffic safety teams
7. On-site direct geological
supervision
8. On-site and laboratory tests
c) Archeological examinations required
by Antique Authority
Please also specify which action is
obligatory.
The Company clarifies that the
Project Designer shall conduct
all the seismic surveys that are
required for the design of the
Project according to the
provisions of National
Infrastructure Plan No. 56 and
applicable Law.
The Company was requested to clarify what
would be required from the Project
Designer in terms of seismic surveys for
earthquakes and/or Tsunamis ( סקר תגובת
.(אתר
Seismic Annex B -
2.4.5.1
Project Designer
Agreement
177.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that all
the related activities mentioned
under this request for
clarification are under the
Project Designer responsibility.
However, in case there will be
for exploratory pit, said will be
carried out by the Company at
its own expense.
Usually for such projects the utility
detections are done by the Employer, with
the designer coordinating the interfacing
tasks only.
Please specify what will be provided by the
Company and what exactly is under the
scope of work of the Designer.
Please specifically refer to all related
activities such as:
a) Utility coordination for the
detection campaign
b) Design of traffic arrangements for
detection campaign, if required
c) Permitting for the detection
campaign if required
d) The detection itself on-site
e) The traffic arrangements including
supervision and traffic safety teams
Any required supervision by utility owners
Utilities Detections
Annex B –
2.4.5.2
4.2.20
Project Designer
Agreement
178.
The files can be downloaded
from the following link:
www.iplan.gov.il in Hebrew
only.
The Company was requested to provide
National Infrastructure Plan No. 56 and
Preferred Housing Plan No. 1025 (English
version) in 2.4.3。
Local plan Annex B - 2.4.3 Project Designer
Agreement
179.
Response Clarification/Question Subject Section Document Name No.
It is clarified that the preparation
of structural survey is under the
Project Designer responsibility,
as detailed under the Design
Tasks and deliverables.
Please specify what will be provided by the
Company with respect to structural survey
and what exactly is the scope of work of the
Project Designer.
Please also specify the type and scope of
the required surveys.
Bridges & Structure
Surveys
Annex B -
2.4.5.3
Project Designer
Agreement
180.
Participants’ attention is drawn
to the provisions of sections 3.5,
4.2.28, 4.2.29 and 4.3.1.3 of
Annex “B” (The Services) to the
Agreement.
Please specify the SoW of the Project’s
Designer in terms of priority lights – rail
traffic lights and road traffic lights.
Priority Lights Annex B -
2.4.5.4
Project Designer
Agreement
181.
The request is rejected. As the statutory provisions are obligatory,
please provide all background and statutory
documents in English, and mainly the
documents marked as “mandatory” ( מסמכים
in the statutory plans – Main (מחייבים
Statutory Document (הוראות התכנית) &
Proposed Stage Plans (מצב מוצע).
Statutory Documents Annex B –
2.9
2.4.3
Project Designer
Agreement
182.
Participants’ attention is drawn
to the provisions of the revised
Section 3.1. of Annex “B” (The
Services) to the Agreement.
In addition, the Company
clarifies that all available
reference design documents
were uploaded as part of Annex
B (Reference Design
The specifications refer to two types of
turnouts with respectively 190 m and 140 m
turning radius, while the turnouts shown in
the drawings appear to have turning radius
of 25 m?
The technical note seams to refer to a
railway/LRT specification, while the
supplied drawings seem to be based on a
tram/LRT specification.
Turnouts Annex B - 2.11 Project Designer
Agreement
183.
Response Clarification/Question Subject Section Document Name No.
Documents) to the Invitation to
Bid.
Please provide the documents, match to
each other, to enable the tenderer to
calculate the design efforts needed or
advice how to proceed on the explained
matter.
The request is rejected.
For the avoidance of doubt, lifts
and escalators are also part of
the civil engineering works.
The Company was requested to specify the
scope in a detail to enable the tenderer to
calculate the design efforts needed. The
sentence “undertake all design and design-
implementation activities, including but not
limited to” does not include any limitation.
Only as an example, there are no chapters
covering lifts and escalators in the Annex
B?
Will it also be part of the scope or it will be
tendered separately?
Scope of work Annex B - 2.2.2 Project Designer
Agreement
184.
Participants’ attention is drawn
to the provisions of Section
9.4.25. of Annex “B” (The
Services) to the Agreement.
The clause mentions tasks which are under
the site supervision responsibility and not
the Project Designer.
The Project Designer may support these
tasks but is not the one responsible for it.
Please acknowledge.
Infra 1 works –
Approving execution and
preparing completion
certificate
Annex B -
2.2.2.5
2.3.3.10
Project Designer
Agreement
185.
The request is rejected.
Participants’ attention is drawn
to the provisions of Section 3.6.
of Annex “B” (The Services) to
the Agreement.
We request that the limit of responsibility
of the Project Designer shall be the TATAL
56 plan boundaries and Road 781 Limit of
Works.
Annex B - 2.4.6 Project Designer
Agreement
186.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that all
the studies, surveys and analyses
which are required for the
Project are included in the
Project Designer’s Scope of
Work.
The Company was requested to define the
list/scope of the required studies, surveys
and analyses to be done.
Required studies, surveys
and analyses
Annex B - 3.
Preliminary
Design and
Final
Design/3.1
General: Design
Standards and
Criteria/3.1.1.2
Project Designer
Agreement
187.
The Company clarifies that all
the utilities assessment and
coordination which are required
for the Project are included in
the Project Designer’s Scope of
Work.
The Company was requested to define the
scope of the utilities assessment and
coordination to be done.
Utilities assessment Annex B - 3.
Preliminary
Design and
Final
Design/3.1
General: Design
Standards and
Criteria/3.1.1.3
Project Designer
Agreement
188.
The Company shall provide the
Project Designer with passenger
forecast modeling.
Passenger forecast modeling (demand
analysis) was already done – AB Plan and
Yefe Nof model and will be used as the
main input by the Project Designer.
The Company was requested to define
explicitly design to be done by the Project
Designer in regard to the “passenger
forecasts (modeling)”.
Traffic counts, Passenger
forecast/modeling
Annex B - 3.
Preliminary
Design and
Final
Design/3.1
General: Design
Standards and
Criteria/3.1.5
Project Designer
Agreement
189.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the provisions of the
Agreement, including Sections
3.2, and 4.2.19-4.2.25 of Annex
“B” (The Services) to the
Agreement.
It is common practice that the Project
Designer can only suggest/propose the
required utilities relocations while the
design for relocation needs to be done by
some of the Utility Company Design Teams
(such as IEE, MEKOROT, etc.). This is
why the Bill is presented by the Utility
companies to the Project Owner/Client (the
“Company”) – as described in the SoW.
The Company was requested to explicitly
define the Project Designer’s services
related to the proposal and design of the
utilities relocation arrangements as well as
the engagement of the respective Utility
Companies in their design
Proposal and design of the
required relocation
arrangements
Annex B - 3.
Preliminary
Design and
Final
Design/3.2
Utilities
Project Designer
Agreement
190.
The Company so clarifies.
The Company was requested to clarify
whether the requirement for the delivery of
façade to façade design (cycle paths, track
bed, road, pavement, lighting, urban
furniture…) in urban sections means the
delivery of the complete urban development
of the streets affected by the LRT
alignment.
Urban Design (Façade to
Façade) of the LRT
alignment
Annex B - 3.3.2 Project Designer
Agreement
191.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that
insofar as the Project Designer’s
design changes the existing
conditions, the Project Designer
will be required to address to all
associated aspects of its design.
The Company was requested to clarify
whether in the interurban sections the
Project Designer will be required to deliver
any other urban development scope apart
from the scope that associated to stations
and car parking facilities (such as road and
pedestrian accesses).
Urban Design (Façade to
Façade) of the LRT
alignment
Annex B - 3.3.2 Project Designer
Agreement
192.
The Company so clarifies.
Participants’ attention is drawn
to the Agreement, including
Sections 3.4.7 and 3.8 of Annex
“B” (The Services) to the
Agreement.
The architectural design of depot, OCC and
Park & Ride facilities is not explicitly
mentioned in the Architectural Design
scope.
The Company was requested to clarify
whether the Project Designer should also
consider these design topics and prepare the
architectural design for the Depot, OCC and
Park & Ride facilities?
Depot, OCC (Operation
Control Center) and Park
& Ride facilities
Annex B - 3.
Preliminary
Design and
Final Design /
3.3. Track
Alignment
/Architectural
design/3.3.3
Project Designer
Agreement
193.
The Company clarifies that no
such complementary feasibility
study was performed thereby.
Participants’ attention is drawn
to the provisions of sections 3.1
and 3.7 of Annex “B” (The
Services) to the Agreement.
The Company was requested to clarify
whether a complementary feasibility study
has been performed by the Company or its
consultants to determine if the rolling stock
manufacturer could achieve the
performances mention in the Tender
Documents?
1. If yes, may the Company share the
conclusion?
2. If not, how the Company expect to
mitigate this risk?
Rolling stock Annex B - 3.3
light rail / tram-
train
Project Designer
Agreement
194.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that no
additional information will be
provided at the Tender stage.
Said Surveys are included
within the Project Designer
Scope of Work.
The Company was requested to provide
data regarding topographic surveys.
Topography Annex B - 3.4.1
Project Designer
Agreement
195.
The Company clarifies that the
Project Designer shall be
required to execute and provide
all relevant topography surveys
to prepare its design.
Participants’ attention is drawn
to the provisions of Sections
3.4.1 and 4.2.4 of Annex B (The
Services) to the Agreement.
Is the Designer expected to carry out
topographic surveys along the entire LRT
route or just to make completions on top of
the surveys carried out in the framework of
the preliminary design
Topography Annex B - 3.4.1
Project Designer
Agreement
196.
The Company clarifies that soil
investigations and laboratory
tests will be carried out by the
Company at its own expense,
but the Project Designer will
define the technical
requirements for soil
investigations and laboratory
tests. For the avoidance of
doubt, the carrying out of said
investigations and test by the
Company shall not release the
We consider, as a common practice, that the
Project Designer defines the technical
requirements for soil investigations and
laboratory tests, but the actual field work is
carried out by the Client (the Company) and
on its own expense.
The Company was requested to explicitly
define the Project Designer’s scope and
required services for the soil investigations,
laboratory tests, etc.
Soil investigations and
laboratory tests
Annex B - 3.
Preliminary
Design and
Final Design /
3.4. Civil
Engineering
Works
/Geology and
soil
conditions/3.4.3
Project Designer
Agreement
197.
Response Clarification/Question Subject Section Document Name No.
Project Designer form its
obligation under the Agreement
including its obligation to meet
the Detailed Service Schedule.
In addition, participants’
attention is drawn to the
provisions of Section 2.4.10 of
Annex B (The Services) to the
Agreement.
The Company shall provide the
Project Designer with Ridership
forecasts at a later stage during
the Agreement Period.
The Company was requested to clarify
whether the Project Designer shall use the
existing passenger capacity and traffic flow
analysis data originating from the existing
Yefe-Nof’s model.
Passenger Capacity and
Traffic Flow Analyses
Annex B - 3.
Preliminary
Design and
Final Design /
3.4. Civil
Engineering
Works /LRT
stations and
park & ride
facilities
/3.4.7.4
Project Designer
Agreement
198.
The Company clarifies that there
is no demand for specific
pedestrian modelling software.
The Design will be required to
comply with the instructions of
the Ministry of Transport and
Road Safety.
The Company was requested to clarify
whether any specific pedestrian modelling
software will be required to perform the
passenger flow analysis.
LRT Stations and Park &
Ride Facilities
Annex B -
3.4.7.4
Project Designer
Agreement
199.
Response Clarification/Question Subject Section Document Name No.
The term “climate audit” shall
mean review of the specific
climate situation at each station
and parking facility (such as but
not limited to exposure to
sunlight, winds, rain/snow fall)
and the means to improve
passengers comfort taking int
account said conditions.
The Company was requested to define the
term “climate audit” and Project Designer’s
tasks in that regard.
Climate audit definition
and services
Annex B - 3.
Preliminary
Design and
Final Design /
3.4. Civil
Engineering
Works /LRT
stations and
park & ride
facilities
/3.4.7.6
Project Designer
Agreement
200.
The Company clarifies that the
Project Designer will be
required to provide any number
of alternative alignment designs,
as shall be required by the
Company and/or Relevant
Authorities.
The Company was requested to define the
required number of the alternative
alignment designs to be prepared by the
Project Designer and analyzed
comparatively accordingly.
Alternative alignments
(and comparative
analysis)
Annex B - 3.
Preliminary
Design and
Final Design /
3.4. Civil
Engineering
Works /LRT
stations and
park & ride
facilities
/Deliverables/3.
4.9.1.1.
Project Designer
Agreement
201.
לא סמן :מעוצב
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that it is
not aware of any requirement to
design additional special stations
other than the stations
mentioned in National
Infrastructure Plan No. 56.
The Company was requested to clarify how
many stations are included under the
provisions of Section 3.4.10 and to clarify
whether this strictly refers to the 3 stations
listed in 1.10.15-24 (Lev Hamifratz,
Government city, Zayad).
Civil works / Buildings-
Special Stations
Annex B -
3.4.10
Project Designer
Agreement
202.
The request is rejected.
The Company was requested to define the
required number of the alternative
alignment designs to be prepared by the
Project Designer and analyzed
comparatively accordingly.
Presentation of the
considered alternatives
Annex B - 3.
Preliminary
Design and
Final Design /
3.4./Civil
works-
Structural /
Deliverables /
3.4.16.1.2
Project Designer
Agreement
203.
The Company shall provide the
Project Designer with the
updated demand analysis model
at a later stage during the
Agreement Period.
The Company was requested to confirm
that the updated Yefe-Nof demand analysis
model will be made available to the Project
Designer as the main input for the
signalized junctions capacity check.
Updated Yefe-Nof model
(demand analysis)
availability + traffic
software
Annex B - 3.
Preliminary
Design and
Final Design /
3.5. Traffic
Arrangements
and Impact Plan
/ Deliverables/
3.5.5.1.2.
Project Designer
Agreement
204.
The Company so confirms.
No additional data will be
provided at the tender stage.
The Company was requested to confirm the
necessity of the power supply simulation as
to provide additional input data.
Power supply simulations
and input data
Annex B - 3.
Preliminary
Design and
Final Design /
Project Designer
Agreement 205.
Response Clarification/Question Subject Section Document Name No.
Annex B - 3.6.
Rail
Systems/Energy
supply and
distribution
systems/
3.6.2.2.
The Company clarifies that all
the activities and systems
mentioned in the request for
clarification are included within
the Project Designer Scope of
Work.
It is our understanding that the required
design activities for the Lighting
installations should be part of the INFRA 2.
To be noted, there are also 2 different types
of SCADA systems: for the tram/LRT
operations and signaling and for the MEP
parts of the buildings/structures.
Please confirm and/or comment
accordingly.
Lighting installations as
part of the INFRA 2 (Rail
Systems) package
Annex B - 3.
Preliminary
Design and
Final Design /
3.6. Rail
Systems/Lightin
g installations
Project Designer
Agreement
206.
The Company clarifies that
clause 3.6.5 relates to all low
voltage and light current rail
systems, including, inter alia,
Signaling and Train Control.
The scope of services described under the
chapter “Low voltage and light current
systems” does not correspond to the given
chapter title. In our understanding it should
be renamed as “Signaling / Train Control”
and other low voltage and light current
systems should be separated from the
railway systems under a separate headline.
Please confirm and / or comment
accordingly.
Chapter “Low voltage and
light current system”
renaming
Annex B - 3.
Preliminary
Design and
Final Design /
3.6. Rail
Systems/Low
voltage and
light current
systems
Project Designer
Agreement
207.
Response Clarification/Question Subject Section Document Name No.
The Tender Documents remain
unchanged.
Participants’ attention is drawn
to the provisions of Section
3.7.2.1-3.7.2.2 of Annex “B”
(The Services) to the
Agreement.
It is not possible at the given design stage to
prepare 3-D images of the train/multiple
unit aesthetic design by the Project
Designer.
This can be only done by a successful
Rolling Stock Supplier (after the Tender
process and Contract award).
For the purposes of the Preliminary/Final
Rolling Stock design the Project Designer
can only provide 3 (three) different
aesthetic designs (high level drafts) based
on a free sample benchmark.
Please confirm the above mentioned and/or
clarify/comment accordingly.
3-D imaging of the
vehicle and/or train – at
least 3(three) aesthetic
design proposals to be
prepared
Annex B - 3.
Preliminary
Design and
Final Design /
3.7. Rolling
Stock/Deliverab
les
Project Designer
Agreement
208.
The Tender Documents remain
unchanged.
The attention of all Participant is
drawn to the provisions of
Section 2.15 of the Invitation to
Bid and Section 3.6.2.5 of
Annex B (The Services) to the
Agreement.
As indicated in 3.6.2.5 of Annex B (The
Services) to the Agreement, the working
scope of power supply includes medium-
voltage network, traction rectifier unit, DC
power supply system, return current system
as well as power supervisory control and
data acquisition system and stray current
protection system of substation, but in
preliminary design files, only DC power
supply system and return current system are
included and other basic information
mentioned above is not reflected.
Energy supply and
distribution systems
Annex B - 3.6.2 Project Designer
Agreement
209.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that the
Project Designer will be
required to base and enhance its
report with applicable and
available information as
described in clauses 3.7.2.2 and
3.7.2.3 of Annex B (The
Services).
From our experience, is the Manufacturer
who usually carries out deliverables of
sections 3.7.2.2 and 3.7.2.3.
We understand that what has to be done by
the Designer is to define general
characteristics of these deliverables
(drawings and 3-D imaging) to be further
developed by the Manufacturer. Please
confirm if our understanding is correct.
Rolling Stock
Deliverables
Annex B –
3.7.2.2 and
3.7.2.3
Project Designer
Agreement
210.
The Company clarifies that
Clause 3.6.2 relates to the design
of the Energy supply and
distribution systems while
clause 3.9 relates to the
operational planning (energy
demands).
The Company was requested to clarify
whether the tasks defined under clauses
3.9.1.3.5 and 3.6.2.2 contain the same
scope?
Energy consumption Annex B - 3.
Preliminary
Design and
Final Design /
3.9. Operating
Principles/3.9.1.
3.5
Project Designer
Agreement
211.
The Tender Documents remain
unchanged.
The Company was requested to clarify the
level and the scope of the Project
Designer’s engagement during the VATAL
Statutory Approval Process to enable the
tenderer to calculate and price the needed
efforts and time.
VATAL Statutory
Approval Process – PD’S
engagement
Annex B - 3.
Preliminary
Design and
Final Design /
3.10.Proejct
Preliminary
Report/3.10.4.
Project Designer
Agreement
212.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that the
Project Designer will prepare all
the tasks as required in
accordance with the provisions
of National Infrastructure Plan
No. 56 and the requirements of
the Relevant Authorities.
The Company was requested to confirm
that any preventive and/or mitigation
methods for electrification of birds is
excluded from the Project Designer’s SoW
and will be done by the Infra 2 Contractor
to follow.
Ecology Annex B -
3.10.5.2.2
Project Designer
Agreement
213.
The Company clarifies that
although National Infrastructure
Plan No. 56 was approved by
the Government of Israel, if the
Project Designer will be
required to make amendments to
the plan within the plan
boundary (i.e. inside the Blue
Line) or amendments with
respect to TTR’s inside and
outside the blue line, it will be
deemed included within the
Project Designer Scope of Work
without any entitlement to
adjustment of the Service Price
or the Project schedule.
The Company was requested to clarify
whether clause 3.10.4.3 imply that it may
be necessary to amend approved statutory
plan?
Statutory plan
TATATL/56
Annex B -
3.10.4 and
3.10.4.3
Project Designer
Agreement
214.
The Company clarifies that the
EIS was approved as part of
National Infrastructure Plan No.
56.
The Project Designer will be
In the framework of preparing the
TATAL/56 plan a comprehensive EIS was
done. In this context:
A. It is not clear why it is required to
carry out an additional EIS.
Environmental Impact
Survey (EIS) –
And Project Designer’s
tasks
Annex B - 3.
Preliminary
Design and
Final Design /
3.10. Proejct
Project Designer
Agreement
215.
Response Clarification/Question Subject Section Document Name No.
required to prepare its design in
compliance with National
Infrastructure Plan No. 56.
documents and according to the
instructions of the VATAL
council.
B. In case that completions to the
already performed EIS will be required,
what will happen if changes will occur in
the already approved statutory plan, from
the standpoints of timetable and the design
costs?
Please comment and clarify the above
stated.
Preliminary
Report/ 3.10.5.
Environmental
Impact Survey
(EIS)
National Infrastructure Plan No.
56 was approved by the
Government of Israel.
The Company clarifies that
clause 3.10.4 refers to
Preliminary Design whereas
clause 4.3.4 refers to Detailed
Design.
The Company was requested to clarify the
current status of the statutory plan, and
what is therefore required from the
Designer for the statutory process? In that
sense, please explain what the difference
between 3.10.4 and 4.3.4
SoW - Statutory Annex B –
3.10.4 and 4.3.4
Project Designer
Agreement
216.
The Company clarifies that the
Project Designer will be
required to conduct all the filed
surveys that are required for the
design of the Project.
The Company was requested to clarify
which filed surveys will be required from
the Project Designer, including:
a) Air quality field measurements in
Road 781
b) EMC measurements
c) Trees
d) Geofits
Environmental Annex B–
3.10.5
Project Designer
Agreement
217.
Response Clarification/Question Subject Section Document Name No.
The Tender Documents remain
unchanged.
It is our understanding that the title under
the paragraph 3.11 “Schedule of Works”
should be renamed to the “Schedule of
Project Designer’s Services” based on the
below given task/chapter description.
Please confirm and/or comment
accordingly.
Title “Schedule of
Works” to be renamed
Annex B - 3.
Preliminary
Design and
Final Design /
3.11. Schedule
of Works
Project Designer
Agreement
218.
Participants’ attention is drawn
to provision of section 4.1.3.2 of
Annex B (The Services) to the
Agreement.
The Company was requested to provide the
project’s segmentation and the maximum
number of packages in which the project
will be tendered.
Infra 1 Segmentation Annex B -
4.1.3.2
Project Designer
Agreement 219.
The Company clarifies that the
Project Designer will be
required to ensure that all
requirements of Relevant
Authorities are implemented
within its design and approved
as required.
The Company was requested to confirm
that the authorization and approval of the
cyber security authority / cyber unit in the
MoT is not under the SoW of the Project
Designer, but only of the Infra 2 Contractor
to follow.
Cyber Security Annex B -
4.2.32
Project Designer
Agreement
220.
The Company clarifies that
typical cross-sections will be
either at 1:50 or 1:100 non-
distorted.
Why a distorted scale (1:50/1:100) for
cross-sections is required?
We consider that an uniform scale of either
1:50 or 1:100 would prevail for selected
sections only For standard cross sections a
larger scale of either 1:200 or 1:250 would
be sufficient.
Cross-section Annex B - 4.
Detailed Design
of Civil Works/
4.2. Detailed
Design / Civil
Engineering
works
generally/4.2.9.
3
Project Designer
Agreement
221.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that the
Project Designer will be
required to design the
restoration and/or development
works of any of the rivers along
the alignment if its design may
cause damage to one of the said
revers or if there is a specific
requirement within National
Infrastructure Plan No. 56.
The Company was requested to confirm
that any restoration and/or development
works of any of the rivers along the
alignment (including Kishon, Gdura,
Shfaraam, Somech, Zipori, Adashim,
Kselot) are excluded in the SoW of the
Project’s Designer, or to specify which
works are required and where.
Water Resources and
Ecology
Annex B -
4.2.10
Project Designer
Agreement
222.
The Company clarifies that the
Project Designer will be
required to prepare the detailed
design in relation to the Infra 1
tenders' works, which will
include mainly the Civil Works,
and prepare its design to the
extent needed to promote and
carry out Infra 2 Tenders.
The supplied scope description does not
match. Text is identical with 5.2.4 from the
INFRA 2 part - duplication.
Only civil engineering related services are
expected to be listed at this chapter with
reference to 5.2.4
Please provide the scope description related
for Infra 1.
Overhead Contact System
–scope repetition
Annex B - 4.
Detailed Design
of Civil Works/
4.2. Detailed
Design/OCS
4.2.26
Project Designer
Agreement
223.
The Company clarifies the
demand is for cross-section
every twenty (20) meters but the
Company reserve its right to
instruct the Project Designer to
provide cross-section every ten
(10) meters in defined sections.
For the avoidance of doubt such
instruction of the Company shall
As based on our experience and common
practice, cross-sections are prepared every
20 meters for tracks and roads alike. It is
unclear why different cross-sections
resolutions is required.
Cross-section every ten
(10) meters along the
track and twenty (20)
meters elsewhere at scales
1:50/1:100 - Costs
implications
Annex B - 4.
Detailed Design
of Civil Works/
4.2. Detailed
Design / Civil
Engineering
works
generally/4.2.9.
3
Project Designer
Agreement
224.
Response Clarification/Question Subject Section Document Name No.
not be deem a Variation Order.
The Company clarifies that the
Project Designer will be
required to prepare the detailed
design in relation to the Infra 1
tenders works, which will
include mainly the Civil Works,
and prepare its design to the
extent needed to promote and
carry out Infra 2 works.
The supplied scope definition does not
match. Text description is identical with
5.2.6.3 from INFRA 2 part (duplication).
Only civil engineering related services are
expected to be listed at this chapter with
reference to 5.2.6.3
Please provide the scope description related
for Infra 1.
LRT Signaling 4. Detailed
Design of Civil
Works/ 4.2.
Detailed
Design/LRT
signaling 4.2.28
Project Designer
Agreement
225.
The Company clarifies that אhe
Project Designer will be
required to prepare the detailed
design in relation to the Infra 1
tenders' works, which will
include mainly the Civil Works,
and prepare its design to the
extent needed to promote and
carry out Infra 2 works.
The supplied scope definition does not
match. Text description is identical with
5.2.8 from the INFRA 2 part (duplication).
Only civil engineering related services are
expected to be listed at this chapter with
reference to 5.2.8
Please provide the scope description related
to the INFRA 1.
Depot and workshop –
scope repetition
Annex B - 4.
Detailed Design
of Civil Works/
4.2. Detailed
Design/Depot
and workshop/
4.2.31
Project Designer
Agreement
226.
Participants’ attention is drawn
to the Agreement, including
Section 3.6 and 3.8 of Annex
“B” (The Services) to the
Agreement.
In drawing for SCADA system, View Node
and Engineering are provided in Corporate
LAN network, please make clear whether
this type of workstation is within the design
scope of the project, and whether all the
workstations in this type shall be arranged
in station, OCC and parking lot, whether
they shall be arranged beyond the scope of
safety protection of
system information.
Annex B - 4.2.8 Project Designer
Agreement
227.
Response Clarification/Question Subject Section Document Name No.
line civil work, which is involved in safety
protection of system information.
Participants’ attention is drawn
to the Agreement, including
Section 9.2.15. of Annex “B”
(The Services) to the
Agreement.
At present, fire prevention is required to
comply with NFPA 130/ Israeli Standard
5435, please make clear whether civil work
and technical schemes of equipment
systems, equipment specification and
material type selection in the project shall
meet the requirements of NFPA 130/ Israeli
Standard 5435.
Fire detection and
extinguishing system
Annex B - 4.3.7 Project Designer
Agreement
228.
The Company clarifies that the
Project Designer will be
required to prepare its design to
the extent needed to promote
and carry out Infra 2 Tender.
The Company was requested to confirm the
necessity of the power supply execution (as
well as the availability of any input data).
Power supply simulations Annex B - 5.
Technical
Engineering
Documents for
Infra 2 Tender /
5.2. Design for
INFRA 2
Tender / Power
Systems/5.2.3.2
Project Designer
Agreement
229.
The Company clarifies that the
Project Designer will be
required to prepare its design to
the extent needed to promote
and carry out Infra 2 Tender.
The tasks description text is identical as text
given under 4.2.26
In our understanding, the OCS should form
part of the INFRA 2. Please confirm.
Scope Overhead Contact
System (OCS)
Annex B -
Overhead
Contact System
(OCS)/5.2.4
Project Designer
Agreement
230.
The Company clarifies that the
Project Designer will be
required to prepare its design to
The tasks description is identical as text
given under the 4.2.27
In our understanding, task under the title
Scope lighting Annex B -
Lighting/5.2.5
Project Designer
Agreement 231.
Response Clarification/Question Subject Section Document Name No.
the extent needed to promote
and carry out Infra 2 Tender.
“Lighting installations” should be part of
the INFRA 2 Please confirm and/or
comment accordingly.
The Tender Documents remain
unchanged.
The scope of services described under the
chapter “Low voltage and light current
systems” does not correspond to the given
chapter title. In our understanding it should
be renamed as “Signaling / Train Control”
and other low voltage and light current
systems should be separated from the
railway systems under a separate headline.
Please confirm and / or comment
accordingly.
Chapter “Low voltage and
light current system”
renaming
Scope allocation
Annex B - Low
voltage and
light current
systems/5.2.6
Project Designer
Agreement
232.
The Tender Documents remain
unchanged.
For the avoidance of doubt, the
Project Designer will be
required to prepare the design to
the extent needed to promote
and carry out Infra 2 Tender.
The tasks description it identical as text
under 4.2.28
In our understanding, Rail/LRT signaling is
part of the INFRA 2. Please confirm.
Rail Signaling – scope
definitions
Annex B - 5.
Technical
Engineering
Documents for
Infra 2 Tender /
5.2. Design for
INFRA 2
Tender / Low
voltage and
light current
systems 5.2.6.3
Project Designer
Agreement
233.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that the
Project Designer will be
required to prepare its design to
the extent needed to promote
and carry out Infra 2 Tender.
For the avoidance of doubt,
traffic lights that are required to
the operation of roads will be
installed during Infra 1 works.
Any changes to infrastructure or
operating of traffic lights that
are required to the
implementation of the LRT
system will be carried out by the
Infra 2 contractor.]
Tasks description is identical as task
provided under the 4.2.29
In our understanding the Traffic Light
Signaling is part of the INFRA 2 scope of
the services.
Please confirm and/or comment
accordingly.
Traffic light signaling –
allocation to INFRA 1 or
INFRA 2
5. Technical
Engineering
Documents for
Infra 2 Tender /
5.2. Design for
INFRA 2
Tender / Low
voltage and
light current
systems/5.2.6.4
Project Designer
Agreement
234.
The Company clarifies that the
Project Designer will be
required to prepare its design to
the extent needed to promote
and carry out Infra 2 Tender.
The tasks description is identical as text
given under 4.2.31
In our understanding that the Depot and
workshop related tasks/services are part of
the INFRA 2. Only civil and building MEP
will be part of Infra 1) - please confirm.
Depot and workshop Annex B - 5.
Technical
Engineering
Documents for
Infra 2 Tender /
5.2. Design for
INFRA 2
Tender / Depot
and workshop
(5.2.8 / 5.2.9)
Project Designer
Agreement
235.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that the
Project Designer will be
required to prepare the design to
the extent needed to promote
and carry out Infra 2 Tender.
For the avoidance of doubt, the
Project Designer will set
requirements of the RS to be
provided by the Infra 2
contractor that may include
records of the vehicle, tests and
RAMS.
Please be aware that at the current stage of
the design & build process – technical
engineering work for the preparation of the
Infra 2 Tender, Rolling Stock design
records, prototype tests and RAMS
documents are not available and cannot be
delivered as such by the Project Designer.
As part of the “D&B” Rolling stock
tendering process, Project Designer can
prepare technical part of the Rolling Stock
procurement tender, with a content similar
to the SoW provision given under the 3.7.
Rolling Stock.
These above-mentioned required items can
be only delivered by the Rolling Stock
Supplier as part of the procurement / testing
& commissioning process.
Please confirm accordingly.
Please specify the Project Designer’s scope
of service in regard to the Rolling stock for
the Design for INFRA 2 Tender.
Design record of the
vehicle, Prototype tests
and RAMS availability at
this design stage
Annex B - 5.
Technical
Engineering
Documents for
Infra 2 Tender /
5.2. Design for
INFRA 2
Tender /Rolling
Stock (5.2.10)
Page 63
Project Designer
Agreement
236.
The Project Designer will be
required to prepare its design to
the extent needed to promote
and catty out Infra 2 Tender.
For the avoidance of doubt,
clause 5.2.12.4 relates to the
It is our understanding that for the purposes
of the engineering works for the INFRA 2
Tender no power supply simulation of the
energy supply and distribution systems is
required (based on the common scope
understanding and previous experience).
Draft power supply calculations should be
Energy consumption Annex B - 5.
Technical
Engineering
Documents for
Infra 2 Tender /
5.2. Design for
INFRA 2
Project Designer
Agreement
237.
Response Clarification/Question Subject Section Document Name No.
operational planning (energy
demands)
sufficient in this regard, while the real
simulation should be done by the System
OEM (Original Equipment Manufacturer).
Please confirm the necessity of the power
supply execution (as well as the availability
of any input data) and/or comment
accordingly.
Tender
/Operation and
maintenance
plans/5.2.12.4.6
The design of the platform width
is one of the Project Designer’s
tasks.
Please clarify what is the correct minimum
platform width, if any, to enable the
participant to calculate the design efforts
needed.
Platform width Annex B - 5.2.7
Project Designer
Agreement 238.
The Project Designer will
provide quantities and cost
estimate for each tender package
at the level that corresponds to
the scope and type of the
applicable tender.
The “Quantities and cost estimates” chapter
is a repetition of the “build only” tender
requirements previously mentioned under
4.3.7.
The Company was requested to provide the
valid scope description of the Project
Designer’s services for the Infra 2 PPP /
design & build tender.
Quantities and cost
estimates
Annex B - 5.
Technical
Engineering
Documents for
Infra 2 Tender /
5.2. Design for
INFRA 2
Tender
/Quantities and
cost estimates
(5.2.15)
Project Designer
Agreement
239.
The Tender Documents remain
unchanged.
At the design stage, the Operations and
Maintenance (O&M) costs can be only
estimated on the basis of the high-level
assumptions as far the operation and
maintenance planning depend on the
Operations and
Maintenance (O&M)
Costs
Annex B - 5.
Technical
Engineering
Documents for
Infra 2 Tender /
Project Designer
Agreement
240.
Response Clarification/Question Subject Section Document Name No.
systems implemented by the PPP
Contractor/O&M operator.
Can the Company confirm this assumption?
5.2. Design for
INFRA 2
Tender
/Quantities and
cost estimates
It is clarified that there is no
change in the Tender
Documents.
Based on the requirement "the interval is 4
minutes in the two directions between Haifa
and Nazareth", mixed traffic section like
level crossing exists for tramcar and social
vehicles, the exclusive road right cannot be
ensured, e.g. the operation interval of the
whole line cannot be ensured.
General descriptions Annex B - 5(d) Project Designer
Agreement
241.
The Company clarifies that the
detailed procurement strategy
will be finalized during the
design period. The Project
Designer will be responsible for
providing all technical
deliverables and consultancy to
the Company with preparing the
Tender package.
Please clarify the tendering approach to be
undertaken for the purposes of the INFRA 2
Tender, namely: tendering strategy (1 or 2
staged), Project Designer’s tasks in the
tendering process, envisaged duration,
turnkey or separated contracts, etc.
Is the Project Designer only accountable for
the technical part/specifications of the
tender or for the whole tender preparation,
issuing and evaluation – including the
administrative, legal, etc. topics?
Tender process –
approach and strategy
Annex B - 5.
Technical
Engineering
Documents for
Infra 2 Tender /
5.2. Design for
INFRA 2
Tender /5.3
Tender Process
& 5.4.
Proposals
Submission and
Evolution &
5.5. Award of
the Contract
Project Designer
Agreement
242.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that the
Project Designer will be
required to prepare the
specifications and all
preparations for Infra 1 at a
Detailed Design level, including
all the tests required for this
purpose.
In addition, it will be required to
mapping of all the potentials to
receive stray currents.
The Company was requested to clarify what
would be required from the Project
Designer in terms of stray current analysis
(calculations, etc.)
Stray Current Annex B -
5.2.3.6
Project Designer
Agreement
243.
For the avoidance of doubt, the
As Built maps will be prepared
by the surveyor and the Project
Designer is required to check
and verify execution according
to design.
Participants’ attention is drawn
to the provisions of Section 9.4.
of Annex “B” (The Services) to
the Agreement.
The As Built maps are to be prepared and
signed by licensed surveyor of the
contractor and not of the Project Designer.
The Project Designer, when receives the
maps in paper and digital format, may
check its conformity or non-conformity
with the design.
Please clarify that the Project Designer
surveyor is not expected to perform survey
of works during construction.
As Built maps Annex B - 5.9 Project Designer
Agreement
244.
The Company confirms that the
Designer will be required to
provide all the deliverables
stated in clauses 5.2.10.1 -
5.2.10.4 in accordance with the
requirements of clause 5.1 of
Annex B (The Services).
In this section it is indicated that the
Designer will have to provide all
documentation listed in paragraph 5.2.1.
We understand that the Designer will have
to prepare documentation listed in 5.2.1 at a
technical specification level, to be included
Rolling Stock
Deliverables
Annex B –
5.2.10.1
Project Designer
Agreement
245.
Response Clarification/Question Subject Section Document Name No.
in a tender for the procurement of rolling
stock. Please confirm if our understanding
is correct.
The Company confirms that the
Designer will be required to
provide all the deliverables
stated in clauses 5.2.10.1 -
5.2.10.4 and in accordance with
the requirements of clause 5.1 of
Annex B (The Services).
From our experience, is the Manufacturer
who usually carries out deliverables of
sections 5.2.10.2, 5.2.10.3 and 5.2.10.4.
We understand that what has to be done by
the Designer is to prepare a list of
documents/characteristics. This list of
documents/characteristic will define what
the Manufacturer has to prepare in order to
get Client´s approval. .
Rolling Stock
Deliverables
Annex B –
5.2.10.2
5.2.10.3
5.2.10.4
Project Designer
Agreement
246.
The request is rejected.
The Company clarifies that the
Project Designer will be
responsible for approving
materials which will be used at
the Site.
Tasks listed under the clauses 6.3.1, 6.3.5.
and 6.3.6. refer to the On-site Supervision
Engineer’s scope of services and cannot be
performed by the Project Designer
performing the Supreme Supervision with
quite limited presence on site (e.g. -1 or 2
days a week on site).
Supreme supervision
scope of work/list of tasks
– MOS and materials
approval
Annex B - 6.
Supreme
Supervision for
Infra 1
Works/6.3
Construction
Site supervision
Milestones/Aut
horization of
the MOS and
materials/ 6.3.1.
and 6.3.5. and
6.3.6.
Project Designer
Agreement
247.
The reference to Chapter 6 is
unclear.
The Company was requested to clarify the
Project Designer’s scope as it relates to
Supreme supervision
scope of work/Inspections
Annex B - 6.
Supreme
Project Designer
Agreement 248.
Response Clarification/Question Subject Section Document Name No.
In addition, Rolling Stock is not
part of Infra 1.
inspection services for Rolling Stock
production.
Our understanding is that the tasks related
to the factory acceptance tests and factory
production visits/tests will be executed by
the On-Site Supervision and should not be
part of the Supreme Supervision’s scope.
Please confirm the above stated and/or
clarify accordingly.
Supervision for
Infra 1
Works/6.3
Construction
Site supervision
Milestones /
The Course of
the execution /
6.3.8
Pages 67
These tasks are part of the
Supreme Supervision for Infra 1
Works.
The Tender Documents remain
unchanged.
The Project Designer’s task to check and
approve in writing the conformance and
compliance of the “as-build” documents is
only possible after the PTO (permit to
operate) and cannot be executed by the
Project Designer at this project stage. Based
on the previously mentioned the whole
process would go beyond the envisaged
project timelines.
Also, in our understanding these tasks
belong to the On-Site Supervision Engineer
and should be removed from the Project
Designer’s scope.
Please comment and clarify accordingly.
Approval of the as-built
documents
Annex B - 6.
Supreme
Supervision for
Infra 1
Works/6.3
Construction
Site supervision
Milestones/Co
mpleted
execution and
delivery of the
Project/6.3.18
Page 68
Project Designer
Agreement
249.
The Company clarifies that the
term the quality assurance
manager was deleted.
Please specify the requirements and the role
and responsibility of the “quality assurance
manager”.
Organization – Quality
Assurance Manager
Annex B - 6.3.2 Project Designer
Agreement 250.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that the
Project Designer will be
required to supervise all the
works executed based on its
design, in both Infra 1 and Infra
2.
According the tentative project schedule,
the supreme supervisions of Infra 1 and
Infra 2 related works are to be performed in
different time lines (overlapping only for 1
year), which cannot cover the whole
interface coordination between Infra 1 and
Infra 2.
Please clarify and comment accordingly the
above stated.
Civil Works component
in the INFRA 2 Supreme
Supervision part
Annex B - 7.
Supreme
Supervision for
Civil Work of
Infra 2
Works/7.1.1
Page 68
Project Designer
Agreement
251.
The Company clarifies that the
term systems works refer to all
of the railway components.
The Tender Documents remain
unchanged.
According to the common practice and
understanding of technical issues, the
procurement of rolling stock should be
treated as a separate item and not to be
listed as part of the Systems related works
as indicated in 7.1.2.
We would kindly ask you to specify the
“etc.” and to explicitly list the systems to be
covered by the Project Designer as part of
the “systems works”.
Rolling Stock
procurement under the
System works
Annex B - 7.
Supreme
Supervision for
Civil Work of
Infra 2
Works/7.1.2
Page 68
Project Designer
Agreement
252.
The Company clarifies that such
manual will not be provided
thereby at the beginning of the
preliminary design.
Participants’ attention is drawn
to the provisions of sections 3.1
and 3.3. of Annex “B” (The
Services) to the Agreement.
The Company was requested to clarify
whether an architectural design manual or
guidelines will be provided as an input at
start of preliminary design?
Architectural design
manual/guidelines
Annex B –
7.2.
Project Designer
Agreement
253.
לא סמן :מעוצב
Response Clarification/Question Subject Section Document Name No.
The Company so confirms.
Participants’ attention is drawn
to the provisions of Sections
2.4.10 of Annex B (The
Services) to the Agreement.
The Company was requested to confirm
that the cost of boreholes, field tests and
test pits will be borne by the Company and
if not, in which milestone the geotechnical
survey will be included.
The Project Designer's
Deliverables
Annex B - 7.2.3 Project Designer
Agreement
254.
The Project Designer will be
responsible for preparation of
CSD during all of the Project
stages, including the Infra 2
stage, until the completion of the
Inra 2 Construction works.
Spatial requirements of the supplier and
interfacing parties will only become
available after award of the PPP contract
and once the PPP contractor’s designers
have finalized their design.
This will be after most of the Infra 1 works
will be implemented. Please explain how
the described approach can work for CSD’s
and SEM’s by the anticipated time
schedule.
Under the given approach the Project
Designer could only provide CSD’s and
SEM’s for the Final Design Stage.
For the Detailed Design the Project
Designer would be dependent on the PPP
Contractor’s Designer without any direct
contractual relation.
It’s not clear how the Project Designer can
anticipate and calculate the required
workload, effort and manpower on such an
unknown input.
Please clarify the above stated and
confirm/comment the topic accordingly.
CSD (Combined Service
Drawings) & SEMs
(Structural electrical
Mechanical Drawings)
Annex B - 8.
Combined
Service
Drawings
Page 69
Project Designer
Agreement
255.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that
Design Management processes
are relevant only to the design
prepared by the Project
Designer.
We assume the Design Management Plan
covers only the design for Infra 1 up to
Detailed Design and for Infra 2 up to Final
Design, excluding the PPP Contractor’s
design services.
Please confirm/comment accordingly.
Scope of design
management process
Annex B - 9.
Design
Management
process
Page 70
Project Designer
Agreement
256.
Without derogating from the
provisions of the Tender
Documents, the Company
clarifies that the division into
teams is relevant for the
provision of Detailed Design
only.
Each team member will be
required to meet the relevant
conditions, as stipulated in the
Agreement.
The SoW specifies 5 respective INFRA 1
teams to be created for the execution of the
whole Design management Process.
Please clarify whether there is a similar
requirement for the INFRA 2 related
activities with clear distinction between the
involved teams.
INFRA 1 Teams versus
INFRA 2 Teams
Annex B - 9.
Design
Management
process/9.1.7.1
Project Designer
Agreement
257.
The Design Management Plan
(DMP) is relevant to all the
design tasks of the Project
Designer, regardless of the
division between Infra 1 and
Infra 2.
It is our understanding that the Design
Management Plan (DMP) to be prepared by
the Project Designer will cover design
activities up to the Detailed Design for
INFRA 1 and up to the Final Design for
INFRA 2.
In case of the INFRA 2 related topics, the
DMP cannot cover the CSD’S since it will
be done by the PPP Contractor Designer.
Please clarify our above given
Design Management Plan
update
Annex B - 9.
Design
Management
Process / 9.1.
Design
management
Plan/ /9.1.8
Project Designer
Agreement
258.
Response Clarification/Question Subject Section Document Name No.
understanding and/or comment accordingly.
The Company clarifies that the
section refers to all prototypes
and/or models which shall be
required by Relevant
Authorities.
The Company was requested to clarify what
mockups / prototypes / models are expected
to be produced by the Designer.
Complete prototypes,
mock-ups, samples,
models, etc.
Annex B - 9.
Design
Management
Process / 9.2.
General Design
Requirements
/9.2.3.13 /
9.4.17.7
and
Clause 9.4.18.1
and 9.4.18.2
Project Designer
Agreement
259.
The request is rejected.
The Company was requested to define the
term “design materials”, which required to
be provided by the Project Designer.
Provision of design
materials
9. Design
Management
Process / 9.2.
General Design
Requirements
/9.2.3.15
Project Designer
Agreement
260.
The request is rejected.
The Tender Documents remain
unchanged.
The Company was requested to exclude the
“Ensurance” of the durability of the
installed material and equipment from the
project Designer’s liability since it can be
done only by the Contractor, Supplier and
OEM’s (warranties, defect notification
periods, etc.).
Ensure Durability Annex B - 9.
Design
Management
Process /
General Design
Requirements /
The Designer /
9.2.6.1.
Project Designer
Agreement
261.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the provisions of Sections
9.2.4 of Annex B (The Services)
to the Agreement.
The Company was requested to clarify
whether the Company would nominate a
design management entity.
Design Manager
Annex B - 9.2.4
Project Designer
Agreement 262.
The request is rejected. The
Company clarifies that the
provisions of this section relate
only to the design carried out by
the Project Designer.
The Company was requested to exclude the
following tasks and activities from the
Project Designer’s scope: (i) the task
related to the “ensurance” of the safety
during the construction and installation
since said ensurance should be executed by
the PPP Contractor (directly) and the On-
Site Supervision Engineer (indirectly)
executing the daily on-site CIW
supervision.
(ii) the Safety during the O&M activities
since said activities can be only ensured by
the respective O&M Operator and their
implemented Safety Management System.
Ensure safety during
construction, operation
and subsequent
maintenance of the LRT
line
Annex B - 9.
Design
Management
Process /
9.2.General
Design
Requirements /
The Designer /
9.2.6.2.
Page 73
Project Designer
Agreement
263.
The Company clarifies that the
Project Designer is required to
carry out a risk assessment for
its design only. In addition, the
Project Designer shall be
required to assist the Company
and provide professional support
for the preparation of a general
risk assessment.
The Project Designer shall prepare and
document the Risk Assessment for all
respective project stages.
Mitigation of risks (as far as practicable)
can be done by the Project Designer up to
(inclusive of) the Detailed Design for the
INFRA 1 – since the Project Designer will
be accountable / responsible for the
execution of the design.
Please confirm the above stated and/or
Detailed and documented
risk assessment (INFRA
1)
Annex B - 9.
Design
Management
Process /
9.2.General
Design
Requirements /
The Designer /
9.2.6.3.
Project Designer
Agreement
264.
Response Clarification/Question Subject Section Document Name No.
clarify accordingly.
The Company clarifies that the
Project Designer is required to
carry out the Risk Assessment
only for the design prepare
thereby. In addition, the Project
Designer shall be required to
contribute to the preparation of a
general risk assessment.
The Project Designer shall prepare and
document the Risk Assessment for all
respective project stages.
Mitigation of risks (as far as practicable)
can be done by the Project Designer up to
(inclusive of) the Final Design for the
INFRA 2 – since the Project Designer will
be in accountable / responsible for the
execution of the design up to this stage.
Please confirm the above stated and/or
clarify accordingly.
Detailed and documented
risk assessment (INFRA
2)
Annex B - 9.
Design
Management
Process /
9.2.General
Design
Requirements /
The Designer /
9.2.6.3.
Project Designer
Agreement
265.
The Company clarifies that
Section 9.2.8 refers to the
management of the schedule for
the design only, throughout the
design and execution stages of
the Project.
Baseline project Schedule indicating the
design schedule for submission of each
design package under the project
Designer’s scope cannot be maintained and
updated during the construction stage since
it is only related to the design packages
submission.
To maintain the design schedule for the
PPP Contractors designer (related to Infra 2
works) is a task for a so called Project
Management Consultant (PMC) who
should be engaged directly by the Client
(Company) to manage and supervise the
“third parties” input.
Is it the intention of the Company that these
Baseline Project Schedule
during the “construction
stages”
Annex B - 9.
Design
Management
Process /
9.2.General
Design
Requirements /
The Designer /
9.2.8
Project Designer
Agreement
266.
Response Clarification/Question Subject Section Document Name No.
tasks should also fall within the Project
Designer’s scope?
Please confirm the above stated and amend
the item accordingly.
The Company clarifies that the
Monthly Progress Reports refers
only to tasks designed by the
Project Designer, regardless of
the division into Inra 1 and Inra
2.
Project Designer can only indicate all
design submissions coming from its own
teams forking on the INFRA 1 and INFRA
2 activities up to the Supervision stages for
both packages.
Design submissions coming from the
Concessionaire’s Designers (INFRA 2)
and/or Successful Contractors (INFRA 1)
cannot be tracked and listed as such in the
PD’s Monthly report since there is no
contractual link between the involved
parties, namely: PD, Concessionaire and
Contractors.
Please confirm the above stated and/or
clarify accordingly.
Status of all design
submissions and
Designs changes as part
of the Monthly Progress
Report
Annex B - 9.
Design
Management
Process /
9.2.General
Design
Requirements /
Design
Schedule / 9.2.9
and 9.2.210
Project Designer
Agreement
267.
The request is rejected.
The Company was requested to clarify
whether the nomination of the design
checker will be made by the Company or
the Project Designer,
In addition, the Company was requested to
clarify whether the Design Checker
incorporation will be on the Company's
expense.
Designer’s Design
Checker role and mandate
Annex B - 9.
Design
Management
Process / 9.2.
General Design
Requirements /
Design Checker
/ 9.2.11 – 9.2.14
Page 73 and 74
Project Designer
Agreement
268.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that there
are no differences between the
design quality and design
packages allocation
requirements for INFRA 1 and
INFRA 2.
The Company was requested to clarify
whether there are different design quality
and design packages allocation
requirements for the INFRA 1 and INFRA
2 work batches based on their internal
differences and requirements.
Design Quality and
Design packages for
INFRA 1 and INFRA 2
Annex B - 9.
Design
Management
Process / 9.2.
General Design
Requirements /
Design Quality
and Design
packages
Project Designer
Agreement
269.
The Company clarifies that the
Project Designer will be
required to amend any
document, as shall be required
by the Company.
The Company was requested to clarify the
approach and the further activities/actions
in case of a quality insufficient design
provided by a Concessionaire referring to
CSD’s and SEM’s, paragraph 8.
Integration of any
requirements arising from
the Company’s review of
the applicable design
Annex B - 9.
Design
Management
Process / 9.3
Project Reviews
and Reporting /
9.3.3.3
Project Designer
Agreement
270.
The request is rejected.
We consider that the software to be used
should be such that is still supported by the
manufacturer or, alternatively, Microsoft
Office 2013 + 2016 and up. Please rephrase
the requirement.
Similarly, we ask to apply this requirement
also to other software and design tools, if
applicable, such as Microsoft Windows 7 +
10 (64bit), AUTOCAD 2018 [ICE (by
IDAN)], etc.
Please confirm the above stated and/or
comment accordingly.
MS Office software
“latest version”
Annex B - 9.
Design
Management
Process / 9.3
Project Reviews
and Reporting /
Presentations /
9.3.8.
Page 76
Project Designer
Agreement
271.
Response Clarification/Question Subject Section Document Name No.
As of this date, the Company
has not yet contracted with a
service provider for this
purpose.
The Company was requested to provide
name(s) type(s) of the EDMS expected to
be used.
Please clarify the technical feature of the
EDMS to be provided by the Company
including the user rights for various
involved parties: Project Designer,
Contractors, Concessionaire, etc.
The clarification is required to know
whether the Project Designer shall create
and run in parallel another DMS for internal
documentation storage and management
purposes.
Electronic Document
management Systems
(EDMS)
Annex B - 9.
Design
Management
Process / 9.3
Project Reviews
and Reporting /
Company’s
design review
process / 9.3.16
Page 77
Project Designer
Agreement
272.
The Project Designer is not
required to prepare the AS-
BUILT design, but only to
approve it.
In the Stage 5, the task description refers to
the supervision.
We consider that instead, it should say
"supreme supervision", since the on-situ
supervision does not pertain to the Project
Designer's tasks and duties.
Having in mind the above stated, the
preparation of the “as-built” design
packages as well as checking and approval
of their compliance with the executed
construction and installation works should
be also allocated to the On-Site
Supervision.
Please confirm our above presented
understanding and/or comment accordingly.
Design Package Stages
(Stage 5)
Annex B - 9.4.
Designer’s
Design Package
Submission
Process / 9.4.7 /
Stage 5
Project Designer
Agreement
273.
Response Clarification/Question Subject Section Document Name No.
This section relates to the type
of design and not to the design
requirement for a specific
component. The requirements
for each component appears in
previous chapters.
It is clarified that Infra 2
contains components which are
at a different design level,
according to the applicable
requirements.
It is our understanding that for the INFRA 2
scope of services, provision of the Detailed
Design related deliverables for the
respective systems/sub-systems will be
provided by a successful Concessionaire on
the PPP tender. Based on the previously
stated, services listed under 9.4.17.2. should
be taken out of the Project Designer’s scope
of services.
Design Packages of
systems/sub-systems
Annex B - 9.
Design
Management
Process / 9.4
Designer’s
Design Package
Submission
Process / Stage
3 (Detailed
Design) /
9.4.17.2
Project Designer
Agreement
274.
The Project Designer will be
required to manage its entire set
of documents by using the
system that will be provided to it
by the Company.
Will the Company (via the EDMS)
supervise this task or do the Project
Designer needs to engage its own
requirements Manager and Requirements
Management Expert (s)?
Design quality assurance /
requirements management
Annex B - 9.
Design
Management
Process / 9.4
Designer’s
Design Package
Submission
Process / Stage
3 (Detailed
Design) /
9.4.17.4
Project Designer
Agreement
275.
The Company clarifies that the
Project Designer shall be
required to base its design on the
level of the design of each
system, as shall be defined by it,
Detailed design is only provided for the
Infra 1 packages.
At this stage the detailed design of the Infra
2 package, to be produced by the PPP
Contractor, will not be available.
Combined and integrated
design and applicable
works
Annex B - 9.
Design
Management
Process / 9.4
Designer’s
Project Designer
Agreement
276.
Response Clarification/Question Subject Section Document Name No.
Regardless of the division
between Infra 1 and Infra 2.
Based on which data/inputs should the
integration be done for the Infra 2 systems?
Design Package
Submission
Process / Stage
3 (Detailed
Design) /
9.4.17.3
The level of design is defined
for each component.
In any case where the Project
Designer will be required to
design at a Detailed Design
level, it shall comply with the
provisions of section 9.4.17.4.
Please specify, test data, reports, samples in
detail to be provided from the Project
Designer.
We understand that it could be only
delivered for the Infra 1 since the Detailed
Design will be delivered. We assume that
all hardware related samples shall be
provided by the future Contractor /
Concessionaire / OEM (Original Equipment
Manufacturer)?
All details, test data,
reports, samples of
images, etc.
Annex B - 9.
Design
Management
Process / 9.4
Designer’s
Design Package
Submission
Process / Stage
3 (Detailed
Design) /
9.4.17. 4
Page 81
Project Designer
Agreement
277.
Participants’ attention is drawn
to the provisions of the revised
Annex “B” (The Services) to the
Agreement.
Please specify, test data, reports, samples
more in detail to be provided from the
Project Designer.
We understand that it could be only
delivered for the Infra 1 since the Detailed
Design will be delivered. We assume that
all hardware related samples shall be
provided by the future Contractor /
Concessionaire / OEM?
Full-size mockups and/or
prototypes
Annex B - 9.
Design
Management
Process / 9.4
Designer’s
Design Package
Submission
Process / Stage
3 (Detailed
Design) /
Project Designer
Agreement
278.
Response Clarification/Question Subject Section Document Name No.
9.4.18.1
Page 82
Participants’ attention is drawn
to the provisions of the revised
Section 9.4. of Annex “B” (The
Services) to the Agreement.
Alternative products and materials
variations cannot be provided by the Project
Designer and (if so) they can be only
provided by the Contractor or Supplier
during the construction and installation
works – design execution.
Alternative products and
materials
Annex B - 9.
Design
Management
Process / 9.4
Designer’s
Design Package
Submission
Process / Stage
3 (Detailed
Design) /
9.4.18.2
Project Designer
Agreement
279.
The Company clarifies that the
Project Designer may propose
alternatives to all of the design
disciplines according to the level
of design required from it in
each discipline.
In our understanding tasks described under
the 9.4.18.2.4. are contradicting the 5.1.1.
tasks of the Project Designer given
previously under the 5. Technical
Engineering Documents for Infra 2
Tender/5.1.1. We assume and understand
that this task is related to the Contractor’s
Designers?
Contradicting to the
Project Designers tasks
for the Infra 2 Tender
works
Annex B - 9.
Design
Management
Process / 9.4
Designer’s
Design Package
Submission
Process / Stage
3 (Detailed
Design) /
9.4.18.2.4
Project Designer
Agreement
280.
The requirements stipulated
under those clauses refers to the
level of design required from the
Project Designer in each
Please confirm that the requirements
stipulated under the following paragraphs:
9.4.19, 9.4.20, 9.4.21 and 9.4.22 are only
valid for the INFRA 1 related works and
Construction design
packages requirements
Annex B - 9.
Design
Management
Process / 9.4
Project Designer
Agreement 281.
Response Clarification/Question Subject Section Document Name No.
discipline, regardless of the
division into Infra 1 and Infra 2.
are not applicable as such for the INFRA 2. Designer’s
Design Package
Submission
Process / Stage
4 (Construction
Design
Packages) /
9.4.19,
9.4.20,9.4.21
and 9.4.22
The Company clarifies that the
Project Designer will be
required to perform supreme
supervision on its Detailed
Design, regardless of in which
tender package it was included.
The “as-built” design Packages can only be
proved by a full on-site supervision
engineer and not by a supreme supervision
entity, with a limited presence on site of
e.g. once a week. To fulfill this task a full
on site supervision would be required.
Please clarify and comment accordingly?
Is this only valid for the INFRA 1 or the
INFRA 2 or for both?
As-built drawings for
INFRA 1 and INFRA 2
Annex B - 9.
Design
Management
Process / 9.4
Designer’s
Design Package
Submission
Process / Stage
5: As-Built
Design
Packages /
9.4.27
Project Designer
Agreement
282.
The request is rejected.
Infra 1 design and design deliverables
should be in Hebrew only. Please
acknowledge.
Infra 1 language of
documents
Annex B -
9.2.15.1
Project Designer
Agreement 283.
Response Clarification/Question Subject Section Document Name No.
The Company clarifies that the
Project Designer is required to
provide the design of Road 781,
including the LRT installations,
as specified under Annex “B”
(The Services) to the
Agreement.
The Tender Documents remain
unchanged
Road 781 works have been indicated as a
separate item in the Price Matrix / Detailed
Price Matrix but not listed as such in Annex
C - Preliminary Schedule.
The Company was requested to confirm
that Road 781 works belong to the INFRA-
1 batch/lot and should be executed as per
the timelines given for the INFRA-1 related
activities.
Road 781 Annex B Project Designer
Agreement
284.
The term “Design Manager”
shall mean Chief Designer.
Please specify the requirements and the role
and responsibility of the “design manager”.
Organization – Design
Manager
Annex B - 9.2.4 Project Designer
Agreement 285.
The Company will provide the
Project Designer with the
license and account information
for its proper use of the EDMS
system.
Please specify if there are any costs
required to be considered by the Project
Designer for the EDMS system.
Document Management Annex B -
9.3.16
Project Designer
Agreement
286.
The request is rejected. Please provide all lists of deliverables in
English.
Lists of Deliverables Annex B - 9.6 Project Designer
Agreement 287.
The request is rejected. Please provide all design guidelines in
English.
Design Guidelines Annex B - 9.8 Project Designer
Agreement 288.
All available reference drawings
were uploaded as part of Annex
B (Reference Design
documents) to the Invitation to
Bid.
Please provide most up-to-date drawings in
DWG format, including general layouts and
cross sections.
DWG Drawings Annex B - 9.8 Project Designer
Agreement
289.
Response Clarification/Question Subject Section Document Name No.
Participants’ attention is drawn
to the provisions of Sections 6
and 7 of Annex “B” (The
Services) to the Agreement.
The Company was requested to clarify
according to which standards should the
supreme supervision be conducted?
Supreme supervision Annex B - 11.3 Project Designer
Agreement 290.
The request is rejected.
Please erase the words “unless the company
determines otherwise”.
Language of the Project Annex B - 17.2 Project Designer
Agreement 291.
The request is rejected.
Please confirm that the Company will be
responsible for:
a) all translations required for
coordination process (excluding the
permit/statutory process) and/or
b) All translations from Hebrew to
English of local standards, criteria,
requirements and regulations.
Language of the Project Annex B - 17.2 Project Designer
Agreement
292.
Participants’ attention is drawn
to the provision of section 1.3 of
Annex “D” (Service Price) to
the Agreement.
The Company was requested to clarify
whether the quantities in the Price Matrix
are final or they are estimated quantities
and the final consideration will be
calculated according to the actual quantities
performed by the Project Designer?
Service Price Annex D Project Designer
Agreement
293.
The Company clarifies that there
will not be additional
compensation for multiple
tenders.
Participants’ attention is drawn
to the provisions of Annex “D”
(Service Price) to the
The Company was requested to clarify how
will the design team be rewarded due to
multiple tenders?
additional payments Annex D Project Designer
Agreement
294.
Response Clarification/Question Subject Section Document Name No.
Agreement.
The Company clarifies that the
Project Designer shall provide
the Company with professional
services with respect to Infra 1
tenders evaluation process, to
the extent required by the
Company.
The Company was requested to confirm
that beyond the Technical Engineering
Documents for Infra 1 that are included in
the scope, Professional services for Infra 1
Tender evaluation are not included in the
scope,
Professional services for
Tender
Annex D –
Service Price –
1.3 Price
Matrix.
Project Designer
Agreement
295.
The Company so clarifies.
Participants’ attention is drawn
to the provisions of section 2.4.5
of Annex “B” (The Services) to
the Agreement.
The Company was requested to clarify
whether the following site investigations
are included in the scope: 1. Soil campaign
2. Hydraulics 3. Utility detection.
Site investigations Annex D –
Service Price –
1.4 Detailed
Price Matrix.
Project Designer
Agreement
296.
The Company so clarifies.
Participants’ attention is drawn
to the provisions of sections 3.5
and 4.3 of Annex “B” (The
Services) to the Agreement.
The Company was requested to clarify
whether the following tasks for advance
works is included in the scope: 1. Site
access road 2. Temporary Traffic
management
Advance works Annex D –
Service Price –
1.4 Detailed
Price Matrix.
Project Designer
Agreement
297.
The Company does not have any
information regarding said
document.
The Company was requested to clarify
whether the EIA was performed by a third
party and when would the result be
available?
Economic Impact
Assessment (EIA)
Annex D –
Service Price –
1.4 Detailed
Price Matrix.
Project Designer
Agreement 298.
Response Clarification/Question Subject Section Document Name No.
The request is rejected.
In addition, Participants’
attention is drawn to the
provision of Section 9.3 of
Annex B (The Services) to the
Agreement.
The Company was requested to elaborate in
more details on the requirements of the
Monthly Report content-wise.
Monthly Reports
requirements
Annex D:
Service Price
1.5 Payment
Terms /1.5.1
Project Designer
Agreement
299.
The request is rejected.
The Progress payment in regard to the
Progress Reports and the “Actual Progress”
to be determined by the Company is
unclear.
Could you please clarify it in more details?
Progress payments Annex D:
Service Price
1.6. Progress
Payments
Project Designer
Agreement
300.
Participants’ attention is drawn
to the provision of Section 5.4 of
the Invitation to Bid and Section
2.3.1.1 of the Agreement.
Should this Annex be signed and included
in the proposal as well?
Annex E Annex E
Project Designer
Agreement 301.
A specified SPPI policy is
required in accordance with the
Tender requirements.
Participants’ attention is drawn
to the provisions of Annex G.
Do we have to take out a SPPI for USD
10M per occurrence and per aggregate (for
the duration of liability) or an annual policy
dedicated to the project?
“…professional
indemnity with Limits of
liability of USD
10,000,000 per
occurrence and in the
aggregate for the annual
insurance period”
Appendix G”1”
- Certificate of
Insurance
Professional
Indemnity –
Single-Project
Professional
Indemnity -
SPPI
Project Designer
Agreement
302.
The request is rejected. In the event that the "Project Designer" is
submitted as a Joint Venture comprising the
Insurance requirements Appendix G“1”
Certificate of
Project Designer
Agreement 303.
Response Clarification/Question Subject Section Document Name No.
Lead Design Firm and the Local Design
Firm, we understand that each party may
present their own insurance policies,
individually, in compliance with the
requirements mentioned in this agreement.
Please confirm.
insurance
The request is rejected. Would it be possible to comply with the
insurance limits set forth for the
Professional Indemnity Insurance,
cumulatively, through the PII policies
submitted, individually, by each party?
Insurance requirements Appendix G“1”
Certificate of
insurance
Project Designer
Agreement
304.
The request is rejected.
To comply with the requirements
established for the Professional Indemnity
Insurance, is it possible to submit policies
under the "annual renewable" form in all or
in some of the insurances specifically
required? Please, confirm.
Insurance requirements Appendix G“1”
Certificate of
insurance
Project Designer
Agreement
305.
The Company so confirms. In line with the coverages described, we
understand that it would be possible to
submit insurance certificates to comply
with the requirements established for Third
Party Liability Insurance and Employer's
Liability Insurance through policies
independent of that required for the
Professional Liability Insurance. Please
confirm.
Insurance requirements Appendix G“1”
Certificate of
insurance
Project Designer
Agreement
306.
Response Clarification/Question Subject Section Document Name No.
With respect to the insurance
period for SPPI, participants’
attention is drawn to the
provisions of clause 3 to the
COI, Annex G1.
With respect to other insurances
policies, participants’ attention
is drawn to the policy period
demands for each policy as
detailed in the COI, under
Annex G1.
In relation to the period of duration of the
different insurance coverage required
(Third party liability insurance, Employer's
Liability Insurance, SPPI), the agreement
refers to the fact that these policies must
remain in effect for the duration of the
"insurance period". We understand that this
refers to the duration of the provision of
services. Please, confirm.
Insurance requirements Appendix G“1”
Certificate of
insurance
Project Designer
Agreement
307.
The Company clarifies that the
Project Designer Name can
consist of two names,
nevertheless it required one COI
which will include all the
insureds as specified in the COI
terms.
(a) It is not clear on behalf of whom the
insurance certificate has to be issued.
Since the Participant’s non--
incorporated JV comprises of two
independent firms, the insurer's
certificate cannot refer to the Project
Designer (as stated in clause (2) of
Appendix G1, but to each one of the
members in the JV, separately.
Considering the above stated we
consider it appropriate to modify the
wording in clause (2) of Annex G1, as
well as in all paragraphs where is
appears as such, replacing them by
name of firm member on the JV. Our
aforementioned interpretation is based
Insurance Annex G + G1 Project Designer
Agreement
308.
Response Clarification/Question Subject Section Document Name No.
on the wording at the bottom of page
63, according to which the insurance
certificate should be issued separately
for the Lead Design Firm and the
Local Design Firm.
(b) Will it be accepted that the certificate
will refer independently to each
member of the JV, subject to a reply to
be provided to the question in literal
(a).
Please clarify and/or comment.
Participants’ attention is drawn
to the provision of Sections
2.3.1 of the Agreement.
Should the certificate be signed by the
insurance company and attached included
in the proposal or executed later after being
declared as the Successful Participant?
Insurance Annex G + G1 Project Designer
Agreement 309.
Participants’ attention is drawn
to the provision of Sections
6.3.3-6.3.4 of the Invitation to
Bid. For the avoidance of doubt,
it is hereby clarified that as part
of its proposal each Participant
shall submit the letter of
undertaking signed only by the
members who were presented by
it within the Bid.
According to the comment on top of Annex
F, this letter of undertaking should be
signed by all the team members of the
Project Designer as well by any other
person who fulfils any function according
to the provisions of Annex H.
please clarify whether this Letter of
Undertaking should be signed by the core
team members (only) and included as such
Office Holders Annex H:
Office Holders
in the Project
Designer
Project Designer
Agreement
310.
Response Clarification/Question Subject Section Document Name No.
in the proposal.
Participant’s attention is drawn
to the revised Annex “H” to the
Agreement.
On the list of the Expert Engineers to be
provided on behalf of the Lead Design Firm
it is stated “Traffic Engineer” (4.1.3).
Going further the term “Traffic Signaling
Engineer” (4.2.3) is mentioned under the
same connotation.
Traffic engineer vs
Traffic Signaling engineer
Annex H
4. Expert
Engineers
(Lead Design
Firm)
4.1.3 & 4.2.3
Project Designer
Agreement
311.
The Company clarifies that for
the purpose of this section, only
Detailed Design will be
considered as a professional
experience.
The Company was requested to clarify
whether a project designed in the "Final
Design" stage ('תכנון סופי') will be
considered as professional experience.
Professional experience Annex H:
Office Holders
in the Project
Designer.
5.2.3 Structural
Engineer
Project Designer
Agreement
312.
The expert on behalf the Local
Design Firm will be stated as
Electricity, Communications and
Lighting Engineer or, Dry
Utilities Engineer and it will be
responsible for all dry utilities.
Participants’ attention is drawn
to the amended provisions of
Annex H to the Agreement.
The specialty of the Electrification
Engineer (on behalf the Lead Design Firm)
is defined in clause 4.2.1, and it refers to
train electrification systems. In our opinion,
the term for the expert on behalf the Local
Design Firm should state Electricity,
Communications and Lighting Engineer or,
preferably, Dry Utilities Engineer (similar
to the definition of Wet Utilities Engineer in
Electrification,
Communications and
Lighting Engineer
Annex H:
Office Holders
in the Project
Designer
5.1.9. & 5.2.9
Electrification,
Communication
, lighting
Engineer
Project Designer
Agreement
313.
Response Clarification/Question Subject Section Document Name No.
clause 5.2.8, pages 70-71), with a
responsibility for all dry utilities.
Please confirm and/or comment.
The Company so confirms.
Participants’ attention is drawn
to the revised Annex “H” to the
Agreement.
The Company was requested to clarify
whether the Landscape Architect must have
a degree in Landscape Architecture and not
Civil Engineering.
Threshold conditions for
the Landscape Architect
Annex “H” -
5.2.4.1
Project Designer
Agreement 314.