13
1 TENDER DOCUMENT FOR TRANSPORTATION OF ZJ-70 (R#27) DRILLING RIG FROM MEHSANA (GUJARAT) TO BAREKURI, TINSUKIA (ASSAM) October 5, 2015 Tender no. QOGIL/LOGISTICS/DR-27/002 Dear Sir, Quippo Oil and Gas Infrastructure Ltd. (QOGIL) propose to give a transportation contract for the following: Mobilization of complete ZJ-70 (2000 HP) Drilling Rig and its allied equipment with accessories from Mehsana (Gujarat) to Oil India Limited Drilling Site located at Barekuri Village, Tinsukia in Assam approximate 2950 kilometers. The transporter is required to complete this job within 30 (Thirty) days for the movement of complete rig as per packing list described in Annexure III. Instruction to Bidders:- The prices to be quoted by contractor are for transportation of the equipment for the scope of work given in Annexure I and Contract conditions as per Annexure II. Prices should be on a lump sum basis as per price format in Annexure IV. Experience Criteria: The Contractor should have minimum Experience of at least 2 (Two) nos of Drilling Rig Transportation of 2000 HP Capacity in Assam Region. Contractor shall submit the required documents (Copy of Work order etc) along with the Bid to substantiate the required experience. Confirmation for understanding complete Scope of Work & acceptance of Contract conditions shall be submitted along with the Bid, otherwise bid shall be straight away rejected. Bidder shall submit signed & stamped copy of this tender document as a token of their acceptance for complete understanding of SOW and other terms & conditions. In case of any clarifications required you may contact the following in our Gurgaon Office. Mr. Mahaveer Singh- Manager (Logistics) E-mail: [email protected] Contact no: (M) - + 91-8588841779 & +91-124-6633453 (Direct) Mr. Vishal Parashar- Manager (SCM & C) E-mail: [email protected] Contact no: (M) - + 91-9953024282 & +91-124-6633758 (Direct)

TENDER DOCUMENT FOR TRANSPORTATION OF ZJ …quippoworld.com/tender/Tender_Document_for... · TENDER DOCUMENT FOR TRANSPORTATION OF ZJ-70 (R#27) ... to Oil India Limited Drilling Site

  • Upload
    ngothuy

  • View
    227

  • Download
    0

Embed Size (px)

Citation preview

1

TENDER DOCUMENT FOR TRANSPORTATION OF ZJ-70 (R#27) DRILLING RIG FROM

MEHSANA (GUJARAT) TO BAREKURI, TINSUKIA (ASSAM)

October 5, 2015 Tender no. QOGIL/LOGISTICS/DR-27/002

Dear Sir,

Quippo Oil and Gas Infrastructure Ltd. (QOGIL) propose to give a transportation contract for the following:

Mobilization of complete ZJ-70 (2000 HP) Drilling Rig and its allied equipment with accessories from

Mehsana (Gujarat) to Oil India Limited Drilling Site located at Barekuri Village, Tinsukia in Assam

approximate 2950 kilometers. The transporter is required to complete this job within 30 (Thirty) days

for the movement of complete rig as per packing list described in Annexure III.

Instruction to Bidders:-

The prices to be quoted by contractor are for transportation of the equipment for the scope of work given

in Annexure – I and Contract conditions as per Annexure – II. Prices should be on a lump sum basis as per

price format in Annexure IV.

Experience Criteria: The Contractor should have minimum Experience of at least 2 (Two) nos of Drilling

Rig Transportation of 2000 HP Capacity in Assam Region. Contractor shall submit the required documents

(Copy of Work order etc) along with the Bid to substantiate the required experience.

Confirmation for understanding complete Scope of Work & acceptance of Contract conditions shall be

submitted along with the Bid, otherwise bid shall be straight away rejected.

Bidder shall submit signed & stamped copy of this tender document as a token of their acceptance for

complete understanding of SOW and other terms & conditions.

In case of any clarifications required you may contact the following in our Gurgaon Office.

Mr. Mahaveer Singh- Manager (Logistics)

E-mail: [email protected]

Contact no: (M) - + 91-8588841779 & +91-124-6633453 (Direct)

Mr. Vishal Parashar- Manager (SCM & C)

E-mail: [email protected]

Contact no: (M) - + 91-9953024282 & +91-124-6633758 (Direct)

2

Sealed quotations are invited in price format as per Annexure IV so as to reach our Gurgaon office latest by

5.00 PM on 14th

October, 2015 at below mentioned address:

Attn: Mr. Sanjeev Ranjan- Head - SCM

Quippo Oil and Gas Infrastructure Ltd.

6th Floor, Plot No. 14 A, Sector-18 | Maruti Industrial Complex | Udhyog Vihar |

Gurgaon-122 015 | Haryana | India|

Bid submitted by e-mail before the bid closing time and date is also acceptable but shall be addressed only to:

Mr. Sanjeev Ranjan (Head-SCM)

E-mail: [email protected]

Mr. Mahaveer Singh- Manager (Logistics)

E-mail: [email protected]

Price bid should not be submitted to anybody else; otherwise your offer will be liable for rejection.

Thanking you,

Yours faithfully,

For Quippo Oil and Gas Infrastructure Ltd.

Sanjeev Ranjan

Head- SCM

3

Annexure I

SCOPE OF WORK

1. Loading, Unloading ,and Transportation of ZJ-70 (2000 HP) Drilling rig and it’s allied equipment as per

packing list by placing of required numbers of trailers / trucks, Labour and cranes etc., as per instructions

of QOGIL representative. Transportation route is from Mehsana (Gujarat) to Oil India Limited Drilling

Site located at Barekuri Village, Tinsukia in Assam approximate 2950 kilometers.

2. All Levies sale tax and duties, Toll tax, Border Clearance, Road tx, RTO fine/ penalty etc charges shall be

sole responsibility of Contractor at its own cost.

3. The entire job of ZJ-70 (2000 HP) Drilling Rig & accessories transportation comprises of the following:

a) The Contractor’s representative shall get the trailers and trucks loaded in the order of priority as indicated

by QOGIL’s supervisors. The trailers and trucks will be placed at loading site on timely basis. Contractor

should specify the free time, which he would give for loading purposes.

b) The loads of equipment’s shall be transported from Mehsana using Contractor’s own or hired trucks and

trailers in the proper order as determines by QOGIL’s authorized representatives. (Securing and lashing

instructions are given in terms and conditions and will be Contractor’s responsibility including all lashing

materials).

c) QOGIL will keep the right to change the List of items to be transported with prior notice to Contractor.

d) The truck and trailers will be unloaded by the Contractor at Tinsukia location at the place indicated by the

QOGIL’s supervisor.

e) The transporter is required to complete the job within time frame of 30 (Thirty) days for complete rig as

defined in Annexure III from Mehsana to Oil India Limited Drilling Site located at Barekuri Village,

Tinsukia, Assam. If Contractor fails to complete the job within this period, then QOGIL will have a right

to charge penalty for delayed delivery.

Basic information:

Distance between old and new location – 2950 km Approx.

Trailer quantity – 90 ± 5 Trailers (Approx.)

Road condition – Will be provided by you but should be acceptable for heavy loads.

Total rig move duration – 30 days approx.

Date of rig move start – 1st November, 2015 (tentative date)

Our experience indicates that the rig moving CONTRACTOR will need a minimum:

02 Nos of 50 ton crane at Loading Point at Mehsana, & 02 Nos of 50 tn. cranes at Unloading Point Oil India

Limited Drilling Site located at Barekuri Village, Tinsukia, Assam till Rig Building, approximate One

Month.

Contractor shall provide the list of equipment & Loads required for this move along with your Bid.

4

You are requested to submit with your offer with the following information:

Road Route with distance + Road route map.

Road condition report ( if possible with photographs)

A lump sum mobilization cost for the loading, unloading & transportation of ZJ-70 (2000 HP) Drilling Rig

including rig up to new well location at Oil India Limited Drilling Site located at Barekuri Village,

Tinsukia, Assam field.

Price shall be exclusive of applicable service tax, but inclusive of all other taxes. Fuel for Trailers and

Crane/Forklift etc. will be sole responsibility of the Contractor.

Additional cost on a per load basis and / or per day basis, should additional loads other than those in the

attached load lists be transported to same location.

CONTRACTOR is required to affirm its familiarity with the route (s) to be used for the mobilization of

the RIG and CAMP, along with any and all existing or potential obstructions and weather-related

problems, and will select the route (s) to be used accordingly.

CONTRACTOR will be responsible for securing all necessary transportation / route access permits, at its

sole cost.

Please indicate in your offer your "best estimate" for the total time necessary to complete the move of the

RIG and CAMP to new location, as well as when you will be able to commence moving the RIG and the

CAMP.

Please provide a complete list of all cranes, trailers, trucks, and other equipment that you will commit to

this job. All equipment provided by Contractor should be qualify by QOGIL QHSE norms. Contractor

may get the copy of QHSE policy upon request.

Although Quippo Oil and Gas reserves the right to select any CONTRACTOR for this work, and will not

necessarily select the lowest bidder, or any bidder, for this work, preference will be given to the bidder

which, A) provides the most immediate commencement of the RIG and CAMP moves, B) offers to

commit the best quality of equipment for the performance of this work, C) proposes as rapid as possible

completion of the work, and D) offers the most economical Lump Sum quote.

The tentative loads, dimensions & weight of each equipment are given in Annexure III and the same is for

contractor’s guidance only. Contractor is advised to visit the Mehsana (Gujarat) location for inspection of

the equipment and may also review transportation route to familiarize himself prior to submission of his

quote.

5

Annexure II

CONTRACT CONDITIONS

1) Fleet & Loading Equipment:-

Contractor shall provide required no of low bed Trailers, HB-SLB, Triple -XL Trailer, Cranes (02 x 50 MT

at Loading & 02 x 50 MT Cranes at Unloading point) for Transportation, Loading, Unloading of drilling

equipment & Rig building from Quippo Yard, Jagudan, Mehsana to Oil India Limited Drilling Site

located at Barekuri Village, Tinsukia, Assam Contractor shall provide daily reports of the placement of

vehicles and movement/tracking status to the company. The daily report shall be sent to below

representatives of Company:-

Mr. Shashi Bhushan Singh (DGM-Operations)

E-mail: [email protected]

Mr. Sanjeev Ranjan (Head-SCM)

E-mail: [email protected]

Mr. Mahaveer Panwar (Manager-Logistics)

E-mail: [email protected]

2) Equipment Breakdown:- In case any vehicles supplied by the Contractor breaks down then Contractor should replace the vehicle

having same capacity within 4 hours, failing which QOGIL shall have option to arrange for alternative

vehicles at risks and cost to Contractor.

3) Lashing /Slinging /Slinging of equipment:- The truck/ trailers of Contractor loaded with Rig Equipment has to be properly secured by adequate lashing

and slinging for transporting by road to Assam, by the Contractor. Contractor will be responsible to

negotiate curves, telephone lines, high tension, traction lines etc. safely without causing damage to

QOGIL’s equipment.

4) Rejection of unsound Vehicles:- The Contractor shall deploy all vehicles in absolute mechanically sound condition with valid state/interstate

permits from RTO and other authorities. The Contractor shall also obtain all necessary permissions for a

smooth transportation of equipment. The QOGIL reserves the right to reject any vehicles of the Contractor,

which in his opinion is not in sound condition. The decision of the QOGIL in this regard shall be final.

5) Transshipment:-

Transshipment of goods from one vehicle to another is not allowed. However in case of accident or damage

to Contractor’s vehicles, Contractor should promptly arrange (Within Same Day) for transporting the

equipment by suitable substitute vehicles, after informing QOGIL and obtaining QOGIL’s consent for the

substitution.

6) Prohibition to carry any other material:- The Contractor shall not carry any other materials in his vehicles other than those of QOGIL. Contractor

shall not transport contraband goods in the vehicles in which QOGIL’s materials are transported.

7) Total Nos of Load:-

Maximum Nos of Load is 90 ± 5 Trailers (Approx.).

8) Waiver of Liens:-

The Contractor will not have liens on the goods, which are in his possession and belonging to QOGIL.

6

9) Sub Contracting:-

Except for hiring of vehicles and handling equipment no sub-contracting of any or part of any job shall be

allowed unless such arrangement is accepted and notified in writing by QOGIL. In any case it is

understood that the Contractor shall be solely and entirely responsible for all the operations and services

covered by this contract.

10) Extra care of ODC Consignments:-

In case of heavy ODC consignments and critical consignments, which will be specified by QOGIL, the

Contractor will provide escort vehicle at its own cost. In our opinion there are minimum 5-10 critical

consignments.

11) Supervision:- The Contractor shall provide efficient supervision at the time of loading so that the packages are placed on

the vehicles in such a manner as to ensure total safety of the equipment against any damages in transit.

When large sizes of over dimension equipment’s are loaded on trailers, the Contractor should be

meticulously careful in adjustment of the load with regard to proper distribution of weights on axle, centre

of gravity etc.

12) Authorized Representatives:-

The Contractor shall depute minimum Two authorized representatives who should be fully empowered to

take on the spot decision and follow instructions from QOGIL’s representative at site.

13)Duration Of Loading Mobilization :-

Loading will start on 1st November and will finish on 15

th of November.

Last Load should reach at unloading point no later than December 15, 2015.

14) Insurance:- The insurance of the QOGIL’s equipment has been arranged by QOGIL. The Contractor shall inform and

assist QOGIL for insurance surveys/ claims in case of accidents, damage to QOGIL’s equipment. The

contractor shall be fully responsible for the insurance of his vehicles and personnel including 3rd

party risks

at his costs. The Contractor shall assist QOGIL in respect of filing of insurance claims and shall arrange for

all reports/ documents, which shall be required to be submitted to insurance company. The security deposit

if any of the Contractor shall be released after he provides all documents for insurance in case of loss or

damage to the goods. The Contractor shall be fully responsible for loss or damage arising due to negligence

or wilful acts of the Contractor or his personnel. The Contractor shall also be responsible for loss or

damages arising on the outside of the equipment due to hitting to road side trees or other object and also, the

inner damages which could arise due to abnormal jerks, drive at an abnormal speed. QOGIL will be

entitled for deducting the cost of loss or damages which are not recoverable under the package policy either

due to exclusion or due to below deductible and which are directly relating to the Contractors negligence, in

the above circumstances.

15) Safety of Equipment:-

The Contractor shall ensure the safety of the equipment and materials in the entire handling and transport

operations and shall not claim from QOGIL any damage caused to the vehicles and handling equipment’s

either owned by him, to public property as well as injuries or otherwise the personnel in his command or

to the public. Contractor shall be fully accountable for all goods delivered to him. In case of any loss or damages to such goods, the Contractor shall provide necessary documents for obtaining payment for such

damages / losses from insurance company failing which the costs of such loss or damage to goods will be

recoverable from the Contractor. In case of any shortage / damages to consignment or his failure to give

papers for insurance claims the contractor shall not be entitled for any freight charges in respect of such

7

consignments and the cost of the loss or damages shall be recovered from the contractor. Cranes and

vehicles to be properly insured under comprehensive risks, copies of policies to be given if required.

Contractor crew should be well equipped with personal protective equipment like coveralls, Safety Shoes,

Safety Helmets and Safety Glasses ensuring proper execution of safety Norms. Contractor shall be

responsible and absorb the cost for all PPE and shall ensure to be bind by and follow company’s HSE

policy and requirement at no extra cost to the company. In case violation of any Safety Norms, QOGIL

reserve the rights to reject the vehicle and or impose the penalty @ INR 2000 per vehicle.

Contractor shall keep company indemnified against the following:-

a. All losses, damages, claims, penalties suffered, expenses incurred in defending the suits or proceeding

consequent to failure on your part to act in accordance with the terms of the Agreement.

b. Any loss which may be suffered by us [except due to Our default] consequent to confiscation of the

Equipment by any governmental authority or any public officer or authority under any law for the time

being in force while the Equipment is under this work-order.

c. Any liability arising out of non-compliance of all statutory requirements and other applicable statutes,

regulation and rules.

d. All damages caused to the equipment - covered or not covered- due to misuse or negligence of your

representatives or operators.

Contractor shall make proper use of Road permits & documents provided to you and shall return all the

unused ones. Failure to do so shall be at Contractor own risk and Contractor should pay any and all

penalties arising out of such failure.

B) Compensation:-

1. Total value of this contract is Rs. ………………………………. (Rupees …………………….only)

including all taxes except Service Tax.

2. The Company shall pay the Lump Sum charges of Rs. …………………………… (Rupees

………………………… only) fix for Complete Transportation for 90 ± 5 Trailers (Approx.) Load

only. Extra load will be paid as per Additional cost on a per load basis / or per day basis according to

the type of Vehicle used. If the no of Loads will be less than 90 ± 5 Trailers in that case cost will be

deducted accordingly.

3. Service Tax shall be payable extra as per rules and necessary TDS will be deducted from your payment.

4. Above rates are inclusive of fuel (HSD) which shall be provided by the contractor. Oil, Lubricants and

operators salary and any other expenses incurred with relation to the equipment and manpower shall be

borne solely and exclusively by the contractor.

5. Detention Charges:- No detention charges will be Applicable for this contract under any

circumstances.

8

(C) Compliance with Safety regulations /Labour /Etc.:-

Vehicles including Trailer’s /cranes should be certified by Quippo HSE department, have a valid license , all

operator and Driver should have certified through Quippo HSE Department and have hold a valid license

issue from RTO / State Transport Department.

Contractor shall ensure strict compliance with all applicable labour laws and regulations and shall adhere to

all safety procedures and norms with respect to manpower and equipment.in case of any act of indiscipline

on the part of the crew, Quippo shall have the right to seek replacement of the operator /Helper immediately.

All Contractors’ crew shall be well equipped with safety protections like coverall, safety shoes, safety

helmets and safety glasses for ensuring proper compliance of safety norms.

All Contractor’s crew (helpers / operators, etc.) shall be fully trained and possess a valid license to operate

Vehicle’s/ Cranes, a proof of which shall be provided to us for verification.

Contractor shall also ensure that all statutory rules and regulation are followed and implemented from time

to time.

HSE manual comprising of policy, goals objectives, checklist, and operational guidelines shall be taken by

you from our site in-charge immediately on receiving this work order. As already indicated, all operator and

equipment should be certified by Quippo HSE.

Contractor shall keep us indemnified against any and all, losses suffered by us due to non-compliance of

any of obligations under this work order.

Notwithstanding anything contained herein or any other provisions of this contract, Contractor shall, under

no circumstances stop the services of equipment for whatsoever reason unless and until a proper notice in

this regard is received from Quippo in terms of this work order. Even Contractor have any pending issues to

be resolved under this work order, services under this work order shall not be stopped without proper notice.

Contractor has been explained and understood fully the financial implications/losses that Quippo will

directly suffer due to such unilateral stoppage of work of equipment on hire.

In case of any pending issues under this work order, Contractor shall take up with the respective

departments of Quippo, meet and discuss and sort out the issues. Quippo shall discuss the issues if any

under the terms of this contract and try to resolve in a fair manner.

If Contractor contravenes any of the above provisions, the entire actual loss incurred by Quippo Shall be

deducted / recovered from Contractor.

D) Invoicing & Payment:-

A. 25 % Advance Payment at the time of Vehicle placement at Mehsana Yard (Loading Point)

B. 15% Payment on 30th Load (Progressive Payment).

C. 15%Payment on 60th Load (Progressive Payment).

D. 20 %Payment on 90th Load (Progressive Payment).

E. 25% Payment against Invoice shall be made within 30 days after submission of Correct & final Invoice along

with all necessary documents as indicated in this work order.

Invoice shall be accompanied by:

Received Gate pass / Challan, GR Copy, Road Permit, Work Completion Certificate duly certified by our Site

In-charge.

9

In addition to the above, first Invoice shall be accompanied by a copy of your Service Tax registration and IT PAN

Copy. The Invoice shall be in conformity with the requirements of service tax.

Invoices in the name of “Quippo Oil and Gas Infrastructure Limited” with the above documents shall be submitted

to:

Mr. Natrajan Venkatesan,

General Manager -

Accounts Department

Quippo Oil and Gas Infrastructure Ltd.

6th Floor, Plot No. 14 A

Sector-18, Maruti Industrial Complex

Gurgaon (Haryana) 122015.

E) Liquidity Damages:-

The Time Frame for complete execution of the Contract is 30 (Thirty) days. Last Load should reach at unloading

point no later than December 15, 2015. LD will be applicable for delay in execution of this work order. The LD rate

will be 1% of the contract value for each day delay, Maximum up to 7.5 % of the contract value.

F) Penalty for Delayed Delivery:

Liquidated Damages per day of delay will apply @1% per day of lump sum value. This penalty for delayed delivery

shall be recovered only for delays, which are attributable to transporter. It may be noted that no unforeseen reasons

are acceptable for any delay by the transporter.

G) Cancellation of Contract:

Should there be any delay on the part of the Contractor in execution of his responsibilities; QOGIL shall have right

to cancel this contract and/ or to arrange additional vehicles/ cranes at Contractor’s cost and risks by giving 8 hour

notice. In such an event all extra cost incurred for execution of the work will be recovered from the Contractor.

H) Governing Law, Jurisdiction & Arbitration:

All and any dispute arising out of or in connection with this contract, including any question regarding its existence,

validity or termination, shall be referred to and finally resolved by arbitration in New Delhi in accordance with the

Arbitration Rules of the Construction Industry Arbitration Council ("CIAC Arbitration Rules") for the time being in

force at the commencement of the arbitration, which rules are deemed to be incorporated by reference in this clause.

The Company shall be entitled to select the sole Arbitrator out of the panel of CIAC. The award of the arbitrator

shall be final and binding on both parties without the right of appeal.

10

Annexure III

LIST OF EQUIPMENTS TO BE TRANSPORTED FROM MEHSANA TO ASSAM

S.NO DESCRIPTION QUANTITY LENGTH(feet) WIDTH(feet) HEIGHT(feet) WEIGHT

TON

POWER PACK

1 DIESEL TANK NO. 01 1 35' 8" 8' 9" 10' 9" 12

2 DIESEL TANK NO. 02 1 35' 8" 8' 9" 10' 9" 12

3 POWER PACK NO. 01 1 35' 7" 10' 4" 11' 7" 24

4 POWER PACK NO. 02 1 35' 7" 10' 4" 11' 7" 24

5 POWER PACK NO. 03 1 35' 7" 10' 4" 11' 7" 24

6 POWER PACK NO. 04 1 35' 7" 10' 4" 11' 7" 24

7 PCR 1 40' 4" 9' 1" 11' 3" 32

8 VFD 1 20' 8' 9' 8

TANKS 9 WATER TANK NO. 01 1 27' 7" 9' 3" 8' 9" 12

10 WATER TANK NO. 02 1 35' 3" 9' 3" 9' 12

11 WATER TANK NO. 03 1 40' 9' 3" 9' 12

12 RESERVE TANK NO. 01 (MIXING TANK) 1 43' 5" 9' 9" 8' 11" 18

13 RESERVE TANK NO. 02 1 35' 5" 9' 1" 8' 11" 18

14 RESERVE TANK NO. 03 1 35' 5" 9' 1" 8' 11" 18

16 SUCTION TANK ( ACTIVE ) 1 35' 5" 9' 1" 8' 11" 18

17 INTERMEDIATE TANK 1 35' 5" 9' 1" 8' 11" 18

18 SHALE SHAKER TANK 1 43' 9" 9' 1" 8' 11" 23

19 BRAKE COOLING TANK (TRIP TANK) 1 42' 3" 8' 11" 11' 14

21 FIRE ENGINE 1 10' 10" 5' 3" 4' 9" 1

MUD SYSTEMS 22 MUD PUMP NO. 01 1 24' 6" 10' 3" 9' 28

23 MUD PUMP NO. 02 1 24' 6" 10' 3" 9' 28

24 SUPER CHARGER WITH SKID 1 16' 9" 10" 5' 5" 8

25 BOP CONTROL UNIT 1 19' 7' 5" 7' 7" 10

26 CHOKE MANIFOLD 1 32' 7" 12' 4" 7' 3" 10

27 HOPPER SKID 1 16' 8" 11" 5' 6" 3

28 KILL MANIFOLD 1 6' 6" 11' 5' 6" 3

29 POOR BOY DEGASSER 1 27' 8" 4' 6" 4' 6" 5

30 SHALE SHAKER-1 1 10' 4" 5' 5" 5' 7" 2

31 SHALE SHAKER-2 1 10' 4" 5' 5" 5' 7" 2

32 SHALE SHAKER-3 1 10' 4" 5' 5" 5' 7" 2

33 DEGASSER 1 13' 3" 3' 9" 5' 10" 1,5

34 DESILTER 1 8' 9" 6' 5" 8' 8" 1.5

35 DE SANDER 1 7' 8" 3' 6' 2

11

36 PIG HOUSE 1 5' 5' 9' 1.5

37 JET SPEAR HOPPER 1 6' 11" 5' 9" 4' 4" 1,5

39 MUD PUMP MANIFOLD 1 12' 1" 9' 3' 5" 2

SUBSTRUCTURE & MAST 40 SECTION-1 1 35.7' 10.8' 1.5' 7

41 SECTION-2 1 32' 9.7' 1.5' 2.5

42 SECTION-3 1 32' 9.3' 1.5' 3

43 SECTION-4 1 32' 8.9' 1.5' 3

44 SECTION-5 1 17.6' 9.5' 1.5' 1.5

45 CROWN BLOCK 1 10.5' 13' 12.8' 11

46 CASING STABING BOARD 1 33' 2.3' 7.5' 1.5

47 ROTARY TABLE 1 7' 3" 6' 3' 6" 10

48 DRAW WORKS 1 24' 3" 14' 5" 10' 5" 44

49 DRAW WORKS DC MOTOR SKID 1 22' 2" 5' 2" 6' 11" 2

50 D/WORKS TRASMISSION 1 24' 3" 14' 5" 10' 5" 12

51 TOP DRIVE 1 42' 5.2' 6.3' 16

52 TRAVELLING BLOCK 1 17.2' 5.6' 5.4' 7

53 DRILLER'S CONTROL 1 15' 4' 3' 3.5

54 DOG HOUSE 1 8' 7.5' 10' 25

55 DERRICK BOARD 1 33' 8.8' 8.5' 5

56 GRASS HOPPER 1 22' 13' 6.5' 8

57 LEFT FRONT LOWER SEAT 1 33.7' 4' 6.2' 13.5

58 LEFT BACK LOWER SEAT 1 38.8´ 10.2' 4.69' 5

59 SECTIONAL BEAM-1 2 22' 6.8' 4.69' 1

60 SECTIONAL BEAM-2 1 19.48' 7.5' 1' 1

61 RIGHT FRONT LOWER SEAT 1 19.48' 7.5' 1' 14

62 RIGHT BACK LOWER SEAT 1 39' 10' 4.5' 5

63 LEFT UPPER SEAT 1 22' 6.8' 4.5' 16.5

64 RIGHT UPPER SEAT 1 43.5' 10' 6.6' 17.5

65 FRONT BEAM 1 43.5' 10' 6.6' 1

66 SET BACK BEAM 1 19.5' 2' 0.6' 11

67 ROTARY TABLE BEAM 1 19.5' 10' 4.6' 4

68 CHAIN BOX BEAM 1 10.82' 9' 4' 1

69 DW FRONT BEAM 1 6.5' 5' 5' 4.5

70 DW BACK BEAM 1 19.5' 6.2' 4.2' 3

71 TIE-ROD 4 19.5' 7.5' 2.4' 1

72 BOP GUIDE RAIL DEVICE 1 6.6' 1.2' 0.4' 3

73 FRONT UP RIGHT POST 2 28.6' 5.8' 2.8' 3

74 INCLINED UPRIGHT POST 2 24' 6.3' 1' 2

75 BACK UPRIGHT POST 2 24' 5' 1' 2.5

76 LIFTING DEVICE 1 24' 6.3' 1' 22.5

12

77 BLOCK 2 41' 4.8' 11.6' 1

78 LIFTING LINE 2 5.4' 3.2' 1.5' 1

79 STAY BAR FRONT(A-FRAME) 2 153' 1' 0.8' 4

80 STAY BAR BACK(A-FRAME) 2 36'5" 3'5" 1'5" 4

81 BIG CROSS BEAM 1 36'5" 3'5" 1'5" 6

82 SMALL PLATFORM 2 20'5" 2' 2' 1

83 SLIDE WAY 1 12' 3.5' 2.8' 1.5

84 DRILLER SIDE LADDER-1 1 33' 31.6' 3' 2

85 OPP DRILLER SIDE LADDER-1 1 42' 32' 3' 2

86 CAT WALK 2 33' 5' 8" 3' 7" 8

87 CROWN HORSE - 1 10' 10' 12' 7" 1

88 MAST HORSE 2 8' 9" 5' 7" 11' 3" 1

89 DRILL LINE SPOOL 1 6' 5" 5' 6' 5" 12

90 RAMP 1 44' 9' 6" 3' 4

STORE CONTAINERS 91 MAIN STORES 1 40' 8' 8' 6" 18

92 STORE CONTAINER NO.1 1 40' 8' 9' 6" 20

93 STORE CONTAINER NO.2 1 39' 7' 7' 20

B O P'S

94 13 5/8 X 10M SINGLE RAM

BOP(SHAFFER) 1 11' 1" 5' 7" 4' 2" 8

95 13 5/8 X 10M DOUBLE RAM

BOP(SHAFFER) 1 10' 7" 5' 7" 6' 7" 12

96 21 1/4" x 2M DOUBLE RAM

BOP(CAMRON) 1 14' 3" 4' 11" 6' 5" 14

97 13 5/8 x 5M ANNULAR BOP(CAMRON) 1 5' 7" 5' 7" 3' 10" 8

98 21 1/4" x 2M ANNULAR

BOP(SHAFFER) 1 4' 6" 4' 6" 3' 10" 6

TOOL BOX'S 99 PIPE RACK'S 4 32' 10" 5' 2" 3' 6" 6

100 250KV GEN SET 1 14' 8" 7' 6" 9" 3

101 250KV GEN SET 1 14' 8" 7' 6" 9" 2.5

13

Annexure IV

Price Format

Sr. No. Particulars Amount (In Figure)

1 Lump-sum charges for transportation of ZJ-70 2000 HP

drilling Rig Equipment (as per Annexure III) Including

Loading/Unloading along with Crane, Hydra, Labour

Etc. from Mehsana (Gujarat) to Oil India Limited

Drilling Site located at Barekuri Village, Tinsukia in

Assam.

Amount In Words (RS.........................................................................................................................)

Note:

Above rates shall be Inclusive of all taxes, duties and levies except Service Tax.

Service Tax shall be quoted separately.

Besides Lump-sum charges, Contractor shall provide Breakup of the cost, Separate cost for each type of

Vehicles used required for cost calculation for additional Loads.