Upload
gerald-harper
View
216
Download
0
Embed Size (px)
Citation preview
TEM and TER Projects’ Master Plan Draft Final Report
Geneva, 8 - 10 June 2005
TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
UNITED NATIONS ECONOMIC COMMISSION
FOR EUROPE
2
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Structure of the presentation
• Background
• Scope
• Terms of reference
• Elaboration
• Conclusions / Recommendation
• What’s next
3
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Background• Survey and review of TEM and TER (1999 – 2001)
• Approval of the short-term strategy (June 2001)
• Master Plan, first priority of the work 2003 – 2004
• Approval of the TOR (May 2003)
• Start of the elaboration of Master Plan (October 2003)
• Nomination of external consultants
- Prof. D. Tsamboulas (NTUA) - Prof. A. Pearman (Leeds University) - Mr. Z. Trcka (Czech Rep.) - Mr. L. Gaspar (Hungary) - Mr. D. Przybyla (Poland)
4
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Elaboration of a strategic plan of action for the implementation of the TEM Project objectives in terms of updated and prioritized rail and combined transport infrastructure needs of TEM member countries and their immediate neighbors
Scope
• Investment priorities
• Timetable for their realization
• Assessment of cost and financing arrangements
5
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Terms of ReferenceObjectives
Consistent and realistic investment strategy for the development of the road transport infrastructure in the wider TEM Region, supporting:
• Promotion of TEM Project goals
• Extension of TEN-T
• Development of Pan-European Transport Corridors
• Promotion of intermodality
• European transport integration
6
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Terms of Reference (cont’d)Tasks
• Review of TEM work and European initiatives• Socioeconomic framework - scenarios of growth• Methodology and main assumptions • Inventory of needs• Elaboration of Master Plan• Truck and coach transport problems• Funding questions and financing arrangements• Border crossing questions• Conclusions / recommendations / dissemination
7
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
TEM Master Plan invited countries
8
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Elaboration Organisation
• PCO Main responsible
• National Experts Consolidate national information
• Invited organizations Thematic support/guidance
• External consultants Technical/ scientific assistance
TEM Master Plan Expert Group
PCO, National Experts, Organizations, Consultants, UNECE
TEM and TER Master Plan Coordination Group
PCOs, External Consultants, UNECE
9
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Elaboration – Initial time tableReviewed Work Time Plan
YEAR 2003 YEAR 2004
MONTHS
WP
1
SEPT
2
OCT
3
NOV
4
DEC
5
JAN
6
FEB
7
MARCH
8
APR
9
MAY
10
JUNE
11
JUL
12
AUG
SEP
WP0
WP1
WP2
WP3
WP4
WP5
WP6
WP7
WP8
WP9
Master Plan Coordination
Group Meetings
Master Plan TEM and TER
Expert Group Meetings
10
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Elaboration – MilestonesCoordinations Group Meetings
• 1st meeting, Budapest 16/9/03 • 2nd meeting, Warsaw 15/12/03• 3rd meeting, Geneva 9/6/04• 4th meeting, Budapest 15/11/04
TEM Master Plan Expert Group Meetings• 1st meeting, Bratislava, February 2004• 2nd meeting, Budapest, September 2004
Completion of work, March 2005
Prepration of separate volume (to follow soon)
11
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Chapter 1 TEM and TER Master Plan
- Introduction of the TEM and TER Projects and their Master Plan
- The TEM and TER environment
- General description of the report and work
12
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
• Two scenarios of growth have been established ( Moderate and Optimistic)
• The year 2000 was chosen as the base year• Data from 1995-2000-2001-2002-2004 were used to
establish trends• Countries were divided in 3 groups
- EU member countries before 01-05-2004 (Group I)- EU member countries after 01-05-2004 (Group II)- Non-EU, non-acceding countries (Group III)
Chapter 2 Socio-economic framework and
scenarios of growth
13
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Transport trends Group I: PassengerAnnual growth transport by car (+ 1.32 to +1.81%)Annual growth transport bus/coach (+ 0.03 to +0.19%)Annual growth transport rail (+ 1.31 to +2.55%)Modal share road-rail the same, slight decrease for roadFreightAnnual growth transport road (+ 3.20 to +3.38%)Annual growth transport rail (+ 3.43 to +3.67%)Modal share road-rail the same, slight decrease for road
Chapter 2 Socio-economic framework and
scenarios of growth (cont’d)
14
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Transport trends Group II: PassengerAnnual growth by car (+ 2.07 to +3.10%)Annual growth bus/coach (- 0.01 to -0.28%)Annual growth rail (+ 0.75 to +1.18%)Modal share road-rail the same, slight increase for roadFreightAnnual growth road (+ 2.49 to +2.77%)Annual growth rail (+ 2.57 to +2.59%)Modal share road-rail dramatic change (+43 road –60% Rail)
Chapter 2 Socio-economic framework and
scenarios of growth (cont’d)
15
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Transport trends Group III: • Limited or no data existed to support forecasting• Based only on limited data from Bosnia&
Herzegovina, Serbia & Montenegro and FYROM• Accumulated road traffic growth ( +187 to
+255%)• Accumulated rail traffic growth (+61 to + 81%)
Chapter 2 Socio-economic framework and
scenarios of growth (cont’d)
16
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Four Phases
A. Identification ( with three screening levels)
B. Forecasting (using scenarios of growth)
C. Evaluation (multi criteria analysis)
D. Prioritization (in three levels)
Chapter 3 Methodology on evaluation and
prioritization
17
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Phase A IdentificationLevel 1: Relevance (technical standards – TEM goals – on main axis-connecting with other regions)Level2: Readiness (project well defined – responsible agent-time plan)Level 3: Viability (10 mill € - IRR – Environmental aspects – Justified need)
Chapter 3 Methodology on evaluation and
prioritization (cont’d)
18
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Phase B Forecasting
Performed on macro level, using the alternative scenarios of growth, and available data as collected from countries through questionnaires (Templates)
Chapter 3 Methodology on evaluation and
prioritization (cont’d)
19
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Phase C Evaluation (multi-criteria analysis)(1) Definition of criteria: - socio-economic return of investment
- functionality and coherency of the network
- strategic / political concerns of the network
(2) Quantification of criteria: (A=5, B=4, C=3, D=2, E=1) 5 highest
(3) Prioritization- Technical (direct application of evaluation providing the scores)
- Compliance with commitments, and corrective actions if needed
(4) Financial capability of country: (comparison to 1.5% of GDP)
Chapter 3 Methodology on evaluation and
prioritization (cont’d)
20
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
• Priority I: projects, which may be funded and implemented rapidly, including on-going projects up to 2010.
• Priority II: projects requiring some additional investigations for final definition before likely financing, or planned for implementation up to 2015.
• Priority III: projects requiring further investigations for final definition and scheduling before possible financing, or planned for implementation up to 2020.
• Priority IV: projects to be implemented in the long run, including the projects where insufficient data existed.
Chapter 3 Methodology on evaluation and
prioritization (cont’d)
21
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Total Final Results• In total 491 TEM and TER Projects 101 billion € • 172 TER (51.5 billion €), 319 TEM (49.5 billion €) • TEM category I: 152 projects of value 25,3 billion € • TEM category II: 93 projects of value 23,2 billion € • TEM category III: 1 project of value 0,24 billion € • TEM category IV: 73 projects of value 0,9 billion €) • TEM 36 % have secured funding and to be completed by
2010• TEM (13 % of projects by 2015) , (10 % by 2020)
Chapter 4 Realization of the Master Plan (cont’d)
22
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
23
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Bottlenecks and Missing Links• Analysis of what may me considered as
a road bottleneck• Complexity of the work not possible to
be considered within set time frame and available resources for the Master Plan
• Missing links identified and proposed
Chapter 4 Realization of the Master Plan (cont’d)
24
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
• Major parts of the TEM Network• EU TEN-T and High Level Group• Pan-European Corridors, MEDA• Euro-Asian Transport Links• Sections on which countries proposed projects• TIRS and REBIS studies• Intermodal terminals/freight villages and ports • Interconnection and continuity of networks
Chapter 5Master Plan Backbone Network and Links
25
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
26
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
27
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Chapter 6Funding considerations – Technical -
Institutional Aspects • Since funding is not secured for 40% of projects focus
- identification of possible sources of funding- eligibility criteria to receive funds- required procedures
• Main sources of funding include: EIB, EBRD, World Bank, EU Cohesion Fund - Structural Funds -ISPA – INTERREG
• Elements analyzed include: Initial approach, legal framework, eligibility criteria, appraisal, examination, monitoring, decision making, contract signature, etc.
• Possibility of private participation, via PPP
28
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
• Inventory of border crossing points was made
• Relevant GIS maps
• Identification of border crossing problems
• Recommendations for problems alleviation
Chapter 7Border Crossing Issues
29
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
General conclusions • Master Plan elaboration has so far achieved its intended
goals by presenting an investment strategy in the wider TEM and TER region, which supports the: Extension of TEN-T, implementation of pan-European Corridors, promotion of intermodal transport, maximum effectiveness of transport infrastructure
• If implementation is ensured, will assist:Economic growth in countries concerned, well being of their populations, integration & harm. in Europe - beyond
• TEM Master Plan process has been successful, but the work is ongoing
Chapter 8Conclusions / Recommendations
30
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
Recommendations• Missing or insufficient data should be completed with
direct inputs of countries • Update of the Backbone network from time to time• Priority projects monitoring and implementation• Close cooperation among TEM countries, between them
and their immediate neighbours and TEM PCO • The presentation of the shape of TEM Backbone
Networks in 2010, 2015, and 2020 should be among the major tasks of TEM in future
• A review of the strategy by 2008
Chapter 8Conclusions / Recommendations (cont’d)
31
UNECE TRANS-EUROPEAN NORTH-SOUTH MOTORWAY (TEM) PROJECT
• Implementation is a long-term process that requires political will and commitment from countries
• Implementation of standards and monitoring the progress in bringing TEM Backbone network up to the required standards could be also among future tasks
• To facilitate this process, countries not yet members to TEM Project, should seriously consider their full membership
• TEM Project provide an ideal framework to ensure the follow-up work
Chapter 9The Way Ahead
TRANS-EUROPEAN NORT-SOUTH MOTORWAY (TEM) PROJECT
UNITED NATIONS ECONOMIC COMMISSION
FOR EUROPE
FOR INTEGRATION AND DEVELOPMENT
IN EUROPE