Project Planning &
ControlTechnical Module D
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 2/17
2
Project Management Consists of all the actions that taken by the
firm’s managers to ensure that the projectmeets four basic objectives
Functionality Timeliness
Cost effectiveness
Quality
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 3/17
3
Project Mechanism Project managers
The firm’s executive committee The firms IS steering committee User area management / IS unit management Project team leader(s) or manager(s)
Project plan Activities or tasks Subdivision of the project into phases
Incorporate into a Gantt chart and network diagram Scheduled meetings
Reports
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 4/17
4
Reports Narrative reports
Progress since the last report
Any problems that must be resolved
Tasks to be performed
Graphic reports Gantt charts
Network diagrams
Critical Path Method (CPM) Project Evaluation Review Technique (PERT)
Tabular reports Milestone report
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 5/17
5
Milestone Summary Report
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 6/17
6
Gantt Chart
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 7/17
7
Gantt Chart Hints Use SDLC stages for some phases.
Use other subdivisions for the remainingphases.
Subdivide each phase into ADCR activity. Identify who will do the work (individuals,
“team”)
Obtain team approval before putting into
action
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 8/17
8
Network Diagrams A net work diagram is a pattern of interconnected
arrows that represents work to be done. Critical Path method (CPM):
Uses a single time estimate for each activity. The estimate
is the best that can be made using the availableinformation.
Program evaluation review technique (PERT)
Uses three time estimates- an optimistic, a pessimistic, anda most likely.
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 9/17
9
Network Diagram Techniques
Activities Each activity is labeled with a brief description plus and estimate of the
amount of time that will be required
Nodes The purpose of the node is to provide a unique identification to each of the
activities Serial Processes
Those processes which are performed one after another
Parallel Processes When more than one activity can be performed simultaneously
Dummy Activities Unlabelled activities represented by dotted lines. Do not represent any work
to be done instead connect some of the activities
Critical Path
The critical Path contains no slack, or excess time. Activities not on criticalpath contains slack time, and can be delayed for that time.
Early start and early completion dates and late start and late completiondates
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 10/17
10
Network Diagram
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 11/17
11
A Network Diagram ofIndianapolis 500 Pit Shop
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 12/17
12
Microsoft Project Network Diagram
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 13/17
13
Program Evaluation Review
Technique (PERT)
Three time estimates
Optimistic
Pessimistic
Most likely
6
4 om p T T T Actime
++
=
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 14/17
14
Project Cost Management Cost management activities
Resource planning Cost estimating
Cost budgeting
Cost control
Cost estimating steps
Estimate the person months Normalize the person days
Estimate project cost
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 15/17
15
Estimation of Person Months
8/6/2019 Tehnical Module D -Project Planning & Control
http://slidepdf.com/reader/full/tehnical-module-d-project-planning-control 16/17
16
Estimation of Person Days and Hours