Upload
sarayudixit
View
219
Download
0
Embed Size (px)
Citation preview
7/29/2019 Technical Test Team Progress - 9 June 2011
http://slidepdf.com/reader/full/technical-test-team-progress-9-june-2011 1/6
“Automation & Performance test ” progress report
DALE Chris - 9 June 2011
This report details the achievements, progress and planned work for the Technical Test area. Details
of this report and past reports are collated here:
http://itzone/Servstratdesign/SS/change/PerfTesting/SitePages/Home.aspx
7/29/2019 Technical Test Team Progress - 9 June 2011
http://slidepdf.com/reader/full/technical-test-team-progress-9-june-2011 2/6
http://itzone/Servstratdesign/SS/change/PerfTesting/SitePages/Home.aspx Page 1
Period report covers: 09 April 2011 – 09 May 2011
Issued to: Eric Chapman, John Bennett, John Goodyer, Paul Smith, Stuart O'Loughnane, Kath Watson, Mike Evans, Dominic Hyland, Malcolm Peck, Jamie Dalton
Achievements & Progress
Visual Studio Set Up:
Testing / Developer collaboration.
o TFS Source control created for the Hewitt’s project allowing both testers and developers to access the performance tests.
o Test and Development have been working more closely together on the Hewitt’s project for performance testing and have identified some issues that needed
to be fixed on the site. Consensus is that this has resulted in defects and issues being resolved earlier.
Have requested that user group G-Performance-Test-U-C (Chris Owner) be added as a “Performance Monitor User” on all of our TEST & PREPROD environments. This
group contains tech test users, test accounts, VS2010 controller user etc. Meeting with Roger Faithful booked to move this forward.
Azizah has now presented to the test team how MTM has been used to plan, test and track defects on the Aon Hewitt’s project, this was a real ly good overview.
Colin Beales (Microsoft) has delivered a presentation covering tests, linking to requirements, defect raising and tracking, reporting.
Working with Jamie Dalton I have been able to make significant progress on the set up of Visual Studio 2010 for the purpose of Performance Testing. We have
encountered many challenges along the way and extremely happy that we have been able to overcome these so quickly and efficiently.
We now have a basic test rig, made up of:
o Controlling server
o Five client machines.
o This rig now needs to be ramped up to ensure we are able to support a whole range of projects.
o A database is required to collect the performance data for projects and to store baseline results; this database is being built by OPS (with our guidance) this
week.
Stuart, Mike & I have been discussing a collaborative approach to running a C# course and have now been able to secure an in house course provided by QA for 10
delegates. This has proved to be extremely good value for money, potentially bringing down the cost per delegate from £2500 to £500.
7/29/2019 Technical Test Team Progress - 9 June 2011
http://slidepdf.com/reader/full/technical-test-team-progress-9-june-2011 3/6
http://itzone/Servstratdesign/SS/change/PerfTesting/SitePages/Home.aspx Page 2
AON Hewitt: (VS2010 proof of concept)
As mentioned in last month’s report, it has now been confirmed that the AON Hewitt PREPROD environment needed the Ram increased from 4 GB to 8 GB. This has
now been resolved, although I have not been able to complete another full test due to the availability of the database mentioned above. Initial results look to have
improved things.
Automated Testing
No movement in this area from the last report the following two points need to be picked up when time permits.
The reusability of the Embassy data migration and how this work could be reused to populate a database for Test Automation & Performance requires an
environment to be built to enable this initiative to be taken forward.
FNZ Regression tests have been put on hold due to the environment reliability issues and recruitment of the senior Test Manager.
AWWIPS
I have fed into Eric’s DSDM Test Approach to suggest the tools we will be using to aid and support his system test team.
Automation will be required to build tests during time boxes to ensure that time boxes are not filled up by manual testing time. We will be using VS2010 to achieve
this. These tests should be delivered as part of the project (time box) output. John Bennett will be leading this activity.
Performance Test will be required. I have met with the business stakeholders briefly to understand the non-functional requirements. Intend to engage with them
further to agree the business scenarios and agree approach to various activities under Performance Testing. The VS2010 toolset will be used for this, led by Chris.
Tool evaluation for HTML Validators, Browser checker and Link checker software is underway. I have approached contacts in other AXA SBU’s for input on what they
use and have had a very good response from this, in particular from Kevin Atkinson at Swiftcover. Scott Readings and I will be discussing this to ensure there is no
Development / Testing overlap.
Belfast
As mentioned in last month’s report no Automated Testing will be required.
Performance test is a requirement for this project. NFR’s have been queried and need enhancing.
Browser checker and Link checker software should be used to help identify problems early in the development / test process. (Should have lessons learnt from AWIPS
by then).
7/29/2019 Technical Test Team Progress - 9 June 2011
http://slidepdf.com/reader/full/technical-test-team-progress-9-june-2011 4/6
http://itzone/Servstratdesign/SS/change/PerfTesting/SitePages/Home.aspx Page 3
Other Business:
Chris has had 1 week paternity leave this month. This is reflected in the progress made.
Planned Work
Visual Studio Set Up / AON Hewitt
Run the performance and load scenarios on AON Hewitt following confirmation that the Test Rig database has been built by OPS.
Analyse the results from the AON tests and produce a final report.
Chris to cross train John Bennett on the Performance activity done with Visual Studio 2010.
John Bennett has been self-teaching C# and has been applying this to Visual Studio. This will help with the deliverables required for the AWIPs project.
Begin the long process of establishing a framework for codedUI testing in Visual Studio 2010, identify where to store things such as function libraries, stored
procedures and functions, how to report results, document procedures and processes (although light touch, but enough to cover business continuity).
John to cross train Chris in findings so far in Visual Studio CodedUI.
John and Chris to work together during the AWIPS project to produce CodedUI, Performance Tests and support for the other tool sets being investigated for this
release.
7/29/2019 Technical Test Team Progress - 9 June 2011
http://slidepdf.com/reader/full/technical-test-team-progress-9-june-2011 5/6
http://itzone/Servstratdesign/SS/change/PerfTesting/SitePages/Home.aspx Page 4
Time Booking
In the short term, time will be required to set up testing frameworks for the use of C# in Visual Studio 2010, where to store things, how to report results, reusable
procedures, document procedures and processes (although light touch, but enough to cover business continuity).
As mentioned in my Automation presentation this is development process to create a computer program that tests a software delivery and as such takes time to achieve.We should be prepared for the fact that the next two projects will not receive great gains.
We intend to meet with John Goodyer to discuss the best way forward to achieve this. To cover the month of June and July (8 weeks) commencing 6 th June we propose
the following. Please let me know if there are any objections to this, if so please suggest an alternative.
Tester Project / Activity Number of Days Category Benefit
John Bennett AWWIPS 7 D CodedUI tests delivered per time box
John Bennett AWWIPS 14 D Access test tools and confirm purchases
John Bennett September 7 R Run automated regression pack
John Bennett BAU 3 O Set up and configuration of CodedUI tests in VS2010 for all future projectsJohn Bennett C# Course / BAU 4 - Progression toward the goal of one tool set for the department
John Bennett Holiday 5 - -
Chris Dale AWWIPS 7 D CodedUI tests delivered per time box
Chris Dale AWWIPS 14 D Access test tools and confirm purchases
Chris Dale BAU 7 O Continued development of technical test strategy and implementation of VS2010
Chris Dale Belfast 8 D Consult on NFR’s for project and agree testing activities for later in the project
Chris Dale C# Course / BAU 4 - Progression toward the goal of one tool set for the department
D = Direct Use
R = Regression Use
O = Generic work and development of technical test for the future
7/29/2019 Technical Test Team Progress - 9 June 2011
http://slidepdf.com/reader/full/technical-test-team-progress-9-june-2011 6/6
http://itzone/Servstratdesign/SS/change/PerfTesting/SitePages/Home.aspx Page 5
Issues & Risks
Ref Date Risk Description Mitigating Action Status Owner Severity Date Closed
01 08/04/2011 To enable competent codedUI tests using
VS2010 a C# Course will be required to give the
testing area the ability to code these tests.
An introduction to C# courses
has been requested, inc costs.
Closed –
Course
booked for
12 July
Chris Dale /
Eric Chapman
High N/A
02 08/04/2011 Until the positions in the OD are filled,
resource will have to be allocated on a priority
basis.
Access projects and other
needs in line with resource
availability.
Open Chris Dale /
Eric Chapman
Med N/A
03 08/04/2011 The issue of what the tech test team should
book their time against should be resolved.
Time should be allocated
across projects.
Open John Goodyer
/ Stuart
Med N/A