Upload
phungdan
View
233
Download
3
Embed Size (px)
Citation preview
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 1 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
TECHNICAL SUPPLY CONDITIONS
FOR
PIPING VALVES
Hindustan Petroleum Corporation Ltd
Hindustan Bhavan
8, S.V. Marg
Ballard Estate
Mumbai 400 001
Mott MacDonald Private Limited,
Mott MacDonald House,
44/45, Street No. 14,
MIDC, Andheri (East),
Mumbai – 400 093.
India
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 2 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
TECHNICAL SUPPLY CONDITIONS
FOR
PIPING VALVES
Client HINDUSTAN PETROLEUM CORPORATION LTD.
MMCI Project No. 272261
Issue and Revision Record:
Rev Date Originator Checked Approved Description
0 29.03.2011 JAT IYS SNA Issued For Tender
Group Disclaimer
“This document is issued for the party which commissioned it and for specific purposes connected with the
above-captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being
used for any other purpose, or containing any error or omission which is due to an error or omission in data
supplied to us by other parties”.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 3 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
List of Contents Page No
1 Scope 4
2 Abbreviation and Definition 4
3 Order of Precedence 5
4 Codes, Standards and Specifications 5
5 Exceptions to Specified Requirements 7
6 General Requirements 7
7 Construction Features 7
8 Gear Operator Requirements 10
9 Test & Inspection 10
10 Markings 12
11 Painting & Coatings 12
12 Substitutions and Variations 13
13 Packing 13
14 Certification & Traceability 13
15 Maintenance Spares 14
16 Despatch 14
17 Documentation 14
18 Guarantee 15
Annexure I: Gate & Globe Valves 16
Annexure II: Check Valves 19
Annexure III: Ball Valves 21
Annexure IV: Butterfly Valves 23
Annexure V: Plug Valves 25
Annexure VI: Non Destructive Examination (NDE) for Valve Castings 27
Annexure VII: Pressure Testing Requirements 29
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 4 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
1 Scope
This specification covers the technical requirements for manufacture, inspection, testing &
dispatch requirements of commonly used valves for process & utility services. This document
specifies the minimum requirements governing the supply of all piping valves, whether
supplied as bulk materials or as part of an equipment package unit including auxiliaries such as
bypass, vent drain and sealant injection valves. It forms an integral part of any Enquiry,
Material Requisition or Purchase Order package for piping components and shall be read in
conjunction with the documentation referenced therein.
2 Abbreviation and Definition
2.1 Abbreviation
ANSI American National Standards Institute
API American Petroleum Institute
ASTM American Society for Testing and Materials
ASME American Society of Mechanical Engineers
CS Carbon Steel
LPG Liquefied Petroleum Gas
LTCS Low Temperature Carbon Steel
NB Nominal Bore
NDT Non Destructive Testing
NPS Nominal Pipe Size
OD Outside Diameter, Specified
QCP Quality Control Plan
WT Wall Thickness, Specified
2.2 Definitions
The following terms are used in this specification:
Manufacturer/Vendor shall mean the manufacturer or supplier of the
Materials covered by this Specification.
Owner shall mean Hindustan Petroleum Corporation Limited.
Consultant shall mean Mott MacDonald Consultant India Pvt. Ltd.
Shall shall indicate a mandatory requirement.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 5 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
3 Order of Precedence
Any conflict between any requirements specified in this document and the requirements of
any other relevant referenced document shall be resolved in the following order of
precedence:
• The Purchase Order Specification, Enquiry or Material Requisition.
• This Document.
• Other reference Project Specifications referred to in this Document.
• Referenced Codes and Standards.
4 Codes, Standards and Specifications
Vendor shall comply with the latest edition of the following codes, standards and
specifications as available at the date of contract award:
A) American Society of Mechanical Engineers (ASME)
B1.1-2003 Unified Inch Screw Threads (UN and UNR Thread Form).
B1.20.1-1983 Screw Threads - Pipe Treads, General Purpose (Inch).
B16.1-2010 Gray Iron Pipe Flanges & Flanged Fittings.
B16.5-2009 Steel Pipe Flanges and Flanged Fittings.
B16.9-2007 Factory made Wrought Steel Butt-Welding Fittings.
B16.10-2009 Face to Face and End to End Dimensions of Valves.
B16.11-2009 Forged Steel Fittings, Socket Welding and Threaded.
B16.14-1991 Pipe Plugs.
B16.20-2007 Metallic Gaskets for Pipe Flanges.
B16.21-2005 Non-metallic Flat Ring Gaskets for Pipe Flanges.
B16.25-2007 Butt-Welding Ends.
B16.34-2009 Steel Valves - Flanged, Threaded and Welding End.
B16.36-2009 Orifice Flanges.
B16.47-2006 Large Diameter Steel Flanges
B16.48-2010 Steel Line Blanks
B18.2.1-2010 Square and Hex. Bolts and Screws (Inch Series).
B18.2.2-2010 Square and Hex. Nuts (Inch Series).
B31.1-2010 Code for Power Piping.
B31.3-2008 Code for Pressure Piping – Chemical Plant and Petroleum
Refinery Piping.
B36.10-2004 Welded and Seamless Wrought Steel Pipes.
B36.19-2004 Stainless Steel Pipes.
B46.1-2009 Surface Textures.
B) Manufacturers Standardisation Society (MSS)
SP-25: 1998 Standard Marking System for Valves, Flanges and Unions.
SP-43 :2001 Wrought Stainless Steel Butt-Welding Fittings.
SP-55 :2006 Quality Standard for Steel Castings for Valves, Flanges, Fittings
and Other Piping Components.
SP-95: 2006 Swaged Nipples and Bull Plugs.
SP-97 :2006 Forged Carbon Steel Branch Outlet Fittings - Socket Welding,
threaded and Butt-Welding Ends.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 6 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
C) American Petroleum Institute (API)
API 594-2004 Wafer Type Check Valves, Steel.
API 598-2009 Valve Inspection and Testing.
API 599-2007 Flanged and Butt-Weld Plug Valves.
API 600-2009 Steel Gate Valves, Flanged and Butt-Weld Ends.
API 602-2009 Compact Steel Gate Valves.
API 607-2010 Fire Test for Soft Seated Quarter Turn Valves.
API 608-2008 Metal Ball Valves - Flanged and Butt-Welding Ends.
API 609-2009 Butterfly Valves, Lug and Wafer Type.
D) British Standards Institute (BS)
BS 1868-1975 Flanged and Butt-Weld Swing and Lift Type Check Valves.
BS 1873-1975 Globe Valves, Flanged & Threaded Copper Alloy, Gate, Globe
& Check Valves.
BS 5353-1989 Specification for Steel Plug Valves.
E) International Organisation for Standardisation (ISO)
ISO 8501-1 Preparation of Steel Substrates Before Application of Paints and
related Products - Visual assessment of surface cleanliness.
BS EN ISO
15761-2002
Steel gate, globe and check valves for sizes DN 100 and smaller,
for the petroleum and natural gas industries
BS EN 12266
Part-1-2003
Industrial valves —Testing of valves
BS EN ISO
17292-2004
Metal ball valves for petroleum, petrochemical and allied
industries
BS EN ISO
17292-2004
Steel Ball Valves for the Petroleum Petrochemical and Allied
Industries.
BS EN ISO
15761-2002
Steel Wedge, Gate, Globe and Check Valves, 4" and Smaller for
the Petroleum, Petrochemical and Natural Gas Industries.
F) Indian Standards and Regulations (IS)
G) Project Specific
All piping components shall conform to the requirements of ASME B31.4:2009 and the
relevant referenced Codes, Standards and Specifications, listed above.
Other Codes or Standards may be specifically referenced in a Stock Code Description
(Material Requisition Item Number Description). In these cases, the requirements of the
Code or Standard so referenced take precedence over any conflicting requirements of ASME
B31.4 or any relevant Code or Standard referenced therein.
IS 1239 Part 1-2004 Mild Steel Tube.
IS 1239 Part 2-1992 Steel Tube Fittings.
IS 3589-2001 Steel Pipes for Water and Sewage Specification
272261-500-SP-PIP-001 Piping Material Specification
272261-500-SP-PIP-013 Valve Material Specification
272261-500-SP-PIP-003 Specification for Painting : Piping
272261-500-PH-PIP-002 Tagging Philosophy for Piping Valves
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 7 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
In case of conflict between Valve Technical Specification sheet and PMS, Valve Technical
specification sheet shall govern.
5 Exceptions to Specified Requirements
Exceptions to the specified requirements of the enquiry package will only be considered by
the Owner / Consultant on a case by case basis for valves or materials procured within the
State of India, provided that the valves or the materials comply with applicable Indian codes
and standards.
6 General Requirements
6.1 All material shall be new and unused and shall be free of detrimental foreign matter.
6.2 Piping valves within packaged equipment shall comply with the applicable Piping Material
Classes in the Project Specification. Vendor’s supplying packaged equipment shall identify
in their quotation, any piping valves within the packaged equipment which does not comply
with project specification and shall include enough details regarding the material
composition of those valves, and the services for which they are intended, to enable Owner /
Consultant’s to judge their suitability for the intended service.
6.3 Valve of sizes 1/4", 3/8", 11/4", 2-1/2", 3-1/2", 5" and 22" shall not be used.
7 Construction Features
7.1 Valves shall be as per the appropriate valve specification sheets.
7.2 Valves shall be capable of satisfactory operation with the valve stem in any position i.e.
vertical, horizontal or inclined.
7.3 Pressure temperature rating for flanged and butt welding end valves shall be as per ASME
B16.34 except for Ball, Butterfly valves and Plug valves. Valve thickness of valve body at
different locations should not be less than as calculated as per ASME B16.34. For Ball and
Butterfly valves, manufacturer’s recommendations shall be obtained before use for intended
service.
7.4 End requirements shall be as follows:-
• Butt welding ends shall conform to ASME B16.25.
• Socket welding ends shall conform to ASME B16.11.
• Threaded ends shall conform to ASME B1.20.1.
• Flanged ends shall conform to ASME B16.5 for sizes 1/2” NPS to 24” NPS.
7.5 All flanged valves shall have flanges integral (except forged valves) with the valve body.
Flange face finish shall be normally specified in the valve specification sheet as 125 AARH
etc. The interpretation for range of face finish shall be as follows.
Stock Finish : 500 µ in AARH max.
125 AARH : Serrations with 125 to 250 in AARH
63 AARH : 32 to 63 µ in AARH
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 8 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
7.6 For all weld end valves with bevel end as per ASME B16.25, the contour of bevel shall be as
follows:
Material Wall Thickness Weld Contour
Upto 22 mm Figure 2 Type A Carbon Steel (Except Low Temp.
Carbon Steel)
> 22 mm Figure 3 Type A
Upto 10 mm Figure 4
> 10 mm & Upto 25 mm Figure 5 Type A
Alloy Steel,
Stainless Steel &
Low Temp. Carbon Steel
> 25 mm Figure 6 Type A
Valve ends shall match thickness of the connecting pipe. Sloping of inside contour of valves
shall be done in accordance with ASME 31.4 wherever necessary to achieve this.
7.7 For flanged valves with ring joint flanges the hardness shall be as follows:
Flange Material Min. Hardness of Groove (BHN)
Carbon Steel 140
1% Cr to 5 % Cr 150
Type 304,316,321,347 160
Type 304L, 316L 140
7.8 No cast, ductile or malleable Iron, aluminium, plastic or copper bearing alloy shall be used in
Hydrocarbon service.
7.9 Valve body / bonnet shall be forged / cast as specified. Forgings are acceptable in place of
casting but not vice-versa.
7.10 Stem shall be forged or machined from forged/rolled bar. No casting is permitted. However,
integral stem of cast stainless steel ball valve is acceptable.
7.11 Valves shall be supplied with lever/wrench except for gear operated/motor operated valves.
Hand wheel wherever used for valve operation shall not be of cast iron. Material for hand
wheel shall be either malleable iron or cast steel.
7.12 Stelliting / hard facing by deposition shall be minimum 1.6mm thick. Renewable seat rings
of valves greater than 3” shall be seal welded.
7.13 All material shall be new, clean and free from rust, pits and any defects.
7.14 Spiral wound bonnet gaskets are to be provided with inner / outer ring except when
encapsulated gaskets type body-bonnet joints are employed. Outer ring may be omitted in the
case of non-circular spiral wound gasket used in 150# valve provided the outermost layer of
spiral touches the bolts ascertaining the centring.
7.15 Where ring joint gaskets are used for the body to bonnet joint the hardness of ring of gasket
shall be lower than the valve body and bonnet.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 9 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
7.16 The term ‘Valve Trim’ is defined as “All wetted internal parts of a valve”.
7.17 Valves shall be installed for ease of operation and maintenance. Valves shall not be installed
with their stem below horizontal.
7.18 The manufacturer shall ensure the interchangeability of parts between valves of same size
and specification by specifying proper tolerances during manufacture. To check compliance
with this clause, the Inspection Engineer of Owner / Consultant shall have the authority to
select any two valves of the same size and specification and ask the Vendor to interchange
the parts and carry out necessary tests after the assembly.
7.19 All gate and globe valves shall have back seating arrangement to facilitate replacement of
gland packing while in open position. Back seat bush shall be renewable.
7.20 Hardness requirements for trim material shall be as follows:
• Wherever body seat and disc seat materials are specified as 13% Cr, hardness of disc seat
shall be 250 BHN (Min) and Hardness of body seat shall be 50 BHN more than disc seat.
• For carbon steel Valves, wherever 13% Cr is specified for disc and disc seat, 13% Cr by
weld deposit on ASTM A216 GR. WCB casting is acceptable for Valve Sizes 6” and
above only.
7.21 Gate and Globe valves of rating 300# and above shall have gland stuffing boxes of sufficient
depth to accommodate lantern rings in addition to gland packing.
7.22 No welding shall be done on stainless steel valves during any stage of manufacturing.
7.23 All stainless steel valve bodies shall be passivated after machining before assembly.
7.24 All flanged valves shall have flanges integral with the valve body. However, forged valves
can have weld on flanges with full penetration joint and with 100% radiography of the
attached welds.
7.25 All valves with non-metallic seats and seals in hydrocarbon service shall be fire-safe type.
Fire safe test shall be as per API-607, API-6FA, API-6FD or BS 12266 Part II. The vender
has to submit test certificate for the particular design of the valve offered.
7.26 Fire safe test witnessed and certified by an approved third party inspection agency (e.g.
LLOYDS / BV / DNV / EIL / CEIL) shall be furnished to the Owner / Consultant for
Approval.
7.27 Soft-seated Ball, Plug and Butterfly valves shall be supplied with antistatic devices.
7.28 Wherever Locking Arrangement is specified in the valve MTO, the valve shall be provided
with locking arrangement such as pad lock and chain.
7.29 The padlocks supplied shall be heavy duty stainless steel weatherproof construction suitable
for outside use to fit the valve. The vendor shall supply 3 (three) keys for each padlock on
two heavy duty split rings with two stainless steel tags hard stamped or permanently etched
with the valve part number and tag.
7.30 Hand wheel diameter shall not exceed 750mm and lever length shall not exceed 500mm on
either side. Effort to operate shall not exceed 35 kg at hand wheel periphery. However failing
to meet the above requirements, vendor shall offer gear operated valve.
7.31 Socket weld end valves with non-metallic seats or seals shall be provided with 100mm long
nipples having materials and thickness equivalent to those specified in the relevant piping
material specifications. These nipples shall be welded to both ends of the valve by the
Vendor, before fitting packing, seats and seals.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 10 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
8 Gear Operator Requirements
8.1 Gear operators shall be provided for valves in accordance with the following Table, with the
exception that:- if any valve specified with hand-wheel or lever requires a torque of 271 NM
or more to open or close against a maximum differential pressure, then that valve shall be
supplied with a gear operator even if not specified in the purchase description.
8.2 Gear operator when required and supplied shall be totally enclosed Helical worm or Bevel
gears in weather resistant metallic grease box manually operable by hand wheel. It shall have
a position indicator for open / close and intermediate positions.
8.3 For gear operated valves, gear ratio shall be such that operating torque shall be less than 25
kg-m, with the differential pressure across the valve equal to the cold non shock pressure
rating.
8.4 Unless noted otherwise, Gear operator shall be provided for valves on the following basis.
--------- ------------------------------------------------------------------------------------
Valve Type ASME Class Valve Size
----------------------------------------------------------------------------------------------
Gate, Globe 150 & 300 12” & Larger
600 10” & Larger
900 6” & Larger
Plug & Ball 150 & 300 6” & Larger
600 4” & Larger
900 & 1500 3” & Larger
Butterfly 150 & 300 6” & Larger
8.5 Lever operated valves shall have Ball, Plug and Butterfly stem heads with a key way for
attaching the wrench. Circular stem heads with one or two flats are acceptable but in all cases
the design must be such that the wrench cannot be installed in a manner that allows the ball /
plug to be rotated more than 90°. Square stem heads are not acceptable. The lever / wrench
shall be at 90° to pipe centre line when the valve is closed. Stops shall be fitted at the fully
open and fully closed position to prevent the ball / plug from moving through more than 90°.
9 Test & Inspection
9.1 In addition to the normal seat test as specified all non return valves shall be tested for leakage
at 25% of the specified seat test pressure. Also a test should be carried out to ensure that all
non return valves start opening at 0.2kg/cm2 differential pressure across the valve.
9.2 Every valve, its components and auxiliaries must be subjected to all the mandatory tests and
checks called for in the respective codes, data sheets etc. by the manufacturer.
9.3 The sequence of pressure testing of soft seated valves shall be as follows:
First the hydro test for body shall be performed, after this the hydro test for seat shall be done
and then the low-pressure air test shall be performed. In case the valve does not pass the low-
pressure air test and leakage is observed through the seat, vendor shall replace the seats and
low-pressure air test is to be repeated.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 11 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
9.4 RADIOGRAPHY OF CAST VALVES
9.4.1 Valve casting shall undergo radiographic examination as specified below:
Material Rating Size Range Radiography
24” and below NIL** 150#
26” and below* 100%
16” and below NIL** 300#
18” and below 100%
All
600# & above All sizes 100%
* No radiography is required for valve of size 26” in cooling water service.
** For sizes 24” & below in 150# and 16” & below in 300#, radiography percentage if
specifically mentioned in individual valve material spec. sheet shall govern.
9.4.2 Valves other than steel castings shall be radio graphed to the following extents:
ASME 150#, DN600 or smaller 25%
ASME 150#, DN650 or larger 100%
ASME 300#, DN400 or smaller 25%
ASME 300#, DN450 or larger 100%
ASME 600#, and higher 100%
Carbon steel to NACE requirements 100%
Stainless and high alloy steel 100%
9.5 Following Inspection procedure shall be applicable where 10 % radiography of casting is
specified:
a) 10% Radiography is specified to indicate that 10 % of the quantity ordered per size per
heat shall be radiographically tested, fractions shall be rounded off to 1 to decide the
number of casting to be radiographically examined.
b) In case of rejection, double the quantity of the casting to be radiographed as determined
by 9.4.1 above shall be offered for radiography. In the event of further rejection of single
casting, the whole lot shall be radiographed.
c) The extent of radiography shall be restricted only to the critical areas as defined in
ASME B16.34. Acceptance of radiography is as defined in ASTM E446.
9.6 All valves shall be hydrotested & pneumatically tested for body & seat as per respective
valve datasheet.
9.7 Valve body thickness, wherever not specified in the standard, shall be as per ASME B16.34.
9.8 Hydrostatic testing shall be completed using potable water containing 1% by volume of
biodegradable wetting agent. Maximum chloride and fluoride content shall be 20ppm and the
ph value shall be between 6.0 and 8.0.
9.9 Castings shall not be impregnated with any material to prevent leakage.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 12 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
9.10 Upon completion of satisfactory testing all components to be thoroughly drained and dried
prior to preparation for packing.
9.11 Quality Control Plans shall be submitted for review with the bid. All valves and speciality
components will be subject to inspection in accordance with the Owner / Consultant
approved Vendor Quality Control Plan.
9.12 Vendors shall, as a minimum be ISO 9001:2008 or equal accredited, with manufacturers
preferably having ISO 9001:2008 or equal accreditation as well.
9.13 The Vendor shall provide full facilities/access for inspection by the Owner / Consultant’s
representative during the course of manufacture. The Vendor shall also arrange for the same
facilities / access to be made available at Sub-Vendors works, where deemed necessary by
the Owner / Consultant.
9.14 Strip check is required for 1% of total ordered quantity of Gate & Globe valves (min.1 no.)
for each Valve sheet no., however strip check is not required for CS/Brass/Bronze material
valves with 13% Cr/Brass/Bronze trims.
Samples for strip check shall be selected at random and shall generally be in the highest size
in the lot.
9.15 In case of motor operated or actuator operated valves, functional / operational checks as per
the requirements of the specifications shall be made on each valve.
10 Markings
10.1 Valve marking, symbols, abbreviations etc. shall be in accordance with MSS-SP 25 or the
standard referred in the specification sheet as applicable. Vendor’s name, valve rating,
material designation, nominal size, direction of flow (if any) etc. shall be integral on the
body.
10.2 Each valve shall have a corrosion resistant tag of stainless steel / aluminum giving size, valve
tag no. / code no. and pressure class rating securely attached to the valve body.
10.3 Paint or ink for marking shall not contain any harmful metal or metal salt such as zinc, lead
or copper which cause corrosive attack on heating.
11 Painting & Coatings
11.1 Unless otherwise specified, painting & coatings shall be done as per Clause 9.1 of API-600.
11.2 All carbon steel valves components and corrodable external parts shall be supplied primer
coated as follows :
a) Preparation: Shot blast to Swedish Standard SA2½.
b) Primer coat: Inorganic Zinc Primer 75 microns DFT minimum.
11.3 For 1¼ Cr- ½ Mo material the Vendor shall propose a suitable primer system to
accommodate design temperature of 550 C.
11.4 Painting shall be carried out after successful completion of all testing and inspection. Refer
Painting Specification (Document no.:272261-500-SP-PIP-003) for detailed instruction.
11.5 Valves shall also be coded in accordance with the requirement if Doc. No. 272261-500-PH-
PIP-005.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 13 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
12 Substitutions and Variations
12.1 Where a Vendor wishes to supply a suitable alternative to that specified in the data sheet,
they shall submit a specification of alternatives to the Owner / Consultant’s for approval at
the bid stage.
12.2 In the event of an order, the Vendor shall make no substitutions or variations to the
requirements of that order without written approval from the Owner / Consultant’s.
12.3 Where the Vendor wishes to make a substitution or variation to an item on the order, the
Vendor shall complete the Owner / Consultant’s “Concession Request Form” and return this
form for approval. If variation will affect the data sheet, this should also be attached showing
the change.
12.4 The Owner / Consultant’s will review each completed Concession Request Form issued by
the Vendor for the Order, for acceptance or rejection.
12.5 Approved Forms shall be sent to the Vendor for inclusion in the Dossier and Rejected Forms
shall be sent for action.
13 Packing
13.1 All valves shall be packed after inspection taking particular care for protection of the valve
yokes and flanges. The flanges shall be closed with plate covers; ends of threaded and socket
welding valves shall be closed using plastic caps.
13.2 All valves having grease seal stem or seat shall be shipped free of grease and provided with
suitable protection for grease fittings and stem to prevent shipping damage.
14 Certification & Traceability
14.1 All valves and speciality components shall be certified and copies of all documentation shall
be supplied for each valve and speciality component. Blanket certification is not acceptable.
If more than one component is on a certificate each component must be identified by the
Contractor’s tag number and purchase order number and Manufacturer's serial number, and
certificates for each valve must be listed for that valve.
14.2 Certificates shall be provided and the number of copies called for will be stated in the
Contractor’s Documentation Specification covering each item supplied. All certificates shall
be fully traceable to the item covered and shall be marked with the Contractor’s order
number, item number and tag/part number. They shall be clearly legible, in the English
language.
14.3 Material Certificates for basic material i.e. plate, forgings, or castings used in the
manufacture of flanges and valve bodies, bonnets and pressure retaining parts shall be
furnished as test certificates of the EN 10204:3.1 type. Vendor shall confirm which parts are
considered pressure retaining and shall include a list in the bid for Contractor review.
14.4 The certificates shall be issued, stamped and signed by the material Manufacturer's inspector,
who shall be independent of the Manufacturer's Production Department. This certificate shall
also be stamped and verified by the valve Manufacturer's QA / QC Department.
14.5 Where basic material is further processed by the Vendor to form the valve body or valve
components and such process may change the mechanical properties, etc., the Vendor shall
also furnish EN 10204:3.1 type certificates for the Manufacture of the furnished item.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 14 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
14.6 For valve internals and non-pressure containing parts works reports of the BS EN 10204 2.2
type shall be acceptable.
14.7 The Vendor shall supply certificates of conformity for non-metallic components of valves.
15 Maintenance Spares
In case of diaphragm valves, PTFE sleeved plug valves and piston valves, bidder should
furnish a complete list of maintenance spares required for two years trouble free operation
along with recommended quantities and quote the price for the same.
16 Despatch
16.1 Each end of the valve shall be protected with the following materials:
Flange face. : Wood or plastic cover
Bevelled end. : Wood or plastic cover
SW or Scrd. End. : Plastic cap
16.2 End protector of wood / plastic to be used on the flange faces shall be attached by at least
three bolts and shall not be smaller than the outside diameter of the flange. However the
plastic cap for SW & Scrd. End valves shall be press fit type.
16.3 End protectors to be used on bevelled end shall be securely and tightly attached.
16.4 For special service valves additional requirement of despatch shall be prescribed in datasheet.
17 Documentation
17.1 Vendor shall submit following documents with the offer.
17.1.1 Manufacturer’s complete descriptive and illustrative catalogue / literature.
17.1.2 Detailed dimensioned cross section drawing with parts / material lists, weight etc.
17.1.3 Drawings for valves with accessories like gear operator, hydraulic / pneumatic operator,
motor, extension bonnet, extended steam with stands, bypass etc. giving major salient
dimensions.
17.1.4 One copy of the valve specification sheets signed as ‘Accepted” by the manufacturer
Deviations, if any shall be marked as applicable on the valve specification sheet.
17.1.5 If the valve is regretted or has no deviation, the manufacturer shall write clearly on valve
specification sheets as “Regret” or “No Deviation”.
17.1.6 On failure to submit documents as specified in clauses 17.1.1 to 17.1.5 above, the offer is
likely to be rejected.
17.2 The following documents shall be submitted after placement of order.
17.2.1 Vendor shall submit for review drawings mentioned in clauses 17.1.1 & 17.1.3 before start of
manufacture. No other drawings shall be submitted for review.
17.2.2 Test report shall be supplied for all mandatory tests as per the applicable code.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 15 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
17.2.3 Material test certificates (physical properties, chemical composition & heat treatment report)
of the pressure containing parts shall be furnished for the valves supplied. Material test
certificates for the other parts shall also be furnished for verification during inspection.
17.2.4 Catalogues / Drawings (6 sets) shall be furnished along with delivery for Purchaser’s /
Owner’s record for all types of valves.
18 Guarantee
18.1 All valves and their components shall be guaranteed for trouble-free operation for a period of
18 months from the date of receipt or 12 months from the date of commissioning whichever
is earlier against the medium as listed in individual technical specification and the service
condition specified in the Pipe Specification Index enclosed.
18.2 Vendor shall guarantee all equipment as being suitable for the design conditions and service
fluids stated in the Piping Specification Index for the pipe class specified in valve data
sheets.
18.3 Confirmation of suitability shall be stated in the Vendors bid e.g. seats, seals etc.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 16 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
Annexure I: Gate & Globe Valves
1 General
1.1 Steel Gate Valves shall conform to one of the following Standards.
API 600 for sizes 2" through 24" and in general for larger sizes.
API 602 for sizes 1/2" through 1-1/2".
1.2 Steel Globe Valves shall conform to the following standards:
BS EN ISO 15761 for sizes 1/2" through 1-1/2"
BS 1873 for sizes 2" and larger.
1.3 The welding of flanges on to valves to meet the requirements for a flanged end valve is not
acceptable without prior approval.
1.4 A one-piece wedge shall be solid, a welded fabrication is not acceptable.
1.5 Lantern rings and leak-off plugs shall not be fitted unless specified.
1.6 By-pass
1.6.1 By-pass requirement for gate valves shall be provided as per the following.
Basic design of by-pass shall be as per MSS-SP-45 and ASME B 16.34.
ASME 150# On sizes 26” and above
ASME 300# On sizes 16” and above
ASME 600# On sizes 6” and above
ASME 900# On sizes 4” and above
1.6.2 By-pass valve shall be a globe valve. The sizes of globe valve shall be as under:
On main valve up to 4” = 1/2” or more
On main valve 6” to 8” = 3/4” or more
On main valve 10” & above = 1” or more
1.7 Vendor shall supply the by-pass valve duly tested and fitted to the main valve. Valves with by-
pass, shall have the direction of flow marked on the main valve. By-pass attachment to the
main valve body shall not be screwed. All the fillet welds for by-pass installation shall be
100% examined by DP / MP test. All butt-weld joints shall be 100% examined by radiography.
1.8 The by-pass piping arrangement shall be such that clearance between main valve body and by-
pass assembly shall be the minimum possible for the layout reasons.
1.9 Valve body / bonnet shall be forged / cast as specified. Forging are acceptable in place of
casting but not vice-versa.
1.10 Material of the construction of the yoke shall be minimum equivalent to body/bonnet material.
1.11 Stem shall be forged or machined from forged / rolled bar. No casting is permitted.
1.12 Stelliting / Hardfacing by depositions shall be minimum 1.6 mm. Renewable seat rings shall be
seal welded.
1.13 If any overlay weld-deposit is used for the body seat ring, seating surface, the seat ring base
material shall be at least equal to the corrosion resistance of material of the shell.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 17 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
1.14 All Gate / Globe valves shall have solid wedge for sizes 11/2” and below and flexible wedge
for sizes 2” and above.
1.15 All valves that require a torque of 271 Nm or more to open or close a valve against the
maximum differential pressure for which the valve is designed, shall be supplied with a gear
operator, even if not specified in the purchase description.
1.16 Gear operators shall be totally enclosed weatherproof type packed with a suitable lubricant, and
fitted with a grease nipple.
1.17 Where ring joint gaskets are used for the body to bonnet joint it shall be an Oval Ring and of
hardness lower than the body and bonnet.
1.18 The carbon content of valve bodies with welding ends, and bodies and bonnets on valves with
welded bonnets shall be 0.25% maximum.
1.19 Gate valves 2" and larger shall be supplied with a flexible wedge.
1.20 All globe valves shall be of guided disc design and suitable for installing in all positions like
stem horizontal, vertical, and inclined etc.
1.21 All fillet welds such as for jacket welds etc. on valve body shall be 100 % DP / MP tested.
1.22 All valve body castings shall be of radiographic quality to ASME B16.34 APPENDIX-I and
shall be governed by the non-destructive testing requirements as per APPENDIX –II,III & IV
of ASME B16.34.
1.23 Stem protection is required for all CS gate and globe valves where 11-13 % Cr trims are
specified. The stem shall be totally enclosed in a sleeve, which shall be packed with grease.
2 Identification Marking Requirements
2.1 For bodies or bonnets the heat or melt number shall be marked and shall be traceable to the
relevant material certificate.
2.2 A metal tag shall be attached as specified under Clause 10 (Markings) of this document. Tags
shall be stainless steel or brass, a minimum of 1 mm thick, and are to be securely wired around
the gland studs with stainless steel wire of a minimum diameter of 1 mm, additionally the
Stock Code number shall be hard stamped on the bonnet flange rim in 3 mm high characters
minimum.
3 Testing
The test fluid for hydrostatic testing shall be water containing a suitable corrosion inhibitor.
The water shall have a maximum chloride content of 20 ppm. The valve shall be thoroughly
dried before despatch.
4 Certification
4.1 Material Certificates in accordance with EN 10204:3.1 are required for Bodies and Bonnets
and as a minimum shall include,
a) Chemical Analysis by Product
b) Mechanical Properties
c) Heat Treatment Statement
d) Non Destructive Test results
e) Hydrostatic and/or Pneumatic Test results
f) Heat or Melt Number
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 18 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
g) Dimensional check report.
4.2 All certificates shall state the Manufacturers name and location, all forging and casting
certificates shall be from original forge or foundry. Certificates shall include the Owner /
Consultant’s purchase order number and purchase order item number.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 19 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
Annexure II: Check Valves
1 General
1.1 Steel Check Valves shall conform to one of the following Standards;-
BS EN ISO 15761 for sizes 1/2" through 1-1/2".
BS 1868 for Swing Check Valves 2" and larger.
API 594 for Wafer Check Valves.
1.2 Unless specified otherwise in the data sheet all the check valves 3” & above (except in 900#,
1500# & 2500# rating) shall have a drain boss. A tapped drain hole with plug shall be provided
as per ASME B16.34. Threads shall be as per ASME B1.20.1 (Taper) NPT. The drain boss
shall be provided at location ’Q’ in accordance with Fig.no.1 of ASME B16.34.
1.3 Wherever check valve disc assembly is supported from the cover of check valves the following
shall be ascertained.
Positive location / positioning of cover must be provided to ensure correct alignment
of valve disc.
Hinge pin design must permit accurate alignment of the disc and valve seat.
1.4 For heavy check valves (50 kg & above), provisions shall be available for lifting by way of
lugs, eyebolts and other such standard devices.
1.5 Piston lift check valves shall be installed only in horizontal lines. Swing type check valves
shall not be installed in vertically downward flowing lines.
1.6 The welding of flanges on to Swing Check valves to meet the requirements for a flanged end
valve is not acceptable without prior approval.
1.7 Where ring joint gaskets are used for the body to bonnet joint on Swing Check Valves it shall
be an Oval Ring and of a hardness lower than the body and bonnet.
Valves supplied by Indian Vendors may use non-metallic gaskets or part of gaskets to
Indian Standards.
1.8 The carbon content of Swing Check Valve bodies with welding ends shall be 0.25% max.
1.9 All Swing Check Valves shall have an integral cast boss at position G in accordance with
ANSI B16.34.
1.10 All fillet welds such as for jacket welds etc. on valve body shall be 100% DP/MP tested.
1.11 All valve body castings shall be of radiographic quality to ASME B16.34 APPENDIX-I and
shall be govern by the non-destructive testing requirements as per APPENDIX–II, III & IV of
ASME B16.34.
2 Identification Marking Requirements
2.1 For bodies or bonnets the heat or melt number shall be marked on and shall be traceable to the
relevant material certificate.
2.2 A metal tag shall be attached as specified under Clause 10 (Markings) of this document. Tags
shall be stainless steel or brass, a minimum of 1 mm thick, and are to be securely wired around
the Valve Body with stainless steel wire of a minimum diameter of 1 mm, additionally the
Stock Code number shall be hard stamped on the cover flange rim in 3 mm high characters
minimum.
3 Testing
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 20 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
3.1 The test fluid for hydrostatic testing shall be water containing a suitable corrosion inhibitor.
The water shall have a maximum chloride content of 20 ppm. The valve shall be thoroughly
dried before despatch.
3.2 For jacketed valves in addition to the testing of valve the jacket shall be tested as per the valve
specifications and shall be thoroughly dried.
4 Certification
4.1 Material Certificates in accordance with EN 10204:3.1 are required for Bodies and Covers and
as a minimum shall include,
a) Chemical Analysis by Product
b) Mechanical Properties
c) Heat Treatment Statement
d) Non Destructive Test results
e) Hydrostatic and/or Pneumatic Test results
f) Heat or Melt Number
g) Fire Safe Test Certificates
h) Dimensional check report.
4.2 All certificates shall state the Manufacturers name and location, all forging and casting
certificates shall be from original forge or foundry. Certificates shall include the Owner /
Consultant’s purchase order number and purchase order item number.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 21 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
Annexure III: Ball Valves
1 General
Steel Ball Valves shall conform to the following requirements:
1.1 The welding of flanges on to valves to meet the requirements for a flanged end valve is not
acceptable without prior approval.
1.2 All Ball valves shall be "Fire Safe" in accordance with either API 6FA, API 607 or BS EN
12266, Part-2 and have anti-static devices in accordance with BS EN ISO 17292. Fire safe
certificates shall be submitted, prior to manufacture, to cover the valves on the Purchase Order.
1.3 The Ball shall be of a one-piece solid construction with a continuous through bore, welded-in
liners are not acceptable.
1.4 The ball of the ball valve shall not protrude outside the end flange of the valve.
1.5 All ball valves shall be Bi-directional.
1.6 Ball shall be solid type unless otherwise specified.
1.7 Body seat shall be renewable type.
1.8 All ball valves shall be forged type for 1 ½ “& below.
1.9 All Ball valves shall be supplied with position indicator.
1.10 Ball valves shall be floating ball type / trunnion mounted as per following:
150# 8” & smaller Floating ball
10” & larger Trunnion mounted
300# 4” & smaller Floating ball
6” & larger Trunnion mounted
600# & above 1.5” & smaller Floating ball
2” & larger Trunnion mounted
1.11 All trunnion-mounted ball valves shall be provided with spring loaded seat rings.
1.12 Trunnion-mounted ball valves shall be supplied with provision for double block and bleed.
1.13 Unless otherwise specified in the data sheets, bore of all reduced bore ball valves shall be in
accordance with API 6D / ISO 17292.
1.14 Ball valves even with wrench or lever operators shall have “Open” Position indicators with
limit stops.
1.15 Stem retention shall not depend on the packing gland, Removable Stem retaining parts inside
the Valve body are not acceptable, Stem shall be of an anti-blow out design.
1.16 All Ball valves are required to provide automatic body cavity pressure relief to prevent over
pressurisation when valve is closed. Vendors to advise when Quoting which side will vent and
whether a specific vent direction can be offered.
1.17 All Valves specified as socket weld shall be supplied fitted with factory welded in pipe nipples
to give an overall length of 300 mm, nipples to be a minimum thickness of schedule 80 for
carbon steel and schedule 40S for stainless steel and of a material similar to the valve body.
1.18 Where ring joint gaskets are used for the body to bonnet joint it shall be an Oval Ring and of a
hardness lower than the body and bonnet.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 22 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
1.19 High Pressure closure test (seat hydrostatic test) shall be conducted on all ball valves as per the
relevant test standards.
1.20 All fillet welds such as for jacket welds etc. on valve body shall be 100% DP/MP tested.
1.21 All valve body castings shall be of radiographic quality to ASME B16.34 APPENDIX-I and
shall be governed by the non-destructive testing requirements as per APPENDIX –II,III & IV.
1.22 Ball valve cavities shall be vented to relieve excess pressure. Venting may be achieved through
self-relieving seat design or by drilling a hole in the bore. The direction of flow shall be
permanently marked on the valve body. The cavity venting side of the valve shall also be
permanently marked on the valve.
1.23 Material selection for soft seats/seals for Ball valves shall be suitable for maximum differential
pressure, corresponding to pressure/temperature rating and service fluid handled on a
continuous basis. The seat/seal material in valve data sheets for Ball valves is indicative only.
Vendor can propose an alternative seat provided he furnishes the pressure/temperature rating of
the proposed seat material which shall cover the class temperature pressure rating of the valve
and is superior to the seat/seal material specified in the valve datasheets.
2 Identification Marking Requirements
2.1 For bodies or bonnets the heat or melt number shall be marked and shall be traceable to the
relevant material certificate.
2.2 A metal tag shall be attached as specified under Clause 10 (Markings) of this document. Tags
shall be stainless steel or brass, a minimum of 1 mm thick, and are to be securely wired around
the gland studs with stainless steel wire of a minimum diameter of 1 mm, additionally the
Stock Code number shall be hard stamped on the bonnet flange rim in 3 mm high characters
minimum.
3 Testing
3.1 The test fluid for hydrostatic testing shall be water containing a suitable corrosion inhibitor.
3.2 The water shall have a maximum chloride content of 20 ppm. The valve shall be thoroughly
dried before despatch.
4 Certification
4.1 Material Certificates in accordance with EN 10204:3.1 are required for Bodies and Bonnets
and as a minimum shall include,
a) Chemical Analysis by Product
b) Mechanical Properties
c) Heat Treatment Statement
d) Non Destructive Test results
e) Hydrostatic and/or Pneumatic Test results
f) Heat or Melt Number
g) Dimensional check report.
4.2 All certificates shall state the Manufacturers name and location, all forging and casting
certificates shall be from original forge or foundry. Certificates shall include the Contractors
purchase order number and purchase order item number.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 23 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
Annexure IV: Butterfly Valves
1 General
1.1 Steel Butterfly Valves (excluding lined valves) shall conform to API 609.
1.2 Valves are to be suitable for installation with the operating shaft in the vertical plane.
1.3 Valves shall be hydrotested in accordance with API 598.
1.4 Valve stem packing shall be adjustable by means of an external gland.
1.5 Valves shall have an anti-blow out shaft design.
1.6 Valves that are torque seated or require a torque of 271 Nm or more to open or close against
the maximum working differential pressure shall be fitted with a gear operator, even if not
specified in the purchase description.
1.7 Gear operator shall be totally enclosed weatherproof type packed with a suitable lubricant, and
fitted with a grease nipple.
1.8 All valve body castings shall be of radiographic quality to ASME B16.34 APPENDIX-I and
shall be govern by the non-destructive testing requirements as per APPENDIX –II,III & IV.
2 Identification Marking Requirements
2.1 For bodies and bonnets the heat or melt number shall be marked on and shall be traceable to
the relevant material certificate.
2.2 The valve serial number(s) shall also be noted on the relevant certificate.
2.3 A metal tag shall be attached as specified under Clause 10 (Markings) of this document. Tags
shall be stainless steel or brass, a minimum of 1 mm thick, and are to be securely wired around
the Valve Body with stainless steel wire of minimum diameter of 1 mm, additionally the Stock
Code number shall be hard stamped on the cover flange rim in 3 mm high characters minimum.
3 Testing
3.1 The test fluid for hydrostatic testing shall be water containing a suitable corrosion inhibitor.
3.2 The water shall have a maximum chloride content of 20 ppm. The valve shall be thoroughly
dried before despatch.
4 Certification
4.1 Material Certificates in accordance with EN 10204:3.1 are required for Bodies and Bonnets
and as a minimum shall include,
a) Chemical Analysis by Product
b) Mechanical Properties
c) Heat Treatment Statement
d) Non Destructive Test results
e) Hydrostatic and/or Pneumatic Test results
f) Heat or Melt Number
g) Valve Serial Number
h) Dimensional check report.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 24 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
4.2 All certificates shall state the Manufacturers name and location, all forging and casting
certificates shall be from original forge or foundry. Certificates shall include the Contractors
purchase order number and purchase order item number.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 25 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
Annexure V: Plug Valves
1 General
1.1 Plug Valves shall conform to BS 5353.
1.2 The welding of flanges on to Valves to meet the requirements for a flanged end Valve is not
acceptable without prior approval.
1.3 Glands shall be of a steel material.
1.4 Valve stem packing shall be adjustable by means of a bolted gland.
1.5 Lubricant sealant shall be suitable for the service & temperatures specified in valve
specifications.
1.6 Seals, diaphragms and gaskets shall be fire resistant and be suitable for the specified service &
temperatures.
1.7 Gear operator shall be totally enclosed weatherproof type packed with a suitable lubricant, and
fitted with a grease nipple.
1.8 All valve body castings shall be of radiographic quality to ASME B16.34 APPENDIX-I and
shall be governed by the non-destructive testing requirements as per APPENDIX –II,III & IV.
2 Identification
2.1 For bodies and bonnets the heat or melt number shall be marked on and shall be traceable to
the relevant material certificate.
2.2 The valve serial number(s) shall also be noted on the relevant certificate.
2.3 A metal tag shall be attached as specified under Clause 10 (Markings) of this document. Tags
shall be stainless steel or brass, a minimum of 1 mm thick, and are to be securely wired around
the Valve Body with stainless steel wire of minimum diameter of 1 mm, additionally the
Stockcode number shall be hard stamped on the cover flange rim in 3 mm high characters
minimum.
3 Testing
3.1 The test fluid for hydrostatic testing shall be water containing a suitable corrosion inhibitor.
3.2 The water shall have a maximum chloride content of 20 ppm. The valve shall be thoroughly
dried before despatch.
4 Certification
4.1 Material Certificates in accordance with EN 10204:3.1 are required for Bodies and Covers and
as a minimum shall include,
a) Chemical Analysis by Product
b) Mechanical Properties
c) Heat Treatment Statement
d) Non Destructive Test results
e) Hydrostatic and/or Pneumatic Test results
f) Heat or Melt Number
g) Valve Serial Number
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 26 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
h) Dimensional check report.
4.2 All Certificates shall state the Manufacturers name and location, all forging and casting
certificates shall be from original forge or foundry. Certificates shall include the Contractors
purchase order number and purchase order item number.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 27 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
Annexure VI: Non Destructive Examination (NDE) for Valve Castings
1 General
1.1 All castings shall be manufactured in accordance with the requirements given in the Purchase
Order/Contract and shall be of radiographic quality.
1.2 Vendor shall demonstrate it has the experience, quality control and personnel to assure the
production of consistently sound castings.
1.3 Vendor may submit an alternative inspection programme for review and approval at the bid
stage. The submittal should address all of the issues referred to in this Specification.
2 Casting Inspection Requirements
2.1 Valve Bodies and Bonnets shall be subjected to the following inspection with a minimum of
one for each size/ stockcode/ batch ,
a) Quality D on all castings plus other quality designations mentioned in Table 1.
b) Each welding end of all butt weld ended valves shall be subjected to Inspection type
Quality A.Testing shall cover a minimum length of 2”, or as per ASME B 16.34
whichever is higher, from each end.
c) For Valves specified to have Extended Bonnets for low temperature service, Valve
casting weld repairs shall also have the weld deposit impact tested in accordance with
ASME B31.3 para. 323.3 at a temperature of minus 185 Degrees C (or lower), as part
of the welding procedure qualification.
2.2 A castings quality designation, which indicates inspection requirements are defined as follows:
a) Quality A
Visual examination (Clause 3.2) plus magnetic particle examination (Clause 3.3) or
dye penetrant examination (Clause 3.4) of all accessible interior and exterior surfaces,
including machined surfaces, plus radiography of critical areas (Clause 3.5).
b) Quality B
Visual examination (Clause 3.2) plus magnetic particle examination (Clause 3.3) of all
accessible interior and exterior surfaces including machined surfaces. For non-
magnetic materials, dye penetrant examination methods shall be used (Clause 3.4).
c) Quality C
Visual examination (Clause 3.2) plus magnetic particle examination (Clause 3.3) of
machined surfaces. For non-magnetic material, dye penetrant examination methods
shall be used (Clause 3.4).
d) Quality D
Visual examination in accordance with Clause 3.2.
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 28 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
Table 1
Type of Inspection
Sr
No
.
Material Rating
(LB) Quality B on
10% of quantity
of castings
Quality A on
10% of
quantity of
castings
Quality A on
100% of
quantity of
castings
150& 300 18” and above i
Carbon Steel and Low
Temp. Carbon Steel
ii Stainless Steel
(Other than those
mentioned above.)
Up to 600 Up to 16” 18” and above
3 Inspection Procedures And Acceptance Standards
3.1 Surface Preparation
Surfaces of all castings shall be suitably cleaned by chipping or blasting.
3.2 Visual Examination
All castings shall be visually examined and proven free from sand, scale, cracks, tears, voids
and other harmful effects.
Acceptance levels shall be as specified in MSS-SP-55.
3.3 Magnetic Particle Examination (MPE)
MPE shall be carried out on ferritic castings in accordance with ASTM E709.
Acceptance Criteria : ASME B16.34, Annex C, Section 2.1
3.4 Dye Penetrant Examination (DPE)
DPE shall be conducted on non-magnetic castings and where MPE is not feasible. The testing
procedure shall be in accordance with ASTM E16.5.
Acceptance Criteria : ASME B16.34, Annex D, Section 2.1
3.5 Radiographic Examination
Radiographic examination of critical areas only shall be conducted as specified in ASME
B16.34. Critical areas are defined as an abrupt change in section, weld ends, at risers, gates or
feeders and areas of highest stress. For valve castings critical areas are as defined Section 8.3
of ASME B16.34.
Acceptance criteria : ASME B16.34, Annex B
3.6 Ultrasonic Examination
Ultrasonic examination may be carried out by agreement where radiographic inspection is not
feasible.
Procedure : ASME VIII, Div. 1, Appendix 7 or ASTM A609
Acceptance Level : ASTM A609
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 29 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
Quality level as follows:
Thickness Acceptance Level
< 50mm 1
50-100mm 2
> 100mm 3
4 Dimensions
All initial castings and randomly selected castings shall be dimensionally checked to ensure
compliance with the minimum wall thickness specified and the overall dimensions.
5 Submittal of NDE Procedures
For quality standard A & B, NDT procedures shall be submitted for review and approval.
6 Repair Procedures
The repair of any defect found on castings by plugging, peening, use of plaster or cement
compounds, or impregnation by plastic materials or similar compounds is prohibited. Repairs
to the pressure boundary shall be by welding only.
Major repairs are defined as those that require removal of 20% of the casting wall thickness or
25 mm which ever is less or those that result in a repair area that exceeds 6,500 mm². For
quality standard A & B, major weld repair procedures shall be submitted for approval.
All repairs by welding shall be made by procedures/welders in accordance with ASTM A488.
The analysis of the deposited weld metal shall conform to the nominal analysis of the parent
casting.
After major weld repair all castings shall be heat treated or stress relieved as required by the
casting specification, however, the Buyer reserves the right to specify solution heat treatment
for repairs to austenitic stainless steel where considered applicable for process or
environmental reasons.
All weld repairs shall be re-examined by appropriate methods and as defined in Section 3.0.
Annexure VII: Pressure Testing Requirements
Table 1
EPMC SERVICES FOR URAN-CHAKAN-
SHIKRAPUR-LPG PIPELINE PROJECT
Doc No.:272261-500-SP-PIP-009 Rev: 0 Page 30 of 30
C:\Documents and Settings\sal51536\Local Settings\Temporary Internet Files\OLK8D\272261-500-SP-PIP-009 Rev 0.doc
Valve
Type
Hydrotest
Body
(1.5 x DP)
Hydrotest
Seat
(1.1 x DP)
Hydrotest
Backseat
(1.1 x DP)
Pneumatic Test
Seat
(7 bar)
Disc Strength
Test
(1.5 x DP)
Ball 100 % 100 % N/A 100 % N/A
Gate 100 % 100 % 100 % 100 % N/A
Globe 100 % 100 % 100 % 100 % N/A
Check 100 % 100 % 100 % 100 % N/A
Butterfly 100 % 100 % N/A 100 % Valves 14”NPS
& Larger
Parallel
Slide 100 % 100 % 100 % 100 % N/A