Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
TECHNICAL SUBMISSION
SPRINKLER SYSTEM – SKY STUDIOS, ELSTREE
Document Reference: E.131886 - SSTS
Date: 01.03.2021
Revision: A
Created By: Nick Strong GIFireE EngTech IRMCert
Revision Description Date Created By Approved By
-
Original Technical Submission.
01.03.21
Nick Strong
Kris Parker
A Additional Pre-Action Valves included. 30.03.21
Nick Strong
Kris Parker
Design Standards
Sprinkler Protection design to The LPC Rules incorporating BSEN12845: 2015,
Technical Bulletins, and Annexes.
The sprinkler protection will be designed to various hazard classifications (refer to
the table below). Annex F – Sprinkler System Enhancements has been applied
across all sprinkler systems where applicable.
Hazard Classifications
Building Reference Hazard Classification
Production Office Building 133 Ordinary Hazard Group 1
Sound Stage 131 Ordinary Hazard Group 4
Sound Stage 132 Ordinary Hazard Group 4
Production Office Building 142 Ordinary Hazard Group 1
Sound Stage 141 Ordinary Hazard Group 4
Visitor / Administration Building 110 Ordinary Hazard Group 1
Production Office Building 154 Ordinary Hazard Group 1
Sound Stage 151 Ordinary Hazard Group 4
Sound Stage 152 Ordinary Hazard Group 4
Sound Stage 153 Ordinary Hazard Group 4
Sound Stage 161 Ordinary Hazard Group 4
Sound Stage 162 Ordinary Hazard Group 4
Sound Stage 163 Ordinary Hazard Group 4
Sound Stage 171 Ordinary Hazard Group 4
Sound Stage 172 Ordinary Hazard Group 4
Sound Stage 181 Ordinary Hazard Group 4
Sound Stage 182 Ordinary Hazard Group 4
Production Office Building 183 Ordinary Hazard Group 1
Production Support Building 121 High Hazard
Production Support Building 122 High Hazard
Multi-Storey Car Park Ordinary Hazard Group 2
Sprinkler protection in the FDR room only
Areas Not Sprinkler Protected
Building Reference
Production Office Building 133
Sound Stage 131
Water Supplies
We propose to attend site and install a new sprinkler water storage tank and sprinkler
pumphouse – details as follows: -
Sprinkler Water Storage Tank
We propose to supply and install 2 No.
280m3 effective capacity galvanised steel
circular LPCB Approved sprinkler water
storage tanks with a total effective capacity
of 560m3.
The sprinkler tanks are to be designed to
The LPC Rules incorporating BSEN12845:
2015, Technical Bulletins and Annexes and
LPS1276 – The Requirements for the LPCB
Certification and Listing of Above Ground
Suction Tanks for Sprinkler Systems.
Fire Sprinkler Tanks – 560m3 Combined Effective Capacity Effective Capacity (per tank) 280.2m3 (250mm freeboard, 255mm dead water)
Dimensions (per tank) Ø6.2m x (H)9.7m
Roof Type Trough deck (0.75kN/m2 live load)
Sealing Type PVC liner
Ground Loading (per tank) 95kN/m2
Seismic Zone N/A
Shell Fixing Angle mount
Coating Internally Galvanised to BSEN10346
Coating Externally Galvanised to BSEN10346
Concrete Base
The concrete base on which the sprinkler tanks will be located are to have a power
float finish to +/- 5mm – By Others.
Tank Design
Below is the proposed design for each of the sprinkler tanks: -
Included with each sprinkler tank is the following: -
Item Description Qty Air gaps AB air gap duct complete with insect mesh - C(7-10R) 1
Contents gauge CYL-0-10M Contents Gauge complete with a no loss
connector & boss
1
Drain CYL – 50mm gate valve complete with boss 1
Float valve chamber CYL – 1 metre x 1 metre x 400mm high hinged float
valve chamber
1
Immersion heater CYL- FW001 Immersion Heater to comply with complete
with boss
1
Inlet 100mm BSP Equilibrium ball valve suitable up to 5 Bar
complete with copper ball & drop arm - flanged
1
External ladder (fixed) Roof platform 750mm LH - C (7-10R) 1
External ladder
(removeable)
BS/FM Ladder 8 walk-off hook-on 1
Level switch CYL - S/S level switch, complete with mini-din plug &
boss
1
Manways CYL - Side access manway - 600mm Square - C (7-
10R) complete with gaskets
1
Overflow 150mm flanged (rolled to C radius) overflow & bell
mouth
(extended) - kit
1
Pump test return CYL - Ø150mm test return - complete with flashing 1
Vortex inhibitor CYL - Vortex inhibitor - 300mm complete with elbow &
PN16 flange
1
Warning pipe CYL – 25mm PVC plain end tank connector 1
Pipe brackets (100mm) CYL – heavyweight pipe bracket - 100mm 4
Pipe brackets (150mm) CYL – heavyweight pipe bracket - 150mm 3
Notes:
• Sprinkler Water Storage Tank concrete base By Others
• Tank Infill from Town’s main to base of the tank By Others
Within our quotation we have included to install the sprinkler water storage tank infill
pipework from the base of the tank to the sprinkler tank ball valve housing. The infill
main from the connection to the Town’s main to the base of the tank is By Others.
Sprinkler Pre-Packaged Pumphouse
Place–Down-and-Connect Fire
Pumphouse.
The fire sprinkler pumphouse will be
designed and manufactured to The LPC
Rules incorporating BSEN12845: 2015,
Technical Bulletins and Annexes.
Fire Pump Details
The fire pumps are to be of the flooded suction type and are as follows: -
• Duty Pump – Electric
• Standby Pump – Diesel
Both fire pumps are rated at 6500 L/min @ 8.5 bar (Inc 0.5 bar margins).
Model: NKF125-315 289mm diameter impeller horizontal
end suction centrifugal pump
Construction: Cast iron casing, all bronze or cast iron with bronze
wear ring impeller, steel shaft fitted with a single
mechanical seal
Connections: Flanged BS4504/16.
Electric set: Long coupled to a 132 kW IP55 motor arranged for
415v/50Hz/3ph AC supply. Supplied fitted with
casing circulation relief valve. Complete with
BSEN12845 Star/Delta Controller supplied fitted to
wall and pre-wired.
Diesel set: As above but with steel shaft and long coupled to a
Clarke diesel engine model JU6H-LP54 161 kW.
All mounted on a fabricated steel base plate with
non-spacer coupling & guard. LPC (with contact to
initiate operation of ventilation louvres) twin sets of
Ni-Cad batteries and 6-hour Fuel tank will be floor-
to-wall mounted, completely piped, wired, and
tested.
Our proposal includes full manufacture of
the sprinkler pumphouse and installation
of
LPCB Fire pump sets & jockey pump
inside with pipework, wiring & lighting to
provide a fully packaged unit.
The pipework termination will be external
to the enclosure with provision in the
base of one wall to accommodate power
and alarm cables.
General Notes
• Fully mechanically and electrically tested including flow test
• Unit can be tailored to suit site layout and orientation
• Standard Kingspan enclosure with C4 Painted base Frame
• 1 hour Fire rated enclosure
Remote Alarm Panel
Model: ‘Harrijess’ remote alarm panel type H400
The remote alarm panel is designed to monitor the state of the pumps / pumphouse
and reports the status via front panel indicators.
The panel incorporates the following:
• Sixteen normally closed inputs (all fully monitored)
Alarms to be repeated:
We Would usually recommend the following alarm signals are repeated per pump:
Electric Pumps
• Pump on demand
• Pump running
• Supply status
• Mains failure
Diesel Pumps
• Pump on demand
• Pump running
• AC mains failure
• Fault at controller
Additional Signals
• Fire in pumphouse
• Low temperature in pumphouse
• Low water level in tanks
• Common fault signals from monitored stop valves
• Trace heating monitoring
Sprinkler Pumphouse Commissioning
We employ Grundfos; as the manufacturer of the sprinkler pumphouse; to undertake
the full commissioning alongside our site engineers.
The scope of the works includes: -
• Installation check
• Voltage and protection check
• Winding resistance measurements for pumps
• Level, pressure switch or sensor installation check
• Setting of proper functions and parameters
• Start-up operation
• Working parameters test
• All settings documented in a service report
• Only for long-coupled pumps: pump alignment included
• Training of your operations and maintenance personnel on daily operation and
minimum maintenance to keep the equipment up and running
• Information about recommended consumables or wear parts
• Service job finalised with a report highlighting all areas covered and including
recommendations
Water supplies – Frost Protection
We propose to design, supply, and install a complete trace heating system providing
frost protection to the sprinkler system suction, delivery and tank infill pipework that
forms part of the water supplies installation.
Trace Heating
The Trace heating system will be designed in accordance with BS EN 12845 dual
trace heating and consists of self-regulating trace heating cable, we have allowed to
provide all necessary junction boxes, connection kits, fixing tapes and end seal kits to
provide a complete trace heating system in accordance with Electrical Resistance
trace heating systems for industrial and commercial applications.
We have included for a trace heating monitoring control unit type THMU2B which
includes the following: -
• Mains Input 230v AC 50/60 Hz
• Power Heating monitoring range:
o 30 Watts to 3.0K Watts (Constant Wattage)
o 30 Watts to 2.0K Watts (Self-regulating)
• Automatic Measurement for both Primary & secondary outputs on Initial Setup
• Number of Circuits:
o 2 Heating Circuits (Primary & secondary) each with 2 output terminals
• Heating monitoring
o Automatic testing of both circuits at 2-hour intervals
• Heating Circuit Protection:
o Short Circuit Protection via 16 Amp Type “B “, 6KA MCB
• Monitoring Trip Fault condition:
o Constant Wattage:
▪ Measurement setting less 25 - 30 % Self Regulating
▪ Measurement setting less 35 - 40 % (Will automatically switch from
Primary to Secondary Output)
• Heating Set Point:
o 5 or 8 O/C via DIL switch (factory set to 5 O/C)
• Sensor Temperature Indication:
o LED Bar Display External Remote Input
o N/O - closing to Power heating circuit
o Common Fault Auxiliary Output
o 1 set CHO rated at 1-amp 50V DC
o Temperature sensor type NTC Thermistor
o 10K Temperature sensor
o Cable Length 1.5 metre
• Enclosure Construction Impact resistant IP55 rated, Grey ABS to RAL 7035.
Thermal Insulation
We propose to supply and install 25mm thick
mineral wool sections outer clad in aluminium
with all valves, flanges etc. shall be fitted with
silicone coated glass cloth mattresses
manufactured with Velcro and drawstring
fasteners to allow for easy removal and
refitting for maintenance purposes.
Testing
Following the installation of the Electric Trace
Heating and prior to the installation of the
thermal Insulation the system will be tested, on
completion of the test (witnessed by client or
his representative) and subject to the results
the thermal Insulation is to be applied.
Warning Labels
We have allowed for trace heating warning labels.
Underground Sprinkler Main
We propose to install an underground sprinkler main across the Sky Studios site. We
have included for the following: -
Pipework
• Supply and install approximately 1800 metres of 225mm diameter SDR11
Black HPPE and 48 metres of 180mm diameter SDR11 HPPE pipe work,
which will commence from the pump house to each of the building entry
points. In trench welding will be using a Manual Butt Fusion Machine where
necessary
• Supply and installation of 22 No. 225mm diameter moulded PE branches, 18
No. 225mm diameter moulded 90° elbows, and 15 No. 225mm diameter 45°
bends
Isolation Valves
We propose to supply and install 29 No. UL/FM approved post indicator valves (post
indicators not included) sectional isolation valves across the site as listed below.
The valves are to be installed as per the detail on Hoare Lea drawing - 0209630-HL-
XX-XX-DR-M- 580-0003.
For each valve this will include 2 No. Viking Johnson Flexlock flange adaptors, 1 No.
Flexlock coupler, 2 No. ductile puddle flanges.
The sections between the 2 No. flange adaptors will be in EN545 ductile iron.
• 24 No. DN200mm
• 5 No. DN150mm
Notes:
• Chamber Sections, access ladders and water proofing membrane to be By
Others
• All civil works – trenching, backfilling etc… By Others
Building Entry Points
We propose to supply and install 22 No. building entry points.
Following the building entry isolation valves SDR11 PE pipe will pass under the
building where it will turn 90° elbow to the vertical . From a PE flange the pipe will
rise up with a 1000mm EN545 blue ductile double flanged spool to finish
approximately 250mm above finished floor level.
• 17 No. DN200mm
• 5 No. DN150mm
Testing
We propose to undertake 4 No. sectional water tests. We will require an abundant
water supply within 30 metres of the test point, supplied By Others.
Upon completion of the installation all pipework will be fully hydrostatically pressure
tested to 15 bar for 2 hours accordance with IGN-4-01-03 standards.
Marker Tape
We will supply only marker tape (free issue) for the fire main to be installed By
Others.
Should the pipe require additional wrapping with marker tape at 500mm centres or
specialist tape in accordance with BS1710 then additional rolls will be required and
charged for.
Connections at the boundary
1. We will provide a quotation for pipework and fittings at the point of connection as
identified by the client. All water authorities are different, and each site has its
own individual requirements based on the site / client requirements.
2. Details of the boundary including any valves, check valves, drain valves or water
meters must be provided by the client. Any additional work and fittings required
at the boundary different to what was originally quoted will be chargeable.
Backfilling of Pipework
1. Most water authorities insist that any new pipework should not be backfilled prior
to their inspection and approval of the trench and system. We will not be
responsible for any costs incurred should you backfill prior to water authority
approval.
2. All new pipework should be pressure tested in accordance with its relevant
testing specification, any backfilling that is required prior to a pressure test should
be discussed with us. We will not be held responsible for any excavation or re-
instatement costs that occur due to failure of pipe or fittings if they have been
backfilled prior to a pressure test being carried out.
3. It is a requirement that any valves, check valves or flanges that are buried must
be fully accessible by way of a manhole or chamber for the routine maintenance
and replacement of these fittings. Our operatives will require access to any
flanges, nuts, and bolts for the re-tightening of flanges, if we cannot gain access
to these area’s we will not be responsible for any costs incurred to re-excavate or
clear out the chambers.
Disinfection
1. All water authorities have different requirements for the process of disinfection of
water mains, the client will need to provide details of the process required for the
relevant water authority.
2. A readily available and abundant water supply within 30 metres of the pipe ends
must be made available for the disinfection process to be carried out. Also,
please ensure that there is sufficient drainage to allow emptying of the pipework
or flushing should disinfection be required.
Sprinkler Installation Control Valves
Wet Alarm Valves
Across the new site we propose to supply and install 23
No. new WET control valve sets complete with: -
A. Main isolation control valve
B. Stop valve
C. Bypass arrangement
D. Main alarm valve
E. Pressure switch
F. Hydraulic alarm bell
G. Valve trim (drains and test lines etc...)
H. Pressure gauges
Pre-Action Valves
Within the Multi-Storey Carpark we propose to supply and install 1 No. new PRE-
ACTION control valve set complete with: -
A. Main isolation control valve
B. Main alarm valve
C. Flow alarm pressure switch
D. Manual emergency station (normally closed and
secured)
E. Solenoid, wet pilot, or dry pilot release
F. Main drain (normally closed)
G. Alarm valve line (normally open)
H. Air compressor
I. Hydraulic alarm bell
J. Valve trim (drains and test lines etc...)
K. Pressure gauges
Installation Control Valve Table
Building Reference ICV Type Size (mm) Production Office Building 133, 142, 154 & 183 Wet 150
Production Office Building 133, 142, 154 & 183 Pre-Action 100
Sound Stage 131 & 132 Wet 200
Sound Stage 141 Wet 200
Sound Stage 151, 152 & 153 Wet 200
Sound Stage 161, 162 & 163 Wet 200
Sound Stage 171 & 172 Wet 200
Sound Stage 181 & 182 Wet 200
Visitor / Administration Building 110 Wet 150
Visitor / Administration Building 110 Pre-Action 100
Visitor / Administration Building 110 Deluge 100
Production Support Building 121 & 122 Wet 200
Multi-Storey Car Park – FDR Room Only Pre-Action 100
Notes:
• The installation control valve sizes are assumed based on the information
provided as part of the enquiry documentation. The actual sizes will be
confirmed following completion of the hydraulic calculations.
Drainage Requirement
Local drainage at each control valve location designed to cater for a flow of 300 litres
per minute is to be provided adjacent to the Sprinkler System valves By Others.
Zone Valve Arrangements
Within the following areas we propose to install zone valve arrangements: -
Building Reference No. of Zones Size (mm) Production Office Building 133 9 150
Production Office Building 142 9 150
Production Office Building 154 9 150
Production Office Building 183 12 150
Visitor / Administration Building 110 4 150
Notes:
• The zone valve sizes are assumed based on the information provided as part
of the enquiry documentation. The actual sizes will be confirmed following
completion of the hydraulic calculations.
Each of the zone valve arrangements will consist of a monitored stop valve,
Zonechecks and drain valves - totalling
43 zones across the site.
The zone valve arrangements will be
installed at each floor level within the
buildings above. The Production Office
Buildings have 3 No. zone valve
arrangements per floor; the Visitor /
Administration Building has 1 No. zone
valve arrangement per floor.
Electrical wiring of the monitored stop valves and the flow switches is by Aquamatic
Fire UK Limited – please refer to electrical section below.
Sprinkler Protection
High Hazard Sprinkler Protection
High hazard sprinkler protection is to be installed within the following buildings on the
Sky Studio’s new site: -
• Production Support Building 121
• Production Support Building 122
The sprinkler protection in these buildings is to be designed and installed to have a
design density of 18mm/min over an Assumed Maximum Area of Operation (AMAO)
of 260m2 on a property protection basis.
The specification for the sprinkler systems within these buildings noted that a design
density of 12.5mm/min is to be provided, but also stated that there would be
excessive storage clearance from the top of the storage solution to the sprinkler
protection at roof level.
Due to the excessive storage clearance, an allowance in the sprinkler systems design
density is required and must increase. In the case of these Production Support
Buildings, the new design density is calculated as follows: -
Original Design Density (A): 12.5mm/min
Excessive Storage Height: 4 metres
Initial Additional Density (B): 2.5mm/min for first excess
metre
Further Requirement per Metre of Height (C): 1mm/min multiplied by 3 (up
to a maximum of 18 metres)
New Design Density: (A)12.5 + (B)2.5 + (C)3 =
18mm/min
As part of the installation within both of these buildings we have included to install
new riser from the installation control valve set and supply mains around the building
for the future installation of racking.
Ordinary Hazard Group 4 Sprinkler Protection
Ordinary hazard group 4 sprinkler protection is to be installed within the following
buildings on the Sky Studio’s new site: -
• Sound Stages 131, 132, 141, 151, 152, 153, 161, 162, 163, 171, 172, 181 &
182
The sprinkler protection in these buildings is to be designed and installed to have a
design density of 5mm/min over an Assumed Maximum Area of Operation (AMAO)
of 360m2 on an enhanced property protection basis.
Ordinary Hazard Group 2 Sprinkler Protection
Ordinary hazard group 2 sprinkler protection is to be installed within the following
buildings on the Sky Studio’s new site: -
• Multi-Storey Car Park – FDR Area only
The sprinkler protection in these buildings is to be designed and installed to have a
design density of 5mm/min over an Assumed Maximum Area of Operation (AMAO)
of 144m2 on an enhanced property protection basis.
Ordinary Hazard Group 1 Sprinkler Protection
Ordinary hazard group 1 sprinkler protection is to be installed within the following
buildings on the Sky Studio’s new site: -
• Production Office Buildings 133, 142, 154 & 183
• Visitor / Administration Building
The sprinkler protection in these buildings is to be designed and installed to have a
design density of 5mm/min over an Assumed Maximum Area of Operation (AMAO)
of 72m2 on an enhanced property protection basis.
Sprinkler Heads
All sprinkler heads are to be LPC Approved, where possible, for use within the
occupancy of this project. Data sheets of the sprinkler heads are issued as part of
this technical submission for Client sign off prior to installation.
Sprinkler Head Details
Area of Use: Roof & Mezzanine
Manufacturer: Reliable
Model No.: GL112
Sprinkler Identification No.: R3226
Approvals: FM Global
Type of Sprinkler: Spray Upright
Finish: Brass
Temperature Rating: 74°C
K-Factor: K160
Response: Quick
Sprinkler Head Details
Area of Use: Ceilings
Manufacturer: Reliable
Model No.: G5
Sprinkler Identification No.: R3415
Approvals: FM Global, LPCB, VdS, CE
Type of Sprinkler: Spray Pendent
Finish: White (Cover Plate)
Temperature Rating: 68°C
K-Factor: K80
Response: Standard
Sprinkler Head Details
Area of Use: Ceiling Voids / Exposed
Manufacturer: Reliable
Model No.: F1FR56
Sprinkler Identification No.: RA1425
Approvals: cULus, FM Global, LPCB, VdS, CE, WM
Type of Sprinkler: Spray Upright / Conventional
Finish: Brass
Temperature Rating: 68°C
K-Factor: K80
Response: Quick Sprinkler Head Details
Area of Use: Roof, Gantry, & Walkways
Manufacturer: Reliable
Model No.: F1FR56
Sprinkler Identification No.: RA1425
Approvals: cULus, FM Global, LPCB, VdS, CE, WM
Type of Sprinkler: Spray Upright
Finish: Brass
Temperature Rating: 93°C
K-Factor: K80
Response: Quick
Sprinkler Tank and Pumphouse Electrics
Fire Pump Power Supply
The mains cable and connection to the mains supply and fire pumps are to be
supplied and installed By Others.
Details of the electrical requirements are to be issued following full design of
sprinkler pumphouse.
Distribution Board Power Supply
A distribution board is provided within the sprinkler pumphouse as part of the pre-
packaged solution. Power to the distribution board is to be supplied and installed By
Others.
Further details to be provided following full design of sprinkler pumphouse.
Tank Immersion Heater
We have included within our tender to provide a power supply from the sprinkler
pumphouse distribution board to the tank immersion heaters at the top of each
sprinkler water storage tanks.
The immersion heaters are supplied as part of the water storage tank build.
The cabling will be sized to suit power requirements for the immersion heaters and
will be installed within appropriate containment.
Sprinkler Pumphouse Wiring
Within our quotation we have included for the pumphouse wiring internally. This
includes the following: -
• Wiring from the electric and diesel pumps to the control panel
• Distribution Board within the Sprinkler Pumphouse
o Power to the pressure maintenance (jockey) pump
o Lighting
o Heating
o Power sockets
Fire Alarm / Signalling
Installation and Connections for Sprinkler Monitoring Panel
We propose to supply and install 1 No. new sprinkler monitoring panel within a
location to be confirmed.
The panel will be a conventionally wired LPC compliant panel with 200 zones.
Each zone will need to be wired in 2 cores from the device to the panel location and
terminated on the respective terminal By Others.
The conventional panel connections are to be in line with current LPC and BS5839
practice where a firing and end of line resistor will need to be fitted at every one of
the 200 zones.
Wiring diagrams will be provided.
Further to this we will undertake all fire and fault signal wiring from the pumphouse /
installation control valve set(s) and zone valves to local interfaces, supplied By
Others.
The signals are then to be taken back to the sprinkler monitoring panel By Others to
a junction box where we will then connect them.
The signals include: -
Sprinkler Tanks
• 2 No. Low Level Switches
Electric Pump
• Pump on Demand
• Pump Running
• Supply Status
Diesel Pump
• Pump on Demand
• Pump Running
• Supply Status
• Engine Failure
Pumphouse
• Open/Close - 2 No. Tank Infill Stop Valves
• Open/Close - 5 No. Suction Stop Valves
• Open/Close - 2 No. Delivery Stop Valves
• Low temperature in pumphouse
• Fire in pumphouse
• Trace heating monitoring
Installation Control Valve Sets
• Open/Close - 31 No. Main Stop Valves
• Open/Close - 48 No . Bypass Stop Valves
Zone Valve Arrangements
• 43 No. Flow Switches - Fire Signal
• 43 No. Stop Valves - Fault Signal
The power supply to the sprinkler indicator panel is to be provided By Others.
Zone Valve Arrangements Electrics & Signalling
We propose to install new fire and fault connections from the zone stop valve (fault)
and the Zonecheck (fire) to the fire alarm system via local interfaces. The local
interfaces are to be installed within 2 metres of the stop valve and the Zonecheck By
Others.
From the local interfaces, Aquamatic Fire UK Limited will connect the stop valve and
Zonecheck.
A fused spur power supply is to be installed within 2 metres of each of the
Zonecheck arrangements - 43 No. This is to be provided By Others.
Sprinkler Pipework
Pipework and Fittings
Steel tube will be medium quality black to
EN 10255.
Screwed fittings will be black malleable
iron to EN 10242.
Mechanical grooved joints will be Victaulic
or equivalent.
Finish with one coat of Red Oxide paint.
Sprinkler Pipework Brackets
Pipework Support
Steel pipework will be supported from the building structure with galvanized
threaded steel rod and galvanized steel pipe filbows. These will be spaced as per the
LPCB requirements. Pipe supports within this quotation will be taken directly from
the structure.
Pipework, fittings and supports will be LPC Approved and the relevant data sheets
for each will be issued as part of the technical submission.
It is assumed that the structure is capable of supporting any additional loads imposed
by the system. The dry and wet weights of the sprinkler pipework is shown in the
table below.
We have not currently included for the use of acoustic and anti-vibration brackets.
Pipework Weights Table
Pipework Weights (Medium Weight Steel)
Diameter
(mm)
Weight of Pipe
per Metre (KG)
Weight of Water Filled Pipe
per Metre (KG)
25 2.48 3.08
32 3.20 4.07
40 3.69 5.04
50 5.21 7.38
65 6.69 10.20
80 8.70 13.59
100 12.51 21.21
150 19.95 38.55