Annexure-1 (CC no. 77627)
TECHNICAL SPECIFICATIONS OF EXISTING LIGHTNING ARRESTORS
S. No. Description Parameter
1. Type Station class heavy duty zinc oxide gapless
2. Applicable standard IEC-60099-4 / IS:3070 part 3 (Latest)
3. Rated voltage of the arrester KV (rms) 216
4.1 Maximum continuous operating KV(rms) Voltage 184
4.2 Rated frequency 50
5. Discharge class III (Three)
6. Nominal discharge current at 8/20 microsecond wave. 10 KA
7. Front of wave protective level with microsecond steep wave at 10KA. KV (peak)
654
8. Max. switching surge protective level at 1000 Amps crest. KV
446
9. Power frequency withstand voltage of arrester insulation.
a) Dry 460
b) Wet 460
10. Impulse withstand voltage of arrester insulation.
Dry KV (peak) 1050
11. Residual voltage at KV (peak)
a) 0.5 P.U. of rated discharge current 485
b) 1.0 P.U. of rated discharge current 525
c) 2.0 P.U. of rated discharge current 600
12. Impulse current withstand
12.1 High current short duration test value KA 100
12.2 Low current long duration test value As per class-3
12.3 Virtual duration of rectangular wave 2400 microsecond
12.4 Long duration rating in amperes for 1000 and 2000 µs As per IEC-60099-4 / IS:3070 part 3
13.0 Discharge capability of the arrester KJ/KV 5KJ/KV (Minimum)
14.0 Temporary over voltage KV (peak) Withstand capability
0.1 Second 382
1.0 Second 366
10.0 Second 351
100.0 Second 336
Continues 260
15.0 Net weight of the arrester ( approx) Kgs < 350
16.0 Is the arrester designed to withstand 200 KMPH wind velocity when it is mounted on a 2500mm tall structure.
Yes
17.0 Wind velocity the lightning arrester can withstand without failure
300 KMPH (Approx.)
18. Cantilever strength of the complete arrester (min.) 350 Kg
19. Discharge counter and leakage current meter provided. Yes
20. Pressure relief device provided yes
21. Minimum Creepage distance of lightning arrester 6400 mm
22. Weather the lightning arrester assembly is designed to withstand applicable seismic load?
Yes
23. Mounting Base Bolts As Shown in drawing
24. Maximum radial distance over which pieces of lightning arrester scatter in the event of its damaged during discharge.
Falls within a distance of 1.3 mtrs. from arrester mounting
Annexure-II
COMPLIANCE FOR BIDDER
(Bidder shall mention specifications of quoted product in the table mentioned below):
Table-1
S. No. Description Bidders specification for quoted item
1. Type
2. Applicable standard
3. Rated voltage of the arrester KV (rms)
4.1 Maximum continuous operating KV(rms) Voltage
4.2 Rated frequency
5. Discharge class
6. Nominal discharge current at 8/20 microsecond wave.
7. Front of wave protective level with microsecond steep wave at 10KA. KV (peak)
8. Max. switching surge protective level at 1000 Amps crest. KV
9. Power frequency withstand voltage of arrester insulation.
a) Dry
b) Wet
10. Impulse withstand voltage of arrester insulation.
Dry KV (peak)
11. Residual voltage at KV (peak)
a) 0.5 P.U. of rated discharge current
b) 1.0 P.U. of rated discharge current
c) 2.0 P.U. of rated discharge current
12. Impulse current withstand
12.1 High current short duration test value KA
12.2 Low current long duration test value
12.3 Virtual duration of rectangular wave
12.4 Long duration rating in amperes for 1000 and 2000 micro seconds
13.0 Discharge capability of the arrester KJ/KV
14.0 Temporary over voltage KV (peak) Withstand capability
0.1 Second
1.0 Second
10.0 Second
100.0 Second
Continues
15.0 Net weight of the arrester ( approx) Kgs
16.0 Is the arrester designed to withstand 200 KMPH wind velocity when it is mounted on a 2500mm tall structure.
17.0 Wind velocity the lightning arrester can withstand without failure
18. Cantilever strength of the complete arrester (min.)
19. Discharge counter and leakage current meter provided.
20. Pressure relief device provided
21. Minimum Creepage distance of lightning arrester
S. No. Description Bidders specification for quoted item
22. Weather the lightning arrester assembly is designed to withstand applicable seismic load?
23. Mounting Base Bolts (To be provided by bidder). If Provided drawing of base is not matching with existing base, then bidder shall arrange the interconnection base, matching with existing foundation base.
24. Maximum radial distance over which pieces of lightning arrester scatter in the event of its damaged during discharge.
Other specifications to be complied by bidder: Bidder should mention details of Compliance of the points mentioned item sr. no. i) to vi) in the Table-2
mentioned below:
Table-2
S. No. Description of other specification Bidders compliance for specification
1 All routine/ Acceptance / Special Acceptance and Type tests will be carried out as per Latest version and amendments of IS /IEC, which are given at Sr. No. 3 of Tentative QA plan in Annexure-IX.
Note: The manufacturer should carry out type test or submit valid test report of type test for lightning arrester being offered for supply. The type test reports should be witness or test should be carried out at NABL accredited/ OEM test laboratory.
2 The offered equipment have to be designed, manufactured and tested as per relevant IS/IEC with latest amendments.
3 Three nos. copies of Instruction Manuals (for operation, maintenance, erection, shipping and storage) in Hindi / English language shall be supplied (Soft and Hard copy), one month prior to the dispatch of the equipment.
4 Has bidder uploaded his offered material`s Dimensional Drawing for Lightning Arrester & Insulating base?
5 Whether the offered drawing of the insulating base is matching with existing insulating base?
6 Has bidder uploaded his offered material`s Dimensional Drawing for Grading Ring?
7 Has bidder uploaded his offered material`s Dimensional Drawing for Terminal connectors?
8 Has bidder uploaded his offered material`s Dimensional Drawing for Surge Monitor cum operation counter & leakage meter?
9 Has bidder uploaded his offered material`s Dimensional Drawing for Name plate details?
10 Has bidder uploaded his offered material`s Dimensional Drawing for Cut way section?
11 Has bidder uploaded his offered material`s Dimensional Drawing for Voltage Time curve?
12 Tentative QA plan is attached in Annexure-IX. However bidder will submit detailed QA plan for approval after PO placement and before manufacturing.
Annexure-IX
Quality assurance programme Zinc oxide surge arresters, insulating base and surge monitors
S. No. Component and operation
Characteristics Classification Types of check
Quantum of check
Reference Documents
Format of record
Agency Action by NPC
1. Raw materials
1.01 Zinc oxide and other additives
1. Purity check Major Chemical On sample basis (3) samples from lot / ton
PS Test Report
OEM R*
2. Moisture check
Major Chemical
3. Grain size analysis
Critical Physical
1.02 Aluminum Alloy Chemical analysis
Critical Chemical On sample basis (1) samples for two tonnes
IS Test report
OEM R
1.03 Copper, Brass, M.S. Stainless steel sheets
1. Visual 2. Thickness 3. Formability
Major Major Major
Visual Measurement Mechanical
On sample basis (1) for every batch of tonne
IS TR OEM R
1.04 Aluminum Castings for arrester base and monitor
1. Dimension 2. Visual 3. Mechanical
test
Major Critical Critical
Measurement Visual Mechanical
100% 100% On sample basis( one for every 100 nos.)
PS TR OEM R
1.05 Cover plate (fabricated hot dip galvanizing)
1. Visual 2. Dimension 3. Galvanizing 4. Weight of
coating 5. Dip test
Major Major Major
Visual Measurement
100% 100% On sample basis( one for every 100 nos.)
IS-2633 and as per Drawing
TR OEM R
1.06 Gasket 1. Dimension 2. Hardness
Major Major
Measurement Chemical Test
10% On sample
As per PS and Drg.
TR OEM R
3. Ageing Test Critical in Lab basis( one for every 100 nos.)
1.07 Capacitor used in Surge Monitor
1. Capacitance Measurement
2. Dielectric Test
Critical Critical
Electrical Electrical
100% On sample basis( one for every 100 nos.)
PS TR -do-
OEM R
1.08 Ammeter used in Surge Monitor
1. Meter Calibration
2. Surge Test
Major Critical
Electrical Electrical
100% On sample basis( one for every 100 nos.)
-do- -do-
-do- -do-
OEM R
1.09 End Terminal Connectors
1. Visual 2. Dimension 3. Chemical
Composition 4. Mechanical
test on connectors
Major -do- -do- -do-
Physical Chemical Chemical Mechanical
Routine 10% On sample basis -do-
---- Customer appd. Drawing as per IS
TR -do- -do- -do-
OEM R
1.10 Procelain Housing
1. Visual 2. Diemension 3. Electrical
withstand test
4. Porosity Test 5. Temp Cycle
Test
Critical Major -do- -do- -do-
Visual Measurement Electrical Mechanical -do-
100% 10% 100% On sample -do-
IS-3070 Appd. Drag. IS-5621 IS-3070 -do-
TR do- -do- -do- -do-
OEM
S. No. Component and operation
Characteristics Classification Types of check
Quantum of check
Reference Documents
Format of record
Agency Action by NPC
2. In process Inspection
2.01 Block 1. Dimension 2. Visual 3. 1mA DC check 4. Residual
Voltage Test 5. Energy Test 6. Long duration 7. Accelerated
Ageing Test
Major -do- Critical -do- -do- -do- -do-
Measurement Visual Electrical -do- -do- -do- -do-
10% 100% One from each lot -do- -do- -do-
PS 04 do- -do- -do- -do-
TR -do- TR -do- -do- -do-
OEM R
2.02 End fitting assembly with porcelain
1. Dimension 2. Visual
Major -do-
Mechanical Visual
5% Routine
As per Drag. -do-
TR OEM R
2.03 Leak Test, Evacuation sealing
1. Sealing Effectiveness
Critical Mechanical -do- PS TR OEM R
S. No. Component and operation
Characteristics Classification Types of check
Quantum of check
Reference Documents
Format of record
Agency Action by NPC
3 Final Inspection
3.01 Lighting Arresters
1 Routine Test 1. Measurement of Reference Voltage
2. RIV Test 3. Residual Voltage
Test 4. Leak Test
Critical -do- -do- -do-
Electrical -do- -do- -do-
Routine -do- -do- -do-
As per IEC Latest do- -do- -do-
TR -do- -do- -do-
OEM R
2 Acceptance Test
1. Measurement of power frequency reference voltage in arrester units
2. Lighting impulse residual voltage test on arrester units
3. RIV Test on Units 4. Galvanizing Test 5. Dimension
-do- -do- -do- Major -do-
Electrical -do- -do- Mechanical Measurement
Nearest higher whole no. to the cube Root of LAs LAs Supplied -do- One No. 3 Nos.
As per IEC -do- -do-
Test Report
OEM HP#
2A Special acceptance test
1. Thermal Stability Test on Sections
Critical Electrical Same as 3.01.2.1 above
As per IEC spec.
-do- OEM -do-
3 Type Test 1. Dry & Wet insulation withstand test
Major Electrical As per IEC As per IEC TR OEM HP
2. Residual Voltage Test
-do- -do- -do- -do- -do- OEM HP
3. Current Impulse withstand tests
-do- -do- -do- -do- -do- OEM HP
4. Operating Duty Test
-do- -do- -do- -do- -do- OEM HP
5. Mechanical Tests on Insulators
-do- -do- -do- -do- -do- OEM HP
6. Porosity Tests on Insulators
-do- -do- -do- -do- -do- OEM R
7. Production of original Type Tests Certificates for Pressure Relief Test
-do- -do- -do- -do- -do- OEM R
8. Visual Corona Discharge Test
-do- -do- -do- -do- -do- OEM R
9. Long Duration Current Test on Surge Monitor
-do- -do- -do- -do- -do- OEM R
3.02 Surge Monitor 1. Routine and acceptance tests
1. Meter calibration
Major Electrical Routine
PS 04
TR OEM R/HP
2. Counter Verification
-do- -do- -do- -do- -do- OEM
3.03 Insulating Base 1. Voltage Withstand Test
-do- -do- -do- OEM R
2. Visual -do- Visual 100% -do- -do- OEM
3. Wet Power Voltage Withstand Test
-do- Electrical One per 100 Nos.
-do- -do- OEM
(*)R - Review of test certificates by bidder and record verification by NPC
(#)HP-Hold point tests to be conducted in presence of NPC & clearance shall be obtained before further proceeding.