174
1 Technical Specifications

Technical Specifications - mopw.gov.afmopw.gov.af/Content/files/Technical_Specification_ (2)(1).pdf · REINFORCEMENT STEEL ... Grouted Stone Pitching ... The details contained in

  • Upload
    ngokien

  • View
    217

  • Download
    2

Embed Size (px)

Citation preview

1

Technical Specifications

2

TABLE OF CONTENTS

SCOPE OF WORKS ............................................................................................................................. 12

A 101. Introduction .............................................................................................................................. 13

A 102. Limits of Site ............................................................................................................................ 13

A 103. Kilometre Referencing System ................................................................................................ 13

A 104. Scope of Works ....................................................................................................................... 13

SECTION 4B: DESIGN SPECIFICATION ........................................................................................... 14

B 101. Introduction .............................................................................................................................. 15

PART 1: GENERAL DESIGN OBLIGATIONS .................................................................................... 16

B 102. Design Responsibility .............................................................................................................. 16

B 103. Contractor´s Documents.......................................................................................................... 16

B 104. Technical Standards and Regulations ..................................................................................... 17

PART 2: SURVEYS AND INVESTIGATIONS ..................................................................................... 18

B 105. Topographical Surveys ............................................................................................................ 18

B 106. Axle Load Survey .................................................................................................................... 23

B 107. Bridge Foundation Ground Investigation ................................................................................. 23

PART 3: DESIGN ................................................................................................................................. 25

B 108. Highway Design ....................................................................................................................... 25

B 109. Pavement Road Design............................................................. Error! Bookmark not defined.

B 110. Drainage Design ...................................................................................................................... 27

B 111. Design of Protection Works ..................................................................................................... 28

B 112. Bridge Design .......................................................................................................................... 31

B 113. Retaining Wall Design ............................................................................................................. 33

B 114. Road Furniture Design ............................................................................................................ 33

B 115. Road Marking Design .............................................................................................................. 34

SECTION 4C : CONSTRUCTION SPECIFICATION .......................................................................... 36

SECTION C 100: PRELIMINARIES ..................................................................................................... 37

PART 1 .................................................................................................................................................. 39

Health and Safety ................................................................................................................................. 39

3

Protection of the Environment: General ............................................................................................... 40

Protection of the Environment: Particular Requirements ..................................................................... 41

Programme Error! Bookmark not defined.

Methods of Construction: Method Statements ..................................................................................... 43

Setting Out 44

Quality Control and Quality Assurance ................................................................................................ 44

Approval of Suppliers ........................................................................................................................... 44

Materials: Alternative Standards .......................................................................................................... 45

Temporary Works ................................................................................................................................. 45

Traffic Safety and Control ..................................................................................................................... 45

Temporary Road Diversions ................................................................................................................. 46

Existing Services and Service Diversions ............................................................................................ 46

Restriction on Working Hours ............................................................................................................... 47

Landmines and Unexploded Ordinance ............................................................................................... 47

Graves and Burial Sites ........................................................................................................................ 47

Local Liaison and Consultation ............................................................................................................ 47

‘As Built’ Drawings ................................................................................................................................ 48

PART 2: FACILITIES AND SERVICES FOR THE ENGINEER AND EMPLOYER ............................. 49

Facilities and Services to be Provided ................................................... Error! Bookmark not defined.

Project/ Site Offices ................................................................................ Error! Bookmark not defined.

Office Accommodation ........................................................................... Error! Bookmark not defined.

Office Equipment .................................................................................... Error! Bookmark not defined.

Office Consumables ............................................................................... Error! Bookmark not defined.

Survey Equipment ................................................................................................................................ 50

Site Cabins Error! Bookmark not defined.

Residential Accommodation ................................................................... Error! Bookmark not defined.

Overnight Site Accommodation .............................................................. Error! Bookmark not defined.

Newly Purchased Vehicles ................................................................................................................... 50

Radio Communication Facilities ............................................................. Error! Bookmark not defined.

Insurance and Ownership....................................................................... Error! Bookmark not defined.

4

Maintenance and Security .................................................................................................................... 52

Office Consumables and Telephone Charges ....................................... Error! Bookmark not defined.

Progress Photographs ............................................................................ Error! Bookmark not defined.

Works Signboards .................................................................................. Error! Bookmark not defined.

Measurement and Payment ................................................................... Error! Bookmark not defined.

SECTION C 200: QUALITY CONTROL ............................................................................................... 53

Scope of Section .................................................................................................................................. 53

Quality Control Plan .............................................................................................................................. 54

General Requirements in Respect of Testing ...................................................................................... 54

PART 1: LABORATORY / FIELD TESTS AND PROCEDURES ......................................................... 55

SOILS, GRAVELS AND AGGREGATES ............................................................................................. 55

Sampling and Preparation of Samples ................................................................................................. 55

Standard Methods of Testing ............................................................................................................... 55

Cement or Lime Treated Materials ....................................................................................................... 56

Stone, Aggregates, Sand and Filler ..................................................................................................... 56

Average Least Dimension .................................................................................................................... 57

The Quantab Test ................................................................................................................................. 58

PORTLAND CEMENTS AND CONCRETES ....................................................................................... 59

Portland Cement ................................................................................................................................... 59

Concrete 59

BITUMINOUS MATERIALS .................................................................................................................. 59

Bituminous Binders ............................................................................................................................... 59

Cut-back Bitumen ................................................................................................................................. 61

AASHTO T201 ...................................................................................................................................... 61

Bituminous Mixes ................................................................................................................................. 61

Loss of Stability: Alternative Test ......................................................................................................... 62

REINFORCEMENT STEEL................................................................................................................... 62

Reinforcing Steel .................................................................................................................................. 62

Prestressing Steel ................................................................................................................................ 62

PART 2: CONSTRUCTION CONTROL TESTING AND QUALITY ASSURANCE ............................. 63

5

Construction Control ............................................................................................................................. 63

Frequency of Testing ............................................................................................................................ 63

Earthworks 63

Pavement Materials .............................................................................................................................. 63

Concrete Works 65

Quality Control of Concrete Production ................................................................................................ 66

Records of Concrete Placing ................................................................................................................ 69

Testing Requirements (Reinforcement) ............................................................................................... 70

Abbreviations 71

SECTION C 300: SETTING OUT AND TOLERANCES ....................................................................... 72

PART 1: PAVEMENT CONSTRUCTION ............................................................................................. 73

Horizontal Alignment ............................................................................................................................ 73

Thickness of Pavement Layers ............................................................................................................ 73

Surface Layers 73

Surface Regularity ................................................................................................................................ 73

Rectification 73

PART 2: CONCRETE STRUCTURES .................................................................................................. 75

Concrete Structures .............................................................................................................................. 75

SECTION C 400: SITE CLEARANCE .................................................................................................. 76

Site Clearance 77

Demolition of Bridges and Culverts ...................................................................................................... 78

Replacement of Bearings by Jacking ................................................................................................... 80

Removal of Road Furniture .................................................................................................................. 80

Removal of Culvert End Structures ...................................................................................................... 80

Removal of Abandoned Military Tanks, Military Vehicles and other Vehicles ..................................... 80

Measurement and Payment ................................................................................................................. 81

SECTION C 500: EARTHWORKS ....................................................................................................... 82

Scope of Section .................................................................................................................................. 83

Classification of Materials ..................................................................................................................... 83

Excavation of Topsoil ........................................................................................................................... 84

6

Preparation Prior to Deposition of Fill ................................................................................................... 84

Construction of Embankments ............................................................................................................. 85

Capping Layer 85

Widening of Existing Embankments ..................................................................................................... 85

Compaction of Earthworks ................................................................................................................... 86

Sub-formation 86

Geotextile Membrane ........................................................................................................................... 86

Structural Excavation ............................................................................................................................ 86

Structural Backfill .................................................................................................................................. 87

Benching 87

Preparation of Formation ...................................................................................................................... 87

Trimming of Embankment Slopes ........................................................................................................ 88

Trimming of Existing Cut Slopes .......................................................................................................... 88

Resoiling 88

Watercourses and Side Drains ............................................................................................................. 88

Scarification of Existing Pavement ....................................................................................................... 88

Reinstatement of Batter Slopes ............................................................................................................ 89

Measurement and Payment ................................................................................................................. 89

SECTION C 600: CULVERTS, DRAINAGE AND PROTECTION WORKS ........................................ 90

Scope of Section .................................................................................................................................. 91

General 91

Classification of Excavated Materials ................................................................................................... 91

Excavation for Culverts and Drainage Structures ................................................................................ 91

Structural Elements Cast Against Excavated Surfaces ....................................................................... 92

Backfilling for Culverts and Drainage Structures .................................................................................. 92

Bedding and Laying of Culverts ........................................................................................................... 92

Jointing 92

Waterproofing 92

Inlet and Outlet Structures .................................................................................................................... 93

Guiding Dams and Scour Checks ........................................................................................................ 93

7

River Training and New Watercourses ................................................................................................. 93

Riprap 93

Grouted Stone Pitching ........................................................................................................................ 94

Carriageway Drainage Outlets ............................................................................................................. 94

Measurement and Payment ................................................................................................................. 95

SECTION C 700: GRANULAR PAVEMENT MATERIALS .................................................................. 96

(SUB-BASE, SHOULDERS AND CRUSHED STONE BASE) ............................................................ 96

Material Requirements ......................................................................................................................... 97

Field Trials 97

Subbase 98

Cement Stabilized Subbase ................................................................................................................. 98

Crushed Stone Base ............................................................................................................................ 98

Shoulders 100

Deposition and Compaction ............................................................................................................... 101

Measurement and Payment ............................................................................................................... 101

SECTION C 800: BITUMINOUS PAVEMENT WORKS ..................................................................... 102

Scope of Section ................................................................................................................................ 103

PART A: MATERIALS FOR ASPHALTIC CONCRETES .................................................................. 104

Bitumen 104

Aggregates for Asphaltic Concrete ..................................................................................................... 104

Adhesion Agents ................................................................................................................................ 105

PART B: ASPHALTIC CONCRETE MIX DESIGN ............................................................................. 106

Mix Design Procedure ........................................................................................................................ 106

Refusal Density Design ...................................................................................................................... 107

Grading Requirements ....................................................................................................................... 107

Physical Properties ............................................................................................................................. 108

Full Scale Production Trials ................................................................................................................ 108

Field Trials 108

PART C: ASPHALTIC CONCRETE PRODUCTION .......................................................................... 110

Storage of Bitumen ............................................................................................................................. 110

8

Mixing 110

Preparation of Surfaces ...................................................................................................................... 111

Transportation and Deposition ........................................................................................................... 111

Field Density Requirements ............................................................................................................... 112

Joints 112

PART D: OTHER BITUMINOUS MATERIALS .................................................................................. 113

Double Layer Surface Dressing ......................................................................................................... 113

Cut-back Bitumen ............................................................................................................................... 118

Bitumen Emulsion ............................................................................................................................... 118

Prime Coat 118

Tack Coat 120

Application of Prime Coat and Tack Coat .......................................................................................... 120

PART E: PAVEMENT REPAIRS ....................................................................................................... 121

Patching 121

Crack Sealing 122

Regulating 123

Measurement and Payment ............................................................................................................... 123

SECTION C 900: CONCRETE WORKS ............................................................................................. 124

Scope of Section ................................................................................................................................ 125

Definitions 125

AASHTO Standards ........................................................................................................................... 125

PART A: MATERIALS FOR CONCRETE .......................................................................................... 126

Cement 126

Fine Aggregate 126

Coarse Aggregate .............................................................................................................................. 127

Water 128

Admixtures 128

Pozzolanic and Fly Ash admixtures ................................................................................................... 128

Reinforcement 129

PART B: DESIGN OF CONCRETE MIXES ........................................................................................ 130

9

Classes of Concrete ........................................................................................................................... 130

Design of Concrete Mixes .................................................................................................................. 130

PART C: MANUFACTURE AND PLACING ....................................................................................... 133

Mixing 133

Transportation of Concrete ................................................................................................................. 133

Placing of Concrete ............................................................................................................................ 133

Protection of Concrete from the Environment .................................................................................... 134

Compaction of Concrete ..................................................................................................................... 135

Curing of Concrete ............................................................................................................................. 135

Construction Joints ............................................................................................................................. 136

Finishes on Unformed Surfaces ......................................................................................................... 137

Finishes on Formed Surfaces............................................................................................................. 137

PART D: FORMWORK and FALSEWORK ....................................................................................... 139

General Obligations ............................................................................................................................ 139

Falsework 139

Formwork 139

Removal of Formwork ........................................................................................................................ 140

PART E: REINFORCEMENT .............................................................................................................. 141

Bar Bending Schedules ...................................................................................................................... 141

Fixing 141

Splicing 141

Substitution by Bars of Different Sizes ............................................................................................... 142

Cover 142

PART F: PILING ................................................................................................................................. 143

General 143

Pile Tests 143

PART G: MISCELLANEOUS.............................................................................................................. 145

Mortar and Grout ................................................................................................................................ 145

Grouting of Pockets and Holes ........................................................................................................... 145

Underpinning of Baseplates ............................................................................................................... 145

10

Precast Concrete ................................................................................................................................ 146

Placing Concrete under Water ........................................................................................................... 146

Sulphate Resisting Concrete .............................................................................................................. 146

Interruptions to Placing ....................................................................................................................... 147

Remedial Work to Defective Concrete ............................................................................................... 147

Waterproofing Buried Concrete Surfaces ........................................................................................... 147

Waterstops 148

Measurement and Payment ............................................................................................................... 148

SECTION C 1000: PRESTRESSED PRE-TENSIONED CONCRETE ............................................... 149

General 150

Submission of Working Drawings ....................................................................................................... 150

Prestressing Wire and Strand ............................................................................................................ 150

Testing 151

Prestressing Operations ..................................................................................................................... 151

SECTION C 1100: CONCRETE REPAIRS ........................................................................................ 153

General 154

Scope of Repair Works ....................................................................................................................... 154

Surface Cleaning ................................................................................................................................ 154

Removal of Existing Concrete ............................................................................................................ 155

Reinforcement 155

Replacement Concrete ....................................................................................................................... 156

Repair Concrete to Beam Soffits ........................................................................................................ 156

Polymer Modified Mortar .................................................................................................................... 157

Impregnation 157

Epoxy Mortar 158

Replacing Handrails ........................................................................................................................... 159

Footpath Repairs ................................................................................................................................ 160

SECTION C 1200: MISCELLANEOUS BRIDGE WORKS ................................................................ 162

Bridge Bearings: General ................................................................................................................... 163

Elastomeric Bearings .......................................................................................................................... 163

11

Hot Poured Elastic Type Expansion Joints ........................................................................................ 164

Strip Type Expansion Joints ............................................................................................................... 165

Filler-Type Expansion Joints .............................................................................................................. 165

Bridge Deck Waterproofing ................................................................................................................ 166

Paint for Structural Steelwork ............................................................................................................. 166

Galvanised Coatings .......................................................................................................................... 166

SECTION C 1300: ROAD FURNITURE ............................................................................................. 167

General 168

Retroreflective Material for Permanent Road Signs ........................................................................... 168

Permanent Road Signs ...................................................................................................................... 169

Guardrail 169

Kerb and Drainage Offlets .................................................................................................................. 170

Measurement and Payment ............................................................................................................... 172

General 172

Equipment 172

Application of Road Markings ............................................................................................................. 173

Retroreflective Studs .......................................................................................................................... 173

Tolerances for Thermoplastic Road Markings.................................................................................... 174

Measurement and Payment ............................................................................................................... 174

12

Section A: SCOPE OF WORKS

13

A 101. Introduction

This section of the Technical Specifications defines the scope of the Works to be designed

and constructed under the Contract. The details contained in this section shall be read in

conjunction with Drawings included in this section.

Specifications for the design of the Works are contained in the following Section 4B.

Specifications for the construction of the Works are contained in the following Section 4C.

A 102. Limits of Site

The roads that comprise the Site of the Permanent Works to be designed and

constructed are NASAJI GULBAHAR TO SANJAN ( Koh Band district,

Kpisa province) 7+530 KM Road

A 103. Kilometre Referencing System

The kilometer referencing system described above is based on preliminary surveys. All

kilometer reference points and road lengths given in Bidding Document are not to be

considered as precise and they may be amended by the Contractor after completing the

detailed topographical survey that forms part of the design works.

A 104. Scope of Works

The scope of works to be designed and constructed under the Contract shall include the

following:

(i) NASAJI GULBAHAR TO SANJAN ( Koh Band district, Kpisa

province) 7+530 KM Road

which shall include:

(a) Preliminaries;

(b) Earthworks

(c) Culverts and Drainage Works;

(d) Pavement Works and

(e) Road furniture and markings

A 105 Mobilization at site is for the cost of establishing security, plant, equipment, facilities and

personnel upon the site. Provision and installation of two (2) sub-project sign boards as directed by the

Engineer.

A106 Demobilization from site shall be compensation in full for the costs of removing plant,

equipment, facilities, personnel, and restoration of site.

14

Section B: DESIGN SPECIFICATION

15

B 101. Introduction

The Design Specification defines the Contractor’s general design obligations, and other

specific requirements related to surveys, investigations and design.

Part 1 of the Design Specification details the Contractor’s general design obligations.

Part 2 of the Design Specification details specific requirements in respect of surveys and

investigations that are to be carried out by the Contractor.

Part 3 of the Design Specification details design criteria and specific requirements in respect

of design that is to be carried out by the Contractor.

16

PART 1: GENERAL DESIGN OBLIGATIONS

B 102. Design Responsibility

The Contractor shall carry out and be responsible for the design of the Works which shall be

carried out in accordance with the Design Specification and all other requirements of this

Contract.

On completion of the design, the Contractor shall provide a certificate to the Engineer

confirming that it has exercised due care in the preparation of the design.

The surveys and investigations to be carried out by the Contractor as detailed in Part 2 of the

Design specification are deemed to be part of the design of the Works.

Design shall be carried out by qualified designers who are professional engineers. For each

part of the Works, the prior consent of the Engineer shall be obtained to the designer and

design Subcontractor, if they are not named as such in the Contract. Nothing contained in the

Contract shall create any contractual relationship or professional obligations between any

designer, and design Subcontractor, and the Employer.

The Contractor holds itself, its designers and design Subcontractors as having the experience

and capability necessary for the design. The Contractor undertakes that the designers shall be

available to attend discussions with the Engineer at all reasonable times during the period of

the Contract.

B 103. Contractor’s Documents

The Construction Documents shall comprise of all design (including survey and investigation)

drawings, calculations, models, reports, and other manuals and information of a similar nature

that the Contractor shall prepare and submit to the Engineer as part of its design obligations.

The Contractor shall prepare the Construction Documents in sufficient detail to demonstrate

that it has complied with the requirements of the Contract, to satisfy all regulatory approvals,

to provide sufficient instruction to execute the Works. The Engineer shall have the right to

review and inspect the preparation of the Construction Documents, wherever they are being

prepared.

Each of the Construction Documents shall, when considered ready fore use, be submitted to

the Engineer for pre-construction review and for the Engineer’s consent. Each submission of

a Construction Document made by the Contractor in an agreed format and shall be

accompanied by notice that the Contractor considers the Construction Document ready for a

pre-construction review and for use. The Engineer shall have a review period of 28 days,

calculated from the date on which the Engineer receives a Construction Document to carry

out the pre-construction review and grant its consent. If the Engineer, within this review

period, notifies the Contractor that such Construction Document is incomplete or fails (to the

extent stated) to comply with the Technical Specifications, it shall be rectified, resubmitted

and reviewed in accordance with this Clause at the Contractor’s cost.

17

For each part of the Works, and except to the extent that the prior consent of the Engineer

shall have been obtained:

(i) Construction shall not commence prior to the expiry of the review periods for the

Construction Documents which are relevant to the design and construction such part;

(ii) Construction shall be in accordance with such Construction Document; and

(iii) If its is necessary, the contractor could modify any design or document which has

previously been submitted for such pre-construction review, the Contractor shall

immediately notify the Engineer, and shall subsequently submit revised Documents to

the Engineer for pre-construction review and consent. Once the contractor’s

documents are approved it is not intended that they should be modified for the

convenience of the contractor. Modifications will be considered if: deemed necessary

by the engineer; if required by changed conditions or conditions not contemplated by

the initial contractor design; if required by updated codes and/or standards; or if the

original design proves to have significant constructability problems

If the Engineer instructs that further Construction Documents are necessary for carrying out

the Works, the Contractor shall upon receiving the Engineer’s instructions prepare such

Construction Documents.

If errors, omissions, ambiguities, inconsistencies and other defects are found in the

Construction Documents, they and the Works shall be rectified by the Contractor at its cost.

B 104. Technical Standards and Regulations

The design and the Construction Documents shall comply with the Country’s national

specifications, technical standards, building, construction and environmental regulations and

the standards quoted in the Technical Specifications. References in the Contract to such

specifications or standards shall be understood to be references to the edition applicable on

the Contract Commencement Date. If substantially changed or new applicable national

specifications, technical standards or regulations come into force after the Contract

Commencement Date, The Contractor shall submit proposals for compliance to the Engineer.

In the event that the Engineer determines such proposals to be a variation, the Engineer shall

then initiate a Variation in accordance with Clauses 13 of the Conditions of Contract.

18

PART 2: SURVEYS AND INVESTIGATIONS

B 105. Topographical Surveys

General

The Contractor shall carry out the following topographical surveys:

(i) Topographical survey and level survey along all the alignments that have been

projected between the project sites and shall be plotted out on 1 to 2,000 scale

drawings;

(ii) Cross section survey of the road section

(iii) Topographical survey of the site of the new bridges, which shall be plotted out on 1 to

200 scale drawing(s).

Existing Survey Control Data

Translations of bench mark record sheets have been obtained from the Department of

Cartography and Geodesy in the areas adjacent to the Contract roads.

No recent inspection has been made to ascertain whether or not all the bench marks are still in

existence, and no check has been made on the national datum levels quoted on the bench

mark record sheets.

The Department of Cartography and Geodesy have no primary trigonometric points close to

the Works and the Contractor shall adopt a local grid system.

Primary Survey Control

Prior to the commencement of the topographic and level surveys, primary control monuments

shall be established along the full length of the section at nominal 5 km spacing. A primary

control survey shall then be carried out to determine X and Y co-ordinates of the primary

control monuments by traversing or by a GPS survey. The elevations of the primary control

monuments shall also be determined with reference to the existing National Datum and they

shall be tied into the existing National Datum benchmarks.

The primary control monuments shall be as follows:

(i) Monument centre shall be a stainless steel pin of 12 mm diameter.

(ii) Body of monument shall be concrete with 20Mpa strength, constructed to the

following dimensions: .

- Monument top surface: 40cm x 40cm

- Monument bottom: 50cm x 50cm

- Monument height: 50cm

- Monument base: 60cm x 60cm x 10cm

19

Monuments shall be established at ground level in stable ground conditions in location where

they shall not be disturbed by the construction works and they shall be maintained throughout

the Contract Period. Sufficient space shall be provided around each monument to enable

survey instruments to be erected and operated.

Each monument shall be marked with its reference number, date of construction, elevation

and co-ordinates. A Survey Monument Description Sheet for each primary control

monuments shall be prepared to the format of the form shown in Appendix B2 and these

sheets shall form part of the Contractor’s Construction Documents.

The traverse survey connecting the primary control monuments shall be carried out using

theodolites, electronic distance meters (EDMs) or total station instruments. The elevation of

each monument shall also be recorded with reference to the Afghanistan National Datum.

Requirements for the traverse survey shall be as follows:

(i) horizontal angle measurement

(a) Horizontal angles shall be observed by 2 rounds of angle on 2 different zero

settings;

(b) a total station or theodolite instrument capable of reading horizontal and

vertical angles to at least 10 seconds shall be used;.

(ii) Distance measurement

an Electronic Distance Meter (EDM) shall be used for distance measuring, which shall

be accurate to at least 10mm + 5ppm x D;

Note: 5ppm: 5cm per 17.427.44km, D: measured distance)

(iii) accuracy of primary traverse

Linear miss-closure of the primary traverse shall be better than 1/10,000.

Requirements for a GPS (Global Positioning System) survey shall be as follows:

(i) GPS observation and measurement

(a) More than three GPS instruments shall be used which shall be capable of

reading to a horizontal and vertical accuracy of at least +5 ppm x distance

between primary control monuments (e.g. 5cm per 10km);

(b) Elevation mask shall be 15 degrees;

(c) Observations shall be made simultaneously at 3 points;

(d) Signals from more than 3 satellites shall be received at each point

simultaneously;

(e) Observations shall be made for more than 1 hour;

20

(f) Maximum measured distance between observation points shall be 10 km;

(ii) Expected accuracy of GPS traverse

Mis-closure of GPS traverse shall be not more than 5ppm x measured distance.

Secondary Survey Control

The Contractor shall establish the secondary control points to provide a suitable basis for the

topographical and level survey of the roads and bridge site. The secondary control survey

shall then be carried out to determine X and Y co-ordinates of secondary control points by

traversing. The elevations of the secondary control points shall also be determined with

reference to the existing National Datum and they shall be tied into the existing National

Datum benchmarks via primary control monuments.

The secondary control points shall be spaced at maximum intervals of 500m and located so

that a minimum of two adjacent points are inter-visible. The secondary control points shall be

located to fully enclose the required area of topographic survey for the roads (scale: 1/2000),

and shall be at a sufficient distance from the proposed works so as not to be disturbed during

the construction. The location of points shall also be suitable for use in setting out.

The secondary control points shall be established at ground level in stable ground conditions

with the requirement that they remain stable during construction. Each point (monument)

shall be as follows:

(i) Control point centre shall be a stainless steel pin of 12mm diameter;

(ii) Body of control point shall be concrete with 20Mpa strength, constructed to the

following dimensions:

- point top surface: 20cm x 20cm

- point bottom: 30cm x 30cm

- point height: 40cm

Each secondary control point shall be marked with its reference number and date of

construction. A Survey Monument Description Sheet for each secondary control point shall

be prepared to the format of the form shown in Appendix B2 and these sheets shall form part

of the Contractor’s Construction Documents.

The requirements for horizontal angle measurement and distance measurement in the

secondary control point traverse survey shall be the same as those specified above for primary

control survey.

Linear miss-closure of secondary traverse shall be less than 1/8,000.

Leveling

Leveling shall be started from an existing National Datum benchmark, a primary control

monument or a secondary control point and closed to another of these benchmarks,

monuments or points.

21

Requirements for the leveling survey shall be as follows:

(i) An automatic level or digital level shall be used;

(ii) miss-closure of leveling between existing National Datum benchmarks and primary

control monuments shall not exceed + 30 mm √D, where D is distance in kilometers

between existing National Datum benchmarks or Primary Control Monuments.

Topographical Survey of Roads (1 / 2,000)

A plan topographic survey shall be conducted to locate man-made features such as roads,

buildings, etc to prepare plans to a scale of 1 to 2000. and natural features such as creek,

canals, etc along the road section using the plan co-ordinates and heights of the primary

control monuments and secondary control points,. The minimum required features and details

to be surveyed are listed in Appendix B3. All features shall have elevations based on the

National Datum benchmarks.

The extent of the 1/2000 plan map survey shall be at least 30m either side of the existing road

highway centerline, and this survey corridor shall be extended as required to ensure that the

full extent of the existing road construction is covered.

Where features cannot be surveyed to the required accuracy without extensive clearing or due

to other obstructions, the Contractor will seek the instruction of the Engineer.

The line or point to be surveyed on a feature shall be at the features intersection with the

ground-surface unless otherwise instructed by the Engineer.

Any feature, which is in a state of change during the survey, will be annotated to this effect,

with the proposed boundary changes marked, if known.

The ground surface shall be surveyed to truly indicate any change in feature, vertical

alignment or horizontal alignment.

Appropriate references such as road section name, section limits (km-marks), north and east

co-ordinates, benchmarks and other important data shall be shown in the topographic plans

and profiles.

The requirements for the survey shall be as follows:

(i) an automatic-level, total station, EDM, theodolite, and surveying tape shall be used;

(ii) traversing points for the topographic survey shall be set up by closed traverse from the

control points;

(iii) the height of traversing points shall be obtained by closed leveling from control

points;

(iv) spot height point shall be measured and distributed uniformly 2 cm x 2 cm for the

1/2,000 scale mapping area;

22

(v) accuracy of closed traverse:

linear mis-closure of closed traverse between control points shall be better than

1/5,000;

(vi) accuracy of closed leveling:

mis-closure of closed leveling between control points and traversing points shall be

within + 30 mm √K;

(vii) accuracy of radiation traverse and cross section survey:

positioning error and height error of spot height point shall be within + 5 cm from

traversing points;

(viii) minor control points established for the mapping survey shall not be permanently

marked.

(ii) Accuracy of cross section leveling:

(a) height error between beginning point, end point, curve point, and cross section

points on structures shall be within + 2 cm and the ground surface points shall be

within + 5 cm;

(b) distance error between beginning point, end point, or curve point and cross section

points shall be within + 5 cm.

Topographical Survey of Bridge Site

A survey of the site of the new bridges shall be carried out to prepare plans to a scale of 1 to

200. This survey shall cover the dry river bed for a minimum distance of 250 metres from the

bridge location, on the upstream side and 200 metres on the downstream side. All other

requirements for the survey shall be as specified above for the 1 to 2,000 scale topographical

survey of the roads.

Survey Drawings

The requirements for all survey plans shall be as follows:

(i) all survey drawings shall be prepared on A1 size drawing sheets;

(ii) names and annotations shall be aligned parallel to the gridlines except for names

relating to linear features which shall be aligned parallel with those features;

(iii) all final drawings shall be provided with a standard border of 50mm for the left

margin and 25mm for the remaining margins. Each drawing will be labelled with the

date of generation, and version number.

(iv) the overlap of adjacent drawings shall give a minimum overlap of 75mm of detail

common to each drawing and match lines shall be included on each drawing;

23

(v) the co-ordinates and heights of all primary control monuments, secondary control

points and the existing National Datum benchmarks within the survey limits shall be

shown on the drawings;

(vi) copies of the survey drawings shall be form part of the Contractor’s Construction

Documents.

The survey drawings shall be used as the base for the As-Built Drawings that the Contractor is

required to prepare.

B 106. Axle Load Survey

The survey shall be carried out for a minimum period of 12 hours on 4 consecutive days and

the wheel loads on each axle of a representative sample of the following vehicle

classifications in each direction shall be determined:

Buses: 2 axle and 3 axle;

Rigid Trucks: 2 axle and 3 axle;

Articulated trucks : 4 axle, 5 axle, 6 axle and more than 6 axle.

The electronic wheel measuring device shall be calibrated and checked using a standard load

weight at the start and finish of the survey.

The Contractor shall be responsible for all traffic management and temporary signing in order

that delays to traffic are minimised and vehicles to be weighed do not impede the safe passage

of other vehicles.

Equivalent standard axle (ESA) values shall be calculated for each vehicle weighed and

average ESA values for each of the vehicle classifications on each road shall be determined.

The detailed method of carrying out the axle load survey as well as the analysis and

presentation of the survey results and the method of calculating ESA values is to be in

accordance with the recommendations given in the Transport Research Laboratory Overseas

Road Note 31 “ A guide to the structural design of bitumen surfaced roads in tropical and sub-

tropical countries” fourth edition 1993 and the Transport and Road Research Laboratory Road

Note 40 “ Guide to the measurement of axle loads in developing countries using a portable

weighbridge” 1978.

B 107. Bridge Foundation Ground Investigation

The Contractor shall carry out a ground investigation at the sites of the new bridges to be

constructed to provide data for the design of the bridge foundations.

A minimum of 1 borehole shall be drilled at the location of each abutment and pier, to a depth

of at least 25 metres (in normal material). If rock is encountered, the drilling can be

terminated after penetrating the rock for a minimum depth of 3 metres.

In-situ standard penetration tests shall be carried out in each borehole.

24

The Bridge foundation ground investigation shall be carried out according to the AASHTO

Manual on Subsurface Investigations, 1988.

25

PART 3: DESIGN

B 108. Highway Design

Highway Cross Section

The general highway cross section that shall be adopted is as follows:

Carriageway width to be 42meters.

Minimum carriageway cross fall of 2.0%

Foot path width to be 3 meters

Minimum shoulder slope of 4%

Horizontal Alignment

The designed horizontal alignment shall be a smooth flowing alignment that matches the

existing road alignment as closely as possible. This alignment is to be computed from survey

data collected during the topographical survey. Horizontal curves shall be designed to

comply with the geometric standards given in the AASHTO publication “A policy on

Geometric Design of Highways and Streets”, 4th edition (The Green Book) 2001, for a design

speed of 80 km/h for flat terrain, 60 km/h for rolling terrain, and 40 km/h for mountainous

terrain. In urban areas, the design speed may be reduced as required to enable the designed

alignment to follow the existing alignment.

Horizontal Alignment of the designed road are included :section 6 drawing

Vertical Alignment

Wherever possible, vertical curves shall be designed to comply with the geometric standards

given in the AASHTO publication “A policy on Geometric Design of Highways and Streets”,

4th edition (The Green Book) 2001, for a design of 80 km/h for flat terrain, 60 km/h for

rolling terrain, and 40 km/h for mountainous terrain. In the next page is shown the Table B01

with the main geometric design Standards Parameter that have to be adopted in the

construction of this road project.

Super elevation shall be designed to comply with the geometric standards given in the

AASHTO publication “A policy on Geometric Design of Highways and Streets”, 4th edition

(The Green Book) 2001, for a design speed of 80 km/h for flat terrain, 60 km/h for rolling

terrain, and 40 km/h for mountainous terrain

Vertical Alignments of the designed road are included: section 6 -drawing

26

Table B01

Main Geometric Design Standards Parameter

Lay-byes

The Contractor shall design and construct new lay-byes on both sides of the road at intervals

of approximately 20+000 kilometers. The locations of the lay-byes shall be selected so as to

best meet the following requirements:

(i) lay-byes should be provided in pairs on each side of the carriageway, but they must

not be directly opposite each other. The lay-byes should be staggered by a minimum

distance of 50 meters so that the lay-bye on the driving side of the carriageway (right

hand side) is reached before the lay-bye on the opposite side (left hand side);

(ii) lay-byes should be located close to major junctions, wherever possible;

(iii) in open country, lay-bye locations should be selected to minimize earthworks.

The lay-byes are to have the following dimensions: (please review the dimension of a lay-bye.

It may be too big.)

27

lay bye pavement to be 20000 meters long and 6 meters wide with 10 meter long entry

and exit taper sections;

Shoulder width to be 2 meters.

(i) The designed horizontal alignment shall be a smooth flowing alignment that matches

the existing road alignment as closely as possible. This alignment is to be computed

from survey data collected during the topographical survey. Horizontal curves shall

be designed to comply with the geometric standards given in the AASHTO

publication “A policy on Geometric Design of Highways and Streets”, 4th edition

(The Green Book) 2001, for a design speed of 100 kilometers per hour. In urban

areas, the design speed may be reduced as required to enable the designed alignment

to follow the existing alignment.

(ii) The designed vertical alignment shall be a smooth flowing alignment that runs parallel to the

existing vertical profile as closely as possible and provides for the construction of the designed

pavement layer thicknesses above the surface that results after existing asphalt layers have

been scarified and re-compacted or removed. Any regulation of this surface to meet the

designed vertical profile shall be carried out using the sub base material. The vertical profile

shall be designed to minimise the need for regulation with additional sub base material. In any

case, the maximum gradient for exceptional situation will be 18 %

Wherever possible, vertical curves shall be designed to comply with the geometric standards

given in the AASHTO publication “A policy on Geometric Design of Highways and Streets”,

4th edition (The Green Book) 2001, for a design speed of 80 km/h for flat terrain, 60 km/h for

rolling terrain, and 40 km/h for mountainous terrain

(iii) Super elevation shall be designed to comply with the geometric standards given in the

AASHTO publication “A policy on Geometric Design of Highways and Streets”, 4th edition

(The Green Book) 2001, for a design speed of 80 km/h for flat terrain, 60 km/h for rolling

terrain, and 40 km/h for mountainous terrain

The Contractor shall lease and coordinate with the contractors for the Rehabilitation of the

nearby Road projects to ensure that the horizontal and vertical alignments at the end point are

identical to those of the adjacent Contract.

B 109. Drainage Design

Inlet and Outlet Control at Culverts

Guiding ditches and guiding dams shall be provided wherever necessary to give an

unimpeded flow of water run off into and out of culverts.

The locations of guiding ditches shall be selected by site inspection and by reference to the 1

to 2,000 scale topographical survey plans.

Guiding ditches are to have a 3 meter wide invert and side slopes of 1.5 horizontal to 1

vertical.

28

Guiding dams are to have a 3 meter wide crest and side slopes of 2.5 horizontal to 1 vertical.

The guiding dams are to be constructed to the same requirements as embankments (re. Clause

C 505).

Rehabilitation of Side Drainage in Cut Sections

Effective side drainage shall be provided in all cut sections to ensure no surface water run off

ponds against the carriageway and that all surface water run off is led away from the cut

section into culverts or towards ground that slopes away from the road.

This rehabilitation of side drainage shall involve:

(i) Removal of screen material and boulders from the foot of cut slopes;

(ii) Provision of retaining walls formed by gabion boxes at the foot of cut slopes at

locations where there is a likely hood of future falls of screen material;

(iii) Re-establishing unlined side drains adjacent to existing cut slopes.

The locations of these works shall be selected by site inspection and by reference to the 1 to

2,000 scale topographical survey plans.

B 110. Design of Protection Works

Protection works for embankment slopes, culvert inlets and outlets, river training works,

guiding dams and around bridge abutments and piers shall be provided where scour has

occurred or where there is a risk of future scour taking place.

Protection works shall be constructed using gabions, grouted stone pitching or rip rap in

accordance with the following requirements:

(i) Gabions

Gabion mattresses and boxes shall have galvanized steel wire mesh and shall be laid

on a geotextile filter membrane, which is suitable for the underlying soil. The

physical and dimensional properties of the stone filling shall conform to gabion

manufacturer’s recommendations.

(ii) Grouted Stone Pitching

Grouted stone pitching shall conform to the construction requirements contained in

clause C 615.

(iii) Rip rap

Rip rap protection shall conform to the construction requirements contained in clause

C 614 and shall be designed in accordance with the following procedure:

29

(a) Rip rap for sloping surfaces

Size and weight of stones for pitching:

The size of the stone required on sloping surface to withstand erosive action of

flow is to be calculated by following equation:

d = Kv^2

Where d is the equivalent diameter of stone in meters,

V is the mean design velocity in meter/second,

And K is a constant and is to be taken as 0.0282 for face slope of 2:1 and

0.0216 for a face slope of 3:1.

The weight of the stone can be worked out by assuming a spherical shape stone

with a specific gravity of 2.65. However the minimum diameter of a stone

shall be 300mm. and the weight shall not be less than 40 kg.

Thickness of pitching:

The thickness of pitching is to be worked out by the following formula:

T= 0.06Q^1/3

Where T is the thickness of pitching and Q is the design discharge in

m^3/second.

Filter design

Filter provided below the boulders pitching shall consist of sound gravel,

stone, over burnt brick ballast and coarse sand. Geotextiles can also be used as

filter material.

(b) Rip rap for launching aprons or cut off blankets

The design of launching apron or cut off blanket shall be carried out based on

following considerations:

Size and weight of stone:

The size of stone required for launching apron is to be calculated based on

following formula-

V = 4.893x (d) ^1/2

Where V is the mean design velocity in meter/second and d is the equivalent

diameter of stone in meters.

30

The weight of the stone can be worked out by assuming spherical shape of

stones having a specific gravity of 2.65. However the minimum diameter of

stone shall be 300mm. and the weight shall not be less than 40 kg.

Depth of scour

The maximum depth of scour for surfaces of the protection works is to be

determined as follows:

Up-stream curved surfaces 2.5 dsm

Straight surfaces upstream and downstream 1.5 dsm

Where dsm is the mean depth of scour

Width of launching apron:

A width of launching apron of 1.5 dmax is to be provided where dmax. Is the

maximum anticipated scour below the bed level in metres.

Thickness of launching apron:

The thickness of pitching is to be worked out by the following formula:

T= 0.06Q^1/3

Where T is the thickness of pitching and Q is the design discharge in

m^3/second.

The thickness of launching apron at inner end is to be kept as 1.50T and outer

end as 2.25T.

Slope of launching apron:

The slope of the launching apron is to be considered as 2 Horizontal and 1

Vertical for loose boulders and 1.50 Horizontal, 1 Vertical for gabions.

31

B 111. Bridge Design

Structural Arrangement Requirements for New Bridges

The Contractor shall design the new bridges which intersect with the new projected road.

(i) Span Arrangement

(ii) Superstructure

(iii) Substructure

(iv) Bearings and Expansion Joints

Bearings shall be Pot c um PTFE type that meet the requirements of section 18 of the

AASHTO Standard Specifications for Highway Bridges, 17th Edition, 2002.

Expansion joints shall be strip seal type that meets the requirements of section 19 of

the AASHTO Standard Specifications for Highway Bridges, 17th Edition, 2002.

(v) Foundations

The foundations will be calculated once studied the geologic conditioners of the land

next to the bridge

(vi) `Miscellaneous

The surfacing for the bridge deck shall consist of:

(i) 6 mm thick layer of mastic asphalt laid on a bituminous prime coat over the

concrete deck. The mastic asphalt is to contain 75% lime stone dust filler and

25% of 30/40 penetration grade bitumen and it shall be laid at a temperature of

1900 C.

(ii) Two layers, each 25 mm thick, of asphalt wearing course.

Drainage spouts with gratings at the top surface shall be provided on the bridge to

ensure proper drainage of surface water.

An approach slab 3.50m long and 300mm thick resting on the bracket taken out from

the dirt wall shall be provided on both sides of the bridge, resting on a 150mm thick

leveling course. The gap between the approach slab and dirt wall shall be filled with a

bituminous joint filler sealing compound.

32

Design Loading Requirements for New Bridges

The contractor shall design the bridges to sustain the most critical combination of the various

loads, forces and stresses that can coexist as given in the Standard Specifications for Highway

Bridges, 17th Edition, 2002. The allowable stresses and the permissible increase in stresses

for various load combinations shall be adopted as given in the relevant clauses of the

AASHTO Standard Specification for Highway Bridges.

Design loadings that shall be considered for bridge are as follows:

(i) Carriageway Live Load

The bridge shall be designed for a carriageway live load of HS20-44.

(ii) Longitudinal Force

The bridge shall be designed for the effect of a longitudinal force of 5% of the live

load in all lanes carrying traffic headed in the same direction. The centre of gravity of

the longitudinal force shall be assumed to be located 6 feet above the deck slab and it

shall be transmitted to the sub-structure through the super-structure.

(iii) Impact

The amount of impact shall be expressed as a fraction of live load stress and it shall be

calculated by the following formula:

I = 50/(L+125)

Where, I = impact fraction maximum 30 percent

L = length in feet of the portion of the span that is loaded to produce the

maximum stress in the member.

(iv) Footpath Live Load

The footpath live load shall be considered as 85 lb. / sq ft.

(v) Krebs Loading

Krebs shall be designed to resist a lateral force of 500 pounds per linear foot of curb,

applied at the top of curb.

(vi) Wind Forces

The effect of wind shall be considered as 50 pounds per square foot. This force shall

be applied at a point 6 feet above the deck level.

(vii) Buoyancy Effects

33

The following buoyancy effects shall be considered, wherever applicable, for the

design of various components of the bridges:

For foundations 100 %

For substructure below water level 15 %

(viii) Seismic Forces

The bridge falls in a seismic zone and it shall be designed to safely sustain the seismic

forces.

Requirements for Design of Bridge Rehabilitation Works The structural arrangements requirements for the bridge deck surfacing, bridge deck drainage

and bridge deck approach slabs in the bridge rehabilitation works shall be as given above for

the new bridges.

The Contractor shall design the bridge rehabilitation works so that they can safely sustain the

most critical combination of the various loads, forces and stresses that can coexist as given in

the Standard Specifications for Highway Bridges, 17th Edition, 2002. The allowable stresses

and the permissible increase in stresses for various load combinations shall be adopted as

given in the relevant clauses of the AASHTO Standard Specification for Highway Bridges.

The design loadings given above for the new bridges shall be considered, where appropriate.

B 112. Retaining Wall Design

Retaining walls shall be designed to comply with the following requirements:

(i) a factor of safety of 1.5 shall be provided against sliding;

(ii) a factor of safety of 2.0 shall be provided against overturning;

(iii) a factor of safety of 2.0 shall be provided for foundation bearing capacity.

The retaining walls to be provided at the foot of the reinstated sections of embankment slope

can be designed as either:

- gravity retaining walls to be constructed in mass concrete, grouted masonry or

gabion boxes;

or

- Cantilever retaining walls to be constructed in reinforced concrete.

B 113. Road Furniture Design

Road national and standards Signs

34

The Contractor shall provide advance direction road signs, route confirmatory road signs,

warning road signs and regulatory road signs and all road signs necessary for safe and

effective traffic operations. The road signs shall be in accordance with national standards.

Road sign posts and foundations shall be designed to withstand forces generated by a

minimum wind velocity of 50 meters per second.

Sign plate and text height dimensions for all road signs shall be suitable for a traffic speed of

100 kilometers per hour.

Text shall be provided in Dari and English languages.

Guardrail

The Contractor shall provide guardrail at the following general locations:

(i) on the outside of horizontal curves with radii generally less than 500 meters;

(ii) where the embankment height exceeds 4 meters.

(iii) before and after bridge parapets where it is necessary to provide a transition barrier.

(iv) where the road is in a mountainside cut with a steep and high drop-pff

B 114. Road Marking Design

The Contractor shall provide the following road markings on all roads, in accordance with

national standards:

(i) centre line marking for normal conditions

3 meter long white line (100mm wide) with 6 meter long gap;

(ii) warning centre line marking at approaches to junctions, at horizontal curves with radii

less than 600 meters and other locations where potential hazards exist

6 meter white line (100 mm wide) with 3 meter long gap

(iii) no overtaking centre line marking where the overtaking sight distance of 375 meters is

not provided (sight distance to be based on eye height and object height of 1.10

meters)

(a) Overtaking sight distance not provided on one lane

Continuous 100 mm wide white line on the side where the overtaking sight

distance is not provided and warning line provided on the other side (gap of

100 mm between the two lines)

35

(b) overtaking sight distance not provided on both lanes

single continuous 100 mm wide line;

(iv) carriageway edge line

continuous white 150 mm wide line on both carriageway edges;

(v) carriageway edge line at lay byes

0.6 meter long, white line (150 mm wide) with 0.3 meter long gap;

(vi) give way line at junctions

double 0.6 meter long white line (200 mm wide) with 0.3 meter long gap across mouth

junction – (lines to be 300 mm apart);

(vii) stop line at junctions

double continuous white line 200 mm wide – (lines to be 300 mm apart).

36

Section C : CONSTRUCTION SPECIFICATION

37

SECTION C 100: PRELIMINARIES

38

Introduction

Part 1

Part 1 of this Section details specific requirements in respect of the following general

obligations of the Contract:

Health and Safety;

Protection of the Environment;

Programmed and Method Statements;

Setting out of the Works;

Quality Control;

Materials supply;

Standards;

Temporary Works;

Traffic Safety Temporary diversions and Control;

Protection of Existing Services;

Landmines and unexploded ordinance;

Graves and burial sites;

Local Liaison and Consultation.

Compliance with the requirements of Part 1of this Section shall not relieve the Contractor of

its obligations in respect of these matters either under Contract or at law.

Part 2

Part 2 of this Section details specific requirements in respect of facilities and services to be provided by the Contractor for the Engineer/Employer.

39

PART 1

Health and Safety

In accordance with Clauses 4.8, 4.22 and 6.7 of the Conditions of Contract:

The Contractor shall take all measures necessary to safeguard the health, safety and welfare of

all persons entitled to be on the Site and shall ensure that the Works are carried out in a safe

manner. The Contractor shall take all reasonable precautions to protect members of the

public and road users from any activity under its control.

The Contractor shall provide and maintain barriers, fencing and lighting around its working areas when and where necessary for the safety and security of the public and road traffic.

The Contractor shall provide adequate lighting wherever any work is to be carried out at night.

The Contractor shall maintain the Site in safe, tidy and sanitary condition. The Contractor

shall provide latrines at areas of the Site where work is in progress and ensure that they are

regularly cleaned and maintained in a hygienic state. The Contractor shall be responsible for

disposing of all rubbish and waste occurring on the Site from whatever source.

The Contractor shall provide, and enforce the utilization of appropriate safety equipment for

all workmen and staff employed directly or indirectly by the Contractor. Such safety

equipment shall include, as appropriate, safety helmets, eye protectors, hearing protectors, and

safety harnesses. The Contractor shall provide, where appropriate, rescue equipment and fire

safety equipment.

First-aid equipment shall be provided at all work locations.

The Contractor shall appoint one member of its staff to act full-time as Safety Officer, and it

shall notify the Engineer of such appointment. The Safety Officer shall be experienced in all

matters relating to health and safety on construction sites and shall be familiar with all

relevant safety regulations and legislation. The Safety Officer shall be authorized to receive

instructions from the Engineer on matters relating to the health and safety.

The Contractor shall maintain such records and make such reports concerning safety, health

and welfare of persons and damage to property as the Engineer may from time to time

prescribe, and as required by law.

In the event that the Contractor temporarily closes down site operations seasonally or for any

other reason, he shall ensure that the Works are left in a safe condition. He shall appoint one

member of its staff to be responsible for the Works during such shutdown period and shall

supply to the Engineer and other relevant authorities the name and contact telephone number

of the responsible person.

The Contractor shall ensure that clauses equivalent to the above in relation to health and

safety are included in all sub-contracts.

The Contractor shall conduct Information, Education and Consultation campaigns, addressed

to all the site staff and workmen employed directly or indirectly by the Contractor, concerning

the risks, dangers and impact, and appropriate avoidance behavior with respect to sexually

transmitted diseases in general and HIV/AIDS in particular.

40

Protection of the Environment: General

The Contractor shall take all reasonable measures to avoid nuisance or disturbance arising

from the construction of the Works. The Contractor shall comply with the requirements

pertaining to construction that is contained in:

(i) the Asian Development Bank publication “Environmental Guidelines for Selected

Infrastructure Development Projects”;

(ii) the Asian Development Bank’s Environment Policy.

Environmental Protection Plan

The Contractor shall prepare an Environmental Protection Plan detailing how the Contractor’s

works shall comply with the relevant environmental laws and the particular requirements of

the Contract.

This Plan shall be submitted to the Engineer, the Employer and relevant Local Authorities at

the same time as its submission of the Programmed prepared in accordance with Clause 8.3

of the Conditions of Contract.

This Plan shall detail the Contractor’s proposed measures in respect of:

fuel storage and distribution;

control of water borne pollution (waste water and rain ‘run-off’);

prevention of pollution of rivers and water courses where these are adjacent to the

works (for example at bridge sites);

control of dust;

removal of rubbish;

sanitation for its work force;

control and reduction of noise;

operation of borrow areas, quarries and tips.

The Plan, and the Contractor’s proposed working methods, shall, so far as they relate to

environmental matters, be subject to the approval of the Employer, any relevant

Environmental Agency and the Engineer.

Environment Protection Manager

The Contractor shall appoint an Environment Protection Manager to be responsible for environmental matters and whose duties shall include supervising the Works to ensure compliance with its Environmental Monitoring Plan.

The Environmental Protection Manager shall liaise directly with the Engineer and Employer

(or Employer’s Environmental Agency) on matters relating to the environment and shall have

power to effect changes in the Contractor’s working practice which affect the environment.

41

Protection of the Environment: Particular Requirements

The Contractor shall comply with the following particular requirements in respect of the

environment.

Fuel and Chemical Storage

All fuel and chemical storage shall be sited on impervious bases within a bund, and shall be secured by fencing. The storage area shall be located away from any watercourse or wetlands. Filling and refueling shall be strictly controlled. All valves and trigger guns shall be locked when not in use.

The contents of any tank or drum shall be clearly marked.

Water Quality

The Contractor shall prevent any interference with, or pollution of, the supply or abstraction

of water, arising from the construction of the works.

The Contractor shall protect all watercourses and waterways adjacent to the works from

pollution, silting, flooding or erosion.

The Contractor shall not discharge or deposit any matter arising from the Works into any

watercourse.

Air Quality: Dust Prevention

The Contractor shall employ effective measures to control dust.

Water shall be sprayed during the delivery and handling of materials when dust is likely to be

created.

Stockpiles of materials shall be sited in sheltered areas or protected by hoarding and /or tarpaulins and away from residential or other sensitive areas. Where appropriate, stockpiled materials shall be sprayed with water to prevent dust pollution.

Vehicles used for transporting potentially dust producing material shall have properly fitting

side and tail boards and the materials shall be covered with a clean tarpaulin.

Works shall not be carried out in windy conditions when this would cause nuisance.

Air Quality: Exhaust Emissions

Construction vehicles and machinery shall be kept in good working order and engines turned

off when not in use.

Measures shall be taken to limit particulate exhaust emissions from construction vehicles, and equipment.

The location of generators and other permanent equipment shall be governed by considerations of exhaust emission, taking into account predominant wind direction.

42

Noise

The Contractor shall take all necessary measures to ensure that the operation of all mechanical

equipment and construction processes on and off the Site shall not cause any unnecessary or

excessive noise.

Generators and other standing equipment near residential areas (including site offices and camps) shall be silenced.

When operating close to residential, medical facilities, or other similar locations, the

Contractor’s hours of working shall be limited to 8 a.m. to 6 pm.

Borrow Areas, Spoil Tips and Quarries

Borrow pits and quarries shall be operated to minimize the impact on the environment, taking

into account requirements in respect of drainage and erosion.

Borrow areas and quarries shall be reinstated to smooth contours, shall be re-soiled and re-

vegetated with matching ground cover.

Spoil arising from the works shall be disposed of to the requirements of the local planning

agency.

Programmed

The Programmed to be furnished in accordance with Clause 8.3 of the Conditions of Contract

shall be fully resourced and developed from proprietary computer software.

The Programme shall be presented in the following formats:

a project bar chart (Gantt Chart) for the Whole of the Works;

a time-chain age chart for earthworks and pavement construction;

resource histograms for major items of equipment;

resource histograms for lab our;

a cumulative cash flow forecast.

The Programme shall include for the surveys, investigations and design that the Contractor is

required to carry out. The Programme shall also show the dates when various Construction

Documents are to be submitted to the Engineer for approval and the Engineer’s review

periods as detailed in clause B 102.

The Programme shall be updated monthly and actual progress charted against the base programme. The monthly updates shall be submitted to the Engineer not later than 7 days after the end of each month and in any event not later than the submission of the Contractor’s Monthly Statement.

The Contractor shall license the Engineer for the use of the software.

43

Methods of Construction: Method Statements General Method Statement

At the time of submission of its Clause 8.3 Programme, the Contractor shall submit a Method Statement detailing its general planning arrangements for the principal work operations, including:

Site establishment;

quarries and borrow areas;

earthworks operations;

aggregate extraction;

screening and crushing operations;

road pavement operations;

new bridge works;

structural repair works.

This general Method Statement shall include details of intended equipment and labour together with general planning and production arrangements in relation to the Works as a whole. Detailed Method Statements

Prior to any particular works operation, the Contractor shall submit a Detailed Method

Statement indicating:

the lab our and equipment resource to be used;

work procedures;

supervision (by named individual);

quality control;

survey methods;

Temporary Works (if any);

particular measures in respect of environmental protection;

Particular measures in respect of health and safety.

Where Temporary Works involve detailed structural calculations, these shall be submitted

separately.

No work shall be carried out by the Contractor prior to his submitting notice to the Engineer. Such notice shall give full details of the operation concerned and be sufficiently in advance of the commencement of the operation to enable the Engineer to make such arrangements, as he deems necessary for inspection and checking.

44

Setting Out

The Contractor shall be responsible for establishing and maintaining temporary survey control

points such as to allow the proper setting out of the Works. The Contractor shall furnish all

such relevant setting out control information to the Engineer to allow independent checking.

Quality Control and Quality Assurance

Pursuant to its obligations under Clause 4.9 of the Conditions of Contract, the Contractor

shall be responsible for implementing quality control and quality assurance procedures.

The Contractor shall prepare and implement a Quality Control Plan, compliance with which

will demonstrate that the various requirements of the Construction Specification in respect of

quality of materials and workmanship are being complied with.

This Plan shall be submitted to the Engineer at the same time as its submission of the

Programme prepared in accordance with Clause 8.3 of the Conditions of Contract. The Plan

shall be subject to the approval of the Engineer.

The Contractor shall establish and operate a Site Laboratory in order to carry out the acceptance and control testing detailed in Section C 200 of the Technical Specifications and its Quality Control Plan.

Notwithstanding the Contractor’s obligation in regard to quality control of its works, the

Engineer retains the right to undertake independent quality control tests. To this end, the

Contractor shall make the facilities in its Site Laboratory available to the Engineer. The

Contractor shall provide, at no charge to the Employer, all assistance, labour, and transport to

enable the Engineer to carry out such independent sampling, field and laboratory tests in the

Contractor’s laboratory.

The tests and testing regime detailed in Section C 200 of the Construction Specification and

any alternative or supplementary testing arranged by the Contractor as part of its Quality

Control Plan shall be deemed to be clearly intended and provided for in the Contract, and

their costs shall be borne by the Contractor.

Should the Contractor default in its obligation to implement quality control in accordance

with the above provisions, the Engineer shall make alternative arrangements for the testing of

the Works, the cost of which shall be contra-charged to the Contractor.

Approval of Suppliers

Before placing any order for supplied materials and/or manufactured articles for incorporation

in the Works, the Contractor shall submit to the Engineer the names of the firms from whom

he proposes to obtain such materials and/or manufactured articles together with a description,

their origin, the manufacturer's specification, and any other relevant details.

The Contractor shall provide the Engineer with samples of such materials and manufactured

articles and, where appropriate, shall provide manufacturer's certificates of recent tests carried

out. In particular, manufacturer’s certificates shall be provided for supplies of:

bitumen;

45

cement;

reinforcement;

bearings;

Pre-cast products.

The Contractor shall provide further test certificates during the course of the Works to demonstrate continuing compliance with the Construction Specification.

Materials: Alternative Standards

Unless otherwise specified, all materials incorporated in the Works shall comply with

“Standard Specifications for Transportation Materials and Methods of Sampling and Testing,

Part 1 Specifications, Seventeenth Edition, 1995” or the latest edition, as adopted by the

American Association of State Highway and Transportation Officials (AASHTO).

Should the Contractor wish to depart from the Standards stated in the Construction

Specification, or to furnish material under equal but alternative standards or specifications, a

statement of the exact nature of the departures fully supported by copies of the alternative

standards / specifications shall be included in the Construction Documents.

Any further testing which the Engineer may consider necessary in order to grant approval shall be at the Contractor’s expense.

Temporary Works

The Contractor shall include in the Construction Documents, full details of its proposed

arrangements in respect of Temporary Works.

Such details shall include drawings, calculations, setting-out details and all other information as the Engineer may reasonably require enabling him to review and give consent to the proposals.

Consent by the Engineer to the Contractor’s proposals shall not relieve the Contractor of its

responsibilities and liabilities under the Contract.

Traffic Safety and Control

The Contractor shall construct the Works without disruption to existing traffic. Accordingly,

the Contractor shall take whatever measures are necessary to maintain traffic flow.

Road closures shall not be permitted. Where the contractor’s working methods prevent the

use of the existing carriageway, diversion roads shall be constructed.

In association with the local Traffic Authorities, the Contractor shall produce a Traffic

Management Plan indicating how traffic is to be managed for the duration of the Works.

This Plan shall be submitted to the Engineer, the Employer and relevant Local Authorities at

the same time as its submission of the Programme prepared in accordance with Clause 8.3 of

the Conditions of Contract.

This Plan shall be subject to the approval of the relevant Traffic Authorities as well as the

Engineer and Employer.

46

For each working area, the Contractor shall provide further a Local Traffic Management Plan.

These Plans shall indicate the actual traffic control measures to be effected at each location.

The Contractor shall appoint a Traffic Control Supervisor who shall be responsible for co-ordinating traffic safety and control between the Engineer and the local Traffic Authorities.

All traffic diversions and traffic management works shall be provided with adequate traffic

warning signs and other traffic flow indicators, which shall be provided and maintained on a

24 hour, 7 day a week basis during the period of construction of the relevant Works.

Temporary Road Diversions

Temporary Diversions shall comply with the following requirements:

at grade construction but with a maximum gradient of 10%;

150 mm thick gravel surfacing to be provided that is to be construction in accordance

with the requirements of Section C 507 of the Construction Specification;

minimum carriageway width of 7m to be provided;

culverts and side drainage to be provided as necessary.

The layout of diversions shall be subject to the approval of the Engineer and shall be included

in the Detailed Traffic Management Plans.

Temporary road diversions shall be maintained throughout their use and original ground

reinstated on completion of the diverted works. The maintenance shall include regular

grading, watering and compaction to provide a smooth, corrugation free running surface that

is free from soft spots.

Existing Services and Service Diversions

‘Services’ includes water, gas and oil pipelines and electricity and telecommunications cables.

The Contractor shall include in its rates and prices for locating and taking measures for the support and protection of pipes, cables and other apparatus during the progress of the Works and for making arrangements with the appropriate authority / owner.

The Contractor shall indemnify the Employer against any claims arising from damage to

existing services.

Where the Contract requires a service diversion, the Contractor shall be responsible for liaising with the owner / operator (or its contractor) and for all matters in connection therewith. In this context ‘diversion’ means any relocation or alteration in position.

The Contractor shall keep Engineer informed of all arrangements he makes with the owners

or suppliers and its proposals shall be subject to the approval of the Engineer and the owner /

operator of the respective service.

The contractor shall have sole and complete responsibility for scheduling and for the timely

implementation of relocations and diversions. No claims will be entertained on the basis that

the contractor’s work was delayed, disrupted or otherwise interfered with by the actions of

those doing the relocations or delays or by their delays in doing such work

47

Restriction on Working Hours Further to Condition of Contract Clause 6.5, ‘night working’ is deemed to be between 20:00 and 07:00 and the ‘locally recognized days of rest’ are Thursday from 12:00 and all day on Friday Should the Contractor’s Programme involve working during ‘night’ or ‘rest days’ or Public Holidays and should this incur the Employer in additional supervision costs, the provisions of Clause 6.5 in respect of the Employer’s right to recover such costs shall apply without the requirement for notice to the Contractor in addition supervision costs, the Employer shall be entitled to recover from the contractor such costs without the requirement of a prior notice to the contractor

Landmines and Unexploded Ordinance

Requirements in respect of surveying and clearing landmines and unexploded ordnance are

given in Sub-Clause 4.25 Part B- Particular Conditions of Contract.

Graves and Burial Sites

There are a number of graves and burial sites located in the road shoulders, on the

embankment slopes and in other areas occupied by the Works. The Contractor shall ensure

that all graves and burial sites are not disturbed or damaged by any site clearance or

construction operation. Suitable temporary warning signs and demarcation measures are to be

provided by the Contractor during the period when site clearance and construction operations

are in progress in the vicinity of the graves and burial sites.

The Contractor shall agree with the Engineer any local modifications to the Permanent Works

that are required in order to ensure that the graves and burial sites remain undisturbed.

Local Liaison and Consultation

The Contractor shall liaise and consult fully with local authorities and local people during the

construction of the Works. Matters covered by this local liaison shall include safety, social

and cultural issues, assistance with recruitment of staff and lab our, design matters relevant to

local residents and landowners, land required for Permanent Works beyond the existing

embankment toe, land required for Temporary Works, local access during the construction of

the Works, traffic safety and control, environmental matters and security. This local liaison

and consultation shall be carried out through correspondence, formal meetings with

authorities, public meetings, and meetings with individuals, the local press and the local radio

and television services.

The Contractor shall prepare a Local Liaison and Consultation Plan detailing the procedures

to be adopted for local liaison and consultation, as well as the extent and coverage of the

liaison and consultation. This Plan shall be submitted to the Engineer, the Employer and

relevant local authorities at the time of submission of the Programme prepared in accordance

with Clause 8.3 of the Conditions of Contract. The Plan shall be subject to the approval of

the Engineer.

The Contractor shall appoint a Local Liaison Officer to be responsible for all local liaison and

consultation. Contact details for the Local Liaison Officer shall be included in the Local

Liaison and Consultation provided to the Engineer, the Employer and local authorities.

48

‘As Built’ Drawings

The Contractor shall submit a full set of draft ‘As-Built’ drawings in hard copy for the

Engineer’s consent. A full set of final ‘As-Built’ drawings shall then be submitted by the

Contractor that incorporate any revisions required by the Engineer, within one month of any

Taking-Over Certificate. The Contractor shall submit one paper copy of the final ‘As-Built’

drawings together with a copy of each drawing in an agreed electronic format.

49

PART 2: FACILITIES AND SERVICES FOR THE ENGINEER AND EMPLOYER

50

Survey Equipment

The Contractor shall provide the following survey equipment.

Schedule of Survey Equipment No.

Engineer's Precise Level (+/- 2mm per km) complete with tripod and staff 2

Total station: Nikon 5 second or equal, including 'Half traverse' set, prisms and on

board data logger. 1

Steel or Fibroin tape: 100m 3

Fibroin tape: 50m 5

Newly Purchased Vehicles The Contractor shall supply vehicles in accordance with the following schedule and specification:

Schedule of Vehicles

Vehicle Type A (car)

Vehicle Type B (de luxe 4x4 sports utility vehicle)

Vehicle Type C (standard 4x4 jeep type)

Vehicle Type D (standard 4x4 hatchback)

Vehicle Type E (mini-bus)

Vehicle Type F (4 x 4 pick up)

The newly purchased vehicles shall be comprehensively insured for any authorized driver.

The vehicles shall be licensed and taxed for use within Afghanistan.

A driver shall be provided for each vehicle. The drivers shall be available during all working

hours and otherwise as required by the Engineer.

Vehicles shall be washed, cleaned and fuelled on a daily basis.

The Contractor shall be responsible for the care of vehicles during any shut down periods.

The vehicles shall be fully serviced and made ready for the use of the Engineer’s staff prior to

the resumption of the construction of the Works immediately following any shut down period.

The vehicles shall revert to the Employer at the date of issuing the Taking over Certificate for

the Whole of the Works, or at such other date instructed by the Engineer.

51

Vehicle Specification

Vehicle Type: Type A

(Car)

Type B

(de luxe

4x4)

Type C

4x4 jeep

Type D

4x4 h/back

Type E

(mini-bus)

Type F

(pickup)

Basic Specification

4x4 (4 wheel drive) No Yes Yes Yes No Yes

Left hand drive Yes Yes Yes Yes Yes Yes

Length (minimum) : meters 4.2 4.8 4.6 4.05 4.44 4.2

Seating capacity 4 5 5 4 7 3

Ground clearance (minimum) 0.18 0.28 0.22 0.22 0.22 0.22

Cargo capacity (minimum) Kg 500 1000 950 300 1150 1000

Engine / Transmission

Engine : petrol / diesel Petrol Either Either Either Either Either

Engine capacity (minimum) : cc 1800 3000 2445 1600 2445 1800

Horse power (minimum) : HP 20 150 75 72 75 90

Transmission (4 or 5 speed) 5 speed 5 speed 4 speed 4 speed 4 speed 4 speed

High/low transfer gear No Yes Yes Yes Yes Yes

Fuel tank (minimum) : litres 60 90 80 40 80 65

Mechanical / Equipment

Power assisted steering Yes Yes No No No No

Independent front suspension

Yes Yes Yes Yes Yes Yes

Independent rear suspension Yes Yes No No No No

Brakes : front Disc Disc Disc Disc Disc Disc

Brakes : rear Disc Disc Drum Drum Drum Drum

ABS system No Yes No No No No

Odometer / tachometer No Yes No No No No

Internal

Air conditioner Yes Yes No No No No

Tinted laminated windscreen Yes Yes No No No No

Clock Yes Yes No No No No

Lockable glove box Yes Yes Yes Yes Yes Yes

External

Rear view side mirrors Fold-away Fold-away Yes Yes Yes Yes

Mudguards front and rear Yes Yes Yes Yes Yes Yes

Safety Equipment

Driver and passenger airbags Yes Yes No No No No

Front and rear seat belts Yes Yes Yes Yes Yes Yes

Head restraints All All Front Front Front Front

First aid kit Yes Yes Yes Yes Yes Yes

Fire extinguisher Yes Yes Yes Yes Yes Yes

Security locking Yes Yes No No No No

52

Vehicle Type: Type A

(Car)

Type B

(de luxe

4x4)

Type C

4x4 jeep

Type D

4x4 h/back

Type E

(mini-bus)

Type F

(pickup)

Miscellaneous

Spare tyre, jack and tools Yes Yes Yes Yes Yes Yes

Front and rear tow hitch Yes Yes Yes Yes Yes Yes

Tool kit Yes Yes Yes Yes Yes Yes

Shovel and steel cable tow-rope Yes Yes Yes Yes Yes Yes

Snow chains Yes Yes Yes Yes Yes Yes

º

Maintenance and Security The Contractor shall service and maintain all facilities provided for the Engineer throughout the duration of the Works, until such time as the facilities are taken over or returned.

Maintenance shall include:

1. cleaning, and repair of buildings and fixtures;

2. servicing of equipment and furniture;

3. the uninterrupted supply of water, electricity and gas (where provided);

4. telephone rental charges including internet access;

5. the maintenance, of driveways, access roads, hard standings, footways, fences,

security lighting, and areas of landscaping including the removal and disposal of

vegetation and debris;

6. refuse collection and disposal;

7. sewage disposal facilities;

8. the provision of toilet and kitchen consumables including cleaning materials;

9. the provision of all survey consumables including field books, road markers, etc;

10. cleaning, repair and replacement of protective clothing;

11. Cleaning, servicing and repair of vehicles including the provision of fuel, oil,

lubricants, and other consumables and replacement parts.

At the principal Site Office the Contractor shall provide a full time chainman / utility person

for general attendance duties for the Engineer.

The Contractor shall provide 24 hour security to the Engineer’s Site Offices and Residential

Accommodation including during any shutdown periods.

If the Works are not completed within the stipulated period or within the granted extension

time of completion, maintenance of all facilities provided for the Engineer shall be carried out

by the Contractor at his own cost beyond the stipulated/extended time of completion.

53

SECTION C 200: QUALITY CONTROL

Scope of Section

54

This Section details testing regimes and standards for the quality control of workmanship and

materials.

The Contractor shall carry out the tests detailed in this section in accordance with its Quality

Control Plan.

Quality Control Plan The Contractor shall prepare a Quality Control Plan which shall detail quality control procedures such as to demonstrate that the requirements of Clause 4.9 of the Conditions of Contract in respect of quality are met. The Quality Control Plan shall provide a formal framework for the approval of the Works by the Engineer.

In particular the Quality Control Plan shall include:

quality control procedures in respect of the selection and control of materials,

distinguishing between approval testing and compliance testing;

quality control procedures in respect of construction operations, identifying

procedures for production control and procedures for survey control;

procedures for the Contractor and Engineer to ‘sign off’ approved construction works.

In preparing the Quality Control Plan the Contractor shall take into consideration the requirements and obligations of the Engineer in respect of checking and inspection of the Works.

The Contractor shall appoint a Quality Control Manager who shall be responsible for ensuring

that the quality control procedures set out in the Quality Control Plan are adhered to. The

Quality Control Manager shall have independent control of all quality control activities.

General Requirements in Respect of Testing

The Contractor shall carry out sampling procedures and testing of materials incorporated in

the Works in accordance with AASHTO Part 2, Sampling and Testing.

Sieves

ASTM E-11 sieves shall be used for all tests. The sieve series in mm and μm are as follows:

Coarse 100, 90, 75, 63, 53, 50, 45, 37.5, 31.5, 26.5, 25.0, 22.4, 19.0, 16.0, 13.2, 12.5, 11.2, 9.5,

8.0, 6.7, 6.3, 5.6, 4.75, 4.00 mm;

Fine 3.35, 2.80, 2.36, 2.00, 1.70, 1.40, 1.18, 1.00 mm, 850, 710, 600, 500, 425, 355, 300, 250,

212, 180, 150, 125, 106, 90, 75, 63, 53, 45, 38 μm.

55

PART 1: LABORATORY / FIELD TESTS AND PROCEDURES SOILS, GRAVELS AND AGGREGATES

Sampling and Preparation of Samples

Sampling of soils and gravels and their sample preparation shall be carried out as specified in:

AASHTO T87 - Dry Preparation of Disturbed Soil and Soil Aggregate Samples for Test;

AASHTO T146 - Wet Preparation of Disturbed Soil Samples for Test.

Standard Methods of Testing

Tests on soils and gravels shall be performed in accordance with the Test Procedures given in

Table 2-1.

Wherever in the text of these Construction Specification, the term "x% of the MDD

(AASHTO T99 or T180)" is used it shall mean that a standard of compaction shall be

achieved such that the dry density of the compacted material is x% of the maximum dry

density determined from the AASHTO T99 or T180 compaction test.

TABLE 2-1: Test Procedures Applicable to Disturbed Samples of Soils and Gravels

Description Test Procedure

Particle Size Analysis of Soils AASHTO T88

Determining the Liquid Limits of Soils AASHTO T89

Determining the Plastic Limit and Plasticity Index of Soils AASHTO T90

The Moisture-Density Relations of Soils Using a 2.5 kg Rammer and a

305 mm Drop AASHTO T99

Specific Gravity of Soils AASHTO T100

Plastic Fines in Graded Aggregates and Soils by Use of the Sand

Equivalent Test AASHTO T176

The Moisture-Density Relations of Soils Using a 4.55 kg Rammer and a

457 mm Drop AASHTO T180

Density of Soil and Soil – Aggregate In-Place by the Sand-Cone Method AASHTO T191

The California Bearing Ratio AASHTO T193

Density of Soil and Soil-Aggregate In-Place by Nuclear Methods AASHTO T238

Moisture Content of Soil and Soil-Aggregate In-Place by Nuclear

Methods AASHTO T239

Laboratory Determination of Moisture Contents of Soils AASHTO T265

Density - Moisture Content Relationship, Vibrating Hammer BS 1377 Test 14

Field Moisture Content Determination AASHTO T217

Samples for the AASHTO T99 and T180 compaction tests shall be taken from the Works

before compaction of the layer concerned begins unless, in the opinion of the Engineer, the

compactive effort proposed by the Contractor is such that the material characteristics would

be altered by the process of compaction, in which case the samples for the tests shall be taken

after all compaction is complete.

56

Compaction tests on materials, which are susceptible to crushing during compaction, shall

require a separate new sample to be prepared for the determination of each point on the

moisture/density curve.

The field density and moisture content of material placed in the Works shall be determined by the Sand Cone Method (AASHTO T191) and the oven and calcium carbide gas pressure moisture tester (AASHTO 217). The Contractor may also employ nuclear methods in accordance with AASHTO T238 and T239.

The standard method of test for density of soil in place by the sand cone method, AASHTO

T191 shall be used for initial calibration of the nuclear density testing equipment and for

check/comparison tests.

For crushed aggregates and granular soils, the laboratory compaction test using vibratory

hammer, BS 1377 - Test 14, may be employed as an alternative to AASHTO T 180.

Cement or Lime Treated Materials Samples shall be prepared in accordance with BS1924. For preparing samples containing particles larger than 20mm for compaction and CBR tests, the fraction coarser than 20mm shall be rejected and replaced by an equal weight of 5mm to 20mm size material.

The tests shall be performed in accordance with the standard methods given in Table 2-10.

It is further specified that:

(a) for compaction tests when cement is used, compaction shall start within one hour

and be complete within two hours after the start of mixing operations;

(b) for determination of the Unconfined Compression Strength (UCS), the specimens

shall be statically compacted to a predetermined density;

(c) for determination of the CBR, the specimens shall be dynamically compacted with a

4.5kg rammer, the number of blows being governed by the relative compaction

chosen. If it is required to soak the specimen, the mould shall be immersed in water

to allow free access of water to the top and bottom of the specimen. During soaking

the water level in the mould and the soaking tank shall be maintained approximately

25mm above the top of the specimen.

Stone, Aggregates, Sand and Filler

Sampling shall be carried out and the samples shall be prepared in accordance with AASHTO

T2 - Sampling of Aggregates.

Tests on stone, aggregate, sand and filler shall be performed in accordance with the Standard

Methods of Test given in Table 2-2.

Table 2 - 2 Test Procedures Applicable to Stone, Aggregates, Sands and Fillers

57

Description Test Procedure

Unit Weight and Voids in Aggregate ASTM C 29

Potential Reactivity of Aggregates (Chemical Method), ASTM C 289

by Washing AASHTO T11

Organic Impurities in Fine Aggregate AASHTO T21

Sieve Analysis of Fine and Coarse Aggregates AASHTO T27

Specific Gravity and Absorption of Fine Aggregate AASHTO T84

Specific Gravity and Absorption of Coarse Aggregate AASHTO T85

Resistance to Degradation of Small-Size Coarse Aggregate by

Abrasion and Impact in the Los Angeles Machine AASHTO T96

Soundness of Aggregates by Use of Sodium Sulphate or

Freeze/Thaw AASHTO 104-99

Flakiness Index BS 812

Elongation Index BS 812

Chloride Content of Fine Aggregates BS 812

Field Moisture Content Determination “Speedy “Apparatus (AASHTO T 217)

Polished Stone Value BS 812

Average Least Dimension Where required in the Contract, the Average Least Dimension (ALD) of an aggregate shall be determined as follows:

A representative sample of such a size as to give at least 200 aggregate particles of each

fraction to be tested shall be divided out by means of a riffle. The sample shall be passed

through a sieve with an aperture size of half the nominal size of the aggregate to be tested and

the particles passing the sieve shall be discarded. The nominal size of aggregate is defined as

the smallest sieve through which at least 85% of the aggregate will pass.

The smallest dimension of each particle retained on the sieve accurate to 0.1 mm shall be

measured by means of calipers with platens of at least 5 mm diameter (or square). The

measurement and the number of particles tested shall be recorded. The Average Least

Dimension is then calculated as the sum of the smallest dimension of the particles divided by

the number of particles measured.

58

The Quantab Test

The Quantab Test is a field test for determining the chloride content of aggregates.

Apparatus required:

Plastic buckets,

Spring balance capable of reading to 5 kg with an accuracy of ± 10 g,

Plastic drinking cups or similar containers,

Whatman No. 90 filter papers 125 mm diameter,

Quantab chloride titrators Type 1175.

Method:

Weight out 2 kg of the aggregate under test into a bucket.

Add 2 kg of clean chloride free water.

Stir once every minute for 15 minutes.

Take a container of the solution from the bucket and place into it, point downwards a filter

paper folded into a cone.

Insert into the clear liquid within the filter paper a Quantab titrator strip and leave until the yellow bar at the top of the strip has turned completely blue.

Read off from the scale on the strip the level reached at which the strip has turned white (to

first decimal point).

Consult the calibration chart supplied with the test strips and read the percentage NaC1

corresponding to the test strip reading.

Calculation:

If the % NaC1 is X, the amount of C1 ion by weight of aggregate is given by:

C1 ion = 0.61X %

Note: It is important to ensure that the control number on the chart corresponds with the

control number on the bottle of test strips in use.

59

PORTLAND CEMENTS AND CONCRETES

Portland Cement

Portland cement shall be sampled in accordance with AASHTO T127, Sampling Hydraulic

Cement.

Tests on Portland cement or Granulated Blast Furnace Slag for compliance with the above

standard maybe performed by an independent testing laboratory.

Testing in the Site laboratory shall be in accordance with the Standard Methods of Test given

in Table 2-3.

Table 2 - 3 Test Procedures Applicable to Portland Cement

Description: Test Procedure

Compressive Strength of Hydraulic Cement Mortars and Slag

Activity Tests AASHTO T106

Mechanical Mixing of Hydraulic Cement Pastes and Mortars of

Plastic Consistency AASHTO T162

Concrete

Sampling and testing of concrete shall be performed in accordance with the methods given in

Table 2-4. Water to be used in concrete shall be tested in accordance with AASHTO T26.

Table 2 - 4 Test Procedures Applicable to Concrete

Description: Test Procedure

Potential Alkali Reactivity of Cement Aggregate Combinations ASTM C 227

Slump of Hydraulic Cement Concrete AASHTO T119

Weight Per Cubic Foot (or Cubic Meter), Yield, and Air Content

(Gravimetric) of Concrete AASHTO T121

Air Content of Hydraulic Cement Mortar AASHTO T137

Sampling Freshly Mixed Concrete AASHTO T141

Air-Entraining Admixtures for Concrete AASHTO T157

Bleeding of Concrete AASHTO T158

Resistance of Concrete to Rapid Freezing and Thawing AASHTO T161

Evaluation by Freezing and Thawing of Air-Entraining Additions

to Portland Cement AASHTO T188

Air Content of Freshly mixed Concrete By the Volumetric

Method AASHTO T196

Methods of Sampling Fresh Concrete BS 1881 Part 1

Methods of Testing Fresh Concrete BS 1881 Part 2

Methods of Making and Curing Test Specimens BS 1881 Part 3

Methods of Testing Concrete for Strength BS 1881 Part 4

BITUMINOUS MATERIALS

Bituminous Binders

60

Sampling of bitumen and cut-back bitumen shall be carried out in accordance with AASHTO T40, Sampling Bituminous Materials.

Bitumen

The Contractor shall provide the Engineer with manufacturer’s certificates for each delivery of bitumen. Testing of bitumen shall be performed in accordance with the methods given in Table 2-5 below.

Table 2 -5 Test Procedures Applicable to Bitumen

Description: Test Procedures

Solubility of Bituminous Materials AASHTO T44

Flash and Fire Points by Cleveland Open Cup AASHTO T48

Penetration of Bituminous Materials AASHTO T49

Softening Point of Bitumen (Ring-and-Ball

Apparatus) AASHTO T53

Water in Petroleum Products and Bituminous

Materials by Distillation AASHTO T55

Effect of Heat and Air on Asphalt Materials (Thin Film

Oven Test) AASHTO T 179 / AASHTO T 240

Kinematics Viscosity of Asphalts (Bitumen) AASHTO T201

Specific Gravity of Semi-Solid Bituminous Materials AASHTO T228

Determination of the Breaking Point of Solid or Semi-

Solid Bitumen (FRAAS method) DIN 51011 or IP 80

61

Cut-back Bitumen Testing of cut-back bitumen shall be performed in accordance with the methods given in Table 2 –6.

Table 2- 6: Test Procedures Applicable to Cut-Back Bitumen

Description: Test Procedure

Residue of Specified Penetration ASTM D 243

Solubility of Bituminous Materials AASHTO T44

Flash and Fire Points by Cleveland Open Cup AASHTO T48

Penetration of Bituminous Materials AASHTO T49

Ductility of Bituminous Materials AASHTO T51

Water in Petroleum Products and Bituminous Materials by

Distillation AASHTO T55

Distillation of Cut-Back Asphaltic (Bituminous) Products AASHTO T78

Flash Point by Tag Open-Cup Apparatus For Use With Materials

Having a Flash Less than 93.3o C AASHTO T79

Spot Test of Asphaltic Materials AASHTO T102

Effect of Heat and Air on Asphalt Materials (Thin Film Oven Test) AASHTO T 179

Kinematics Viscosity of Asphalts (Bitumens) AASHTO T201

Specific Gravity of Semi-Solid Bituminous Materials AASHTO T228

Determination of the Breaking Point of Solid or Semi-Solid

Bitumen’s (FRAAS method) DIN 51011

Bituminous Mixes

Sampling of bituminous mixtures shall be carried out in accordance with AASHTO T 168,

Sampling Bituminous Paving Mixtures.

Testing of bituminous mixes shall be performed in accordance with the methods given in

Table 2-7.

Table 2-7: Test Procedures Applicable to Bituminous Mixes

Description Test Procedure

Mechanical Analysis of Extracted Aggregate AASHTO T30

Quantitative Extraction of Bitumen from Bituminous Paving Mixtures AASHTO T164

Bulk Specific Gravity of Compacted Bituminous Mixtures Using

Saturated Surface-Dry Specimens AASHTO T166

Sampling Bituminous Paving Mixtures AASHTO T168

Maximum Specific Gravity of Bituminous Paving Mixtures AASHTO T209

Degree of Pavement Compaction of Bituminous-Aggregate Mixtures AASHTO T230

Resistance to Plastic Flow of Bituminous Mixtures Using Marshall

Apparatus AASHTO T245

Percent Air Voids in Compacted Dense and Open Bituminous Paving

Mixtures AASHTO T269

62

Loss of Stability: Alternative Test

As an alternative to ASTM 1075, the Contractor may measure the loss of stability on

immersion in water by measuring the loss of Marshall Stability.

In this case the test procedure shall be modified as follows:

ASTM 1075 7.1.1 Group 1 - Immerse the test specimen in water for 30 – 40 minutes at 60

degrees Celsius +/- 1 degree. Follow the Marshall procedure to

measure the Marshall Stability;

ASTM 1075 7.1.2 Group 2 - Immerse the test specimen in water for 22 – 24 hours at 60

degrees Celsius +/- 1 degree. Follow the Marshall procedure to

measure the Marshall Stability.

REINFORCEMENT STEEL

Reinforcing Steel

Steel for the reinforcement of concrete shall comply with either the AASHTO Standard

Specifications or the British Standards set out in Table 2 - 8.

The Contractor shall supply certified mill test reports for all reinforcement.

Reinforcing steel shall be tested at an independent testing laboratory acceptable to the Engineer for compliance with and in accordance with the applicable specification.

1.1.a.i.1.1 Table 2 - 8 Specifications Applicable To Reinforcing Steel

Description Specification Number

Deformed and Plain Billet-Steel for Concrete Reinforcement

(Metric) AASHTO M 31M

Steel Welded Wire Fabric, Deformed, for Concrete

Reinforcement AASHTO M 221M

Steel Wire, Deformed, for Concrete Reinforcement AASHTO M 225 M

Carbon Steel Bars for the Reinforcement of Concrete BS 4449

Steel Fabric for the Reinforcement of concrete BS 4483

Prestressing Steel

High tensile steel wire strand for the prestressing of concrete shall comply with AASHTO M

203M, Steel Strand, Uncoated Seven-Wire for Priestesses Concrete.

High tensile alloy steel bars for the prestressing of concrete shall comply with AASHTO M

275, Uncoated High-Strength Steel Bar for Prestressing Concrete.

Prestressing steel shall be tested at an independent testing laboratory.

63

PART 2: CONSTRUCTION CONTROL TESTING AND QUALITY ASSURANCE

Construction Control As part of its Quality Control Plan the Contractor shall institute a Quality Assurance (QA) scheme that shall allow for the systematic control of the works. The QA scheme shall allow for ‘signing off’ by the Contractor’s and Engineer’s delegated representatives of each work area.

The QA scheme shall allow for the systematic submission by the Contractor and the consent

of the Engineer of:

all materials to be incorporated in the Works;

earthworks layers (by section);

backfill to culverts and other structures;

pavement layers (by section);

all foundations (prior to blinding concrete);

all placement of in-situ structural concrete.

The scheme shall reference all relevant testing and works shall not be submitted to the Engineer for consent until all relevant tests have been satisfactorily concluded.

Frequency of Testing The frequency of testing shall be in accordance with the guidelines set out below. In case of obtaining variable results or results which are only marginally acceptable, the Engineer will instruct the Contractor to increase the frequency of testing and the contractor shall comply

Earthworks Original Ground

The AASHTO T99 maximum Dry Density and Optimum Moisture Content for existing ground under new embankments shall be determined for each new material encountered and at a frequency of at least once per 1,000 m

2 or once per 100 m along the alignment whichever is the more frequent.

Embankment Construction

The physical properties defined in Section C 500 of the Construction Specification for

earthworks shall be determined at source for each new material encountered and at least once

per 10,000 m3 of earthwork excavated for use as suitable fill or structural backfill.

The field dry density in the permanent works for general earthworks shall be determined at

least once per 1,000 m3 of each layer of compacted material placed.

The field dry density in the permanent works for earthworks within 300mm of subgrade shall

be determined at least once per 750 m2 of each layer of compacted material placed.

The field dry density in the permanent works for structural backfill shall be determined at least once per 100 m

3 of compacted material.

Pavement Materials Granular Materials in Shoulders and Sub base

The physical properties for materials in shoulders and sub base respectively shall be determined at source for each new material encountered.

64

The field dry density in the permanent works shall be determined at least once per 750m2 of

each layer of compacted material.

Crushed Stone Base

Granular sub base material shall consist of crushed rock or stone and shall be clean and free

from dirt, organic matter and other deleterious substances, and shall be of such nature that it

can be compacted readily under watering and rolling to form a firm, stable sub base to the

specified standards.

a) The sub base material shall have a smooth gradation curve.

b) The material shall have a CBR value of at least 30% determined according to

AASHTO T-193, soaked for 4 days and the maximum swell shall be 0.5%. The CBR

value shall be obtained at a density corresponding to ninety five (95) percent of the

maximum dry density, determined according to AASHTO T- 180 Method-D.

c) 50% or more of particles retained on the 4.75mm sieve shall have at least one crushed

face

d) The fraction passing the 0.075mm (no. 200) sieve shall not be greater than two thirds

of the fraction passing the 0.425mm sieve and shall have a Liquid Limit of not greater

than 35. The sub base material shall have a Plasticity Index of 6 or less and a Linear

Shrinkage of 3 or less.

The physical properties shall be determined after crushing, screening, and washing for each

new source of material and at least once per 1000 m3

of material processed.

The field dry density in the permanent works shall be determined at least once per 750 m2 of

each layer of compacted material.

Bituminous Mixes: Aggregates

The physical properties of aggregates shall be determined after crushing, screening, and washing for each new source of material and at least once per 1000 cu m of material processed.

In addition, the grading of aggregates shall be determined at least once per day during mixing.

Mineral Filler

The grading and bulk density in toluene shall be determined once per 100 tones of filler used, or when the source of filler is changed.

Bitumen

Bitumen shall be tested for each new delivery for Penetration and Softening Point, before and after Rolling Thin-film Oven tests. All other tests shall be carried out for each 2500 tones of bitumen delivered.

Bituminous Mixture (from the mixing plant)

The following properties of the bituminous mixture, as appropriate to the type of mix specified, shall be determined every 4 hours from samples taken from the mixing plant, or from the asphalt pavers:

bitumen content,

65

grading,

Marshall stability,

flow,

absorbed water,

voids,

voids at refusal density.

Bituminous Mixture (on cores from the compacted layer)

The following properties of the bituminous mixture shall be determined at least once for every

500 m2 of mix laid from single core samples cut through the compacted layer:

density,

voids in mix.

A minimum of 2 cores shall be cut for any single working day.

The positioning of the cores shall be to a systematic method approved by the Engineer.

Double Layer Surface Dressing

The physical properties of the aggregate chippings shall be determined after crushing,

screening, and washing for each new source of material and at least once per 1000 cu m of

material processed. In addition, the grading of the aggregate chippings shall be determined at

least once per 250 cu m of aggregate chippings used.

Application rates of bituminous binder shall be determined for every 1,000 sq m of a surface

dressing layer and at least once per day by the following two methods:

(i) By measuring the increased weight of a timber board placed on the road surface

during spraying of bituminous binder;

(ii) By recording the tank volume (or weight) before and after each days spraying

operations and comparing this with the total area sprayed.

Application rates of aggregate chippings shall be determined for every 1,000 sq m of a surface

dressing layer and at least once per day by measuring the increased weight of a steel tray

placed on the road surface during spraying of bituminous binder.

Concrete Works Cement

All cement to be used in the Works shall be tested by the Contractor in an independent

laboratory acceptable to the Engineer. The Contractor shall supply a copy of each test

certificate or test result to the Engineer.

The frequency of testing shall be one set of tests for every 200 tones of cement delivered to Site.

66

The Contractor shall keep full records of all data relevant to the manufacture, delivery, testing

and use of all cement used in the Works and shall provide the Engineer with copies thereof. Aggregates: Acceptance Testing

Before casting any concrete, the Contractor shall deliver to the Engineer sample loads of all aggregates that it proposes to use in the Works. Representative samples of each proposed source of aggregate shall be prepared by the Contractor in accordance with AASHTO T2, of minimum mass 50 kg for fine aggregate and 100 kg for coarse aggregate, and forwarded to the Engineer together with such further samples as the Engineer may require. Each sample shall be clearly labelled to show its origin and shall be accompanied by all the information called for in AASHTO T2.

Tests to determine compliance of the aggregates with the requirements of Section C 900 of

the Construction Specification shall be carried out by the Contractor.

Aggregates: Compliance Testing

The Contractor shall carry out routine testing of aggregates for compliance with the

Construction Specification and Project Quality Control Plan.

The tests set out below shall be performed on aggregates from each separate source on the

basis of one set of tests for each day on which aggregates are delivered to Site provided that

no set of tests shall represent more than 250 tonnes of fine aggregates nor more than 500

tonnes of coarse aggregate, and provided also that the aggregates are of uniform quality. If

the aggregate from any source is variable, the frequency of testing shall be increased as

instructed by the Engineer.

(a) Grading AASHTO T27;

(b) Flakiness index BS 812;

(c) Plastic fines AASHTO T176;

(d) Moisture content “Speedy” Apparatus;

(e) Check on organic impurities AASHTO T21.

In addition to the above routine tests, the Contractor shall carry out the following tests at the intervals stated:

(a) moisture content; as frequently as may be required in order to control the water

content of the concrete as required by the Construction Specification;

(b) chloride content: as frequently as may be required to ensure that the proportion of

chlorides in the aggregates does not exceed the limit stated in Section C 900 of the

Construction Specification.

The Contractor shall take account of the fact that when the chloride content is variable it may be necessary to test every load in order to prevent excessive amounts of chloride contaminating the concrete. For this purpose the Contractor may elect to use a rapid field test such as the Quanta test. In the event of disagreement regarding the results of such rapid field tests, the chloride content of the aggregate shall be determined in the laboratory as described in BS 812 (the Volhard test).

Quality Control of Concrete Production Sampling

For each consistence and class of concrete in production at each plant, samples of concrete for

use in the Works shall be taken at the point of mixing or of deposition as required by the

Project Quality Control Plan or as instructed by the Engineer, all in accordance with the

67

sampling procedures described in BS 1881 and with the further requirements set out in these

Construction Specification.

Six 150 mm size cubes shall be made from each sample and shall be cured and tested all in

accordance with BS 1881 Part 3, three at seven days and three at 28 days.

Each sample shall be taken from one batch selected at random and at intervals such that each sample represents not more than 50 m

3 of concrete.

Until compliance with the Construction Specification has been established the frequency of

sampling shall be such that each sample represents not more than 20 m3 of concrete or as

otherwise instructed by the Engineer.

The Contractor shall arrange for the Engineer to be present during the sampling of the concrete and the manufacture, storing and curing of the test cubes. Unfitness test cubes shall be deemed unacceptable for quality control purposes.

Consistence

The slump or compacting factor of the concrete shall be determined for all batches at the

frequency instructed by the Engineer.

The slump of the concrete in any batch shall not differ from the value established by the Site

trial mixes by more than 20 mm or one third of the value, whichever is the greater.

The variation in value of the compacting factor, if used in place of a slump value, shall be

within the following limits:

(a) for a value of 0.9 or more ±0.03;

(b) for a value of between 0.8 and 0.9 ±0.04;

(c) for a value of 0.8 or less ±0.05.

Water/Cement Ratio

The water/cement ratio shall not vary by more than five per cent from the value established during Site trial mixes.

Air Content

The air content of air-entrained concrete in any batch shall be within 1.5 percentage points of the values specified in Table 9 - 5 in Section C 900 of the Construction Specification and the averaged value of four consecutive measurements shall be within 1.0 percentage points of the specified value, expressed as a percentage of the volume of freshly mixed concrete. Testing shall be in accordance with AASHTO T196.

Flakiness Index

If the Flakiness Index of the coarse aggregate should vary by more than five units from the average value of the aggregate used in the approved mix and if the workability of the mixes should be adversely affected by such variation, a new set of Site trial mixes and corresponding tests shall be carried out.

68

Crushing Concrete Cubes

The compressive strength of test cubes shall be determined in accordance with BS 1881 Part

4.

The results of all cube tests shall be shown on an approved form that shall include, but not be limited to, the following information:

(a) the cube reference number,

(b) the cube size and weight,

(c) the date the cube was made,

(d) the grade of concrete from which the cube was made,

(e) the location in the structure at which the concrete sample was taken,

(f) the slump of the concrete,

(g) the date on which the cube was tested,

(h) the total load at failure, and,

(i) the stress in MPa at failure.

Two copies of each test certificate, containing all the information mentioned above, shall be forwarded to the Engineer for his retention and a third copy retained in the Site laboratory.

69

Valid Cube Results

A result is defined as the average 28 day compressive strength from testing a set of three cubes from one batch of concrete. The testing of a set of three cubes shall be deemed valid only if the range in compressive strength of the three cubes tested is less than 15% of their average compressive strength.

Until such time as sufficient valid test results are available to apply the method of control described in Section C 900 of the Construction Specification, the compressive strength of the concrete at 28 days shall be such that no single result is less than the characteristic strength minus 3 MPa and the average value of any three consecutive results shall be greater than the characteristic strength plus 2 Map.

If the average of any three consecutive results is less than the characteristic strength plus 2

Map but at least equal to the characteristic strength, the concrete shall be considered

acceptable but the Contractor shall adjust the mix design and the standard of control.

The 7-day cube result may be used as an early strength indicator, at the discretion of the

Engineer.

Acceptance Criteria for Characteristic Strength Concrete

When valid cube results are available for at least 30 consecutive batches of any class of concrete of the same consistence mixed in any one plant, the mean compressive strength shall be greater or equal to the characteristic strength plus 1.7 times their standard deviation and each individual cube tested shall be greater than 85 per cent of the characteristic strength.

Non-Compliant Test Results

If any one test cube result in a group of three consecutive results is less than 85 per cent of the

characteristic strength but the average of the group of three results of which it is part satisfies

the strength requirements of Section C 900 of the Construction Specification, then only the

batch from which the failed cube was taken shall be deemed not to comply with the

Construction Specification.

If more than one test cube result in a group of three consecutive results is less than 85 per cent of the characteristic strength or if the average strength of the group of three results fails to satisfy the specified strength requirements then all the batches between those represented by the first and last cubes in the group of three results shall be deemed not to comply with the Construction Specification, and the Contractor shall immediately adjust the mix design, subject to the approval of the Engineer, to restore compliance with the Construction Specification. After adjustment of the mix design the Contractor shall again comply with the requirements of Section C 900 of the Construction Specification.

If the mean compressive strength of three test cores is more than 85 % of the characteristic

strength and no single test core has a compressive strength of less than 75 % of the

characteristic strength, the Engineer may, at his discretion, consider leaving the defective

concrete in place.

Records of Concrete Placing

70

Records, in a form agreed by the Engineer, shall be kept by the Contractor of the details of every pour of concrete placed in the Works. These records shall include, but not be limited to:

(a) Class of concrete,

(b) Slump,

(c) Location of pour,

(d) Date of pour,

(e) Ambient temperature and concrete temperature at time of placing,

(f) Moisture contents of aggregates,

(g) Details of mixes,

(h) Batch numbers,

(i) cement batch number,

(j) Ambient temperatures during curing,

(k) Results of all tests undertaken,

(l) Location of test cube sample points, and,

(m) Details of any cores taken.

The Contractor shall supply to the Engineer four copies of these records each week covering

work carried out during the preceding week. In addition he shall supply to the Engineer

monthly histograms of all 28 day cube strengths together with cumulative and monthly

standard deviations and any other information that the Engineer may require concerning the

concrete placed in the Works.

Testing Requirements (Reinforcement)

The Contractor shall obtain reinforcement from an approved manufacturer and shall submit

manufacturer’s test certificates to the Engineer.

The Contractor shall test all reinforcement intended for use in the Works for compliance with

the applicable AASHTO Standard in a laboratory acceptable to the Engineer, and supply two

copies of each test certificate to the Engineer. The frequency of testing shall be as set out in

the appropriate AASHTO Standard.

In addition to the testing requirements described above, the Contractor shall be required to

carry out such additional tests as may be instructed by the Engineer.

The Contractor shall promptly remove from Site any reinforcement that does not comply with

the Construction Specification.

71

Abbreviations

The following abbreviations are used in this Section.

AASHTO American Association of State highway and Transportation Officials

ACV Aggregate Crushing Value

ASTM American Society of Testing and Materials

AIV Aggregate Impact Value

ALD Average Least Dimension

BA Bitumen Affinity

BS British Standard

CBR California Bearing Ratio

DIN Deutche Industrie Norm

FI Flakiness Index

IP Institute of Petroleum

LAA Los Angeles Abrasion Value

LL Liquid Limit

LS Linear Shrinkage

MC Moisture Content

MDD Maximum Dry Density

OMC Optimum Moisture Content

OPC Ordinary Portland Cement

PI Plasticity Index

PL Plastic Limit

PM Plasticity Modulus

SE Sand Equivalent

QA Quality Assurance

SG Specific Gravity

SSS Sodium Soleplate Soundness Test, loss on 5 cycles

STV Standard Tar Viscosity

UC Uniformity Coefficient

UCS Unconfined Compressive Strength

VIM Voids in Mix

VMA Voids in Mineral Aggregates

w/c Water / cement (ratio)

72

SECTION C 300: SETTING OUT AND TOLERANCES

73

PART 1: PAVEMENT CONSTRUCTION

Horizontal Alignement The centerline co-ordinates of the pavement surface as constructed and offsets there from shall be correct within a tolerance of ± 10 mm.

Thickness of Pavement Layers

The average thickness of any pavement layer measured at five points in any length of 100 m

shall not be less than 100% nor more than 120% of the thickness specified. In addition the

thickness of any pavement layer measured at any point shall be not less than 95% nor more

than 125% of the thickness specified.

Surface Layers

The level measured at any point on the surface of a finished pavement layer or formation level

shall not deviate from the corresponding level calculated from the Construction Documents

by more than the tolerances shown in Table 3-1. For verification of compliance with Table 3-1, measurements of surface levels shall be taken at points to be selected by the Engineer at 10 m centers longitudinally and at 1.5 m centers transversely to the road centerline. At junctions the requisite grid point spacing to verify compliance shall be determined by the Engineer.

Description of the pavement projected - Section 6 Drawing

Surface Regularity The surface regularity of a finished pavement layer or formation level shall be tested at points decided by the Engineer with a rigid steel straight-edge, 3 m long, placed parallel or perpendicular to the centerline of the road. The maximum allowable deviation of the surface below the straight-edge shall be as given in Table 3 - 1. In addition the longitudinal slope or transverse cross fall shall not deviate from that shown in the Construction Documents by more than the tolerances shown in Table 3 – 1.

Rectification Areas failing to comply with Clauses 301 to 304 shall be rectified; the minimum such area to be rectified shall be 3 m wide and 30 m long.

74

Table 3 – 1 Surface Tolerances for Formation Level and Pavement Layers

Layer Max. deviation from

surface level

Max. depth below

3 m straight-edge

Max. deviation

from slope or

crossfall

Wearing course ± 6 mm 6 mm ± 0.25%

Asphalt concrete base

course ± 6 mm 6 mm ± 0.25%

Unbound Road Bases +10 mm

- 15 mm 10 mm ± 0.25%

Sub base and shoulders +10 mm to -30 mm 15 mm ± 0.50%

Formation level +10 to -30 mm 20 mm ± 0.50%

75

PART 2: CONCRETE STRUCTURES

Concrete Structures Concrete elements shall be constructed within the tolerances set out in Tables 3-2 and 3-3 in relation to substructure and superstructure respectively.

Table 3 - 2: Tolerances for Concrete Elements for Substructure

Category Tolerance

Variation from specified cross-sectional dimensions + 10 mm, -5 mm

Displacement from specified position in plan 10 mm

Variation from specified level of top surfaces ± 10 mm

Variation from specified level of bearing areas ± 5 mm

Variation from plumb over full height 10 mm

Table 3 - 3 Tolerances for Concrete Elements for Superstructure

Category Tolerance

Variation from specified thickness of slabs, box girder slabs and T-

girder flanges + 10 mm, -5 mm

Variation from specified web thickness + 10 mm, -5 mm

Variation from specified overall depth or width ± 5 mm

Variation from specified overall length and length between bearings ± 10 mm

Allowable deviation of the surface below 3 m straight-edge or

template 5 mm

76

SECTION C 400: SITE CLEARANCE

77

a-Site Clearance

Site clearance is defined as the clearing, grubbing, breaking out, removal, and disposal of all

vegetation, underground obstructions, structures, and debris.

Site clearance shall be carried out only as instructed by the Engineer or as described in the Contract.

Trees or other features immediately adjacent to the road reserve shall be protected.

Voids arising from the removal of underground obstructions shall be backfilled with suitable

material compacted to 95% MDD (AASHTO T99) up to the existing ground level.

B-DESCRIPTION

This Specification section address excavating, ripping, loading, hauling and

spreading in waste areas, of soil material designated by the Engineer as

“Unsuitable” from 3+200 up to 7+200 located un suitable material should remove

30cm from both site wide 25 m and transport in a safe area with advice site

engineer

UNSUITABLE MATERIAL

(a) Material shall be classified as “Unsuitable” in the following cases:

When the material resulting from the excavation made for the construction of the road or structure is declared in writing by the Engineer to be unsuitable for use in the embankment or other work. Such materials will generally include highly organic clays and silts, peat, soil containing large amounts of roots, grass and other vegetable matter, domestic or industrial waste.

When the material resulting from the excavation made for the construction of the road is surplus to the amount required for the construction of the embankment, provided, however, it is not material rendered surplus by reason of the Contractor having opened borrow pits solely for his own convenience as provided under Specification section 03300.

(b) The material proposed for wasting shall not be wasted until approved or directed in writing by the Engineer.

(c) Materials that are soft or unsuitable merely because they are too wet or dry are not to be classified as unsuitable unless otherwise directed by the Engineer.

WORK REQUIREMENTS

(a) Unsuitable material shall be excavated below sub-grade level in cut and below

embankment foundation level to the depth shown on the Drawings or directed by

the Engineer. Where unsuitable material is excavated below the normal sub-grade

level or below embankment foundation or for benching under embankments, the

excavation shall be back filled with material and in a manner in conformance with

the requirements of Specification section 03400 “Embankment Construction”.

78

(b) Unsuitable material shall be removed and disposed of in waste areas provided by

the Contractor in such manner as to present a neat appearance and not to obstruct

drainage to any highway nor to cause injury to highway works or property. If it

becomes necessary for the Contractor to locate or relocate any waste areas, the

Engineer prior to spreading any waste shall approve them.

(c) The relevant provisions of Specification section 01700 “Environmental

Management” shall be adhered to for the hauling and disposal of unsuitable

materials.

(d) Waste areas shall be left in a smooth, neat and drainable condition, as required by

the Engineer, and all waste material shall be placed in such manner that adjacent

property will not be damaged or endangered. Soil slopes shall not be steeper than

2:1, unless otherwise noted on the drawings or as directed by the Engineer.

MEASUREMENT AND PAYMENT

MEASUREMENT

The quantity of Unsuitable Material to be paid for shall be the number of cubic meters

of material acceptably excavated in accordance with Specification requirements and

approved by the Engineer, based on field measurements. The material shall be

measured in the original position in the natural ground after Site Clearing.

Demolition of Bridges and Culverts

The Contractor shall not demolish any bridge or culvert until the Traffic Control measures

prepared in accordance with Section C 100 have been put into operation.

Demolition of bridges and culverts shall include the removal of the superstructure and

complete substructure down to existing ground level or watercourse bed level.

Over excavation shall be reinstated with Class 10/20 concrete or compacted selected granular

fill.

Materials arising from bridge and culvert demolition shall be disposed of in a manner

approved by the Engineer.

Partial demolition shall include the removal of deck components including pre cast concrete

deck beams, concrete footways and up stands, bridge bearings, pedestrian handrails, vehicular

guard-rails, expansion joints, road pavement and other sundry items.

Partial demolition shall be carried out in manner that avoids damage to the remaining parts of

the structure.

The Contractor shall make well the existing ground and banks of watercourses following

demolition works.

Where indicated in the Drawings or the Construction Documents or elsewhere in the Contract,

materials to be retained by the Employer are to be carefully dismantled and set aside for re-

use, or transported to a store designated by the Employer.

79

80

Replacement of Bearings by Jacking Where required in the Contract, the Contractor shall raise bridge decks by jacking to allow replacement of bearings. The jacking shall be carried out from temporary supports which shall be designed by the Contractor to support all relevant loads from and maintain stability of the existing bridge deck. The temporary supports shall remain in place until the replacement bearings have been installed and the bridge deck lowered onto the bearings. The bridge deck shall be jacked in a manner approved by the Engineer. The sequence of jacking operations shall be such as to maintain the integrity of the existing bridge deck. All jacks shall be suitable for their intended purpose and shall have a load capacity adequate to support all relevant loads from the bridge deck. The jacks shall contain a suitable locking mechanism.

Removal of Road Furniture

Where required in the Contract road furniture including traffic signs, vehicular safety barriers,

posts and foundations and the like shall be removed. The resulting voids shall be backfilled

with selected suitable material and compacted.

All debris shall be disposed of. Road furniture shall be retained for re-use when so required or

delivered to a store designated by the Employer, or otherwise disposed of.

The Contractor shall install such temporary replacement signs and barriers that may be required to ensure the safety of the public until such time as permanent replacement road furniture is installed.

Removal of Culvert End Structures

Demolition of an end structure shall include the removal of the structure down to the levels

shown in the Construction Documents or, if not shown, to a depth 200 mm below existing

ground level or watercourse bed level or new invert level, whichever is the lower.

Over excavation shall be filled with grade 10/20 concrete or compacted selected granular fill.

Removal of Abandoned Military Tanks, Military Vehicles and other Vehicles

All abandoned military tanks, military vehicles and other vehicles located within 10 meters of

the edge of the existing carriageway shall be moved to a location at least 25 meters clear of

the Permanent Works, which does not obstruct any vehicular or pedestrian access or surface

water drainage path and does not lie on any cultivated land.

81

Measurement and Payment The units that have been used in this contract associated to the Bill 2 ( Site Clearance ), are

the following

Note : Section 4, The Bill of Quantities described all the measurement method that have to be

taken in order to assign the Payment for every Item in this project

Nº of Item Description Unit

401 General site clearance Ha

402Removal of abandoned military tanks, military vehicles and other

vehicles

No

403 Demolition of existing buildings, structures or other elements cu m

82

SECTION C 500: EARTHWORKS

83

Scope of Section

This Section covers earthworks for new embankment construction. This includes:

excavation of cuttings, including the removal and stockpiling of topsoil,

excavation of side drains and benches,

ground compaction and preparation of the sub grade,

placing and compaction of material for fill in embankments,

excavation and rock fill to swamps,

top soiling and grassing,

Excavation and backfilling at highway structures such as bridges, culverts and walls.

The Section also contains clauses in respect of earthworks for rehabilitation works to existing

carriageways. This includes:

milling / scarifying existing pavement;

preparation of sub grade;

the reinstatement of revetments and batter slopes at existing bridges, including

reinstatement of protection works.

Classification of Materials

Earthworks materials shall be classified as follows.

1. “Topsoil” shall mean the top layer of soil which can support vegetation.

2. “Hard material” shall mean material which cannot be ripped by a track type crawler tractor

rated 250 kW flywheel power or over, or an operating weight of not less than 30 tonnes, using

a single type rock ripper.

The use of explosives will, of itself, not be a sufficient reason for classification of

material as “hard”.

Individual boulders greater than 0.3 cu meters in volume shall be classified as hard

material.

3. “Soft” excavation shall mean all excavation other than that in “hard material”.

4. “Unsuitable material” shall be material not acceptable for embankment construction

and shall include:

material with an organic content greater than 2% when tested accordance with

AASHTO 267,

material from swamps, peat, logs, stumps or perishable material and topsoil,

material with a swell of more than 2.5%,

material containing clays with a Liquid Limit exceeding 45% or Plasticity Index

exceeding 20%, unless otherwise permitted by the Engineer,

materials susceptible to spontaneous combustion,

frozen material which may otherwise be suitable when unfrozen,

84

material with a CBR of less than 4 % measured after a 4-day soak on a laboratory

mix compacted to a dry density of 95 % MDD (AASHTO T180).

5. “Suitable material” shall be material acceptable for embankment construction and is

defined as material other than that classified as unsuitable. Suitable material will

comprise “soft suitable” and “hard suitable”. “Hard suitable” material shall comprise

excavated hard material broken down or otherwise treated to comply with the

Construction Specification for use in embankment construction.

6. “Non frost susceptible material” shall be suitable material with the following

additional properties:

maximum particle size of 63mm;

CBR greater than 6% measured after a 4-day soak on a laboratory mix compacted

to 95% MDD (AASHTO T180);

Plasticity Index of less than 9%;

Liquid Limit of less than 25 %;

Passing 75 μm sieve: less than 10%.

7. “Rock fill” shall mean hard material to the requirements of Clause C 507 placed in

designated areas of the Works.

Excavation of Topsoil

Topsoil shall be excavated prior to other earthworks operations.

Where instructed by the Engineer the Contractor shall, prior to removal of topsoil, excavate

trial holes to a depth sufficient to enable the Engineer to measure the depth of topsoil.

The Contractor shall regularly water topsoil heaps as required to promote the re-establishment

of covering vegetation and prevent loss of topsoil by wind erosion.

Topsoil shall remain the property of the Employer and shall not be run to spoil without approval.

Preparation Prior to Deposition of Fill

Prior to the deposition of fill, existing ground shall be leveled off and compacted to 90%

MDD (AASHTO T180).

Whenever the existing ground is, in the opinion of the Engineer, unsuitable for receiving fill,

the Contractor shall excavate to the depth instructed by the Engineer, remove the unsuitable

material and replace it with suitable material.

85

Construction of Embankments Suitable materials shall be placed in layers and compacted. The maximum depth of layer for the proposed compaction equipment shall be determined from field trials in accordance with Section C 200 of the Construction Specification.

In the absence of field trials, soft suitable material in embankments shall be deposited in

layers not less than 150 mm, or exceeding 200 mm.

Each layer shall extend over the full width of the embankment.

Hard suitable material used for fill shall have a maximum dimension of 350 mm and shall be well graded. The material shall be deposited in horizontal layers not exceeding 400 mm loose depth and shall extend over the full width of the embankment. The material shall be spread and leveled by a crawler tractor weighing not less than 15 tones. After compaction each layer shall, if voids remain, be blinded with smaller rock fragments and granular material so as to fill as many of the voids as possible. The top of the layer shall be blinded with a fine graded material to seal the surface.

During the construction of embankments the Contractor shall control and direct construction

traffic uniformly over the full width

When constructing embankments up to drainage structures and bridges, the Contractor shall

raise the embankment equally on each side of such structure.

Capping Layer

In those zones which are describe in the Volume V drawings, a capping layer will be designed

as a coronation layer over the rest of the embankment

The measurement of imported suitable fill for capping layer shall be the volumes of the

compacted fill, less the volumes of:

(a) the suitable material excavated from within the Site measured in this Section;

(b) Other stated types of imported fill.

The measurement of other stated types of fill shall be to the outlines shown on the Drawings

or ordered by the Engineer. This type of fill is obtained in the cut zones

A CBR superior to 10 is required for this material.

Imported rock fill shall only be separately measured where rock fill as such is specifically

shown on the Drawings or ordered by the Engineer.

Widening of Existing Embankments

Widening of existing embankments shall be carried out using suitable material placed in

layers and compacted. Each layer shall be benched into the existing embankment in

accordance with Clause C 512. The width and maximum depth of each layer shall be suitable

for the compaction plant used and shall be determined from field trails in accordance with

Section C 200 of the Construction Specification.

86

Compaction of Earthworks Soft Material

Each layer of material shall be compacted to a minimum of 95 % MDD (AASHTO T180).

The moisture content of the material shall be brought into the range –2% to +1% of OMC. (AASHTO T180). The Contractor shall provide all water necessary for compaction. The water to be used shall be clean, fresh, and free from all impurities and deleterious substances. Hard Material

Each layer of hard material used, as fill in embankments shall be systematically compacted by

at least 6 passes of a towed vibrating roller weighting not less than 3 tones per meter.

During compaction the surface of the layer shall be watered as necessary to facilitate the

filling of the voids with blinding material.

Sub-formation

Sub-formation is defined as the 0.5 m immediately below the earthworks outline indicated in

the Construction Documents, other than below pavement scarified in accordance with Clause

C 519.

The sub-formation shall be constructed in ‘non frost susceptible material’.

The sub-formation shall be compacted to 98% MDD (AASHTO T188).

In cuttings, where this level of compaction cannot be achieved on the existing soil, it shall be

removed and replaced as necessary.

Geotextile Membrane Where rock fill is placed onto geotextile membrane, the fabric shall be blinded with a cushioning layer.

Where the geotextile membrane is placed around the rock fill the final layer of rock fill shall be blinded with gravel so as to present a smooth surface to receive the geotextile membrane.

Geotextile membrane shall extend at least one meter beyond the toe of the fill.

Structural Excavation

Structural excavation shall mean excavation for the repair or construction of bridges and

culverts.

Structural excavations shall be excavated to the underside of the foundation or to the

underside of blinding layer (if shown). The bottom of the excavation shall be trimmed to

level with all loose and soft material being removed. Voids in hard material below the bottom

of base level shall be filled with Class 10/20 concrete

87

Where in the opinion of the Engineer the material in the bottom of the excavation is for any reason unsuitable, the additional material may be removed, as directed by the Engineer, down to a firm base. The resulting voids shall be filled with Class 10/20 concrete or otherwise as directed.

Structural excavations shall be kept dry at all times.

Structural Backfill The Contractor shall submit to the Engineer his proposals for the compaction of backfill adjacent to structures prior to commencing such work.

Where shown on the Drawings or Construction Documents, structural backfill shall be with

selected granular fill complying with the grading requirements of Table 5-1.

Table 5 -1 Selected Granular Fill

Sieve Size Percent Passing

37.5 mm 100 %

19 mm 70 – 100 %

9.5 mm 45 - 65 %

4.75 mm 30 - 50 %

2.36 mm 15 - 40 %

425 μm 5 - 25 %

75 μm < 5%

Selected granular fill shall also comply with the following:

material passing the 425µm sieve shall have a plasticity index of less than 6;

the water soluble sulphate content shall be less than 2 g of sulphate per litre.

Benching

Where the existing slope is greater than 10%, or elsewhere, where shown on the Construction

Documents, the Contractor shall excavate benches in natural ground or to existing

embankment side slopes. The initial bench at the toe of the fill shall be cut to sufficient

dimensions to permit the operation of placing and compaction equipment. Each subsequent

bench shall be cut as the fill is compacted and built up. The material that is excavated to form

benches shall either be taken to spoil or, if suitable in accordance with this section of the

Construction Specification, the material shall be reused as fill. The maximum bench height

shall be 500 mm or as shown on the Construction Documents.

Preparation of Formation

“Formation” is defined as the top surface of the earthworks outline as shown in Drawings or

Construction Documents overlain by pavement or shoulder construction.

88

Prior to the laying of pavement materials and / or shoulder material any protection layer shall

be removed and any soft or damaged areas shall be rectified. The surface of the formation

shall be trimmed and cleaned free from mud, slurry and loose material.

Trimming of Embankment Slopes

The side slopes of embankments shall be trimmed to uniform batters as shown on the

Construction Documents. Any loose, improperly compacted or oversize material shall be

trimmed back and removed from embankment faces.

Any rock or boulder appearing in the face of an embankment shall be trimmed back to within

the tolerance specified. If any exposed rock or boulder should be unstable, it shall be

completely removed and the resulting void filled with suitable material compacted to the

approval of the Engineer.

Trimming of Existing Cut Slopes

Existing cut slopes shall be trimmed to remove unstable or loose material, where indicated in

the Scope of Works.

Resoiling

Topsoil arising from the Works shall be reused as topsoil to new embankment side slopes or

elsewhere shown on the Drawings or Construction Documents. After placing and spreading,

topsoil shall be renovated and lightly compacted. The Contractor shall water topsoil areas

during summer months to promote plant growth.

Watercourses and Side Drains

Where shown in the Construction Specification, Drawings, or Construction Documents,

existing drains and watercourses shall be cleaned and re-graded. The original channels shall

be cleared of all vegetable growth and obstructions prior to earthworks. Where soft spots

occur below finished invert level the unsuitable material shall be removed and replaced with

suitable fill.

The final invert and slopes shall be trimmed to provide a uniform cross section and

longitudinal profile.

Scarification of Existing Pavement In this clause “Pavement” means bituminous bound surfacing materials only.

“Scarification” means the breaking down of the pavement in place by mechanical means to

dis-aggregate the bound material to particles no larger than 50mm.

The existing pavement shall be saw cut at the limits of scarifying to provide a sound

construction joint with subsequent paving materials.

89

The resulting surface shall be bladed smooth, graded and compacted such that the surface is

tight and free from movement. The surface shall be to the tolerance requirements of formation

level.

The Contractor shall be required to demonstrate the efficacy of its proposed method of

scarification at a field trial. This unit is not defined in the budget , so it could be used

specially in urban areas

Reinstatement of Batter Slopes

Batter slopes shall be reinstated where shown in the Scope of Works and Construction

Documents.

Areas of subsidence and slippage shall be excavated and backfilled in accordance with the

requirements for earthworks as set out in this section of the Construction Specification. The

area reinstated shall be finished to match the profile of the existing slope.

Measurement and Payment The units that have been used in this contract associated to the Bill 3 ( Earthworks ), are the

following

Note : Section 4, The Bill of Quantities described all the measurement method that have to be

taken in order to assign the Payment for every Item in this project

Nº of Item Description Unit

Excavation of Materials

In cross sections, according to drawings cu m

In improvement of profile section cu m

502 Deposition of suitable fill for capping layer ( origin cut zones) cu m

503 Deposition of imported suitable fill for capping layer cu m

504 Deposition and compaction of fill adjacent to structures cu m

505 Re-shaping sand dunes cu m

Disposal of Materials

In cross sections, according to drawings cu m

In improvement of profile section cu m

Deposition of Suitable Fill in Embankments

In cross sections, according to drawings cu m

In improvement of profile section cu m

508 Provisional gravel path sq m

506

507

501

90

SECTION C 600: CULVERTS, DRAINAGE AND PROTECTION WORKS

91

Scope of Section

This section covers:

culverts and drainage structures generally;

installation and repair of concrete culverts;

culvert inlet and outlet works;

carriageway drainage offlets, chutes and the like;

ditching;

drainage protection works.

Concrete works forming part of drainage structures shall be in accordance with Section C 900 of the Construction Specification.

General

All concrete for culverts and drainage structures shall be made with sulphate resisting cement.

The works are described in the Contract generally as precast elements. Cast in place concrete

to an equivalent standard shall be acceptable, subject to the consent of the Engineer. In the

case of highly visible items such as kerb, any proposal to use cast in place methods will be

subject to a trial to demonstrate that an acceptable and aesthetically pleasing visual

appearance is achieved

Cast in place concrete works in drainage structures shall be class B 30/20 unless described

otherwise. Cast in place concrete shall comply with the requirements of Section C 900 of the

Construction Specification. All RCP that is not certified to meet the pertinent AASHTO

designation, or similar, will be covered with a nominal mix concrete at least form the mid-

point up and for 300 mm over the top

Classification of Excavated Materials Earthworks materials shall be classified in accordance with Section C 500 of the Construction Specification.

Excavation for Culverts and Drainage Structures

The Contractor shall make provision for dealing with and maintaining water flows and for

maintaining excavations free from water.

The final excavated surface on which culverts or structures are to be constructed shall be

compacted to a dry density of at least 95% MDD (AASHTO T99) to a depth of 150 mm

below the foundation..

Where ground conditions are such that a satisfactory foundation cannot be achieved, the

Contractor shall remove the unsuitable material to the depth and width instructed by the

Engineer.

Where, in the opinion of the Engineer, the surface of the excavation has become soft or

unsuitable due to the Contractor’s method of working, the Contractor shall at his own cost

remove and replace the unsuitable material with approved granular material or non-structural

concrete as instructed by the Engineer.

92

In hard material, excavations shall allow for a minimum of 50mm Class 10/20 concrete to the

underside of foundation.

Structural Elements Cast Against Excavated Surfaces

Where the Construction Documents show structural elements cast against an excavated

surface, the Contractor shall carry out the excavation neatly to the specified slope and shape.

Over-excavation shall be backfilled with concrete Class 10/20.

Backfilling for Culverts and Drainage Structures

Backfill to culverts and drainage structures shall be with selected granular fill to the

requirements of Table 5-1 (Section C 500).

Backfill shall be compacted to a minimum dry density of 95% MDD (AASHTO T180).

Moisture content shall be adjusted to –2% to +1.5% of OMC (AASHTO T180).

Above ground level the Contractor shall use the same material as that being used for the

adjacent embankment.

Bedding and Laying of Culverts

Pipe bedding material shall be well graded granular material with a maximum stone size of 20

mm and a maximum of 10% by weight passing the 75mm sieve.

Pipe bedding shall be compacted to 95% MDD (AASHTO T180).

Voids shall be formed under the sockets to allow pipe jointing. When the pipe joint has been

completed, the void shall be rammed with pipe bedding material.

Jointing

Culvert joints shall be filled with oakum filler or similar, taped for 25cm each side of the joint

and covered with one layer of bit mastic paint or similar.

Waterproofing

A protective bituminous coating shall be applied to the outside surfaces of the culvert barrel

and other concrete faces in contact with soil.

93

The protective coating shall be one of:

one coat of proprietary bit mastic paint;

one coat of mastic asphalt or similar propriety product;

one coat of brush applied bitumen;

two coats of cut-back bitumen or bitumen emulsion.

Inlet and Outlet Structures

Inlet and outlet structures shall include headwalls, wing walls and apron slabs.

In-situ concrete for drainage structures shall be Class 20/20. The surface finish shall be Class

U1 for unformed surfaces and Class F1 for formed surfaces.

Guiding Dams and Scour Checks

The construction of embankments for guiding dams shall conform to provisions of Section C

500 of the Construction Specification.

Guiding dams shall be formed in selected/suitable fill material compacted to a minimum dry

density of 95% MDD (AASHTO T99).

Concrete for scour checks shall be Class 20/20 complying with the requirements of Section C

900 of the Construction Specification.

River Training and New Watercourses

Excavation for river training shall include site clearance, trimming of slopes, grading of beds

and disposal of the excavated material.

Where watercourses are required to be diverted, the original channels shall be cleared of all

vegetative growth and soft deposits and backfilled and compacted with approved materials.

Riprap

Stone for riprap shall consist of well shaped, hard, dense and durable rock. The minimum weight and dimensions of individual stone pieces shall be as shown in the Construction Documents.

The stones shall be laid with close joints from the bottom of the slope of embankment, or existing ground upward, the larger of the stones being laid at the bottom. The surface shall be hand packed, carefully bedded and tightly wedged with suitable spells to form an even, densely packed surface.

94

Grouted Stone Pitching

Stone for pitching shall be hard and durable and shall exclude mudstones and the like. Stone shall be free from weathering, cracks, and other deleterious imperfections. Stone pitching shall be roughly dressed square. The least dimension of any stone shall not be less than 200 mm, and the weight not less than 10kg. No rounded cobbles or boulders shall be used.

The area to be pitched shall be prepared by excavating, shaping and trimming to

accommodate the stonework and bedding. The area shall be compacted by plate compactor or

equivalent.

Grouted stone pitching shall be placed on a selected granular fill bedding as shown on the Construction Documents.

A trench shall be excavated along the toe of any slope to be pitched or along the unprotected edge of the pitching in the beds of watercourses. Commencing at the bottom of the trench stones shall be laid and firmly bedded into the slope and against adjoining stones. The stones shall be set on edge with their largest dimension at right angles to the slope. The stones shall be securely rammed into the surface to be protected. The stones shall be fitted closely together so as to leave only a minimum of interstices which shall be filled with suitably shaped and tightly wedged spalls. The top of the pitching shall be finished flush with the adjacent material.

Before grout is applied the surfaces of the stones shall be thoroughly cleaned and free from

adhering dirt and clay. Grout, composed of one part cement to three parts sand, shall be

rammed into the wetted interstices between the stones so as to ensure all voids are completely

filled. The grout shall be smoothed off flush with the pitched face and the stones shall be

thoroughly brushed such that their top surfaces are exposed. The grouted stone pitching shall

be cured with wet sacking or other approved method for a period of not less than seven days

after grouting.

Carriageway Drainage Outlets

Carriageway drainage outlets comprise:

drainage outlet channels;

embankments chutes;

toe of slope energy dissipaters.

In-situ concrete shall be Class 15/20.

Bedding shall be well graded granular material to the requirements of Clause C 607. 1.1.a.i.1.1.1.1.1

95

Measurement and Payment The units that have been used in this contract associated to the Bill 4 (Culvert and drainage

works), are the following

Note : Section 4, The Bill of Quantities described all the measurement method that have to be

taken in order to assign the Payment for every Item in this project

Nº of Item Description Unit

Box Culverts

601A Concrete box culverts 1x1 lin m

601B Concrete box culverts 1.5x1 lin m

601C Concrete box culverts 2x2 lin m

601D Concrete box culverts 4x2 lin m

601E Concrete box culverts 6x4 lin m

601F Concrete box culverts 2x(4x2) lin m

601G Concrete box culverts 2x(6x4) lin m

End Structures

602A End structures units to concrete box culverts 1x1 No

602B End structures units to concrete box culverts 1.5x1 No

602C End structures units to concrete box culverts 2x2 No

602D End structures units to concrete box culverts 4x2 No

602E End structures units to concrete box culverts 6x4 No

602F End structures units to concrete box culverts 2x(4x2) No

602G End structures units to concrete box culverts 2x(6x4) No

603 In-situ concrete for repairs to pipes, headwalls, wingwalls and aprons cu m

604 Concrete lined channel ln m

605 Riprap protection works cu m

606 Gabions cu m

607 De-silting of culverts No

96

SECTION C 700: GRANULAR PAVEMENT MATERIALS (SUB-BASE, SHOULDERS AND CRUSHED STONE BASE)

97

Material Requirements

Materials for sub-base and shoulders may be from naturally occurring sands and gravels, or

from crushed rock, crushed slag, or crushed concrete.

Materials for crushed stone base shall be crushed rock, crushed slag, or crushed concrete.

Materials shall be free from deleterious components including organic matter, friable or

weathered materials, clay minerals, plate-like or scaly particles, soft stones, potentially

expansive minerals, chemically unsound materials and soluble salts.

Field Trials

Full-scale laying and compaction trials shall be carried out by the Contractor on all pavement

materials.

The trials shall be carried out in the presence of the Engineer.

Each trial area shall be at least 100 meters long and of the full construction width. Material

shall be placed and compacted to achieve the depth specified. The trial area may form part of

the Works provided that it fully complies with the Construction Specification.

The Contractor shall compact each type of material over the range of comp active efforts

proposed for each pavement layer.

The following data shall be recorded for each level of comp active effort, as appropriate:

1) the composition and grading of the material before the Site trial,

2) the composition and grading of the material after compaction,

3) the moisture content at the time of compaction and the optimum moisture content for

the specified compaction,

4) the type, size, tire pressures, frequency of vibration and the number of passes of the

compaction equipment,

5) the maximum dry density or target density as appropriate measured on a sample before

and at intervals throughout the Site trial,

6) the density achieved,

7) the compacted thickness of the layer.

Where the results of the site trial indicate that the proposed equipment and methods place material in accordance with the Construction Specification, the proposed methods may be incorporated into a formal Method Statement for the consent of the Engineer.

98

Subbase Material shall be processed to give a product with a smooth grading curve within the specified envelope and with the engineering properties specified below.

Table 7 - 1 Gradation Requirements for Subbase Material

Sieve Size Percentage passing

(by mass)

63.0 mm 100%

37.5 mm 85 - 100%

9.5 mm 40 - 70%

4.75 mm 25 - 45%

425 μm 6 - 20%

75 μm 2 – 8%

Sub base shall comply with the following:

Liquid limit: maximum 25%;

Plasticity Index: maximum 6%;

Plasticity Modulus: maximum 60;

CBR at 98% MDD (AASHTO T180) and after a 4-day soak: minimum 30.

Cement Stabilized Sub base

Cement stabilized sub base shall comprise sub base material to Clause C 703 with the

addition of 6% cement (or other percentage stated in the Contract).

Mixing shall be by batching. The period from mixing to deposition and compaction shall not

exceed 3 hours. Moisture shall be added as necessary to achieve 98% MDD (AASHTO

T188).

The Contractor shall demonstrate the efficacy of his mixing and deposition methods by a

Field Trial.

This unit is not defined in the project, but if the contractor considered it necessary , this unit

could be used.

Crushed Stone Base The grading of crushed stone base after placing and compaction shall be a smooth curve within and approximately parallel to the envelope shown in Table 7 - 2.

99

Table 7 - 2 Gradation Requirements for Graded Crushed Stone Base Material

Sieve Size Percentage passing

(by mass)

50.0 mm 100%

37.5 mm 90 - 100%

25.0 mm 80 - 95%

19.0 mm 60 - 80%

9.5 mm 40 - 60%

4.75 mm 25 - 40%

2.00 mm 15 - 30%

425 μm 7 - 19%

75 μm 2 - 8%

Non-plastic angular sand from an approved secondary source may be combined with crushed

materials if the amount of fine aggregate produced during crushing is insufficient.

Crushed stone base shall comply with the following:

Plasticity Index: NIL;

Los Angeles Abrasion Value (AASHTO T96): maximum 30;

Flakiness Index (BS 812): maximum 35.

Crushed stone base material shall be free from any potentially deleterious material such as

significantly weathered igneous rock. In case the material contains any significant fraction

(more than 2%) of mica, the contractor shall be required to demonstrate to the satisfaction of

the Engineer that the methods selected to verify proper compaction are truly representative of

the condition actually obtained in the field.”

After the third bullet point add a fourth stating: “Not less than 90% by weight of the total

particles retained on the 4.75mm sieve shall have at least two crushed faces

100

Shoulders Preparation of Shoulder

In all cases there shall be a requirement to construct a ‘formation’ at the earthworks outline in

the shoulder area.

Depending on site conditions this may involve:

trimming of the existing shoulder to the earthworks outline; or

formation on widened embankment; or

a combination of both.

In the case of widened embankments, the embankment shall be formed to the earthworks

outline and formation prepared at that outline prior to commencing shoulder fills.

In the case of trimming, the existing shoulder shall be cut back to the earthworks outline and

formation prepared at that outline prior to commencing shoulder fills.

Shoulder Fill

Shoulder Fill shall be formed in sub-base material complying with Clause C 702.

Shoulder fill may be placed contiguously with sub base under carriageway.

Granular Shoulder Material

The upper 100mm of shoulder shall be constructed with Granular Shoulder Material.

Granular Shoulder Material shall comply with the grading requirements of Table 7-3 and the

following engineering criteria.

Table 7.3: Gradation Requirements for Granular Shoulder Material

Sieve Size Percentage Passing*

(by mass)

25 mm 100%

9.5 mm 80 – 100%

4.75 mm 60 – 85%

2.36 mm 45 – 70%

425 μm 25 – 45%

75 μm 10 – 25%

*Not less than 10% of the material shall be retained between each pair of successive sieves,

excepting the 20mm and 10mm.

Granular Shoulder Material shall have:

a minimum CBR of 30 at 95% MDD (AASHTO T180) and 4 days soak;

a maximum Liquid Limit of 25;

101

a Plasticity Index of between 4 and 9.

Deposition and Compaction The moisture content during compaction shall be maintained between 1% above and 2% below the Optimum Moisture Content (AASHTO T180).

Granular pavement materials up to 200 mm compacted thicknesses may be spread and

compacted in one layer. Granular pavement materials of compacted thickness greater than

200 mm shall be laid in two or more layers and the minimum compacted thickness of any

such layer shall be 110 mm. for granular sub base and 80 mm. for crushed stone base.

Shoulder fill, and sub base shall be compacted to a minimum of 97 % MDD (AASHTO

T180). Crushed stone base and Granular Shoulder Material shall be compacted to a minimum

of 98 % MDD (AASHTO T180).

On completion of compaction, the surface shall be well closed and free from movement under

compaction plant and from compaction planes, laminations, ridges, cracks, loose or

segregated material, potholes, ruts or other defects.

Pavement operations shall be conducted in such a manner that the works are well drained.

Measurement and Payment The units that have been used in this contract associated to the Bill 5 ( Pavement Works ), are

the following

Note : Section 4 The Bill of Quantities are described all the measurement method that have to

be taken in order to assign the Payment for every Item in this project

Nº of Item Description Unit

Granular Pavament MaterialsCrushed Stone Base ( Macadam )

Base cu m

Hard shoulders and verge cu m

702 Gravel Subbase cu m

703 Imported suitable fill for subgrade cu m

Bituminous Pavement Works

801 Prime coat sq m

802 Tack coat sq m

803 Asphaltic concrete base course cu m

804 Asphaltic concrete wearing course cu m

805 Bitumen for asphaltic concrete tonne

806 DBST (Double Bituminous Surface Treatment) on hard Shoulders sq m

807 Sidewalk sq m

701

102

SECTION C 800: BITUMINOUS PAVEMENT WORKS

103

Scope of Section

This Section covers bituminous works generally.

Part A covers material requirements for asphalted concretes.

Part B covers design requirements for asphalted concretes.

Part C covers asphalted concrete production and laying

Part D covers other bituminous products.

Part E covers repairs to existing bituminous pavements.

104

PART A: MATERIALS FOR ASPHALTIC CONCRETES

Bitumen Bitumen for asphalted concrete shall be Penetration Grade 60/70. Please review this and recommend proper type of bitumen.) Complying with Table 8-1.

Table 8 – 1 Bitumen for Asphaltic Concrete (please revise accordingly)

Unit

Penetration at 25˚C (100 g, 5 s) 60/70 0.1 mm

Softening point (Ring-and-Ball) Min 48 - Max 57 ˚C

Flash point (Cleveland open cup) > 220 ˚C

Frays breaking point < -8 ˚C

Viscosity at 135˚C > 250 centistokes

Solubility in tricolour-ethylene 99 % min

Water content 0,2 Max

1.1.a.i.1.2 Tests on Residue from thin-film oven test

Loss on heating after thin film oven test < 0.5%

Change of Softening Point temperature < 5 ˚C

Loss of penetration at 25˚C (100 g, 5 s) < 50% (% of original)

Bitumen shall be homogeneous, free from water, and shall not foam when heated to 175 ˚C.

Bitumen from different suppliers or sources shall not be combined.

Aggregates for Asphalted Concrete Coarse Aggregate

At least three different sizes of aggregate, plus mineral filler if required, will be mixed in the

asphalt concrete mix plant Coarse aggregate (material retained on a 6.3 mm sieve) shall

consist of crushed angular stone free from, muscovite in excess of 1% by weight” and in the

second paragraph substitute “90%” instead of clay, silt, organic and other deleterious matter.

The minimum size of the stone to be crushed shall be at least 4 times the nominal size of the

aggregate. At least 90% by weight of the total fraction of the blended aggregates in the mix

which are retained on the 4.75mm sieve shall have two or more faces split by the crushing.

The aggregate shall comply with the following requirements:

Los Angeles Abrasion max. 25;

Sodium Sulphate Soundness max. 12;

Water Absorption max 2%;

Flakiness Index max. 25.

Fine Aggregate

105

Fine aggregate (material passing a 6.3 mm sieve) shall consist of crushed stone screenings

produced from stone having a Los Angeles Abrasion value of not more than 30.

Fine aggregates shall be free from, clay, silt, organic and other deleterious matter and shall be

non-plastic.

The Sand Equivalent of the fine aggregate shall not be less than 40.

Subject to the approval of the Engineer, and following production and field trials, the total

aggregates in the mix may contain 5% to 15% by weight of natural sand.

Mineral Filler

Mineral filler shall consist of finely ground particles of limestone, hydrated lime, ordinary

Portland cement or other non-plastic mineral matter approved by the Engineer. It shall be

thoroughly dry and free from lumps. At least 75% by weight of the mineral filler shall pass

the 75 micron sieve and 100% shall pass the 425 micron sieve.

Mineral filler shall have a bulk density in toluene measured in accordance with BS 812 of

between 0.5 g/ml and 0.9 g/ml.

Adhesion Agents The Contractor may, subject to the approval of the Engineer, use adhesion agents.

106

PART B: ASPHALTIC CONCRETE MIX DESIGN

Mix Design Procedure

The Contractor shall be responsible for asphalted concrete mix design shall be conducted

using the actual aggregates produced in at least three different sizes plus mineral filler, if

required for production paving

The mix designs shall be carried out in accordance with the Marshall Test Procedure detailed

in the Asphalt Institute’s Manual No. 2 (MS-2) (6th

edition; 1996), ‘Mix Design Methods for

Asphalt Concrete’, using 75 blows on each face, (referred to hereinafter as the ‘standard

Marshall Design’).

The standard Marshall Design shall be augmented by the ‘Refusal Density Design’ described

in Clause C 806.

The design will establish a Job Mix Formula for each mix required for the Contract.

The Job Mix Formula shall be determined using the following procedure:

laboratory testing in accordance with the Marshall Test Procedure;

full scale production trials using the Contractor’s production equipment over the range

of binder contents used in the laboratory design procedure;

field trials to determine the adequacy of the Contractor’s compaction equipment.

On completion of the above process, the Contractor shall submit a Job Mix Formula to the Engineer.

A Job Mix Formula shall be defined by:

(a) a single percentage of aggregate passing each required sieve size,

(b) a single percentage of bitumen to be added to the aggregate,

(c) a temperature range within which the mixture is to be mixed,

(d) a recommended temperature range for compaction of the mixture.

(e) proportions of the different aggregate sizes and mineral filler, if required, to be

mixed in the plant

The Engineer shall give consent to the use of the proposed Job Mix Formula or shall reject the

proposal with reasons for its rejection.

The Contractor shall use only the approved standard mix formula for the production of each

bituminous mixture. No modifications to a standard mix or changes in the nature or source of

the constituent materials shall be made without a written submission by the Contractor to the

Engineer and his subsequent consent.

If a standard mix formula proves unsatisfactory, a new standard mix formula together with

supporting test data shall be submitted by the Contractor for review and approval by the

Engineer prior to production.

107

Refusal Density Design

Additional test samples, in sets of three, shall be prepared at three binder contents:

(a) that corresponding to 5% Voids in Mix (VIM);

(b) 0.5% above (a);

(c) 0.5% below (a).

These sample sets shall then be compacted to ‘refusal’. ‘Refusal’ is defined as 300 blows on

each face of a Marshall specimen at the temperature defined in MS-2.

A graph of VIM at the refusal density shall be plotted against binder content.

The binder content that corresponds to VIM of 3 per cent, shall be determined. This value

shall be obtained by interpolation and not by extrapolation. Further samples shall be made

and tested in order to comply with this condition.

The Job Mix binder content shall be based on consideration of the various Marshall Design

parameters and the value at 3% VIM at ‘refusal’. If a VIM of 3% at refusal can not be

attained using the proposed grading, the mix shall be re-designed with an alternative grading.

Grading Requirements

The grading of the mixture of coarse and fine aggregate shall be within and approximately

parallel to the grading envelopes given in Table 8-2. The grading of the mix shall not pass

through the “Restricted Zone Boundary” as defined in “Super pave Mix Design1 ”.

Table 8-2: Grading Requirements of Aggregate for Asphalted Concrete

Sieve Size

Mm

Percentage by Mass Passing

Base Course Wearing Course

25 mm 100 % -

19 mm 84 – 95 % 100 %

12.5 mm 60 – 77 % 75 – 88 %

9.5 mm 50 – 68 % 62 – 79 %

4.75 mm 32 – 53 % 39 – 60 %

2 mm 20 – 41 % 26 – 47 %

9 – 21 % 10 – 25 %

5 – 10 % 5 – 12 %

It will be permitted to deviate from the above envelopes in order to comply with the

requirements of Clause C 806.

1 Published by the Asphalt Institute (SP-20, 1996).

108

Physical Properties

Asphalted concrete shall comply with Table 8-3.

Table 8-3: Physical Properties for Asphalted Concrete

Base Course Wearing Course

Marshall Stability 75 blows (N) Min 8000 Min 7000

Flow Value (mm) 3 – 5 3 – 5

Voids in total mix (VIM)(%) 3 – 5 3 – 5

Voids in mix at refusal density (%) 2 - 3 2- 3

Voids in Mineral Aggregate (VMA)

(%) 13 - 15 14 – 16

% voids filled with bitumen (VFB) 65 - 78 65 – 78

Water sensitivity (ASTM 1075) Loss

of stability on immersion in water

Min. 75% retained

strength

Min. 75% retained

strength

Where the asphalt mix does not meet the requirements in Table 8-3 above for the Water

Sensitivity Test (ASTM 1075), the Contractor shall propose the use of a suitable adhesion

agent such as Portland cement, hydrated lime or other proprietary agent for the Engineer’s

approval. The beneficial properties of the proposed agent when incorporated in the mix and

the percentage of agent to be added to the mix shall be demonstrated by further test results.

Full Scale Production Trials

Following completion of the laboratory Marshall Design Procedure, augmented by the

Refusal Design, the Contractor shall undertake full scale production trials.

These trials shall involve a repetition of the Marshall Design Procedure and the Refusal

Density Procedure using material produced from the Contractor’s proposed asphalt mixing

plant.

The purpose of the production trials is to validate the laboratory mix design for the actual

production process.

Field Trials The Contractor shall carry out full-scale laying and compaction trials on all proposed asphalt mixes. The trials shall be carried out, under supervision of the Engineer and at a location approved by the Engineer. Each trial area shall be at least 50m long, and to the full construction width and depth for the material.

The Contractor shall compact each section of the trial area over the range of compactive effort it proposes. The following data shall be recorded for each level of compactive effort:

(a) the composition and grading of the material including the bitumen content,

(b) the temperature of the bitumen and aggregate immediately prior to entering the mixer, and

the temperature of the mix on discharge from the mixer, on commencement of laying, on

commencement of compaction and on completion of compaction,

109

(c) the type, size, mass, width of roll, number of wheels, wheel-load, tyre pressures,

frequency of vibration and the number of passes of the compaction equipment, as

appropriate for each roller type,

(d) the density and voids achieved,

(e) the compacted thickness of the layer

(f) pavement riding quality,

(g) Pavement level tolerances.

Site trials shall determine the minimum number, type and condition of rollers required to

compact the mixture to the specified density and pavement tolerances.

The Contractor shall, in the presence of the Engineer, carry out tests on at least eight cores

from each trial section.

The field trial shall be considered successful if:

the results of the tests on the cores satisfy the requirements for Field Density

Requirements of Clause C 815; and

the surface after compaction complies with the requirements of Clause C 817, and

the pavement tolerance complies with the requirements of Section C 300 of the

Construction Specification.

On completion of a successful field trial the Contractor shall submit, for the Engineer’s

consent, a proposed Job Mix Formula and a proposed surfacing Method Statement..

The Engineer shall give consent to the Formula and Method Statement, or reject both or

either, giving reasons for their rejection.

110

PART C: ASPHALTIC CONCRETE PRODUCTION

Storage of Bitumen

The maximum continuous storage temperature for bitumen over a 24 hour period shall not

exceed 125oC.

Bitumen tanks shall be capable of maintaining their contents at the specified temperature

within a tolerance of ±5oC, and shall be equipped with thermostatic control to prevent the

temperature rising above 170oC.

Bitumen tanks shall have fixed thermometers able to be read from outside the tanks.

Mixing The Contractor shall mix bituminous materials in a mixing plant complying with AASHTO M156. The mixing plant may be either the batch-mix type or the continuous-mix type and shall be capable of regulating the composition of the mixture to within the tolerances detailed in Table 8-4. In case the contractor elects to use a continuous mix-type plant, the contractor shall propose for the Engineer’s approval, and then implement when approved, a rigorous program of sampling and testing the gradation of the various sizes of aggregate produced by taking samples directly off the crusher/screening plant discharge belts as well as from the various stockpiles for each size of aggregate

Bins shall be covered to prevent ingress of moisture. Mixing plants shall be fitted with

adequate filters to prevent dust pollution.

Bitumen and aggregate shall be mixed within the range 140˚C to 170˚C. Bitumen shall not be

heated above 180 ˚C.

Acceptability criteria for mix composition are detailed in Table 8-4.

Table 8-4 Acceptability Criteria for Asphalted Concrete Mixes

Tolerance relative to Job Mix Formula

Bitumen Content ± 0.2% by total weight of total mix

Passing 10 mm sieve and larger sieves ± 6% by total weight of dry aggregate including

mineral filler

Passing sieves between 10 mm and 1 mm sieves ± 4% by total weight of dry aggregate including

mineral filler

Passing sieves between 1 mm and 75 m sieves ± 3% by total weight of dry aggregate including

mineral filler

Passing 75 m sieve ± 2% by total weight of dry aggregate including

mineral filler

111

Preparation of Surfaces

Immediately before placing asphalted concrete, the Contractor shall clean the existing surface

of all loose material and foreign matter and make good any defects.

All crushed stone base course shall be prime coated prior to the laying of binder course. Primed surfaces shall be cured.

All binder courses shall be tack coated prior to laying wearing course.

Transportation and Deposition Ambient Weather Conditions

Asphalted concrete shall be placed only when either of Case 1 or Case 2 conditions shown

below are met.

Ambient air

temperature

Road surface

temperature Wind velocity

Case 1 > 5 deg C > 10 deg C < 14m/sec

Case 2 > 0 deg C > 0 deg C < 5 m/sec

Notwithstanding these provisions, the Contractor shall not carry out asphaltic concrete work

in otherwise adverse weather conditions.

Transportation and Deposition

Base course shall be placed using guide wires and joint matching ski and electronic sensors.

Subject to achieving the specified grades on the base course surface, the wearing course shall

be placed by setting the pavers to run constant depth and manual operation to avoid an

undulating surface.

The width of the paving and the fleet of hauling equipment shall be such that a constant and

reasonable rate of forward movement of the pavers can be maintained, non-stop throughout

each daily shift given the output of the mixing plant

Asphalted concrete shall be kept free of contamination during transportation. Each load shall be covered. Transportation vehicles shall be cleaned after each trip. Tipper bodies shall be lightly oiled to prevent adhesion.

Asphalted concretes shall be placed only by purpose built self-propelled asphalt paver

equipped with automatic controls.

Compaction shall be carried out in accordance with the procedures determined from the Field

Trials. The minimum temperature of asphalt concrete at the commencement of compaction

shall be 125oC and the minimum temperature at completion of compaction shall be 80

oC.

112

The final surface shall be uniformly textured free from segregation, tearing, tracking or other

surface irregularities and within the tolerances specified in Section C 300 of the Construction

Specification.

Compaction equipment shall not be parked on asphaltic concrete surfaces which are less than

48 hours old.

Field Density Requirements

Field densities of asphaltic concrete shall be verified by taking cores in accordance with

Section C 200 of the Construction Specification.

Cores shall be cut through the full thickness of the layer.

The average field density shall be determined daily from core densities.

The daily average field density shall be not less than 98 % of the average density of Marshall

specimens compacted from that day’s mix (the ‘Field Marshall Density’).

Not more than 1 in any 10 consecutive core densities shall be less than 97% of the Field

Marshall Density and not more than 1 in any 10 consecutive core densities shall be more than

102% of the Field Marshall Density.

Areas of asphaltic concrete where the standard of compaction specified above has not been

achieved shall be identified and further cores taken and tested.

Where the Field Density Requirements are not met the material shall be replaced.

Joints

Transverse joints shall be cut in a straight line across the previous face to expose the full

depth of the course. The vertical face so formed shall be heated with a propane joint heater

and painted lightly with hot bitumen.

The above treatment shall be required at longitudinal joints where these are exposed for more

than 24 hours. Otherwise, cold longitudinal joints should be avoided either by full-width

paving if the mixing plant has sufficient capacity to sustain fast enough forward motion by a

full-width paver to achieve good rideability, or by operating two pavers in tandem with a

slight stagger and properly hand-raking the joint to obtain a well-filled and barely visible

joint.

113

PART D: OTHER BITUMINOUS MATERIALS

Double Layer Surface Dressing

General

Double layer surface dressing shall consist of an initial application of bituminous binder to the

road surface followed immediately by a layer of uniformly graded aggregate chippings. A

second application of bituminous binder is again applied which is followed immediately by a

second layer of uniformly graded chippings.

Bituminous Binder

The bituminous binder shall be Penetration Grade 80 / 100 (please amend as according to C

802.) complying with Table 8-6.

Table 8 – 6 Bituminous Binder for Double Layer Surface Dressing

Unit

Penetration at 25˚C (100 g, 5 s) 80 / 100 0.1 mm

Softening point (Ring-and-Ball) > 47 ˚C

Flash point (Cleveland open cup) > 220 ˚C

Frass breaking point < -20 ˚C

Viscosity at 135˚C > 250 centistokes

Solubility in trichloro-ethylene 99 % min

Water content Nil

1.1.a.i.1.3 Tests on Residue from thin-film oven test

Loss on heating after thin film oven test < 0.5%

Change of Softening Point temperature < 5 ˚C

Loss of penetration at 25˚C (100 g, 5 s) < 50% (% of original)

Bituminous binder shall be homogeneous, free from water, and shall not foam when heated to

175 ˚C.

Bituminous binders from different suppliers or sources shall not be combined.

Other grades of cut back bituminous binder may be used with the agreement of the Engineer,

subject to satisfactory field trials.

The penetration grade bitumen can be cut back with kerosene to suit road surface

temperatures at the time of spraying as detailed in Table 8-7.

114

(ii) Table 8-7 Kerosene Volume for Cut Back Bitumen

Range of Road Surface

Temperatures oC

Maximum Addition of Kerosene

by Volume %

Range (approximately) of

corresponding ambient air

temperatures oC

16 – 24 7 10 – 16

24 – 32 5 16 – 21

32 – 40 3 21 – 26

40 – 48 1 26 – 31

The bituminous binder shall be heated in boilers or bulk storage containers equipped with

adequate pumps and accurate thermometers. No bitumen shall be heated in a boiler when the

thermometer is broken or inaccurate.

The minimum pumping temperatures, range of spraying temperatures and the maximum

heating temperatures of cut backs and penetration grade bitumen are given below in Table 8-

8.

Table 8-8 Pumping, Spraying and Maximum Heating Temperatures of Penetration

Grade and Cut Back Bitumen

Binder

Temperature o C

Minimum Pumping Spraying

Maximum Heating Slot Jets Atomising Jets

Penetration Grade

80 / 100 115 160 – 170 170 - 180 180

Cut Back MC 800 60 100 – 115 120 - 135 135

Cut Back MC 3000 80 125 – 135 135 - 150 150

Aggregate Chippings

Aggregate chippings shall consist of crushed angular stone free from, clay, silt, organic and

other deleterious matter.

Deleterious matter includes materials with potentially deleterious properties such as

muscovite in excess of 1%”. The minimum size of the stone to be crushed shall be at least 4

times the both nominal sizes of chippings of the aggregate. At least 90% by weight of the

coarse aggregate shall have two or more faces split by the crushing.

The aggregate chippings shall comply with the following requirements:

Los Angeles Abrasion max. 25;

Sodium Sulphate Soundness max. 12;

Water Absorption max 2%;

Flakiness Index max. 20.

115

The polished stone value of aggregate chippings when determined in accordance with BS 812

shall not be less than 55 unless otherwise approved by the Engineer.

The grading of aggregate chippings shall be within the grading envelopes shown in Table 8-9

below.

Table 8-9 Grading Requirements for Aggregate Chippings

Sieve Size

(mm)

Percentage by Mass Passing

First Layer Second Layer

19 mm - -

13.2 mm 100 % -

9.5 mm 85 – 100 % 100 %

6.3 mm 0 – 25 % 80 – 100 %

4.75 mm 0 – 7 % 0 – 30 %

2.36 mm - 0 – 4 %

0.5 mm 0 – 0.5 % 0 – 0.5 %

Rates of Application of Bituminous Binder and Aggregate Chippings

The approximate rates of application of bituminous binder and aggregate chippings shall be as

given below:

(i) application of first layer of bituminous binder 1.0 liter / square metre

(ii) application of first layer of aggregate chippings 1.5 cubic meter / 100

square metres

(iii) application of second application of bituminous binder 1.0 liter / square metre

(iv) application of second layer of aggregate chippings 1.0 cubic metre / 100 square

metres

The rates of application of bituminous binder and aggregate chippings shall be fixed during

site trials so as to achieve:

(i) adequate coverage and adhesion of chippings without bleeding for the bituminous

binder

(ii) tight uniform packing of aggregate chippings without excessive traffic whip off.

Construction

(i) Weather Limitations

116

The temperature at the road surface shall not be less than 10o C when bituminous

binder is sprayed.

No bituminous binder shall be applied during rain, fog or during a strong wind.

The existing road surface shall be dry prior to applying bituminous binder.

(ii) Preparation of Surface

Immediately before applying bituminous binder, the existing road surface shall be

cleaned of all loose material and foreign matter with mechanical brooms or

compressed air. The debris shall be deposited well clear of the surface to be covered.

Any defect in the surface shall be made good as instructed by the Engineer and no

bituminous binder shall be applied until the surface has been approved by the

Engineer.

Kerb, channels guardrails bridge parapets and any other structures that may be soiled

by the bituminous binders during spraying shall be covered with suitable plastic

sheeting during spraying operations.

(iii) Bitumen Distributors

All bituminous binder shall be applied with a truck mounted bitumen distributor that is

capable of spraying the binder uniformly over the width of the spray bar. The

distributor tank shall have a minimum capacity of 4,000 litres and shall be fitted with a

device for indicating the quantity in the tank at any time. It shall be fitted with heaters

capable of maintaining temperatures up to 200 o C and an accurate thermometer. The

circulation system shall be capable of pumping around the tank and around the spray

bar without actually spraying. Spray bars shall be available for spraying in widths

varying from 1 metre to 4 metres and shall be adjusted transversally so that the

operator can follow the required edge independently. The spray nozzles shall be

arranged to give a uniform spray and the shut off shall be quick acting with an anti-

drip device. The pressure in the spray bar shall be sufficient to give a good uniform

distribution and spaying of the binder.

Distributors shall be checked and calibrated during the site trials, before starting work

and when required by the Engineer.

No bituminous binder is to be applied with a hand spray lance.

(iv) Mechanical Aggregate Chipping Spreaders

Mechanical chipping spreaders shall be capable of spreading the chippings uniformly

over variable widths from 0.5 to 4.0 metres, at the rates fixed in the site trials.

117

Chipping spreaders shall be checked and calibrated during the site trials, before

starting any work and when required by the Engineer.

Hand application of aggregate chippings shall not be permitted.

(v) Application of Surface Dressing

The spraying width shall normally be one lane so that construction traffic may run on

the other lane.

Immediately after the bituminous binder has been sprayed, clean dry aggregate

chippings shall be uniformly applied at the rate fixed in the site trials by the use of as

many mechanical aggregate chipping spreaders as necessary to match the rate of

spraying. The elapsed time between spraying of bituminous binder and spreading of

aggregate chippings shall in no case exceed one minute.

Chipping spreaders shall be operated in such a manner that the bituminous binder shall

be covered with aggregate chippings before the wheels of the chipping spreader or

truck pass over the binder.

Should it become apparent that the supply of aggregate chippings is about to fail, the

bituminous binder spraying shall be immediately stopped and shall not resume until an

adequate supply is assured.

(v) Compaction

The main compaction shall be carried out with self propelled pneumatic tyred rollers

or rubber covered steel drum rollers. Pneumatic tyred rollers shall have smooth tyres

and their pressure shall be more than 0.4 Mpa.

Compaction shall commence immediately after the aggregate chippings have been

spread and in no case later than two minutes after application of the bituminous

binder. Compaction shall continue until all chippings are firmly embedded into the

binder. The number of passes of each roller shall be fixed in the site trials, but usually

at least 6 passes shall be made.

Steel wheeled rollers shall not be used for surface dressing.

The number and output of rollers shall be sufficient to ensure that compaction does not

lag behind the spraying and chipping application operations.

Compaction shall be carried out in such a manner as to ensure that no crushing of the

aggregate chippings takes place.

Additional compaction on a previously completed section shall be given later by a

pneumatic tyred roller if required by the Engineer.

118

(vi) Traffic Control and Finishing

Each layer of the surface dressing shall not be opened to traffic until the bituminous

binder has set sufficiently to retain the aggregate chippings. The Contractor shall erect

temporary restriction signs, barriers, removable bumps or other speed control devices

as agreed with the Engineer to prevent vehicles traveling too fast over the newly laid

surface dressing to ensure that excessive aggregate chippings do not become

dislodged.

After traffic has been permitted to run on a surface dressing layer for a period of at

least two days, and when required by the Engineer, all loose aggregate chippings shall

be swept and taken way. Windrows of loose aggregate chippings shall not be

permitted to acc umulate at the sides of the road.

(vii) Tolerances

The final average overall width of the surface dressing measured at six equidistant

points over a length of 100 metres shall be at least equal to the required width. At no

point shall the distance between the centre line of the road and the edge of the

surfacing be less than 20 mm of that required.

The rates of application of bituminous binder along and across each lane shall not vary

by more than plus or minus 10% of the rates fixed in the site trials and for each length

of lane sprayed in a single pass, the average rate of binder application shall not be less

than the fixed rate.

The average rate of application of aggregate chippings along and across the lane width

for each single pass of the spreader shall not vary by more than plus or minus 10% of

the rate fixed in the site trials.

Cut-back Bitumen

Rapid curing cut-back bitumen shall comply with all the requirements of AASHTO Standard

Specification M 81, Cut-Back Asphalt (Rapid-Curing Type).

Medium-curing cut-back bitumen shall comply with all the requirements of AASHTO

Standard Specification M 82, Cut-Back Asphalt (Medium-Curing Type).

Bitumen Emulsion

Bitumen emulsions shall comply with all the requirements of the following AASHTO

Standard Specifications:

M 140: Emulsified Asphalt,

M 208, Cationic Emulsified Asphalt, and

R 5, Standard Recommended Practice for Selection and Use of Emulsified Asphalts.

Prime Coat

119

Prime coat shall be MC 30 cutback bitumen.

The rate of application shall be determined from field trials and shall be such as to satisfy the

following requirements:

the depth of penetration shall be between 3mm and 10mm after 24 hours;

the minimum rate of application shall be 0.8 litres / sq metre.

Material treated with prime coat shall not be trafficked for 24 hours after application.

120

Tack Coat

Tack coat shall be either:

(a) a dilute bitumen emulsion, applied at sufficient time before laying the bituminous

layer to allow the emulsion to break and the water to run off or evaporate, spread to

give not less than 0.2 litres / sq metre residual bitumen.

Application of Prime Coat and Tack Coat

The Contractor shall thoroughly clean surfaces by compressed air or other approved means to

remove all loose material. Defects shall be made good.

Depending on site conditions, prior to the application of prime coat, surfaces of crushed stone road base may be lightly and evenly sprayed with water.

Prime and tack coats shall be sprayed from a constant pressure, or other approved, distributor.

Hand spraying shall be permitted only in small areas or to make good defective areas.

During spraying all kerb, road furniture, culvert headwalls and the like shall be protected.

MC30 cut back shall not be heated above 65˚C and shall be sprayed at a temperature between

40˚C and 60˚C depending on the type of equipment and ambient temperatures.

Tack coated base course shall be covered by surface course within 12 hours of application.

121

PART E: PAVEMENT REPAIRS

Patching

This work consists of repairs to an existing bituminous surface showing local discontinuous

damage in the form of pot-holes, ravelling, transverse and longitudinal cracking, crocodile

cracking, loss of edge support, local deformation or layer de-lamination. The main objetive

of this project is to construct a new road, so all the pavement will be designed despite this

unit will be able to be used when deteriorations of the pavement take place during the

construction of the same one

Classification

Patching work shall be classified into the following categories:

Type 1 Patching

Removal of damaged bituminous surfacing for a depth of up to 75 mm below the surface and

reconstruction in bituminous materials.

Type 2 Patching

Removal of the damaged bituminous surfacing and base layers for a depth of up to 250 mm

below the surface, and their replacement with corresponding layers of crushed stone base and

asphaltic concrete base and wearing courses.

Type 3 Patching

Removal of the damaged bituminous surfacing, base and subbase layers for a depth of up to

600 mm below the surface, and their replacement with corresponding layers of subbase,

crushed stone base, and asphaltic concrete base and wearing courses.

Prior to pavement works the exposed formation shall be re-compacted and prepared in

accordance with the Construction Specification for earthworks sub-formation and formation.

(iii) Work procedures

Areas of pavement requiring different the types of patching shall be identified and demarcated

by the Contractor in traffic-resistant paint.

Patching activities shall be carried out according to a programme and in accordance with

safety procedures agreed in advance on a weekly basis with the Engineer. Patching at any

particular time shall not occupy more than one traffic lane, if no diversion road is provided.

The marked pavement areas shall be excavated in accordance with their size and the type of

patching instructed. The excavated areas shall be regular in shape, having perpendicular sides

and vertical edges. Consecutive layers shall be stepped back by 150 mm on all sides. The

bottom of any excavated area shall have the same cross-fall as that of the finished surface.

The excavated area shall be cleaned out by air jetting.

122

Reinstatement shall be as applicable for each pavement layer and material type. Before

placing asphalt the base and the sides of the excavation shall be treated with prime coat.

Crack Sealing

(iv) Classification

Sealing shall be classified as:

1. Sealing cracks up to 10 mm wide;

2. Patching cracks greater than 10 mm wide.

(v) Sealing cracks up to 10 mm wide

Crack sealing activities shall be carried out in accordance with safety procedures agreed in

advance on a weekly basis with the Engineer. Crack sealing at any particular time shall not

occupy more than one traffic lane, if no diversion road is provided.

The Contractor shall, in sections generally of about 1 km in length, identify and demarcate the

extent of cracks in the existing bituminous pavement. Individual cracks shall be denoted by

prominent marks (20 mm x 50 mm) across the crack ends, and at 5 m intervals where the

crack is longer than 10 m, in traffic-resistant paint.

The Contractor shall submit fully marked sections to the Engineer for his approval prior to

commencing crack sealing operations.

Prior to sealing, the Contractor shall ensure that cracks are clean of all dirt, dust, vegetation,

other loose materials by using wire brushes, mechanical brooms and high-pressure pneumatic

jetting. The cracks shall be dried by blowing with hot oil free compressed air.

After cracks have been thoroughly cleaned and dried they shall be sealed with a medium

curing cut-back bitumen MC 250 or MC 800 heated to a temperature of 80 - 100 degrees

Celsius. A spray lance blowing hot oil free compressed air may be used to introduce bitumen

into the crack. Fine sand and cement dust may be mixed with the cutback bitumen, to the

extent that the flow of bitumen into the crack remains unimpeded.

When cracks are fully sealed, a blinding layer of coarse sand shall be applied before the

bitumen cools.

123

(vi) Patching cracks greater than 10 mm wide

The Contractor shall identify, demarcate the extent of and denote cracks greater than 10 mm

wide in the existing bituminous pavement as indicated above.

The existing asphalt pavement material shall be removed to a minimum width of 200 mm

along the line of the crack using powered pavement cutting or cold milling equipment.

The resulting void shall be dried by blowing with hot oil free compressed air.

The trimmed and cleaned void shall be painted at the bottom and sides using hot cut-back

bitumen MC 250 or MC 800. The void shall then be patched with asphaltic concrete wearing

course material.

Regulating

The Contractor shall identify and visibly delineate on the existing pavement surface all areas

to be regulated.

Regulating shall be in asphaltic concrete wearing course material.

Measurement and Payment The units that have been used in this contract associated to the Bill ( Preliminaries ), are the

following

Note : In the Section 4, The Bill of Quantities are described all the measurement method that

have to be taken in order to assign the Payment for every used Item in this project

Nº of Item Description Unit

901 Cast-in-place concrete cu m

902 Bridges sq m

903 Replacement concrete cu m

124

SECTION C 900: CONCRETE WORKS

125

Scope of Section

This section covers:

material requirements for concrete mixes,

design of concrete mixes,

mixing, transport, placing, compaction and curing of concrete,

reinforcement,

falsework and formwork.

Part A covers material requirements.

Part B covers design requirements.

Part C covers concrete production and placing.

Part D covers falsework and formwork.

Part E covers reinforcing steel.

Part F covers piling.

Part G covers miscellaneous matters.

Definitions

In this Section, concrete means any cement bound concrete which is used in reinforced, pre-

stressed or non-reinforced concrete construction.

Structural concrete shall generally be load bearing and shall be described by its Class

reference detailed in Clause C 905.

Non-structural (or blinding) concrete means cement bound concrete Class 10/20.

AASHTO Standards

The Construction Specification in relation to Portland cement concretes refer generally to

AASHTO standards and relate primarily to concrete cast in place.

Structural elements pre-cast off site shall comply with standards set out in the Construction

Documents.

Structural elements pre-cast on site shall comply either with the Construction Specification in

relation to cast in place concrete or, in the alternative, standards set out in the Construction

Documents.

Concrete cast in place shall comply with the requirements of this Section C 900.

The Contractor shall detail in its Construction Documents, Quality Control Plan and its

Method Statements the Standards to which pre-cast elements are being constructed.

126

PART A: MATERIALS FOR CONCRETE

Cement

Cement shall be either:

Ordinary Portland Cement (OPC) complying with AASHTO M85 Type 1A, or

Sulphate Resisting Cement (SRC) complying with AASHTO M85 Type 1A, or

as required in the Contract.

Granulated blast furnace slag for use with OPC shall comply with AASHTO M 302.

Cement shall be free flowing and free of lumps. It shall be supplied in the manufacturer's

sealed bags or in bulk from a certified supplier.

All cement for any one structure shall be from the same source.

Fine Aggregate

Fine aggregate shall be clean hard and durable and shall be natural sand, crushed gravel sand

or crushed rock sand complying with AASHTO M6. All the material shall pass through the

9.5 mm sieve and the grading shall be within and approximately parallel to the grading

envelopes in Table 9 - 1. In order to achieve an acceptable grading, it may be necessary to

blend materials from more than one source.

The fine aggregate shall not contain iron pyrites, iron oxides, ” add “mica (less than 1%

muscovite and 6% total mica), shale, laminar, soft or porous materials or organic matter.

Table 9 -1 Grading Requirements for Fine Aggregate

Sieve Size Percent passing by mass

Non-structural concrete

Percent passing by mass

Structural concrete

9.5 mm 100 % 100 %

4.75 mm 95 - 100 % 95 - 100 %

1.18 mm 45 - 80 % 45 - 80 %

300 μm 10 - 30 % 5 – 30 %

150 μm 2 – 10 % 0 – 10 %

The amount of fine aggregate retained between any pair of successive sieves shall not exceed

45 %.

Other properties of fine aggregate shall be:

the fineness modulus shall be between 2.3 and 3.1,

the content passing the 75 mm sieve shall not exceed 3 per cent for natural or crushed

gravel sand,

127

the chloride content when tested with a Quantab chloride titrator shall not exceed 0.01

per cent by weight for prestressed concrete or 0.03 for other classes of concrete,

the soundness of aggregates by the use of sodium sulphate shall be less than 12%,

the aggregate shall be non-reactive when tested in accordance with ASTM C 289 for

alkali silica reaction.

Coarse Aggregate

Coarse aggregate shall be clean hard and durable crushed rock, crushed gravel or natural

gravel complying with the requirements of AASHTO M 80. The material shall not contain

any iron pyrites, iron oxides, flaky or laminated material, coal or other soft or porous material,

or organic matter.

The shape of the coarse aggregate shall be angular, rounded or irregular with a flakiness index

of less than 30%.

The maximum nominal size of coarse aggregate shall be 20 mm for prestressed and structural

concrete and 40 mm for non-structural concrete.

Grading of nominal sized coarse aggregate shall be within and approximately parallel to the

grading envelopes in Table 9 - 2.

Table 9 -2 Grading Requirements for Coarse Aggregate for Portland Cement Concrete

Sieve Size

Percentage passing by mass

Nominal Size

Nominal Size

Nominal Size

10 mm 20 mm 40 mm

50 mm - - 100 %

37.5 mm - - 95 - 100 %

25.0 mm - 100 % 65 - 85 %

19.0 mm - 90 - 100 % 35 - 70 %

12.5 mm 100 % 55 - 80 % 25 - 50 %

9.5 mm 85 - 100 % 20 - 55 % 10 - 30 %

4.75 mm 10 - 30 % 0 - 10 % 0 - 5 %

2.36 mm 0 -10 % 0 - 5%

1.18 mm 0 - 5%

For 20mm and 40mm nominal size aggregates, the amount of coarse aggregate retained

between any pair of successive sieves shall not exceed 45 %.

Other properties of course aggregate shall be:

the proportion of clay, silt and other impurities passing a 75 mm sieve shall be not

more than one per cent by weight;

the chloride content shall not exceed 0.05 per cent by weight when tested with a

Quantab chloride titrator;

the soundness of aggregates by the use of sodium sulphate shall be less than 12%;

128

the aggregate shall be non-reactive when tested in accordance with ASTM C 289 for

alkali silica reaction;

the aggregate shall have a water absorption of less than 2.5 per cent when tested in

accordance with AASHTO T85;

the aggregate shall have a Los Angeles Abrasion (LAA) in accordance with AASHTO

T96 of less than 35%.

Water

Water for mixing or curing concrete shall be clean and free from harmful matter and shall

have a pH value between 6 and 8. Water shall be tested in accordance with AASHTO T26.

Water with the following properties shall not be used for mixing or curing concrete:

1) saline or brackish water,

2) containing more than 500 mg/l chloride ion,

3) containing more than 1000 mg/l sulphate ion,

4) containing more than 1000 mg/l alkali carbonates and bicarbonates,

5) containing more than 2000 mg/l total dissolved solids,

6) contaminated with oil, sugar, organic matter or other deleterious material.

Admixtures

Air-entraining agents shall be used to increase the durability of concrete subject to frost action

unless otherwise directed by the Engineer.

The Contractor shall submit to the Engineer full details of any admixture, including air entraining agents, he proposes to use.

Chemical admixtures used in concrete shall comply with the requirements of AASHTO

M194. Air-entraining admixtures shall comply with AASHTO M154. The Contractor shall

have all proposed air-entraining admixtures tested at a laboratory acceptable to the Engineer.

The effects of a proposed air entraining agent shall be tested by the Contractor in trial mixes

produced in the plant which he proposes to use for the Permanent Works.

Workability agents shall not have any adverse effect on the properties of the concrete.

The chloride ion content of any admixture shall not exceed 2 per cent by weight of the

admixture nor 0.03 per cent by weight of the cement in the mix.

Calcium chloride or admixtures containing calcium chloride shall not be used. Admixtures

shall not be mixed together.

Pozzolanic and Fly Ash admixtures

The use of pozzolanic admixtures, whether as a separate material or incorporated in the

cement before delivery to Site, may be permitted with the provision that the proportion of

pozzolanic material used shall not exceed 50 percent by weight of the cement in the mix,

except in the case of ground iron blast furnace slag, in which case the proportion shall be

129

subject to the agreement of the Engineer. When ground iron blast furnace slag is blended

with cement the mixture shall comply with AASHTO M240. Fly ash shall have a carbon content not exceeding seven percent by weight. The maximum sulphate content expressed as SO3 shall be 2.0 percent by weight. The fineness shall be in accordance with that Specified in Table 2 of AASHTO M295. Fly ash shall only be used in conjunction with cement complying with ASTM C150 and the total sulphate content of the mix from all sources, expressed as SO3 shall not exceed four percent of the weight of cement.

Reinforcement

All reinforcing bars shall be high yield stress deformed.

Reinforcement shall comply with either of the following British Standards or AASHTO

Specifications:

BS 4449 Carbon Steel Bars for the Reinforcement of Concrete;

BS 4482 Cold Reduced Steel Wire for the Reinforcement of Concrete;

BS 4483 Steel Fabric for the Reinforcement of Concrete;

AASHTO M 31 M Deformed and Plain Billet-Steel Bars [Metric];

AASHTO M 221 M Steel Welded Wire Fabric, Deformed for Concrete Reinforcement;

AASHTO M 225 M Steel wire, Deformed for Concrete Reinforcement.

130

PART B: DESIGN OF CONCRETE MIXES

Classes of Concrete

The classes of concrete shall be those designated in Table 9-3 below.

Table 9 - 3 Concrete Classes and Strengths

Concrete Class

Characteristic

Cube Strength at

28 days

Maximum

Nominal Size of

Aggregate

Maximum

water/cement

ratio

Target Mean

Strength

at 28 days

MPa Mm B MPa

10/20

(non structural) 10 20 0.45 None

20/20 20 20 0.45 28.5

25/20 25 20 0.42 33.5

30/20 30 20 0.43 38.5

30/10 30 10 0.43 38.5

40/20 40 20 0.40 48.5

40/10 40 10 0.40 48.5

Design of Concrete Mixes

The Contractor shall design mixes for all structural concrete. Design Parameters

The design parameters are:

the aggregate portion shall be well graded from the nominal maximum size of stone

down to the 150 m size;

the cement content shall be such as to achieve the target strengths called for in Table 9

– 3;

the minimum cement content shall be as shown in Table 9-4;

workability shall be consistent with ease of placing and proper compaction;

air-entraining agents shall be added to the Concrete in sufficient quantity to produce

the air contents set out in Table 9 – 5;

the water/cement ratio shall be the minimum consistent with adequate workability but

in any case not greater than that shown in Table 9 – 3;

the length change of hardened concrete determined in accordance with AASHTO

T160 shall not be greater than 0.05 per cent;

the total chloride content, expressed as chloride ion, arising from all constituents in a

mix including cement, water and admixtures shall not exceed the following limits,

expressed as a percentage of the weight of cement in the mix:

(a) for prestressed concrete, steam cured concrete or concrete containing sulphate

resisting cement: 0.05 per cent by weight,

(b) for any other reinforced concrete: 0.3 per cent in 95 per cent of all test results

provided no result is more than 0.5 per cent;

131

The total sulphate content, expressed as SO3, of all the ingredients in a mix including

cement, water and admixtures shall not exceed 2.0% by weight of the aggregate or

4.0% of the weight of cement in the mix, whichever is the lesser.

Table 9 - 4 Minimum Cement Content for Durability and Low Permeability

Type of structure Minimum Cement Content (in kg/m3

of compacted concrete)

Thin sections, bridge decks, reinforced piles 435

Moderate sections, retaining walls, beams,

piers 420

Table 9 - 5 Air Content for Frost Resistance

Nominal maximum size of aggregate Entrained air content

40 mm 5.5 %

20 mm 6.0 %

10 mm 7.5 %

Proposed Mix Design

Before commencing placement of concrete in the Permanent Works, the Contractor shall

supply the Engineer with concrete mix designs for each proposed class of concrete together

with relevant test results.

The proposed concrete mix designs shall include:

(a) the cement type,

(b) the cement content in kg/m3,

(c) the sizes and grading of aggregates,

(d) the weights, in the saturated surface-dry condition, of aggregates in kg/m3,

(e) the water content in kg/m3, which shall be taken to mean the mixing water, the water

in any admixtures and any water in the aggregates in excess of the saturated surface-

dry condition,

(f) the design slump, measured in accordance with AASHTO T119,

(g) the manufacturer of the air-entraining agent and the required dose per cu m,

(h) the limits for air content,

(i) the manufacturers of any plasticisers, dispersing agents or other proposed admixtures

and their required doses per m3.

132

Site Trial Mixes

As part of the design process, the Contractor shall prepare Site trial mixes.

For each Site trial mix of concrete the Contractor shall prepare three separate batches of

concrete using the mixing plant proposed for the execution of the Works. The volumes of

each batch shall be the capacity of the concrete mixer proposed for full production.

Samples shall be taken from each batch and the following tests carried out:

(a) the slump of the concrete shall be determined in accordance with AASHTO T119,

(b) from each batch six test cubes shall be cast, cured and tested in accordance with BS

1881,

(c) three cubes from each batch shall be tested for compressive strength at seven days and

the remaining three at twenty eight days,

(d) the density of all the cubes shall be determined before the strength tests are carried

out,

(e) the length change of hardened concrete shall be determined in accordance with

AASHTO T160 shall not be greater than 0.05 per cent.

The compacting factor apparatus may be used in place of a slump cone. In this case the

correlation between slump and compacting factor shall be established during preparation of

the trail mixes.

The average strength of the nine cubes tested at 28 days shall be not less than the applicable target mean strength shown in Table 9 - 3 and no single cube shall have a strength of less than 3 MPa lower than the applicable characteristic strength shown in Table 9 - 3.

Method Statement: Consent of Engineer

Following completion of successful site trials, the Contractor shall formally submit Method

Statements to the Engineer detailing the mix design(s) and the proposed working methods.

The Method Statement shall indicate procedures for adjusting added water to compensate for

the variability of aggregate moisture.

The Engineer shall give consent to the Method Statement and mix design(s) and or shall give

reasons for their rejection.

Structural Concrete shall not be used in the works without the formal consent of the Engineer

to the mix design. Structural Concrete which does not conform to a mix design shall not be

used in the Works.

133

PART C: MANUFACTURE AND PLACING

Mixing

Concrete shall not be mixed by hand.

Cement and aggregates shall be batched by weight. Water may be measured by weight or

volume. Liquid admixtures shall be dispensed by an electrically controlled flowmeter.

The weights of cement, water, admixtures and of each size of aggregate as indicated by the

mechanisms employed shall be within the tolerance shown in Table 9 - 6.

Table 9 - 6 Allowable Tolerances in the Proportioning of Concrete Mixes

Allowable tolerance in

proportioning: Percentage by weight

Mass of cement 0 % to +4 %

Mass of fine aggregate -2 % to +2 %

Mass of coarse aggregate -2 % to +2 %

Admixtures -2 % to +3 %

Water -1 % to +1 %

All concrete batching equipment shall be calibrated prior to use.

The water to be added to the mix shall be adjusted to allow for the amount of free water

contained in the coarse and fine aggregates.

Transportation of Concrete

Concrete shall be transported in purpose built vehicles. During transportation the concrete

shall be protected from any adverse effects of sun, rain and wind.

The time elapsing between mixing and placing a batch of concrete shall, not exceed 60 minutes, provided that this period may be exceeded by the use of retarding agents, subject to the consent of the Engineer.

Concrete shall not be incorporated in the Works after the onset of initial set has occurred.

Placing of Concrete

The Contractor shall prepare a Method Statement for all concrete placement detailing:

equipment and methods to be used for placing,

preliminary treatment of surfaces,

compaction methods.

The following constraints on placing shall apply:

134

the maximum height of free fall shall be restricted to 1.5m;

the formation of feather edges shall be avoided;

concrete shall be placed continuously between construction or expansion joints;

the delivery rate, placing sequence and methods shall be such that formation of cold

joints is precluded;

the dimensions and sequence of pours shall be such that cracking of the concrete due

to thermal or shrinkage is eliminated;

concrete shall be protected from the environment (Clause C 915 refers);

compaction shall be in accordance with Clause C 916.

The Contractor shall ensure that shuttering joiners and steel fixers are in attendance during all

concreting operations. They shall be responsible for ensuring that the formwork is maintained

in accordance with the Construction Specification, temporary construction joints are inserted

as necessary, and steel reinforcement and fittings are maintained in place as placing proceeds.

Protection of Concrete from the Environment General

The Contractor shall take all necessary precautions to protect concrete from damage due to climatic or other environmental conditions during placing and curing.

The temperature of the concrete immediately before placing shall be between 10˚C and 32˚C.

The maximum temperature of concrete for placement in bridge decks shall be 27˚C. Hot Weather Working

When ambient temperatures are above 32˚C, formwork, steel reinforcement, and other

surfaces that will come into contact with the fresh concrete shall be cooled by means of water

sprays or other approved methods.

All fresh concrete surfaces shall be protected from evaporation or be continuously wet-cured

with a fine mist spray. Cold Weather Working

If concrete is to be placed when, sub-zero ambient temperatures are likely the Contractor shall

make provision for heating water and aggregates.

Concrete shall not be placed without heating and protection from freezing if either:

(a) the ambient air temperature is falling and has fallen below 7˚C;

(b) the ambient air temperature is rising and is below 3˚C.

When the ambient air temperature is below 5˚C, the temperature of the concrete at the time of

placement in sections less than 300 mm thick shall be not less than 15˚C.

Irrespective of air temperature, aggregates shall be free of ice, frost and frozen lumps when

batched and concrete shall not be placed against any material whose temperature is 0 ˚C or

less.

135

Aggregates may be heated to a temperature of between 20˚C and 65˚C and water shall be

heated to a temperature of between 55˚C and 65˚C. The temperature of the mixed concrete

shall be between 15˚C and 32˚C when placed in the formwork.

The newly placed concrete shall be protected against freezing for 8 full days after the

completion of the pour. Limitation of Temperature Differentials

The development of temperature differentials in placed concrete shall be inhibited by one or

other the following means, depending on ambient conditions and the exposure of the placed

concrete:

limiting concrete temperatures at placing;

the insulation of exposed concrete surfaces;

the use of insulated formwork left in place;

shielding exposed surfaces from the wind;

avoiding the use of ponding or sprayed water when such use would cause rapid

cooling of the surface.

The above requirements shall be taken into account in determining appropriate curing

methods.

Compaction of Concrete

Concrete shall be fully compacted throughout the full extent of the placed material. Concrete

shall be thoroughly worked against the formwork and around any reinforcement and other

embedded items, without displacing them.

Concrete shall generally be compacted with the assistance of mechanical poker (immersion)

vibrators. The Contractor may, use supplementary beam vibrators for the compaction of slabs

and bridge decks.

Non structural concrete may be compacted manually by the use of screeding boards or other

means, subject to satisfactory site trials and subject to the consent of the Engineer.

Curing of Concrete

All newly placed concrete shall be cured so as to prevent loss of water. Curing can be by one

of the following methods:

retaining formwork in position;

liquid membrane curing compound;

accelerated curing by steam treatment.

Curing methods shall be included in the Contractor’s Method Statement for concreting.

In addition, the Contractor shall provide sunshades and/or windshields to prevent excessive

drying of the concrete surface. If the surface of the concrete begins to dry before the selected

cure method can be applied, the surface of the concrete shall be kept moist by a fog spray.

136

Curing shall be continued for as long as may be necessary to prevent loss of moisture and

shrinkage, and in any case, for not less than the periods stated in Table 9-8.

Table 9 - 8 Minimum Curing Periods

Cement type

Average ambient

temperature greater

than 15oC

Average ambient

temperature 5oC to

15oC

Average ambient

temperature less than

5oC

Portland Cement with

less than 10% added

pozzolans

7 days 10 days 14 days

Portland Cement with

more than 10% added

pozzolans

10 days 15 days 20 days

The curing method shall comply with the requirements in respect of limiting temperature

differentials described in Clause C 915.

Construction Joints

Construction joints shall be so arranged as to reduce to a minimum the effects of shrinkage in

the concrete after placing, and shall be placed in the most advantageous positions with regard

to stresses in the structures and the desirability of staggering joints.

The intersections of horizontal or near horizontal joints and exposed faces of concrete shall

appear as straight lines produced by use of a guide strip fixed to the formwork.

Surface aggregates shall be exposed either by brushing with a stiff bristled brush or by scabbling and / or sand blasting as necessary.

Fresh concrete cast against the exposed aggregate surface. Where directed, a mortar grout

shall be applied immediately prior to placing fresh concrete.

No concrete shall be placed in position or against a construction joint until the joint has been

inspected and approved by the Engineer.

Where a joint is to be formed to prevent bonding between contiguous structural elements, the Contractor shall place two intermediate layers of approved waterproof building paper at the location specified.

137

Finishes on Unformed Surfaces All concrete shall be levelled to the tolerance stated in Table 9-9, as appropriate, to produce a uniform plain or ridged surface, surplus concrete being struck off by a straight edge immediately after compaction.

Where a floated finish is indicated in the Construction Documents, concrete shall be floated

with a wooden or cork surfaced hand or power float such as to produce a uniform surface free

from screed marks and to the appropriate tolerance of Table 9-9.

Where a power float finish is indicated in the Construction Documents, the surface shall be

floated as above, but to the tolerances stated in Table 9-9. When the moisture film has

disappeared and the concrete has hardened sufficiently to prevent laitance from being worked

to the surface, it shall be power floated to produce a dense, smooth uniform surface free from

trowel marks.

Table 9 - 9 Allowable Tolerances of Unformed Concrete Surfaces

Class of finish

Maximum gap between the

surface and a 3 m straight edge

or correctly shaped template

placed on the surface.

Maximum difference in level or

position from the correct level or

position

Unspecified 10 mm + 10 mm or - 10 mm

Floated finish 5 mm + 10 mm or - 10 mm

Power float finish 5 mm + 5 mm or - 5 mm

Finishes on Formed Surfaces

This finish shall be a smooth even concrete surface free of honeycombing, fins, projections,

bulges, offsets, streaks, surface discoloration or other surface imperfections.

Cavities or holes shall be filled carefully and to their full depth, with a cement-sand grout of the same quality and mix as that used in the surrounding concrete but with the fraction remaining on the 2.36 mm sieve discarded. Patched areas shall be rubbed flush with the surrounding surface after the cement grout has hardened.

Honeycombed concrete shall be removed and replaced in accordance with Clause C 937.

Where the overall finish is not of a uniform standard, the concrete shall be given a ‘rubbed’

finish as described below.

1. After grout for pointing has set the entire surface shall be thoroughly brushed with

clean water. The surface shall be rubbed with a power operated stone to bring the

surface to a paste. Rubbing shall be continued sufficiently to remove all formwork

marks, projections and other surface irregularities to produce a smooth dense surface

free from blemishes or other imperfections.

2. Material which has been ground to a paste during rubbing shall be spread uniformly

over the entire surface and allowed to take a set. The final finish shall be obtained

through a second rubbing with a fine carborundum stone that shall continue until the

entire surface is of a smooth even texture and a uniform colour.

138

3. After the final rubbing has been completed and the surface has dried it shall be rubbed

with burlap to remove loose powder. The final surface shall be free from unsound

patches, paste, powder and objectionable marks. Under no circ umstances shall a

cement wash or plaster be applied.

139

PART D: FORMWORK and FALSEWORK

General Obligations

The Contractor shall include in the Construction Documents design calculations and working

drawings showing details of the proposed formwork and falsework.

The structural design of formwork shall conform to ACI Standard, “Recommended Practice for Concrete Formwork,” (ACI 347) or some other internationally recognised standard acceptable to the Engineer.

The design calculations shall be undertaken and certified by a qualified structural engineer.

The calculations shall take into consideration the sequence and rate of concrete placing and

the equipment proposed for placing, compacting and finishing the concrete.

Falsework The design assumptions as to foundation support shall be stated in the design submission. The design submissions shall be verified by appropriate ground investigation and soils testing.

The Contractor shall make necessary allowances for dead load deflection and any other

deformations caused by the placing of concrete.

For cast-in-place concrete structures, the calculated deflection of falsework flexural members

shall not exceed 1/240 of their span.

Formwork

Formwork shall be of an approved construction surfaced with wood, steel or other approved

sheet material. The inner surfaces of the forms shall produce a smooth surface of uniform

texture and colour.

Where a plywood surface is shown in the Construction Documents or otherwise required by the Contract, formwork shall be faced with plywood complying with BS 1088 Plywood for Marine Craft or equivalent.

Joints in formwork for exposed faces shall be evenly spaced horizontally and vertically and

shall be continuous or form a regular pattern. The same type of formwork surfacing material

shall be used throughout each element of a structure.

All formwork surfaces that are to make contact with the concrete shall be thoroughly cleaned

and treated with an approved chemical or wax emulsion release agent before the reinforcing

steel is placed. Neat mineral oils and water soluble emulsions shall not be used. The

Contractor shall construct trial panels to demonstrate the suitability of any release agents

proposed.

Metal ties or anchorages within the forms shall be so constructed as to permit their removal to

a depth of at least 60 mm from the face without injury to the concrete. The cavities shall be

filled with cement mortar and the surface left sound in accordance with Section C 900 of the

Construction Specification.

140

Supports for formwork may be bolted to previously placed concrete. If metal ties through the concrete should be used in conjunction with bolts, the metal left in place shall not be closer than 60 mm from the face of the concrete.

The internal and external angles on concrete surfaces shall be formed to a chamfer utilising 20

mm x 20 mm hardwood timber fillets of new material. New 25 mm square hardwood timber

shall be incorporated in the formwork to form a clean, level horizontal joint on exposed

concrete surfaces at the top of each lift unless otherwise agreed with the Engineer.

Removal of Formwork The minimum periods which shall elapse between completion of placing concrete and the removal of formwork and falsework are given in Table 9 – 10.

Table 9 - 10 Minimum Period Before Striking Formwork

Average ambient temperature

Formwork type Minimum period before striking

> 25 oC 20 oC 15 oC 10 oC 5 oC <0 oC

Vertical formwork to columns,

walls and large beams 9 hours 10 hours 12 hours 15 hours 20 hours 30 hours

Soffit formwork to slabs 3 days 3 days 4 days 5 days 7 days 10 days

Soffit formwork to beams and

props to slabs 7 days 8 days 10 days 13 days 17 days 25 days

Props to beams 10 days 12 days 14 days 18 days 24 days 36 days

Alternatively, formwork and falsework may be removed when the concrete has attained the

strength set out in Table 9 - 11, provided that the attained strength is determined from test

cubes cured under the same conditions as the concrete to which they refer.

Table 9 - 11 Minimum Concrete Cube Crushing Strengths to be Attained Before Striking Formwork

Type of formwork / falsework

Percentage of characteristic 28 day

compressive cube strength to be

attained before striking formwork

Vertical formwork to columns, walls and large beams 30 %

Soffit formwork to slabs 35 %

Soffit formwork to beams and props to slabs 40 %

Props to beams 50 %

As soon as formwork has been removed, bolt holes in concrete faces that are not required for subsequent operations shall be completely filled with mortar and made good in accordance with Clause C 920.

141

PART E: REINFORCEMENT

Bar Bending Schedules The Contractor shall include bar bending schedules in the Construction Documents. Bar bending schedules shall include the following information:

bar location and placing details;

reference mark;

grade of steel;

size designation;

number of bars;

length of bars;

shape code of bars.

Fixing Reinforcing steel shall be supported in its proper position by use of mortar blocks, wire bar supports, supplementary bars or other approved devices.

All intersecting bars shall be tied together with annealed galvanised iron wire of not less than

1.25 mm diameter with the ends of the tying wire turned back into the main body of the

concrete.

Mortar blocks shall have a compressive strength of not less than that of the concrete in which

they are to be embedded. The face of blocks in contact with forms for exposed surfaces shall

not exceed 50 mm by 50 mm in size and shall have a colour and texture that will match the

concrete surface. Mortar blocks shall have an embedded annealed galvanised iron wire of

diameter 1.25 mm for securing the block to the reinforcement. An alternative type of spacer

block may be used subject to the approval of the Engineer.

Splicing

All reinforcement shall be fabricated in the full length indicated on the plans unless otherwise

permitted. Except where shown in the Construction Documents, splicing of bars shall be

subject to the approval of the Engineer. Splices shall be staggered as far as possible.

Lapped splices shall be of the lengths shown in the Construction Documents. If not

dimensioned in the Construction Documents, the length of lapped splices shall be in

accordance with Division I, Clause 8.32 of AASHTO Standard Specifications for Highway

Bridges.

Welding shall conform to the Structural Welding Code, Reinforcing Steel, AWS D1.4 of the

American Welding Society and applicable special provisions.

Mechanical couplings shall develop both in tension and compression at least 125% of the specific yield strength of the bar, two field splices out of each 100, or portion thereof, placed in the work, shall be selected by the Engineer, removed by the Contractor and tested to 125% of the specified yield strength.

Sheets of welded mesh reinforcement shall be spliced by a lap of one and a half times the

spacing of the mesh with all ends and edges securely tied.

142

Substitution by Bars of Different Sizes Substitution of the reinforcement indicated in the Construction Documents with reinforcement of different sizes or yield strengths will be permitted at the discretion of the Engineer. The product of the area and yield strength of the substituted bars shall be not less than that of the bars indicated in the Construction Documents.

Cover Where not indicated on the Construction Documents, the minimum cover to reinforcement in in-situ reinforced concrete shall be 60mm in piles, pile caps and foundations constructed with sulphate resisting cement and 50mm elsewhere.

143

PART F: PILING

General

Piling shall comply with the applicable recommendations of BS 8004.

Concrete, reinforcement and any pre-casting operations shall comply with the relevant clauses

of this Section C 900.

Piles shall be installed within the following maximum permitted tolerances:

Position: 75mm in either direction at cut-off level;

Verticality: 1 in 75 deviations from the vertical;

Rake: 1 in 25 deviations from the specified rake.

The Contractor shall include in the Construction Documents a programmed of its proposed

sequence and timing for casting or driving piles.

A piling record shall be kept by the Contractor, and a signed copy of the record of the work

done each day shall be given to the Engineer on a daily basis while piling is in progress. On

completion of piling the Contractor shall deliver to the Engineer a schedule recording the final

toe levels of all piles.

Pile Tests Test piles shall be working piles selected by the Engineer for load testing. Piles shall be tested by the Constant Rate of Penetration Method. Working piles shall not be used as reaction piles without the approval of the Engineer.

Load measuring devices shall be calibrated before and after each series of tests, whenever adjustments or replacements are made to the devices or at the intervals recommended by the manufacturer of the equipment. Pressure gauges and hydraulic jacks shall be calibrated together. Certificates of calibration shall be supplied to the Engineer for acceptance. The calibration shall be carried out at a testing house acceptable to the Engineer.

The Constant Rate of Penetration Method

The rate of loading shall be such that a constant rate of movement is maintained throughout

the test.

The rate of movement of the pile shall be agreed with the Engineer before the start of the test.

Each increment of test load shall be measured within an accuracy of 2%, and movements shall

be measured within an accuracy of 0.25mm.

Readings of load, movement and time shall be made simultaneously at regular intervals and

agreed with the Engineer.

Loading shall be continued until one of the following results is obtained:

(i) the test load is reached,

(ii) a constant or reducing load has been recorded for an interval of movement of

10mm,

144

(iii) a total movement of the pile base equal to 10% of the base diameter has been

reached;

The load shall then be reduced in 5 approximately equal stages to zero load, and movement at

each load stage including zero load shall be recorded.

The Contractor shall, within 24 hours of the completion of the test, submit to the Engineer a complete record of each pile test including the maximum load reached and a graph of load against movement.

The Contractor shall, within seven days of the completion of the test, submit to the Engineer a

comprehensive pile testing report. The form of the report shall be as agreed with the Engineer.

145

PART G: MISCELLANEOUS

Mortar and Grout

Surfaces to receive mortar or grout shall be cleaned of all loose or foreign material that would

inhibit bonding with the mortar. They shall then be flushed with water and allowed to dry to

a surface dry condition immediately prior to placing the mortar or grout.

Mortar shall be composed of fine aggregate complying with Section C 900 of the

Construction Specification and Portland cement Type IA complying with AASHTO M85.

The mix proportions shall be as stated in the Construction Documents or elsewhere in the

Construction Specification or if not stated shall be one part of cement to two parts of fine

aggregate by weight.

The water content of the mortar shall be as low as possible consistent with the use for which it

is required but in any case the water/cement ratio shall not be more than 0.5.

Mortar which is specified as "dry pack" shall be mixed with sufficient water for the mix to

become cohesive but not plastic when squeezed in the hand. Dry pack mortar shall be

rammed into the cavity it is required to fill, using a hand rammer with sufficient force to

ensure full compaction.

Grouting of Pockets and Holes Pockets and holding-down bolt holes shall be thoroughly cleaned out using compressed air and water jets. Holes drilled by diamond bit shall be roughened. Pockets and holes shall be filled with grout consisting of cement and clean fresh water mixed in proportion of two parts by weight of cement to one part by weight of water. The pouring of liquid grout shall cease as soon as each hole is filled and any excess grout on the surface of the concrete foundation shall be completely removed and the surface dried off before the next operation proceeds.

Underpinning of Base plates The space between the top surface of foundation concrete and the underside of base plates shall be filled with a special mortar made up of materials in the proportions of one part Portland cement to one part fine aggregate. An additive to counteract shrinkage, acceptable to the Engineer and in accordance with ASTM C845, shall be added in the proportions recommended by the manufacturer. The special mortar shall have the minimum water-cement ratio compatible with sufficient workability to enable maximum compaction to be achieved.

The special mortar shall be well rammed in horizontally below the base plate from one edge only until it is extruded from the other three sides. The mortar which has extruded shall then be rammed back to ensure complete support without voids.

146

Precast Concrete

Precast units manufactured on Site shall comply with the relevant clauses of this Section C

900.

Structural units shall be marked with a reference number and date of casting.

Pre-tensioned precast units shall comply with the further requirements of Section C 1100 of

the Construction Specification.

Placing Concrete under Water

Concrete shall be deposited either through funnel-shaped tremmies which shall have

discharging bottom fitted with a trapdoor or by concrete pumps fitted with a device at the end

of the discharge tube to prevent the ingress of water whilst the tube fills with concrete.

During pumping, once the delivery of concrete has started, the end of the discharge tube shall

be kept full of concrete and below the surface of the deposited concrete until placement is

completed.

The cement content of concrete that is to be placed under water shall be 10 per cent more than the standard mix for the corresponding grade and workability to compensate for loss due to washing.

Concrete shall be placed in one continuous operation and the surface of the concrete during

placement shall be kept as near to horizontal as practicable. Still water shall be maintained at

the discharge point of pumps and tremmies.

To ensure thorough bonding, each successive layer of concrete shall be placed before the

initial set of the preceding layer has taken place.

Sulphate Resisting Concrete

Where shown on the Drawings or the Construction Documents, concrete shall be made with

Sulphate Resisting Cement.

The water content of the mix shall be carefully controlled and regulated so as to produce concrete of minimum permeability. The concrete shall be thoroughly compacted to maximum density. The depth of cover from the face of the concrete to the reinforcing steel shall be not less than 60 mm.

Formwork shall be left in place for a minimum of 7 days after casting to protect newly formed

concrete surfaces from attack.

Except for the repair of any surface cavities and the plugging of form tie holes, the original

formed surface of the concrete shall be left undisturbed.

147

Interruptions to Placing

If concrete placing is interrupted for any reason, the Contractor shall immediately take the

necessary action to form a construction joint.

Any concrete already placed shall be thoroughly compacted. All work on the concrete shall be completed while it is still plastic and it shall not thereafter be disturbed until it has hardened enough to resist damage.

Before concreting is resumed after such an interruption the Contractor shall cut out and

remove all damaged or un-compacted concrete, feather edges or any other undesirable

features and shall leave a clean, sound surface prepared in accordance with Section C 900 of

the Construction Specification against which fresh concrete may be placed.

If it should become possible to resume concrete placing without contravening the Construction Specification and with the Engineer's consent, new concrete shall be thoroughly worked into the existing concrete and compacted so as to eliminate any cold joints.

Remedial Work to Defective Concrete Defective surfaces shall not be made good by plastering.

Areas of honeycombing that the Engineer agrees may be repaired shall be cut back to sound

concrete or to 75 mm which ever is the greater distance. In the case of reinforced concrete the

area shall be cut back to at least 25 mm clear distance behind the reinforcement or to 75 mm,

whichever is the greater distance. The cavity shall have sides at right angles to the face of the

concrete. After cleaning out with water and compressed air the cavity shall be coated with an

approved epoxy resin and then be filled immediately with concrete of the same class as the

main body but with aggregate larger than 10 mm nominal size removed. A form shall be used

against the cavity, provided with a lip to enable concrete to be placed. The form shall be

filled to a point above the top edge of the cavity.

After seven days the lip of concrete shall be broken off and the surface ground smooth.

Surface irregularities which are outside the limits of tolerance set out in Section C 900 of the

Construction Specification shall be ground down to achieve transition slopes of less than 1 in

50 between adjacent surfaces in the manner and to the extent instructed by the Engineer.

Waterproofing Buried Concrete Surfaces All buried concrete surfaces, whether for new structures or in the repair and rehabilitation of existing structures, shall be protected by means of medium curing cut back bitumen, grades MC 30 or MC 70. A compatible primer shall be used having a viscosity which allows the primer to penetrate the concrete without forming a skin.

The concrete surfaces shall be thoroughly cleaned and primed to ensure complete coating and

penetration of the concrete. Two coats of cut back bitumen shall then be applied at a rate of

spread per coat of 0.6 litres / square metre. The first coat shall be allowed to dry before the

second coat is applied.

148

Waterstops All references to waterstops include groutstops.

Waterstops shall be made of material resistant to chlorides, sulphates, or other deleterious

substances which may be present in the environment of the Works. Rubber waterstops may

be of natural or synthetic rubber and shall have an elongation at breaking stress of at least 500

per cent at 25 ˚C and shall allow a joint movement of at least 50 mm.

Poly vinyl chloride (PVC) waterstops shall be extruded from an unfilled plasticised PVC

polymer or copolymer which does not contain any reclaimed or scrap PVC. PVC waterstops

shall have an elongation at breaking stress of at least 225 per cent at 25oC and shall allow a

joint movement of at least 10 mm.

Low modulus waterstops shall be of rubber or PVC as described above but shall have an

elongation of at least 200 per cent at 25oC under a tensile stress of 6 N/mm

2 and shall allow a

joint movement of at least 50 mm.

Measurement and Payment The units that have been used in this contract associated to the Bill 6 ( Structural Works ), are

the following

Note : In the Section 4, The Bill of Quantities are described all the measurement method that

have to be taken in order to assign the Payment for every used Item in this project

Nº of Item Description Unit

901 Cast-in-place concrete cu m

902 Bridges sq m

903 Replacement concrete cu m

149

SECTION C 1000: PRESTRESSED PRE-TENSIONED CONCRETE

150

General

The work shall consist of the fabrication and installation of precast pretensioned concrete

beams.

Notwithstanding the provisions of this Section, factory produced pretensioned precast

structural elements shall be acceptable for the Works, provided they comply with standards

set out in the Construction Documents.

All concrete work, including the production of precast units, shall comply with the appropriate requirements of Section C 900 of the Construction Specification.

Submission of Working Drawings

Prestressed pretensioned beams shall be constructed to the dimensions shown in the

Construction Documents subject to minor adjustments to individual beams as may be

necessary to conform with the lengths of the beams in the existing structure which are being

replaced.

The Contractor shall include in the Construction Documents detailled working drawings, with supporting calculations, showing the methods and materials the Contractor proposes to use. Such details shall include:

(a) the method and sequence of prestressing,

(b) specifications for the prestressing steel,

(c) working stresses,

(d) transfer stresses,

(e) arrangement of wires and strands in the precast units,

(f) allowances for prestressing losses,

(g) the arrangements for debonding of wires and strands,

(h) the arrangement of reinforcement,

(i) reinforcement bending schedules,

(j) details of any embedded or cast in items, and

(k) such other details pertaining to the prestressing operations.

Prestressing Wire and Strand

Prestressing wire shall be uncoated stress relieved wire conforming to the requirements of

AASHTO M204.

Prestressing strand shall be uncoated stress relieved seven wire strand conforming to the

requirements of AASHTO M203.

151

Testing

Sampling and testing shall be in accordance with AASHTO M203 or M204 as appropriate.

Each package of prestressing wire or strand shall be accompanied by a manufacturer’s

certificate of compliance, a mill certificate, and a test report. The mill certificate and test

report shall include:

(a) the cross-sectional area,

(b) yield strength,

(c) ultimate strength,

(d) elongation at rupture,

(e) modulus of elasticity, and,

(f) the stress strain curve for intended use.

All values certified shall be based on test values and nominal sectional areas of the materials

being certified.

Should the Engineer so require, the Contractor shall test samples of prestressed wire or strand

at a laboratory approved by the Engineer. Such testing shall be at the expense of the

Contractor. The selection of samples shall be made at the manufacturer’s plant by the

Engineer.

A test sample shall comprise a 2.0 m length of prestressing wire or strand. Three representative samples shall be supplied for each 20 tonne lot, or portion thereof, of material used in the Works.

Prestressing Operations Prior to prestressing the Contractor shall submit the work for inspection and approval by the Engineer. All prestressing wire or strand shall be tensioned by means of hydraulic jacks so that the force in the prestressing wire or strand is not less than that shown in the Construction Documents.

Tensioning shall not be carried out at a temperature below 0˚C without the approval of the

Engineer.

No welds shall be made on the forms or on the steel in the member after the prestressing steel

has been installed.

The tension in the wires or strands shall be maintained by some positive means during the

period between tensioning and transfer.

Where the Construction Documents show requirements for debonding the ends of specified

wires or strands debonding shall be accomplished by the use of polythene tubes or wrapping

the wires or strands subject to the approval of the Engineer.

Following concreting, no prestressing wire or strand shall be cut until the concrete in the member has attained a compressive strength at transfer of not less than that shown in the Construction Documents. The cutting and releasing of prestressing wire shall be performed in such an order that lateral eccentricity of prestressed will be a minimum. All prestressing wires and strands shall be cut off flush with the end of the member. The exposed ends of the prestressing wires and strands and a 25 mm strip of concrete shall be cleaned and painted. Cleaning shall be by wire brush or abrasive

152

blast cleaning. The surfaces which are not to be covered by concrete or mortar shall be painted with an approved zinc rich paint which shall be thoroughly mixed prior to application and worked into any voids in the prestressing strands.

153

SECTION C 1100: CONCRETE REPAIRS

154

General

This Section covers repair works to existing structures, including:

surface cleaning,

mortar repairs,

epoxy repairs,

concrete repairs,

repairs to existing furniture.

Scope of Repair Works

Repair works shall generally comprise one or other of the following treatments:

repair of superficial damage by cement mortar;

repair of deep damage by concrete;

protective waterproof treatment with a polymer based resin mortar;

repair by use of epoxy based concretes;

pressure injection of cracks with an epoxy resin.

The use of ordinary Portland or sulphate resisting cement shall be governed by the location of

the repair.

Where particular repair treatments are detailed in the Drawings or the Construction

Documents, these shall prevail over the requirements of this Section.

Surface Cleaning

Before cleaning work all surface attachments (signs, notices, electrical fittings etc.) shall be

removed from the areas to be repaired. The method of removal shall be such as to avoid

unnecessary damage.

The cleaning operation shall remove all dirt or other contaminants, previous coatings, laitance, paint, algae, moss, lichens, plant growth and shall comprise one or other of the following:

(1) grit blasting (wet, dry or vacuum blasting); and or

(2) high pressure water jetting, steam cleaning employing wax free detergents or

biocides together with power scrubbing as required.

Cleaning shall be undertaken without damaging underlying sound concrete.

Trial areas shall be carried out before the main cleaning operation commences.

155

Removal of Existing Concrete Existing concrete shall be removed to the extent necessary to reach sound concrete. The extent and depth of concrete removed at any time shall be approved by the Engineer as the work proceeds and shall be recorded by the Contractor.

The limits of each repair area shall be cut as a series of straight lines at right angles to the

surface to a depth of approximately 10 mm (5 mm for repairs using epoxy mortar) using a

disc cutter or similar. The disc cut surfaces shall be roughened prior to reinstatement.

Where reinforcing bars are exposed by concrete removal, the concrete shall be removed for a

minimum of 20 mm behind the bars or until sound concrete is reached, whichever is the

greater.

Additional concrete removal shall be carried out along actively corroding exposed bars until a

continuous length of 50 mm of bar free from active corrosion is exposed. The limit of active

corrosion shall be assessed on a visual basis. The edges of any additional areas removed shall

be cut square as specified above.

Where redundant fixings, including lifting hooks, formwork ties and the like, are present on a

concrete surface, the concrete shall be removed to a minimum depth of 25 mm around the

fixing. The fixing shall then be cut or ground back such that a minimum cover of 25 mm is

achieved to the fixing from the concrete surface. The area of concrete broken out shall then

be reinstated with repair mortar in accordance with this Section of the Construction

Specification.

Before concrete removal begins the Contractor shall install temporary propping at locations

directed by the Engineer. Temporary propping shall remain in place until the member has

been fully repaired and the repair mortar has gained the required strength.

Reinforcement

Rust scale corrosion products and other deposits shall be removed from reinforcement

exposed within the area of repair by grit blasting.

Abrasives shall be new, clean and dry and of a grade suitable for the preparation of steel to the

standard indicated above. Exhausted abrasive shall be bagged up and removed from site after

a single use.

The exposed reinforcement shall be thoroughly washed down with clean water as part of the

preparation operations.

Subject to the approval of the Engineer, the existing reinforcement shall be moved or

supplemented or replaced by new bars in accordance with Section C 900 of the Construction

Specification welded or spliced to existing bars. Bars to be removed shall be cut by disc

cutter.

Replacement bars shall be cleaned if required by the Engineer to the British Standard specified above. Where bars are lapped a minimum lap of forty times the bar diameter shall be provided.

156

Replacement Concrete

Concrete used in repair work shall comply with the requirements of Section C 900 of the

Construction Specification, supplemented by the additional provisions of this Section.

The mix required for any particular repair shall be as directed by the Engineer. In general, repair concrete shall be from one or other of the following:

Class 50/10 Bridge decks, piers and columns;

Class 40/10 Foundations: depths up to 50mm;

Class 40/20 Foundations: elsewhere.

Concrete in foundations or otherwise in contact with soil shall be made using Sulphate

Resisting Cement.

Non-reactive aggregates shall be used in beam and crosshead repairs; the maximum sodium

oxide content shall be 3.0 kg in any cubic meter of concrete.

Repair concrete shall not be placed without the prior inspection of he works and the consent of the Engineer.

Repair Concrete to Beam So fits

Where shown in the Construction Specification, the Drawings or the Construction

Documents, beam so fits shall be repaired by concrete ‘capping’.

For this repair work the Contractor shall be required to demonstrate the efficacy of its working methods by the means of a full scale field trial.

The following methodology involving a ‘Flow Test’ and a ‘Flow Trough Test’ shall be

acceptable.

Flow Test

The flow characteristics of the concrete shall be assessed at an ambient temperature of

between 50C and 20

0C in the flow trough shown in Figure 1.

The temperature of the materials and mixer shall be as close as possible to those expected

during the Contract.

The funnel shall be fitted with a rubber bung and charged with 6 liters of concrete. On the

release of the bung the concrete shall flow along the trough and the length of the flow shall be

measured. The minimum length of flow along the trough for each test shall be 450 mm

without signs of segregation or bleeding.

157

Flow Trough Test

The flow characteristics for repairs to so fits shall be assessed by pouring the concrete mix

having the same water: cement ratio as in Clause C 1107 into the model shown in Figure 2.

The pre-cast concrete slab shall be wetted for 2 hours before the test but the surface shall be

free of surplus water at the time of test. The concrete shall be poured from one side of the

model until the level of the concrete has reached at least 10 mm above the underside of the

top plate. The material shall be placed in the model in one pour.

After 24 hours the top plate shall be removed and the exposed surface shall be lightly brushed

with a stiff bristle brush to remove any surface cement skin which may be covering voids.

The exposed surface of the concrete shall be examined for air pockets, cracks, and other

defects.

The trial shall be deemed successful if the concrete thus formed is homogeneous and free from voids.

Polymer Modified Mortar

Where described in the Contract, polymer modified cementations mortar shall be used for

repairs.

The total chloride ion content shall not exceed 0.3 per cent of the mass of cement. Calcium

chloride or admixtures containing chloride salts shall not be used.

The content of equivalent sodium oxide in the mortar shall be restricted or non reactive

aggregates shall be used as specified in Clause C 1108 of this Section.

Batching and placing shall be in accordance with the manufacturer’s recommendations.

Impregnation Impregnation may be used in conjunction with concrete repairs in accordance with this Section of the Construction Specification.

Undiluted monomeric alkyl alkoxy silane (isobutyl) shall be used.

After 14 days curing of the concrete the material shall be applied evenly in two applications

each at a rate of 300 ml / m2 with a minimum interval of 2 hours.

Alternatively the first application may be made after 7 days curing of the concrete followed

by the final application not less than 7 days later.

Concrete surfaces shall be clean and free from dust and loose matter before treatment. Light

grit blasting may be used if necessary. Areas to be treated shall be surface dry and if

necessary protected from the weather before application.

158

Material shall not be applied in the following conditions:

(a) when the air temperature in the shade is greater than 350 C;

(b) when the air temperature in the shade is less than 50C;

(c) when it is raining unless suitable precautions have been taken which have been

approved by the Engineer.

Application shall be made by wet spray without misting at a nozzle pressure not greater than

0.2 N / mm2.

Epoxy Mortar

The epoxy resins for use in the mortar shall be obtained from an approved manufacturer and

shall be prepared in conformity with the manufacturer's recommendations.

The minimum requirements are:

Pot Life : 90 minutes at 25 degrees Celsius;

60 minutes at 30 degrees Celsius;

45 minutes at 35 degrees Celsius;

Bond Strength: 12 MPa;

Tensile Strength: 16 MPa.

Surface Preparation

Surface upon which epoxy is to be placed shall be free of rust, grease, oil, paint, asphalt, loose material, unsound concrete, dust or any other deleterious material. Contaminants, such as oil, grease, tar, asphalt, paint, wax curing compounds or surface impregnants like linseed oil or silicons, laitance and weak or loose concrete shall be removed.

Epoxy bonding agents shall not be applied in the rain, or in standing water. The surface must

be dry.

Two general methods of surface preparation shall be followed:

(a) mechanical, including grinding, grit blasting, water blasting and scarification; (b) chemical that includes acid etching with 15 percent by weight of hydrochloric solution,

followed by repeated flushing with high-pressure stream of water. Application

Epoxy primer coat shall be applied with the help of stiff nylon bristle brushes or hard rubber rollers or spray gun depending upon the nature of surface and extent of work area.

Before the primer coat is fully cured, epoxy mortar shall be applied by means off trowels and

floats. The interval between the application of primer coat and epoxy mortar shall be

approximately 15/30 minutes depending upon the ambient temperature. Seal coat shall be

applied after 24 hours curing, after mild roughening of the surface of the mortar.

159

Coverage

The coverage of resin mix will depend in the system of resin used. However, as a general

guideline the coverage area shall be as under:

(a) primer coat: 1 kg of resin-hardener mix covers an area of 3-6 square metres per

cost depending on the finish of the concrete;

(b) epoxy mortar: one square metre of surface required approximately 20-24 kg of

epoxy when laid to a thickness of 10mm;

(c) seal coat: 4 to 6 square metres per kg of mix depending on the temperature of

application.

Replacing Handrails

Where shown in the Contractor´s Documents or as directed by the Engineer, existing

handrails shall be removed and replaced.

Where the existing railing post base concrete is sound, the new posts can be fitted directly to

the post footing. Where the existing railing post base is not sound, it shall be broken out to

expose the parapet / edge beam reinforcement to which dowel bars will be welded. The

existing concrete will be made good as directed either by epoxy mortar or by concrete.

The works are to be undertaken in accordance with the following general requirements.

(a) The existing handrails will be removed by cutting at the bottom of their railing posts.

(b) The steel base part of the existing handrails attached to the T-beam will be checked

for stability, corrosion and other defects.

(c) If, in the Engineer’s opinion, the existing steel base is unsatisfactory it will be

removed in accordance with sub-clause (e).

(d) If the Engineer accepts the steel base as suitable for further use four dowel bars shall

be welded on to it.

(e) A 500mm x 500mm x 40 mm deep void will be removed by hand (pneumatic

hammers shall not be used) in the concrete surface of the girder.

(f) The void shall be thoroughly cleaned by high-pressure water.

(g) The dowel bars to be placed on the inside of the railing posts shall be welded on to

the transverse reinforcement bar of the underlying beam. The hole will be filled

with epoxy concrete or OPC concrete as directed.

(h) No further work shall be carried out until the concrete infill has reached 70% of its

28-day-strength.

(i) The steel pipe railing posts will be placed over the dowel bars.

(j) The steel railing posts will be tightly filled in by M30 concrete.

(k) Hand railing will then proceed as for new construction.

160

Footpath Repairs

Footpaths shall be reinstated with a 50mm nominal Class 30/20 plain concrete screed coat.

The existing footpath will be scabbled, and prior to the application of the concrete screed given a cement mortar bonding coat.

The footpath will be given a float finish.

Figure 1 - Flow Trough and Funnel

300

5

42 Int.

Bung onDrawWire

230

80 3 rad

Section A - A

FunnelDetails

230

80

3 rad.

1000

90°

90°

Rivetedend plate

Trough

A

A

Length of f

low

measured

at m

axim

um

83

238

1515

3 rad.

hole

10

Funnel Support

This edge to beflush with end

of trough 100

NOTES:

1. Trough and funnel to be made of galvanised steel (14 gauge).

2. Trough to be horizontal while concrete being poured.

3. All dimensions in mm.

161

Figure 2 - Model Flow Test for Horizontal Surfaces

7575

50

10

150 crs. 19

19

750 x 750Pre-cast concrete slab

with rough surface

Plywoodcontaining

walls600 x 600

top glass plate(6 mm float)

Top of Concretein Test

R6 Steel bars at 150 crs.each way mesh placedat mid-depth

Taped Joint

NOTES:-

1. Concrete to be mixed and poured using Contractor’s proposed site

apparatus and poured until it reaches underside of top plate and has

risen up containing walls to depth of at least 10 mm.

2. All dimensions in mm.

3. Wooden, 20 x 20 spacers at corners required to support glass.

162

SECTION C 1200: MISCELLANEOUS BRIDGE WORKS

163

Bridge Bearings: General Bearings shall comply with the requirements of AASHTO M251 and shall be designed in accordance with AASHTO Standard Specifications for Highway Bridges. Bearings shall be manufactured and installed in accordance with the details shown in the Construction Documents and as described in the Construction Specification. They shall adequately provide for the thermal expansion and contraction, rotation, tilting, creep and shrinkage of the structural elements that they support.

Bearing surfaces of bearings shall be kept free from contamination and after the deck has been

completed, each bearing and the area around it shall be left clean.

All bearings shall be indelibly marked with their appropriate type and identification numbers

that shall be visible after installation and shall be supplied complete with anchors, anchor

bolts, nuts, washers, bolts, seals and the like as required.

0Should the Contractor wish to use an alternative system to that shown in the Construction

Specification or Drawings it shall include in the Construction Documents full details and

technical specifications of the alternative system and shall satisfy the Engineer with regard to

the suitability of the alternative system. The Contractor shall obtain the written approval of

the Engineer for any alternative or amended type of bearing or bearing system.

Bearings shall not be dispatched to the Site until they have been tested in accordance with the

Construction Specification and the certified results of such tests approved by the Engineer.

Bearings and their components shall be stored clear of the ground in a storage shed until

required for installation. Particular care shall be taken to prevent damage to the sliding

surfaces of bearing components. Protective wrapping around bearings shall not be removed

until immediately prior to the installation of the bearings.

Elastomeric Bearings

Bearings shall be manufactured to the design dimensions and the Construction Specification

within the tolerances set out in Section 6 of AASHTO M251.

The Contractor shall submit manufacturer‘s test certificates for all raw materials.

Sampling, testing and acceptance criteria for bearings shall be made on a lot basis. The

physical properties of the cured elastomeric compound shall be determined by using samples

taken from production bearings. Testing of the physical properties of the elastomer may

require the destruction of one or more bearings.

The manufacturer shall select random sample bearings for testing from completed lots of bearings. The manufacturer shall carry out the required testing and determine compliance with the Construction Specification before submitting the lots for quality assurance inspection, testing, and acceptance consideration by the Engineer. The results of the manufacturer’s tests shall be furnished to the Engineer.

Testing shall be carried out by the manufacturer in accordance with the requirements of

Section 8 of AASHTO M251. A minimum of two bearings per lot shall be tested for cold

temperature shear in accordance with Section 9.1 of AASHTO M251.

164

If any bearings tested fail to satisfy any of these requirements the entire lot shall be rejected.

Bearings that sustain no discernible damage under testing may be incorporated in the

Permanent Works.

The Engineer shall have the right to obtain one sample bearing of each type from the Site for

testing to confirm compliance with the Construction Specification. A minimum of 28 days

shall be allowed for inspection, sampling, and quality assurance testing of production bearings

and component materials.

Where indicated in the Contract bearings shall be installed under the supervision of the

manufacturer’s representative. Bearing installation and seating shall be carried out in

accordance with the manufacturer’s instructions. The method adopted shall be subject to the

prior approval of the Engineer.

The bedding material beneath bearings shall be either a Portland cement based non-shrink

mortar with an air-entraining agent in accordance with Section C 900 of the Construction

Specification or an approved epoxy based grout. Proprietary grout mixes shall be mixed,

placed and cured strictly in accordance with their manufacturer’s instructions. The Contractor

shall conduct Site trials, to the satisfaction of the Engineer, to determine a preferred bedding

material, before any bridge bearings are seated.

Working loads shall only be transferred on to bearings when the bedding material has

developed sufficient strength as determined from cube crushing tests.

Hot Poured Elastic Type Expansion Joints Materials

Hot poured elastic type expansion joints shall comply with the following requirements:

(a) joints shall comprise a hot poured bituminous plug constructed in place using

approved proprietary expansion joint components,

(b) a strip extending down to the concrete surface and past the waterproof membrane shall

be saw cut through the finished asphalt concrete surfacing,

(c) the expansion gap between adjacent bridge elements shall be caulked with a foam

caulking,

(d) the base of the expansion joint shall be closed with a hot dip galvanised steel base

plate held in position by locating pins driven through the base plate into the caulking,

(e) the plug shall be constructed from a single size aggregate and hot poured elastomer

modified bituminous binder,

(f) the plug shall develop a strong bond with both the exposed horizontal concrete

surfaces and the vertical cut faces of asphalt surfacing,

(g) the dimensions of the joint shall be sufficient to accommodate longitudinal

movements of 50 mm as determined in accordance with the manufacturer’s

specifications,

(h) joints shall have a high load carrying capacity, be tolerant to ambient temperatures

ranging between -300C and +45

0C, completely waterproof and flexible in all

directions,

165

(i) joints shall be capable of accommodating movements in longitudinal, rotational, and

transverse directions.

The binder shall be a blend of bitumen, polymers, fillers, and surface active agents formulated to combine fluidity at application temperature with low temperature flexibility and resistance to flow at higher ambient temperatures.

The aggregate to be incorporated in expansion joints shall be 20 mm single-sized aggregate in

accordance with BS 63 from either the Basalt, Gritstone, Gabbro, or Granite groups listed in

BS 812. Aggregate shall be cleaned, sized, and bagged under factory conditions for dispatch

to site.

The finished asphalt surfacing layers shall be saw cut and the surfacing and the waterproofing

fully removed to expose the underlying concrete surfaces. The recess shall be thoroughly

cleaned and free from any dirt or debris. The surfaces of the recess shall be prepared with a

hot compressed air lance, the expansion joint caulked, and the base plate installed and fixed

all in accordance with the manufacturer’s recommendations.

The recess shall be primed with hot binder. A layer of heated stone of maximum thickness 40 mm shall be placed in the joint and flooded with hot binder. The joint shall be built up in successive layers until it is within 25 mm of the surface. The final layer shall be constructed from premix made from the same materials and finished flush with the asphalt concrete wearing course.

Strip Type Expansion Joints

Strip type expansion joints shall be in accordance with section 19 of the AASHTO Standard

Specifications for Highway Bridges (2002) and shall be constructed from the following

materials:

(a) profiled copper strip of minimum thickness 2 mm;

(b) tarred hemp yarn 40mm or 40 mm thick compressible bitumen-impregnated fibre;

(c) joint sealer comprising coarse sand and 6% bitumen or other approved joint sealing

compound.

Filler-Type Expansion Joints

This type of joint shall be constructed from the following materials:

(a) preformed joint filler to stated thicknesses; and,

(b) an approved joint sealing compound.

Preformed joint fillers shall conform to one of the following specifications either AASHTO

M213, Preformed Expansion Joint Fillers for Concrete Paving and Structural Construction, or

AASHTO M33, Preformed Expansion Joint Filler for Concrete.

Compressible bitumen-impregnated fibreboard or other approve expansion joint filler shall be

cut to shape from full size sheets of material.

166

Surfaces of joint gaps shall be thoroughly cleaned to remove all loose materials, dirt and

debris, then washed or jetted out. No joint shall be sealed without inspection and prior

approval by the Engineer.

Preformed expansion joint filler shall only be positioned immediately prior to the placing of

the contiguous material. If opposite surfaces of the same joint are to be placed at different

times, joint filler shall not be positioned until the material forming the second face is about to

be placed.

Sealants and joint primers shall be applied in accordance with their manufacturer’s recommendations. The joint sealant shall be of a type which is resilient to pedestrian traffic and which will perform satisfactorily in the environmental conditions prevailing in Afghanistan.

Bridge Deck Waterproofing

Where a proprietary bridge deck waterproofing system is shown in the Drawings or

Construction Documents, it shall be installed in accordance with the manufacturer’s

instructions.

Where no deck waterproofing system is shown in the Drawings or Construction Documents, bridge decks shall be waterproofed by a prefabricated cold applied sheet membrane. The membrane shall comprise a self-adhesive heavy-duty polypropylene mesh reinforced rubber bitumen compound membrane protected with a silicon release paper. The minimum overall thickness of the membrane shall be 1.5 mm. The membrane shall be supplied in rolls generally 1 m wide and 20 m in length. The membrane shall be capable of accepting a cold asphalt protective layer and hot rolled asphalt concrete surfacing.

The Contractor shall ensure that concrete surfaces to receive the waterproofing membrane are clean, dry, and free from laitance, loose aggregate, and other deleterious materials. Abrupt surface irregularities greater than 3 mm shall be ground down or filled with a high strength mortar. The concrete surface shall be primed in accordance with the manufacturer’s instructions prior to applying the waterproof membrane.

A cold asphalt protective layer complying with Section C 800 of the Construction

Specification shall be laid over the waterproof membrane.

Paint for Structural Steelwork Paint systems for steel structures shall comply with Division II, Construction - Section 14 Painting Metal Structures, of AASHTO Standard Specifications for Highway Bridges. The paint system shall comprise one of two alternatives:

two coats of organic zinc primer, vinyl wash undercoat, and two coats of vinyl finish

in accordance with Section 14.2 of the above referenced standard. The colour of the

last finish coat shall be as directed by the Engineer;

two coats of inorganic zinc primer, vinyl wash undercoat, and one coat of alkyd finish.

Galvanised Coatings

Galvanised coatings on ferrous materials shall comply with AASHTO M 232, Zinc Coating

(Hot-Dip) on Iron and Steel Hardware and AASHTO M 111, Zinc (Hot-Dip Galvanised)

Coatings on Iron and Steel Products as appropriate.

167

SECTION C 1300: ROAD FURNITURE

168

General All road furniture shall comply with appropriate Afghanistan standards.

Retro reflective Material for Permanent Road Signs

The retro reflective material shall comply with AASHTO M 268, Retro reflective Sheeting for

Traffic Control as amended below.

The retro reflective material, when applied to the sign plate, shall give the appearance of a

continuous reflecting surface under any angle of observation. It shall consist of a smooth exterior

film with spherical lenses embedded beneath the surface, and shall have a protected, precoated

adhesive backing which shall be tack-free, heat-activated for mechanical vacuum-heat application.

The combination of various elements shall result in a non-exposed lens type optical reflecting

system. The retro reflective material shall be applied in accordance with the instructions from the

manufacturer of the retro reflective material used.

The retro reflective surface of the sign shall be weather resistant and shall show no appreciable

cracking, blistering, crazing or dimensional changes after 2 years unprotected outdoor exposure at

45˚ upwards inclination to the vertical facing west.

When retro reflective surface are laminated to the base materials, the adhesion shall be such that the

retro reflective material shall resist peeling, scuffing and marring during normal handling or

shocking off when jabbed with a spatula at 20˚C. It shall withstand 8 hours of soaking in water at

25˚C without any noticeable edge lifting or curling. The adhesive shall have no staining effect on

the retro reflective material. The adhesive shall permit the retro reflective material to adhere

securely 48 hours after application at temperatures between -40˚C and + 93˚C.

When bent around a 20 mm diameter mandrel at a temperature of 20˚C, the retro reflective material

applied to an aluminum panel of 0.5 mm thickness shall show no evidence of cracking around the

outside of the bend.

When a 25 mm diameter steel ball is dropped from 2 meters height onto the retro reflective face of

the sign specimen at the ambient temperature of 20˚C.

The retro reflective material around the impact point shall show no evidence of cracking or peeling

off.

After immersion of a specimen of retro reflective sign material for 10 minutes in methyl alcohol,

kerosene or turpentine, or for 1 minute in toluene or xylol, the retro reflective material shall show

no evidence of dissolving, puckering or blistering. The retro reflective material shall be capable of

withstanding washing with a mixture of water and mild detergent, turpentine and methanol.

The retro reflective surface shall be such as to be readily refurbished by cleaning and recoating in

accordance with the manufacturer's recommendations.

169

Permanent Road Signs

The Contractor shall obtain road signs only from a manufacturer / supplier approved by the

Engineer.

The Contractor shall include the following information in the Construction Documents:

(a) name of the firm from which it proposes to obtain the signs together with place of

manufacture or fabrication;

(b) a description of the items to be supplied;

(c) manufacturer's specification together with a description of quality, grade, weight and

strength;

(d) Manufacturer's test certificates, or recent test results carried out on similar items by an

authority or laboratory recognized by the Engineer;

(e) A sample sign, post and fittings that shall be stored on site;

(f) Manufacturer’s instructions on the operation and maintenance of the signs.

Unless directed otherwise posts, frames, fittings and the backs of signs shall be painted with a finish

coat of grey. Bolts and nuts shall be spot welded after erection to prevent theft, and grey epoxy

paint shall be applied to all areas so treated.

Finished sign plates (with sign face attached) shall be clearly and durably marked on the back, with

the following information in English and Dari:

(a) the number of the Standard Specification to which they have been manufactured;

(b) the name, trade mark or other means of identification of the manufacturer or supplier;

(c) the classification of any retroreflective material used in the manufacture of the sign face;

(d) the month and year of assembly.

The Contractor shall excavate in any material for the foundation of the road signs, provide and place concrete Class 20/20, embedded all round and under the posts and backfill the remaining excavation all as shown in the Construction Documents. Foundations for signs of areas over 5 sq metres shall not be covered up until they have been approved by the Engineer.

Guardrail

Beams for guardrails shall be Class A with a Type 1 finish in accordance with AASHTO M180.

The beams shall be mounted on 150 x 75 x 5 mm steel posts with spacers provided between the

beam and post.

All exposed ends of guardrails shall be flared away from the traffic and fitted with terminal

sections. Connection pieces shall be provided where guard rail connects to bridge parapets. and

otherwise an AASHTO and rail manufacturer approved cable anchor assembly and concrete block

anchor will be provided at each run end

Guardrails shall be erected so that the over laps point in the same direction as the flow of the traffic.

170

Posts for guard-rails off bridges shall either be driven or placed in pre-excavated holes as approved by the Engineer. Backfilling of postholes shall be with Class 10/20 concrete.

Guard-rail posts on bridges shall not be erected until the concrete in which the holding down bolts

have been cast has reached its 28 day strength.

Guard-rail shall be correct within a tolerance of ± 20 mm in line and level.

Kerb and Drainage Offlets Materials

Edge kerb include barrier kerb, mountable and semi-mountable kerb shall be constructed in Class

20/20 pre-cast concrete.

Chutes shall be manufactured in Class 20/20 pre-cast concrete, and the units shall fit neatly into each other.

Channels shall be constructed from Class 20/14 concrete and reinforced with high yield steel mesh

reinforcement in both faces.

Cold-poured joint sealant shall be a two-part polysulphide sealing compound conforming to the

requirements of BS 4254.

The material on which concrete kerb and channels are to be bedded shall consist of crushed stone

sand or other approved porous material with a maximum particle size of 13 mm.

Where concrete bedding material is shown in the Construction Documents, it shall be Class 10/20.

Construction

Trenches for kerb and channels shall be excavated to the required depth and all unsuitable material

shall be removed and replaced with a layer of selected bedding material at least 75 mm thick. The

bedding shall be compacted and accurately shaped to the required grade. No concrete shall be

placed on uncompacted or disturbed material.

Excavations for chutes shall be neatly trimmed. All loose material shall be compacted and where overbreak occurs in hard material it shall be backfilled with non-structural concrete.

Pre-cast concrete kerbing shall be laid and bedded in Class 15/20 concrete with close joints of 3:1

sand:cement mortar at the ends. The joints may not exceed 10 mm in thickness and must be neatly

pointed with a pointing trowel. Guidelines and straight-edges shall be used to ensure that the

exposed faces of kerb and edgings are set true to line and elevation. Kerbing around curves shall be

laid along the full curve length before the joints are made, unless otherwise allowed by the

Engineer.

171

Concrete channels shall be cast in alternate sections. The lengths of sections shall be uniform

throughout and shall be equal to 2 m for every 100 mm average thickness or depth of concrete

measured perpendicular to the bed, except where shorter sections are necessary for closures or

where otherwise shown in the Construction Documents. The exposed surfaces of the concrete shall

be finished in accordance with Section C 900 of the Construction Specification. The concrete shall

be cured in accordance with the requirements of Section C 900 of the Construction Specification.

Abutting joints shall be painted with mastic asphalt coating before intermediate sections are cast.

Guidelines and straight-edges shall be used to ensure that the exposed are formed to line and

elevation.

When curing is complete the joints shall be sealed with an application of joint sealant as specified.

Concrete Chutes in cascades on side slopes shall be laid from the bottom upwards so that each

consecutive unit fits into the previous one, with the bottom unit resting against the outlet structure.

A transition section shall be constructed at the inlet to lead the water into the chute as shown in the

Construction Documents.

Concrete-Lined Open Drains shall be constructed from Class 20/20 concrete. The surface of the excavation against which the lining is to be placed shall be covered by polythene sheet 0.15 mm thick and all joints in the sheeting shall overlap by at least 150 mm. The concrete lining shall be cast in alternate panels and cold joints shall be painted as specified before adjoining slabs are cast.

Transition sections for chutes shall be constructed in situ in Class 20/20 concrete to the dimensions

indicated in the Construction Documents or as otherwise agreed with the Engineer. They shall be

built to the same standards as described for the edge kerbing.

Where kerb and channels are laid after construction of the base, the spaces between the concrete and

adjoining base shall be filled with compacted pre-mixed bituminous material and the cost shall be

included in the rates for the items.

Tolerances

The maximum horizontal deviation of kerb and drainage channels shall be 25 mm or 1:500 when

taken over any section more than 10 m in length.

The invert level of channels and drains and the top of kerbing shall nowhere deviate more than 10 mm from the required level and nowhere shall channels or drains have any adverse grade.

When tested with a 3 m straight-edge, no surface irregularities shall exceed 10mm.

172

Measurement and Payment The units that have been used in this contract associated to the Bill 7 ( Road Furniture and markings

), are the following

Note : In the Section 4, The Bill of Quantities are described all the measurement method that have

to be taken in order to assign the Payment for every used Item in this project

SECTION C 1400: ROAD TRAFFIC MARKINGS

General

Road marking paint shall be specially manufactured for that purpose and comply with AASHTO M

248, Ready-Mixed White and Yellow Traffic Paints.

Thermoplastic material for road marking shall comply with AASHTO M249, White and Yellow Reflective Thermoplastic Striping Material (Solid Form). Road markings shall be reflectorised with glass beads that comply with AASHTO M247, Glass Beads Used in Traffic Paint.

The Contractor shall submit, for each consignment of thermoplastic material delivered to Site, a

Manufacturer’s certificate to show that the materials comply with the Construction

Specification.Paint will be cheaper and thermo will last longer

Equipment

Line marking and the surface application of glass beads shall be carried out only by mechanical

means.

Equipment shall be capable of mechanically extruding hot thermoplastic material to produce a line

thickness of between 4 and 6 mm. The Contractor shall conduct Site trials to demonstrate the

satisfactory performance of his equipment to the Engineer.

Nº of Item Description Unit

Road Furniture

1001 Edge marker posts No

1002 Kilometre posts No

1003-01 Road signs less than 1 sq m

Traffic signs No

Other signs (villages, directions,..) No

1003-02 Information road signs of 2 sq m No

1004 Guard-rail ( safety fence) lin m

173

Letters, figures and symbols shall be marked on the road by means of stencils.

Application of Road Markings

Traffic markings shall be applied to bituminous surfaces only after sufficient time has elapsed to

allow for the evaporation of volatile substances from the bitumen.

Before road marking commences, the road surface shall be clean and dry and completely free from

soil, dust, grease, petroleum products or other deleterious material.

Thermoplastic material shall be applied mechanically in a single layer. Rates of application of thermoplastic materials shall be checked and adjusted if necessary on a daily basis.

The Contractor shall apply retro reflective beads to road markings by means of a spraying device,

forming an integral part of the road marking machine, immediately after the application of the road

marking material and in one continuous operation. Machines that apply beads by means of gravity

only shall not be used.

The rate of application of glass beads to thermoplastic material shall be 0.35 kg/m2 or such other

rate as may be instructed by the Engineer.

Retroreflective Studs

Retro reflective road studs shall not be placed over longitudinal or transverse pavement joints.

Dowel holes shall be drilled in accordance with the manufacturer’s instructions. The dowel hole

and the adjacent portion of the pavement surface to which the marker is to be bonded by adhesive

shall be thoroughly cleaned by blasting.

The adhesive shall be placed uniformly inside the dowel hole and on the adjacent pavement surface, or alternatively, directly to the dowel and on the underside of the marker in a quantity to ensure complete coverage of the contact area with no voids present and with a slight excess after the marker has been pressed into place. The marker shall be placed in position and uniform pressure applied until firm contact is established. Excess adhesive around the marker shall be immediately removed. Soft rags moistened with an approved solvent complying with the manufacturer’s recommendations may be used, if necessary, to remove adhesive from exposed faces of pavement markers. Only approved solvents may be used for this purpose.

Mixing and use of adhesive shall be in strict accordance with the manufacturer’s instructions to ensure that materials are used within the permissible limits. Any adhesive which becomes too viscous shall not be used.

Retro reflective markers shall be placed so that the reflective face of the marker faces the oncoming

traffic.

Retro reflective road studs shall be within ± 20 mm of the required longitudinal position and within

± 5 mm of the required lateral position.

174

Tolerances for Thermoplastic Road Markings

The width of lines and other markings shall not deviate from the specified width by more than 5%.

The position of letters, figures, symbols or lines shall not deviate from that shown in the Drawings

or Construction Documents by more than 20 mm in any direction.

The alignment of any edge of a line parallel to the road centreline shall not deviate from that shown

in the Drawings or Construction Documents by more than 10 mm in 15 m.

The length of segments of any broken line parallel to the road centreline shall not deviate from that

shown in the Drawings or Construction Documents by more than 150 mm.

Both broken and unbroken lines on horizontal curves shall not be marked as chords but shall follow

the correct arc, not deviating from it by more than 20 mm.

Measurement and Payment The units that have been used in this contract associated to the Bill : Road Furniture and markings

are the following

Nº of Item Description Unit

Road Markings

Thermoplastic Road Lane Markings

1101-01 Continous white line 100mm ln m

1101-02 Intermittent line 100mm (3:1) ln D47m

1102 Road marking symbols sq m