18
Technical Report: Summary: Preliminary Design of Timber Jetty, Pontoon and Dredging at Doug's Boatyard Opua. This report presents the preliminary design for a timber jetty with adjoining concrete pontoon which is proposed to be constructed in small bay in the north west corner of Opua Bay in the Bay of Islands (indicated by the blue mark and arrow). A 43m long 3m wide pile support timber jetty, with an adjoining 12m aluminium gangway which provides access to a 12m x 4m polystyrene filled concrete pontoon is propose. In addition, some dredging will be required to allow a vessel to navigate to and berth alongside the pontoon. The design chosen, had the smallest environmental impact and is the least invasive on the natural aesthetics of the bay, while still accommodating the working requirements of the boatyard. However, to achieve these goals; construction difficulty, accessibility and cost have been sacrificed. 1 429539.1

Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

  • Upload
    others

  • View
    6

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

Technical Report:

Summary:

Preliminary Design of Timber Jetty, Pontoon and Dredging at Doug's Boatyard Opua.

This report presents the preliminary design for a timber jetty with adjoining concrete pontoon which

is proposed to be constructed in small bay in the north west corner of Opua Bay in the Bay of Islands

(indicated by the blue mark and arrow). A 43m long 3m wide pile support timber jetty, with an

adjoining 12m aluminium gangway which provides access to a 12m x 4m polystyrene filled concrete

pontoon is propose. In addition, some dredging will be required to allow a vessel to navigate to and

berth alongside the pontoon. The design chosen, had the smallest environmental impact and is the

least invasive on the natural aesthetics of the bay, while still accommodating the working

requirements of the boatyard. However, to achieve these goals; construction difficulty, accessibility

and cost have been sacrificed.

1 429539.1

Page 2: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

Table of Contents Technical Report:

Opua.

Preliminary Design of Timber Jetty, Pontoon

1

and Dredging at Doug's Boatyard

1.0 Introduction ................................................................................................................................ 3

2.0 Site Locality ................................................................................................................................. 4

2.1 Beach Morphodynamics .......................................................................................................... 5

2.2 Aesthetics ................................................................................................................................ 6

3.0 Construction ................................................................................................................................ 7

3.1 Design .............. ........................................................................................................................ 7

3.2 Dredging .................................................................................................................................. 8

3.3 Subsea Erosion Barrier ............................................................................................................ 9

3.4 Timber Jetty ........................................................................................................................... 10

3.5 Pontoon ................................................................................................................................. 10

4.0 Conclusion ................................................................................................................................. 11

5.0 References ................................................................................................................................. 11

2 429539.1

Page 3: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

1.0 Introduction

A jetty and pontoon is proposed to be constructed in Walls Bay to replace the existing structure

directly off Doug's Boatyard located at 1 Richardson St Opua. The pontoon should be capable of

berthing a 50ft launch in all reasonable weather conditions.

An approximately 43m long 3m wide pile supported timber jetty will be constructed starting from the

grassy berm at the north side of the beach. It will arch north-west following approximately the same

arch as the natural bulkhead line of the northern end of the foreshore. The head of the jetty is a 4m x

6m timber turning area, which forms the abutment for the 12m long and 1.2m wide aluminium

gangway. The aluminium gangway provides access to a 12m long 4m wide polystyrene filled floating

concrete pontoon, which will be anchored in place using plastic sleeved driven steel piles. The area

will then be dredged to allow a vessel to approach and berth alongside the pontoon.

This report analyses the sites locality and design considerations as well as the construction

methodology.

3 429539.1

Page 4: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

2.0 Site Locality Opua is part of a large confluence where the Kawakawa River/Inlet and Waikare River/Inlet meet. The

site of the wharf is in a small bay in the northwest corner of the main bay in Opua. The bay is comprised

of mud/sand gravel pocket beach separated by hard exposed rocky cusps on the boarders of the bay.

Currently the Opua Bay foreshore has many dwellings used as both permanent residents and holiday

batches. There are several access routes via Franklin St, Beechy St and Richardson St. There is

significant other marine development (large concrete wharf, ferry landing and extensive timber

boardwalks) in the bay itself and the immediate surrounding area.

The design and location proposed for the structure (Figure 1) is intended to have negligible or minor

impact on the unique natural aesthetics, environment, current residents and stakeholders in the area.

The exact site proposed is shown in detail in the accompanied drawing series 0155-0504

Figure 1: Opua Bay (Google Maps)

4 429539.1

Page 5: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

2.1 Beach Morphodynamics Because the site is a juxtaposition of harder igneous rock at soft sedimentary clays the costal effects

of erosion and sediment transportation are still altering the coast line. Consideration was given to the

location of the site, so that the new structure and construction activities have negligible or minor

impact on the natural beach morphodynamics.

The morphodynamics acting in the proposed bay are a function of two primary morphodynamic

principles- swash and alongshore swash motion

Swash is simply the layer of turbulent water that travels up a beach, this moves material up and down

a beach, which results in cross-shore sediment exchange. However, over the length of beach, breaking

waves create a circulation system where the water-driven shoreward across the surface zone, travels

along the shore and returns to the offshore at the weakest point in the wave front at the centre of the

bay via a backwash mini-rip (as shown in Figure 2). Swash causes erosion of the material away from

the cusp horns (leaving only the hard, coarse material) and depositing it in the bay, from which point

it is then transported out by the backwash.

Original beach material

consisting of both coarse and ---+-'~

fine grains

Backwash returns as mini-rip

Uprush diverges at the cusp horn

Coarse deposition on cusp horn

Figure 2: Beach cusp morphology (Masselink & Hughes 2003)

Fine deposition on subaquous delta

When you have beach cusp swash combining with alongshore swash motion this results in a slightly

unsymmetrical beach cusp shape, which is exactly what we see when we look at an aerial shot of the

proposed bay.

This alongshore swash motion is believed to be caused by a current moving N-NW, the presence of

this current was confirmed by Brown {2018) current observations. MetOcean Solutions (2013) also

indicate this current is due to tidal flows on the site; their analysis work also indicated a N-NW

direction.

5 429539.1

Page 6: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

It is likely this NW current is also enhanced by alongshore motion call longshore drift. This is when the

incoming wave approaches the beach at an oblique angle, as they can at the proposed site as the only

long fetch is from the E - SE, this creates an alongshore swash motion called longshore drift which is

illustrated by Figure 3.

Beach Backviash

Sea

Figure 3: Longshore drift (Brunn, 2005)

This understanding of the natural morphodynamics occurring on the beach has been used to influence

the design and positioning of the dredge cut, fixed structure and subsea erosion barrier.

2.2 Aesthetics It was important that the design does not visually inhibit the view of the residents of Opua. And despite

the existing structure already being there for years, for those residents that could see the structure it

was important it does not compromise the natural flow of the coast line and spoil the view.

Several different steps were taken to achieve this :

1. The positioning of the jetty as close as possible to the northern side of the proposed site

adjacent to the steep vertical bank, restricts it from the view of most residents to the north.

2. By shifting the structure north on the beach, it exposes more of the beach for other onlookers

and the general public.

3. For those residents that will be able to see the structure (to the south, east and by water) the

jetty does not protrude perpendicular to the beach, it arcs following the natural radius the

beach makes with the rocky cusp and hugs that bulkhead line as close as feasibly possible so as

not to impose on the beach front view.

4. For residents and public using the beach or the jetty, the jetty is designed with the lowest

possible freeboard so it does not look invasive at low tide when the gap between the deck and

the water is largest while still meeting the minimum engineering requirements for freeboard.

5. Lastly, the piles will be sleeved with PE sleeves, and the Joist and headstocks will be stained

recessive colours so the structure "blends" in with the natural backdrop.

6 429539.1

Page 7: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

3.0 Construction All different companies within the Total Marine Group will be involved in this construction.

Total Marine Services Ltd. will conduct all engineering design and project management, as

well as conducting all the construction work on site.

Total Floating Systems Ltd. will conduct the design and construction of the polystyrene core

concrete floating pontoon.

Total Engineering Services Ltd. will fabricate all the bracketry and pile guides used on the

pontoon and jetty.

Total Dredging Ltd. will dredge the site to the required depth and batter angles, and then

dispose of the dredged tailings.

Total Marine will also work with Manson Marine and Engineering Ltd to design and build the

aluminium gangway.

3.1 Design Please refer to drawing series 0155-0504 Rev 5

The design of the Jetty, Pontoon and Gangway is in accordance with relevant international and

national standards.

AS-NZS 3962 Guidelines for Design of Marinas

AS-NZS 3600 Concrete Structures

AS-NZS 1720 Timber Structures

AS-NZS 1170 Structural Design Actions

AS-NZS 1664 Aluminium Structures

AS-NZS 1665 Welding of Aluminium Structures

DNV-RP-C205 Environmental Conditions and Environmental Loads

Preliminary analysis suggests the sea state will be as shown in Table 1, for design conditions in

accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum

analysis shown in Figure 4.

Table 1: Sea State Parameters for fetch 6 SOOm, wind speed 35.49 ms·1

Sea state parameter Sym Value

Significant wave height Hs 1.4613 m

Zero crossing period T, 3.04 sec

Mean period Tm 3.21 sec

Wave length L 16.46 m

429539.1

7

Page 8: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

JONSWAP Wave Spectrum 1.8 r-----,-----,,------r-------.----,-------,----....

~, Wind Speed= 35.49 ~ /s , Fetch = 6.5 km j 1.6 ... .. . .. .... . . ... .. ... r·· ··· ·· ·· ··t .. ... .. ···· 1· .... ...... r ......... ·· i .......... .

. . 1 . .4 . . . . . . . . . . . . . . . . .... . .. : ... .. .... ' . : . ......................... : ..... . .. .. ... : .... ... . . . .

N : ; ; : ~ : : 11.2 .......... ······· ·· ···;········ ···/····· ·····-r··· ········:········ ·· ·r····· ····· <I) • •

~ ·· ·· · ····· · .... . .. . ·:·-- -- ··· · ···, · ······ ·· ·· ;·--······· ·· :· ·· · · · ······(· · ··--···

Cl : : . . ~ 0:8 • • • • • • • • • • • • • • • • • • o • • • ~ • • • • • • o o o o o <• • • • • o • • • • • •: • • • 0 • • • • o o o •: o O • o • o O Io o O O = 0 0 0 0 I Io o O ,

u (I) 0..

(.IJ

(D

>

~

. . . . . . . . . . . .

0.6 . . . .. ... ...... . ... ··· ··y·········· )·· ·········1· ······· ···)············; .. .. ...... . : . .

0.4

0.2

···· ·i·· ········· T· "'········:·· ··· ···· ··,:·-·· ··· ····· r ······ ···· : .. .... ... .. , ..... ..... : ... ... ... · r · .......... I .... .. ... .

o L--.....L....L_ _ _ J_ __ .:::::c===.=d-----.L....--....1....--_J o 0.2 0.4 0.6 0.8 1 1.2 1.4

Frequency (Hz)

Figure 4: JONSWAP Analysis Longest fetch onsite

3.2 Dredging Please refer to drawing series 0155-0504 Rev 5

The area will be dredged to allow all requi red vessels to access t he wharf and berth alongside the

pontoon. l·t is proposed to dredge t he channel and berth to a depth 0f CD -1.Sm. It is estimated that

the inground volume is 6743.8m3, based on a hydrographic survey that was conducted by Total

Marine.

Figure 5: Total Dredging Ltd.'s Longreach excavator and hopper barge

The primary method for dredging will be using a long reach excavator on a dredge barge, with a ripping

tooth and rock bucket. All work associated with the dredging will be undertaken from a barge on the

8 429539.1

Page 9: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

water and material removed from the sea bed will be transported to a land-based disposal site. The

dredge barge will not be tidally restricted. However, due to the travel time between the disposal site

and dredge site it is most likely that the barge will only be onsite dredging for 4-5 hours per day. It is

proposed to use a silt curtain which will fully enclose the dredge barge to prevent sediment depositing

outside the dredge area and reduce the plume.

A desktop study was conducted on the design of the dredge cut to determine the most suitable batter

angles of the dredge profile, based on the predicted current and sediment volumes established by

MetOcean Solutions (2013). A convergence study was done of all the batter angles in the dredge

profile to maintain as high as possible average velocity, while also maintaining the lowest possible

deviation in the velocity profile. Based on some more extensive previous dredge model studies we

have conducted, this has proved to be a reliable method of determining an optimum dredge profile

without doing extensive sedimentation modelling. The established optimum profile is shown on the

attached 0155-0504 drawings.

3.3 Subsea Erosion Barrier Please refer to drawing series 0155-0504 Rev 5

It has been identified Brown (2018) that there is a small shellfish bed on the southern end of the beach.

Due to the alongshore swash motion discussed above, it was apparent that there may be a migration

of the shellfish bed north and onto the existing slipway.

To stabilise the shellfish bed and prevent material building up on the slipway it is proposed a groyne

is placed on the edge of the shellfish bed running parallel to the slipway. Given the nature of the beach

and in an attempt to manage the visual impact ofthis additional structure we have proposed a slightly

alternative design to a traditional groyne having a smaller subsurface erosion barrier constructed from

placed rock. This barrier will still have the same effect as a traditional groyne, being to interrupt the

alongshore swash motion and in turn limit the movement of the sediment. As shown in Figure 6, the

structure will maintain the shellfish bed by allowing material to be deposited but will keep the slipway

clear by scouring out the material sitting on the slipway. Because the slipway is a hard structure this

scouring will not cause any damage to the slipway structure.

1,)r gma.l s ho-rnh. c / -. . -.......

/ ..Ji../ - ---------

Figure 6: Illustration of how a groyne works

9 429539.1

Page 10: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

3.4 Timber Jetty Please refer to drawing series 0155-0504 Rev 5

The timber jetty will be constructed using marine grade H6 timber and piles, as per the drawings.

The piles will be pile driven, drilled and piled or drilled and grouted depending on the strata

encountered. Preliminary geotechnical data suggests the latter option is most likely. In total there are

30 pine piles and 4 PVC sleeved steel piles. This work will be conducted from Total Marine's piling

barge. Considering tolerances and over drilling it is assessed that the total area affected for all the

piles will be approximately 4m2 and an average of about 0.25 m3 of seabed removed per pile.

Figure 7: sot Piling barge 'Northland Piler'

3.5 Pontoon The pontoon will be constructed to support the maximum bending moment and shearing forces that

will be incurred in the pontoon. As well it will be capable of resisting the berthing impact loads and

environmental forces of a 60' launch.

The pontoon is primarily comprised of a polystyrene core which gives it the required buoyancy, and

strategically placed steel rebar for strength. Then an approximately 50mm of concrete cover will be

used to bind it all together. Timber wale rs run down the sides of the pontoon and are held in place

with galvanized steel through rods to support the bending moment. The stainless-steel pile guides

and fenders are then attached.

10 429539.1

Page 11: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

Figure 8: Concrete pontoon casting process.

4.0 Conclusion The proposed design, structure and methodology is consistent with other structures built by Total

Marine historically. The design and materials proposed will result in a structure that will be fit for

sound and fit for purpose with minimal maintenance for 35+ years.

5.0 References Masse/ink, G. and Hughes MG. 2003, Introduction to coastal processes and geomorphology, Hodder

Arnold, London

Reeve, D; Chadwick, A; Fleming, C 2004, Coastal engineering-processes, theory and design practice.

New York: Span Press.

Brown, S. 2018, Ecological Assessment: Doug's Opua Boatyard. 4Sight Consulting report prepared for

Doug Schmuck. July 2018.

Met Ocean Solutions Ltd. 2013, Opua Marina Stage 2 Development modelling. Report prepared for Far

North Holdings Ltd

Andrew Johnson BEng (Ocean)(HONS) BEng {NavArch){HONS)

Design & Project Engineer - Total Marine Group.

Date: 11/07/2018

429539.1 11

Page 12: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

_J

"-, ,_ I ,I

,,/ Rev

2 3 4 5

Dat

e

04/0

5/20

18

09/0

5/20

18

18/0

5/20

18

Dts

eha

rgip)

te..,;a

lr, &

_

Offe

nsiv

e e<

iloC'lr

c 601

1Jnda

l'y)

Bow

inda

~lii

f 0'e

itffi11

tatib

rrar' a

rea1J

'-----

----

----

--

-28

.1m

62

·9 m

I. "

I ,o

.8m

112

HDm

"-------..

1 -----

@

~

. M

udcr

e.te

._G

.r id

.

_ ._I

@

CD

+0

.6m

~

~ -

-A

~_ -

. '

. ~

Exi

stff

l~!S

ttf)w

ay-t

e-be

Fefu

tiilt-

Boa

t pul

l. T

imbe

r P

ile w

ith f

loat

ing

rirng

i:

Si;i

ELL

FIS

H B

ED

.....

i---

-...

~~

12m

~--

---.

Exi

stin

g frq

m a

eri~

I ph

ote

Exi

stin

g sl

ipw

ay

,_..

_. __

___

---~

·

_J

0 ~, I I __

____

____

J E

xist

in!!.

I T

li.lrn

bloc

k

, 68

'.(i))i

'l---------------------------------1

Des

crip

tion

Che

cked

A

ppro

ved

AD

DE

D S

HE

ET

S 6

& 7

IC

C

AJ

UP

DA

TE

DR

ED

GIN

G &

MO

OR

ING

MA

NA

GE

ME

NT

PLA

N

ICC

.. A

J U

PD

AT

ED

DR

ED

GIN

G &

BA

CK

GR

OU

ND

IM

AG

E

ICC

A

J

:Ora

win

g N

o:1

01

55

-05

04

-00

01

Dat

e:l 1

3/0

7/2

01

8

Scal

e:11

:250

Clie

nt .

au

g's

Op

ua

Bo

aty

ard

Dra

wn

by

raig

Ca

ve

TOTA

L I

~

-03

96

50

-01

-01

Str

uctu

ral S

ite A

eria

l O

verl

ay

13/0

7/20

18

!VA

RIO

US

MIN

OR

CH

AN

GE

S

!CC

A

J ~ A

ll d

esi

gn

s 11

1nd

c.ilc

ul1t

itln1

co

nta

ine

d i

n t

his

pl11

1n 1

11re

the

SO

ie i

nd

who

I~ o

wiie

d •n

telle

ctua

l pro

pert

y iil

Tciti

f M

an

n•

Ser

vice

s Lt

d N

-Z

eala

nd

M~E

~1~L

~ -<

r-

Page 13: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

_J

----------------------------------

62.9

m ---------

---~

----------------------

-$C

J 28

.1m

.-

=i

A

•, •

r0.8

m

12.0

m

c5 F"

""'W

orkb

oat

Dav

it F

ram

e ~

Wor

king

Ber

ths

. ,

Div

e La

dder

IF--;

;;,=

==-

==

==

==

==

=;,

;;;;

,~ -n

:

C!

ii;;>

Ladd

er_

/

-----

--+

-12

m -----

-

L

7 -

1---

---=

-== =

= §

orm

VV

ate

rext

en

sio

n-=-=

-L

__

Boo

m K

nuck

le

Cra

ne

----

-

Sec

urity

gat

e

Dec

k C

D +

3.6

ml

03

00

SE

O

Tim

ber

pile

s

etai

l 2

12m

Ali

Gan

gway

0

40

6 P

E s

leev

ed

CD

+ 4

.5

X/'-

"' A

,(y>

( ·..7

x..>

<vrv

·;vv ..

.I' X

JV

..>' x

;v v

150

----

.---------

-30

00--------

------

Det

ail

1 T

ypic

al J

etty

co

nstr

uctio

n S

cale

1:2

0 rA

[

j~

~ =-=-=

-=r=¥·1

---

-1

I Fr==

=t~ ~ A

200

X 1

00 H

5 Jo

ist

300

X 1

00 H

5 H

eads

tock

0 0 0 .,...

M24

Thr

eade

d ro

ds

with

squ

are

was

hers

an

d sp

rings

Rev

I

Dat

e I D

escr

iptio

n

2 10

4/05

/201

8 IA

DD

ED

SH

EE

TS

6 &

7

~

Sec

tion

A:A

S

cale

1:2

0

15

0x5

0H

5

Dec

king

50

0 T

yp

Che

cked

l I Ap

prov

ed

cc

I IA

J I

3 09

/05/

2018

!U

PD

ATE

DR

ED

GIN

G &

_MO

OR

ING

MA

NA

GE

ME

NT

PLA

N

ICC

,

'AJ

4 18

/05/

2018

P

DA

TE

D D

RE

DG

ING

& B

AC

KG

RO

UN

D I

MA

GE

IC

C

AJ

5 13

/07/

2018

!V

AR

IOU

S M

INO

R C

HA

NG

ES

IC

C

AJ

Ben

ch B

ox

0 0 .,...

.,...

_M 12

Tijr

eade

d ro

d tie

-~ow

ns ~

l

,-~7£

,. 1 Man

ila

I-

Rop

e

1 ,

: 1

, 40

Typ

-

100

Typ

~

l .

r' 1

I B

==

==~

I --

~ I

~==~~

-;il~

! =7

==

I I

~B

D

etai

l 2

Gan

gway

Ab

utm

en

t S

cale

1:2

0

Dra

win

g N

o:1

01

55

-05

04

-00

02

S

cale,

11 :2

00

& 1

:20

Dat

e: 1

13/0

7/2

01

8

Clie

nt :

o

ug

's O

pu

a B

oa

tya

rd

Dra

wn

by

raig

Ca

ve

11:1 A

ll de

sign

s ;1

nd c

ak:tJ

lalio

ns c

on

tain

ed

rn

this

pfa

n ,u

e t

he

SO

ie 1

.nd

wh

olly

ow

ne

d n

teH

ectu

al p

rop

rrty

ol T

Ota

M

anne

Ser

vtce

s lt

d N

ew Z

ea

lan

d

150

x 50

H5

Dec

king

~

'-/ =

= =·=

~-=--

= [iJ ~1

_,__

)oo

x 1

00H

5/

Jois

t

ive

Ladd

er

300

X 1

00 H

5 H

eads

tock

M24

Thr

eade

d 30

0 X

100

H5

Hea

dsto

ck~

' ~

i ro

ds w

ith s

quar

e w

ashe

rs a

nd s

prin

gs

Sec

tion

B:B

S

cale

1 :2

0

AP

P-0

3965

0-01

-01

Gen

eral

Str

uctu

ral A

rra

ng

em

en

t

i-

Page 14: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

_J

.$cJ

6

6

6

6

665

8

665

7 --

----.

.......

,/

',

,/'

/ ',["'

-,, /

/ /

\\

/ \

\

/ ,/

I'

/ J

\

/

, ,

I ,

/ I

"//

/ /

j D

isch

arge

to a

ir &

,,,

,/ ,,

,, 6

6 0

,/

/

Off

ensi

ve o

dour

bo

un

da

ryl

,/,/

, ,

,/

/ .A

/

/ /

/

,..

, B

ound

ary

of

,/

1 :4

Bat

ter

, ,

/

664

2

667

0

!::::.6

86

,,,,

-"

\\

occu

pa~i

onal

are

a\

,,/,,

__

, ,/

,,/'

-,,-

" \

Mar

ina

/[

, /

/ .,

...,

...,

...,

../

\ M

oorin

g A

rea\

__,,,, "

,

,,~

-,,

,,

,/ ,

,,/,

,

~

'~

--

__

__

_

_/'

\ ,

' D

r dg

to

D

-.5

/

,/

~7

-,,

----

-_

__

__

., ---

/ /

;-"

~-

/ /

!::::.6

50

/ ~

/ '11

Dre

dge

to C

D-2

j ,,

/ ,,

/ e,'

/ 6

, ;§

/

6 52

,

~v

/

~ +

~ ~

rr f 1

1 ,_

-,,, J

i / / "

~/,, __

J U

I----1-,

~~~ --1

r: -•-r

L 0 •

: ~a~ ~:

~ ,),, ii'"~

:~/

'

........ --..

.....,..

....._

I ...

"'{

.,,..

,,. ',

r

', \

',

,

',"" __

_/-

-',

__

...---

'---,-

----

~---

__,,-

----

i

Rev

D

ate

Des

crip

tion

Che

cked

A

ppro

ved

2 04

/05/

2018

A

DD

ED

SH

EE

TS

6 &

7

cc

AJ

3 09

/05/

2018

U

PD

AT

E D

RE

DG

ING

& M

OO

RIN

G M

AN

AG

EM

EN

T P

LAN

cc

A

J D

raw

ing

No:

01

55-0

50

4-0

00

3

4 18

/05/

2018

U

PD

AT

ED

DR

ED

GIN

G &

BA

CK

GR

OU

ND

IM

AG

E

cc

AJ

Dat

e:

13/0

7/2

018

5 13

/07/

2018

V

AR

IOU

S M

INO

R C

HA

NG

ES

cc

A

J

ll.68

2

664

8

667

3

667

2

664

1

668

3

667

1

I::::.

!:::,

!:::,

6

6

6 Ll

.

TOTA

L I

~

M~E

~I~

L~

·<

-039

650-

01-0

1

Dre

dgin

g &

Moo

ring

ma

na

ge

me

nt

Pla

n

r-

Page 15: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

_J

1 C

heck

ed

App

rove

d

2 04

/05/

2018

C

A

J 3

09/0

5/20

18

IUP

DA

TE

DR

ED

GIN

G &

MO

OR

ING

MA

NA

GE

ME

NT

PLA

N

ICC

A

J 4

18

/05

/20

18

!U

PD

AT

ED

DR

ED

GIN

G &

BA

CK

GR

OU

ND

IM

AG

E

ICC

A

J

5 1

3/0

7/2

01

8

!VA

RIO

US

MIN

OR

CH

AN

GE

S

ICC

A

J

Dra

win

g N

o:1

01

55

-05

04

-00

04

Dat

e:l 1

3/0

7/2

01

8

Sca

le:11

:60

0

Clie

nt

: o

ug

's O

pu

a B

oa

tya

rd

Dra

wn

by

raig

Ca

ve

II d

esi

gn

s ,I

nd

c.il

cul;1

tions

con

t;1,n

ed ,

n th

is p

lan

are

th

e s

ole

and

wh

olli

j o

wn

ed

inte

llect

ua

l pro

pe

rty

of T

ot;1

] V

arr

.w S

,arv

1ce:

. Lid

Ne

w Z

ea

lan

d

TOTA

L I

~

Tot

al l

ngro

und

Vol

ume

4329

.3 C

ub

ic M

etr

e

Foo

tpri

nt l

ngro

und

Vo

lum

e 2

51

5.6

Cu

bic

Me

tre

T

otal

Are

a 45

26.0

Sq

ua

re M

etr

e

AP

P-0

3965

0-01

-01

MA

RIN

E ~

SE c

:·,;, C

E::,

L T

. ·

Dre

dgin

g P

lan

With

NR

C a

eria

l ove

rla

y

r-----

Page 16: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

Sec

1 SO

686

34

Dre

dgin

g Ar

ea

From

CTS

Sec

3

SO 4

6155

Pt S

ec 1

SO 1

6553

Sec

2SO

241

39

Boun

dary

of

Occ

upat

ion

Area

Wha

rf

Dre

dge

Batte

r Bou

ndar

y

Sec

3SO

686

34

Con

cret

ed A

rea

Wid

th o

f Tur

ntab

le

Secu

rity

Gat

e

Dre

dge

Batte

r Bou

ndar

y

Dre

dge

Foot

prin

t/Cha

nnel

Bou

ndar

y

Mar

ina

Moo

ring

Area D

redg

eC

hann

elBo

unda

ry

Sub-

Surfa

ce E

rosi

onBa

rrier

Dis

char

ge

to a

ir a

nd

Off

ensi

ve o

dou

r b

oun

dar

y

Dis

char

ge

to la

nd

Dis

char

ge

to a

ir a

nd

Off

ensi

ve o

dou

r b

oun

dar

y

Slip

way

Turn

ing

Bloc

k

Turn

Tab

le S

truct

ures

Mud

cret

e W

ashd

own

Dis

char

ge A

rea

Roc

k W

all/

Wha

rf Ab

utm

ent

Bolla

rd

MH

WS

Mar

k (e

stab

201

0)

Seaw

all

BoatyardReserve

c

Din

ghy

Ram

p

6.1m

7.3m

6.1m

18.3m

6.1m 10

.0m

CTS

Con

tain

men

t Stru

ctur

es

Sec

2SO

686

34

Sec

4 S

O 6

8634

Publ

ic D

ingh

yR

acks

© A

ll de

sign

s an

d ca

lcul

atio

ns c

onta

ined

in th

is p

lan

are

the

sole

and

who

lly o

wne

d in

telle

ctua

l pro

perty

of T

otal

Mar

ine

Serv

ices

Ltd

, New

Zea

land

.

Clie

nt :

Dra

win

g N

o:

Dra

wn

by:

Dat

e:

Scal

e:

Cra

ig C

ave

Dou

g's

Opu

a Bo

atya

rd1:

250

Stru

ctur

al S

ite B

ound

ary

Det

ails

APP-

0396

50-0

1-01

0155

-050

4-00

05

13/0

7/20

18

Boun

dary

of

Occ

upat

iona

l Are

a

Rev

Dat

eD

escr

iptio

nC

heck

edAp

prov

ed

513

/07/

2018

VAR

IOU

S M

INO

R C

HAN

GES

CC

AJ4

18/0

5/20

18U

PDAT

ED D

RED

GIN

G &

BAC

KGR

OU

ND

IMAG

EC

CAJ

309

/05/

2018

UPD

ATE

DR

EDG

ING

& M

OO

RIN

G M

ANAG

EMEN

T PL

ANC

CAJ

204

/05/

2018

ADD

ED S

HEE

TS 6

& 7

CC

AJ

Dis

char

ge to

Air

and

Offe

nsiv

eO

dour

Bou

ndar

yD

isch

arge

to L

and

Dis

char

ge to

Mud

cret

e G

ridEx

istin

g Su

rvey

Peg

s

Dis

char

ge to

Lan

d Ar

ea A

& B

Area

B

Area

A

Page 17: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

_J

,• .

.. -~

·~:-

.<~= ...

~~ ~·-~

· .. ·.to

:.? •.

.::.-.

. .-~ ... '

.......

~..

• ~

2 3 4 5

"··

Mud

Ne

w D

red

ge

d

Gro

und

Leve

l .. J S

poil

J ·; 0

Run

·

·R •

A

"-V,"-~ ~ >"

" >\ V

. ~

_J

" .

• · ..

Sub

Sur

face

Ero

sion

Bar

rier

Sec

tion

Sca

le 1

:50

Rev

D

ate

Des

crip

tion

04

/05

/20

18

A

DD

ED

SH

EE

TS

6 &

7

09

/05

/20

18

U

PD

AT

E D

RE

DG

ING

& M

OO

RIN

G M

AN

AG

EM

EN

T P

LA

N

18

/05

/20

18

U

PD

AT

ED

DR

ED

GIN

G &

BA

CK

GR

OU

ND

IM

AG

E

13

/07

/20

18

V

AR

IOU

S M

INO

R C

HA

NG

ES

Che

cked

cc

cc

cc

cc

\

-- J -

--

-/-

.-

--

--

--

--

--

--

-\~

--

--

--

--

--

--

--

--

--

__

__

_ SJl

p~

ay _

__

__

__

__

__

__

__

_

Se

c 3

so 6

86

34

App

rove

d

AJ

AJ

AJ

AJ

\ I '1 I \ I

______

______

___ \~

------

------

-0

Wo

rk B

oa

t P

ull

,, .....

_ __ _

~~

,L~

,L~

~~

.,/~

~--

----

----

----

----

----

----

---

olla

rd

Su

b-S

urf

ace

Ero

sion

B

arr

ier

Se

aw

all

Dra

win

g N

o: 0

15

5-0

50

4-0

00

6

Sca

le: 1

: 15

0

Clie

nt :

o

ug

's O

pu

a B

oa

tya

rd

Dat

e: 1

3/0

7/2

01

8

Dra

wn

by

raig

Ca

ve

:AH

des

igns

and

Cl

at:o

nseo

nt11

ned

1n t

his

pla

n ar

e th

e '°

le a

nd

who

lly o

wne

d 1n

telle

ctua

l pro

pert

y o

f ~

I

~i,.

,Ser

v1ee

s Li

d N

ew

Zea

land

--------

...__, '~

, o

un

da

ry o

f Occ

up

atio

na

l A

rea

'"' u

d-S

an

d in

terf~

~e--

.,

TO

TA

L

MA

RIN

E

SE ,

;·,;1C

E =·

LTD

.......

.......

'""", '"""

',"--,

, ,,,,

,'"-,

,"-,

,-_

-------- ..-

..-

..­..­

..-..-

..­..-

..­..-

.......

..-.....

.. ..-

.......

..-.....

.. ..-

..-.....

.. .....

.. ..-

.......

..-.....

.. .....

.. ..-

.......

.......

..-.....

.. .....

.. .....

.. ..-

.......

.......

..-.....

.. ..-

.......

.......

.......

..-.....

.. .....

.. ..-

..-.....

.. ..-

.......

AP

P-0

3965

0-01

-01

She

llfis

h be

d S

ub

-Su

rfa

ce

Ero

sion

Bar

rier

r-

Page 18: Technical Report: Preliminary Design of Timber Jetty ... · accordance with AS-NZS 1170 for a 50year design life, derived from the JONSWAP wave spectrum analysis shown in Figure 4

Sec

1 SO

686

34

Dre

dgin

g Ar

ea

From

CTS

Sec

3

SO 4

6155

Pt S

ec 1

SO 1

6553

Sec

2SO

241

39

Dis

char

ge

to a

ir a

nd

Off

ensi

ve o

dou

r b

oun

dar

y

Wha

rf

Slip

way

Wor

k Bo

at P

ull

Sec

3SO

686

34

Con

cret

ed A

rea

Wid

th o

f Tur

ntab

le

Dis

char

ge

to a

ir a

nd

Off

ensi

ve o

dou

r b

oun

dar

y

Dis

char

ge

to la

nd

Dis

char

ge

to a

ir a

nd

Off

ensi

ve o

dou

r b

oun

dar

y

N

Stre

am in

Cul

vert

Inco

rp. w

ithSt

orm

wat

er T

reat

men

t Sys

tem

Area B

Mud

cret

e W

ashd

own

Dis

char

ge A

rea

Roc

k W

all/

Wha

rf Ab

utm

ent

Stor

m W

ater

Dis

char

ge

8m

10m

Bolla

rd

MH

WS

Mar

k (e

stab

201

0)

Pont

oon

Sec

2SO

686

34

Not

e: M

HW

S fix

ed 2

010

from

fiel

d m

easu

rem

ents

and

obse

rvat

ions

on

18 D

ec 2

010,

by

Thom

son

Surv

ey L

td

Seaw

all

BoatyardReserve

cAr

ea A

Din

ghy

Ram

p

Sec

4 S

O 6

8634

Publ

ic D

ingh

yR

acks

© A

ll de

sign

s an

d ca

lcul

atio

ns c

onta

ined

in th

is p

lan

are

the

sole

and

who

lly o

wne

d in

telle

ctua

l pro

perty

of T

otal

Mar

ine

Serv

ices

Ltd

, New

Zea

land

.

Clie

nt :

Dra

win

g N

o:

Dra

wn

by:

Dat

e:

Scal

e:

Cra

ig C

ave

Dou

g's

Opu

a Bo

atya

rd1:

350

Dis

char

ge B

ound

arie

sAP

P-03

9650

-01-

0101

55-0

504-

0007

13/0

7/20

18

Rev

Dat

eD

escr

iptio

nC

heck

edAp

prov

ed

513

/07/

2018

VAR

IOU

S M

INO

R C

HAN

GES

CC

AJ4

18/0

5/20

18U

PDAT

ED D

RED

GIN

G &

BAC

KGR

OU

ND

IMAG

EC

CAJ

309

/05/

2018

UPD

ATE

DR

EDG

ING

& M

OO

RIN

G M

ANAG

EMEN

T PL

ANC

CAJ

204

/05/

2018

ADD

ED S

HEE

TS 6

& 7

CC

AJ

10m

Off

ensi

ve o

dou

r b

oun

dar

y an

d D

isch

arg

e to

air

bou

nd

arie

s, D

isch

arg

es t

o la

nd

an

d t

o th

e C

MA

Dis

char

ge to

Air

and

Offe

nsiv

eO

dour

Bou

ndar

yD

isch

arge

to L

and

Dis

char

ge to

Mud

cret

e G

ridEx

istin

g Su

rvey

Peg

s

Dis

char

ge to

Lan

d Ar

ea A

& B