Upload
ronniendozireho
View
10
Download
0
Embed Size (px)
DESCRIPTION
Work Program for bid
Citation preview
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and construction of
New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo Ring Road, Kampala.
TECHNICAL PROPOSAL
149
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and construction of New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo
Ring Road, Kampala.
TECHNICAL PROPOSAL
150
11.0 ESTIMATED TIME SCHEDULE FOR PROFESSIONAL STAFF
11.1 INTRODUCTION
This Section shows the work Programme proposed for the consultancy and construction work and the time input by the Consultancy
Team and each of the key project personnel.
Months (in the form of a Bar Chart)
Feasib
ility
Pla
nnin
g
Outlin
e (
Pre
limin
ary
)
desig
n P
roposals
Schem
e D
esig
n
Deta
iled D
esig
n
Tender
Action
Construction Stage
Post –Construction and Project Closure
Defects Liability Period
Name Position Reports Due/Activities 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1 2 3 4 5 6 Number of Months
Weeks (in the form of a Bar Chart)
Arch. Ahaisibwe Flora RUNUMI
Project Manager / Overall Team Leader
Direction and coordination of
all consultancy activities and
consultant team,
Liaison with Client
Collect existing data and
analysis,
Carryout initial surveys and
prepare site analysis
Twenty (20) Months
Subtotal (20)
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and construction of New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo
Ring Road, Kampala.
TECHNICAL PROPOSAL
151
schedule,
Assess existing drawings and
buildings in order to establish
requirements for proposed
works,
Preparation of concept and
detailed designs,
Technical specifications,
Contract administration,
Project management and
documentation and
construction supervision
Arch. Enock KIBBAMU
Project Architect (Building)
Assisting the team Leader in
directing and coordinating the
activities of all consultancy
and liaison with the client
Data collection and analysis,
Physical Survey,
Concept and scheme design
development and presentation
to the client,
Report on scheme drawings,
Report on the tasks outlined
above for the Client’s
approval,
Preparation of design and
tender documents and
supervision of work
Twenty (20) Months
Subtotal (20)
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and construction of New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo
Ring Road, Kampala.
TECHNICAL PROPOSAL
152
Arch. Charlotte KICONCO
Landscape
Architect
Preparation of landscaping
designs,
specifications and
supervision of planting and
maintenance
Twenty (20) Months
Subtotal (20)
Caleb
MWESIGWA
Land
Surveyor
Carry out reconnaissance
with team members;
Ascertain Land ownership;
Carryout Cadastral survey to
ascertain plot boundaries and
Size of land available;
Carry out Topographical
surveys aimed at establishing
level changes, surrounding
areas;
Act as the activity leader and
appoint support staff to assist
in carrying out this phase;
Attend consequent
consultation meetings;
Liaison with other consultants
during the design phase;
Assist in setting out activities
One & a half (1 1/2) Months
Subtotal (1 1/2)
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and construction of New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo
Ring Road, Kampala.
TECHNICAL PROPOSAL
153
Simon NYANZI
Quantity
Surveyor
Prepare initial cost estimates,
Prepare Bills of Quantities for
phased construction of works
depending on funds available
Monitoring cost during
detailed design,
Advise on the effect of
decisions,
Preparation of specification,
Assist in tender action
activities such as evaluation,
contract management and
Construction supervision
Twenty (20) Months
Subtotal (20)
Eng. Anthony KUSEMERERWA
Civil /
Structural
Engineer
Preparation of Civil and
Structural design drawings,
detailing and specifications,
design of drainage systems,
Preparation of quantities and
cost estimates for all Civil /
Structural works,
Ascertaining site conditions
including wind speeds and
sun orientation,
Review previously
Twenty (20) Months
Subtotal (20)
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and construction of New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo
Ring Road, Kampala.
TECHNICAL PROPOSAL
154
undertaken Soil
investigations,
Construction supervision and
Assisting Team Leader
Eng. Samuel SEDIDE SENTONGO
Building Services Engineer
(Electrical)
Review the conditions of the
existing Electrical
connections and services,
Carryout design of Electrical
installations,
Preparation of electrical
Specifications, quantities and
cost estimates for all power,
distributions and electrical
works
Fourteen (14) Months
Subtotal (14)
Eng. Judah MAWUBE
Building Services Engineer
(Mechanical)
Review the conditions of the
existing mechanical services,
Carryout Mechanical design,
Preparation of mechanical
Specifications, quantities and
cost estimates for mechanical
works
Fourteen (14) Months
Subtotal (14)
Eng. Sunday SHEM
ICT Specialist
(IT Networks)
Design and supervision of IT
installations, Specification,
and;
Fourteen (14) Months
Subtotal (14)
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and construction of New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo
Ring Road, Kampala.
TECHNICAL PROPOSAL
155
quantities and cost estimates
of IT installation works
Eng. Gumisiriza Gideon LWANGA
Resident Engineer/ Clerk of Works
Site management and
supervision ;
coordination of construction
activities on site,
Checking quality of materials,
and workmanship,
Monitoring the progress of
work against work
Programme, recording details
for as built drawings, and;
Checking Compliance with
safety precautions.
Nine (9) Months
Subtotal (9)
Full time: .…………………………………………………… Part time: …………………………………………………….
Signature: …………………………………………………….
(Authorized Representative)
Full Name: Arch. Kibbamu Enock
Designation: Managing Director
Bidder: Plantek Consultants
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and construction of
New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo Ring Road, Kampala.
TECHNICAL PROPOSAL
156
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and construction of New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo Ring Road, Kampala.
TECHNICAL PROPOSAL
157
12.0 ACTVITY (WORK) SCHEDULE
A. Technical Input
MONTHS FROM START OF ASSIGNMENT
TASK DESCRIPTION DURATION
(WEEKS) 1ST 2ND 3RD 4TH 5TH 6TH 7TH 8TH 9TH 10TH 11TH 12TH 13TH 14TH 15TH 16TH 17TH 18TH 19TH 20TH
DESIGN AND TENDER
ACTION 5 MONTHS
1 Stage 1: Feasibility Planning
1.1 Consultant Mobilization 3 days
1.2 Site visit and Project
appreciation 3 days
1.3
Topographic and cadastral
survey, Geo-technical
investigations
1 week
1.4 Preliminary Project Brief 1 week
1.5 Approval of design concept in
Preliminary project brief 1 week
1.6 Preparation of Final Project
brief 1 week
1.7 Approval of Final Project
brief 1 week
1.8
Preparation and approval of
Comprehensive Plan for
construction implementation
2 weeks
1.9 Preparation and submission of
a feasibility Planning Report 1 week
2
Stage 2: Outline
(Preliminary) Design
Proposals
2.1
Preparation of Outline
(Preliminary) Drawings for
client approval
2 weeks 23
2.2 Preparation and Submission of
Preliminary Design Report 1 week
3 Stage 3: Scheme Design
3.1
Preparation of Scheme design
drawings and Draft Bills of
Quantities
3 weeks
3.2 Planning Permissions 2 weeks
3.3 Preparation and submission of
scheme design report 1 week
4 Stage 4: Detailed Design
Stage
4.1
Preparation of Final Detailed
Drawings, specifications, Bills
of Quantities
2 weeks
4.2 Preparation and Submission of
Final Design Report 2 weeks
5 Stage 5: Tender action
Preparation of Bid/Tender
documents
5.1 a) Invitation of Bids 7 days
5.2 b) Pre-Bid Conference 1 day
5.3
c) Preparation,
submission and
opening of Bids
2 days
5.4 d) Evaluations of Bids 3 days
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and construction of New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo Ring Road, Kampala.
TECHNICAL PROPOSAL
158
& Recommendations
5.5 e) Contract Documents 1 week
5.6 f) Contract signing 1 day
MONITORING &
SUPERVISION WORKS
15
MONTHS
6 Stage 6: Construction Stage
6.1 Handing over/possession of site
to the contractor 2 days
6.2 Mobilization by Contractor /
Suppliers 2 weeks
6.3 New Construction /
Installations 42 weeks
7 Stage 7: Post-construction
and Project Closure stage
7.1 Maintenance / Defects liability
period 26 weeks
7.2
Post-construction evaluation,
inspections, preparation of final
accounts and closure activities
2 weeks
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and
construction of New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo Ring Road, Kampala.
TECHNICAL PROPOSAL
159
B. Completion and Submission of Reports and other deliverables
Reports Date
(week from commencement)
1. Inception Report (Commencing on date of
Contract Signing)
2nd week
MONTHLY REPORTS
2. Progress Reports
(on consultant’s own contract)
1st Week of every Calendar
Month
3. Progress Reports
(on construction contract)
1st Week of every Calendar
Month(starting after works
contract is signed)
QUARTERLY REPORTS
4. Progress Reports
5. (on consultant’s contract)
10th day of first month of every
quarter (from date of
commencement)
6. Progress Reports
(on construction contract)
10th day of first month of every
quarter (from date of
commencement of construction
works)
7. Feasibility Planning Report 10th week (from date of
commencement)
8. Outline (Preliminary Design Report) 10th week
9. Scheme design Report 14th week
10. Final Design Report 16th week
11. Tender Documents 17th week
12. Pre-Bid conference report 18th week
13. Evaluation Report on Bids for construction 19th week
14. Issues for Pre-contract discussion 19th week
15. Construction Contract Agreement 20th week
Consultancy service for Design and Construction Supervision of Proposed Extension to the Existing Office Block and
construction of New Store Block and perimeter wall on plot.no. 8 - 13, Kyambogo Ring Road, Kampala.
TECHNICAL PROPOSAL
160
16. Post-Project evaluation report End of Defects Liability Period
17. Other Deliverables
a) Schedule of Defects First week during Defects
Liability Period.
b) Final Report End of Defects Liability Period.